CN101823447A - Guide pulley type pendant limiting system - Google Patents

Guide pulley type pendant limiting system Download PDF

Info

Publication number
CN101823447A
CN101823447A CN 201010187335 CN201010187335A CN101823447A CN 101823447 A CN101823447 A CN 101823447A CN 201010187335 CN201010187335 CN 201010187335 CN 201010187335 A CN201010187335 A CN 201010187335A CN 101823447 A CN101823447 A CN 101823447A
Authority
CN
China
Prior art keywords
leading sheave
stone roller
guide
support frame
frame
Prior art date
Legal status (The legal status is an assumption and is not a legal conclusion. Google has not performed a legal analysis and makes no representation as to the accuracy of the status listed.)
Pending
Application number
CN 201010187335
Other languages
Chinese (zh)
Inventor
王兴全
杨铜新
王玉环
田志军
韩佳栋
周维仁
王亮
刘勇
白明慧
陈世荣
Current Assignee (The listed assignees may be inaccurate. Google has not performed a legal analysis and makes no representation or warranty as to the accuracy of the list.)
SHAANXI WANLIDA RAILWAY ELECTRIC EQUIPMENT CO Ltd
Original Assignee
SHAANXI WANLIDA RAILWAY ELECTRIC EQUIPMENT CO Ltd
Priority date (The priority date is an assumption and is not a legal conclusion. Google has not performed a legal analysis and makes no representation as to the accuracy of the date listed.)
Filing date
Publication date
Application filed by SHAANXI WANLIDA RAILWAY ELECTRIC EQUIPMENT CO Ltd filed Critical SHAANXI WANLIDA RAILWAY ELECTRIC EQUIPMENT CO Ltd
Priority to CN 201010187335 priority Critical patent/CN101823447A/en
Publication of CN101823447A publication Critical patent/CN101823447A/en
Pending legal-status Critical Current

Links

Images

Landscapes

  • Finish Polishing, Edge Sharpening, And Grinding By Specific Grinding Devices (AREA)

Abstract

The invention relates to an electric railway contact network system, in particular to a guide pulley type pendant limiting system comprising an upright post foxed on a foundation, wherein an upper support frame and a lower support frame are respectively fixed at the upper part and the lower part of the upright post. The guide pulley type pendant limiting system is characterized in that a guide frame is connected between the upper support frame and the lower support frame; a pendant is connected between an upper guide pulley pendant and a lower guide pulley pendant to form a pendant; the upper guide pulley pendant and the lower guide pulley pendant are slidably connected with a guide groove of the guide frame through a guide pulley assembly; and the pendant is limited between the guide pulley pendant and a guide rail. The invention provides a guide pulley type pendant limiting system with the advantages of reasonable structural design, convenient adjustment, high strength, reliable use and capability of meeting the requirement on the development of a high-speed electric railway.

Description

Guide pulley type pendant limiting system
Technical field
The present invention relates to the contact nets in electrified railways system, being applicable to particularly that the contact nets in electrified railways system casts anchor to rise in the compensating device adjusts the used bob stone roller of catenary or contact wire compensation tension force and guiding and weighs down stone roller and move up and down and limit and weigh down stone roller and cause the bob stone roller restraint device of swing, the guide pulley type pendant limiting system of saying so accurately by wind.
Background technology
It is that driving produces wind eddies stream or has under the wind condition restriction weigh down the stone roller swing that common bob stone roller restriction frame mainly acts on, and anti-falling stop stone roller is invaded limit.But at the big section of wind-force such as strong wind section, coastal typhoon zone, because of weighing down the effect of stone roller swing, cause thread tension force to change greatly, the property at any time of wind direction simultaneously causes very big influence to the safety of clue, has reduced the safety factor of entire mechanism.For this reason, we to have designed a kind of novel bob stone roller restraint device that can use at the big section of wind-force such as strong wind district, coastal typhoon zone be the guide pulley type pendant restraint device.
Disregarding wind-force, wind direction to weighing down under the perfect condition of cutting or polish jade with an emery wheel beat, owing to weigh down the effect of stone roller self gravitation, when temperature Change, the autoregulation of compensating device makes clue relaxation degree keep substantially constant, thereby guarantee the normal operation of electrified railway, the characteristics of Here it is traditional mechanism.Generally be made up of conduit, anchor ear and other union piece, anchor ear plays the effect that the stone roller beat is weighed down in restriction.But at the big section of wind-force such as strong wind section, coastal typhoon zone, weigh down stone roller and be subjected to wind effect, beat is bigger, and the safety of clue is caused very big influence.
Summary of the invention
The purpose of this invention is to provide a kind of reasonable in design, easy to adjust, intensity is high, use is reliable, can satisfy the guide pulley type pendant limiting system of high-speed electric railway demand for development.
The object of the present invention is achieved like this, guide pulley type pendant limiting system, comprise the column that is fixed on the basis, the column upper-lower position respectively is fixed with a upper support frame and a lower support frame, it is characterized in that: connect guide frame between upper support frame and the lower support frame, last leading sheave weighs down to connect between stone roller and the following leading sheave bob stone roller and weighs down stone roller, form and weigh down stone roller integral body, last leading sheave bob stone roller and following leading sheave weigh down the guide groove formation sliding block joint of cutting or polish jade with an emery wheel by leading sheave assembly and guide frame, weigh down stone roller and are limited between leading sheave bob stone roller and the guide rail.
Connect one group or two groups of guide frame between described upper support frame and the lower support frame, there is last leading sheave to weigh down stone roller and following leading sheave bob stone roller in every group of guide frame, it is to weigh down stone roller that last leading sheave weighs down between stone roller and the following leading sheave bob stone roller, form two groups and weigh down stone roller integral body, last leading sheave bob stone roller and following leading sheave weigh down the guide groove formation sliding block joint of cutting or polish jade with an emery wheel by leading sheave assembly and every group of guide frame, weigh down stone roller and are limited between leading sheave bob stone roller and the guide rail.
The described leading sheave of going up weighs down stone roller and following leading sheave and weighs down to cut or polish jade with an emery wheel and can choose 2 groups or 3 groups or 4 groups of leading sheave assemblies are connected with guide frame.
Described upper support frame and lower support frame and guide frame connect into monolateral framed structure or bilateral framed structure.
Described upper support frame and lower support frame and guide frame constitute monolateral framed structure, and last leading sheave weighs down stone roller and following leading sheave and weighs down to cut or polish jade with an emery wheel and choose 2 groups or 4 groups of leading sheave assemblies and be connected with guide frame.
Described guide frame is a vertically-guided frame, between upper support frame and a lower support frame a middle bracing frame is arranged, and connects a vertically-guided frame between upper support frame, middle bracing frame and the lower support frame.
Described leading sheave assembly comprises the leading sheave and the axis of guide, between the leading sheave and the axis of guide bearing is arranged.
Two ends adopt " O " RunddichtringO to seal between the described leading sheave and the axis of guide.
Described upward leading sheave weighs down stone roller and following leading sheave bob stone roller is that steel structure welds body or foundry goods.
Described guide frame is channel-section steel or pipe or I-beam section or angle steel etc.
Advantage of the present invention is: owing to weigh down stone roller and following leading sheave bob stone roller based on leading sheave in the guide rail guide frame structure qualification of vertically holding up guide frame, last leading sheave weighs down to connect between stone roller and the following leading sheave bob stone roller and weighs down stone roller, so just define to weigh down and cut or polish jade with an emery wheel and in guide rail, to slide up and down, thereby restriction wind-force deflection angle, whole bob stone roller side-play amount is 2mm to the maximum, the bob stone roller beat that actv. has been avoided causing because of wind-force, wind direction is bigger, solved thread tension force and changed big problem.Leave little and suitable gap between leading sheave and guide rail, guide wheel and guide rail belong to rolling friction character, so frictional resistance is very little, and unnecessary catching phenomenon, unlikely reduction mechanical efficiency take place when having avoided up-and-down movement.Weigh down simultaneously the stone roller restraint device be designed to adjustable, the convenient manufacturing and the on-site installation adjustment, the contact contact wire that has guaranteed the block of bow collector of electric locomotive safety and steady slides and is subjected to electricity to get stream.
Description of drawings
The invention will be further described below in conjunction with the embodiment accompanying drawing:
Fig. 1 is embodiment 1 structural representation;
Fig. 2 is embodiment 2 structural representations;
Fig. 3 is embodiment 3 structural representations;
Fig. 4 is that the leading sheave of Fig. 1 weighs down first kind of example structure scheme drawing of stone roller;
Fig. 5 is that the leading sheave of Fig. 1 weighs down second kind of example structure scheme drawing of stone roller;
Fig. 6 is that the leading sheave of Fig. 1 weighs down the third example structure scheme drawing of stone roller;
Fig. 7 is that the leading sheave of Fig. 1 weighs down the 4th kind of example structure scheme drawing of stone roller;
Fig. 8 is that the leading sheave of Fig. 1 weighs down the 5th kind of example structure scheme drawing of stone roller;
Fig. 9 is that the leading sheave of Fig. 1 weighs down the 6th kind of example structure scheme drawing of stone roller;
Figure 10 is the birds-eye view that the leading sheave of Fig. 2 weighs down stone roller embodiment;
Figure 11 is that the leading sheave of Fig. 3 weighs down first kind of example structure scheme drawing of stone roller;
Figure 12 is a kind of example structure scheme drawing that combines Fig. 1 and Fig. 3;
Figure 13 is a kind of example structure scheme drawing that combines Fig. 2 and Fig. 3.
Among the figure: 1,The basis; 2, column; 3, upper support frame; 4, lower support frame; 5, guide frame; 6,Weigh down stone roller; 7, second weighs down stone roller; 8, go up leading sheave and weigh down stone roller; 9, leading sheave weighs down stone roller down; 10, leading sheave assembly; 11, middle bracing frame.
The specific embodiment
Embodiment 1:
As shown in Figure 1, guide pulley type pendant limiting system, comprise the column 2 that is fixed on the basis 1, column 2 upper-lower positions respectively are fixed with a upper support frame 3 and a lower support frame 4, connect guide frame 5 between upper support frame 3 and the lower support frame 4, last leading sheave weighs down to connect between stone roller 8 and the following leading sheave bob stone roller 9 and weighs down stone roller 6, and it is whole that stone roller is weighed down in formation, last leading sheave weighs down stone roller 8 and following leading sheave bob stone roller 9 respectively has the four groups of leading sheave assemblies 10 and the guide groove of guide frame 5 to form sliding block joint, as shown in Figure 4.So just define and weigh down stone roller and can only in guide rail, slide up and down, thus restriction wind-force deflection angle, whole bob stone roller side-play amount is 2mm to the maximum, and actv. avoided the bob stone roller beat that causes because of wind-force, wind direction bigger, solved thread tension force and changed big problem.
As Fig. 5, Fig. 6, Fig. 7, shown in Figure 8, last leading sheave weighs down stone roller 8 can have two groups of leading sheave assemblies 10 to be connected with guide frame 5 with following leading sheave bob stone roller 9, can vertical summetry connect, as Fig. 5, shown in Figure 6, also can be to corner connection, as shown in Figure 7, can also horizontal symmetrical connect, as shown in Figure 8.Last leading sheave weighs down stone roller 8 can have three groups of leading sheave assemblies 10 to be connected with guide frame 5 with following leading sheave bob stone roller 9, as shown in Figure 9.Last leading sheave weighs down to connect between stone roller 8 and the following leading sheave bob stone roller 9 and weighs down stone roller 6, makes 6 stable the moving up and down along guide frame 5 of bob stone roller, and guide frame 5 is channel-section steels in the present embodiment.
Embodiment 2:
As Fig. 2, Figure 10, shown in Figure 13.Connect two groups of guide frames 5 between upper support frame 3 and the lower support frame 4, there is last leading sheave to weigh down stone roller 8 and following leading sheave bob stone roller 9 in every group of guide frame 5, leading sheave weighs down to connect between stone roller 8 and the following leading sheave bob stone roller 9 and weighs down stone roller 6 on one group, another group goes up between leading sheave bob stone roller 8 and the following leading sheave bob stone roller 9 and connects the second bob stone roller 7, form two groups and weigh down stone roller integral body, last leading sheave weighs down stone roller 8 and following leading sheave and weighs down the guide grooves of stone roller 9 by leading sheave assembly 10 and every group of guide frame 5 and form sliding block joints, weigh down stone roller be limited in leading sheave weigh down cut or polish jade with an emery wheel and guide rail between.
As Figure 11, Figure 12, shown in Figure 13.Upper support frame 3 and lower support frame 4 connects into monolateral framed structure with guide frame 5, and during monolateral framed structure, last leading sheave weighs down stone roller 8 and the bob of following leading sheave and cuts or polish jade with an emery wheel 9 and can choose 2 groups or 4 groups of leading sheave assemblies 10 and be connected with guide frame 5.Guide frame 5 is round steel in the present embodiment.
Embodiment 3:
Embodiment shown in Figure 3 is that weight device is weighed down in the guiding slip of only adopting a guide frame 5 to constitute.As shown in Figure 3, different with embodiment 1 with embodiment 2, embodiment comprises the column 2 that is fixed on the basis 1 equally, column 2 upper-lower positions respectively are fixed with a upper support frame 3 and a lower support frame 4, between upper support frame 3 and a lower support frame 4, a middle bracing frame 11 is arranged, connect guide frame 5 between upper support frame 3, middle bracing frame 11 and the lower support frame 4.
Upper support frame 3 and lower support frame 4 can adopt monolateral bracing frame, also can adopt bilateral bracing frame.During monolateral bracing frame, available anchor ear is fixed on bracing frame on the fixed link, guide frame 5 is fixing with upper support frame 3 and lower support frame 4, last leading sheave bob stone roller 8 and following leading sheave weigh down cuts or polish jade with an emery wheel the 9 leading sheave assemblies of fixing 10 when the guide groove of guide frame 5 slides, a horizontal leading sheave assembly 10 is arranged simultaneously in the outside of guide frame 5, guaranteed on horizontal surface to weigh down stone roller is limited and with the guide groove sliding block joint of guide frame 5, as shown in figure 11.It is fixing with upper support frame 3 and lower support frame 4 to constitute guide frame 5 by two steelframes, last leading sheave weigh down stone roller 8 and following leading sheave weigh down the fixing leading sheave assemblies 10 of stone roller 9 about in the layout, two horizontal leading sheave assemblies 10 are arranged simultaneously in the outside of guide frame 5, guide frame 5 sliding block joints that stone roller is limited and constitute with two steelframes have been guaranteed on horizontal surface to weigh down, in order to guarantee that guide frame 5 is unlikely to the slip that deformation effect weighs down stone roller, increased at the middle part of guide frame 5 and to have rigidly fixed framework, to guarantee the integral rigidity of guide frame.As shown in figure 12.Guide frame 5 is I-beam sections in the present embodiment.
In the present invention, last leading sheave weighs down stone roller 8 and the bob of following leading sheave and cuts or polish jade with an emery wheel 9 and can choose 2 groups or 3 groups or 4 groups of leading sheave assemblies 10 are connected with guide frame 5.Last leading sheave weighs down stone roller 8 and following leading sheave bob stone roller 9 is steel structure welding body or foundry goods.
Guide frame 5 is channel-section steel or pipe or I-beam section or angle steel etc.Based on the guide frame 5 of vertically holding up guide frame, weighing down stone roller 6 is limited by track adjusting wheel in guide frame 5 guide rails, so just define to weigh down and cut or polish jade with an emery wheel and in guide rail, to slide up and down, thereby restriction wind-force deflection angle, whole bob stone roller side-play amount is 2mm to the maximum, the bob stone roller beat that actv. has been avoided causing because of wind-force, wind direction is bigger, solved thread tension force and changed big problem.Leave little and suitable gap between leading sheave and guide rail, guide wheel and guide rail belong to rolling friction character, so frictional resistance is very little, and unnecessary catching phenomenon, unlikely reduction mechanical efficiency take place when having avoided up-and-down movement.Weigh down simultaneously stone roller restriction frame be designed to adjustable, the convenient manufacturing and the on-site installation adjustment.
Leading sheave assembly 10 comprises the leading sheave and the axis of guide, and bearing or axle sleeve are arranged between the leading sheave and the axis of guide, and bearing can be an environment-friendly type copper radical self-lubricating bearing, and according to our use experience and the testing result on tension pulley, mechanical efficiency is not less than 98%.While two ends between axle and wheel adopt the O RunddichtringO to seal, and can guarantee that like this sand and dust can't enter axle sleeve, to reduce wearing and tearing and to increase frictional resistance, can guarantee the use of track adjusting wheel and axis of guide long-term safety.
When at the scene adjustment being installed, between axle and wheel two ends, adopt " O " RunddichtringO to seal, can guarantee that like this sand and dust can't enter axle sleeve,, can guarantee the use of track adjusting wheel and axis of guide long-term safety to reduce wearing and tearing and to increase frictional resistance.

Claims (10)

1. guide pulley type pendant limiting system, comprise the column (2) that is fixed on the basis (1), column (2) upper-lower position respectively is fixed with a upper support frame (3) and a lower support frame (4), it is characterized in that: connect guide frame (5) between upper support frame (3) and the lower support frame (4), last leading sheave weighs down to connect between stone roller (8) and the following leading sheave bob stone roller (9) and weighs down stone roller (6), form and weigh down stone roller integral body, last leading sheave weighs down stone roller (8) and following leading sheave and weighs down the guide groove of stone roller (9) by leading sheave assembly (10) and guide frame (5) and form sliding block joint, weigh down that stone roller is limited in that the leading sheave bob is cut or polish jade with an emery wheel and guide rail between.
2. guide pulley type pendant limiting system according to claim 1, it is characterized in that: connect (5) one groups or two groups of guide frames between described upper support frame (3) and the lower support frame (4), there is last leading sheave to weigh down stone roller (8) and following leading sheave bob stone roller (9) in every group of guide frame (5), it is to weigh down stone roller that last leading sheave weighs down between stone roller (8) and the following leading sheave bob stone roller (9), form two groups and weigh down stone roller integral body, last leading sheave weighs down stone roller (8) and following leading sheave and weighs down the guide groove of stone roller (9) by leading sheave assembly (10) and every group of guide frame (5) and form sliding block joint, weigh down that stone roller is limited in that the leading sheave bob is cut or polish jade with an emery wheel and guide rail between.
3. guide pulley type pendant limiting system according to claim 1 is characterized in that: described upper support frame (3) and lower support frame (4) connect into monolateral framed structure or bilateral framed structure with guide frame (5).
4. guide pulley type pendant limiting system according to claim 4, it is characterized in that: described upper support frame (3) and lower support frame (4) and guide frame (5) constitute monolateral framed structure, and last leading sheave weighs down stone roller (8) and the bob of following leading sheave and cuts or polish jade with an emery wheel (9) and choose 2 groups or 4 groups of leading sheave assemblies (10) and be connected with guide frame (5).
5. guide pulley type pendant limiting system according to claim 1, it is characterized in that: described guide frame (5) is a vertically-guided frame, between a upper support frame (3) and a lower support frame (4), a middle bracing frame (11) is arranged, connect a vertically-guided frame between upper support frame (3), middle bracing frame (11) and the lower support frame (4).
6. guide pulley type pendant limiting system according to claim 1 is characterized in that: described leading sheave assembly (10) comprises the leading sheave and the axis of guide, between the leading sheave and the axis of guide bearing is arranged.
7. guide pulley type pendant limiting system according to claim 7 is characterized in that: two ends adopt " O " RunddichtringO to seal between the described leading sheave and the axis of guide.
8. guide pulley type pendant limiting system according to claim 1 is characterized in that: described upward leading sheave weighs down stone roller (8) and following leading sheave bob stone roller (9) is that steel structure welds body or foundry goods.
9. guide pulley type pendant limiting system according to claim 1 is characterized in that: the described leading sheave of going up weighs down stone roller (8) and the bob of following leading sheave and cuts or polish jade with an emery wheel (9) and choose 2 groups or 3 groups or 4 groups of leading sheave assemblies (10) are connected with guide frame (5).
10. the guide pulley type pendant limiting system of leading according to claim 1 is characterized in that: described guide frame (5) is channel-section steel or pipe or I-beam section or angle steel.
CN 201010187335 2010-05-31 2010-05-31 Guide pulley type pendant limiting system Pending CN101823447A (en)

Priority Applications (1)

Application Number Priority Date Filing Date Title
CN 201010187335 CN101823447A (en) 2010-05-31 2010-05-31 Guide pulley type pendant limiting system

Applications Claiming Priority (1)

Application Number Priority Date Filing Date Title
CN 201010187335 CN101823447A (en) 2010-05-31 2010-05-31 Guide pulley type pendant limiting system

Publications (1)

Publication Number Publication Date
CN101823447A true CN101823447A (en) 2010-09-08

Family

ID=42687681

Family Applications (1)

Application Number Title Priority Date Filing Date
CN 201010187335 Pending CN101823447A (en) 2010-05-31 2010-05-31 Guide pulley type pendant limiting system

Country Status (1)

Country Link
CN (1) CN101823447A (en)

Cited By (2)

* Cited by examiner, † Cited by third party
Publication number Priority date Publication date Assignee Title
CN103031846A (en) * 2012-12-11 2013-04-10 中交第二航务工程局有限公司 Straddle type stepped hydraulic support guide frame
CN110203111A (en) * 2019-06-17 2019-09-06 中铁十九局集团电务工程有限公司 Falling mound limit frame

Citations (4)

* Cited by examiner, † Cited by third party
Publication number Priority date Publication date Assignee Title
JPS59220426A (en) * 1983-05-26 1984-12-11 Sanwa Tekki Corp Easy installation type weight falling preventing apparatus
GB2207403A (en) * 1987-06-19 1989-02-01 Spie Batignolles Tensioning a catenary support device in a tunnel
CN2292857Y (en) * 1996-07-10 1998-09-30 王辉 Anti-overturning and anti-falling integrally lifting scaffold
CN201703270U (en) * 2010-05-31 2011-01-12 陕西万里达铁路电气化器材有限公司 Guide pulley type weight limiting device

Patent Citations (4)

* Cited by examiner, † Cited by third party
Publication number Priority date Publication date Assignee Title
JPS59220426A (en) * 1983-05-26 1984-12-11 Sanwa Tekki Corp Easy installation type weight falling preventing apparatus
GB2207403A (en) * 1987-06-19 1989-02-01 Spie Batignolles Tensioning a catenary support device in a tunnel
CN2292857Y (en) * 1996-07-10 1998-09-30 王辉 Anti-overturning and anti-falling integrally lifting scaffold
CN201703270U (en) * 2010-05-31 2011-01-12 陕西万里达铁路电气化器材有限公司 Guide pulley type weight limiting device

Cited By (3)

* Cited by examiner, † Cited by third party
Publication number Priority date Publication date Assignee Title
CN103031846A (en) * 2012-12-11 2013-04-10 中交第二航务工程局有限公司 Straddle type stepped hydraulic support guide frame
CN103031846B (en) * 2012-12-11 2015-05-06 中交第二航务工程局有限公司 Straddle type stepped hydraulic support guide frame
CN110203111A (en) * 2019-06-17 2019-09-06 中铁十九局集团电务工程有限公司 Falling mound limit frame

Similar Documents

Publication Publication Date Title
CN201703270U (en) Guide pulley type weight limiting device
CN106012716A (en) Symmetric permanent-magnetic suspension system and permanent-magnetic suspension train rail system
US8602178B2 (en) Constant strain spring compensation device
CN108621857B (en) Suspension type magnetic levitation vehicle and track system
KR102087454B1 (en) Vehicle For A Magnetic Levitation Track
CN103938544B (en) Medium-and low-speed maglev traffic system rail telescopic adjustment structure
CN104452483A (en) Medium and low speed maglev traffic engineering low line curve rail bearing beam structure
CN203403354U (en) Tension-bearing cast steel support
AU2010352460B2 (en) Railway freight car bogie
CN101823447A (en) Guide pulley type pendant limiting system
CN201753028U (en) Novel non-slide sectional insulator for electrified railway contact system
CN204325812U (en) Middle low speed magnetic suspension traffic engineering is low puts route curve support rail girder construction
CN105752855A (en) Windproof stable gantry crane
CN205615360U (en) Electronic railway connecting net pulley compensation arrangement
CN104911964A (en) Magnetic levitation traffic curve track beam
CN205295914U (en) A single line letter U roof beam for inter -city railway
CN218858217U (en) Formula flexible removal contact net is moved to long distance intelligence side
CN202608587U (en) Oil-free lubrication wind-resisting type weight limit frame
CN204753277U (en) Magnetism floats traffic curve track roof beam
CN109398399B (en) Variable gauge stabilizing suspension for vehicle
CN213651647U (en) Adjusting device is used in hoist and mount of assembled bridge
CN208717670U (en) A kind of laying Prefabricated slab type railway roadbed accurate adjustment vehicle
CN101941388A (en) Design method of wind-proof anti-theft weight restraint bracket
RU2266212C1 (en) Anchor section of compensated system with catenary suspension of high-speed railway
CN207141065U (en) A kind of steady interactive system of space crossed track

Legal Events

Date Code Title Description
C06 Publication
PB01 Publication
C10 Entry into substantive examination
SE01 Entry into force of request for substantive examination
C12 Rejection of a patent application after its publication
RJ01 Rejection of invention patent application after publication

Application publication date: 20100908