CN101798820A - Cast-in-situ bored pile double sleeve for separating contact of piles and earth - Google Patents

Cast-in-situ bored pile double sleeve for separating contact of piles and earth Download PDF

Info

Publication number
CN101798820A
CN101798820A CN201010115426A CN201010115426A CN101798820A CN 101798820 A CN101798820 A CN 101798820A CN 201010115426 A CN201010115426 A CN 201010115426A CN 201010115426 A CN201010115426 A CN 201010115426A CN 101798820 A CN101798820 A CN 101798820A
Authority
CN
China
Prior art keywords
sleeve
pile
inner sleeve
bored pile
outer tube
Prior art date
Legal status (The legal status is an assumption and is not a legal conclusion. Google has not performed a legal analysis and makes no representation as to the accuracy of the status listed.)
Pending
Application number
CN201010115426A
Other languages
Chinese (zh)
Inventor
王卫东
吴江斌
翁其平
Current Assignee (The listed assignees may be inaccurate. Google has not performed a legal analysis and makes no representation or warranty as to the accuracy of the list.)
East China Architectural Design and Research Institute Co Ltd
Original Assignee
East China Architectural Design and Research Institute Co Ltd
Priority date (The priority date is an assumption and is not a legal conclusion. Google has not performed a legal analysis and makes no representation as to the accuracy of the date listed.)
Filing date
Publication date
Application filed by East China Architectural Design and Research Institute Co Ltd filed Critical East China Architectural Design and Research Institute Co Ltd
Priority to CN201010115426A priority Critical patent/CN101798820A/en
Publication of CN101798820A publication Critical patent/CN101798820A/en
Pending legal-status Critical Current

Links

Images

Landscapes

  • Piles And Underground Anchors (AREA)

Abstract

The invention relates to a cast-in-situ bored pile double sleeve for separating contact of piles and earth in the field of in-situ bored concrete pile for fixing building foundations. The invention is characterized in that an outer sleeve is coaxially sleeved outside an inner sleeve; a gap is reserved between the outer and inner sleeves; the inner diameter of the inner sleeve is not less than the diameter of the cast-in-situ bored pile body so that the inner sleeve is vertically and coaxially adhered on the cast-in-situ bored pile body; elevation of the sleeve bottom of the outer sleeve is the elevation of a substrate excavating surface; the elevation of the sleeve bottom of the inner sleeve is lower than the elevation of the sleeve bottom of the outer sleeve; and the sleeve bottom of the outer sleeve is provided with a circular rubber water-stop band for sealing the gap between the outer and inner sleeves. The double sleeve is arranged in the range from ground surface to the substrate excavating surface within the pile body range which needs to separate the pile from earth when tests on the cast-in-situ bored pile are carried out, and the pile and earth separation of the excavating section is achieved, thus the result of the tests on the pile directly represents a load capacity of the engineering pile with an effective pile length range so that the dereference of the load capacity of the pile base is more close to the practical conditions.

Description

The two sleeve pipes of bored pile of a kind of isolation pile soil contact
Technical field
The invention belongs to the on-site concrete castinplace pile field on fixed buildings basis.
Background technology
Along with the acceleration of Urbanization in China, the underground building area is also increasing, and cutting depth is constantly deepened, as above about 400,000 m of marine rainbow bridge comprehensive transportation hub basement excavation area 2, the about 22m of maximum dredging depth; About 9.6 ten thousand m of Tianjin first high building, 117 mansion basement excavation areas 2, the about 32m of maximum dredging depth.For soft clay area, because the test pile of load test and engineering piles are substantially all finished in the surface drilling perfusion.During test pile, the bored pile top mark is tall and big to push up residing substrate excavation face absolute altitude in actual engineering piles stake, the bearing capacity of single pile that test pile obtains is greater than actual engineering piles, need deduction excavation section pile body side friction, obtain the actual carrying capacity of effective length, otherwise can be relatively dangerous for engineering is actual.At present, often the empirical value by each soil layer limit pile side friction standard value of excavation section calculates pile body excavation section side friction, then it is deducted from the test pile bearing capacity, obtains the theoretical bearing capacity in the engineering piles effective length scope.But for the darker engineering piles of buried depth, this to deduct the method for empirical Calculation value by the field trial value very unreasonable, can bring bigger error, has engineering safety hidden danger.
Summary of the invention
Technical problem to be solved by this invention has provided the two sleeve pipes of bored pile of a kind of isolation pile soil contact, the pile body scope that the required stake soil of excavation face was isolated from ground to the substrate when this pair sleeve pipe was arranged in the bored pile test pile, realize that excavation section stake soil separates, thereby test pile result has directly been represented the bearing capacity of the engineering piles of effective length scope, and the value of bearing capacity of pile foundation is more tallied with the actual situation.
For solving the problems of the technologies described above, basic design of the present invention is: the two sleeve pipes of bored pile that the contact of a kind of isolation pile soil is set, outer tube is coaxial to be enclosed within outside the inner sleeve, and leave the gap, the inner sleeve internal diameter is not less than the diameter of bored pile pile body, described inner sleeve vertically is attached on the described bored pile pile body with axle sleeve, absolute altitude is a substrate excavation face absolute altitude at the bottom of the pipe of described outer tube, at the bottom of the described inner sleeve pipe absolute altitude than described outer tube pipe at the bottom of absolute altitude low, described outer tube pipe bottom is provided with the ring-shaped rubber waterstop and seals gap between outer tube and the inner sleeve.
Based on above-mentioned technical characterictic, can between ring-shaped rubber waterstop and outer tube, be provided with annular shutoff plate, one side of described annular shutoff plate connects with described outer sleeve inner wall, and the another side of described annular shutoff plate withstands the ring-shaped rubber waterstop.Perhaps also can adopt: be provided with annular shutoff plate between ring-shaped rubber waterstop and inner sleeve, weld with described inner sleeve outer wall on one side of described annular shutoff plate, and the another side of described annular shutoff plate withstands the ring-shaped rubber waterstop.
Based on above-mentioned technical characterictic, on the inner sleeve outer wall, weld annular ribs at interval, described annular brace rib and described outer sleeve inner wall leave the gap.Perhaps weld annular ribs at interval on the outer sleeve inner wall, described annular brace rib and inner sleeve outer wall leave the gap.Owing to have the gap with internal and external casing, for bored pile, longer when excavation section, the stake top is stressed when big, the unstability of excavation section pile body may occur, sets up above-mentioned annular brace rib and can effectively solve destabilization problems.The annular brace rib can be forms such as reinforcing bar commonly used on the present engineering, steel plate.
Because the use of the two sleeve pipes of above-mentioned bored pile realize that excavation section stake soil separates, thereby test pile result has directly been represented the bearing capacity of the engineering piles of effective length scope, makes building safer.The two sleeve pipes of above-mentioned bored pile also can be used on other bored pile that needs the contact of isolation pile soil except being used under the test pile condition.
Description of drawings
The invention will be further described below in conjunction with drawings and Examples and application construction method.
Fig. 1 is a longitudinal plan of the present invention.
Fig. 2 is a drawing in side sectional elevation of the present invention.
Fig. 3 is a ring-shaped rubber waterstop connection detail of the present invention.
Fig. 4 is that the present invention's annular shutoff plate is arranged on the connection detail between ring-shaped rubber waterstop and the outer sleeve inner wall.
Fig. 5 is that the present invention's annular shutoff plate is arranged on the connection detail between ring-shaped rubber waterstop and the inner sleeve outer wall.
Fig. 6 is that annular brace rib of the present invention is arranged on the connection detail on the inner sleeve outer wall.
Fig. 7 is that annular brace rib of the present invention is arranged on the connection detail on the outer sleeve inner wall.
The specific embodiment
As depicted in figs. 1 and 2, two sleeve pipes are made up of inside and outside sleeve pipe, inner sleeve 1 internal diameter is not less than the diameter of bored pile, leave gap 3 between outer tube 2 and the inner sleeve 1,2 end of outer tube absolute altitude is a substrate excavation face absolute altitude, 1 end of inner sleeve absolute altitude is lower than outer tube 2, is convenient to outside cannula tip and carries out shutoff, prevents that concrete from entering the gap 3 between internal and external casing.As shown in Figure 3, outer tube 2 plug at end part adopt ring-shaped rubber waterstop 5 to end the slurry measures, can effectively stop concrete or slurries to enter gap 3 between internal and external casing, and rigidity is little does not simultaneously exist bigger constraint to guarantee slippage between the internal and external casing.During the test pile construction, adopt earlier than the drill bit of the outer tube 2 slightly larger in diameter absolute altitude at the bottom of the inner sleeve of constructing, inside and outside sleeve pipe is installed, and fixing, and then adopt the drill bit of construction pile foundation to continue to construct to bored pile stake end absolute altitude, behind the concreting, inner sleeve 1 is close to the bored pile pile body, outer tube 2 is close to the soil body, and the isolation of stake with soil realized in 3 in the space between internal and external casing, and guaranteeing can not have the constraint slippage between the internal and external casing.
On the basis of the above, as shown in Figure 4, annular shutoff plate 4 can be set between ring-shaped rubber waterstop 5 and outer tube 2, also can as shown in Figure 5 annular shutoff plate 8 be set between ring-shaped rubber waterstop 5 and inner sleeve 1.
Because there is the gap in internal and external casing, during to the bored pile pressurized, longer when excavation section, the stake top is stressed when big, the unstability of excavation section pile body may occur.Therefore, along the anti-unstability ribs that annular vertically is set at a certain distance, as Fig. 6, ribs 6 and inner sleeve 1 welding, ribs and outer sleeve inner wall leave spacing, perhaps adopt the mode of Fig. 7, ribs 7 and outer tube 2 welding, ribs and inner sleeve outer wall leave spacing.
More than the scheme that the embodiment of the invention provided is introduced in detail, for one of ordinary skill in the art, according to the thought of the embodiment of the invention, part in specific embodiments and applications all can change.In sum, this description should not be construed as limitation of the present invention, and all any changes of making according to design philosophy of the present invention are all within protection scope of the present invention.

Claims (5)

1. two sleeve pipes of the bored pile of isolation pile soil contact, it is characterized in that: outer tube (2) is coaxial to be enclosed within outside the inner sleeve (1), and leave gap (3), described inner sleeve (1) internal diameter is not less than the diameter of bored pile pile body, described inner sleeve (1) vertically is attached on the described bored pile pile body with axle sleeve, absolute altitude is a substrate excavation face absolute altitude at the bottom of the pipe of described outer tube (2), described inner sleeve (1) pipe end absolute altitude is lower than described outer tube (2) pipe end absolute altitude, and described outer tube (2) pipe bottom is provided with ring-shaped rubber waterstop (5) and seals gap (3) between described outer tube (2) and the described inner sleeve (1).
2. the two sleeve pipes of bored pile of a kind of isolation pile soil according to claim 1 contact, it is characterized in that: between described ring-shaped rubber waterstop (5) and outer tube (2), be provided with annular shutoff plate (4), weld with described outer sleeve inner wall on one side of described annular shutoff plate (4), and the another side of described annular shutoff plate (4) withstands described ring-shaped rubber waterstop (5).
3. the two sleeve pipes of bored pile of a kind of isolation pile soil according to claim 1 contact, it is characterized in that: between described ring-shaped rubber waterstop (5) and inner sleeve (1), be provided with annular shutoff plate (8), weld with described inner sleeve outer wall on one side of described annular shutoff plate (8), and the another side of described annular shutoff plate (8) withstands described ring-shaped rubber waterstop (5).
4. according to claim 1 or the two sleeve pipes of the native bored pile that contacts of 2 or 3 described a kind of isolation piles, it is characterized in that: weld annular ribs (6) on described inner sleeve (1) outer wall at interval, described annular brace rib (6) leaves the gap with described outer tube (2) inwall.
5. according to claim 1 or the two sleeve pipes of the native bored pile that contacts of 2 or 3 described a kind of isolation piles, it is characterized in that: weld annular ribs (7) on described outer tube (2) inwall at interval, described annular brace rib (7) leaves the gap with described inner sleeve (1) outer wall.
CN201010115426A 2010-03-01 2010-03-01 Cast-in-situ bored pile double sleeve for separating contact of piles and earth Pending CN101798820A (en)

Priority Applications (1)

Application Number Priority Date Filing Date Title
CN201010115426A CN101798820A (en) 2010-03-01 2010-03-01 Cast-in-situ bored pile double sleeve for separating contact of piles and earth

Applications Claiming Priority (1)

Application Number Priority Date Filing Date Title
CN201010115426A CN101798820A (en) 2010-03-01 2010-03-01 Cast-in-situ bored pile double sleeve for separating contact of piles and earth

Publications (1)

Publication Number Publication Date
CN101798820A true CN101798820A (en) 2010-08-11

Family

ID=42594651

Family Applications (1)

Application Number Title Priority Date Filing Date
CN201010115426A Pending CN101798820A (en) 2010-03-01 2010-03-01 Cast-in-situ bored pile double sleeve for separating contact of piles and earth

Country Status (1)

Country Link
CN (1) CN101798820A (en)

Cited By (9)

* Cited by examiner, † Cited by third party
Publication number Priority date Publication date Assignee Title
CN102720221A (en) * 2012-06-29 2012-10-10 中国建筑第八工程局有限公司 Double casing pipe and pile testing method for eliminating lateral frictional resistance of portion above top pile elevation of test pile
CN102747729A (en) * 2012-07-13 2012-10-24 中铁二十四局集团上海铁建工程有限公司 Sleeve connection device for bored cast-in-place pile construction
CN103233465A (en) * 2013-05-06 2013-08-07 中国建筑第八工程局有限公司 Collimation permanent point structure and construction method thereof
CN105507321A (en) * 2015-12-16 2016-04-20 上海市城市建设设计研究总院 High-efficiency pile sinking process for existing precast pile
CN108425383A (en) * 2018-03-23 2018-08-21 深圳市工勘岩土集团有限公司 The construction method of side friction is isolated in test pile
CN112302004A (en) * 2020-11-11 2021-02-02 辽宁工程技术大学 Cast-in-place pile with upper straight rod and lower expanded-base structure for reducing negative frictional resistance and construction method thereof
CN113175011A (en) * 2021-05-11 2021-07-27 南京长江都市建筑设计股份有限公司 Pile testing method for cast-in-situ bored pile
CN113981962A (en) * 2021-10-20 2022-01-28 北京城投地下空间开发建设有限公司 Double-casing-pipe pile structure capable of overcoming upward floating of surrounding soil body and construction method
CN114922169A (en) * 2022-06-06 2022-08-19 山东建勘集团有限公司 Device for eliminating negative hole frictional resistance of cast-in-place pile and using method thereof

Citations (3)

* Cited by examiner, † Cited by third party
Publication number Priority date Publication date Assignee Title
CN2352579Y (en) * 1998-08-14 1999-12-08 林誊 Structure for isolating double mould-pipe base for making pile
CN101545270A (en) * 2009-04-17 2009-09-30 上海隧道工程股份有限公司 Double sleeve for pile foundation test and construction technique thereof
CN201704688U (en) * 2010-03-01 2011-01-12 华东建筑设计研究院有限公司 Double sleeve for cast-in-situ bored pile capable of isolating pile-earth contact

Patent Citations (3)

* Cited by examiner, † Cited by third party
Publication number Priority date Publication date Assignee Title
CN2352579Y (en) * 1998-08-14 1999-12-08 林誊 Structure for isolating double mould-pipe base for making pile
CN101545270A (en) * 2009-04-17 2009-09-30 上海隧道工程股份有限公司 Double sleeve for pile foundation test and construction technique thereof
CN201704688U (en) * 2010-03-01 2011-01-12 华东建筑设计研究院有限公司 Double sleeve for cast-in-situ bored pile capable of isolating pile-earth contact

Non-Patent Citations (1)

* Cited by examiner, † Cited by third party
Title
李福清等: "软土扩底灌注桩玻璃钢双套管专利开发与应用", 《地下空间与工程学报》 *

Cited By (12)

* Cited by examiner, † Cited by third party
Publication number Priority date Publication date Assignee Title
CN102720221A (en) * 2012-06-29 2012-10-10 中国建筑第八工程局有限公司 Double casing pipe and pile testing method for eliminating lateral frictional resistance of portion above top pile elevation of test pile
CN102720221B (en) * 2012-06-29 2015-09-30 中国建筑第八工程局有限公司 Eliminate test pile stake top mark high with the double-jacket tube of upper part side friction and pile testing method
CN102747729A (en) * 2012-07-13 2012-10-24 中铁二十四局集团上海铁建工程有限公司 Sleeve connection device for bored cast-in-place pile construction
CN102747729B (en) * 2012-07-13 2014-10-08 中铁二十四局集团上海铁建工程有限公司 Sleeve connection device for bored cast-in-place pile construction
CN103233465A (en) * 2013-05-06 2013-08-07 中国建筑第八工程局有限公司 Collimation permanent point structure and construction method thereof
CN103233465B (en) * 2013-05-06 2016-05-11 中国建筑第八工程局有限公司 Collimate permanent dot structure and construction method thereof
CN105507321A (en) * 2015-12-16 2016-04-20 上海市城市建设设计研究总院 High-efficiency pile sinking process for existing precast pile
CN108425383A (en) * 2018-03-23 2018-08-21 深圳市工勘岩土集团有限公司 The construction method of side friction is isolated in test pile
CN112302004A (en) * 2020-11-11 2021-02-02 辽宁工程技术大学 Cast-in-place pile with upper straight rod and lower expanded-base structure for reducing negative frictional resistance and construction method thereof
CN113175011A (en) * 2021-05-11 2021-07-27 南京长江都市建筑设计股份有限公司 Pile testing method for cast-in-situ bored pile
CN113981962A (en) * 2021-10-20 2022-01-28 北京城投地下空间开发建设有限公司 Double-casing-pipe pile structure capable of overcoming upward floating of surrounding soil body and construction method
CN114922169A (en) * 2022-06-06 2022-08-19 山东建勘集团有限公司 Device for eliminating negative hole frictional resistance of cast-in-place pile and using method thereof

Similar Documents

Publication Publication Date Title
CN101798820A (en) Cast-in-situ bored pile double sleeve for separating contact of piles and earth
CN108060908B (en) Long-distance horizontal directional drilling and grouting reinforcement process for water-rich sand layer under building group
Chen et al. Long rectangular box jacking project: a case study
CN201704688U (en) Double sleeve for cast-in-situ bored pile capable of isolating pile-earth contact
CN102286984A (en) Water-stop curtain and construction method thereof
CN103114609B (en) Newly, the linkage of old diaphragm wall and construction method
CN102852141B (en) Rock-socketed pipe pile foundation with pile core by concrete pouring and pile side by static pressure grouting and construction method for rock-socketed pipe pile foundation
CN104612696B (en) Construction method for large-section underground excavation subway station to pass through viaduct in fine sand layer by using column hole method
CN204199335U (en) A kind of pressure release well reducing PHC tube pile construction soil compaction effect
CN102286981A (en) Waterproof curtain and construction method thereof
CN202689031U (en) Deep foundation pit retaining and protecting retaining wall
CN101614020A (en) Flexible bladder type anti-corrosive apparatus and use the anticorrosion stake and the job practices of this device
CN105714772A (en) Re-drilling concrete wall protecting method for hole formation of rock-socketed pile in karst region
CN202194149U (en) Water-proof curtain
CN107386297B (en) Deep weathering stratum foundation pit water stopping structure
CN103572764A (en) Ultra-deep manual hole digging pile dado water stop structure and construction method thereof
CN109944600A (en) Shield receiving end reinforced construction method
CN102134861B (en) Method for testing precast pile in soil body
CN104988914A (en) Cast-in-situ bored pile breakage processing method under water area environment
CN101793027A (en) Core-grouted static pressure anchor rod pile
CN101586341B (en) Water sealing method for civil engineering groundwork
CN101161947A (en) Integration method of lagging pile and dewatering well for foundation ditch support
CN108625388A (en) A kind of sleeve combination formula large diameter single pile foundation and its construction method suitable for Shallow Bedrock geological conditions
CN105804049A (en) Anti-hole-collapsing foundation reinforced structure during underground diaphragm wall construction
CN105065774B (en) A kind of underground piping branch connects construction method

Legal Events

Date Code Title Description
C06 Publication
PB01 Publication
C10 Entry into substantive examination
SE01 Entry into force of request for substantive examination
C02 Deemed withdrawal of patent application after publication (patent law 2001)
WD01 Invention patent application deemed withdrawn after publication

Application publication date: 20100811