CN101736803B - Sewage deodorization and discharge system with water storage pipes - Google Patents

Sewage deodorization and discharge system with water storage pipes Download PDF

Info

Publication number
CN101736803B
CN101736803B CN200910227218XA CN200910227218A CN101736803B CN 101736803 B CN101736803 B CN 101736803B CN 200910227218X A CN200910227218X A CN 200910227218XA CN 200910227218 A CN200910227218 A CN 200910227218A CN 101736803 B CN101736803 B CN 101736803B
Authority
CN
China
Prior art keywords
pipeline
trap
cloudy well
pipe
well
Prior art date
Legal status (The legal status is an assumption and is not a legal conclusion. Google has not performed a legal analysis and makes no representation as to the accuracy of the status listed.)
Expired - Fee Related
Application number
CN200910227218XA
Other languages
Chinese (zh)
Other versions
CN101736803A (en
Inventor
鲍福来
Current Assignee (The listed assignees may be inaccurate. Google has not performed a legal analysis and makes no representation or warranty as to the accuracy of the list.)
Individual
Original Assignee
Individual
Priority date (The priority date is an assumption and is not a legal conclusion. Google has not performed a legal analysis and makes no representation as to the accuracy of the date listed.)
Filing date
Publication date
Application filed by Individual filed Critical Individual
Priority to CN200910227218XA priority Critical patent/CN101736803B/en
Publication of CN101736803A publication Critical patent/CN101736803A/en
Application granted granted Critical
Publication of CN101736803B publication Critical patent/CN101736803B/en
Expired - Fee Related legal-status Critical Current
Anticipated expiration legal-status Critical

Links

Images

Classifications

    • YGENERAL TAGGING OF NEW TECHNOLOGICAL DEVELOPMENTS; GENERAL TAGGING OF CROSS-SECTIONAL TECHNOLOGIES SPANNING OVER SEVERAL SECTIONS OF THE IPC; TECHNICAL SUBJECTS COVERED BY FORMER USPC CROSS-REFERENCE ART COLLECTIONS [XRACs] AND DIGESTS
    • Y02TECHNOLOGIES OR APPLICATIONS FOR MITIGATION OR ADAPTATION AGAINST CLIMATE CHANGE
    • Y02ATECHNOLOGIES FOR ADAPTATION TO CLIMATE CHANGE
    • Y02A20/00Water conservation; Efficient water supply; Efficient water use
    • Y02A20/20Controlling water pollution; Waste water treatment
    • Y02A20/208Off-grid powered water treatment

Landscapes

  • Sewage (AREA)

Abstract

The invention belongs to the technical field of urban sewage discharge and treatment, in particular to a sewage deodorization and discharge system with water storage pipes. In the system, water storage pipes are additionally arranged between a sewage pipe and a sewage discharge pipeline, between the sewage discharge pipeline and a septic tank, and between the septic tank and a pit as well as between two pits, wherein the water storage pipe is in an arc shape, and a distance from the upper edge of the pipeline to the bottom of a lower arc is not larger than 2.5 times of the pipe diameter; the bottom of an upper arc is lower than the lower edge of the pipeline; and a sewage well is arranged between the pits and a total sewage discharge pipe. The pipeline is sealed by utilizing water stored in an arc section of the water storage pipe so as to ensure that gas in the pipeline cannot circulate. The system can be applied to the construction of a new sewage discharge system and the transformation of an old sewage discharge system, has wide application range and can solve the problem of odors of toilets. Moreover, the arc pipeline reduces the resistance of flowing water, and meanwhile, feculences in water can be effectively prevented from depositing at the bottom of the arc so as to avoid pipeliune blockage. The system can also solve the problem of odors given by pits of housing districts and roads and improve the travel environment of people.

Description

The sewage deodorization and discharge system of band trap
Technical field:
The invention belongs to urban sewage discharge and administer technical field, be specifically related to a kind of sewage deodorization and discharge system with trap.
Background technology:
Along with economic development, increasing of people's income, the increasing quality of life of paying close attention to oneself of people, but, perplex the foul smell problem of people's washroom for a long time, the foul smell problem of sewer, cloudy well that is seen everywhere and cloudy well foul smell problem never are solved, have a strong impact on people's quality of life, at washroom foul smell problem and sewer foul smell problem, people have designed " U " shape pipe and serpentine pipe, these two kinds of pipelines are to have a certain amount of water in pipeline, thereby it is air in air in the washroom and the sewer pipe is isolated, prevent that the foul smell in the sewer pipe from leading to washroom even indoor by channel flow, this method has well solved the foul smell problem of washroom, but, no matter be " U " shape pipe or serpentine pipe, its resistance to flowing water is all very big, dirt in the water deposits in pipe bent position easily, thereby cause line clogging, cause many inconvenience to people's life, no matter be to see cloudy well everywhere in the sub-district or on the highway, if running into cloudy well stops up, leak, the stench that distributes in the cloudy well brings very big influence for people's trip.
Summary of the invention:
In sum, in order to overcome the deficiency of prior art problem, the invention provides a kind of sewage deodorization and discharge system with trap, it can be used for the construction of new foul water system, also can be used for the transformation to existing system, applied range, can effectively solve washroom foul smell problem, and pipeline is not easy to stop up, and can also solve the foul smell that the cloudy well on sub-district and the highway distributes, and improves people's living environment.
For realizing above-mentioned target, the technical solution used in the present invention is:
A kind of sewage deodorization and discharge system with trap, comprise sewer pipe 3, sewer pipe 3 is provided with first soil pipe 1 and second soil pipe 5, second soil pipe 5 connects the 3rd soil pipe 7, the horizontal segment of sewer pipe 3 connects septic tank 9, septic tank 9 connects the first cloudy well 12 by first pipeline 10, the first cloudy well 12 connects the second cloudy well 15 by second pipeline 13, the second cloudy well 15 connects the 3rd public cloudy well 18 that municipal administration is provided with by the 3rd pipeline 16, wherein: described first soil pipe 1, be respectively arranged with first trap 2 on the horizontal segment of second soil pipe 5 and the 3rd soil pipe 7, second trap 4 and the 3rd trap 6, the horizontal segment of sewer pipe 3 is arranged under the liquid level of septic tank 9, described first pipeline, 10 length are at least 1m, the two ends of first pipeline 10 are arranged on the liquid level of the septic tank 9 and the first cloudy well 12, first pipeline 10 is provided with the 4th trap 11, the length of second pipeline 13 is at least 1m, second pipeline 13 two ends be arranged on the liquid level of the first cloudy well 12 and the second cloudy well 15, second pipeline 13 is provided with the 5th trap 14, the length of the 3rd pipeline 16 is at least 1m, the 3rd pipeline 16 two ends be arranged on the liquid level of the second cloudy well 15 and the 3rd cloudy well 18, the 3rd pipeline 16 is provided with the 6th trap 17, be provided with sink hole 20 between the described the 3rd cloudy well 18 and the blowdown main 22, sink hole 20 is connected with the 3rd cloudy well 18 by the 4th pipeline 19, the 4th pipeline 19 two ends be arranged under the liquid level of the 3rd cloudy well 18 and sink hole 20, sink hole 20 is arranged on the liquid level of sink hole 20 and blowdown main 22 by the two ends that the 5th pipeline 21 connects blowdown main 22 the 5th pipeline 21, the well head sealing of sink hole 20, the distance 〉=1m between its well head and the ground.
Further, be provided with the 7th trap 8 between described sewer pipe 3 and the septic tank 9.
Further, the described sink hole 20 and the 3rd cloudy well 18 shared boreholes wall, the shared borehole wall is provided with passage 23, and passage 23 is arranged under the liquid level of sink hole 20 and the 3rd cloudy well 18.
Further, the horizontal segment of described first pipeline 10, second pipeline 13, the 3rd pipeline 16, the 4th pipeline 19 two ends and first soil pipe 1, second soil pipe 5, the 3rd soil pipe 7 all keeps level.
Further, described first trap 2, second trap 4, the 3rd trap 6, the 7th trap 8, the 4th trap 11, the 5th trap 14 and the 6th trap 17 are circular arc, the caliber of 26 distance≤2.5 times at the bottom of the circular arc down, pipeline upper edge 24,27 are lower than pipeline lower edge 25 at the bottom of the last circular arc.
Beneficial effect of the present invention is:
1, the invention provides a kind of sewage deodorization and discharge system with trap, it mainly utilizes the water that retains in the pipeline with seal for pipe joints, and the gas in the pipeline can not be flowed, and can not form convection current, reaches the purpose of deodorization.
2, the present invention can be used for the construction of new foul water system, also can be used for transformation to old foul water system, applied range, can effectively solve washroom foul smell problem, the trap that is provided with on soil pipe and the blow-off pipe is the circular arc pipeline, not only can reduce the resistance of flowing water, can prevent effectively that simultaneously dirt in the sealing is in the circular arc bottom deposit, avoid line clogging, can also solve the foul smell that the cloudy well on sub-district and the highway distributes, improve people's living trip environment.
3, the present invention can utilize current material construction, and do not need to add auxiliary material such as deodorant and can realize deodorization functions, labor and material saving, easy construction, construction costs is low.
Description of drawings:
Fig. 1 is used for the schematic diagram that new foul water system is built for the present invention;
Fig. 2 is used for the schematic diagram that existing foul water system is transformed for the present invention;
Fig. 3 is the enlarged drawing of A portion among Fig. 1 of the present invention.
The specific embodiment:
The present invention is described in further detail below in conjunction with drawings and Examples.
Embodiment one
As Fig. 1, shown in 3, sewer pipe 3 is provided with first soil pipe 1 and second soil pipe 5, second soil pipe 5 connects the 3rd soil pipe 7, on the horizontal segment of first soil pipe 1, be respectively arranged with first trap 2 on the horizontal segment of second soil pipe 5 and on the horizontal segment of the 3rd soil pipe 7, second trap 4 and the 3rd trap 6, the horizontal segment of sewer pipe 3 connects septic tank 9, the horizontal segment of sewer pipe 3 is arranged under the liquid level of septic tank 9, septic tank 9 connects the first cloudy well 12 by first pipeline 10, the length of first pipeline 10 is 1m, first pipeline, 10 two ends keep level, the two ends of first pipeline 10 are arranged on the liquid level of the septic tank 9 and the first cloudy well 12, first pipeline 10 is provided with the 4th trap 11, the first cloudy well 12 connects the second cloudy well 15 by second pipeline 13, the length of second pipeline 13 is 2m, second pipeline, 13 two ends keep level, the two ends of second pipeline 13 are arranged on the liquid level of the first cloudy well 12 and the second cloudy well 15, second pipeline 13 is provided with the 5th trap 14, the second cloudy well 15 connects the 3rd public cloudy well 18 by the 3rd pipeline 16, the length of the 3rd pipeline 16 is 4m, the 3rd pipeline 16 two ends keep level, the two ends of the 3rd pipeline 16 are arranged on the liquid level of the second cloudy well 15 and the 3rd cloudy well 18, the 3rd pipeline 16 is provided with the 6th trap 17, the 3rd cloudy well 18 connects sink hole 20 by the 4th pipeline 19, the two ends of the 4th pipeline 19 are arranged under the liquid level of the 3rd cloudy well 18 and sink hole 20, sink hole 20 connects blowdown main 22 by the 5th pipeline 21, the two ends of the 5th pipeline 21 are arranged on the liquid level of sink hole 20 and blowdown main 22, the well head sealing of sink hole 20, distance between its well head and the ground is 1m, referring to Fig. 3, first trap 2, second trap 4, the 3rd trap 6, the 4th trap 11, the 5th trap 14 and the 6th trap 17 are circular arc, its pipeline upper edge 24 distance of 26 at the bottom of the following circular arc is the caliber of twice, and 27 are lower than pipeline lower edge 25 at the bottom of the last circular arc.
Shown in Fig. 1,3, during use, with 1 blowdown of first soil pipe is example, sewage flows to sewer pipe 3 from first soil pipe 1, flows to septic tank 9 through sewer pipe 3, flows to the first cloudy well 12 through septic tank 9 by first pipeline 10 then, flow to the second cloudy well 15 through second pipeline 13 again, flow to the 3rd cloudy well 18 through the 3rd pipeline 16 again, flow to sink hole 20 through the 4th pipeline 19 again, after the 5th pipeline 21 flows to blowdown main 22.
As Fig. 1, shown in 3, after blowdown stops, the circular arc portion of first trap 2 has a certain amount of water, water is with 1 sealing of first soil pipe, thereby prevent that the foul smell in the sewer pipe 3 from entering in the washroom, the horizontal segment of sewer pipe 3 is arranged under the liquid level of septic tank 9, like this after blowdown stops, horizontal segment at sewer pipe 3 can have a certain amount of water, with sewer pipe 3 sealings, prevent that the gas in the septic tank 9 from entering sewer pipe 3, first pipeline 10 between the septic tank 9 and the first cloudy well 12 is provided with the 4th trap 11, after blowdown stops, there is a certain amount of water in the arc sections branch of the 4th trap 11, water is with 10 sealings of first pipeline, thereby stop the gas communication between the septic tank 9 and the first cloudy well 12, as a same reason, the 5th trap 14 between the first cloudy well 12 and the second cloudy well 15 is with 13 sealings of second pipeline, prevent the gas communication between the first cloudy well 12 and the second cloudy well 15, the 6th trap 17 between the second cloudy well 15 and the 3rd cloudy well 18 is with 16 sealings of the 3rd pipeline, prevent the gas communication between the second cloudy well 15 and the 3rd cloudy well 18, the 3rd cloudy well 18 connects sink hole 20 by the 4th pipeline 19, the two ends of the 4th pipeline 19 are arranged under the liquid level of the 3rd cloudy well 18 and sink hole 20, prevent the gas communication between the 3rd cloudy well 18 and the sink hole 20, so just guaranteed that the gas in the entire sewage exhaust system can not circulate each other, gas does not flow, foul smell just can't spread, thereby realizes the purpose of deodorization.
Embodiment two
As shown in Figure 2, repeat embodiment one, following difference is arranged: be provided with the 7th trap 8 between sewer pipe 3 and the septic tank 9, the sink hole 20 and the 3rd cloudy well 18 shared boreholes wall, the shared borehole wall is provided with passage 23, and passage 23 is arranged under the liquid level of sink hole 20 and the 3rd cloudy well 18.As shown in Figure 3, the 7th trap 8 is a circular arc, pipeline upper edge 24 distance of 26 at the bottom of the following circular arc is 1.5 times a caliber, 27 are lower than pipeline lower edge 25 at the bottom of the last circular arc, present embodiment is the transformation at old foul water system, it mainly is to set up the 7th trap 8 between the sewer pipe 3 of old foul water system and septic tank 9, respectively at first pipeline 10, set up the 4th trap 11 on second pipeline 13 and the 3rd pipeline 16, the 5th trap 14 and the 6th trap 17, between the 3rd cloudy well 18 and sewer house steward 22, sink hole 20 is set, the sink hole 20 and the 3rd cloudy well 18 shared boreholes wall, sink hole 20 and the 3rd cloudy well 18 are by passage 23 UNICOMs, passage 23 is arranged under the liquid level of sink hole 20 and the 3rd cloudy well 18, and sink hole 20 is connected by the 5th pipeline 21 with blowdown main 22.
Be noted that at last, the above embodiment is to the explanation of technical solution of the present invention and unrestricted, other modification that is equal to replacement or makes of affiliated technical field those of ordinary skill according to prior art, as long as do not exceed the thinking and the scope of technical solution of the present invention, all should be included within the interest field of the presently claimed invention.

Claims (5)

1. sewage deodorization and discharge system with trap, comprise sewer pipe (3), sewer pipe (3) is provided with first soil pipe (1) and second soil pipe (5), second soil pipe (5) connects the 3rd soil pipe (7), the horizontal segment of sewer pipe (3) connects septic tank (9), septic tank (9) connects the first cloudy well (12) by first pipeline (10), the first cloudy well (12) connects the second cloudy well (15) by second pipeline (13), the second cloudy well (15) connects the 3rd public cloudy well (18) that municipal administration is provided with by the 3rd pipeline (16), it is characterized in that: described first soil pipe (1), second soil pipe (5), be respectively arranged with first trap (2) on the horizontal segment of the 3rd soil pipe (7), second trap (4) and the 3rd trap (6), the horizontal segment of sewer pipe (3) is arranged under the liquid level of septic tank (9), the length of described first pipeline (10) is at least 1m, the two ends of first pipeline (10) are arranged on the liquid level of the septic tank (9) and the first cloudy well (12), first pipeline (10) is provided with the 4th trap (11), the length of second pipeline (13) is at least 1m, the two ends of second pipeline (13) are arranged on the liquid level of the first cloudy well (12) and the second cloudy well (15), second pipeline (13) is provided with the 5th trap (14), the length of the 3rd pipeline (16) is at least 1m, the two ends of the 3rd pipeline (16) are arranged on the liquid level of the second cloudy well (15) and the 3rd cloudy well (18), the 3rd pipeline (16) is provided with the 6th trap (17), be provided with sink hole (20) between the described the 3rd cloudy well (18) and the blowdown main (22), sink hole (20) is connected with the 3rd cloudy well (18) by the 4th pipeline (19), the two ends of the 4th pipeline (19) are arranged under the liquid level of the 3rd cloudy well (18) and sink hole (20), sink hole (20) connects blowdown main (22) by the 5th pipeline (21), the two ends of the 5th pipeline (21) are arranged on the liquid level of sink hole (20) and blowdown main (22), the well head sealing of sink hole (20), the distance 〉=1m between its well head and the ground.
2. the sewage deodorization and discharge system of band trap according to claim 1 is characterized in that: be provided with the 7th trap (8) between described sewer pipe (3) and the septic tank (9).
3. the sewage deodorization and discharge system of band trap according to claim 1, it is characterized in that: the described sink hole (20) and the shared borehole wall of the 3rd cloudy well (18), the shared borehole wall is provided with passage (23), and passage (23) is arranged under the liquid level of sink hole (20) and the 3rd cloudy well (18).
4. the sewage deodorization and discharge system of band trap according to claim 1 is characterized in that: the horizontal segment of the two ends of described first pipeline (10), second pipeline (13), the 3rd pipeline (16), the 4th pipeline (19) and first soil pipe (1), second soil pipe (5), the 3rd soil pipe (7) all keeps level.
5. the sewage deodorization and discharge system of band trap according to claim 1 and 2, it is characterized in that: described first trap (2), second trap (4), the 3rd trap (6), the 7th trap (8), the 4th trap (11), the 5th trap (14) and the 6th trap (17) are circular arc, the caliber of distance≤2.5 times of (26) at the bottom of the following circular arc, pipeline upper edge (24), (27) are lower than pipeline lower edge (25) at the bottom of the last circular arc.
CN200910227218XA 2009-12-01 2009-12-01 Sewage deodorization and discharge system with water storage pipes Expired - Fee Related CN101736803B (en)

Priority Applications (1)

Application Number Priority Date Filing Date Title
CN200910227218XA CN101736803B (en) 2009-12-01 2009-12-01 Sewage deodorization and discharge system with water storage pipes

Applications Claiming Priority (1)

Application Number Priority Date Filing Date Title
CN200910227218XA CN101736803B (en) 2009-12-01 2009-12-01 Sewage deodorization and discharge system with water storage pipes

Publications (2)

Publication Number Publication Date
CN101736803A CN101736803A (en) 2010-06-16
CN101736803B true CN101736803B (en) 2011-09-07

Family

ID=42460787

Family Applications (1)

Application Number Title Priority Date Filing Date
CN200910227218XA Expired - Fee Related CN101736803B (en) 2009-12-01 2009-12-01 Sewage deodorization and discharge system with water storage pipes

Country Status (1)

Country Link
CN (1) CN101736803B (en)

Citations (3)

* Cited by examiner, † Cited by third party
Publication number Priority date Publication date Assignee Title
DE9214863U1 (en) * 1992-11-02 1993-01-28 Koch, Hans-Helmut, Dipl.-Betriebsw., 5600 Wuppertal Self-sufficient toilet facility
CN1516773A (en) * 2001-05-23 2004-07-28 ����ˡ�J������˹ Toilet system
WO2007109722A3 (en) * 2006-03-22 2008-04-10 Bonnie Schnitta Plumbing trap system

Patent Citations (3)

* Cited by examiner, † Cited by third party
Publication number Priority date Publication date Assignee Title
DE9214863U1 (en) * 1992-11-02 1993-01-28 Koch, Hans-Helmut, Dipl.-Betriebsw., 5600 Wuppertal Self-sufficient toilet facility
CN1516773A (en) * 2001-05-23 2004-07-28 ����ˡ�J������˹ Toilet system
WO2007109722A3 (en) * 2006-03-22 2008-04-10 Bonnie Schnitta Plumbing trap system

Also Published As

Publication number Publication date
CN101736803A (en) 2010-06-16

Similar Documents

Publication Publication Date Title
CN104129889B (en) A kind of community, Mountainous City rainwater treatment reclaiming system
CN105951969B (en) A kind of water storage flood drainage system and storage discharge method
CN205839797U (en) There is the underground pipe gallery of water storage function
JP3213600U (en) Washed vent siphon structure of sewer installation pipe
CN205875342U (en) Urban rainwater filters storage leakage system
CN101736803B (en) Sewage deodorization and discharge system with water storage pipes
CN205296347U (en) Arrangement structure that utility tunnel internal drain pipe said
CN106284591A (en) A kind of pervious concrete pipeline system reducing rain water pollutant content
CN207633472U (en) Sponge urban water system for building district
KR101433076B1 (en) System for managing stormwater runoff and underground water
CN207243686U (en) A kind of overpass rain processing system
CN203821558U (en) Back-flowing-proof decompression well
CN110029721A (en) A kind of combine with the pipe culvert of blowdown and first rain Regulation Function cuts dirty structure
JP2005350867A (en) Rainwater utilization system
CN205475601U (en) River course box culvert with distribution of rain and sewage and overflow function
CN205444388U (en) Pipeline holds structure of drainage
CN210151877U (en) Novel rainwater inspection well with built-in sewage pipeline
CN204370519U (en) A kind of domatic flowing water and road surface water of utilizing is as the tunnel fire protection system at water source
CN206956891U (en) A kind of sponge city double-layer drainage pipeline with filtering function
CN205604409U (en) Compound complete piping system of rainwater
CN206245445U (en) Suitable for the drainpipe of sponge urban construction
CN104975644A (en) Special pipe storage system for road initial rainwater
CN220377471U (en) Sewage collection device suitable for mountain area is in shore water villages and towns
CN219219299U (en) Intelligent flow discarding well
CN216238847U (en) Rainwater purification and diversion device for sponge city

Legal Events

Date Code Title Description
C06 Publication
PB01 Publication
C10 Entry into substantive examination
SE01 Entry into force of request for substantive examination
C14 Grant of patent or utility model
GR01 Patent grant
CF01 Termination of patent right due to non-payment of annual fee

Granted publication date: 20110907

Termination date: 20141201

EXPY Termination of patent right or utility model