CN101736105B - Method for perforating and positioning engineering air port and air supply device of blast furnace - Google Patents

Method for perforating and positioning engineering air port and air supply device of blast furnace Download PDF

Info

Publication number
CN101736105B
CN101736105B CN2008101531341A CN200810153134A CN101736105B CN 101736105 B CN101736105 B CN 101736105B CN 2008101531341 A CN2008101531341 A CN 2008101531341A CN 200810153134 A CN200810153134 A CN 200810153134A CN 101736105 B CN101736105 B CN 101736105B
Authority
CN
China
Prior art keywords
air port
furnace
furnace shell
carry out
perforate
Prior art date
Legal status (The legal status is an assumption and is not a legal conclusion. Google has not performed a legal analysis and makes no representation as to the accuracy of the status listed.)
Active
Application number
CN2008101531341A
Other languages
Chinese (zh)
Other versions
CN101736105A (en
Inventor
索建红
Current Assignee (The listed assignees may be inaccurate. Google has not performed a legal analysis and makes no representation or warranty as to the accuracy of the list.)
MCC Tiangong Construction Co Ltd
Original Assignee
MCC Tiangong Construction Co Ltd
Priority date (The priority date is an assumption and is not a legal conclusion. Google has not performed a legal analysis and makes no representation as to the accuracy of the date listed.)
Filing date
Publication date
Application filed by MCC Tiangong Construction Co Ltd filed Critical MCC Tiangong Construction Co Ltd
Priority to CN2008101531341A priority Critical patent/CN101736105B/en
Publication of CN101736105A publication Critical patent/CN101736105A/en
Application granted granted Critical
Publication of CN101736105B publication Critical patent/CN101736105B/en
Active legal-status Critical Current
Anticipated expiration legal-status Critical

Links

Images

Landscapes

  • Furnace Housings, Linings, Walls, And Ceilings (AREA)

Abstract

The invention relates to a method for perforating and positioning an engineering air port and an air supply device of a blast furnace, which is carried out according to the following steps: (1) reinforcing plates are installed on single-piece furnace casings, a saddle plate is arranged between the two adjacent single-piece furnace casings after a plurality of single-piece furnace casings are spliced, and a reinforcing component is installed between the two opposite single-piece furnace casings; (2) the furnace casings at the section of the air port are hung, and the inspection of the elevation, the levelness, the ellipticity and the staggered edges of the grooves of circular seams and the inspection of the centrad of the furnace casings are sequentially carried out; then, the circular seams of the furnace casings are welded clockwise, and finally, the inspection of the internal quality of the circular seams is carried out; (3) the furnace casings of an upper zone are installed and positioned, and the centers of the furnace casings are positioned; and (4) the air port is perforated and positioned. The invention has the advantages that the furnace casings have favorable stability, the accuracy of the opening and the positioning of the air port can be ensured, the positioning is more accurate, and the manpower is saved.

Description

Blast furnace engineering air port and air-supply arrangement perforate localization method
Technical field:
The present invention relates to the mechanical workout boring method, particularly a kind of blast furnace engineering air port and air-supply arrangement perforate localization method.
Background technology:
At present, along with the development of ironmaking technology, newly-built large blast furnace engineering plays huge pushing effect to the Economic development of metallurgy industry.Therefore, during newly-built or overhaul blast furnace, the on-the-spot perforate of last furnace shell structure is had higher requirement.And in the metallurgical construction industry, the perforate bearing accuracy in large-scale iron-smelting blast furnace engineering air port cannot say for sure card, some make with installation process in progressive error be difficult for eliminating, this brings bigger influence to go into operation back stove operation and the coefficient that taps a blast furnace of blast furnace.In the at present conventional at home blast-furnace tuyere locating holes construction, still adopt comparatively the primary halving method to construct, cause air port systems center and stove center to intersect at a point or deviation bigger.
Summary of the invention:
The object of the invention just is to overcome the deficiency that exists in the above-mentioned prior art, and a kind of blast furnace engineering air port and air-supply arrangement perforate localization method are provided, and this method accurate positioning, speed are fast, and practices thrift manpower.
Technical scheme of the present invention is: a kind of blast furnace engineering air port and air-supply arrangement perforate localization method; It is characterized in that: carry out according to the following step: 1, on the monolithic furnace shell, gusset plate is installed; After the assembly unit of some monolithic furnace shells; Between two adjacent monolithic furnace shells, saddle plate is housed, and between two relative monolithic furnace shells, reinforcing member is installed; 2, carry out the lifting of air port section furnace shell, and carry out the inspection of absolute altitude, levelness, ovality, the inspection of circumferential weld groove misalignment and furnace shell centrad successively; Then the furnace shell ring is met and carry out welded clockwise, encircle at last and meet the internal soundness inspection; 3, will go up band furnace shell installation in position, and carry out the furnace shell positioned centrally; 4, carry out the perforate location in air port; After at first adopting precision level and transit instrument to get ready the horizontal center line in air port and vertical center line it is labeled on the furnace shell inwall; Check then whether its horizontal center line conforms to the drawing design with vertical center line; Confirm just can carry out perforate after errorless; Because perforate locating accuracy in air port directly influences the installation and inner precision of building by laying bricks or stones of air port system, so the perforate location must guarantee that the absolute altitude in each air port and medullary ray intersect at a point.
Advantage of the present invention is: 1, the present invention is through the fabrication and installation precision of strict control furnace shell; Make furnace shell have satisfactory stability property; And reduce furnace shell welding distortion error through reasonable arrangement furnace shell welding sequence, and then increased the control accuracy of furnace shell welding.Therefore, can guarantee the bearing accuracy that the air port system installs effectively.2, the present invention can guarantee that the absolute altitude in each air port and medullary ray intersect at a point, and therefore can further guarantee air port perforate locating accuracy.3, the present invention adopts accurate spirit-leveling instrument and transit instrument, therefore also can guarantee air port perforate locating accuracy, makes the location more accurate, and has practiced thrift manpower.
Description of drawings:
Fig. 1 is a process flow sheet of the present invention.
Fig. 2 is vertical center line location, an air port synoptic diagram.
Fig. 3 is inlet horizontal medullary ray (absolute altitude) location synoptic diagram.
Fig. 4 is back, location, an air port synoptic diagram,
Fig. 5 monolithic furnace shell is reinforced synoptic diagram.
Fig. 6 reinforces synoptic diagram before the furnace shell welding.
Fig. 7 is the A-A sectional view of Fig. 6.
Fig. 8 is furnace shell girth welding sequence control principle figure.
Fig. 9 is furnace shell band and band assembly unit inspection synoptic diagram.
Embodiment:
As shown in the figure: a kind of blast furnace engineering air port and air-supply arrangement perforate localization method; Carry out according to the following step: 1, gusset plate 2 is installed on monolithic furnace shell 1; After the assembly unit of some monolithic furnace shells; Between two adjacent monolithic furnace shells, saddle plate 3 is housed, and between two relative monolithic furnace shells, reinforcing member 4 is installed; 2, carry out the lifting of air port section furnace shell, and carry out the inspection of absolute altitude, levelness, ovality, the inspection of circumferential weld groove misalignment and furnace shell centrad successively; Then the furnace shell ring is met and carry out welded clockwise, encircle at last and meet the internal soundness inspection; 3, will go up band furnace shell installation in position, and carry out the furnace shell positioned centrally; 4, carry out the perforate location (like Fig. 2,3, shown in 4) in air port; After at first adopting precision level 5 and transit instrument 6 to get ready the horizontal center line in air port and vertical center line it is labeled on furnace shell 7 inwalls; Check then whether its horizontal center line conforms to the drawing design with vertical center line; Confirm just can carry out perforate after errorless; Because perforate locating accuracy in air port directly influences the installation and inner precision of building by laying bricks or stones of air port system, so the perforate location must guarantee that the absolute altitude in each air port and medullary ray intersect at a point 8.

Claims (1)

1. blast furnace engineering air port and air-supply arrangement perforate localization method; It is characterized in that: carry out according to the following step: (1) is equipped with gusset plate on the monolithic furnace shell; After the assembly unit of some monolithic furnace shells; Between two adjacent monolithic furnace shells, saddle plate is housed, and between two relative monolithic furnace shells, reinforcing member is installed; (2) carry out the lifting of air port section furnace shell, and carry out the inspection of absolute altitude, levelness, ovality, the inspection of circumferential weld groove misalignment and furnace shell centrad successively; Then the furnace shell ring is met and carry out welded clockwise, encircle at last and meet the internal soundness inspection; (3) will go up band furnace shell installation in position, and carry out the furnace shell positioned centrally; (4) perforate of carrying out the air port is located; After at first adopting precision level and transit instrument to get ready the horizontal center line in air port and vertical center line it is labeled on the furnace shell inwall; Check then whether its horizontal center line conforms to the drawing design with vertical center line; Confirm just can carry out perforate after errorless; Because perforate locating accuracy in air port directly influences the installation and inner precision of building by laying bricks or stones of air port system, so the perforate location must guarantee that the absolute altitude in each air port and medullary ray intersect at a point.
CN2008101531341A 2008-11-18 2008-11-18 Method for perforating and positioning engineering air port and air supply device of blast furnace Active CN101736105B (en)

Priority Applications (1)

Application Number Priority Date Filing Date Title
CN2008101531341A CN101736105B (en) 2008-11-18 2008-11-18 Method for perforating and positioning engineering air port and air supply device of blast furnace

Applications Claiming Priority (1)

Application Number Priority Date Filing Date Title
CN2008101531341A CN101736105B (en) 2008-11-18 2008-11-18 Method for perforating and positioning engineering air port and air supply device of blast furnace

Publications (2)

Publication Number Publication Date
CN101736105A CN101736105A (en) 2010-06-16
CN101736105B true CN101736105B (en) 2012-03-14

Family

ID=42460135

Family Applications (1)

Application Number Title Priority Date Filing Date
CN2008101531341A Active CN101736105B (en) 2008-11-18 2008-11-18 Method for perforating and positioning engineering air port and air supply device of blast furnace

Country Status (1)

Country Link
CN (1) CN101736105B (en)

Families Citing this family (1)

* Cited by examiner, † Cited by third party
Publication number Priority date Publication date Assignee Title
CN109666770A (en) * 2018-12-28 2019-04-23 中国二冶集团有限公司 The construction method of tuyere flange equipment mounting and adjusting

Citations (3)

* Cited by examiner, † Cited by third party
Publication number Priority date Publication date Assignee Title
US6030430A (en) * 1998-07-24 2000-02-29 Material Conversions, Inc. Blast furnace with narrowed top section and method of using
CN1330160A (en) * 2000-06-27 2002-01-09 北京科技大学 Method for in-situ measuring charge of blast furnace
CN1967121A (en) * 2005-11-16 2007-05-23 烟台鲁宝钢管有限责任公司 Rebuilding method for ring furnace

Patent Citations (3)

* Cited by examiner, † Cited by third party
Publication number Priority date Publication date Assignee Title
US6030430A (en) * 1998-07-24 2000-02-29 Material Conversions, Inc. Blast furnace with narrowed top section and method of using
CN1330160A (en) * 2000-06-27 2002-01-09 北京科技大学 Method for in-situ measuring charge of blast furnace
CN1967121A (en) * 2005-11-16 2007-05-23 烟台鲁宝钢管有限责任公司 Rebuilding method for ring furnace

Also Published As

Publication number Publication date
CN101736105A (en) 2010-06-16

Similar Documents

Publication Publication Date Title
CN105046359A (en) BIM (Building Information Modelling) technology based municipal pipeline factory prefabrication and installation method
CN104690471B (en) The spherical case base ring of a kind of 5M level thin-walled tank stitches little clearance control method
CN101723056B (en) Ship multi-beam acoustic equipment mounting process
CN107127615A (en) The axle turntable special hydraulic clamp of pump housing three surface processing four
CN103394792B (en) Method for forming hole in bustle pipe of blast furnace blowing-in device
CN101736105B (en) Method for perforating and positioning engineering air port and air supply device of blast furnace
CN104439849A (en) Main platform ear plate fast assembling tooling and ear plate assembling method
CN109332982B (en) Steel bar butt joint positioning device for pile foundation steel reinforcement cage machining and construction method
CN106119454A (en) The installation method of blast-furnace hot-air surrounding pipes
CN112251557A (en) Opening method of blast furnace hot air surrounding pipe
CN105625754B (en) A kind of HTGR Nuclear Power Plant steam generator partition module
CN202576455U (en) Opening device at tuyere of blast furnace hot air bustle pipe
CN101260964A (en) Ring apparatus foundation bolt rapid mounting method
CN209891544U (en) Large-diameter steel pipe dome ring beam
CN113814676B (en) Manufacturing method of large-diameter tower equipment
CN101462211A (en) Laser delicate-adjustment large-sized mechanical component coaxial automatic welding technique
CN106826176B (en) A kind of support platform well drilling module guide-localization installation method
CN206263499U (en) A kind of servicing unit being connected with hard tube for exhaust hose
CN206346817U (en) A kind of device for being used to install exhaust hose and hard tube
CN207295754U (en) A kind of high precision apparatus foundation built-in bolt sleeve device
CN117984053A (en) Manufacturing method of air compressor box body
CN106216864A (en) A kind of radial canal preheater assembly welding method
CN204321476U (en) Main platform otic placode fixtures for rapid assembly
CN104100094A (en) Installation method of personnel air lock of steel containment of nuclear power plant
CN206233213U (en) Man-made island oil gas module pad pier structure with installation and guide device

Legal Events

Date Code Title Description
C06 Publication
PB01 Publication
C10 Entry into substantive examination
SE01 Entry into force of request for substantive examination
C14 Grant of patent or utility model
GR01 Patent grant