CN101718208B - 煤矿井下“u+h”型布置的通风系统 - Google Patents

煤矿井下“u+h”型布置的通风系统 Download PDF

Info

Publication number
CN101718208B
CN101718208B CN200910227867XA CN200910227867A CN101718208B CN 101718208 B CN101718208 B CN 101718208B CN 200910227867X A CN200910227867X A CN 200910227867XA CN 200910227867 A CN200910227867 A CN 200910227867A CN 101718208 B CN101718208 B CN 101718208B
Authority
CN
China
Prior art keywords
air intake
work plane
air
lane
assistant conveyance
Prior art date
Legal status (The legal status is an assumption and is not a legal conclusion. Google has not performed a legal analysis and makes no representation as to the accuracy of the status listed.)
Active
Application number
CN200910227867XA
Other languages
English (en)
Other versions
CN101718208A (zh
Inventor
贺天才
闫振东
董文敏
程建祯
赵彬
Current Assignee (The listed assignees may be inaccurate. Google has not performed a legal analysis and makes no representation or warranty as to the accuracy of the list.)
SHANXI JINCHENG ANTHRACITE MINING GROUP TECHNOLOGY RESEARCH INSTITUTE CO., LTD.
Shanxi Jincheng Anthracite Mining Group Co Ltd
Original Assignee
Shanxi Jincheng Anthracite Mining Group Co Ltd
Priority date (The priority date is an assumption and is not a legal conclusion. Google has not performed a legal analysis and makes no representation as to the accuracy of the date listed.)
Filing date
Publication date
Application filed by Shanxi Jincheng Anthracite Mining Group Co Ltd filed Critical Shanxi Jincheng Anthracite Mining Group Co Ltd
Priority to CN200910227867XA priority Critical patent/CN101718208B/zh
Publication of CN101718208A publication Critical patent/CN101718208A/zh
Application granted granted Critical
Publication of CN101718208B publication Critical patent/CN101718208B/zh
Active legal-status Critical Current
Anticipated expiration legal-status Critical

Links

Images

Abstract

本发明涉及一种煤矿开采中使用的通风布置系统,具体为一种适用于高瓦斯矿的煤矿井下“U+H”型布置的通风系统。解决了现有煤矿工作面回采过程中通风系统存在的问题。包括回采工作面,回采工作面一侧依次设置有皮带运输兼进风巷、辅助运输兼进风巷,回采工作面另一侧依次设有辅助运输兼进风巷、第一回风巷、第二回风巷,皮带运输兼进风巷、及两个辅助运输兼进风巷进风并通过回采工作面前通道与第一回风巷、第二回风巷连通后回风,形成三进两回“U+H”型通风系统。

Description

煤矿井下“U+H”型布置的通风系统
技术领域
本发明涉及一种煤矿开采中使用的通风布置系统,具体为一种适用于高瓦斯矿的煤矿井下“U+H”型布置的通风系统。
背景技术
煤矿回采工作面的通风系统分为一进一回、一进二回、二进一回、二进二回、三进二回几种通风系统类型,适用不同的开采条件、巷道布置、采煤方法、工作面接替等情况的通风要求,设计选择不同的通风系统,对于高瓦斯工作面,以上方法有许多问题没有解决:如上隅角瓦斯的有效治理,采空区瓦斯抽放系统的建立,采掘关系紧张,通风风量不足等多种弊端。
发明内容
本发明为了解决现有煤矿工作面回采过程中通风系统存在的问题而提供了一种煤矿井下“U+H”型布置的通风系统。
本发明是由以下技术方案实现的,一种煤矿井下“U+H”型布置的通风系统,结构包括工作面巷道采用五巷布置,三条进风两条回风通风方式,具体包括设置在工作面一侧的双巷,其中临近工作面的一条为承担工作面运煤、进风任务的皮带运输兼进风巷,另一条为承担工作面材料、设备、人员运输及工作面进风的进风及辅助运输巷;还包括设置在在工作面另一侧的三巷,从内向外依次为承担工作面进风及辅助运输的辅助运输兼进风巷,承担工作面回风任务的两条回风巷;其中进风及辅助运输巷截止于工作面处,并通过联络巷和皮带运输兼进风巷连通,皮带运输兼进风巷、辅助运输兼进风巷与工作面前的通道贯通并连通整个采空区,辅助运输兼进风巷在工作面前后分别通过联络巷与回风巷连通,两条回风巷延伸至采空区最里端,并在此处连通,这样一来形成“U+H”型通风系统。
采用以三进两回为基础的“U+H”型通风系统,工作面回采后报废三巷,留两巷作为下一个工作面的巷道复用,这样每个工作面的巷道工程仅需开掘三条巷道。
与现有技术相比,本发明所述“U+H”型通风系统的特点及优势:
(1)、每个工作面有五条巷道,巷道在工作面两侧布置,通风阻力小,过风断面大,风量大,风排瓦斯能力大,适宜高瓦斯矿井的开采。
(2)、采区内工作面采用顺序开采,巷道复用率高、工作面工程量小,有利于工作面的接替。
(3)、工作面上隅角后部有通风负压,上隅角瓦斯不易超限,同时,也抑制了采空区瓦斯向工作面涌出。
(4)、回风巷为双巷,改变了上隅角处采空区瓦斯的流动方向,工作面后部的复用巷道保留其通风系统,便于人员进入观察巷道情况,便于巷道维护,同时省掉了复用排瓦斯带来的不安全隐患。
三进二回的“U+H”型通风系统。工作面上隅角后部有通风负压,上隅角瓦斯不易超限,同时,也抑制了采空区瓦斯向工作面涌出。双回风巷布置。始终保留其通风系统,不密封、不排瓦斯,能够及时有效维护,为下个工作面缩短了接替时间。
(5)、工作面侧巷道均为进风巷,五巷布置,靠工作面两侧均为进风巷。机电设备均布置在进风巷内,风流稳定,作业环境好。
(6)、工作面两侧分别有一条辅助运输巷,工作面两侧均布置辅助运输巷,便于工作面顺槽皮带、负荷中心设备的检修,工作面材料及人员运输均在进风巷内,运输环境好,运输快捷,能及时、安全处理设备故障,员工上下班辅助时间短,减轻了员工的劳动强度。
附图说明
图1为本发明的通风系统结构布置示意图
图中:1-煤柱,2、3-回风巷,4-煤柱,5-联络巷,6-隔离墙,7-辅助运输兼进风巷,8-皮带运输兼进风巷,9-进风及辅助运输巷,10-煤柱,11-联络巷,12-隔离墙,13-工作面,14-采空区
具体实施方式
如图1所示意,一种煤矿井下“U+H”型布置的通风系统,结构为工作面巷道采用五巷布置,三条进风两条回风通风方式,具体包括设置在工作面13一侧的双巷,其中临近工作面的一条为承担工作面运煤、进风任务的皮带运输兼进风巷8,另一条为承担工作面材料、设备、人员运输及工作面进风的进风及辅助运输巷9;还包括设置在在工作面13另一侧的三巷,从内向外依次为承担工作面进风及辅助运输的辅助运输兼进风巷7,承担工作面回风任务的两条回风巷3、2;其中进风及辅助运输巷9截止于工作面13处,并通过联络巷11和皮带运输兼进风巷8连通,皮带运输兼进风巷8、辅助运输兼进风巷7与工作面13前的通道贯通并连通整个采空区14,辅助运输兼进风巷7在工作面13前后分别通过联络巷5与回风巷3连通,两条回风巷2、3延伸至采空区14最里端,并在此处连通,这样一来形成“U+H”型通风系统。
其具体的通风路径如图中箭头所指方向:皮带运输兼进风巷8、辅助运输兼进风巷7、进风及辅助运输巷9三巷进风,然后将工作面13及采空区涌出的高浓度瓦斯带走,然后通过联络巷5进入到回风巷3,一部分气流顺回风巷3排出,另一部分则反向到达最里端,然后经过联络巷到达回风巷2,再通过回风巷2排出。

Claims (1)

1.一种煤矿井下“U+H”型布置的通风系统,结构为工作面巷道采用五巷布置,三条进风两条回风通风方式,其特征在于:具体包括设置在工作面(13)一侧的双巷,其中临近工作面的一条为承担工作面运煤、进风任务的皮带运输兼进风巷(8),另一条为承担工作面材料、设备、人员运输及工作面进风的进风及辅助运输巷(9);还包括设置在在工作面(13)另一侧的三巷,从内向外依次为承担工作面进风及辅助运输的辅助运输兼进风巷(7),承担工作面回风任务的两条回风巷(3、2);其中进风及辅助运输巷(9)截止于工作面(13)处,并通过联络巷(11)和皮带运输兼进风巷(8)连通,皮带运输兼进风巷(8)、辅助运输兼进风巷(7)与工作面(13)前的通道贯通并连通整个采空区(14),辅助运输兼进风巷(7)在工作面(13)前后分别通过联络巷(5)与两条回风巷(2、3)连通,两条回风巷(2、3)延伸至采空区(14)最里端,并在此处连通,这样一来形成“U+H”型通风系统。
CN200910227867XA 2009-12-17 2009-12-17 煤矿井下“u+h”型布置的通风系统 Active CN101718208B (zh)

Priority Applications (1)

Application Number Priority Date Filing Date Title
CN200910227867XA CN101718208B (zh) 2009-12-17 2009-12-17 煤矿井下“u+h”型布置的通风系统

Applications Claiming Priority (1)

Application Number Priority Date Filing Date Title
CN200910227867XA CN101718208B (zh) 2009-12-17 2009-12-17 煤矿井下“u+h”型布置的通风系统

Publications (2)

Publication Number Publication Date
CN101718208A CN101718208A (zh) 2010-06-02
CN101718208B true CN101718208B (zh) 2011-02-23

Family

ID=42432837

Family Applications (1)

Application Number Title Priority Date Filing Date
CN200910227867XA Active CN101718208B (zh) 2009-12-17 2009-12-17 煤矿井下“u+h”型布置的通风系统

Country Status (1)

Country Link
CN (1) CN101718208B (zh)

Families Citing this family (8)

* Cited by examiner, † Cited by third party
Publication number Priority date Publication date Assignee Title
CN102345469B (zh) * 2010-08-05 2013-12-04 太原理工大学 研究不同通风条件下采空区瓦斯运移的试验模拟装置
CN102071958B (zh) * 2011-01-21 2012-07-25 中国矿业大学 采煤工作面反y型通风方法
CN102392642A (zh) * 2011-11-02 2012-03-28 王晓利 一种无煤柱回采工作面的巷道布置方法
CN103603673B (zh) * 2013-11-22 2015-11-04 山西晋城无烟煤矿业集团有限责任公司 回采工作面并列双u型巷道
CN103628911B (zh) * 2013-12-06 2016-04-20 中国矿业大学 一种综采/放工作面分段式沿空留巷方法
CN103939125A (zh) * 2014-04-29 2014-07-23 中国矿业大学(北京) 一种采空区热风治理方法
CN106968701A (zh) * 2017-05-27 2017-07-21 中国恩菲工程技术有限公司 用于连续采矿系统的通风结构
CN110469329B (zh) * 2018-05-10 2021-07-23 华亭煤业集团有限责任公司 矿井回采末期的开采方法

Citations (4)

* Cited by examiner, † Cited by third party
Publication number Priority date Publication date Assignee Title
WO2001088337A2 (en) * 2000-05-19 2001-11-22 Eskom Underground mining method
CN1648412A (zh) * 2004-01-19 2005-08-03 靖远煤业有限责任公司 高瓦斯综采放顶煤工作面通风系统
CN101498225A (zh) * 2009-02-24 2009-08-05 太原理工大学 一种放顶煤工作面u+i型通风系统
CN201301723Y (zh) * 2008-11-26 2009-09-02 山西焦煤集团有限责任公司 综采工作面通风结构

Patent Citations (4)

* Cited by examiner, † Cited by third party
Publication number Priority date Publication date Assignee Title
WO2001088337A2 (en) * 2000-05-19 2001-11-22 Eskom Underground mining method
CN1648412A (zh) * 2004-01-19 2005-08-03 靖远煤业有限责任公司 高瓦斯综采放顶煤工作面通风系统
CN201301723Y (zh) * 2008-11-26 2009-09-02 山西焦煤集团有限责任公司 综采工作面通风结构
CN101498225A (zh) * 2009-02-24 2009-08-05 太原理工大学 一种放顶煤工作面u+i型通风系统

Also Published As

Publication number Publication date
CN101718208A (zh) 2010-06-02

Similar Documents

Publication Publication Date Title
CN101718208B (zh) 煤矿井下“u+h”型布置的通风系统
CN201802435U (zh) 煤矿通风系统
CN102071958B (zh) 采煤工作面反y型通风方法
CN201723246U (zh) 采煤工作面瓦斯抽采排放通风结构
CN201301723Y (zh) 综采工作面通风结构
CN103775085B (zh) 急倾斜中厚煤层柔性掩护支架采掘一体支护无煤柱采煤法
CN1963149A (zh) 建筑物下矸石置换条带煤柱的开采方法
CN102865092B (zh) 回采工作面u+u型巷道通风系统
CN101649741A (zh) 大U套小u方式布置的巷道
CN105221179A (zh) 一种高瓦斯矿井y型通风方法
CN103953345B (zh) 一种沿空小断面留巷开采方法
CN103821515A (zh) 一种对拉工作面充填采煤工艺
CN102748064A (zh) 一种大采高综放工作面瓦斯治理方法
CN103485786A (zh) 一种急倾斜煤层走向长壁机械化开采方法
CN109252860A (zh) 一种薄煤层连采机高度机械化开采方法
CN103174424B (zh) 一种长壁布置下的房柱式采煤法
CN104975857B (zh) 全井工区段无煤柱无沿空平巷的采煤方法
CN102865099A (zh) “三下”开采充填工艺
CN102031972A (zh) 露井联采的l型开采方法
CN108412531A (zh) 一种急倾斜厚煤层综采放顶煤的z型回风设备及方法
CN102425431A (zh) 一种极近距离煤层开采巷道布置方法
CN202882975U (zh) 急倾斜厚煤层水平分段放顶煤沿空留巷z型通风设备
CN103266907A (zh) 一种用于局部瓦斯突出的隧道施工通风系统
CN109915198B (zh) 采煤工作面超前钻孔全风压瓦斯排放方法
CN104832179B (zh) 急倾斜厚煤层水平分段全负压通风放顶煤采煤方法

Legal Events

Date Code Title Description
C06 Publication
PB01 Publication
C10 Entry into substantive examination
SE01 Entry into force of request for substantive examination
C14 Grant of patent or utility model
GR01 Patent grant
ASS Succession or assignment of patent right

Owner name: SHANXI JIN COAL GROUP TECHNOLOGY INSTITUTE LLC

Effective date: 20130225

C41 Transfer of patent application or patent right or utility model
TR01 Transfer of patent right

Effective date of registration: 20130225

Address after: 048006 Shanxi province Jincheng city BeiShiDian town of Shanxi Coal Group

Patentee after: Shanxi Jincheng Anthracite Mining Industry Group Co., Ltd.

Patentee after: SHANXI JINCHENG ANTHRACITE MINING GROUP TECHNOLOGY RESEARCH INSTITUTE CO., LTD.

Address before: 048006 Shanxi province Jincheng city BeiShiDian town of Shanxi Coal Group

Patentee before: Shanxi Jincheng Anthracite Mining Industry Group Co., Ltd.