CN101694099B CN2009101540311A CN200910154031A CN101694099B CN 101694099 B CN101694099 B CN 101694099B CN 2009101540311 A CN2009101540311 A CN 2009101540311A CN 200910154031 A CN200910154031 A CN 200910154031A CN 101694099 B CN101694099 B CN 101694099B
Authority
CN
China
Prior art keywords
pylon
hole
hypomere
epimere
pile frame
Prior art date
Legal status (The legal status is an assumption and is not a legal conclusion. Google has not performed a legal analysis and makes no representation as to the accuracy of the status listed.)
Expired - Fee Related
Application number
CN2009101540311A
Other languages
English (en)
Other versions
CN101694099A (zh
Inventor
马海龙
马宇飞
Current Assignee (The listed assignees may be inaccurate. Google has not performed a legal analysis and makes no representation or warranty as to the accuracy of the list.)
Zhejiang Sci Tech University ZSTU
Zhejiang University of Science and Technology ZUST
Original Assignee
Zhejiang Sci Tech University ZSTU
Priority date (The priority date is an assumption and is not a legal conclusion. Google has not performed a legal analysis and makes no representation as to the accuracy of the date listed.)
Filing date
Publication date
Application filed by Zhejiang Sci Tech University ZSTU filed Critical Zhejiang Sci Tech University ZSTU
Priority to CN2009101540311A priority Critical patent/CN101694099B/zh
Publication of CN101694099A publication Critical patent/CN101694099A/zh
Application granted granted Critical
Publication of CN101694099B publication Critical patent/CN101694099B/zh
Expired - Fee Related legal-status Critical Current
Anticipated expiration legal-status Critical

Links

Images

Abstract

本发明公开了一种升降式锚杆静压桩桩架,包括下段桩架组件和上段桩架组件;下段桩架组件包括底座(1),在底座(1)上分别设置相互平行的下段左柱架(3)和下段右柱架(6),下段左柱架(3)上设有下左通孔(4),在下段右柱架(6)上设有下右通孔(7);上段桩架组件包括相互平行的上段左柱架(9)和上段右柱架(11),上段左柱架(9)上设有上左通孔(10),在上段右柱架(11)上设有上右通孔(12);缀板(8)的两端分别与上段左柱架(9)和上段右柱架(11)相连;下左通孔(4)与上左通孔(10)通过插销(13)的一端相连;下右通孔(7)与上右通孔(12)通过插销(13)的另一端相连。该桩架能随意调节高度。

Description

一种升降式锚杆静压桩桩架
技术领域
本发明涉及土木工程桩基础的一种压桩桩架,特别涉及一种升降式锚杆静压桩桩架。
背景技术
现有的锚杆静压桩桩架长度固定,不可伸长或缩短。遇到压桩空间高度不足时,就要截断桩架长度,重新加工,以便能适应压桩空间高度的不足。压桩完成后,还要恢复原压桩桩架长度,给锚杆静压桩施工带来了很大不便。
发明内容
本发明要解决的技术问题是提供一种能随意调节高度的升降式锚杆静压桩桩架,该桩架能适用于任意狭小空间的锚杆静压桩的施工。
为了解决上述技术问题,本发明提供一种升降式锚杆静压桩桩架,包括下段桩架组件和上段桩架组件;
下段桩架组件包括底座,在底座上分别设置相互平行的下段左柱架和下段右柱架,下段左柱架上设有至少2个的下左通孔,在下段右柱架上设置与下左通孔相平行对应的下右通孔;
上段桩架组件包括相互平行的上段左柱架和上段右柱架,上段左柱架上设有至少2个的上左通孔,在上段右柱架上设置与上左通孔相平行对应的上右通孔;缀板的两端分别与上段左柱架和上段右柱架相连;
下左通孔与上左通孔通过插销的一端相连;下右通孔与上右通孔通过插销的另一端相连。
作为本发明的升降式锚杆静压桩桩架的改进:下段左柱架和下段右柱架之间的间距=上段左柱架和上段右柱架之间的间距;下左通孔之间的孔距=上左通孔之间的孔距。
作为本发明的升降式锚杆静压桩桩架的进一步改进:在底座上还分别设置相互平行的前侧板和后侧板,下段左柱架和下段右柱架均被夹持在前侧板和后侧板之间。
作为本发明的升降式锚杆静压桩桩架的进一步改进:下段左柱架、下段右柱架、上段左柱架和上段右柱架均为U型柱架。
本发明的升降式锚杆静压桩桩架,由于下段桩架组件和上段桩架组件通过插销活动相连,因此能任意调节下段桩架组件和上段桩架组件在长度方向上的重叠长度,所以整个锚杆静压桩桩架能轻易伸长或缩短,从而适应不同施工高度的既有建构筑物的压桩,特别适应既有建构筑物狭小空间内的压桩。在本发明中,4个柱架均选用U型柱架,能使升降式锚杆静压桩桩架既有重量轻的优势,又能保证足够的强度。
本发明的升降式锚杆静压桩桩架,由于下段桩架组件和上段桩架组件能相互分离,因此具有分段重量轻、易于搬运的优点,实际使用中能提高压桩效率。
附图说明
下面结合附图对本发明的具体实施方式作进一步详细说明。
图1是本发明的升降式锚杆静压桩桩架的立体结构示意图;
图2是图1中的下段桩架组件的立体结构示意图;
图3是图1中的上段桩架组件的立体结构示意图;
图中:
1--底座、2--后侧板、30--下段左柱架、4--下左通孔、5--前侧板、6--下段右柱架、7--下右通孔、8--缀板、9--上段左柱架、10--上左通孔、11--上段右柱架、12--上右通孔、13--插销。
具体实施方式
实施例1、一种升降式锚杆静压桩桩架,由下段桩架组件、上段桩架组件和插销13组成。
下段桩架组件包括底座1,在底座1上分别设置相互平行、且大小相同的下段左柱架3和下段右柱架6,下段左柱架3和下段右柱架6均选用相同的U型柱架(该U型柱架由底面和2个侧面组成)。在底座1上还分别设置相互平行的前侧板5和后侧板2,下段左柱架3和下段右柱架6均被夹持在前侧板5和后侧板2之间,即下段左柱架3的两侧分别与前侧板5和后侧板2固定相连,同理,下段右柱架6的两侧也分别与前侧板5和后侧板2固定相连。设置前侧板5和后侧板2的目的是使下段左柱架3和下段右柱架6在底座1上稳定得更加牢固。在下段左柱架3的底面的中心线位置处设有5个孔距相等的下左通孔4;在下段右柱架6的底面的中心线位置处设置与下左通孔4相平行对应的下右通孔7,即在下段右柱架6的底面的中心线位置处设置5个孔距相等的下右通孔7,下左通孔4的孔距=下右通孔7的孔距,下左通孔4的孔径=下右通孔7的孔径。
上段桩架组件包括相互平行、且大小相同的上段左柱架9和上段右柱架11,上段左柱架9和上段右柱架11均选用相同的U型柱架(该U型柱架由底面和2个侧面组成),该U型柱架略窄于下段左柱架3和下段右柱架6所选用的U型柱架;从而保证上段左柱架9能在下段左柱架3内滑动、上段右柱架11能在下段右柱架6内滑动。在上段左柱架9和上段右柱架11之间设置4块相互平行的缀板8,每块缀板8的两端分别与上段左柱架9和上段右柱架11固定相连。上段左柱架9的底面的中心线位置处设有7个孔距相等的上左通孔10;在上段右柱架11的底面的中心线位置处设置与上左通孔10相平行对应的上右通孔12,即在上段右柱架11底面的中心线位置处设置7个孔距相等的上右通孔12,上左通孔10的孔距=上右通孔12的孔距=下左通孔4的孔距,上左通孔10的孔径=上右通孔12的孔径=下左通孔4的孔径。
下段左柱架3和下段右柱架6之间的间距=上段左柱架9和上段右柱架11之间的间距。
将上段左柱架9套装在下段左柱架3内,将上段右柱架11套装在下段右柱架6内;从而使2个下左通孔4与2个上左通孔10相重叠,2个下右通孔7与2个上右通孔12相重叠。在下段桩架组件和上段桩架组件之间设置2个插销13,即,每个插销13依次穿过一个上右通孔12、一个下右通孔7、一个上左通孔10和一个下左通孔4;从而使下段桩架组件和上段桩架组件组合成一个完整的升降式锚杆静压桩桩架。
通过改变下右通孔7与上右通孔12相重叠的个数(也同时改变了上左通孔10和下左通孔4相重叠的个数),就可以改变升降式锚杆静压桩桩架的高度。
最后,还需要注意的是,以上列举的仅是本发明的一个具体实施例。显然,本发明不限于以上实施例,还可以有许多变形。本领域的普通技术人员能从本发明公开的内容直接导出或联想到的所有变形,均应认为是本发明的保护范围。

Claims (4)

1.一种升降式锚杆静压桩桩架,其特征是:包括下段桩架组件和上段桩架组件;
所述下段桩架组件包括底座(1),在底座(1)上分别设置相互平行的下段左柱架(3)和下段右柱架(6),下段左柱架(3)上设有至少2个下左通孔(4),在下段右柱架(6)上设置与下左通孔(4)相平行对应的下右通孔(7);
所述上段桩架组件包括相互平行的上段左柱架(9)和上段右柱架(11),上段左柱架(9)上设有至少2个上左通孔(10),在上段右柱架(11)上设置与上左通孔(10)相平行对应的上右通孔(12);缀板(8)的两端分别与上段左柱架(9)和上段右柱架(11)相连;
下左通孔(4)与上左通孔(10)通过插销(13)的一端相连;下右通孔(7)与上右通孔(12)通过插销(13)的另一端相连。
2.根据权利要求1所述的升降式锚杆静压桩桩架,其特征是:所述下段左柱架(3)和下段右柱架(6)之间的间距等于上段左柱架(9)和上段右柱架(11)之间的间距;下左通孔(4)之间的孔距等于上左通孔(10)之间的孔距。
3.根据权利要求1或2所述的升降式锚杆静压桩桩架,其特征是:在底座(1)上还分别设置相互平行的前侧板(5)和后侧板(2),下段左柱架(3)和下段右柱架(6)均被夹持在前侧板(5)和后侧板(2)之间。
4.根据权利要求3所述的升降式锚杆静压桩桩架,其特征是:所述下段左柱架(3)、下段右柱架(6)、上段左柱架(9)和上段右柱架(11)均为U型柱架。
CN2009101540311A 2009-10-22 2009-10-22 一种升降式锚杆静压桩桩架 Expired - Fee Related CN101694099B (zh)

Priority Applications (1)

Application Number Priority Date Filing Date Title
CN2009101540311A CN101694099B (zh) 2009-10-22 2009-10-22 一种升降式锚杆静压桩桩架

Applications Claiming Priority (1)

Application Number Priority Date Filing Date Title
CN2009101540311A CN101694099B (zh) 2009-10-22 2009-10-22 一种升降式锚杆静压桩桩架

Publications (2)

Publication Number Publication Date
CN101694099A CN101694099A (zh) 2010-04-14
CN101694099B true CN101694099B (zh) 2010-12-08

Family

ID=42093092

Family Applications (1)

Application Number Title Priority Date Filing Date
CN2009101540311A Expired - Fee Related CN101694099B (zh) 2009-10-22 2009-10-22 一种升降式锚杆静压桩桩架

Country Status (1)

Country Link
CN (1) CN101694099B (zh)

Families Citing this family (1)

* Cited by examiner, † Cited by third party
Publication number Priority date Publication date Assignee Title
CN102269648B (zh) * 2010-06-02 2014-03-26 煤炭科学研究总院 一种液压支架试验台及其调高方法

Citations (4)

* Cited by examiner, † Cited by third party
Publication number Priority date Publication date Assignee Title
CN2313962Y (zh) * 1997-11-14 1999-04-14 顺德市伦教镇荔村伟力机械五金厂 一种压桩机
CN2354997Y (zh) * 1999-02-08 1999-12-22 方阿河 液压步进式静力压桩机
FR2794149B1 (fr) * 1999-05-31 2003-01-17 Sing Hian Lau Amelioration concernant un appareil pour un systeme de battage a verins incorpores
WO2008111032A1 (en) * 2007-03-15 2008-09-18 Lilianto Ong Poi Nguan Method of preparing a hole for a post pile cast in place using hydraulic pressure and apparatus therefor

Patent Citations (4)

* Cited by examiner, † Cited by third party
Publication number Priority date Publication date Assignee Title
CN2313962Y (zh) * 1997-11-14 1999-04-14 顺德市伦教镇荔村伟力机械五金厂 一种压桩机
CN2354997Y (zh) * 1999-02-08 1999-12-22 方阿河 液压步进式静力压桩机
FR2794149B1 (fr) * 1999-05-31 2003-01-17 Sing Hian Lau Amelioration concernant un appareil pour un systeme de battage a verins incorpores
WO2008111032A1 (en) * 2007-03-15 2008-09-18 Lilianto Ong Poi Nguan Method of preparing a hole for a post pile cast in place using hydraulic pressure and apparatus therefor

Non-Patent Citations (5)

* Cited by examiner, † Cited by third party
Title
JP平1-304217A 1989.12.07
张希,赵荣欣.锚杆静压桩施工过程及正常工作中的桩身应力分布研究.《施工技术》.2005,65-67. *
蔡有钊.小直径静压预制方桩施工方法.《山西建筑》.2007,第33卷(第10期),172-173. *
郭纯,陈华,高厚强.锚杆静压桩在井塔工程中的应用.《施工技术》.2005,(第s期), *
陈利民等.锚杆静压桩技术在住宅工程地基加固中的应用.《彭城职业大学学报》.2004,第19卷(第2期), *

Also Published As

Publication number Publication date
CN101694099A (zh) 2010-04-14

Similar Documents

Publication Publication Date Title
CN108678423B (zh) 钢筋混凝土结构逆向拆除竖向转换支撑结构
CN101694099B (zh) 一种升降式锚杆静压桩桩架
CN103043298A (zh) 魔力板类材料堆放支撑工具架
CN203885141U (zh) 一种可升降的展架
CN202830966U (zh) 一种用于陆地复合模块式钻机基础
CN103712811A (zh) 组合梁预应力式液压支架试验台
CN201794601U (zh) 一种可调向悬移顶梁液压支架
CN204906264U (zh) 一种太阳能发电站光伏板固定基座
CN201413959Y (zh) 电缆桥架
CN204826620U (zh) 一种建筑施工梁架
CN210888814U (zh) 一种修井机偏房支架装置
CN207420014U (zh) 一种加强型建筑模板装置
CN201228445Y (zh) 大结构体高空滑移安装落位装置
CN208456627U (zh) 一种承载力大的隧道钢模板
CN110255423A (zh) 一种用于提升的多级丝杆与提升油缸组合提升装置
CN207724283U (zh) 一种大型铸件加工用划线模板
CN207993340U (zh) 可拆装单层工业厂房教学模型
CN203643179U (zh) 组合梁预应力式液压支架试验台
CN116733108B (zh) 一种建筑用装配式钢结构
CN208200288U (zh) 一种液压同步增量举升装置
CN204881946U (zh) 一种用于气门导管的扭力测试机构
CN204473845U (zh) 一种新型料盘自动收放机构
CN205153309U (zh) 一种钢筋混凝土梁的中空门钢板组合式预埋结构架
CN203655314U (zh) 轻型薄煤层导杆式液压支架
CN220022686U (zh) 一种利用气弹簧可调节倾角的光伏支架装置

Legal Events

Date Code Title Description
C06 Publication
PB01 Publication
C10 Entry into substantive examination
SE01 Entry into force of request for substantive examination
C14 Grant of patent or utility model
GR01 Patent grant
C17 Cessation of patent right
CF01 Termination of patent right due to non-payment of annual fee

Granted publication date: 20101208