CN101635505B - Method for controlling structure of a plurality of input-series and output-parallel converters - Google Patents

Method for controlling structure of a plurality of input-series and output-parallel converters Download PDF

Info

Publication number
CN101635505B
CN101635505B CN2008101332795A CN200810133279A CN101635505B CN 101635505 B CN101635505 B CN 101635505B CN 2008101332795 A CN2008101332795 A CN 2008101332795A CN 200810133279 A CN200810133279 A CN 200810133279A CN 101635505 B CN101635505 B CN 101635505B
Authority
CN
China
Prior art keywords
converter
discontinuous operation
converters
operation cycle
make
Prior art date
Legal status (The legal status is an assumption and is not a legal conclusion. Google has not performed a legal analysis and makes no representation as to the accuracy of the status listed.)
Active
Application number
CN2008101332795A
Other languages
Chinese (zh)
Other versions
CN101635505A (en
Inventor
叶浩屹
曾剑鸿
吴洪洋
言超
刘腾
应建平
Current Assignee (The listed assignees may be inaccurate. Google has not performed a legal analysis and makes no representation or warranty as to the accuracy of the list.)
Delta Optoelectronics Inc
Original Assignee
Delta Optoelectronics Inc
Priority date (The priority date is an assumption and is not a legal conclusion. Google has not performed a legal analysis and makes no representation as to the accuracy of the date listed.)
Filing date
Publication date
Application filed by Delta Optoelectronics Inc filed Critical Delta Optoelectronics Inc
Priority to CN2008101332795A priority Critical patent/CN101635505B/en
Publication of CN101635505A publication Critical patent/CN101635505A/en
Application granted granted Critical
Publication of CN101635505B publication Critical patent/CN101635505B/en
Active legal-status Critical Current
Anticipated expiration legal-status Critical

Links

Images

Abstract

The invention discloses a method for controlling a structure of a plurality of input-series and output-parallel converters, which comprises the following steps: providing N converters of the structure, wherein the inputs of the N converters are connected in series and the outputs of the N converters are connected in parallel; ensuring that each of the N converters has an interval working period, an interval working time segment and an interval working duty ratio, wherein the ratio of the interval working time segment to the interval working period is the interval working duty ratio; and making the N converters work alternately in the interval working period, wherein the N is an integer of more than or equal to 2.

Description

The control method of the structure of a plurality of converters of input series and output parallel
Technical field
The present invention discloses a kind of control method of structure of a plurality of converters based on input series and output parallel, and particularly the converter when this structure works in the staggered batch (-type) control method under underloading or the idle mode, with the efficient of the converter that improves this structure.
Background technology
The development trend of DC/DC converter is the same as most power supply product, develops towards high efficiency direction.The high efficiency here not only requires when nominal load, to realize, also requires in full-load range, promptly is downloaded on the lenient side in the fully loaded scope to realize.This is just to the efficient of DC/DC converter, and especially the efficient during underloading is had higher requirement.
Adopt the framework of the input of a plurality of DC/DC converters, output parallel connection, and close when underloading wherein that the way of portion convertor can improve the efficient of whole converter when underloading effectively, this method is called as cut (phase shedding) control method.
What Fig. 1 showed is the framework of a kind of a plurality of DC/DC converter input series connection, output-parallel, and wherein these a plurality of DC/DC converters can or be controlled resonant converter for pwm converter.Converter as shown in Figure 11,2 ..., the n input connects receiving input voltage vin in proper order, and each converter input be parallel with corresponding input capacitance C1, C2 ..., Cn; Converter 1,2 ..., n output be parallel to output capacitance Co so that output voltage V o to be provided.This framework is fit to be applied in the high voltage input, the occasion of big electric current output.Simultaneously, to have the characteristic of each converter load of automatic equalization be that the DC component of each converter input current is identical to this framework.Yet because the connected mode of input series connection can't directly be carried out cut control between each converter.With two input series connection shown in Figure 2, the DC/DC converter of output-parallel is this problem of example explanation below:
As shown in Figure 2, converter 1 and 2 inputs are connected in series with the reception input voltage vin in proper order, and corresponding dividing potential drop capacitor C 1, and C2 is parallel to the input of converter 1 and 2; Converter 1 and 2 output are connected in parallel so that output voltage V o to be provided.Wherein, Iin1 and Iin2 are respectively the DC components of the input current of converter 1 and 2, and Vin1 and Vin2 are respectively the voltage on dividing potential drop capacitor C 1 and the C2, and its DC component is expressed as Vin1_d and Vin2_d respectively.Under the sort circuit structure, according to different design requirements, each converter all exist one can operate as normal scope.At this moment, thus the input voltage of each converter exists a maximum Vmax and minimum value Vmin to guarantee that converter works normally in this input voltage range.Wherein the scope of input voltage is to obtain with requirements such as design requirement of exporting and element stress according to each converter input.
In the equal operate as normal of two converters and reach under the situation of stable state, Iin1=Iin2, the DC component of electric current is 0 among C1 and the C2, direct voltage Vin1_d and Vin2_d remain unchanged.If under certain loading condition, for example: under the underloading condition, close converter 1, then Iin1=0 causes direct current to flow through capacitor C 1 and C2, and C1 is charged, and C2 is discharged, and Vin1 rises, and Vin2 descends.When Vin2 drops to when being lower than converter 2 input voltage ranges, converter 1 and 2 is all with cisco unity malfunction.
Therefore be directed against These characteristics under the framework of a plurality of converter input series and output parallel, the present invention proposes the generation that a kind of novel controlling schemes can be avoided the problems referred to above, can effectively improve this framework again under the certain loads condition, for example the efficient of underloading.
Because of above-mentioned reason, the inventor improves prior art in view of the defective of known technology, invents out " control method of the structure of a plurality of converters of input series and output parallel " of the present invention.
Summary of the invention
Main purpose of the present invention is to provide a kind of staggered batch (-type) control method of structure of a plurality of converters based on input series and output parallel, works in the efficient under underloading or the idle mode with the converter that improves when this structure.
Another main purpose of the present invention is to provide a kind of control method of a structure of a plurality of converters that are used for input series and output parallel, comprises following step: provide this structure N converter, wherein the input series connection and the output-parallel of this N converter; Make this N converter respectively have a discontinuous operation cycle, a discontinuous operation time period and an interval working duty ratio, wherein this discontinuous operation time period was this interval working duty ratio than last this discontinuous operation cycle; And make this N converter with this discontinuous operation cycle alternation, wherein N is the integer more than or equal to 2.
According to above-mentioned method, N equals 2.
According to above-mentioned method, at least 2 converters of this N converter transmit identical power.
According to above-mentioned conception, this method also comprises a step: make the discontinuous operation cycle of these at least 2 converters identical.
According to above-mentioned method, this discontinuous operation time period of these at least 2 converters is complementary.
According to above-mentioned method, this discontinuous operation time period of these at least 2 converters overlaps.
According to above-mentioned method, there is a Dead Time section in this discontinuous operation time period of these at least 2 converters.
According to above-mentioned method, this method also comprises a step: make the discontinuous operation cycle of these at least 2 converters inequality.
According to above-mentioned method, at least 2 converters of this N converter transmit different power.
Another main purpose of the present invention is to provide a kind of control method of a structure of a plurality of converters that are used for input series and output parallel, comprises following step: provide this structure N converter, wherein the input series connection and the output-parallel of this N converter; Make at least one converter in this N converter have big discontinuous operation cycle and little discontinuous operation cycle; And make this at least one converter in an operating time section in this big discontinuous operation cycle, according to this little discontinuous operation cycle discontinuous operation, wherein N is the integer more than or equal to 2.
According to above-mentioned conception; This method also comprises a step: make this N converter all have big discontinuous operation cycle and little discontinuous operation cycle; And each converter is in an operating time section in this big discontinuous operation cycle, according to this little discontinuous operation cycle discontinuous operation.
According to above-mentioned method, this method also comprises a step: make respectively should the operating time section not overlapping each other of this N converter.
According to above-mentioned method, this method also comprises a step: what make this N converter should the operating time section be partly overlapping each other respectively.
According to above-mentioned method, this method also comprises a step: make respectively should the operating time section not overlapping each other of this N converter, and have a Dead Time section.
Next main purpose of the present invention is to provide a kind of control method of a structure of a plurality of converters that are used for input series and output parallel, comprises following step: provide this structure N converter, wherein the input series connection and the output-parallel of this N converter; Make this N converter all have an interval working duty ratio: k/N, wherein 0<k≤N and N are the integer more than or equal to 2; And make have an average k converter to work simultaneously by synchronization in this N converter.
According to above-mentioned method, k is a positive integer.
According to above-mentioned method, each converter all has a discontinuous operation cycle T, and the operating time section in the intermittent time section: (k/N) *T.
According to above-mentioned method, this method also comprises a step: make an initial time difference of the operating time section in this intermittent time section between any two adjacent converters in this N converter be (1/N) *T.
Description of drawings
Fig. 1 is the circuit diagram of structure of a plurality of DC/DC converters of a known input series and output parallel;
Fig. 2 is the circuit diagram of structure of two DC/DC converters of a known input series and output parallel;
Fig. 3 (a)~(c) be one according to first to the 3rd preferred embodiment of the present invention conception when the delivering power of two DC/DC converters among Fig. 2 the associated voltage and the enable signal oscillogram of the control method when identical and discontinuous operation cycle is identical;
Fig. 4 be one according to the 4th preferred embodiment of the present invention conception in Fig. 2 the associated voltage and the enable signal oscillogram of the identical and asynchronous control method of discontinuous operation cycle of the delivering power of two DC/DC converters;
Fig. 5 (a)~(b) be one according to the 5th to the 6th preferred embodiment of the present invention conception the associated voltage and the enable signal oscillogram of the control method when the delivering power difference of two DC/DC converters among Fig. 2 and discontinuous operation cycle are identical;
Fig. 6 (a)~(c) one all comprises the enable signal oscillogram of the control method of two discontinuous operations during the cycle when two DC/DC converters among Fig. 2 according to the 7th to the 9th preferred embodiment of the present invention conception; And
Fig. 7 (a)~(b) is the enable signal oscillogram of a control method that a plurality of DC/DC converters switch each other in Fig. 1 according to the tenth to the 11 preferred embodiment of the present invention conception.
Embodiment
For let above-mentioned purpose of the present invention, feature and advantage can be more obviously understandable, hereinafter is special lifts preferred embodiment, and conjunction with figs., elaborates as follows:
In the framework shown in Figure 2, the average power of two converter transmission can have different combinations, and for example the power of converter 1 and 2 transmission can be identical, also can be different.Suppose that the average power that converter 1 and 2 transmits is respectively P1, P2, then P1=Vin1_d *Iin1, P2=Vin2_d *Iin2.Because Iin1=Iin2, Vin1_d/Vin2_d=P1/P2 then, promptly the DC quantity of input voltage is directly proportional with the average power of transmission.
It is identical that control method shown in Fig. 3 (a)-(c) is based on the average power that two converters transmit in Fig. 2 framework, i.e. the condition of P1=P2, that is Vin1_d=Vin2_d.Under control method shown in Figure 3, setting Vin1_d=Vin2_d earlier is Vcenter, and Vcenter=Vin/2.Vmax is the maximum input voltage that each converter can bear among Fig. 3 (a)-(c), and Vmin is the required minimum voltage of each converter operate as normal.EN1 and EN2 are respectively the enable signal of converter 1 and converter 2, and because of being that high potential enables, when EN1 or EN2 were high potential, corresponding converter 1 or 2 was worked.
Control method one shown in Fig. 3 (a) is first preferred embodiment of the present invention, two converter alternations, and the time period of work do not have overlappingly, promptly any has only a converter job constantly.T0~t1 is in the time period, and enable signal EN2 is a high potential, converter 2 work this moment, and converter 1 is not worked, so Vin2 descends the Vin1 rising; T1~t2 is in the time period, and enable signal EN1 is a high potential, converter 1 work this moment, and converter 2 is not worked, so Vin1 descends the Vin2 rising.Vin1 and Vin2 all fluctuate up and down at Vcenter, but are no more than by Vmax and Vmin institute restricted portion.Wherein t0~t2 time period is a discontinuous operation cycle, and (t1~t2) is the operating time section in a discontinuous operation cycle to t0~t1.Shown in Fig. 3 (a), converter 1 is identical with 2 discontinuous operation frequency, and operating time section separately also is all 50% of a discontinuous operation cycle mutually, and promptly separately interval working duty ratio (operating time section/discontinuous operation cycle) is 50%.Can be implemented in arbitrary moment in this way has only a converter in work, thus the efficient when having improved the converter underloading, but and the input voltage that guarantees each converter all within the scope of operate as normal and safety.
Control method two shown in Fig. 3 (b) is second preferred embodiment of the present invention; Two converter alternations; But have one two period that converter is all worked between the working hour of two converters, promptly the operating time section in the discontinuous operation cycle of two converters has crossover.In time period, converter 1 and 2 is worked simultaneously at t0~t1 and t2~t3; In t1~t2 only converter 2 work in the time period, its input voltage vin 2 descends and input voltage vin 1 rising of converter 1; In t3~t4 only converter 1 work in the time period, its input voltage vin 1 descends, and the input voltage vin 2 of converter 2 rises.Shown in Fig. 3 (b); Converter 1 is identical with 2 discontinuous operation frequency; Be the inverse of discontinuous operation cycle t0~t4, and the operating time section in its discontinuous operation cycle separately is also identical, equals t0~t3; Account for more than 50% of whole discontinuous operation cycle, promptly separately interval working duty ratio is greater than 50%.
Control method three shown in Fig. 3 (c) is the 3rd preferred embodiment of the present invention; Two converter alternations; But have one two all idle period of converter between the working hour of two converters, promptly the operating time section in the discontinuous operation cycle of two converters does not have crossover.In t0~t1 only converter 2 work in the time period, its input voltage vin 2 descends and input voltage vin 1 rising of converter 1; In t2~t3 only converter 1 work in the time period, its input voltage vin 1 descends and input voltage vin 2 risings of converter 2; In t1~t2 and t3~t4 time period, when two converters were not all worked, Vin1 and Vin2 all remained unchanged.Equally, Vin1 and Vin2 all fluctuate up and down at Vcenter, but are no more than by Vmax and Vmin institute restricted portion.Shown in Fig. 3 (c), converter 1 is identical with 2 discontinuous operation frequency, is the inverse of discontinuous operation cycle t0~t4.And the operating time in the discontinuous operation cycle of two converters is identical, but is below 50% of discontinuous operation cycle, and promptly separately interval working duty ratio is less than 50%.
Be different from the control method shown in Fig. 3 (a)-(c), converter 1 all is identical with 2 discontinuous operation frequency, and in the 4th preferred embodiment shown in Figure 4, converter 1 and 2 discontinuous operation frequency are also inequality.As shown in Figure 4, t0~t2 time period is a discontinuous operation cycle of converter 1, and t0~t6 time period is a discontinuous operation cycle of converter 2, and the discontinuous operation frequency of converter 1 is 3 times of converter 2 like this.Wherein at t0~t1, t2~t3 time period inner conversion device 1 and 2 is worked simultaneously; Work independently at t1~t2 time period inner conversion device 2; At t3~t4, two converters are not worked in t5~t6 time period; Work independently at t4~t5 time period inner conversion device 1.
Among the embodiment described above, the power that converter 1 and 2 transmits is identical.Preferred embodiment shown in Fig. 5 (a)-(b) is the control method under the power different situations that transmit of converter 1 and 2.Identical among Fig. 5 (a)-(b) among the meaning of identical label representative and the front embodiment.In the preferred embodiment shown in Fig. 5 (a)-(b), converter 1 is identical with 2 discontinuous operation frequency, but its intermittently used duty ratio is different, and is directly proportional with the average power of its transmission.
Fig. 5 (a) is depicted as the 5th preferred embodiment of the present invention.Converter 1 is identical with 2 discontinuous operation cycle, all is t0~t2 time period.In time period, only converter 1 is worked at t0~t1, and the input voltage vin 2 of converter 2 rises; In time period, only converter 2 is worked at t1~t2, and the input voltage vin 2 of converter 2 descends.
Fig. 5 (b) is depicted as the 6th preferred embodiment of the present invention.Converter 1 is identical with 2 discontinuous operation cycle, all is t0~t4 time period.In time period, only converter 1 is worked at t0~t1, and the input voltage vin 2 of converter 2 rises; In time period, only converter 2 is worked at t2~t3, and the input voltage vin 2 of converter 2 descends; At t1~t2, t3~t4 is in the time period, and converter 1 and 2 is not worked, and the input voltage vin 2 of converter 2 remains unchanged.
In the control method shown in Fig. 3 (a)-(c), in the operating time of resting period section, all continuous operations of each converter.If also interrupter duty of each converter in the operating time in each converter discontinuous operation cycle section just becomes the control method shown in Fig. 6 (a)-(c), such two converters have all comprised two discontinuous operation cycles.
The 7th preferred embodiment of the present invention shown in Fig. 6 (a), t0~t2 time period is a discontinuous operation cycle T 1 of converter 2, wherein t0~t1 time period is the operating time of this discontinuous operation cycle T 1; At t0~t3 time period inner conversion device 2 with discontinuous operation cycle T 1 discontinuous operation; And quit work at t3~t4 time period inner conversion device 2; Therefore t0~t4 time period can be regarded as a big discontinuous operation cycle T 2 of converter 2, and wherein t0~t3 time period is the operating time in this discontinuous operation cycle T 2.Same converter 1 also exists a little discontinuous operation cycle and a big discontinuous operation cycle.Shown in Fig. 6 (a), the operating time section in the discontinuous operation cycle that it is big is nonoverlapping, but complementary.
Fig. 6 (b) is depicted as the 8th preferred embodiment of the present invention, and the embodiment difference shown in itself and Fig. 6 (a) is that the operating time section in big discontinuous operation cycle is partly overlapping.
Fig. 6 (c) is depicted as the 9th preferred embodiment of the present invention, and the embodiment difference shown in itself and Fig. 6 (a) is that the operating time section in big discontinuous operation cycle does not only have an overlapping Dead Time section such as the t3~t4 of also existing.
In like manner, in the control method shown in Fig. 4 and Fig. 5 (a)-(b), also can make any one converter discontinuous operation in the operating time section in the cycle of doing of knocking off betwixt, this converter has just comprised two discontinuous operation cycles like this.
Said method can expand in the transformer configuration of a plurality of input series connection as shown in Figure 1, output-parallel.Method shown in Fig. 7 (a) is the tenth preferred embodiment of the present invention.Setting converter quantity is n; Among Fig. 7 (a); The discontinuous operation cycle of each converter is T; Operating time section in an one of which discontinuous operation cycle for example for is that interval working duty ratio is
Figure S2008101332795D00082
; Converter 1 be operated in
Figure S2008101332795D00083
converter 2 be operated in
Figure S2008101332795D00084
converter n be operated in
Figure S2008101332795D00085
and wherein m be positive integer, 1≤m≤n.Can be implemented in synchronization only has m converter to work simultaneously.Work as n=2, during m=1, this method is the control method shown in Fig. 3 (a).
In the method shown in Fig. 7 (a), m is an integer, and can be implemented in synchronization has m converter to work simultaneously just.Method shown in Fig. 7 (b) is the 11 preferred embodiment of the present invention.Wherein k is an any number between 0~n; Each converter is alternation and the operating time is
Figure S2008101332795D00087
is that interval working duty ratio is that
Figure S2008101332795D00088
can guarantee like this in cycle T successively in cycle T, and the converter number of work is k in the time of average.Work as n=2,1<k<2 o'clock, this method is the control method shown in Fig. 3 (b).Work as n=2,0<k<1 o'clock, this method is the control method shown in Fig. 3 (c).
In sum; The present invention has disclosed a kind of staggered batch (-type) control method of a structure of a plurality of converters based on input series and output parallel; Converter to improve when this structure works in the efficient under underloading or the idle mode, thereby its progressive and novelty are arranged really.
Be with, though the present invention is described in detail by the above embodiments, and can change, all within claim scope of the present invention by the personnel of skilled.

Claims (10)

1. the control method of a structure of a plurality of converters that are used for input series and output parallel comprises the following step:
Provide this structure N converter, wherein the input series connection and the output-parallel of this N converter;
Make this N converter respectively have a discontinuous operation cycle, a discontinuous operation time period and an interval working duty ratio, wherein this discontinuous operation time period was this interval working duty ratio than last this discontinuous operation cycle; And
Make this N converter with this discontinuous operation cycle alternation, wherein N is the integer more than or equal to 2.
2. the method for claim 1 is characterized in that, said N equals 2.
3. the method for claim 1 is characterized in that, at least 2 converters of this N converter transmit identical power.
4. method as claimed in claim 3 is characterized in that, also comprises a step: make the discontinuous operation cycle of these at least 2 converters identical, wherein:
This discontinuous operation time period of these at least 2 converters is complementary; Or
This discontinuous operation time period of these at least 2 converters overlaps; Or
There is a Dead Time section in this discontinuous operation time period of these at least 2 converters.
5. method as claimed in claim 3 is characterized in that, also comprises a step: make the discontinuous operation cycle of these at least 2 converters inequality.
6. the method for claim 1 is characterized in that, wherein:
At least 2 converters of this N converter transmit different power;
This method also comprises a step: make the discontinuous operation cycle of these at least 2 converters identical, wherein:
This discontinuous operation time period of these at least 2 converters is complementary; Or
There is a Dead Time section in this discontinuous operation time period of these at least 2 converters.
7. the control method of a structure of a plurality of converters that are used for input series and output parallel comprises the following step:
Provide this structure N converter, wherein the input series connection and the output-parallel of this N converter;
Make at least one converter in this N converter have big discontinuous operation cycle and little discontinuous operation cycle; And
Make this at least one converter in an operating time section in this big discontinuous operation cycle, according to this little discontinuous operation cycle discontinuous operation, wherein N is the integer more than or equal to 2.
8. method as claimed in claim 7; It is characterized in that; Also comprise a step: make this N converter all have big discontinuous operation cycle and little discontinuous operation cycle; And each converter is in an operating time section in this big discontinuous operation cycle, and according to this little discontinuous operation cycle discontinuous operation, wherein this method also comprises a step:
Make respectively should the operating time section not overlapping each other of this N converter;
What make this N converter should the operating time section be partly overlapping each other respectively; Or
Make respectively should the operating time section not overlapping each other of this N converter, and have a Dead Time section.
9. the control method of a structure of a plurality of converters that are used for input series and output parallel comprises the following step:
Provide this structure N converter, wherein the input series connection and the output-parallel of this N converter;
Make this N converter all have an interval working duty ratio: k/N, wherein 0<k≤N, and N is the integer more than or equal to 2; And
Make and have an average k converter to work simultaneously by synchronization in this N converter.
10. method as claimed in claim 9 is characterized in that, wherein:
K is a positive integer; Or
Each converter all has a discontinuous operation cycle T, and the operating time section in the intermittent time section: (k/N) *T, and this method also comprises a step: make an initial time difference of the operating time section in this intermittent time section between any two adjacent converters in this N converter be (1/N) *T.
CN2008101332795A 2008-07-25 2008-07-25 Method for controlling structure of a plurality of input-series and output-parallel converters Active CN101635505B (en)

Priority Applications (1)

Application Number Priority Date Filing Date Title
CN2008101332795A CN101635505B (en) 2008-07-25 2008-07-25 Method for controlling structure of a plurality of input-series and output-parallel converters

Applications Claiming Priority (1)

Application Number Priority Date Filing Date Title
CN2008101332795A CN101635505B (en) 2008-07-25 2008-07-25 Method for controlling structure of a plurality of input-series and output-parallel converters

Publications (2)

Publication Number Publication Date
CN101635505A CN101635505A (en) 2010-01-27
CN101635505B true CN101635505B (en) 2012-08-15

Family

ID=41594599

Family Applications (1)

Application Number Title Priority Date Filing Date
CN2008101332795A Active CN101635505B (en) 2008-07-25 2008-07-25 Method for controlling structure of a plurality of input-series and output-parallel converters

Country Status (1)

Country Link
CN (1) CN101635505B (en)

Families Citing this family (11)

* Cited by examiner, † Cited by third party
Publication number Priority date Publication date Assignee Title
CN102035416B (en) * 2010-12-14 2014-04-16 北京理工大学 Method for controlling power equipartition of input-series output-series high-frequency link inverters
CN102158095B (en) * 2011-05-24 2013-08-14 卢其威 Full-bridge power inverter with series-input and series-output and control method thereof
US9762134B2 (en) * 2014-09-08 2017-09-12 Infineon Technologies Austria Ag Multi-cell power conversion method and multi-cell power converter
US9837921B2 (en) 2014-09-08 2017-12-05 Infineon Technologies Austria Ag Multi-cell power conversion method and multi-cell power converter
CN105743372A (en) * 2016-04-21 2016-07-06 张心益 Power conversion device of input power supply during superposed DC charging
CN106099862B (en) * 2016-06-20 2018-10-09 华南理工大学 A kind of low-voltage protection method based on multimode input-series and output-parallel structure
CN107634639B (en) * 2016-07-15 2021-03-02 中兴通讯股份有限公司 Current control method and device and power supply
CN107395014B (en) 2017-08-04 2019-09-03 华为技术有限公司 Power supply circuit, electronic building brick, mobile phone terminal and method for controlling power supply
CN110429824A (en) * 2019-08-08 2019-11-08 东北大学 A kind of two-way cascade input cascaded-output DC-DC transformation topology structure
CN111211679A (en) * 2020-02-18 2020-05-29 中国科学院电工研究所 High-power high-transformation-ratio high-voltage direct-current converter for space and photovoltaic power generation system
CN112187090B (en) * 2020-08-25 2022-06-14 南京工业大学 IPOx framework type high-voltage microsecond pulse power supply based on energy efficiency and stability design model

Citations (1)

* Cited by examiner, † Cited by third party
Publication number Priority date Publication date Assignee Title
CN1047176A (en) * 1990-05-04 1990-11-21 杨彬 Capacitive voltage regulating dc power supply

Patent Citations (1)

* Cited by examiner, † Cited by third party
Publication number Priority date Publication date Assignee Title
CN1047176A (en) * 1990-05-04 1990-11-21 杨彬 Capacitive voltage regulating dc power supply

Also Published As

Publication number Publication date
CN101635505A (en) 2010-01-27

Similar Documents

Publication Publication Date Title
CN101635505B (en) Method for controlling structure of a plurality of input-series and output-parallel converters
TWI387188B (en) Controlling method for multi-converter structure having series-connected inputs and parallel-connected outputs
CN101247083B (en) Switching regulator
CN100463339C (en) Multi-mode charge pump driving circuit of improving input noise when switching modes
Hwu et al. A novel buck–boost converter combining KY and buck converters
CN102484423B (en) Charge pump circuit and operation control method thereof
CN101741249B (en) Current balancing circuit and method
CN101110550A (en) Switching power supply unit
CN102468741A (en) Rectification circuit
CN101369733A (en) Electric power system
US11817781B2 (en) Power converter having power stage circuits and an auxiliary module
CN104283417A (en) Multiphase voltage reduction direct-current converter
US11936290B2 (en) Switched capacitor converter and control method
US8854021B2 (en) DC-DC converter and DC-DC conversion method
CN109256945A (en) For providing the PWM control program of minimum ON time
CN105099175A (en) Charge pump
US10277124B2 (en) DC-DC converter, boosting unit, electric vehicle and battery backup system
CN106169869B (en) A kind of puppet pwm control circuit
CN103683932B (en) Electric pressure converter under PWM mode or pulse omission pattern and changing method
CN104009627B (en) Multiphase switching controller
CN102611311A (en) Flyback type power supply system
CN103390996B (en) Control circuit and relevant switching type voltage stabilizer
KR102575944B1 (en) Switching regulator
CN102474182A (en) Integrated circuit comprising voltage modulation circuitry and method therefor
CN102487243B (en) Power supply and power-supply system provided with plurality of power supplies

Legal Events

Date Code Title Description
C06 Publication
PB01 Publication
C10 Entry into substantive examination
SE01 Entry into force of request for substantive examination
C14 Grant of patent or utility model
GR01 Patent grant