CN101624831B - 可报警的施工中沉井的预警方法 - Google Patents

可报警的施工中沉井的预警方法 Download PDF

Info

Publication number
CN101624831B
CN101624831B CN200910063361XA CN200910063361A CN101624831B CN 101624831 B CN101624831 B CN 101624831B CN 200910063361X A CN200910063361X A CN 200910063361XA CN 200910063361 A CN200910063361 A CN 200910063361A CN 101624831 B CN101624831 B CN 101624831B
Authority
CN
China
Prior art keywords
data
open caisson
construction
sidewall
group
Prior art date
Legal status (The legal status is an assumption and is not a legal conclusion. Google has not performed a legal analysis and makes no representation as to the accuracy of the status listed.)
Expired - Fee Related
Application number
CN200910063361XA
Other languages
English (en)
Other versions
CN101624831A (zh
Inventor
黎明中
Current Assignee (The listed assignees may be inaccurate. Google has not performed a legal analysis and makes no representation or warranty as to the accuracy of the list.)
China First Metallurgical Group Co Ltd
Original Assignee
China First Metallurgical Group Co Ltd
Priority date (The priority date is an assumption and is not a legal conclusion. Google has not performed a legal analysis and makes no representation as to the accuracy of the date listed.)
Filing date
Publication date
Application filed by China First Metallurgical Group Co Ltd filed Critical China First Metallurgical Group Co Ltd
Priority to CN200910063361XA priority Critical patent/CN101624831B/zh
Publication of CN101624831A publication Critical patent/CN101624831A/zh
Application granted granted Critical
Publication of CN101624831B publication Critical patent/CN101624831B/zh
Expired - Fee Related legal-status Critical Current
Anticipated expiration legal-status Critical

Links

Images

Landscapes

  • Emergency Alarm Devices (AREA)

Abstract

本发明涉及一种在施工中的沉井。其公开了预警方法:刃角2及中部外周4上对称安装报警器的压力计6每两个相对称的为一个判断组;依据刃角2的判断组数据:一个判断组中两个数据之差在10~400KPa内,另一判断组的两个数据差在0~10KPa内判断可能产生的倾向并提前采取相应措施;对其井壁压力状况分析:依据中部外周4的侧壁判断组数据:当一组侧壁判断组数据之差在10~400KPa内,另一侧壁判判断组的数据差在0~10KPa内判断可能产生的倾向,并予以提前采取相应措施。

Description

可报警的施工中沉井的预警方法
技术领域
本发明涉及一种沉井,具体属于在施工中的沉井。
背景技术
建筑物地下沉井的施工平衡状况是关系到建筑物建筑质量的重要环节,如若其地下沉井的施工偏离设计要求,则会产生“差之一毫失之千厘”的问题,严重影响建筑质量,且危及周围建筑物的安全。目前,沉井的施工平衡状况是利用观测仪进行不均匀沉降及位移观测,判定沉井分段下沉时的垂直度及偏移等质量问题。若发生上述问题,只能在事后采取纠偏的方式进行,其不足;沉井的施工偏离要求只能在事后进行纠偏,造成返工量大,施工期长,施工效率低,不能满足现代施工要求,甚至可能发生无法纠偏的后果,从而降低建筑物的使用功能或报废。
发明内容
本发明的目的在于解决现有技术的不足,提供一种在沉井的施工中随时能预报沉井即将产生的情况,提示施工人员及时采取措施以保证沉井施工的垂直度及控制位移的可报警的施工中沉井。
实现上述目的技术措施:
可报警的施工中沉井的预警方法,其步骤:
1)刃角上对称安装的报警器的压力计每两个相对称点为一个判断组;沉井本体的中部外周上对称安装的侧壁报警器的压力计每两个相对称点为一个侧壁判断组;
2)对施工中沉井下端面沉降状况的分析:通过刃角上连接的报警器的信号显示仪的显示数据,在一组判断组的数据中,当其中一个数据大于另一个数据在10~400KPa内,而在另一判断组的数据相差在0~10KPa内,则为数据大的点周围的土层结构较硬,预示施工的沉井产生向数据小的点位方向有下沉相对过大的倾向,施工人员则应及时采取相应措施予以纠正,反之亦然。
3)对施工中沉井井壁压力状况的分析:
通过中部外周上连接的侧壁报警器的信号显示仪的显示数据,在一组侧壁判断组的数据中,当其中一个侧壁数据大于另一个侧壁数据在10~400KPa内,而在另一侧壁判断组的同侧壁数据差在0~10KPa内,则预示沉井侧壁数据大的一侧的摩阻力较大,沉井在即将下沉过程中摩阻力较小的一侧下沉速度快于摩阻力较大的一侧,会产生沉井倾斜或偏移,反之亦然,施工人员则应及时采取相应措施予以纠正;
4)通过刃角上的信号显示仪的显示数据以沉井处于静止状态时的初始数据为依据,其数据变化为初始数据的10~30%时,预示沉井每段即将下沉或下沉将要结束的稳定状态,施工人员提前做好下一步工序施工准备或停止开挖。
本发明与现有技术相比,能随时知道沉井的施工中即将产生的情况,提示施工人员及时采取措施以保证沉井施工的平衡下沉,满足了施工要求及建筑质量,大大减少了返工量及劳动强度,使施工速度得以提高。
附图说明
图1为可报警的施工中沉井的结构示意图
图2为图1中多个压力计与一个信号显示仪连接的结构示意图
图3为图1中B向的施工中沉井的测点分布图
具体实施方式
下面结合附图作进一步描述;
可报警的施工中沉井,包括沉井本体1,其在沉井本体1下端的刃角2上对称安装四个/六个报警器3;在沉井本体1的中部距刃角2的3米/4米/6米的外周4上对称安装四个/六个侧壁报警器5。
报警器3或侧壁报警器5的结构:在压力计6上连接输入导线8和输出导线9,输入导线8和输出导线9再连接于一个信号显示仪7上或为一一对压连接方式,输入导线8和输出导线9为带有接触头的。将信号显示仪7安装在便于施工人员观测之处。
将四个/六个压力计6采用螺栓或嵌入式连接于沉井本体1下端的刃角2上,并为对称均匀分布;
将四个/六个压力计6采用螺栓或嵌入式连接于沉井本体1中部外周4上,并为对称均匀分布;
所述可报警的施工中沉井的预警方法:
刃角2及中部外周4以各设四个测点为例,即
刃角2上的四个测点分别为A、B、C、D,其中A、B两个为相对称点,并为一个判断组,C、D两个为相对称点,并为一个判断组;中部外周4上的四个测点分别为E、F、G、H,其中,E、F两个为相对称点,并为一个判断组,G、H两个为相对称点,并为一个判断组。
1)刃角2上对称安装的报警器3的压力计6与测点A、B、C、D相对压;沉井本体1的中部外周4上对称安装的侧壁报警器5的压力计6与测点相对压;
2)对施工中沉井下端面沉降状况的分析:通过刃角2上连接的报警器3的信号显示仪7的显示数据,在A、B判断组的数据中,当其中A点数据大于B点数据在10/80/150/260/400KPa内时,而C、D判断组的数据相差在上下0/2/5/8/10KPa内,则表明A点周围的土层结构较硬,预示施工的沉井产生向B点位方向有下沉相对过大的倾向,施工人员则应及时采取相应措施予以纠正,即使A点周围的土层结构变松软,反之亦然。
3)对施工中沉井井壁压力状况的分析:
通过中部外周4上连接的侧壁报警器5的信号显示仪7的显示数据,在E、F侧壁判断组的数据中,当E点侧壁数据大于F点侧壁数据在10/80/150/260/400KPa内,而在G、H侧壁判断组的数据中G点数据大于H点数据也在10/80/150/260/400KPa内,则预示沉井E、G侧壁的摩阻力较大,沉井在即将下沉过程中F、H侧下沉速度快于摩阻力较大的E、G侧,预示将产生沉井向F、H侧倾斜或偏移,反之亦然,此时,告知施工人员应及时采取相应措施予以纠正;
4)通过刃角上的信号显示仪的显示数据以沉井处于静止状态时的初始数据为依据,根据所处的地质层情况,其数据变化在初始数据的10~30%时取值,当数据变化为所取值时,预示沉井每段即将下沉或下沉将要结束的稳定状态,施工人员提前做好下一步工序施工准备或停止开挖。

Claims (1)

1.可报警的施工中沉井的预警方法,其步骤:
1)刃角(2)上对称安装的报警器(3)的压力计(6)每两个相对称点为一个判断组;沉井本体(1)的中部外周(4)上对称安装的侧壁报警器(5)的压力计(6)每两个相对称点为一个侧壁判断组;
2)对施工中沉井下端面沉降状况的分析:通过刃角(2)上连接的报警器(3)的信号显示仪(7)的显示数据,在一组判断组的数据中,当其中一个数据大于另一个数据在10~400KPa内,而在另一判断组的数据相差在0~10KPa内,则为数据大的点周围的土层结构较硬,预示施工的沉井产生向数据小的点位方向有下沉相对过大的倾向,施工人员则应及时采取相应措施予以纠正,反之亦然。
3)对施工中沉井井壁压力状况的分析:
通过中部外周(4)上连接的侧壁报警器(5)的信号显示仪(7)的显示数据,在一组侧壁判断组的数据中,当其中一个侧壁数据大于另一个侧壁数据在10~400KPa内,而在另一侧壁判断组的同侧壁数据差在0~10KPa内,则预示沉井侧壁数据大的一侧的摩阻力较大,沉井在即将下沉过程中摩阻力较小的一侧下沉速度快于摩阻力较大的一侧,会产生沉井倾斜或偏移,反之亦然,施工人员则应及时采取相应措施予以纠正;
4)通过刃角(2)上的信号显示仪(7)的显示数据以沉井处于静止状态时的初始数据为依据,其数据变化为初始数据的10~30%时,预示沉井每段即将下沉或下沉将要结束的稳定状态,施工人员提前做好下一步工序施工准备或停止开挖。
CN200910063361XA 2009-07-28 2009-07-28 可报警的施工中沉井的预警方法 Expired - Fee Related CN101624831B (zh)

Priority Applications (1)

Application Number Priority Date Filing Date Title
CN200910063361XA CN101624831B (zh) 2009-07-28 2009-07-28 可报警的施工中沉井的预警方法

Applications Claiming Priority (1)

Application Number Priority Date Filing Date Title
CN200910063361XA CN101624831B (zh) 2009-07-28 2009-07-28 可报警的施工中沉井的预警方法

Publications (2)

Publication Number Publication Date
CN101624831A CN101624831A (zh) 2010-01-13
CN101624831B true CN101624831B (zh) 2011-07-06

Family

ID=41520811

Family Applications (1)

Application Number Title Priority Date Filing Date
CN200910063361XA Expired - Fee Related CN101624831B (zh) 2009-07-28 2009-07-28 可报警的施工中沉井的预警方法

Country Status (1)

Country Link
CN (1) CN101624831B (zh)

Families Citing this family (2)

* Cited by examiner, † Cited by third party
Publication number Priority date Publication date Assignee Title
CN105714842B (zh) * 2016-02-04 2018-07-27 西南交通大学 沉井下沉预警方法和系统
CN110004963B (zh) * 2019-04-18 2024-02-06 郑州市市政工程总公司 沉井下沉全过程纠偏预防报警系统及沉井下沉纠偏方法

Citations (2)

* Cited by examiner, † Cited by third party
Publication number Priority date Publication date Assignee Title
CN101169663A (zh) * 2007-11-02 2008-04-30 上海市基础工程公司 气压沉箱气压自动调节系统
CN201459747U (zh) * 2009-07-28 2010-05-12 武汉京冶地基基础工程有限责任公司 可报警的施工中沉井

Patent Citations (2)

* Cited by examiner, † Cited by third party
Publication number Priority date Publication date Assignee Title
CN101169663A (zh) * 2007-11-02 2008-04-30 上海市基础工程公司 气压沉箱气压自动调节系统
CN201459747U (zh) * 2009-07-28 2010-05-12 武汉京冶地基基础工程有限责任公司 可报警的施工中沉井

Non-Patent Citations (2)

* Cited by examiner, † Cited by third party
Title
孙德新等.压气沉箱下沉时的计测数据分析.《工程建设》.2006,第38卷(第1期), *
张凤祥等.监测系统.《沉井与沉箱》.中国铁道出版社,2002, *

Also Published As

Publication number Publication date
CN101624831A (zh) 2010-01-13

Similar Documents

Publication Publication Date Title
CN100483081C (zh) 水下砼灌注标高定位仪
CN102288157B (zh) 一种地基深层沉降监测方法
CN108412547B (zh) 一种承压断层活化突水多场信息协同监测临突预报方法及监测系统
CN108489435A (zh) 对井壁进行监测的钢弦式传感器系统和变形预警的方法
CN101251498B (zh) 一种基于电磁辐射原理的围岩松动圈测试及评价方法
CN108918012B (zh) 一种用于地铁盾构隧道围岩扰动应力监测方法
CN103352455A (zh) 开挖基坑坑底土体隆起的监测方法
CN102943493B (zh) 测量预制桩内力及变形的方法
CN103215974B (zh) 基于分布式光纤传感技术的基桩挠度量测方法
CN108442419B (zh) 建筑物基桩检测装置以及检测方法
CN103321201B (zh) 密封式液体压差分层沉降计及其埋设、测量方法
CN106442937B (zh) 一种新型海洋浅层土体特性探测系统及其评估方法
CN103994846A (zh) 围岩应力场分布测试装置及方法
CN101718201A (zh) 隧道钻爆法施工安全5参数判定方法
CN101787712B (zh) 一种沉井倾斜测量装置及测量方法
CN201459747U (zh) 可报警的施工中沉井
CN101624831B (zh) 可报警的施工中沉井的预警方法
CN208183819U (zh) 一种新型的扩底桩承载力试验装置
CN104237973A (zh) 一种用于岩质边坡滑坡预警的气象监测系统及监测方法
CN110107358A (zh) 一种巷道掘进期间的大范围岩爆危险性预测方法
CN206386142U (zh) 具有警示功能的锚杆让压装置
CN110579194A (zh) 沿空巷道侧向基本顶岩梁断裂位置的现场测试方法及应用
CN110991009A (zh) 一种基于上覆荷载作用下埋地管线下方土体流失对管线受力形变的确定方法
CN103205956B (zh) 一种通过观测孔隙水压力以控制路基加载速率的方法
Guilloteau et al. Long-term behaviour of EDF dams regarding concrete swelling structures

Legal Events

Date Code Title Description
C06 Publication
PB01 Publication
C10 Entry into substantive examination
SE01 Entry into force of request for substantive examination
ASS Succession or assignment of patent right

Owner name: CHINA FIRST METALLURGICAL CONSTRUCTION GROUP CO.,

Free format text: FORMER OWNER: WUHAN JINGYE FOUNDATION ENGINEERING CO., LTD.

Effective date: 20110104

C41 Transfer of patent application or patent right or utility model
COR Change of bibliographic data

Free format text: CORRECT: ADDRESS; FROM: 430080 NO.1, BIN'GANG ROAD, QINGSHAN DISTRICT, WUHAN CITY, HUBEI PROVINCE TO: 430081 NO.3, GONGYE AVENUE, QINGSHAN DISTRICT, WUHAN CITY, HUBEI PROVINCE

TA01 Transfer of patent application right

Effective date of registration: 20110104

Address after: 430081 Wuhan Industrial Zone, Qingshan District, Hubei, No. 3

Applicant after: China First Metallurgical Group Co., Ltd.

Address before: 430080, No. 1, foreshore Road, Qingshan District, Hubei, Wuhan

Applicant before: Wuhan Jingye Foundation Engineering Co., Ltd.

C14 Grant of patent or utility model
GR01 Patent grant
CF01 Termination of patent right due to non-payment of annual fee
CF01 Termination of patent right due to non-payment of annual fee

Granted publication date: 20110706

Termination date: 20190728