CN101550695B - Construction method of reinforcing broken stump by using prestress steel twist-beam replacement grouting method - Google Patents
Construction method of reinforcing broken stump by using prestress steel twist-beam replacement grouting method Download PDFInfo
- Publication number
- CN101550695B CN101550695B CN2009100961313A CN200910096131A CN101550695B CN 101550695 B CN101550695 B CN 101550695B CN 2009100961313 A CN2009100961313 A CN 2009100961313A CN 200910096131 A CN200910096131 A CN 200910096131A CN 101550695 B CN101550695 B CN 101550695B
- Authority
- CN
- China
- Prior art keywords
- slip casting
- stake
- sick
- reinforced
- steel twist
- Prior art date
- Legal status (The legal status is an assumption and is not a legal conclusion. Google has not performed a legal analysis and makes no representation as to the accuracy of the status listed.)
- Active
Links
Images
Landscapes
- Piles And Underground Anchors (AREA)
Abstract
Description
Claims (10)
Priority Applications (1)
Application Number | Priority Date | Filing Date | Title |
---|---|---|---|
CN2009100961313A CN101550695B (en) | 2009-02-10 | 2009-02-10 | Construction method of reinforcing broken stump by using prestress steel twist-beam replacement grouting method |
Applications Claiming Priority (1)
Application Number | Priority Date | Filing Date | Title |
---|---|---|---|
CN2009100961313A CN101550695B (en) | 2009-02-10 | 2009-02-10 | Construction method of reinforcing broken stump by using prestress steel twist-beam replacement grouting method |
Publications (2)
Publication Number | Publication Date |
---|---|
CN101550695A CN101550695A (en) | 2009-10-07 |
CN101550695B true CN101550695B (en) | 2013-11-13 |
Family
ID=41155166
Family Applications (1)
Application Number | Title | Priority Date | Filing Date |
---|---|---|---|
CN2009100961313A Active CN101550695B (en) | 2009-02-10 | 2009-02-10 | Construction method of reinforcing broken stump by using prestress steel twist-beam replacement grouting method |
Country Status (1)
Country | Link |
---|---|
CN (1) | CN101550695B (en) |
Families Citing this family (5)
Publication number | Priority date | Publication date | Assignee | Title |
---|---|---|---|---|
CN102345292B (en) * | 2011-07-21 | 2016-01-27 | 从卫民 | A kind of composite prestressed uplift pile with enlarged footing |
CN103174135B (en) * | 2011-12-23 | 2015-06-03 | 五冶集团上海有限公司 | Repair method of unqualified post-grouting bored concrete pile |
CN103225300B (en) * | 2013-04-18 | 2015-03-18 | 贵州建工集团第二建筑工程有限责任公司 | Process and equipment for reinforcing and strengthening concrete filling pile |
CN109680737B (en) * | 2017-10-18 | 2021-05-07 | 中车株洲电力机车研究所有限公司 | Foundation deviation correction construction method for wind generating set |
CN111945716A (en) * | 2020-06-22 | 2020-11-17 | 广东省建筑科学研究院集团股份有限公司 | Reinforcing construction method for mud-sandwiched fractured cast-in-place pile |
Citations (6)
Publication number | Priority date | Publication date | Assignee | Title |
---|---|---|---|---|
US3483707A (en) * | 1968-03-11 | 1969-12-16 | Homayoun Joe Meheen | Method for reinforcing steel pipe piling in situ and the resultant piling |
CN1137088A (en) * | 1996-04-10 | 1996-12-04 | 李宪奎 | Construction method for soil bulkhead structure |
CN2365264Y (en) * | 1998-12-23 | 2000-02-23 | 刘冀豪 | Reinforced cast-in-place pile |
CN1619063A (en) * | 2004-12-08 | 2005-05-25 | 重庆交通科研设计院 | Post stress method stake body prestressed antislid stake and construction method |
CN1837469A (en) * | 2006-03-30 | 2006-09-27 | 中铁八局集团有限公司 | Stretching method for applying prestress on track slab |
CN101070702A (en) * | 2007-06-14 | 2007-11-14 | 北京科技大学 | Single-hole composite anchoring pile |
Family Cites Families (2)
Publication number | Priority date | Publication date | Assignee | Title |
---|---|---|---|---|
JP3289085B2 (en) * | 1995-05-02 | 2002-06-04 | 株式会社大阪防水建設社 | Repair method of foundation pile |
JP3245669B2 (en) * | 1995-05-02 | 2002-01-15 | 株式会社大阪防水建設社 | Repair method of foundation pile |
-
2009
- 2009-02-10 CN CN2009100961313A patent/CN101550695B/en active Active
Patent Citations (6)
Publication number | Priority date | Publication date | Assignee | Title |
---|---|---|---|---|
US3483707A (en) * | 1968-03-11 | 1969-12-16 | Homayoun Joe Meheen | Method for reinforcing steel pipe piling in situ and the resultant piling |
CN1137088A (en) * | 1996-04-10 | 1996-12-04 | 李宪奎 | Construction method for soil bulkhead structure |
CN2365264Y (en) * | 1998-12-23 | 2000-02-23 | 刘冀豪 | Reinforced cast-in-place pile |
CN1619063A (en) * | 2004-12-08 | 2005-05-25 | 重庆交通科研设计院 | Post stress method stake body prestressed antislid stake and construction method |
CN1837469A (en) * | 2006-03-30 | 2006-09-27 | 中铁八局集团有限公司 | Stretching method for applying prestress on track slab |
CN101070702A (en) * | 2007-06-14 | 2007-11-14 | 北京科技大学 | Single-hole composite anchoring pile |
Also Published As
Publication number | Publication date |
---|---|
CN101550695A (en) | 2009-10-07 |
Similar Documents
Publication | Publication Date | Title |
---|---|---|
CN101550695B (en) | Construction method of reinforcing broken stump by using prestress steel twist-beam replacement grouting method | |
CN103967036B (en) | Stake and sleeve grouting attachment structure and construction method thereof for offshore wind farm | |
KR101069815B1 (en) | Post grouting system of Cast-in-place concrete piles and the post grouting method for increasing end bearing capacity at pile base | |
CN201722685U (en) | No-adhesive prestress and pile side rear grouting punching pile structure | |
CN102828509B (en) | Joint grouting method from bottom and side of prestressed pipe pile | |
JP2008150774A (en) | Two step high/low concentration grout construction method | |
CN104846810A (en) | Self-circulating posterior grouting bored pile construction method | |
CN104976424B (en) | Anchor cable construction method for rectangular top pipe joint connecting and strengthening | |
CN103541359A (en) | Method for repairing and treating quality defect of cast-in-place pile | |
CN102828498B (en) | Method for constructing gravel pile of hoop of immersed tube for reinforcing soft foundation | |
CN103410182A (en) | Unilateral pile foundation unloading horizontal top-level pull deviation rectifying and broken pile reinforcement construction method | |
CN101200897A (en) | Construction method for grouting curtain combined with steel reinforced concrete guard ring | |
CN109208631A (en) | A kind of gravity retaining wall inclination deviation rectification and reinforcement means | |
CN201241344Y (en) | Controllable capsule type expansion device | |
CN103410144B (en) | Prestressed reinforcement piles set into rock and construction method | |
CN102808413A (en) | Reinforcement-replacing sectional-grouting pipe with inner piston and construction method thereof | |
CN112012749A (en) | Tunnel advanced grouting small conduit and construction method | |
CN105714827A (en) | Post-grouting construction method of cast-in-situ bored pile | |
CN102094421A (en) | Prestressed anchor bar and construction method using same | |
CN111350310B (en) | Reinforcing method for finding that steel bars at lower section in full grouting sleeve are cut off before grouting | |
CN101793027A (en) | Core-grouted static pressure anchor rod pile | |
CN104018499A (en) | Grouting method capable of saving grouting amount on pre-stressed anchor cable tension section | |
CN104032738B (en) | Pre-stressed anchor rod and construction method using same | |
CN201635072U (en) | Centrally grouted static-pressured anchor pile former | |
CN209162840U (en) | A kind of more anchor disk jet mixing stiffening piles |
Legal Events
Date | Code | Title | Description |
---|---|---|---|
C06 | Publication | ||
PB01 | Publication | ||
C10 | Entry into substantive examination | ||
SE01 | Entry into force of request for substantive examination | ||
C14 | Grant of patent or utility model | ||
GR01 | Patent grant | ||
ASS | Succession or assignment of patent right |
Free format text: FORMER OWNER: ZHU KUI Effective date: 20150604 Owner name: LAI BIN Free format text: FORMER OWNER: YE CHANGQING Effective date: 20150604 |
|
C41 | Transfer of patent application or patent right or utility model | ||
COR | Change of bibliographic data |
Free format text: CORRECT: ADDRESS; FROM: 325000 WENZHOU, ZHEJIANG PROVINCE TO: 330000 NANCHANG, JIANGXI PROVINCE |
|
TR01 | Transfer of patent right |
Effective date of registration: 20150604 Address after: 330000 Jiangxi city of Nanchang province Xihu District Xinyu garden 11 Building 2 unit 801 room Patentee after: Lai Bin Address before: Ouhai District of Zhejiang city in Wenzhou province 325000 Rong Road No. 39 Patentee before: Ye Changqing Patentee before: Zhu Kui |
|
EE01 | Entry into force of recordation of patent licensing contract |
Application publication date: 20091007 Assignee: CHENGDU KECHUANG JIASI TECHNOLOGY CO., LTD. Assignor: Lai Bin Contract record no.: 2015360000076 Denomination of invention: Construction method of reinforcing broken stump by using prestress steel twist-beam replacement grouting method Granted publication date: 20131113 License type: Exclusive License Record date: 20150610 |
|
LICC | Enforcement, change and cancellation of record of contracts on the licence for exploitation of a patent or utility model | ||
C41 | Transfer of patent application or patent right or utility model | ||
TR01 | Transfer of patent right |
Effective date of registration: 20151125 Address after: 330000 Jiangxi city of Nanchang Province in the Tang Nan Town Nanchang County Street No. 28 Patentee after: CHENGDU KECHUANG JIASI TECHNOLOGY CO., LTD. Address before: 330000 Jiangxi city of Nanchang province Xihu District Xinyu garden 11 Building 2 unit 801 room Patentee before: Lai Bin |
|
DD01 | Delivery of document by public notice |
Addressee: CHENGDU KECHUANG JIASI TECHNOLOGY CO., LTD. Document name: Notification of Passing Examination on Formalities |