CN101483898A - Method and apparatus for accelerating RRC connection establishment - Google Patents

Method and apparatus for accelerating RRC connection establishment Download PDF

Info

Publication number
CN101483898A
CN101483898A CNA200810002522XA CN200810002522A CN101483898A CN 101483898 A CN101483898 A CN 101483898A CN A200810002522X A CNA200810002522X A CN A200810002522XA CN 200810002522 A CN200810002522 A CN 200810002522A CN 101483898 A CN101483898 A CN 101483898A
Authority
CN
China
Prior art keywords
district
rrc
sub
message
umts
Prior art date
Legal status (The legal status is an assumption and is not a legal conclusion. Google has not performed a legal analysis and makes no representation as to the accuracy of the status listed.)
Granted
Application number
CNA200810002522XA
Other languages
Chinese (zh)
Other versions
CN101483898B (en
Inventor
谢明江
黄颖华
朱作燕
Current Assignee (The listed assignees may be inaccurate. Google has not performed a legal analysis and makes no representation or warranty as to the accuracy of the list.)
Huawei Technologies Co Ltd
Original Assignee
Huawei Technologies Co Ltd
Priority date (The priority date is an assumption and is not a legal conclusion. Google has not performed a legal analysis and makes no representation as to the accuracy of the date listed.)
Filing date
Publication date
Application filed by Huawei Technologies Co Ltd filed Critical Huawei Technologies Co Ltd
Priority to CN200810002522XA priority Critical patent/CN101483898B/en
Publication of CN101483898A publication Critical patent/CN101483898A/en
Application granted granted Critical
Publication of CN101483898B publication Critical patent/CN101483898B/en
Expired - Fee Related legal-status Critical Current
Anticipated expiration legal-status Critical

Links

Images

Landscapes

  • Mobile Radio Communication Systems (AREA)

Abstract

The invention discloses a method and a device for fastening radio resource to control the setup of RRC connection, wherein, the method comprises that uplink RRC message sent by a piece of UE is received; and when a base station where a target district is located does not have the context of the UE, the message carrying random access related parameters needed by RRC setup is sent to the UE, and the UE initiates a RRC setup process according to the random access related parameters, thus greatly reducing the setup time of the RRC connection, and moreover, balancing network load and the switching method process of the UE among systems with different modes. The device provided by the invention comprises a receiving unit, a sending unit, a detecting unit, and a redirecting unit. According to the method and the device of the invention, the setup time of the RRC can be effectively reduced, business interrupting time can be reduced, the feelings of users can be effectively improved, and network load condition can be effectively balanced, thus leading the network to run more steadily.

Description

A kind of RRC that accelerates connects method and the device of setting up
Technical field
The present invention relates to wireless communication technology field, the RRC that relates in particular in the wireless communication system connects method and the device of setting up.
Background technology
In the existing mobile communications system, radio resource control RRC (Radio Resource Control) connects be UE with the RRC protocol layer of network side between being connected of a kind of bi-directional point to multipoint of setting up, concerning a UE, have a RRC connection at the most.Be connected between UE and the network side based on RRC and transmit radio network signaling, as carry out wireless resource allocation or the like.RRC sets up at the beginning of being connected call setup, keeps during conversing always, and discharges behind end of conversation.Usually, RRC establishment of connection is to be connected by first signaling to this UE of setting up from the request of UE high level, the RRC establishment of connection comprise the sub-district gravity treatment, allow the foundation of control and second layer signaling link.
Rrc layer is handled the assignment of RRC connection and control and the needed Radio Resource of user plane.Rrc layer comprises the assignment to a plurality of wireless bearer service Radio Resources in the same RRC connection with allocation radio resource when a RRC connection is set up.RRC controls Radio Resource so that can use unbalanced Radio Resource to communicate (asymmetric up-downgoing) between UE and the RAN in uplink and downlink.RRC also is used to be handed off to purposes such as GSM or other wireless system to the resource assignation of UE.In addition, the locomotive function that RRC connects, specifically, when setting up a RRC connection, rrc layer is also carried out estimation, decision and execution etc. and is moved function associated with RRC, as equipment to the function based on the UE measurement such as the renewal of GSM or switchings of other wireless system, sub-district gravity treatment, cell paging area.
LTE is the wireless communication standard of future generation that 3GPP is formulating, and has the higher availability of frequency spectrum and transmission speed, lower advantages such as propagation delay time.Radio Link Failure (RLF takes place in wireless communication system (as the LTE system), Radio Link Failure) after, need carry out the recovery of Radio Link, it is the wireless user equipment re-accessing network, at first carry out the RRC establishment of connection, comprise the foundation of gravity treatment, permission control and the second layer signaling link of sub-district.Be connected between UE and the network based on RRC and transmit radio network signaling, comprise and carry out wireless resource allocation etc.RRC establishment of connection is to be connected by the signaling of setting up from the request of UE high level to this UE.
Usually, being divided into two stages carries out the recovery of Radio Link, as shown in Figure 1, in Phase I, UE selects former sub-district to carry out the recovery of Radio Link earlier, if can't recover in Phase I, then enter Phase, in Phase, UE is autonomous to select a sub-district to attempt recovering, UE sends RRC connection reconstruction request RRC connection Re-establishment request message to the sub-district of selecting, after this message is received in the sub-district, check the context of whether preserving this UE, when having this UE context, send RRC connection reconstruction RRC connection re-establishment message informing UE Radio Link to UE and recover, UE sends the RRC connection reconstruction to network side and finishes RRC connectionre-establishment complete message; When there was not the context of this UE in this sub-district, network sent refusal RRC connection reconstruction RRC connection re-establishment reject message to UE, and UE receives that needing to initiate again new RRC after this message connects the process of setting up.Because this moment, high-level business did not also discharge, and only was the rrc layer service disconnection, so the susceptibility in order to reduce time of service interruption and to improve the user need shorten the time that RRC sets up as far as possible.
Summary of the invention
In view of this, the invention provides a kind of RRC of quickening and connect method and the device of setting up.
A kind of radio resource control RRC of accelerating provided by the invention connects the method for setting up, and comprising:
Receive the up RRC message that UE sends;
When there is not the context of this UE in base station, Target cell place, sends and carry RRC and set up the required message that inserts relevant parameter at random to described UE.
Ground preferably determines whether to allow described UE in the given time or initiate to set up the RRC connection requests after the scheduled time again according to the buffer status report BSR information of carrying in the described up RRC message:
When UE does not have on the data to send out, when Target cell does not have downlink data and reaches predetermined load for UE and Target cell, the sub-district allows described UE in the given time or initiate to set up the RRC connection requests after the scheduled time again.
The present invention also provides a kind of radio resource control RRC of accelerating to connect the device of setting up, and comprising:
Receiving element is used to receive the up RRC message that UE sends;
Transmitting element is used to send message to described UE;
When there is not the context of this UE in Target cell place base station eNB, described transmitting element sends and carries RRC and set up the required message that inserts relevant parameter at random to described UE.
Ground preferably, this device also comprises:
Detecting unit is used for the load condition of detected cells;
When described receiving element receives the up RRC message that described UE sends,, then detect the information on load of neighbor cell if described detecting unit detects the current network load of Target cell greater than predetermined value;
Be redirected the unit, described UE be redirected on the corresponding neighbor cell according to the information on load of described neighbor cell.
The technical scheme that the embodiment of the invention provides is applicable to that the RRC that sets up when calling out between UE and the sub-district is connected foundations, or behind the Radio Link Failure, the RRC connection foundation when recovering Radio Link.UE sends up RRC message to Target cell, target cell base station judges according to the content of this message whether Target cell has the context of this UE, the context that in target cell base station, does not have this UE, transmission is carried RRC and is set up the required message that inserts relevant parameter at random to this UE, this UE initiates RRC according to the described relevant parameter that inserts at random and sets up flow process, make RRC connection setup time significantly reduce, in addition, the mechanism of the neighbor cell by described UE being redirected to Target cell is carried out equilibrium to network load, and the changing method flow process of UE between the system of different systems, by the present invention, can shorten the time that RRC sets up effectively, reduce time of service interruption, effectively raise user's susceptibility, the simultaneously effectively balanced load condition of network makes network to move more steadily.
Description of drawings
Fig. 1 is the recovery process schematic diagram of Radio Link of the prior art;
The Radio Link method for building up flow chart of Fig. 2 for providing in the first embodiment of the invention;
The Radio Link method for building up flow chart of Fig. 3 for providing in the second embodiment of the invention;
Fig. 4 is the Radio Link method for building up flow chart in the third embodiment of the invention.
Embodiment
The embodiment of the invention is applicable to that the RRC that sets up when calling out between UE and the sub-district is connected, and also is applicable to the wireless link recovery behind the Radio Link Failure.UE sends up RRC message to target cell base station, target cell base station judges according to the content of this message whether Target cell has the context of this UE, if there is not the context of this UE, then carry RRC and set up the required message that inserts relevant parameter at random to the UE transmission, this UE sets up flow process according to the described relevant parameter initiation RRC that inserts at random after receiving this message, significantly reduce RRC connection setup time, the mechanism of the neighbor cell by this UE being redirected to Target cell is carried out equilibrium to network load in addition.The embodiment of the invention can effectively reduce the time that RRC sets up, and has reduced time of service interruption, effectively raises user's susceptibility, and the effectively balanced simultaneously load condition of network makes network to move more steadily.
For ease of understanding the present invention, connection is briefly described to RRC below.
In the mobile communication system, RRC connects be UE with the RRC protocol layer of UTRAN between being connected of a kind of bi-directional point to multipoint of setting up, concerning a UE, have a RRC connection at the most.Be connected between UE and the UTRAN based on RRC and transmit radio network signaling, as carry out wireless resource allocation or the like.RRC is connected between UE and the sub-district and sets up at the beginning of the call setup, discharges behind end of calling, and keeps during calling out always.Usually, RRC establishment of connection is to be connected by first signaling of setting up from the request of UE high level, the RRC establishment of connection comprise the sub-district gravity treatment, allow the foundation of control and second layer signaling link.
Relate to during RRC connects Radio Resource appointment, reconfigure and discharge.
Rrc layer is handled the assignment of RRC connection and control and the needed Radio Resource of user plane.Rrc layer comprises the assignment to a plurality of wireless bearer service Radio Resources in the same RRC connection with allocation radio resource when a RRC connection is set up.RRC controls Radio Resource so that can use unbalanced Radio Resource to communicate (asymmetric up-downgoing) between UE and the RAN in uplink and downlink.RRC also is used to be handed off to purposes such as GSM or other wireless system to the resource assignation of UE.In addition, the locomotive function that RRC connects, specifically, when setting up a RRC connection, rrc layer is also carried out estimation, decision and execution etc. and is moved function associated with RRC, as equipment to the function based on the UE measurement such as the renewal of GSM or switchings of other wireless system, sub-district gravity treatment, cell paging area.
For making principle of the present invention, characteristic and advantage clearer, describe the present invention in conjunction with specific embodiments below with reference to figure.
Embodiment one
In wireless communication system, set up between UE and the sub-district and need set up RRC when calling out and is connected, and after Radio Link Failure RLF takes place, carry out the recovery of Radio Link, promptly wireless user equipment need at first carry out the reconstruction of RRC connection with re-accessing network.Setting up after RRC connects, be connected between UE and the network based on RRC and transmit radio network signaling, comprising and carry out wireless resource allocation etc.
Present embodiment carries out in the process of wireless link recovery with after Radio Link Failure takes place, and reconstruction RRC is connected to example and is described.
With reference to Fig. 2, the Radio Link method for building up flow process that the embodiment of the invention provides comprises the steps:
S201, UE are by being that cell base station eNB sends random access guiding message to network side: send at the ascending resource piece of appointment and insert RA (Random Access) targeting signal preamble at random, to initiate random access procedure;
S202, network side is that cell base station eNB sends to UE: accidental access response message RAresponse, this message includes the ascending resource UL resource information of UE, sub-district casual network sign C-RNTI parameters such as (Radio network temporary identity);
S203, according to the configuration of accidental access response message, UE sends RRC connection reconstruction request RRC connection re-establishment request message to network, requires to recover RRC and connects.UE can carry buffer status report BSR (Buffer Status Report) information in this message, so that the sub-district decision need distribute great ascending resource to UE.
S204, if the sub-district is the contextual information of this UE not, cell base station eNB sends refusal to UE and rebuilds RRC connection connection re-establishment reject message so, in this message, carried the relevant parameter of access at random when being used for RRC and setting up, as up resource UL resource etc.
After S205, UE received this message, then UE need be introduced into RRC IDLE state, and then, this UE sets up the required relevant parameter of access at random according to described RRC connection and uses network to specify ascending resource, initiates Initial R RC and sets up flow process.
Embodiment two
The method step S301 to S303 of present embodiment is identical with step S201 to S203 in the previous embodiment one, and with reference to Fig. 3, its difference is,
S304 carries buffer status report BSR information in the up RRC message that UE sends, determine whether to allow this UE in the given time or initiate to set up the RRC connection requests after the scheduled time again according to described buffer status report BSR information,
Such as, when UE does not have on the data to send out and cell base station eNB does not have downlink data to give UE and sub-district when reaching predetermined load yet, allow this UE to initiate to set up the RRC connection requests in the given time again.
After cell base station eNB receives this message, load condition according to self is adjudicated, if the current network duty ratio is bigger, current network load as the sub-district reaches fully loaded 90%, cell base station eNB sends refusal to UE and rebuilds RRC connection RRC connection re-establishmentreject message so, this message is carried time indication (Wait Time) information, described time indication information can identify with the System Frame Number (SFN, System Frame Number) of sub-district.In addition, can also dispose a proprietary preamble ID, new C-RNTI as required and give UE, so that UE initiates to insert at random after waiting for a period of time again.
After S305, UE receive this message, initiate again to insert at random according to the time of indicating in the message.
Embodiment three
Step S201 in the method step S401 to S403 that present embodiment provides and the previous embodiment one) identical to S203, with reference to Fig. 4, its difference is,
S404, after cell base station eNB receives this message, load condition according to the sub-district is adjudicated, if the current network load condition is bigger, current network load as the sub-district reaches fully loaded 90%, and cell base station eNB tests the load condition of neighbor cell, obtains the information on load of neighbor cell, and from above-mentioned neighbor cell, select the less sub-district of load as Target cell, this UE is redirected on the selected neighbor cell.Be that the sub-district sends handoff request HO request message to Target cell, carry the relevant context of UE in the message, Target cell returns handoff response HO response message.
S405, target cell base station eNB sends refusal to UE and rebuilds RRC connection RRC connectionre-establishment reject message, this message carries relevant parameter and the redirection information (as the information of one or more Target cell) that is used for inserting at random, requires UE to initiate again to insert at random in other sub-districts of appointment.
After S406, UE receive this message, initiate again to insert at random at the Target cell of appointment according to information in the message, perhaps UE selects the Target cell that wherein load is lighter to insert according to the measurement of oneself.
Embodiment four
In the continuous evolution of mobile communication, the situation that has multiple communication standard coexistence, therefore, relate to the switching of UE between the system of different systems, be that the mutual Inter-RAT of wireless access technology (Radio Access Technology) switches, as the switching of UE between LTE and UMTS system.
If after Radio Link Failure RLF takes place, UE switches to the UMTS sub-district will initiate cell update cell update flow process.At this moment, if a ready Target cell has been arranged, promptly this Target cell is preserved the contextual information of this UE, and generally speaking, and the cell base station eNB that this ready Target cell may insert with UE is under a RNC control.
UE switches to the situation of UMTS sub-district from the LTE sub-district, specific as follows:
When UE switches to the UMTS sub-district from the LTE sub-district, if above-mentioned UMTS sub-district is not the determined UMTS Target cell in the former sub-district of LTE, but the radio network controller (RNC) at place, above-mentioned UMTS sub-district has the context of this UE, and promptly UMTS Target cell and above-mentioned UMTS sub-district belong to same RNC control.
With this UE from above-mentioned UMTS redirecting cell to the determined UMTS Target cell in the former sub-district of LTE; Or
Set up new Radio Link in above-mentioned UMTS sub-district, finish switching.
When UE switches to the UMTS sub-district from the LTE sub-district, if the contextual information of no above-mentioned UE among the RNC at place, above-mentioned UMTS sub-district can carry out subsequent treatment according to one of following three kinds of modes:
(1) RNC of above-mentioned UMTS sub-district obtains the contextual information of above-mentioned UE from above-mentioned LTE base station, to carry out the forward direction switching flow;
(2) access of the RNC of above-mentioned UMTS sub-district refusal UE;
(3) RNC of above-mentioned UMTS sub-district is that UE sets up new RRC and connects.
Embodiment five
Another kind of Inter-RAT switch instances is that above-mentioned UE switches to the UMTS sub-district from the LTE sub-district,
If subsequent treatment under same radio network controller (RNC) control, can not carried out according to one of following three kinds of modes in above-mentioned LTE sub-district and above-mentioned UMTS sub-district:
(1) RNC of above-mentioned UMTS sub-district obtains the contextual information of above-mentioned UE from above-mentioned LTE base station, to finish the forward direction switching flow;
(2) access of the RNC of above-mentioned UMTS sub-district refusal UE;
(3) RNC of above-mentioned UMTS sub-district is that UE sets up new RRC and connects.
If above-mentioned Target cell is the LTE sub-district, if above-mentioned LTE sub-district does not have the contextual information of this UE,
Then obtain the contextual information of this UE, to carry out the forward direction switching flow from the RNC of above-mentioned UMTS sub-district; Perhaps, refuse the access of this UE.
In the embodiment of the invention, also provide a kind of radio resource control RRC of accelerating to connect the device of setting up, comprising:
Receiving element is used to receive the up RRC message that UE sends;
Transmitting element is used to send message to above-mentioned UE;
When there is not the context of this UE in Target cell place base station eNB, above-mentioned transmitting element sends and carries RRC and set up the required message that inserts relevant parameter at random to this UE.
And
Detecting unit is used for the load condition of detected cells;
When above-mentioned receiving element receives the up RRC message that above-mentioned UE sends,, then detect the information on load of neighbor cell if above-mentioned detecting unit detects the current network load of Target cell greater than predetermined value;
Be redirected the unit, above-mentioned UE be redirected on the corresponding neighbor cell according to the information on load of above-mentioned neighbor cell.
In sum, among the embodiment provided by the invention, set up between UE and the sub-district when needing to set up RRC at the beginning of calling out and being connected, or carry out wireless link recovery behind the Radio Link Failure.UE sends up RRC message to Target cell; Target cell base station judges according to the content of this message whether Target cell has the context of this UE, when the context that does not have this UE, transmission is carried RRC and is set up the required message that inserts relevant parameter at random to this UE, this UE initiates RRC according to the described relevant parameter that inserts at random and sets up flow process, make ensuing RRC connection setup time significantly reduce, in addition, by the neighbor cell mechanism that this UE is redirected to Target cell network load is carried out equilibrium, and the changing method flow process of UE between the system of different systems, by the present invention, can effectively reduce the time that RRC sets up, reduced time of service interruption, effectively raise user's susceptibility, the simultaneously effectively balanced load condition of network makes network to move more steadily.
It will be appreciated by those skilled in the art that, all or part of module in the foregoing description or each step are to instruct related hardware to realize by program, described program can be stored in the computer read/write memory medium, and described storage medium is as ROM/RAM, disk, laser disc etc.Perhaps they are made into each integrated circuit modules respectively, perhaps a plurality of modules in them or step are made into the single integrated circuit module and realize.Like this, the present invention is not restricted to any specific hardware and software combination.
The foregoing description is used for description and interpretation principle of the present invention.Be appreciated that the specific embodiment of the present invention is not limited thereto.To those skilled in the art, various changes of carrying out under the prerequisite that does not break away from the spirit and scope of the invention and modification all are encompassed within protection scope of the present invention.Therefore, protection scope of the present invention is determined by claim.

Claims (14)

1, a kind of radio resource control RRC of accelerating connects the method for setting up, and it is characterized in that, comprising:
Receive the up RRC message that UE sends;
When there is not the context of this UE in base station, Target cell place, sends and carry RRC and set up the required message that inserts relevant parameter at random to described UE.
2, the method for claim 1 is characterized in that,
According to the buffer status report BSR information of carrying in the described up RRC message is the ascending resource that described UE distributes.
3, the method for claim 1 is characterized in that, also comprises:
Base station, Target cell place determines whether to allow described UE to initiate to set up the RRC connection requests in the given time or after the scheduled time again according to the BSR information of carrying in the described up RRC message:
When UE does not have on the data to send out, when Target cell does not have downlink data and reaches predetermined load for UE and Target cell, the sub-district allows described UE in the given time or initiate to set up the RRC connection requests after the scheduled time again.
4, method as claimed in claim 3 is characterized in that, also comprises:
When allowing described UE in the given time or initiate to set up the RRC connection requests after the scheduled time again, in the message that sends to UE, carrying corresponding temporal information.
5, method as claimed in claim 4 is characterized in that,
Described temporal information identifies with the system frame number SFN of sub-district.
6, as claim 3 or 4 described methods, it is characterized in that, also comprise:
In the message that UE sends, carry proprietary preface information preamble ID, new Cell Radio Network Temporary Identifier/Identity, Cell-RNTI C-RNTI to UE.
7, the method for claim 1 is characterized in that, also comprises:
When receiving the described up RRC message that UE sends, Target cell detects the load condition of self, load described load greater than predetermined value, then detect the information on load of the neighbor cell of described Target cell, and described UE is redirected on the corresponding neighbor cell according to the information on load of described neighbor cell.
8, as claim 1,2,3 or 7 described methods, it is characterized in that, described described UE be redirected on the corresponding neighbor cell, comprising:
Described UE is redirected on the less neighbor cell of load.
9, as claim 1,2,3 or 7 described methods, it is characterized in that,
Radio Link Failure between UE and cell base station, when needing to recover Radio Link, described up RRC message is RRC connection reconstruction message.
10, the method for claim 1 is characterized in that, when described UE switches to the UMTS sub-district from the LTE sub-district, this method also comprises:
If described UMTS sub-district is not the determined UMTS Target cell in former LTE sub-district, the radio network controller (RNC) at place, described UMTS sub-district has the context of this UE,
With UE from described UMTS redirecting cell to the determined UMTS Target cell in the former sub-district of LTE; Or
Set up new Radio Link in described UMTS sub-district, finish switching.
11, the method for claim 1 is characterized in that, when described UE switches to the UMTS sub-district from the LTE sub-district, this method also comprises:
If the RNC at place, described UMTS sub-district does not have the contextual information of described UE,
The RNC of described UMTS sub-district obtains the contextual information of described UE from described LTE base station, to carry out the forward direction switching flow; Or
The access of the RNC refusal UE of described UMTS sub-district; Or
The RNC of described UMTS sub-district is that UE sets up new RRC connection.
12, the method for claim 1 is characterized in that, when described UE switches to the LTE sub-district from the UMTS sub-district, this method also comprises:
Described Target cell is the LTE sub-district, if place, described LTE sub-district base station eNB does not have the contextual information of described UE,
Then obtain the contextual information of described UE, to carry out the forward direction switching flow from the RNC of described UMTS sub-district; Or
Refuse the access of described UE.
13, a kind of radio resource control RRC of accelerating connects the device of setting up, and it is characterized in that, comprising:
Receiving element is used to receive the up RRC message that UE sends;
Transmitting element is used to send message to described UE;
When there is not the context of this UE in Target cell place base station eNB, described transmitting element sends and carries RRC and set up the required message that inserts relevant parameter at random to described UE.
14, device as claimed in claim 13 is characterized in that, also comprises:
Detecting unit is used for the load condition of detected cells;
When described receiving element receives the up RRC message that described UE sends,, then detect the information on load of neighbor cell if described detecting unit detects the current network load of Target cell greater than predetermined value;
Be redirected the unit, described UE be redirected on the corresponding neighbor cell according to the information on load of described neighbor cell.
CN200810002522XA 2008-01-07 2008-01-07 Method and apparatus for accelerating RRC connection establishment Expired - Fee Related CN101483898B (en)

Priority Applications (1)

Application Number Priority Date Filing Date Title
CN200810002522XA CN101483898B (en) 2008-01-07 2008-01-07 Method and apparatus for accelerating RRC connection establishment

Applications Claiming Priority (1)

Application Number Priority Date Filing Date Title
CN200810002522XA CN101483898B (en) 2008-01-07 2008-01-07 Method and apparatus for accelerating RRC connection establishment

Publications (2)

Publication Number Publication Date
CN101483898A true CN101483898A (en) 2009-07-15
CN101483898B CN101483898B (en) 2012-08-08

Family

ID=40880781

Family Applications (1)

Application Number Title Priority Date Filing Date
CN200810002522XA Expired - Fee Related CN101483898B (en) 2008-01-07 2008-01-07 Method and apparatus for accelerating RRC connection establishment

Country Status (1)

Country Link
CN (1) CN101483898B (en)

Cited By (31)

* Cited by examiner, † Cited by third party
Publication number Priority date Publication date Assignee Title
CN101848554A (en) * 2010-05-19 2010-09-29 新邮通信设备有限公司 Wireless interface restoration method and donor base station
CN101848497A (en) * 2010-05-24 2010-09-29 新邮通信设备有限公司 Method and system for establishing data radio bearer (DRB)
CN101998664A (en) * 2009-08-12 2011-03-30 大唐移动通信设备有限公司 Method, system and equipment for reestablishing radio resource control connection
CN101998466A (en) * 2009-08-17 2011-03-30 中兴通讯股份有限公司 Method and system for judging unexpected switched scene
CN102143552A (en) * 2010-11-24 2011-08-03 华为技术有限公司 Access processing method, base station and terminal
CN102143539A (en) * 2010-02-02 2011-08-03 中兴通讯股份有限公司 Method and system for acquiring context of terminal
CN102215545A (en) * 2010-04-09 2011-10-12 中国移动通信集团公司 Method and device for re-establishing return link in relay network
CN102223713A (en) * 2011-06-15 2011-10-19 电信科学技术研究院 Method, system and equipment for notifying connection reestablishment of cell information and RRC (radio resource control)
WO2012041111A1 (en) * 2010-09-29 2012-04-05 中兴通讯股份有限公司 Method, system, terminal and network-side equipment for terminal access time control
CN102469514A (en) * 2010-11-05 2012-05-23 中兴通讯股份有限公司 Terminal and method for accessing terminal to network
WO2012092814A1 (en) * 2011-01-07 2012-07-12 中兴通讯股份有限公司 Method and system for re-establishing radio link
WO2013113159A1 (en) * 2012-02-01 2013-08-08 富士通株式会社 Method for recovering wireless connections, mobile communication system, user equipment and base station
WO2013185669A1 (en) * 2012-07-13 2013-12-19 中兴通讯股份有限公司 Method and apparatus for implementing voice service fallback
CN103686878A (en) * 2012-08-30 2014-03-26 中兴通讯股份有限公司 Redirection method and device, terminal and base station
CN103765798A (en) * 2011-08-11 2014-04-30 英特尔公司 Reduced signaling overhead during radio resource control (RRC) state transitions
CN103826272A (en) * 2014-02-24 2014-05-28 大唐移动通信设备有限公司 Cell redirecting method and device
TWI501602B (en) * 2011-08-12 2015-09-21 Blackberry Ltd Handling a connection in a wireless communication system
CN104955163A (en) * 2014-03-28 2015-09-30 中国移动通信集团公司 Mobile terminal communication control method, equipment and system
US9155121B2 (en) 2012-03-27 2015-10-06 Blackberry Limited Re-establishment of suspended RRC connection at a different eNB
CN105025536A (en) * 2014-04-29 2015-11-04 中国电信股份有限公司 Long term evolution (LTE) to evolution high-rate packet data (eHRPD) switching method, LTE to eHRPD system, terminal and evolved node B (eNB)
US9247575B2 (en) 2012-03-27 2016-01-26 Blackberry Limited eNB storing RRC configuration information at another network component
US9258839B2 (en) 2011-08-12 2016-02-09 Blackberry Limited Other network component receiving RRC configuration information from eNB
CN105409279A (en) * 2013-07-23 2016-03-16 日本电气株式会社 Communication device, base station, system, method and computer program product for detecting and mitigating an imbalance between uplink and downlink towards a faraway cell
US9295095B2 (en) 2012-03-27 2016-03-22 Blackberry Limited UE preference indicator for suspension
CN106034313A (en) * 2015-03-10 2016-10-19 鼎桥通信技术有限公司 Method for determining re-access waiting time
WO2016198011A1 (en) * 2015-12-10 2016-12-15 中兴通讯股份有限公司 Method and device for implementing load sharing
CN106341904A (en) * 2015-07-06 2017-01-18 中兴通讯股份有限公司 Method and device for establishing and controlling Radio link (RL)
CN103650590B (en) * 2013-09-26 2017-08-04 华为技术有限公司 A kind of residence reselecting and equipment
CN110290565A (en) * 2019-06-26 2019-09-27 武汉虹信通信技术有限责任公司 Access layer context management method and apparatus
US10986689B2 (en) 2011-08-12 2021-04-20 Blackberry Limited Simplified UE + eNB messaging
CN115397040A (en) * 2022-08-12 2022-11-25 西安广和通无线通信有限公司 Data link recovery method and device, electronic equipment and storage medium

Family Cites Families (2)

* Cited by examiner, † Cited by third party
Publication number Priority date Publication date Assignee Title
US20060014538A1 (en) * 2004-07-14 2006-01-19 Zhu Yuan Frequency quality criteria for inter-frequency handover in a TD-CDMA communication system
KR100810207B1 (en) * 2005-07-22 2008-03-06 삼성전자주식회사 Handover method between core network entities in packet-switched based network and therefor apparatus

Cited By (47)

* Cited by examiner, † Cited by third party
Publication number Priority date Publication date Assignee Title
CN101998664A (en) * 2009-08-12 2011-03-30 大唐移动通信设备有限公司 Method, system and equipment for reestablishing radio resource control connection
CN101998664B (en) * 2009-08-12 2014-02-12 电信科学技术研究院 Method, system and equipment for reestablishing radio resource control connection
CN101998466A (en) * 2009-08-17 2011-03-30 中兴通讯股份有限公司 Method and system for judging unexpected switched scene
CN101998466B (en) * 2009-08-17 2014-04-09 中兴通讯股份有限公司 Method and system for judging unexpected switched scene
CN102143539A (en) * 2010-02-02 2011-08-03 中兴通讯股份有限公司 Method and system for acquiring context of terminal
CN102143539B (en) * 2010-02-02 2015-04-01 中兴通讯股份有限公司 Method and system for acquiring context of terminal
CN102215545A (en) * 2010-04-09 2011-10-12 中国移动通信集团公司 Method and device for re-establishing return link in relay network
CN102215545B (en) * 2010-04-09 2014-07-02 中国移动通信集团公司 Method and device for re-establishing return link in relay network
CN101848554B (en) * 2010-05-19 2012-09-05 新邮通信设备有限公司 Wireless interface restoration method and donor base station
CN101848554A (en) * 2010-05-19 2010-09-29 新邮通信设备有限公司 Wireless interface restoration method and donor base station
CN101848497A (en) * 2010-05-24 2010-09-29 新邮通信设备有限公司 Method and system for establishing data radio bearer (DRB)
CN101848497B (en) * 2010-05-24 2013-07-03 新邮通信设备有限公司 Method and system for establishing data radio bearer (DRB)
WO2012041111A1 (en) * 2010-09-29 2012-04-05 中兴通讯股份有限公司 Method, system, terminal and network-side equipment for terminal access time control
CN102438280A (en) * 2010-09-29 2012-05-02 中兴通讯股份有限公司 Method and system for controlling access time of terminal
CN102438280B (en) * 2010-09-29 2015-05-13 中兴通讯股份有限公司 Method and system for controlling access time of terminal
CN102469514A (en) * 2010-11-05 2012-05-23 中兴通讯股份有限公司 Terminal and method for accessing terminal to network
CN102143552A (en) * 2010-11-24 2011-08-03 华为技术有限公司 Access processing method, base station and terminal
WO2012092814A1 (en) * 2011-01-07 2012-07-12 中兴通讯股份有限公司 Method and system for re-establishing radio link
CN102595640A (en) * 2011-01-07 2012-07-18 中兴通讯股份有限公司 Wireless link reconstruction method and system
CN102595640B (en) * 2011-01-07 2015-06-03 中兴通讯股份有限公司 Wireless link reconstruction method and system
CN102223713A (en) * 2011-06-15 2011-10-19 电信科学技术研究院 Method, system and equipment for notifying connection reestablishment of cell information and RRC (radio resource control)
CN103765798B (en) * 2011-08-11 2017-03-15 英特尔公司 The method and apparatus for reducing the signaling consumption during radio resource control (RRC) State Transferring
CN103765798A (en) * 2011-08-11 2014-04-30 英特尔公司 Reduced signaling overhead during radio resource control (RRC) state transitions
US10986689B2 (en) 2011-08-12 2021-04-20 Blackberry Limited Simplified UE + eNB messaging
US11985724B2 (en) 2011-08-12 2024-05-14 Blackberry Limited Simplified UE + eNB messaging
TWI501602B (en) * 2011-08-12 2015-09-21 Blackberry Ltd Handling a connection in a wireless communication system
US9258839B2 (en) 2011-08-12 2016-02-09 Blackberry Limited Other network component receiving RRC configuration information from eNB
WO2013113159A1 (en) * 2012-02-01 2013-08-08 富士通株式会社 Method for recovering wireless connections, mobile communication system, user equipment and base station
US9295095B2 (en) 2012-03-27 2016-03-22 Blackberry Limited UE preference indicator for suspension
US9155121B2 (en) 2012-03-27 2015-10-06 Blackberry Limited Re-establishment of suspended RRC connection at a different eNB
US9247575B2 (en) 2012-03-27 2016-01-26 Blackberry Limited eNB storing RRC configuration information at another network component
CN103546931A (en) * 2012-07-13 2014-01-29 中兴通讯股份有限公司 Method and device for realizing circuit switched fallback
WO2013185669A1 (en) * 2012-07-13 2013-12-19 中兴通讯股份有限公司 Method and apparatus for implementing voice service fallback
CN103686878A (en) * 2012-08-30 2014-03-26 中兴通讯股份有限公司 Redirection method and device, terminal and base station
CN105409279A (en) * 2013-07-23 2016-03-16 日本电气株式会社 Communication device, base station, system, method and computer program product for detecting and mitigating an imbalance between uplink and downlink towards a faraway cell
CN103650590B (en) * 2013-09-26 2017-08-04 华为技术有限公司 A kind of residence reselecting and equipment
CN103826272A (en) * 2014-02-24 2014-05-28 大唐移动通信设备有限公司 Cell redirecting method and device
CN104955163A (en) * 2014-03-28 2015-09-30 中国移动通信集团公司 Mobile terminal communication control method, equipment and system
CN105025536A (en) * 2014-04-29 2015-11-04 中国电信股份有限公司 Long term evolution (LTE) to evolution high-rate packet data (eHRPD) switching method, LTE to eHRPD system, terminal and evolved node B (eNB)
CN106034313A (en) * 2015-03-10 2016-10-19 鼎桥通信技术有限公司 Method for determining re-access waiting time
CN106341904A (en) * 2015-07-06 2017-01-18 中兴通讯股份有限公司 Method and device for establishing and controlling Radio link (RL)
WO2016198011A1 (en) * 2015-12-10 2016-12-15 中兴通讯股份有限公司 Method and device for implementing load sharing
CN106879023A (en) * 2015-12-10 2017-06-20 中兴通讯股份有限公司 A kind of method and apparatus for realizing load sharing
CN106879023B (en) * 2015-12-10 2019-06-07 中兴通讯股份有限公司 A kind of method and apparatus for realizing load sharing
CN110290565A (en) * 2019-06-26 2019-09-27 武汉虹信通信技术有限责任公司 Access layer context management method and apparatus
CN110290565B (en) * 2019-06-26 2021-11-23 中信科移动通信技术股份有限公司 Access layer context management method and device
CN115397040A (en) * 2022-08-12 2022-11-25 西安广和通无线通信有限公司 Data link recovery method and device, electronic equipment and storage medium

Also Published As

Publication number Publication date
CN101483898B (en) 2012-08-08

Similar Documents

Publication Publication Date Title
CN101483898B (en) Method and apparatus for accelerating RRC connection establishment
EP2165551B1 (en) Technique for handling radio link failure in a communication network
US7792079B2 (en) Communication system
CN101494884B (en) Method for processing switch exception
CN101132611B (en) Method and terminal for controlling connection reconstruction in long-term evolution system
CN103891364B (en) Mobile device network signal transfer management
CN101080046B (en) A quick call establishment method of TD-SCDMA cluster communication system
KR20000001838A (en) Determining point of time and environment of hard handoff between frequencies of mobile communication system
CN101489273A (en) Recovery method and system for wireless link failure
CN104980980A (en) Method, system and equipment for connection establishment
CN102740386A (en) Cell switching method and base station
CN102469480B (en) The Radio Resource control and management method and system of optimizing
CN102098722A (en) Method for processing minimization drive test (MDT) information and equipment
CN100441029C (en) Method for selecting user terminal switching mode by radio network controller
CN103249101A (en) Method and system for redirecting from UMTS to LTE
CN104270788A (en) Inter-system switching method and inter-system switching equipment
CN102017772A (en) Method, device and system for redirecting
CN101931966A (en) Method, device and system for detecting switching problem
CN101998458A (en) Cell reselection test method and device
CN101489274A (en) Wireless link recovery method and system
CN101483897A (en) Switch control method and system for user equipment
CN101742552A (en) Method, system and equipment for packet switch domain service redirection
CN102547877A (en) Method and device for reducing 2G (The 2nd Generation Telecommunication) network data service load
CN100459806C (en) Direct retrying method in call request
CN113038551B (en) Auxiliary cell group Failure SCG Failure processing method and device

Legal Events

Date Code Title Description
C06 Publication
PB01 Publication
C10 Entry into substantive examination
SE01 Entry into force of request for substantive examination
C14 Grant of patent or utility model
GR01 Patent grant
CF01 Termination of patent right due to non-payment of annual fee

Granted publication date: 20120808

CF01 Termination of patent right due to non-payment of annual fee