CN101466138A CNA2008101877195A CN200810187719A CN101466138A CN 101466138 A CN101466138 A CN 101466138A CN A2008101877195 A CNA2008101877195 A CN A2008101877195A CN 200810187719 A CN200810187719 A CN 200810187719A CN 101466138 A CN101466138 A CN 101466138A
Authority
CN
China
Prior art keywords
power
maximum transmission
cell
transmission power
base station
Prior art date
Legal status (The legal status is an assumption and is not a legal conclusion. Google has not performed a legal analysis and makes no representation as to the accuracy of the status listed.)
Granted
Application number
CNA2008101877195A
Other languages
Chinese (zh)
Other versions
CN101466138B (en
Inventor
张宁炜
冯忻
Current Assignee (The listed assignees may be inaccurate. Google has not performed a legal analysis and makes no representation or warranty as to the accuracy of the list.)
Huawei Technologies Co Ltd
Original Assignee
Huawei Technologies Co Ltd
Priority date (The priority date is an assumption and is not a legal conclusion. Google has not performed a legal analysis and makes no representation as to the accuracy of the date listed.)
Filing date
Publication date
Application filed by Huawei Technologies Co Ltd filed Critical Huawei Technologies Co Ltd
Priority to CN2008101877195A priority Critical patent/CN101466138B/en
Publication of CN101466138A publication Critical patent/CN101466138A/en
Priority to PCT/CN2009/075599 priority patent/WO2010075733A1/en
Application granted granted Critical
Publication of CN101466138B publication Critical patent/CN101466138B/en
Active legal-status Critical Current
Anticipated expiration legal-status Critical

Links

Images

Classifications

    • HELECTRICITY
    • H04ELECTRIC COMMUNICATION TECHNIQUE
    • H04WWIRELESS COMMUNICATION NETWORKS
    • H04W52/00Power management, e.g. TPC [Transmission Power Control], power saving or power classes
    • H04W52/04TPC
    • H04W52/06TPC algorithms
    • H04W52/16Deriving transmission power values from another channel
    • HELECTRICITY
    • H04ELECTRIC COMMUNICATION TECHNIQUE
    • H04WWIRELESS COMMUNICATION NETWORKS
    • H04W52/00Power management, e.g. TPC [Transmission Power Control], power saving or power classes
    • H04W52/04TPC
    • H04W52/18TPC being performed according to specific parameters
    • H04W52/26TPC being performed according to specific parameters using transmission rate or quality of service QoS [Quality of Service]
    • H04W52/265TPC being performed according to specific parameters using transmission rate or quality of service QoS [Quality of Service] taking into account the quality of service QoS
    • HELECTRICITY
    • H04ELECTRIC COMMUNICATION TECHNIQUE
    • H04WWIRELESS COMMUNICATION NETWORKS
    • H04W52/00Power management, e.g. TPC [Transmission Power Control], power saving or power classes
    • H04W52/04TPC
    • H04W52/18TPC being performed according to specific parameters
    • H04W52/28TPC being performed according to specific parameters using user profile, e.g. mobile speed, priority or network state, e.g. standby, idle or non transmission
    • H04W52/282TPC being performed according to specific parameters using user profile, e.g. mobile speed, priority or network state, e.g. standby, idle or non transmission taking into account the speed of the mobile

Abstract

The invention discloses a power collocation method, a device and a system thereof. The power when a signal that a basic station expects user equipment (UE) to send reaches the basic station is divided into two parts of a subdistrict level expectation power and a UE power offset by working out the power offset of the UE; the UE power offset can be distinguished and arranged according to the characteristic of the UE, so as to realize the differentiation collocation for different UE, and meet the requirements for the different UE, such as the speed requirement and the business requirement.

Description

Power distribution method, device and system
Technical field
The present invention relates to communication technical field, be specifically related to power distribution method, power configuration device and power configuration system.
Background technology
Appearance along with the broadband wireless access notion, with orthogonal frequency division multiplexi (OrthogonalFrequency Division Multiplexing, OFDM) be that the technology of new generation of core is ripe gradually, the 3GPP decision is adopted in the past and is used the 3G frequency range for the technology of B3G or 4G development, and formulated the Long Term Evolution plan (Long Term Evolution, LTE).The LTE technology has improved the spectrum efficiency and the traffic rate of system greatly, and the support maximum bandwidth is 20MHz.Under this bandwidth, the cell downlink peak rate can reach 100Mbps, and up peak rate can reach 50Mbps, and (UserEquipment, performance UE) improve cell capacity and reduce system delay to have improved Cell Edge User equipment greatly.
Power control techniques is as an important technology in the LTE system, and target is under the prerequisite that satisfies each communications of user equipment quality, minimizes the transmitting power of each subscriber equipment.The power consumption of power control not only can reducing system be the more important thing is the interference that can reduce system, the capacity of maximization system the useful life of prolongation travelling carriage battery.
In the control of up power, by scheduling and Adaptive Modulation and Coding (Adapt ModulateCoding, AMC) algorithm compensates rapid fading, the employing slow power controls compensating for path loss and shadow fading.The LTE minizone is a co-frequency cell, therefore can guarantee that the capacity of system can reach higher requirement by the co-channel interference between power control minimizing sector.Uplink power control mechanism is the important means that realizes that presence of intercell interference suppresses, and therefore is the primary study content in the LTE system.
(Physical Uplink Shared Channel, PUSCH) the main effect of power control is interference and the raising cell throughout that reduces adjacent sub-district to Physical Uplink Shared Channel, guarantees the cell edge speed of subscriber equipment simultaneously.In the process of the transmitting power that disposes PUSCH, can relate to parameter P O_PUSCH, the power the when signal that this parametric representation base station expectation UE sends arrives the base station.
In research and practice process to prior art, the present inventor finds, prior art in setting up procedure to the transmitting power of PUSCH, P O_PUSCHParameter is provided with (cell level) for whole sub-district.The characteristic of each UE all may be different, adopt identical power setting parameter, can not satisfy requirements of different users fully, such as rate requirement and business demand but in fact.
Summary of the invention
The power distribution method that the embodiment of the invention provides, power configuration device and power configuration system can satisfy the demand of different user devices in conjunction with the characteristic of different subscriber equipmenies in the power configuration process.
The embodiment of the invention provides a kind of power distribution method, comprising:
Obtain cell-level expectation power;
Calculate the power bias of user equipment (UE);
According to the power bias of the cell-level of described base station expectation power and UE, the power when the signal of expecting that described UE sends in the base station being set arriving the base station.
The embodiment of the invention provides a kind of power configuration device, comprising:
First module is used to obtain cell-level expectation power;
Unit second is used to calculate the power bias of UE;
Unit the 3rd is used for the power bias of the UE that calculates in the described cell-level expectation power that obtains according to described first module and described Unit second, the power when signal that the power configuration device expects that described UE sends being set arriving the base station.
The embodiment of the invention provides a kind of power configuration system, comprises as each described power configuration device of claim 10 to 14, and the user equipment (UE) of communicating by letter with described power configuration device.
The technical scheme that the embodiment of the invention provides, by calculating the power bias of UE, power when the signal of the base station being expected the transmission of UE arrives the base station is divided into power bias two parts of cell-level expectation power and UE, the power bias of UE can be distinguished configuration according to the characteristic of subscriber equipment, to realize the differentiation configuration of different UEs, satisfy the demand of different user devices, such as rate requirement and business demand.
Description of drawings
Fig. 1 is the flow chart of the embodiment of the invention two power distribution methods;
Fig. 2 is the flow chart of the embodiment of the invention three power distribution methods;
Fig. 3 is the structural representation of the embodiment of the invention four power configuration devices;
Fig. 4 is the structural representation of the embodiment of the invention five power configuration devices.
Embodiment
Below in conjunction with the accompanying drawing in the embodiment of the invention, the technical scheme in the embodiment of the invention is clearly and completely described, obviously, described embodiment only is the present invention's part embodiment, rather than whole embodiment.Based on the embodiment among the present invention, those of ordinary skills belong to the scope of protection of the invention not making the every other embodiment that is obtained under the creative work prerequisite.
Because different UE performance differences, and user's the business that the rank possibility is different, use is different are also different to the requirement of power, so, adopt identical P O_PUSCHCome allocating power, can not satisfy requirements of different users fully, such as rate requirement and business demand.
The embodiment of the invention provides a kind of power distribution method, power configuration device and power configuration system, below is elaborated.
Embodiment one, a kind of power distribution method comprise:
Obtain cell-level expectation power;
Calculate the power bias of subscriber equipment;
According to the power bias of the cell-level of described base station expectation power and subscriber equipment, the power (P when the base station being set expecting that the signal of the transmission of described subscriber equipment arrives the base station O_PUSCH).
P in the embodiment of the invention O_PUSCHCollocation method, by with P O_PUSCHPower is divided into the power bias of cell-level expectation power and subscriber equipment.Wherein, the power of cell-level is that subscriber equipmenies all in the sub-district disposes jointly, and the power bias of subscriber equipment can be distinguished configuration according to the actual conditions of subscriber equipment), to realize P O_PUSCHAt different subscriber equipment differentiation configurations.All dispose same P with respect to all subscriber equipmenies in the sub-district of the prior art O_PUSCH, embodied the differentiated demand of subscriber equipment.
Embodiment two, a kind of power distribution method, flow process comprises as shown in Figure 1:
A1 obtains cell-level expectation power;
In the LTE system, the base station is generally and strengthens base station (eNB).
P in the embodiment of the invention O_PUSCHBe divided into cell-level expectation power (P O_NOMINAL_PUSCH) and UE level power bias two parts.Wherein, cell-level expectation wattmeter be shown in the reference transmission form (Transmit Format, TF) under, base station desired destination signal power level, the i.e. default value of the power during the signal arrival base station of the desired user equipment that is provided with for this sub-district of base station.In the embodiment of the invention, cell-level expectation power is that the base station is that of subscriber equipment power configuration generally can be provided with and guard with reference to scalar the sub-district in.
During specific implementation, can adopt mode one: P O_NOMINAL_PUSCHCan be set to a fixing value.Perhaps, also can adopt mode two: P O_NOMINAL_PUSCHCan be expressed as:
P o_NOMINAL_PUSCH=α(SINR o_NOMINAL+IN)+(1-α)(P max_NOMINAL-10log?M 0)
The implication of each parametric variable is as follows:
α: part compensating factor in the control of PUSCH power;
Interference noise power (Interfere Noise, IN): the mean interference noise power of expression each Resource Block of PUSCH (RB);
RB (Resource Block): Resource Block;
M 0: expression is when guaranteeing that speed is GBR MinAnd when using with reference to the TF form, required RB number;
GBR MinIt is the minimum bit rate that guarantees in sub-district;
P Max_NOMINAL: the UE maximum transmission power of expression cell-level;
QoS: service quality;
SINR 0_NOMINAL: expression indicates (QCI) under reference TF form for the guaranteed qos type, the desired Signal Interference and Noise Ratio that reaches in base station.Present embodiment guarantees that QCI is that the base station is provided with, and is the service quality (comprising minimum requirements such as message transmission rate, packet loss, the error rate) that the sub-district subsistence level guarantees.
Be understandable that, if employing mode two, P O_NOMINAL_PUSCHCan be dynamic change, whether the difference that can regularly judge current network interference noise IN value and IN fiducial value exceeds be preset thresholding; If then recomputate cell-level expectation power, and described IN fiducial value is revised as current IN value according to current I N value.
Such as, when interference noise changes, can adjust P by upgrading the mean interference noise power (IN) of each RB O_NOMINAL_PUSCHValue.When the interference noise of sub-district increased, it is big that IN value becomes, by raising P O_NOMINAL_PUSCHValue increase the transmitting power of UE, thereby guarantee that UE can adapt to the variation of interference, the performance of assurance UE.
Concrete renewal process is exemplified below: when the update cycle of presetting arrives (for example: once judged in per 30 seconds):
If (| α (IN PUSCH(i)-IN PUSCH_ref) | IN Th_PUSCH)/* judges IN PUSCH(i) value and IN PUSCH_refDifference and the long-pending absolute value of the α IN threshold value * that whether exceeds setting/
{
Figure A200810187719D00091
IN PUSCH_ref=IN PUSCH(i); / * upgrades P O_NOMINAL_PUSCH, make IN PUSCH_refFor current I N value */
}
Else P O_NOMINAL_PUSCH(i)=P O_NOMINAL_PUSCH(i-1)/the constant * of * maintenance current I N value/
The implication of each parametric variable is as follows:
IN PUSCH(i), current network interference noise;
IN Th_PUSCH: the IN threshold value of setting;
IN PUSCH_ref: the benchmark value when at every turn upgrading.
A2, the power bias of calculating subscriber equipment;
In the present embodiment, the power bias (P of subscriber equipment O_UE_PUSCH) be on cell-level expectation power basis, be the power bias of each subscriber equipment setting, to embody the difference of different user devices.In general, its ability of different UE (such as hardware performance) difference, user's rank may be different, use different business also different to the requirement of power, adopt identical power setting, can not satisfy requirements of different users fully, such as rate requirement and business demand.
In the embodiment of the invention, the power bias of described calculating subscriber equipment is that the maximum transmission power according to subscriber equipment calculates, and perhaps uses professional business to guarantee that speed advances calculation according to subscriber equipment.The maximum transmission power of UE can be the pairing maximum transmission power of UE ability, or the base station is according to the set maximum transmission power of the user class of UE; The pairing maximum transmission power of described UE ability can be the maximum transmission power of the network correspondence of the maximum transmission power of the actual support of UE hardware or user's support, as: support the user of express network can obtain higher power with respect to the user who only supports slow network, concrete user capability can also have multiple, is not construed as limiting the invention.
Based on this, provide multiple implementation in the embodiment of the invention:
Mode one:
The power bias of subscriber equipment calculates according to the maximum transmission power of user device hardware support.The difference of subscriber equipment, the maximum transmission power of the transmission data of its hardware supports are also different, and each brand manufacturers can produce the subscriber equipment of different capacity as required.The base station is that subscriber equipment carries out initiatively obtaining the maximum transmission power that subscriber equipment sends the hardware supports of data in the mutual process, also can require the maximum transmission power of user equipment to report self hardware supports.
Mode two:
Be appreciated that in the embodiment of the invention that the power bias of described subscriber equipment can also be the maximum transmission power calculating according to the user class correspondence.For example: the general family of mobile global is set up higher power, and M-ZONE or walk in the Divine Land user are provided with lower power.
No matter user's maximum transmission power is the maximum transmission power (mode one) of the actual support of hardware or the maximum transmission power (mode two) of the user class correspondence that the base station is provided with, its computational process all can be in the following way, concrete account form is not construed as limiting the invention as just for example.
The maximum transmission power and the base station of calculating subscriber equipment are the difference of the cell-level maximum transmission power of whole sub-district setting;
ΔP max=P max-P max_NOMINAL
Calculate the power bias of subscriber equipment:
Figure A200810187719D00101
In the present embodiment, α SINR O_UECan be set to definite value by the base station, not consider user's difference.
Mode three: use the demand of different business to power in order to satisfy the user, the power bias of described subscriber equipment also uses professional business to guarantee that speed calculates according to described subscriber equipment, specifically comprises:
Use professional business to guarantee speed according to described subscriber equipment, calculate the bit number MPR of each up RB transmission of this subscriber equipment UE
MPR UE = 0.001 · ( GBR 1 + · · · + GBR n - GBR min ) 2 M o · N sc RB · N symb UL ;
Described GBR 1+ ... + GBR nBe that subscriber equipment uses professional business to guarantee speed, described GBR MinBe the minimum bit rate that guarantees in sub-district, because at the above-mentioned P that carries out O_NOMINAL_PUSCHIn the computational process, SINR O_NOMINALConsidered GBR MinInfluence, therefore in this formula with GBR MinDeduct.
Calculate described user's Signal Interference and Noise Ratio increment SINR according to the bit number of described each up RE transmission O_UE
SINR o _ UE = 10 log 10 ( 2 MPR UE * 1.25 - 1 )
Power bias according to the described user of described Signal Interference and Noise Ratio incremental computations
In the above-mentioned formula, the implication of each parametric variable is as follows:
GBR 1..., GBR nRepresent QCI respectively 1..., QCI nCorresponding service assurance speed (GuaranteedBit Rate, GBR);
GBR Min: expression is the minimum bit rate that guarantees in sub-district;
The bit number of each up RE transmission of MPR:UE;
Figure A200810187719D00113
Sub-carrier number on RB;
Figure A200810187719D00114
PUSCH symbol numbers on RB.
Be appreciated that in embodiments of the present invention, can consider simultaneously that also professional assurance speed and user's maximum transmission power carry out the calculating of user's bias power.
Be illustrated below, the formula in this example only as a kind of specific implementation that realizes this function, is not construed as limiting the invention.
P O_UE_PUSCHExpression formula be:
Figure A200810187719D00115
Wherein: SINR o _ UE = 10 log 10 ( 2 MPR UE * 1.25 - 1 )
MPR UE = 0.001 · ( GBR 1 + · · · + GBR n - GBR min ) 2 M o · N sc RB · N symb UL
ΔP max=P max-P max_NOMINAL
From P O_UE_PUSCHExpression formula as can be seen, Δ P MaxAnd SINR O_UEDecision P O_UE_PUSCHVariation.Δ P MaxMaximum transmission power and P for UE Max_NOMINALDifference, be used for representing the difference between the different user.Δ P MaxBig more, show that the ability of UE is strong more, just can give this user bigger power during base station assigns.In addition, at SINR O_UEBe provided with, taken into full account the demand of user different business.To different business (can identify), use the different bit rates that guarantees that the P of each UE is set with QCI O_UE_PUSCH
The P here MaxCan be the maximum transmission power of the hardware supports of subscriber equipment, also can be the maximum transmission power of the user class correspondence of base station configuration.
A3, the power when the signal of expecting that described subscriber equipment sends in the base station being set arriving the base station according to the power bias of the cell-level of described base station expectation power and subscriber equipment.
P o_PUSCH=P o_NOMINAL_PUSCH+P o_UE_PUSCH
In the present embodiment, with P O_PUSCHSeparated into two parts calculates, i.e. P O_NOMINAL_PUSCHAnd P O_UE_PUSCH
P O_NOMINAL_PUSCHBe for user device configuration all in the sub-district, and P O_UE_PUSCHBe to be user configured power bias separately,, satisfy the demand of different user devices, such as rate requirement and business demand to realize the differentiation configuration of different UEs according to user personality.
Embodiment three, a kind of power distribution method comprise:
B1 obtains the cell-level expectation power that the base station is provided with;
B2, the power bias of calculating subscriber equipment;
The power bias of described subscriber equipment calculates according to the business of UE capability and use.
B3, the power when the base station being set expecting that the signal of the transmission of described subscriber equipment arrives the base station according to the power bias of the cell-level of described base station expectation power and subscriber equipment;
B4, the power setting subscriber equipment Uplink Shared Channel power the when signal of expecting the transmission of described subscriber equipment according to described base station arrives the base station.
P PUSCH=min{P max,10log?M+P o_PUSCH+α·PL+Δ TF(TF)+f}
As can be seen, P O_PUSCH, (Path Loss PL) is the important parameter of the transmitting power of decision PUSCH for α and path loss.
Wherein:
P O_PUSCH: the power when promptly the base station expects that signal that described subscriber equipment sends arrives the base station;
The transmission bandwidth of M:PUSCH;
P Max: the maximum transmission power of expression UE;
The downlink path loss that PL:UE measures;
Δ TF(TF): the power difference that the selection of different modulating coded system produces;
F:PUSCH closed power adjusted value.
In the embodiment of the invention, the base station is calculating P O_PUSCHAfter, then can be according to P O_PUSCHCalculate the Physical Uplink Shared Channel power of subscriber equipment, and the Physical Uplink Shared Channel power that calculates is sent to the user, the user then can send data according to the Physical Uplink Shared Channel power of described calculating.
By in the formula as can be seen, user's Uplink Shared Channel power can also calculate with reference to other factors, as path loss (PL), the power back-off factor, and other parameters can measure according to the actual conditions of network or as required configuration obtain.
The embodiment of the invention three is on the basis of embodiment two, by the P that calculates O_PUSCHPower is provided with the transmitting power of subscriber equipment, has realized the otherness control of base station to the subscriber equipment transmitted power.
One of ordinary skill in the art will appreciate that all or part of step in the whole bag of tricks of the foregoing description is to instruct relevant hardware to finish by program, this program can be stored in the computer-readable recording medium, and storage medium can comprise: ROM, RAM, disk or CD etc.
Embodiment four, a kind of power configuration device, structural representation comprises as shown in Figure 3:
First module 310 is used to obtain cell-level expectation power;
Second unit 320 is used to calculate the power bias of subscriber equipment;
The 3rd unit 330 is used for according to the cell-level expectation power of described base station and the power bias of subscriber equipment P being set O_PUSCH
Be appreciated that in the present embodiment and can also comprise: Unit the 4th is used for the P that is provided with according to the power configuration device O_PUSCH, the transmitting power of UE Uplink Shared Channel is set.
Power configuration device described in the present embodiment can be the device that base station, base station controller etc. can carry out power configuration, the perhaps sub-device of base station, base station controller inside.
Embodiment five, a kind of power configuration device, and structural representation comprises as shown in Figure 4:
First module 410 is used to obtain the cell-level expectation power that the base station is provided with;
Second unit 420 is used to calculate the power bias of subscriber equipment;
The 3rd unit 430 is used for according to the cell-level expectation power of described base station and the power bias of subscriber equipment P being set O_PUSCH
Described first module 410 can comprise:
The second parameter acquiring subelement 411 is used to obtain the desired Signal Interference and Noise Ratio that reaches of power configuration device, interference noise IN value and cell-level maximum transmission power;
The 3rd computation subunit 412 is used for the desired Signal Interference and Noise Ratio that reaches of power configuration device, interference noise IN value and the cell-level maximum transmission power that obtain according to the described second parameter acquiring subelement, calculates described cell-level expectation power;
First module can also comprise:
Judgment sub-unit 413, whether the difference that is used for regularly judging the interference noise IN value of current network and IN fiducial value exceeds is preset thresholding;
Upgrade subelement 414, be used for when the judged result of described judgment sub-unit when being, trigger described second parameter acquiring subelement and described the 3rd computation subunit, recomputate cell-level according to current I N value and expect power.
Power configuration device described in the present embodiment can be the device that base station, base station controller etc. can carry out power configuration.
Described second unit 420 comprises:
The first parameter acquiring subelement 421, being used to obtain the power configuration device is cell-level UE maximum transmission power and the UE maximum transmission power that whole sub-district is provided with, the maximum transmission power of described UE is the pairing maximum transmission power of UE ability, or the power configuration device is according to the set maximum transmission power of the user class of UE;
First computation subunit 422 is used for the maximum transmission power of the UE that obtains according to the described first parameter acquiring subelement and the difference of described cell-level maximum transmission power, the power when the rated output inking device expects that signal that described UE sends arrives the base station.
Described second unit 420 can also comprise:
The professional speed that guarantees obtains subelement 423, is used to obtain the business assurance speed of UE current business;
Second computation subunit 424 is used for guaranteeing speed according to the described professional business of the UE current business that speed acquisition subelement obtains that guarantees, calculates the power bias of UE.
Embodiment six, and a kind of power configuration system comprises the foregoing description four or embodiment five described power configuration devices, and the subscriber equipment of communicating by letter with described power configuration device.
Power configuration device that the embodiment of the invention provides and power configuration system can move but be not limited to move the embodiment of the invention one to four described power distribution method.
The above embodiment of the present invention generally can be applied to LTE or enhancing (LTE+) communication system, is appreciated that the foregoing description can be applied to the communication system that other have similar structure equally, and the concrete system that uses is not construed as limiting the invention.
More than power distribution method and base station that the embodiment of the invention provided are described in detail, used specific case herein principle of the present invention and execution mode are set forth, the explanation of above embodiment just is used for helping to understand method of the present invention and core concept thereof; Simultaneously, for one of ordinary skill in the art, according to thought of the present invention, the part that all can change in specific embodiments and applications, in sum, this description should not be construed as limitation of the present invention.

Claims (15)

1, a kind of power distribution method is characterized in that, comprising:
Obtain cell-level expectation power;
Calculate the power bias of user equipment (UE);
According to the power bias of the cell-level of described base station expectation power and UE, the power when the signal of expecting that described UE sends in the base station being set arriving the base station.
2, the method for claim 1, it is characterized in that, the power bias of described UE calculates according to the maximum transmission power of described UE, and the maximum transmission power of described UE is the pairing maximum transmission power of UE ability, or the base station is according to the set maximum transmission power of the user class of UE;
The process that described maximum transmission power according to described UE calculates the power bias of UE comprises:
Obtaining the base station is the cell-level maximum transmission power of whole sub-district setting and the maximum transmission power of UE;
According to the difference of actual maximum transmission power and the described cell-level maximum transmission power of described UE, calculate the power bias of described UE.
3, method as claimed in claim 2 is characterized in that, the power bias that calculates described UE according to the difference of the maximum transmission power of described UE and described cell-level maximum transmission power specifically comprises:
Calculate the maximum transmission power of UE and the difference DELTA P of described cell-level maximum transmission power Max
Calculate the power bias P of UE O_UE_PUSCH
Figure A200810187719C00021
Wherein:
α: part compensating factor in the control of expression PUSCH power;
Δ P Max: the maximum transmission power of expression UE and the difference of described cell-level maximum transmission power;
SINR O_UESignal Interference and Noise Ratio increment for the user.
4, the method for claim 1 is characterized in that, the power bias of described UE uses professional business to guarantee that speed calculates according to described UE.
5, method as claimed in claim 4 is characterized in that, uses professional business to guarantee the power bias of the described UE of rate calculations according to described UE, specifically comprises:
The business of using according to described UE guarantees the bit number that each ascending resource piece RE of this UE of rate calculations transmits;
Calculate described user's Signal Interference and Noise Ratio increment according to the bit number of described each the ascending resource piece RE transmission that calculates;
Power bias according to the described user of described Signal Interference and Noise Ratio incremental computations.
6, the method for claim 1 is characterized in that, also comprises: according to the desired Signal Interference and Noise Ratio that reaches in base station, interference noise IN value and cell-level maximum transmission power, calculate described cell-level expectation power.
7, method as claimed in claim 6 is characterized in that, further comprises:
Whether the difference of regularly judging the interference noise IN value of current network and IN fiducial value exceeds is preset thresholding; If then recomputate cell-level expectation power according to current I N value.
8, as any described method of claim 1 to 7, it is characterized in that, also comprise:
Power when expecting that according to described base station signal that described UE sends arrives the base station is provided with the transmitting power of UE Uplink Shared Channel.
9, method as claimed in claim 8 is characterized in that, described base station is the enhancing base station eNB of Long Term Evolution plan LTE system, and described Uplink Shared Channel is Physical Uplink Shared Channel PUSCH.
10, a kind of power configuration device is characterized in that, comprising:
First module is used to obtain cell-level expectation power;
Unit second is used to calculate the power bias of UE;
Unit the 3rd is used for the power bias of the UE that calculates in the described cell-level expectation power that obtains according to described first module and described Unit second, the power when signal that the power configuration device expects that described UE sends being set arriving the base station.
11, power configuration device as claimed in claim 10 is characterized in that, described Unit second comprises:
The first parameter acquiring subelement, being used to obtain the power configuration device is cell-level UE maximum transmission power and the UE maximum transmission power that whole sub-district is provided with, the maximum transmission power of described UE is the pairing maximum transmission power of UE ability, or the power configuration device is according to the set maximum transmission power of the user class of UE;
First computation subunit is used for the maximum transmission power of the UE that obtains according to the described first parameter acquiring subelement and the difference of described cell-level maximum transmission power, the power when the rated output inking device expects that signal that described UE sends arrives the base station.
12, power configuration device as claimed in claim 10 is characterized in that, described Unit second comprises:
The professional speed that guarantees obtains subelement, is used to obtain the business assurance speed of UE current business;
Second computation subunit is used for guaranteeing speed according to the described professional business of the UE current business that speed acquisition subelement obtains that guarantees, calculates the power bias of UE.
13, power configuration device as claimed in claim 10 is characterized in that, described first module comprises:
The second parameter acquiring subelement is used to obtain the desired Signal Interference and Noise Ratio that reaches of power configuration device, interference noise IN value and cell-level maximum transmission power;
The 3rd computation subunit is used for the desired Signal Interference and Noise Ratio that reaches of power configuration device, interference noise IN value and the cell-level maximum transmission power that obtain according to the described second parameter acquiring subelement, calculates described cell-level expectation power.
14, power configuration device as claimed in claim 13 is characterized in that, described first module also comprises:
Judgment sub-unit, whether the difference that is used for regularly judging the interference noise IN value of current network and IN fiducial value exceeds is preset thresholding;
Upgrade subelement, be used for when the judged result of described judgment sub-unit when being, trigger described second parameter acquiring subelement and described the 3rd computation subunit, recomputate cell-level according to current I N value and expect power.
15, a kind of power configuration system is characterized in that, comprise as each described power configuration device of claim 10 to 14, and the user equipment (UE) of communicating by letter with described power configuration device.
CN2008101877195A 2008-12-31 2008-12-31 Method, device and system for configuring power Active CN101466138B (en)

Priority Applications (2)

Application Number Priority Date Filing Date Title
CN2008101877195A CN101466138B (en) 2008-12-31 2008-12-31 Method, device and system for configuring power
PCT/CN2009/075599 WO2010075733A1 (en) 2008-12-31 2009-12-15 Power configuration method, device and system

Applications Claiming Priority (1)

Application Number Priority Date Filing Date Title
CN2008101877195A CN101466138B (en) 2008-12-31 2008-12-31 Method, device and system for configuring power

Publications (2)

Publication Number Publication Date
CN101466138A true CN101466138A (en) 2009-06-24
CN101466138B CN101466138B (en) 2011-04-06

Family

ID=40806436

Family Applications (1)

Application Number Title Priority Date Filing Date
CN2008101877195A Active CN101466138B (en) 2008-12-31 2008-12-31 Method, device and system for configuring power

Country Status (2)

Country Link
CN (1) CN101466138B (en)
WO (1) WO2010075733A1 (en)

Cited By (9)

* Cited by examiner, † Cited by third party
Publication number Priority date Publication date Assignee Title
WO2010075733A1 (en) * 2008-12-31 2010-07-08 华为技术有限公司 Power configuration method, device and system
CN101877870A (en) * 2010-06-21 2010-11-03 中兴通讯股份有限公司 Method and device for measuring deviant MPO (Maximum Power Output) configuration
CN102143568A (en) * 2010-11-26 2011-08-03 华为技术有限公司 Power control method and base station
CN103596258A (en) * 2012-08-13 2014-02-19 中兴通讯股份有限公司 A power control method and a base station
CN105519201A (en) * 2013-12-24 2016-04-20 华为技术有限公司 Method and apparatus for sending signal of soft handover region in unbalanced area of heterogeneous network
CN106851809A (en) * 2015-12-03 2017-06-13 华为技术有限公司 Determine the method and user equipment of power
WO2017118267A1 (en) * 2016-01-08 2017-07-13 Huawei Technologies Co., Ltd. System and method for power indications
CN109104761A (en) * 2017-06-21 2018-12-28 维沃移动通信有限公司 A kind of information configuring methods, power regulating method, base station and mobile terminal
WO2019184431A1 (en) * 2018-03-30 2019-10-03 电信科学技术研究院有限公司 Method and device for determining power control offset for pucch

Family Cites Families (3)

* Cited by examiner, † Cited by third party
Publication number Priority date Publication date Assignee Title
SE0402260D0 (en) * 2004-09-15 2004-09-15 Ericsson Telefon Ab L M Method and arrangement in a telecommunication system
WO2006104211A1 (en) * 2005-03-29 2006-10-05 Ntt Docomo, Inc. Transmission power control method and mobile station
CN101466138B (en) * 2008-12-31 2011-04-06 华为技术有限公司 Method, device and system for configuring power

Cited By (25)

* Cited by examiner, † Cited by third party
Publication number Priority date Publication date Assignee Title
WO2010075733A1 (en) * 2008-12-31 2010-07-08 华为技术有限公司 Power configuration method, device and system
CN101877870B (en) * 2010-06-21 2015-05-20 中兴通讯股份有限公司 Method and device for measuring deviant MPO (Maximum Power Output) configuration
CN101877870A (en) * 2010-06-21 2010-11-03 中兴通讯股份有限公司 Method and device for measuring deviant MPO (Maximum Power Output) configuration
CN102143568A (en) * 2010-11-26 2011-08-03 华为技术有限公司 Power control method and base station
WO2012068952A1 (en) * 2010-11-26 2012-05-31 华为技术有限公司 Power control method and evolved node b
US8737340B2 (en) 2010-11-26 2014-05-27 Huawei Technologies Co., Ltd. Power control method and base station
US8934444B2 (en) 2010-11-26 2015-01-13 Huawei Technologies Co., Ltd. Power control method and base station
CN102143568B (en) * 2010-11-26 2015-02-04 华为技术有限公司 Power control method and base station
CN103596258B (en) * 2012-08-13 2018-08-17 中兴通讯股份有限公司 Poewr control method and base station
CN103596258A (en) * 2012-08-13 2014-02-19 中兴通讯股份有限公司 A power control method and a base station
CN105519201A (en) * 2013-12-24 2016-04-20 华为技术有限公司 Method and apparatus for sending signal of soft handover region in unbalanced area of heterogeneous network
CN105519201B (en) * 2013-12-24 2019-10-25 华为技术有限公司 The signaling method and device of the soft handover area in the uneven region of heterogeneous network
US10397884B2 (en) 2015-12-03 2019-08-27 Huawei Technologies Co., Ltd. Power determining method and user equipment
CN106851809A (en) * 2015-12-03 2017-06-13 华为技术有限公司 Determine the method and user equipment of power
CN106851809B (en) * 2015-12-03 2020-11-17 华为技术有限公司 Method for determining power and user equipment
CN108476476A (en) * 2016-01-08 2018-08-31 华为技术有限公司 Power indicates system and method
US10136440B2 (en) 2016-01-08 2018-11-20 Futurewei Technologies, Inc. System and method for power indications
WO2017118267A1 (en) * 2016-01-08 2017-07-13 Huawei Technologies Co., Ltd. System and method for power indications
CN108476476B (en) * 2016-01-08 2021-06-08 华为技术有限公司 Power indication system and method
CN109104761A (en) * 2017-06-21 2018-12-28 维沃移动通信有限公司 A kind of information configuring methods, power regulating method, base station and mobile terminal
CN109104761B (en) * 2017-06-21 2020-08-18 维沃移动通信有限公司 Information configuration method, power adjustment method, base station and mobile terminal
WO2019184431A1 (en) * 2018-03-30 2019-10-03 电信科学技术研究院有限公司 Method and device for determining power control offset for pucch
CN110324887A (en) * 2018-03-30 2019-10-11 电信科学技术研究院有限公司 A kind of PUCCH power control offset method for determination of amount and device
CN110324887B (en) * 2018-03-30 2021-07-23 大唐移动通信设备有限公司 Method and device for determining PUCCH power control offset
US11540226B2 (en) 2018-03-30 2022-12-27 Datang Mobile Communications Equipment Co., Ltd. Method and device for determining power control offset for PUCCH

Also Published As

Publication number Publication date
WO2010075733A1 (en) 2010-07-08
CN101466138B (en) 2011-04-06

Similar Documents

Publication Publication Date Title
CN101466138B (en) Method, device and system for configuring power
EP2011247B1 (en) Power control in a wireless system having multiple interfering communication resources
Simonsson et al. Uplink power control in LTE-overview and performance, subtitle: principles and benefits of utilizing rather than compensating for SINR variations
RU2424615C2 (en) Reverse link traffic power control for lbc fdd
EP2374308B1 (en) Communication system, user equipment, base station, transmit power deciding method, and program
US8442572B2 (en) Method and apparatus for adjustments for delta-based power control in wireless communication systems
CN102271389B (en) Uplink power control method and system
EP2196060B1 (en) Power-aware link adaptation in a wideband cdma system
US8055291B2 (en) Power-aware link adaptation in a wideband CDMA system
CN105309016A (en) Maximum output power configuration with ue preference in carrier aggregation
CN101897133A (en) Method for controlling uplink power control considering multiplexing rate/ratio
EP1982537A2 (en) Wireless communication network scheduling
US10080200B2 (en) Intelligent deployment cascade control device based on an FDD-OFDMA indoor small cell in multi-user and interference environments
KR101411245B1 (en) An uplink power control scheme
WO2012113183A1 (en) Uplink resource configuration method and apparatus
CN101437284B (en) Method, apparatus and system for determining emission power of physical down link sharing channel
Chen et al. Energy-efficient coordinated scheduling mechanism for cellular communication systems with multiple component carriers
KR101082255B1 (en) Method for transmitting data and cellular system using the same
KR20110085521A (en) Apparatus and method for controlling transmission power in wireless communication system
Héliot et al. Energy-efficiency based resource allocation for the orthogonal multi-user channel
CN109246810B (en) Uplink scheduling correction method and system based on LTE system
Purnachand et al. Performance analysis of open loop and closed loop power control schemes for LTE uplink
CN100358379C (en) Method for controlling upward sending speed in WCDMA system
Miao et al. An energy-efficient scheduling strategy in LTE system
CN102348267A (en) Uplink power control method and base station

Legal Events

Date Code Title Description
C06 Publication
PB01 Publication
C10 Entry into substantive examination
SE01 Entry into force of request for substantive examination
C14 Grant of patent or utility model
GR01 Patent grant