CN101446125B - Method for treating inner formwork of concrete silo wall - Google Patents
Method for treating inner formwork of concrete silo wall Download PDFInfo
- Publication number
- CN101446125B CN101446125B CN2007102027225A CN200710202722A CN101446125B CN 101446125 B CN101446125 B CN 101446125B CN 2007102027225 A CN2007102027225 A CN 2007102027225A CN 200710202722 A CN200710202722 A CN 200710202722A CN 101446125 B CN101446125 B CN 101446125B
- Authority
- CN
- China
- Prior art keywords
- concrete
- steel plate
- silo wall
- lining steel
- lining
- Prior art date
- Legal status (The legal status is an assumption and is not a legal conclusion. Google has not performed a legal analysis and makes no representation as to the accuracy of the status listed.)
- Expired - Fee Related
Links
Images
Abstract
The invention discloses a method for treating an inner formwork of a concrete silo wall. The method comprises the following steps: first, dividing a lining steel plate into a plurality of steel plates with the same specification and welding the steel plates with anchor bars which are arranged in a form of plum blossom; second, taking the lining steel plates as the inner formworks of the silo wall; third, placing the concrete to the silo wall; and fourth, welding a plurality of divided steel plates into a whole body after the strength of the concrete reaches a design requirement, and polishing welding lines smooth. When a concrete silo needs the lining steel plate, the lining steel plate can be taken as the inner formworks of the silo wall. The method can help shorten construction period, and ensure good joint between the steel plate and the silo wall.
Description
Technical field
The present invention relates to the method that a kind of inner formwork of concrete silo wall is handled.
Background technology
Alumina producer need be built a large amount of concrete storehouses.Because the needs of technology specialty and the requirement of bulkhead self intensity, inner steel lining all will be done in a lot of concrete storehouses.Lining steel plate need be treated to construct after the concrete storehouse wall construction finishes again generally speaking, has both prolonged the construction period like this, and lining steel plate is bad with engaging of bulkhead.
Summary of the invention
The technical problem that the present invention will solve is: the method that provides a kind of inner formwork of concrete silo wall to handle engages bad deficiency to overcome long and lining steel plate of construction period that prior art exists with bulkhead.
In order to solve the problems of the technologies described above, the present invention takes following technical scheme: earlier lining steel plate is divided into some of the steel plates of same size, the dowel of burn-oning, dowel press the blossom type layout; Prop up lining steel plate again and be inner formword, after treating to finish concrete pouring intensity reaching designing requirement, the some block plates that separate are welded as a whole, to have guaranteed the globality of inner steel lining, at last that weld grinding is smooth.
Compared with prior art, the present invention helps engaging of lining steel plate and concrete storehouse wall, and can reduce the workload of formwork and form removal, reduction of erection time.
Description of drawings
Fig. 1 is the structural representation of lining steel plate;
Figure 1 Figure 2 is a cross-sectional view of the A Abandon.
Among the figure, L is a lining steel plate length, and B is the lining steel plate width, and T is a lining steel plate thickness.
The specific embodiment
Embodiments of the invention: the present invention comprises following steps: the first, lining steel plate is divided into some of the steel plates of same size, and the dowel of burn-oning, dowel are pressed blossom type and are arranged; The second, when bulkhead needs lining steel plate, lining steel plate is propped up the inner formword into bulkhead; The 3rd, cast bulkhead concrete; The 4th, treat that concrete strength reaches designing requirement after, the some block plates that separate are welded as a whole and weld grinding is smooth.
Claims (2)
1. the processing method of an inner formwork of concrete silo wall, it is characterized in that: this method comprises following steps: the first, lining steel plate is divided into some of the steel plates of same size and the dowel of burn-oning; The second, lining steel plate is propped up the inner formword into bulkhead; The 3rd, cast bulkhead concrete; The 4th, treat that concrete strength reaches designing requirement after, the some block plates that separate are welded as a whole and weld grinding is smooth.
2. the processing method of inner formwork of concrete silo wall according to claim 1 is characterized in that: dowel is pressed blossom type and is arranged.
Priority Applications (1)
Application Number | Priority Date | Filing Date | Title |
---|---|---|---|
CN2007102027225A CN101446125B (en) | 2007-11-27 | 2007-11-27 | Method for treating inner formwork of concrete silo wall |
Applications Claiming Priority (1)
Application Number | Priority Date | Filing Date | Title |
---|---|---|---|
CN2007102027225A CN101446125B (en) | 2007-11-27 | 2007-11-27 | Method for treating inner formwork of concrete silo wall |
Publications (2)
Publication Number | Publication Date |
---|---|
CN101446125A CN101446125A (en) | 2009-06-03 |
CN101446125B true CN101446125B (en) | 2012-05-23 |
Family
ID=40741985
Family Applications (1)
Application Number | Title | Priority Date | Filing Date |
---|---|---|---|
CN2007102027225A Expired - Fee Related CN101446125B (en) | 2007-11-27 | 2007-11-27 | Method for treating inner formwork of concrete silo wall |
Country Status (1)
Country | Link |
---|---|
CN (1) | CN101446125B (en) |
Families Citing this family (2)
Publication number | Priority date | Publication date | Assignee | Title |
---|---|---|---|---|
CN103669894B (en) * | 2012-09-14 | 2016-08-31 | 贵阳铝镁设计研究院有限公司 | The reinforcement means of a kind of reinforced concrete silo inwall and structure |
CN103964084B (en) * | 2014-05-06 | 2016-10-05 | 华新环境工程有限公司 | The moving system of a kind of mummification rubbish and technique |
Citations (4)
Publication number | Priority date | Publication date | Assignee | Title |
---|---|---|---|---|
CN88211104U (en) * | 1988-02-24 | 1988-09-21 | 戴受天 | Mould board needless to dismount |
US5809726A (en) * | 1996-08-21 | 1998-09-22 | Spude; Gerald T. | Foundation construction system |
CN2493682Y (en) * | 2001-07-19 | 2002-05-29 | 曲俊义 | Disposable form for concrete engineering |
CN2705528Y (en) * | 2004-04-23 | 2005-06-22 | 朱秦江 | Polystyrene heat insulation wall form work |
-
2007
- 2007-11-27 CN CN2007102027225A patent/CN101446125B/en not_active Expired - Fee Related
Patent Citations (4)
Publication number | Priority date | Publication date | Assignee | Title |
---|---|---|---|---|
CN88211104U (en) * | 1988-02-24 | 1988-09-21 | 戴受天 | Mould board needless to dismount |
US5809726A (en) * | 1996-08-21 | 1998-09-22 | Spude; Gerald T. | Foundation construction system |
CN2493682Y (en) * | 2001-07-19 | 2002-05-29 | 曲俊义 | Disposable form for concrete engineering |
CN2705528Y (en) * | 2004-04-23 | 2005-06-22 | 朱秦江 | Polystyrene heat insulation wall form work |
Also Published As
Publication number | Publication date |
---|---|
CN101446125A (en) | 2009-06-03 |
Similar Documents
Publication | Publication Date | Title |
---|---|---|
CN202519709U (en) | Precast block post-cast strip structure of foundation slab | |
CN101446125B (en) | Method for treating inner formwork of concrete silo wall | |
CN203452378U (en) | Post-cast strip locating structure | |
CN107503460A (en) | A kind of feed pipe reserves groove construction method | |
CN102587588A (en) | Multifunctional concrete cushion block | |
CN106150084B (en) | A kind of mold method and its formwork erecting structure for wearing muscle template | |
CN101666159B (en) | Single silo slip form construction device | |
CN208777720U (en) | Wall hangs the detachable straight thread reinforced bar pedestal of mould diagonal brace | |
CN202509764U (en) | Template bracing structure for constructional column | |
CN202882438U (en) | Cast-in-situ concrete inclined wall and inclined column tumbling barrel | |
CN202370010U (en) | Post-cast strip structure | |
CN103075003A (en) | Building construction method of internal corners and external corners | |
CN101858118A (en) | Reinforced concrete hollow floor slab and construction method | |
CN206529942U (en) | A kind of overlaid plate type sandwich heat preservation shear wall with split bolt | |
CN203361643U (en) | Removing-free and dabbing-free template provided with preformed holes | |
CN201588318U (en) | Late poured band structure | |
CN101864835B (en) | Early-dismantling support of aluminum alloy top plate | |
KR20070107212A (en) | Construction method of water tank and structure of water tank and sepatie for construction | |
CN210712849U (en) | Portable trench wall concrete placement device | |
CN106760214B (en) | A kind of octagon circular section solid steel tube concrete component and preparation method thereof | |
CN106759415A (en) | A kind of concrete structure catch pit template anti-floating control technology | |
CN207892243U (en) | A kind of template assembly system | |
CN207620379U (en) | A kind of side mould fixing device | |
CN102251673B (en) | Construction method for reinforced concrete hollow floor | |
CN202031328U (en) | Fixing device of outer formwork for casting outer concrete wall on floor slab of building |
Legal Events
Date | Code | Title | Description |
---|---|---|---|
C06 | Publication | ||
PB01 | Publication | ||
C10 | Entry into substantive examination | ||
SE01 | Entry into force of request for substantive examination | ||
C14 | Grant of patent or utility model | ||
GR01 | Patent grant | ||
CF01 | Termination of patent right due to non-payment of annual fee |
Granted publication date: 20120523 Termination date: 20151127 |
|