CN101335541B - Method implementing data synchronization between main and spare circuit board - Google Patents
Method implementing data synchronization between main and spare circuit board Download PDFInfo
- Publication number
- CN101335541B CN101335541B CN2008100678673A CN200810067867A CN101335541B CN 101335541 B CN101335541 B CN 101335541B CN 2008100678673 A CN2008100678673 A CN 2008100678673A CN 200810067867 A CN200810067867 A CN 200810067867A CN 101335541 B CN101335541 B CN 101335541B
- Authority
- CN
- China
- Prior art keywords
- control board
- main control
- data
- execution
- synchronization
- Prior art date
- Legal status (The legal status is an assumption and is not a legal conclusion. Google has not performed a legal analysis and makes no representation as to the accuracy of the status listed.)
- Expired - Fee Related
Links
Images
Abstract
The invention relates to a method for realizing data synchronization between a main control board and a standby main control board, comprising a cyclic backup and a manual synchronization. For the cyclic backup, the way of timing synchronization is adopted in the main control board, when a data synchronizing cycle is reached, the main control board can synchronize all data that need to be backed up presently to the standby main control board; for the manual synchronization, for compensating the inconformity of data caused by various factors, a manual instruction can be given to ensure that the main control board can synchronize all data that need to be backed up presently to the standby main control board, particularly, when the main control board and the standby main control board are switched with each other manually, the method can ensure that the system can still run normally, stably and reliably after the switching between the main control board and the standby main control board. Compared with the prior art, as the method of the invention compensates the reliability of the data synchronization technology with various forms of the original process, reliable warm backup of data between the main control board and the standby main control board can be realized, thus enhancing the reliability and stability of the whole communication system.
Description
Technical field
The present invention relates to a kind of a kind of method of data synchronization that the 1+1 hot backup function adopts of in communication system, realizing; It can realize making under the situation that data at the work mainboard change; Make the backup plate to be consistent, thereby improve the reliability and stability of system with the main board data in real time.
Background technology
In the optical communication system, especially core net because its network site of living in is extremely important, does not allow to occur Single Point of Faliure in modern times, and equipment generally all is equipped with two master control borads, is called main control board (Master) and slave control board (Slave) respectively.Wherein, main control board carries out service communication, the normal function of each module in the completion system as the core of control plane with outside and business board; Slave control board then only as the backup of main control board, is not communicated by letter with business board with outside.When main control board broke down, system carried out active and standby switching automatically, took over the work of main control board by slave control board, guaranteed professional normal operation.And the key of guaranteeing the reliable and stable operation of said system be reach active and standby between the Hot Spare of data.The traditional data method for synchronous mainly comprises the Hot Spare that starts synchronously and reach data in real time synchronously,
Although these two kinds of methods can realize most of data sync; But these synchronous prerequisites all are to be based upon synchronous mouth and not have under the prerequisite of fault; If synchronous mouth has problem in the start-up course, synchronous mouthful fault perhaps appears, though carried out synchronously in logical running; But do not reach synchronous effect, cause synchronization failure.
Summary of the invention
It is not enough that the problem that the present invention need solve is to overcome traditional data method of synchronization synchrodata reliability, proposes the mode of two kinds of data sync, can increase the reliable synchronization of data.
First kind is periodic backups, and mainboard adopts regularly synchronous mode, and when arriving data sync during the cycle, main control board can all be synchronized to slave control board with the current backed up data that needs; It may further comprise the steps:
Step 1, plank begin after powering on and bringing into operation, the counter of at first zero clearing periodic synchronous;
Whether step 2, whenever to detect oneself at a distance from one second be mainboard, if, execution in step 3, otherwise zero clearing coincidence counter, continuation execution in step 2.
Whether step 3, detect on the thronely to plate (slave board), if then the value of coincidence counter adds one, execution in step 4, otherwise zero clearing coincidence counter continue execution in step 2.
Whether the value of step 4, the current coincidence counter of detection equals synchronizing cycle, if, just carry out data sync, send portion to all synchrodatas to slave board, execution in step 2, otherwise zero clearing coincidence counter continue execution in step 2.
Second kind is manual synchronization; In order to remedy the inconsistent phenomenon of data that causes owing to various factors; Can make main control board that the current backed up data that needs all is synchronized to slave control board through the mode of manual transmitting order to lower levels, especially manually masterslave switchover the time; Can guarantee like this after the active and standby switching that system still can the normal and stable reliability service.It may further comprise the steps:
Step 1, whenever at a distance from 10 milliseconds of detections whether the manual data synch command is arranged once, if having, then execution in step 2, otherwise continue execution in step 1.
Whether step 2, to detect oneself be mainboard, if, just carry out data sync, send all synchrodatas a to slave board.Otherwise execution in step 1.
Adopt the method for the invention; Compared with prior art; Because this method has remedied the reliability of data synchronization technology multi-form in the original process, reached active and standby between the effect of reliable Hot Spare of data, improved the reliability and stability of whole communication system.
Description of drawings
Fig. 1 is the synchronous flow chart manual synchronization flow chart of periodic synchronous;
Fig. 2 is the manual synchronization flow chart;
Fig. 3 embodiment reduced graph.
Embodiment
To combine accompanying drawing and embodiment that technical scheme of the present invention is explained in more detail below.
, may further comprise the steps with the method that the periodic synchronous explanation the present invention relates at this:
Step 1, plank begin after powering on and bringing into operation, the counter of at first zero clearing periodic synchronous;
Whether step 2, whenever to detect oneself at a distance from one second be mainboard, if, execution in step 3, otherwise zero clearing coincidence counter, continuation execution in step 2.
Whether step 3, detect on the thronely to plate (slave board), if then the value of coincidence counter adds one, execution in step 4, otherwise zero clearing coincidence counter continue execution in step 2.
Whether the value of step 4, the current coincidence counter of detection equals synchronizing cycle, if, just carry out data sync, send portion to all synchrodatas to slave board, execution in step 2, otherwise zero clearing coincidence counter continue execution in step 2.
, may further comprise the steps with the method that the manual synchronization explanation the present invention relates at this:
Step 1, whenever at a distance from 10 milliseconds of detections whether the manual data synch command is arranged once, if having, then execution in step 2, otherwise continue execution in step 1.
Whether step 2, to detect oneself be mainboard, if, just carry out data sync, send all synchrodatas a to slave board.Otherwise execution in step 1.
Certainly; The present invention also can have other various embodiments; Under the situation that does not deviate from spirit of the present invention and essence thereof; Those of ordinary skill in the art work as can make various corresponding changes and distortion according to the present invention, but these corresponding changes and distortion all should belong to the protection range of the appended claim of the present invention.
Claims (2)
1. the method for data synchronization of mainboard and slave board in the communication system is characterized in that, comprises the steps:
(1), behind the Board Power up, zero clearing periodic synchronous counter;
(2) whether, whenever detecting oneself at a distance from one second is mainboard, if execution in step (3), otherwise zero clearing coincidence counter continue execution in step (2);
(3) whether, it is on the throne to detect slave board, if then the value of coincidence counter adds one, execution in step (4), otherwise the said coincidence counter of zero clearing continue execution in step (2);
(4), whether the value that detects current coincidence counter equals synchronizing cycle, if, carry out data sync, send all synchrodatas to slave board, execution in step (2), otherwise zero clearing coincidence counter continue execution in step (2).
2. the method for claim 1 is characterized in that, said method further comprises:
(5), whenever whether the manual data synch command is once arranged at a distance from 10 milliseconds of detections, if having, execution in step (6) then, otherwise continue execution in step (5);
(6) whether, detecting is mainboard, if, then carry out data sync, send all synchrodatas to slave board, otherwise execution in step (5).
Priority Applications (1)
Application Number | Priority Date | Filing Date | Title |
---|---|---|---|
CN2008100678673A CN101335541B (en) | 2008-06-12 | 2008-06-12 | Method implementing data synchronization between main and spare circuit board |
Applications Claiming Priority (1)
Application Number | Priority Date | Filing Date | Title |
---|---|---|---|
CN2008100678673A CN101335541B (en) | 2008-06-12 | 2008-06-12 | Method implementing data synchronization between main and spare circuit board |
Publications (2)
Publication Number | Publication Date |
---|---|
CN101335541A CN101335541A (en) | 2008-12-31 |
CN101335541B true CN101335541B (en) | 2012-05-23 |
Family
ID=40197891
Family Applications (1)
Application Number | Title | Priority Date | Filing Date |
---|---|---|---|
CN2008100678673A Expired - Fee Related CN101335541B (en) | 2008-06-12 | 2008-06-12 | Method implementing data synchronization between main and spare circuit board |
Country Status (1)
Country | Link |
---|---|
CN (1) | CN101335541B (en) |
Families Citing this family (3)
Publication number | Priority date | Publication date | Assignee | Title |
---|---|---|---|---|
CN101931550B (en) * | 2009-06-23 | 2014-01-01 | 中兴通讯股份有限公司 | Method and device for synchronizing main and standby main control boards |
CN102117209B (en) * | 2010-12-20 | 2015-04-22 | 深圳市科陆电子科技股份有限公司 | Method for processing intermediate data at a regular time in WEB system |
CN102664675A (en) * | 2012-04-10 | 2012-09-12 | 郭磊 | Hot standby processing scheme of optical communication signals |
Citations (2)
Publication number | Priority date | Publication date | Assignee | Title |
---|---|---|---|---|
CN1741404A (en) * | 2004-08-27 | 2006-03-01 | 华为技术有限公司 | Method for negat main spare board in communication equipment |
CN101155015A (en) * | 2006-09-28 | 2008-04-02 | 中兴通讯股份有限公司 | Synchronization method for data and condition between host computer and standby computer |
-
2008
- 2008-06-12 CN CN2008100678673A patent/CN101335541B/en not_active Expired - Fee Related
Patent Citations (2)
Publication number | Priority date | Publication date | Assignee | Title |
---|---|---|---|---|
CN1741404A (en) * | 2004-08-27 | 2006-03-01 | 华为技术有限公司 | Method for negat main spare board in communication equipment |
CN101155015A (en) * | 2006-09-28 | 2008-04-02 | 中兴通讯股份有限公司 | Synchronization method for data and condition between host computer and standby computer |
Also Published As
Publication number | Publication date |
---|---|
CN101335541A (en) | 2008-12-31 |
Similar Documents
Publication | Publication Date | Title |
---|---|---|
CN101316184B (en) | Disaster tolerance switching method, system and device | |
CN103532753B (en) | A kind of double hot standby method of synchronization of skipping based on internal memory | |
CN102045332B (en) | Method for processing control message in intelligent resilient framework and line card boards | |
CN107634855A (en) | A kind of double hot standby method of embedded system | |
WO2017024688A1 (en) | Control method and system capable of system upgrade without interrupting services | |
CN103488721A (en) | Database bisynchronous method and system for master and slave boards | |
CN105790825B (en) | Method and device for hot backup of controller in distributed protection | |
CN102388570B (en) | Single board running method and system under active-standby mode | |
CN103139033B (en) | Single main communications control bus main equipment redundancy switching method | |
CN101335541B (en) | Method implementing data synchronization between main and spare circuit board | |
CN102195796A (en) | Method and equipment for updating software version of distributed dual master control equipment | |
CN101267392A (en) | A realizing method for notifying downstream device in case of switch of uplink link status | |
CN101931550A (en) | Method and device for synchronizing main and standby main control boards | |
CN100461646C (en) | Method for negat main spare board in communication equipment | |
CN1128558C (en) | Base station control maintenance module backup system | |
CN110471491A (en) | A kind of method of management system time synchronization in blade server | |
CN105591801B (en) | A kind of virtual network function VNF fault handling method and VNF management equipment | |
EP2887592A1 (en) | Enum-dns disaster recovery method and system in ims network | |
CN103944697A (en) | Double-link double-server voice dispatching system and redundant backup method | |
CN103812680A (en) | System and method for achieving single plate switching | |
CN104780067A (en) | Method and device for rebooting PE (port extender) | |
CN101094049B (en) | Smoothing restarting method and neighbor devices | |
CN100395962C (en) | Method and system for equipment switching in communication system | |
CN101447728A (en) | Synchronous pulse-sending method and system thereof for UPS parallel machine | |
CN101582802B (en) | Operation maintenance system and method of network access device |
Legal Events
Date | Code | Title | Description |
---|---|---|---|
C06 | Publication | ||
PB01 | Publication | ||
C10 | Entry into substantive examination | ||
SE01 | Entry into force of request for substantive examination | ||
C14 | Grant of patent or utility model | ||
GR01 | Patent grant | ||
CF01 | Termination of patent right due to non-payment of annual fee | ||
CF01 | Termination of patent right due to non-payment of annual fee |
Granted publication date: 20120523 Termination date: 20180612 |