CN101291067B - 图形化的检同期方法 - Google Patents

图形化的检同期方法 Download PDF

Info

Publication number
CN101291067B
CN101291067B CN 200710039523 CN200710039523A CN101291067B CN 101291067 B CN101291067 B CN 101291067B CN 200710039523 CN200710039523 CN 200710039523 CN 200710039523 A CN200710039523 A CN 200710039523A CN 101291067 B CN101291067 B CN 101291067B
Authority
CN
China
Prior art keywords
data
phase difference
meet
frequency
voltage
Prior art date
Legal status (The legal status is an assumption and is not a legal conclusion. Google has not performed a legal analysis and makes no representation as to the accuracy of the status listed.)
Expired - Fee Related
Application number
CN 200710039523
Other languages
English (en)
Other versions
CN101291067A (zh
Inventor
杨浩赟
Current Assignee (The listed assignees may be inaccurate. Google has not performed a legal analysis and makes no representation or warranty as to the accuracy of the list.)
Shanghai Sunrise Power Technology Co., Ltd.
Original Assignee
SHANGHAI SUNRISE POWER AUTOMATION CO Ltd
Priority date (The priority date is an assumption and is not a legal conclusion. Google has not performed a legal analysis and makes no representation as to the accuracy of the date listed.)
Filing date
Publication date
Application filed by SHANGHAI SUNRISE POWER AUTOMATION CO Ltd filed Critical SHANGHAI SUNRISE POWER AUTOMATION CO Ltd
Priority to CN 200710039523 priority Critical patent/CN101291067B/zh
Publication of CN101291067A publication Critical patent/CN101291067A/zh
Application granted granted Critical
Publication of CN101291067B publication Critical patent/CN101291067B/zh
Expired - Fee Related legal-status Critical Current
Anticipated expiration legal-status Critical

Links

Images

Landscapes

  • Supply And Distribution Of Alternating Current (AREA)

Abstract

本发明公开一种图形化的检同期方法,涉及电力系统技术领域;所要解决的是使检同期非常直观,易于操作,安全性高的技术问题;该检同期方法的流程如下:1)来自二个PT电压接入检同期装置;2)通过AD采样部分;3)计算出二者相位、电压、频率,通过比相获得二者相位差;4)然后将这些数据进行(特殊)编码;5)结合通讯控制;6)发到上位机上显示或者在装置的液晶上显示。本发明具有非常直观,易于操作,安全性高,发命令时对操作结果可预知,发生异常能及时撤消命令的特点。

Description

图形化的检同期方法
技术领域
本发明涉及电力系统技术,特别是涉及一种用于电力系统合闸并网的检同期方法的技术。
背景技术
在电力系统里,由于不同发电厂出来的电源之间有一定的频率差、电压差、相位差。在并网之前必须调整发电机,使得二者频率差、电压差、相位差在规定的范围里,并网时同期装置需要检测二者频率差、电压差、相位差是否在规定的范围里,然后选择相位差最小的时刻合闸并网,这就是检同期。如果不检同期,强行并网将导致电网震荡,引起一系列连锁反应,可能导致灾难性的后果。最早的检同期装置是使用同期继电器,它限制只能在相位差小于30度时合闸并网,这种方式精度差,不能限制频率差,对电网的冲击教大。随着电力自动化的发展,现在检同期装置普遍使用智能装置,采用微处理器计算二者相位差、频率差及电压差,能够较精确的检同期合闸。但是,目前无论是国内还是国外,检同期装置都是个黑匣子操作,当用户想检同期合闸时,他不清楚需要多长时间能合上,也不能预先知道合闸时的相位差,所以也就无法预测合闸对电网的冲击程度。另外,由于在检同期的过程中对关键数据不清楚,如果有异常发生也就无法及时知道,自然也就无法及时撤消命令,这样可能导致灾难性的后果。本发明采用了图形化的检同期方法,很好的解决了这些问题。
发明内容
针对上述现有技术中存在的缺陷,本发明所要解决的技术问题是提供一种非常直观,易于操作,安全性高,发命令时对操作结果可预知,发生异常能及时撤消命令的图形化的检同期方法。
为了解决上述技术问题,本发明所提供的一种图形化的检同期方法,其特征在于,检同期方法的流程如下:
1)、来自二个PT电压接入检同期装置;
2)、通过AD采样部分;
3)、计算出二者相位、电压、频率,通过比相获得二者相位差;
4)、然后将这些数据进行(特殊)编码;
5)、结合通讯控制;
6)、发到上位机上显示或者在装置的液晶上显示。
进一步的,所述步骤4)、数据进行(特殊)编码为将PT1电压、PT2电压、PT1频率、PT2频率、相位差、采样点编号等关键数据进行(特殊)编码,使数据编码简洁、高效、且容易实现。
进一步的,所述步骤4)、数据(采样点)编码与步骤5)、的通讯编码能合二为一,以提高效率。
进一步的,所述步骤5)、通讯控制的流程如下:
1)是否有检同期命令?有则转至2);否则转至7);
2)是否有封锁条件?有则转至1);否则转至3);
3)电压、频率是否符合要求?符合则转至4);否则转至1);
4)最小相位差是否符合要求?符合则转至5);否则转至1);
5)加导前时间是否是最小相位?是则转至6);否则转至5);
6)合闸,并转至1);
7)是否有数据丢失?有则转至8);否则转至9);
8)补发数据,并转至1);
9)发最新数据,并转至1)。
本发明提供的图形化的检同期方法与传统黑匣子模式检同期装置相比,其有益效果:
A),检同期过程图形化,非常直观,易于操作;
B),发命令时对操作结果可预知,发生异常能及时撤消命令,所以安全性高。
附图说明
图1是本发明实施例图形化的检同期方法的流程图;
图2是本发明实施例图形化的检同期方法中通讯控制部分的流程图;
图3是本发明实施例图形化的检同期方法的图形界面显示图。
具体实施方式
以下结合附图说明对本发明的实施例作进一步详细描述,但本实施例并不用于限制本发明,凡是采用本发明的相似方法及其相似变化,均应列入本发明的保护范围。
如图1所示,本发明实施例所提供的一种图形化的检同期方法,其流程如下:
1)自2个PT电压接入检同期装置;
2)通过AD采样部分;
3)计算出二者相位、电压、频率,通过比相获得二者相位差;
4)然后将这些数据进行(特殊)编码;
5)结合通讯控制;
6)发到上位机上显示或者在装置的液晶上显示。
本发明的关键点是数据编码和通讯控制。数据编码要简洁高效且容易实现,所以本发明只考虑影响检同期的关键数据:PT1电压、PT2电压、PT1频率、PT2频率、相位差、采样点编号,为了在装置的生命周期里采样点编号不翻转,采用4字节编号,从1开始;为了防止因误码或其它因素影响通讯,须增加通讯编码,也采用4字节编码。为了提高效率,通讯编码与采样点编码可以合二为一,装置每次收到上位机的应答报文都要比较编码以判断是否有信息丢失。具体格式如下:
通讯帧格式:帧头(EB90)、帧类型(2字节)、通讯编码(4字节)、对象个数(2字节)、对象1-N、CRC校验;
对象格式:PT1电压(2字节)、PT2电压(2字节)、PT1频率(2字节)、PT2频率(2字节)、相位差;
如图2所示,本发明的图形化的检同期方法中,通讯控制的流程如下:
1)是否有检同期命令?有则转至2);否则转至7);
2)是否有封锁条件?有则转至1);否则转至3);
3)电压、频率是否符合要求?符合则转至4);否则转至1);
4)最小相位差是否符合要求?符合则转至5);否则转至1);
5)加导前时间是否是最小相位?是则转至6);否则转至5);
6)合闸,并转至1);
7)是否有数据丢失?有则转至8);否则转至9);
8)补发数据,并转至1);
9)发最新数据,并转至1)。
如图3所示,本发明的图形化的检同期方法中,上位机界面如下所示:水平方向是时间坐标,实时显示2个PT的电压、频率及相位差,通过此图能方便直观地看出相位差的变化周期,是否能检同期一目了然,任意时刻发命令都很清楚将要多长时间能合闸。在检同期的过程中,如果发现频率、电压、相位发生异常变化,可以立即终止检同期。比如,假如你在5秒的时候发命令,你会清楚的知道再过3秒多的时间就能合闸。图3显示发合闸命令时的系统状态是:相位差5.6度、频率差0.12赫兹、电压差0.8V。本例子的导前时间为100毫秒,也就是说系统真正合闸并网是在此时刻之后100毫秒,从图3中可以看出,并网时相位差大约为0.5度。

Claims (1)

1.一种图形化的检同期方法,其特征在于,检同期方法的步骤如下:
1)、来自二个PT电压接入检同期装置;
2)、通过AD采样部分;
3)、计算出二者相位、电压、频率,通过比相获得二者相位差;
4)、然后将这些数据进行编码;
5)、结合通讯控制;其中通讯控制的流程如下:
a)是否有检同期命令?有则转至b);否则转至g);
b)是否有封锁条件?有则转至a);否则转至c);
c)电压、频率是否符合要求?符合则转至d);否则转至a);
d)最小相位差是否符合要求?符合则转至e);否则转至a);
e)加导前时间是否是最小相位?是则转至f);否则转至e);
f)合闸,并转至a);
g)是否有数据丢失?有则转至h);否则转至i);
h)补发数据,并转至a);
i)发最新数据,并转至a);
6)、发到上位机上显示或者在装置的液晶上显示。
CN 200710039523 2007-04-17 2007-04-17 图形化的检同期方法 Expired - Fee Related CN101291067B (zh)

Priority Applications (1)

Application Number Priority Date Filing Date Title
CN 200710039523 CN101291067B (zh) 2007-04-17 2007-04-17 图形化的检同期方法

Applications Claiming Priority (1)

Application Number Priority Date Filing Date Title
CN 200710039523 CN101291067B (zh) 2007-04-17 2007-04-17 图形化的检同期方法

Publications (2)

Publication Number Publication Date
CN101291067A CN101291067A (zh) 2008-10-22
CN101291067B true CN101291067B (zh) 2011-08-31

Family

ID=40035203

Family Applications (1)

Application Number Title Priority Date Filing Date
CN 200710039523 Expired - Fee Related CN101291067B (zh) 2007-04-17 2007-04-17 图形化的检同期方法

Country Status (1)

Country Link
CN (1) CN101291067B (zh)

Citations (4)

* Cited by examiner, † Cited by third party
Publication number Priority date Publication date Assignee Title
CN85104919A (zh) * 1985-06-25 1987-01-07 武汉水利电力学院 同步发电机自动准同期新方法及其实施装置
CN1053152A (zh) * 1990-01-03 1991-07-17 北京市西城新开通用试验厂 一种机电一体化同期并网装置
CN2341312Y (zh) * 1998-04-08 1999-09-29 北京天时利科技发展有限公司 准同期控制器
CN1564418A (zh) * 2004-04-08 2005-01-12 陕西鼓风机(集团)有限公司 高炉煤气余压透平发电装置自动准同期并网方法

Patent Citations (4)

* Cited by examiner, † Cited by third party
Publication number Priority date Publication date Assignee Title
CN85104919A (zh) * 1985-06-25 1987-01-07 武汉水利电力学院 同步发电机自动准同期新方法及其实施装置
CN1053152A (zh) * 1990-01-03 1991-07-17 北京市西城新开通用试验厂 一种机电一体化同期并网装置
CN2341312Y (zh) * 1998-04-08 1999-09-29 北京天时利科技发展有限公司 准同期控制器
CN1564418A (zh) * 2004-04-08 2005-01-12 陕西鼓风机(集团)有限公司 高炉煤气余压透平发电装置自动准同期并网方法

Also Published As

Publication number Publication date
CN101291067A (zh) 2008-10-22

Similar Documents

Publication Publication Date Title
US20200220351A1 (en) Systems and Methods for Model-Driven Demand Response
US8180622B2 (en) Systems and methods for a real-time synchronized electrical power system simulator for “what-if” analysis and prediction over electrical power networks
US8577661B2 (en) Systems and methods for alarm filtering and management within a real-time data acquisition and monitoring environment
US8036872B2 (en) Systems and methods for performing automatic real-time harmonics analyses for use in real-time power analytics of an electrical power distribution system
EP2038782B1 (en) Systems and methods for real-time dynamic simulation of uninterruptible power supply solutions and their control logic systems
US7844440B2 (en) Systems and methods for real-time dynamic simulation of uninterruptible power supply solutions and their control logic systems
US20170228653A1 (en) Systems And Methods For Model-Based Solar Power Management
CA2657330C (en) Systems and methods for alarm filtering and management within a real-time data acquisition and monitoring environment
US20160246904A1 (en) Systems And Methods For Integrated, Model, And Role-Based Management Of A Microgrid Based On Real-time Power Management
US20150161298A1 (en) Systems and methods for real-time dc microgrid power analytics for mission-critical power systems
US20120191439A1 (en) Systems and methods for automated model-based real-time simulation of a microgrid for market-based electric power system optimization
AU2007275451B2 (en) Systems and methods for real-time advanced visualization for predicting the health, reliability and performance of an electrical power system
AU2007238094B2 (en) Systems and methods for performing automatic real-time harmonics analyses for use in real-time power analytics of an electrical power distribution system
AU2007308995B2 (en) Systems and methods for a real-time synchronized electrical power system simulator for "what-if" analysis and prediction over electrical power networks
CN101291067B (zh) 图形化的检同期方法
EP2147411A1 (en) Systems and methods for creation of a schematic user interface for monitoring and predicting the real- time health, reliability and performace of an electrical power system
CN206270709U (zh) 基于Arduino的楼宇机电设备远程短信控制系统
CN201234231Y (zh) 三相鼠笼型感应电动机用智能型自耦减压起动控制系统
CN115509185A (zh) 一种控制系统开放式改造方法

Legal Events

Date Code Title Description
C06 Publication
PB01 Publication
C10 Entry into substantive examination
SE01 Entry into force of request for substantive examination
C14 Grant of patent or utility model
GR01 Patent grant
ASS Succession or assignment of patent right

Owner name: SHANGHAI SUNRISE PROTECTIVE RELAY ELECTRIC CO.,LTD

Free format text: FORMER OWNER: SHANGHAI SUNRISE POWER AUTOMATION CO., LTD.

Effective date: 20130228

C41 Transfer of patent application or patent right or utility model
TR01 Transfer of patent right

Effective date of registration: 20130228

Address after: 200233 Guiping Road, Xuhui District, No. 470, building 12, building 5, building

Patentee after: Shanghai Sunrise Power Technology Co., Ltd.

Address before: 200233, room 6, building 15, building 481, Guiping Road, Xuhui District, Shanghai,

Patentee before: Shanghai Sunrise Power Automation Co., Ltd.