CN101275692B - Integral loop metal flexible pipe and assembling method thereof - Google Patents

Integral loop metal flexible pipe and assembling method thereof Download PDF

Info

Publication number
CN101275692B
CN101275692B CN2008100610172A CN200810061017A CN101275692B CN 101275692 B CN101275692 B CN 101275692B CN 2008100610172 A CN2008100610172 A CN 2008100610172A CN 200810061017 A CN200810061017 A CN 200810061017A CN 101275692 B CN101275692 B CN 101275692B
Authority
CN
China
Prior art keywords
metal
straight tube
joint
net
flexible pipe
Prior art date
Legal status (The legal status is an assumption and is not a legal conclusion. Google has not performed a legal analysis and makes no representation as to the accuracy of the status listed.)
Expired - Fee Related
Application number
CN2008100610172A
Other languages
Chinese (zh)
Other versions
CN101275692A (en
Inventor
黄伟
Current Assignee (The listed assignees may be inaccurate. Google has not performed a legal analysis and makes no representation or warranty as to the accuracy of the list.)
Individual
Original Assignee
Individual
Priority date (The priority date is an assumption and is not a legal conclusion. Google has not performed a legal analysis and makes no representation as to the accuracy of the date listed.)
Filing date
Publication date
Application filed by Individual filed Critical Individual
Priority to CN2008100610172A priority Critical patent/CN101275692B/en
Publication of CN101275692A publication Critical patent/CN101275692A/en
Application granted granted Critical
Publication of CN101275692B publication Critical patent/CN101275692B/en
Expired - Fee Related legal-status Critical Current
Anticipated expiration legal-status Critical

Links

Images

Landscapes

  • Joints Allowing Movement (AREA)

Abstract

The invention is a one-piece type loop metal hose and the assembling method which relate to a metal hose, wherein the hose includes a corrugated pipe, a straight tube, a wire netting case, the straight tube connected with the corrugated pipe is one-piece, the design point is that the straight tube, the wire netting case, the metal grid are one-piece to pass through the loop joint, and exposed on the side of the loop joint in the single flanging. The assembling method is that two sides of the single flanging or the two-side flanging are connected with the corresponding matched loop joint. The invention solves the technical problems of the hose joint connection, and the assembling method is feasible, which has strong applicability, long service life, fast assemble. The invention has the characteristic of high efficiency, low cost, suitable for mass production, which is the ideal matching piece connected between the installed device and the part.

Description

Integral loop metal flexible pipe and assembling method
Technical field
The present invention relates to a kind of metallic hose.
Background technique
At present, metallic hose is one of major part that connects between equipment installation, the parts, and it has the advantages that flexibility is good, high temperature resistant, corrosion-resistant, pressure-bearing is higher.Therefore, be able to extensive use in Aero-Space, machine-building, petrochemical industry, electric power, metallurgy, building industry etc.Metallic hose generally is made up of parts such as corrugated stainless steel tubing, net, retaining ring, adapter, weld-ring, joints, and joint comprises inipple and flanged joint, has fixed and loop type.The general employing of existing metallic hose production technology finished bellows, webmaster, the welding of retaining ring one, again with adapter or joint welding.Another kind of Placement is bellows two ends elder generation and takes over and weld, and again net is enclosed within the bellows two ends, with retaining ring net is pressed in to take over upward and welds, and takes over then and takes over and weld.
The mode of production of above-mentioned metallic hose all is could realize by the multiple tracks welding, because welding produces a large amount of heat, the difference of the wall thickness of each part and material in addition, cause welding part change in shape and thermal stress to be concentrated, cause the structure of metallic material to change, reduced the mechanical strength of product.Therefore, existing metallic hose is shorter working life, and the welding process complexity, manufacturing efficiency is low, cost is high, is not suitable for producing in enormous quantities.
The patent No. ZL 200520102168.X that discloses in the Chinese patent literature, July 5 2006 notice of authorization day, model utility title " metallic hose of band net ", though this part patent has proposed new scheme to known like product, but this design for scheme also exists some deficiency, and especially the connection of hose coupling owes desirable.
Summary of the invention
The present invention plans to overcome above-mentioned deficiency, and purpose is to provide integral loop metal flexible pipe and assembling method to related domain, makes it can solve the technical problem that hose coupling connects.The objective of the invention is to realize by the following technical solutions.
A kind of integral loop metal flexible pipe, this flexible pipe comprises bellows, straight tube, metal net, the straight tube that bellows connected is an one, its key points in design is that straight tube, metal net, metal retaining ring are the metal joints that penetrates of integral type, and is single flange and exposes a side that is arranged on described metal joint.
Described single flange is at the socket Duan Duanwei soldering point of the straight tube of metal joint one side, metal net, metal retaining ring.Black ellipse as shown in Figure 2 is a soldering point.The position of soldering point is the one connection for the ease of straight tube, metal net, this three of metal retaining ring, plays seal action.
Described single flange or be made as double-turnup promptly is the twice flange, is continuity at the Duan Duan of the straight tube of described metal joint one side, metal net, metal retaining ring, and the port of described metal net is arranged between single flange and the double-turnup.
The assembling method of described integral loop metal flexible pipe, described straight tube, metal net, metal retaining ring are the metal joints that penetrates of integral type, and be single flange and expose a side that is arranged on described metal joint, two sides of metal joint are connected by corresponding supporting metal joint respectively.
The assembling method of described integral loop metal flexible pipe, described single flange or be made as double-turnup promptly is the twice flange, is continuity at the Duan Duan of the straight tube of described metal joint one side, metal net, metal retaining ring, and double-turnup does not have soldering point.The port of described metal net is arranged between single flange and the double-turnup, and two side is connected by corresponding supporting metal joint respectively.
Above-mentioned described straight tube, metal net, metal retaining ring are the metal joints that penetrates of integral type, carry out single flange or double-turnup again.The wall thickness of described metal retaining ring directly has influence on the mechanical strength of single flange or double-turnup and the tensile strength of metal net.
The invention solves the technical problem that hose coupling connects.Change in shape has been eliminated in no butt welding and thermal stress is concentrated, and has improved the mechanical strength of product; Assembling method is feasible.Its applicability is stronger, and working life is longer, and assembling is quick.Have the manufacturing efficiency height, cost is low, is fit to the characteristics produced in enormous quantities, be that equipment is installed, connect comparatively desirable auxiliary equipment between the parts.
Description of drawings
Fig. 1 is a structural representation of the present invention, has confined A among the figure to the position.
Fig. 2 be the A of Fig. 1 to enlarged diagram, this figure also is the local enlarged diagram of single flange.
Fig. 3 also is a structural representation of the present invention, has confined B among the figure to the position.
Fig. 4 be the B of Fig. 3 to enlarged diagram, this figure is the local enlarged diagram of double-turnup.
Above figure number and title: 1, bellows, 2, straight tube, 3, the metal net, 4, the metal retaining ring, 5, metal joint, 6, single flange, 7, double-turnup.
Embodiment
The concrete enforcement of the present invention is described as follows.As shown in Figures 1 to 4, single flange 6 of integral loop metal flexible pipe roughly is identical with the structure of double-turnup 7, all is to be made of bellows 1, straight tube 2, metal net 3, metal retaining ring 4, metal joint 5.Metal net 3 is enclosed within the external diameter of bellows 1, straight tube 2, and is metal net 3 between straight tube 2 and metal retaining ring 4.Setting is single flange and is double-turnup respectively, penetrates metal joint, is separately positioned on a side of described metal joint.Described single flange and double-turnup all with in be expanded into shape equipment and be configured as corrugated, thereafter, axially press process is finished and is close to a continuous whole flange sealing surface.The both ends of the surface of integral loop metal flexible pipe are identical structures, only turnup structure are slightly had any different, and all are to match with corresponding metal joint 5, and this metal joint is meant flange or similar auxiliary equipment.

Claims (2)

1. integral loop metal flexible pipe, this flexible pipe comprises bellows, straight tube, metal net; Bellows (1) is an one with the straight tube that is connected (2), straight tube (2), metal net (3), metal retaining ring (4) be integral type penetrate metal joint (5), and be the twice flange and expose a side that is arranged on described metal joint; It is characterized in that:
Duan Duan at the straight tube (2) of described metal joint (5) one sides, metal net (3), metal retaining ring (4) is a continuity; The port of described metal net is arranged between single flange (6) and the double-turnup (7).
2. the assembling method of integral loop metal flexible pipe, this flexible pipe comprises bellows, straight tube, metal net; Bellows (1) is an one with the straight tube that is connected (2), straight tube (2), metal net (3), metal retaining ring (4) be integral type penetrate metal joint (5), and be the twice flange and expose a side that is arranged on described metal joint, it is characterized in that:
Duan Duan at the straight tube (2) of described metal joint (5) one sides, metal net (3), metal retaining ring (4) is a continuity; The port of described metal net is arranged between single flange (6) and the double-turnup (7), two sides of metal joint are connected by corresponding supporting metal joint respectively, metal net (3) is enclosed within the external diameter of bellows (1), straight tube (2), and is metal net (3) between straight tube (2) and metal retaining ring (4);
Described single flange and double-turnup all with in be expanded into shape equipment and be configured as corrugated, thereafter, axially press process is finished and is close to a continuous whole flange sealing surface.
CN2008100610172A 2008-04-30 2008-04-30 Integral loop metal flexible pipe and assembling method thereof Expired - Fee Related CN101275692B (en)

Priority Applications (1)

Application Number Priority Date Filing Date Title
CN2008100610172A CN101275692B (en) 2008-04-30 2008-04-30 Integral loop metal flexible pipe and assembling method thereof

Applications Claiming Priority (1)

Application Number Priority Date Filing Date Title
CN2008100610172A CN101275692B (en) 2008-04-30 2008-04-30 Integral loop metal flexible pipe and assembling method thereof

Publications (2)

Publication Number Publication Date
CN101275692A CN101275692A (en) 2008-10-01
CN101275692B true CN101275692B (en) 2010-06-02

Family

ID=39995394

Family Applications (1)

Application Number Title Priority Date Filing Date
CN2008100610172A Expired - Fee Related CN101275692B (en) 2008-04-30 2008-04-30 Integral loop metal flexible pipe and assembling method thereof

Country Status (1)

Country Link
CN (1) CN101275692B (en)

Families Citing this family (2)

* Cited by examiner, † Cited by third party
Publication number Priority date Publication date Assignee Title
CN102198463A (en) * 2011-03-21 2011-09-28 苏州工业园区云白华鼎烟囱制造有限公司 Double flanging machine
CN106311840B (en) * 2016-11-03 2018-05-01 燕山大学 A kind of motor-car shaft coupling corrugated tube port forming method

Citations (4)

* Cited by examiner, † Cited by third party
Publication number Priority date Publication date Assignee Title
US5865475A (en) * 1996-04-12 1999-02-02 Witzenmann Gmbh Metallschlauch-Fabrik Pforzheim Connection between a building component and a pipe-shaped line element
CN2793492Y (en) * 2005-05-12 2006-07-05 吴文庆 Flexible metal pipe with netted sleeve
CN1888507A (en) * 2006-07-21 2007-01-03 泰州市博特机械制造有限公司 Weldless joint metal hose and producing method thereof
CN201190847Y (en) * 2008-04-30 2009-02-04 黄伟 Integral loop metal hose

Patent Citations (4)

* Cited by examiner, † Cited by third party
Publication number Priority date Publication date Assignee Title
US5865475A (en) * 1996-04-12 1999-02-02 Witzenmann Gmbh Metallschlauch-Fabrik Pforzheim Connection between a building component and a pipe-shaped line element
CN2793492Y (en) * 2005-05-12 2006-07-05 吴文庆 Flexible metal pipe with netted sleeve
CN1888507A (en) * 2006-07-21 2007-01-03 泰州市博特机械制造有限公司 Weldless joint metal hose and producing method thereof
CN201190847Y (en) * 2008-04-30 2009-02-04 黄伟 Integral loop metal hose

Also Published As

Publication number Publication date
CN101275692A (en) 2008-10-01

Similar Documents

Publication Publication Date Title
CN201078525Y (en) Steel strip enhancement polythene helical bellows of spigot-and-socket electric melting connecting type
CN101706228A (en) Core of shell-and-tube heat exchanger and connection method of tube plate and tube
CN201407423Y (en) Double-metal composite bend pipe with both metallurgical bonding ends and mechanical bonding middle part
CN101275692B (en) Integral loop metal flexible pipe and assembling method thereof
CN201202902Y (en) Integral non-welding corrugated metal soft connecting part
CN201190847Y (en) Integral loop metal hose
CN102313107B (en) Wire rope enhanced thermoplastic composite pipe heating type buckling and pressing joint and connection method
CN210741166U (en) Heat exchanger and gas water heater with same
RU2298143C1 (en) Heat exchange panel and its assembling method
KR102098578B1 (en) Cladding for pipe curved line
CN100419322C (en) Weldless joint metal hose and producing method thereof
CN210689274U (en) Heat exchanger and gas water heater with same
CN200975566Y (en) Copper aluminum composite adapter connector used for air-conditioner
CN2937739Y (en) Non-welding joint metal hose
CN211449959U (en) Flange structure for aluminum alloy vacuum system
CN202349483U (en) Stamping type bimetallic composite bend pipe
CN209743836U (en) Novel composite pipeline combined connecting piece
CN203663822U (en) Acrylate esterification reactor with titaniumtim and stainless steel combined structure
CN101649934A (en) Extrusion type hard-sealing fast-connection pipeline
CN218544868U (en) Geothermal energy transducer and geothermal energy air conditioning system
CN205987432U (en) Heating pipe
CN207600277U (en) A kind of heat conduction spiral fin coil
CN201909577U (en) Weld joint and air-conditioning heat exchanger
CN216843636U (en) Widened anti-seepage corrugated plate structure
CN210689273U (en) Heat exchanger and gas water heater with same

Legal Events

Date Code Title Description
C06 Publication
PB01 Publication
C10 Entry into substantive examination
SE01 Entry into force of request for substantive examination
C14 Grant of patent or utility model
GR01 Patent grant
CF01 Termination of patent right due to non-payment of annual fee
CF01 Termination of patent right due to non-payment of annual fee

Granted publication date: 20100602

Termination date: 20180430