CN101264850A - Tower machine descending method used for normal descend of building interference tower machine upper component - Google Patents

Tower machine descending method used for normal descend of building interference tower machine upper component Download PDF

Info

Publication number
CN101264850A
CN101264850A CNA2008100311058A CN200810031105A CN101264850A CN 101264850 A CN101264850 A CN 101264850A CN A2008100311058 A CNA2008100311058 A CN A2008100311058A CN 200810031105 A CN200810031105 A CN 200810031105A CN 101264850 A CN101264850 A CN 101264850A
Authority
CN
China
Prior art keywords
tower
tower machine
interference
obstructed
jacks
Prior art date
Legal status (The legal status is an assumption and is not a legal conclusion. Google has not performed a legal analysis and makes no representation as to the accuracy of the status listed.)
Granted
Application number
CNA2008100311058A
Other languages
Chinese (zh)
Other versions
CN100562482C (en
Inventor
朱森林
Current Assignee (The listed assignees may be inaccurate. Google has not performed a legal analysis and makes no representation or warranty as to the accuracy of the list.)
HUNAN SIXTH ENGINEERING CORP
Original Assignee
HUNAN SIXTH ENGINEERING CORP
Priority date (The priority date is an assumption and is not a legal conclusion. Google has not performed a legal analysis and makes no representation as to the accuracy of the date listed.)
Filing date
Publication date
Application filed by HUNAN SIXTH ENGINEERING CORP filed Critical HUNAN SIXTH ENGINEERING CORP
Priority to CNB2008100311058A priority Critical patent/CN100562482C/en
Publication of CN101264850A publication Critical patent/CN101264850A/en
Application granted granted Critical
Publication of CN100562482C publication Critical patent/CN100562482C/en
Expired - Fee Related legal-status Critical Current
Anticipated expiration legal-status Critical

Links

Images

Abstract

The invention discloses a tower crane descending method which is used for ensuring the normal descending of the components of the upper part of the tower crane when interfered by buildings; the method is characterized in that: one or two attached supports at the upper part of the disassembly crane tower enable the tower body to suspend out; then use a jack to get the tower body inclined so that blocked components can leave the interference position and then descend the tower crane. The descending method has the advantages that the method is applicable for any type of tower cranes when blocked by buildings during the descending process; in particular when the interference size is not so large, the method is very simple and efficient.

Description

The tower machine descending method that is used for normal descend of building interference tower machine upper component
Technical field
The present invention relates to a kind of landing method of tower crane
Background technology
The tower mast of tower crane, main trunk body of the tower is made by standard knot, its consistent size, the jacking stock of tower machine upper, the size of members such as rotation body of the tower is a bit larger tham body of the tower.There is the phenomenon of interim change (such as the interim change of edge, roof gutter in construction) at the edge that sometimes can run into building a part in real work, the generations such as equilibrium arm girder that can cause stretching out edge and tower machine jacking stock and tower machine are interfered, the tower machine is obstructed when descending, and does not descend.
Summary of the invention
The object of the present invention is to provide a kind of tower machine descending method that is used for normal descend of building interference tower machine upper component, make the landing that still can make tower crane under the jacking stock of tower crane and the situation that rotation body of the tower and building interfere.
The tower machine descending method that the present invention is used for normal descend of building interference tower machine upper component is: dismounting tower machine topmost together or twice adhere to support, make body of the tower top hang, again with jack top leaning tower body, the tower machine is obstructed after member leaves interference position, tower machine again descends.
The principle of the inventive method is: the steel structure formula rod member that the body of the tower of tower machine is made up of the body of the tower standard knot, as the iron and steel stressed member, has the resistance to deformation rigidity in the certain limit of bearing, when the deformation force that applies, in the scope that its rigidity can bear (being not unstability of tower mast), after the scope of distance that distortion produces, can make the tower machine be obstructed member safely, realize the decline of tower machine by interfering the position greater than its interference.Therefore the present invention be suitable for any pattern the tower machine when height descends in the air, stopped by building etc., but interfere not very very big situation of size that this method is very simple, efficient.
Description of drawings
Fig. 1 is the scheme drawing that the inventive method is implemented.
Force analysis figure when Fig. 2 is the invention process.
The specific embodiment
The contriver has used a dwelling house complex building with the inventive method, what used construction period in this building is a Taijiang foot of a hill or mountain board QT125 type tower machine, when the finishing on building main body and top is finished substantially, edge, the roof gutter of finding this building when tearing this tower machine open need fall, because the interim change in the construction, all produced interference to the jacking stock that stretches out edge and this tower machine that makes the roof gutter and the equilibrium arm girder of tower machine, the gutter outer rim is height 0.8m vertically, interfere the about 0.7m of the degree of depth, the member that is obstructed on the tower machine is long equilibrium arm girder and the how high jacking stock of vertical direction 6m of horizontal direction 14m.At first should ajust tower machine crane arm when using the inventive method,, carry out as follows then referring to Fig. 1:
1. fall two joint standard knots, make the jacking stock 2 of this tower machine drop to the gutter boundary position;
2. remove first and second roads that the tower machine goes up most and adhere to and support 4,5, make the 3rd road adhere to supporting 6 apart from about the about 40m of distance of cat head, promptly body of the tower hangs highly 40m.At this moment tower machine can also rotate, owing to the strut of removing that adheres to support, enclose member such as hoop and need the master winch of tower machine to hang down, when tearing second road open and adhere to support, consider to make tower machine mainmast top hang oversize, should when turning round, crane arm remove the strut of back earlier; Ajust arm support position do not need the revolution after, tear fwd again open and adhere to bar, like this work comparatively safe.
3. for increasing safety rate, should adopt following two measures.
1. penetrate a Φ 20mm steel rope 7 hanging the body of the tower middle part, watchman's wooden clapper is tied on the building beam column, and watchman's wooden clapper will guarantee to leave free distance when pricking, and left room for when oblique for body of the tower pushes up, but this distance is not more than 200mm.
2. in the pinnacle of a pagoda on the bar beam on the building top watchman's wooden clapper prick Φ 15mm steel rope 8, and hang the bottle gouard moved by hands 9 of a 10t, in order to regulate tense wire rope, in case body of the tower is outwards pounced on suddenly in inter-burst.
4. distinguish two main strings of outside head tower body in the position of being obstructed with two jacks, with the body of the tower top tiltedly, be obstructed after member leaves interference distance until the tower machine, tower machine again descends, replace when becoming flexible as above-mentioned two jacks with two jacks more simultaneously and use, guarantee that two main strings are held out against by jack all the time, get rid of up to interference.Jack is owing to be that level is shelved, and every place should arrange jointly operation of two workmans, should put up the erect-position platform on body of the tower in advance, and also available iron wire horizontally suspends jack, alleviates hand-held labour intensity.
Because the extension elongation of jack is limited, can need distance by actual jacking, make the cushion block of all thickness in advance.
If it is long to hinder distance, need shift out standard knot in the time of can be because of the decline body of the tower, at this moment there has not been body of the tower master string, the jack of this moment can only withstand on the jacking stock, thus should select this member stiffness than the strength, or do in advance to strengthen processing, prevent to push up bad parts.
5. at tower machine 6m jacking stock how long 2 descend, then should solve the problem that equilibrium arm 3 is interfered by behind the gutter.Because equilibrium arm 3 rear portions are equipped with the various parts of hoisting mechanism, it is outer many that the equilibrium arm girder is deflected away from the position installation, and 0.8m is arranged approximately.Therefore the hold-down bolt of each parts of hoisting mechanism, pin hinge etc. should be taken apart, its translation is entered in the girder, install fasteningly temporarily again, recover the winch function, and the sidebar that girder is outer dismounting.Do like this is not increase the top as far as possible to stretch to outer distance y Max,, cause many adverse factors because the increase of top inclined range can cause the increase of pushing up the power of stretching.
6. jacking process should be provided with a special messenger and be responsible for seeing the feelings commander, as run into jam or other fault takes place, and the inspection of should stopping is carried out after the eliminating again.
Outwards skew is approximately greater than the interference distance of 0.7m when body of the tower, and the jacking stock 2 and the equilibrium arm 3 that can descend and be blocked after these members that are obstructed pass through gutter, just can recover the plumbness of body of the tower 1, just can descend body of the tower according to a conventional method later.
To above-mentioned embodiment body of the tower top stressed with displacement relation as shown in Figure 2, body of the tower top is under horizontal top power effect, its displacement deformation should be calculated as follows:
y max=Pl 3/3EJ(1)
In the formula: y MaxThe maximum defluxion of-body of the tower in elastic range; The horizontal force that the P-jack need apply; 1-top origin of force is to following vertical distance of adhering to the place together; The modulus of elasticity of E-material, steel are got E=2 * 10 11N/m 2The polar moment of inertia in J-body of the tower cross section.The cross section that this tower machine shows by Fig. 3 can calculate J=0.0213m 4.
It is the size that needs strict control that tower mast hangs length 1, and the whole hazard level of long more then tower machine is big more.By actual conditions as calculated, twice are adhered to after the supporting on removing, and the distance 1 that three roads, application of force place to the of jack the adhere to support 40m that has an appointment is ejecting distance y MaxWhen reaching 0.7m, calculate needed top by (1) formula and stretch power P and be:
P = Y max × 2 EJ L 3 = 0.7 × 3 × 2 × 10 11 × 0.0213 40 3 = 140 kN ( 14 t )
So, should adopt the mechanical type jack of two 8t.
In brief under the situation of building interference distance less than 700mm, the tower machine is descended should be comprised the steps:
A, the tower machine member that is obstructed is come to the building interference place;
The twice that b, dismounting are gone up are most adhered to support, make body of the tower hang height<40m;
C, in tower machine pinnacle of a pagoda on the binder of roofing colligation one guy steel rope, in the middle of this guy steel rope, be connected in series a bottle gouard moved by hands by described binder place, send the special messenger to tighten up the guy stay cord constantly, twine the enough steel ropes of an intensity in body of the tower to the building pocket adhere to the position of support in second road near, assurance has free distance, and this distance is not more than 200mm;
D, with two jacks at the respectively two main strings of outside head tower body of position that are obstructed, with the body of the tower top tiltedly, be obstructed after member leaves interference distance until the tower machine, tower machine again descends, replace when becoming flexible as above-mentioned two jacks with two jacks more simultaneously and use, guarantee that two main strings are held out against by jack all the time, get rid of up to interference.
If the building interference distance should be carried out as follows less than the situation of 500mm:
A, the tower machine member that is obstructed is come to the building interference place;
B, remove go up most adhere to support together, make body of the tower hang height<28m;
C, in tower machine pinnacle of a pagoda on the binder of roofing colligation one guy steel rope, in the middle of this guy steel rope,, send the special messenger to tighten up the guy stay cord constantly by 10 bottle gouards moved by hands of described binder place serial connection;
D, with two jacks at the respectively two main strings of outside head tower body of position that are obstructed, with the body of the tower top tiltedly, be obstructed after member leaves interference distance until the tower machine, tower machine again descends, replace when becoming flexible as above-mentioned two jacks with two jacks more simultaneously and use, guarantee that two main strings are held out against by jack all the time, the former member that is obstructed is not interfered in the decline process.

Claims (3)

1. a tower machine descending method that is used for normal descend of building interference tower machine upper component is characterized in that, dismounting tower machine topmost together or twice adhere to support, make body of the tower top hang, again with jack top leaning tower body, the tower machine is obstructed after member leaves interference position, tower machine again descends.
2. tower machine descending method according to claim 1 is characterized in that comprising the steps:
A, the tower machine member that is obstructed is come to the building interference place;
B, under building interference distance situation less than 500mm, remove go up most adhere to support together, make body of the tower hang height<28m;
C, in tower machine pinnacle of a pagoda on the binder of roofing colligation one guy steel rope, in the middle of this guy steel rope,, send the special messenger to tighten up the guy stay cord constantly by bottle gouard moved by hands of described binder place serial connection;
D, with two jacks at the respectively two main strings of outside head tower body of position that are obstructed, with the body of the tower top tiltedly, be obstructed after member leaves interference distance until the tower machine, tower machine again descends, replace when becoming flexible as above-mentioned two jacks with two jacks more simultaneously and use, guarantee that two main strings are held out against by jack all the time, get rid of up to interference.
3. tower machine descending method according to claim 1 is characterized in that comprising the steps:
A, the tower machine member that is obstructed is come to the building interference place;
B, under building interference distance situation less than 700mm, remove the twice that go up most and adhere to support, make body of the tower hang height<40m;
C, in tower machine pinnacle of a pagoda on the binder of roofing colligation one guy steel rope, in the middle of this guy steel rope, be connected in series a bottle gouard moved by hands by described binder place, send the special messenger to tighten up the guy stay cord constantly, twine the enough steel ropes of an intensity in body of the tower to the building pocket adhere to the position of support in second road near, assurance has free distance, and this distance is not more than 200mm;
D, with two jacks at the respectively two main strings of outside head tower body of position that are obstructed, with the body of the tower top tiltedly, be obstructed after member leaves interference distance until the tower machine, tower machine again descends, replace when becoming flexible as above-mentioned two jacks with two jacks more simultaneously and use, guarantee that two main strings are held out against by jack all the time, get rid of up to interference.
CNB2008100311058A 2008-04-21 2008-04-21 The tower machine descending method that is used for normal descend of building interference tower machine upper component Expired - Fee Related CN100562482C (en)

Priority Applications (1)

Application Number Priority Date Filing Date Title
CNB2008100311058A CN100562482C (en) 2008-04-21 2008-04-21 The tower machine descending method that is used for normal descend of building interference tower machine upper component

Applications Claiming Priority (1)

Application Number Priority Date Filing Date Title
CNB2008100311058A CN100562482C (en) 2008-04-21 2008-04-21 The tower machine descending method that is used for normal descend of building interference tower machine upper component

Publications (2)

Publication Number Publication Date
CN101264850A true CN101264850A (en) 2008-09-17
CN100562482C CN100562482C (en) 2009-11-25

Family

ID=39987581

Family Applications (1)

Application Number Title Priority Date Filing Date
CNB2008100311058A Expired - Fee Related CN100562482C (en) 2008-04-21 2008-04-21 The tower machine descending method that is used for normal descend of building interference tower machine upper component

Country Status (1)

Country Link
CN (1) CN100562482C (en)

Cited By (3)

* Cited by examiner, † Cited by third party
Publication number Priority date Publication date Assignee Title
CN103922232A (en) * 2014-04-14 2014-07-16 南通庞源机械工程有限公司 Self-elevating tower crane descending process
CN105000485A (en) * 2015-08-02 2015-10-28 周兆弟 Guide rail supporting system used for being connected with tower crane
CN107531464A (en) * 2015-03-26 2018-01-02 利勃海尔工厂比伯拉赫股份有限公司 Crane tower

Cited By (4)

* Cited by examiner, † Cited by third party
Publication number Priority date Publication date Assignee Title
CN103922232A (en) * 2014-04-14 2014-07-16 南通庞源机械工程有限公司 Self-elevating tower crane descending process
CN103922232B (en) * 2014-04-14 2016-09-14 南通庞源机械工程有限公司 A kind of tower crane fall tower process
CN107531464A (en) * 2015-03-26 2018-01-02 利勃海尔工厂比伯拉赫股份有限公司 Crane tower
CN105000485A (en) * 2015-08-02 2015-10-28 周兆弟 Guide rail supporting system used for being connected with tower crane

Also Published As

Publication number Publication date
CN100562482C (en) 2009-11-25

Similar Documents

Publication Publication Date Title
CN206376515U (en) High-lift operation hanging cradle device
CN103643800B (en) The erection & lift system of buckling-restrained bracing member and construction method thereof
CN103523683B (en) Construction method for dismantling tower crane by use of small hoisting equipment
CN100562482C (en) The tower machine descending method that is used for normal descend of building interference tower machine upper component
CN106758837A (en) A kind of Inclined cable-stayed construction system of combination spandrel column
CN101284628A (en) Hoisting method for framework of large tonnage pressing machine
CN203856187U (en) Elevator shaft operation platform
CN201288415Y (en) Subsection gradual change overhanging type external scaffold for tall building
CN106544959B (en) The construction method of king-tower lifting segment and bridge main tower saddle containing saddle
CN202175488U (en) Lifter for building construction
CN103422508B (en) Deep foundation ditch inner support platform structure machinery is vexed tears method and structure open
CN107012797A (en) Construction system and method that a kind of Support Method is combined with stayed knotting method
CN105829203A (en) Saddle and hook system
CN106760558A (en) A kind of suspension type boiler-steam dome aerial aligning method after installing
CN101387152A (en) Tool type scaffold for elevator well
CN103171911B (en) Ship loader installation technology
CN202718125U (en) Positioning and guiding frame for bailey steel trestle bridge pier foundation construction
CN205369044U (en) Integration prestressing force stretch -draw frame construction
CN107130990A (en) A kind of large-mining-height working surface tears frame method open
CN202831591U (en) Special-shaped truss operation platform capable of hoisting to super high space
CN203904839U (en) Combined hanging basket structure
CN206872341U (en) One kind building hoistable platform
CN207110429U (en) Roofing attaching beam formula hanging basket mechanism arrangement
CN105926915B (en) Grow the construction method for workbench of encorbelmenting in Bailey beam high-altitude
CN212128854U (en) Bridge construction machine with stabilizing device for bridge construction

Legal Events

Date Code Title Description
C06 Publication
PB01 Publication
C10 Entry into substantive examination
SE01 Entry into force of request for substantive examination
C14 Grant of patent or utility model
GR01 Patent grant
CF01 Termination of patent right due to non-payment of annual fee

Granted publication date: 20091125

Termination date: 20150421

EXPY Termination of patent right or utility model