CN101153788A - Manufacturing process for water defector component of vertical current force cooling tower - Google Patents

Manufacturing process for water defector component of vertical current force cooling tower Download PDF

Info

Publication number
CN101153788A
CN101153788A CN 200610116692 CN200610116692A CN101153788A CN 101153788 A CN101153788 A CN 101153788A CN 200610116692 CN200610116692 CN 200610116692 CN 200610116692 A CN200610116692 A CN 200610116692A CN 101153788 A CN101153788 A CN 101153788A
Authority
CN
China
Prior art keywords
cooling tower
water
water retaining
retaining member
current force
Prior art date
Legal status (The legal status is an assumption and is not a legal conclusion. Google has not performed a legal analysis and makes no representation as to the accuracy of the status listed.)
Pending
Application number
CN 200610116692
Other languages
Chinese (zh)
Inventor
张恒钦
Current Assignee (The listed assignees may be inaccurate. Google has not performed a legal analysis and makes no representation or warranty as to the accuracy of the list.)
Shanghai Liangji Cooling Equipment Co Ltd
Original Assignee
Shanghai Liangji Cooling Equipment Co Ltd
Priority date (The priority date is an assumption and is not a legal conclusion. Google has not performed a legal analysis and makes no representation as to the accuracy of the date listed.)
Filing date
Publication date
Application filed by Shanghai Liangji Cooling Equipment Co Ltd filed Critical Shanghai Liangji Cooling Equipment Co Ltd
Priority to CN 200610116692 priority Critical patent/CN101153788A/en
Publication of CN101153788A publication Critical patent/CN101153788A/en
Pending legal-status Critical Current

Links

Images

Landscapes

  • Heat-Exchange Devices With Radiators And Conduit Assemblies (AREA)

Abstract

The invention discloses a manufactured process of a water retaining member of a cooling tower of vertical type flow force, which mainly includes the following steps that: A. a water retaining member is provided to make the upper section and the lower section of the body upright sections; the water retaining member is connected with a part bending backward and the middle part is an upright section; B. the surface of the body is provided with an insertion hole, and the other face is provide with a positioning hole plate corresponding with the insertion hole. The manufactured water retaining member of the cooling tower of vertical type flow force is arranged at the top of the cooling tower with simple assembly and easy installation and maintainance; As the five-folds water retaining design is adopted also with a hollow convex strip arranged, a better water way design is formed, which makes the tiny vapor and fog agglomerate into big water drops during flowing the winding path, and then fall back to the inside of the cooling tower, reducing the splashing loss of water drops; the invention has a high intensity and a stable structure performance with high promotion value.

Description

The manufacturing process of the water defector component of vertical current force cooling tower
Technical field:
The present invention relates to a kind of cooling device and make the field, particularly relate to the manufacturing technology of the water defector component in a kind of cooling tower.
Background technology:
Since mid-term in last century, cooling tower came out, be to drive air motion as the air power source of water tower with blower fan always, make outside air with through the recirculated cooling water generation heat exchange in the tower, to reach the purpose that reduces cooling water.
But along with the raising of social progress and people's living standard, people are more and more higher to the cry of conserve water resource and environmental protection, and for this reason, we need the vertical current force cooling tower of development of new.And the dash device of traditional mechanical ventilation type cooling tower all adopts the polyvinyl chloride material to make, and its hardness is little, is unsuitable for being installed in the cooling tower outside, and is yielding, fade, and is difficult to accomplish that at the water curtain of ejection at a high speed steam separates, and easily causes water-drop sputtering.
Summary of the invention:
Technical problem to be solved by this invention provides and a kind ofly can effectively overcome above-mentioned defective, is convenient to the manufacturing process of the water defector component of the vertical current force cooling tower that steam separates.The technical solution adopted for the present invention to solve the technical problems is, a kind of manufacturing process of water defector component of vertical current force cooling tower, mainly comprise following steps: A. and make upper and lower two sections of body to be vertical section, it is connected with bending segment backward, and the centre is a vertical section; B. the surface of body provides a kind of patchhole that has, and another side provides the location orifice plate with the patchhole coupling.Owing to adopt such scheme, be not difficult to draw the present invention and have following beneficial effect: the water defector component of the vertical current force cooling tower that it produces, 1. owing to adopt the design of polypropylene material easy plugged type, assembling is easily, and be installed on the cooling tower top, installation and maintenance are quite easy; 2. owing to adopt five folding formula dash designs, and be provided with the hollow raised line, preferable bent road design is arranged, can make tiny steam and water smoke in the time through bent road, be condensed into big water droplet, row falls the inside of cooling tower after rise again, has reduced the spatter loss of water droplet, after tested, its spatter loss can be controlled between 0.005--0.009%;
3. owing to adopt Mold Making, its intensity height, structural behaviour is stable, the tool promotional value.
Description of drawings:
Below in conjunction with drawings and Examples the present invention is described in further detail.
The main TV structure schematic diagram of the water defector component of the vertical current force cooling tower that Fig. 1 produces for the present invention;
Fig. 2 is the structural representation of looking up of this water defector component;
Fig. 3 looks the sectional structure schematic diagram for the left side of this water defector component.
The specific embodiment:
A kind of manufacturing process of water defector component of vertical current force cooling tower mainly comprises following steps: A. and makes upper and lower two sections of body to be vertical section, and it is connected with bending segment backward, and the centre is a vertical section; B. the surface of body provides a kind of patchhole that has, and another side provides the location orifice plate with the patchhole coupling.The structure of the water defector component of the vertical current force cooling tower that the present invention is produced below in conjunction with accompanying drawing describes in further detail.Among the figure, the water defector component of vertical current force cooling tower, mainly form by a body, body adopts five folding formulas designs, and upper and lower two sections of body is vertical section 4, and it is connected with backward bending segment 5 at an angle, the centre is a vertical section 6, a kind of patchhole 2 that has is established on the surface of body, and another side is provided with the location orifice plate 1 with patchhole 2 couplings, and it is convenient to the assembly and disassembly of water defector component.Wherein, every folding is equipped with the hollow raised line 3 of evagination, and this hollow raised line 3 is a bending.During every water defector component assembling, the bent road of bending of certain interval is arranged, when being installed on the cooling tower top, can form large-area five bending triton roads, the recirculated water of being convenient to upwards to spray is done steam and is separated.Be installed on the cooling tower top during water defector component assembling, the member top all is upright situation during assembling, can make the tower body top all horizontal, and it is attractive in appearance to be convenient to the assembling of cooling tower part, maintenance and overall structure; The member bottom also all is upright situation, is convenient to enter when recirculated water upwards sprays do the steam separation in the dash device; The bending design of member middle part can increase steam time of staying in bend, makes steam condense into droplet in bend, under the gravity effect, falls after rise to cooling tower again; The water defector component assembling is parallel placement with cooling tower inner nozzle direction.Preferred configuration because of five bending roads of the present utility model, and design has the hollow raised line of evagination in every bending road, can make tiny steam the time through five folding formula bends, condense become big water droplet after, fall inside again after rise to cooling tower, the area that its dash device is shared, very close with cooling tower tower body area occupied, thus the loss that is produced when greatly reducing water-drop sputtering.

Claims (1)

1. the manufacturing process of the water defector component of a vertical current force cooling tower mainly comprises following steps: A. and makes upper and lower two sections of body to be vertical section, and it is connected with bending segment backward, and the centre is a vertical section; B. the surface of body provides a kind of patchhole that has, and another side provides the location orifice plate with the patchhole coupling.
CN 200610116692 2006-09-28 2006-09-28 Manufacturing process for water defector component of vertical current force cooling tower Pending CN101153788A (en)

Priority Applications (1)

Application Number Priority Date Filing Date Title
CN 200610116692 CN101153788A (en) 2006-09-28 2006-09-28 Manufacturing process for water defector component of vertical current force cooling tower

Applications Claiming Priority (1)

Application Number Priority Date Filing Date Title
CN 200610116692 CN101153788A (en) 2006-09-28 2006-09-28 Manufacturing process for water defector component of vertical current force cooling tower

Publications (1)

Publication Number Publication Date
CN101153788A true CN101153788A (en) 2008-04-02

Family

ID=39255574

Family Applications (1)

Application Number Title Priority Date Filing Date
CN 200610116692 Pending CN101153788A (en) 2006-09-28 2006-09-28 Manufacturing process for water defector component of vertical current force cooling tower

Country Status (1)

Country Link
CN (1) CN101153788A (en)

Cited By (2)

* Cited by examiner, † Cited by third party
Publication number Priority date Publication date Assignee Title
CN106091795A (en) * 2016-06-21 2016-11-09 四川中乙制冷设备有限公司 Fan-free energy-saving cooling tower high-efficient water-recovering device
CN107796238A (en) * 2017-11-30 2018-03-13 四川理工学院 Bottom blast formula cooling tower cloth wind structure

Cited By (3)

* Cited by examiner, † Cited by third party
Publication number Priority date Publication date Assignee Title
CN106091795A (en) * 2016-06-21 2016-11-09 四川中乙制冷设备有限公司 Fan-free energy-saving cooling tower high-efficient water-recovering device
CN106091795B (en) * 2016-06-21 2019-05-07 四川中乙制冷设备有限公司 Fan-free energy-saving cooling tower high-efficient water-recovering device
CN107796238A (en) * 2017-11-30 2018-03-13 四川理工学院 Bottom blast formula cooling tower cloth wind structure

Similar Documents

Publication Publication Date Title
CN113539057B (en) Energy-saving wind-swing electronic billboard
CN101153787A (en) Technology for preventing water drop splashing of vertical current force cooling tower
CN102861749A (en) Automatically rotary catkin collector
CN101153788A (en) Manufacturing process for water defector component of vertical current force cooling tower
CN2529182Y (en) Water vapour, spray recovery device of vertical cooling tower
CN205245825U (en) Exempt from energy -conserving cooling tower of fan
CN201627758U (en) Face shield structure for ventilating fan
CN207881168U (en) A kind of drawing water structure and air conditioner of wall-hanging air conditioner
CN205919197U (en) Stage light
CN109584744A (en) A kind of LED electronic light box of outdoor use
CN210271539U (en) Novel high-precision ultra-wide temperature working display screen
CN201103994Y (en) Indoor machine for cabinet air conditioner
CN205332906U (en) Air cooling condenser is restrained high -pressure rapid washout and is sprayed cooling integration system
CN2529181Y (en) Nozzle of spray tube of vertical cooling tower
CN2458581Y (en) Jet cooling tower
CN2335707Y (en) Flow-guiding three-splashing type spray head
CN208720041U (en) The anti-haze street lamp of depositing dust
CN203982711U (en) Display screen
CN101153773A (en) Technology for improving heat exchange effect of vertical current force cooling tower
CN101153774A (en) Manufacturing process for jet pipe nozzle of vertical current force cooling tower
CN212550815U (en) Liquid crystal display screen dust keeper
CN206531276U (en) A kind of novel coal Air hot-blast furnace
CN203479146U (en) Nozzle of overshot flow-force spraying pipe for cooling tower
CN203718904U (en) Golden pipe heater
CN210547953U (en) Efficient rectangular arc-imitating spray

Legal Events

Date Code Title Description
C06 Publication
PB01 Publication
C10 Entry into substantive examination
SE01 Entry into force of request for substantive examination
C02 Deemed withdrawal of patent application after publication (patent law 2001)
WD01 Invention patent application deemed withdrawn after publication

Open date: 20080402