CN101139836A - Drilling grout pile end follow-up grouting construction method - Google Patents
Drilling grout pile end follow-up grouting construction method Download PDFInfo
- Publication number
- CN101139836A CN101139836A CN 200710044791 CN200710044791A CN101139836A CN 101139836 A CN101139836 A CN 101139836A CN 200710044791 CN200710044791 CN 200710044791 CN 200710044791 A CN200710044791 A CN 200710044791A CN 101139836 A CN101139836 A CN 101139836A
- Authority
- CN
- China
- Prior art keywords
- grouting
- pile
- pipe
- slurry
- cast
- Prior art date
- Legal status (The legal status is an assumption and is not a legal conclusion. Google has not performed a legal analysis and makes no representation as to the accuracy of the status listed.)
- Granted
Links
Images
Abstract
Description
Claims (3)
Priority Applications (1)
Application Number | Priority Date | Filing Date | Title |
---|---|---|---|
CN 200710044791 CN100532732C (en) | 2007-08-10 | 2007-08-10 | Drilling grout pile end follow-up grouting construction method |
Applications Claiming Priority (1)
Application Number | Priority Date | Filing Date | Title |
---|---|---|---|
CN 200710044791 CN100532732C (en) | 2007-08-10 | 2007-08-10 | Drilling grout pile end follow-up grouting construction method |
Publications (2)
Publication Number | Publication Date |
---|---|
CN101139836A true CN101139836A (en) | 2008-03-12 |
CN100532732C CN100532732C (en) | 2009-08-26 |
Family
ID=39191927
Family Applications (1)
Application Number | Title | Priority Date | Filing Date |
---|---|---|---|
CN 200710044791 Active CN100532732C (en) | 2007-08-10 | 2007-08-10 | Drilling grout pile end follow-up grouting construction method |
Country Status (1)
Country | Link |
---|---|
CN (1) | CN100532732C (en) |
Cited By (17)
Publication number | Priority date | Publication date | Assignee | Title |
---|---|---|---|---|
CN102433884A (en) * | 2011-10-17 | 2012-05-02 | 同济大学建筑设计研究院(集团)有限公司 | System and design method applying tree-root piles and pile side compacted grouting |
CN102535527A (en) * | 2010-12-14 | 2012-07-04 | 上海市基础工程有限公司 | Testing device and method of breast wall slurry pressure during pore-forming construction of cast-in-situ bored pile |
CN101713189B (en) * | 2008-10-06 | 2012-10-17 | 吴保全 | Construction process of floral tube dry filling piles |
CN102864775A (en) * | 2012-08-28 | 2013-01-09 | 福建省大地管桩有限公司 | Method for producing prestressed uplift tubular pile by utilizing secondary grouting method |
CN101333812B (en) * | 2008-08-04 | 2013-06-12 | 上海市基础工程有限公司 | Grouter for back side grouting and its construction method |
CN103174135A (en) * | 2011-12-23 | 2013-06-26 | 五冶集团上海有限公司 | Repair method of unqualified post-grouting bored concrete pile |
CN103184737A (en) * | 2011-12-28 | 2013-07-03 | 上海市基础工程有限公司 | Grouting machine for post grouting under embedded rock geological condition |
CN103498465A (en) * | 2013-10-08 | 2014-01-08 | 重庆建工市政交通工程有限责任公司 | Method for strengthening pile bottom sediment |
CN104612134A (en) * | 2014-12-16 | 2015-05-13 | 中铁建大桥工程局集团第五工程有限公司 | Cast-in place pile post-grouting construction method for pouring construction |
CN104711989A (en) * | 2013-12-13 | 2015-06-17 | 国家电网公司 | Cast-in-place pile post-grouting retaining-sealing two-in-one foundation pit supporting method |
CN105239563A (en) * | 2015-10-27 | 2016-01-13 | 贵州开磷建设集团有限公司 | Dry-method hole forming filling pile structure for post-grouting matched rotary drilling rig and construction method |
CN107687171A (en) * | 2017-09-15 | 2018-02-13 | 中建三局第建设工程有限责任公司 | Diaphram wall double pump post-grouting device and construction method |
CN110468938A (en) * | 2019-07-02 | 2019-11-19 | 北京质诚捷讯水利工程有限公司 | A kind of municipal drain pipeline construction method |
CN110686739A (en) * | 2019-10-08 | 2020-01-14 | 南通万都建设工程有限公司 | River water level measuring device |
CN111691420A (en) * | 2020-06-22 | 2020-09-22 | 福建省华策建设集团有限公司 | Construction method of PHC tubular pile |
CN112697652A (en) * | 2020-11-30 | 2021-04-23 | 云南建设投资控股集团有限公司 | Experimental device for be used for indoor simulation soil body splitting slip casting |
CN114032881A (en) * | 2021-08-31 | 2022-02-11 | 山东高速股份有限公司 | Sectional grouting reinforcement method for existing pile foundation |
Families Citing this family (1)
Publication number | Priority date | Publication date | Assignee | Title |
---|---|---|---|---|
CN111945713A (en) * | 2020-07-24 | 2020-11-17 | 中交第三航务工程局有限公司 | Construction method for grouting after rock-socketed inclined pile of offshore wind power foundation steel pipe pile |
-
2007
- 2007-08-10 CN CN 200710044791 patent/CN100532732C/en active Active
Cited By (20)
Publication number | Priority date | Publication date | Assignee | Title |
---|---|---|---|---|
CN101333812B (en) * | 2008-08-04 | 2013-06-12 | 上海市基础工程有限公司 | Grouter for back side grouting and its construction method |
CN101713189B (en) * | 2008-10-06 | 2012-10-17 | 吴保全 | Construction process of floral tube dry filling piles |
CN102535527A (en) * | 2010-12-14 | 2012-07-04 | 上海市基础工程有限公司 | Testing device and method of breast wall slurry pressure during pore-forming construction of cast-in-situ bored pile |
CN102433884A (en) * | 2011-10-17 | 2012-05-02 | 同济大学建筑设计研究院(集团)有限公司 | System and design method applying tree-root piles and pile side compacted grouting |
CN103174135B (en) * | 2011-12-23 | 2015-06-03 | 五冶集团上海有限公司 | Repair method of unqualified post-grouting bored concrete pile |
CN103174135A (en) * | 2011-12-23 | 2013-06-26 | 五冶集团上海有限公司 | Repair method of unqualified post-grouting bored concrete pile |
CN103184737A (en) * | 2011-12-28 | 2013-07-03 | 上海市基础工程有限公司 | Grouting machine for post grouting under embedded rock geological condition |
CN102864775A (en) * | 2012-08-28 | 2013-01-09 | 福建省大地管桩有限公司 | Method for producing prestressed uplift tubular pile by utilizing secondary grouting method |
CN103498465A (en) * | 2013-10-08 | 2014-01-08 | 重庆建工市政交通工程有限责任公司 | Method for strengthening pile bottom sediment |
CN103498465B (en) * | 2013-10-08 | 2015-04-15 | 重庆建工市政交通工程有限责任公司 | Method for strengthening pile bottom sediment |
CN104711989A (en) * | 2013-12-13 | 2015-06-17 | 国家电网公司 | Cast-in-place pile post-grouting retaining-sealing two-in-one foundation pit supporting method |
CN104612134A (en) * | 2014-12-16 | 2015-05-13 | 中铁建大桥工程局集团第五工程有限公司 | Cast-in place pile post-grouting construction method for pouring construction |
CN105239563A (en) * | 2015-10-27 | 2016-01-13 | 贵州开磷建设集团有限公司 | Dry-method hole forming filling pile structure for post-grouting matched rotary drilling rig and construction method |
CN107687171A (en) * | 2017-09-15 | 2018-02-13 | 中建三局第建设工程有限责任公司 | Diaphram wall double pump post-grouting device and construction method |
CN110468938A (en) * | 2019-07-02 | 2019-11-19 | 北京质诚捷讯水利工程有限公司 | A kind of municipal drain pipeline construction method |
CN110686739A (en) * | 2019-10-08 | 2020-01-14 | 南通万都建设工程有限公司 | River water level measuring device |
CN111691420A (en) * | 2020-06-22 | 2020-09-22 | 福建省华策建设集团有限公司 | Construction method of PHC tubular pile |
CN111691420B (en) * | 2020-06-22 | 2021-08-03 | 福建省华策建设集团有限公司 | Construction method of PHC tubular pile |
CN112697652A (en) * | 2020-11-30 | 2021-04-23 | 云南建设投资控股集团有限公司 | Experimental device for be used for indoor simulation soil body splitting slip casting |
CN114032881A (en) * | 2021-08-31 | 2022-02-11 | 山东高速股份有限公司 | Sectional grouting reinforcement method for existing pile foundation |
Also Published As
Publication number | Publication date |
---|---|
CN100532732C (en) | 2009-08-26 |
Similar Documents
Publication | Publication Date | Title |
---|---|---|
CN101139836A (en) | Drilling grout pile end follow-up grouting construction method | |
CN106049557B (en) | Using the test method of the laboratory testing rig of simulation grout pile end follow-up grouting | |
CN201722685U (en) | No-adhesive prestress and pile side rear grouting punching pile structure | |
CN105239563B (en) | A kind of supporting rotary drilling rig dry method pore-creating filling pile structure of grouting behind shaft or drift lining and construction method | |
CN102206939B (en) | Method for processing soft soil foundation of high vacuum drainage filter pipe capable of being grouted | |
CN111945713A (en) | Construction method for grouting after rock-socketed inclined pile of offshore wind power foundation steel pipe pile | |
CN101230570A (en) | Layered multitime pressure regulating pulp conditioning casting method | |
CN107513995A (en) | A kind of bridge struction pile post grouting construction method | |
CN103572808A (en) | Building toilet caisson waterproof device and construction method | |
Gao et al. | Field load testing study of vertical bearing behavior of a large diameter belled cast-in-place pile | |
CN104947723B (en) | Presplitting grouting method at the bottom of rock-socketed bored concrete pile | |
CN110700266A (en) | Underground continuous wall toe post-grouting construction method | |
CN215165608U (en) | Grouting system for enhancing bearing capacity of offshore wind power pile foundation | |
CN206971247U (en) | A kind of concrete plinth foundation ruggedized construction being placed on Unloading Rock | |
CN204112318U (en) | A kind of technique device improving CFG guncreting pile bearing capacity | |
CN205116159U (en) | Supporting rig dry process pore -forming bored concrete pile that digs soon of back slip casting | |
CN208844629U (en) | Device for sounding and slip casting | |
CN207866664U (en) | A kind of rock foundation grouting test device | |
CN113431046B (en) | Post-grouting construction method for cast-in-place pile | |
CN105625303A (en) | Post-grouting technology for cast-in-situ bored pile | |
CN113186963A (en) | Tower crane foundation pit decompression grouting construction method | |
Wan et al. | Post-grouting of drilled shaft tips in coral-reef limestone formations: a case study | |
CN1074001A (en) | The technological method for processing of borehole pouring mortar pile | |
Cui | Nondestructive Controllable Grouting: A Novel Method to Correct Deviation of Building Foundation | |
CN105442594A (en) | Hole reaming mud-jacking construction technology for prestress hollow square pile with built-in mud-jacking pipe |
Legal Events
Date | Code | Title | Description |
---|---|---|---|
C06 | Publication | ||
PB01 | Publication | ||
C10 | Entry into substantive examination | ||
SE01 | Entry into force of request for substantive examination | ||
C14 | Grant of patent or utility model | ||
GR01 | Patent grant | ||
C56 | Change in the name or address of the patentee |
Owner name: SHANGHAI FOUNDATION ENGINEERING CO., LTD Free format text: FORMER NAME: FOUNDATION ENGINEERING CO. OF SHANGHAI CITY |
|
CP01 | Change in the name or title of a patent holder |
Address after: 200002 No. 406 middle Jiangxi Road, Shanghai, Huangpu District Patentee after: Shanghai Foundation Engineering Co., Ltd. Address before: 200002 No. 406 middle Jiangxi Road, Shanghai, Huangpu District Patentee before: Foundation Engineering Co. of Shanghai City |
|
C56 | Change in the name or address of the patentee |
Owner name: SHANGHAI FOUNDATION ENGINEERING GROUP CO., LTD. Free format text: FORMER NAME: SHANGHAI FOUNDATION ENGINEERING CO., LTD. |
|
CP01 | Change in the name or title of a patent holder |
Address after: 200002 No. 406 middle Jiangxi Road, Shanghai, Huangpu District Patentee after: Shanghai Foundation Engineering Group Co., Ltd. Address before: 200002 No. 406 middle Jiangxi Road, Shanghai, Huangpu District Patentee before: Shanghai Foundation Engineering Co., Ltd. |