CN101029486A - 一种快速加固软弱地基的施工方法 - Google Patents
一种快速加固软弱地基的施工方法 Download PDFInfo
- Publication number
- CN101029486A CN101029486A CNA2007100616206A CN200710061620A CN101029486A CN 101029486 A CN101029486 A CN 101029486A CN A2007100616206 A CNA2007100616206 A CN A2007100616206A CN 200710061620 A CN200710061620 A CN 200710061620A CN 101029486 A CN101029486 A CN 101029486A
- Authority
- CN
- China
- Prior art keywords
- hole
- pile
- water
- stake
- component
- Prior art date
- Legal status (The legal status is an assumption and is not a legal conclusion. Google has not performed a legal analysis and makes no representation as to the accuracy of the status listed.)
- Pending
Links
Images
Classifications
-
- Y—GENERAL TAGGING OF NEW TECHNOLOGICAL DEVELOPMENTS; GENERAL TAGGING OF CROSS-SECTIONAL TECHNOLOGIES SPANNING OVER SEVERAL SECTIONS OF THE IPC; TECHNICAL SUBJECTS COVERED BY FORMER USPC CROSS-REFERENCE ART COLLECTIONS [XRACs] AND DIGESTS
- Y02—TECHNOLOGIES OR APPLICATIONS FOR MITIGATION OR ADAPTATION AGAINST CLIMATE CHANGE
- Y02W—CLIMATE CHANGE MITIGATION TECHNOLOGIES RELATED TO WASTEWATER TREATMENT OR WASTE MANAGEMENT
- Y02W30/00—Technologies for solid waste management
- Y02W30/50—Reuse, recycling or recovery technologies
- Y02W30/91—Use of waste materials as fillers for mortars or concrete
Abstract
本发明属于一种软弱地基的浅层加固技术,对于淤泥地基目前的处理技术是采用预制桩穿透淤泥层直达持力层或者采用堆载预压插板排水固结方案,但是这些方案都存在投资高和工期长的缺点。本发明采用石灰在水中反应的方法使熟化后的石灰在水中结硬形成坚固的桩体,并利用反应中放出的热量使桩间淤泥中的含水气化和硬化,达到提高淤泥土的承载力和消除后期沉降影响的目的,是一种既经济又能快速成桩和快速使淤泥固结的复合地基浅层加固技术。特别适用于淤泥层厚度大和地下水位浅的房屋、道路、广场以及河堤等淤泥地基的浅层加固。
Description
技术领域
本发明属于一种软弱地基的浅层加固技术,尤其涉及淤泥地基的快速加固技术。本发明特别适用于淤泥层厚度大和地下水位浅的房屋、道路、广场以及河堤等淤泥地基的浅层加固。
背景技术
对于软弱地基的处理,目前大多数都采用桩基穿过软弱层或采用不同材料做成挤密桩进行深层处理。而在江河湖泊和沿海一带,由于地下水位较浅,淤泥层较厚,当采用挤密桩做成的复合地基时,不仅成本高,而且由于不能挤出淤泥中的水份,故不仅对复合地基的承载力提高非常有限,尤其不能解决地基的后期沉降问题,因此不能满足设计要求。所以,目前对于淤泥地基的处理较为可靠的方法是:
1.对房屋建筑采用预制桩穿透淤泥层直达持力层。该技术方案虽然安全可靠,但是在淤泥厚度较大的地方,桩长超过了房屋的高度,不仅基础工期长,而且成本高。同时,作为房屋的地坪和室内堆场等,为了避免地基下沉而做成架空地板,也增加了工程造价和延长了工期。
2.对道路等室外工程由于覆盖面积大,采用堆载预压插板排水使淤泥固结。该技术方案能使淤泥在一定深度内挤出空隙水,从而不仅提高了地基承载力,而且也基本消除了后期的沉降影响。但是,该技术方案由于工序多,成本高,堆载预压需要超过一年的时间,因此地基处理的工期相当长。而且由于堆载时要填土,卸载时又要挖土,使施工场地的土方工程量特别大,不仅延长了工期,还污染了环境。
发明内容
本发明意在解决软弱地基的加固处理方案中,既不采用挤密桩处理效果差的方法,不采用预制桩穿透淤泥层工期长、成本高的方法,同时也不采用堆载预压插板排水固结工序多、成本高、工期长、施工环境差的方法,而采用一种既经济又能快速成桩和使桩间淤泥固结的复合地基浅层加固技术。
本发明地基加固原理是利用浓硫酸生成二氧化碳与熟化后的石灰作用后在水中结硬而形成坚固的桩体,利用浓硫酸和石灰在水中放热使桩间淤泥含水气化和硬化,达到提高淤泥土的承载力和消除后期沉降影响的目的。
本发明采用一种快速加固软弱地基的施工方法,是按以下技术方案完成的:
用于软土地基的浅层加固时,总体技术方案由桩体材料配制以及施工技术措施组成。
桩体材料配制是由生石灰1~3份和填充材料1~3份按重量比混合而成的A组份以及由煤粉4~6份、石灰石粉5~3份和浓硫酸0.5~2.5份按重量比混合而成的B组份,使用前再将A组份8~10份和B组份1~2份按重量比干拌混合后待用。填充材料采用粉煤灰、石碴或煤矸石等工业废料。B组份中的煤粉和浓硫酸在地下水中产生二氧化碳,石灰石粉又使地下水中新生成的有害物质二氧化硫转化为无害的固体物质。
施工技术措施是按复合地基进行浅层加固要求布置桩孔,孔径取d=0.3~0.5m,孔距取(2~3)d,孔深取0.5~4.5m。孔深较浅的桩体采用人工洛阳铲成孔,原土护壁,当坍孔时采用可透水的塑料网格护壁。孔深较深的桩体采用机械成孔,泥浆护壁,在孔内加设可透水的塑料网格固定孔壁后,再抽干护壁泥浆。桩体成孔并抽干积水后,快速将拌合均匀的A、B两组份材料分层装入桩孔之内,并用夯锤分层压实至距地面0.3~0.5m为止。当孔内桩体材料与渗入孔内的地下水反应放出热量时,快速用挖出的淤泥土封孔。当孔内无地下水渗入时,应向孔内注水助其反应后再用淤泥土封孔。
用于无地下水浸泡的高压缩性粘性土和回填土等其它软弱地基的浅层加固时,还需要在桩体材料填压完成之后,于桩体附近另行布置注水用的桩孔,注水桩孔成孔以后,其孔底要用灰土夯填密实,以防止孔内水向下渗透,然后向孔内灌水助桩体材料进行反应,直到桩体不再放热,则表示完成了反应过程,随后再用灰土分层夯实回填该注水桩孔。
本发明施工简便,速度快,成本低。本发明特别适用于淤泥层厚度大和地下水位浅的房屋、道路、广场以及河堤等淤泥地基的浅层加固,也可用于不受地下水影响的粘土、亚粘土和回填土等其它软弱地基的浅层加固处理。
附图说明
图1为本发明A、B两组份在室内堆放示意图;
图2为本发明桩孔位置俯视图;
图3为本发明桩位成孔剖视图;
图4为本发明桩孔内成桩材料剖视图;
图5为本发明压力板检测位置俯视图。
具体实施方式
将A组份1按重量比生石灰块(二八灰)∶填充材料(粉煤灰)为1∶2干拌混合均匀,防止受潮,集中堆放在棚3内,再将B组份2按重量比煤粉∶石灰石粉∶浓硫酸为6∶3∶1在工厂干拌混合均匀装入加盖的塑料容器中运至棚3内存放备用,如图1所示。操作人员应注意安全防护。
平整场地后按桩孔间距为(2~3)d放线挖孔4,采用桩径d=0.4m,孔距1.0m,梅花布孔,如图2所示。
孔深取1.5m,人工洛阳铲成孔,原土护壁,如孔底约0.5m高处坍孔,则加设双层塑料网格5围成圆形护壁,如图3所示。
抽干孔内渗入的地下水6,将A组份1与B组份2按重量比A∶B为10∶1干拌混合均匀后用小车运至桩孔4旁,快速分层倒入桩孔4内,再用木夯分层压实,分层高度约为0.3m,直到距地表约为0.3m处为止,随即压实桩体表面,当孔内放出热量时即可用挖出的淤泥土封口。当孔内迟迟不放热时,应注水助其放热以后再封口,如图4所示。操作人员应注意安全防护。
次日即可挖去封口淤泥土7,将桩口内注满水助其继续反应,约7天以后即可检测复合地基的承载力。采用压力板法进行检测,压力板8平面位置如图5所示。抽检位置不少于2处,压力板8的平面尺寸与桩距相同,按下沉量为压力板8边长尺寸的1%终止试压荷载。采用边长为1.0m的压力板,如当下沉量为10mm时的终止试压荷载为240KPa,则复合地基设计承载力按120KPa取用。
Claims (2)
1.一种快速加固软弱地基的施工方法,其特征在于:用于软土地基的浅层加固时,技术方案由桩体材料配制及施工技术措施组成,所述的桩体材料包括由生石灰1~3份和填充材料1~3份按重量比混合而成的A组份和由煤粉4~6份、石灰石粉5~3份和浓硫酸0.5~2.5份按重量比混合而成的B组份,使用前再将A组份8~10份和B组份1~2份按重量比干拌混合后待用;所述的填充材料采用粉煤灰、石碴或煤矸石等工业废料;施工技术措施是按复合地基进行浅层加固要求布置桩孔,孔径取d=0.3~0.5m,孔距取(2~3)d,孔深取0.5~4.5m,孔深较浅的桩体采用人工洛阳铲成孔,原土护壁,当坍孔时采用可透水的塑料网格护壁,孔深较深的桩体采用机械成孔,泥浆护壁,在孔内加设可透水的塑料网格固定孔壁后,再抽干护壁泥浆,桩体成孔并抽干积水后,快速将拌合均匀的A、B两组份材料分层装入桩孔之内,并用夯锤分层压实至距地面0.3~0.5m为止,当孔内桩体材料与渗入孔内的地下水反应放出热量时,快速用挖出的淤泥土封孔,当孔内无地下水渗入时,应向孔内注水助其反应后再用淤泥土封孔。
2.根据权利要求1所述的一种快速加固软弱地基的施工方法,其特征在于:用于无地下水浸泡的高压缩性粘性土和回填土等其它软弱地基的浅层加固时,还需要在桩体材料填压完成之后,于桩体附近另行布置注水用的桩孔,注水桩孔成孔以后,其孔底要用灰土夯填密实,以防止孔内水向下渗透,然后向孔内灌水助桩体材料进行反应,直到桩体不再放热,则表示完成了反应过程,随后再用灰土分层夯实回填该注水桩孔。
Priority Applications (1)
Application Number | Priority Date | Filing Date | Title |
---|---|---|---|
CNA2007100616206A CN101029486A (zh) | 2007-03-23 | 2007-03-23 | 一种快速加固软弱地基的施工方法 |
Applications Claiming Priority (1)
Application Number | Priority Date | Filing Date | Title |
---|---|---|---|
CNA2007100616206A CN101029486A (zh) | 2007-03-23 | 2007-03-23 | 一种快速加固软弱地基的施工方法 |
Publications (1)
Publication Number | Publication Date |
---|---|
CN101029486A true CN101029486A (zh) | 2007-09-05 |
Family
ID=38715024
Family Applications (1)
Application Number | Title | Priority Date | Filing Date |
---|---|---|---|
CNA2007100616206A Pending CN101029486A (zh) | 2007-03-23 | 2007-03-23 | 一种快速加固软弱地基的施工方法 |
Country Status (1)
Country | Link |
---|---|
CN (1) | CN101029486A (zh) |
Cited By (7)
Publication number | Priority date | Publication date | Assignee | Title |
---|---|---|---|---|
CN100567193C (zh) * | 2008-03-11 | 2009-12-09 | 天津市建筑科学研究院 | 石灰、粉煤灰预制桩和成桩工艺及形成复合地基的方法 |
CN103898896A (zh) * | 2012-12-28 | 2014-07-02 | 青岛天力建筑加固工程有限公司 | 预埋件灌浆密实回填土的方法 |
CN104264655A (zh) * | 2014-10-16 | 2015-01-07 | 中化岩土工程股份有限公司 | 预成孔深层水下夯实法 |
CN108952579A (zh) * | 2018-07-27 | 2018-12-07 | 中国铁建大桥工程局集团有限公司 | 一种射流式成孔工具及成孔施工方法 |
CN111140199A (zh) * | 2019-12-25 | 2020-05-12 | 北京正和恒基滨水生态环境治理股份有限公司 | 一种井筒封堵方法 |
CN112229704A (zh) * | 2020-08-28 | 2021-01-15 | 河海大学 | 可视化就地固化浅层地基及组合地基试验系统及方法 |
CN113111411A (zh) * | 2021-03-24 | 2021-07-13 | 湖南城市学院 | 一种加固深层淤泥地基的系统及方法 |
-
2007
- 2007-03-23 CN CNA2007100616206A patent/CN101029486A/zh active Pending
Cited By (8)
Publication number | Priority date | Publication date | Assignee | Title |
---|---|---|---|---|
CN100567193C (zh) * | 2008-03-11 | 2009-12-09 | 天津市建筑科学研究院 | 石灰、粉煤灰预制桩和成桩工艺及形成复合地基的方法 |
CN103898896A (zh) * | 2012-12-28 | 2014-07-02 | 青岛天力建筑加固工程有限公司 | 预埋件灌浆密实回填土的方法 |
CN104264655A (zh) * | 2014-10-16 | 2015-01-07 | 中化岩土工程股份有限公司 | 预成孔深层水下夯实法 |
CN108952579A (zh) * | 2018-07-27 | 2018-12-07 | 中国铁建大桥工程局集团有限公司 | 一种射流式成孔工具及成孔施工方法 |
CN111140199A (zh) * | 2019-12-25 | 2020-05-12 | 北京正和恒基滨水生态环境治理股份有限公司 | 一种井筒封堵方法 |
CN112229704A (zh) * | 2020-08-28 | 2021-01-15 | 河海大学 | 可视化就地固化浅层地基及组合地基试验系统及方法 |
CN113111411A (zh) * | 2021-03-24 | 2021-07-13 | 湖南城市学院 | 一种加固深层淤泥地基的系统及方法 |
CN113111411B (zh) * | 2021-03-24 | 2024-01-30 | 湖南城市学院 | 一种加固深层淤泥地基的系统及方法 |
Similar Documents
Publication | Publication Date | Title |
---|---|---|
CN110512589B (zh) | 一种真空降排水联合氧化镁碳化的浅层超软地基固化方法 | |
CN101029486A (zh) | 一种快速加固软弱地基的施工方法 | |
Rajasekaran et al. | Permeability characteristics of lime treated marine clay | |
CN102995599B (zh) | 湿陷性黄土输水渠道的抗冻防渗导水治理方法 | |
CN201883438U (zh) | 一种坑中坑钢板桩基坑支护结构 | |
CN105220674A (zh) | 深厚软基加固处理方法 | |
CN108951675A (zh) | Hdpe土工膜和膨润土-粘土复合垂直防渗墙及其安装施工方法 | |
Chu et al. | Methods for improvement of clay slurry or sewage sludge | |
CN1807773A (zh) | 一种深厚湿陷性黄土地基的处理方法 | |
CN100570077C (zh) | 用于岩溶地区赤泥堆场的水平防渗结构 | |
CN110512591B (zh) | 一种真空预压利导管桩注气碳化超软地基的加固方法 | |
CN110512592B (zh) | 一种真空预压利导管桩注气碳化超软地基的加固处理系统 | |
CN109252433A (zh) | 软弱土地基强化处理构造及加固软弱土地基基坑的方法 | |
CN106284434A (zh) | 一种地下建筑物的抗浮方法及其隔渗装置 | |
CN202559379U (zh) | 一种土石地基条件的垂直柔性屏障安装结构 | |
CN106337422B (zh) | 一种处理湿陷性黄土地区填方地基的方法 | |
CN2908612Y (zh) | 用于岩溶地区赤泥堆场的水平防渗结构 | |
CN1155606A (zh) | 基坑挡土墙作地下室侧墙及其施工方法 | |
CN100595390C (zh) | 建筑垃圾挤淤河塘回填方法 | |
CN102720174A (zh) | 一种深淤区高填方地基处理方法 | |
Zotsenko et al. | Construction features durable storage of toxic waste in boreholes | |
CN114293596A (zh) | 大型垃圾山垂直防渗工艺 | |
KR102309857B1 (ko) | 벤토텍스, 벤토쉬트, gcl방수재, 벤토씰, 씰스트랩, 벤토매스틱 및 이를 이용한 방수, 차수, 복토, 방근, 방근방수 시설, 방법 | |
KR102309856B1 (ko) | 방수, 차수, 방근, 방근방수용 벤토텍스, 벤토쉬트, gcl방수재 및 이의 적용 시설, 방법 | |
CN114457855A (zh) | 一种下沉式水平防渗与垂直防渗组合结构 |
Legal Events
Date | Code | Title | Description |
---|---|---|---|
C06 | Publication | ||
PB01 | Publication | ||
C10 | Entry into substantive examination | ||
SE01 | Entry into force of request for substantive examination | ||
AD01 | Patent right deemed abandoned | ||
C20 | Patent right or utility model deemed to be abandoned or is abandoned |