CN101020160A - Re-separating process for non-ferrous metal tailings - Google Patents
Re-separating process for non-ferrous metal tailings Download PDFInfo
- Publication number
- CN101020160A CN101020160A CN 200710054022 CN200710054022A CN101020160A CN 101020160 A CN101020160 A CN 101020160A CN 200710054022 CN200710054022 CN 200710054022 CN 200710054022 A CN200710054022 A CN 200710054022A CN 101020160 A CN101020160 A CN 101020160A
- Authority
- CN
- China
- Prior art keywords
- mine tailing
- flotation
- slurry
- new
- hole
- Prior art date
- Legal status (The legal status is an assumption and is not a legal conclusion. Google has not performed a legal analysis and makes no representation as to the accuracy of the status listed.)
- Granted
Links
Images
Abstract
The recovering process from non-ferrous metal tailings includes the steps of digging pit, injecting water, stirring, extracting tailing pulp, ball milling, floating and exhausting and utilizing dregs. The present invention is suitable for recovering mineral material from low grade non-ferrous metal tailings, especially from the tailings of closed mine.
Description
Technical field
The invention belongs to the waste recovery field, relate to the mine tailing re-separating process, relate to a kind of re-separating process of non-ferro metals debris particularly.
Background technology
The copper mine of China, plumbous zinc ore, gold mine, silver ore exploitation early, the river course is injected in the discharging that during it is produced there is the mine tailing in ore dressing plant, majority is taked to build in the river course and is built tailings reservoir for piling, because recovery rate in ore-dressing is lower, contains callable kish resource in the mine tailing.At present existing many old mines are closed because of source of crude is deficient, and the ore dressing plant also stops production, and cause preparation equipment idle.Because mineral resources can not be regenerated, the development and use of mine tailing have become the urgent task of these ore deposit factories.
Existing part mine tailing directly is used as building material by people, makes building block or cement baking, and valuable metal tailings resource is not reasonably developed.
Summary of the invention
The inventor is through social investigation, find that existing nonferrous metal mine exists the problems referred to above, at the present situation of the non-ferro metals debris of being sunk into sleep in a large number, purpose is to provide a kind of re-separating process of non-ferro metals debris, so that a large amount of non-ferro metals debris is developed.
For realizing above-mentioned task, the technical solution used in the present invention is the re-separating process of a kind of non-ferro metals debris of design, and its technological process is: dig pit, and---water filling---is stirred---extracting mine tailing slurry---the new tailings discharging utilization of ball milling---flotation---.
Wherein dig pit, excavate shallow mine tailing hole at the mine tailing upper epidermis successively in upstream, mine tailing storehouse, middle reaches, erection bracket on the hole is installed mixer, and mortar pump is installed; Water filling adds water in the hole; Stir, stir the mine tailing hole, make mine tailing pulp in the hole with mixer or water under high pressure; Extracting mine tailing slurry is sent into ore dressing plant ball mill with above-mentioned mine tailing slurry by pipeline with mortar pump; Ball milling is with ore dressing plant ball mill fine grinding mine tailing slurry; Flotation is sent the slurry of the mine tailing after the fine grinding into the flotation device flotation; New tailings discharging utilization enters new mine tailing storehouse with the new mine tailing after the flotation, and new mine tailing can be used as the raw material of construction material.
The present invention takes above technical measures, existing mine tailing is returned choosing handle, and has following remarkable advantage:
Employing is digged pit on the top layer, storehouse, and construction is convenient to mechanical personnel and is entered the storehouse easily, and construction is installed, because the mine tailing accumulation is dark in the mine tailing storehouse, area is big, and middle lower floor can avoid with excavator or civilian worker's difficult like marshland; Save again simultaneously outside the storehouse, to build and stir ground; Take in the order of upstream, mine tailing storehouse, middle reaches recovery successively, because mine tailing flows in the process in mine tailing storehouse, the mine tailing grain is more in the upstream enrichment, can improve the processing tailings grade, reduce treating capacity and can improve the rate of recovery again, improve the grade of tail concentrate, again entail dangers to safety not; The present invention can make full use of idle ore dressing plant capital equipment, does not need newly-built ore dressing plant; Mine tailing of the present invention had both been peeled off attached to the outmoded medicine on the mine tailing grain through ball milling, argillization thing and oxide layer, again fine grinding the mine tailing grain, the metal flotation that helps in the mine tailing is reclaimed.It is little that the present invention has investment, is convenient to enterprise's exploitation and reclaims, and makes the non-ferro metals debris of being sunk into sleep in a large number obtain comprehensive utilization through handling.
Description of drawings
Fig. 1 represents the re-separating process process chart of non-ferro metals debris of the present invention.
The specific embodiment
Further specify the concrete steps of technological process of the re-separating process of non-ferro metals debris of the present invention in conjunction with the accompanying drawings and embodiments, its feature and advantage are clearer.
The embodiment of the re-separating process of non-ferro metals debris of the present invention, stacking bore 2m of top layer, storehouse excavation of upstream, mine tailing storehouse for many years, the shallow mine tailing of dark 1.5m hole, solid frame support on the hole, the rotating shaft of vertical mixer is erected on the support by screw rod, deepen to regulate the height of mixer along with the mine tailing hole, install 4 " mortar pump; water filling in the mine tailing hole; the enough mixer stirrings of water injection rate energy mine tailing is cheated and be made mine tailing be pulpous state, washes away mine tailing with water under high pressure when running into undermixing, with mortar pump the mine tailing slurry is delivered to day from the interior extraction in mine tailing hole by conveyance conduit and handles the further fine grinding of 200T ore dressing plant ball mill; the slurry of the mine tailing after the fine grinding is sent into flotation cell, flotation; Mine tailing enters the technology behind the ore dressing plant, comprises ball milling, floating agent, the mine tailing concentrate filters, and new tailings discharging, all the technology with traditional ore dressing plant is the same, after new mine tailing reclaims through processing, can be used as construction material, brickmaking, system cement etc. can be as storing up new mine tailing after handle in old mine tailing storehouse, saving takies newly, does not need newly-built mine tailing storehouse.
Claims (2)
1, a kind of re-separating process of non-ferro metals debris is characterized in that taking following technological process: dig pit, and---water filling---is stirred---extracting mine tailing slurry---the new tailings discharging utilization of ball milling---flotation---.
2, according to the re-separating process of the non-ferro metals debris of claim 1, it is characterized in that described digging pit, dig shallow hole at the mine tailing upper epidermis successively, on the hole, set up mixer and mortar pump are installed in upstream, mine tailing storehouse, middle reaches; Described water filling adds water in the hole; Described stirring is stirred the mine tailing hole with mixer or water under high pressure; Described extracting mine tailing slurry is sent into ore dressing plant ball mill with above-mentioned mine tailing slurry by pipeline with mortar pump; Described ball milling is with ore dressing plant ball mill fine grinding mine tailing slurry; Described flotation is sent the slurry of the mine tailing after the fine grinding into the flotation device flotation; Described new tailings discharging utilization enters new mine tailing storehouse with the new mine tailing after the flotation, and new mine tailing is used as building material.
Priority Applications (1)
Application Number | Priority Date | Filing Date | Title |
---|---|---|---|
CNB2007100540226A CN100506391C (en) | 2007-02-14 | 2007-02-14 | Re-separating process for non-ferrous metal tailings |
Applications Claiming Priority (1)
Application Number | Priority Date | Filing Date | Title |
---|---|---|---|
CNB2007100540226A CN100506391C (en) | 2007-02-14 | 2007-02-14 | Re-separating process for non-ferrous metal tailings |
Publications (2)
Publication Number | Publication Date |
---|---|
CN101020160A true CN101020160A (en) | 2007-08-22 |
CN100506391C CN100506391C (en) | 2009-07-01 |
Family
ID=38708084
Family Applications (1)
Application Number | Title | Priority Date | Filing Date |
---|---|---|---|
CNB2007100540226A Expired - Fee Related CN100506391C (en) | 2007-02-14 | 2007-02-14 | Re-separating process for non-ferrous metal tailings |
Country Status (1)
Country | Link |
---|---|
CN (1) | CN100506391C (en) |
Cited By (2)
Publication number | Priority date | Publication date | Assignee | Title |
---|---|---|---|---|
CN105272033A (en) * | 2015-10-19 | 2016-01-27 | 嘉善远大新型墙体有限公司 | Brown concrete block and preparation method thereof |
CN107774439A (en) * | 2016-08-31 | 2018-03-09 | 北京新康华环保科技有限公司 | A kind of non-ferro metals debris comprehensive processing method |
-
2007
- 2007-02-14 CN CNB2007100540226A patent/CN100506391C/en not_active Expired - Fee Related
Cited By (2)
Publication number | Priority date | Publication date | Assignee | Title |
---|---|---|---|---|
CN105272033A (en) * | 2015-10-19 | 2016-01-27 | 嘉善远大新型墙体有限公司 | Brown concrete block and preparation method thereof |
CN107774439A (en) * | 2016-08-31 | 2018-03-09 | 北京新康华环保科技有限公司 | A kind of non-ferro metals debris comprehensive processing method |
Also Published As
Publication number | Publication date |
---|---|
CN100506391C (en) | 2009-07-01 |
Similar Documents
Publication | Publication Date | Title |
---|---|---|
Yilmaz | Advances in reducing large volumes of environmentally harmful mine waste rocks and tailings | |
CN101435021B (en) | Acid heap leaching process for cupric oxide ore | |
CN102155261B (en) | Paste combined filling method utilizing solid wastes of mine | |
CN101215976B (en) | Down-hole gangue pump packing system and method | |
WO2019076061A1 (en) | Disposal method for gold mine cyanide tailing paste | |
CN204139227U (en) | Gas mixing pumping drainage type mine sump desilting machine | |
CN101099940A (en) | Kaolin high concentration ore dressing technology | |
CN201738297U (en) | Construction device for filling silt and reclaiming land | |
CN101906793A (en) | Automatic iron sand separation pumping machine | |
CN102432234B (en) | comprehensive treatment method for mud nonferrous metal oxidized ore dressing tailing water residue | |
CN105971605B (en) | A kind of underground mines exploration without waster method | |
CN101912866B (en) | Iron tailing solidifying method | |
CN201275498Y (en) | Preperation equipment for extracting sand for building from mine tailing | |
CN100506391C (en) | Re-separating process for non-ferrous metal tailings | |
CN108167017A (en) | A kind of metal mine consolidated fill method of environmental protection cementitious material | |
CN102775105A (en) | Mine paste filling aggregate prepared from building waste materials and preparation method of mine paste filling aggregate | |
CN108531726A (en) | A kind of Tailings Dam Situ Leaching liquid collecting tunnel mining technique and reaction unit | |
CN110566207A (en) | covering layer full-tailings piling method for open-air to underground non-bottom-pillar sublevel caving method | |
CN202467923U (en) | Continuous stirring and filling device for preparing mining paste by utilizing building wastes | |
CN102976647B (en) | Wet discharge, consolidation and deposition method for tailings | |
Breitenbach | Overview: Tailings disposal and dam construction practices in the 21st century | |
CN207331011U (en) | A kind of Tailings Dam Situ Leaching liquid collecting reaction unit | |
CN111606687A (en) | Tailing dewatering and mining method for sintered brick raw material | |
CN110563296A (en) | mud separation method and system for realizing circulation by using same | |
CN104088664A (en) | Method and system for treating waste water of mine suitable for upward filling and mining |
Legal Events
Date | Code | Title | Description |
---|---|---|---|
C06 | Publication | ||
PB01 | Publication | ||
C10 | Entry into substantive examination | ||
SE01 | Entry into force of request for substantive examination | ||
C14 | Grant of patent or utility model | ||
GR01 | Patent grant | ||
CF01 | Termination of patent right due to non-payment of annual fee | ||
CF01 | Termination of patent right due to non-payment of annual fee |
Granted publication date: 20090701 Termination date: 20160214 |