Prior art keywords
copper pipe
copper
pipe
section
fin
Prior art date
Legal status (The legal status is an assumption and is not a legal conclusion. Google has not performed a legal analysis and makes no representation as to the accuracy of the status listed.)
Active
Application number
CN200710045752A
Other languages
Chinese (zh)
Other versions
CN101190486A (en
Inventor
胡新胜
董顺德
乔高攀
石太智
于林奎
周功兵
王召飞
张一帆
李勇
Current Assignee (The listed assignees may be inaccurate. Google has not performed a legal analysis and makes no representation or warranty as to the accuracy of the list.)
SHANGHAI LONGYANG PRECISION COMPOUND COPPER PIPE CO Ltd
Original Assignee
SHANGHAI LONGYANG PRECISION COMPOUND COPPER PIPE CO Ltd
Priority date (The priority date is an assumption and is not a legal conclusion. Google has not performed a legal analysis and makes no representation as to the accuracy of the date listed.)
Filing date
Publication date
Application filed by SHANGHAI LONGYANG PRECISION COMPOUND COPPER PIPE CO Ltd filed Critical SHANGHAI LONGYANG PRECISION COMPOUND COPPER PIPE CO Ltd
Priority to CN200710045752A priority Critical patent/CN100594090C/en
Publication of CN101190486A publication Critical patent/CN101190486A/en
Application granted granted Critical
Publication of CN100594090C publication Critical patent/CN100594090C/en
Active legal-status Critical Current
Anticipated expiration legal-status Critical

Links

Images

Landscapes

  • Perforating, Stamping-Out Or Severing By Means Other Than Cutting (AREA)
  • Air Conditioning Control Device (AREA)

Abstract

The invention relates to a copper pipe defect repairing technical method, in particular to the defect repairing technical method for an air conditioner heat exchanger copper pipe and a special tool for implementing the method. The technical key point of the invention is that a cutter rod is arranged at the mouth of the copper pipe with defects and is beaten into the copper pipe by an air hammer and passes through the copper pipe; a copper skin of the copper pipe wall connected with the copper pipe is cut off; the gap jacked by the cutter rod is enlarged by joint pliers; part of the copper pipeof a fin exceeding the copper pipe is removed by the joint pliers and the copper skin is kept; a jig is pulled out and the copper pipe is passes through by a steel wire which also sleeves and backwards draws the copper skin; the copper pipe is contracted by the joint pliers and the copper skin is clamped and backwards pulled by a vice till the copper pipe and the copper skin are pulled out together. The invention has the advantages of simpleness and practicability, effectively maintaining the copper pipe with defects and obviously improving the yield of air conditioner heat exchanger.

Description

Air conditioner heat-exchanger brass pipe defect servicing technique method and realize the special implement of this method
Technical field
The present invention relates to a kind of brass pipe defect servicing technique method, particularly air conditioner heat-exchanger brass pipe defect servicing technique method; Also relate to the special implement of realizing this method.
Background technology
At present, air-conditioning producer is when producing heat exchanger, used length " U " type copper pipe (hair fastener pipe) is in case leakage, the linear defectives such as cracking, impurity that scratch occur, whole heat exchanger can be scrapped, cause very big economic loss for air-conditioning producer, air-conditioning producer can transfer to copper pipe manufacturer to this loss, also causes certain loss for copper pipe manufacturer.
Summary of the invention
The first aspect of purpose of the present invention is to propose a kind of air conditioner heat-exchanger brass pipe defect servicing technique method.
Air conditioner heat-exchanger brass pipe defect servicing technique method is characterized in that, may further comprise the steps:
1) detects defective copper pipe;
2) the defective copper pipe that will detect partly disconnects in " U " type and is divided into two sections copper pipes;
3) respectively every section copper pipe is pulled out from fin;
4) new copper pipe is inserted fin;
5) will rise bar and the head assembling of rising use the pneumatic hammer bar that will rise to hit into the described new copper pipe bar that rises.
The invention allows for the method for copper pipe being pulled out fin, promptly before step 3), carry out following steps:
A) a section of described two sections copper pipes is placed on the plastic mattress of workbench; Source of the gas is connected with pneumatic hammer, described pneumatic hammer is connected with connector; Knife bar and blade assembling;
B) described knife bar is placed on the flared end of described one section copper pipe, with described pneumatic hammer with described knife bar hit into described one section copper pipe and will be described one section copper pipe push up and wear to " U " type part, the copper pipe wall of described one section copper pipe cut out one with described one section copper sheet that copper pipe links to each other;
C) at " U " of described one section copper pipe type part place end, with nipper plier the breach that described knife bar ejects is enlarged, on the copper pipe wall of described one section copper pipe, can be clear that the vertical copper bar that is cut out by blade;
D) at " U " of described one section copper pipe type part place end, the outer part copper pipe of fin that will exceed on described one section copper pipe with nipper plier removes, and removes the copper sheet that is cut out by blade;
E) with pulling out tool, iron wire is passed described one section copper pipe, described copper sheet is entangled toward post-tensioning with iron wire from described flared end; Appear at the flared end of described copper pipe until described copper sheet, and exceed the mouth of pipe 10~20cm of described flared end;
F) with nipper plier with described one section copper pipe reducing; Contract in the copper pipe wall of described one section copper pipe, littler than described fin internal diameter, the defective part of described copper pipe contracts in all;
G) with the tiger pincers described copper sheet is clamped toward post-tensioning, be drawn out fin together until described one section copper pipe and described copper sheet.
Further, after step 5), use the heat exchanger comb that described fin comb is flat.
Further, the air-conditioning heat-exchange tube is put into water, detect defective copper pipe with the method for inflating bubbling.
The special implement that is to propose to realize said method on the other hand of purpose of the present invention.
Realize the special implement of above-mentioned air conditioner heat-exchanger brass pipe defect servicing technique method, comprise described connector, blade and knife bar is characterized in that: a headband of described connector has a blind hole that is used to entangle described knife bar.
Described blade comprises two blade body, an installing handle; Described two blade body are set in parallel in of described installing handle, and described two parallel blade and described installing handles are integrative-structure.
The internal diameter size of described knife bar external diameter and described copper pipe matches, and the side that described knife bar is has an installing handle blind hole that is used to install blade.
Method for maintaining of the present invention detects defective copper pipe earlier, destroys closely cooperating between copper pipe and the fin then, copper pipe is pulled out from fin again, is installed into new copper pipe at last.The present invention is simple and practical, can obviously improve the yield rate of heat exchanger of air condition so that defective copper pipe is effectively keeped in repair.Special implement of the present invention is used for method for maintaining of the present invention, has improved the efficient of maintenance greatly.
Description of drawings
Fig. 1 is the structural representation of existing connector.
Fig. 2 is the structural representation of connector of the present invention.
Fig. 3 is the structural representation of blade of the present invention.
Fig. 4 is the side-looking structural representation of Fig. 3.
Fig. 5 is the structural representation of knife bar of the present invention.
Fig. 6 is the schematic diagram that copper pipe is worn on the knife bar top.
Fig. 7 is the schematic diagram that iron wire is pulled out copper sheet.
The specific embodiment
For technological means, creation characteristic that the present invention is realized, reach purpose and effect is easy to understand, below in conjunction with the specific embodiment, further set forth the present invention.
Air conditioner heat-exchanger brass pipe defect servicing technique method, heat exchanger of air condition at first that defectiveness is to be repaired is put into water, detects defective copper pipe with the method for inflating bubbling.
With cutting nippers or diagonal cutting pliers copper pipe " U " type is partly cut off; " U " type copper pipe (hair fastener pipe) just has been divided into two sections like this.Also can cut out copper sheet earlier, cut off " U " type part of copper pipe again.
Then, one section copper pipe 4 wherein is placed on the plastic mattress of workbench.Source of the gas is connected with pneumatic hammer, pneumatic hammer is connected with connector 1; Knife bar 3 and blade 2 assemblings; The bar that will rise assembles with the head that rises; Perform the preparation of repairing.
Existing connector is a tip as shown in Figure 1.As shown in Figure 2, connector 1 of the present invention is not a tip, and has a blind hole 11, and blind hole 11 is used to entangle knife bar 3.Referring to Fig. 3,4, blade 2 comprises two parallel blade body 21,22, one installing handles 23.Two parallel blade body 21,22 are arranged on of installing handle 23, and two parallel blade 21,22 and installing handles 23 are integrative-structure.Referring to Fig. 5, the internal diameter size of the external diameter of knife bar 3 and copper pipe 4 matches, and a side of one of knife bar 3 has a blind hole 31, and blind hole 31 is used to install the installing handle 23 of blade 2.Knife bar 3 should long enough, is beneficial under the driving of pneumatic hammer blade 2 shifted onto copper pipe 4 bottoms.
Referring to Fig. 6.Knife bar 3 is placed on the flared end 41 of copper pipe 4, and one that specifically knife bar 3 is equipped with blade 2 is placed on flared end 41.Knife bar 3 is hit copper pipe 4 and copper pipe 4 is pushed up through " U " type part the copper pipe wall of copper pipe 4 a cutting-out copper sheet 40 that links to each other with copper pipe 4 (copper sheet 40 width are identical with blade 2 width) with pneumatic hammer.This step is actually from copper pipe 4 upper edge axis directions and crosses out one, and will draw the copper pipe wall.After like this this copper sheet 40 being pulled out, copper pipe wall two side sections will be inwardly recessed, occurs becoming flexible, and is convenient to whole copper pipe 4 pulled out.
The breach that described knife bar 3 ejects is enlarged at copper pipe " U " type part place end 42 with nipper plier, on the copper pipe wall of copper pipe 4, can be clear that the part of being cut by blade 2.Make the iron wire 5 that can make things convenient for the back like this and pull out the copper sheet that blade 2 is downcut.
Remove at the part copper pipe that copper pipe " U " type part place end 42 will exceed the fin 44 on the copper pipe 4 with nipper plier, remove and cut the copper sheet 40 at place by blade.Can be clear that the copper sheet 40 that is cut after removing.The purpose of this step is that by external diameter is bigger than fin 44 internal diameters the part copper pipe that exceeds the fin 44 on the copper pipe 4 is removed, and eliminates the obstruction of next step being pulled out copper sheet.Stay the copper sheet 40 that exceeds fin 44, made things convenient for the past post-tensioning of the copper sheet of back.
Referring to Fig. 7.With pulling out tool, iron wire 5 is passed copper pipe 4 from copper pipe flared end 41, with iron wire 5 copper sheet 40 is entangled toward post-tensioning; Appear at the flared end 41 of described copper pipe until copper sheet 40, and exceed described copper pipe 4 mouths of pipe 10~20cm.After copper sheet 40 was pulled out, the contact-making surface of copper pipe wall and fin 44 inwalls was just littler, and the frictional force that can produce is also littler, had made things convenient for the pulling out of whole copper pipe 4 of back.After copper sheet 40 pulled out, copper pipe wall and fin 44 inwalls had become matched in clearance by tight fit, be beneficial to next step defective copper pipe 4 is all pulled out.
With nipper plier with copper pipe 4 reducings; Contract in the copper pipe wall, littler than fin 44 internal diameters, copper pipe 4 defective parts contract in all.Like this, the contact-making surface of copper pipe wall and fin inwall is littler, and the frictional force that can produce is also littler.Can protect the aluminium foil on fin 44 inwalls like this, not make aluminium foil produce distortion as far as possible, prevent to influence the coefficient of heat transfer of interchanger.
With the tiger pincers described copper sheet 40 is clamped toward post-tensioning, be drawn out together until copper pipe 4 and described copper sheet 40.The plumber's preface that rises is arranged when producing heat exchanger of air condition---two sections straight line portion external diameters of U type pipe being risen greatly, make it closely to contact with peripheral aluminium foil, is interference fit, is convenient to heat exchange.So copper pipe 4 is difficult for directly pulling out, and directly draws copper pipe to destroy aluminium foil easily.So this step adopts the method for drawing copper sheet 40, pulls out whole copper pipe.
Another section copper pipe is also extracted out from fin by above-mentioned steps.
New " U " type copper pipe is inserted in two fins 44.Use the pneumatic hammer bar that will rise to hit, make it to present interference fit with aluminium foil into the new copper pipe pipe that rises.Use at last that the heat exchanger comb is flat with described fin comb, reinstatement gets final product.
Certainly, the present invention is not limited only to keep in repair air conditioner heat-exchanger brass pipe, is used for the maintenance of finned copper pipe of the heat exchanger of other aspect, also can use the present invention.
More than show and described basic principle of the present invention, principal character and advantage of the present invention.The technical staff of the industry should understand; the present invention is not restricted to the described embodiments; that describes in the foregoing description and the specification just illustrates principle of the present invention; the present invention also has various changes and modifications without departing from the spirit and scope of the present invention, and these changes and improvements all fall in the claimed scope of the invention.The claimed scope of the present invention is defined by appending claims and equivalent thereof.

Claims (3)

1, air conditioner heat-exchanger brass pipe defect servicing technique method is characterized in that, may further comprise the steps:
1) detects defective copper pipe;
2) the defective copper pipe that will detect partly disconnects in " U " type and is divided into two sections copper pipes;
3) respectively every section copper pipe is pulled out from fin;
4) new copper pipe is inserted fin;
5) will rise bar and the head assembling of rising use the pneumatic hammer bar that will rise to hit into the described new copper pipe pipe that rises;
Wherein, before step 3), carry out following steps:
A) a section of described two sections copper pipes is placed on the plastic mattress of workbench; Source of the gas is connected with pneumatic hammer, described pneumatic hammer is connected with connector; Knife bar and blade assembling;
B) described knife bar is placed on the flared end of described one section copper pipe, with described pneumatic hammer with described knife bar hit into described one section copper pipe and will be described one section copper pipe push up and wear to " U " type part, the copper pipe wall of described one section copper pipe cut out one with described one section copper sheet that copper pipe links to each other;
C) at " U " of described one section copper pipe type part place end, with nipper plier the breach that described knife bar ejects is enlarged, on the copper pipe wall of described one section copper pipe, can be clear that the vertical copper bar that is cut out by blade;
D) at " U " of described one section copper pipe type part place end, the outer part copper pipe of fin that will exceed on described one section copper pipe with nipper plier removes, and keeps the copper sheet that is cut out by blade;
E) with pulling out tool, iron wire is passed described one section copper pipe, described copper sheet is entangled toward post-tensioning with iron wire from described flared end; Appear at the flared end of described copper pipe until described copper sheet, and exceed the mouth of pipe 10~20cm of described flared end;
F) with nipper plier with described one section copper pipe reducing; Contract in the copper pipe wall of described one section copper pipe, littler than described fin internal diameter, the defective part of described copper pipe contracts in all;
G) with the tiger pincers described copper sheet is clamped toward post-tensioning, be drawn out fin together until described one section copper pipe and described copper sheet.
2, air conditioner heat-exchanger brass pipe defect servicing technique method according to claim 1 is characterized in that, uses the heat exchanger comb that described fin comb is flat after step 5).
3, air conditioner heat-exchanger brass pipe defect servicing technique method according to claim 1 is characterized in that: heat-exchange tube is put into water, detect defective copper pipe with the method for inflating bubbling.
CN200710045752A 2007-09-10 2007-09-10 Air conditioner heat-exchanger brass pipe defect servicing technique method and special-purpose apparatus for implementing the method Active CN100594090C (en)

Priority Applications (1)

Application Number Priority Date Filing Date Title
CN200710045752A CN100594090C (en) 2007-09-10 2007-09-10 Air conditioner heat-exchanger brass pipe defect servicing technique method and special-purpose apparatus for implementing the method

Applications Claiming Priority (1)

Application Number Priority Date Filing Date Title
CN200710045752A CN100594090C (en) 2007-09-10 2007-09-10 Air conditioner heat-exchanger brass pipe defect servicing technique method and special-purpose apparatus for implementing the method

Publications (2)

Publication Number Publication Date
CN101190486A CN101190486A (en) 2008-06-04
CN100594090C true CN100594090C (en) 2010-03-17

Family

ID=39485765

Family Applications (1)

Application Number Title Priority Date Filing Date
CN200710045752A Active CN100594090C (en) 2007-09-10 2007-09-10 Air conditioner heat-exchanger brass pipe defect servicing technique method and special-purpose apparatus for implementing the method

Country Status (1)

Country Link
CN (1) CN100594090C (en)

Families Citing this family (3)

* Cited by examiner, † Cited by third party
Publication number Priority date Publication date Assignee Title
CN101767260A (en) * 2008-12-30 2010-07-07 湖北双环科技股份有限公司 Welding method for overhaul of furnace chamber heat exchange tube
CN102225501A (en) * 2011-03-24 2011-10-26 中色奥博特铜铝业有限公司 Method and device for repairing copper pipe component on heat exchanger of air conditioner
CN104588961A (en) * 2014-11-25 2015-05-06 麦克维尔空调制冷(武汉)有限公司 Heat exchanger three-tube plate expanding and inner leaking repairing method

Citations (1)

* Cited by examiner, † Cited by third party
Publication number Priority date Publication date Assignee Title
US3628246A (en) * 1968-09-06 1971-12-21 Carrier Corp Apparatus for tube removal

Patent Citations (1)

* Cited by examiner, † Cited by third party
Publication number Priority date Publication date Assignee Title
US3628246A (en) * 1968-09-06 1971-12-21 Carrier Corp Apparatus for tube removal

Non-Patent Citations (8)

* Cited by examiner, † Cited by third party
Title
50m~3/h制氧机冷凝蒸发器的检修. 昌子林.深冷技术,第1987年卷第2期. 1987
50m~3/h制氧机冷凝蒸发器的检修. 昌子林.深冷技术,第1987年卷第2期. 1987 *
热交换器管泄漏的衬管修复工艺. 周立.管道技术与设备,第2005年卷第4期. 2005
热交换器管泄漏的衬管修复工艺. 周立.管道技术与设备,第2005年卷第4期. 2005 *
空调器修理从入门到精通. 陈鹏飞,宋友山,105-106,国防工业出版社. 2003
空调器修理从入门到精通. 陈鹏飞,宋友山,105-106,国防工业出版社. 2003 *
蒸发器和冷凝器用铜管质量缺陷的解决对策. 向功平.矿业研究与开发,第17卷第2期. 1997
蒸发器和冷凝器用铜管质量缺陷的解决对策. 向功平.矿业研究与开发,第17卷第2期. 1997 *

Also Published As

Publication number Publication date
CN101190486A (en) 2008-06-04

Similar Documents

Publication Publication Date Title
US20050235473A1 (en) Removing method of tube
CN100594090C (en) Air conditioner heat-exchanger brass pipe defect servicing technique method and special-purpose apparatus for implementing the method
CN101623738B (en) Clamping device of pipe expander
JPH0230339A (en) Two-stage impact type bell section forming device
CN208408139U (en) Using the control mechanism of double heating inductor push-making angle fittings
US5502997A (en) Gripper and mandrel assembly for tube bender
CN108672529A (en) Using the control mechanism and control processing method of double heating inductor push-making angle fittings
JP6398128B2 (en) Manufacturing method and apparatus of heat exchanger
CN108772448A (en) Prepare the bending machine of U-tube
CN210586793U (en) Fixed frock of oil pipe reaming shaping
CN111571111B (en) Heat exchange tube maintenance method
CN102225501A (en) Method and device for repairing copper pipe component on heat exchanger of air conditioner
CN111633047A (en) Method and device for reducing wall and extending cluster steel wire core rod and metal pipe
CN202291675U (en) Pipe head reshaping cutter
US6654996B1 (en) Tube remover and method for axially removing a metal tube
JP4660603B2 (en) Extubation jig and extubation method
JP3836082B2 (en) Branch diameter reduction method
CN210818278U (en) Grabbing mechanism of clamp
CN210063467U (en) Single-hand needle tube-penetrating pressure point forming machine
CN216857858U (en) Full-automatic joint angle bending equipment
CN203936864U (en) The U-shaped pipe overshot of finned heat exchanger
CN218591524U (en) Bending head for square tube bending machine
CN216883713U (en) Pagoda joint dismounting tool
JPH08118252A (en) Tube drawing method and tube drawing tool
JP4800261B2 (en) Heat exchanger tube repair method for equipment cooling water heat exchanger

Legal Events

Date Code Title Description
C06 Publication
PB01 Publication
C10 Entry into substantive examination
SE01 Entry into force of request for substantive examination
C14 Grant of patent or utility model
GR01 Patent grant
PE01 Entry into force of the registration of the contract for pledge of patent right
PE01 Entry into force of the registration of the contract for pledge of patent right

Denomination of invention: Air conditioner heat-exchanger brass pipe defect servicing technique method and special-purpose apparatus for implementing the method

Effective date of registration: 20171204

Granted publication date: 20100317

Pledgee: Zhengzhou Branch of China Minsheng Bank Co.,Ltd.

Pledgor: GOLDEN DRAGON PRECISE COPPER TUBE Group Inc.|SHANGHAI LONGYANG PRECISION COMPOUND COPPER PIPE Co.,Ltd.

Registration number: 2017990001110

PC01 Cancellation of the registration of the contract for pledge of patent right

Date of cancellation: 20190814

Granted publication date: 20100317

Pledgee: Zhengzhou Branch of China Minsheng Bank Co.,Ltd.

Pledgor: SHANGHAI LONGYANG PRECISION COMPOUND COPPER PIPE Co.,Ltd.

Registration number: 2017990001110

PC01 Cancellation of the registration of the contract for pledge of patent right
PE01 Entry into force of the registration of the contract for pledge of patent right

Denomination of invention: Air conditioner heat-exchanger brass pipe defect servicing technique method and special-purpose apparatus for implementing the method

Effective date of registration: 20190822

Granted publication date: 20100317

Pledgee: Zhengzhou Branch of China Minsheng Bank Co.,Ltd.

Pledgor: SHANGHAI LONGYANG PRECISION COMPOUND COPPER PIPE Co.,Ltd.

Registration number: Y2019990000123

PE01 Entry into force of the registration of the contract for pledge of patent right
PC01 Cancellation of the registration of the contract for pledge of patent right

Date of cancellation: 20220729

Granted publication date: 20100317

Pledgee: Zhengzhou Branch of China Minsheng Bank Co.,Ltd.

Pledgor: SHANGHAI LONGYANG PRECISION COMPOUND COPPER PIPE Co.,Ltd.

Registration number: Y2019990000123

PC01 Cancellation of the registration of the contract for pledge of patent right