CN100587166C - External prestress strengthening method for prestressed concrete box-beam bridge - Google Patents

External prestress strengthening method for prestressed concrete box-beam bridge Download PDF

Info

Publication number
CN100587166C
CN100587166C CN200710169033A CN200710169033A CN100587166C CN 100587166 C CN100587166 C CN 100587166C CN 200710169033 A CN200710169033 A CN 200710169033A CN 200710169033 A CN200710169033 A CN 200710169033A CN 100587166 C CN100587166 C CN 100587166C
Authority
CN
China
Prior art keywords
bundle
external
stress
anchoring
short
Prior art date
Legal status (The legal status is an assumption and is not a legal conclusion. Google has not performed a legal analysis and makes no representation as to the accuracy of the status listed.)
Active
Application number
CN200710169033A
Other languages
Chinese (zh)
Other versions
CN101230562A (en
Inventor
汪正兴
梅秀道
李星新
汪双炎
王戒躁
童智洋
郑平伟
刘德煜
Current Assignee (The listed assignees may be inaccurate. Google has not performed a legal analysis and makes no representation or warranty as to the accuracy of the list.)
China Railway Major Bridge Engineering Group Co Ltd MBEC
China Railway Bridge Science Research Institute Ltd
Original Assignee
China Railway Major Bridge Engineering Co Ltd
China Railway Major Bridge Engineering Group Co Ltd MBEC
Priority date (The priority date is an assumption and is not a legal conclusion. Google has not performed a legal analysis and makes no representation as to the accuracy of the date listed.)
Filing date
Publication date
Application filed by China Railway Major Bridge Engineering Co Ltd, China Railway Major Bridge Engineering Group Co Ltd MBEC filed Critical China Railway Major Bridge Engineering Co Ltd
Priority to CN200710169033A priority Critical patent/CN100587166C/en
Publication of CN101230562A publication Critical patent/CN101230562A/en
Application granted granted Critical
Publication of CN100587166C publication Critical patent/CN100587166C/en
Active legal-status Critical Current
Anticipated expiration legal-status Critical

Links

Images

Abstract

The invention provides a reinforcing method for the prestressing force in vitro, and the reinforcing method aims at a prestressed concrete box girder bridge, and adopts a space steel truss installed inside a box girder as the anchorage and steering configuration of a prestressing force beam in vitro; the prestressing force beam in vitro is distributed under the condition of considering the damnification of the structure based on optimizing the calculating result, and adopts a beam distribution mode of combining a full-length beam and a fulcrum crest slab short beam, wherein, the crest slab short beam can be bended to the lower boom of the steel truss to be anchored to provide a ventral shield with pre-shearing force according to the split situation; the steel truss is distributed accordingto the requirements of anchorage and steering of the prestressing force beam in vitro, and a girder grillage is respectively arranged in the box girder firmly close to the ventral shield side; each merithal is provided with a horizontal bracing to provide the anchorage and steering configuration of the prestressing force beam in vitro, and at the same time, the rigidity and the shearing resistance bearing capacity of the ventral shield of the concrete box girder are enhanced; the steel truss and the box girder are connected into a whole by adopting a plant ribbon mode, thereby ensuring the dosage and the distribution of the prestressing force beam in vitro to be more flexible, the direction to be stronger and the distribution efficiency of the prestressing force beam in vitro to be high.

Description

A kind of external prestress strengthening method of prestressed concrete box-beam bridge
Technical field
The present invention relates to the reinforcement means of the common disease of a kind of prestressed concrete beam bridge, the external prestressing strengthening that is particularly useful for common diseases such as the large-span prestressed concrete beam of box section, firm structure and T structure bridge, belong to the fixedly field of reinforcement of structure such as bridge, specifically relate to a kind of external prestress strengthening method at diseases such as downwarp in the prestressed concrete box tee section spanning, web crackings.
Technical background
Has the favor of striding stressed approaching, advantage is subjected to world's bridge engineering circle such as system stiffness big, the driving steady, the later maintenance workload is little of footpath wide accommodation, construction state and operation state owing to prestressed concrete box-beam bridge, obtained extensive use in countries in the world since the sixties in 20th century, maximum span has reached 330m.Yet in this bridge type development, the long-term shrinkage and creep influence that causes owing to high-level compressive stress under the dead load, the construction quality of structure are uneven, overload effect, the effect of local temperature stress and the high-stress state concrete fatigue down of the loss of prestressing force effective stress, carload or the like reason, cause both at home and abroad the disease cases such as span centre downwarp, web cracking about the prestressed concrete continuous box girder bridge quite general; Stride greatly downwarp in the prestressed concrete continuous box girder spanning of footpath and web cracking the two be association, in case take place, then reciprocal causation forms vicious circle, has caused the linear influence driving even exist the accident potential of caving in to become unsafe bridge of having some setbacks of bridge.And these similar bridge defects are reinforced targetedly, can prolong the service life of bridge construction, produce direct economic results in society.
Have the reinforcing of comparative maturity to calculate and use different with the external prestressing strengthening of simply supported girder bridge, the external prestress strengthening method of bridge complex structures such as continuous beam is still immature.Way the most close with the present invention in existing external prestressing strengthening technology is for providing the external pre-stress bundle anchoring and turn to reinforcement means at inner concreting diaphragm of case beam and tooth plate, as the South Sea, Guangdong Jinsha bridge, the reinforcement means of engineerings such as the Yellow River, Sanmenxia Gorge highway bridge, be at the inner concreting tooth plate of case beam, external pre-stress bundle is anchoring and stretch-draw on tooth plate, all pass to case beam base plate or top board and tooth plate is stressed by the bar planting of shearing groove, turning to by build powerful concrete diaphragm in case beam inside of external pre-stress bundle realizes, diaphragm needs the turning point setting at external pre-stress bundle, by bar planting mode and case back plate, base plate is connected with web.The defective of this method is: 1. because the inconsistent of shrinkage and creep makes that new-old concrete co-operation effect is undesirable; 2. in order to satisfy local anchoring and to turn to the requirement of stress, the anchoring tooth plate is with to turn to diaphragm relative powerful, and case beam built-in function space is limited, the difficulty of construction of a large amount of concreting is big, increased burden, and the strengthening construction cycle is long, engineering quantity is big, need interruption of bridge deck traffic to original structure; 3. the present bundle mode of joining is striden this three of web shearing resistance with pier top hogging moment, span centre positive bending moment and 1/4 and is equal to and treats, and the cross section property minimum of spaning middle section, positive bending moment is little a lot of with respect to pier top hogging moment, shearing is zero substantially, its external bundle consumption is controlled by the spaning middle section compressive stress, far can not reach the requirement of balance pier top hogging moment; 4. because anchoring and turn to the restriction of factors such as constructing local stress and original structure concrete strength to make that the consumption of external bundle is also limited.Above factor makes external bundle not reach desirable consolidation effect, and therefore domestic many bridge blocks have to take the limit for tonnage measure.
Summary of the invention
The purpose of this invention is to provide a kind of external prestress strengthening method at the common disease of prestressed concrete box-beam bridge, be optimized by the layout of analytic method, adopt the Steel Space Truss be installed in the case beam as the anchoring of external pre-stress bundle with turn to structure external pre-stress bundle.External pre-stress bundle consideration structural damage situation on the basis of optimizing result of calculation is arranged, the cloth bundle mode that adopts the short bundle of elongated bundle and fulcrum top board to combine, the short bundle of top board can according under the web cracking situation curved to the anchoring of steel truss lower edge to provide web pre-shearing; Steel truss is arranged according to turning to the anchoring needs of external pre-stress bundle, the steel truss rod member adopts section steel manufacture, in the case beam, respectively arrange a truss structure near the web side, each internode is provided with sway bracing, so that turning to and anchoring structure of external pre-stress bundle to be provided, concrete box web rigidity and shear-carrying capacity have been strengthened simultaneously; Steel truss and case beam adopt the bar planting mode to be linked to be integral body.Owing to adopt steel truss as the anchoring of external pre-stress bundle with turn to structure, make external pre-stress bundle consumption and arrange more flexibly, specific aim is stronger, external pre-stress bundle layout efficient height.
Technical scheme of the present invention is achieved in that
Described external prestressing strengthening technology is optimized layout according to influencing the lineation opinion to external pre-stress bundle.Because external pre-stress bundle is only got in touch with original structure at anchor point and turning point, so can adopt the mode of nodal forces to analyze the effect of external pre-stress bundle to original structure.The variation that external pre-stress bundle is arranged can be simulated by nodal forces different active positions structurally, adopt influencing line numerical value and just can drawing the action effect of nodal forces to structure of structure, the external bundle layout of finding out maximum action effect correspondence is The optimum layout.Optimizing the result shows: 1. there is an optimal value in the layout of fulcrum top board bundle; 2. there is an optimal value in the layout of striding the base plate bundle in; 3. end bay base plate bundle is unfavorable to the main span span centre; 4. the web bundle is little to the mid-span deflection contribution, but favourable to the web shearing resistance in its coverage; 5. there is an optimal value in the layout of full UNICOM head's bundle.Therefore, the layout of external pre-stress bundle is wanted targetedly, and top board bundle, base plate bundle will be raised the efficiency to obtain maximum acting force arm away from the girder centre of form as far as possible, and the web bundle then will provide enough pre-shearings at the web fracture area.
Described external prestressing strengthening technology, the employing steel truss is as the external pre-stress bundle anchoring and turn to structure.Steel truss can make full use of the Materials with High Strength characteristic of steel work, and local anchorage stress is handled easily, reduces difficulty of construction in the case; The flexible arrangement that is set to external pre-stress bundle of steel truss is provided convenience, and makes the layout of external pre-stress bundle more to consider the structural damage situation and needn't be limited by the processing of local structure; The invar truss is in light weight, and only only need arrange usually in web cracking scope, and is little to the side effect of original structure; Sway bracing is set between longitudiual truss, strengthens the globality of truss, for the anchoring of external pre-stress bundle provides the space.Steel truss can adopt the trifle spacing with the joint face of increase with the case beam, guarantees the reliable delivery of external prestressing.
Described external prestressing strengthening technology can be according to the analysis result of above-mentioned optimization cloth bundle, the cloth bundle mode that adopts the short bundle of elongated bundle and fulcrum top board to combine.Elongated bundle can be regarded the combination of the short bundle of top board, the short bundle of web and the short bundle of base plate as, turns to by optimum turning point and can obtain best consolidation effect; In addition, introduced the compressive stress deposit in the elongated Shu Zailiang body, for short layout of restrainting provides condition, and long short bundle is for providing the compressive stress deposit than short short bundle.Be balance pier top hogging moment, need to adopt the short bundle of top board, the short bundle of top board should be arranged in the last turning point of elongated bundle, thereby utilize tensile stress behind the compressive stress deposit balance anchor of elongated bundle, the short bundle of top board can be in the top board anchoring, also curved under the needs that can reinforce in conjunction with web at web cracking place to base plate, in the anchoring of truss lower edge.The short bundle of elongated bundle and top board can disperse anchoring and turn to, and promptly the processing of steel truss and case beam joint construction is convenient in anchoring and turning on vertically different panel points successively.Adopt the cloth bundle mode of " many of tuftlets ", help eliminating tensile stress behind the anchor, and the moment of flexure that this dispersed placement external pre-stress bundle forms meets the shape that fulcrum hogging moment envelope diagram gradually changes, and also can better cover the web fracture area that needs reinforcement, and more helps the reinforcing of web.
Advantage of the present invention:
1. can adopt influences the lineation opinion various external pre-stress bundle arrangement forms is carried out analytical optimization, takes all factors into consideration to optimize the result and the structural damage situation is arranged external pre-stress bundle, the efficient height and the flexible arrangement of external pre-stress bundle.
2. adopt the steel truss be connected with the case beam as the anchoring of external pre-stress bundle with turn to structure, make external pre-stress bundle and to turn to according to the needs anchoring of structural calculation, by using Materials with High Strength and only need being arranged in the web cracking scope usually, alleviated side effect greatly, strengthened concrete box web rigidity and shear-carrying capacity simultaneously original structure.
3. the arrangement that adopts the short bundle of elongated bundle and top board to combine is reinforced targetedly, can arrange external pre-stress bundle according to the degree of impairment of structure, reinforces the restriction that consumption is not subjected to local structure.
4. all strengthening constructions all carry out in case beam inside, need not to dig the top board concrete perfusion, can uninterrupted traffic, or carry out the temporary transient traffic control of part, and the economic loss that causes is few, and social influence is little.
Description of drawings
Fig. 1 is that the vertical bridge of the embodiment of the invention is to the general arrangement schematic diagram;
Fig. 2 is that the steel truss structure is indulged bridge to arranging schematic diagram in the embodiment of the invention;
Fig. 3 is that external pre-stress bundle is indulged bridge to arranging schematic diagram in the embodiment of the invention;
Fig. 4 is the elongated bundle enlarged diagram of external pre-stress bundle in the embodiment of the invention;
Fig. 5 is the short bundle of an external pre-stress bundle top board enlarged diagram in the embodiment of the invention;
Fig. 6 be Fig. 1 external pre-stress bundle on steel truss A anchoring and turn to the layout enlarged diagram;
Fig. 7 is the fulcrum cross sectional representation in the embodiment of the invention;
Fig. 8 is the main span span centre cross sectional representation in the embodiment of the invention;
Fig. 9 is a steel truss layout place cross sectional representation in the embodiment of the invention.
The specific embodiment
The invention will be further described below in conjunction with embodiment and accompanying drawing, and this embodiment is the prestressed concrete continuous box girder bridge of a span for (65.425+126+65.425) m.
Fig. 1 is that the vertical bridge of the embodiment of the invention is to the general arrangement schematic diagram.Adopt plane leverage finite element program to calculate the nodal forces of being concerned about the cross section mechanics parameter at the concrete structure in the present embodiment and influence line, using this influences the The optimum layout that line is obtained elongated bundle of external prestressing and the short bundle of external prestressing top board, and the stressing conditions of consideration structure is determined the final arrangement form of external prestressing; Fig. 3 is that the vertical bridge of external pre-stress bundle is to arranging schematic diagram in the embodiment of the invention, and Fig. 4 is the elongated bundle enlarged diagram of external pre-stress bundle in the embodiment of the invention, and Fig. 5 is the short bundle of an external pre-stress bundle top board enlarged diagram in the embodiment of the invention.Stride the bearing capacity restriction of spaning middle section in the consumption basis of the elongated bundle of external prestressing wherein and determine, afterwards, the reinforcing amount that deducts the elongated bundle of external prestressing according to the definite total reinforcing amount of fulcrum top board hogging moment is determined the short consumption of restrainting of external prestressing top board.Fig. 2 is that the steel truss structure is indulged bridge to arranging schematic diagram in the embodiment of the invention.According to turning to and the anchoring needs of the The optimum layout form of external prestressing, consider the web degree of impairment of structure, determine the steel truss inner vertically arrangement form of original structure case beam in an embodiment, the internode of truss is got the active force of little internode distance with the dispersion external pre-stress bundle apart from according to the anchoring of external prestressing with turn to the needs that the joint construction of needs, truss and concrete box girder handles and the convenience of case beam case chamber interior construction to be provided with as far as possible when meeting above the requirement.
Fig. 6 be Fig. 1 external pre-stress bundle on steel truss anchoring and turn to the layout enlarged diagram, i.e. external prestressing turning on steel truss with anchoring and in vertical layout of original structure case beam case chamber interior.Steel truss upper chord 3 is connected by steel truss web 5 with steel truss lower chord 4, winding up by steel truss is connected steel truss upper chord 3 with case back plate joint construction 6 with case back plate 1, steel truss lower chord 4 is connected with case beam base plate 2 with case beam base plate joint construction 7 by the steel truss lower edge; When elongated bunchy top plate portion 8 was elongated bundle, it turned on steel truss upper chord 3; When elongated bunchy top plate portion 8 is the short bundle of top board, if the short bundle of external prestressing top board does not need to bend down then directly to be anchored on the steel truss upper chord 3, if it is curved down that the short bundle of top board needs, then by turning to back anchoring on steel truss lower chord 4 on the steel truss upper chord 3, the short corset plate portion 11 of top board has remedied common corset plate portion 10 disappearance herein, has improved the shear-carrying capacity of web; Elongated bundle different node on steel truss upper chord 3 and steel truss lower chord 4 disperses to turn to, the short bundle of top board different node on steel truss upper chord 3 and steel truss lower chord 4 disperses anchoring and turns to, and alleviated wind up intractability with case back plate joint construction 6 and steel truss lower edge and case beam base plate joint construction 7 of steel truss.
Fig. 7 is the fulcrum cross sectional representation in the embodiment of the invention.Elongated bundle 8 ' of external prestressing and external prestressing top board weak point bundle 8 " in the case beam, bore a hole on the pier diaphragm 12 and pass through; the position of perforation is as far as possible near case back plate 1 lower edge; the elongated bundle 8 ' of external prestressing restraints 8 with the external prestressing top board is short like this " and can obtain maximum acting force arm, improve the efficient of external pre-stress bundle.
Fig. 8 is the main span span centre cross sectional representation in the embodiment of the invention.The elongated bundle 9 ' of external prestressing is as far as possible near case beam base plate 2 upper limbs, and the elongated bundle of external prestressing can be obtained maximum acting force arm like this, improves the efficient of external bundle.
Fig. 9 is a steel truss layout place cross sectional representation in the embodiment of the invention, transverse truss 13 connects two Pin longitudiual truss 14, last integral node plate 15 connects transverse truss 13 and case back plates 1, on the last integral node plate 15 perforation for external pre-stress bundle pass through, anchoring; Following integral node plate 16 connects transverse truss 13 and case beam base plates 2, on the following integral node plate 16 perforation for external pre-stress bundle by, anchoring; Last integral node plate 15 laterally all is connected by the bar planting mode with the case beam in whole case beam camber with following integral node plate 16, and contact area is big, but the bar planting position is many, and being connected of reliable longitudiual truss 14 and concrete box girder is provided; Go up simultaneously integral node plate 15 and perforation on the following integral node plate 16 and can be used for locating external pre-stress bundle, handle with local anchoring structure processing by the structure of putting more energy into and also have for the external pre-stress bundle damping, turn to and the anchoring function.

Claims (2)

1. the external prestress strengthening method of a prestressed concrete box-beam bridge is characterized in that:
Employing is installed in Steel Space Truss in the case beam as the anchoring of external pre-stress bundle with turn to structure, steel truss is according to the needs with anchoring of turning to of external pre-stress bundle, being arranged in external pre-stress bundle along vertical bridge to segmentation need turn to and anchoring, and the zone of web cracking, its chord member that winds up is connected with case back plate by last integral node plate along direction across bridge, its lower edge chord member is connected with case beam base plate by following integral node plate, last integral node plate is bored a hole with the location external pre-stress bundle with following integral node plate, handle and the damping of local anchoring structure processing realization external pre-stress bundle by the structure of putting more energy into, turn to and the anchoring function, in the case beam, respectively arrange a Pin longitudiual truss near the web side, sway bracing is set between longitudiual truss, strengthen the globality of truss, for the anchoring of external pre-stress bundle provides the space;
The cloth bundle mode that adopts the short bundle of elongated bundle of external prestressing and fulcrum top board to combine, the elongated bundle of external prestressing, its end anchorage is on the end diaphragm of original box-beam structure, the case chamber interior by steel truss wind up or lower edge repeatedly turns to, make the elongated bundle of external prestressing be arranged in the top board lower edge near the fulcrum, near spaning middle section, be arranged in the base plate upper limb, provide the compressive stress deposit for short bundle in the elongated like this Shu Zailiang body, for short layout of restrainting provides condition, and long short bundle is for providing the compressive stress deposit than short short bundle; Be balance pier top hogging moment, adopt the short bundle of external prestressing top board, two ends are anchored in the steel truss node that winds up, and pass the fulcrum diaphragm along case back plate lower edge, the short bundle of top board should be arranged in the last turning point of elongated bundle, thereby utilize tensile stress behind the compressive stress deposit balance anchor of elongated bundle, the short bundle of top board is directly in the truss anchoring of winding up.
2. the external prestress strengthening method of prestressed concrete box-beam bridge according to claim 1 is characterized in that the integral node plate laterally all is connected by the bar planting mode with the case beam in whole case beam camber with following integral node plate.
CN200710169033A 2007-12-26 2007-12-26 External prestress strengthening method for prestressed concrete box-beam bridge Active CN100587166C (en)

Priority Applications (1)

Application Number Priority Date Filing Date Title
CN200710169033A CN100587166C (en) 2007-12-26 2007-12-26 External prestress strengthening method for prestressed concrete box-beam bridge

Applications Claiming Priority (1)

Application Number Priority Date Filing Date Title
CN200710169033A CN100587166C (en) 2007-12-26 2007-12-26 External prestress strengthening method for prestressed concrete box-beam bridge

Publications (2)

Publication Number Publication Date
CN101230562A CN101230562A (en) 2008-07-30
CN100587166C true CN100587166C (en) 2010-02-03

Family

ID=39897346

Family Applications (1)

Application Number Title Priority Date Filing Date
CN200710169033A Active CN100587166C (en) 2007-12-26 2007-12-26 External prestress strengthening method for prestressed concrete box-beam bridge

Country Status (1)

Country Link
CN (1) CN100587166C (en)

Families Citing this family (12)

* Cited by examiner, † Cited by third party
Publication number Priority date Publication date Assignee Title
CN101838970B (en) * 2009-03-17 2012-10-03 上海建泰预应力工程有限公司 Construction method for transversely strengthening railway bridge by utilizing prestressing steel structure
CN102322025B (en) * 2011-08-22 2014-07-30 陈东军 Pre-stressing reinforced and widened bridge structure
CN102352597B (en) * 2011-11-04 2013-07-24 湖南大学 Prestressed ultrahigh-performance concrete continuous box girder bridge and construction method thereof
CN103046476A (en) * 2012-12-31 2013-04-17 中铁第四勘察设计院集团有限公司 Railway long-span rotator T-shaped bridge construction method
CN103198172B (en) * 2013-01-29 2015-12-23 清华大学 Based on simulation method and the system of the bridge collapse of finite element analysis
CN104963300B (en) * 2015-07-24 2016-08-31 重庆交通大学 A kind of external prestressing multi-point-anchoring reinforcement means of bridge structure
CN107908861B (en) * 2017-11-13 2020-12-01 安徽省交通控股集团有限公司 Variable base plane design method for external prestressed stay cable of bridge
CN108193607B (en) * 2018-01-12 2019-05-03 长沙理工大学 A kind of reinforce uses prefabricated PC truss and its construction method
CN108342996B (en) * 2018-02-26 2019-05-21 陈建伟 A kind of highway bridge prestress strengthening method
CN112942890A (en) * 2021-04-07 2021-06-11 上海悍马建筑科技有限公司 Method for simultaneously reinforcing positive and negative bending moments of concrete flexural member
CN114319066A (en) * 2021-12-01 2022-04-12 中国建筑土木建设有限公司 Spliced steel truss box girder and mounting method thereof
CN116024907B (en) * 2023-01-10 2023-11-14 中交第四航务工程勘察设计院有限公司 Port steel-concrete composite beam for improving crack resistance of bridge deck and construction method thereof

Non-Patent Citations (6)

* Cited by examiner, † Cited by third party
Title
体外预应加固箱型连续梁桥方案的探讨. 关梦林.水道港口,第23卷增刊卷. 2002
体外预应加固箱型连续梁桥方案的探讨. 关梦林.水道港口,第23卷增刊卷. 2002 *
预应力混凝土箱形连续梁桥裂缝成因分析及对加固方案的评价. 廖娟,叶贵如,徐兴.中国公路学报,第17卷第1期. 2004
预应力混凝土箱形连续梁桥裂缝成因分析及对加固方案的评价. 廖娟,叶贵如,徐兴.中国公路学报,第17卷第1期. 2004 *
预应力混凝土连续箱梁桥的养护与加固. 彭卫等.混凝土,第7期. 2007
预应力混凝土连续箱梁桥的养护与加固. 彭卫等.混凝土,第7期. 2007 *

Also Published As

Publication number Publication date
CN101230562A (en) 2008-07-30

Similar Documents

Publication Publication Date Title
CN100587166C (en) External prestress strengthening method for prestressed concrete box-beam bridge
CN204185755U (en) A kind of Wavelike steel webplate post-stressed concrete T beam
CN202047377U (en) Reinforcing structure of concrete box girder
CN104695341B (en) Non-self-balanced beam string structure for reinforcing large-span continuous beam bridge
CN107916617B (en) A kind of spacial special-shaped oblique pull combined bridge of rapid construction three stride continuous and construction method
CN103556565B (en) A kind of connecting structure of different performance beams of concrete
CN111749337A (en) Large-span cable net structure supported by self-balancing arch truss
CN102877407A (en) Concrete continuous box girder of corrugated steel web for curved bridge
CN110904864B (en) Steel-concrete combined system for improving bearing capacity of concrete box girder bridge
CN105386404A (en) Girder bridge structure formed by combining open U-shaped steel box girders and hybrid fiber concrete bridge decks
CN210458916U (en) Bridge assembled bent cap prefabricated steel pedestal
Zhang et al. The world's first extradosed bridge with corrugated steel webs: Japan's Ohmi–Odori Bridge
CN100427683C (en) Wide pier with canopy beam
CN208072166U (en) Hybrid combining beam three stride continuous suspension bridge
CN109137760A (en) The active reinforcement means of multispan normal reinforced concrete beam bridge
CN210420862U (en) Stay cable tower end anchoring device
CN104532733A (en) Partial cable-stayed bridge of fish bone beam structure
CN110373990A (en) The double-deck whole hole of Combined steel truss beam manufactures and erection construction method
CN110004816A (en) Wavelike steel webplate Prestressed U HPC combined box beam and its construction method
CN212336314U (en) Large-span cable net structure supported by self-balancing arch truss
CN110029569A (en) A kind of Wavelike steel webplate-purlin formula chord member UHPC combined box beam and its construction method
CN104532732B (en) The self-anchored suspension bridge of fish spine structure
CN209244093U (en) Ultra-high performance concrete is without regular reinforcement Prestressed U type beam
CN106836556A (en) A kind of composite reinforcing steel bar cage truss support shear wall
CN208267379U (en) A kind of trapezoidal steel structure support being used to support 24-32m cast-in-situ box girder and adjustable span

Legal Events

Date Code Title Description
C06 Publication
PB01 Publication
C10 Entry into substantive examination
SE01 Entry into force of request for substantive examination
C14 Grant of patent or utility model
GR01 Patent grant
ASS Succession or assignment of patent right

Owner name: GROUP CO., LTD., ZHONGTIE DAQIAO BUREAU

Free format text: FORMER OWNER: CHINA ZHONGTIE MAJOR BRIDGE ENGINEERING CO., LTD.

Effective date: 20150225

C41 Transfer of patent application or patent right or utility model
TR01 Transfer of patent right

Effective date of registration: 20150225

Address after: No. 103 430034 Qiaokou District in Hubei province Wuhan city road construction

Patentee after: China Zhongtie Major Bridge Engineering Group Co., Ltd.

Patentee after: Group Co., Ltd., Zhongtie Daqiao Bureau

Address before: 103 No. 430034 Hubei Province in Qiaokou District of Wuhan city road construction

Patentee before: China Zhongtie Major Bridge Engineering Group Co., Ltd.

Patentee before: China Zhongtie Major Bridge Engineering Co., Ltd.

C56 Change in the name or address of the patentee
CP03 Change of name, title or address

Address after: 103 No. 430000 Hubei Province in Qiaokou District of Wuhan city road construction

Patentee after: BRIDGE SCIENCE AND TECHNOLOGY INSTITUTE CO., LTD., CHINA RAILWAY ENGINEERING GROUP

Patentee after: Group Co., Ltd., Zhongtie Daqiao Bureau

Address before: 103 No. 430034 Hubei Province in Qiaokou District of Wuhan city road construction

Patentee before: China Zhongtie Major Bridge Engineering Group Co., Ltd.

Patentee before: Group Co., Ltd., Zhongtie Daqiao Bureau