CN100532786C - 浅埋洞室的开挖方法 - Google Patents

浅埋洞室的开挖方法 Download PDF

Info

Publication number
CN100532786C
CN100532786C CNB2004100542228A CN200410054222A CN100532786C CN 100532786 C CN100532786 C CN 100532786C CN B2004100542228 A CNB2004100542228 A CN B2004100542228A CN 200410054222 A CN200410054222 A CN 200410054222A CN 100532786 C CN100532786 C CN 100532786C
Authority
CN
China
Prior art keywords
cavern
tunnel
little
excavate
excavation
Prior art date
Legal status (The legal status is an assumption and is not a legal conclusion. Google has not performed a legal analysis and makes no representation as to the accuracy of the status listed.)
Expired - Fee Related
Application number
CNB2004100542228A
Other languages
English (en)
Other versions
CN1587643A (zh
Inventor
丁文其
朱合华
陶履彬
杨林德
夏才初
李晓军
俞登华
王晓形
Current Assignee (The listed assignees may be inaccurate. Google has not performed a legal analysis and makes no representation or warranty as to the accuracy of the list.)
Tongji University
Original Assignee
Tongji University
Priority date (The priority date is an assumption and is not a legal conclusion. Google has not performed a legal analysis and makes no representation as to the accuracy of the date listed.)
Filing date
Publication date
Application filed by Tongji University filed Critical Tongji University
Priority to CNB2004100542228A priority Critical patent/CN100532786C/zh
Publication of CN1587643A publication Critical patent/CN1587643A/zh
Application granted granted Critical
Publication of CN100532786C publication Critical patent/CN100532786C/zh
Expired - Fee Related legal-status Critical Current
Anticipated expiration legal-status Critical

Links

Images

Abstract

本发明公开了一种浅埋洞室的开挖方法,在大洞室顶部的覆盖层中先沿垂直于跨度方向开挖纵向小导洞,并按“新奥法”原理及时进行喷射混凝土、锚杆施作;再沿跨度方向开挖多条横向小隧道,并及时进行喷射混凝土、锚杆施作;然后对横向小隧道和纵向小导洞施作二次衬砌,形成多连拱小隧道棚,成为主要承重结构;最后开挖其下的大洞室。本施工方法只在覆盖层中开挖小隧道,开挖方量大大减少,降低了工程量,节省了施工费用,适用于大跨度浅埋地下洞室,尤其适合于要求保护顶部地表原貌的浅埋地下洞室的设计与施工。

Description

浅埋洞室的开挖方法
技术领域
本发明涉及土木、岩土、交通、水利等工程中的一种施工方法,特别是一种浅埋洞室的开挖方法。
背景技术
洞室位置分为深埋和浅埋两种。在浅埋部位选择洞室位置时,首先要考虑洞顶覆盖深度,即洞顶以上应留有足够的新鲜岩层,其厚度应能在节理裂隙面上产生足够的正应力,以便拱顶能够自成拱,对于拱顶以上厚度不满足要求的情形,以往的做法是常常予以挖除。
目前,对于位置已定的必建地下洞室,浅埋地下洞室的设计和施工一般采用大开挖后浇注洞室,然后再覆土回填的方法。但是大开挖破坏地面环境,占用的施工场地大,施工时间长,开挖难度较高,施工费用也高。也有采用所谓的“明顶暗墙法”,这种设计和施工方法是先浅开挖浇注完成洞顶,回填覆土后再用洞挖法完成下部洞室结构。这种设计和施工方法较大开挖优越,占用的场地由于上部开挖方量的减少而较小,开挖难度也较小,施工费用也相对较低。还有一种方法是对洞室顶部围岩进行固结灌浆,这种方法对提高岩体强度效果显著,但是施工难度高,施工费用亦不菲。上述前两种浅埋地下洞室的设计型式和施工方法都能解决一般地下洞室的开挖施工问题,尤其是第一种方法应用非常普遍。然而这两种方法造价都比较高,对环境的破坏也较大;对洞室上部地表有保护性建筑物、植被等情况缺乏解决方法,适用性相对较低。特别对于大跨度的浅埋地下洞室,覆土回填使得洞顶结构必须要有足够的强度来承受上部荷载,造价很高,施工复杂,且目前对其稳定性缺乏研究。
发明内容
本发明要解决的技术问题在于提供一种浅埋洞室的开挖方法,这种开挖方法不会破坏地表原貌,开挖方量小,洞室的稳定性好。
为解决上述技术问题,本发明的开挖方法包括以下步骤:先在大洞室顶部的覆盖层中间、在平行于大洞室轴线方向并位于跨度方向的平面内垂直跨度方向开挖纵向小导洞,并按“新奥法”原理及时进行喷射混凝土、锚杆施作;再沿跨度方向间隔有效距离开挖多条横向小隧道,并及时进行喷射混凝土、锚杆施作;然后对横向小隧道和纵向小导洞施作二次衬砌,形成多连拱小隧道棚;最后开挖其下的大洞室。
作为上述开挖方法的一种优选方案,在开挖横向小隧道时,要使横向小隧道的长度大于洞室跨度,在跨度两端保证一定的搁置长度,并施作锚杆将两端固定在围岩体内。
在开挖上述小隧道棚时,所述横向小隧道的横截面可以是矩形、直墙拱形或圆形;横向小隧道的纵截面可以是直梁形、拱形或变截面形。由于小隧道的纵、横断面形式可以灵活调整,对于拱顶以上厚度不满足自成拱要求但是有一定厚度的情形同样适用,扩大了地下洞室的型式范围。
在上述开挖方法中,横向小隧道的数量、截面大小及其平面布置方式可根据实际情形作灵活调整,所述纵向小导洞的截面大小根据施工的可操作性合理确定。
由于承载的横向小隧道断面较小,并在开挖后及时支护,纵向导洞和横向小隧道棚本身的稳定性得到保证。由于多连拱横向小隧道之间连接锚杆的存在,有利于增强洞室顶部支护结构的整体强度,从而保证洞室的整体稳定性。这种洞室顶部覆盖层中间形成小隧道棚结构能够承受较大的上部载荷,同时部分利用围岩的自承载能力,使两者成为一个受力的联合体,起到支承覆盖荷载与悬吊洞室顶部围岩的作用。
由于洞室上部覆盖层得以保留,地表设施以及植被得到很好的保护,尤其是可满足风景旅游区等对洞室顶保留岩石原貌的特别要求。只在覆盖层中开挖小隧道,开挖方量大大减少,降低了工程量,缩短了工期,节省了施工费用。本发明较适用于大跨度浅埋地下洞室,对地表、洞室顶有保持原貌的特别要求的浅埋地下洞室的设计与施工,本发明尤其适合。
附图说明
图1是多连拱小隧道棚平面布置图。
图2是洞室横断面示意图。
图3是洞室纵断面示意图。
具体实施方式
下面通过具体实例结合附图对本发明做进一步的说明:
我们采用本发明对一旅游景点的洞室开挖设计支护结构,该工程的制约条件是:A、地表因有树木存在,不得大面积开挖;B、洞顶上部覆盖很薄(5-7m,相对洞室20m的跨度);C、与外侧洞室间间距小,拱脚水平抗力小,侧向稳定性差。实际设计中采用在覆盖中部先施作纵向小导洞,及横向多连拱小隧道棚,在纵向小导洞和横向小隧道内再施作锚杆、喷网、二衬,形成洞室主体承重结构。小导洞和小隧道按新奥法进行设计与施工,衬砌结构为锚喷网初期支护与二次模筑相结合的复合式衬砌,横向多连拱小隧道棚与围岩联合形成其下大洞室的承重体系。
具体实施的施工步骤如下:
1、如图1、图2所示在洞室3顶部围岩7中开挖纵向小导洞1,按新奥法施工原理及时进行纵向小导洞1的初期支护,包括喷射混凝土4、锚杆5施作。
2、如图3所示开挖横向小隧道2,按新奥法施工原理及时进行横向小隧道2的初期支护,包括喷射混凝土4、锚杆5施作。
3、如图2、图3所示,施作横向小隧道和纵向小导洞的二次衬砌6。
4、在多连拱小隧道棚与围岩联合承重下,再开挖下部大洞室3。

Claims (4)

1.一种浅埋洞室的开挖方法,其特征在于:先在大洞室(3)顶部的覆盖层中间、在平行于大洞室轴线方向并位于跨度方向的平面内垂直跨度方向开挖纵向小导洞(1),并按“新奥法”原理及时进行喷射混凝土(4)、锚杆(5)施作;再沿跨度方向开挖多条横向小隧道(2),并及时进行喷射混凝土(4)、锚杆(5)施作;然后对横向小隧道和纵向小导洞施作二次衬砌(6),形成多连拱小隧道棚;最后开挖其下的大洞室(3)。
2.根据权利要求1所述的浅埋洞室的开挖方法,其特征在于:所述横向小隧道(2)横跨洞室跨度且在跨度两端保证一定的搁置长度,并施作锚杆将两端固定在围岩体内。
3.根据权利要求1所述的浅埋洞室的开挖方法,其特征在于:所述横向小隧道(2)的横截面为矩形、直墙拱形或圆形。
4.根据权利要求1所述的浅埋洞室的开挖方法,其特征在于:所述横向小隧道(2)的纵截面为直梁形、拱形或变截面形。
CNB2004100542228A 2004-09-02 2004-09-02 浅埋洞室的开挖方法 Expired - Fee Related CN100532786C (zh)

Priority Applications (1)

Application Number Priority Date Filing Date Title
CNB2004100542228A CN100532786C (zh) 2004-09-02 2004-09-02 浅埋洞室的开挖方法

Applications Claiming Priority (1)

Application Number Priority Date Filing Date Title
CNB2004100542228A CN100532786C (zh) 2004-09-02 2004-09-02 浅埋洞室的开挖方法

Publications (2)

Publication Number Publication Date
CN1587643A CN1587643A (zh) 2005-03-02
CN100532786C true CN100532786C (zh) 2009-08-26

Family

ID=34603089

Family Applications (1)

Application Number Title Priority Date Filing Date
CNB2004100542228A Expired - Fee Related CN100532786C (zh) 2004-09-02 2004-09-02 浅埋洞室的开挖方法

Country Status (1)

Country Link
CN (1) CN100532786C (zh)

Families Citing this family (10)

* Cited by examiner, † Cited by third party
Publication number Priority date Publication date Assignee Title
CN101487393B (zh) * 2009-02-20 2011-09-21 中铁西南科学研究院有限公司 隧道易切削锚杆全断面预加固施工方法
CN102071945B (zh) * 2010-12-29 2012-11-28 上海隧道工程股份有限公司 三面封闭已建结构下盾构进出洞施工方法
CN103375169A (zh) * 2012-04-22 2013-10-30 赵兵 使金刚石绳锯用于大截面地下岩石工程的方法
CN104047621B (zh) * 2013-03-14 2015-12-23 上海市城市建设设计研究总院 基于顶部小净距地下室开挖条件的高断面横通道施工方法
CN103291316B (zh) * 2013-06-14 2015-12-09 中国电建集团成都勘测设计研究院有限公司 大型地下洞室群布置设计方法
CN103306682B (zh) * 2013-06-26 2015-03-25 中国电建集团中南勘测设计研究院有限公司 一种大跨度高边墙地下空间建筑物及其开挖支护方法
CN104500077B (zh) * 2014-12-10 2016-06-29 中铁二十局集团有限公司 一种浅埋暗挖隧道穿越平房区施工方法
CN107676103B (zh) * 2017-10-30 2019-12-31 中国人民解放军陆军工程大学 一种特大跨度洞库格栅拱架支护的施工方法
CN111412002A (zh) * 2020-04-21 2020-07-14 中铁二院工程集团有限责任公司 一种锚索对拉型支护结构体系及施工方法
CN114320340B (zh) * 2021-12-28 2023-09-12 中铁第六勘察设计院集团有限公司 基于超前导洞及对拉锚索的大跨无柱地下隧洞结构及方法

Citations (8)

* Cited by examiner, † Cited by third party
Publication number Priority date Publication date Assignee Title
DE3447872A1 (de) * 1984-12-11 1986-07-10 Rodio Foundation Engineering Ltd., Zürich Verfahren zur konsolidierung des gelaendes beim tunnelausbruch
US4666336A (en) * 1985-09-26 1987-05-19 Okumura Corporation Method of and apparatus for building thin lining on tunnel
CN87100318A (zh) * 1987-01-23 1987-08-26 陶义 超前棚顶暗挖法
CN1055214A (zh) * 1991-05-25 1991-10-09 北京市城建设计研究院 修建大型地下空间的方法
CN1083896A (zh) * 1993-07-24 1994-03-16 徐州矿务局庞庄煤矿 用于煤矿井下沿空掘巷的巷道支护方法
CN1179501A (zh) * 1997-10-24 1998-04-22 北京城建地铁地基工程有限责任公司 土质隧道插板棚顶支护暗挖施工方法及其插板机
CN1350109A (zh) * 2001-12-18 2002-05-22 李宪奎 地下构筑物的暗挖施工方法
CN1517495A (zh) * 2003-01-24 2004-08-04 诺比利费拉里有限责任公司 地下工程、隧道及坑道的连续实现方法,一般包括通过引导冲孔而获得的加固工程、密封工程以及排水工程

Patent Citations (8)

* Cited by examiner, † Cited by third party
Publication number Priority date Publication date Assignee Title
DE3447872A1 (de) * 1984-12-11 1986-07-10 Rodio Foundation Engineering Ltd., Zürich Verfahren zur konsolidierung des gelaendes beim tunnelausbruch
US4666336A (en) * 1985-09-26 1987-05-19 Okumura Corporation Method of and apparatus for building thin lining on tunnel
CN87100318A (zh) * 1987-01-23 1987-08-26 陶义 超前棚顶暗挖法
CN1055214A (zh) * 1991-05-25 1991-10-09 北京市城建设计研究院 修建大型地下空间的方法
CN1083896A (zh) * 1993-07-24 1994-03-16 徐州矿务局庞庄煤矿 用于煤矿井下沿空掘巷的巷道支护方法
CN1179501A (zh) * 1997-10-24 1998-04-22 北京城建地铁地基工程有限责任公司 土质隧道插板棚顶支护暗挖施工方法及其插板机
CN1350109A (zh) * 2001-12-18 2002-05-22 李宪奎 地下构筑物的暗挖施工方法
CN1517495A (zh) * 2003-01-24 2004-08-04 诺比利费拉里有限责任公司 地下工程、隧道及坑道的连续实现方法,一般包括通过引导冲孔而获得的加固工程、密封工程以及排水工程

Also Published As

Publication number Publication date
CN1587643A (zh) 2005-03-02

Similar Documents

Publication Publication Date Title
CN102226403B (zh) 地铁大跨度车站主体拱盖法施工方法及车站主体结构
CN100582386C (zh) 通透肋式拱梁隧道施工方法
CN102134998B (zh) 一种风积沙隧道的施工方法
CN100543239C (zh) 一种地下工程中一桩三用的方法
CN110318770A (zh) 一种公路隧道半明半暗进洞施工方法
CN201137148Y (zh) 双排毛竹桩复合土钉围护系统
CN104047613B (zh) 煤矿巷道底板用锚固方法
CN102828520A (zh) 一种应用于深厚泥炭土深基坑中的环形内支撑结构
CN205776249U (zh) 一种组合型内支撑结构
CN107060771A (zh) 中短隧道单向出洞开挖方法
CN101324071B (zh) 通透肋式拱梁隧道
CN104763433A (zh) 上软下硬地层大跨地铁车站暗挖施工方法
CN102733827A (zh) 隧道换拱施工方法及用于隧道换拱施工中的施工结构
CN106703828A (zh) 采用预制装配式衬砌结合pba建造地铁车站的施工方法
CN201991017U (zh) 基于拱盖法施工成型的地铁大跨度车站主体结构
CN101338678A (zh) 一次扣拱暗挖逆作施工方法
CN100532786C (zh) 浅埋洞室的开挖方法
CN108775252A (zh) 深井软岩巷道的支护结构及支护方法
CN109853399A (zh) 用于拱桥的大截面倾斜隧道式拱座结构及其施工方法
CN103939115B (zh) 一种半暗挖法施工棚洞的方法及结构
CN109881683A (zh) 一种联合人工填土注浆加固技术的多桩分阶支挡结构及其施工方法
CN205260048U (zh) 一种通透肋式连拱隧道
CN109487793A (zh) 一种复杂环境下的密排灌注桩内支撑基坑永久支护结构
CN209244590U (zh) 洞室围岩预支护系统以及洞室结构
CN111594168A (zh) 一种岩矸配合成形的伪采空层支护限沉回采方法

Legal Events

Date Code Title Description
C06 Publication
PB01 Publication
C10 Entry into substantive examination
SE01 Entry into force of request for substantive examination
C14 Grant of patent or utility model
GR01 Patent grant
C17 Cessation of patent right
CF01 Termination of patent right due to non-payment of annual fee

Granted publication date: 20090826

Termination date: 20120902