CN100525142C CNB200510035518XA CN200510035518A CN100525142C CN 100525142 C CN100525142 C CN 100525142C CN B200510035518X A CNB200510035518X A CN B200510035518XA CN 200510035518 A CN200510035518 A CN 200510035518A CN 100525142 C CN100525142 C CN 100525142C
Authority
CN
China
Prior art keywords
power deviation
value
message
access
power
Prior art date
Legal status (The legal status is an assumption and is not a legal conclusion. Google has not performed a legal analysis and makes no representation as to the accuracy of the status listed.)
Expired - Fee Related
Application number
CNB200510035518XA
Other languages
Chinese (zh)
Other versions
CN1885743A (en
Inventor
赵建荣
Current Assignee (The listed assignees may be inaccurate. Google has not performed a legal analysis and makes no representation or warranty as to the accuracy of the list.)
Huawei Technologies Co Ltd
Original Assignee
Huawei Technologies Co Ltd
Priority date (The priority date is an assumption and is not a legal conclusion. Google has not performed a legal analysis and makes no representation as to the accuracy of the date listed.)
Filing date
Publication date
Application filed by Huawei Technologies Co Ltd filed Critical Huawei Technologies Co Ltd
Priority to CNB200510035518XA priority Critical patent/CN100525142C/en
Publication of CN1885743A publication Critical patent/CN1885743A/en
Application granted granted Critical
Publication of CN100525142C publication Critical patent/CN100525142C/en
Expired - Fee Related legal-status Critical Current
Anticipated expiration legal-status Critical

Links

Images

Classifications

    • YGENERAL TAGGING OF NEW TECHNOLOGICAL DEVELOPMENTS; GENERAL TAGGING OF CROSS-SECTIONAL TECHNOLOGIES SPANNING OVER SEVERAL SECTIONS OF THE IPC; TECHNICAL SUBJECTS COVERED BY FORMER USPC CROSS-REFERENCE ART COLLECTIONS [XRACs] AND DIGESTS
    • Y02TECHNOLOGIES OR APPLICATIONS FOR MITIGATION OR ADAPTATION AGAINST CLIMATE CHANGE
    • Y02DCLIMATE CHANGE MITIGATION TECHNOLOGIES IN INFORMATION AND COMMUNICATION TECHNOLOGIES [ICT], I.E. INFORMATION AND COMMUNICATION TECHNOLOGIES AIMING AT THE REDUCTION OF THEIR OWN ENERGY USE
    • Y02D30/00Reducing energy consumption in communication networks
    • Y02D30/70Reducing energy consumption in communication networks in wireless communication networks

Abstract

The optimal method for power offset between physical random access channel predecessor and information comprises: setting access capture threshold, predicted access user and block error code rate; selecting an initial value for the offset and a stepping unit and counting comparison value; periodical counting access success user number and error code rate; if the access quantity over the threshold and the error code rate also over the target value, it shows the offset too small; counting till up to mean value, and adding a stepping unit to the offset.

Description

A kind of method of optimizing power deviation between PRACH lead and message
Technical field
The present invention relates to a kind of mobile communication system, more particularly, relate to the access technology of the Random Access Channel in WCDMA (Wide CodeDivision Multiple Address, the Wideband Code Division Multiple Access (WCDMA)) communication system.
Background technology
In the WCDMA system, Physical Random Access Channel is mapped on the public uplink physical channel, the carrying Random Access Channel, and access way is to adopt to divide time slot ALOHA technology at random.Subscriber equipment can begin transmission at a predefined time offset, is expressed as access slot.Per two frames have 15 access slots, are spaced apart 5120 chips (chip).Timing information on the access slot and catch indication as shown in Figure 1.Fig. 1 has shown the quantity of access slot and the space between them.The information of which access slot can be used in the current area, is provided by high layer information.
The structure of access emission as shown in Figure 2 at random.Insert emission at random and comprise that one or more length are leading part and long message part that comprises data and control information for 10ms or 20ms of 4096 chips.Among Fig. 2, subscriber equipment at first calculates leading Initial Trans according to open loop power control, if can not receive the successful response of acquisition indicator, then subscriber equipment continues to send leading according to power ramp stepping and the leading Initial Trans of the soaring number of times adjustment of maximum power.If received the success response of acquisition indicator, then subscriber equipment is adjusted the transmitting power of message again according to leading last transmitting power and power deviation, and sequential relationship according to the rules sends information.The value of above-mentioned parameter is all determined when the WCDMA BTS channel is set up.
In fact the transmitting power of message is made up of two parts: control section power and data division power.Last message transmit power and power deviation have just been determined the transmitting power of control section
Cntl dBm=Pre dBm+P p-m。And the transmitting power of data division then depends on power factor c, the d of control section and data division.The gross power of message part is actual to be 10Log[10 (Data dbm/10+ (3))+ 10 (Cntl dBm/10+ (3))].C, d give subscriber equipment by broadcast channel, and for Physical Random Access Channel, its value is constant usually.Therefore, in fact we can say between power deviation and the message gross power and have fixed relationship.
Wherein, the soaring number of times equivalence of power ramp stepping and maximum power choose the direct acquisition performance that influences Physical Random Access Channel, and directly determined user's access acquisition probability, require usually to insert acquisition probability more than 99%, comparatively speaking, choose than being easier to by emulation, test.And power deviation will directly influence the demodulation performance of Physical Random Access Channel, and the requirement to demodulation performance when power deviation is big is also higher, in the communication protocol span of defined be-5db is to 10db.Therefore, during selection, in span, suitable little unsuitable big.If select hour, will cause the user can insert (by the acquisition probability decision), but demodulation result is always wrong, just bLock error rate very high (because the message part gross power is less than normal) causes subscriber equipment can not complete successfully whole access procedure.Therefore, need on the basis of balanced acquisition probability and bLock error rate, choose according to field testing usually.If but selection is too high, then not only makes user's installation cost electricity, simultaneously, also causes the uplink interference to other user easily.
Summary of the invention
The technical problem that the present invention will solve is, the method of power deviation between a kind of leading and message of optimizing Physical Random Access Channel is provided, it can guarantee to greatest extent the effectively access-in resource of using system, improves access efficiency, also can make the subscriber equipment power saving.
The technical scheme that the present invention addresses the above problem is, a kind of method of optimizing power deviation between PRACH lead and the message is provided, and this method may further comprise the steps:
(1) desired value of the access customer number that inserts detection threshold, interior expectation of cycle and the desired value of bLock error rate are set, and in the span of power deviation, choose a power offset value initial value, step units of setting power deviation and counting comparison value;
(2) in the physical layer of WCDMA base station, handle the module that inserts judgement and periodically add up the number of users that access channel successfully inserts, handle the module of access channel message decoding and periodically add up the bLock error rate of access channel message, and statistics is reported the software layer of WCDMA base station;
(3) the bLock error rate statistics that reports of the successful access customer number that periodically module that handle to insert judgement reported of the software layer of WCDMA base station and the module of handling access channel message decoding is differentiated: surpass access customer number order desired destination value if insert energy in the cycle greater than the number of users of detection threshold, and bLock error rate is also greater than the expectation target value of having set, this differentiation result is counted, when count value reaches described counting comparison value, make power deviation increase a step units.
The method of power deviation between the leading and message of optimization Physical Random Access Channel provided by the invention, be provided with under the rational situation at detection threshold, statistics in conjunction with acquisition performance and demodulation performance can be optimized power deviation, thereby, can guarantee the access-in resource of effective using system to greatest extent, improve access efficiency, also can make the subscriber equipment power saving, reduce its uplink transmission power, reduce its uplink interference, therefore can increase the soft capacity of system and catching and demodulation performance of system cut-in channel other user.
Description of drawings
Fig. 1 is the quantity of the access slot in the WCDMA system and the space schematic diagram between them;
Fig. 2 is the emitting structural of the access at random schematic diagram in the WCDMA system;
Fig. 3 is a kind of workflow diagram of optimizing the method for power deviation between PRACH lead and the message of the present invention.
Embodiment
The method of power deviation is applicable to the Physical Random Access Channel transfer of data of WCDMA system between the leading and message of optimization Physical Random Access Channel provided by the invention.
Please refer to Fig. 3, the method of power deviation at first will be according to system requirements between optimization PRACH lead provided by the invention and the message, the desired value that inserts detection threshold, access customer number and bLock error rate is set, and in the span of power deviation, choose the initial value of a power offset value, step units of setting power deviation and counting comparison value.Wherein, described access detection threshold can obtain by specifying false alarm rate (one thousandth) emulation; The desired value of the desired value of the access customer number of expectation and bLock error rate and counting comparison value obtain by the field testing checking in described access detection threshold, cycle, as in the applied in network performance test of WCDMA, promptly can obtain its reasonable parameter configuration scope in network in conjunction with test result.
The demodulation performance of Physical Random Access Channel depends primarily on power offset value, requirement to demodulation performance when power deviation is big is also higher, since the span of power deviation (in the agreement span of defined be-5db is to 10db, be not limited only to this scope) in, be suitable little unsuitable big in principle, so should choose a smaller value, therefore should in the span of power deviation, choose a smaller value as the power deviation initial value.Then, in the physical layer of WCDMA base station, add up the number of users that access channel successfully inserts by handling the module cycle of inserting judgement, and statistics is reported the software layer of WCDMA base station; Equally, in the physical layer of WCDMA base station, by the bLock error rate of the module cycle statistics access channel message of handling access channel message decoding, this cycle can be provided with according to different execution modes, but should be a minute level at least.And statistics is reported the software layer of WCDMA base station; The software layer cycle of WCDMA base station is differentiated the bLock error rate statistics that the successful access customer number that inserts judging module and report and access channel message decoding module report: if user's (promptly inserting the user of energy) that success inserts in the cycle greater than detection threshold outnumber the desired value that inserts the user, but target value set is very high for relative one of bLock error rate simultaneously, then to be that power deviation is provided with too small in explanation, will differentiate the result to this and count, add 1 as counter.
At last, need carry out the optimization step of last power deviation, to guarantee the reliability of system, the count value of differentiating the result is compared with the counting comparison value that sets, if count value is greater than the counting comparison value, then make power deviation increase a step units, this power deviation can be adjusted by the 0.5db stepping, also can adjust by other step value.Because in fact the access-in resource of WCDMA base station is always limited, therefore can guarantee the access-in resource of efficient using system to greatest extent by adjusting power deviation.The reduction of the uplink transmission power of subscriber equipment can reduce its uplink interference to other user, thereby also can increase the soft capacity of system and catching and demodulation performance of system cut-in channel.After the optimization of finishing power deviation between above-mentioned channel leading and the message, carry out again in the physical layer of WCDMA base station, handle the module that inserts judgement, the number of users that cycle statistics access channel successfully inserts, and statistics reported the software layer of WCDMA base station, to proceed follow-up monitoring and adjustment.In addition, by repeatedly adjusting power deviation after optimal value, with the preset parameter of this optimal value as system.
Being appreciated that the present invention also can adopt chooses bigger power offset value earlier, reduces to the execution mode of a desired value again.If after having chosen a power deviation, it causes uplink interference to other user, illustrates that then this power deviation is bigger, therefore it suitably need be reduced.When uplink interference reduces to some extent, and insert energy in the cycle and meet access customer number order desired destination value greater than the number of users of detection threshold, bLock error rate also meets the expectation target value of having set, illustrates that power deviation reaches to preferred values.

Claims (6)

1, a kind of method of optimizing power deviation between PRACH lead and the message is characterized in that, this method may further comprise the steps:
(1) desired value of the access customer number that inserts detection threshold, interior expectation of cycle and the desired value of bLock error rate are set, and in the span of power deviation, choose a power offset value initial value, step units of setting power deviation and counting comparison value;
(2) in the physical layer of WCDMA base station, handle the module that inserts judgement and periodically add up the number of users that access channel successfully inserts, handle the module of access channel message decoding and periodically add up the bLock error rate of access channel message, and statistics is reported the software layer of WCDMA base station;
(3) the bLock error rate statistics that reports of the successful access customer number that periodically module that handle to insert judgement reported of the software layer of WCDMA base station and the module of handling access channel message decoding is differentiated: surpass access customer number order desired destination value if insert energy in the cycle greater than the number of users of detection threshold, and bLock error rate is also greater than the expectation target value of having set, this differentiation result is counted, when count value reaches described counting comparison value, make power deviation increase a step units.
2, the method for power deviation between optimization PRACH lead according to claim 1 and the message is characterized in that, after this method also is included in completing steps (3), returns step (2) again, to continue follow-up monitoring and adjustment.
3, the method for power deviation between optimization PRACH lead according to claim 1 and the message is characterized in that, and the span of described power deviation is-and 5db is to 10db.
4, the method for power deviation between optimization PRACH lead according to claim 1 and the message, it is characterized in that wherein step (1) comprises by field testing checking and obtains the desired value of the access customer number expected in the described cycle and the desired value of described bLock error rate.
5, the method for power deviation between optimization PRACH lead according to claim 1 and the message is characterized in that, described power deviation is pressed 0.5db stepping adjustment.
6, the method for power deviation between optimization PRACH lead according to claim 1 and the message is characterized in that, by repeatedly adjusting power deviation after optimal value, with the preset parameter of this optimal value as system.
CNB200510035518XA 2005-06-23 2005-06-23 Method for optimizing power deviation between PRACH lead and message Expired - Fee Related CN100525142C (en)

Priority Applications (1)

Application Number Priority Date Filing Date Title
CNB200510035518XA CN100525142C (en) 2005-06-23 2005-06-23 Method for optimizing power deviation between PRACH lead and message

Applications Claiming Priority (1)

Application Number Priority Date Filing Date Title
CNB200510035518XA CN100525142C (en) 2005-06-23 2005-06-23 Method for optimizing power deviation between PRACH lead and message

Publications (2)

Publication Number Publication Date
CN1885743A CN1885743A (en) 2006-12-27
CN100525142C true CN100525142C (en) 2009-08-05

Family

ID=37583743

Family Applications (1)

Application Number Title Priority Date Filing Date
CNB200510035518XA Expired - Fee Related CN100525142C (en) 2005-06-23 2005-06-23 Method for optimizing power deviation between PRACH lead and message

Country Status (1)

Country Link
CN (1) CN100525142C (en)

Families Citing this family (5)

* Cited by examiner, † Cited by third party
Publication number Priority date Publication date Assignee Title
WO2008087941A1 (en) * 2007-01-19 2008-07-24 Ntt Docomo, Inc. Base station device, mobile station, mobile communication system, and communication control method
CN101137239B (en) * 2007-09-28 2012-01-11 中兴通讯股份有限公司 Random access parameter automatic optimization method
CN101730256B (en) * 2008-10-14 2012-07-25 上海摩波彼克半导体有限公司 Method for realizing rapid and random switching-in process in wireless honeycomb network
CN102624483B (en) * 2012-03-02 2014-12-03 华为技术有限公司 Method and device for data transmission
US10595280B2 (en) * 2015-03-06 2020-03-17 Qualcomm Incorporated Repetition level coverage enhancement techniques for physical random access channel transmissions

Non-Patent Citations (2)

* Cited by examiner, † Cited by third party
Title
Random access channel (PACH) parameters optimizationinWCDMA systems. 2004 IEEE 60th Vehicular Technlology Conference,第6卷. 2005
Random access channel (PACH) parameters optimizationinWCDMA systems. 2004 IEEE 60th Vehicular Technlology Conference,第6卷. 2005 *

Also Published As

Publication number Publication date
CN1885743A (en) 2006-12-27

Similar Documents

Publication Publication Date Title
US7245935B2 (en) Method and apparatus for transmission power control
CN101494482B (en) Method and apparatus for power control in a wireless communication system
CN102077676B (en) Method and apparatus for optimizing the terminal random access
CN101595662B (en) Method and apparatus for detecting contention during random access procedure in a mobile communication system
CN1265672C (en) Reservation multiple access
US20060089104A1 (en) Method for improving an HS-DSCH transport format allocation
US7505448B2 (en) Method of wireless channel resource allocation and rate control in a cdma communication system
CN101686559B (en) Method and system for randomly accessing relay station
US20020155840A1 (en) Base station device and wireless communication method
US8072915B1 (en) Common power control channel in a CDMA system and a system and method for using such a channel
CN101682891A (en) The method and the device that are used for configuring mode timers
CN100525142C (en) Method for optimizing power deviation between PRACH lead and message
CN101132184A (en) Method and apparatus for reducing power consumption of a decoder in a communication system
CN101346906A (en) Method and procedures for unsynchronized, synchronized and synchronization stand by communications in E-UTRA systems
CN101385250A (en) Adaptive preamble length for continuous connectivity transmission
EP1055340A1 (en) Access request in a radio communication system
KR20170137763A (en) System and method for reducing collisions in wireless networks
CN101689871B (en) Method for fast acknowledgement and identification of a service access request message or a preamble thereof
CN101521902A (en) Method for reporting downlink channel measurement information, terminal equipment and base station equipment
CN100477574C (en) Method for operating main wireless station
CN1859036B (en) Regulating method and its device for physically random cut-in channel judging threshold
CN103814620A (en) Method and apparatus for adjusting random access parameters
CN1471767B (en) Simplified quality indicator bit test procedures
CN106792927B (en) Uplink service identification switching method and device, and base station
KR100566233B1 (en) Apparatus and method for data rate transmission of user element in mobile communication system

Legal Events

Date Code Title Description
C06 Publication
PB01 Publication
C10 Entry into substantive examination
SE01 Entry into force of request for substantive examination
C14 Grant of patent or utility model
GR01 Patent grant
CF01 Termination of patent right due to non-payment of annual fee

Granted publication date: 20090805