CA1212042A - Down hole blow out preventer and method of use - Google Patents
Down hole blow out preventer and method of useInfo
- Publication number
- CA1212042A CA1212042A CA000446732A CA446732A CA1212042A CA 1212042 A CA1212042 A CA 1212042A CA 000446732 A CA000446732 A CA 000446732A CA 446732 A CA446732 A CA 446732A CA 1212042 A CA1212042 A CA 1212042A
- Authority
- CA
- Canada
- Prior art keywords
- valve
- pressure
- housing
- sleeve
- mud
- Prior art date
- Legal status (The legal status is an assumption and is not a legal conclusion. Google has not performed a legal analysis and makes no representation as to the accuracy of the status listed.)
- Expired
Links
- 238000000034 method Methods 0.000 title claims abstract description 9
- 238000005553 drilling Methods 0.000 claims description 24
- 238000001514 detection method Methods 0.000 claims description 3
- 230000002441 reversible effect Effects 0.000 claims description 3
- 238000007789 sealing Methods 0.000 claims description 3
- 230000002829 reductive effect Effects 0.000 claims description 2
- 238000003754 machining Methods 0.000 claims 1
- 230000015572 biosynthetic process Effects 0.000 description 12
- 230000002706 hydrostatic effect Effects 0.000 description 9
- 239000004519 grease Substances 0.000 description 7
- 239000011148 porous material Substances 0.000 description 7
- 229910000831 Steel Inorganic materials 0.000 description 5
- 239000010959 steel Substances 0.000 description 5
- 239000012530 fluid Substances 0.000 description 3
- 210000002445 nipple Anatomy 0.000 description 3
- 238000004891 communication Methods 0.000 description 2
- 238000005520 cutting process Methods 0.000 description 2
- 238000007667 floating Methods 0.000 description 2
- 230000000644 propagated effect Effects 0.000 description 2
- 241000239290 Araneae Species 0.000 description 1
- 238000006066 Comins reaction Methods 0.000 description 1
- 125000003338 L-glutaminyl group Chemical group O=C([*])[C@](N([H])[H])([H])C([H])([H])C([H])([H])C(=O)N([H])[H] 0.000 description 1
- XAGFODPZIPBFFR-UHFFFAOYSA-N aluminium Chemical compound [Al] XAGFODPZIPBFFR-UHFFFAOYSA-N 0.000 description 1
- 229910052782 aluminium Inorganic materials 0.000 description 1
- 239000004411 aluminium Substances 0.000 description 1
- 230000006835 compression Effects 0.000 description 1
- 238000007906 compression Methods 0.000 description 1
- 230000001054 cortical effect Effects 0.000 description 1
- 230000003247 decreasing effect Effects 0.000 description 1
- 238000003780 insertion Methods 0.000 description 1
- 230000037431 insertion Effects 0.000 description 1
- 239000007788 liquid Substances 0.000 description 1
- 239000003129 oil well Substances 0.000 description 1
- 230000035515 penetration Effects 0.000 description 1
- 238000011084 recovery Methods 0.000 description 1
- 230000000284 resting effect Effects 0.000 description 1
- 239000007787 solid Substances 0.000 description 1
- 239000003381 stabilizer Substances 0.000 description 1
- 230000003068 static effect Effects 0.000 description 1
Classifications
-
- E—FIXED CONSTRUCTIONS
- E21—EARTH OR ROCK DRILLING; MINING
- E21B—EARTH OR ROCK DRILLING; OBTAINING OIL, GAS, WATER, SOLUBLE OR MELTABLE MATERIALS OR A SLURRY OF MINERALS FROM WELLS
- E21B21/00—Methods or apparatus for flushing boreholes, e.g. by use of exhaust air from motor
- E21B21/10—Valve arrangements in drilling-fluid circulation systems
-
- E—FIXED CONSTRUCTIONS
- E21—EARTH OR ROCK DRILLING; MINING
- E21B—EARTH OR ROCK DRILLING; OBTAINING OIL, GAS, WATER, SOLUBLE OR MELTABLE MATERIALS OR A SLURRY OF MINERALS FROM WELLS
- E21B33/00—Sealing or packing boreholes or wells
- E21B33/10—Sealing or packing boreholes or wells in the borehole
- E21B33/12—Packers; Plugs
- E21B33/127—Packers; Plugs with inflatable sleeve
Landscapes
- Engineering & Computer Science (AREA)
- Geology (AREA)
- Mining & Mineral Resources (AREA)
- Life Sciences & Earth Sciences (AREA)
- General Life Sciences & Earth Sciences (AREA)
- Fluid Mechanics (AREA)
- Environmental & Geological Engineering (AREA)
- Physics & Mathematics (AREA)
- Geochemistry & Mineralogy (AREA)
- Mechanical Engineering (AREA)
- Earth Drilling (AREA)
- Centrifugal Separators (AREA)
- Medical Preparation Storing Or Oral Administration Devices (AREA)
- Drilling Tools (AREA)
- Containers And Packaging Bodies Having A Special Means To Remove Contents (AREA)
- Acyclic And Carbocyclic Compounds In Medicinal Compositions (AREA)
- Safety Valves (AREA)
- Farming Of Fish And Shellfish (AREA)
- Fertilizing (AREA)
Abstract
ABSTRACT
DOWN HOLE BLOW OUT PREVENTER END METHOD OF USE
A down hole blow out preventer which can be installed at the lower end of a drill string (71) as close as possible to the drill bit (72) and which can isolate an unexpected producing zone in a bore hole (73) from the rest of the hole by closing off the annulus (74) between the drill string and the wall of the bore hole by means of an inflatable packer (54). The packer can be operated when a predetermined pressure difference exists between the annulus and the mud column inside the tool.
DOWN HOLE BLOW OUT PREVENTER END METHOD OF USE
A down hole blow out preventer which can be installed at the lower end of a drill string (71) as close as possible to the drill bit (72) and which can isolate an unexpected producing zone in a bore hole (73) from the rest of the hole by closing off the annulus (74) between the drill string and the wall of the bore hole by means of an inflatable packer (54). The packer can be operated when a predetermined pressure difference exists between the annulus and the mud column inside the tool.
Description
"DOWN HOLE BLOW OUT PREVENTER AND METHOD OF USE"
The invention relates to a down-hole blow-out preventer for use in drilling oil and gas wells and weils that may be drilled for recovery of geothermal energy, etc.
Surface blow-out preventers are in common use in the oil industry but so far no blow-out preventer is in commercial use which can be used successfully to block off the oil well down the drill hole and close to the drill bit.
Various proposals have been made for closing the drill hole but none has ever been used successfully commercially for various reasons.
For example U.S. Specification No. 3908769 shows a drill hole packer -to be carried by a drill string but this packer is dependant for its operation upon a high flow rate of fluid in the reverse direction on encountering a kick. The device according to the invention works on detection of a static pressure difference.
, I, . - :
~L2~
U. S. Specifications Nos. 3941190 and 3503445 both show down hole packers but both packers are operated by tools which have to be pumped down the hole which would take several hours.
The invention provides a down hole blow ou* preventer comprising an elongated tubular housing having a through bore for the passage of drilling mud and means for connecting the ends of the housing into a drilling string, a packer element arranged circumferentially around the housing and inflatable into engagement with the bore hole to seal the hole, passage means extending through the housing wall for connecting the bore of the housing with the packer element to inflate the element by mud pressure from within the housing, a cylindrical valve sleeve mounted inside the housing for movement between a drilling position when the sleeYe closes said passage means and an inflating position when the passage means is open, a one-way valve for closing the housing bore on the side of the sleeve to be nearer the drill bit, said valve means being operable to allow the passage of mud under pump pressure, but not allowing reverse flow of mud, said valve sleeve providing a through bore for the passage of mud, second valve means for closing the bore in the valYe sleeve and means to close said second valve means automatically when pressure in the housing is reduced to a level below the pressure in the bore hole by a predetermined amount, the arrangement being such that after closing of the second valve means the pressure in the housing can be re-applied to urge the valve sleeve to its inflating position allowing the packer element to be inflated, means to prevent closure of the second valve means during running-in, a mud circulation channel extending through the housing on the side of the sleeve valve nearer the surface, means being provided to open said channel when the paclcer element is inflated whereby mud may be circulated through the drill string, the channel and the bore hole to increase the mud density, and means for deflating the packer element only when the mud density is sufficient to balance the pressure below the packer element.
The invention is also concerned with a method of using such a device.
A specific embodiment of a down hole blow out preventer (D.~. BOP) in accordance with the invention will now be described in detail with reference to the drawings in which:.-Figure l shows the D.H. BOP connected in a drill pipe-string run into a hole;
~21.~r~f~ 1l Figure 2 is a vertical sectional view of the P.H.BOP in the running-in position;
Figure 3 is a horizontal cross-section along line III-III in Figure 2;
5Figure 4 is a horizontal cross-section along line IV-I~ in Figure 2~
Figure 5 is a horizontal cross-section along line.V-~:in Figure 2;
Figure 6 shows a.vertical cross-sectional 10......................... yiew of the D.H.BOP, in drilling position;
Figure 7 is a horizontal cross-section along lin.e VII-~II in Figure 6,.
Figure 8 shows a vertical cross-sectional vie of the D.H.BOP during a wellkick after closing the flapper valye.
Figure 9 shows cortical cross~sectional tow of the D.H.BOP, with the packer inflated' Figure 10 shows.a.~ertical cross-sectional view of the D.H.BQP, with the circuIating port open.;
20Figure 11 is a horizontal cross-section along line XI-XI in Figure 10;
Figure 12 is a horizontal cross-section along line XII-XII in Figure 10, Figure:13 shows a vertical cross-section.al view of the D.H.BOP, deflating the packer' and Al 2~ 4 - s -Figure 14 shows a horizontal cross-section on the line XIV-XIV in Figure 13.
As can be seen from Figure 2 the D.H.BOP
comprises two barrels an outer barrel 1 and an inner barrel 2.
The inside of the outer barrel 1 and the outside of the inner barrel 2 are fine machined to the required tolerances.
The various channels and holes are milled and drillèd in the inner barrel 2 and after being machined the two barrels are shrunk together by undercooling of the inner barrei 2.
The position of the two barrels in relation to each other must be precise.
After shrinking the two barrels 1 and 2 together, the various ra.dial holes can be drilled and the channels for the fill-up.valve assembly 41, the grease bolt 1', the check.val~e 53, the circulating vale 57 and the equalising valve 62 can be drilled and machined.
The top of the outer barrel 1 is provided with an external thread 4 for connection with an API
threaded substitute 3 to enable the insertion of the inner parts of the D.H.BOP from the top.
The outer barrel 1, is provided at its lower . .. .. .. .. .... .... . . .. .
end with an internal thread 4' to connect it with a packersleeve 5.
The packersleeve 5 is at its bottom-end provided with a threaded API box connection 6 to connect it with the drilling bit.
Inside the packersleeve 5 a chamber is machined which is nearly as long as the packersleeve 5, and in which a floatvalve assembly 7 is inserted for sliding movement from a lower to an elevated position.
Floatvalve assembly 7 comprises a piston-like substantially hollow body 7' in which is mounted a conical valve 8 spring-loaded by spring 9 into sealing engagement with a valve seat, formed inside body 7', Valve 8 is fixed to valve stem iO which is guided for sliding up and down movement in guiding sleeve 11 mounted in bushing 12 which is fixed inside body 7 by means of a spider.
A snapring sleeve 13 is insexted into the top of packersleeye 5. The top of packersleeve 5 is provided with four pressure equalising channels 15 in the snapring sleeve 13.
Around snapring sleeve 13 a helical spring 16 is inserted before a snapring 17 is pressed over the snapring sleeve 13. . -A flappervalve sleeve 18 is pressed o'er the s snapring 17 mounted around snapring sleeve 13 until it sits in a snapring recess 19.
Flapper~alve sleeve 18 is proyided with a friction cam 20 which can be forced over the snapring 17 until snapring 17 snaps into snapring s]ot 21 of flapperyalve sleeve 18, by pump pressure when the flappervalve 22 is closed. The flappervalve 22 is pi~otally mounted on top of flapperyalve sleeve 18 and spring biased towards a closed position in which it is in sealing engagement with the top edge 18' of flappervalve sleeve 18. Closing movement is prevented by a flapperval~e release sleeve 23 during circulating and drilling.
The flappervalve release sleeve 23 comprises a plunger holder 24 to which are fixed two plungers 25 which are received into bores formed in a plunger housing 26.
The plunger holder 24 and the plunger housing 26 are provided with four pressure equalising channels 27 and 28 respectively.
A helical spring 29 bears with its cover end against the top of the plunger holder 24 with its upper end against a retainer ring 30 by which the tension of spring 29 can be adjusted. The retainer ring 30 is also provided with four pressure equalising channels 31~ A steel arresting ball biassed in~axdly by a calibrated helical spring rests in a circumferential groove in plunger holder 24.
By stopring 32 upward movement of the plunger holder 24 is limited to keep he plungers 25 inside the plunger housing 26.
Against the top of retainer ring 30 bears a helical spring 33 which bears with its other end against a shut-off sleeve 34 to keep the sleeve 34 in its highest position in which a channel 35 and a fill-up channel 36 are open see Figure 3).
The fill-up valve assembly 41 is shown in lO running-in position in Figures2 and 3 and in circulating or drilling position in Figures 6 and 7. It comprises a gate 41' having a substantially rectangular cross-section and running in a hole 42 which hole is closed at one end by locking nut 45 having a slotted part 46 in communication with a bore 35 in the body part 2. A
screen 47 covers a recess, formed in outer barrel l which is in communication with fill-up channel 36, and an inlet 48 which opens into flappervalve release channel 49. Channel 49 extends through inner barrel 2 and 20 opens into circumferential groove 50 formed in plunger housing 26 and ports 51 extend from g.roove 50 into the plunger cylinders.
The first purpose of the fill-up valve assembly 41 is to be in open position (Figure 3) to fill up the 25 drill pipe when running thedrill pipe into the hole and simultaneously to close off the flappervalve release :!
;
.,, channel 49 when running into the hole so that no pressure difference between the annulus and drillpipe can lift the plungers 25 and accidentally cause the flappervalve 22 to close.
Its second purpose is to close off the fill-up channel 36 once circulation or drilling has commenced.
The greater pressure inside the drill pipe is propagated through channel 35 to gate 41 and moves the gate 41 to close the fill-up channel 36, against the lesser pressure in the annulus as shown in Figure 7. When the gate 41 moves it also closes the fill up channel 36 and mud will fill the fluid lock 52.
The shut-off sleeve 34 is moyed downardly when circulation is started and to increase the pressure drop an aluminium disc 37' with an orifice may be provided - by means of threaded ring 37 which disc will be disintegrated during circulation. The position is shown in Figure 6.
When the shut-off sleeve 34 moves downwardly against the tension of spring 33, the locking spring snaps into the locking groove 39 formed in the inner wall of inner barrel 2 and shuts off the channels 35 and 36. The shut-off sleeve 34 is provided with three pressure equalising channels 40.
After the shut-off sleeve 34 has mowed `` ~.2~
I] o -downwardly to close channel 35 the entrapped mud in the fluid lock 52 will cause khe fill-up channel 36 to be permanently closed while the flappervalve release channel 49 remains open. The plungers 25 are from now on permanently connected to and subjected to the pressure in the annulus through inlet 48 and channel 49.
Another purpose of the fill-up valve assembly is to provide the possibility to calibrate the tension of the spring loaded steel ball 23' (Figure 2) and the spiral spring 29 before running the D.H.BOP into the hole. The spring loaded steel ball 23' is there to prevent fluttering of the flapper.valve release sleeve 23 by pressures lower than the setting of the spring 29 for releasing the flapper ale 22.
To enable calibration of the spring loaded steel ball ~3' and the spiral opening 29 the fill-up valve gate 41 is set in the drilling position as shown in Figure 7 whereafter a grease pump with a pressure gauge is connected to the threaded inlet 48 leading to flapper.val~e release channel 49. The ten.sion set for the spiral spring 29 depends on the maximum expected penetration rate per hour, the hole size, the depth of the hole, the pump volume and the cross sectional area of the plungers 25.
Easy to read chaxts can be developed for this l Z
purpose.
The required spriny tension is the tension required to overbalance the greater hydrostatic head of the mud column in the annulus caused by the presence of drilled formation cuttings when the pump is stopped.
A checkvalve 53 is provieed to allow mud to enter and to inflate the inflatable packer element 54 when the flappervalve 22 has been released and closed, and the flapperval~e sleeve 18 has been pumped down to uncover the inflating port 55. This operation will be described later. Mud can then be pumped through port 55 and channel 56 into packer element 54. The check valve 53 closes and retains the mud in the inflatable packer element 54 when the pressure in the drillpipe drops.
It will be seen that the outside diameter of the outer barrel 1 has a partly enlarged diameter la, which is proyided with spiral grooves 16 figure 4) like an undersized solid body stabilizer.
The enlarged diameter provides protection for the packer element 54. Furthermore a steel ring 54' at the bottom end of the packer element 54 is connected to the packer sleeve 5 by means of shearpins 54''.
This to protect the packer element whilst running into the hole and to withstand rotational forces when drilling.
--`` 3L2~ Z
The shearpins 5~'' are sheared when the packer 54 is inflated say at a pressure of 700 psi.
A shut-off valve assembly 57 is provided which is composed of a shut-off piston 57' with O-ring seals, a helical pressure spring 58 and a bushing 59 with a thread 59' for a grease nipple.
When running in and drilling (Figure 5), the shut-off piston 57' is isolated from the pressure inside the tool by the flappervalve sleeve 18 with which is provided O-ring seals (Figure 2). It is exposed to the pressure inside the tool when in inflating the packer element 54 the flappervalve sleeve 18 is pushed downardly and its friction cam 20 rides over the snapring 17 which then snaps into the slot 21 as will be described later.
The object of the shut-of-f piston 57' is to close the channel 60 while pump pressure is present within the tool, and to open the channel 60 when the pump is stopped. This is achieved by the pressure within the tool moving the piston 57l against the spring 58 to close the channel 60 from the annulus.
An equalising valve 62 is provided (Figure 5) which comprises an equalising piston 62, hazing a conical nose, a helical pressure spring 63 and a threaded bushing 64 in which bolt 65 is screwed.
The purpose of the equalising valve is to open the packer element to the channel 60 when the pressure in the annulus below the packer (which is fed to the valve via channel 66) is exceeded by 300 psi by the mud pressure which is above the packer. The mud pressure is present in channel 60 when piston 57' opens the channel 60 to the annulu.s~
When a kick i.s encountered and the packer element 54 has been inflated (Figure lO) then during circulation through the circulating channels 61 the equalising channel 60 is closed and no extra circulation pressure is behind the equalising piston 62. However when the pump is stopped and the shut-off pistion 57' is pushed back by spring 58 then. the equalising channel 60 is open to the mud pressure in the annulus so that the hydrostatic pressure acts on the conical nose of the equalising piston 62.
on the opposite side of the equalising piston 62 the formation pressure below the packer is received via equalising port 64 and aligned ports 67 and 68 formed in flappervalve sleeve 18 and snapring sleeve 13 respectively.
If now the mud weight is sufficiently increased to overbalance the formation porepressure and the pump is stopped then the hydrostatic head of the mud column 3l21;~
in the annulus above the packer exerts pressure against the equalising piston 62 and moves this piston until it opens the deflating channel 69 so that the pressure inside the packer element escapes into the annulus through equalising channel 60 assisting the equalising piston 62 to remain in open position (Figure 4).
The overpressure required to move and open the equalising piston 62 can be adiusted by means of the spring loaded ball 84 resting in groove 92 and can be tested with a grease pump having a pressure gauge when the grease nipple i5 screwed into the thread 57.
When the flappervalve sleeve 18 is pumped down after the packer element has been inflated, the mud below the flappervalve is trapped and, although of very small volume, the closed floatvalve 7 will move downwardly and compress the gas or liquid or squeeze it back into the formation against the formation pore pressure.
After the ~H.BOP is prepared fox running in, the D.~l.BOP can be run into the hole, so that it reaches eventually the position as shown in Figure 1. In Figure 1 is shown the D.H.BOP 70, interconnected between the drillpipe-string 71 and drillbit 72 and run into 25 hole 73 so that annulus 74 i5 formed. A casing 75 is -~15-cemented in the upper portion 73' of the hole 73, while at the surface a surface blow out preventer 76 of known type is provided below rotary table 77. Mud can be pumped by pump 78 t'nrough hose 79 and swivel 80 down into drillpipe-string 71, which mud then is ejected from drillbit 72 and flows upwardly through annulus 74. With reference numeral 81 a pressure gauge is shown.
When running in, the drillpipe is empty and the floatvalve 7 is closed and in its highest position (see Figure 2) so that no mud can enter the drillpipe through the bit nozzles and no formation cuttings can settle down inside the bit on top of the bit nozzles causing the bit to become plugged when circulation is started. The filling of the drillpipe takes place through the fill-up opening 36 and hole 42 of the fill-up gate 41.
The mud is screened by the mudscreen 47.
Figures 1 and 3 give a clear insight on the operation and position of each valve and part when running into the hole.
Attention should be given to the fact that when for one reason or the other circulation has been established during running into the hole, it will be necessary that the drillpipe will be filled from the ... , . .~............... .. ..
top of every stand to be run into the hole because after circulation the fill-up valve will be permanently closed as described herein aboveO
When the bit has reached the bottom of the hole the mudpumps are started and circulation is established through the floatvalve 7 and the bit nozzles. Figure 6 gives a clear insight on the operation and position of each valve and part when circulating or drilling.
Drilling may continue without encountering a kick and a roundtrip to change the bit is then made without having used the D.H.BOP.
When the bit is pulled and unscrewed, the floatvalve 7, the valve seat inside body 7' and the valve assembly circumferential body seals should be inspected and be in a good condition or changed for new ones before maklng-up a new bit.
ext, take out the threaded ring 37 from shut-off sleeve 34 with a set and pulling tool, and screw a set and pulling tool into the same thread and pull the shut-off sleeve 34 up until its highest position unscrew tool and screw in threaded ring 37 again.
The fill-up valve gate 41 has to be cleaned and to be xeset after each roundtrip. Unscrew locking nut 45, put grease nipple in the thread, pump out the , . - . . . . ., . ......... . . . .y .
- ~2~
housing 44 for gate piston ~3 together with the gate 41, clean and reinsert gate 41 and housing 44, use grease, set gate 41 in fill-up position with a set bolt "s"
and screw in locking nut 45, take out set bolt and tighten locking nut ~5. The D.H.BOP can be run again and is ready to operate again when necessary.
Figure 8 gives a clear insight of the operation and the position of each valve and part when a kick is encountered and the annulus is closed in by the surface BOP 76.
If a kick is encountered during drilling then the pumps are stopped, the standard pipe valve closed, the kelly picked-up and the annular BOP closedr The closed~in drill pipe pressure is then read and recorded. As soon as the pumps are stopped the floatvalve 7 will close due to the tension of spring 9.
As the well is completely closed-in, now pressure will be built up inside the well.
The floatvalve assembly-7 was in its lowest position when circulating. Now the pumps 78 (Figure 1) are stopped so that the closed floatvalve assembly 7 acts like a floating piston and when pressure below it is building up it can move upwardly making it possible to read the closed in drillpipe pressure (C.I.D.P.P.) from the pressure gauge 81 (Figure 1).
The C.I.D.P.P. + hydrostatic head of the mud column in the drillpipe = formation pore pressure.
If the kick is observed at an early stage then the time required for the C.I.D.P.P. to build up should be about ten (10] minutes, depending on the column of gas already produced in the annulus 74 (compression).
The C.I.D.P.P. is recored and the required mud weight calculated with sufficient overbalance over the formation pore pressure.
Now the C~I~D~PoP~ is slowly bled-off at the drillpipe. Wait a few seconds and start pump 78 slowly.
In the meantime the following occurs downhole:
When the well is closed in, the C.I.D.P.P. + hydrostatic head of the mud column in the drillpipe = closed in annular pressure t hydrostatic head of mud column in the annulus because these are co}~municating vessels with the floating floatvalv0 assembly 7 between them.
Say that the C.I.D.P.P. is 300 psi. and the pressure is bled-off at the drillpipe, now the annular pressure at the bottom of the hole is 300 psi.
higher than in the drillpipe. The floatvalve assembly 7 moves into its highest position and the pressure in the annulus 74 is propagated via the inlet 48 and through hole 42 in fill-up valve gate 41 through the flappervalve z~
release channel 49 underneath the plungers 25, which are then moved upwardly lifting the flappervalve release sleeve 23 until the spring biased flappervalve 22 falls on the seat 18' formed by the upper edge of flappervalve sleeve 18, which is then closed off (see Figure 8).
All above occurs when the C.I.D.P.P. is bled-off at the drillpipe.
Now the pump 78 is started very slowly.
Pressure builds up to abt. 1500 pse. and drops. Pump speed is increased to 100-200 gln/min. depending on the size of the D.H.BOP and the size of the circulating channels 59.
As shown in Figure 9 downhole the following occurs:
The flappervalve 22 is already closed. Pump 78 runs slowly. The flappervalve sleeve 18 is pushed downwardly by the pump pressure against the helical spring until the inlet 55 of the check valve 53 is uncovered and the 1appervalve sleeve 18 hits the snapring 17 with the calibrated friction cam 20~ Pressure is now building up and the packer element 5~ is inflated through inflation channel 56.
At about 1500 psi. the flappervalve sleeve 18 snaps With its friction cam 20 over the snapring 17 which is locked in the snapring slot 21 and the packer 52 is set.
-.20-As shown in Figure 10 when the snapring 17 is snapped into the snapring slot 21 the mud pushes shut-ofE piston 57' (Figure 8, 52) outwardly so that piston 57 closes channel 60.
In this position of the sleeve 18 mud can be circulated through the circulation ports 61. When circulation is established the drillstring is lowered to put some weight on the packer to make certain that the packer 54 is set.
. The packer 54 is now isolating the producin.
zone from the remaining portion of the hole.
The tool is closed-off at the bottom by the float.valve assembly 7 and from the top by the flappervalve 22.
When the mudweight has been increased by circulation to the required weight so that the hydrostatic pressure of the mud column above the packer 54 is overbalancing the pore pressure of the formation below the packer the pump should be stopped.
The chann.el 60 will then be opened by the pistion 57' and the equalising valve so that the packer is deflated and the string can be pulled out of the hole.
As shown in Figure 13 the following occurs downhole when the mud is overbalancing the formation pore pressure and the pump is stopped.
~Z~ }4~
When the pump is stopped the shut-off piston 57 ovens the equalisin~ channel 60.
The hydrostatic pressure of the mud column above the packer 54 acts on the one side of the equalising piston 62 which normally shuts off deflating channel 69.
The other side of the equalising piston 62 is connected through channel 66 and pOrtS 67, 68 with the space between the flapperva.lve 22 and the float 10 .~alve a.ssembly 7, below which the formation pore pressure acts.
If no the hydrostatic pressure ox the mud column in the annulus above the packer.54 overbalances sufficiently the formation pore pressure below the packer then the equalising piston 62 moves and opens the deflating channel 69. The pressure of abt. 1500 psi.
behind the packer element 54 i9 now released in the annulus through channels 69 and.60.and the packer elements deflates and the packer is free.
If the packer does not deflate then the recorded C.I.p.P.P. was not correct and the mudweight should be increased gradually and the pumps stopped at intervals.
When a well starts comin.g in during roundtripping the same procedure should be followed as during drilling but instead of pulling out continuously one should kill ~z~
~22-the well, unseat the packex and run back to bottom decreasing the mudweight when going deepex and cirCulating at 2ntervals.
Circulating takes then place through the circulating ports instead of through the bit nozzles.
When the bottom of the Cole is reached, condition the mud and pull-out to inspect all parts of the D.H.BOP.
An alternative use of the D.H.BOP i5 when drilling on the sea bed with a surface BOP positioned on the sea bed and it is desired to suspend drilling operations e.g. when weather us bad.
The surface BOP is first closed and the mud pressure within the string is bled down. Mud undar pressure is then forced into the annulus whereby the pressure in the annulus exceeds the pressure setting of the arresting ball and helical spring in the tool by at least the amount necessary to operate the D.H.BOP
to close the flapper valve. The packer element can then be inflated as before and this will seal the bottom end of the caslng and the drill string and the surface pipe from the sea bed to the drilling vessel can be removed.
Reconnecting the surface pipe and the drill pipe and releasing the packer can be achieved by closing the drill pipe at the surface and pressurising the annulus, below the clvsed BOP rays a thç surface, to open the eq~lising valve, whereafter the rams are opened.
An advantage of the DHP~P described is that in addition to controlling a well in a novei manner, a well can be hrought under control in the conventional manner. Ion this case on detecting a kick the surface BOP
is closed and the closed in drill pipe pressure is read. Instead of lowering the closed in pressure to close the flapper valve, the closed in pressure is maintained. The flapper valve does not close and the well can be brought under control in the normal way by the introduction of heavier mud.
,,
The invention relates to a down-hole blow-out preventer for use in drilling oil and gas wells and weils that may be drilled for recovery of geothermal energy, etc.
Surface blow-out preventers are in common use in the oil industry but so far no blow-out preventer is in commercial use which can be used successfully to block off the oil well down the drill hole and close to the drill bit.
Various proposals have been made for closing the drill hole but none has ever been used successfully commercially for various reasons.
For example U.S. Specification No. 3908769 shows a drill hole packer -to be carried by a drill string but this packer is dependant for its operation upon a high flow rate of fluid in the reverse direction on encountering a kick. The device according to the invention works on detection of a static pressure difference.
, I, . - :
~L2~
U. S. Specifications Nos. 3941190 and 3503445 both show down hole packers but both packers are operated by tools which have to be pumped down the hole which would take several hours.
The invention provides a down hole blow ou* preventer comprising an elongated tubular housing having a through bore for the passage of drilling mud and means for connecting the ends of the housing into a drilling string, a packer element arranged circumferentially around the housing and inflatable into engagement with the bore hole to seal the hole, passage means extending through the housing wall for connecting the bore of the housing with the packer element to inflate the element by mud pressure from within the housing, a cylindrical valve sleeve mounted inside the housing for movement between a drilling position when the sleeYe closes said passage means and an inflating position when the passage means is open, a one-way valve for closing the housing bore on the side of the sleeve to be nearer the drill bit, said valve means being operable to allow the passage of mud under pump pressure, but not allowing reverse flow of mud, said valve sleeve providing a through bore for the passage of mud, second valve means for closing the bore in the valYe sleeve and means to close said second valve means automatically when pressure in the housing is reduced to a level below the pressure in the bore hole by a predetermined amount, the arrangement being such that after closing of the second valve means the pressure in the housing can be re-applied to urge the valve sleeve to its inflating position allowing the packer element to be inflated, means to prevent closure of the second valve means during running-in, a mud circulation channel extending through the housing on the side of the sleeve valve nearer the surface, means being provided to open said channel when the paclcer element is inflated whereby mud may be circulated through the drill string, the channel and the bore hole to increase the mud density, and means for deflating the packer element only when the mud density is sufficient to balance the pressure below the packer element.
The invention is also concerned with a method of using such a device.
A specific embodiment of a down hole blow out preventer (D.~. BOP) in accordance with the invention will now be described in detail with reference to the drawings in which:.-Figure l shows the D.H. BOP connected in a drill pipe-string run into a hole;
~21.~r~f~ 1l Figure 2 is a vertical sectional view of the P.H.BOP in the running-in position;
Figure 3 is a horizontal cross-section along line III-III in Figure 2;
5Figure 4 is a horizontal cross-section along line IV-I~ in Figure 2~
Figure 5 is a horizontal cross-section along line.V-~:in Figure 2;
Figure 6 shows a.vertical cross-sectional 10......................... yiew of the D.H.BOP, in drilling position;
Figure 7 is a horizontal cross-section along lin.e VII-~II in Figure 6,.
Figure 8 shows a vertical cross-sectional vie of the D.H.BOP during a wellkick after closing the flapper valye.
Figure 9 shows cortical cross~sectional tow of the D.H.BOP, with the packer inflated' Figure 10 shows.a.~ertical cross-sectional view of the D.H.BQP, with the circuIating port open.;
20Figure 11 is a horizontal cross-section along line XI-XI in Figure 10;
Figure 12 is a horizontal cross-section along line XII-XII in Figure 10, Figure:13 shows a vertical cross-section.al view of the D.H.BOP, deflating the packer' and Al 2~ 4 - s -Figure 14 shows a horizontal cross-section on the line XIV-XIV in Figure 13.
As can be seen from Figure 2 the D.H.BOP
comprises two barrels an outer barrel 1 and an inner barrel 2.
The inside of the outer barrel 1 and the outside of the inner barrel 2 are fine machined to the required tolerances.
The various channels and holes are milled and drillèd in the inner barrel 2 and after being machined the two barrels are shrunk together by undercooling of the inner barrei 2.
The position of the two barrels in relation to each other must be precise.
After shrinking the two barrels 1 and 2 together, the various ra.dial holes can be drilled and the channels for the fill-up.valve assembly 41, the grease bolt 1', the check.val~e 53, the circulating vale 57 and the equalising valve 62 can be drilled and machined.
The top of the outer barrel 1 is provided with an external thread 4 for connection with an API
threaded substitute 3 to enable the insertion of the inner parts of the D.H.BOP from the top.
The outer barrel 1, is provided at its lower . .. .. .. .. .... .... . . .. .
end with an internal thread 4' to connect it with a packersleeve 5.
The packersleeve 5 is at its bottom-end provided with a threaded API box connection 6 to connect it with the drilling bit.
Inside the packersleeve 5 a chamber is machined which is nearly as long as the packersleeve 5, and in which a floatvalve assembly 7 is inserted for sliding movement from a lower to an elevated position.
Floatvalve assembly 7 comprises a piston-like substantially hollow body 7' in which is mounted a conical valve 8 spring-loaded by spring 9 into sealing engagement with a valve seat, formed inside body 7', Valve 8 is fixed to valve stem iO which is guided for sliding up and down movement in guiding sleeve 11 mounted in bushing 12 which is fixed inside body 7 by means of a spider.
A snapring sleeve 13 is insexted into the top of packersleeye 5. The top of packersleeve 5 is provided with four pressure equalising channels 15 in the snapring sleeve 13.
Around snapring sleeve 13 a helical spring 16 is inserted before a snapring 17 is pressed over the snapring sleeve 13. . -A flappervalve sleeve 18 is pressed o'er the s snapring 17 mounted around snapring sleeve 13 until it sits in a snapring recess 19.
Flapper~alve sleeve 18 is proyided with a friction cam 20 which can be forced over the snapring 17 until snapring 17 snaps into snapring s]ot 21 of flapperyalve sleeve 18, by pump pressure when the flappervalve 22 is closed. The flappervalve 22 is pi~otally mounted on top of flapperyalve sleeve 18 and spring biased towards a closed position in which it is in sealing engagement with the top edge 18' of flappervalve sleeve 18. Closing movement is prevented by a flapperval~e release sleeve 23 during circulating and drilling.
The flappervalve release sleeve 23 comprises a plunger holder 24 to which are fixed two plungers 25 which are received into bores formed in a plunger housing 26.
The plunger holder 24 and the plunger housing 26 are provided with four pressure equalising channels 27 and 28 respectively.
A helical spring 29 bears with its cover end against the top of the plunger holder 24 with its upper end against a retainer ring 30 by which the tension of spring 29 can be adjusted. The retainer ring 30 is also provided with four pressure equalising channels 31~ A steel arresting ball biassed in~axdly by a calibrated helical spring rests in a circumferential groove in plunger holder 24.
By stopring 32 upward movement of the plunger holder 24 is limited to keep he plungers 25 inside the plunger housing 26.
Against the top of retainer ring 30 bears a helical spring 33 which bears with its other end against a shut-off sleeve 34 to keep the sleeve 34 in its highest position in which a channel 35 and a fill-up channel 36 are open see Figure 3).
The fill-up valve assembly 41 is shown in lO running-in position in Figures2 and 3 and in circulating or drilling position in Figures 6 and 7. It comprises a gate 41' having a substantially rectangular cross-section and running in a hole 42 which hole is closed at one end by locking nut 45 having a slotted part 46 in communication with a bore 35 in the body part 2. A
screen 47 covers a recess, formed in outer barrel l which is in communication with fill-up channel 36, and an inlet 48 which opens into flappervalve release channel 49. Channel 49 extends through inner barrel 2 and 20 opens into circumferential groove 50 formed in plunger housing 26 and ports 51 extend from g.roove 50 into the plunger cylinders.
The first purpose of the fill-up valve assembly 41 is to be in open position (Figure 3) to fill up the 25 drill pipe when running thedrill pipe into the hole and simultaneously to close off the flappervalve release :!
;
.,, channel 49 when running into the hole so that no pressure difference between the annulus and drillpipe can lift the plungers 25 and accidentally cause the flappervalve 22 to close.
Its second purpose is to close off the fill-up channel 36 once circulation or drilling has commenced.
The greater pressure inside the drill pipe is propagated through channel 35 to gate 41 and moves the gate 41 to close the fill-up channel 36, against the lesser pressure in the annulus as shown in Figure 7. When the gate 41 moves it also closes the fill up channel 36 and mud will fill the fluid lock 52.
The shut-off sleeve 34 is moyed downardly when circulation is started and to increase the pressure drop an aluminium disc 37' with an orifice may be provided - by means of threaded ring 37 which disc will be disintegrated during circulation. The position is shown in Figure 6.
When the shut-off sleeve 34 moves downwardly against the tension of spring 33, the locking spring snaps into the locking groove 39 formed in the inner wall of inner barrel 2 and shuts off the channels 35 and 36. The shut-off sleeve 34 is provided with three pressure equalising channels 40.
After the shut-off sleeve 34 has mowed `` ~.2~
I] o -downwardly to close channel 35 the entrapped mud in the fluid lock 52 will cause khe fill-up channel 36 to be permanently closed while the flappervalve release channel 49 remains open. The plungers 25 are from now on permanently connected to and subjected to the pressure in the annulus through inlet 48 and channel 49.
Another purpose of the fill-up valve assembly is to provide the possibility to calibrate the tension of the spring loaded steel ball 23' (Figure 2) and the spiral spring 29 before running the D.H.BOP into the hole. The spring loaded steel ball 23' is there to prevent fluttering of the flapper.valve release sleeve 23 by pressures lower than the setting of the spring 29 for releasing the flapper ale 22.
To enable calibration of the spring loaded steel ball ~3' and the spiral opening 29 the fill-up valve gate 41 is set in the drilling position as shown in Figure 7 whereafter a grease pump with a pressure gauge is connected to the threaded inlet 48 leading to flapper.val~e release channel 49. The ten.sion set for the spiral spring 29 depends on the maximum expected penetration rate per hour, the hole size, the depth of the hole, the pump volume and the cross sectional area of the plungers 25.
Easy to read chaxts can be developed for this l Z
purpose.
The required spriny tension is the tension required to overbalance the greater hydrostatic head of the mud column in the annulus caused by the presence of drilled formation cuttings when the pump is stopped.
A checkvalve 53 is provieed to allow mud to enter and to inflate the inflatable packer element 54 when the flappervalve 22 has been released and closed, and the flapperval~e sleeve 18 has been pumped down to uncover the inflating port 55. This operation will be described later. Mud can then be pumped through port 55 and channel 56 into packer element 54. The check valve 53 closes and retains the mud in the inflatable packer element 54 when the pressure in the drillpipe drops.
It will be seen that the outside diameter of the outer barrel 1 has a partly enlarged diameter la, which is proyided with spiral grooves 16 figure 4) like an undersized solid body stabilizer.
The enlarged diameter provides protection for the packer element 54. Furthermore a steel ring 54' at the bottom end of the packer element 54 is connected to the packer sleeve 5 by means of shearpins 54''.
This to protect the packer element whilst running into the hole and to withstand rotational forces when drilling.
--`` 3L2~ Z
The shearpins 5~'' are sheared when the packer 54 is inflated say at a pressure of 700 psi.
A shut-off valve assembly 57 is provided which is composed of a shut-off piston 57' with O-ring seals, a helical pressure spring 58 and a bushing 59 with a thread 59' for a grease nipple.
When running in and drilling (Figure 5), the shut-off piston 57' is isolated from the pressure inside the tool by the flappervalve sleeve 18 with which is provided O-ring seals (Figure 2). It is exposed to the pressure inside the tool when in inflating the packer element 54 the flappervalve sleeve 18 is pushed downardly and its friction cam 20 rides over the snapring 17 which then snaps into the slot 21 as will be described later.
The object of the shut-of-f piston 57' is to close the channel 60 while pump pressure is present within the tool, and to open the channel 60 when the pump is stopped. This is achieved by the pressure within the tool moving the piston 57l against the spring 58 to close the channel 60 from the annulus.
An equalising valve 62 is provided (Figure 5) which comprises an equalising piston 62, hazing a conical nose, a helical pressure spring 63 and a threaded bushing 64 in which bolt 65 is screwed.
The purpose of the equalising valve is to open the packer element to the channel 60 when the pressure in the annulus below the packer (which is fed to the valve via channel 66) is exceeded by 300 psi by the mud pressure which is above the packer. The mud pressure is present in channel 60 when piston 57' opens the channel 60 to the annulu.s~
When a kick i.s encountered and the packer element 54 has been inflated (Figure lO) then during circulation through the circulating channels 61 the equalising channel 60 is closed and no extra circulation pressure is behind the equalising piston 62. However when the pump is stopped and the shut-off pistion 57' is pushed back by spring 58 then. the equalising channel 60 is open to the mud pressure in the annulus so that the hydrostatic pressure acts on the conical nose of the equalising piston 62.
on the opposite side of the equalising piston 62 the formation pressure below the packer is received via equalising port 64 and aligned ports 67 and 68 formed in flappervalve sleeve 18 and snapring sleeve 13 respectively.
If now the mud weight is sufficiently increased to overbalance the formation porepressure and the pump is stopped then the hydrostatic head of the mud column 3l21;~
in the annulus above the packer exerts pressure against the equalising piston 62 and moves this piston until it opens the deflating channel 69 so that the pressure inside the packer element escapes into the annulus through equalising channel 60 assisting the equalising piston 62 to remain in open position (Figure 4).
The overpressure required to move and open the equalising piston 62 can be adiusted by means of the spring loaded ball 84 resting in groove 92 and can be tested with a grease pump having a pressure gauge when the grease nipple i5 screwed into the thread 57.
When the flappervalve sleeve 18 is pumped down after the packer element has been inflated, the mud below the flappervalve is trapped and, although of very small volume, the closed floatvalve 7 will move downwardly and compress the gas or liquid or squeeze it back into the formation against the formation pore pressure.
After the ~H.BOP is prepared fox running in, the D.~l.BOP can be run into the hole, so that it reaches eventually the position as shown in Figure 1. In Figure 1 is shown the D.H.BOP 70, interconnected between the drillpipe-string 71 and drillbit 72 and run into 25 hole 73 so that annulus 74 i5 formed. A casing 75 is -~15-cemented in the upper portion 73' of the hole 73, while at the surface a surface blow out preventer 76 of known type is provided below rotary table 77. Mud can be pumped by pump 78 t'nrough hose 79 and swivel 80 down into drillpipe-string 71, which mud then is ejected from drillbit 72 and flows upwardly through annulus 74. With reference numeral 81 a pressure gauge is shown.
When running in, the drillpipe is empty and the floatvalve 7 is closed and in its highest position (see Figure 2) so that no mud can enter the drillpipe through the bit nozzles and no formation cuttings can settle down inside the bit on top of the bit nozzles causing the bit to become plugged when circulation is started. The filling of the drillpipe takes place through the fill-up opening 36 and hole 42 of the fill-up gate 41.
The mud is screened by the mudscreen 47.
Figures 1 and 3 give a clear insight on the operation and position of each valve and part when running into the hole.
Attention should be given to the fact that when for one reason or the other circulation has been established during running into the hole, it will be necessary that the drillpipe will be filled from the ... , . .~............... .. ..
top of every stand to be run into the hole because after circulation the fill-up valve will be permanently closed as described herein aboveO
When the bit has reached the bottom of the hole the mudpumps are started and circulation is established through the floatvalve 7 and the bit nozzles. Figure 6 gives a clear insight on the operation and position of each valve and part when circulating or drilling.
Drilling may continue without encountering a kick and a roundtrip to change the bit is then made without having used the D.H.BOP.
When the bit is pulled and unscrewed, the floatvalve 7, the valve seat inside body 7' and the valve assembly circumferential body seals should be inspected and be in a good condition or changed for new ones before maklng-up a new bit.
ext, take out the threaded ring 37 from shut-off sleeve 34 with a set and pulling tool, and screw a set and pulling tool into the same thread and pull the shut-off sleeve 34 up until its highest position unscrew tool and screw in threaded ring 37 again.
The fill-up valve gate 41 has to be cleaned and to be xeset after each roundtrip. Unscrew locking nut 45, put grease nipple in the thread, pump out the , . - . . . . ., . ......... . . . .y .
- ~2~
housing 44 for gate piston ~3 together with the gate 41, clean and reinsert gate 41 and housing 44, use grease, set gate 41 in fill-up position with a set bolt "s"
and screw in locking nut 45, take out set bolt and tighten locking nut ~5. The D.H.BOP can be run again and is ready to operate again when necessary.
Figure 8 gives a clear insight of the operation and the position of each valve and part when a kick is encountered and the annulus is closed in by the surface BOP 76.
If a kick is encountered during drilling then the pumps are stopped, the standard pipe valve closed, the kelly picked-up and the annular BOP closedr The closed~in drill pipe pressure is then read and recorded. As soon as the pumps are stopped the floatvalve 7 will close due to the tension of spring 9.
As the well is completely closed-in, now pressure will be built up inside the well.
The floatvalve assembly-7 was in its lowest position when circulating. Now the pumps 78 (Figure 1) are stopped so that the closed floatvalve assembly 7 acts like a floating piston and when pressure below it is building up it can move upwardly making it possible to read the closed in drillpipe pressure (C.I.D.P.P.) from the pressure gauge 81 (Figure 1).
The C.I.D.P.P. + hydrostatic head of the mud column in the drillpipe = formation pore pressure.
If the kick is observed at an early stage then the time required for the C.I.D.P.P. to build up should be about ten (10] minutes, depending on the column of gas already produced in the annulus 74 (compression).
The C.I.D.P.P. is recored and the required mud weight calculated with sufficient overbalance over the formation pore pressure.
Now the C~I~D~PoP~ is slowly bled-off at the drillpipe. Wait a few seconds and start pump 78 slowly.
In the meantime the following occurs downhole:
When the well is closed in, the C.I.D.P.P. + hydrostatic head of the mud column in the drillpipe = closed in annular pressure t hydrostatic head of mud column in the annulus because these are co}~municating vessels with the floating floatvalv0 assembly 7 between them.
Say that the C.I.D.P.P. is 300 psi. and the pressure is bled-off at the drillpipe, now the annular pressure at the bottom of the hole is 300 psi.
higher than in the drillpipe. The floatvalve assembly 7 moves into its highest position and the pressure in the annulus 74 is propagated via the inlet 48 and through hole 42 in fill-up valve gate 41 through the flappervalve z~
release channel 49 underneath the plungers 25, which are then moved upwardly lifting the flappervalve release sleeve 23 until the spring biased flappervalve 22 falls on the seat 18' formed by the upper edge of flappervalve sleeve 18, which is then closed off (see Figure 8).
All above occurs when the C.I.D.P.P. is bled-off at the drillpipe.
Now the pump 78 is started very slowly.
Pressure builds up to abt. 1500 pse. and drops. Pump speed is increased to 100-200 gln/min. depending on the size of the D.H.BOP and the size of the circulating channels 59.
As shown in Figure 9 downhole the following occurs:
The flappervalve 22 is already closed. Pump 78 runs slowly. The flappervalve sleeve 18 is pushed downwardly by the pump pressure against the helical spring until the inlet 55 of the check valve 53 is uncovered and the 1appervalve sleeve 18 hits the snapring 17 with the calibrated friction cam 20~ Pressure is now building up and the packer element 5~ is inflated through inflation channel 56.
At about 1500 psi. the flappervalve sleeve 18 snaps With its friction cam 20 over the snapring 17 which is locked in the snapring slot 21 and the packer 52 is set.
-.20-As shown in Figure 10 when the snapring 17 is snapped into the snapring slot 21 the mud pushes shut-ofE piston 57' (Figure 8, 52) outwardly so that piston 57 closes channel 60.
In this position of the sleeve 18 mud can be circulated through the circulation ports 61. When circulation is established the drillstring is lowered to put some weight on the packer to make certain that the packer 54 is set.
. The packer 54 is now isolating the producin.
zone from the remaining portion of the hole.
The tool is closed-off at the bottom by the float.valve assembly 7 and from the top by the flappervalve 22.
When the mudweight has been increased by circulation to the required weight so that the hydrostatic pressure of the mud column above the packer 54 is overbalancing the pore pressure of the formation below the packer the pump should be stopped.
The chann.el 60 will then be opened by the pistion 57' and the equalising valve so that the packer is deflated and the string can be pulled out of the hole.
As shown in Figure 13 the following occurs downhole when the mud is overbalancing the formation pore pressure and the pump is stopped.
~Z~ }4~
When the pump is stopped the shut-off piston 57 ovens the equalisin~ channel 60.
The hydrostatic pressure of the mud column above the packer 54 acts on the one side of the equalising piston 62 which normally shuts off deflating channel 69.
The other side of the equalising piston 62 is connected through channel 66 and pOrtS 67, 68 with the space between the flapperva.lve 22 and the float 10 .~alve a.ssembly 7, below which the formation pore pressure acts.
If no the hydrostatic pressure ox the mud column in the annulus above the packer.54 overbalances sufficiently the formation pore pressure below the packer then the equalising piston 62 moves and opens the deflating channel 69. The pressure of abt. 1500 psi.
behind the packer element 54 i9 now released in the annulus through channels 69 and.60.and the packer elements deflates and the packer is free.
If the packer does not deflate then the recorded C.I.p.P.P. was not correct and the mudweight should be increased gradually and the pumps stopped at intervals.
When a well starts comin.g in during roundtripping the same procedure should be followed as during drilling but instead of pulling out continuously one should kill ~z~
~22-the well, unseat the packex and run back to bottom decreasing the mudweight when going deepex and cirCulating at 2ntervals.
Circulating takes then place through the circulating ports instead of through the bit nozzles.
When the bottom of the Cole is reached, condition the mud and pull-out to inspect all parts of the D.H.BOP.
An alternative use of the D.H.BOP i5 when drilling on the sea bed with a surface BOP positioned on the sea bed and it is desired to suspend drilling operations e.g. when weather us bad.
The surface BOP is first closed and the mud pressure within the string is bled down. Mud undar pressure is then forced into the annulus whereby the pressure in the annulus exceeds the pressure setting of the arresting ball and helical spring in the tool by at least the amount necessary to operate the D.H.BOP
to close the flapper valve. The packer element can then be inflated as before and this will seal the bottom end of the caslng and the drill string and the surface pipe from the sea bed to the drilling vessel can be removed.
Reconnecting the surface pipe and the drill pipe and releasing the packer can be achieved by closing the drill pipe at the surface and pressurising the annulus, below the clvsed BOP rays a thç surface, to open the eq~lising valve, whereafter the rams are opened.
An advantage of the DHP~P described is that in addition to controlling a well in a novei manner, a well can be hrought under control in the conventional manner. Ion this case on detecting a kick the surface BOP
is closed and the closed in drill pipe pressure is read. Instead of lowering the closed in pressure to close the flapper valve, the closed in pressure is maintained. The flapper valve does not close and the well can be brought under control in the normal way by the introduction of heavier mud.
,,
Claims (15)
PROPERTY OR PRIVILEGE IS CLAIMED ARE DEFINED AS FOLLOWS:
1. A down-hole blow-out preventer comprising an elongated tubular housing having a through bore for the passage of drilling mud and means for connecting the ends of the housing into a drilling string, a packer element arranged circumferentially around the housing and inflatable into engagement with the bore hole to seal the hole, passage means extending through the housing wall for connecting the bore of the housing with the packer element to inflate the element by mud pressure from within the housing, a cylindrical valve sleeve mounted inside the housing for movement between a drilling position when the sleeve closes said passage means and an inflating position when the passage means is open, a one-way valve for closing the housing bore on the side of the sleeve to be nearer the drill bit, said valve means being operable to allow the passage of mud under pump pressure, but not allowing reverse flow of mud, said valve sleeve providing a through bore for the passage of mud, second valve means for closing the bore in the valve sleeve and means to close said second valve means automatically when pressure in the housing is reduced to a level below the pressure in the bore hole by a predetermined amount, the arrangement being such that after closing of the second valve means the pressure in the housing can be re-applied to urge the valve sleeve to its inflating position allowing the packer element to be inflated, means to prevent closure of the second valve means during running-in, a mud circulation channel extending through the housing on the side of the sleeve valve nearer the surface, means being provided to open said channel when the packer element is inflated whereby mud may be circulated through the drill string, the channel and the bore hole to increase the mud density, and means for deflating the packer element only when the mud density is sufficient to balance the pressure below the packer element.
2. A device as claimed in claim 1 wherein there is means to allow mud to flow through the housing during running in whereby to allow the drill string to be filled during running in.
3. A device as claimed in claim 1 in which the second valve means is biased towards its closed position and there is means to hold the said valve means open which means is releasable on detection of a predetermined pressure difference between the bore hole and the bore of the housing.
4. A device as claimed in claim 2 in which the second valve means is biased towards its closed position and there is means to hold the said valve means open which means is releasable on detection of a predetermined pressure difference between the bore hole and the bore of the housing.
5. A device as claimed in claim 3 in which the second valve means comprises a flapper valve member at the upper end of the valve sleeve and the releasable holding means, comprises an upper flapper valve sleeve within the housing which sleeve is slidable axially within the housing between a first position in which the flapper valve is held open and a second position in which the flapper valve is released for movement to its closed position.
6. A device as claimed in claim 4 in which the second valve means comprises a flapper valve member at the upper end of the valve sleeve and the releasable holding means comprises an upper flapper valve sleeve within the housing which sleeve is slidable axially within the housing between a first position in which the flapper valve is held open and a second position in which the flapper valve is released for movement to its closed position.
7. A device as claimed in claim 5 in which the means to move the second sleeve to its second position comprises a piston and cylinder device which is open to the pressure in the bore hole.
8. A device as claimed in claim 6 in which the means to move the second sleeve to its second position comprises a piston and cylinder device which is open to the pressure in the bore hole.
9. A device as claimed in claim 1 in which means are provided to retain the valve sleeve in its inflating position and there is means operable when the sleeve is in its inflating position to deflate the packer element when the density of the mud reaches a value sufficient to overcome the pressure at the bore hole below the first valve means.
10. A device as claimed in claim 1 in which there is means to prevent deflation of the packer element when the mud is being circulated.
11. A device as claimed in claim 1 in which the first valve means comprises a valve body which is slidably axially in the housing between end stops and in sealing engagement with the housing whereby the pressure below the first valve means may be measured at the well head.
12. A device as claimed in claim 1 wherein an axially extending passageway in the housing is provided by making the housing of two concentric sleeves, machining the passageway in one of the sleeves on the surface of the sleeve to be adjacent the other sleeve and then joining the two sleeves together by a shrinking or expanding process.
13. A method of drilling using a drill hole blow out preventer as claimed in claims 1, 2 or 12 in conjunction with a surface blow out preventer wherein on a kick being detected, the surface blow out preventer is closed to close the bore hole at the surface, the pressure of the kick is measured at the surface, the drill string is depressurised so that the pressure in the bore hole is greater than that on the drill string which closes the second valve, pressure is then applied within the drill string to move the valve sleeve to its inflating position whereby the pressure within the drill string inflates the packer element, a valve with an orifice by passing the surface blow out preventer is opened and mud of an increased density is circulated through the drill string and the bore hole via the circulation channel, and the packer element is deflated when the pressure generated by the mud is sufficient to overbalance the pressure generated by the kick.
14. A method of using a drill hole blow out preventer as claimed in any of claims 1, 2 or 12 to close off a bore hole in conjunction with a surface blow out preventer wherein the surface blow out preventer is closed, mud is pumped into the bore hole at a pressure sufficient to close the second valve means, and mud is then circulated to the inside of the blow out preventer to inflate the packer element to close off the bore hole.
15. A method of drilling using a drill hole blow out preventer as claimed in claims 1, 2 or 12 in conjunction with a surface blow out preventer wherein on a kick being detected, the surface blow out preventer is closed to close the bore hole at the surface, the pressure of the kick is measured at the surface, and the well is brought under control in the conventional manner.
Applications Claiming Priority (2)
Application Number | Priority Date | Filing Date | Title |
---|---|---|---|
US46367483A | 1983-02-04 | 1983-02-04 | |
US463,674 | 1983-02-04 |
Publications (1)
Publication Number | Publication Date |
---|---|
CA1212042A true CA1212042A (en) | 1986-09-30 |
Family
ID=23840923
Family Applications (1)
Application Number | Title | Priority Date | Filing Date |
---|---|---|---|
CA000446732A Expired CA1212042A (en) | 1983-02-04 | 1984-02-03 | Down hole blow out preventer and method of use |
Country Status (9)
Country | Link |
---|---|
EP (1) | EP0116443B1 (en) |
JP (1) | JPS59145893A (en) |
AT (1) | ATE25868T1 (en) |
AU (1) | AU2405484A (en) |
BR (1) | BR8400483A (en) |
CA (1) | CA1212042A (en) |
DE (1) | DE3462619D1 (en) |
NO (1) | NO168131C (en) |
RO (1) | RO89841A (en) |
Families Citing this family (8)
Publication number | Priority date | Publication date | Assignee | Title |
---|---|---|---|---|
NO871995D0 (en) * | 1987-05-14 | 1987-05-14 | Smedvig A S Peder | Blowout preventer. |
NO180055C (en) * | 1992-10-16 | 1997-02-05 | Norsk Hydro As | Blowout for closing an annulus between a drill string and a well wall when drilling for oil or gas |
GB9516114D0 (en) * | 1995-08-05 | 1995-10-04 | French Clive | Improved downhole apparatus |
CA2228840A1 (en) * | 1995-08-05 | 1997-02-20 | Clive John French | Downhole apparatus |
NO325521B1 (en) * | 2006-11-23 | 2008-06-02 | Statoil Asa | Assembly for pressure control during drilling and method for pressure control during drilling in a formation with unforeseen high formation pressure |
EP2415960B1 (en) | 2007-07-27 | 2017-04-12 | Weatherford Technology Holdings, LLC | Continuous flow drilling systems and methods |
US9353587B2 (en) | 2011-09-21 | 2016-05-31 | Weatherford Technology Holdings, Llc | Three-way flow sub for continuous circulation |
US10006262B2 (en) | 2014-02-21 | 2018-06-26 | Weatherford Technology Holdings, Llc | Continuous flow system for drilling oil and gas wells |
Family Cites Families (6)
Publication number | Priority date | Publication date | Assignee | Title |
---|---|---|---|---|
US2858838A (en) * | 1955-11-10 | 1958-11-04 | Scaramucci Domer | Drill pipe float valve |
US3419040A (en) * | 1966-12-27 | 1968-12-31 | Edward J. Thibodeaux | Drill pipe valve having means for rendering it temporarily inoperative |
US3503445A (en) * | 1968-04-16 | 1970-03-31 | Exxon Production Research Co | Well control during drilling operations |
US3908769A (en) * | 1973-01-04 | 1975-09-30 | Shell Oil Co | Method and means for controlling kicks during operations in a borehole penetrating subsurface formations |
US3941190A (en) * | 1974-11-18 | 1976-03-02 | Lynes, Inc. | Well control apparatus |
US4294314A (en) * | 1979-12-31 | 1981-10-13 | Hydril Company | Inside blowout preventer well tool |
-
1984
- 1984-01-26 RO RO84113422A patent/RO89841A/en unknown
- 1984-01-31 JP JP59016918A patent/JPS59145893A/en active Pending
- 1984-01-31 NO NO840367A patent/NO168131C/en unknown
- 1984-02-02 EP EP84300664A patent/EP0116443B1/en not_active Expired
- 1984-02-02 DE DE8484300664T patent/DE3462619D1/en not_active Expired
- 1984-02-02 AT AT84300664T patent/ATE25868T1/en not_active IP Right Cessation
- 1984-02-03 AU AU24054/84A patent/AU2405484A/en not_active Abandoned
- 1984-02-03 BR BR8400483A patent/BR8400483A/en unknown
- 1984-02-03 CA CA000446732A patent/CA1212042A/en not_active Expired
Also Published As
Publication number | Publication date |
---|---|
AU2405484A (en) | 1984-08-09 |
EP0116443A1 (en) | 1984-08-22 |
DE3462619D1 (en) | 1987-04-16 |
RO89841A (en) | 1986-07-30 |
EP0116443B1 (en) | 1987-03-11 |
BR8400483A (en) | 1984-09-11 |
ATE25868T1 (en) | 1987-03-15 |
NO168131C (en) | 1992-01-15 |
NO840367L (en) | 1984-08-06 |
NO168131B (en) | 1991-10-07 |
JPS59145893A (en) | 1984-08-21 |
Similar Documents
Publication | Publication Date | Title |
---|---|---|
US5499687A (en) | Downhole valve for oil/gas well | |
US5494107A (en) | Reverse cementing system and method | |
US5890537A (en) | Wiper plug launching system for cementing casing and liners | |
US4986361A (en) | Well casing flotation device and method | |
US5641021A (en) | Well casing fill apparatus and method | |
US5181571A (en) | Well casing flotation device and method | |
US4694903A (en) | Flapper type annulus pressure responsive tubing tester valve | |
US4270569A (en) | Valve assembly for the remote control of fluid flow having an automatic time delay | |
US5335731A (en) | Formation testing apparatus and method | |
US4082298A (en) | Inflatable packer and valve mechanism therefor | |
US5150756A (en) | Well completion apparatus | |
US4588035A (en) | Down hole blow out preventer and method of use | |
US4979568A (en) | Annulus fluid pressure operated testing valve | |
US7066281B2 (en) | Formation fluid sampling and hydraulic testing tool and packer assembly therefor | |
EP0223553B1 (en) | Pressure operated downhole tool with releasable safety device | |
CA1212042A (en) | Down hole blow out preventer and method of use | |
US4881598A (en) | Blow-out preventor test tool | |
EP1070195A1 (en) | A valve, a float shoe and a float collar for use in the construction of oil and gas wells | |
CA2067587A1 (en) | Bypass valve | |
CA2446868C (en) | Apparatus and method for drilling a wellbore with casing and cementing the casing in the wellbore | |
US4577692A (en) | Pressure operated test valve | |
US5680902A (en) | Wellbore valve | |
US3373820A (en) | Apparatus for drilling with a gaseous drilling fluid | |
WO2020036920A1 (en) | Deep set production tubing pressure insensitive wireline retrievable safety valve | |
WO1999022114A1 (en) | Method and apparatus for shutting in a well while leaving drill stem in the borehole |
Legal Events
Date | Code | Title | Description |
---|---|---|---|
MKEX | Expiry |