BE557810A - - Google Patents

Info

Publication number
BE557810A
BE557810A BE557810DA BE557810A BE 557810 A BE557810 A BE 557810A BE 557810D A BE557810D A BE 557810DA BE 557810 A BE557810 A BE 557810A
Authority
BE
Belgium
Prior art keywords
slag
blast furnace
elements
tunnel
additions
Prior art date
Application number
Other languages
French (fr)
Priority date (The priority date is an assumption and is not a legal conclusion. Google has not performed a legal analysis and makes no representation as to the accuracy of the date listed.)
Publication of BE557810A publication Critical patent/BE557810A/fr

Links

Classifications

    • BPERFORMING OPERATIONS; TRANSPORTING
    • B28WORKING CEMENT, CLAY, OR STONE
    • B28BSHAPING CLAY OR OTHER CERAMIC COMPOSITIONS; SHAPING SLAG; SHAPING MIXTURES CONTAINING CEMENTITIOUS MATERIAL, e.g. PLASTER
    • B28B11/00Apparatus or processes for treating or working the shaped or preshaped articles
    • B28B11/24Apparatus or processes for treating or working the shaped or preshaped articles for curing, setting or hardening
    • B28B11/245Curing concrete articles
    • BPERFORMING OPERATIONS; TRANSPORTING
    • B28WORKING CEMENT, CLAY, OR STONE
    • B28BSHAPING CLAY OR OTHER CERAMIC COMPOSITIONS; SHAPING SLAG; SHAPING MIXTURES CONTAINING CEMENTITIOUS MATERIAL, e.g. PLASTER
    • B28B11/00Apparatus or processes for treating or working the shaped or preshaped articles
    • B28B11/24Apparatus or processes for treating or working the shaped or preshaped articles for curing, setting or hardening
    • BPERFORMING OPERATIONS; TRANSPORTING
    • B28WORKING CEMENT, CLAY, OR STONE
    • B28BSHAPING CLAY OR OTHER CERAMIC COMPOSITIONS; SHAPING SLAG; SHAPING MIXTURES CONTAINING CEMENTITIOUS MATERIAL, e.g. PLASTER
    • B28B15/00General arrangement or layout of plant ; Industrial outlines or plant installations
    • BPERFORMING OPERATIONS; TRANSPORTING
    • B28WORKING CEMENT, CLAY, OR STONE
    • B28BSHAPING CLAY OR OTHER CERAMIC COMPOSITIONS; SHAPING SLAG; SHAPING MIXTURES CONTAINING CEMENTITIOUS MATERIAL, e.g. PLASTER
    • B28B17/00Details of, or accessories for, apparatus for shaping the material; Auxiliary measures taken in connection with such shaping
    • B28B17/02Conditioning the material prior to shaping
    • BPERFORMING OPERATIONS; TRANSPORTING
    • B28WORKING CEMENT, CLAY, OR STONE
    • B28BSHAPING CLAY OR OTHER CERAMIC COMPOSITIONS; SHAPING SLAG; SHAPING MIXTURES CONTAINING CEMENTITIOUS MATERIAL, e.g. PLASTER
    • B28B23/00Arrangements specially adapted for the production of shaped articles with elements wholly or partly embedded in the moulding material; Production of reinforced objects
    • B28B23/0081Embedding aggregates to obtain particular properties
    • B28B23/0087Lightweight aggregates for making lightweight articles

Landscapes

  • Engineering & Computer Science (AREA)
  • Chemical & Material Sciences (AREA)
  • Ceramic Engineering (AREA)
  • Mechanical Engineering (AREA)
  • Structural Engineering (AREA)
  • Manufacturing & Machinery (AREA)
  • Curing Cements, Concrete, And Artificial Stone (AREA)

Description

       

   <Desc/Clms Page number 1> 
 



   Dans la fabrication d'éléments en ciment ou en béton, notamment en matériaux légers, l'inconvénient le plus désagréable est jusqu'ici le fait que la durée de durcissement des éléments moulés atteint jusqu'à 28 jeose, ce qui exige un vaste entrepôt pour les produits. De plus, la fabrication entraîne des pertes de temps indési- rables, qui résultent des différentes interruptions et des difficultés de transport qu'elles provoquent. Enfin les liants usuels, nécessaires en quantités relativement grandes, entraînent des dépenses très importantes. Tou- tes ces conditions imposent un nombreux personnel de   fabri'   cation et de direction.

   Un procédé de fabrication d'élé- ments moulés, mis en oeuvre sans interruption en partant de la préparation et du des matériaux jusqu'aux produits prêts à l'expédition, est inconnu jusqu'ici, par- ce que la longue durée de durcissement provoque déjà une interruption. 



   En outre, les éléments de construction en béton léger actuellement connus, durcis artificiellement à la vapeur contiennent encore jusqu'à 30% d'eau. Ils ne sont donc ni propres à l'expédition, car ils sont trop lourds, ni propres à la construction, car ils sont trop mouillés. 



   L'invention ne concerne pas seulement un procé- dé entièrement nouveau pour la préparation des matériaux nécessaires au moulage d'éléments agglomérés par du ci- ment, mais également un mode de préparation continu et automatique des additions, et de traitement des éléments comprenant le séchage et le durcissement, permettant de livrer à la rampe d'expédition des objets terminés, en six heures, c'est-à-dire dans les limites d'une journée d'équipe, par exemple des éléments de construction prêts au chargement,   c'est-à-dire   durcis et également séchés- 

 <Desc/Clms Page number 2> 

 Un avantage important consiste en ce que, selon l'inven- tion, le traitement du mélange composé d'additions et de liant, ainsi que le chauffage pour le séchage et le durcis- sement des éléments ont lieu par des moyens nouveaux. 



   Pour la mise en oeuvre du procédé selon l'inven- tion on se sert d'une installation, par exemple d'une bri- queterie comprenant certains appareils connus et mettant en oeuvre certaines opérations également connues, mais com- binées et utilisées d'une nouvelle manière pour donner un produit entièrement nouveau représentant un progrès important. A titre d'exemple, le fonctionnement d'une grande briqueterie selon l'invention, traitant en 24 heu- res environ 1500 tonnes de matériaux de départ, n'exige qu'environ 80 ouvriers et employés au lieu de 600 à 700, abstraction faite de la suppression du très vaste entre- pôt nécessaire au durcissement, de l'économie importante en énergie thermique, et de l'économie appréciable en liant usuel coûteux. 



   L'invention est principalement fondée sur le fait, confirmé par des essais, qu'un chauffage préalable du mélange composé d'additions et de liants modifie com- plètement le processus de durcissement par rapport aux procédés connus, le ciment utilisé provenant de   préféren-   ce de hauts-fourneaux parce que sa résistance à la com- pression est rapidement assurée par la chaleur. 



   Un autre avantage inconnu jusqu'ici consiste en ce que le mélange de départ destiné à la fabrication des éléments de construction, c'est-à-dire le mélange d'addi- tions et de liants, peut être proportionné à volonté pen- dant le procédé continu, ce qui permet de modifier rapide- ment la faculté d'isolement et la résistance à la compres- sion en fonction de la destination des éléments terminés. 



   Une autre particularité de l'invention consiste 

 <Desc/Clms Page number 3> 

 en ce qu'on peut utiliser des additions légères telles que la pierre ponce, la lave, notamment la lave spongieuse et le laitier de hauts-fourneaux, ainsi que le ciment comme liant, de préférence en combinaison avec du laitier de haut-fourneau en grains fins, ces constituants permet- tant de modifier les propriétés des éléments de construc- tion selon la qualité du mélange, et d'obtenir par exem- ple des éléments : a) à forte résistance à la compression avec une faculté d'isolement plus réduite, b) à grande faculté d'isolement avec une résis- tance à la compression plus réduite, c) à forte résistance à la compression avec une grande faculté d'isolement par addition de laitier de haut-fourneau et de ciment. 



   Un avantage particulièrement important consiste en ce que, selon l'invention, le laitier peut être pris à l'état liquide directement à la sortie d'un haut-four- neau pour être introduit dans cet état dans la briquete- rie, ce qui permet alors d'utiliser son énergie thermique et de le traiter pour l'utiliser lui-même. 



   Pour les diverses applications, il est égale- ment nécessaire d'utiliser les additions en grains de grosseurs différentes. D'une façon générale, le laitier de haut-fourneau destiné à être utilisé comme addition se présente en grains ayant des grosseurs allant de 1 à 10 mm, comme la lave et la pierre ponce, tandis que le lai- tier utilisé comme liant doit se présenter en grains n'ayant qu'une grosseur, inférieure à 1 mm, de préférence de 0 à 35/u . 



   Les additions légères telles que la pierre pon- ce, la lave et le laitier de hauts-fourneaux, qui doivent être introduites d'ans un mélangeur après leur lavage et criblage, ou même d'autres additions telles que le béton, 

 <Desc/Clms Page number 4> 

 
 EMI4.1 
 gravier, et.c... t.,-vr-r;:';. 'J.'s::'.)i"d a=i r # = g. #i ;; .?- =.. ,= .. > ¯ '';.- r;.':e::nple utt tar.njD.jr i.=o#;>i #i' =;* CË.l.citj.air.n-; .>,; 'ic.r-.'!;. o.;i-= suite dans le mélangeur dans lecuel sont. =;jzi;téJ 'Le <#:1-= i8 i1ut....f0ltl.nerJH Lr,):'4' .; .. ;¯ , .i, -. ==- ,; :r. i¯ .¯ = l." =. = ¯¯ a 'Lé- x # <; J dépf.1rt.

   En pa r.; < <.> L .:= ;: i:..é 8. - =... n i :1:.= j.'.- #= i . à; - i ;i gi<= é- 1 .: s 1 pré- paré arrive dans  des    distrib@@eurs   appropries   qui   le   font.   passer   Clans   les   machines     @@@ieu.   Les élémants moulés humides sortant de ces   mac@@@     @nemient   ensuite   dans   une installation de   chauffât;   ayant   @@@   lengueur   .de.   450 mè- tres, à tunnel en   serpentin..   dans lequel les éléments sont durcis et séchés. En sortant   de   ce tunnel les éléments sont amenés directement au   qu@i de   chargement et d'expé- dition. 



   Il est connu de durcir des éléments   moulés   frais daas une chambre   humide   alimentée par   uns   source de chaleur quelconque.   Cette   opération   ne @@ffit   cependant pas à l'obtention d'éléments de construction en   béton   léger pouvant être   expédies     imm@diatment   et   p@@s   à l'utilisation, parce que cas éléments durcis contiennent 
 EMI4.2 
 encore jusqu'à µJ0 jà Li'l;ii,x.u,-,±.n4.

   J;i;=:i;;, >.:¯iÔ =.¯i :=-i;é j,<=.Il-- pr6céde.-Pment les .µ'[.4,;:éii'i:.5 :'.e =##>#.si:1;=:#'#<.<>i#. :=<> l:.é..#=i;z léger ou poreux doivent   reposer     pré@@@@lement   l'air   @i-   
 EMI4.3 
 bre pendant une durée al':r..it J.ix<1,;.#à 3>;> gi=,i:.=:= . ;: : q:-;¯< n'est pas possible e 1:: u:n . i  ; : i#= J,;i i 1 ,i. 1= :..;: =i,#.i-; ;. , # ;=: ..; ¯= ;>;: .J¯ (i <; ¯ .Oc plus, la mise en plai... m, l; " =iili é#;>i.;:#<=ni, ;>¯1:; é,i¯ j;¯n#,:=>s (D2 les chanujres de <.::.ir;:1.:> ;;:#:r;:t, c-..'tt ii:'."..'.':,sL)::.;'.j.; ù.3 j;;.a;1.i;#;5 pert.-, 1: ":.-:.:- ¯¯: "'1'.--.,.!....."..- à ces incofivéi;iufit,,; i,,-1 1 .''.n' .j>;. =¯-.¯# u::;..'-;.'... d-.!.- =. qi=:=¯. ci>iiià et sec, J cÍl'3ut'l"3 ;t:; :;ià.1',ire:n##.c:

   ,'Si-' :¯<<;.,oe ....Ot.'-'cs de chaleur 1 µ<cupér.ée Cài;.u'l.-= :?Gi ;cj,i;";à.=; .'.'';-:t'5 -J..;..':.: l';= li,=.:=.:: tunnel en par''.:. - 1:) :.>#>uitc <...<) chaleur, i.=l.i t-.::..;':.','. 

 <Desc/Clms Page number 5> 

 d'un échangeur de chaleur, l'air très chaud et sec entrant par une extrémité du tunnel. Dans la deuxième moitié de ce tunnel en serpentin, les éléments moulés sont séchés à fond, et l'air chaud chargé de l'humidité résultant du séchage revient au point de départ à travers ia première moitié du tunnel de chauffage, dans laquelle cet air chaud et humide assure le durcissement pour retourner finalement à la source de chaleur. Il en résulte une économie de chaleur énorme qui.est capitale pour le rendement du pro- cédé selon l'invention. 



   L'ensemble du procédé comprend donc les opéra- tions consécutives suivantes : 
1. Le transport, éventuellement le lavage, ensuite le broyage et le criblage des additions ainsi que leur mouillage et chauffage jusqu'à une température de 30 à 60  C. 



   2. Le mélange des additions chauffées avec les liants, et la distribution du mélange aux machines à mouler. 



   3. L'introduction et l'entraînement des élé- ments moulés dans une installation de durcissement con- nue en principe; dans laquelle un courant d'air très chaud et sec circule en circuit fermé d'une manière nou- velle et dans le sens opposé au cheminement des éléments moulés, ce courant d'air chaud sortant par l'orifice d'entrée des éléments pour être ramené à travers un échan- geur de chaleur vers la source de chaleur en vue de son séchage et de son réchauffage. 



   4. Le transport des éléments terminés vers le quai de chargement et d'expédition. 



   Le traitement de 50 à 100 -tonnes de matériaux exige pour les opérations de transport et de mélange environ 1 heure, tandis que le cheminement à travers 

 <Desc/Clms Page number 6> 

 l'installation de chauffage s'étend sur une durée de 6 heures, ce qui permet à trois équipes consécutives de produire environ 1500 tonnes de produits secs sous la forme d'éléments prêts au chargement et à l'exédition. 



  On peut également atteindre ce rendement en utilisant du laitier de haut-fourneau liquide comme constituant pour le mélange de départ. 



   Lorsqu'on utilise du laitier de haut-fourneau en grains ayant des grosseurs déterminées, notamment de 0 à 35 /u et de 1 à 10 mm, on peut économiser jusqu'à 90 % des liants usuels tels que le ciment de Portland. 



  La briqueterie pour la mise en oeuvre du procédé selon l'invention comprend essentiellement six groupes d'appa- reils : 
I. Les appareils pour le transport des addi- tions et pour leur préparation, c'est-à-dire les appa- reils de lavage, de criblage, de broyage et de pulvérisa- tion.qui doivent fournir les grains ayant les grosseurs désirées. 



   II. Ces appareils sont suivis d'un appareil de chauffage préalable, qui peut être similaire à un tambour rotatif de calcination. 



   III. Le mélange chauffé formé par les additions, telles que la pierre ponce, la lave et le laitier de haut-fourneau, passe ensuite dans une cuve de distribu- tion communiquant avec les mélangeurs, dans lesquels sont introduits les liants préparés, c'est-à-dire le ciment de Portland et le laitier de haut-fourneau, ou ciment de haut-fourneau finement pulvérisé. 



   IV. Les mélangeurs sont reliés aux machines à mouler qui sont alimentées en mélange chaud par des dis- tributeurs secondaires, et équipées d'une manière connue en soi de moules à secousses. Devant les postes récep- 

 <Desc/Clms Page number 7> 

 teurs des éléments terminés passe un transporteur, de pré- férence à cages suspendues, dans lesquelles les éléments terminés sont déposés automatiquement. 



   V. Ces cages ainsi chargées cheminent ensuite à travers l'installation de durcissement et de séchage formée par le tunnel en serpentin, dans lequel un courant d'air chaud et see circule dans le sens opposé au chemi- nement des cages. 



   VI. La source fournissant l'énergie nécessaire est une centrale de force motrice, et une installation à haut-fourneau fournit éventuellement le laitier   nécessai-   re ainsi que la chaleur à récupérer dans ce laitier. 



   On doit ajouter les appareils auxiliaires tels que cribles, broyeurs, préparateurs de liant et doseurs de proportions, la source de chaleur récupérée avec son échangeur de chaleur, l'appareil destiné à faire circuler en circuit fermé l'air chaud et sec, l'appareil régula-   teur¯de   la température, de l'humidité, de la résistance à la compression de l'énergie engendrant les secousses, etc... 



   Lorsqu'on utilise le laitier de haut-fourneau, une partie importante de l'invention est également formée par le groupe du haut-fourneau fournissant ce laitier, une partie de ce laitier liquide étant alors utilisée pour la préparation d'une addition poreuse, tandis que l'autre partie est divisée en grains fins pour être uti- lisée comme liant. Le laitier liquide sortant du haut- fourneau est débarrassé autant que possible du fer et re- froidi brusquement dans une cuve d'eau. Les additions poreuses et les grains massifs destinés au liant se sépa- rent automatiquement, et les deux parties sont distri- buées aux mélangeurs après le criblage. 



   La vapeur d'eau dégagée pendant le refroidis- 

 <Desc/Clms Page number 8> 

 sement brusque du laitier est utilisée directement, ou introduite dans des accumulateurs ou des échangeurs de cha- leur; et on l'utilise pour le séchage et le durcissement, ce qui permet de réaliser une économie surprenante de com- bustible par rapport à la quantité nécessaire jusqu'ici. 



   Pour la récupération de la chaleur du laitier liquide par refroidissement brusque dans l'eau, on débar- rasse d'abord le laitier autant que possible du fer avant le refroidissement, parce que ce fer présente un risque d'explosion, l'eau étant décomposée par le fer en fusion. 



   Pour le traitement continu du laitier liquide et la récupération continue de sa chaleur sous la forme de vapeur, une autre particularité de l'invention consis- te en ce que l'introduction du laitier et de 11-eau dans la cuve de refroidissement brusque, ainsi que l'évacua- tion de la vapeur et du laitier   solidifié   de préférence chaud sont réglées automatiquement par des appareils de commande connus en   soi."   
L'opération du refroidissement brusque est de préférence précédée d'un réglage de la température du laitier encore liquide, ce qui permet d'obtenir des pro- duits à base de laitier ayant des propriétés différentes en fonction de la température, en partant de laquelle est effectué le refroidissement brusque.

   Ainsi, en par- tant d'un laitier d'une température relativement élevée, par exemple d'environ 1400  C, on obtient par refroidis- sement brusque un produit spongieux. Le refroidissement brusque d'un laitier d'une température moyenne, par exem- ple d'environ 1300  C, donne un produit vitreux. Enfin le refroidissement brusque d'un laitier d'une tempéra- ture relativement basse, par exemple d'environ   12000   C, donne un produit cristallisé. 



   Pour l'utilisation du laitier liquide dans le 

 <Desc/Clms Page number 9> 

 procédé selon l'invention, on peut également diviser en plusieurs parties le laitier liquide sortant du haut-four- neau en vue de l'obtention de produits à base de laitier ayant des propriétés différentes. Les diverses parties de laitier sont ensuite séparément amenées à des niveaux de température différents. 



   De cette manière on peut obtenir simultanément et d'une manière continue des produits différents sans interruption du fonctionnement de l'installation, et sans modification des appareils de récupération, ce qui offre notamment cet autre avantage que les appareils de traite- ment complémentaires des différents produits peuvent   travailler/sans   interruption. 



   La briqueterie prise comme exemple est repré- sentée schématiquement sur le dessin annexé. les figures 1 et la montrent l'installation de manutention avec les appareils de criblage et de broyage I suivis d'un chauffeur II, d'un mélangeur et d'un distributeur III, tandis que les machines .à mouler IV sont disposées à l'étage le plus bas; - la figure 2 montre séparément le groupe III avec les mélangeurs et les distributeurs, - les figures 3 et 3a sont une vue en plan de l'installation comprenant le tunnel de durcissement et de séchage V; - la figure   4   montre l'installation précédant les groupes I et III et comprenant le haut-fourneau ainsi que les appareils destinés au refroidissement brusque, au criblage, au broyage et à la récupération de la cha- leur ;

   - la figure 5 est une vue schématique en plan et montre certains détails de l'installation de refroi- dissement brusque du laitier de haut-fourneau; les figuras 1 et la représentent les groupes -   lU -   

 <Desc/Clms Page number 10> 

 I,II,III et IV. Le groupe I comprend les silos 1 et 2 contenant les additions telles que la pierre ponce, la lave spongieuse, éventuellement d'autres additions comme le laitier de haut-fourneau. Des élévateurs   4     t   5 char- gent ces additions dans la trémie 7 combinée avec un ap- pareil de criblage. Les grains retenus, d'une grosseur supérieure à 1 - 10 mm, sont introduits dans le broyeur 8.

   Les grains des additions réduits à la grosseur néces- saire descendent par une goulotte en pente 9 dans le tambour rotatif de calcination 10, qui les porte à une température de 30 à 60  C. Les additions sortant du tam- bour tombent dans un distributeur 11, duquel partent des transporteurs 12 aboutissant aux mélangeurs 14. En de- hors des additions, telles que la pierre ponce, la lave spongieuse, etc..., la trémie 7 reçoit également comme addition du laitier pulvérisé de haut-fourneau dans une      proportion désirée. Ce laitier est chauffé avec les au- tres additions dans le tambour 10.

   Les mélangeurs 14 re-   çoivent   d'un collecteur 3 du liant sous la forme de lai- tier de haut-fourneau finement pulvérisé, en grains d'une grosseur de 0 à 1 mm, de préférence de 0 à 35 /u , éven- tuellement un complément de ciment de Portland dans une proportion allant jusqu'à 10 % de la masse du liant. 



  Le mélange sortant des mélangeurs 14 est amené par les transporteurs 15 aux machines de moulage 16 équipées d'ap- pareils générateurs de secousses 18. Les éléments façon- nés par moulage dans ces machines sont empilés en 20. 



  Les éléments empilés sont chargés automatiquement dans les cages suspendues d'un transporteur 21, qui les fait cheminer dans le tunnel en serpentin 22 jusqu'à ce qu'ils arrivent à la fin du circuit fermé aux postes d'enlève- ment 23, où ils sont déposés sur le quai de chargement et d'expédition 24. 

 <Desc/Clms Page number 11> 

 



   Le laitier utilisé comme addition et comme liant arrive d'un haut-fourneau 33 par un conduit   34   dé- bouchant dans une cuve à eau 35. Le laitier passe préa- lablement dans des appareils destinés à le débarrasser du fer qu'il contient éventuellement, et qui seront décrits plus loin en regard de la figure 5. Le laitier liquide est brusquement refroidi dans la cuve à eau, et le laitier refroidi, mais encore chaud, est repris par un élévateur 36 qui le dépose sur un transporteur à courroie 37, duquel il tombe dans un appareil de criblage   38.   Les gros grains retenus par le crible sont repris par un éléva- teur 39 et déposés sur un transporteur qui les fait pas- ser dans la trémie 7 du groupe I.

   Les grains traversant le crible, d'une grosseur de 0 à 1 mm, et destinés à servir de liant, sont recueillis par un transporteur   40   qui les dépose dans un pulvériseur   41,   qui reçoit égale-      ment du ciment de Portland provenant de la trémie 42. 



  Le liant ainsi préparé, de préférence en grains d'une grosseur de 0 à 35 /u , passe par le conduit   43   dans le collecteur 3 du groupe III. 



   On a trouvé que le laitier de haut-fourneau finement pulvérisé est un excellent liant, et sert de constituant principal du liant dans le mélange de départ avec une proportion convenablement choisie de ciment de Portland, ce constituant principal pouvant être dosé en fonction de la résistance mécanique, de la faculté d'iso- lement, et de la durée de durcissement ainsi qu'il a été indiqué précédemment. 



   Les vapeurs (composées d'air et de vapeur d'eau) dégagées dans la cuve à eau 35 et dans les cuves 35a, 35b et 35c passent par les tuyauteries 44 du groupe V et les tuyauteries   44a,     44b   et 44c dans l'échangeur de cha- leur 30, dans lequel ces vapeurs humides sont utilisées 

 <Desc/Clms Page number 12> 

 pour le chauffage de l'air sec, qui passe ensuite dans le chauffeur 32 pour être porté à la température néces- saire au séchage dans le tunnel de séchage et de durcisse- ment.

   Cet air chaud entre dans le tunnel en serpentin par l'orifice de sortie des éléments moulés, et circule dans le sens opposé au cheminement de ces éléments, d'a- bord dans la deuxième moitié du tunnel 22 pour sécher les éléments durcis mais encore très humides, en absor- bant l'humidité dégagée de ces éléments, ensuite dans la première moitié, dans laquelle la vapeur humide assure le durcissement des éléments fraîchement moulés, qui dé- gagent ainsi un complément de chaleur. L'air chaud et humide sortant du tunnel passe par le conduit 31 dans l'échangeur de chaleur 30 pour être réchauffé, et pour repasser ensuite en circuit fermé dans le tunnel. 



   Pour que le fonctionnement continu de l'ensem- ble de l'installation soit bien assuré, le conduit dtar- rivée du laitier 34, le conduit d'entrée de l'eau et les tuyauteries de circulation 36 et   44   pour le laitier et les vapeurs sont munis de dispositifs régulateurs dépen- dants les uns des autres, et agencés d'une manière connue en soi (non représentée sur le dessin). Les vapeurs (com- posées d'air et.de vapeur d'eau) sont aspirées d'une manière continue dans la cuve 35. A cet effet on peut intercaler un ventilateur approprié ou un appareil si- milaire dans la tuyauterie 44. 



   Les différents appareils de contrôle et de commande sont installés dans un poste central. L'appa- reil 26, par exemple, sert au réglage de la résistance à la compression des   éléments   moulés, et il est relié à l'appareil 29 destiné à régler l'humidité des éléments. 



  L'appareil 27 sert ,Au contrôle et au réglage de l'inten- 

 <Desc/Clms Page number 13> 

 sité des secousses appliquées aux machines à mouler, tandis que l'appareil 28 contrôle et commande la tempéra- ture dans le tunnel en serpentin 22. En 45 est indiquée la centrale de force motrice faisant fonctionner toute l'installation, et qui permet éventuellement d'utiliser la chaleur récupérée dans le laitier, par exemple. 



   Ainsi qu'il a été indiqué précédemment on peut au besoin ajouter au mélange de pierre-ponce, lave, etc.. du laitier basique de haut-fourneau comme addition ou liant selon la grosseur des grains pour l'obtention d'une résistance suffisante à la compression et à la rupture des éléments terminés.

   Par exemple, les propor- tions des différentes grosseurs des grains peuvent être les suivantes : 
0 à 50   /u ,   environ 10 % (du poids de la masse   totaledes   additions) 
50 à 200/u, environ 1%" 
1 à   3   mm , environ 5 % " 
3 à 10 mm , environ 15 % " 
Au lieu de la grande quantité des liants usuels du commerce nécessaire jusqu'ici, il suffit donc d'ajou- ter 1 à 2   % du   poids de la masse totale du mélange, ce qui représente une économie extrêmement importante dans l'industrie de la fabrication des éléments de construc- tion légers. 



   Le groupe III contient les mélangeurs qui sont de préférence prévus par paires, parce qu'il est néces- saire de les nettoyer et même de les réparer assez fré- quemment. Il est alors facile de mettre en circuit l'un ou l'autre des mélangeurs sans contrarier le fonctionne- ment de l'installation. Il en est de même en ce qui con- cerne les machines à mouler 16, 18 du groupe IV. Grâce 

 <Desc/Clms Page number 14> 

 au doublage de ces appareils, le fonctionnement continu de l'installation est assuré par leur utilisation alter- née. 



   La figure 5 est une vue en plan d'un   disposi-   tif pour le refroidissement brusque du laitier de haut- fourneau. Le haut-fourneau 33 est muni de la manière usuelle d'une tubulure de coulée 52 pour le fer, et d'un collecteur de coulée 34 pour le laitier. 



   Le collecteur 34 du laitier communique par trois tubulures 54, 55, 56 avec des bacs 57, 58, 59, dans lesquels le laitier liquide est amené à la tempéra- ture désirée avant le refroidissement brusque, et passe ensuite dans des cuves de refroidissement brusque corres- pondantes 35a, 35b, 35c. 



   On peut par exemple amener le laitier à   1400    dans le bac 57, à 1300  dans le bac 58, et à 1200  dans      le bac 59 avant de le faire passer dans la cuve de re- froidissement brusque correspondante. Le laitier refroi- di est ensuite respectivement repris dans les cuves. 



  Pour les températures indiquées, la cuve 35a donne par exemple un laitier spongieux, la cube 35b un laitier vitreux et homogène, et la cuve 35c un laitier cristal- lisé. 



   Dans l'exemple représenté sur la figure, le collecteur 34 est formé par une partie élargie de la tu-   ulure   de coulée du laitier. Du fond de ce collecteur part également une tubulure complémentaire 53, tandis que les tubulures 54, 55, 56 sont raccordées à un niveau plus élevé. 



   La tubulure 53 sert à l'évacuation de la majeu- re partie du fer que contient encore le laitier. Grâce à sa densité plus grande, le fer se dépose dans le col- lecteur 34 et peut ensuite s'écouler par la tubulure 53, de sorte que le laitier passant dans les cuves de refroi- 

 <Desc/Clms Page number 15> 

 dissement brusque 35a, 35b, 35c ne contient tout au plus      que des proportions insignifiantes de fer. 



   A l'opposé de ce que montre la figure schéma- tique, l'espace autour du haut-fourneau n'est fréquemment pas suffisant pour l'installation'destinée au refroidis- sement brusque du laitier. Le collecteur   34   est alors remplacé par des poches mobiles, munies dans le bas d'une tubulure similaire à la tubulure 53 et destinée à l'éva- cuation du fer. Ces poches mobiles sont alors vidées dans des bacs collecteurs séparés du haut-fourneau, cor- respondants aux bacs 57, 58, 59 destinés au refroidisse- ment préalable du laitier. Au lieu de munir les poches de tubulures pour l'évacuation du fer, on peut prévoir ces tubulures sur chacun des bacs, et ces derniers peu- vent même être complémentairement munis de ces tubulures partant du fond.

   L'essentiel est que le laitier soit débarrassé de la majeure partie du fer avant le refroidis- sement brusque. 

**ATTENTION** fin du champ DESC peut contenir debut de CLMS **.



   <Desc / Clms Page number 1>
 



   In the manufacture of cement or concrete elements, especially lightweight materials, the most unpleasant drawback so far is the fact that the hardening time of the molded elements reaches up to 28 jeose, which requires a large warehouse. for products. In addition, the production involves undesirable losses of time, which result from the various interruptions and the transport difficulties which they cause. Finally, the usual binders, necessary in relatively large quantities, entail very high costs. All these conditions impose a large number of manufacturing and management personnel.

   A process for the manufacture of molded parts, carried out without interruption from preparation and materials to products ready for shipment, is heretofore unknown, because the long curing time already causes an interruption.



   In addition, the currently known lightweight concrete construction elements, which are artificially steam-hardened, still contain up to 30% water. They are therefore neither fit for shipping, because they are too heavy, nor fit for construction, because they are too wet.



   The invention relates not only to an entirely new process for the preparation of the materials necessary for the molding of elements agglomerated by cement, but also to a method of continuous and automatic preparation of the additions, and of the treatment of the elements comprising the cement. drying and curing, making it possible to deliver finished items to the shipping ramp in six hours, i.e. within a shift day, for example construction elements ready for loading, i.e. hardened and also dried-

 <Desc / Clms Page number 2>

 An important advantage is that, according to the invention, the treatment of the mixture composed of additions and binder, as well as the heating for drying and hardening of the elements takes place by novel means.



   For the implementation of the method according to the invention, use is made of an installation, for example a brickyard comprising certain known apparatuses and implementing certain operations also known, but combined and used by a new way to produce an entirely new product representing significant progress. By way of example, the operation of a large brickyard according to the invention, treating in 24 hours about 1500 tonnes of starting materials, requires only about 80 workers and employees instead of 600 to 700, abstraction made of the elimination of the very large warehouse necessary for the hardening, of the significant saving in thermal energy, and of the appreciable saving by costly usual binding.



   The invention is mainly based on the fact, confirmed by tests, that preheating the mixture composed of additions and binders completely modifies the hardening process compared to known methods, the cement used coming from preferentially. this blast furnace because its resistance to compression is quickly ensured by heat.



   Another advantage hitherto unknown is that the starting mixture intended for the manufacture of the building elements, that is to say the mixture of additions and binders, can be proportioned as desired during the continuous process, which makes it possible to quickly modify the insulation capacity and the compressive resistance according to the destination of the finished elements.



   Another feature of the invention consists

 <Desc / Clms Page number 3>

 in that light additions such as pumice stone, lava, especially spongy lava and blast furnace slag, as well as cement as a binder can be used, preferably in combination with blast furnace slag in fine grains, these constituents make it possible to modify the properties of the building elements according to the quality of the mixture, and to obtain, for example, elements: a) with high compressive strength with a more insulating capacity. reduced, b) high isolating power with lower compressive strength, c) high compressive strength with high isolating ability by addition of blast furnace slag and cement.



   A particularly important advantage consists in that, according to the invention, the slag can be taken in the liquid state directly at the outlet of a blast furnace in order to be introduced in this state into the brickyard, which then makes it possible to use its thermal energy and to process it to use it itself.



   For the various applications it is also necessary to use the grain additions of different sizes. In general, blast furnace slag intended for use as an addition is in grains ranging in size from 1 to 10 mm, such as lava and pumice stone, while slag used as a binder should be in grains having only one size, less than 1 mm, preferably 0 to 35 µm.



   Light additions such as sandstone, lava and blast furnace slag, which must be introduced into a mixer after washing and screening, or even other additions such as concrete,

 <Desc / Clms Page number 4>

 
 EMI4.1
 gravel, et.c ... t., - vr-r ;: ';. 'J.'s ::'.) I "da = ir # = g. #I ;;.? - = .., = ..> ¯ ''; .- r;. ': E :: nple utt tar.njD.jr i. = o #;> i #i '=; * CË.l.citj.air.n-;.> ,;' ic.r -. '!;. o.; i- = continued in the mixer in the current one are. =; jzi; téJ 'Le <#: 1- = i8 i1ut .... f0ltl.nerJH Lr,):' 4 '.; ..; ¯, .i, -. = = -,;: r. ī .¯ = l. " =. = ¯¯ a 'L- x # <; J depf.1rt.

   In by.; <<.> L.: =;: I: .. é 8. - = ... n i: 1:. = J .'.- # = i. at; - i; i gi <= é- 1.: s 1 prepared arrives in appropriate distributors who do so. pass through the machines @@@ ieu. The wet molded elements coming out of these machines then go into a heating installation; having @@@ lengueur .de. 450 meters, serpentine tunnel .. in which the elements are hardened and dried. On leaving this tunnel, the items are brought directly to the loading and shipping qu @ i.



   It is known to harden fresh molded elements in a humid chamber supplied by any heat source. However, this operation does not affect the production of lightweight concrete construction elements that can be shipped immediately and ready for use, because hardened elements contain
 EMI4.2
 again up to µJ0 j to Li'l; ii, x.u, -, ± .n4.

   J; i; =: i ;;,> .: ¯iÔ = .¯i: = - i; é j, <=. It-- precedes. -Pment the .µ '[. 4,;: éii'i : .5: '. E = ##> #. If: 1; =: #' # <. <> I #. : = <> l: .é .. # = i; z light or porous must rest pre @@@@ lament the air @ i-
 EMI4.3
 bre for a period al ': r..it J.ix <1,;. # to 3>;> gi =, i:. =: =. ;:: q: -; ¯ <is not possible e 1 :: u: n. i; : i # = J,; i i 1, i. 1 =: ..;: = i, #. I-; ;. , #; =: ..; ¯ =;> ;: .J¯ (i <; ¯ .Oc plus, setting ... m, l; "= iili é #;> i.;: # <= Ni,;> ¯1: ; é, ī j; ¯n #,: => s (D2 chanujres de <. ::. ir;: 1.:> ;;: #: r;: t, c - .. 'tt ii: '. "..'. ':, sL) ::.;'. j .; ù.3 j ;;. a; 1.i; #; 5 pert.-, 1:": .-:.: - ¯¯: "'1' .--.,.! ....." ..- to these incofivéi; iufit ,,; i ,, - 1 1. ''. N '.j> ;. = ¯-.¯ # u ::; ..'-; .'... d -.! .- =. Qi =: = ¯. Ci> iiià and sec, J cÍl'3ut'l "3; t: ;:; ià.1 ', ire: n ##. c:

   , 'Si-': ¯ <<;., Oe .... Ot .'- 'cs of heat 1 µ <cupér.ée Cài; .u'l .- =:? Gi; cj, i; "; at. =;. '.' '; -: t'5 -J ..; ..':.: l '; = li, =.: =. :: tunnel in par' '.:. - 1: ):.> #> uitc <... <) heat, i. = li t -. :: ..; ':.', '.

 <Desc / Clms Page number 5>

 heat exchanger, very hot, dry air entering through one end of the tunnel. In the second half of this serpentine tunnel, the castings are thoroughly dried, and the hot air laden with moisture resulting from drying returns to the starting point through the first half of the heating tunnel, in which this air. hot and humid ensures curing to eventually return to the heat source. This results in an enormous heat saving which is essential for the efficiency of the process according to the invention.



   The entire process therefore comprises the following consecutive operations:
1. Transport, possibly washing, then crushing and screening of the additions as well as their wetting and heating to a temperature of 30 to 60 C.



   2. Mixing the heated additions with the binders, and distributing the mixture to the molding machines.



   3. The introduction and entrainment of the molded elements in a curing plant known in principle; in which a current of very hot and dry air circulates in a closed circuit in a new way and in the direction opposite to the path of the molded elements, this current of hot air exiting through the inlet orifice of the elements for be returned through a heat exchanger to the heat source for drying and reheating.



   4. Transportation of finished items to the loading and shipping dock.



   The processing of 50 to 100 tons of material requires for the transport and mixing operations about 1 hour, while the routing through

 <Desc / Clms Page number 6>

 the heating installation extends over a period of 6 hours, which allows three consecutive teams to produce around 1,500 tonnes of dry products in the form of elements ready for loading and shipping.



  This efficiency can also be achieved by using liquid blast furnace slag as a component for the starting mixture.



   When using granular blast furnace slag having determined sizes, in particular from 0 to 35 µm and from 1 to 10 mm, up to 90% of the usual binders such as Portland cement can be saved.



  The brickyard for implementing the method according to the invention essentially comprises six groups of devices:
I. Apparatus for conveying additions and for their preparation, that is to say apparatus for washing, screening, crushing and pulverizing. Which must provide grains of the desired size .



   II. These devices are followed by a preheater, which can be similar to a rotating calcining drum.



   III. The heated mixture formed by the additions, such as pumice stone, lava and blast furnace slag, then passes into a distribution tank communicating with the mixers, into which the prepared binders are introduced, that is, ie Portland cement and blast furnace slag, or finely ground blast furnace cement.



   IV. The mixers are connected to the molding machines which are supplied with hot mixture by secondary distributors, and equipped in a manner known per se with shaking molds. In front of the reception posts

 <Desc / Clms Page number 7>

 The finished elements pass a conveyor, preferably with suspended cages, in which the finished elements are automatically deposited.



   V. These cages thus loaded then pass through the curing and drying installation formed by the serpentine tunnel, in which a current of hot and see air circulates in the direction opposite to the path of the cages.



   VI. The source providing the necessary energy is a motive power plant, and a blast-furnace installation possibly supplies the necessary slag as well as the heat to be recovered in this slag.



   Auxiliary devices such as screens, grinders, binder preparers and proportioners, the heat source recovered with its heat exchanger, the device intended to circulate hot and dry air in a closed circuit, must be added. device for regulating temperature, humidity, resistance to compression of energy causing tremors, etc ...



   When using the blast furnace slag, an important part of the invention is also formed by the blast furnace group providing this slag, a part of this liquid slag then being used for the preparation of a porous addition, while the other part is divided into fine grains to be used as a binder. The liquid slag leaving the blast furnace is freed as much as possible from the iron and suddenly cooled in a tank of water. The porous additions and the solid grains for the binder separate automatically, and the two parts are distributed to the mixers after screening.



   The water vapor released during cooling

 <Desc / Clms Page number 8>

 Suddenly slag is used directly, or introduced into accumulators or heat exchangers; and it is used for drying and curing, which makes it possible to achieve a surprising saving in fuel compared to the quantity required heretofore.



   To recover the heat from liquid slag by sudden cooling in water, the slag is first freed as much as possible of iron before cooling, because this iron presents a risk of explosion, the water being decomposed by molten iron.



   For the continuous treatment of liquid slag and the continuous recovery of its heat in the form of steam, another feature of the invention consists in that the introduction of the slag and of the water into the sudden cooling tank, as well as the discharge of the steam and the preferably hot solidified slag are regulated automatically by control devices known per se. "
The abrupt cooling operation is preferably preceded by an adjustment of the temperature of the still liquid slag, which makes it possible to obtain slag-based products having different properties depending on the temperature, starting from which abrupt cooling is carried out.

   Thus, starting with a slag of a relatively high temperature, for example about 1400 ° C., a spongy product is obtained by sudden cooling. Abrupt cooling of a slag to an average temperature, eg about 1300 ° C, results in a glassy product. Finally, the sudden cooling of a slag to a relatively low temperature, for example about 12000 ° C., gives a crystalline product.



   For the use of liquid slag in the

 <Desc / Clms Page number 9>

 process according to the invention, it is also possible to divide the liquid slag leaving the blast furnace into several parts with a view to obtaining slag-based products having different properties. The various parts of slag are then separately brought to different temperature levels.



   In this way, different products can be obtained simultaneously and continuously without interrupting the operation of the installation, and without modifying the recovery devices, which offers in particular this other advantage than the additional treatment devices of the different products can work / without interruption.



   The brickyard taken as an example is shown schematically in the accompanying drawing. Figures 1 and show the handling installation with the screening and grinding devices I followed by a driver II, a mixer and a distributor III, while the molding machines IV are arranged at the lowest floor; - figure 2 shows group III separately with the mixers and distributors, - figures 3 and 3a are a plan view of the installation comprising the curing and drying tunnel V; FIG. 4 shows the installation preceding groups I and III and comprising the blast furnace as well as the apparatus intended for sudden cooling, screening, grinding and heat recovery;

   FIG. 5 is a schematic plan view showing certain details of the installation for the sudden cooling of the blast furnace slag; figures 1 and represent groups - lU -

 <Desc / Clms Page number 10>

 I, II, III and IV. Group I includes silos 1 and 2 containing additions such as pumice stone, spongy lava, possibly other additions such as blast furnace slag. Elevators 4 to 5 load these additions into hopper 7 combined with a screening device. The retained grains, larger than 1 - 10 mm, are introduced into the grinder 8.

   The grains of the additions reduced to the necessary size descend through a sloping chute 9 into the rotary calcining drum 10, which brings them to a temperature of 30 to 60 C. The additions leaving the drum fall into a distributor 11. , from which conveyors 12 leave leading to the mixers 14. Apart from the additions, such as pumice stone, spongy lava, etc., the hopper 7 also receives as an addition pulverized blast furnace slag in a proportion desired. This slag is heated with the other additions in drum 10.

   The mixers 14 receive from a collector 3 the binder in the form of finely pulverized blast furnace slag, in grains of a size of 0 to 1 mm, preferably 0 to 35 µm, if necessary. tally an additional Portland cement in a proportion of up to 10% of the mass of the binder.



  The mixture exiting the mixers 14 is conveyed by the conveyors 15 to the molding machines 16 equipped with shaker generating devices 18. The elements formed by molding in these machines are stacked at 20.



  The stacked elements are automatically loaded into the suspended cages of a conveyor 21, which moves them through the serpentine tunnel 22 until they reach the end of the closed circuit at the collection stations 23, where they are placed on the loading and shipping dock 24.

 <Desc / Clms Page number 11>

 



   The slag used as an addition and as a binder arrives from a blast furnace 33 via a duct 34 opening into a water tank 35. The slag first passes through devices intended to rid it of any iron which it may contain. , and which will be described later with reference to FIG. 5. The liquid slag is suddenly cooled in the water tank, and the cooled slag, but still hot, is picked up by an elevator 36 which deposits it on a conveyor belt 37 , from which it falls into a screening apparatus 38. The coarse grains retained by the screen are picked up by an elevator 39 and deposited on a conveyor which passes them into the hopper 7 of group I.

   Grains passing through the screen, 0 to 1 mm in size, and intended for use as a binder, are collected by a conveyor 40 which deposits them in a pulverizer 41, which also receives Portland cement from the hopper. 42.



  The binder thus prepared, preferably in grains with a size of 0 to 35 µm, passes through line 43 into the collector 3 of group III.



   Finely pulverized blast furnace slag has been found to be an excellent binder, and serves as the main component of the binder in the starting mixture with a suitably selected proportion of Portland cement, which main component can be dosed according to strength. mechanics, the ability to isolate, and the hardening time as previously indicated.



   The vapors (composed of air and water vapor) released in the water tank 35 and in the tanks 35a, 35b and 35c pass through the pipes 44 of group V and the pipes 44a, 44b and 44c in the exchanger heat 30, in which these wet vapors are used

 <Desc / Clms Page number 12>

 for heating the dry air, which then passes through the heater 32 to be brought to the temperature necessary for drying in the drying and curing tunnel.

   This hot air enters the serpentine tunnel through the outlet of the molded elements, and circulates in the opposite direction to the path of these elements, first in the second half of the tunnel 22 to dry the hardened elements but also very humid, absorbing the moisture released from these elements, then in the first half, in which the humid steam ensures the hardening of the freshly molded elements, which thus release additional heat. The hot and humid air leaving the tunnel passes through the duct 31 in the heat exchanger 30 to be reheated, and then to pass again in a closed circuit in the tunnel.



   So that the continuous operation of the whole installation is assured, the slag diverter duct 34, the water inlet duct and the circulation pipes 36 and 44 for the slag and the Vapors are provided with regulating devices dependent on each other, and arranged in a manner known per se (not shown in the drawing). The vapors (composed of air and water vapor) are sucked continuously into the tank 35. For this purpose a suitable fan or similar device can be inserted in the pipe 44.



   The various control and command devices are installed in a central station. Apparatus 26, for example, is used for adjusting the compressive strength of molded elements, and is connected to apparatus 29 for controlling the humidity of the elements.



  The device 27 is used to check and adjust the intensity

 <Desc / Clms Page number 13>

 sity of the shocks applied to the molding machines, while the apparatus 28 monitors and controls the temperature in the serpentine tunnel 22. At 45 is indicated the central motive force which operates the whole installation, and which possibly allows to 'use the heat recovered in the slag, for example.



   As previously indicated, basic blast furnace slag can be added to the mixture of pumice, lava, etc. as an addition or binder depending on the size of the grains to obtain sufficient strength. compression and fracture of finished elements.

   For example, the proportions of the different grain sizes may be as follows:
0 to 50 / u, approximately 10% (of the weight of the total mass of the additions)
50 to 200 / u, about 1% "
1 to 3 mm, about 5% "
3 to 10 mm, about 15% "
Instead of the large quantity of the usual commercial binders required hitherto, it is therefore sufficient to add 1 to 2% of the weight of the total mass of the mixture, which represents an extremely significant saving in the construction industry. manufacture of lightweight building components.



   Group III contains the mixers which are preferably provided in pairs, because it is necessary to clean and even repair them quite frequently. It is then easy to switch on one or the other of the mixers without hindering the operation of the installation. The same applies to the molding machines 16, 18 of group IV. Grace

 <Desc / Clms Page number 14>

 when these devices are doubled, the continuous operation of the installation is ensured by their alternate use.



   Figure 5 is a plan view of a device for the sudden cooling of blast furnace slag. The blast furnace 33 is provided in the usual manner with a casting pipe 52 for the iron, and a casting manifold 34 for the slag.



   The slag collector 34 communicates by three pipes 54, 55, 56 with tanks 57, 58, 59, in which the liquid slag is brought to the desired temperature before the sudden cooling, and then passes into sudden cooling tanks. corresponding 35a, 35b, 35c.



   For example, the slag can be brought to 1400 in the tank 57, to 1300 in the tank 58, and to 1200 in the tank 59 before passing it into the corresponding sudden cooling tank. The cooled slag is then respectively taken up in the tanks.



  For the temperatures indicated, the tank 35a gives, for example, a spongy slag, the cube 35b a glassy and homogeneous slag, and the tank 35c a crystallized slag.



   In the example shown in the figure, the manifold 34 is formed by an enlarged part of the slag pouring tube. From the bottom of this manifold also leaves a complementary pipe 53, while the pipes 54, 55, 56 are connected at a higher level.



   The tubing 53 serves to evacuate most of the iron still contained in the slag. Thanks to its greater density, the iron is deposited in the collector 34 and can then flow through the tubing 53, so that the slag passing into the cooling tanks.

 <Desc / Clms Page number 15>

 Sudden hardening 35a, 35b, 35c contains at most only insignificant proportions of iron.



   Contrary to what the schematic figure shows, the space around the blast furnace is frequently not sufficient for the installation intended for the sudden cooling of the slag. The collector 34 is then replaced by mobile pockets, provided at the bottom with a tube similar to the tube 53 and intended for the evacuation of the iron. These mobile pockets are then emptied into collecting tanks separate from the blast furnace, corresponding to the tanks 57, 58, 59 intended for the precooling of the slag. Instead of providing the pockets with tubes for the removal of the iron, these tubes can be provided on each of the tanks, and the latter can even be additionally provided with these tubes starting from the bottom.

   The main thing is that the slag is freed of most of the iron before the sudden cooling.

** ATTENTION ** end of DESC field can contain start of CLMS **.


    

Claims (1)

REVENDICATIONS 1. Procédé pour la fabrication entièrement auto- matique et continue d'éléments de construction en maté- riaux légers ou poreux, tels que la pierre ponce, la lave spongieuse., le laitier de haut-fourneau, etc..., agglomérés par du ciment, caractérisé en ce qu'il consis- te à chauffer préalablement à une température de 30 à 60 une grande quantité (environ 500 m3 pour chaque journée de travail d'une équipe) de matériaux de départ (addi- tions) en grains et mélangés, à mélanger ces matériaux de départ avec des liants connus en soi tels que le ci- ment brut et le laitier de haut-fourneau finement pulvé- risé pour former le mélange de départ, à faire passer ce mélange dans les machines à mouler, à empiler les éléments <Desc/Clms Page number 16> moulés, de préférence automatiquement, CLAIMS 1. Process for the fully automatic and continuous manufacture of construction elements made of light or porous materials, such as pumice stone, spongy lava, blast furnace slag, etc., agglomerates by cement, characterized in that it consists in preheating to a temperature of 30 to 60 a large quantity (approximately 500 m3 for each working day of a shift) of starting materials (additions) in grains and mixed, mixing these starting materials with binders known per se such as crude cement and finely pulverized blast furnace slag to form the starting mixture, passing this mixture through the machines. mold, stacking elements <Desc / Clms Page number 16> molded, preferably automatically, à charger les empilages d'éléments sur un transporteur connu en soi cheminant à travers un sécheur à air chaud, à utiliser les vapeurs humides et saturées, dégagées par le séchage, pour le durcissement des éléments, à sécher les éléments avec de l'air chaud et à les déposer sur un quai de char- gement pour l'expédition, la continuité du procédé étant assurée par des transporteurs reliant entre eux les dif- férents appareils 2. Procédé suivant la revendication 1, caractéri- sé en ce qu'avant le chauffage, on/réduit en grains d'une grosseur de 1 à 10 mm les additions destinées à former le mélange de départ pour la fabrication d'éléments en béton légers, telles que la pierre ponce, la lave spon- gieuse et le laitier de haut-fourneau. in loading the stacks of elements on a conveyor known per se passing through a hot air dryer, in using the humid and saturated vapors given off by the drying, for the hardening of the elements, in drying the elements with air hot and deposit them on a loading dock for shipment, the continuity of the process being ensured by conveyors interconnecting the various devices 2. Process according to Claim 1, characterized in that before heating, the additions intended to form the starting mixture for the manufacture of lightweight concrete elements, such as pumice stone, sponge lava and slag, are reduced to grains of a size of 1 to 10 mm blast furnace. 3. Procédé suivant la revendication 1 et 2, carac- térisé en ce que pour économiser le ciment, on mélange les additions après le chauffage avec du laitier de haut- fourneau basique destiné à servir de liant en grains d'une grosseur de 0 à 1 mm, de oréférence d'environ 35/u (0,035 mm), et dans une proportion allant jusqu'à environ 90 % du poids total des liants, et avec un complément de ciment brut ou similaire. 3. A method according to claim 1 and 2, characterized in that in order to save cement, the additions are mixed after heating with basic blast furnace slag intended to serve as a binder in grains of a size from 0 to. 1 mm, of orereference of about 35 µm (0.035 mm), and in an amount of up to about 90% of the total weight of the binders, and with additional raw cement or the like. 4. Procédé suivant les revendications 1 à 3, ca- ractérisé en ce que dans le tunnel de séchage, on fait circuler un courant d'air chaud dans le sens opposé au cheminement du transporteur des éléments, en faisant en- trer l'air chaud par l'orifice de sortie des éléments moulés de façon que cet air assure le séchage des éléments préalablement durcis, et en faisant ensuite passer l'air chaud humide dans la première partie du tunnel pour le durcissement des éléments fraîchement moulés, l'air sor- <Desc/Clms Page number 17> tant de la partie du tunnel destinée au durcissement étant ensuite réchauffé et réintroduit dans le circuit du tun- nel de séchage. 4. Method according to claims 1 to 3, charac- terized in that in the drying tunnel, a current of hot air is circulated in the direction opposite to the path of the conveyor of the elements, making the air enter. hot through the outlet of the molded elements so that this air ensures the drying of the previously hardened elements, and then passing the humid hot air into the first part of the tunnel for the hardening of the freshly molded elements, the air get out <Desc / Clms Page number 17> both of the part of the tunnel intended for curing then being reheated and reintroduced into the circuit of the drying tunnel. 5. Procédé suivant la revendication 4, caractérisé en ce que pour le chauffage de l'air destiné au séchage et au durcissement on utilise la chaleur récupérée dans le laitier liquide de haut-fourneau. 5. Method according to claim 4, characterized in that for the heating of the air intended for drying and hardening, the heat recovered in the liquid blast furnace slag is used. 6. Procédé suivant les revendications 1 et 5, carac- térisé en ce qu'on fait passer dans un échangeur de cha- leur, le laitier sortant du haut-fourneau, et on utilise la chaleur ainsi récupérée pour le chauffage de l'air circulant dans le tunnel, de séchage et de durcissement, et pour le chauffage des additions mélangées, on fait passer ensuite le-laitier dans des appareils de broyage et de criblage qui fournissent le laitier en grains ayant les grosseurs désirées pour les mélangeurs d'additions et de liants. 6. A method according to claims 1 and 5, characterized in that the slag leaving the blast furnace is passed through a heat exchanger, and the heat thus recovered is used for heating the air. circulating through the tunnel, drying and curing, and for heating the mixed additions, the slag is then passed through crushing and screening devices which provide the slag in grains of the desired sizes for the additive mixers and binders. 7.. briqueterie ou installation pour la mise en - oeuvre du procédé suivant l'une ou l'autre des revendica- tions précédentes, caractérisée en ce qu'elle comprend des appareils de broyage et de criblage destinés à la préparation des additions pour le mélange de d-épart, suivis d'un dispositif de chauffage, par exemple d'un tambour rotatif de calcination communiquant avec un mé- langeur recevant complémentairement les liants, et faisant automatiquement passer le mélange de départ dans des machines à mouler disposées à côté d'un transporteur, par exemple d'un transporteur à cages suspendues, qui fait cheminer les éléments moulés dans un tunnel de dur- cissement et de séchage à la sortie duquel est prévu un appareil de chargement et d'expédition automatique. 7 .. brickyard or installation for carrying out the process according to one or the other of the preceding claims, characterized in that it comprises crushing and screening apparatus intended for the preparation of additions for the starting mixture, followed by a heating device, for example a rotary calcination drum communicating with a mixer which additionally receives the binders, and automatically passing the starting mixture through molding machines placed next to it a conveyor, for example a suspended cage conveyor, which leads the molded elements through a curing and drying tunnel at the outlet of which an automatic loading and dispatching apparatus is provided. 8. Installation suivant la revendication 7, ca- <Desc/Clms Page number 18> ractérisée en ce que le tunnel de chauffage est inter- calé dans le circuit fermé d'une source de chaleur, l'entrée du tunnel étant raccordée à la sortie de la source de chaleur, tandis que la sortie du tunnel est raccordée à l'entrée de cette source. 8. Installation according to claim 7, ca- <Desc / Clms Page number 18> ractérized in that the heating tunnel is interposed in the closed circuit of a heat source, the entrance of the tunnel being connected to the exit of the heat source, while the exit of the tunnel is connected to the input from this source. 9. Installation suivant l'une ou l'autre des reven- dications 7 et 8, caractérisée en ce qu'elle est divisée en plusieurs groupes coopérant les uns avec les autres, et dont le groupe I assure la préparation des additions, le groupe II contient le dispositif de chauffage, le groupe III assure le mélange des additions chaudes avec les liants préparés, Le groupe IV comprend les machines à mouler communiquant avec le groupe V comprenant l'installation de durcissement et de séchage, tandis que le groupe VI comprend les dispositifs réglant la chaleur et dosant le laitier en coopération avec une installation à haut-fourneau. 9. Installation according to either of claims 7 and 8, characterized in that it is divided into several groups cooperating with each other, and of which group I ensures the preparation of additions, group It contains the heating device, group III ensures the mixing of hot additions with the prepared binders, Group IV includes molding machines communicating with group V comprising the curing and drying plant, while group VI includes devices regulating the heat and metering the slag in cooperation with a blast furnace installation. 10. Installation suivant l'une ou l'autre des re- vendications 7 à 9, caractérisée en ce que que le mélan ge de départ est préparé dans deux mélangeurs, et le moulage de ce mélange est assuré dans deux groupes de machines de moulage entrant alternativement en action. 10. Installation according to one or the other of claims 7 to 9, characterized in that the starting mixture is prepared in two mixers, and the molding of this mixture is carried out in two groups of molding machines. alternately entering into action. Il. Installation suivant l'une ou l'autre des re- vendications 7 à 10, caractérisée en ce que le haut- fourneau communique avec une cuve à eau destinée au re- froidissement brusque du laitier liquide, dans laquelle débouche une tubulure d'arrivée de l'eau, et de laquelle part un conduit d'écoulement du laitier et un conduit d'évacuation des vapeurs. He. Installation according to one or the other of claims 7 to 10, characterized in that the blast furnace communicates with a water tank intended for the sudden cooling of the liquid slag, into which opens an inlet pipe for water, and from which a slag flow pipe and a vapor discharge pipe. 12. Installation suivant la revendication 11, ca- ractérisée en ce qu'entre la tubulure de coulée du laitier partant du haut-fourneau et la tubulure d'entrée du laitier dans la cuve à eau est intercalé un collec- <Desc/Clms Page number 19> teur destiné à la précipitation et à l'évacuation du fer liquide entraîné par le laitier. 12. Installation according to claim 11, charac- terized in that between the slag casting pipe leaving the blast furnace and the slag inlet pipe in the water tank is interposed a collec- <Desc / Clms Page number 19> tor intended for the precipitation and the evacuation of the liquid iron entrained by the slag. 13. Installation suivant la revendication 12, ca- ractérisée en ce qu'entre la tubulure de coulée du lai- tier partant du haut-fourneau et la tubulure d'entrée du laitier dans la cuve à eau est intercalé un disposi- tif pour le.réglage de la, température du laitier dans la gamme des températures de fusion. 13. Installation according to claim 12, charac- terized in that between the slag pouring pipe leaving the blast furnace and the slag inlet pipe in the water tank is interposed a device for the slag. .adjustment of the temperature of the slag in the range of melting temperatures. 14. Installation suivant l'une ou l'autre des re- vendications 12 et 13, caractérisée en ce que des moyens sont prévus pour diviser le laitier en plusieurs par- ties et pour le refroidissement brusque de ces différen- tes parties en partant de températures différentes. 14. Installation according to one or the other of claims 12 and 13, characterized in that means are provided for dividing the slag into several parts and for the sudden cooling of these different parts starting from different temperatures. 15. Installation suivant la revendication 11, ca- ractériséè en ce que des organes régulateurs de l'entrée du laitier, de l'arrivée d'eau dans la cuve de refroi- dissement brusque, de l'évacuation des vapeurs et de l'écoulement du laitier de cette cuve agissent en fonc- tion les uns des autres. 15. Installation according to claim 11, charac- terized in that the organs regulating the entry of slag, the entry of water into the sudden cooling tank, the evacuation of vapors and the slag flow from this tank act in relation to each other.
BE557810D 1956-05-26 BE557810A (en)

Applications Claiming Priority (1)

Application Number Priority Date Filing Date Title
DE1183027X 1956-05-26

Publications (1)

Publication Number Publication Date
BE557810A true BE557810A (en)

Family

ID=7730480

Family Applications (1)

Application Number Title Priority Date Filing Date
BE557810D BE557810A (en) 1956-05-26

Country Status (1)

Country Link
BE (1) BE557810A (en)

Similar Documents

Publication Publication Date Title
KR101757630B1 (en) Dry granulation of metallurgical slag
JP2857437B2 (en) Method and apparatus for preparing slag from waste combustion furnace
FR2853919A1 (en) PROCESS FOR THE MANUFACTURE OF A BITUMINOUS COATING
CN211134112U (en) Wet-mixed mortar sand screening mechanism
EP3307854B1 (en) Method and facility for preparing biomass
EP1219336B1 (en) Method and apparatus for removing harmful volatile elements, especially sulfates and/or chlorides, from a flue gas
FR2542760A1 (en) IMPROVED INSTALLATION FOR THE CONTINUOUS PROCESSING OF MOLTEN MATERIALS FOR THE PRODUCTION OF SLICED PRODUCTS
EP3818019B1 (en) Preparation of raw materials for glass furnace
CA1155876A (en) Method and device for the manufacture of cement clinker
TW201221325A (en) Mobile device and method for concrete production with cooling of bulk material
BE557810A (en)
FR2764367A1 (en) PLANT FOR THE HEAT TREATMENT OF PULVERULENT MATERIALS IN SUSPENSION, AND APPLICATION FOR THE FLASH CALCINATION OF MINERAL MATERIALS ESPECIALLY CLAYY
FR2533912A1 (en) METHOD AND INSTALLATION FOR COOKING A FINE GRAIN PRODUCT, IN PARTICULAR THE CEMENT FLOUR
CN105732001B (en) A kind of method with stainless steel belt type roasting machine pelletizing method production lytag
RU2600297C2 (en) Method for complex processing melts and process line for its implementation
EA023119B1 (en) Method and device for manufacturing vitreous slag
JP2004277191A (en) Coarse aggregate for concrete
JP2003328015A (en) Method for treating slag in refining
US3319949A (en) Apparatus for making pallet of iron ore and flux
EP3865202A1 (en) Use of co2-containing gaseous effluent in wet concrete preparation
JPS599106A (en) Method for generating steam by melt of blast furnace slag
JP2022175823A (en) Method for producing blast furnace annealing slag, method for producing coarse aggregate for concrete, method for producing roadbed material, and blast furnace annealing slag
FR2668474A1 (en) PROCESS AND PLANT FOR TREATING HIGH - FURNACE VITRIFIED DAIRY PRODUCTS AND PRODUCTS OBTAINED THEREBY.
JPS6158417B2 (en)
KR100762433B1 (en) A Manufacturing Equipment for Limestone Sludgy Pellet