AU689950B2 - Method for constructing and installing an offshore gravity plaftorm structure and platform structure designed for the implementation of this method - Google Patents

Method for constructing and installing an offshore gravity plaftorm structure and platform structure designed for the implementation of this method Download PDF

Info

Publication number
AU689950B2
AU689950B2 AU34414/95A AU3441495A AU689950B2 AU 689950 B2 AU689950 B2 AU 689950B2 AU 34414/95 A AU34414/95 A AU 34414/95A AU 3441495 A AU3441495 A AU 3441495A AU 689950 B2 AU689950 B2 AU 689950B2
Authority
AU
Australia
Prior art keywords
column
accordance
caisson
axis
seabed
Prior art date
Legal status (The legal status is an assumption and is not a legal conclusion. Google has not performed a legal analysis and makes no representation as to the accuracy of the status listed.)
Ceased
Application number
AU34414/95A
Other versions
AU3441495A (en
Inventor
Loic Marie Jacques Danguy Des Deserts
Vincent Frederic Paul Foglia
Dominique Michel
Current Assignee (The listed assignees may be inaccurate. Google has not performed a legal analysis and makes no representation or warranty as to the accuracy of the list.)
Individual
Original Assignee
Individual
Priority date (The priority date is an assumption and is not a legal conclusion. Google has not performed a legal analysis and makes no representation as to the accuracy of the date listed.)
Filing date
Publication date
Application filed by Individual filed Critical Individual
Publication of AU3441495A publication Critical patent/AU3441495A/en
Application granted granted Critical
Publication of AU689950B2 publication Critical patent/AU689950B2/en
Anticipated expiration legal-status Critical
Ceased legal-status Critical Current

Links

Classifications

    • EFIXED CONSTRUCTIONS
    • E02HYDRAULIC ENGINEERING; FOUNDATIONS; SOIL SHIFTING
    • E02BHYDRAULIC ENGINEERING
    • E02B17/00Artificial islands mounted on piles or like supports, e.g. platforms on raisable legs or offshore constructions; Construction methods therefor
    • E02B17/02Artificial islands mounted on piles or like supports, e.g. platforms on raisable legs or offshore constructions; Construction methods therefor placed by lowering the supporting construction to the bottom, e.g. with subsequent fixing thereto
    • E02B17/025Reinforced concrete structures
    • EFIXED CONSTRUCTIONS
    • E02HYDRAULIC ENGINEERING; FOUNDATIONS; SOIL SHIFTING
    • E02BHYDRAULIC ENGINEERING
    • E02B17/00Artificial islands mounted on piles or like supports, e.g. platforms on raisable legs or offshore constructions; Construction methods therefor
    • E02B2017/0039Methods for placing the offshore structure
    • EFIXED CONSTRUCTIONS
    • E02HYDRAULIC ENGINEERING; FOUNDATIONS; SOIL SHIFTING
    • E02BHYDRAULIC ENGINEERING
    • E02B17/00Artificial islands mounted on piles or like supports, e.g. platforms on raisable legs or offshore constructions; Construction methods therefor
    • E02B2017/0056Platforms with supporting legs
    • E02B2017/0065Monopile structures
    • EFIXED CONSTRUCTIONS
    • E02HYDRAULIC ENGINEERING; FOUNDATIONS; SOIL SHIFTING
    • E02BHYDRAULIC ENGINEERING
    • E02B17/00Artificial islands mounted on piles or like supports, e.g. platforms on raisable legs or offshore constructions; Construction methods therefor
    • E02B2017/0056Platforms with supporting legs
    • E02B2017/0069Gravity structures
    • EFIXED CONSTRUCTIONS
    • E02HYDRAULIC ENGINEERING; FOUNDATIONS; SOIL SHIFTING
    • E02BHYDRAULIC ENGINEERING
    • E02B17/00Artificial islands mounted on piles or like supports, e.g. platforms on raisable legs or offshore constructions; Construction methods therefor
    • E02B2017/0056Platforms with supporting legs
    • E02B2017/0073Details of sea bottom engaging footing
    • E02B2017/0086Large footings connecting several legs or serving as a reservoir for the storage of oil or gas

Landscapes

  • Engineering & Computer Science (AREA)
  • General Engineering & Computer Science (AREA)
  • Mechanical Engineering (AREA)
  • Civil Engineering (AREA)
  • Structural Engineering (AREA)
  • Foundations (AREA)
  • Revetment (AREA)

Description

1A- Method for constructing and installing an offshore gravity platform structure and platform structure designed for the implementation of this method.
The present invention relates to a method for constructing and installing an offshore gravity platform structure, more particularly, a structure which consists of at least one column for supporting a deck and of a caisson which is integral with the column and is designed to rest on the seabed.
According to usual methods for constructing such a structure, the caisson of the structure is built in a dry dock, with its axis being oriented vertically, like in its final position on the site where it is to be installed. Once 10 the caisson has been constructed, the dry dock is flooded and buoyancy means, installed internally or externally to the caisson ensure that the latter floats. The caisson is towed out of the dock by tugs to deep water, where the construction of the structure can continue. This allows the said structure to submerge progressively in the water as it becomes heavier, while continuing 15 to float. Once construction is finished, the structure is equipped with a deck and it is towed to its final installation site. The caisson is then ballasted appropriately to lower it down onto the seabed so that it rests at its designated o location. Final ballasting is carried out with seawater or solid materials to o o ensure the structure stability on the seabed.
20 Due to the shallow draught of the dry dock, this known method often leads to the caisson being oversized in order to satisfy the condition of its floatation at this stage of construction, in comparison to the dimensions which it could be designed for to fulfil its final function of providing a support for the deck and ensuring the stability of the structure in deep water.
Furthermore, this method requires a well-sheltered deep-water site to be available close to the dry dock so that the construction of the structure can be completed.
This last constraint may be eliminated by constructing the structure, base and column, entirely in the vertical position, in a dry dock. However, the consequential oversizing of the caisson which is then required to enable the whole assembly to float in the condition of the shallow dry dock draught, becomes prohibitive in terms of materials and labour cost.
-2becomes prohibitive in terms of materials and labour cost.
Alternatively, to avoid the draught restriction, recourse may be to deepen the dry dock. However, this solution generally leads to excessive costs.
A structure for loading tankers at sea known as the "MAUREEN articulated loading column" was also constructed (see the British magazine OFFSHORE ENGINEER, pages 76-77, August 1982) using the method in which the elements of its column and of its base were ,ssembled in a dry dock and the column was completed in horizontal position resting on the bottom of the dock. After the dock was flooded, the column and the base were towed separately out of the dry dock, the column floating horizontally, and then assembled together outside the dock with a cardan-type articulation. The column was then uprighted by ballasting it to come to a vertical position perpendicular to its base, this being made possible by the articulation. The 15 structure was then fitted with a deck and its equipment, was towed to its final site and lowered down onto the seabed under gravity.
When a platform structure has to accommodate conductor tubes to ior allow the installation of surface wellheads, the structure described hereinabove cannot be envisaged because such conductor tubes would have to pass in the vicinity of the articulation, which would singularly complicate the :construction. Furthermore, this concept is characterized by substantial torsional loadings at the articulation, during a phase of mounting the column horizontally with the base, and during the operational phase on the final site.
The final point is that the assembly of the column and of the base in floating S 25 condition outside the dry dock is a complication of the construction method ooand makes it more expensive.
and makes it m~ore expensive.
-3- It would therefore be desirable to provide an economical method for constructing and installing a gravity type offshore platform structure, eliminating the oversizing of the caisson of the said structure induced by the temporary construction phases, the need to have use of a well-sheltered deepwater construction site, and using a design which is not hampered by the drawbacks of articulated structures.
According to an aspect of the present invention there is provided a gravity platform structure made of reinforced concrete consisting of at least one support column of a deck and of a caisson integral with the column and designed to rest on a seabed wherein the column and the caisson are situated on one and the same side of a common tangential place substantially parallel to a longitudinal axis of the column.
According to another aspect of the invention, there is provided a method for constructing and installing the offshore gravity platform structure described 15 above comprising the steps according to which: a Sii the structure is constructed at a quayside on a substantially horizontal surface parallel to the axis of the column under construction, iO": the structure is then loaded onto a ballastable barge, J 0 the structure is then placed afloat in shallow water by releasing the barge 20 from the structure, keeping the said axis in a substantially horizontal position, the structure is uprighted in deep water so that the axis of the column S: comes to a substantially vertical position, the structure is towed to an installation site, and Sothe structure is ballasted down to rest on a seabed in the same vertical position.
The structure, as it will be demonstrated later, can float in shallow water without the need to oversize its caisson to limit the draught, as is the case when such a structure is constructed in the vertical position. Furthermore, as the concrete structure is entirely constructed on dry land, it is no longer necessary to provide a sheltered deep-water site to complete its construction. As the caisson is rigidly connected to the column, the structure is also free of the drawbacks of the articulated structure described hereinabove.
VAT:WinwordWiole\PhiRNodelete\34414-95.doc 3a- According to a first embodiment of the invention, the structure is constructed at the quayside, it is then loaded onto a ballastable barge, and it is placed in the water by releasing the barge from the structure, either by ballasting the barge or by launching similarly to a method used for steel structures.
According to another embodiment of the invention, the structure is constructed in a dry dock.
By virtue of this geometry, it becomes possible to construct or to assemble the structure according to the invention on a horizontal surface coinciding substantially with the said tangential plane, on a quay or in a dry dock.
The above and further features and advantages of the present invention will become more apparent from the following description of preferred embodiments of the invention with reference to the accompanying drawings, in 15 which: 00 o* *0 *oooo* VAT:Wnword\Violet\PhifNodelete\3441 4-95.doc -4- Figures 1A to 1H diagrammatically illustrate a first implementation of the method according to the invention, Figures 2A to 2C are three sectional views of one embodiment of the platform structure according to the invention, Figure 3 represents a detail of an alternative implementation of the said structure, Figures 4A to 4C diagrammatically illustrate another implementation of the construction and installation method according to the invention, Figures 5A and 5B represent another embodiment of the structure according to the invention, and Figures 6A and 6B represent yet another embodiment of the structure according to the invention.
Reference is made to Figures 1A to 1H of the appended drawing, 15 which diagrammatically illustrate the successive steps in the method according to the invention, with a purpose to installing a gravity platform structure 1 on a predetermined site of the seabed 2 (see Figure 1H), so that the top of the structure carries a deck 3 above the surface 4 of the water. The deck is able to o• support any kind of equipment for exploiting an offshore production oil field, S 20 such as wellheads, production equipment, living quarters, or tanker loading stations for example.
The structure 1 is represented in more detail in Figures 2A, 2B and S" 2C which are sections of this structure along section lines A, B and C respectively. In these views, it is clear that the structure, according to the embodiment represented, comprises an axisymmetric cylindrical column connected to a caisson 6 designed to rest on the seabed 2 and forming a monolithic assembly with the column. The caisson 6 comprises ballasting compartments 71 to 710 capable of holding solid ballast materials such as sand, gravel, iron ore, etc. Some of these compartments may, as is well known, be closed and provided with sealing means so that they can be converted temporarily into buoyancy tanks for towing the structure to its final installation site.
The column 5 is hollow and it too may be closed off in order to form a buoyancy tank, before receiving water or other ballasting materials on the final site. Any conductors or risers which are provided within the structure are located preferably inside the column, thus being sheltered from wave action, and pass between the seabed and the deck 3 installed out of the water on the top 9 of the column, as will be explained later. Stiffeners 101, 102, stiffen the anchorage of the column 5 to the caisson 6.
:i The structure is designed to be made from reinforced and/or 15 prestressed concrete. After ballasting it rests on the sea bed under its own weight.
According to one characteristic of the structure according to the invention, the column 5 and its caisson 6 are situated on one and the same side of a common tangential plane P (see Figure 2B) substantially parallel to the axis X of the column. The structure therefore has no axial symmetry which allows it to be manufactured by the method according to the invention, as explained hereinbelow in conjunction with Figures 1A to 1H.
According to a first implementation of the method according to the invention, the structure 1 is constructed or assembled on a quay 11 (see Figure 1A) exhibiting a substantially horizontal surface. This construction is therefore conveniently carried out from the plane P which is then substantially coincident with the surface of the quay, using conventional techniques known in the art of building offshore platforms in reinforced and/or prestressed concrete. The column may itself be produced by assembling lengths of column, which are cast vertically, then assembled horizontally.
The 0), 1 ished structure is then loaded onto a barge 12 (Figure 1 B) moored alongside the quay 11 in shallow water. Such loading is possible for structures of medium dimensions, for example with an overall height of 120 metres and a total weight of approximately 15,000 tonnes (subsequently equipped with a deck of approximately 2000 tonnes) intended for marginal or satellite fields which may be developed only in an economical manner. In this respect, it should be noted that a conventional vertical construction of this structure in a dry dock would limit the height of the structure constructed on dry land to approximately 30 metres, so that this structure can be floated in shallow water close to the dry dock. It is then necessary to tow the part of the structure thus constructed to a sheltered deep-water site in order to finish the construction, which makes the costs excessive. The other conventional solution consists in greatly oversizing the caisson in order to decrease the draught of the part constructed in dry dock this solution is also very expensive in terms of materials and labour.
S S After the structure has been loaded onto the barge 12, a tug 13 :i tows the assembly to deep water (Figure 1C). After checking that the platform
IS
15 will float horizontally by guaranteeing the watertightness of the column or of part of the column and, possibly, of some compartments of the caisson which are used as buoyancy tanks, the barge is released from the structure by appropriate ballasting or any other launching means (Figure 1D). Flooding some of the ballasting compartments of the structure then makes it possible to 20 tilt the latter up progressively (Figure 1E) to a substantially vertical position (Figure 1F). The platform is designed to float in this vertical position possibly with the aid of additional buoyancy means or counterweights (not represented) and the deck 3 is placed on the top of the column 9 using one or more loading cranes 14, carried for example by a pontoon 15. Structural connection between the deck 3 and the top of the column 9 is then carried out. The structure is then towed (Figure 1G) to the final site (Figure 1 The platform is then slowly submerged down towards the seabed by appropriate control of the progressive flooding of the column 5. The caisson finally comes to rest on the bottom. The caisson may optionally, as represented in Figure 2A, be equipped with long skirts 16, 162 etc. intended to penetrate into a loose seabed to give the structure lateral stability, as described in French Patent FR-A-2,492,429. Appropriate ballasting of the compartments 7, of the caisson with a solid ballast ensures the stability of the structure on the seabed.
-7- This example shows a possibility to install a complete gravity platform structure together with a deck above the water, and ready for installation of intended equipment, at offshore deep water site, for example 100 or more metres deep. By virtue of the horizontal construction method according to the invention, which makes it possible to transport the complete structure through shallow water, an economical construction results from the fact that the structure can be constructed entirely "on dry land" and that the caisson 6 is dimensioned solely for its final function of acting as a foundation, and not in order to satisfy temporary condition of a heavy structure floatting at a shallow draught. The caisson may therefore have smaller dimensions, which is advantageous both in terms of materials and labour costs.
*0*4 Figure 3 illustrates a part of an alternative implementation of the structure represented in Figure 2A. By virtue of this embodiment, the column is composed of a concrete lower part 5' which is entirely submerged at its 15 final site, and of an upper metal lattice support 5" of a height capable of supporting the deck 3 above the water. This support may be assembled with the concrete part of column when horizontal, during construction on the quayside, or on site with the aid of floating cranes. Such a support greatly *...*decreases the stress loadings on the structure which are due to the wave S 20 action.
Figures 4A to 4C represent a variation on the method illustrated in S: Figures 1A to 1 H. Instead of constructing the structure on the quayside, the latter is constructed, still horizontally, in dry dock (Figure 4A). Once the construction is finished, the dock is flooded (Figure 4B) after it has been checked that the structure will float horizontally. The structure is then towed out of the dock (Figure 4C). The installation method then continues as illustrated in Figures 1 E to 1 H. Such a construction in dry dock provides a saving on the cost of the barge 12 used in the method illustrated in Figures 1A to 1H in case where the use of such a dry dock becomes more economical than the use of the barge.
In the foregoing, the deck is installed while the structure is floating in a vertical position. Alternatively, the deck may be installed once the structure has been put in place on the seabed under its own weight.
-8- The column of the structure could be not cylindrical, but have a square or polygonal cross-section. It could also have a circular cross-section of variable diameter, so as to exhibit a truncated cone shape. The column crosssection will also comply with the operational conditions of use such as diameter or minimum internal dimensions, to allow enough clearance for receiving the conductor tubes for example.
Figures 5A and 5B represent sectional views of another embodiment of the structure according to the invention, along the section lines A and B respectively. The structure comprises two columns 5, and 52 integral with one and the same caisson 6' defining ballasting compartments 7', and 7' 8 The strength of the structure may be enhanced by compartments 8, and 82 forming an intermediate brace for the columns. Such a two-column :structure allows the installation, for example, of an elongated rectangular deck, or alternatively the use of columns for two different functions, such as drilling 15 and the provision of utilities.
When circumstances dictate (for example increased depth or specific foundation conditions), the present invention also provides a solution to design structures with a symmetrical caisson shape, despite the asymmetry of the structures of Figures 2A, 2B and 5A, 5B. Figures 6A, 6B represent a 20 platform structure according to the invention exhibiting this characteristic. In the elevation view of Figure 6A and in the plane view of Figure 6B it is clear that the structure comprises a structure 1 like that of Figures 2A, 2B, represented in dotted line, associated with a complementary caisson element 6" represented in solid line, consisting of ballasting compartments 7", to 7"6 and of stiffeners 10' symmetrical with the corresponding elements of the caisson 6 of the structure 1.
The complementary element 6" is made on dry land at the same time as the structure. It is placed in the water after it has been made buoyant by any known means or after having been fixed to floating support pontoons.
It is assembled with the structure 1 while the latter is floating in the horizontal position. The complementary element is winched into the assembly position and this assembly is rendered permanent using prestressing cables. The assembly is then uprighted and installed on the site as illustrated in Figures 1E to 1H.
-9- It is now clear that the present invention makes it possible to construct and to install gravity platform structures at sea in a particularly economical manner. Such structures are particularly, although not exclusively, intended for exploiting marginal or satellite hydrocarbon fields. They may also be associated with the concept of unmanned platforms.
a a e **o 6« «a

Claims (13)

1. Gravity platform structure made of reinforced concrete consisting of at least one support column of a deck and of a caisson integral with the column and designed to rest on a seabed wherein the column and the caisson are situated on one and the same side of a common tangential pla~e substantially parallel to a longitudinal axis of the column.
2. '2,ucture in accordance with claim 1, wherein the caisson supports at least two columns. Structure in accordance with either one of claims 1 and 2, wherein the cross-section of the column varies along the axis of the column. S..l 15 4. Structure in accordance with either one of claims 1 and 2, wherein the ,column is of cylindrical shape. e •o 5. Structure in accordance with any one of claims 1 to 3, wherein the column is of truncated cone shape.
6. Structure in accordance with any one of claims 1 to 3, wherein the cross- •.isection of the column is polygonal.
7. Structure in accordance with any one of claims 1 to 6, wherein a complementary caisson element is provided so as to be assembled with the caisson constructed with the column, along the plane tangenial to the column and to the caisson.
8. Structure in accordance with any one of claims 1 to 7, wherein the column is comprised of a concrete lower part which is entirely submerged in its final position, and of an upper metal lattice support which supports a deck above the water. VAT.Winword\Viotet\Phi\Nodelete\344 14.95.doc I "I -11
9. Structure in accordance with any one of claims 1 to 8, wherein the caisson is equipped with long skirts for anchoring it into the seabed.
10. Structure in accordance with any one of claims 1 to 9, wherein at least one part thereof is made of prestressed reinforced concrete.
11. Method for constructing and installing an offshore gravity platform structure according to any one of claims 1 to 10, comprising the steps according to which: the structure is constructed at a quayside on a substantially horizontal surface parallel to th3 axis of the column under construction, the said structure is then loaded onto a ballastable barge, the structure is then placed afloat in shallow water by releasing the barge 15 from the structure, keeping the said axis in a substantially horizontal position, the structure is uprighted in deep water so that the axis of the column comes to a substantially vertical position, the structure is towed to an installation site, and the structure is ballasted down to rest on a seabed in the same ve 'cal position.
12. Method in accordance with claim 11, wherein prior to towing the structure to the installation site, a deck is installed on the column.
13. Method in accordance with claim 11, wherein a deck is installed on the column after the structure has been put in place in the seabed.
14. Method in accordance with any one of claims 11 to 13, wherein a complementary caisson element is constructed at the quayside and wherein this element is assembled with the caisson after the structure and this element have been placed afloat. 0" L4I, VAT;WlnwordVtiolet\PhirNodelete\34414.95,doc ^L2^ -12- Method in accordance with any one of claims 11 to 14, wherein the column is composed of a concrete lower part which is entirely submerged on the final installation site, and of a metal lattice support structure which is mounted on the said concrete part for supporting the deck above the water.
16. Gravity platform structure substantially as herein described with reference to any one of the embodiments illustrated in the accompanying drawings.
17. Method of constructing and installing an offshore gravity platform structure substantially as herein described with reference to any one of the embodiments illustrated in the accompanying drawings. **I Dated: 12 February, 1998 15 PHILLIPS ORMONDE FITZPATRICK Attorneys for: DORIS ENGINEERING a a PWG:VT o VAT:Winword\Violet\PhIRNodelete\34414.95.doc Method for constructing and installing an offshore gravity platform structure and platform structure designed for the implementation of this method. ABSTRACT The structure is constructed on dry land on a substantially horizontal surface (11) parallel to the axis of the column under construction, the structure is placed afloat in shallow water, maintaining the said axis in a substantially horizontal position, the structure is uprighted in deep water so that the axis of the column comes to a substantially vertical position, the structure is towed to the site of installation, and the structure is ballasted down to rest on a seabed in the same vertical position. Figure 1B
AU34414/95A 1994-10-26 1995-10-24 Method for constructing and installing an offshore gravity plaftorm structure and platform structure designed for the implementation of this method Ceased AU689950B2 (en)

Applications Claiming Priority (2)

Application Number Priority Date Filing Date Title
FR9412821 1994-10-26
FR9412821A FR2726302B1 (en) 1994-10-26 1994-10-26 METHOD OF CONSTRUCTING AND INSTALLING A SEA GRAVITY PLATFORM STRUCTURE AND PLATFORM STRUCTURE DESIGNED FOR THE IMPLEMENTATION OF THIS PROCESS

Publications (2)

Publication Number Publication Date
AU3441495A AU3441495A (en) 1996-05-09
AU689950B2 true AU689950B2 (en) 1998-04-09

Family

ID=9468243

Family Applications (1)

Application Number Title Priority Date Filing Date
AU34414/95A Ceased AU689950B2 (en) 1994-10-26 1995-10-24 Method for constructing and installing an offshore gravity plaftorm structure and platform structure designed for the implementation of this method

Country Status (3)

Country Link
AU (1) AU689950B2 (en)
FR (1) FR2726302B1 (en)
GB (1) GB2294490B (en)

Families Citing this family (2)

* Cited by examiner, † Cited by third party
Publication number Priority date Publication date Assignee Title
GB2330854B (en) * 1997-10-31 2002-04-17 Ove Arup Partnership Method of transporting and installing an offshore structure
GB0618885D0 (en) * 2006-09-26 2006-11-01 Seacore Ltd Improvements in and relating to pile or column installation

Citations (3)

* Cited by examiner, † Cited by third party
Publication number Priority date Publication date Assignee Title
US3729940A (en) * 1970-02-20 1973-05-01 Brown & Root Offshore tower
GB1538759A (en) * 1975-09-26 1979-01-24 Canadian Patents Dev Marine piers
GB2009291A (en) * 1977-12-05 1979-06-13 Dev Operationnels Comp Gen Structure allowing the attainment of a precise seabed location

Family Cites Families (5)

* Cited by examiner, † Cited by third party
Publication number Priority date Publication date Assignee Title
NO142535C (en) * 1974-09-06 1980-09-03 Canadian Patents Dev FRONT DRAWING FOR GREAT DEPTHS.
FR2337793A1 (en) * 1976-01-07 1977-08-05 Sea Tank Co METHOD OF IMMERSION OF AN OFF SHORE STRUCTURE-WEIGHT FOR MEDIUM DEPTHS
FR2494745A1 (en) * 1980-11-21 1982-05-28 Sea Tank Co WEIGHT STRUCTURE FOR SUPPORTING OFF SHORE WORK PLATFORM AND METHOD FOR IMPLEMENTING THE SAME
NO841368L (en) * 1984-04-06 1985-10-07 Saga Petroleum HYBRID GRAVITATION PLATFORM FOR LARGE WATER DEPTH
US5102266A (en) * 1990-09-10 1992-04-07 Cbs Engineering, Inc. Offshore support structure

Patent Citations (3)

* Cited by examiner, † Cited by third party
Publication number Priority date Publication date Assignee Title
US3729940A (en) * 1970-02-20 1973-05-01 Brown & Root Offshore tower
GB1538759A (en) * 1975-09-26 1979-01-24 Canadian Patents Dev Marine piers
GB2009291A (en) * 1977-12-05 1979-06-13 Dev Operationnels Comp Gen Structure allowing the attainment of a precise seabed location

Also Published As

Publication number Publication date
GB2294490A (en) 1996-05-01
AU3441495A (en) 1996-05-09
GB9521967D0 (en) 1996-01-03
FR2726302B1 (en) 1996-12-13
GB2294490B (en) 1998-12-09
FR2726302A1 (en) 1996-05-03

Similar Documents

Publication Publication Date Title
AU2017269088B2 (en) A seabed supported unit and method to provide a shallow water drilling terminal
US6817309B2 (en) Cellular spar apparatus and method
CN110382781B (en) Marine structure for laying the foundation of buildings, equipment and wind turbines by gravity in a marine environment
US6190089B1 (en) Deep draft semi-submersible offshore structure
US4451174A (en) Monopod jackup drilling system
US4266887A (en) Self-elevating fixed platform
US6565286B2 (en) Method for fabricating and assembling a floating offshore structure
WO2002092425A1 (en) Floating multipurpose platform structure and method for constructing same
GB2147549A (en) Minimum heave offshore structure
US10352010B2 (en) Self-installing offshore platform
AU689950B2 (en) Method for constructing and installing an offshore gravity plaftorm structure and platform structure designed for the implementation of this method
IE57532B1 (en) Floating platform structure
AU2021202442B2 (en) Gravity-Based Structure For Off-Shore Structures
EP0178311A1 (en) Gravity platform for great water depth, method of manufacturing same, and use of such a platform
JPS60208512A (en) Installation of tower type marine structure
Logan et al. Atlantic alliance: The next generation tension leg platform
GB2292167A (en) Self-installing shallow water platform for hydrocarbon production
GB2314576A (en) Offshore platform assembly
GB2311319A (en) Assembly method for offshore platform
RU2049849C1 (en) Overlaid structure formed by welding
WO2015126237A1 (en) Offshore support structure and methods of installation
CA1288960C (en) Method of installing offshore constructions
JP2953818B2 (en) Construction method for deep water structures
GB2034789A (en) Offshore structure
Cholley et al. Heavy Production Platform for Offshore LNG Development