AU2021101475A4 - Pier deep foundation pit blasting method capable of controlling flying stone by water coupling soil pressing - Google Patents

Pier deep foundation pit blasting method capable of controlling flying stone by water coupling soil pressing Download PDF

Info

Publication number
AU2021101475A4
AU2021101475A4 AU2021101475A AU2021101475A AU2021101475A4 AU 2021101475 A4 AU2021101475 A4 AU 2021101475A4 AU 2021101475 A AU2021101475 A AU 2021101475A AU 2021101475 A AU2021101475 A AU 2021101475A AU 2021101475 A4 AU2021101475 A4 AU 2021101475A4
Authority
AU
Australia
Prior art keywords
blasting
holes
foundation pit
steel
pier
Prior art date
Legal status (The legal status is an assumption and is not a legal conclusion. Google has not performed a legal analysis and makes no representation as to the accuracy of the status listed.)
Ceased
Application number
AU2021101475A
Inventor
Baoxin JIA
Jinshan SUN
Xin Zhang
Junlei ZHOU
Current Assignee (The listed assignees may be inaccurate. Google has not performed a legal analysis and makes no representation or warranty as to the accuracy of the list.)
Liaoning Technical University
Jianghan University
China Railway 18th Bureau Group Co Ltd
Wuhan Jiujiang Railway Passenger Dedicated Line Hubei Co Ltd
Original Assignee
Liaoning Technical University
Jianghan University
China Railway 18th Bureau Group Co Ltd
Wuhan Jiujiang Railway Passenger Dedicated Line Hubei Co Ltd
Priority date (The priority date is an assumption and is not a legal conclusion. Google has not performed a legal analysis and makes no representation as to the accuracy of the date listed.)
Filing date
Publication date
Application filed by Liaoning Technical University, Jianghan University, China Railway 18th Bureau Group Co Ltd, Wuhan Jiujiang Railway Passenger Dedicated Line Hubei Co Ltd filed Critical Liaoning Technical University
Priority to AU2021101475A priority Critical patent/AU2021101475A4/en
Application granted granted Critical
Publication of AU2021101475A4 publication Critical patent/AU2021101475A4/en
Ceased legal-status Critical Current
Anticipated expiration legal-status Critical

Links

Classifications

    • FMECHANICAL ENGINEERING; LIGHTING; HEATING; WEAPONS; BLASTING
    • F42AMMUNITION; BLASTING
    • F42DBLASTING
    • F42D1/00Blasting methods or apparatus, e.g. loading or tamping
    • F42D1/08Tamping methods; Methods for loading boreholes with explosives; Apparatus therefor
    • EFIXED CONSTRUCTIONS
    • E02HYDRAULIC ENGINEERING; FOUNDATIONS; SOIL SHIFTING
    • E02BHYDRAULIC ENGINEERING
    • E02B3/00Engineering works in connection with control or use of streams, rivers, coasts, or other marine sites; Sealings or joints for engineering works in general
    • E02B3/04Structures or apparatus for, or methods of, protecting banks, coasts, or harbours
    • E02B3/06Moles; Piers; Quays; Quay walls; Groynes; Breakwaters ; Wave dissipating walls; Quay equipment
    • FMECHANICAL ENGINEERING; LIGHTING; HEATING; WEAPONS; BLASTING
    • F42AMMUNITION; BLASTING
    • F42DBLASTING
    • F42D3/00Particular applications of blasting techniques
    • F42D3/04Particular applications of blasting techniques for rock blasting
    • FMECHANICAL ENGINEERING; LIGHTING; HEATING; WEAPONS; BLASTING
    • F42AMMUNITION; BLASTING
    • F42DBLASTING
    • F42D5/00Safety arrangements

Landscapes

  • Life Sciences & Earth Sciences (AREA)
  • General Life Sciences & Earth Sciences (AREA)
  • Engineering & Computer Science (AREA)
  • General Engineering & Computer Science (AREA)
  • Piles And Underground Anchors (AREA)

Abstract

The present disclosure discloses a pier deep foundation pit blasting method capable of controlling flying stone by water coupling soil pressing. The method includes the following 5 steps: cleaning up floating slag, movable stones, and accumulated water on a working face before drilling holes; perpendicularly drilling holes in designated positions, where the bottoms of blastholes are basically on the same horizontal plane; clearing the holes after hole drilling is completed; making stemming, selecting specification emulsion explosives for charging, and connecting by using non-electric millisecond delay detonators and detonating cords firmly; o covering a blasting body with steel plates and sandy soil, and finally, filling the gaps in the blastholes and the gaps below and above the steel plates with water; arranging sandy soil piles to surround and protect one side, close to high-tension cables, existing lines, residential areas, and workshops, of a bridge pier, especially the sections close to the high-tension cables and the existing lines; arranging a blasting warning at each intersection; after a monitor gives a blasting 5 command, blowing, by a blaster, a warning whistle to confirm that a surrounding area is safe and then starting to detonate; relieving the warning after confirming that there is no danger. The present disclosure accelerates the construction progress, reduces the blasting vibration velocity, blasting dust, and noises, ensures the safety of the residential areas and the workshops, solves the difficult problem that villagers hinder construction, and reduces the economic loss of an !o enterprise. 1/2 -47 -4N cq -;v IQ wC toC-o C11 r n &

Description

1/2
-47
-4N
cq IQ -;v wC
toC-o C11 r n &
PIER DEEP FOUNDATION PIT BLASTING METHOD CAPABLE OF CONTROLLING FLYING STONE BY WATER COUPLING SOIL PRESSING
TECHNICAL FIELD The present disclosure relates to a pier deep foundation pit blasting method capable of controlling flying stone by water coupling soil pressing for effectively eliminating flying stones, and in particular, to a controlled blasting technology of covering sandy soil above a blasting body.
BACKGROUND The grand bridge is 1959.65 m long and has 2 abutments and 58 piers. There are three types of pier foundations: cast-in-situ bored piles, open cut foundations, and well digging foundations. The geological conditions of deep foundations are: plain fill, silty clay, fine coarse sand, and underlying completely weathered to weakly weathered granite in sequence from top to bottom. is The well digging foundation depth of 53# to 58# piers is 6 to 8 m. During on-site construction, the weakly weathered granite is encountered after the average excavation of 2 to 3 m. The grand bridge is located in Laomanzi Village, Pulepu Town, Huanren County, and is close to existing lines, 220KV high-tension cables, workshops, and residential areas. In order to ensure the safety of a transmission line, not a conventional blasting method, but ?o manual and mechanical excavation without a blasting method can be adopted. The progress is too slow.
SUMMARY The objective of the present disclosure is to provide a pier deep foundation pit blasting method capable of controlling flying stone by water coupling soil pressing for effectively eliminating flying stones, so as to solve the problems that flying stones are produced by conventional blasting and excavation, and the non-blasting progress is too slow. The method is practical, efficient, and economic. The technical solution of the present disclosure is that: a pier deep foundation pit blasting method capable of controlling flying stone by water coupling soil pressing is performed according to the following steps: Sl, cleaning up floating slag, movable stones, and accumulated water on a working face before drilling holes, so as to avoid inaccurate hole fixation and drill sticking during a hole drilling process; S2, making ensure that the overall working face is basically flat, the holes are distributed uniformly, and the holes are fixed accurately, perpendicularly drilling the holes by using a pneumatic drill without an air leg, where drill pipes use 018 mm x (1.8 to 4.5 m) hollow hexagonal steel with unequal lengths, a drill bit uses a D42 mm straight alloy steel drill bit, and the bottoming depth of the blastholes are basically on one horizontal plane; S3, after hole drilling is completed, connecting a hole sweeper to compressed air to clean up debris and muddy water in the blastholes, so as to ensure that explosives are charged to bottoms; S4, selecting emulsion explosives with the specification of (30 mm x 200 mm x 200 g, making the stemming with the diameter of (35 mm and the length of about 200 mm on site, which facilitates placing into the blastholes; charging the explosives by using a positive continuous charging structure, where the charge decoupling coefficient K = 45/30 = 1.5; filling remaining blasthole length with the stemming; connecting non-electric millisecond delay detonators and detonating cords with the length of 7.0 m firmly to ensure good electrification, and ensuring that detonator pin wires are intact and are prevented from damage and breakage in subsequent work; S5, in order to avoid detonation interruption, charging one detonator with the same segment 1s number, namely, a segment 1 detonator, in the 5th section of explosives in cut holes charged with much explosive; in rectangular auxiliary holes, additionally charging one detonator with the same segment number, namely, a segment 3 detonator, in the 4th section of explosives of every other three holes, which ensures that all explosives are detonated; S6, covering a blasting body with two steel plates with corresponding area and with the !o thickness of 6 mm, connecting the steel plates in an overlapped manner by using 4 bolts, pressing the steel plates with 2 to 4 pieces of waste section steel, pressing the waste section steel with about 0.5 m thick sandy soil, placing one layer of steel plate, then covering the steel plate with 0.5 m thick sandy soil, and finally, filling the gaps in the blastholes and the gaps below and above the steel plates with water, where in a process of setting up protection, the connecting wires of the detonators are protected to prevent the pin wires and the connecting wires from breakage; S7, arranging sandy soil piles to surround and protect one side, close to high-tension cables, existing lines, residential areas, and workshops, of a bridge pier, where the surrounding and protecting height of the sand soil piles is as high as possible, or arranging color steel plates or bamboo fences to surround and protect, especially the sections close to the high-tension cables and the existing lines; S8, setting the warning distance to be greater than 200 m, arranging a blasting warning at each intersection, evacuating equipment, staff, animals, and the like out of a safety distance of 200 meters, ensuring that all operators wear helmets; S9, implementing a system of chain shooting by a blaster, a monitor and a safety officer, where the safety officer is responsible for blasting warning, the monitor is responsible for commanding, and the blaster blows a warning whistle after the monitor gives a blasting order and then starts detonating after making sure that the surrounding area is safe; checking and eliminating danger 15 minutes after detonating, and relieving the warning after confirming that there is no danger. The present disclosure has the following advantages and beneficial effects: 1. the construction efficiency is greatly improved by adopting a soil pressing blasting technology, which improves the excavation speed from original 0.2 to 0.3 m/d to 3.0 to 4.0m/d, improves the work efficiency by over 13 times, and accelerates the construction speed; 2. the blasting body is covered with the steel plates and the sandy soil, and the water is filled, which eliminates flying stones, and ensures the safety of adjacent high-tension cables and existing railways, reduces the blasting vibration velocity, blasting dust, and noises, ensures the safety of the residential areas and the workshops, controls the disturbance to residents, solves the difficult problem that villagers hinder the construction, and reduces the economic loss of an 1s enterprise. Table 2 shows original blasting conditions and expected blasting effect of 55# pier of Jiangjiapuzi Grand Bridge.
BRIEF DESCRIPTION OF THE DRAWINGS FIG. 1 is a blasthole layout drawing of a well digging foundation of 55# pier (metering !o dimensions in meters). FIG. 2 is an A-A section view.
DETAILED DESCRIPTION FIGs. 1 to 2 show a controlled blasting technology of covering a blasting body with sandy oil. A specific implementation process is as follows: 1, cleaning up floating slag, movable stones, and accumulated water on a working face before drilling holes, so as to avoid inaccurate hole fixation and drill sticking during a hole drilling process; 2, making ensure that the overall working face is basically flat, the holes are distributed uniformly, and the holes are fixed accurately, perpendicularly drilling the holes by using a YT-29 pneumatic drill without an air leg, where ©18 mm x (1.8 to 4.5 m) hollow hexagonal steel drill pipes with unequal lengths are selected and used, a 042 mm straight alloy steel drill bit is used, and the bottoms of the blastholes are basically on one horizontal plane; 3, after hole drilling is completed, connecting a hole sweeper to compressed air to clean the holes, so as to ensure that explosives are charged to bottoms;
4, selecting emulsion explosives with the specification of 030 mm x 200 mm x 200 g, making stemming with the diameter of 035 mm and the length of about 200 mm on site, which facilitates placing into the blastholes; charging the explosives by using a positive continuous charging structure, where the charge decoupling coefficient K = 45/30 = 1.5; filling the remaining blasthole length with the stemming; connecting non-electric millisecond delay detonators and detonating cords with the length of 7.0 m firmly to ensure good electrification, where attention should be paid to protection in subsequent work; 5. in order to avoid detonation interruption, charging one detonator with the same segment number (segment 1) in the 5th section of explosives in cut holes charged with much explosive; o in rectangular auxiliary holes, charging one detonator with the same segment number (segment 3) is additionally in the 4th section of explosives of every other three holes, which ensures that all explosives are detonated; 6. covering the blasting body with two steel plates with corresponding area and with the thickness of 6 mm, connecting the steel plates in an overlapped manner by using 4 bolts, pressing the steel plates with 2 to 4 pieces of waste section steel, pressing the waste section steel with about 0.5 m thick sandy soil (with stones removed to avoid flying stones), placing one layer of steel plate, then covering the steel plate with 0.5 m thick sandy soil, and finally, filling the gaps in the blastholes and the gaps below and above the steel plates with water, where in a process of setting up protection, the connecting wires of the detonators are protected, and the pin !o wires and the connecting wires must not be broken; 7, arranging, as high as possible, sandy soil piles to surround and protect one side, close to high-tension cables, existing lines, residential areas, and workshops, of a bridge pier, or arranging color steel plates or the like to surround and protect, especially the sections close to the high-tension cables and the existing lines;
Detonation Sequence
Detonator Segment Number
Clay Filling
Charge amount (kg)AA
Resistance (mm)
' Hole distance C (mm) 00 0 O
Hole Depth (m)C
Inclination Angle c (0)
00 cl
Hole Quantity (Holes) \OC lcl
Name dC d d ;:I ;: ;:I;:
Hole Number 00 Cl
Cl ? 0 \ OC I 0 III I T t~- -FC
8. setting the warning distance to be greater than 200 m, arranging a blasting warning at each intersection, evacuating equipment, staff, animals, and the like out of a safety distance, and ensuring that all operators wear helmets; 9, implementing a system of chain shooting by a blaster, a monitor and a safety officer, where the safety officer is responsible for blasting warning, the monitor is responsible for commanding, and the blaster blows a warning whistle after the monitor gives a blasting order and then starts detonating after making sure that the surrounding area is safe; checking and eliminating danger 15 minutes after detonating, and relieving the warning after confirming that 1 there is no danger.
Note
Cd
Quantity 00 0C
Unit
Project Name 0- 0 0 -Cd ~n d -=1 -d
N - d>~ ,.DQ0 LC
Sequence Ml~' ~\ 00 number -
Note -e
Quantity Cl - I Cl00
Z Cd -Qd
Project Nam C0 0 C
Cd Cd -d
SequenceH MW) 0 r-0 l number

Claims (5)

Claims WHAT IS CLAIMED IS:
1. A pier deep foundation pit blasting method for controlling flying stone by water coupling soil pressing, wherein the method is performed according to the following steps:
Si, cleaning up floating slag, movable stones, and accumulated water on a working face before drilling holes;
S2, perpendicularly drilling holes in designated positions, wherein the bottoms of blastholes are essentially on the same horizontal plane;
S3, clearing the holes after hole drilling is completed; S4, making stemming, selecting 1o emulsion explosives with the specification of 030 mm x 200 mm x 200 g for charging, and connecting non-electric millisecond delay detonators and detonating cords firmly, wherein attention is paid to protection in subsequent work;
S5, covering a blasting body with steel plates and sandy soil, and filling the gaps in the blastholes and the gaps below and above the steel plates with water;
S6, arranging sandy soil piles to surround and protect one side, close to high-tension cables, existing lines, residential areas, and workshops, of a bridge pier, including the sections close to the high-tension cables and the existing lines;
S7, arranging a blasting warning at each intersection, evacuating equipment, staff, animals, and the like out of a safety distance of 200 meters, and ensure all operators wear helmets; !o S8, after a monitor gives a blasting command, blowing, by a blaster, a warning whistle to confirm that a surrounding area is safe and then starting to detonate; checking and eliminating danger 15 minutes after detonating, and rcancelling the warning after confirming that there is no danger.
2. The pier deep foundation pit blasting method for controlling flying stone by water coupling soil pressing according to claim 1, wherein the holes are drilled by using 018 mm x (1.8 to 4.5 m) hollow hexagonal steel drill pipes with unequal lengths, a 042 mm straight alloy steel drill bit, and a pneumatic drill without an air leg.
3. The pier deep foundation pit blasting method for controlling flying stone by water coupling soil pressing according to claim 1, wherein the stemming with the diameter of 035 mm and the length of about 200 mm is made on site, which facilitates placing into the blastholes; the explosives are charged by using a positive continuous charging structure; the charge decoupling coefficient K = 45/30 = 1.5; the remaining blasthole length is filled by using the stemming; non-electric millisecond delay detonators and detonating cords with a length of 7.0 m are used.
4. The pier deep foundation pit blasting method for controlling flying stone by water coupling soil pressing according to claim 1, wherein in order to avoid detonation interruption, one detonator with the same segment number, namely, segment 1, is charged into the 5th section of explosives in cut holes charged with explosive; in rectangular auxiliary holes, one detonator with the same segment number, namely, segment 3, is additionally charged into the 4th section of explosives of every other three holes, which ensures that all explosives are detonated.
5. The pier deep foundation pit blasting method capable of controlling flying stone by water coupling soil pressing according to claim 1, wherein the blasting body is covered with two steel 1o plates with corresponding area and with the thickness of 6 mm; the steel plates are connected in an overlapped manner by using 4 bolts; 2 to 4 pieces of waste section steel are pressed on the steel plates, then about 0.5 m thick sandy soil is pressed on the waste section steel, one layer of steel plate is placed, and the steel plate is covered with 0.5 m thick sandy soil; finally, the gaps in the blastholes and the gaps below and above the steel plates are filled with water; detonator 1s connecting wires are protected in a process of setting up protection, and pin wires and the connecting wires are not broken.
AU2021101475A 2021-03-23 2021-03-23 Pier deep foundation pit blasting method capable of controlling flying stone by water coupling soil pressing Ceased AU2021101475A4 (en)

Priority Applications (1)

Application Number Priority Date Filing Date Title
AU2021101475A AU2021101475A4 (en) 2021-03-23 2021-03-23 Pier deep foundation pit blasting method capable of controlling flying stone by water coupling soil pressing

Applications Claiming Priority (1)

Application Number Priority Date Filing Date Title
AU2021101475A AU2021101475A4 (en) 2021-03-23 2021-03-23 Pier deep foundation pit blasting method capable of controlling flying stone by water coupling soil pressing

Publications (1)

Publication Number Publication Date
AU2021101475A4 true AU2021101475A4 (en) 2021-05-13

Family

ID=75829146

Family Applications (1)

Application Number Title Priority Date Filing Date
AU2021101475A Ceased AU2021101475A4 (en) 2021-03-23 2021-03-23 Pier deep foundation pit blasting method capable of controlling flying stone by water coupling soil pressing

Country Status (1)

Country Link
AU (1) AU2021101475A4 (en)

Cited By (1)

* Cited by examiner, † Cited by third party
Publication number Priority date Publication date Assignee Title
CN114577082A (en) * 2022-02-28 2022-06-03 浙江公铁建设工程有限公司 Safe covering system and covering method for buffering blasting impact of foundation pit

Cited By (2)

* Cited by examiner, † Cited by third party
Publication number Priority date Publication date Assignee Title
CN114577082A (en) * 2022-02-28 2022-06-03 浙江公铁建设工程有限公司 Safe covering system and covering method for buffering blasting impact of foundation pit
CN114577082B (en) * 2022-02-28 2023-09-29 浙江公铁建设工程有限公司 Safety covering system and method for buffering blasting impact of foundation pit

Similar Documents

Publication Publication Date Title
Wyllie Stabilisation of rock slopes
CN103629980B (en) Near existing line steep massif Loose Control Blasting construction method
CN111121575B (en) Town deep foundation pit shallow layer loosening control blasting construction method
CN108360527A (en) A kind of earthwork evacuation construction method
CN106677786B (en) A kind of ultra-deep big cross section vertical shaft shaft formatting by one blasting method based on electric detonator
CN110567329A (en) differential blasting vibration and flyrock control method
CN110118084B (en) Ultra-deep shaft construction method
CN111442701B (en) Refined blasting construction method for narrow deep foundation pit under complex geological condition
CN106595410A (en) Deep foundation pit earth pressure controlled blasting method
CN108517877A (en) Miscellaneous fill ultra-deep foundation pit consolidates slip casting combination double-row steel pipe stake supporting construction method
AU2021101475A4 (en) Pier deep foundation pit blasting method capable of controlling flying stone by water coupling soil pressing
CN111472356A (en) Larsen steel sheet pile sleeve obstacle clearing and pile pulling construction method
CN112228079B (en) Construction method for newly-built tunnel by crossing existing line at small angle
CN110512594B (en) Simple method for forming hole and pile in cavity of rotary drilling rig
CN114575746A (en) Construction method for natural gas pipeline reverse well drilling crossing
CN206989839U (en) Basement rock projection explosion pretreatment system in shield gauge
CN113684838A (en) Grooving construction method for rock-socketed ultra-deep underground diaphragm wall
CN113091542A (en) Railway blasting construction method
CN111692932A (en) Rotary excavating drilling internal auxiliary blasting construction technology for rock-socketed pile foundation
US20240068790A1 (en) Piston-type explosive loading and blasting structure and method for hard rock cable pit
Gupta et al. Design of underground artificial dams for mine water storage
AU2021102017A4 (en) Method for large-scale blasting with triple millisecond delays by loading explosive in three sections separated by stone powder in ultra-deep blast hole
CN115493467B (en) Underwater loose blasting construction method for bored pile
CN114319264A (en) Construction method for excavating large-section surge shaft by one-time drilling and blasting of ultra-deep hole and rapid well expansion
CN116104412A (en) Hard rock pile foundation composite pore-forming construction method

Legal Events

Date Code Title Description
FGI Letters patent sealed or granted (innovation patent)
MK22 Patent ceased section 143a(d), or expired - non payment of renewal fee or expiry