AU2010248209A1 - Step CAM mooring system - Google Patents

Step CAM mooring system Download PDF

Info

Publication number
AU2010248209A1
AU2010248209A1 AU2010248209A AU2010248209A AU2010248209A1 AU 2010248209 A1 AU2010248209 A1 AU 2010248209A1 AU 2010248209 A AU2010248209 A AU 2010248209A AU 2010248209 A AU2010248209 A AU 2010248209A AU 2010248209 A1 AU2010248209 A1 AU 2010248209A1
Authority
AU
Australia
Prior art keywords
mooring
vessel
arm
column
chains
Prior art date
Legal status (The legal status is an assumption and is not a legal conclusion. Google has not performed a legal analysis and makes no representation as to the accuracy of the status listed.)
Abandoned
Application number
AU2010248209A
Inventor
Pieter Liem
Jack Pollack
Sebastien Jean-Francois Truchi
Current Assignee (The listed assignees may be inaccurate. Google has not performed a legal analysis and makes no representation or warranty as to the accuracy of the list.)
Single Buoy Moorings Inc
Original Assignee
Single Buoy Moorings Inc
Priority date (The priority date is an assumption and is not a legal conclusion. Google has not performed a legal analysis and makes no representation as to the accuracy of the date listed.)
Filing date
Publication date
Application filed by Single Buoy Moorings Inc filed Critical Single Buoy Moorings Inc
Publication of AU2010248209A1 publication Critical patent/AU2010248209A1/en
Abandoned legal-status Critical Current

Links

Classifications

    • BPERFORMING OPERATIONS; TRANSPORTING
    • B63SHIPS OR OTHER WATERBORNE VESSELS; RELATED EQUIPMENT
    • B63BSHIPS OR OTHER WATERBORNE VESSELS; EQUIPMENT FOR SHIPPING 
    • B63B21/00Tying-up; Shifting, towing, or pushing equipment; Anchoring
    • B63B21/50Anchoring arrangements or methods for special vessels, e.g. for floating drilling platforms or dredgers
    • B63B21/507Anchoring arrangements or methods for special vessels, e.g. for floating drilling platforms or dredgers with mooring turrets
    • BPERFORMING OPERATIONS; TRANSPORTING
    • B63SHIPS OR OTHER WATERBORNE VESSELS; RELATED EQUIPMENT
    • B63BSHIPS OR OTHER WATERBORNE VESSELS; EQUIPMENT FOR SHIPPING 
    • B63B21/00Tying-up; Shifting, towing, or pushing equipment; Anchoring
    • B63B21/50Anchoring arrangements or methods for special vessels, e.g. for floating drilling platforms or dredgers
    • BPERFORMING OPERATIONS; TRANSPORTING
    • B63SHIPS OR OTHER WATERBORNE VESSELS; RELATED EQUIPMENT
    • B63BSHIPS OR OTHER WATERBORNE VESSELS; EQUIPMENT FOR SHIPPING 
    • B63B21/00Tying-up; Shifting, towing, or pushing equipment; Anchoring
    • B63B21/50Anchoring arrangements or methods for special vessels, e.g. for floating drilling platforms or dredgers
    • B63B21/507Anchoring arrangements or methods for special vessels, e.g. for floating drilling platforms or dredgers with mooring turrets
    • B63B21/508Anchoring arrangements or methods for special vessels, e.g. for floating drilling platforms or dredgers with mooring turrets connected to submerged buoy
    • BPERFORMING OPERATIONS; TRANSPORTING
    • B63SHIPS OR OTHER WATERBORNE VESSELS; RELATED EQUIPMENT
    • B63BSHIPS OR OTHER WATERBORNE VESSELS; EQUIPMENT FOR SHIPPING 
    • B63B21/00Tying-up; Shifting, towing, or pushing equipment; Anchoring
    • B63B2021/001Mooring bars, yokes, or the like, e.g. comprising articulations on both ends
    • B63B2021/002Yokes, or the like
    • BPERFORMING OPERATIONS; TRANSPORTING
    • B63SHIPS OR OTHER WATERBORNE VESSELS; RELATED EQUIPMENT
    • B63BSHIPS OR OTHER WATERBORNE VESSELS; EQUIPMENT FOR SHIPPING 
    • B63B27/00Arrangement of ship-based loading or unloading equipment for cargo or passengers
    • B63B27/24Arrangement of ship-based loading or unloading equipment for cargo or passengers of pipe-lines

Landscapes

  • Chemical & Material Sciences (AREA)
  • Engineering & Computer Science (AREA)
  • Combustion & Propulsion (AREA)
  • Mechanical Engineering (AREA)
  • Ocean & Marine Engineering (AREA)
  • Other Liquid Machine Or Engine Such As Wave Power Use (AREA)
  • Revetment (AREA)
  • Jib Cranes (AREA)
  • Cultivation Of Seaweed (AREA)
  • Filling Or Discharging Of Gas Storage Vessels (AREA)

Abstract

This invention relates to a mooring system comprising a vessel and a elongate mooring column having an upper end connected to an arm on the vessel projecting from the vessel bow and a lower end connected to the sea bed via anchor lines, characterised in that the arm is pivotable arond a transverse axis.

Description

WO 2010/131965 PCT/NL2010/050280 2 STEP CAM SYSTEM The present invention relates to an offshore system for mooring a vessel in a sea comprising: a vessel; a mooring column having a height and having an upper end and a 5 lower end; a pivoting mooring arm coupling the upper end of said mooring column to said vessel for permitting the mooring column to rotate about a pair of horizontal axes relative to the vessel; a plurality of heavy chains having upper ends coupled to the lower end of said mooring column, said heavy chains extending in loose catenary curves to the sea floor and giving the restoring force required to keep the vessel moored once 10 connected; the mooring column being free of attachment to any buoyant body, the system is self buoyant holds up the chains weight at the bottom and restrains the chains from drifting. 15 BACKGROUND OF THE INVENTION Hydrocarbons can be transferred from an undersea pipeline, such as one which leads to undersea wells, to tankers at the sea surface, by a variety of types of offshore terminals. Under severe environmental conditions, such as where there are intrusions of ice packs as well as severe storms, it is desirable to enable a tanker to disconnect from the 20 terminal to sail away, while much of the terminal sinks a considerable depth below the sea surface to lie free of much of the severe environmental conditions. One type of offshore terminal which can be used under these conditions includes a riser having a lower end that is loosely anchored to the sea floor, as through a group of catenary chains. The chains hold the riser deep under water but above the sea floor, while enabling the 25 riser to be easily lifted up to the vessel. Improvements in such a system which facilitate connection of the top of the riser to the vessel and which provide improved mooring at minimal cost, one of considerable value. A known system from The US Patent No.4,645,467 describes an offshore 30 structure of a type which includes a riser that is loosely anchored as by chains, which can facilitate the dynamics of anchoring. In a detachable riser, the riser can be lifted until WO 2010/131965 PCT/NL2010/050280 2 most of its height extends out of the sea and have a lower end that is weighted, to provide better mooring dynamics. The weight can include a clump weight hanging from the lower end of the riser. 5 Another patent Re32,578 describes a mooring system comprising a floating device, chains for anchoring the floating device, said chains being connected to a body which is rotatable about a vertical axis on an arm attached to the floating device. Conduits extend through the body, from the sea bottom towards the floating device. The patent focuses more particularly on the improvement in which the arm is rigidly attached 10 to the floating device and the body comprises a buoy having its own buoyancy, which buoy can be connected to or disconnected from the arm via a quick connecting coupling comprising releasable locking means. The present invention describes a two-step lifting of a mooring column during 15 connection of the vessel via its mooring arm to the mooring column. This 2 stage lifting during connection has the advantage of minimizing both the size and stiffness of the winching equipment. Should this lift be made entirely by the winching equipment (winch, line, sheaves, etc), this equipment would be large and negatively impact the geometry, physics and cost of the connection equipment. Making the initial lift short with low 20 tension winching equipment, keeps the components small and results in a lower tension and stiffness for the lifting line which eases the initial connection. The structural connection according to the present invention can handle large loads and thus the hydraulic lift system on the mooring arm is designed to lift the CAM to its highly tensioned moored operating position. 25 SUMMARY OF THE INVENTION It is an object of the present invention to provide an offshore system for mooring a vessel wherein after the connection of the vessel with the mooring column is done, the 30 upward lifting of the heavy chains with the mooring column is realized by the use of the pivoting arm only.
WO 2010/131965 PCT/NL2010/050280 3 It is therefore an further object of the present invention to provide a system of the above mentioned type which is cost-efficient and which is also suitable for use at smaller water depths than corresponding systems according to the prior art. According to the present invention, the offshore mooring system provides a pivoting arm 5 and mooring arrangement where the arm reaching down and lifting up the mooring column is eased and does not require the use of an expensive and large-size winch. Further, in the configuration according to the present invention, the arm is mounted to allow it to be moved from an inboard position to its operating position projecting beyond 10 the vessel's bow and hence prevents components from hanging over the bow and from potentially being damaged, partly by green water impact, while in transit. The novel features of the invention are set forth with particularity in the appended claims. The invention will be best understood from the following description when read 15 in conjunction with the accompanying drawings. BRIEF DESCRIPTION OF THE DRAWINGS Fig. la and lb shows a detailed view of the mooring arm retractor mechanism. 20 Fig. 2 shows a three dimensional view of one possible embodiment the mooring arm rectractor mechanism according to the present invention. Fig. 3 to 6 show the system according to the invention in different step of the connecting procedure 25 DESCRIPTION OF THE PREFERRED EMBODIMENTS Fig. la and lb show top views of the system according to the present invention. According to the present invention, the mooring arm 1 is mounted horizontally on a vessel 5 on bogie wheels/rails that allow it to be moved forward to its operating position 30 projecting beyond the vessel's bow as shown in figure lb. In Figure la, the arm 1 is stowed and does not project beyond the vessel's bow 15 which prevents components WO 2010/131965 PCT/NL2010/050280 4 from hanging over the bow and from potentially being damaged, partly by green water impact, while in transit. Figure 2 shows a three-dimensional view of one possible embodiment of a 5 mooring arm retractor mechanism according to the present invention. In the embodiment shown, a rack and pinion driving system 17,18 for the retraction and extension of the arm 1 is used. Teeth 17 of a ranch of the pinion system are provided along the length of the arm 1, whereas a toothed sprocket wheel 18 is provided on the box 3. The pinion is driven by a hydraulic or electrical motor. The rack and pinion restrict the arm 1 from 10 accelerating due to dynamic motions of the vessel. The sliding of the arm is done via friction pads 2 that are positioned inside a box type structure 3. The box 3 will also function as a pivoting system to pivot the arm 1 down- and upwards, around axis 16. The box 3 is hinged onto two supports 19 with shafts (not shown). 15 The arm 1 pivots around the axis 16 under the action of heavy duty hydraulic cylinders 4. When the upper position of the arm has been reached a mechanical locking system is activated in order to release the hydraulic pressure in the cylinders 4. The cylinders 4 are provided with a mechanical failsafe system when failure occurs during operation. The connection of the piping of the retractable arm 1 will be done with a spool piece that 20 can retract and extend side ways. When the arm is extended the spool piece will extend and connected with a graylock to the export line on the arm. To operate the system, the vessel 5 sails close to a mooring column 8 that projects above water level and the vessel stops and maintains station. Figure 3 shows the vessel 25 when the mooring arm 1 is moved forward along the rails 6 on deck and through a gate in the vessel's bow until the arm 1 projects to a pre-determined distance beyond the bow 15. The export line on the arm is located inside the arm to avoid problems with the sliding box system. 30 Figure 4 shows the first connecting step, when the vessel 5 is in contact with the mooring column 8. The mooring column 8 is a Counterweight Articulated Mooring WO 2010/131965 PCT/NL2010/050280 5 (CAM) that comprises a slim structural riser column, floating vertically in the water with its upper end projecting above water and its lower end secured to the sea bed by mooring chains 9 in a catenary configuration. In operation, the first part of the system is connected to the mooring column 8 by means of a mechanical connector 7 with articulated joints to 5 permit free weathervaning of the moored vessel as well as heave, pitch, surge, sway and roll motions of the vessel 5. A piping system 10 is provided on both the arm 1 and the mooring column 8 to allow the transfer of natural gas (or other product) from the vessel's storage tanks to a seabed 10 pipeline to shore, or, from a seabed pipeline into the vessel. A pick-up line is lowered from the outward end of the mooring arm 1 for connection (by work boat) to a line 11 that is pre-attached to the top of the CAM column. The mooring arm 1 is then articulated downwards using hydraulic rams at the vessel's deck such that 15 the outward end of the arm 1 is close to the top of the mooring column. Figure 5 shows the step further when the pick-up line has been pulled in to lift the mooring column top 12 into contact with the mechanical connector 7 and mooring arm 1 and mooring column 8 are connected together. By making the initial lift short with a low 20 tension winching equipment 13 keeps the components small and results in a low tension requirement for the lifting line. This low tension requirement results in a much softer line that will stretch more easily and better avoid line snatch loads that result from the physics of the initial lift of the 25 mooring column 8 where the relative motions between the column 8 and vessel 5 are brought into unison. As the column 8 is lifted by the line toward the connector 7 the now in phase motions allow for a low impact structural connection. Figure 6 shows the ultimate step of the connection between the vessel and the mooring 30 column. In this embodiment it is clearly shown that the mooring arm 1 is articulated back up to a higher position (and not only back to horizontal) and the vessel is now safely WO 2010/131965 PCT/NL2010/050280 6 moored to the mooring column 8. The structural connection can handle large loads and thus the hydraulic lift system on the mooring arm 1 is designed to lift the column to its highly tensioned moored operating position. This is the ultimate step when mooring chains are lifted from the sea floor increasing the 5 tension in the lifting line. Hence the heavy chains are giving the restoring force required for the mooring column function. The piping systems 10 of the mooring arm 1 and the mooring column 8 are connected and product may then be transferred from (or to) the vessel 5. 10 To disconnect the two parts of the mooring system after cargo transfer, the piping systems are first flushed clean and disconnected. The mooring arm is then pivoted back to its lower level and the mechanical connector is then released. The vessel moves away from the mooring point. 15 In the event of an emergency the mooring column 8 and piping 10 can be rapidly disconnected and released from the operational mooring position. Further, in order to cope with a collision the column 8 needs to have watertight compartments all along its length. Watertight compartments are accessible via a bolted flange access with a gasket in between the flanges. 20 A fender system may be installed around the top of the column 8 to allow a support vessel to moor onto the column and facilitating personnel intervention and maintenance. As will be apparent to those skilled in the art in the light of the foregoing disclosure, many alterations and modifications are possible in the practice of this 25 invention without departing from the spirit or scope thereof. Accordingly, the scope of the invention is to be construed in accordance with the substance defined by the following claims. 30

Claims (7)

1. Mooring system comprising a vessel (5) and a elongate mooring column (10) having an upper end (12) connected to an arm (1) on the vessel (5) projecting 5 from the vessel bow (15) and a lower end connected to the sea bed via anchor lines (9), characterised in that the arm (1) is pivotable arond a transverse axis (16).
2. Mooring system according to claim 1, wherein the arm (1) comprises a 10 displacment member(2,3) for moving the arm in a length direction of the vessel (5) between a retracted position in which the arm (1) for at least a larger part extends inboard of the vessel and a mooring position in which the arm (1) projects outboard from the bow (15). 15
3. Mooring system according to claims 1 or 2, wherein the arm (1) can pivot along axis (16) in an upward direction relative to the horizontal.
4. Mooring system according to any of the preceding claims, wherein the arm (1) is displaceable in the length direction via a pinion system (17,18). 20
5. Mooring system for mooring a vessel (5) according to claim 4 the mooring column being pivotable about a pair of horizontal axes relative to the vessel; a plurality of chains having upper ends coupled to the lower end of said mooring column, said chains extending in catenary curves to the sea floor and giving the 25 restoring force required to keep the vessel moored once connected; the mooring column being free of attachment to any buoyant body, the column is being self buoyant and holding up the chains weight at the bottom and restraining the chains from drifting, characterized in that after the connection of the vessel with the mooring column lifting up of the chains and the mooring column is realized 30 by the use of the pivoting arm only, the pivoting of the arm being able to apply the required tension. WO 2010/131965 PCT/NL2010/050280 8
6. Mooring system for mooring a vessel as claimed in claim 2 wherein the pivoting arm is also retractable so that it can be move forward to its operating position projecting beyond the vessel's bow and backwards so that it does not project beyond the vessel's bow during transit. 5
7. Method for mooring a vessel in a sea comprising: a vessel (5); a mooring column (10) having a height and having an upper end (12) and a lower end; a pivoting arm (1) coupling the upper end of said mooring column to said vessel for permitting the mooring column to pivot about a pair of horizontal axes 10 relative to the vessel; a plurality of chains (9) having upper ends coupled to the lower end of said mooring column, said heavy extending in catenary curves to the sea floor and giving the restoring force required to keep the vessel moored once connected; the lower half of said mooring column being free of attachment to any buoyant body having a greater positive buoyancy than the negative 15 buoyancy of said heavy chains, the method comprising the steps of: - sailing the vessel to the point where the upper end of the mooring column projects above water - stoping the vessel and maintaining station - moving the pivoting arm along the length direction until the arm projects 20 to a pre-determined distance beyond the bow - lowering a pick-up line from the outward end of the mooring arm for connection to a messenger line that is pre-attached to the top of the elongated mooring column by means of a pull in line - articulating the pivoting arm downwards about axis (16) using hydraulic 25 rams at the vessel's deck such that the outward end of the arm is close to the top of the upper part of the elongated mooring column - Pulling in the pick-up line to bring the top of mooring column up into contact with a mechanical connector until the pivoting arm and the mooring column are connected together, wherein 30 - after the connection, the pivoting arm is articulated back up to a level applying tension in the mooring column and chains to moor the vessel to the mooring column, and wherein WO 2010/131965 PCT/NL2010/050280 9 - Piping systems of the arm and the buoy element are connected and product is transferred from /or to the vessel via the piping systems. 5 10 15 20 25 30
AU2010248209A 2009-05-12 2010-05-12 Step CAM mooring system Abandoned AU2010248209A1 (en)

Applications Claiming Priority (3)

Application Number Priority Date Filing Date Title
EP09006397 2009-05-12
EP09006397.5 2009-05-12
PCT/NL2010/050280 WO2010131965A2 (en) 2009-05-12 2010-05-12 2 step cam system

Publications (1)

Publication Number Publication Date
AU2010248209A1 true AU2010248209A1 (en) 2011-12-01

Family

ID=42562986

Family Applications (1)

Application Number Title Priority Date Filing Date
AU2010248209A Abandoned AU2010248209A1 (en) 2009-05-12 2010-05-12 Step CAM mooring system

Country Status (7)

Country Link
US (1) US20120055388A1 (en)
JP (1) JP2012526702A (en)
CN (1) CN102448809A (en)
AU (1) AU2010248209A1 (en)
BR (1) BRPI1010552A2 (en)
GB (1) GB2484018A (en)
WO (1) WO2010131965A2 (en)

Families Citing this family (6)

* Cited by examiner, † Cited by third party
Publication number Priority date Publication date Assignee Title
EP3110689B1 (en) * 2014-02-25 2018-10-24 Excelerate Energy Limited Partnership Retractable lng cargo transfer bow manifold for tandem marine cargo transfers
KR101633650B1 (en) * 2014-11-27 2016-06-28 오션어스(주) Mooring apparatus for offshore construction
CN106542051A (en) * 2017-01-12 2017-03-29 上海海事大学 A kind of landing stage is tethered at composite structure equipment
KR102438692B1 (en) * 2018-07-20 2022-08-31 삼성중공업 주식회사 Floating vessel
CN109484571B (en) * 2018-09-27 2020-04-28 武汉船用机械有限责任公司 Ship mooring device
CN109625182B (en) * 2018-10-31 2020-10-02 中国船舶重工集团公司第七一九研究所 Soft rigid arm single-point mooring device with sliding block and capable of being rapidly disengaged

Family Cites Families (12)

* Cited by examiner, † Cited by third party
Publication number Priority date Publication date Assignee Title
FR2367654A1 (en) * 1976-10-15 1978-05-12 Emh IMPROVEMENTS FOR SYS
US4175903A (en) * 1976-12-20 1979-11-27 Carson William S Pick-up apparatus and containing assembly
NO145826C (en) * 1979-02-14 1982-06-09 Moss Rosenberg Verft As DEVICE FOR SUPPLYING A LIQUID CONSTRUCTION
NL8100936A (en) * 1981-02-26 1982-09-16 Single Buoy Moorings MOORING SYSTEM.
US4645467A (en) * 1984-04-24 1987-02-24 Amtel, Inc. Detachable mooring and cargo transfer system
US5381750A (en) * 1993-12-02 1995-01-17 Imodco, Inc. Vessel turret mooring system
US6037913A (en) * 1999-05-13 2000-03-14 Johnson; Pamela Kay Moveable satellite dish antenna mount
NL1013075C1 (en) * 1999-09-17 2001-03-20 Bluewater Terminal Systems Nv System for mooring a body floating on a body of water.
GB2361459A (en) * 2000-04-20 2001-10-24 Bluewater Terminal Systems Nv Floating vessel with pipeline attachment apparatus
GB0321768D0 (en) * 2003-09-17 2003-10-15 Ocean Power Delivery Ltd Mooring system
GB0421795D0 (en) * 2004-10-01 2004-11-03 Baross John S Full weathervaning bow mooring and riser inboarding assembly
CN101057042B (en) * 2004-11-11 2010-10-13 辛格尔浮筒系船公司 Soft quay mooring system

Also Published As

Publication number Publication date
WO2010131965A2 (en) 2010-11-18
JP2012526702A (en) 2012-11-01
US20120055388A1 (en) 2012-03-08
GB2484018A (en) 2012-03-28
WO2010131965A3 (en) 2011-10-20
BRPI1010552A2 (en) 2016-03-15
CN102448809A (en) 2012-05-09
GB201119731D0 (en) 2011-12-28

Similar Documents

Publication Publication Date Title
US5339760A (en) Apparatus for securing a vessel to a submersible mooring buoy
US8047151B2 (en) System and method for mooring of offshore structures
US7377225B2 (en) Spar-type offshore platform for ice flow conditions
US5941746A (en) Vessel with a disconnectable riser supporting buoy
US20120055388A1 (en) 2 step cam mooring system
NO167906B (en) VESSEL WITH A RELEASABLE MOLDING SYSTEM
US5678503A (en) Method for mooring floating storage vessels
US6893190B2 (en) Method and structure for connecting a floating structure with rope anchor lines to the seabed
JPH09511469A (en) Vessels for the transport and production and / or filling / discharging and / or good handling of hydrocarbons off the sea.
KR100280022B1 (en) Device for guiding submerged loading or unloading buoys
WO2000027692A1 (en) Device for positioning of vessels
AU2001291717A1 (en) Method and structure for connecting a floating structure with rope anchor lines to the seabed
CN112601697A (en) Detachable multi-point mooring and riser tower system and method
AU2013341863A1 (en) Device and method for interconnecting a tanker and a floating terminal
WO2010147478A1 (en) Device and method for transferring crew and personell between vessels and offshore structures
US6932127B2 (en) System for transferring oil from an offshore platform to a tanker
KR101842665B1 (en) Retractable chain connector
CA2440248C (en) A mooring buoy
CN109415107B (en) Disconnectable bow turret
GB2514773A (en) Underwater turbine installation apparatus and methods
CN115489669A (en) Deepwater SIT type single point mooring FPSO tie-back method
KR20220137987A (en) Spread mooring vessel with riser moonpool
Yan et al. Investigation On Scheme of Penglai 19-3 Phase? Jumper Hoses and Cables Installation
MXPA06013864A (en) Method for deploying floating platform

Legal Events

Date Code Title Description
MK4 Application lapsed section 142(2)(d) - no continuation fee paid for the application