AU2010227086A1 - A Method of Beneficiating Minerals - Google Patents

A Method of Beneficiating Minerals Download PDF

Info

Publication number
AU2010227086A1
AU2010227086A1 AU2010227086A AU2010227086A AU2010227086A1 AU 2010227086 A1 AU2010227086 A1 AU 2010227086A1 AU 2010227086 A AU2010227086 A AU 2010227086A AU 2010227086 A AU2010227086 A AU 2010227086A AU 2010227086 A1 AU2010227086 A1 AU 2010227086A1
Authority
AU
Australia
Prior art keywords
blasting
mineral
ore
waste
extracted
Prior art date
Legal status (The legal status is an assumption and is not a legal conclusion. Google has not performed a legal analysis and makes no representation as to the accuracy of the status listed.)
Granted
Application number
AU2010227086A
Other versions
AU2010227086B2 (en
Inventor
Alan Bye
Current Assignee (The listed assignees may be inaccurate. Google has not performed a legal analysis and makes no representation or warranty as to the accuracy of the list.)
CRC ORE Ltd
Original Assignee
CRC ORE Ltd
Priority date (The priority date is an assumption and is not a legal conclusion. Google has not performed a legal analysis and makes no representation as to the accuracy of the date listed.)
Filing date
Publication date
Priority to AU2010227086A priority Critical patent/AU2010227086B2/en
Application filed by CRC ORE Ltd filed Critical CRC ORE Ltd
Priority to BR112013008835A priority patent/BR112013008835A2/en
Priority to US13/878,697 priority patent/US20140144342A1/en
Priority to CA2814209A priority patent/CA2814209A1/en
Priority to AU2011316473A priority patent/AU2011316473B2/en
Priority to PCT/AU2011/001294 priority patent/WO2012048368A1/en
Publication of AU2010227086A1 publication Critical patent/AU2010227086A1/en
Application granted granted Critical
Publication of AU2010227086B2 publication Critical patent/AU2010227086B2/en
Priority to CL2013000985A priority patent/CL2013000985A1/en
Ceased legal-status Critical Current
Anticipated expiration legal-status Critical

Links

Classifications

    • EFIXED CONSTRUCTIONS
    • E21EARTH DRILLING; MINING
    • E21CMINING OR QUARRYING
    • E21C41/00Methods of underground or surface mining; Layouts therefor
    • E21C41/26Methods of surface mining; Layouts therefor
    • E21C41/30Methods of surface mining; Layouts therefor for ores, e.g. mining placers
    • EFIXED CONSTRUCTIONS
    • E21EARTH DRILLING; MINING
    • E21CMINING OR QUARRYING
    • E21C37/00Other methods or devices for dislodging with or without loading
    • E21C37/16Other methods or devices for dislodging with or without loading by fire-setting or by similar methods based on a heat effect
    • FMECHANICAL ENGINEERING; LIGHTING; HEATING; WEAPONS; BLASTING
    • F42AMMUNITION; BLASTING
    • F42DBLASTING
    • F42D3/00Particular applications of blasting techniques
    • F42D3/04Particular applications of blasting techniques for rock blasting

Abstract

A blasting method for beneficiating minerals comprising mining of a geological body (10) including a value portion (20) having at least a threshold content of a mineral to be extracted and a waste portion (30) relatively lean in content of a 5 mineral to be extracted wherein mining comprises controlled blasting of the geological body (10) such that the value portion (20) fragments differently than the waste portion (30), the difference in fragmentation between the value portion (20) and the waste portion (30) enabling separation of a mineral stream concentrated in the mineral to be extracted from the waste portion (30). m

Description

Pool Secton 29 ReguIlato? 3.2(2)) AUSTRALIA Patents Act 1990 COMPLETE SPECIFICATION STANDARD PATENT Application Number: Lodged: Invention Title: A Blasting Method for Beneficiating Minerals The following statement is a full description of this invention, including the best method of performing it known to me / us: P1 I1AAAU/0B10 1 A BLASTING METHOD FOR BENEFICIATING MINERALS The present invention relates to a blasting method for beneficiating minerals, for example beneficiating ores to increase metal grade prior to mineral 5 processing. Energy comes at a great cost to our world and societies so it should be used wisely and optimally. There is a need for industry, including the minerals industry, to respond proactively to calls for energy conservation. The major impediments to more efficient energy use in the minerals sector 10 are driven by the scale and complexity of mineral resource extraction. Energy use on mining operations is complex and there is much scope for optimizing extraction energy. High energy consumption in mineral production arises primarily as follows: * Moving huge tonnages of ore and waste material. In most precious and 15 base metal operations more than 96% of the material moved is uneconomic. * Ore comminution to liberate the micron scale valuable minerals. Fine grinding is energy intensive and has a low efficiency in creating new mineral surface area for liberation of metals. 20 9 Increasingly prevalent lower grade deposits require significantly more energy to achieve equivalent metal liberation compared to historical higher grade deposits. The mine to mill approach to integrated mine and SAG mill optimization that came out of the JKMRC demonstrated that throughput gains of up to 20% 25 could be obtained through a closer match of blasted run-of-mine ore to the feed best treated by a SAG mill (Various, 1998, Proceedings Mine to Mill, 11-14 October, Brisbane, 248p, Morell and Valery, Influence of feed size on AG/SAG mill performance, in Proceedings International Autogenous and Semi Autogenous Grinding Technology 2001 (Eds. Barratt et al.), vol 1, pp 203-214, University of 30 British Columbia: Vancouver); Lam et al., Maximising SAG mill throughput at Porgera gold mine by optimizing blast fragmentation, in Proceedings international Autogenous and Semi-Autogenous Grinding Technology 2001 (Eds. Barratt et al.), vol 1, pp 271-288 (University of British Columbia: Vancouver); Eloranta, 2 Optimised iron ore blast designs for SAG/AG mills, op cit, pp 262-270; Scott, Morell and Clark, Tracking and quantifying value from 'mine to mill' improvement, Value Tracking Symposium, 2002, pp 77-84; and Bye, The strategic and tactical value of a 3D geotechnical model for mining optimization, Anglo Platinum, 5 Sandsloot Open Pit, Journal South African Institute of Mining and Metallurgy, 106(2), pp 97-104). There are new drivers since the inception of mine-to-mill that bring a new imperative to the ongoing quest for optimal operation: Energy - the world at large is acutely aware of the cost and penalty of 10 excessive energy use. * Water - the competition for this resource and absolute constraints on its availability. * Massive low-grade orebodies - leading to vastly increased waste and often these ores are more competent and complex than older orebodies. 15 * Increasing demand for natural resources. The consequence of the increase in demand and the drop-off in grade is that even a saving of 10 to 20% of energy usage in terms of kWh/t of ore does not offset the massive increase in total energy usage per unit of product required in the future. Based on the trends of mineral usage published in the report on 20 Australian minerals usage (Australian Bureau of Agricultural and Resource Economics (ABARE), Minerals and Energy [online], volume14, no 4, 2007. Available http://www.abareeconomics.com/publications.html/energy/energy 07/ me nov 07 listing.pdf>), the average rise in energy consumption is about three per cent per annum. It is estimated that ore grade is dropping at about one per cent 25 per annum. Based on these figures, to achieve the oft-stated company targets of 10 to 20% saving in absolute energy (RioTinto, 2008, BHP Billiton, 2009; Anglo, 2009), specific energy usage (kWh/t ore treated) needs to drop below 40% of the usage in 2000 by 2020 and 20% by 2050. Applying current technology will not achieve anything near this objective. 30 Comminution, the size reduction process preceding metallurgical processing, requires very significant energy consumption. Overall comminution energy usage in the mining and concentrator stages of the process is as tabulated in Table 1.
3 TABLE 1 Approximate Distribution of Energy Usage Stage Feed Size (mm) Product (mm) Energy (% of process) 5 Mining (size reduction only) >1000 <300 1 Crushing 300 20 10 10 Milling 20 0.1 89 Subtotal 100 Fine grinding 0.1 0008 100 (extra) 15 The table confirms that major opportunities for energy reduction are in milling. Due to the very high energy cost of fine grinding, if it is incorporated in the flow sheet, it must be used judiciously. However, in the case of finely disseminated ores - whatever the minerals of interest (base metals, iron, tantalum or other) - fine grinding is typically required as part of the extraction 20 process. Following comminution, concentration steps are typically required, sometimes being conducted distant from the mine (raising the issue of transportation costs), to upgrade metal content in the feed material to concentration to a level sufficient to enable economic metal extraction. 25 Concentration involves separation of metal rich ore particles from waste or gangue particles through control over the surface properties of the feed material to concentration in concentrators. Concentrators may also have a large "footprint" taking up a significant amount of space. Such concentration steps, which may involve flotation, density separation and other operations, also add 30 capital and operating expense to processing of a mineral resource, For example, flotation is a common operation for the beneficiation of base metal sulphide ores, such as copper, zinc and lead bearing ores. Again, however, where an ore is finely disseminated and fine grinding has been required, difficulties may arise during flotation operations due to the changes in surface activity of the ore 35 particles during fine grinding. If concentration could be simplified, this would be advantageous for mineral resource economics.
4 It is an object of the present invention to provide a method for beneficiating minerals which enables reduction in energy consumption and other capital and operating costs in a mining operation. It is a further object of the invention to provide a method for beneficiating 5 minerals that increases economically viable ore reserves. With this object in view, the present invention provides a blasting method for beneficiating minerals comprising mining of a geological body including a value portion having at least a threshold content of a mineral to be extracted and a waste portion relatively lean in content of a mineral to be extracted wherein 10 mining comprises controlled blasting of the geological body such that the value portion fragments differently than the waste portion, the difference in fragmentation between the value portion and the waste portion enabling separation of a mineral stream concentrated in the mineral to be extracted from the waste portion. 15 Such selective fragmentation of the geological body differs from conventional blasting which is designed to blast an entire block of the geological body at a given energy to produce a top size that can be processed through a primary crushing step and later in concentrators. For example, such a scheme would be commonplace in the treatment of base and precious metal ores. 20 The geological body is, or includes, an orebody or ore block containing metal containing minerals in association with waste or gangue minerals. The metal containing minerals may be sulphide or oxide minerals of base metals and/or precious metals. For example, the orebody may contain base metal oxides or sulphides. The beneficiation method may enable reduced comminution 25 energy usage. As the controlled blasting of the method enables concentration of the mineral to be extracted, and thereby the metal content of the ore block, the beneficiation operations required following mining may be simplified and energy requirements reduced. The pre-concentration and size reduction that can be achieved by efficient controlled blasting will also have a major benefit on the 30 down stream process generally. Separation of the concentrated material, after mining, advantageously proceeds through physical separation. Separation on the basis of fragment size is particularly advantageous. In one scenario, though more complex scenarios 5 may be envisaged, blasting may result in production of a "fine" stream and a "coarse stream". The "fine" material has a finer size distribution than the coarse stream and blasting may be controlled to enable focused generation of fines in value portion(s) of the geological body, it further being observed that the value 5 portion(s) have at least a threshold content or grade of mineral/metal to be extracted. Such threshold content or grade is the minimum enabling economically viable extraction of the mineral from the geological body or deposit. As to economic viability, use of the method may also change what is defined as economic ore through blast beneficiation. This would significantly increase the ore 10 reserves of mining operations by upgrading marginally economic ore and/or converting low grade 'stockpile' material into mill feed grade material. The fine ore material has a higher mineral or metal content than mineral or metal content in material having the coarse fragment or particle size distribution. The coarse or waste stream may then be separated from the fine stream by 15 screening and other operations suitable for separation by particle size. However, it is logical that other physical separation steps may be used. Use of further concentration steps, such as flotation, is not precluded particularly for complex orebodies, for example containing polymetallic ores requiring to be separated. It is expected that such further separation steps may be simplified. 20 Although the above description implies that a single coarse stream and single fine stream will be generated by blasting in accordance with the method, this is solely for purposes of illustration and outcomes from the method may be more complex. That is, an ore may be sorted to produce a number of streams or fractions using the method, these streams then being further separated or 25 fractionated to produce a plurality of concentrate streams enriched to varying degree in the same or different minerals. The mineral streams may then be directed to further extraction steps which may be selected with reference to mineral or metal grade of each stream. Hydrometallurgical or pyrometallurgical processes may be used. For example, in the case of a gold bearing ore, the fines 30 fraction may be treated by cyanidation. A coarse fraction having a lower gold content, perhaps bound within an iron matrix - perhaps of pyrite or arsenopyrite may be treated by heap or dump leaching. Alternatively, if there is no economic incentive for further treatment, the coarse fraction may be rejected.
6 Blasting may be controlled to achieve such selective fragmentation behaviour, and beneficiation as above described, through a number of methodologies. Characterization andlor evaluation of the geological body, for example an ore block, is required as a first step. Exploration and sampling, 5 involving downhole assay at different intervals by reverse circulation drilling, allow a three dimensional ("3D") model of the geological body to be generated using various computer simulation packages. The geological characterization step may particularly focus the method for use where value portions are isolated or makeup small tonnages that are uneconomic to mine selectively with large mining 10 equipment. This is often the case at the periphery of geological bodies. Characterisation and evaluation also requires the geo-mechanical characteristics of the geological body to be identified. This needs rock material properties to be identified, for example by use of geophysical probes. Characterization and/or evaluation of the geological body allows definition 15 of a 3D blast volume within which blasting is to be conducted for extraction of the mineral(s) of interest. Such simulation allows zones rich in waste portion and rich in value portion to be identified and may also enable mapping of the blast volume by metal grade. Blasting is then advantageously controlled through a blasting design such 20 that those locations in a blast volume high in waste are fragmented to produce "coarser" material than those locations in the blast volume rich in value portion. A software package particularly useful for ensuring that blasting is conducted to achieve this objective - generally of directing the explosive energy from blasting to those locations where greatest degree of fragmentation is required - is the 25 Hybrid Stress Blasting Model (HSBM) developed by the Bryan Mining and Geology Research Centre at the University of Queensland. Other blast simulation and design packages to achieve such objective may also be adopted. Whichever software package, or other technique, is adopted, a blasting design is generated to achieve the desired fragmentation behaviour of the geological body or ore 30 block. Blast design may involve various inputs and the use of blasting techniques adapted to the geological body, or ore block, to be mined. Among those inputs may be included selection of appropriate electronic detonation systems, decking 7 and the use of selected explosive products. Decking is a process of creating a gap in the explosive column of a blasthole so that blasting energy can be directed to a specific location, Infill drilling may also be necessary to target high explosive energy to those areas with higher metal content. 5 The waste portion may still comprise some mineral(s) of economic interest. Therefore, further processing of the waste portion for liberation of minerals or metals, for example by heap or dump leaching, is not precluded. However, following the method of the present invention, extractive processes will be focused on the value portion, typically comprised in the above described fine 10 stream. The blasting method of beneficiating the geological body enables reductions in comminution energy consumption and may make exploitation of some ore bodies economic where previously processing could not have been economic. The method also offers scope for simplification of concentration and 15 extraction steps when exploiting a mineral resource. The blasting method of beneficiating minerals of the present invention may be more fully understood from the following description of a preferred embodiment thereof made with reference to the accompanying figures: Figure 1 is a graphic showing a blast design for a geological body to be 20 beneficiated using blasting in accordance with the method of one embodiment of the present invention; Figure 2 is a graphic showing generation of fines in an ore body when a method in accordance with one embodiment of the present invention is conducted. 25 Figure 3 shows fragment size distributions for ore and waste streams produced following blasting of the geological body with the blast design illustrated in Figure 1. Referring to Figure 1, the graphic shows a geological body or ore block 10 including a value portion in the form of a mineralized ore body - for example 30 being a finely disseminated gold containing ore body 20 containing 5 g/t ore in gold. The ore body 20 forms an incline or vein in geological body 10. Surrounding the gold containing ore body 20 is a body 30 of waste or gangue material, this forming the waste portion of ore block 10. The gold containing ore 8 body 20 was defined following exploration and sampling and it is established that the ore body 20 comprises finely disseminated ore. Such exploration activity also well defines waste body 30, allowing a 3D model of the ore block 10 to be designed using modelling packages available to those skilled in the art. The ore 5 block 10 could not be economically exploited by conventional means. In addition, the rock material properties of ore body 20 are identified by use of geophysical probes, as are known in the art. Such identification enables the geo-mechanical characteristics of the ore body 20 to be identified and input to the blast design as described below. 10 These procedures result in identification of a 3D blast volume 40 which is to be blasted during the mining operation. Prior to blasting, a blasting design is developed with the use of a blast simulation software package, here the Hybrid Stress Blasting Model (HSBM) developed by the Bryan Mining and Geology Research Centre at the University of Queensland. The HSBM model is described 15 in literature including S Esen, A Hybrid Stress Blast Model based on Non-Ideal Detonation Behaviour of Commercial Explosives, PhD Thesis, University of Queensland, 2004; and I Onederra et al., Burden Movement Experiments using the Hybrid Stress Blasting Model (HSBM), Explo 2007, Wollongong, 3-4 September, 2007, the contents of which are hereby incorporated herein by 20 reference. The blasting design has the objective of generating a higher degree of fragmentation in ore body 20 than in waste body 30. To that end, the blasting design, which is illustrated by Fig. 1, here requires a majority of the explosive charges to be located in ore body or value portion 20. That is, release of 25 explosive energy during blasting is concentrated in value portion 20 and only the minimum blasting energy required for loading and hauling is used in the waste body 30. Various blast designs can be used to achieve this, for example two holes, one marked 22 and the other being marked 24, are drilled into the ore body 20, Hole 22 is drilled to a slightly greater depth than hole 24. However both 30 holes 22 and 24, which have a diameter of 89mm, are drilled to near the base of ore body 22. Both holes 22 and 24 are then packed with an explosive emulsion in respective locations 22a and 24a at the base of holes 22 and 24.
9 A single hole 26 is drilled into the waste body 30 and this hole 26 is packed with explosive emulsion at three locations (one location 26a being within the ore body 20 and located between locations of explosive 22a and 24a, and two locations 26b and 26c within the waste body 30. 5 Schematically, lesser quantities of explosive emulsion are used at locations 26b and 26c than at the other locations for explosive. However, the quantity of explosive emulsion is selected to assure a lower degree of fragmentation within waste body 30. This blasting design results in controlled blasting ensuring that material in the ore body 20 is fragmented to a smaller 10 average particle size, D 5 o, than the material in the body of waste or gangue. The resultant focused generation of fines within ore body 20 is shown schematically in Fig. 2 where the clouded region 25 shows where finest fragments are generated. Some fines are also formed in the waste body 30, in the vicinity of hole 26 but not to an extent which affects beneficiation in accordance with the blasting method 15 described here. Fragmentation of the waste body 30 is schematically illustrated by the grey lines 36. The resultant fragment size distributions for the value or ore stream; and waste stream are illustrated in Fig. 3. Fig. 3 clearly shows a distinct difference between D 60 for the value or ore stream (80 mm) and D 50 for the waste stream (210 mm), this difference being 20 sufficient to allow selective physical separation on the basis of size. For example, screening could be used to separate the value or ore stream, this being a finer fraction from the waste stream which is a coarse stream. The fine ore stream is concentrated and has a higher gold content than the coarse stream. Therefore, as a result of the controlled blasting, a stream having higher metal content is 25 generated than would be generated by conventional blasting which produces material with D O of 150 mm and still requiring beneficiation. The blasting therefore results in beneficiation or upgrading of ore block 10 not achievable by conventional blasting. In conventional blasting, in contrast, the entire ore block 10 would be 30 blasted at a given energy to achieve a top size that can be transported in haul trucks and processed through the primary crusher which is not always reliably achieved.
10 Following mining of ore block 10, run of mine material is screened at 200mm, this size being determined as the the optimum economic size fraction in this example, with >200mm coarse material going to a waste dump or leach pad to enable heap or dump leaching. The <200mm fine material is directed to a 5 process plant for high grade conventional gold extraction, Table 2 provides results of a simulation showing how the potential uneconomic ore block 10 has been beneficiated by controlled blasting in accordance with the method described here. 10 TABLE 2 Scenario illustrating the Upgrading of Ore Block 10 Ore tonnage (t) Grade (g/t) Recovered Metal (Oz) Results Conventional Blasting 1514 1.01 491 Uneconomic 15 Controlled Blasting 717 1.91 438 Economic The grades in Table 2 are less than the 5 g/t gold present in the ore since waste material is still present after blasting. However, because controlled blasting results in a lesser tonnage of material to be processed, the effective 20 grade is very significantly increased over conventional blasting. Essentially, the grade of the ore feed to the processing plant has been increased by 90 per cent and the tonnage to be processed has been reduced by 50 per cent. Even though less metal has been recovered than using conventional blasting, the savings in energy, approximately 20 per cent, and other capital and 25 operating costs resulting from the lower tonnage processed, an uneconomic ore body 10 has become economically viable to mine and process. The method is not limited to beneficiation of gold bearing ores. Base metal ores, such as copper and other base metal ores may also be beneficiated in accordance with the method. 30 It will be apparent that the above described beneficiation method results in increased energy efficiency and reduced processing costs, such cost reduction increasing the possibility for mining and processing lower grade mineral deposits. In particular, crushing and milling energy costs may be reduced in accordance with the method of the invention. It also highlights to ability to beneficiate 11 previously uneconomic ore bodies by upgrading the metal content through blasting and screening, thereby offering the potential to expand ore resources available for treatment.

Claims (9)

1. A blasting method for beneficiating minerals comprising mining of a geological body including a value portion having at least a threshold content of a mineral to be extracted and a waste portion relatively lean in content of a mineral 5 to be extracted wherein mining comprises controlled blasting of the geological body such that the value portion fragments differently than the waste portion, the difference in fragmentation between the value portion and the waste portion enabling separation of a mineral stream concentrated in the mineral to be extracted from the waste portion, 10
2. A method of claim I wherein separation of the mineral stream concentrated in the mineral to be extracted is separated by physical separation.
3. A method of claim 2 wherein physical separation is separation on the basis of fragment size.
4. A method of claim 3 wherein physical separation is by screening. 15
5. A method of claim 3 or claim 4 wherein blasting produces a fine material and a coarse material, said fine material having a higher metal content than said coarse material, the fine and coarse fractions being separated by physical separation.
6. A method of claim 5 wherein said blasting is controlled through a blasting 20 design such that locations in the geological body high in waste portion are fragmented to produce coarser material than those locations in the geological body high in value portion.
7. A method of any one of the preceding claims wherein said geological body includes an ore body. 25
8. A method of claim 7 wherein said ore body contains at least a base metal or a precious metal. 13
9. A blasting method of beneficiating an orebody substantially as hereinbefore described with reference to the Figures. CRC ORE LTD WATERMARK PATENT & TRADE MARKS ATTORNEYS P33778AU00
AU2010227086A 2010-10-11 2010-10-11 A Method of Beneficiating Minerals Ceased AU2010227086B2 (en)

Priority Applications (7)

Application Number Priority Date Filing Date Title
AU2010227086A AU2010227086B2 (en) 2010-10-11 2010-10-11 A Method of Beneficiating Minerals
US13/878,697 US20140144342A1 (en) 2010-10-11 2011-10-11 Blasting method for beneficiating minerals
CA2814209A CA2814209A1 (en) 2010-10-11 2011-10-11 A blasting method for beneficiating minerals
AU2011316473A AU2011316473B2 (en) 2010-10-11 2011-10-11 A blasting method for beneficiating minerals
BR112013008835A BR112013008835A2 (en) 2010-10-11 2011-10-11 dynamiting method for minerals beneficiation
PCT/AU2011/001294 WO2012048368A1 (en) 2010-10-11 2011-10-11 A blasting method for beneficiating minerals
CL2013000985A CL2013000985A1 (en) 2010-10-11 2013-04-11 Blasting method for the benefit of materials comprising the extraction of a geological body that includes a valuable portion that has at least a threshold content of a mineral to be extracted and a discard portion, said method also comprises a controlled blasting of the geological body , so that the fragments of the valuable portion are different from the discard portion.

Applications Claiming Priority (1)

Application Number Priority Date Filing Date Title
AU2010227086A AU2010227086B2 (en) 2010-10-11 2010-10-11 A Method of Beneficiating Minerals

Publications (2)

Publication Number Publication Date
AU2010227086A1 true AU2010227086A1 (en) 2012-04-26
AU2010227086B2 AU2010227086B2 (en) 2012-09-13

Family

ID=45937765

Family Applications (2)

Application Number Title Priority Date Filing Date
AU2010227086A Ceased AU2010227086B2 (en) 2010-10-11 2010-10-11 A Method of Beneficiating Minerals
AU2011316473A Ceased AU2011316473B2 (en) 2010-10-11 2011-10-11 A blasting method for beneficiating minerals

Family Applications After (1)

Application Number Title Priority Date Filing Date
AU2011316473A Ceased AU2011316473B2 (en) 2010-10-11 2011-10-11 A blasting method for beneficiating minerals

Country Status (6)

Country Link
US (1) US20140144342A1 (en)
AU (2) AU2010227086B2 (en)
BR (1) BR112013008835A2 (en)
CA (1) CA2814209A1 (en)
CL (1) CL2013000985A1 (en)
WO (1) WO2012048368A1 (en)

Families Citing this family (17)

* Cited by examiner, † Cited by third party
Publication number Priority date Publication date Assignee Title
US9316537B2 (en) 2011-06-29 2016-04-19 Minesense Technologies Ltd. Sorting materials using a pattern recognition, such as upgrading nickel laterite ores through electromagnetic sensor-based methods
CA2840545C (en) 2011-06-29 2017-06-13 Minesense Technologies Ltd. Extracting mined ore, minerals or other materials using sensor-based sorting
US11219927B2 (en) 2011-06-29 2022-01-11 Minesense Technologies Ltd. Sorting materials using pattern recognition, such as upgrading nickel laterite ores through electromagnetic sensor-based methods
CA2871632C (en) 2012-05-01 2017-06-06 Minesense Technologies Ltd. High capacity cascade-type mineral sorting machine and method
RU2511330C2 (en) * 2012-07-16 2014-04-10 Федеральное государственное бюджетное учреждение науки ИНСТИТУТ ПРОБЛЕМ КОМПЛЕКСНОГО ОСВОЕНИЯ НЕДР РОССИЙСКОЙ АКАДЕМИИ НАУК (ИПКОН РАН) Method for large-scale explosive destruction of mine rock masses of complex structure for selective extraction of mineral deposit at open-pit mining
CN110090812B (en) 2014-07-21 2021-07-09 感矿科技有限公司 High capacity separation of coarse ore minerals from waste minerals
US9522415B2 (en) 2014-07-21 2016-12-20 Minesense Technologies Ltd. Mining shovel with compositional sensors
CA3063537A1 (en) * 2017-06-27 2019-01-03 Reflex Instruments Asia Pacific Pty Ltd Method and system for acquiring geological data from a bore hole
BR112020015361B1 (en) * 2018-01-29 2022-06-07 Dyno Nobel Inc Explosive release method
ES2725321A1 (en) * 2018-03-21 2019-09-23 Accenture Global Solutions Ltd SYSTEM AND METHOD TO CONTROL A PERFORATION AND FLYING EVENT (Machine-translation by Google Translate, not legally binding)
US11307327B2 (en) 2018-10-26 2022-04-19 Tata Consultancy Services Limited Method and system for online monitoring and optimization of mining and mineral processing operations
BR112021011853A2 (en) * 2018-12-18 2021-09-08 Technological Resources Pty. Limited AUTOMATED UPDATE OF GEOLOGICAL MODEL CONTOURS FOR BETTER ORE EXTRACTION
EA039837B1 (en) * 2018-12-20 2022-03-18 Дайно Нобел Инк. System for automated loading of blastholes and method related thereto
SE544132C2 (en) 2019-07-29 2022-01-11 Metso Sweden Ab A beneficiation arrangement for use with geological material
CN110608040B (en) * 2019-09-20 2021-02-02 瓮安大信北斗山磷矿 Complex phosphate ore mining method
CN112378300B (en) * 2020-10-09 2022-12-27 包头钢铁(集团)有限责任公司 Separation blasting method for mixed blasting area of ore and rock
CN113154976A (en) * 2021-05-19 2021-07-23 安徽马钢张庄矿业有限责任公司 Novel fan-shaped deep hole distribution method for mining blasting

Family Cites Families (19)

* Cited by examiner, † Cited by third party
Publication number Priority date Publication date Assignee Title
US2775940A (en) * 1953-10-07 1957-01-01 Jr Robert L Klotz Method for blasting
US2877954A (en) * 1954-06-14 1959-03-17 Taggart & Myers Dressing of ore
US3145163A (en) * 1960-10-03 1964-08-18 Int Minerals & Chem Corp Beneficiation of potash ores
FR2381108A1 (en) * 1977-02-16 1978-09-15 Minemet Rech Sa PROCESS FOR THE PRECONCENTRATION OF METALLIC PRODUCTS
US4326751A (en) * 1979-09-17 1982-04-27 Occidental Oil Shale Inc. Blasting to a horizontal free face with mixing of fragments
DE3108425A1 (en) * 1981-03-06 1982-09-23 Basf Ag, 6700 Ludwigshafen METHOD FOR DEVELOPING A VERY DEEP COAL
US4423814A (en) * 1981-06-05 1984-01-03 Occidental Research Corporation Separation or concentration of magnesium-bearing minerals by induced fluorescence
US4560205A (en) * 1984-07-06 1985-12-24 Occidental Oil Shale, Inc. Method for control of geometry of fragmented mass in an situ oil shale retort
SE505963C2 (en) * 1993-02-25 1997-10-27 Nitro Nobel Ab Method for loading boreholes with explosives
DE19983580T1 (en) * 1998-09-24 2001-08-16 Schlumberger Technology Corp Detonators for use in explosive devices
US6772105B1 (en) * 1999-09-08 2004-08-03 Live Oak Ministries Blasting method
UA67398A (en) * 2003-09-12 2004-06-15 State Scient Res Mining I Well charge of explosive of controlled power
AU2004293486C1 (en) * 2003-11-28 2013-10-24 Orica Explosives Technology Pty Ltd Method of blasting multiple layers or levels of rock
US8272247B2 (en) * 2006-05-18 2012-09-25 The University Of Queensland Apparatus for determining breakage properties of particulate material
FI123153B (en) * 2006-12-22 2012-11-30 Sandvik Mining & Construction Oy Drawing up a drilling plan for mining a rock space
RU2350896C2 (en) * 2007-05-16 2009-03-27 Федеральное государственное образовательное учреждение высшего профессионального образования Забайкальский горный колледж Method for blasting preparation of gold-bearing ore for leaching
US8820847B2 (en) * 2010-02-22 2014-09-02 Technological Resources Pty. Ltd. Block caving method
ES2675807T3 (en) * 2010-04-15 2018-07-12 Orica International Pte Ltd High energy blasting
WO2013006896A1 (en) * 2011-07-08 2013-01-17 Technological Resources Pty. Limited Sorting in a mining operation

Also Published As

Publication number Publication date
AU2011316473B2 (en) 2014-06-19
AU2010227086B2 (en) 2012-09-13
AU2011316473A1 (en) 2013-03-14
CL2013000985A1 (en) 2014-03-07
US20140144342A1 (en) 2014-05-29
WO2012048368A1 (en) 2012-04-19
CA2814209A1 (en) 2012-04-19
BR112013008835A2 (en) 2017-01-31

Similar Documents

Publication Publication Date Title
AU2010227086B2 (en) A Method of Beneficiating Minerals
CA3067503C (en) Beneficiation of values from ores with a heap leach process
US11203044B2 (en) Beneficiation of values from ores with a heap leach process
Norgate et al. The greenhouse gas impact of IPCC and ore-sorting technologies
Klein et al. A hybrid flotation–gravity circuit for improved metal recovery
Sekisov et al. Low-waste mining technology for structurally complex deposits with mixed-type process flows of ore extraction and processing
CN108514950A (en) A method of improving copper-sulphide ores copper recovery
Omarova et al. Flotation enrichment of enrichment factory tailings for use as technogenic ore
Grigg et al. The pre-concentration of precious and base metal deposits using the inline pressure jig (IPJ), higher feed grades and more metal
Klein et al. Integrating mining and mineral processing for advanced mining systems
Kržanović et al. Maximizing the net present value by applying an optimal cut-off grade for long-term planning of the copper open pits
Mosher Comminution circuits for gold ore processing
Von Michaelis How energy efficient is HPGR
Gorain Physical processing: innovations in mineral processing
Bustillo Revuelta et al. Mineral Processing
Brent et al. Ultra-high-intensity blasting-a new paradigm in mining
Duffy et al. Resource efficient mining processes of tomorrow
Bamber et al. Reducing selectivity in narrow-vein mining through the integration of underground pre-concentration
Barns et al. Designing the optimal flotation circuit–the Prominent Hill case
Grammatikopoulos et al. The disruptive role of process mineralogy in geology and mineral processing industry
Grguric et al. An integrated geometallurgical approach to optimize business outcomes at the MKD5 nickel deposit, Mount Keith, Western Australia
Rasskazov et al. Improvement of Mining and Processing Flowsheets at Structurally Complex Ore Deposits
Mosher Comminution circuits for gold ore processing
Cheban Technology of extraction and primary processing of low-grade and off-balance ores
Salmi et al. Value chain optimization for grade engineering by mine-wide frag-mentation optimisation

Legal Events

Date Code Title Description
FGA Letters patent sealed or granted (standard patent)
MK14 Patent ceased section 143(a) (annual fees not paid) or expired