AU2004237885B2 - Metal melt boring process - Google Patents

Metal melt boring process Download PDF

Info

Publication number
AU2004237885B2
AU2004237885B2 AU2004237885A AU2004237885A AU2004237885B2 AU 2004237885 B2 AU2004237885 B2 AU 2004237885B2 AU 2004237885 A AU2004237885 A AU 2004237885A AU 2004237885 A AU2004237885 A AU 2004237885A AU 2004237885 B2 AU2004237885 B2 AU 2004237885B2
Authority
AU
Australia
Prior art keywords
melt
borehole
pipeline
rock
metal
Prior art date
Legal status (The legal status is an assumption and is not a legal conclusion. Google has not performed a legal analysis and makes no representation as to the accuracy of the status listed.)
Ceased
Application number
AU2004237885A
Other versions
AU2004237885A1 (en
Inventor
Werner Foppe
Current Assignee (The listed assignees may be inaccurate. Google has not performed a legal analysis and makes no representation or warranty as to the accuracy of the list.)
Individual
Original Assignee
Individual
Priority date (The priority date is an assumption and is not a legal conclusion. Google has not performed a legal analysis and makes no representation as to the accuracy of the date listed.)
Filing date
Publication date
Priority claimed from AU26709/00A external-priority patent/AU2670900A/en
Application filed by Individual filed Critical Individual
Priority to AU2004237885A priority Critical patent/AU2004237885B2/en
Publication of AU2004237885A1 publication Critical patent/AU2004237885A1/en
Application granted granted Critical
Publication of AU2004237885B2 publication Critical patent/AU2004237885B2/en
Anticipated expiration legal-status Critical
Ceased legal-status Critical Current

Links

Description

AUSTRALIA
PATENTS ACT 1990 DIVISIONAL APPLICATION NAME OF APPLICANT: Werner FOPPE ADDRESS FOR SERVICE: DAVIES COLLISON CAVE Patent Attorneys 1 Nicholson Street Melbourne, 3000.
INVENTION TITLE: "METAL MELT BORING PROCESS" The following statement is a full description of this invention, including the best method of performing it known to us: P 'OPER\D I I255IWI II Ap I7 ip I doc :/!5/2ix)7 -1- MOLTEN BATH DRILLING METHOD AND APPARATUS Cross Reference to Related Applications I/I This application is a national stage of PCT/EP00/01015 filed 00 00 5 9 February 2000 and claims priority from German national C. application 19909836.0 of 5 March 1999.
CI Field of the Invention The present invention concerns a fusion drilling process for the placement of dimensionally accurate borings, particularly those of large diameter, in rock, in which the waste melt is pressed into the surrounding rock, which is cracked due to the effects of temperature and pressure, and in which a borehole lining is produced during boring by solidifying melt.
Background of the Invention The placement of borings in rock by means of melting the rock to be removed is generally known. Thus, for example, US Patent 3,357,505 discloses a boring head with which the melting of rock is performed.
This known boring head, which consists of a metal resistant to high temperatures, such as a molybdenum or tungsten, is heated by means of heating elements to a temperature above the melting temperature (1000-2000°C) of the rock and pressed at high pressure by means of costly extendable propulsion rods into the rock, which then melts.
P %OPEl\DA- 30 APr 0? p I doc 2A)i ,21X -2- The problems associated with transporting away the waste rock melt occurring in the boring process are solved in this case in that the rock melt enters into an opening of the Sboring head and is then conveyed to the surface within a 00 00 5 conductor pipe by a rapid gas stream.
c, In spite of the resistant material, the boring head is Ci subject to great wear due to the corrosive effects of the molten rock, so that it occasionally has to be replaced.
Furthermore, solving the problems associated with the waste by subjecting the melt to a high pressure, in addition to the naturally prevailing extremely high temperature gradients between the rock melt and the surrounding solid rock at the boring head, in order to cause the formation of cracks and splits of the surrounding solid rock into which the waste rock melt can be pressed through temperature and pressure stress is also known. It is thus no longer necessary to convey the waste material to the surface due to this process.
Also known is the pressing of the rock melt around the boring head during the production of fusion drilling borings, so that the melt solidifies above and around the fusion drilling head, particularly due to additional cooling measures which are provided, and the borehole is lined with a uniform glassy melt layer.
A device of this type, in which the rocks is melted by an
H
2
/O
2 flame, is known from DE 2,554,101.
P OPERDH I 25454Af) 0 pl )7 spll do p)? -3- A fusion drilling device and a process for the operation of the device, which utilizes the pressing of the waste into the surrounding stone and the borehole lining, is known from n DE 195 01 437 Al. The device described here is used in salt 00 00 5 galleries and uses the molten salt itself as the boring r- M medium.
In the known devices, there is a problem in that, due to the melt solidifying above and around the boring device, adhesion occurs between the wall of the boring device and the lining of the borehole, which typically must be overcome through special hydraulic propulsion and lifting facilities in order to bore further.
Correspondingly, a continuous hydraulic pressure must be used when operating with the known process, which makes the boring facility as a whole very costly, because it must be designed for enormous pressures of up to several thousand tons.
A boring device known from US 5,168,940 uses a metal-ceramic mixture for the boring head in order to reduce wear and more easily overcome the adhesive forces between the boring head surface and the rock melt.
The known facilities must be equipped with costly supply lines in order to supply the enormous quantities of energy for heating to the boring head over several kilometres of bore depth.
P \OPERDW I 2545(Wd W A p, ii? rp dO 2A,5/ll7 -4- Due to the melting around the boring head, the later lifting of the boring device is also problematic in this case.
V) Summary of the Invention 00 00 5 In accordance with the invention, there is provided a process for fusion drilling of a borehole in rock comprising the steps of: C-i advancing a pipeline element by element into a borehole in rock; feeding a molten metal as a boring medium through said pipeline to emerge from a lowest element of said pipeline, melt away the rock at a base of said borehole and produce a waste melt comprised of the molten metal and molten rock; cracking rock surrounding said borehole by effects of temperature and pressure of the feeding of the molten metal into said borehole; pressing said waste melt into cracked rock surrounding said borehole; and forming a lining for said borehole from solidification of the waste melt around said borehole.
In another aspect, there is provided an apparatus for fusion drilling of a borehole in rock, comprising: a pipeline comprised of a plurality of pipeline elements extendable element by element into a borehole in rock; means for feeding a molten metal as a boring medium through said pipeline to emerge from a lowest element of said pipeline, to melt away the rock at a base of said P 'OPER loC .254:N, 07 sp, I .1 1:1 -4aborehole and to produce a waste melt comprised of the molten metal and molten rock, rock surrounding said borehole cracking by effects of temperature and pressure of the V) feeding of the molten metal into said borehole, said waste 00 00 5 melt being pressed into cracked rock surrounding said
C--
C borehole; and a lining for said borehole formed in situ from C- solidification of the waste melt around said borehole.
In another aspect, there is provided a boring device for the production of fusion drilling borings of large-diameter in rock with which rock to be removed is meltable and by means of which a borehole lining made of solidified melt can be produced from the melt occurring in the melt process and fed into the borehole, wherein surfaces of the boring device in contact with the molten or solidified melt mass consist of graphite.
Preferably, the heated melt containing metal, which is also understood to mean a pure metal melt, e.g. an iron melt at a pouring temperature of approximately 2000 0 C, is poured as a low viscosity boring medium into the first pipeline element in the direction of boring, so that the metal melt comes out of the last pipeline element directly over the base of the borehole and melts and removes the rock from the base of the borehole.
The removal of the molten waste rock is hereby promoted in that the rock has a significantly lower density than the metal melt, so that the rock melt automatically floats on P iOPER'.DHI 2545-WI) 1 Api IL7 spa doc 2/2W)7 -4bthe metal melt. The base of the borehole is thus automatically a continuously freed from the molten rock melt.
00 00 5 Due to the high static pressure which results from the metal Cmelt column standing in the pipeline elements, the metal melt coming out of the lowermost pipeline element is guided O with the waste material (rock melt), in the process according to the invention, between the outer side of the pipeline elements and the inner wall of the borehole, where they solidify as the boring progresses. Because the boring process is performed without further cooling measures, energy and cost savings of over 50% relative to known fusion drilling processes result.
r The solidified melt, which can also be a mixture of melts made of metal and rock, forms a pressure seal between the Spipeline element and the inner wall of the borehole, so that, due to the extremely high temperature gradients in the rock and the pressure generated, splitting of the rock I material occurs automatically, whereby above all the oO oO lighter waste melt is pressed into the surrounding rock.
c, N The loss of metal melt which results due to the compression FD and solidification can be compensated at the beginning of C the boring at the first pipeline element through addition of metal melt. This addition can be performed continuously or discontinuously, because the volume of the melt column resting on the base of the borehole acts as a reservoir.
In this way, it is possible according to the invention to produce a dimensionally stable lined borehole, particularly lined with cast metal, which can have a large diameter, e.g. of more than 1 m, and essentially any desired profile, with this borehole able to be supplied for its intended use without any further post-processing, due to the automatic cast metal lining. The boring can hereby be performed not only vertically, but also horizontally or at other angles to the surface of the earth, so that borings for greatly differing intended uses such as, geothermal power stations, supply lines, or tunnels can be produced.
This means that, in the metal melt boring process according to the invention, in one single work cycle a borehole is melted, the borehole melt is pressed into the surrounding rock, and a compressed, stable borehole lining is made from the cooled rock melt which is simultaneously also lined with a seamless metal wall.
The process according to the invention thus advantageously allows the possibility of sinking metal-lined boreholes of the dimensions mentioned even to depths of over 6kilometers in one work cycle, without having to remove the d borehole melt or having to supply coolant, and with work able to be done at the boring target at temperatures of over 3000 CC, rock pressures of over 1,000 bar, melt cutting forces of up to 10,000 bar or more, and a pipeline ^I element weicht of over 10,000 tons, which the current 00oO 00 mechanical boring technology does not allow.
c, It is particularly advantageous if the melt used as the boring medium contains magnetic metals, such as iron, N cobalt, or nickel, and/or completely consists of these metalsor Iertal alloys. Various non-magnetic metal melts, such as copper, can also be used in the process according to the invention, however, iron melt, for example, particularly suggests itself in this case, because the costs of this type of melt are low, iron is readily available, and it has a high vaporization point of approximately 3000 °C at atmospheric pressure.
The use of a magnetic melt results, as will be explained later, in the possibility of electromagnetically manipulating and/or controlling the entire boring device.
Because, even at atmospheric pressure, an overheated iron melt at approximately 3000 °C can be worked with in the fusion drilling process, the highest material demands are placed on the pipeline elements through which the iron melt is supplied to the base of the borehole.
In general, it is proposed that greatly varying boring devices for the production of fusion drilling borings in rock, with which the rock to be removed can be melted and by means of which a borehole lining made of solidified melt can be produced through the melt arising in the melting process and/or the melt supplied into the borehole, be advantageously implemented in such a way that the surfaces of the boring device in contact with the molten or -7solidified melt mass consist of a material resistant to high temperatures.
The boring devices may be not only the device according to Sthe invention, but all fusion drilling devices, as they are 00 00 known, for example, from US 3,357,505, and, in particular, SDE 2,554,101.
F It should be noted here that the concept of melt should be C understood to include not only the pure rock melt arising in typical processes, but also the melt supplied to the borehole according to the process according to the invention described here and/or the mixture of both of these melts which occurs.
Correspondingly, the pipeline elements, which are used to perform the process according to the invention, are preferably implemented in such a way that the surfaces in contact with the molten or solidified melt mass consist of a material resistant to high temperatures.
In a particularly advantageous embodiment, the pipeline elements for performing the process according to the invention are manufactured completely from the preferred material, because in this way composite construction and excessive complexity of the individual components are avoided.
In order to prevent adhesion between the solidified melt and the elements of boring devices, and particularly the pipeline elements of the boring device according to the invention, the material is to be selected so that, for example, its frictional coefficient is smaller than 0.5 and the material has a low surface tension, in order to ensure that no wetting occurs between the material and the melt.
-8- Graphite or metal composite ceramics are, for example, suitable as the material selected.
Graphite can meet all of the required demands as a material O for the boring device and particularly for the pipeline elements. Thus, graphite is, for example, a good heat and Scurrent conductor parallel to its lamination, but acts as 00 00 an insulator perpendicular to its lamination. Graphite can Stherefore be used both for thermal insulation of the metal melt and for current conduction. Furthermore, it has a high strength and slides easily, can be worked like metal, and can be preformed and shaped in its raw state with dimensjpnal accuracy.
Furthermore, a particular advantage of graphite is that it is not moistened by metal or the rock melts, as desired, and is temperature resistant at normal pressure up to approximately 3000 'C in a non-oxidizing atmosphere. In addition, graphite is distinguished in that its strength also increases with increasing temperature, with the tensile strength and compressive strength, respectively, reaching their maximum of approximately 100 and 400 MPa, respectively, at approximately 2500 *C.
Because, however, graphite oxidizes in an oxygen atmosphere from approximately 400 0 C, i.e. burns, the boring process is preferably performed, or at least begun, under an inert gas atmosphere. The inert gas is preferably argon, which, due to its high density, does not leak away from the borehole on its own. As the boring progresses, the graphite elements are no longer under an oxygen atmosphere, so that the inert gas supply can be turned off.
The pipeline elements used for the process should essentially be understood to be individual cylindrical parts, particularly made of graphite, as mentioned, which have a central boring.
9 The individual cylindrical parts, in which the ratio of the external diameter to the internal diameter is large, particularly larger than 10 to 1, can be connected with one another so that a graphite pipeline can be made which, in the fusion drilling process according to the invention, assumes the functions of fusion drilling head, boring 00 device body, and supply and pressure lines.
OO
M It is also advantageous that, due to the metal content according to the invention, the melt can additionally be C heated by current, in order to ensure that the melt reaches the base of the borehole in a heated, fluid condition.
In this case, for example, an iron melt, as an electrically conductive fluid, can assume both the function of energy transport to the rock to be melted and the function of current conductor.
The current flow can here be closed at an uppermost pipeline element, i.e. at the beginning of the boring, through the metal melt guided in the pipeline elements, via the metal melt present at the base of the borehole, and back via the external solidified metallic borehole lining.
It is also possible to carry the current through the graphite pipeline down to the melt over the base of the borehole.
The current for heating of the metal melt can hereby be coupled directly or inductively into the melt.
As the depth of the bore progresses, it is provided that further pipeline elements, for example, further graphite cylinders, can be attached to each preceding element.
This results, in the final effect, in a pipeline made of graphite pipe which extends through the entire depth of the P OPERDWIM254 5(W) 11) A p ,0 sp I 4m .2,1512NXI' bore. Due to the lower density of graphite relative to the metal melt, the graphite pipeline initially floats on the melt and slides toward the depths while supplying metal melt I and removing the base of the bore. Then an equilibrium 00 5 results between the pressure necessary for compressing the 00 melt and the pressure obtaining in the melt due to the Ci weight of the upright graphite pipe and the melt column.
The thickness of the melt cushion under the graphite pipeline is hereby approximately 10 cm. The boring speed is approximately 5 mm per second, whereby it should be noted that the boring according to the invention is performed without changing the boring head, without cooling, and without conveyance of waste.
Changing the boring head is unnecessary in any case because the pipeline elements consisting of graphite can be mechanically identical, so that a possible burning away of the lowest element is not disadvantageous. However, care should be taken here that each lowest pipeline element subject to possibly being burned away does not have any electrical elements surrounding the burning zone whose consumption could lead to destruction or malfunction.
Due to the unusual material properties of graphite, no obstructive adhesion occurs between the solidified cast metal borehole lining and the outer side of the pipeline elements consisting of graphite, so that the graphite pipeline can actually slide into the depths essentially without friction losses and is just as easy to lift out later.
This results due to the low surface tension relative to the melt and the low friction coefficients of graphite, which even become smaller with increasing temperature.
11 It is further advantageous if the individual pipeline o elements have controllable magnetic devices in their particularly thickly implemented walls, through which the h pipeline elements can be guided and/or supported like a magnetic glider in the solidified metallic borehole lining, which preferably consists of iron.
00 00 S In order to ensure that the individual electromagnets can c- be controlled from outside the borehole, the individual pipeline elements have internal control lines and contact points which correspond to one another, via which the magnetic devices can be supplied with control signals over the entire pipeline.
Through this embodiment, it is possible to realize a traveling magnetic field between the metallic borehole lining and the magnetic devices mentioned, so that the graphite pipeline can be moved up and down like a magnetic glider in the borehole through appropriate control of the magnetic devices. In particular, this makes it possible to influence the pressure ratios at the base of the borehole and to, in turn, lift the graphite pipeline at the end of the boring procedure.
Thus, in combination with the magnetic borehole lining, tensile, retention, or pressure forces can be exercised on the pipeline elements through electronic control. The weight of the pipeline elements acting in the depths is therefore able to be manipulated, so that the thickness of the melt cushion on which the pipeline elements float is also adjustable.
The later lifting can be made even easier if the completed borehole is flooded for support, particularly with pressurized water, with, in the case of intended fluid mining or energy mining, the lower production region of this type of borehole remaining unlined, and the borehole 1 12- C wall, which is glassed over with molten rock, broken up O under the delivery pressure of the water and the fluid or high temperature geothermal water released.
In a further embodiment, it is additionally provided that Sfurther controllable magnetic devices, which act as valves 00 for the metal melt to be supplied, are inserted within the 00 wall of the pipeline elements, so that the flow of the C metal melt within the pipeline elements can be influenced.
C Through this installation of the valves (magnetic valves) according to the invention, it is possible that a portion of the-entire metal melt strand standing on the base of the borehole is carried in each pipeline element by closing the magnetic valves, so that the increasing weight of the metal melt strand can be distributed onto several support points, which results in the individual pipeline elements of the graphite pipeline being held in place with the support/guide magnets in the cast-iron lining of the borehole.
It is thus possible to vary the weight of the metal melt column. Thus for example, a predefined amount of metal melt can be supplied to the base of the borehole through the targeted opening of the magnetic valves, or, through simultaneous opening of all magnetic valves, the entire weight of the metal melt strand can have a pulsed action upon the base of the borehole. At a depth of 10,000 m, the pressure of the iron melt column is hereby already over 7,000 bar.
Through pulsed control of the valves, a vibration can be generated in the melt over the base of the borehole, which produces a suction effect, thereby freeing the base of the borehole from molten rock and thus increasing the progress of boring.
13 C- The magnetic devices according to the invention for the O implementation of support/guide magnets and/or magnetic valves or other control devices, whose effects are based on magnetic forces, can, for example, also consist of conducting graphite coils inserted in insulating graphite.
It is also conceivable that the devices be formed from In 00 metal melts flowing in coil-shaped graphite channels. In 00 this case, the channels can be implemented in the pipeline C- elements consisting of graphite.
C In order to start the fusion drilling process according to the invention, it is advantageous if the fusion drilling procedure begins in a pre-bore, filled with inert gas, which is lined with a metal pipe anchored at the surface, particularly in a reinforced concrete cover. This steellined pre-bore should have a depth of approximately 30 to meters, with at least the bottom meter remaining free from the metal piping.
Furthermore, it is necessary to provide power units, a metal melting facility with filling machines, and a device for attachment of the individual pipeline elements to one another at the boring surface. Further devices, such as oversized boring towers or hydraulic pressure and lifting facilities, are not necessary for the boring process according to the invention.
Care should be taken that the reinforced concrete cover is designed appropriately thickly and surrounds a large area around the borehole, so that the melt is prevented from breaking through to the surface during the start of the metal melt boring process and during the beginning of the compression of the rock melt, and possibly parts of the metal melt, into the surrounding rock.
Because cracks are typically already present in the rock, a pressure of only a few multiples of 10 bar is necessary to 14 C- further widen the cracks which are present and to allow O compression. This means that the depth of approximately to 50 meters mentioned for a conventional pre-bore is sufficient to start the metal melt process according to the invention.
In 00 At the beginning of the boring, the first pipeline element 00 oO is sunk into the metal-lined pre-bore, which is done by C means of a manipulator device and/or with the aid of guide/support magnets located in the elements. After C- appropriate assembly of several pipeline elements, which advance up to just before the base of the borehole, the metal -melt is poured into the inside of the pipeline until the metal melt rises, between the pipeline elements inserted into the borehole and the inner wall of the conventional pre-bore, up to the edge of the metal pipe lining. There, it bonds with the pipe through welding. The diameter of the graphite pipeline is hereby to be dimensioned in such a way that the outer side of the pipeline element and the inner side of the metal pipe lie tightly against one another in their heated condition, in order to prevent the fluid metal melt from penetrating.
In this way, a pressure seal is formed, so that the fusion drilling process can be started. In addition, the current loop for supplementary heating of the metal melt is closed through the connection between the metal melt strand and/or.
the graphite pipeline and the metal pipe inserted in the pre-bore.
To optimize the removal of rock from the base of the borehole, it is advantageous if the lowermost pipeline element, which acts as a boring head, has at least one magnetic pump/nozzle arrangement, by means of which the metal melt can be shot onto the base of the borehole in the form of at least one melt stream.
15 Through the further induction coils provided, which can be O formed by the flowing metal melt itself (appropriate coilshaped flow channels in the boring head), it is possible to overheat the melt stream in such a way that a stream at an extraordinarily high temperature of several thousand degrees or a plasma stream results, with which In oO extraordinary boring progress can be achieved.
00 c This overheated melt and/or plasma stream generates a local overheating as it penetrates into the melt, particularly in the central region, so that the rock removal is optimized there.
Through the implementation of at least one melt stream, which can preferably be directed by means of a magnetic coil arrangement provided in the lowermost pipeline element, the possibility also exists of counteracting uneven rock removal at the base of the borehole, which can result due to the different types of rock or anisotropy in the rock. For this purpose, the melt stream is directed onto the points in the base of the borehole where the removal is slowest.
One can make an image of the irregular removal of rock in the base of the borehole by sending electrical impulses via, for example, the melt column and/or the graphite pipeline down to the base of the borehole and measuring the runtime of the impulses reflected from there. A topographical image of the base of the borehole can be produced and evaluated via the surface of the melt column/graphite pipeline and the runtime of the impulses, and control of the melt stream can be achieved.
Depending on the alignment of the melt stream, increased rock removal advantageously occurs in the region around the stream, so that the base of the borehole becomes coneshaped in the direction-of the stream, whereby the overall 16 working surface for the hot metallic melt is increased and O a larger overall removal rate can be realized.
The magnetic arrangements mentioned here can be controlled through control lines integrated in the pipeline elements, with the other notable advantage being that the magnetic In 00 arrangements operate without wear.
00 C- In order to ensure free movability of the metal melt stream below the magnetic coil arrangement integrated in the lowermost pipeline element (boring head), it is practical to implement a funnel-shaped recess in the boring head, particu-larly a centrally located one, within which the melt stream can be pivoted up to, for example, 60 degrees in all directions relative to the metal melt column.
The boring process can also be advantageously optimized by setting the melt over the base of the borehole in rotation, so that the rock melt, which is lighter than the metal melt, is conveyed upward and, due to centrifugal force, outward, and pressed into the cracks.
The rotation of the melt can hereby be effected through the magnetic arrangement, which also deflects the melt streams.
The rotational axis of the melt is hereby given by the melt stream, so that the rotational axis of the melt is also adjustable.
It is advantageous if control elements, which cause a rotation of the melts and/or an alignment of the streams, are provided at least in the lowermost pipeline element, distributed over the entire length of the element, but preferably in several of the lower pipeline elements, acting on the melt in an identical way. In this case, burning away of the pipeline elements is not harmful and does not affect the control of the melt (streams).
17 O Thus, for example, for the placement of a 10 km deep O boring, a lower region of identical pipeline elements of a length of over 100 meters can be used, so that even if O large amounts are burned away at the end of the deep boring, the boring head still forms a controllable pipeline element 00 00 0 As a simple embodiment, the control elements can be at least three current conductors in contact with the melt, which are inserted in the pipeline elements. Through O control of these conductors with polyphase current, rotation of the melts can be achieved. Through different current strengths on the phases, the rotational axis of the rotating melts can be pivoted, particularly around up to approximately 600.
It is also possible to form the control elements through graphite coils or melts flowing in channels, as mentioned earlier.
Parts of the metal melt which are also compressed can be reclaimed because these parts of the melt can also be heated by the current flow, whereby the poftions of melt remain fluid and again sink in the direction of the base of the borehole due to gravity.
Reclamation of the parts of the metal melt from the cracks in the rock is additionally promoted in that an attractive force can be exercised on the compressed parts of the metal melt through the magnets located in the pipeline elements.
The implementation of a pure metal lining of the borehole is thereby promoted due to the influence of the magnetic attractive forces.
Through the influence of these attractive forces it is also possible to purposely produce a borehole without a lining.
P \OPERDOHI I2l4 $5l, 10 A pr Spa Ioc-) 2/0/2(X)7 -18- For this purpose, the magnetic devices producing the attractive force are switched off during the boring process, so that the lighter rock melt always floats on the metal 00 melt and solidifies without being pushed away by the 00 0-0 5 attractive force.
Correspondingly, a lining made of pure rock is implemented CI in this way.
Brief description of the Drawings The invention is described, by way of non-limiting example only, with reference to the drawing which is a crosssectional view of a schematic exemplary embodiment of the invention.
Detailed Description A pre-bore with the placement and anchoring underground of a thick-walled metal pipe made of, for example, steel secures the start of the metal melt boring process without additional cooling.
A pipeline made of several pipeline elements which completely consist of graphite, is first assembled element by element from the individual pipeline elements via a hydraulic automatic (manipulator), with the boring head element (18) first.
(For reasons of viewability, surface devices such as the manipulator, the metal melting facility with filling device, and power units with power connections are not depicted in P \OPER125II 451)(2 WAP ApDS I doc .210SI/2(Xl7 c- 18athe schematic drawing).
As soon as the graphite pipeline slides, with its V' elements into the metal pipe of the pre-bore filled 00 00 5 with inert gas, the guiding and support magnets take C- over the further propulsion of the graphite pipeline (1) When the end of the pre-bore lining is reached and the Cq boring head element (18) lies a handsbreadth from the base of the borehole, the metal melt boring process can begin through pouring in, for example, iron melt and can continuously proceed up to the boring target, while the 19 S iron melt (10) can be supplied discontinuously due to the O melt reservoir in the metal melt strand so that in the Smeantime the lengthening of the graphite pipeline can be performed element by element by the manipulator at the surface.
In 00 Through activation of at least one magnetic pump and 00 one magnetic nozzle a defined amount of the already C overheated iron melt of the metal melt strand is compressed, further overheated, and pressed at high S pressure through the magnetic nozzle by magnetic force, and shot as a melt or plasma stream onto the base of the boreho-.e with, due to the rapid sequence of the process, a pulsed stream (17) arising, whereby the melting and removal effect is strengthened even more.
In order to ensure uniform removal at the base of the borehole, the iron melt stream is rotated by at least three rotary magnets like a cone (14) in the function of a "fluid roller bit" around the axis of the melt stream with the cone able to be pivoted through magnetic force within an angle of approximately 60 degrees in all directions Because the melt stream automatically follows every pivot, uniform removal of the rock in front of the boring head element (18) of the graphite pipeline is ensured.
The control of the metal melt cone (14) is performed from the surface via control lines provided in the pipeline elements.
The iron melt and the rock melt released fill the available space around the boring head element (18) of the graphite pipeline while the pressure in the melt increases. A part of the iron melt is concentrated by the support magnets around the graphite pipeline above the boring head element (18) in a desired thickness, such as, P %OPER'\DikI 25451.,: )i A p I7 spal doc. 210,) ,.,7I for example, that of the metal pipe of the pre-bore, and formed into a uniform cast-iron lining (11) in the continuously progressing fusion drilling process.
00 00 5 Conditioned by the density of the iron melts, the lighter r.
M, rock melts rise upward and are pressed into the surrounding rock (12) due to the rock splitting under the pressure of Cl the pumped-in melts and/or under the pressure of the graphite pipeline as it moves forward. Iron melt which is also pressed in is subject to heating by means of current flow and, due to gravity, flows back into the lower-lying melt zone around the melt cone (14) as the graphite pipeline moves forward.
The speed of progression of boring increases as the temperature and the relative pressure in the melt stream increase relative to the surrounding melt and its pulsed sequence (suction effect), as well as with the rotational speed of the melt stream and/or the rotational speed of the rotating melt.
As the boring depth increases, the intrinsic weight of the graphite pipeline including the metal melt strand, also increases, until its weight and the pressure necessary for compression of the melt in the melt zone are in equilibrium and the graphite pipeline glides as if on a melt cushion.
The magnetic valves installed in each graphite pipeline element, which each support a part of the metal melt strand, P \OPER\DH 12 545 j 10 A p, (P pa I do ,l)5/2(XI) -21work to maintain this condition, so that the increasing weight of the metal melt strand is distributed onto many support points as the depth increases. The same applies for ttn the support magnets in the outer region of the graphite 00 00 5 pipeline.
c, If a sufficient weight has built up in the metal melt strand this hydraulic pressure, in combination with the magnetic pump and magnetic nozzle can be used to form the melt stream (15) by simultaneously opening all the magnetic valves and releasing a small, concrete amount of iron melt in a pulsed fashion. At 10,000 metres, the pressure of the iron melt column is already over 7000 bar if all magnetic valves open simultaneously.
After pumping out the metal melt strand and reaching the boring target, the graphite pipeline is slid back out with the aid of the support and guide magnets and the graphite pipeline is disassembled element by element. For this purpose, the borehole can be flooded with pressurized water for support.
The reference in this specification to any prior publication (or information derived from it), or to any matter which is known, is not, and should not be taken as an acknowledgment or admission or any form of suggestion that that prior publication (or information derived from it) or known matter forms part of the common general knowledge in the field of endeavour to which this specification relates.
P 'OPER\I)F 2I .154li) Apr (17 spJl do.2)5/2i(w7i -22- Throughout this specification and the claims which follow, unless the context requires otherwise, the word "comprise", and variations such as "comprises" and "comprising", will be I understood to imply the inclusion of a stated integer or 00 00 5 step or group of integers or steps but not the exclusion of
C'-
C any other integer or step or group of integers or steps.
Oq Ot

Claims (22)

  1. 2. The process according to claim 1 wherein the metal melt coming out of the lowermost pipeline element over the base of the borehole is guided between the outer side of the pipeline element and the inner wall of the borehole and solidifies there.
  2. 3. The process according to claim 2 wherein the solidified melt forms a pressure seal.
  3. 4. The process according to claim 1 wherein the metal melt is heated by an electric current. P )OPER\3H\12S45 ,lI 11] Ap (07 ,pIl Ioc. 2 I)'ll2 -24- The process according to claim 4 wherein the electric current is passed through the melt in the pipeline and the V) solidified borehole lining. 00 00 Mj 6. The process according to claim 1 wherein a loss of metal melt occurring due to pressing solidification is compensated by the addition of melt at the beginning of the borehole.
  4. 7. The process according to claim 1 wherein the fusion drilling process begins in a pre-bore which is lined with a metal pipe anchored at a ground surface in a reinforced concrete cover.
  5. 8. The process according to claim 7 wherein the fusion drilling process is begun under an inert gas atmosphere.
  6. 9. The process according to claim 7 wherein the pipeline elements are lowered into the metal pipe down to shortly above the base of the borehole. The process according to claim 9 wherein the lowering of the pipeline elements is performed by means of a manipulator device and with the aid of guide/support magnets located in the elements.
  7. 11. The process according to claim 10 wherein magnetic devices located in the pipeline elements are controlled for lifting of the pipeline elements. P %OPER\D' I154 5(W) VII) InI spa I do.2A) 5/2(9)7
  8. 12. The process according to claim 11 wherein to simplify lifting of the pipeline elements, the borehole is flooded V) with pressurized water. 00 00 r- M13. The process according to claim 1 wherein the lowermost O pipeline element has at least one magnetic pump/nozzle arrangement, by means of which the metal melt can be shot, in the form of at least one melt/plasma stream, onto the base of the borehole.
  9. 14. The process according to claim 13 wherein at least the lowermost pipeline element has at least one control arrangement, by which the melt/plasma stream can be aligned and by means of which the metal melt located over the base of the bore can be set in motion. The process according to claim 1 wherein the melt stream is further heated by means of an induction coil arrangement and forms a plasma stream.
  10. 16. An apparatus for fusion drilling of a borehole in rock, comprising: a pipeline comprised of a plurality of pipeline elements extendable element by element into a borehole in rock; means for feeding a molten metal as a boring medium through said pipeline to emerge from a lowest element of said pipeline, to melt away the rock at a base of said borehole and to produce a waste melt comprised of the molten P %OPERDH\1I 54S6 I' I SP I d -2AlS '2(W -26- metal and molten rock, rock surrounding said borehole cracking by effects of temperature and pressure of the feeding of the molten metal into said borehole, said waste V) melt being pressed into cracked rock surrounding said 00 00 5 borehole; and r- Mc, a lining for said borehole formed in situ from solidification of the waste melt around said borehole.
  11. 17. The apparatus according to claim 16 wherein surfaces of the pipeline elements in contact with the molten or solidified melt consist of a material resistant to high temperatures.
  12. 18. The apparatus according to claim 16 wherein the pipeline elements consist completely of a material resistant to high temperatures.
  13. 19. The apparatus according to claim 18 wherein the material has a low friction coefficient smaller than and a low surface tension. The apparatus according to claim 19 wherein the material is graphite or a metal composite ceramic.
  14. 21. The apparatus according to claim 16 wherein each said pipeline element corresponds to a cylindrical piece with a central bore.
  15. 22. The apparatus according to claim 21 wherein the ratio of the external diameter to the internal diameter of the P \OPER\,Dt 25 404) I) Ap Spa d7 p Aoc2OS/2X} c1 -27- pipeline element is larger than 10:1.
  16. 23. The apparatus according to claim 16 wherein 00 controllable magnetic devices, which are usable as support 00 00 5 and guide magnets in combination with the metallic borehole C-- Cq lining, are located in the wall of a pipeline element. CI 24. The apparatus according to claim 16 wherein magnetic devices which are usable as valves for the melt to be guided are located in the wall of a pipeline element. The apparatus according to claim 16, characterized in that the lowermost pipeline element forms a boring head and has a funnel-shaped recess.
  17. 26. The apparatus according to claim 18 wherein at least the lowermost pipeline element has at leas tone magnetic arrangement which forms a pump for conveyance of the melt and for producing at least one directable melt stream.
  18. 27. The apparatus according to claim 16 wherein control elements are provided, at least in the lowermost pipeline element, through which the melt can be set in rotation, can be pivoted and can be directed.
  19. 28. The apparatus according to claim 27 wherein the control elements consist of at least three current conductors in contact with the melt. P OPERIIA IaIZMO4 1 33) Apt I)7 sp I doc.2/)5l2(X)7 -28-
  20. 29. A boring device for the production of fusion drilling 0' borings of large-diameter in rock with which rock to be removed is meltable and by means of which a borehole lining IV made of solidified melt can be produced from the melt 00 00 5 occurring in the melt process and fed into the borehole, r- M wherein surfaces of the boring device in contact with the molten or solidified melt mass consist of graphite. A process for fusion drilling, substantially as described with reference to the drawings and/or examples.
  21. 31. An apparatus for fusion drilling, substantially as described with reference to the drawings and/or examples.
  22. 32. A boring device, substantially as described with reference to the drawings and/or examples.
AU2004237885A 1999-03-05 2004-12-09 Metal melt boring process Ceased AU2004237885B2 (en)

Priority Applications (1)

Application Number Priority Date Filing Date Title
AU2004237885A AU2004237885B2 (en) 1999-03-05 2004-12-09 Metal melt boring process

Applications Claiming Priority (3)

Application Number Priority Date Filing Date Title
DE19909836 1999-03-05
AU26709/00A AU2670900A (en) 1999-03-05 2000-02-09 Moulten bath drilling method
AU2004237885A AU2004237885B2 (en) 1999-03-05 2004-12-09 Metal melt boring process

Related Parent Applications (1)

Application Number Title Priority Date Filing Date
AU26709/00A Division AU2670900A (en) 1999-03-05 2000-02-09 Moulten bath drilling method

Publications (2)

Publication Number Publication Date
AU2004237885A1 AU2004237885A1 (en) 2005-01-13
AU2004237885B2 true AU2004237885B2 (en) 2007-07-12

Family

ID=34382434

Family Applications (1)

Application Number Title Priority Date Filing Date
AU2004237885A Ceased AU2004237885B2 (en) 1999-03-05 2004-12-09 Metal melt boring process

Country Status (1)

Country Link
AU (1) AU2004237885B2 (en)

Also Published As

Publication number Publication date
AU2004237885A1 (en) 2005-01-13

Similar Documents

Publication Publication Date Title
US6591920B1 (en) Moulten bath drilling method
US20110220409A1 (en) Method and device for fusion drilling
CA2674393C (en) Casting of tungsten carbide matrix bit heads and heating bit head portions with microwave radiation
US20210164295A1 (en) Metal Matrix Compositions and Methods for Manufacturing Same
US20200047253A1 (en) Methods Of Fabricating Ceramic Or Intermetallic Parts
CN1179605C (en) High efficiency induction melting system
US5168940A (en) Profile melting-drill process and device
EP1242711B1 (en) Drilling bit for drilling while running casing
CN103611602B (en) A kind of hammer mill three metal quartering hammers and preparation method thereof
AU2004237885B2 (en) Metal melt boring process
US9993869B2 (en) Directional solidification of polycrystalline diamond compact (PDC) drill bits
JP2023539504A (en) Cooling for geothermal well drilling
CN116856898B (en) In-situ oil gas development system for oil-rich coal
CN108914028A (en) A kind of Al alloy composite of high-strength and high ductility and preparation method thereof
CN106164389A (en) It is associated with the heat insulation sealing cover of rigidity heat-barrier material
FI74114C (en) Method and assemblies for performing wire bolting
GB2364529A (en) Methods of high temperature infiltration of drill bits and infiltrating binder
CN105765154B (en) Cutting element for drill bit supports hoof part
RU2804095C1 (en) Method of drilling wells in continental ice
RU2191895C1 (en) Method of increasing oil recovery from formation
CN115210445A (en) Drilling tool with prefabricated parts
PL154762B1 (en) Method of and apparatus for manufacturing a bore-hole broadener

Legal Events

Date Code Title Description
FGA Letters patent sealed or granted (standard patent)
MK14 Patent ceased section 143(a) (annual fees not paid) or expired