WO2021059427A1 - Procurement assistance method and procurement assistance system - Google Patents

Procurement assistance method and procurement assistance system Download PDF

Info

Publication number
WO2021059427A1
WO2021059427A1 PCT/JP2019/037810 JP2019037810W WO2021059427A1 WO 2021059427 A1 WO2021059427 A1 WO 2021059427A1 JP 2019037810 W JP2019037810 W JP 2019037810W WO 2021059427 A1 WO2021059427 A1 WO 2021059427A1
Authority
WO
WIPO (PCT)
Prior art keywords
procurement
parts
start date
date
support system
Prior art date
Application number
PCT/JP2019/037810
Other languages
French (fr)
Japanese (ja)
Inventor
和行 高土
明達 原田
弘晃 土井
Original Assignee
株式会社日立製作所
Priority date (The priority date is an assumption and is not a legal conclusion. Google has not performed a legal analysis and makes no representation as to the accuracy of the date listed.)
Filing date
Publication date
Application filed by 株式会社日立製作所 filed Critical 株式会社日立製作所
Priority to PCT/JP2019/037810 priority Critical patent/WO2021059427A1/en
Publication of WO2021059427A1 publication Critical patent/WO2021059427A1/en

Links

Images

Classifications

    • GPHYSICS
    • G05CONTROLLING; REGULATING
    • G05BCONTROL OR REGULATING SYSTEMS IN GENERAL; FUNCTIONAL ELEMENTS OF SUCH SYSTEMS; MONITORING OR TESTING ARRANGEMENTS FOR SUCH SYSTEMS OR ELEMENTS
    • G05B19/00Programme-control systems
    • G05B19/02Programme-control systems electric
    • G05B19/418Total factory control, i.e. centrally controlling a plurality of machines, e.g. direct or distributed numerical control [DNC], flexible manufacturing systems [FMS], integrated manufacturing systems [IMS] or computer integrated manufacturing [CIM]
    • GPHYSICS
    • G06COMPUTING; CALCULATING OR COUNTING
    • G06QINFORMATION AND COMMUNICATION TECHNOLOGY [ICT] SPECIALLY ADAPTED FOR ADMINISTRATIVE, COMMERCIAL, FINANCIAL, MANAGERIAL OR SUPERVISORY PURPOSES; SYSTEMS OR METHODS SPECIALLY ADAPTED FOR ADMINISTRATIVE, COMMERCIAL, FINANCIAL, MANAGERIAL OR SUPERVISORY PURPOSES, NOT OTHERWISE PROVIDED FOR
    • G06Q50/00Information and communication technology [ICT] specially adapted for implementation of business processes of specific business sectors, e.g. utilities or tourism
    • G06Q50/04Manufacturing
    • YGENERAL TAGGING OF NEW TECHNOLOGICAL DEVELOPMENTS; GENERAL TAGGING OF CROSS-SECTIONAL TECHNOLOGIES SPANNING OVER SEVERAL SECTIONS OF THE IPC; TECHNICAL SUBJECTS COVERED BY FORMER USPC CROSS-REFERENCE ART COLLECTIONS [XRACs] AND DIGESTS
    • Y02TECHNOLOGIES OR APPLICATIONS FOR MITIGATION OR ADAPTATION AGAINST CLIMATE CHANGE
    • Y02PCLIMATE CHANGE MITIGATION TECHNOLOGIES IN THE PRODUCTION OR PROCESSING OF GOODS
    • Y02P90/00Enabling technologies with a potential contribution to greenhouse gas [GHG] emissions mitigation
    • Y02P90/02Total factory control, e.g. smart factories, flexible manufacturing systems [FMS] or integrated manufacturing systems [IMS]
    • YGENERAL TAGGING OF NEW TECHNOLOGICAL DEVELOPMENTS; GENERAL TAGGING OF CROSS-SECTIONAL TECHNOLOGIES SPANNING OVER SEVERAL SECTIONS OF THE IPC; TECHNICAL SUBJECTS COVERED BY FORMER USPC CROSS-REFERENCE ART COLLECTIONS [XRACs] AND DIGESTS
    • Y02TECHNOLOGIES OR APPLICATIONS FOR MITIGATION OR ADAPTATION AGAINST CLIMATE CHANGE
    • Y02PCLIMATE CHANGE MITIGATION TECHNOLOGIES IN THE PRODUCTION OR PROCESSING OF GOODS
    • Y02P90/00Enabling technologies with a potential contribution to greenhouse gas [GHG] emissions mitigation
    • Y02P90/30Computing systems specially adapted for manufacturing

Definitions

  • the present invention relates to a procurement support method and a procurement support system.
  • Procurement operations in the manufacturing industry are roughly divided into procurement processes such as ordering requests and orders, and the period (buffer) for performing work in the operations is determined in order from the one for which the procurement instruction for parts is issued in each process. Work between. However, in many cases, it is not possible to prioritize the procurement lead time (hereinafter abbreviated as "LT") and the work start date, so the manufacturing work that actually uses the parts is started. Parts may not be delivered on a daily basis (delayed) or may be delivered early (early).
  • Patent Document 1 discloses a design development / procurement instruction management system for the purpose of reducing development delays caused by material procurement delays from the design / development progress management stage.
  • This design development / procurement instruction management system is based on the procurement lead time acquired from the parts list that stores the item composition of the product in the work progress information acquired from the work division configuration table that stores the progress status of the work group.
  • Procurement instruction required date addition means to add procurement instruction required date to, and work division configuration recreating means to recreate the work division configuration table based on the work group progress information correction file created by the procurement instruction required date addition means. It has a procurement instruction management means for presenting a member requiring a procurement instruction based on the recreated work division configuration.
  • the present invention has been made in view of the above problems, and is a procurement support capable of managing parts to be delivered without delay or prematurely on the production start date, which is an overall index in a procurement business having a plurality of procurement processes.
  • the purpose is to provide methods and procurement support systems.
  • the procurement support method executed by the procurement support system is the production of at least one manufacturing process that manufactures the product based on the production plan of the product consisting of a plurality of parts.
  • the start date is determined, the procurement work of each part is divided into a plurality of procurement processes, and the deadline for process completion in each procurement process is set based on the production start date.
  • FIG. 8A It is a flowchart explaining an example of the delivery waiting task priority determination process by the procurement support system which concerns on embodiment, and is the flowchart which shows the continuation process of FIG. 8A. It is a flowchart explaining an example of the follow-up task priority determination process by the procurement support system which concerns on Example. It is a flowchart explaining an example of the follow-up task priority determination process by the procurement support system which concerns on Example, and is the flowchart which shows the continuation process of FIG. 9A. It is a flowchart explaining an example of the state determination process of the follow-up by the procurement support system which concerns on Example. It is a flowchart explaining an example of ordering task priority determination processing by the procurement support system which concerns on Example.
  • FIG. 13A It is a flowchart explaining an example of order request task priority determination processing by the procurement support system which concerns on Example. It is a figure which shows the work sequence diagram of the follow-up by the procurement support system which concerns on Example. It is a figure which shows the business sequence diagram of the follow-up by the procurement support system which concerns on Example, and is the figure which shows the continuation sequence of FIG. 13A. It is a figure which shows the outline of the priority determination period in the procurement support system which concerns on Example. It is a figure which shows the outline of the judgment of the risk level in the procurement support system which concerns on Example. It is a figure which shows the outline of the determination of the delivery status in the procurement support system which concerns on Example.
  • the procurement support method and procurement support system of this embodiment have the following configuration as an example.
  • the procurement work is divided into a plurality of procurement processes, a date that is a different individual index is set for each process, and finally the overall index of whether the delivery is in time for the start of the manufacturing work is satisfied.
  • the purpose was to support. Furthermore, based on the date of the individual index, the time required for each procurement process was deducted, and this period was considered as a buffer.
  • Patent Document 1 is a procurement instruction management system for design and development, but this embodiment is a procurement support system for the manufacturing industry, and is fully prepared for each work phase as an element necessary for the manufacturing industry. We also considered the concept that it should be a kit.
  • the work phase (manufacturing process) of the product is taken into consideration, and the procurement process called follow-up is performed with the aim of arranging the parts with the full kit on the manufacturing work start date of the work phase.
  • the procurement process called follow-up is performed with the aim of arranging the parts with the full kit on the manufacturing work start date of the work phase.
  • xxx data may be used as an example of information, but the data structure of the information may be any. That is, the "xxx data” can be referred to as a “xxx table” to show that the information does not depend on the data structure. Further, “xxx data” may be simply referred to as "xxx”. Then, in the following description, the configuration of each information is an example, and the information may be divided and held, or may be combined and held.
  • -Procurement work A series of work to procure parts and materials necessary for manufacturing-Procurement process: A unit that makes it easy to manage the procurement work in the procurement work. Order request, ordering, follow-up, waiting for delivery, etc.
  • -Manufacturing process A unit that makes it easy to manage a series of manufacturing operations-Full kit: A state in which the necessary parts for the work phase are delivered without missing the required quantity.
  • ⁇ Work phase A unit that collectively represents the manufacturing process and work location of a certain product
  • Procurement LT The time required for a certain part to be delivered to the specified location after requesting procurement from a supplier (purchase contract). Buffer: The period for performing work in a certain business.
  • the length of the buffer varies depending on the business.
  • Follow-up: The name of the procurement process that confirms the status of the procured items with the supplier in the procurement operation.
  • Risk Level An index that indicates the degree of influence of the delivery date contracted (contracted) with the supplier on the production plan for a certain part.
  • Delivery Status An index showing the delivery status of a part from the supplier, the presence or absence of delivery, and the degree of influence on the production plan when the part is not delivered.
  • BOM Bill of Materials. There are various BOMs such as design BOM, manufacturing BOM, service BOM, etc., and the type of BOM handled may differ depending on the company.
  • -Express delivery Procurement items arrive from the supplier, and after acceptance inspection, they are immediately delivered to the work site without being placed in the warehouse.
  • -Overall index In this embodiment, the work start date (production start date) in each work phase. Since the parts are available in a full kit on the work start date, they are also set to prevent parts from arriving well earlier than the work start date.
  • -Individual index In this embodiment, the schedule determined for each procurement process (order request, order, follow-up, waiting for delivery). Specific examples of individual indicators will be described later. It is set to complete the required tasks by each work deadline, and to prevent work from being performed sufficiently earlier than the work deadline.
  • FIGS. 1 and 2 the hardware configuration and functional block configuration of the procurement support system of the embodiment will be described, and the processing of the procurement support method executed by the procurement support system will be described in FIGS. 3 and later.
  • FIG. 1 is a diagram showing a schematic configuration of a procurement support system according to an embodiment.
  • the procurement support system S has a procurement support device 1 and a core system 2, and these procurement support devices 1 and the core system 2 are communicably connected by a network 3.
  • the procurement support device 1 is a device capable of various information processing, for example, an information processing device such as a computer.
  • the information processing device has an arithmetic element, a storage medium, and a communication interface, and further has an input device such as a mouse and a keyboard, and a display device such as a display.
  • the arithmetic element is, for example, a CPU (Central Processing Unit), an FPGA (Field-Programmable Gate Array), or the like.
  • the storage medium includes, for example, a magnetic storage medium such as an HDD (Hard Disk Drive), a semiconductor storage medium such as a RAM (Random Access Memory), a ROM (Read Only Memory), and an SSD (Solid State Drive). Further, a combination of an optical disk such as a DVD (Digital Versatile Disk) and an optical disk drive is also used as a storage medium. In addition, a known storage medium such as a magnetic tape medium is also used as the storage medium.
  • Programs such as firmware are stored in the storage medium.
  • a program such as firmware is read from this storage medium and executed to perform overall control of the procurement support device 1.
  • the storage medium stores data and the like required for each process of the procurement support device 1.
  • the core system 2 is also a device capable of various information processing, for example, an information processing device such as a computer.
  • the procurement support device 1 and the core system 2 of this embodiment may each be configured by a so-called cloud in which the information processing device is configured to be able to communicate via a communication network. Further, although it is shown as a single core system 2 in FIG. 1, there may be a plurality of core systems 2.
  • the network 3 enables mutual communication between the procurement support device 1 and the core system 2.
  • various well-known networks can be adopted based on the location and environment in which the procurement support device 1 and the core system 2 are installed.
  • the procurement support device 1 and the core system 2 may be connected by a LAN (Local Area Network), or may be connected by a WAN (Wide Area Network) represented by the Internet or a mobile communication network.
  • the network 3 may be either a wired / wireless network, or a wired / wireless network may be partially adopted.
  • FIG. 2 is a functional block diagram showing a schematic configuration of the procurement support system S according to the embodiment.
  • the procurement support device 1 has a control unit 10, a storage unit 14, a display unit 15, and a communication unit 16.
  • the control unit 10 controls the entire procurement support device 1.
  • the control unit 10 has a production start date determination unit 11, a process deadline setting unit 12, and a priority calculation unit 13.
  • the production start date determination unit 11 determines the production start date of at least one manufacturing process for manufacturing the product, based on the production plan of the product composed of a plurality of parts. As described above, since the production start date is the overall index in this embodiment, it can be said that the production start date determination unit 11 determines the overall index.
  • the production start date determination unit 11 determines the production start date for each part.
  • the production start date determination unit 11 determines the production start date based on the parts list of parts for each manufacturing process and the procurement lead time of parts.
  • the procurement process has at least an order request process, an ordering process, and a delivery waiting process, and further has a follow-up process set prior to the delivery waiting process.
  • the process deadline setting unit 12 divides the procurement work of each part into a plurality of procurement processes, and sets the deadline for process completion in each procurement process based on the production start date, which is an overall index. In this embodiment, as will be described later, since it is the deadline for completing the process in each procurement process, it can be said that the process deadline setting unit 12 sets an individual index.
  • the process deadline setting unit 12 sets the deadline for process completion of the follow-up process based on the delivery date set in the ordering process.
  • the deadline for completing the follow-up process is also an individual index in this embodiment.
  • the priority calculation unit 13 calculates the priority of the procurement process related to the process completion deadline based on the process completion deadline and the current date, which are individual indicators.
  • the priority is an index indicating the context of the process completion deadline and the current date, and the magnitude of the period from the process completion deadline to the current date. The details of the priority will be described later.
  • the priority calculation unit 13 calculates the priority of the manufacturing process related to the production start date based on the production start date and the current date, which are the overall indicators.
  • the storage unit 14 temporarily or permanently stores programs and data.
  • a program such as firmware and data required for the operation of the procurement support device 1 are stored in the storage unit 14.
  • the display unit 15 visually displays the control progress and result of the control unit 10, data stored in the storage unit 14, and the like based on instructions from the control unit 10. Further, the display unit 15 displays the priority of the manufacturing process calculated by the priority calculation unit 13 for each part. Preferably, the display unit 15 displays the priorities of different manufacturing processes in different colors.
  • the communication unit 16 transmits the data transmitted from the control unit 10 to the core system 2 via the network 3, and also receives the data transmitted from the core system 2 via the network 3. To do.
  • the core system 2 has a storage unit 20 and a communication unit 21.
  • the storage unit 20 stores various data necessary for the operation of the entire procurement support system S. Details of the data stored in the storage unit 20 will be described later.
  • the communication unit 21 transmits data to the procurement support device 1 via the network 3 and receives the data transmitted from the procurement support device 1 in the same manner as the communication unit 16 of the procurement support device 1.
  • FIG. 3 is a diagram for explaining an example of an outline of the procurement support system according to the embodiment.
  • the procurement person P is also the operator of the procurement support device 1 that constitutes the procurement support system S.
  • the procurement person P operates the input unit (not shown in FIGS. 1 and 2) of the procurement support device 1 and causes the display unit 15 to display the display screens D1 and D2 as shown in FIG.
  • X, Y, and Z are products constituting the final product X. Therefore, XY indicates a project for producing the product Y constituting the final product X.
  • the priority of each project is displayed for each project.
  • the priority is displayed by hatching or the like in the present embodiment, but since the display unit 15 can actually display in color, different priorities are different as shown in the legend of FIG. It is displayed in color.
  • Procurement person P selects and specifies the project (business) he / she is in charge of from the projects displayed on the display screen D1 by the input unit.
  • the procurement person P selects the project XX.
  • the procurement support system S displays the display screen D2 for the project XX.
  • a table is displayed in which the manufacturing processes Work1 to Work5 constituting the project XX are arranged in columns and the work place Assembury1 ... Are arranged in rows. Then, in the cells constituting this table, the priority for the work phase specified by the manufacturing process and the work place is displayed.
  • the procurement person P looks at the display screen D2 and confirms whether the ordered procured items (parts) will be a full kit at the required timing for each work phase in the selected project. This is because if even one part is not prepared (missing) at the required timing in the work phase, work delay or work rework will occur, so the procured items are prepared for each work phase of each product (project). Because it needs to be.
  • the procurement person P confirms the priority for each work phase in each project. Then, the procurement work is managed so that the priority of the work phase preferably stays at High Priority (so that it does not become Past Due Date).
  • FIG. 4 is a diagram for explaining another example of the outline of the procurement support system according to the embodiment.
  • the current date will be described as June 1.
  • the procurement person P selects a specific work phase (in the example shown in FIG. 4, the manufacturing process is Work4 and the work place is Assembury1) by the input unit on the display screen D2 shown in FIG.
  • a specific work phase in the example shown in FIG. 4, the manufacturing process is Work4 and the work place is Assembury1
  • the procurement support system S causes the display unit 15 to display the display screen D3 as shown in FIG.
  • the delivery date, follow-up status, new delivery date, production start date, and Risk Level are displayed for each part (procured item) that constitutes the selected work phase.
  • the priority of each part is also displayed. Details of follow-up and Risk Level will be described later.
  • Procurement person P first looks at the display screen D2 in FIG. 3 and identifies the work phase that should be prioritized.
  • the priority of the work phase in which the manufacturing process is Work4 and the work place is Assembury1 is Past Due Date (see FIG. 3). Therefore, it is determined that this work phase should be prioritized and selected by the input unit.
  • the details are displayed on the display screen D3.
  • the procurement person P looks at the display screen D3 and confirms the priority of the parts that are not complete (not yet delivered).
  • the procurement product Part 1 has not yet been delivered even after the production start date, and since the supplier has already been requested to change the delivery date, the procurement person P does not take any action at this time.
  • the procured product Part 2 has a high priority, and the new delivery date exceeds the production start date. In this way, if the delivery date of the procured item is delayed, the influence of the work plan in the work phase is confirmed as Risk Level, and if the influence is large (for example, Risk Level is Critical), the supplier SP and delivery (mainly delivery date). Can negotiate (about the day) (follow-up).
  • the procurement person P can follow the supplier SP to see if the delivery is performed as scheduled for the high-priority procurement work by checking the display screen D3. Then, the procurement department including the procurement person P can grasp whether the delivery is possible or delayed from the supplier SP as scheduled before the delivery schedule.
  • the procurement person P can grasp whether each part can be delivered as scheduled before the delivery date by checking the display screen D3, and thereby the parts are scheduled for each work phase. It is possible to check for each part whether or not they are aligned.
  • FIG. 5 is a diagram for explaining another example of the outline of the procurement support system according to the embodiment.
  • the procurement person P confirms the Risk Level after the delivery date is changed, and confirms whether or not the work plan of the work phase is affected.
  • the procurement manager P notifies the material manager M that the delivery of the procured product Part 3 is delayed, and in some cases, the procured product Part 3 is delivered to the workplace as soon as it arrives.
  • the person in charge of procurement P tells the person in charge of production planning that it is necessary to change the work in the corresponding work phase, the work start date, and the person in charge of production planning delivers the procured product Part 2 to the work place as soon as it is delivered to the material manager M. Notify PP and field manager FM.
  • the procurement person P can grasp that the delivery delay occurs for each part before the delivery date by checking the display screen D4, and notifies the persons concerned according to the influence on the work plan for each work phase. can do.
  • FIG. 6A is a diagram showing an example of the bill of materials (BOM) data 100 according to the embodiment.
  • the bill of materials data 100 has a factory ID 101, a BOM ID 102, a work phase 103, a parts ID 104, and a required quantity 105.
  • Factory ID 101 is the ID of the factory where the parts are used.
  • BOM ID 102 is an ID for each bill of materials.
  • the work phase 103 is the ID of the work phase 103 in which the component is used.
  • the part ID 104 is the ID of the part.
  • the required quantity 105 is the required quantity of the parts specified by the part ID 104 in the work phase specified by the work phase 103.
  • FIG. 6B is a diagram showing an example of the procurement LT data 110 according to the embodiment.
  • the procurement LT data 110 has a factory ID 111, a BOM ID 112, a part ID 113, a supplier ID 114, and a procurement LT 115. In the following description, the description of the items already described will be omitted.
  • Supplier ID 114 is the supplier's ID.
  • the procurement LT 115 is the number of days of the procurement LT of the parts specified by the part ID 113 and the supplier ID 114.
  • FIG. 6C is a diagram showing an example of the parts inventory data 120 according to the embodiment.
  • the parts inventory data 120 has a factory ID 121, a project ID 122, a BOM ID 123, a parts ID 124, and an inventory quantity 125.
  • Project ID 122 is the project ID.
  • the inventory quantity 125 is a numerical value indicating the inventory quantity of parts for each project, which is specified by the BOM ID123 and the part ID124.
  • FIG. 6D is a diagram showing an example of the order request data 130 according to the embodiment.
  • the order request data 130 has a factory ID 131, a project ID 132, an order request ID 133, a part ID 134, a supplier ID 135, an order request quantity 136, a delivery request date 137, and an order request completion flag 138.
  • the order request ID 133 is the ID of the order request made by the order requester.
  • the order request quantity 136 is a value indicating the quantity of the parts for which the order request is made in the order request specified by the order request ID 133.
  • the delivery request date 137 is a date indicating the delivery request date instructed to the supplier specified by the supplier ID 135 in the order request specified by the order request ID 133.
  • the order request completion flag 138 is a flag indicating whether or not the order requester has completed the work of the order request specified by the order request ID 133, and if it is a true value (TRUE), it indicates the completion of the order request.
  • FIG. 6E is a diagram showing an example of order data 140 according to the embodiment.
  • the order data 140 has a factory ID 141, a project ID 142, an order ID 143, a part ID 144, a supplier ID 145, a delivery date 146, an order quantity 147, a delivered quantity 148, and an order completion flag 149.
  • Ordering ID 143 is an ordering ID placed by the ordering party.
  • the delivery date 146 is a date indicating the delivery date indicated to the supplier in the order specified by the order ID 143.
  • the order quantity 147 is a value indicating the quantity of parts to be ordered from the supplier in the order specified by the order ID 143.
  • the delivered quantity 148 is a value indicating the quantity of the delivered parts among the parts related to the order specified by the order ID 143 on the current date.
  • the order completion flag 149 is a flag indicating whether or not the orderer has completed the ordering work specified by the order ID 143, and if it is a true value (TRUE), it indicates the order completion.
  • FIG. 6F is a diagram showing an example of work phase list data 150 according to the embodiment.
  • the work phase list data 150 has a factory ID 151, a project ID 152, a BOM ID 153, an organization 154, and a work phase 155.
  • Knitting 154 is a numerical value for specifying each product when manufacturing a plurality of the same products.
  • the work phase 155 is an ID indicating the work phase.
  • FIG. 6G is a diagram showing an example of the overall index list data 160 according to the embodiment.
  • the overall index list data 160 has a factory ID 161, a project ID 162, a BOM ID 163, an organization 164, a work phase 165, a work phase production start date 166, a part ID 167, a required quantity 168, and a procurement LT169.
  • the work phase production start date 166 is a date indicating the production start date of the work phase specified by the work phase 165.
  • FIG. 6H is a diagram showing an example of the component availability list data 170 according to the embodiment.
  • the parts available list data 170 has a factory ID 171, a project ID 172, a BOM ID 173, a parts ID 174, an inventory quantity 175, an order ID 176, a delivery date 177, an order quantity 178, a delivered quantity 179, and an available quantity 180.
  • the available quantity 180 is the sum of the inventory quantity 175 and the delivered quantity 179.
  • FIG. 6I is a diagram showing an example of the order target list data 190 according to the embodiment.
  • the order target list data 190 includes factory ID 191 and project ID 192, BOM ID 193, organization 194, work phase 195, work phase production start date 196, order request ID 197, order ID 198, part ID 199, supplier ID 200, procurement LT201, and order request quantity 202. , Delivery request date 203, delivery date 204, order quantity 205, delivered quantity 206, and order completion flag 207.
  • FIG. 6J is a diagram showing an example of the order request target list data 210 according to the embodiment.
  • the order request target list data 210 includes factory ID 211, project ID 212, BOM ID 213, organization 214, work phase 215, work phase production start date 216, part ID 217, procurement LT218, inventory quantity 219, required quantity 220, order required quantity 221 and. It has an order request completion flag 222.
  • the required order quantity 221 is a numerical value obtained by subtracting the inventory quantity 219 from the required quantity 220.
  • FIG. 6K is a diagram showing an example of the production planning data 220 according to the embodiment.
  • the production plan data 220 has a factory ID 221 and a project ID 222, a BOM ID 223, an organization 224, a work phase 225, and a work phase production start date 226.
  • FIG. 7 is a flowchart showing an example of each task priority determination process by the procurement support system S according to the embodiment. The flow of the entire procurement support method by the procurement support system S of this embodiment will be described with reference to the flowchart of FIG. 7.
  • the procurement support device 1 obtains the production start date of the work phase as an overall index mainly based on the production plan data 220, the bill of materials data 100, and the procurement LT data 110 by the production start date determination unit 11 (step S300). ).
  • the procurement support device 1 mainly uses the process deadline setting unit 12 to obtain the delivery waiting deadline date as an individual index based on the production start date of the work phase, which is an overall index.
  • the procurement support device 1 mainly calculates the priority of each task by the priority calculation unit 13 based on the delivery waiting deadline date obtained by the process deadline setting unit 12 (step S301).
  • the procurement support device 1 mainly uses the process deadline setting unit 12 to obtain the follow-up deadline date as an individual index based on the production start date of the work phase, which is an overall index. Next, the procurement support device 1 mainly calculates the priority of each task by the priority calculation unit 13 based on the follow-up deadline date obtained by the process deadline setting unit 12 (step S302).
  • the procurement support device 1 mainly uses the process deadline setting unit 12 to obtain the order deadline date as an individual index based on the production start date of the work phase, which is an overall index. Next, the procurement support device 1 mainly calculates the priority of each task by the priority calculation unit 13 based on the order deadline date obtained by the process deadline setting unit 12 (step S303).
  • the procurement support device 1 mainly uses the process deadline setting unit 12 to obtain the order request deadline date as an individual index based on the production start date of the work phase, which is an overall index.
  • the procurement support device 1 mainly calculates the priority of each task by the priority calculation unit 13 based on the order request deadline date obtained by the process deadline setting unit 12 (step S304).
  • FIGS. 8A and 8B are flowcharts for explaining an example of the delivery waiting task priority determination process by the procurement support system according to the embodiment, and are flowcharts corresponding to steps S300 and S301 of FIG.
  • the procurement support device 1 mainly creates work phase list data 150 based on the production plan data 220 and the bill of materials data 100 by the production start date determination unit 11 (step S400).
  • the procurement support device 1 mainly has the production start date determination unit 11, and the overall index list data 160 having the production start date of the work phase for each part based on the production plan, the parts list data 100, and the procurement LT data 110. Is created (step S401).
  • the procurement support device 1 mainly acquires the parts inventory data 120 and the order request data 130 by the production start date determination unit 11, and the parts availability list based on the inventory quantity, the delivered quantity, and the order quantity of each part.
  • Data 170 is created (step S402).
  • the procurement support device 1 repeatedly assigns the work phase of the parts described below and determines the priority for 160 minutes of the overall index list data (step S403).
  • the procurement support device 1 mainly allocates the available quantity 180 of the same parts of the parts available list data 170 to the required quantity 168 of the parts of the overall index list data 160 by the process deadline setting unit 12 (step). S404).
  • the procurement support device 1 mainly determines the magnitude relationship between the required quantity 168 of the parts of the overall index list data 160 and the available quantity 180 of the parts available list data 170 by the process deadline setting unit 12 (step S405). ). Then, when it is determined that the required quantity of parts of the overall index list data 160 is 168 or more than the available quantity of 180 of the parts available list data 170, the flow proceeds to step S406, and the required quantity of parts of the overall index list data 160 is determined. If it is determined that 168 is less than the available quantity 180 of the component available list data 170, the flow proceeds to step S407.
  • step S406 the procurement support device 1 mainly substitutes the values as shown in the figure for the required quantity 168 of the parts of the overall index list data 160 and the available quantity 180 of the parts available list data 170 by the process deadline setting unit 12. To do. Then, the satisfaction flag is set to True.
  • step S407 the procurement support device 1 mainly uses the process deadline setting unit 12 to set the required quantity 168 of the parts of the overall index list data 160 and the available quantity 180 of the parts available list data 170 as shown in the figure. Substitute. Then, the satisfaction flag is set to False.
  • the procurement support device 1 mainly uses the priority calculation unit 13 to calculate the delivery waiting start date, the delivery waiting deadline date, the red determination date, and the yellow determination date of each part (step S408). Further, the procurement support device 1 mainly obtains the Delivery Status of each component by the priority calculation unit 13 (step S409).
  • step S410 the repetition from step S403 is completed.
  • the procurement support device 1 mainly uses the priority calculation unit 13 to repeatedly determine the priority for each work phase for the organization within the work phase and the work phase (step S411).
  • the procurement support device 1 mainly determines the presence / absence of the corresponding work phase component in the overall index list data 160 for which the priority has been calculated by the priority calculation unit 13 (step S412). Then, if it is determined that there is no corresponding work phase component in the overall index list data 160, the flow shifts to step S417, and if it is determined that there is a corresponding work phase component in the overall index list data 160, the flow changes. The process proceeds to step S413.
  • the procurement support device 1 mainly determines whether or not the satisfaction flag is True for all the parts by the priority calculation unit 13 (step S413). Then, when it is determined that the sufficiency flag is True for all the parts, the flow proceeds to step S418, and when it is determined that the sufficiency flag is False for at least one component, the flow shifts to step S414.
  • the procurement support device 1 determines the presence or absence of expired parts mainly by the priority calculation unit 13 (step S414). Then, if it is determined that there are expired parts, the flow proceeds to step S419, and if it is determined that there are no expired parts, the flow proceeds to step S415.
  • the procurement support device 1 mainly determines the presence / absence of a part having a red priority by the priority calculation unit 13 (step S415). Then, if it is determined that there is a component having a red priority, the flow shifts to step S420, and if it is determined that there is no component having a red priority, the flow shifts to step S416.
  • the procurement support device 1 mainly determines the presence / absence of a part having a yellow priority by the priority calculation unit 13 (step S416). Then, if it is determined that there is a component having a yellow priority, the flow shifts to step S421, and if it is determined that there is no component having a yellow priority, the flow shifts to step S422.
  • step S417 the priority of the corresponding work phase is set to none (white).
  • step S4108 the priority of the corresponding work phase is set to complete (light blue).
  • step S419 the priority of the corresponding work phase is set to expired (black).
  • step S420 the priority of the corresponding work phase is set to red.
  • step S421 the priority of the corresponding work phase is set to yellow. Then, in step S422, the priority of the corresponding work phase is set to green.
  • step S423 the repetition from step S411 is completed.
  • FIGS. 9A and 9B are flowcharts for explaining an example of the follow-up task priority determination process by the procurement support system according to the embodiment, and are flowcharts corresponding to step S302 in FIG.
  • steps S500 to S507 in FIG. 9A are the same processes as steps S400 to S407 in FIG. 8A, description thereof will be omitted.
  • the procurement support device 1 mainly calculates the follow-up start date, follow-up deadline date, red determination date, and yellow determination date of each part by the priority calculation unit 13 (step S508). Further, the procurement support device 1 obtains the Risk Level of each component mainly by the priority calculation unit 13 (step S509).
  • steps S510 to S523 of FIGS. 9A and 9B are the same processes as steps S410 to S423 of FIGS. 8A and 8B, the description thereof will be omitted.
  • FIG. 10 is a flowchart illustrating an example of the follow-up state determination process by the procurement support system according to the embodiment, and is a flowchart corresponding to step S302 of FIG. 7.
  • the procurement support device 1 acquires parts ordering information mainly by the priority calculation unit 13 based on the information input by the procurement person P or the like via the input unit (step S600).
  • the procurement support device 1 confirms and determines the state of the follow-up status input to the procurement support system S by the supplier mainly by the priority calculation unit 13 (step S601).
  • the "follow-up status" is one of "confirmation without change of delivery date, no follow-up required, confirmation with change of delivery date, confirmation with request for change of delivery date, confirmation without request for change of delivery date".
  • the flow shifts to step S602 and if it is determined that the follow-up status is confirmed with changing delivery date, the flow shifts to step S603 and follows. If it is determined that the up status is confirming that there is a delivery date change request, the flow proceeds to step S604, and if it is determined that the follow-up status is confirming that there is no delivery date change, the flow proceeds to step S605.
  • step S602 the follow-up completion flag is set to True. After that, the flow shifts to step S608. In step S603, the follow-up completion flag is set to True, and the new delivery date is acquired. After that, the flow shifts to step S606. In step S603, the follow-up completion flag is set to False, and the new delivery date is acquired. After that, the flow shifts to step S606. In step S606, the follow-up completion flag is set to False. After that, the flow shifts to step S608.
  • the procurement support device 1 mainly updates the Risk Level of each part by the priority calculation unit 13 (step S606), updates the changed delivery date and the Risk Level of the parts order information (step S607), and updates the risk level of the parts.
  • the completion flag in the order information is updated (step S608).
  • FIG. 11 is a flowchart illustrating an example of the ordering task priority determination process by the procurement support system according to the embodiment, and is a flowchart corresponding to step S303 of FIG. 7.
  • step S700 in FIG. 11 is the same process as step S400 in FIG. 8A, the description thereof will be omitted.
  • the procurement support device 1 mainly uses the priority calculation unit 13 to collate the order request data 130, the order data 140, and the overall index list data 160 to create the order target list data 190 for the parts that need to be ordered. (Step S701).
  • the procurement support device 1 mainly uses the priority calculation unit 13 to repeatedly determine the priority of the task for 190 minutes of the order target list data (step S702).
  • the procurement support device 1 mainly uses the priority calculation unit 13 to obtain the order deadline date, the red determination date, and the yellow determination date of each part (step S703).
  • the procurement support device 1 mainly determines the state of the order completion flag 207 of the order target list data 190 by the priority calculation unit 13 (step S704). Then, if it is determined that the order completion flag 207 is True, the flow proceeds to step S708, and if it is determined that the order completion flag 207 is False or Null (undecided), the flow proceeds to step S705.
  • the procurement support device 1 mainly determines whether or not the order deadline date obtained in step S703 is today by the priority calculation unit 13 (step S705). Then, if it is determined that the order deadline date is today, the flow shifts to step S709, and if it is determined that the order deadline date is not today, the flow shifts to step S706.
  • the procurement support device 1 mainly determines whether or not the red determination date obtained in step S703 is today by the priority calculation unit 13 (step S706). Then, if it is determined that the red determination date is today, the flow proceeds to step S710, and if it is determined that the red determination date is not today, the flow proceeds to step S706.
  • the procurement support device 1 mainly determines whether or not the yellow determination date obtained in step S703 is today by the priority calculation unit 13 (step S706). Then, if it is determined that the yellow determination date is today, the flow proceeds to step S711, and if it is determined that the yellow determination date is not today, the flow proceeds to step S712.
  • step S708 it is determined that the color code is light blue, in step S709 it is determined that the color code is black, in step S710 it is determined that the color code is red, and in step S711 it is determined that the color code is yellow. Then, in step S712, it is determined that the color code is green.
  • step S713 the repetition from step S702 is completed.
  • FIG. 12 is a flowchart illustrating an example of the order request task priority determination process by the procurement support system according to the embodiment, and is a flowchart corresponding to step S304 of FIG. 7.
  • step S800 in FIG. 12 is the same process as step S400 in FIG. 8A, the description thereof will be omitted.
  • the procurement support device 1 mainly acquires the parts inventory data 120 and the order request data 130 by the priority calculation unit 13, collates these with the overall index list data 160, and orders the parts for which the order request is required.
  • Request target list data 210 is created (step S801).
  • the procurement support device 1 mainly uses the priority calculation unit 13 to repeatedly determine the priority of the task for 210 minutes of the order request target list data (step S802).
  • the procurement support device 1 mainly uses the priority calculation unit 13 to obtain an order request deadline date, a red determination date, and a yellow determination date for each part (step S803).
  • the procurement support device 1 mainly determines the state of the order request completion flag 222 of the order request target list data 210 by the priority calculation unit 13 (step S804). Then, if it is determined that the order request completion flag 222 is True, the flow proceeds to step S808, and if it is determined that the order request completion flag 222 is False or Null (undecided), the flow proceeds to step S805.
  • the procurement support device 1 mainly determines whether or not the order request deadline date obtained in step S803 is today by the priority calculation unit 13 (step S805). Then, if it is determined that the order request deadline date is today, the flow shifts to step S809, and if it is determined that the order request deadline date is not today, the flow shifts to step S806.
  • steps S806 to S813 in FIG. 12 are the same processes as steps S706 to S713 in FIG. 11, and thus description thereof will be omitted.
  • FIGS. 13A and 13B are diagrams showing a follow-up work sequence diagram by the procurement support system according to the embodiment.
  • the follow-up sequence shown in FIGS. 13A and 13B includes contents that overlap with the contents already described, but is intended to show a sequence that includes not only the procurement support system S but also operations such as operators of the procurement support system S. I will explain here.
  • the procurement support device 1 performs follow-up priority determination processing (step S900).
  • the follow-up priority determination process performed by the procurement support device 1 has already been described with reference to FIGS. 9A and 9B, and thus the description thereof will be omitted here.
  • the procurement person P instructs the procurement support device 1 to confirm the priority of the follow-up task (step S902), and the procurement support device 1 displays the follow-up in units of work phases accordingly (step S902).
  • Step S903 The procurement person P visually recognizes the display unit 15 of the procurement support device 1 and selects a work phase to be preferentially processed via the input unit (step S904).
  • the procurement person P instructs the procurement support device 1 to confirm the follow-up priority of the parts unit (step S905), and the procurement support device 1 displays the follow-up priority of the parts unit accordingly. (Step S906).
  • the procurement person P selects a task to be processed via the input unit while looking at the display unit 15 of the procurement support device 1 (step S907). After that, the procurement person P confirms with the supplier whether or not the delivery date has been changed (step S908), and the supplier replies whether or not the delivery date has been changed (step S909).
  • the procurement person P registers the follow-up status in the core system 2 (step S910).
  • the procurement support device 1 appropriately accesses the core system 2, refers to the follow-up status (step S911), and captures the follow-up status information (step S912).
  • the procurement support device 1 performs a follow-up state determination process (step S913). Since the follow-up state determination process performed by the procurement support device 1 has already been described with reference to FIG. 10, the description here will be omitted.
  • the procurement manager P requests the production control department to reschedule the production plan (step S914), and the production control department notifies the new production plan accordingly. Then (step S915), the new production plan is registered in the core system 2.
  • the procurement manager P informs the material management department that the parts need to be shipped immediately after they are received (step S916).
  • FIG. 14 is a diagram showing an outline of a priority determination period in the procurement support system S according to the embodiment.
  • Each procurement process of order request, ordering, follow-up, and waiting for delivery has a priority determination period as shown in the figure. It should be noted that the detailed period and the time at which the priority is changed are design matters, and the example shown in FIG. 14 is merely an example.
  • FIG. 15 is a diagram showing an outline of the determination of the risk level (Risk Level) in the procurement support system S according to the embodiment
  • FIG. 16 is an outline of the determination of the delivery status (Delivery Status) in the procurement support system S according to the embodiment. It is a figure which shows. It should be noted that the detailed period and the time at which the priority is changed are design matters, and the examples shown in FIGS. 15 and 16 are merely examples.
  • the production start date determination unit 11 determines the production start date of at least one manufacturing process in which the product is manufactured, based on the production plan of the product composed of a plurality of parts.
  • Procurement support that divides the procurement work of each part into a plurality of procurement processes, and the process deadline setting unit 12 sets the deadline for process completion in each procurement process based on the production start date determined by the production start date determination unit 11. Realize the method.
  • the data shown in FIGS. 6A to 6K are stored in the storage unit 20 of the core system 2, but each of these data is the procurement support device 1 and the core system constituting the procurement support system S. It may be stored in any of the storage units 14 and 20 of 2.
  • each of the above configurations, functions, processing units, processing means, etc. may be realized by hardware by designing a part or all of them by, for example, an integrated circuit.
  • the present invention can also be realized by a program code of software that realizes the functions of the examples.
  • a storage medium in which the program code is recorded is provided to the computer, and the processor included in the computer reads the program code stored in the storage medium.
  • the program code itself read from the storage medium realizes the functions of the above-described embodiment, and the program code itself and the storage medium storing the program code itself constitute the present invention.
  • Examples of the storage medium for supplying such a program code include a flexible disk, a CD-ROM, a DVD-ROM, a hard disk, an SSD (Solid State Drive), an optical disk, a magneto-optical disk, a CD-R, and a magnetic tape.
  • Non-volatile memory cards, ROMs, etc. are used.
  • program code that realizes the functions described in this embodiment can be implemented in a wide range of programs or script languages such as assembler, C / C ++, perl, Shell, PHP, and Java (registered trademark).
  • the program code of the software that realizes the functions of the examples via the network it is stored in a storage means such as a hard disk or memory of a computer or a storage medium such as a CD-RW or a CD-R.
  • the processor provided in the computer may read and execute the program code stored in the storage means or the storage medium.
  • control lines and information lines indicate those that are considered necessary for explanation, and do not necessarily indicate all the control lines and information lines in the product. All configurations may be interconnected.

Landscapes

  • Engineering & Computer Science (AREA)
  • Manufacturing & Machinery (AREA)
  • Business, Economics & Management (AREA)
  • General Physics & Mathematics (AREA)
  • Physics & Mathematics (AREA)
  • Tourism & Hospitality (AREA)
  • General Business, Economics & Management (AREA)
  • Marketing (AREA)
  • Primary Health Care (AREA)
  • Strategic Management (AREA)
  • General Health & Medical Sciences (AREA)
  • Economics (AREA)
  • Human Resources & Organizations (AREA)
  • Health & Medical Sciences (AREA)
  • Theoretical Computer Science (AREA)
  • General Engineering & Computer Science (AREA)
  • Quality & Reliability (AREA)
  • Automation & Control Theory (AREA)
  • General Factory Administration (AREA)
  • Management, Administration, Business Operations System, And Electronic Commerce (AREA)

Abstract

The present invention performs management in which components are delivered neither late nor prematurely on a production start date that is an overall indicator in procurement work including a plurality of procurement steps. In this procurement assistance method executed by a procurement assistance system S, a production start date determination unit 11 uses a production plan for a product comprising a plurality of components as a basis to determine a production start date for at least one production step for producing the product and divides procurement work for individual components into a plurality of procurement steps, and a step deadline setting unit 12 sets a step completion deadline in each procurement step on the basis of the production start date determined by the production start date determination unit 11.

Description

調達支援方法及び調達支援システムProcurement support method and procurement support system
 本発明は、調達支援方法及び調達支援システムに関する。 The present invention relates to a procurement support method and a procurement support system.
 製造業における調達業務には大きく分けて発注依頼、発注等の調達工程があり、各工程で部品の調達指示が出たものから順番に定められた、業務における作業を行うための期間(バッファ)の間で作業をする。しかし、多くの場合は調達リードタイム(以下、「LT」と省略する)や作業開始日を意識した優先度を付けての作業ができていないなどで、部品を実際に利用する製造作業の開始日に部品が納入されないことがあり(遅延)、あるいは早く納入されてしまう(過早)ことがある。 Procurement operations in the manufacturing industry are roughly divided into procurement processes such as ordering requests and orders, and the period (buffer) for performing work in the operations is determined in order from the one for which the procurement instruction for parts is issued in each process. Work between. However, in many cases, it is not possible to prioritize the procurement lead time (hereinafter abbreviated as "LT") and the work start date, so the manufacturing work that actually uses the parts is started. Parts may not be delivered on a daily basis (delayed) or may be delivered early (early).
 特許文献1には、設計開発の進捗管理段階から、部材調達遅延に起因する開発遅延を低減することを目的とした設計開発・調達指示管理システムが開示されている。この設計開発・調達指示管理システムは、作業群の進捗状況を格納している作業分割構成表から取得した作業進捗情報に製品の品目構成を格納している部品表から取得した調達リードタイムを基に調達指示必要日を追加する調達指示必要日追加手段と、調達指示必要日追加手段が作成した作業群別進捗情報修正ファイルを基に作業分割構成表を再作成する作業分割構成再作成手段と、再作成した作業分割構成を基に調達指示が必要な部材を提示する調達指示管理手段とを有する。 Patent Document 1 discloses a design development / procurement instruction management system for the purpose of reducing development delays caused by material procurement delays from the design / development progress management stage. This design development / procurement instruction management system is based on the procurement lead time acquired from the parts list that stores the item composition of the product in the work progress information acquired from the work division configuration table that stores the progress status of the work group. Procurement instruction required date addition means to add procurement instruction required date to, and work division configuration recreating means to recreate the work division configuration table based on the work group progress information correction file created by the procurement instruction required date addition means. It has a procurement instruction management means for presenting a member requiring a procurement instruction based on the recreated work division configuration.
特開2005-346319号公報Japanese Unexamined Patent Publication No. 2005-346319
 しかし、特許文献1に開示されたシステムでは、調達指示必要日を超えた部品のみが強調表示されるため、特定日に一斉に部品が必要になり、大量の作業が一気に表示されてしまう可能性がある。そのため、大量の部品調達が必要な製造業等に適用すると処理するタスクが多くなりすぎてしまうという問題があり、適用が難しい。また、調達には最低でも発注依頼と発注という複数の工程があるため、それ毎に期限を設定しなければ、各工程の遅延を低減できない。特に、複数の調達工程においてこの工程を管理する各部署が独自の(個別)指標をもって業務を行うため、各部署の個別指標を満たしても全体指標である生産開始日が満たされない可能性がある。 However, in the system disclosed in Patent Document 1, only the parts that exceed the procurement instruction required date are highlighted, so that the parts are required all at once on a specific day, and a large amount of work may be displayed at once. There is. Therefore, if it is applied to a manufacturing industry or the like that requires a large amount of parts procurement, there is a problem that the number of tasks to be processed becomes too large, and it is difficult to apply it. In addition, since procurement has at least a plurality of processes of ordering and ordering, delays in each process cannot be reduced unless a deadline is set for each process. In particular, in multiple procurement processes, each department that manages this process operates with its own (individual) index, so even if the individual index of each department is satisfied, the production start date, which is the overall index, may not be satisfied. ..
 さらに、ワークフェイズで必要な部品がその工程の作業開始時点ですべてそろう(フルキット)必要があるが、一部部品の遅延により製造作業が直前になり開始できないことが判明し、緊急的に製造計画を変更せざるを得ない事態が発生することがあり、事業へのインパクトが大きくなりがちである。 Furthermore, it is necessary to have all the necessary parts in the work phase at the start of work in the process (full kit), but it was found that the manufacturing work could not be started just before due to the delay of some parts, so it was urgently manufactured. There may be situations where the plan has to be changed, and the impact on the business tends to be large.
 本発明は上記の課題に鑑みてなされたもので、複数の調達工程を有する調達業務において全体指標である生産開始日に遅延も過早もせず部品を納入させる管理をすることが可能な調達支援方法及び調達支援システムを提供することにある。 The present invention has been made in view of the above problems, and is a procurement support capable of managing parts to be delivered without delay or prematurely on the production start date, which is an overall index in a procurement business having a plurality of procurement processes. The purpose is to provide methods and procurement support systems.
 上記課題を解決すべく、本発明の一つの観点に従う調達支援システムにより実行される調達支援方法は、複数の部品からなる製品の生産計画に基づいて、製品を製造する少なくとも一つの製造工程の生産開始日を決定し、各々の部品の調達業務を複数の調達工程に分割し、生産開始日に基づいて個々の調達工程における工程完了の期限を設定する。 In order to solve the above problems, the procurement support method executed by the procurement support system according to one viewpoint of the present invention is the production of at least one manufacturing process that manufactures the product based on the production plan of the product consisting of a plurality of parts. The start date is determined, the procurement work of each part is divided into a plurality of procurement processes, and the deadline for process completion in each procurement process is set based on the production start date.
 本発明によれば、大量の部品調達作業を一斉に表示することなく、調達工程に分けた表示をすることが可能な調達支援方法及び調達支援システムを実現することができる。 According to the present invention, it is possible to realize a procurement support method and a procurement support system capable of displaying a large amount of parts procurement work separately for each procurement process without displaying them all at once.
実施例に係る調達支援システムの概略構成を示す図である。It is a figure which shows the schematic structure of the procurement support system which concerns on Example. 実施例に係る調達支援システムの概略構成を示す機能ブロック図である。It is a functional block diagram which shows the schematic structure of the procurement support system which concerns on Example. 実施例に係る調達支援システムの概要の一例を説明するための図である。It is a figure for demonstrating an example of the outline of the procurement support system which concerns on Example. 実施例に係る調達支援システムの概要の他の例を説明するための図である。It is a figure for demonstrating another example of the outline of the procurement support system which concerns on Example. 実施例に係る調達支援システムの概要のまた他の例を説明するための図である。It is a figure for demonstrating another example of the outline of the procurement support system which concerns on Example. 実施例に係る部品表(BOM)データの一例を示す図である。It is a figure which shows an example of the bill of materials (BOM) data which concerns on Example. 実施例に係る調達LTデータの一例を示す図である。It is a figure which shows an example of the procurement LT data which concerns on Example. 実施例に係る部品在庫データの一例を示す図である。It is a figure which shows an example of the parts inventory data which concerns on Example. 実施例に係る発注依頼データの一例を示す図である。It is a figure which shows an example of order request data which concerns on Example. 実施例に係る発注データの一例を示す図である。It is a figure which shows an example of ordering data which concerns on Example. 実施例に係るワークフェイズリストデータの一例を示す図である。It is a figure which shows an example of the work phase list data which concerns on Example. 実施例に係る全体指標リストデータの一例を示す図である。It is a figure which shows an example of the whole index list data which concerns on Example. 実施例に係る部品利用可能リストデータの一例を示す図である。It is a figure which shows an example of the parts use list data which concerns on Example. 実施例に係る発注対象リストデータの一例を示す図である。It is a figure which shows an example of ordering target list data which concerns on Example. 実施例に係る発注依頼対象リストデータの一例を示す図である。It is a figure which shows an example of the order request target list data which concerns on Example. 実施例に係る生産計画データの一例を示す図である。It is a figure which shows an example of the production planning data which concerns on Example. 実施例に係る調達支援システムによる各タスク優先度判定処理の一例を示すフローチャートである。It is a flowchart which shows an example of each task priority determination process by the procurement support system which concerns on Example. 実施例に係る調達支援システムによる納品待ちタスク優先度判定処理の一例を説明するフローチャートである。It is a flowchart explaining an example of the delivery waiting task priority determination process by the procurement support system which concerns on Example. 実施例に係る調達支援システムによる納品待ちタスク優先度判定処理の一例を説明するフローチャートであり、図8Aの続きの処理を示すフローチャートである。It is a flowchart explaining an example of the delivery waiting task priority determination process by the procurement support system which concerns on embodiment, and is the flowchart which shows the continuation process of FIG. 8A. 実施例に係る調達支援システムによるフォローアップタスク優先度判定処理の一例を説明するフローチャートである。It is a flowchart explaining an example of the follow-up task priority determination process by the procurement support system which concerns on Example. 実施例に係る調達支援システムによるフォローアップタスク優先度判定処理の一例を説明するフローチャートであり、図9Aの続きの処理を示すフローチャートである。It is a flowchart explaining an example of the follow-up task priority determination process by the procurement support system which concerns on Example, and is the flowchart which shows the continuation process of FIG. 9A. 実施例に係る調達支援システムによるフォローアップの状態判定処理の一例を説明するフローチャートである。It is a flowchart explaining an example of the state determination process of the follow-up by the procurement support system which concerns on Example. 実施例に係る調達支援システムによる発注タスク優先度判定処理の一例を説明するフローチャートである。It is a flowchart explaining an example of ordering task priority determination processing by the procurement support system which concerns on Example. 実施例に係る調達支援システムによる発注依頼タスク優先度判定処理の一例を説明するフローチャートである。It is a flowchart explaining an example of order request task priority determination processing by the procurement support system which concerns on Example. 実施例に係る調達支援システムによるフォローアップの業務シーケンス図を示す図である。It is a figure which shows the work sequence diagram of the follow-up by the procurement support system which concerns on Example. 実施例に係る調達支援システムによるフォローアップの業務シーケンス図を示す図であり、図13Aの続きのシーケンスを示す図である。It is a figure which shows the business sequence diagram of the follow-up by the procurement support system which concerns on Example, and is the figure which shows the continuation sequence of FIG. 13A. 実施例に係る調達支援システムにおける優先度の判定期間の概略を示す図である。It is a figure which shows the outline of the priority determination period in the procurement support system which concerns on Example. 実施例に係る調達支援システムにおけるリスクレベルの判定の概略を示す図である。It is a figure which shows the outline of the judgment of the risk level in the procurement support system which concerns on Example. 実施例に係る調達支援システムにおけるデリバリーステータスの判定の概略を示す図である。It is a figure which shows the outline of the determination of the delivery status in the procurement support system which concerns on Example.
 以下、本発明の実施形態について、図面を参照して説明する。なお、以下に説明する実施形態は請求の範囲に係る発明を限定するものではなく、また実施形態の中で説明されている諸要素及びその組み合わせの全てが発明の解決手段に必須であるとは限らない。 Hereinafter, embodiments of the present invention will be described with reference to the drawings. It should be noted that the embodiments described below do not limit the invention according to the claims, and that all the elements and combinations thereof described in the embodiments are indispensable for the means for solving the invention. Not exclusively.
 本実施形態の調達支援方法及び調達支援システムは、一例として次のような構成を有する。 The procurement support method and procurement support system of this embodiment have the following configuration as an example.
 本実施形態では、調達業務を複数の調達工程に分けて捉え、それぞれの工程毎に異なる個別指標となる日付を設定し、最終的に納品が製造作業開始に間に合うかという全体指標を満たすことの支援を目的とした。さらに、個別指標の日付を基に、各調達工程の所要時間を差引この期間をバッファと考えた。 In the present embodiment, the procurement work is divided into a plurality of procurement processes, a date that is a different individual index is set for each process, and finally the overall index of whether the delivery is in time for the start of the manufacturing work is satisfied. The purpose was to support. Furthermore, based on the date of the individual index, the time required for each procurement process was deducted, and this period was considered as a buffer.
 すなわち、本実施例の調達支援システムは、各調達工程において、部品単位で優先度を持った個別指標を設け、それを遵守することで全体指標である製造作業開始日に遅延も過早もせず部品が納入されることをサポートするシステムである。 That is, in the procurement support system of this embodiment, individual indexes with priorities are set for each part in each procurement process, and by observing them, the manufacturing work start date, which is the overall index, is not delayed or premature. It is a system that supports the delivery of parts.
 以上の構成により、TOC(Theory of Constraints)のS-DBR(Simplified Drum Buffer Rope)の考え方を適用し、期限超過だけではなく、バッファの消費具合に合わせた作業の優先度を計算し、必要な作業から順次早すぎず遅すぎず作業ができるように強調表示を行っている。 With the above configuration, the concept of S-DBR (Simplified Drum Buffer Rope) of TOC (Theory of Constraints) is applied, and not only the deadline is exceeded, but also the priority of work according to the consumption of the buffer is calculated and required. Highlighting is done so that the work can be done sequentially from the work, not too early and not too late.
 これにより、大量の部品調達作業が一斉に表示されることなく、調達工程に分けた表示がされ、さらに優先度によって強調表示が異なることで、各調達工程の担当者が必要な作業に集中して調達業務を行うことができる。 As a result, a large amount of parts procurement work is not displayed all at once, but is displayed separately for the procurement process, and the highlighting differs depending on the priority, so that the person in charge of each procurement process concentrates on the necessary work. Can carry out procurement operations.
 また、上述した特許文献1に開示されたシステムは設計開発向け調達指示管理システムであるが、本実施例は製造業向けの調達支援システムであり、製造業に必要な要素としてワークフェイズ毎にフルキットであるべきという概念も考慮した。 Further, the system disclosed in Patent Document 1 described above is a procurement instruction management system for design and development, but this embodiment is a procurement support system for the manufacturing industry, and is fully prepared for each work phase as an element necessary for the manufacturing industry. We also considered the concept that it should be a kit.
 すなわち、本実施例の調達支援システムでは、製品のワークフェイズ(製造工程)を考慮し、そのワークフェイズの製造作業開始日にフルキットで部品がそろうことを目的とした、フォローアップという調達工程を提示する。これにより納入前にサプライヤーとコミュニケーションを取ることで納品の期限厳守の可能性を高めるとともに、遅延が発生しそうな場合は、それを事前に把握し、リスクレベルを計算するシステムを提供する。これにより、リスクレベルに応じて特急配達や生産計画変更を行い事業へのインパクトを最小限に収めることをサポートできる。 That is, in the procurement support system of this embodiment, the work phase (manufacturing process) of the product is taken into consideration, and the procurement process called follow-up is performed with the aim of arranging the parts with the full kit on the manufacturing work start date of the work phase. Present. By communicating with the supplier before delivery, we will increase the possibility of meeting the delivery deadline, and if a delay is likely to occur, we will provide a system to grasp it in advance and calculate the risk level. As a result, it is possible to support the minimization of the impact on the business by making express delivery or changing the production plan according to the risk level.
 なお、実施例を説明する図において、同一の機能を有する箇所には同一の符号を付し、その繰り返しの説明は省略する。 In the figure for explaining the embodiment, the same reference numerals are given to the parts having the same function, and the repeated description thereof will be omitted.
 また、以下の説明では、情報の一例として「xxxデータ」といった表現を用いる場合があるが、情報のデータ構造はどのようなものでもよい。すなわち、情報がデータ構造に依存しないことを示すために、「xxxデータ」を「xxxテーブル」と言うことができる。さらに、「xxxデータ」を単に「xxx」と言うこともある。そして、以下の説明において、各情報の構成は一例であり、情報を分割して保持したり、結合して保持したりしても良い。 Further, in the following description, an expression such as "xxx data" may be used as an example of information, but the data structure of the information may be any. That is, the "xxx data" can be referred to as a "xxx table" to show that the information does not depend on the data structure. Further, "xxx data" may be simply referred to as "xxx". Then, in the following description, the configuration of each information is an example, and the information may be divided and held, or may be combined and held.
 以下、本実施形態における用語の概要について説明する。
・調達業務:製造に必要な部品・材料を調達する一連の業務
・調達工程:調達業務における、調達作業を管理しやすい単位としたもの。発注依頼、発注、フォローアップ、納品待ちなど。
・製造工程:一連の製造作業を管理しやすい単位としたもの
・フルキット:ワークフェイズに必要な部品が必要数量欠けることなく納品されている状態。
・ワークフェイズ:ある製品の製造工程と作業場所をひとまとまりに表す単位
・調達LT:ある部品において、サプライヤーに調達を依頼(購入契約)してから所定の場所に納品されるまでに要する時間
・バッファ:ある業務における作業を行うための期間。業務によってバッファの長さは異なる。
・フォローアップ:調達業務においてサプライヤーに調達品の状況確認を行う調達工程の名称
・Risk Level:ある部品において、サプライヤーと契約する(契約した)納期が生産計画に対して与える影響度合いを示す指標
・Delivery Status:ある部品がサプライヤーからの納品状況、納品の有無及び納品されていない場合の生産計画に与える影響度合いを示す指標
・BOM:部品表(Bill of Materials)のこと。設計BOM・製造BOM・サービスBOMなど様々なBOMがあり、会社によって扱うBOMの種類が異なる場合がある。
・特急出庫:サプライヤーから調達品が届き、検収を行った後に倉庫へ置かずすぐに作業現場へ届けること
・全体指標:本実施形態では、各ワークフェイズにおける作業開始日(生産開始日)。作業開始日に部品がフルキットで揃っているため、加えて、部品が作業開始日よりも十分に早く到着することを防ぐために設定される。
・個別指標:本実施形態では、各調達工程(発注依頼、発注、フォローアップ、納品待ち)においてそれぞれ定められる日程。個別指標の具体例については後述する。必要なタスクを各作業期限までに終わらせるため、加えて、作業期限よりも十分に早く作業を行うことを防ぐために設定される。
Hereinafter, an outline of terms in the present embodiment will be described.
-Procurement work: A series of work to procure parts and materials necessary for manufacturing-Procurement process: A unit that makes it easy to manage the procurement work in the procurement work. Order request, ordering, follow-up, waiting for delivery, etc.
-Manufacturing process: A unit that makes it easy to manage a series of manufacturing operations-Full kit: A state in which the necessary parts for the work phase are delivered without missing the required quantity.
・ Work phase: A unit that collectively represents the manufacturing process and work location of a certain product ・ Procurement LT: The time required for a certain part to be delivered to the specified location after requesting procurement from a supplier (purchase contract). Buffer: The period for performing work in a certain business. The length of the buffer varies depending on the business.
・ Follow-up: The name of the procurement process that confirms the status of the procured items with the supplier in the procurement operation. ・ Risk Level: An index that indicates the degree of influence of the delivery date contracted (contracted) with the supplier on the production plan for a certain part. Delivery Status: An index showing the delivery status of a part from the supplier, the presence or absence of delivery, and the degree of influence on the production plan when the part is not delivered. BOM: Bill of Materials. There are various BOMs such as design BOM, manufacturing BOM, service BOM, etc., and the type of BOM handled may differ depending on the company.
-Express delivery: Procurement items arrive from the supplier, and after acceptance inspection, they are immediately delivered to the work site without being placed in the warehouse.-Overall index: In this embodiment, the work start date (production start date) in each work phase. Since the parts are available in a full kit on the work start date, they are also set to prevent parts from arriving well earlier than the work start date.
-Individual index: In this embodiment, the schedule determined for each procurement process (order request, order, follow-up, waiting for delivery). Specific examples of individual indicators will be described later. It is set to complete the required tasks by each work deadline, and to prevent work from being performed sufficiently earlier than the work deadline.
 まず、図1及び図2を参照し、実施例の調達支援システムのハードウェア構成及び機能ブロック構成を説明し、図3以降で調達支援システムが実行する調達支援方法の処理の説明をする。 First, with reference to FIGS. 1 and 2, the hardware configuration and functional block configuration of the procurement support system of the embodiment will be described, and the processing of the procurement support method executed by the procurement support system will be described in FIGS. 3 and later.
 図1は、実施例に係る調達支援システムの概略構成を示す図である。 FIG. 1 is a diagram showing a schematic configuration of a procurement support system according to an embodiment.
 本実施例に係る調達支援システムSは、調達支援装置1及び基幹システム2を有し、これら調達支援装置1及び基幹システム2はネットワーク3により通信可能に接続されている。 The procurement support system S according to this embodiment has a procurement support device 1 and a core system 2, and these procurement support devices 1 and the core system 2 are communicably connected by a network 3.
 調達支援装置1は、各種情報処理が可能な装置、一例としてコンピュータ等の情報処理装置である。情報処理装置は、演算素子、記憶媒体及び通信インターフェースを有し、さらに、マウス、キーボード等の入力装置、ディスプレイ等の表示装置を有する。 The procurement support device 1 is a device capable of various information processing, for example, an information processing device such as a computer. The information processing device has an arithmetic element, a storage medium, and a communication interface, and further has an input device such as a mouse and a keyboard, and a display device such as a display.
 演算素子は、例えばCPU(Central Processing Unit)、FPGA(Field-Programmable Gate Array)等である。記憶媒体は、例えばHDD(Hard Disk Drive)などの磁気記憶媒体、RAM(Random Access Memory)、ROM(Read Only Memory)、SSD(Solid State Drive)などの半導体記憶媒体等を有する。また、DVD(Digital Versatile Disk)等の光ディスク及び光ディスクドライブの組み合わせも記憶媒体として用いられる。その他、磁気テープメディアなどの公知の記憶媒体も記憶媒体として用いられる。 The arithmetic element is, for example, a CPU (Central Processing Unit), an FPGA (Field-Programmable Gate Array), or the like. The storage medium includes, for example, a magnetic storage medium such as an HDD (Hard Disk Drive), a semiconductor storage medium such as a RAM (Random Access Memory), a ROM (Read Only Memory), and an SSD (Solid State Drive). Further, a combination of an optical disk such as a DVD (Digital Versatile Disk) and an optical disk drive is also used as a storage medium. In addition, a known storage medium such as a magnetic tape medium is also used as the storage medium.
 記憶媒体には、ファームウェアなどのプログラムが格納されている。調達支援装置1の動作開始時(例えば電源投入時)にファームウェア等のプログラムをこの記憶媒体から読み出して実行し、調達支援装置1の全体制御を行う。また、記憶媒体には、プログラム以外にも、調達支援装置1の各処理に必要なデータ等が格納されている。 Programs such as firmware are stored in the storage medium. At the start of operation of the procurement support device 1 (for example, when the power is turned on), a program such as firmware is read from this storage medium and executed to perform overall control of the procurement support device 1. In addition to the program, the storage medium stores data and the like required for each process of the procurement support device 1.
 基幹システム2も、調達支援装置1と同様に、各種情報処理が可能な装置、一例としてコンピュータ等の情報処理装置である。 Similar to the procurement support device 1, the core system 2 is also a device capable of various information processing, for example, an information processing device such as a computer.
 なお、本実施例の調達支援装置1及び基幹システム2は、それぞれ、情報処理装置が通信ネットワークを介して通信可能に構成された、いわゆるクラウドにより構成されてもよい。また、図1においては単独の基幹システム2として図示しているが、複数の基幹システム2があってもよい。 Note that the procurement support device 1 and the core system 2 of this embodiment may each be configured by a so-called cloud in which the information processing device is configured to be able to communicate via a communication network. Further, although it is shown as a single core system 2 in FIG. 1, there may be a plurality of core systems 2.
 ネットワーク3は、調達支援装置1及び基幹システム2の間の相互の通信を可能にするものである。ネットワーク3は、調達支援装置1及び基幹システム2が設置されている位置、環境に基づいて種々の周知のネットワークが採用可能である。ネットワーク3の一例として、調達支援装置1及び基幹システム2はLAN(Local Area Network)により接続されてもよいし、インターネットや移動体通信網に代表されるWAN(Wide Area Network)により接続されてもよい。また、ネットワーク3は有線/無線いずれのネットワークであってもよいし、部分的に有線/無線ネットワークが採用されてもよい。 The network 3 enables mutual communication between the procurement support device 1 and the core system 2. As the network 3, various well-known networks can be adopted based on the location and environment in which the procurement support device 1 and the core system 2 are installed. As an example of the network 3, the procurement support device 1 and the core system 2 may be connected by a LAN (Local Area Network), or may be connected by a WAN (Wide Area Network) represented by the Internet or a mobile communication network. Good. Further, the network 3 may be either a wired / wireless network, or a wired / wireless network may be partially adopted.
 図2は、実施例に係る調達支援システムSの概略構成を示す機能ブロック図である。 FIG. 2 is a functional block diagram showing a schematic configuration of the procurement support system S according to the embodiment.
 調達支援装置1は、制御部10、記憶部14、表示部15及び通信部16を有する。 The procurement support device 1 has a control unit 10, a storage unit 14, a display unit 15, and a communication unit 16.
 制御部10は、調達支援装置1全体の制御を行う。制御部10は、生産開始日決定部11、工程期限設定部12及び優先度算出部13を有する。 The control unit 10 controls the entire procurement support device 1. The control unit 10 has a production start date determination unit 11, a process deadline setting unit 12, and a priority calculation unit 13.
 生産開始日決定部11は、複数の部品からなる製品の生産計画に基づいて、製品を製造する少なくとも一つの製造工程の生産開始日を決定する。既に説明したように、生産開始日は本実施例における全体指標であるから、生産開始日決定部11は全体指標を決定するともいえる。 The production start date determination unit 11 determines the production start date of at least one manufacturing process for manufacturing the product, based on the production plan of the product composed of a plurality of parts. As described above, since the production start date is the overall index in this embodiment, it can be said that the production start date determination unit 11 determines the overall index.
 より詳細には、生産開始日決定部11は、部品毎の生産開始日を決定する。特に、生産開始日決定部11は、製造工程毎の部品の部品表、及び部品の調達リードタイムにも基づいて生産開始日を決定する。ここに、既に説明したように、調達工程は、少なくとも発注依頼工程、発注工程及び納品待ち工程を有し、さらに、納品待ち工程に先んじて設定されるフォローアップ工程も有する。 More specifically, the production start date determination unit 11 determines the production start date for each part. In particular, the production start date determination unit 11 determines the production start date based on the parts list of parts for each manufacturing process and the procurement lead time of parts. Here, as already described, the procurement process has at least an order request process, an ordering process, and a delivery waiting process, and further has a follow-up process set prior to the delivery waiting process.
 工程期限設定部12は、各々の部品の調達業務を複数の調達工程に分割し、全体指標である生産開始日に基づいて個々の調達工程における工程完了の期限を設定する。本実施例では、後述するように、個々の調達工程における工程完了の期限であるので、工程期限設定部12は個別指標を設定するともいえる。 The process deadline setting unit 12 divides the procurement work of each part into a plurality of procurement processes, and sets the deadline for process completion in each procurement process based on the production start date, which is an overall index. In this embodiment, as will be described later, since it is the deadline for completing the process in each procurement process, it can be said that the process deadline setting unit 12 sets an individual index.
 さらに、工程期限設定部12は、発注工程において設定された納期日に基づいて、フォローアップ工程の工程完了の期限を設定する。このフォローアップ工程の工程完了の期限も本実施例における個別指標である。 Further, the process deadline setting unit 12 sets the deadline for process completion of the follow-up process based on the delivery date set in the ordering process. The deadline for completing the follow-up process is also an individual index in this embodiment.
 優先度算出部13は、個別指標である工程完了の期限と現在の日付とに基づいて、工程完了の期限に係る調達工程の優先度を算出する。ここに、優先度とは、工程完了の期限と現在の日付との前後関係、工程完了の期限から現在の日付までの期間の大小を示す指標である。優先度の詳細については後述する。 The priority calculation unit 13 calculates the priority of the procurement process related to the process completion deadline based on the process completion deadline and the current date, which are individual indicators. Here, the priority is an index indicating the context of the process completion deadline and the current date, and the magnitude of the period from the process completion deadline to the current date. The details of the priority will be described later.
 さらに、優先度算出部13は、全体指標である生産開始日と現在の日付とに基づいて、生産開始日に係る製造工程の優先度を算出する。 Further, the priority calculation unit 13 calculates the priority of the manufacturing process related to the production start date based on the production start date and the current date, which are the overall indicators.
 記憶部14は、プログラムやデータを一時的または永続的に格納する。記憶部14にはファームウェア等のプログラム、及び、調達支援装置1の動作時に必要となるデータ等が格納される。 The storage unit 14 temporarily or permanently stores programs and data. A program such as firmware and data required for the operation of the procurement support device 1 are stored in the storage unit 14.
 表示部15は、制御部10の制御経過及び結果、さらには記憶部14に格納されたデータ等が、制御部10からに指示に基づいて視認可能に表示される。さらに、表示部15には、優先度算出部13により算出された製造工程の優先度が部品毎に表示される。好ましくは、表示部15は異なる製造工程の優先度を異なる色で表示する。 The display unit 15 visually displays the control progress and result of the control unit 10, data stored in the storage unit 14, and the like based on instructions from the control unit 10. Further, the display unit 15 displays the priority of the manufacturing process calculated by the priority calculation unit 13 for each part. Preferably, the display unit 15 displays the priorities of different manufacturing processes in different colors.
 通信部16は、制御部10の制御に基づいて、制御部10から送出されるデータをネットワーク3経由で基幹システム2に送信し、また、ネットワーク3経由で基幹システム2から送信されたデータを受信する。 Based on the control of the control unit 10, the communication unit 16 transmits the data transmitted from the control unit 10 to the core system 2 via the network 3, and also receives the data transmitted from the core system 2 via the network 3. To do.
 基幹システム2は、記憶部20及び通信部21を有する。 The core system 2 has a storage unit 20 and a communication unit 21.
 記憶部20には、調達支援システムS全体の動作に必要な各種データが格納されている。記憶部20に格納されているデータの詳細については後述する。通信部21は、調達支援装置1の通信部16と同様に、ネットワーク3経由で調達支援装置1にデータを送信し、また、調達支援装置1から送信されたデータを受信する。 The storage unit 20 stores various data necessary for the operation of the entire procurement support system S. Details of the data stored in the storage unit 20 will be described later. The communication unit 21 transmits data to the procurement support device 1 via the network 3 and receives the data transmitted from the procurement support device 1 in the same manner as the communication unit 16 of the procurement support device 1.
 次に、図3~図5を参照して、本実施例の調達支援システムSの動作について説明する。 Next, the operation of the procurement support system S of this embodiment will be described with reference to FIGS. 3 to 5.
 図3は、実施例に係る調達支援システムの概要の一例を説明するための図である。 FIG. 3 is a diagram for explaining an example of an outline of the procurement support system according to the embodiment.
 調達担当者Pは、調達支援システムSを構成する調達支援装置1のオペレータでもある。調達担当者Pは、調達支援装置1の入力部(図1、図2において図示を省略)を操作し、表示部15に図3に示すような表示画面D1、D2を表示させる。 The procurement person P is also the operator of the procurement support device 1 that constitutes the procurement support system S. The procurement person P operates the input unit (not shown in FIGS. 1 and 2) of the procurement support device 1 and causes the display unit 15 to display the display screens D1 and D2 as shown in FIG.
 表示画面D1には、調達担当者Pが担当している工場(A工場)において製造/生産されている製品がプロジェクト単位で表示されている。図3に示す例では、X、Y、Zが最終製品Xを構成する製品である。従って、XYは最終製品Xを構成する製品Yを生産するプロジェクトを示す。 On the display screen D1, the products manufactured / produced at the factory (factory A) in charge of the procurement person P are displayed in project units. In the example shown in FIG. 3, X, Y, and Z are products constituting the final product X. Therefore, XY indicates a project for producing the product Y constituting the final product X.
 各プロジェクトにはプロジェクト単位の優先度が表示されている。図示の関係で、本実施形態ではハッチング等により優先度を表示しているが、実際には表示部15はカラー表示が可能であるので、図3の凡例に示すように、異なる優先度は異なる色で表示されている。 The priority of each project is displayed for each project. In relation to the illustration, the priority is displayed by hatching or the like in the present embodiment, but since the display unit 15 can actually display in color, different priorities are different as shown in the legend of FIG. It is displayed in color.
 調達担当者Pは、表示画面D1に表示されているプロジェクトの中から、自分が担当するプロジェクト(業務)を入力部により選択、指定する。図3に示す例では、調達担当者PはプロジェクトXXを選択したものとする。プロジェクトの選択により、調達支援システムSは、プロジェクトXXについての表示画面D2を表示させる。 Procurement person P selects and specifies the project (business) he / she is in charge of from the projects displayed on the display screen D1 by the input unit. In the example shown in FIG. 3, it is assumed that the procurement person P selects the project XX. Upon selection of the project, the procurement support system S displays the display screen D2 for the project XX.
 表示画面D2には、プロジェクトXXを構成する製造工程Work1~Work5を列とし、作業場所Assembly1…を行とする表が表示されている。そして、この表を構成するセルには、製造工程及び作業場所により特定されるワークフェイズについての優先度が表示されている。 On the display screen D2, a table is displayed in which the manufacturing processes Work1 to Work5 constituting the project XX are arranged in columns and the work place Assembury1 ... Are arranged in rows. Then, in the cells constituting this table, the priority for the work phase specified by the manufacturing process and the work place is displayed.
 調達担当者Pは、表示画面D2を見ることで、選択したプロジェクトにおけるワークフェイズ毎に、発注済の調達品(部品)が必要なタイミングでフルキットとなるかどうかを確認する。これは、ワークフェイズで部品が一つでも必要なタイミングで揃っていない(不足している)と、作業遅延または作業手戻りが生じるので、各製品(プロジェクト)のワークフェイズ単位で調達品が揃っている必要があるからである。 The procurement person P looks at the display screen D2 and confirms whether the ordered procured items (parts) will be a full kit at the required timing for each work phase in the selected project. This is because if even one part is not prepared (missing) at the required timing in the work phase, work delay or work rework will occur, so the procured items are prepared for each work phase of each product (project). Because it needs to be.
 このため、調達担当者Pは各プロジェクトにおけるワークフェイズ毎の優先度を確認する。そして、ワークフェイズの優先度が好ましくはHigh Priorityに止まる(Past Due Dateにならないようにする)ように調達業務を管理する。 Therefore, the procurement person P confirms the priority for each work phase in each project. Then, the procurement work is managed so that the priority of the work phase preferably stays at High Priority (so that it does not become Past Due Date).
 図4は、実施例に係る調達支援システムの概要の他の例を説明するための図である。なお、図4及び図5において、現在の日付は6月1日であるとして説明を行う。 FIG. 4 is a diagram for explaining another example of the outline of the procurement support system according to the embodiment. In addition, in FIG. 4 and FIG. 5, the current date will be described as June 1.
 調達担当者Pは、図3に示す表示画面D2において、入力部により特定のワークフェイズ(図4に示す例では製造工程がWork4、作業場所がAssembly1)を選択する。ワークフェイズの選択により、調達支援システムSは、図4に示すような表示画面D3を表示部15に表示させる。 The procurement person P selects a specific work phase (in the example shown in FIG. 4, the manufacturing process is Work4 and the work place is Assembury1) by the input unit on the display screen D2 shown in FIG. By selecting the work phase, the procurement support system S causes the display unit 15 to display the display screen D3 as shown in FIG.
 表示画面D3には、選択されたワークフェイズを構成する部品(調達品)単位で納期日、フォローアップ状況、新納期日、生産開始日、Risk Levelが表示されている。また、部品単位の優先度も表示されている。なお、フォローアップやRisk Levelについては詳細を後述する。 On the display screen D3, the delivery date, follow-up status, new delivery date, production start date, and Risk Level are displayed for each part (procured item) that constitutes the selected work phase. In addition, the priority of each part is also displayed. Details of follow-up and Risk Level will be described later.
 調達担当者Pはまず、図3の表示画面D2を見て、優先的に対応すべきワークフェイズを特定する。図示例では、製造工程がWork4、作業場所がAssembly1のワークフェイズの優先度がPast Due Date(図3参照)であるので、このワークフェイズを優先的に対応すべきと判断し、入力部により選択して表示画面D3に詳細を表示させている。 Procurement person P first looks at the display screen D2 in FIG. 3 and identifies the work phase that should be prioritized. In the illustrated example, the priority of the work phase in which the manufacturing process is Work4 and the work place is Assembury1 is Past Due Date (see FIG. 3). Therefore, it is determined that this work phase should be prioritized and selected by the input unit. The details are displayed on the display screen D3.
 調達担当者Pは、表示画面D3を見て、揃っていない(まだ納品されていない)部品の優先度を確認する。図4に示す例では、調達品Part1は生産開始日を超えてもまだ納品されておらず、既に納期変更をサプライヤーに依頼しているので調達担当者Pは現時点での対応はしない。調達品Part2については優先度がHigh Priorityであり、しかも新納期日が生産開始日を超えている。このように、調達品の納期が遅れる場合、ワークフェイズの作業計画の影響をRisk Levelとして確認し、影響が大きい(例えばRisk LevelがCriticalである)場合は、サプライヤーSPと納入について(主に納期日について)交渉を行うことができる(フォローアップ)。 The procurement person P looks at the display screen D3 and confirms the priority of the parts that are not complete (not yet delivered). In the example shown in FIG. 4, the procurement product Part 1 has not yet been delivered even after the production start date, and since the supplier has already been requested to change the delivery date, the procurement person P does not take any action at this time. The procured product Part 2 has a high priority, and the new delivery date exceeds the production start date. In this way, if the delivery date of the procured item is delayed, the influence of the work plan in the work phase is confirmed as Risk Level, and if the influence is large (for example, Risk Level is Critical), the supplier SP and delivery (mainly delivery date). Can negotiate (about the day) (follow-up).
 従って、調達担当者Pは、表示画面D3を確認することで、優先度の高い調達業務について納品が予定通り行われるかサプライヤーSPをフォローすることができる。そして、調達担当者Pを含む調達部門は、サプライヤーSPから予定通り納品が可能な、もしくは納入が遅れるかを納品予定前に把握することができる。 Therefore, the procurement person P can follow the supplier SP to see if the delivery is performed as scheduled for the high-priority procurement work by checking the display screen D3. Then, the procurement department including the procurement person P can grasp whether the delivery is possible or delayed from the supplier SP as scheduled before the delivery schedule.
 以上のことから、調達担当者Pは、表示画面D3を確認することで、納期日前に各部品が予定通り納入が可能かどうかを把握することができ、これにより、ワークフェイズ毎に部品が予定通り揃うかどうかを部品単位で確認することができる。 From the above, the procurement person P can grasp whether each part can be delivered as scheduled before the delivery date by checking the display screen D3, and thereby the parts are scheduled for each work phase. It is possible to check for each part whether or not they are aligned.
 図5は、実施例に係る調達支援システムの概要の他の例を説明するための図である。 FIG. 5 is a diagram for explaining another example of the outline of the procurement support system according to the embodiment.
 サプライヤーから納期変更の要請及び交渉があり、この結果、納期が変更された部品があったものとする(図5の表示画面D4において調達品Part2、Part3)。調達担当者Pは、納期変更後のRisk Levelを確認し、ワークフェイズの作業計画に影響が出るかどうかを確認する。 It is assumed that the supplier has requested and negotiated a change in the delivery date, and as a result, there are parts whose delivery date has been changed (procured items Part2 and Part3 on the display screen D4 in FIG. 5). The procurement person P confirms the Risk Level after the delivery date is changed, and confirms whether or not the work plan of the work phase is affected.
 調達品Part3については、新納期日が生産開始日以前であるので作業計画に影響が出ないと判断できる。そこで、調達担当者Pは、調達品Part3の納入が遅れ、場合によっては調達品Part3が届き次第すぐに作業場に届けてもらうことを資材管理者Mに対して通達する。 Regarding the procured product Part3, since the new delivery date is before the production start date, it can be judged that the work plan will not be affected. Therefore, the procurement manager P notifies the material manager M that the delivery of the procured product Part 3 is delayed, and in some cases, the procured product Part 3 is delivered to the workplace as soon as it arrives.
 一方、調達品Part2については、サプライヤーに対するフォローアップは行っているものの、新納期日が生産開始日以降であるので作業計画に影響が出ると判断できる。そこで、調達担当者Pは、該当するワークフェイズの作業変更が必要である旨、作業開始日、そして、資材管理者Mに納入され次第すぐに調達品Part2を作業場に届けることを生産計画担当者PPや現場責任者FMに対して通達する。 On the other hand, regarding the procured product Part2, although we are following up with the suppliers, it can be judged that the work plan will be affected because the new delivery date is after the production start date. Therefore, the person in charge of procurement P tells the person in charge of production planning that it is necessary to change the work in the corresponding work phase, the work start date, and the person in charge of production planning delivers the procured product Part 2 to the work place as soon as it is delivered to the material manager M. Notify PP and field manager FM.
 以上のことから、調達担当者Pは、表示画面D4を確認することで、納期日前に部品単位で納入遅延が起きることを把握でき、ワークフェイズ毎の作業計画に対する影響に応じて関係者に通達することができる。 From the above, the procurement person P can grasp that the delivery delay occurs for each part before the delivery date by checking the display screen D4, and notifies the persons concerned according to the influence on the work plan for each work phase. can do.
 次に、調達支援システムSの基幹システム2の記憶部20に格納されたデータの詳細について図6A~図6Kを参照して説明する。 Next, the details of the data stored in the storage unit 20 of the core system 2 of the procurement support system S will be described with reference to FIGS. 6A to 6K.
 図6Aは、実施例に係る部品表(BOM)データ100の一例を示す図である。 FIG. 6A is a diagram showing an example of the bill of materials (BOM) data 100 according to the embodiment.
 部品表データ100は、工場ID101、BOM ID102、ワークフェイズ103、部品ID104及び必要数量105を有する。 The bill of materials data 100 has a factory ID 101, a BOM ID 102, a work phase 103, a parts ID 104, and a required quantity 105.
 工場ID101は部品が用いられる工場のIDである。BOM ID102は部品表単位のIDである。ワークフェイズ103は部品が用いられるワークフェイズ103のIDである。部品ID104は部品のIDである。必要数量105はワークフェイズ103により特定されるワークフェイズにおいて部品ID104で特定される部品の必要数量である。 Factory ID 101 is the ID of the factory where the parts are used. BOM ID 102 is an ID for each bill of materials. The work phase 103 is the ID of the work phase 103 in which the component is used. The part ID 104 is the ID of the part. The required quantity 105 is the required quantity of the parts specified by the part ID 104 in the work phase specified by the work phase 103.
 次に、図6Bは、実施例に係る調達LTデータ110の一例を示す図である。 Next, FIG. 6B is a diagram showing an example of the procurement LT data 110 according to the embodiment.
 調達LTデータ110は、工場ID111、BOM ID112、部品ID113、サプライヤーID114及び調達LT115を有する。なお、以下の説明において既に説明した項目についての説明を省略する。 The procurement LT data 110 has a factory ID 111, a BOM ID 112, a part ID 113, a supplier ID 114, and a procurement LT 115. In the following description, the description of the items already described will be omitted.
 サプライヤーID114はサプライヤーのIDである。調達LT115は、部品ID113及びサプライヤーID114により特定される部品の調達LTの日数である。 Supplier ID 114 is the supplier's ID. The procurement LT 115 is the number of days of the procurement LT of the parts specified by the part ID 113 and the supplier ID 114.
 次に、図6Cは、実施例に係る部品在庫データ120の一例を示す図である。 Next, FIG. 6C is a diagram showing an example of the parts inventory data 120 according to the embodiment.
 部品在庫データ120は、工場ID121、プロジェクトID122、BOM ID123、部品ID124及び在庫数量125を有する。 The parts inventory data 120 has a factory ID 121, a project ID 122, a BOM ID 123, a parts ID 124, and an inventory quantity 125.
 プロジェクトID122はプロジェクトのIDである。在庫数量125は、BOM ID123及び部品ID124により特定される、プロジェクト単位の部品の在庫数量を示す数値である。 Project ID 122 is the project ID. The inventory quantity 125 is a numerical value indicating the inventory quantity of parts for each project, which is specified by the BOM ID123 and the part ID124.
 次に、図6Dは、実施例に係る発注依頼データ130の一例を示す図である。 Next, FIG. 6D is a diagram showing an example of the order request data 130 according to the embodiment.
 発注依頼データ130は、工場ID131、プロジェクトID132、発注依頼ID133、部品ID134、サプライヤーID135、発注依頼数量136、納品要求日137及び発注依頼完了フラグ138を有する。 The order request data 130 has a factory ID 131, a project ID 132, an order request ID 133, a part ID 134, a supplier ID 135, an order request quantity 136, a delivery request date 137, and an order request completion flag 138.
 発注依頼ID133は、発注依頼者が行う発注依頼のIDである。発注依頼数量136は、発注依頼ID133により特定される発注依頼において発注依頼がされる部品の数量を示す値である。納品要求日137は、発注依頼ID133により特定される発注依頼においてサプライヤーID135により特定されるサプライヤーに指示する納品要求日を示す日付である。発注依頼完了フラグ138は、発注依頼者が発注依頼ID133により特定される発注依頼の作業を完了したか否かを示すフラグであり、真値(TRUE)であれば発注依頼完了を示す。 The order request ID 133 is the ID of the order request made by the order requester. The order request quantity 136 is a value indicating the quantity of the parts for which the order request is made in the order request specified by the order request ID 133. The delivery request date 137 is a date indicating the delivery request date instructed to the supplier specified by the supplier ID 135 in the order request specified by the order request ID 133. The order request completion flag 138 is a flag indicating whether or not the order requester has completed the work of the order request specified by the order request ID 133, and if it is a true value (TRUE), it indicates the completion of the order request.
 次に、図6Eは、実施例に係る発注データ140の一例を示す図である。 Next, FIG. 6E is a diagram showing an example of order data 140 according to the embodiment.
 発注データ140は、工場ID141、プロジェクトID142、発注ID143、部品ID144、サプライヤーID145、納期日146、発注数量147、納品済み数量148及び発注完了フラグ149を有する。 The order data 140 has a factory ID 141, a project ID 142, an order ID 143, a part ID 144, a supplier ID 145, a delivery date 146, an order quantity 147, a delivered quantity 148, and an order completion flag 149.
 発注ID143は、発注者が行う発注のIDである。納期日146は、発注ID143により特定される発注においてサプライヤーに示す納期日を示す日付である。発注数量147は、発注ID143により特定される発注においてサプライヤーに発注する部品の数量を示す値である。納品済み数量148は、現在の日付において発注ID143により特定される発注に係る部品のうち納品済みの部品の数量を示す値である。発注完了フラグ149は、発注者が発注ID143により特定される発注作業を完了したか否かを示すフラグであり、真値(TRUE)であれば発注完了を示す。 Ordering ID 143 is an ordering ID placed by the ordering party. The delivery date 146 is a date indicating the delivery date indicated to the supplier in the order specified by the order ID 143. The order quantity 147 is a value indicating the quantity of parts to be ordered from the supplier in the order specified by the order ID 143. The delivered quantity 148 is a value indicating the quantity of the delivered parts among the parts related to the order specified by the order ID 143 on the current date. The order completion flag 149 is a flag indicating whether or not the orderer has completed the ordering work specified by the order ID 143, and if it is a true value (TRUE), it indicates the order completion.
 次に、図6Fは、実施例に係るワークフェイズリストデータ150の一例を示す図である。 Next, FIG. 6F is a diagram showing an example of work phase list data 150 according to the embodiment.
 ワークフェイズリストデータ150は、工場ID151、プロジェクトID152、BOM ID153、編成154及びワークフェイズ155を有する。 The work phase list data 150 has a factory ID 151, a project ID 152, a BOM ID 153, an organization 154, and a work phase 155.
 編成154は、同一の製品を複数個製造する際に個々の製品を特定するための数値である。ワークフェイズ155はワークフェイズを示すIDである。 Knitting 154 is a numerical value for specifying each product when manufacturing a plurality of the same products. The work phase 155 is an ID indicating the work phase.
 次に、図6Gは、実施例に係る全体指標リストデータ160の一例を示す図である。 Next, FIG. 6G is a diagram showing an example of the overall index list data 160 according to the embodiment.
 全体指標リストデータ160は、工場ID161、プロジェクトID162、BOM ID163、編成164、ワークフェイズ165、ワークフェイズ生産開始日166、部品ID167、必要数量168及び調達LT169を有する。 The overall index list data 160 has a factory ID 161, a project ID 162, a BOM ID 163, an organization 164, a work phase 165, a work phase production start date 166, a part ID 167, a required quantity 168, and a procurement LT169.
 ワークフェイズ生産開始日166は、ワークフェイズ165により特定されるワークフェイズの生産開始日を示す日付である。 The work phase production start date 166 is a date indicating the production start date of the work phase specified by the work phase 165.
 次に、図6Hは、実施例に係る部品利用可能リストデータ170の一例を示す図である。 Next, FIG. 6H is a diagram showing an example of the component availability list data 170 according to the embodiment.
 部品利用可能リストデータ170は、工場ID171、プロジェクトID172、BOM ID173、部品ID174、在庫数量175、発注ID176、納期日177、発注数量178、納品済み数量179及び利用可能数量180を有する。 The parts available list data 170 has a factory ID 171, a project ID 172, a BOM ID 173, a parts ID 174, an inventory quantity 175, an order ID 176, a delivery date 177, an order quantity 178, a delivered quantity 179, and an available quantity 180.
 利用可能数量180は、在庫数量175と納品済み数量179とを足し合わせた数値である。 The available quantity 180 is the sum of the inventory quantity 175 and the delivered quantity 179.
 次に、図6Iは、実施例に係る発注対象リストデータ190の一例を示す図である。 Next, FIG. 6I is a diagram showing an example of the order target list data 190 according to the embodiment.
 発注対象リストデータ190は、工場ID191、プロジェクトID192、BOM ID193、編成194、ワークフェイズ195、ワークフェイズ生産開始日196、発注依頼ID197、発注ID198、部品ID199、サプライヤーID200、調達LT201、発注依頼数量202、納品要求日203、納期日204、発注数量205、納品済み数量206及び発注完了フラグ207を有する。 The order target list data 190 includes factory ID 191 and project ID 192, BOM ID 193, organization 194, work phase 195, work phase production start date 196, order request ID 197, order ID 198, part ID 199, supplier ID 200, procurement LT201, and order request quantity 202. , Delivery request date 203, delivery date 204, order quantity 205, delivered quantity 206, and order completion flag 207.
 次に、図6Jは、実施例に係る発注依頼対象リストデータ210の一例を示す図である。 Next, FIG. 6J is a diagram showing an example of the order request target list data 210 according to the embodiment.
 発注依頼対象リストデータ210は、工場ID211、プロジェクトID212、BOM ID213、編成214、ワークフェイズ215、ワークフェイズ生産開始日216、部品ID217、調達LT218、在庫数量219、必要数量220、発注必要数量221及び発注依頼完了フラグ222を有する。 The order request target list data 210 includes factory ID 211, project ID 212, BOM ID 213, organization 214, work phase 215, work phase production start date 216, part ID 217, procurement LT218, inventory quantity 219, required quantity 220, order required quantity 221 and. It has an order request completion flag 222.
 発注必要数量221は、必要数量220から在庫数量219を差し引いた数値である。 The required order quantity 221 is a numerical value obtained by subtracting the inventory quantity 219 from the required quantity 220.
 そして、図6Kは、実施例に係る生産計画データ220の一例を示す図である。 Then, FIG. 6K is a diagram showing an example of the production planning data 220 according to the embodiment.
 生産計画データ220は、工場ID221、プロジェクトID222、BOM ID223、編成224、ワークフェイズ225及びワークフェイズ生産開始日226を有する。 The production plan data 220 has a factory ID 221 and a project ID 222, a BOM ID 223, an organization 224, a work phase 225, and a work phase production start date 226.
 次に、図7~図13Bを参照して、本実施例の調達支援システムSの動作について説明する。 Next, the operation of the procurement support system S of this embodiment will be described with reference to FIGS. 7 to 13B.
 図7は、実施例に係る調達支援システムSによる各タスク優先度判定処理の一例を示すフローチャートである。図7のフローチャートにより、本実施例の調達支援システムSによる調達支援方法全体の流れを説明する。 FIG. 7 is a flowchart showing an example of each task priority determination process by the procurement support system S according to the embodiment. The flow of the entire procurement support method by the procurement support system S of this embodiment will be described with reference to the flowchart of FIG. 7.
 まず、調達支援装置1は、主に生産開始日決定部11により、生産計画データ220、部品表データ100及び調達LTデータ110に基づいて、全体指標としてワークフェイズの生産開始日を求める(ステップS300)。 First, the procurement support device 1 obtains the production start date of the work phase as an overall index mainly based on the production plan data 220, the bill of materials data 100, and the procurement LT data 110 by the production start date determination unit 11 (step S300). ).
 次いで、調達支援装置1は、主に工程期限設定部12により、全体指標であるワークフェイズの生産開始日に基づいて、個別指標として納品待ち期限日を求める。次いで、調達支援装置1は、主に優先度算出部13により、工程期限設定部12が求めた納品待ち期限日に基づいて各タスクの優先度を算出する(ステップS301)。 Next, the procurement support device 1 mainly uses the process deadline setting unit 12 to obtain the delivery waiting deadline date as an individual index based on the production start date of the work phase, which is an overall index. Next, the procurement support device 1 mainly calculates the priority of each task by the priority calculation unit 13 based on the delivery waiting deadline date obtained by the process deadline setting unit 12 (step S301).
 さらに、調達支援装置1は、主に工程期限設定部12により、全体指標であるワークフェイズの生産開始日に基づいて、個別指標としてフォローアップ期限日を求める。次いで、調達支援装置1は、主に優先度算出部13により、工程期限設定部12が求めたフォローアップ期限日に基づいて各タスクの優先度を算出する(ステップS302)。 Further, the procurement support device 1 mainly uses the process deadline setting unit 12 to obtain the follow-up deadline date as an individual index based on the production start date of the work phase, which is an overall index. Next, the procurement support device 1 mainly calculates the priority of each task by the priority calculation unit 13 based on the follow-up deadline date obtained by the process deadline setting unit 12 (step S302).
 さらに、調達支援装置1は、主に工程期限設定部12により、全体指標であるワークフェイズの生産開始日に基づいて、個別指標として発注期限日を求める。次いで、調達支援装置1は、主に優先度算出部13により、工程期限設定部12が求めた発注期限日に基づいて各タスクの優先度を算出する(ステップS303)。 Further, the procurement support device 1 mainly uses the process deadline setting unit 12 to obtain the order deadline date as an individual index based on the production start date of the work phase, which is an overall index. Next, the procurement support device 1 mainly calculates the priority of each task by the priority calculation unit 13 based on the order deadline date obtained by the process deadline setting unit 12 (step S303).
 そして、調達支援装置1は、主に工程期限設定部12により、全体指標であるワークフェイズの生産開始日に基づいて、個別指標として発注依頼期限日を求める。次いで、調達支援装置1は、主に優先度算出部13により、工程期限設定部12が求めた発注依頼期限日に基づいて各タスクの優先度を算出する(ステップS304)。 Then, the procurement support device 1 mainly uses the process deadline setting unit 12 to obtain the order request deadline date as an individual index based on the production start date of the work phase, which is an overall index. Next, the procurement support device 1 mainly calculates the priority of each task by the priority calculation unit 13 based on the order request deadline date obtained by the process deadline setting unit 12 (step S304).
 次に、図8A及び図8Bは、実施例に係る調達支援システムによる納品待ちタスク優先度判定処理の一例を説明するフローチャートであり、図7のステップS300、S301に対応するフローチャートである。 Next, FIGS. 8A and 8B are flowcharts for explaining an example of the delivery waiting task priority determination process by the procurement support system according to the embodiment, and are flowcharts corresponding to steps S300 and S301 of FIG.
 まず、調達支援装置1は、主に生産開始日決定部11により、生産計画データ220及び部品表データ100に基づいてワークフェイズリストデータ150を作成する(ステップS400)。次いで、調達支援装置1は、主に生産開始日決定部11により、生産計画、部品表データ100及び調達LTデータ110に基づいて、部品毎のワークフェイズの生産開始日を有する全体指標リストデータ160を作成する(ステップS401)。 First, the procurement support device 1 mainly creates work phase list data 150 based on the production plan data 220 and the bill of materials data 100 by the production start date determination unit 11 (step S400). Next, the procurement support device 1 mainly has the production start date determination unit 11, and the overall index list data 160 having the production start date of the work phase for each part based on the production plan, the parts list data 100, and the procurement LT data 110. Is created (step S401).
 次いで、調達支援装置1は、主に生産開始日決定部11により、部品在庫データ120及び発注依頼データ130を取得し、各部品の在庫数量、納品済み数量及び発注数量に基づいて部品利用可能リストデータ170を作成する(ステップS402)。 Next, the procurement support device 1 mainly acquires the parts inventory data 120 and the order request data 130 by the production start date determination unit 11, and the parts availability list based on the inventory quantity, the delivered quantity, and the order quantity of each part. Data 170 is created (step S402).
 次に、調達支援装置1は、以下に説明する部品のワークフェイズの割り当てと優先度の判定とを、全体指標リストデータ160分だけ繰り返し行う(ステップS403)。 Next, the procurement support device 1 repeatedly assigns the work phase of the parts described below and determines the priority for 160 minutes of the overall index list data (step S403).
 すなわち、調達支援装置1は、主に工程期限設定部12により、全体指標リストデータ160の部品の必要数量168に対して、部品利用可能リストデータ170の同一部品の利用可能数量180を割り当てる(ステップS404)。 That is, the procurement support device 1 mainly allocates the available quantity 180 of the same parts of the parts available list data 170 to the required quantity 168 of the parts of the overall index list data 160 by the process deadline setting unit 12 (step). S404).
 次いで、調達支援装置1は、主に工程期限設定部12により、全体指標リストデータ160の部品の必要数量168と部品利用可能リストデータ170の利用可能数量180との大小関係を判定する(ステップS405)。そして、全体指標リストデータ160の部品の必要数量168が部品利用可能リストデータ170の利用可能数量180以上であると判定したら、フローはステップS406に移行し、全体指標リストデータ160の部品の必要数量168が部品利用可能リストデータ170の利用可能数量180未満であると判定したら、フローはステップS407に移行する。 Next, the procurement support device 1 mainly determines the magnitude relationship between the required quantity 168 of the parts of the overall index list data 160 and the available quantity 180 of the parts available list data 170 by the process deadline setting unit 12 (step S405). ). Then, when it is determined that the required quantity of parts of the overall index list data 160 is 168 or more than the available quantity of 180 of the parts available list data 170, the flow proceeds to step S406, and the required quantity of parts of the overall index list data 160 is determined. If it is determined that 168 is less than the available quantity 180 of the component available list data 170, the flow proceeds to step S407.
 ステップS406では、調達支援装置1が、主に工程期限設定部12により、全体指標リストデータ160の部品の必要数量168及び部品利用可能リストデータ170の利用可能数量180に図示のような値を代入する。そして、充足フラグをTrueに設定する。 In step S406, the procurement support device 1 mainly substitutes the values as shown in the figure for the required quantity 168 of the parts of the overall index list data 160 and the available quantity 180 of the parts available list data 170 by the process deadline setting unit 12. To do. Then, the satisfaction flag is set to True.
 一方、ステップS407では、調達支援装置1が、主に工程期限設定部12により、全体指標リストデータ160の部品の必要数量168及び部品利用可能リストデータ170の利用可能数量180に図示のような値を代入する。そして、充足フラグをFalseに設定する。 On the other hand, in step S407, the procurement support device 1 mainly uses the process deadline setting unit 12 to set the required quantity 168 of the parts of the overall index list data 160 and the available quantity 180 of the parts available list data 170 as shown in the figure. Substitute. Then, the satisfaction flag is set to False.
 次に、調達支援装置1は、主に優先度算出部13により、各部品の納品待ち開始日、納品待ち期限日、赤判定日及び黄判定日を算出する(ステップS408)。さらに、調達支援装置1は、主に優先度算出部13により、各部品のDelivery Statusを求める(ステップS409)。 Next, the procurement support device 1 mainly uses the priority calculation unit 13 to calculate the delivery waiting start date, the delivery waiting deadline date, the red determination date, and the yellow determination date of each part (step S408). Further, the procurement support device 1 mainly obtains the Delivery Status of each component by the priority calculation unit 13 (step S409).
 ステップS410にてステップS403からの繰り返しを終了する。 In step S410, the repetition from step S403 is completed.
 次に、調達支援装置1は、主に優先度算出部13により、ワークフェイズ毎の優先度の判断をワークフェイズ内の編成及びワークフェイズ分だけ繰り返し行う(ステップS411)。 Next, the procurement support device 1 mainly uses the priority calculation unit 13 to repeatedly determine the priority for each work phase for the organization within the work phase and the work phase (step S411).
 すなわち、調達支援装置1は、主に優先度算出部13により、優先度の算出が済んでいる全体指標リストデータ160内における該当するワークフェイズの部品の有無を判定する(ステップS412)。そして、全体指標リストデータ160内に該当するワークフェイズの部品がないと判定したら、フローはステップS417に移行し、全体指標リストデータ160内に該当するワークフェイズの部品があると判定したら、フローはステップS413に移行する。 That is, the procurement support device 1 mainly determines the presence / absence of the corresponding work phase component in the overall index list data 160 for which the priority has been calculated by the priority calculation unit 13 (step S412). Then, if it is determined that there is no corresponding work phase component in the overall index list data 160, the flow shifts to step S417, and if it is determined that there is a corresponding work phase component in the overall index list data 160, the flow changes. The process proceeds to step S413.
 次に、調達支援装置1は、主に優先度算出部13により、全ての部品について充足フラグがTrueであるか否かを判定する(ステップS413)。そして、全ての部品について充足フラグがTrueであると判定したら、フローはステップS418に移行し、少なくとも一つの部品について充足フラグがFalseであると判定したら、フローはステップS414に移行する。 Next, the procurement support device 1 mainly determines whether or not the satisfaction flag is True for all the parts by the priority calculation unit 13 (step S413). Then, when it is determined that the sufficiency flag is True for all the parts, the flow proceeds to step S418, and when it is determined that the sufficiency flag is False for at least one component, the flow shifts to step S414.
 次に、調達支援装置1は、主に優先度算出部13により、期限切れの部品の有無を判定する(ステップS414)。そして、期限切れの部品があると判定したらフローはステップS419に移行し、期限切れの部品がないと判定したらフローはステップS415に移行する。 Next, the procurement support device 1 determines the presence or absence of expired parts mainly by the priority calculation unit 13 (step S414). Then, if it is determined that there are expired parts, the flow proceeds to step S419, and if it is determined that there are no expired parts, the flow proceeds to step S415.
 さらに、調達支援装置1は、主に優先度算出部13により優先度が赤の部品の有無を判定する(ステップS415)。そして、優先度が赤の部品があると判定したらフローはステップS420に移行し、優先度が赤の部品がないと判定したらフローはステップS416に移行する。 Further, the procurement support device 1 mainly determines the presence / absence of a part having a red priority by the priority calculation unit 13 (step S415). Then, if it is determined that there is a component having a red priority, the flow shifts to step S420, and if it is determined that there is no component having a red priority, the flow shifts to step S416.
 そして、調達支援装置1は、主に優先度算出部13により優先度が黄の部品の有無を判定する(ステップS416)。そして、優先度が黄の部品があると判定したらフローはステップS421に移行し、優先度が黄の部品がないと判定したらフローはステップS422に移行する。 Then, the procurement support device 1 mainly determines the presence / absence of a part having a yellow priority by the priority calculation unit 13 (step S416). Then, if it is determined that there is a component having a yellow priority, the flow shifts to step S421, and if it is determined that there is no component having a yellow priority, the flow shifts to step S422.
 ステップS417では、該当のワークフェイズの優先度をなし(白)に設定する。ステップS418では、該当のワークフェイズの優先度を完了(水色)に設定する。ステップS419では、該当のワークフェイズの優先度を期限切れ(黒)に設定する。ステップS420では、該当のワークフェイズの優先度を赤に設定する。ステップS421では、該当のワークフェイズの優先度を黄に設定する。そして、ステップS422では、該当のワークフェイズの優先度を緑に設定する。 In step S417, the priority of the corresponding work phase is set to none (white). In step S418, the priority of the corresponding work phase is set to complete (light blue). In step S419, the priority of the corresponding work phase is set to expired (black). In step S420, the priority of the corresponding work phase is set to red. In step S421, the priority of the corresponding work phase is set to yellow. Then, in step S422, the priority of the corresponding work phase is set to green.
 ステップS423にてステップS411からの繰り返しを終了する。 In step S423, the repetition from step S411 is completed.
 次に、図9A及び図9Bは実施例に係る調達支援システムによるフォローアップタスク優先度判定処理の一例を説明するフローチャートであり、図7のステップS302に対応するフローチャートである。 Next, FIGS. 9A and 9B are flowcharts for explaining an example of the follow-up task priority determination process by the procurement support system according to the embodiment, and are flowcharts corresponding to step S302 in FIG.
 図9AのステップS500~S507は、図8AのステップS400~S407と同じ処理であるので説明を省略する。 Since steps S500 to S507 in FIG. 9A are the same processes as steps S400 to S407 in FIG. 8A, description thereof will be omitted.
 次に、調達支援装置1は、主に優先度算出部13により、各部品のフォローアップ開始日、フォローアップ期限日、赤判定日及び黄判定日を算出する(ステップS508)。さらに、調達支援装置1は、主に優先度算出部13により、各部品のRisk Levelを求める(ステップS509)。 Next, the procurement support device 1 mainly calculates the follow-up start date, follow-up deadline date, red determination date, and yellow determination date of each part by the priority calculation unit 13 (step S508). Further, the procurement support device 1 obtains the Risk Level of each component mainly by the priority calculation unit 13 (step S509).
 そして、図9A、図9BのステップS510~S523は、図8A、図8BのステップS410~S423と同じ処理であるので説明を省略する。 Since steps S510 to S523 of FIGS. 9A and 9B are the same processes as steps S410 to S423 of FIGS. 8A and 8B, the description thereof will be omitted.
 次に、図10は、実施例に係る調達支援システムによるフォローアップの状態判定処理の一例を説明するフローチャートであり、図7のステップS302に対応するフローチャートである。 Next, FIG. 10 is a flowchart illustrating an example of the follow-up state determination process by the procurement support system according to the embodiment, and is a flowchart corresponding to step S302 of FIG. 7.
 まず、調達支援装置1は、主に優先度算出部13により、入力部を介して調達担当者P等が入力した情報に基づいて部品の発注情報を取得する(ステップS600)。 First, the procurement support device 1 acquires parts ordering information mainly by the priority calculation unit 13 based on the information input by the procurement person P or the like via the input unit (step S600).
 次いで、調達支援装置1は、主に優先度算出部13により、サプライヤーにより調達支援システムSに入力されたフォローアップステータスの状態を確認、判定する(ステップS601)。ここに、「フォローアップステータス」は「納期変更なし確定、フォローアップ不要、納期変更あり確定、納期変更依頼あり確認中、納期変更依頼なし確認中」のいずれかであるとする。そして、フォローアップステータスが納期変更なし確定、またはフォローアップ不要であると判定したらフローはステップS602に移行し、フォローアップステータスが納期変更あり確定であると判定したらフローはステップS603に移行し、フォローアップステータスが納期変更依頼あり確認中であると判定したらフローはステップS604に移行し、フォローアップステータスが納期変更なし確認中であると判定したらフローはステップS605に移行する。 Next, the procurement support device 1 confirms and determines the state of the follow-up status input to the procurement support system S by the supplier mainly by the priority calculation unit 13 (step S601). Here, it is assumed that the "follow-up status" is one of "confirmation without change of delivery date, no follow-up required, confirmation with change of delivery date, confirmation with request for change of delivery date, confirmation without request for change of delivery date". Then, if it is determined that the follow-up status is confirmed without changing the delivery date or follow-up is unnecessary, the flow shifts to step S602, and if it is determined that the follow-up status is confirmed with changing delivery date, the flow shifts to step S603 and follows. If it is determined that the up status is confirming that there is a delivery date change request, the flow proceeds to step S604, and if it is determined that the follow-up status is confirming that there is no delivery date change, the flow proceeds to step S605.
 ステップS602では、フォローアップの完了フラグをTrueに設定する。その後、フローはステップS608に移行する。ステップS603では、フォローアップの完了フラグをTrueに設定し、新納期日を取得する。その後、フローはステップS606に移行する。ステップS603では、フォローアップの完了フラグをFalseに設定し、新納期日を取得する。その後、フローはステップS606に移行する。ステップS606では、フォローアップの完了フラグをFalseに設定する。その後、フローはステップS608に移行する。 In step S602, the follow-up completion flag is set to True. After that, the flow shifts to step S608. In step S603, the follow-up completion flag is set to True, and the new delivery date is acquired. After that, the flow shifts to step S606. In step S603, the follow-up completion flag is set to False, and the new delivery date is acquired. After that, the flow shifts to step S606. In step S606, the follow-up completion flag is set to False. After that, the flow shifts to step S608.
 次いで、調達支援装置1は、主に優先度算出部13により各部品のRisk Levelを更新し(ステップS606)、部品の発注情報のうち変更納期及びRisk Levelを更新し(ステップS607)、部品の発注情報のうち完了フラグを更新する(ステップS608)。 Next, the procurement support device 1 mainly updates the Risk Level of each part by the priority calculation unit 13 (step S606), updates the changed delivery date and the Risk Level of the parts order information (step S607), and updates the risk level of the parts. The completion flag in the order information is updated (step S608).
 次に、図11は、実施例に係る調達支援システムによる発注タスク優先度判定処理の一例を説明するフローチャートであり、図7のステップS303に対応するフローチャートである。 Next, FIG. 11 is a flowchart illustrating an example of the ordering task priority determination process by the procurement support system according to the embodiment, and is a flowchart corresponding to step S303 of FIG. 7.
 図11のステップS700は図8AのステップS400と同じ処理であるので説明を省略する。 Since step S700 in FIG. 11 is the same process as step S400 in FIG. 8A, the description thereof will be omitted.
 次に、調達支援装置1は、主に優先度算出部13により、発注依頼データ130、発注データ140及び全体指標リストデータ160を突き合わせて、発注が必要な部品の発注対象リストデータ190を作成する(ステップS701)。 Next, the procurement support device 1 mainly uses the priority calculation unit 13 to collate the order request data 130, the order data 140, and the overall index list data 160 to create the order target list data 190 for the parts that need to be ordered. (Step S701).
 次に、調達支援装置1は、主に優先度算出部13により、タスクの優先度の判断を発注対象リストデータ190分だけ繰り返し行う(ステップS702)。 Next, the procurement support device 1 mainly uses the priority calculation unit 13 to repeatedly determine the priority of the task for 190 minutes of the order target list data (step S702).
 まず、調達支援装置1は、主に優先度算出部13により、各部品の発注期限日、赤判定日及び黄判定日を求める(ステップS703)。 First, the procurement support device 1 mainly uses the priority calculation unit 13 to obtain the order deadline date, the red determination date, and the yellow determination date of each part (step S703).
 次いで、調達支援装置1は、主に優先度算出部13により、発注対象リストデータ190の発注完了フラグ207の状態を判定する(ステップS704)。そして、発注完了フラグ207がTrueであると判定したらフローはステップS708に移行し、発注完了フラグ207がFalseまたはNull(未定)であると判定したらフローはステップS705に移行する。 Next, the procurement support device 1 mainly determines the state of the order completion flag 207 of the order target list data 190 by the priority calculation unit 13 (step S704). Then, if it is determined that the order completion flag 207 is True, the flow proceeds to step S708, and if it is determined that the order completion flag 207 is False or Null (undecided), the flow proceeds to step S705.
 次いで、調達支援装置1は、主に優先度算出部13により、ステップS703で求めた発注期限日が今日であるか否かを判定する(ステップS705)。そして、発注期限日が今日であると判定したらフローはステップS709に移行し、発注期限日が今日ではないと判定したらフローはステップS706に移行する。 Next, the procurement support device 1 mainly determines whether or not the order deadline date obtained in step S703 is today by the priority calculation unit 13 (step S705). Then, if it is determined that the order deadline date is today, the flow shifts to step S709, and if it is determined that the order deadline date is not today, the flow shifts to step S706.
 次いで、調達支援装置1は、主に優先度算出部13により、ステップS703で求めた赤判定日が今日であるか否かを判定する(ステップS706)。そして、赤判定日が今日であると判定したらフローはステップS710に移行し、赤判定日が今日ではないと判定したらフローはステップS706に移行する。 Next, the procurement support device 1 mainly determines whether or not the red determination date obtained in step S703 is today by the priority calculation unit 13 (step S706). Then, if it is determined that the red determination date is today, the flow proceeds to step S710, and if it is determined that the red determination date is not today, the flow proceeds to step S706.
 次いで、調達支援装置1は、主に優先度算出部13により、ステップS703で求めた黄判定日が今日であるか否かを判定する(ステップS706)。そして、黄判定日が今日であると判定したらフローはステップS711に移行し、黄判定日が今日ではないと判定したらフローはステップS712に移行する。 Next, the procurement support device 1 mainly determines whether or not the yellow determination date obtained in step S703 is today by the priority calculation unit 13 (step S706). Then, if it is determined that the yellow determination date is today, the flow proceeds to step S711, and if it is determined that the yellow determination date is not today, the flow proceeds to step S712.
 ステップS708ではカラーコードが水色であると判定し、ステップS709ではカラーコードが黒であると判定し、ステップS710ではカラーコードが赤であると判定し、ステップS711ではカラーコードが黄であると判定し、そして、ステップS712ではカラーコードが緑であると判定する。 In step S708, it is determined that the color code is light blue, in step S709 it is determined that the color code is black, in step S710 it is determined that the color code is red, and in step S711 it is determined that the color code is yellow. Then, in step S712, it is determined that the color code is green.
 ステップS713にてステップS702からの繰り返しを終了する。 In step S713, the repetition from step S702 is completed.
 そして、図12は、実施例に係る調達支援システムによる発注依頼タスク優先度判定処理の一例を説明するフローチャートであり、図7のステップS304に対応するフローチャートである。 Then, FIG. 12 is a flowchart illustrating an example of the order request task priority determination process by the procurement support system according to the embodiment, and is a flowchart corresponding to step S304 of FIG. 7.
 図12のステップS800は図8AのステップS400と同じ処理であるので説明を省略する。 Since step S800 in FIG. 12 is the same process as step S400 in FIG. 8A, the description thereof will be omitted.
 次に、調達支援装置1は、主に優先度算出部13により、部品在庫データ120及び発注依頼データ130を取得し、これらと全体指標リストデータ160を突き合わせて、発注依頼が必要な部品の発注依頼対象リストデータ210を作成する(ステップS801)。 Next, the procurement support device 1 mainly acquires the parts inventory data 120 and the order request data 130 by the priority calculation unit 13, collates these with the overall index list data 160, and orders the parts for which the order request is required. Request target list data 210 is created (step S801).
 次に、調達支援装置1は、主に優先度算出部13により、タスクの優先度の判断を発注依頼対象リストデータ210分だけ繰り返し行う(ステップS802)。 Next, the procurement support device 1 mainly uses the priority calculation unit 13 to repeatedly determine the priority of the task for 210 minutes of the order request target list data (step S802).
 まず、調達支援装置1は、主に優先度算出部13により、各部品の発注依頼期限日、赤判定日及び黄判定日を求める(ステップS803)。 First, the procurement support device 1 mainly uses the priority calculation unit 13 to obtain an order request deadline date, a red determination date, and a yellow determination date for each part (step S803).
 次いで、調達支援装置1は、主に優先度算出部13により、発注依頼対象リストデータ210の発注依頼完了フラグ222の状態を判定する(ステップS804)。そして、発注依頼完了フラグ222がTrueであると判定したらフローはステップS808に移行し、発注依頼完了フラグ222がFalseまたはNull(未定)であると判定したらフローはステップS805に移行する。 Next, the procurement support device 1 mainly determines the state of the order request completion flag 222 of the order request target list data 210 by the priority calculation unit 13 (step S804). Then, if it is determined that the order request completion flag 222 is True, the flow proceeds to step S808, and if it is determined that the order request completion flag 222 is False or Null (undecided), the flow proceeds to step S805.
 次いで、調達支援装置1は、主に優先度算出部13により、ステップS803で求めた発注依頼期限日が今日であるか否かを判定する(ステップS805)。そして、発注依頼期限日が今日であると判定したらフローはステップS809に移行し、発注依頼期限日が今日ではないと判定したらフローはステップS806に移行する。 Next, the procurement support device 1 mainly determines whether or not the order request deadline date obtained in step S803 is today by the priority calculation unit 13 (step S805). Then, if it is determined that the order request deadline date is today, the flow shifts to step S809, and if it is determined that the order request deadline date is not today, the flow shifts to step S806.
 これ以降、図12のステップS806~S813は図11のステップS706~S713と同じ処理であるので説明を省略する。 From this point onward, steps S806 to S813 in FIG. 12 are the same processes as steps S706 to S713 in FIG. 11, and thus description thereof will be omitted.
 図13A、図13Bは、実施例に係る調達支援システムによるフォローアップの業務シーケンス図を示す図である。なお、図13A、図13Bに図示するフォローアップのシーケンスは既に説明した内容と重複する内容を含むが、調達支援システムSのみならずこの調達支援システムSのオペレータ等の業務を含むシーケンスを示すためにここで説明を行う。 13A and 13B are diagrams showing a follow-up work sequence diagram by the procurement support system according to the embodiment. The follow-up sequence shown in FIGS. 13A and 13B includes contents that overlap with the contents already described, but is intended to show a sequence that includes not only the procurement support system S but also operations such as operators of the procurement support system S. I will explain here.
 まず、調達支援装置1はフォローアップの優先度判定処理を行う(ステップS900)。調達支援装置1により実施されるフォローアップの優先度判定処理については、図9A及び図9Bを参照して既に説明しているので、ここでの説明は省略する。 First, the procurement support device 1 performs follow-up priority determination processing (step S900). The follow-up priority determination process performed by the procurement support device 1 has already been described with reference to FIGS. 9A and 9B, and thus the description thereof will be omitted here.
 次いで、調達担当者Pは、調達支援装置1に対してフォローアップタスクの優先度の確認を指示し(ステップS902)、調達支援装置1はこれに応じてフォローアップをワークフェイズ単位で表示する(ステップS903)。調達担当者Pは、調達支援装置1の表示部15を視認して、入力部を介して優先的に処理するワークフェイズを選択する(ステップS904)。 Next, the procurement person P instructs the procurement support device 1 to confirm the priority of the follow-up task (step S902), and the procurement support device 1 displays the follow-up in units of work phases accordingly (step S902). Step S903). The procurement person P visually recognizes the display unit 15 of the procurement support device 1 and selects a work phase to be preferentially processed via the input unit (step S904).
 次いで、調達担当者Pは、部品単位のフォローアップの優先度の確認を調達支援装置1に指示し(ステップS905)、調達支援装置1はこれに応じて部品単位のフォローアップの優先度を表示する(ステップS906)。 Next, the procurement person P instructs the procurement support device 1 to confirm the follow-up priority of the parts unit (step S905), and the procurement support device 1 displays the follow-up priority of the parts unit accordingly. (Step S906).
 次いで、調達担当者Pは調達支援装置1の表示部15を見ながら、入力部を介して処理すべきタスクを選択する(ステップS907)。この後、調達担当者Pは、サプライヤーに対して納品日変更の有無を確認し(ステップS908)、サプライヤーは納品日の変更の有無を回答する(ステップS909)。 Next, the procurement person P selects a task to be processed via the input unit while looking at the display unit 15 of the procurement support device 1 (step S907). After that, the procurement person P confirms with the supplier whether or not the delivery date has been changed (step S908), and the supplier replies whether or not the delivery date has been changed (step S909).
 サプライヤーからの回答結果に基づいて、調達担当者Pは基幹システム2にフォローアップステータスを登録する(ステップS910)。調達支援装置1は適宜基幹システム2にアクセスし、フォローアップステータスを参照して(ステップS911)フォローアップステータスの情報を取り込む(ステップS912)。 Based on the response result from the supplier, the procurement person P registers the follow-up status in the core system 2 (step S910). The procurement support device 1 appropriately accesses the core system 2, refers to the follow-up status (step S911), and captures the follow-up status information (step S912).
 そして、調達支援装置1はフォローアップ状態の判定処理を行う(ステップS913)。調達支援装置1により実施されるフォローアップ状態の判定処理については、図10を参照して既に説明しているので、ここでの説明は省略する。 Then, the procurement support device 1 performs a follow-up state determination process (step S913). Since the follow-up state determination process performed by the procurement support device 1 has already been described with reference to FIG. 10, the description here will be omitted.
 ここで、フォローアップタスクのRisk LevelがCriticalであると、調達担当者Pは生産管理部門に生産計画のリスケジュールを依頼し(ステップS914)、生産管理部門はこれに応じて新しい生産計画を連絡し(ステップS915)、新しい生産計画を基幹システム2に登録する。 Here, if the Risk Level of the follow-up task is Critical, the procurement manager P requests the production control department to reschedule the production plan (step S914), and the production control department notifies the new production plan accordingly. Then (step S915), the new production plan is registered in the core system 2.
 一方、フォローアップタスクのRisk LevelがHighであると、調達担当者Pは資材管理部門に部品の入庫後即出荷が必要であることを連絡する(ステップS916)。 On the other hand, if the Risk Level of the follow-up task is High, the procurement manager P informs the material management department that the parts need to be shipped immediately after they are received (step S916).
 図14は、実施例に係る調達支援システムSにおける優先度の判定期間の概略を示す図である。発注依頼、発注、フォローアップ及び納品待ちの各調達工程において図示するような優先度の判定期間を設けている。なお、詳細な期間やどの時点で優先度を変更するかは設計事項であり、図14に示す例は単なる一例である。 FIG. 14 is a diagram showing an outline of a priority determination period in the procurement support system S according to the embodiment. Each procurement process of order request, ordering, follow-up, and waiting for delivery has a priority determination period as shown in the figure. It should be noted that the detailed period and the time at which the priority is changed are design matters, and the example shown in FIG. 14 is merely an example.
 図15は、実施例に係る調達支援システムSにおけるリスクレベル(Risk Level)の判定の概略を示す図、図16は、実施例に係る調達支援システムSにおけるデリバリーステータス(Delivery Status)の判定の概略を示す図である。なお、詳細な期間やどの時点で優先度を変更するかは設計事項であり、図15、図16に示す例は単なる一例である。 FIG. 15 is a diagram showing an outline of the determination of the risk level (Risk Level) in the procurement support system S according to the embodiment, and FIG. 16 is an outline of the determination of the delivery status (Delivery Status) in the procurement support system S according to the embodiment. It is a figure which shows. It should be noted that the detailed period and the time at which the priority is changed are design matters, and the examples shown in FIGS. 15 and 16 are merely examples.
 このように構成される本実施例によれば、複数の部品からなる製品の生産計画に基づいて、生産開始日決定部11が製品を製造する少なくとも一つの製造工程の生産開始日を決定し、各々の部品の調達業務を複数の調達工程に分割し、生産開始日決定部11が決定した生産開始日に基づいて工程期限設定部12が個々の調達工程における工程完了の期限を設定する調達支援方法を実現している。 According to the present embodiment configured as described above, the production start date determination unit 11 determines the production start date of at least one manufacturing process in which the product is manufactured, based on the production plan of the product composed of a plurality of parts. Procurement support that divides the procurement work of each part into a plurality of procurement processes, and the process deadline setting unit 12 sets the deadline for process completion in each procurement process based on the production start date determined by the production start date determination unit 11. Realize the method.
 従って、本実施例によれば、複数の調達工程を有する調達業務において全体指標である生産開始日に遅延も過早もせず部品を納入させる管理をすることが可能となる。 Therefore, according to this embodiment, it is possible to manage the delivery of parts without delay or prematurely on the production start date, which is an overall index, in the procurement business having a plurality of procurement processes.
 なお、上記した実施例は本発明を分かりやすく説明するために構成を詳細に説明したものであり、必ずしも説明した全ての構成を備えるものに限定されるものではない。また、各実施例の構成の一部について、他の構成に追加、削除、置換することが可能である。 It should be noted that the above-described embodiment describes the configuration in detail in order to explain the present invention in an easy-to-understand manner, and is not necessarily limited to the one including all the described configurations. In addition, a part of the configuration of each embodiment can be added, deleted, or replaced with another configuration.
 一例として、上記した実施例における図4及び図5に示す表示画面D3、D4において、優先度(色分け)毎に表示内容を絞り込んだ(フィルタリング)表示を行うことも可能である。また、調達工程に適した分類でフィルタリング表示(例えばサプライヤーでのフィルタ)を行うことも可能である。 As an example, on the display screens D3 and D4 shown in FIGS. 4 and 5 in the above-described embodiment, it is possible to perform (filtering) display in which the display contents are narrowed down for each priority (color coding). It is also possible to perform a filtering display (for example, a filter at a supplier) according to a classification suitable for the procurement process.
 また、上記した実施例では、図6A~図6Kに示すデータが基幹システム2の記憶部20に格納されていたが、これらデータのそれぞれは調達支援システムSを構成する調達支援装置1、基幹システム2の各々の記憶部14、20のいずれに格納されていてもよい。 Further, in the above-described embodiment, the data shown in FIGS. 6A to 6K are stored in the storage unit 20 of the core system 2, but each of these data is the procurement support device 1 and the core system constituting the procurement support system S. It may be stored in any of the storage units 14 and 20 of 2.
 また、上記の各構成、機能、処理部、処理手段等は、それらの一部または全部を、例えば集積回路で設計する等によりハードウェアで実現してもよい。また、本発明は、実施例の機能を実現するソフトウェアのプログラムコードによっても実現できる。この場合、プログラムコードを記録した記憶媒体をコンピュータに提供し、そのコンピュータが備えるプロセッサが記憶媒体に格納されたプログラムコードを読み出す。この場合、記憶媒体から読み出されたプログラムコード自体が前述した実施例の機能を実現することになり、そのプログラムコード自体、及びそれを記憶した記憶媒体は本発明を構成することになる。このようなプログラムコードを供給するための記憶媒体としては、例えば、フレキシブルディスク、CD-ROM、DVD-ROM、ハードディスク、SSD(Solid State Drive)、光ディスク、光磁気ディスク、CD-R、磁気テープ、不揮発性のメモリカード、ROMなどが用いられる。 Further, each of the above configurations, functions, processing units, processing means, etc. may be realized by hardware by designing a part or all of them by, for example, an integrated circuit. The present invention can also be realized by a program code of software that realizes the functions of the examples. In this case, a storage medium in which the program code is recorded is provided to the computer, and the processor included in the computer reads the program code stored in the storage medium. In this case, the program code itself read from the storage medium realizes the functions of the above-described embodiment, and the program code itself and the storage medium storing the program code itself constitute the present invention. Examples of the storage medium for supplying such a program code include a flexible disk, a CD-ROM, a DVD-ROM, a hard disk, an SSD (Solid State Drive), an optical disk, a magneto-optical disk, a CD-R, and a magnetic tape. Non-volatile memory cards, ROMs, etc. are used.
 また、本実施例に記載の機能を実現するプログラムコードは、例えば、アセンブラ、C/C++、perl、Shell、PHP、Java(登録商標)等の広範囲のプログラムまたはスクリプト言語で実装できる。 Further, the program code that realizes the functions described in this embodiment can be implemented in a wide range of programs or script languages such as assembler, C / C ++, perl, Shell, PHP, and Java (registered trademark).
 さらに、実施例の機能を実現するソフトウェアのプログラムコードを、ネットワークを介して配信することによって、それをコンピュータのハードディスクやメモリ等の記憶手段またはCD-RW、CD-R等の記憶媒体に格納し、コンピュータが備えるプロセッサが当該記憶手段や当該記憶媒体に格納されたプログラムコードを読み出して実行するようにしてもよい。 Further, by distributing the program code of the software that realizes the functions of the examples via the network, it is stored in a storage means such as a hard disk or memory of a computer or a storage medium such as a CD-RW or a CD-R. , The processor provided in the computer may read and execute the program code stored in the storage means or the storage medium.
 上述の実施例において、制御線や情報線は、説明上必要と考えられるものを示しており、製品上必ずしも全ての制御線や情報線を示しているとは限らない。全ての構成が相互に接続されていてもよい。 In the above-described embodiment, the control lines and information lines indicate those that are considered necessary for explanation, and do not necessarily indicate all the control lines and information lines in the product. All configurations may be interconnected.
 S…調達支援システム 1…調達支援装置 2…基幹システム 3…ネットワーク 10…制御部 11…生産開始日決定部 12…工程期限設定部 13…優先度算出部 14…記憶部 15…表示部 16…通信部 20…記憶部 21…通信部
 
 
S ... Procurement support system 1 ... Procurement support device 2 ... Core system 3 ... Network 10 ... Control unit 11 ... Production start date determination unit 12 ... Process deadline setting unit 13 ... Priority calculation unit 14 ... Storage unit 15 ... Display unit 16 ... Communication unit 20 ... Storage unit 21 ... Communication unit

Claims (14)

  1.  調達支援システムにより実行される調達支援方法であって、
     複数の部品からなる製品の生産計画に基づいて、前記製品を製造する少なくとも一つの製造工程の生産開始日を決定し、
     各々の前記部品の調達業務を複数の調達工程に分割し、前記生産開始日に基づいて個々の前記調達工程における工程完了の期限を設定する
    ことを特徴とする調達支援方法。
    It is a procurement support method executed by the procurement support system.
    Based on the production plan of the product consisting of a plurality of parts, the production start date of at least one manufacturing process for manufacturing the product is determined.
    A procurement support method characterized in that the procurement operation of each of the parts is divided into a plurality of procurement processes, and the deadline for process completion in each of the procurement processes is set based on the production start date.
  2.  複数の部品からなる製品の生産計画に基づいて、前記製品を製造する少なくとも一つの製造工程の生産開始日を決定する生産開始日決定部と、
     各々の前記部品の調達業務を複数の調達工程に分割し、前記生産開始日に基づいて個々の前記調達工程における工程完了の期限を設定する工程期限設定部と
    を有することを特徴とする調達支援システム。
    A production start date determination unit that determines a production start date of at least one manufacturing process that manufactures the product based on a production plan of a product composed of a plurality of parts.
    Procurement support characterized by having a process deadline setting unit that divides the procurement work of each of the parts into a plurality of procurement processes and sets a deadline for process completion in each of the procurement processes based on the production start date. system.
  3.  前記生産開始日決定部は、前記部品毎の生産開始日を決定することを特徴とする請求項2に記載の調達支援システム。 The procurement support system according to claim 2, wherein the production start date determination unit determines a production start date for each of the parts.
  4.  前記生産開始日決定部は、前記製造工程毎の前記部品の部品表、及び前記部品の調達リードタイムにも基づいて前記生産開始日を決定することを特徴とする請求項2に記載の調達支援システム。 The procurement support according to claim 2, wherein the production start date determination unit determines the production start date based on the parts list of the parts for each manufacturing process and the procurement lead time of the parts. system.
  5.  前記調達工程は、少なくとも発注依頼工程、発注工程及び納品待ち工程を有することを特徴とする請求項2に記載の調達支援システム。 The procurement support system according to claim 2, wherein the procurement process includes at least an order request process, an ordering process, and a delivery waiting process.
  6.  前記工程完了の期限と現在の日付とに基づいて、前記工程完了の期限に係る前記調達工程の優先度を算出する優先度算出部を有することを特徴とする請求項2に記載の調達支援システム。 The procurement support system according to claim 2, further comprising a priority calculation unit that calculates the priority of the procurement process related to the process completion deadline based on the process completion deadline and the current date. ..
  7.  前記優先度算出部は、前記生産開始日と現在の日付とに基づいて、前記生産開始日に係る前記製造工程の優先度を算出することを特徴とする請求項6に記載の調達支援システム。 The procurement support system according to claim 6, wherein the priority calculation unit calculates the priority of the manufacturing process related to the production start date based on the production start date and the current date.
  8.  前記優先度は、前記工程完了の期限と現在の日付との前後関係、前記工程完了の期限から現在の日付までの期間の大小を示す指標であることを特徴とする請求項6に記載の調達支援システム。 The procurement according to claim 6, wherein the priority is an index indicating the context of the process completion deadline and the current date, and the magnitude of the period from the process completion deadline to the current date. Support system.
  9.  前記調達工程は、前記納品待ち工程に先んじて設定されるフォローアップ工程を有することを特徴とする請求項5に記載の調達支援システム。 The procurement support system according to claim 5, wherein the procurement process includes a follow-up process that is set prior to the delivery waiting process.
  10.  前記工程期限設定部は、前記発注工程において設定された納期日に基づいて、前記フォローアップ工程の工程完了の期限を設定することを特徴とする請求項9に記載の調達支援システム。 The procurement support system according to claim 9, wherein the process deadline setting unit sets a deadline for process completion of the follow-up process based on a delivery date set in the ordering process.
  11.  前記製造工程の優先度を前記部品毎に表示する表示部を有することを特徴とする請求項7記載の調達支援システム。 The procurement support system according to claim 7, further comprising a display unit that displays the priority of the manufacturing process for each of the parts.
  12.  前記表示部は、異なる前記製造工程の優先度を異なる色で表示することを特徴とする請求項11記載の調達支援システム。 The procurement support system according to claim 11, wherein the display unit displays different priorities of the manufacturing processes in different colors.
  13.  前記表示部は、特定の前記製造工程の優先度を有する前記部品を表示することを特徴とする請求項11記載の調達支援システム。 The procurement support system according to claim 11, wherein the display unit displays the parts having a specific priority of the manufacturing process.
  14.  前記表示部は、特定の前記調達工程に係る前記部品を表示することを特徴とする請求項11記載の調達支援システム。
     
    The procurement support system according to claim 11, wherein the display unit displays the parts related to the specific procurement process.
PCT/JP2019/037810 2019-09-26 2019-09-26 Procurement assistance method and procurement assistance system WO2021059427A1 (en)

Priority Applications (1)

Application Number Priority Date Filing Date Title
PCT/JP2019/037810 WO2021059427A1 (en) 2019-09-26 2019-09-26 Procurement assistance method and procurement assistance system

Applications Claiming Priority (1)

Application Number Priority Date Filing Date Title
PCT/JP2019/037810 WO2021059427A1 (en) 2019-09-26 2019-09-26 Procurement assistance method and procurement assistance system

Publications (1)

Publication Number Publication Date
WO2021059427A1 true WO2021059427A1 (en) 2021-04-01

Family

ID=75165659

Family Applications (1)

Application Number Title Priority Date Filing Date
PCT/JP2019/037810 WO2021059427A1 (en) 2019-09-26 2019-09-26 Procurement assistance method and procurement assistance system

Country Status (1)

Country Link
WO (1) WO2021059427A1 (en)

Citations (3)

* Cited by examiner, † Cited by third party
Publication number Priority date Publication date Assignee Title
JPH1185860A (en) * 1997-09-10 1999-03-30 Hitachi Ltd Automatic managing system for parts-ordering deadline
JP2012088784A (en) * 2010-10-15 2012-05-10 Kozo Keikaku Engineering Inc Production control system, production control method, and program
JP2019149104A (en) * 2018-02-28 2019-09-05 株式会社日立製作所 Component order system and component order device

Patent Citations (3)

* Cited by examiner, † Cited by third party
Publication number Priority date Publication date Assignee Title
JPH1185860A (en) * 1997-09-10 1999-03-30 Hitachi Ltd Automatic managing system for parts-ordering deadline
JP2012088784A (en) * 2010-10-15 2012-05-10 Kozo Keikaku Engineering Inc Production control system, production control method, and program
JP2019149104A (en) * 2018-02-28 2019-09-05 株式会社日立製作所 Component order system and component order device

Similar Documents

Publication Publication Date Title
CN105787637A (en) Factory management system
JP2007094467A (en) Progress management system
JP2008299762A (en) Production management program
GB2385954A (en) Managing a Virtual Environment
JPH05225205A (en) Sequential defined production planning system
EP3961523A1 (en) Managing production pipelines
JP2011090595A (en) Production management system, and control method and program for the same
JPH11120248A (en) System and method for scheduling production
WO2011121703A1 (en) Production management device, production management program, and production management method
WO2022014048A1 (en) Scheduler system, scheduler management device, and machine learning device
WO2021059427A1 (en) Procurement assistance method and procurement assistance system
JP2010262361A (en) Business management system
JP2016536655A (en) Computer-based system and method for flexible project management
WO2021090572A1 (en) Resource operation plan creation support device, resource operation plan creation support method, and program
US20040122724A1 (en) System and method for generating priorities of manufacturing orders
JP5901513B2 (en) Item requirement prediction apparatus, item requirement prediction method and program
JP2006260598A (en) Schedule planning method
JP2021117945A (en) Method and system for customizing work order
JPH04184602A (en) System and method for preparation of production schedule
WO2017160532A1 (en) Device, system, and method for tracking job management
TWI784311B (en) Management device, management system, and management program
JP2003345419A (en) Answering method and system
JP4679091B2 (en) Production management system for resetting production plan and program for executing the system
JP2000322119A (en) Substitutive lot determination system
JP5199795B2 (en) Forecast management system and program

Legal Events

Date Code Title Description
121 Ep: the epo has been informed by wipo that ep was designated in this application

Ref document number: 19946779

Country of ref document: EP

Kind code of ref document: A1

NENP Non-entry into the national phase

Ref country code: DE

122 Ep: pct application non-entry in european phase

Ref document number: 19946779

Country of ref document: EP

Kind code of ref document: A1

NENP Non-entry into the national phase

Ref country code: JP