WO2007116008A1 PCT/EP2007/053348 EP2007053348W WO2007116008A1 WO 2007116008 A1 WO2007116008 A1 WO 2007116008A1 EP 2007053348 W EP2007053348 W EP 2007053348W WO 2007116008 A1 WO2007116008 A1 WO 2007116008A1
Authority
WO
WIPO (PCT)
Prior art keywords
well
production
wells
cluster
commingled
Prior art date
Application number
PCT/EP2007/053348
Other languages
French (fr)
Inventor
Jan Jozef Maria Briers
Keat-Choon Goh
Charles Edward Moncur
Peter Overschee
Original Assignee
Shell Internationale Research Maatschappij B.V.
Shell Canada Limited
Priority date (The priority date is an assumption and is not a legal conclusion. Google has not performed a legal analysis and makes no representation as to the accuracy of the date listed.)
Filing date
Publication date
Application filed by Shell Internationale Research Maatschappij B.V., Shell Canada Limited filed Critical Shell Internationale Research Maatschappij B.V.
Priority to DE602007002702T priority Critical patent/DE602007002702D1/en
Priority to AU2007235959A priority patent/AU2007235959B2/en
Priority to CA2645902A priority patent/CA2645902C/en
Priority to BRPI0708835-3A priority patent/BRPI0708835B1/en
Priority to AT07727816T priority patent/ATE445083T1/en
Priority to EP07727816A priority patent/EP2004953B1/en
Priority to EA200802116A priority patent/EA200802116A1/en
Priority to NZ571278A priority patent/NZ571278A/en
Publication of WO2007116008A1 publication Critical patent/WO2007116008A1/en
Priority to NO20084606A priority patent/NO341307B1/en

Links

Classifications

    • EFIXED CONSTRUCTIONS
    • E21EARTH DRILLING; MINING
    • E21BEARTH DRILLING, e.g. DEEP DRILLING; OBTAINING OIL, GAS, WATER, SOLUBLE OR MELTABLE MATERIALS OR A SLURRY OF MINERALS FROM WELLS
    • E21B43/00Methods or apparatus for obtaining oil, gas, water, soluble or meltable materials or a slurry of minerals from wells
    • EFIXED CONSTRUCTIONS
    • E21EARTH DRILLING; MINING
    • E21BEARTH DRILLING, e.g. DEEP DRILLING; OBTAINING OIL, GAS, WATER, SOLUBLE OR MELTABLE MATERIALS OR A SLURRY OF MINERALS FROM WELLS
    • E21B41/00Equipment or details not covered by groups E21B15/00 - E21B40/00
    • E21B41/0092Methods relating to program engineering, design or optimisation
    • EFIXED CONSTRUCTIONS
    • E21EARTH DRILLING; MINING
    • E21BEARTH DRILLING, e.g. DEEP DRILLING; OBTAINING OIL, GAS, WATER, SOLUBLE OR MELTABLE MATERIALS OR A SLURRY OF MINERALS FROM WELLS
    • E21B49/00Testing the nature of borehole walls; Formation testing; Methods or apparatus for obtaining samples of soil or well fluids, specially adapted to earth drilling or wells
    • E21B49/08Obtaining fluid samples or testing fluids, in boreholes or wells

Definitions

  • the invention relates to a method for optimising the production of a hydrocarbon production system comprising a cluster of hydrocarbon production wells and an associated fluid separation assembly.
  • fluid streams produced by individual wells of a well cluster are commingled into multiphase streams in one or more production manifold (header) conduits and routed via a fluid separation assembly (comprising one or more bulk separators and/or production separators) into fluid outlet conduits for transportation and sales of at least nominally separated streams of liquids, gas and/or other fluids .
  • a fluid separation assembly comprising one or more bulk separators and/or production separators
  • a problem associated with management of fluid flow at the outlets of the bulk or production separator is that this fluid flow stems from the commingled flux from all the wells of the cluster and does not provide information about the composition and flux of fluids produced by the individual wells . Consequently, the individual flux of fluids produced by the individual wells cannot customarily be tracked accurately in real time or instantaneously.
  • a further problem with monitoring and controlling the production of a hydrocarbon production well is that such a well may produce a mixture of crude oil, gas, water and condensates and that the production may contain irregular slugs of crude oil, water, solids and/or condensates.
  • Multiphase flowmeters are often too expensive, have too restricted an operating envelop and are too complex to install on individual well flowlines to allow individual oil, water and gas components of the well production to be measured continuously in real time, particularly as the well multiphase flow characteristic changes significantly over the life of the well.
  • These multiphase flowmeters also require calibration at start up and/or from time to time thereafter. Consequently, in the vast plurality of cases, the production of fluids by the individual wells is not customarily measured directly accurately continuously, or in real time.
  • PU RTM Production Universe Real Time Monitoring
  • the PU RTM method allows accurate real time estimation of the contributions of individual wells to the total commingled production of a cluster of crude oil, gas and/or other fluid production wells, based on well models derived from well test data and updated regularly using commingled production dynamic data.
  • the PU RTM method also does not require the deployment of multiphase meters at each monitored well.
  • An object of the present invention is to provide a method and system to optimise production of a cluster of wells on the basis of an estimation of the contributions of individual wells to the production of the cluster of wells, tailored to the particular constraints and requirements of the oil and gas production environment.
  • the wells in the cluster may differ in terms of nature and flux of its effluents, and/or mode of operation, stimulation and/or manipulation.
  • the wells may also produce from multiple subsurface zones or branches.
  • the wellheads of the wells in the cluster may be located on land or offshore, above the surface of the sea or on the seabed.
  • the method according to the invention may be used to generate one or more optimisation models, taking into account only significantly relevant well and production system characteristics and effects.
  • a method for optimising production of a cluster of wells of which well effluent streams are commingled and separated in a fluid separation assembly into at least partly separated streams of crude oil, gas and/or other fluids comprising: a) performing a well test on each of the wells during which production from the tested well is varied and one or more individual well production variables are monitored; b) deriving from data obtained by the well tests an estimation model for each well relating to the variation of the flow pattern of effluents produced by the tested well and of the monitored well production variables; c) putting the wells in normal commingled oil and/or gas production; d) monitoring during step c) a dynamic fluid flow pattern of the at least partly separated streams of crude oil, gas and/or other fluids by means of flow meters arranged in the at least partly separated streams of crude oil, gas and/or other fluids downstream of the fluid separation assembly; e) monitoring during step c) one or more well production variables relating to characteristics
  • step f) is assumed that the estimated dynamic commingled fluid flow pattern according to step f) is an accumulation of said individual well production estimation models that are multiplied by unknown weight coefficients;
  • the unknown weight coefficients are estimated by iteratively varying each weight coefficient until the estimated dynamic commingled fluid flow pattern substantially matches with the monitored dynamic fluid flow pattern; and -best estimates of production flow are provided for the selected reconciliation period, and using the individual well reconciliation factors with the estimation models to estimate production from each well for a next reconciliation period; h) defining an operational optimisation target consisting of a target to be optimised regarding production of one or more wells and/or the cluster of wells; i) adjusting production of well effluents of the well cluster such that the optimisation target is approached; and j) steps g and i are repeated from time to time.
  • the method according to the invention may further comprise the steps of: identifying for at least one of the wells in the cluster one or more numerical manipulated variables that can be manipulated directly to vary the production of the well, and thereafter deriving from data, obtained by the well tests and/or during normal commingled production, and/or the estimation model, a prediction model relating the well manipulated variables to the variation of the flux or the flow pattern and/or other characteristics of the produced well effluents.
  • Wells without identified manipulated variables will have prediction models that are constant numbers equal to the nominal estimated productions of wells; summing the prediction models of all wells of the well cluster to provide an overall commingled production prediction model; adjusting production of well effluents by means of the well manipulated variables as guided by the individual well prediction models and the overall commingled production prediction model to achieve the said optimisation target.
  • the method according to the invention may yet further comprise the steps of: measuring an interaction pressure (s), such as a pressure (s) within one or more production manifolds in the flowlines that are connected to the wellheads of the wells of the cluster of wells, in which manifolds which the flux from a plurality of well flowlines is commingled, the variation of which, as total well productions vary, indicates and links interactions between effluent streams from various wells; obtaining dynamic data relating the variations of interaction pressure (s) to the measured variables of the wells, from normal commingled production and / or during periods of production upsets and / or by performing a series of well interaction tests during which the interaction pressure is varied; obtaining from dynamic data relating the variations of interaction pressure (s) to the measured variables of the wells well prediction models relating the variations of well manipulated variable (s) and interaction pressure (s) to the production of the wells; obtaining dynamic data relating the variations of interaction pressure (s) to the total commingled production, from
  • the method according to the invention may further comprise the step of periodically repeating the optimisation method by aligning the prediction models with the current flows so that the aligned prediction models reflect the current flows as estimated by the dynamic reconciliation process.
  • the optimisation target may be a revenue function relating accumulated or averaged combined and / or individual well production to actual net or gross or incremental monetary revenue, optionally including associated production costs.
  • the optimisation target may be required to be achieved while obeying production constraints, consisting of bounds on the manipulated variables and / or the individual well productions, and / or well production quantities, including measurements, and / or that of groups of wells and / or on the interaction pressure (s), and / or on the commingled total productions .
  • the method according to the invention may further comprise the step of performing an optimisation using any of a plurality of numerical optimization algorithms over the manipulated variables based on the operational optimisation target, optionally with constraints, and well and/or overall commingled production prediction models to yield a set of optimised manipulated variables that achieve the operational optimisation target.
  • the production of well effluents of the wells may be varied by adjusting the opening of a production choke valve at the wellhead of the wells or in flowlines connected to the wells, or of a flow control valve in a lift gas injection system of the wells, or by other means of stimulating or restricting the production of the wells .
  • the production of well effluents of the wells may be varied by adjusting the interaction pressure (s) of the production system by means of rerouting well production through parallel production manifold conduits that are connected between upstream and downstream manifolds, or by adjusting the pressure of the fluid separation assembly or assemblies.
  • Required adjustments predicted by the method according to the invention to achieve the optimisation targets may be automatically transmitted to the wells and the production system, or alternatively, after validation by a human operator .
  • estimation and/or prediction models may optionally be generated in part or in full from theoretical and/or empirical physical and/or mechanical and/or chemical characterization of the wells and/or the production system.
  • the optimization target can be adjusted in reaction to and/or in anticipation of changes to the production requirements and/or costs and/or revenues and/or production infrastructure and/or state of the wells and/or the state of the production facilities; and optionally followed up by the conduct of the optimization process, the results of which are implemented and/or used for analysis and planning and/or recorded for future action .
  • the method and system outlined herein is further applicable to the case where the optimisation target is achieved by optional means of temporary close in of production in one or more wells of the well cluster, or the initiation of production of wells of the well cluster that were initially not in production.
  • estimation and/or prediction models may optionally be compared and/or evaluated against theoretical and/or empirical physical and/or mechanical and/or chemical characterization of the wells and/or the production system; for the purposes of troubleshooting and/or diagnosis and/or for improving the models and/or for analysis leading to longer time horizon production management and optimization activities.
  • the methods of this invention apply also when one or more of the wells from the cluster of wells are periodically, or intermittently, operated, or are operated from time to time, and the production or associated quantities to be optimised, and optionally, constrained, are evaluated, for example averaged, over fixed periods of time larger than that characteristic of the periodicity or intermittent operation.
  • the methods of this invention apply also when one or more of the wells from the cluster of wells are periodically, or intermittently, operated, or are operated from time to time, and the duration of its operation, as a proportion of a fixed period of time, is taken a manipulated variable for the well .
  • the methods of this invention apply additionally to an optimization target defined on wells in the well cluster with two or more subsurface zones.
  • zone production estimation models and “zone production prediction models” are generated in addition to the “well production estimation models” and “well production prediction models”.
  • the method according to the invention allows the characterization of the behaviour of wells individually and within the context of the overall production facility as a function of variables that can be freely manipulated at the wells and also for the overall facility.
  • the characterization of the wells and their interactions with the facility allows directly the accurate real time prediction and optimisation of well production within the context of the production facility.
  • the method according to the invention may include consideration of constraints on the production, arising from both the interactions between wells due to the limitations on the facilities, as well as externally imposed constraints .
  • the method according to the invention is also referred to as "Production Universe Real Time Optimisation" (PU RTO) .
  • the "PU RTO” method according to the invention has several advantages over prior art methods, for example, as outlined in PU RTM described in International patent application PCT/EP2005/055680.
  • the "PU RTO” method according to the invention may be used to derive various well and production system characteristics from simple well and production testing at the well and production facility alone, enabling easier model maintenance and dispensing with measurements and quantities not continuously measured, but nevertheless unpredictably variable over periods of time in a production environment, such as piping surface roughness, reservoir pressure-volume-temperature fluid characteristics and composition, equipment and well performance curves, and similar.
  • "PU RTO” is "data driven” .
  • the "overall well and production system model" of the commingled well production system may be constructed without preconceptions as to its underlying physical nature other than the use basic fundamental topological and physical relations, and purely from measured data.
  • the method according to the present invention may be used to provide characterization of the combined well and production system that will be of benefit additionally for offline analysis and planning activities.
  • it is another benefit of the present invention that it may provide a method and system to link real time current well production characteristics to the offline analysis and modelling to support wider, weekly, monthly planning and optimisation of the potential of an integrated production system comprising of multiple cluster of wells and associated production facilities.
  • FIG. 1 schematically shows a production system according to the invention in which a multiphase fluid mixture comprising crude oil, water, natural gas and/or other fluids is produced by a cluster of multiple wells of which two are represented and transported via multiphase fluid transport pipelines to a bulk separator;
  • FIG. 2 schematically shows how the "Aligned Well Production Prediction Models” and “Aligned Well and Overall Production Prediction Model” is generated from a set of well and production system testing data; and
  • FIG. 3 schematically shows how the "Well Operational
  • FIG. 1 depicts a simple embodiment of a production system comprising a cluster of wells of which effluents are commingled at a production manifold and routed to a production separator.
  • Well 1 is shown in detail, and may be taken as representative of the other wells in the cluster.
  • the other wells in the cluster may however differ in terms of nature and flux of its effluents, and / or mode of operation / stimulation / manipulation .
  • Well 1 comprises a well casing 3 secured in a borehole in the underground formation 4 and production tubing 5 extending from surface to the underground formation.
  • the well 1 further includes a wellhead 10 provided with monitoring equipment for making well measurements, typically for measuring Tubing Head Pressure (THP) 13 and Flowline Pressure (FLP) 14.
  • monitoring equipment for making subsurface measurements, for example Downhole Tubing Pressure (DHP) 18, and/or subsurface and/or surface tubing and/or flowline differential pressure meters, for example wet gas meters (not shown) .
  • DHP Downhole Tubing Pressure
  • the wells may also produce from multiple subsurface zones or branches.
  • the wellheads of the wells in the cluster may be located on land or offshore, above the surface of the sea or on the seabed.
  • the well 1 like well 2, and some but not necessarily all of the other wells in the cluster, will also have some means of adjusting production, such as: a production control choke 11 or a fixed bean choke (not shown) and/or a lift-gas injection control system 12 or downhole interval control valves (not shown), which control the production from one or more inflow regions of the well. Numerical "manipulated variables" are associated with each of these means of adjusting production.
  • the production system further includes a plurality of well production flow lines 20, extending from the wellheads 10 to a production manifold 21, a production pipeline 23 and a means of separating the commingled multiphase flow, in this case a production separator 25.
  • Production manifold pressure measurement 22 and production separator pressure measurement 26 will often be available on the production manifold and the production separator as shown. There will be some means of regulating the level of the production separator, and optionally its pressure or the pressure difference between the separator its the single-phase outlets.
  • a pressure control loop 27 is show in FIG. 1.
  • the production manifold pressure measurement 22 (alternatively the production separator pressure measurement 26) will be used as "interaction pressure", the variation of which as the well production rates are varied, is an indicator of the degree of interaction between the wells.
  • the production separator 25 is provided with outlets for water, oil and gas 35, 36 and 37 respectively. Each outlet 35, 36 or 37 is provided with flow metering devices, 45, 46 and 47 respectively. Optionally, the water and oil outlets can be combined.
  • the production separator pressure may optionally be controlled by regulating the gas flow from 37, thereby affecting the manifold pressure 26 and the flowline pressure 14 and thus the production of the individual wells.
  • the well measurements comprising at least data from 13 and optionally from 14, 18, liftgas injection rate from 12, position of production choke 11, and other measurements as available, are continuously transmitted to the "Production Data Acquisition and Control System” 50.
  • the commingled production measurements 45, 46, 47 are continuously transmitted to the "Production Data Acquisition and Control System” 50.
  • the typical data transmission paths are illustrated as 14a and 45a.
  • the data in 50 is stored and is then subsequently available for non-real time data retrieval for data analysis and model construction as outlined in this patent.
  • the data in the "Production Data Acquisition and Control System” is also accessed by "PU RTM" in real time for use in conjunction with "well production estimation models” for the continuous real time estimation of individual well productions.
  • Some well production rate controls will also be adjustable from "Production Data Acquisition and Control System” 50 for remotely adjusting and optimising the well production, for example, the production choke opening or the liftgas injection rate, and the signal line for lift- gas injection rate control is shown as 12a.
  • An associated well testing facility may optionally and is preferably to be available for the individual testing and characterization of the wells .
  • testing for well model construction may be conducted utilizing measurements 45, 46, 47 from the production separator.
  • FIG. 2 provides one preferred embodiment of the "data driven" modelling process for this invention. The intent is to generate sustainably useful models fit for the purpose of the invention, taking into account only significantly relevant well and production system characteristics and effects.
  • the procedure for constructing "well production estimation model" using dedicated well test facilities is as previously outlined in "PU RTM".
  • the relation between the "manipulated variable” and the measurements at the well flowline may be derived from well test data 60, for example "DDWTs", or from "production data” 63 by adjusting the manipulated variable during normal well production, and recording the reactions of the measurements at the well flowline.
  • the "interaction pressure" at the production manifold in this embodiment to the total commingled production flows routed via the production manifold, and optionally, of variables, v w , that are manipulated at a overall facilities level which also affect the "interaction pressure", for example, the production separator pressure setpoint 27.
  • Well Optimisation 78 for selected wells, defined by an index set / which is a proper subset of 1)2,..., «, in the form max R ⁇ y 1 ,V 1 )
  • the symbols A> 5 can be envisaged as either matrices or functionals operating on ⁇ v , anc j ⁇ w .
  • cross terms and second and higher order terms on ⁇ v , and Aw can be inserted without loss of generality.
  • the well optimisation, 78 may then be conducted to solve for the optimal value of v ⁇ , 79, the manipulated variable at well i .
  • the well optimisation necessarily assumes the common well interaction variable w , which is an variable affected by the collective production of the wells and variables at the overall production system level, is unchanged by the well optimisation, or has negligible effect on the optimisation result.
  • Aw J ⁇ AAv 1 +( ⁇ B 1 ](KAy + LAv J
  • ⁇ B,,K,L are matrice s of real number s , f or example , we have
  • the optimised variables 84 may be directly computed or an automated numerical iterative optimisation procedure applied.
  • automated numerical iterative optimisation approaches that are applicable depending on the form of 83.
  • manipulated variables are continuous variables, and 83 is defined by continuous smooth nonlinear model and revenue functions and inequality constraints
  • SQL sequential quadratic programme
  • the set of “optimised manipulated variables” is then available for further action.
  • the "optimised manipulated variables” are reported to the production facility operators for implementation at the wells and the facility, or alternatively, directly transmitted to the "Production Data Acquisition & Control System” 50 for automated implementation.
  • optimised manipulated variables is conducted from time to time, and is controlled by a "Optimization Initiation System” 90.
  • "Well Operational Production Optimisation” and the “Overall Facility Operational Production Optimisation” are initiated on a periodic basis, for example once every day, and/or on demand, in anticipation of changes to the state of the philosophy of management of the wells or of the production system or of the constraints or of the optimisation target.
  • changes in gaslift availability will automatically initiate an optimisation.
  • the "PU RTM Well Production Estimation Model” is verified and updated periodically by checking against normal well testing.
  • the well manipulated variables are cycled periodically during normal well production to allow verification and updates of the "Well Manipulation & Interaction Models".
  • - Production data is captured during normal operations to validate and update as necessary the "Well Manipulation & Interaction Models", and the "Interaction Pressure Model”.
  • the "optimised manipulated variables" are transmitted after inspection by a human operator.
  • the computational optimisation step determines the wells that will either be opened up to resume the individual well production, or closed in to stop the individual well production, or switched between different production separators, addition to the "optimised manipulated variables" for the well while in production.
  • the manipulated variables v ,' v » will include binary values 0 or 1, and various rigorous and heuristic methods are available for its solution, depending on the structure of the models and optimisation formulations used.
  • the prediction models of the wells and the overall production system should periodically be compared and evaluated against theoretical physical and mechanical models of the wells and/or the production system, if these are available.
  • the evaluation and comparison of the models derived from the actual well performances as per this invention against theoretical models will yield information to aid in longer time horizon production management and optimization activities.

Abstract

The present invention relates to a method to optimise production of a cluster of wells on the basis of an estimation of the contributions of individual wells to the production of the cluster of wells, tailored to the particular constraints and requirements of the oil and gas production environment. The wells in the cluster may differ in terms of nature and flux of its effluents, and/or mode of operation, stimulation and/or manipulation. The wells may also produce from multiple subsurface zones or branches. The wellheads of the wells in the cluster may be located on land or offshore, above the surface of the sea or on the seabed. The method according to the invention may be used to generate one or more optimisation models, taking into account only significantly relevant well and production syatem characeristics and effects.

Description

METHOD FOR OPTIMISING THE PRODUCTION OF A CLUSTER OF
WELLS
BACKGROUND OF THE INVENTION
The invention relates to a method for optimising the production of a hydrocarbon production system comprising a cluster of hydrocarbon production wells and an associated fluid separation assembly.
Typically, fluid streams produced by individual wells of a well cluster are commingled into multiphase streams in one or more production manifold (header) conduits and routed via a fluid separation assembly (comprising one or more bulk separators and/or production separators) into fluid outlet conduits for transportation and sales of at least nominally separated streams of liquids, gas and/or other fluids .
A problem associated with management of fluid flow at the outlets of the bulk or production separator is that this fluid flow stems from the commingled flux from all the wells of the cluster and does not provide information about the composition and flux of fluids produced by the individual wells . Consequently, the individual flux of fluids produced by the individual wells cannot customarily be tracked accurately in real time or instantaneously. The inability to track the individual well productions, together with the variability of well production and properties over time, leads immediately to the inability to fully characterize the wells for the purposes of predicting flows if various well adjustments are made. Further, the production from the wells often interact due to limited capacity in the manifold and the separator to handle the full potential productions from the wells. As an example, over-production of gas in one well may reduce the total oil production in the cluster of wells .
A further problem with monitoring and controlling the production of a hydrocarbon production well is that such a well may produce a mixture of crude oil, gas, water and condensates and that the production may contain irregular slugs of crude oil, water, solids and/or condensates. Multiphase flowmeters are often too expensive, have too restricted an operating envelop and are too complex to install on individual well flowlines to allow individual oil, water and gas components of the well production to be measured continuously in real time, particularly as the well multiphase flow characteristic changes significantly over the life of the well. These multiphase flowmeters also require calibration at start up and/or from time to time thereafter. Consequently, in the vast plurality of cases, the production of fluids by the individual wells is not customarily measured directly accurately continuously, or in real time. International patent application WO03/046485 discloses a production metering and well testing system, wherein the accumulated production of wells of an entire field is measured downstream of a bulk separator in which the produced fractions of crude oil, water, natural gas, solids and/or condensates are separated and the flux and composition of the produced crude oil and/or other fractions can be accurately monitored. This accurate measurement of the accumulated production of wells of an entire field is made simultaneously, and compared, with less accurate measurements upstream multiphase flow measurements that are taken simultaneously at each individual well.
Applicant's International patent application PCT/EP2005/055680, filed on 1 November 2005, "Method and system for determining the contributions of individual wells to the production of a cluster of wells" discloses a method and system named and hereafter referred to as "Production Universe Real Time Monitoring" (PU RTM) . The PU RTM method allows accurate real time estimation of the contributions of individual wells to the total commingled production of a cluster of crude oil, gas and/or other fluid production wells, based on well models derived from well test data and updated regularly using commingled production dynamic data. The PU RTM method also does not require the deployment of multiphase meters at each monitored well.
An object of the present invention is to provide a method and system to optimise production of a cluster of wells on the basis of an estimation of the contributions of individual wells to the production of the cluster of wells, tailored to the particular constraints and requirements of the oil and gas production environment. The wells in the cluster may differ in terms of nature and flux of its effluents, and/or mode of operation, stimulation and/or manipulation. The wells may also produce from multiple subsurface zones or branches. The wellheads of the wells in the cluster may be located on land or offshore, above the surface of the sea or on the seabed. The method according to the invention may be used to generate one or more optimisation models, taking into account only significantly relevant well and production system characteristics and effects. SUMMARY OF THE INVENTION
In accordance with the invention there is provided a method for optimising production of a cluster of wells of which well effluent streams are commingled and separated in a fluid separation assembly into at least partly separated streams of crude oil, gas and/or other fluids, the method comprising: a) performing a well test on each of the wells during which production from the tested well is varied and one or more individual well production variables are monitored; b) deriving from data obtained by the well tests an estimation model for each well relating to the variation of the flow pattern of effluents produced by the tested well and of the monitored well production variables; c) putting the wells in normal commingled oil and/or gas production; d) monitoring during step c) a dynamic fluid flow pattern of the at least partly separated streams of crude oil, gas and/or other fluids by means of flow meters arranged in the at least partly separated streams of crude oil, gas and/or other fluids downstream of the fluid separation assembly; e) monitoring during step c) one or more well production variables relating to characteristics of the multiphase flow streams produced by the individual wells; f) repeatedly estimating a dynamic commingled fluid flow pattern of the cluster of wells on the basis of the estimation models according to step b) and production variables monitored in accordance with step e) ; g) performing a dynamic reconciliation process, wherein during a selected reconciliation period:
-it is assumed that the estimated dynamic commingled fluid flow pattern according to step f) is an accumulation of said individual well production estimation models that are multiplied by unknown weight coefficients;
-the unknown weight coefficients are estimated by iteratively varying each weight coefficient until the estimated dynamic commingled fluid flow pattern substantially matches with the monitored dynamic fluid flow pattern; and -best estimates of production flow are provided for the selected reconciliation period, and using the individual well reconciliation factors with the estimation models to estimate production from each well for a next reconciliation period; h) defining an operational optimisation target consisting of a target to be optimised regarding production of one or more wells and/or the cluster of wells; i) adjusting production of well effluents of the well cluster such that the optimisation target is approached; and j) steps g and i are repeated from time to time. Optionally, the method according to the invention may further comprise the steps of: identifying for at least one of the wells in the cluster one or more numerical manipulated variables that can be manipulated directly to vary the production of the well, and thereafter deriving from data, obtained by the well tests and/or during normal commingled production, and/or the estimation model, a prediction model relating the well manipulated variables to the variation of the flux or the flow pattern and/or other characteristics of the produced well effluents. Wells without identified manipulated variables will have prediction models that are constant numbers equal to the nominal estimated productions of wells; summing the prediction models of all wells of the well cluster to provide an overall commingled production prediction model; adjusting production of well effluents by means of the well manipulated variables as guided by the individual well prediction models and the overall commingled production prediction model to achieve the said optimisation target. Optionally, the method according to the invention may yet further comprise the steps of: measuring an interaction pressure (s), such as a pressure (s) within one or more production manifolds in the flowlines that are connected to the wellheads of the wells of the cluster of wells, in which manifolds which the flux from a plurality of well flowlines is commingled, the variation of which, as total well productions vary, indicates and links interactions between effluent streams from various wells; obtaining dynamic data relating the variations of interaction pressure (s) to the measured variables of the wells, from normal commingled production and / or during periods of production upsets and / or by performing a series of well interaction tests during which the interaction pressure is varied; obtaining from dynamic data relating the variations of interaction pressure (s) to the measured variables of the wells well prediction models relating the variations of well manipulated variable (s) and interaction pressure (s) to the production of the wells; obtaining dynamic data relating the variations of interaction pressure (s) to the total commingled production, from periods of normal commingled production and / or during periods of production upsets and / or by performing a series of tests during which the interaction pressure is varied, and thereafter one or more manifold interaction models relating the variation of the interaction pressure (s) with the total commingled production flows flowing through the manifolds; combining the well prediction models to the interaction pressure models to obtain an overall commingled production prediction model.
Optionally the method according to the invention may further comprise the step of periodically repeating the optimisation method by aligning the prediction models with the current flows so that the aligned prediction models reflect the current flows as estimated by the dynamic reconciliation process. The optimisation target may be a revenue function relating accumulated or averaged combined and / or individual well production to actual net or gross or incremental monetary revenue, optionally including associated production costs. The optimisation target may be required to be achieved while obeying production constraints, consisting of bounds on the manipulated variables and / or the individual well productions, and / or well production quantities, including measurements, and / or that of groups of wells and / or on the interaction pressure (s), and / or on the commingled total productions .
The method according to the invention may further comprise the step of performing an optimisation using any of a plurality of numerical optimization algorithms over the manipulated variables based on the operational optimisation target, optionally with constraints, and well and/or overall commingled production prediction models to yield a set of optimised manipulated variables that achieve the operational optimisation target. Optionally, the production of well effluents of the wells may be varied by adjusting the opening of a production choke valve at the wellhead of the wells or in flowlines connected to the wells, or of a flow control valve in a lift gas injection system of the wells, or by other means of stimulating or restricting the production of the wells .
Optionally, the production of well effluents of the wells may be varied by adjusting the interaction pressure (s) of the production system by means of rerouting well production through parallel production manifold conduits that are connected between upstream and downstream manifolds, or by adjusting the pressure of the fluid separation assembly or assemblies.
Required adjustments predicted by the method according to the invention to achieve the optimisation targets may be automatically transmitted to the wells and the production system, or alternatively, after validation by a human operator .
One or more of the estimation and/or prediction models may optionally be generated in part or in full from theoretical and/or empirical physical and/or mechanical and/or chemical characterization of the wells and/or the production system.
The optimization target can be adjusted in reaction to and/or in anticipation of changes to the production requirements and/or costs and/or revenues and/or production infrastructure and/or state of the wells and/or the state of the production facilities; and optionally followed up by the conduct of the optimization process, the results of which are implemented and/or used for analysis and planning and/or recorded for future action .
The method and system outlined herein is further applicable to the case where the optimisation target is achieved by optional means of temporary close in of production in one or more wells of the well cluster, or the initiation of production of wells of the well cluster that were initially not in production.
One or more of the estimation and/or prediction models may optionally be compared and/or evaluated against theoretical and/or empirical physical and/or mechanical and/or chemical characterization of the wells and/or the production system; for the purposes of troubleshooting and/or diagnosis and/or for improving the models and/or for analysis leading to longer time horizon production management and optimization activities.
The methods of this invention apply also when one or more of the wells from the cluster of wells are periodically, or intermittently, operated, or are operated from time to time, and the production or associated quantities to be optimised, and optionally, constrained, are evaluated, for example averaged, over fixed periods of time larger than that characteristic of the periodicity or intermittent operation.
The methods of this invention apply also when one or more of the wells from the cluster of wells are periodically, or intermittently, operated, or are operated from time to time, and the duration of its operation, as a proportion of a fixed period of time, is taken a manipulated variable for the well .
The methods of this invention apply additionally to an optimization target defined on wells in the well cluster with two or more subsurface zones. In this case, "zone production estimation models" and "zone production prediction models" are generated in addition to the "well production estimation models" and "well production prediction models".
The method according to the invention allows the characterization of the behaviour of wells individually and within the context of the overall production facility as a function of variables that can be freely manipulated at the wells and also for the overall facility. The characterization of the wells and their interactions with the facility allows directly the accurate real time prediction and optimisation of well production within the context of the production facility. The method according to the invention may include consideration of constraints on the production, arising from both the interactions between wells due to the limitations on the facilities, as well as externally imposed constraints . The method according to the invention is also referred to as "Production Universe Real Time Optimisation" (PU RTO) . The "PU RTO" method according to the invention has several advantages over prior art methods, for example, as outlined in PU RTM described in International patent application PCT/EP2005/055680. In particular, the "PU RTO" method according to the invention may be used to derive various well and production system characteristics from simple well and production testing at the well and production facility alone, enabling easier model maintenance and dispensing with measurements and quantities not continuously measured, but nevertheless unpredictably variable over periods of time in a production environment, such as piping surface roughness, reservoir pressure-volume-temperature fluid characteristics and composition, equipment and well performance curves, and similar. In other words, "PU RTO" is "data driven" . Specifically, the "overall well and production system model" of the commingled well production system may be constructed without preconceptions as to its underlying physical nature other than the use basic fundamental topological and physical relations, and purely from measured data. The method according to the present invention may be used to provide characterization of the combined well and production system that will be of benefit additionally for offline analysis and planning activities. In other words it is another benefit of the present invention that it may provide a method and system to link real time current well production characteristics to the offline analysis and modelling to support wider, weekly, monthly planning and optimisation of the potential of an integrated production system comprising of multiple cluster of wells and associated production facilities. BRIEF DESCRIPTION OF THE DRAWINGS
The invention will be described by way of example in more detail with reference to the accompanying drawings in which: FIG. 1 schematically shows a production system according to the invention in which a multiphase fluid mixture comprising crude oil, water, natural gas and/or other fluids is produced by a cluster of multiple wells of which two are represented and transported via multiphase fluid transport pipelines to a bulk separator;
FIG. 2 schematically shows how the "Aligned Well Production Prediction Models" and "Aligned Well and Overall Production Prediction Model" is generated from a set of well and production system testing data; and FIG. 3 schematically shows how the "Well Operational
Production Optimisation" problem and the "Overall Facility Operational Production Optimisation" problem are formulated to solve for the "Optimised Setpoints" for the wells selected for individual well optimisation, and the "Optimised Setpoints" for the other wells and the overall production facility.
DETAILED DESCRIPTION OF PREFERED EMBODIMENTS OF THE INVENTION
Reference is made to FIG. 1. FIG. 1 depicts a simple embodiment of a production system comprising a cluster of wells of which effluents are commingled at a production manifold and routed to a production separator. Well 1 is shown in detail, and may be taken as representative of the other wells in the cluster. The other wells in the cluster may however differ in terms of nature and flux of its effluents, and / or mode of operation / stimulation / manipulation .
Well 1 comprises a well casing 3 secured in a borehole in the underground formation 4 and production tubing 5 extending from surface to the underground formation. The well 1 further includes a wellhead 10 provided with monitoring equipment for making well measurements, typically for measuring Tubing Head Pressure (THP) 13 and Flowline Pressure (FLP) 14. Optionally, there may be downhole monitoring equipment for making subsurface measurements, for example Downhole Tubing Pressure (DHP) 18, and/or subsurface and/or surface tubing and/or flowline differential pressure meters, for example wet gas meters (not shown) . The wells may also produce from multiple subsurface zones or branches. The wellheads of the wells in the cluster may be located on land or offshore, above the surface of the sea or on the seabed.
The well 1 , like well 2, and some but not necessarily all of the other wells in the cluster, will also have some means of adjusting production, such as: a production control choke 11 or a fixed bean choke (not shown) and/or a lift-gas injection control system 12 or downhole interval control valves (not shown), which control the production from one or more inflow regions of the well. Numerical "manipulated variables" are associated with each of these means of adjusting production.
The production system further includes a plurality of well production flow lines 20, extending from the wellheads 10 to a production manifold 21, a production pipeline 23 and a means of separating the commingled multiphase flow, in this case a production separator 25. Production manifold pressure measurement 22 and production separator pressure measurement 26 will often be available on the production manifold and the production separator as shown. There will be some means of regulating the level of the production separator, and optionally its pressure or the pressure difference between the separator its the single-phase outlets. For simplicity a pressure control loop 27 is show in FIG. 1. Typically, the production manifold pressure measurement 22 (alternatively the production separator pressure measurement 26) will be used as "interaction pressure", the variation of which as the well production rates are varied, is an indicator of the degree of interaction between the wells.
The production separator 25 is provided with outlets for water, oil and gas 35, 36 and 37 respectively. Each outlet 35, 36 or 37 is provided with flow metering devices, 45, 46 and 47 respectively. Optionally, the water and oil outlets can be combined. The production separator pressure may optionally be controlled by regulating the gas flow from 37, thereby affecting the manifold pressure 26 and the flowline pressure 14 and thus the production of the individual wells.
The well measurements comprising at least data from 13 and optionally from 14, 18, liftgas injection rate from 12, position of production choke 11, and other measurements as available, are continuously transmitted to the "Production Data Acquisition and Control System" 50. Similarly, the commingled production measurements 45, 46, 47 are continuously transmitted to the "Production Data Acquisition and Control System" 50. The typical data transmission paths are illustrated as 14a and 45a. The data in 50 is stored and is then subsequently available for non-real time data retrieval for data analysis and model construction as outlined in this patent. The data in the "Production Data Acquisition and Control System" is also accessed by "PU RTM" in real time for use in conjunction with "well production estimation models" for the continuous real time estimation of individual well productions. Some well production rate controls will also be adjustable from "Production Data Acquisition and Control System" 50 for remotely adjusting and optimising the well production, for example, the production choke opening or the liftgas injection rate, and the signal line for lift- gas injection rate control is shown as 12a.
An associated well testing facility may optionally and is preferably to be available for the individual testing and characterization of the wells . In the absence of a well testing facility, testing for well model construction may be conducted utilizing measurements 45, 46, 47 from the production separator. Reference is now made to FIG. 2, which provides one preferred embodiment of the "data driven" modelling process for this invention. The intent is to generate sustainably useful models fit for the purpose of the invention, taking into account only significantly relevant well and production system characteristics and effects. The procedure leading to the generation of "Aligned Well Production Prediction Models" and "Aligned Well and Overall Production Prediction Model" for a cluster of n wells indexed i = l,2,...,n r for which one "manipulated variable" for each well has been identified, and for which a dedicated well test facility are available, is described as follows: a series of well tests are conducted during which production from each well is varied for well characterization by changing the "manipulated variable" of the well. The well test data 60 is used to generate a
"well production estimation model" 61 in the form y, =f,(u, >v,) , valid for a range of u,>v, within a set u,xV, , wherein the vector J, is the oil, water and gas production of well i, uι is the vector of measurements at well i, and vι is the manipulated variable at well i. The procedure for constructing "well production estimation model" using dedicated well test facilities is as previously outlined in "PU RTM". In "PU RTM" distinction is not made between the measured variables uι and the manipulated variable vι , (which is also measured) but the distinction is required for this invention; a series of "well and production facilities interaction tests" are then conducted to obtain "well and production facilities interaction test data" 62, or alternatively, data can also be derived from "production data" 63 which contains a record of dynamic events during normal production, such as when major gas producing wells are closed in. a "well production manipulation and interaction model" 65 is then constructed relating the variations of "manipulated variable" of the well and the "interaction pressure" to the measurements at the well flowline. The relation between the "manipulated variable" and the measurements at the well flowline may be derived from well test data 60, for example "DDWTs", or from "production data" 63 by adjusting the manipulated variable during normal well production, and recording the reactions of the measurements at the well flowline.
Similarly, the relation between "interaction pressure" and the measurements at the well flowline is established from "well and production facilities interaction tests" data 62 or from "production data" 63 recording dynamic events during normal production.
The "well production manipulation and interaction model" 65 will have the form u, = S1(v, >w) , for each of the wells i = l,2,...,n where weT¥ is the common "interaction pressure" ranging over set W , uι is the vector of measurements at well i, and vι is the manipulated variable at well i , as before.
A "well production prediction model" 66 for each well i = l,2,...,n is then generated from the "well production estimation model" 61 and the "well production manipulation and interaction model" 65 as follows: y, = f,(«,,v,) = f,(g,(v,,w),v,) = A1(V1,w) t so that the function ",(v, >w) relates the vector Ji, the oil, water and gas production of well i, to the w, the common "interaction pressure", and vι , the manipulated variable at well i .
Given the characterization of the well 66, it is now required to derive the dependence of W, the "interaction pressure" at the production manifold in this embodiment, to the total commingled production flows routed via the production manifold, and optionally, of variables, vw , that are manipulated at a overall facilities level which also affect the "interaction pressure", for example, the production separator pressure setpoint 27. This is achieved by using the "well and production facilities interaction test" data 62 to build an "interaction pressure model" 67, w
Figure imgf000018_0001
, where 9 is defined to be the vector of the sum of the production of the wells routed to the production manifold, in this case n i=i
There will be instances wherein data from well testing or production is not available or reliable for a particular well or parts of the overall system, for example when a well is not yet been brought into production. In such cases, models based on theoretical and/or empirical physical and/or mechanical and/or chemical characterization of the wells and/or the production system can be used in place of 65 or 67. Once the "well production manipulation and interaction models" 66 and the "interaction pressure model" 67 are developed, the optimisation process is implemented as per the online part of the workflow in Fig.2 and then as in Fig.3. The desired production optimisation formulations are also set out as follows:
Well Optimisation 78, for selected wells, defined by an index set / which is a proper subset of 1)2,...,«, in the form max R^y1,V1)
subject to constraints
Figure imgf000019_0001
. where
Figure imgf000019_0002
is the objective or revenue function 76 for the well i to be maximized by varying v, , the manipulated variable at well i, subject to Λ constraints on J1^1'",, the well production, the well manipulated variables and the measured variables, respectively, defined by the constraint inequalities
Figure imgf000019_0003
, 77.
Overall Production Optimisation, 83, for wells i£ I (which are wells not already optimised as part of 78), in the form max /?(_y,v,,w,,w,vw)
subject to constraints c J^'-y''V''M''H7'vw)≥0 , 7 = l,2,...,/w ; where Ru>vι >uι >w>vw) is the objective or revenue function, 81, to be maximized by varying v, , the manipulated variable at wells i£l , subject to Jw constraints, 82, c,(;y.;y,.v,,«,,w,vw)>0 on y,w,vWf the overall commingled production, the interaction pressure, and the optional vector of variables that can be manipulated at a overall facilities level, respectively, and 3V^'"*' z =1,2,3,...« r ^j1Q individual well productions, well manipulated variables, and well measured variables for the wells i = 1,2,3,...« .
With the wells in normal commingled production, "PU RTM" is run online to produce continuous real time estimates of production at each individual well 70. The "current" "PU RTM" estimates of individual well production J,, and the "current" measurements and manipulated variable values v^w are used to align the "well production manipulation and interaction models" y, =\(v,'w) by defining a constant offset ^, = y, - Λ,(v,, w) at J,'V,,w _ The "Aligned Well Production Prediction Models"
75 then have the form J, =v, >w> +", . The alignment process allows the optimisation focus to be on incremental changes in the production at the well and overall production, so that if Δv,=v,-^, Aw = W-W and Ay1=J1-J,, then Ay, =0, if Δv, = ° and Δw = 0. For illustrative purposes, the "Aligned Well Production Prediction Model", 75, for each well z, can be cast in the "separated difference" form ΔJ, = AΔv, + BAW, . The symbols A>5, can be envisaged as either matrices or functionals operating on Δv, ancj Δw . Optionally, cross terms and second and higher order terms on Δv, and Aw can be inserted without loss of generality.
For each well is I, which are wells for which a well optimization is desired, given its "Aligned Well Production Prediction Model", 75, and the objective or revenue function 76, and associated optimisation constraints 77, the well optimisation, 78, may then be conducted to solve for the optimal value of vι , 79, the manipulated variable at well i . Note that the well optimisation necessarily assumes the common well interaction variable w , which is an variable affected by the collective production of the wells and variables at the overall production system level, is unchanged by the well optimisation, or has negligible effect on the optimisation result. The "interaction pressure model" 67 w = k[y,vw) can ^g aligned by defining constant "w =
Figure imgf000021_0001
, where the "current nominal value" of the commingled production measurements 9 is denoted by y . The "aligned interaction pressure model" is then of the form w = k\9,vw)+ dw _
Further, we assume the estimates X have been fully reconciled by "PU RTM" with the latest nominal overall commingled production measurements so that
Again, for illustrative purposes, the "aligned interaction pressure model" can also have the "separated difference" form Aw = KAy+ LAvWf where n
A9 = y-y = y-∑y1
Figure imgf000021_0002
Now
Figure imgf000021_0003
is the estimate of total commingled production from the "Aligned Well Production Prediction Models" 75. Hence the "Aligned Well + Overall Production Prediction Model" 80 in "Difference" form is then constructed by combining "Aligned Well Production Prediction Models" 75 with the "aligned interaction pressure model". From
Ay = {∑y]- y = ∑Ay, = ∑ A^1 +B1Aw = J^ AAv1 +(^B1](KAy + LAv J
V I=I J I=I I=I I=I V I=I / we get
Ay = + LAvJ
Figure imgf000021_0004
which is an implicit form of the "Aligned Well + Overall Production Prediction Model" 80 relating the variables
Ay,Avτ,Avw r respectively, the total commingled production, the manipulated variables at the wells, and the manipulated variables at the overall production system level. For given values of ^v1,Avw r depending on the form of the functionals
Figure imgf000022_0001
the implicit form of 80 can be solved Δ_y by a plurality of methods. In the case where the interaction components
∑B,,K,L are matrice s of real number s , f or example , we have
/ - Σ*. K Δy = ∑AΔv, + ϊ>, ILAv
which is solvable for Δ_y given values of vi'v», unless, for example, the operator
i 's-n{Pot:i)nκvertible.
An estimate of the manipulated variables vi'v» required to optimise the production of the overall facility is then obtained by combining "Aligned Well + Overall Production Prediction Model" 80 with the objective or revenue function 81, and associated optimisation constraints 82 to form the "Overall Facility Operational Production Optimisation" 83. The optimisation is then conducted to solve that for optimal values of the
"optimised manipulated variables" vi'v», 84.
Depending on the form of 83, the optimised variables 84 may be directly computed or an automated numerical iterative optimisation procedure applied. There is a plurality of automated numerical iterative optimisation approaches that are applicable depending on the form of 83. Refer for example to the textbook "Nonlinear Programming - Theory and Algorithms", 2nd Edition, 1993, by M Bazaraa, H. D. Sherali and CM. Shetty, or more generally for various rigorous or heuristic "Global Optimisation" methods, see for example, Computers and Chemical Engineering 28 (2004) 1169-1218, "Part I Retrospective on optimization", and "Part II. Future Perspective on Optimization", by L. T. Biegler, I.E. Grossmann, and references therein. For a preferred embodiment where the manipulated variables are continuous variables, and 83 is defined by continuous smooth nonlinear model and revenue functions and inequality constraints, a sequential quadratic programme (SQP) with multiple starting points is used for the automated numerical iterative optimisation to yield the "optimised manipulated variables". The set of "optimised manipulated variables" is then available for further action. Optionally, the "optimised manipulated variables" are reported to the production facility operators for implementation at the wells and the facility, or alternatively, directly transmitted to the "Production Data Acquisition & Control System" 50 for automated implementation.
The computation and application of the optimised manipulated variables is conducted from time to time, and is controlled by a "Optimization Initiation System" 90. Preferably, "Well Operational Production Optimisation" and the "Overall Facility Operational Production Optimisation" are initiated on a periodic basis, for example once every day, and/or on demand, in anticipation of changes to the state of the philosophy of management of the wells or of the production system or of the constraints or of the optimisation target. In one embodiment, changes in gaslift availability will automatically initiate an optimisation.
In a preferred embodiment of the "PU RTO" method according to the invention: All models are validated and updated as necessary using current latest and historical test data.
The "PU RTM Well Production Estimation Model" is verified and updated periodically by checking against normal well testing.
The well manipulated variables are cycled periodically during normal well production to allow verification and updates of the "Well Manipulation & Interaction Models". - Production data is captured during normal operations to validate and update as necessary the "Well Manipulation & Interaction Models", and the "Interaction Pressure Model".
The "optimised manipulated variables" are transmitted after inspection by a human operator.
The computational optimisation step determines the wells that will either be opened up to resume the individual well production, or closed in to stop the individual well production, or switched between different production separators, addition to the "optimised manipulated variables" for the well while in production.
In this case, the manipulated variables v,'v» will include binary values 0 or 1, and various rigorous and heuristic methods are available for its solution, depending on the structure of the models and optimisation formulations used.
The prediction models of the wells and the overall production system, which reflect the reality of the well and production system, should periodically be compared and evaluated against theoretical physical and mechanical models of the wells and/or the production system, if these are available. The evaluation and comparison of the models derived from the actual well performances as per this invention against theoretical models will yield information to aid in longer time horizon production management and optimization activities.

Claims

02- 24 -C L A I M S
1. A method for optimising production of a cluster of wells of which well effluent streams are commingled and separated in a fluid separation assembly into at least partly separated streams of crude oil, gas and/or other fluids, the method comprising: a) performing a well test on each of the wells during which production from the tested well is varied and one or more individual well production variables are monitored; b) deriving from data obtained by the well tests an estimation model for each well relating to the variation of the flow pattern of effluents produced by the tested well and of the monitored well production variables; c) putting the well cluster in normal commingled oil and/or gas production; d) monitoring during step c) a dynamic fluid flow pattern of the at least partly separated streams of crude oil, gas and/or other fluids by means of flow meters arranged in the at least partly separated streams of crude oil, gas and/or other fluids downstream of the fluid separation assembly; e) monitoring during step c)one or more well production variables relating to characteristics of the multiphase flow streams produced by the individual wells; f) repeatedly estimating a dynamic commingled fluid flow pattern of the cluster of wells on the basis of the estimation models according to step b) and production variables monitored in accordance with step e); g) performing a dynamic reconciliation process, wherein during a selected reconciliation period:
-it is assumed that the estimated dynamic commingled fluid flow pattern according to step f) is an accumulation of said individual well production estimation models that are multiplied by unknown weight coefficients;
-the unknown weight coefficients are estimated by iteratively varying each weight coefficient until the estimated dynamic commingled fluid flow pattern substantially matches with the monitored dynamic fluid flow pattern; and -best estimates of production flow are provided for the selected reconciliation period, and using the individual well reconciliation factors with the estimation models to estimate production from each well for a next reconciliation period; h) defining an operational optimisation target consisting of a target to be optimised regarding production of one or more wells and/or the cluster of wells; i) adjusting production of well effluents of the well cluster such that the optimisation target is approached; and j) steps g and i are repeated from time to time.
2. The method of claim 1, further comprising the steps of: - identifying for at least one of the wells in the cluster one or more numerical manipulated well production variables that can be manipulated directly to vary the production of the well, and thereafter deriving from data, obtained by the well tests and/or during normal commingled production, and/or the estimation model, a prediction model relating the well manipulated variables to the variation of the flux or the flow pattern and/or other characteristics of the produced well effluents, wherein any wells without identified manipulated well production variables will have prediction models that are constant numbers equal to a nominal estimated production of the wells; summing the prediction models of all wells of the well cluster to provide an overall commingled production prediction model; adjusting production of well effluents by means of the well manipulated variables as guided by the individual well prediction models and the overall commingled production prediction model to achieve the said optimisation target.
3. The method of claim 2, further comprising the steps of:
- measuring one or more interaction pressures, such as a pressure within one or more production manifolds in well flowlines that are connected to the wellheads of the wells of the cluster of wells, in which manifolds the flux from a plurality of well flowlines is commingled, the variation of which interaction pressure, as total well productions vary, indicates and links interactions between effluent streams from various wells;
- obtaining dynamic data relating the variations of interaction pressure (s) to the measured variables of the wells, from normal commingled production and/or during periods of production upsets and/or by performing a series of well interaction tests during which the interaction pressure is varied;
- obtaining from dynamic data relating the variations of interaction pressure (s) to the measured variables of the wells well prediction models relating the variations of well manipulated variable (s) and interaction pressure (s) to the production of the wells;
- obtaining dynamic data relating to the variations of one or more interaction pressures to the total commingled production, from periods of normal commingled production and/or during periods of production upsets and/or by performing a series of tests during which the interaction pressure is varied, and thereafter one or more manifold interaction models relating the variation of one or more interaction pressures with the total commingled production flows flowing through the manifolds;
- combining the well prediction models to the interaction pressure models to obtain an overall commingled production prediction model.
4. The method of claims 2 and 3, wherein the method further comprises periodically repeating the optimisation method by aligning the prediction models with the current flows so that the aligned prediction models reflect the current flows as estimated by the dynamic reconciliation process.
5. The method of any one of claims 1-4, wherein the optimisation target is a revenue function relating accumulated or averaged combined and/or individual well production to actual net or gross or incremental monetary revenue, optionally including associated production costs .
6. The method of claim 5, wherein the optimisation target is to be achieved while obeying production constraints, consisting of bounds on the manipulated variables, and/or the individual well productions, and/or well production quantities, including measurements, and/or that of groups of wells and/or on one or more interaction pressures, and/or on the commingled total production of the well cluster.
7. The method of claims 5 or 6, further comprising the step of performing an optimisation using any of a plurality of numerical optimisation algorithms over the manipulated variables based on the operational optimisation target, optionally with constraints, and the well and/or overall commingled production prediction models to yield a set of optimised manipulated variables that achieve the operational optimisation target.
8. The method of any of the claims 1-7, wherein the production of well effluents of the wells is varied by adjusting the opening of a production choke valve at the wellhead of the wells or in flowlines connected to the wells, or of a flow control valve in a lift gas injection system of the wells, or by other means of stimulating or restricting the production of the wells, such as any means of reversible and controlled closing in and opening up of a well, a setpoint of a control loop at the well with the production choke valve as an actuator, a setpoint of a control loop on the well gas-lift injection rate or pressure, well gas-lift injection off duration, well gas-lift injection on duration, well gas-lift injection rate, a setpoint of a control loop on the well jet pump hydraulic fluid injection line, well electrical submersible pump (ESP) speed, well rod pump motor speed, well rod pump off duration, and/or well downhole interval control valve opening.
9. The method of any of the claims 1-8, wherein the production of well effluents of the wells is varied by adjusting one or more interaction pressures of the production system by means of rerouting well production through parallel production manifold conduits that are connected between upstream and downstream manifolds, and/or by adjusting the pressure of the fluid separation assembly and/or by adjusting the valves for the routing of well effluents to one or more manifolds that commingle production or that route the commingled production to one or more production separators, and/or by adjusting speed of a compressor in an outlet conduit of the fluid separation assembly.
10. The method of any of the claims 1-9, wherein required adjustments predicted to achieve the optimisation targets are automatically transmitted to the wells and the production system, optionally, after validation by a human operator .
11. The method of any of the claims 1-10, wherein one or more of the estimation and/or prediction models may optionally be generated in part or in full from theoretical and/or empirical physical and/or mechanical and/or chemical characterization of the wells and/or the production system.
12. The method of any of the claims 1-11, wherein the optimisation target is adjusted in reaction to and/or in anticipation of changes to the production requirements and/or costs and/or revenues and/or production infrastructure and/or state of the wells and/or the state of the production facilities; and optionally followed up by the conduct of the optimisation process, the results of which are implemented and/or used for analysis and planning and/or recorded for future action.
13. The method of any of the claims 1-12, wherein the optimisation target is achieved by optional means of temporary close in of production in one or more wells of the well cluster, or the initiation of production of wells of the well cluster that were initially not in production .
14. The methods of claims 2 and 3, whereby one or more of the estimation and/or prediction models may optionally be compared and/or evaluated against theoretical and/or empirical physical and/or mechanical and/or chemical characterization of the wells and/or the production system; for the purposes of troubleshooting and/or diagnosis and/or for improving the models and/or for analysis leading to longer time horizon production management and optimisation activities.
15. The methods of the claims 1-13, wherein one or more of the wells from the cluster of wells are periodically, or intermittently, operated, or are operated from time to time, and the production or associated quantities to be optimised and optionally constrained are evaluated, for example averaged, over fixed periods of time larger than that characteristic of the periodicity or intermittent operation .
16. The method of claim 15, wherein one or more of the wells from the cluster of wells are periodically, or intermittently, operated, or are operated from time to time, and the duration of its operation, as a proportion of a fixed period of time, is taken a manipulated variable for the well .
17. The method of any one of claims 1-13, wherein of the method is applied additionally to an optimisation target defined on wells in the well cluster with two or more subsurface inflow zones, in which case, "zone production estimation models" and "zone production prediction models" are generated in addition to the "well production estimation models" and "well production prediction models".
18. The method of Claim 1, whereby the well production variables, such as pressure and/or other fluid flow characteristics of the individual well effluent streams include one or more of the following variables : well tubing head pressure, well flowline pressure, well tubing head temperature, well flowline temperature, differential pressures across well production choke valve, differential pressures across any differential pressure producer, including a wet gas venturi, on the well flowline, flow meters, nominally suitable only for single phase flow, which are suitable to be used to provide an input to the well estimation models even if the well has multiphase flow, well production choke valve opening state or position, opening state or position of any means of reversible and controlled closing in and opening up of the well, well lift-gas injection rate, well jet pump hydraulic fluid injection rate, well production casing pressure, well electrical submersible pump (ESP) speed, well ESP pump intake pressure, well ESP down hole pump discharge pressure, well ESP down hole venturi differential pressure, well ESP power consumption, well ESP motor phase current, well rod pump motor power input, well rod pump motor speed, well rod pump stroke displacement, well rod pump load cell, beam pump gear box shaft position, well rod pump differential speed / motor/gear box slip, well downhole tubing pressure, well downhole annulus pressure, well downhole tubing or annulus temperature , or various derivations thereof monitored by distributed temperature sensors, well downhole interval control valve opening, amplitude of a selection of sound frequencies from one or more sound sensors mounted on well flowline, propagation delay of correlated sound patterns at a selection of frequencies from two or more sound sensors mounted in an upstream- downstream direction on a well flowline.
PCT/EP2007/053348 2006-04-07 2007-04-05 Method for optimising the production of a cluster of wells WO2007116008A1 (en)

Priority Applications (9)

Application Number Priority Date Filing Date Title
DE602007002702T DE602007002702D1 (en) 2006-04-07 2007-04-05 PROCESS FOR OPTIMIZING THE PRODUCTION OF A BORE ROLLING GROUP
AU2007235959A AU2007235959B2 (en) 2006-04-07 2007-04-05 Method for optimising the production of a cluster of wells
CA2645902A CA2645902C (en) 2006-04-07 2007-04-05 Method for optimising the production of a cluster of wells
BRPI0708835-3A BRPI0708835B1 (en) 2006-04-07 2007-04-05 METHOD TO OPTIMIZE PRODUCTION OF A GROUP OF WELLS
AT07727816T ATE445083T1 (en) 2006-04-07 2007-04-05 METHOD FOR OPTIMIZING THE GENERATION OF A BOREHOLE GROUP
EP07727816A EP2004953B1 (en) 2006-04-07 2007-04-05 Method for optimising the production of a cluster of wells
EA200802116A EA200802116A1 (en) 2006-04-07 2007-04-05 METHOD OF OPTIMIZING A PRODUCTION FROM A WANPET BAR
NZ571278A NZ571278A (en) 2006-04-07 2007-04-05 Method for optimising the production of a cluster of wells
NO20084606A NO341307B1 (en) 2006-04-07 2008-10-30 Procedure for optimizing production from a group of wells

Applications Claiming Priority (4)

Application Number Priority Date Filing Date Title
EP06112401 2006-04-07
EP06112401.2 2006-04-07
EP06112440 2006-04-10
EP06112440.0 2006-04-10

Publications (1)

Publication Number Publication Date
WO2007116008A1 true WO2007116008A1 (en) 2007-10-18

Family

ID=38110150

Family Applications (1)

Application Number Title Priority Date Filing Date
PCT/EP2007/053348 WO2007116008A1 (en) 2006-04-07 2007-04-05 Method for optimising the production of a cluster of wells

Country Status (10)

Country Link
EP (1) EP2004953B1 (en)
AT (1) ATE445083T1 (en)
AU (1) AU2007235959B2 (en)
BR (1) BRPI0708835B1 (en)
CA (1) CA2645902C (en)
DE (1) DE602007002702D1 (en)
EA (1) EA200802116A1 (en)
NO (1) NO341307B1 (en)
NZ (1) NZ571278A (en)
WO (1) WO2007116008A1 (en)

Cited By (38)

* Cited by examiner, † Cited by third party
Publication number Priority date Publication date Assignee Title
US8204693B2 (en) 2007-08-17 2012-06-19 Shell Oil Company Method for virtual metering of injection wells and allocation and control of multi-zonal injection wells
US8265915B2 (en) 2007-08-24 2012-09-11 Exxonmobil Upstream Research Company Method for predicting well reliability by computer simulation
WO2012134327A1 (en) * 2011-03-29 2012-10-04 Общество С Ограниченной Ответственностью "Дискрит" Well operating method
US8290632B2 (en) 2007-08-17 2012-10-16 Shell Oil Company Method for controlling production and downhole pressures of a well with multiple subsurface zones and/or branches
US8423337B2 (en) 2007-08-24 2013-04-16 Exxonmobil Upstream Research Company Method for multi-scale geomechanical model analysis by computer simulation
US8548782B2 (en) 2007-08-24 2013-10-01 Exxonmobil Upstream Research Company Method for modeling deformation in subsurface strata
WO2014096356A1 (en) * 2012-12-21 2014-06-26 Cappelen Skovholt As Method for separating substances mixed in fluids from oil wells
US8768672B2 (en) 2007-08-24 2014-07-01 ExxonMobil. Upstream Research Company Method for predicting time-lapse seismic timeshifts by computer simulation
WO2014207568A3 (en) * 2013-06-28 2015-04-23 Sitepp Sistemas Y Tecnología Para El Petróleo, S.A. De C.V. System and method for enhancing the production levels of wells
US9058445B2 (en) 2010-07-29 2015-06-16 Exxonmobil Upstream Research Company Method and system for reservoir modeling
US9058446B2 (en) 2010-09-20 2015-06-16 Exxonmobil Upstream Research Company Flexible and adaptive formulations for complex reservoir simulations
US9128693B2 (en) 2007-11-10 2015-09-08 Landmark Graphics Corporation Systems and methods for workflow automation, adaptation and integration
US9134454B2 (en) 2010-04-30 2015-09-15 Exxonmobil Upstream Research Company Method and system for finite volume simulation of flow
US9187984B2 (en) 2010-07-29 2015-11-17 Exxonmobil Upstream Research Company Methods and systems for machine-learning based simulation of flow
US9260947B2 (en) 2009-11-30 2016-02-16 Exxonmobil Upstream Research Company Adaptive Newton's method for reservoir simulation
WO2016046455A1 (en) * 2014-09-25 2016-03-31 Total S.A. Production of hydrocarbons with test separator
WO2016046454A1 (en) * 2014-09-25 2016-03-31 Total S.A. Production of hydrocarbons with metric counter
US9489176B2 (en) 2011-09-15 2016-11-08 Exxonmobil Upstream Research Company Optimized matrix and vector operations in instruction limited algorithms that perform EOS calculations
US9754056B2 (en) 2010-06-29 2017-09-05 Exxonmobil Upstream Research Company Method and system for parallel simulation models
US9957781B2 (en) 2014-03-31 2018-05-01 Hitachi, Ltd. Oil and gas rig data aggregation and modeling system
US10012059B2 (en) 2014-08-21 2018-07-03 Exxonmobil Upstream Research Company Gas lift optimization employing data obtained from surface mounted sensors
US10036829B2 (en) 2012-09-28 2018-07-31 Exxonmobil Upstream Research Company Fault removal in geological models
US10087721B2 (en) 2010-07-29 2018-10-02 Exxonmobil Upstream Research Company Methods and systems for machine—learning based simulation of flow
US10101194B2 (en) 2015-12-31 2018-10-16 General Electric Company System and method for identifying and recovering from a temporary sensor failure
WO2019060227A1 (en) * 2017-09-22 2019-03-28 General Electric Company System and method for determining production from a plurality of wells
US10319143B2 (en) 2014-07-30 2019-06-11 Exxonmobil Upstream Research Company Volumetric grid generation in a domain with heterogeneous material properties
US10364655B2 (en) 2017-01-20 2019-07-30 Saudi Arabian Oil Company Automatic control of production and injection wells in a hydrocarbon field
WO2019147986A1 (en) * 2018-01-26 2019-08-01 Ge Inspection Technologies, Lp Determination of virtual process parameters
US10401207B2 (en) 2016-09-14 2019-09-03 GE Oil & Gas UK, Ltd. Method for assessing and managing sensor uncertainties in a virtual flow meter
WO2020154468A1 (en) * 2019-01-25 2020-07-30 Ge Inspection Technologies, Lp Flow network model analysis
US10803534B2 (en) 2014-10-31 2020-10-13 Exxonmobil Upstream Research Company Handling domain discontinuity with the help of grid optimization techniques
US10839114B2 (en) 2016-12-23 2020-11-17 Exxonmobil Upstream Research Company Method and system for stable and efficient reservoir simulation using stability proxies
US11041976B2 (en) 2017-05-30 2021-06-22 Exxonmobil Upstream Research Company Method and system for creating and using a subsurface model in hydrocarbon operations
CN113153281A (en) * 2021-03-29 2021-07-23 中国地质大学(北京) Optimization model for realizing offshore platform oil-gas well collaborative production
CN113898323A (en) * 2020-06-22 2022-01-07 中国石油化工股份有限公司 Offshore oil and gas field underwater production system and design method thereof
US11409023B2 (en) 2014-10-31 2022-08-09 Exxonmobil Upstream Research Company Methods to handle discontinuity in constructing design space using moving least squares
WO2023154808A1 (en) * 2022-02-09 2023-08-17 Schlumberger Technology Corporation Integrated asset modeling for energy consumption and emission
US11940318B2 (en) 2016-09-27 2024-03-26 Baker Hughes Energy Technology UK Limited Method for detection and isolation of faulty sensors

Families Citing this family (5)

* Cited by examiner, † Cited by third party
Publication number Priority date Publication date Assignee Title
US9702243B2 (en) 2013-10-04 2017-07-11 Baker Hughes Incorporated Systems and methods for monitoring temperature using a magnetostrictive probe
US11180976B2 (en) 2018-12-21 2021-11-23 Exxonmobil Upstream Research Company Method and system for unconventional gas lift optimization
US11591936B2 (en) 2019-09-04 2023-02-28 Saudi Arabian Oil Company Systems and methods for proactive operation of process facilities based on historical operations data
KR102599305B1 (en) * 2021-09-15 2023-11-07 광성지엠(주) Test method for esp and tubing monitoring system reflecting production conditions and obstacle elements in oil and gas wells(esp mapping and surging)
KR102599460B1 (en) * 2021-09-15 2023-11-07 광성지엠(주) Test method for esp and tubing monitoring system reflecting production conditions and obstacle elements in oil and gas wells(tubing leakage)

Citations (2)

* Cited by examiner, † Cited by third party
Publication number Priority date Publication date Assignee Title
WO2002029195A2 (en) * 2000-10-04 2002-04-11 Sofitech N.V. Production optimization for multilayer commingled reservoirs
US6434435B1 (en) * 1997-02-21 2002-08-13 Baker Hughes Incorporated Application of adaptive object-oriented optimization software to an automatic optimization oilfield hydrocarbon production management system

Patent Citations (2)

* Cited by examiner, † Cited by third party
Publication number Priority date Publication date Assignee Title
US6434435B1 (en) * 1997-02-21 2002-08-13 Baker Hughes Incorporated Application of adaptive object-oriented optimization software to an automatic optimization oilfield hydrocarbon production management system
WO2002029195A2 (en) * 2000-10-04 2002-04-11 Sofitech N.V. Production optimization for multilayer commingled reservoirs

Non-Patent Citations (5)

* Cited by examiner, † Cited by third party
Title
CHRISTIAN OBERWINKLER ET AL: "From Real Time Data to Production Optimization", SPE 87008, August 2005 (2005-08-01), pages 229 - 239, XP002393968 *
MAHMUT SENGUL ET AL: "Applied Production Optimization: i-Field", SPE 77608, 29 September 2002 (2002-09-29), pages 1 - 12, XP002393969 *
MOCHIZUKI ET AL: "Real Time Optimization: Classification and Assessment", SPE 90213, 26 September 2004 (2004-09-26), pages 1 - 14, XP002393967 *
SAPUTELLI ET AL: "Promoting Real-Time Optimization of Hydrocarbon Producing Systems", SPE 83978, 2 September 2003 (2003-09-02), pages 1 - 9, XP002393965 *
T. UNNELAND ET AL: "Real-Time Asset Management: From Vision to Engagement-An Operator's Experience", SPE 96390, 9 October 2005 (2005-10-09), pages 1 - 10, XP002393966 *

Cited By (50)

* Cited by examiner, † Cited by third party
Publication number Priority date Publication date Assignee Title
US8204693B2 (en) 2007-08-17 2012-06-19 Shell Oil Company Method for virtual metering of injection wells and allocation and control of multi-zonal injection wells
US8290632B2 (en) 2007-08-17 2012-10-16 Shell Oil Company Method for controlling production and downhole pressures of a well with multiple subsurface zones and/or branches
US8265915B2 (en) 2007-08-24 2012-09-11 Exxonmobil Upstream Research Company Method for predicting well reliability by computer simulation
US8423337B2 (en) 2007-08-24 2013-04-16 Exxonmobil Upstream Research Company Method for multi-scale geomechanical model analysis by computer simulation
US8548782B2 (en) 2007-08-24 2013-10-01 Exxonmobil Upstream Research Company Method for modeling deformation in subsurface strata
US8768672B2 (en) 2007-08-24 2014-07-01 ExxonMobil. Upstream Research Company Method for predicting time-lapse seismic timeshifts by computer simulation
US9164194B2 (en) 2007-08-24 2015-10-20 Sheng-Yuan Hsu Method for modeling deformation in subsurface strata
US9128693B2 (en) 2007-11-10 2015-09-08 Landmark Graphics Corporation Systems and methods for workflow automation, adaptation and integration
US9260947B2 (en) 2009-11-30 2016-02-16 Exxonmobil Upstream Research Company Adaptive Newton's method for reservoir simulation
US9134454B2 (en) 2010-04-30 2015-09-15 Exxonmobil Upstream Research Company Method and system for finite volume simulation of flow
US9754056B2 (en) 2010-06-29 2017-09-05 Exxonmobil Upstream Research Company Method and system for parallel simulation models
US9187984B2 (en) 2010-07-29 2015-11-17 Exxonmobil Upstream Research Company Methods and systems for machine-learning based simulation of flow
US9058445B2 (en) 2010-07-29 2015-06-16 Exxonmobil Upstream Research Company Method and system for reservoir modeling
US10087721B2 (en) 2010-07-29 2018-10-02 Exxonmobil Upstream Research Company Methods and systems for machine—learning based simulation of flow
US9058446B2 (en) 2010-09-20 2015-06-16 Exxonmobil Upstream Research Company Flexible and adaptive formulations for complex reservoir simulations
WO2012134327A1 (en) * 2011-03-29 2012-10-04 Общество С Ограниченной Ответственностью "Дискрит" Well operating method
US9489176B2 (en) 2011-09-15 2016-11-08 Exxonmobil Upstream Research Company Optimized matrix and vector operations in instruction limited algorithms that perform EOS calculations
US10036829B2 (en) 2012-09-28 2018-07-31 Exxonmobil Upstream Research Company Fault removal in geological models
GB2523523A (en) * 2012-12-21 2015-08-26 Seabed Separation As Method for separating substances mixed in fluids from oil wells
WO2014096356A1 (en) * 2012-12-21 2014-06-26 Cappelen Skovholt As Method for separating substances mixed in fluids from oil wells
US9827509B2 (en) 2012-12-21 2017-11-28 Seabed Separation As Method for separating substances mixed in fluids from oil wells
US9952603B2 (en) 2013-06-28 2018-04-24 Sitepp Sistemas Y Technologia Para El Petroleo, S.A. De C.V. System and method for enhancing the production level of wells
WO2014207568A3 (en) * 2013-06-28 2015-04-23 Sitepp Sistemas Y Tecnología Para El Petróleo, S.A. De C.V. System and method for enhancing the production levels of wells
US9957781B2 (en) 2014-03-31 2018-05-01 Hitachi, Ltd. Oil and gas rig data aggregation and modeling system
US10202826B2 (en) 2014-03-31 2019-02-12 Hitachi, Ltd. Automatic method of generating decision cubes from cross dependent data sets
US10319143B2 (en) 2014-07-30 2019-06-11 Exxonmobil Upstream Research Company Volumetric grid generation in a domain with heterogeneous material properties
US10012059B2 (en) 2014-08-21 2018-07-03 Exxonmobil Upstream Research Company Gas lift optimization employing data obtained from surface mounted sensors
WO2016046454A1 (en) * 2014-09-25 2016-03-31 Total S.A. Production of hydrocarbons with metric counter
WO2016046455A1 (en) * 2014-09-25 2016-03-31 Total S.A. Production of hydrocarbons with test separator
US10989039B2 (en) 2014-09-25 2021-04-27 Total Se Production of hydrocarbons with test separator
US20170275981A1 (en) * 2014-09-25 2017-09-28 Total S.A. Production of hydrocarbons with test separator
EA036893B1 (en) * 2014-09-25 2021-01-12 Тоталь С.А. Production of hydrocarbons with test separator
EA038623B1 (en) * 2014-09-25 2021-09-23 Тоталь С.А. Production of hydrocarbons with metric counter
US10393561B2 (en) 2014-09-25 2019-08-27 Total S.A. Production of hydrocarbons with metric counter
US11409023B2 (en) 2014-10-31 2022-08-09 Exxonmobil Upstream Research Company Methods to handle discontinuity in constructing design space using moving least squares
US10803534B2 (en) 2014-10-31 2020-10-13 Exxonmobil Upstream Research Company Handling domain discontinuity with the help of grid optimization techniques
US10101194B2 (en) 2015-12-31 2018-10-16 General Electric Company System and method for identifying and recovering from a temporary sensor failure
US10401207B2 (en) 2016-09-14 2019-09-03 GE Oil & Gas UK, Ltd. Method for assessing and managing sensor uncertainties in a virtual flow meter
US11940318B2 (en) 2016-09-27 2024-03-26 Baker Hughes Energy Technology UK Limited Method for detection and isolation of faulty sensors
US10839114B2 (en) 2016-12-23 2020-11-17 Exxonmobil Upstream Research Company Method and system for stable and efficient reservoir simulation using stability proxies
US10364655B2 (en) 2017-01-20 2019-07-30 Saudi Arabian Oil Company Automatic control of production and injection wells in a hydrocarbon field
US11041976B2 (en) 2017-05-30 2021-06-22 Exxonmobil Upstream Research Company Method and system for creating and using a subsurface model in hydrocarbon operations
WO2019060227A1 (en) * 2017-09-22 2019-03-28 General Electric Company System and method for determining production from a plurality of wells
CN111971637A (en) * 2018-01-26 2020-11-20 威盖特技术美国有限合伙人公司 Determination of virtual process parameters
WO2019147986A1 (en) * 2018-01-26 2019-08-01 Ge Inspection Technologies, Lp Determination of virtual process parameters
WO2020154468A1 (en) * 2019-01-25 2020-07-30 Ge Inspection Technologies, Lp Flow network model analysis
CN113898323A (en) * 2020-06-22 2022-01-07 中国石油化工股份有限公司 Offshore oil and gas field underwater production system and design method thereof
CN113898323B (en) * 2020-06-22 2024-02-23 中国石油化工股份有限公司 Marine oil and gas field underwater production system and design method thereof
CN113153281A (en) * 2021-03-29 2021-07-23 中国地质大学(北京) Optimization model for realizing offshore platform oil-gas well collaborative production
WO2023154808A1 (en) * 2022-02-09 2023-08-17 Schlumberger Technology Corporation Integrated asset modeling for energy consumption and emission

Also Published As

Publication number Publication date
EP2004953B1 (en) 2009-10-07
ATE445083T1 (en) 2009-10-15
EA200802116A1 (en) 2009-04-28
NO20084606L (en) 2008-10-30
BRPI0708835B1 (en) 2017-09-26
NO341307B1 (en) 2017-10-02
DE602007002702D1 (en) 2009-11-19
AU2007235959A1 (en) 2007-10-18
CA2645902A1 (en) 2007-10-18
CA2645902C (en) 2014-05-20
BRPI0708835A2 (en) 2011-06-14
EP2004953A1 (en) 2008-12-24
NZ571278A (en) 2011-08-26
AU2007235959B2 (en) 2010-11-11

Similar Documents

Publication Publication Date Title
CA2645902C (en) Method for optimising the production of a cluster of wells
US8290632B2 (en) Method for controlling production and downhole pressures of a well with multiple subsurface zones and/or branches
CA2645253C (en) Method for production metering of oil wells
AU2008290584B2 (en) Method for virtual metering of injection wells and allocation and control of multi-zonal injection wells
US8670966B2 (en) Methods and systems for performing oilfield production operations
US8818777B2 (en) System and method for performing oilfield simulation operations
Saputelli et al. Self-learning reservoir management
CN101415905A (en) Method for optimising the production of a cluster of wells
US7474969B2 (en) Method and system for production metering of oil wells
EP3339565B1 (en) Systems and methods for assessing production and/or injection system startup
Gutierrez et al. A new approach to gas lift optimization using an integrated asset model
Goh et al. Production surveillance and optimization with data driven models
Bieker Topics in offshore oil production optimization using real-time data
CA2671367A1 (en) A method for performing oilfield production operations
RU2754408C1 (en) Distributed system and method for measuring flow rates of multiphase and/or multicomponent fluids extracted from oil and gas wells
US20230313647A1 (en) Methods to dynamically control fluid flow in a multi-well system, methods to dynamically provide real-time status of fluid flow in a multi-well system, and multi-well fluid flow control systems

Legal Events

Date Code Title Description
121 Ep: the epo has been informed by wipo that ep was designated in this application

Ref document number: 07727816

Country of ref document: EP

Kind code of ref document: A1

DPE1 Request for preliminary examination filed after expiration of 19th month from priority date (pct application filed from 20040101)
WWE Wipo information: entry into national phase

Ref document number: 2007727816

Country of ref document: EP

WWE Wipo information: entry into national phase

Ref document number: 2645902

Country of ref document: CA

WWE Wipo information: entry into national phase

Ref document number: 571278

Country of ref document: NZ

WWE Wipo information: entry into national phase

Ref document number: 2007235959

Country of ref document: AU

WWE Wipo information: entry into national phase

Ref document number: 12008502248

Country of ref document: PH

Ref document number: 5353/CHENP/2008

Country of ref document: IN

WWE Wipo information: entry into national phase

Ref document number: 200780012532.5

Country of ref document: CN

NENP Non-entry into the national phase

Ref country code: DE

ENP Entry into the national phase

Ref document number: 2007235959

Country of ref document: AU

Date of ref document: 20070405

Kind code of ref document: A

WWE Wipo information: entry into national phase

Ref document number: 200802116

Country of ref document: EA

ENP Entry into the national phase

Ref document number: PI0708835

Country of ref document: BR

Kind code of ref document: A2

Effective date: 20080930