US20190324069A1 - Scaffold system - Google Patents

Scaffold system Download PDF

Info

Publication number
US20190324069A1
US20190324069A1 US16/458,281 US201916458281A US2019324069A1 US 20190324069 A1 US20190324069 A1 US 20190324069A1 US 201916458281 A US201916458281 A US 201916458281A US 2019324069 A1 US2019324069 A1 US 2019324069A1
Authority
US
United States
Prior art keywords
wall mount
height
secured
bar
post
Prior art date
Legal status (The legal status is an assumption and is not a legal conclusion. Google has not performed a legal analysis and makes no representation as to the accuracy of the status listed.)
Abandoned
Application number
US16/458,281
Inventor
George R. Gardner
Edmund P. Gasiecki
Current Assignee (The listed assignees may be inaccurate. Google has not performed a legal analysis and makes no representation or warranty as to the accuracy of the list.)
International Chimney Corp
Original Assignee
International Chimney Corp
Priority date (The priority date is an assumption and is not a legal conclusion. Google has not performed a legal analysis and makes no representation as to the accuracy of the date listed.)
Filing date
Publication date
Application filed by International Chimney Corp filed Critical International Chimney Corp
Priority to US16/458,281 priority Critical patent/US20190324069A1/en
Publication of US20190324069A1 publication Critical patent/US20190324069A1/en
Abandoned legal-status Critical Current

Links

Images

Classifications

    • GPHYSICS
    • G01MEASURING; TESTING
    • G01RMEASURING ELECTRIC VARIABLES; MEASURING MAGNETIC VARIABLES
    • G01R21/00Arrangements for measuring electric power or power factor
    • G01R21/133Arrangements for measuring electric power or power factor by using digital technique
    • EFIXED CONSTRUCTIONS
    • E04BUILDING
    • E04GSCAFFOLDING; FORMS; SHUTTERING; BUILDING IMPLEMENTS OR AIDS, OR THEIR USE; HANDLING BUILDING MATERIALS ON THE SITE; REPAIRING, BREAKING-UP OR OTHER WORK ON EXISTING BUILDINGS
    • E04G3/00Scaffolds essentially supported by building constructions, e.g. adjustable in height
    • E04G3/28Mobile scaffolds; Scaffolds with mobile platforms
    • EFIXED CONSTRUCTIONS
    • E04BUILDING
    • E04GSCAFFOLDING; FORMS; SHUTTERING; BUILDING IMPLEMENTS OR AIDS, OR THEIR USE; HANDLING BUILDING MATERIALS ON THE SITE; REPAIRING, BREAKING-UP OR OTHER WORK ON EXISTING BUILDINGS
    • E04G3/00Scaffolds essentially supported by building constructions, e.g. adjustable in height
    • E04G3/20Scaffolds essentially supported by building constructions, e.g. adjustable in height supported by walls
    • EFIXED CONSTRUCTIONS
    • E04BUILDING
    • E04GSCAFFOLDING; FORMS; SHUTTERING; BUILDING IMPLEMENTS OR AIDS, OR THEIR USE; HANDLING BUILDING MATERIALS ON THE SITE; REPAIRING, BREAKING-UP OR OTHER WORK ON EXISTING BUILDINGS
    • E04G3/00Scaffolds essentially supported by building constructions, e.g. adjustable in height
    • E04G3/24Scaffolds essentially supported by building constructions, e.g. adjustable in height specially adapted for particular parts of buildings or for buildings of particular shape, e.g. chimney stacks or pylons
    • E04G3/246Scaffolds essentially supported by building constructions, e.g. adjustable in height specially adapted for particular parts of buildings or for buildings of particular shape, e.g. chimney stacks or pylons following the inside contour of a building
    • EFIXED CONSTRUCTIONS
    • E04BUILDING
    • E04GSCAFFOLDING; FORMS; SHUTTERING; BUILDING IMPLEMENTS OR AIDS, OR THEIR USE; HANDLING BUILDING MATERIALS ON THE SITE; REPAIRING, BREAKING-UP OR OTHER WORK ON EXISTING BUILDINGS
    • E04G5/00Component parts or accessories for scaffolds
    • E04G5/06Consoles; Brackets
    • GPHYSICS
    • G06COMPUTING; CALCULATING OR COUNTING
    • G06FELECTRIC DIGITAL DATA PROCESSING
    • G06F1/00Details not covered by groups G06F3/00 - G06F13/00 and G06F21/00
    • G06F1/26Power supply means, e.g. regulation thereof
    • G06F1/32Means for saving power
    • G06F1/3203Power management, i.e. event-based initiation of a power-saving mode
    • G06F1/3206Monitoring of events, devices or parameters that trigger a change in power modality
    • G06F1/3231Monitoring the presence, absence or movement of users
    • GPHYSICS
    • G06COMPUTING; CALCULATING OR COUNTING
    • G06FELECTRIC DIGITAL DATA PROCESSING
    • G06F1/00Details not covered by groups G06F3/00 - G06F13/00 and G06F21/00
    • G06F1/26Power supply means, e.g. regulation thereof
    • G06F1/32Means for saving power
    • G06F1/3203Power management, i.e. event-based initiation of a power-saving mode
    • G06F1/3234Power saving characterised by the action undertaken
    • G06F1/325Power saving in peripheral device
    • G06F1/3265Power saving in display device
    • EFIXED CONSTRUCTIONS
    • E04BUILDING
    • E04GSCAFFOLDING; FORMS; SHUTTERING; BUILDING IMPLEMENTS OR AIDS, OR THEIR USE; HANDLING BUILDING MATERIALS ON THE SITE; REPAIRING, BREAKING-UP OR OTHER WORK ON EXISTING BUILDINGS
    • E04G3/00Scaffolds essentially supported by building constructions, e.g. adjustable in height
    • E04G3/28Mobile scaffolds; Scaffolds with mobile platforms
    • E04G2003/286Mobile scaffolds; Scaffolds with mobile platforms mobile vertically
    • HELECTRICITY
    • H04ELECTRIC COMMUNICATION TECHNIQUE
    • H04WWIRELESS COMMUNICATION NETWORKS
    • H04W4/00Services specially adapted for wireless communication networks; Facilities therefor
    • H04W4/02Services making use of location information
    • H04W4/025Services making use of location information using location based information parameters
    • H04W4/027Services making use of location information using location based information parameters using movement velocity, acceleration information
    • YGENERAL TAGGING OF NEW TECHNOLOGICAL DEVELOPMENTS; GENERAL TAGGING OF CROSS-SECTIONAL TECHNOLOGIES SPANNING OVER SEVERAL SECTIONS OF THE IPC; TECHNICAL SUBJECTS COVERED BY FORMER USPC CROSS-REFERENCE ART COLLECTIONS [XRACs] AND DIGESTS
    • Y02TECHNOLOGIES OR APPLICATIONS FOR MITIGATION OR ADAPTATION AGAINST CLIMATE CHANGE
    • Y02DCLIMATE CHANGE MITIGATION TECHNOLOGIES IN INFORMATION AND COMMUNICATION TECHNOLOGIES [ICT], I.E. INFORMATION AND COMMUNICATION TECHNOLOGIES AIMING AT THE REDUCTION OF THEIR OWN ENERGY USE
    • Y02D10/00Energy efficient computing, e.g. low power processors, power management or thermal management
    • YGENERAL TAGGING OF NEW TECHNOLOGICAL DEVELOPMENTS; GENERAL TAGGING OF CROSS-SECTIONAL TECHNOLOGIES SPANNING OVER SEVERAL SECTIONS OF THE IPC; TECHNICAL SUBJECTS COVERED BY FORMER USPC CROSS-REFERENCE ART COLLECTIONS [XRACs] AND DIGESTS
    • Y02TECHNOLOGIES OR APPLICATIONS FOR MITIGATION OR ADAPTATION AGAINST CLIMATE CHANGE
    • Y02DCLIMATE CHANGE MITIGATION TECHNOLOGIES IN INFORMATION AND COMMUNICATION TECHNOLOGIES [ICT], I.E. INFORMATION AND COMMUNICATION TECHNOLOGIES AIMING AT THE REDUCTION OF THEIR OWN ENERGY USE
    • Y02D30/00Reducing energy consumption in communication networks
    • Y02D30/50Reducing energy consumption in communication networks in wire-line communication networks, e.g. low power modes or reduced link rate

Definitions

  • the invention broadly relates to scaffold systems, more specifically to a height adjustable scaffold system, and even more particularly to a height adjustable scaffold system adapted to be repositionable throughout its range of use along the full height of a structure.
  • Scaffold systems are often assembled as static structures.
  • ground based scaffolds and scaffolds securely affixed to the side of a structure are commonly used for construction and demolition work.
  • Such structures must be at least partially disassembled in order to be moved to a different location, e.g., height, or in the alternatively, additionally elements, e.g., frames, must be added to the original structure in order to increase the overall height. Changes of this type are time consuming and may require multiple people to assist with the process to ensure a safe transition.
  • forming extremely large scaffold structures requires a large number of frames and boards thereby increasing the cost of building the structure.
  • Some scaffold systems may be moved vertically through the use of complex pulley and motor systems.
  • window washing scaffolds are mounted from a crane like apparatus on the roof of a building via cables connecting the scaffold to the crane motor. The height of the scaffold is altered by activating the crane thereby causing the scaffold to raise or lower.
  • Such arrangements require the mounting of an additional apparatus, i.e., a crane, and further require clear paths for cables to extend from the crane to the scaffold.
  • Other systems use hydraulic cylinders to move a scaffold up or down. Hydraulic cylinders require a hydraulic power pack, and a hydraulic power pack is bulky and reduces the load capacity of the scaffold. Moreover, such power packs are electronically powered.
  • the present invention broadly comprises a scaffold system adapted for securing to a structure and for vertical movement relative to the structure.
  • the scaffold system includes first and second wall mounts, each of the wall mounts having a bar and at least one spring biasing the bar in a first direction, a slide post having a slide hook, a slide arm and a hanging pad secured to the slide arm, the slide post arranged for vertical axial movement within at least one of the first and second wall mounts, a main post having at least one post hook, a first deck fixedly secured to the main post, and a ball screw jack having a mounting plate and a lifting screw, the mounting plate secured to the first deck and the lifting screw secured to the hanging pad.
  • the main post is arranged to complementarily fit within slide post, the slide hook is adapted for releasable engagement with the first wall mount bar or the second wall mount bar and the at least one post hook is adapted for releasable engagement with the first wall mount bar or the second wall mount bar.
  • first wall mount is secured to the structure at a first height
  • second wall mount is secured to the structure at a second height elevationally lower than the first height
  • the slide hook is releasably engaged with the first wall mount bar.
  • first wall mount is secured to the structure at a first height
  • second wall mount is secured to the structure at a second height elevationally lower than the first height
  • the at least one post hook is releasably engaged with the second wall mount bar.
  • the first wall mount is secured to the structure at a first height
  • the second wall mount is secured to the structure at a second height elevationally lower than the first height
  • the slide hook is releasably engaged with the first wall mount bar
  • the at least one post hook is releasably engaged with the second wall mount bar.
  • the scaffold system further includes a third wall mount having a bar and at least one spring biasing the bar in a first direction, wherein the first wall mount is secured to the structure at a first height, the second wall mount is secured to the structure at a second height elevationally lower than the first height, the third wall mount is secured to the structure at a third height elevationally lower than the second height and the slide hook is releasably engaged with the first wall mount bar and the at least one post hook is releasably engaged with the third wall mount bar.
  • the scaffold system further includes a third wall mount having a bar and at least one spring biasing the bar in a first direction, wherein the first wall mount is secured to the structure at a first height, the second wall mount is secured to the structure at a second height elevationally lower than the first height, the third wall mount is secured to the structure at a third height elevationally higher than the first height and the slide hook is releasably engaged with the third wall mount bar and the at least one post hook is releasably engaged with the first wall mount bar or the second wall mount bar.
  • a third wall mount having a bar and at least one spring biasing the bar in a first direction
  • the scaffold system further includes at least one limit switch arranged to engage the hanging pad or the slide arm.
  • the scaffold system further includes a second deck positioned elevationally higher than the first deck.
  • the scaffold system further includes at least one safety lug secured to the structure and the first deck.
  • the present invention further broadly comprises a method of modifying the height of a scaffold system mounted on a structure.
  • the scaffold system includes first and second wall mounts, a slide post having a slide hook, a slide arm and a hanging pad secured to the slide arm, a main post having at least one post hook, a first deck fixedly secured to the main post, and a ball screw jack having a mounting plate and a lifting screw.
  • Each of the wall mounts includes a bar and at least one spring biasing the bar in a first direction
  • the slide post is arranged for vertical axial movement within at least one of the first and second wall mounts
  • the mounting plate is secured to the first deck
  • the lifting screw is secured to the hanging pad
  • the main post is arranged to complementarily fit within slide post
  • the slide hook is adapted for releasable engagement with the first wall mount bar or the second wall mount bar
  • the at least one post hook is adapted for releasable engagement with the first wall mount bar or the second wall mount bar.
  • the method includes: a) securing the first wall mount to the structure at a first height and securing the second wall mount to the structure at a second height elevationally lower than the first height; b) releasably engaging the at least one post hook with the second wall mount bar; c) releasably engaging the slide hook with the first wall mount bar; d) securing a third wall mount to the structure at a third height elevationally higher the first height, the third wall mount includes a bar and at least one spring biasing the bar in a first direction; e) energizing the ball screw jack, wherein the ball screw jack extends the lifting screw thereby increasing a vertical height of the slide post; f) releasably engaging the slide hook with the third wall mount bar; g) energizing the ball screw jack, wherein the ball screw jack retracts the lifting screw thereby increasing the vertical height of the main post; and, h) releasably engaging the at least one post hook with first wall
  • the present invention yet further broadly comprises a method of modifying the height of a scaffold system mounted on a structure.
  • the scaffold system includes first and second wall mounts, a slide post having a slide hook, a slide arm and a hanging pad secured to the slide arm, a main post having at least one post hook, a first deck fixedly secured to the main post, and a ball screw jack having a mounting plate and a lifting screw.
  • Each of the wall mounts includes a bar and at least one spring biasing the bar in a first direction
  • the slide post is arranged for vertical axial movement within at least one of the first and second wall mounts
  • the mounting plate is secured to the first deck
  • the lifting screw is secured to the hanging pad
  • the main post is arranged to complementarily fit within slide post
  • the slide hook is adapted for releasable engagement with the first wall mount bar or the second wall mount bar
  • the at least one post hook is adapted for releasable engagement with the first wall mount bar or the second wall mount bar.
  • the method includes: a) securing the first wall mount to the structure at a first height and securing the second wall mount to the structure at a second height elevationally lower than the first height; b) releasably engaging the at least one post hook with the second wall mount bar; c) releasably engaging the slide hook with the first wall mount bar; d) securing a third wall mount to the structure at a third height elevationally lower the second height, the third wall mount includes a bar and at least one spring biasing the bar in a first direction; e) energizing the ball screw jack, wherein the ball screw jack extends the lifting screw thereby decreasing a vertical height of the main post; f) releasably engaging the at least one post hook with the third wall mount bar; g) energizing the ball screw jack, wherein the ball screw jack retracts the lifting screw thereby decreasing the vertical height of the slide post; and, h) releasably engaging the slide hook with second wall
  • FIG. 1 is a perspective view of a structure, i.e., a chimney, having an embodiment of a present invention scaffold system secured thereto;
  • FIG. 2 is a side elevational view of an embodiment of a present invention scaffold system
  • FIG. 3 is a front elevational view of an embodiment of a present invention scaffold system
  • FIG. 4 is a top plan view of an embodiment of a wall mount
  • FIG. 5 is a front elevational view of the wall mount of FIG. 4 ;
  • FIG. 6 is a side elevational view of the wall mount of FIG. 4 ;
  • FIG. 7 is a top plan view of an embodiment of a main post within a slide post wherein the slide post is releasably secured to a wall mount;
  • FIG. 8 is a top plan view of the wall mount of FIG. 7 ;
  • FIG. 9 is a top plan view of the slide post of FIG. 7 ;
  • FIG. 10 is a top plan view of the main post of FIG. 7 ;
  • FIG. 11 is a side elevational view of an embodiment of a present invention scaffold system showing a ball screw jack in a retracted position;
  • FIG. 12 is a side elevational view of an embodiment of a present invention scaffold system showing a ball screw jack in an extended position;
  • FIG. 13 is a side elevational exploded view of the embodiment of the scaffold system shown in FIG. 12 ;
  • FIG. 14 is a side elevational view of an embodiment of a slide post
  • FIG. 15 is a top plan view of an embodiment of an upper deck having an access hole arranged therein.
  • FIG. 16 is a front elevational view of an embodiment of a present invention scaffold system including two adjacent scaffold systems connected by a folding walkway.
  • FIG. 1 shows a perspective view of an embodiment of the present invention scaffold system 10 mounted on chimney 12 .
  • the nature and mode of operation of scaffold 10 is best understood in view of FIG. 1 through 15 .
  • Scaffold system 10 is adapted for securing to structure 12 , e.g., a chimney, and for vertical movement relative to structure 12 .
  • Scaffold system 10 comprises first and second wall mounts 14 and 16 , respectively.
  • Each of wall mounts 14 and 16 comprise a bar, i.e., bars 14 a and 16 a, respectively, and at least one spring, i.e., springs 14 b and 16 b, respectively, which are arranged to bias the bar in a first direction, i.e., the direction depicted by uni-directional arrow 20 .
  • Scaffold system 10 further comprises slide post 22 comprising slide hook 24 , slide arm 26 and hanging pad 28 secured to slide arm 26 .
  • Slide post 22 is arranged for vertical axial movement within at least one of first and second wall mounts 14 and 16 , respectively.
  • Scaffold system 10 further comprises main post 30 comprising post hooks 32 and still yet further comprises first deck 34 fixedly secured to main post 30 .
  • Scaffold system 10 further comprises ball screw jack 36 comprising mounting plate 38 and lifting screw 40 .
  • Mounting plate 38 is secured to first deck 34 and lifting screw 40 is secured to hanging pad 28 .
  • Main post 30 is arranged to complementarily fit within slide post 22 .
  • Slide hook 24 is adapted for releasable engagement with first wall mount bar 14 a or second wall mount bar 16 a
  • post hooks 32 are adapted for releasable engagement with first wall mount bar 14 a or the second wall mount bar 16 a.
  • first wall mount 14 is secured to structure 12 at a first height, e.g., height 42
  • second wall mount 16 is secured to structure 12 at a second height elevationally lower than the first height, e.g., height 44 .
  • slide hook 24 is releasably engaged with first wall mount bar 14 a
  • one of post hooks 32 is releasably engaged with second wall mount bar 16 a
  • slide hook 24 is releasably engaged with first wall mount bar 14 a and one of post hooks 32 is releasably engaged with second wall mount bar 16 a.
  • ball screw jack 36 is a 10-ton ball screw jack.
  • the jack is powered with a 220 volt single phase motor, and is equipped with a brake and pendant cord with an up-and-down switch to control the scaffold movement. Existing power cords are utilized to energize ball screw jack 36 .
  • scaffold system 10 further comprises third wall mount 46 comprising a bar, i.e., bar 46 a, and at least one spring, i.e., springs 46 b.
  • Springs 46 b bias bar 46 a in a first direction, i.e., the direction depicted by uni-directional arrow 20 .
  • third wall mount 46 is secured to structure 12 at a third height elevationally lower than second height 44 , e.g., height 48 b.
  • slide hook 24 is releasably engaged with first wall mount bar 14 a and post hook 32 is releasably engaged with third wall mount bar 46 a. Additional embodiments are described below. For example, embodiments are set forth below where third wall mount 46 is secured to structure 12 at a third height elevational higher than first height 42 , e.g., height 48 a (as shown in FIG. 13 ).
  • scaffold system 10 further comprises at least one limit switch, e.g., limit switches 50 and 52 , arranged to engage hanging pad 28 when ball screw jack 36 is moving in a direction to retract lifting screw 40 or to engage slide arm 26 when ball screw jack 36 is moving in a direction to extend lifting screw 40 .
  • limit switches provide feedback to the system regarding the position of ball screw jack 36 , e.g., reaching its full extension or full retraction, thereby preventing damage to ball screw jack 36 and failure of scaffold system 10 by automatically stopping travel of the lifting mechanism.
  • a single limit switch may be used thereby detecting the position of ball screw jack 36 in a single location.
  • greater than two limit switches may be included thereby providing more detailed position information.
  • the limit switch or switches are an added safety factor which helps eliminate human error.
  • scaffold system 10 further comprises second deck 54 positioned elevationally higher than first deck 34 .
  • the arrangement of decks included with scaffold system 10 depends upon the needs of the user. For example, two levels may be needed, e.g., a first lower level for finish assembly work and a second upper level for preparation work.
  • more than two decks may also be included, e.g., three, and that the number of decks is limited by the structure of the scaffold and the size of the ball screw jack, e.g., 10-ton, 20-ton, etc., and such variations fall within the scope of the claims.
  • the upper working deck is eliminated from the scaffold when it is used as a demolition scaffold.
  • the main support tubes of scaffold system 10 have been modified to allow the upper deck to be added as required for different job specific requirements, such as repair work.
  • scaffold system 10 may include further safety features.
  • scaffold system 10 may comprise at least one safety lug, e.g., lug 56 , secured to structure 12 and first deck 34 .
  • Safety lug 56 is anchored into structure 12 .
  • Lug 56 is then connected to individual scaffold sections with a steel choker and secured to the scaffold with a safety shackle secured at the top working deck. Lug 56 helps ensure the scaffold sections are secured to structure 12 .
  • scaffold system 10 may include other safety equipment incorporated to maintain a safe working environment.
  • the scaffold system may be equipped with folding walkway 58 extending between adjacent scaffold systems (See FIG. 16 ), wherein the walkway minimizes or eliminates a tripping hazard as a user walks from one scaffold section to an adjacent scaffold section.
  • Such safety equipment is essential when the scaffold systems are moving up or down.
  • the scaffold system may include hand rails 60 , and at each open end of a deck, hand rails 60 may be equipped with a self-closing gate. The foregoing gates help secure the open ends of a deck thereby minimizing or eliminating fall hazards. The nature and mode of operation of such gates are well known to one having ordinary skill in the art.
  • First, second and third wall mounts 14 , 16 and 46 share a similar structural arrangement.
  • the structure of first wall mount 14 is described in detail herein. As each wall mount is configured in the same fashion, the description herein is applicable second and third wall mounts 16 and 46 , respectively.
  • Wall mount 14 comprises mounting plate 62 and side plates 64 extending therefrom. Side plates 64 comprise flanges 66 .
  • Springs 14 b extend between flanges 66 and mount bar 14 a. Springs 14 b bias mount bar 14 a in the direction of uni-directional arrow 20 , thereby biasing mount bar 14 a away from mounting plate 62 . As mount bar 14 a is actuated towards mounting plate 62 , a load is applied to springs 14 b.
  • mount bar 14 a After removal of the load, springs 14 b return mount bar 14 a to its rest position.
  • a load is applied to mount bar 14 a during each instance of a hook, e.g., slide hook 24 and post hooks 32 , passing by mount bar 14 a.
  • a load in order to release a hook from a mount bar so that slide post 22 or main post 30 may pass by the mount bar, a load must be applied to mount bar 14 a in a direction opposite than uni-directional arrow 20 , for example, by an operator.
  • Slide post 22 and main post 30 are arranged in a nested relationship.
  • the nested arrangement is described herein.
  • main post 30 is positioned partially within opening 68 and moves vertically within opening 68 and slot 70 . Embodiments using the foregoing arrangement are set forth herebelow.
  • first wall mount 14 is secured to structure 12 at height 42 and second wall mount 16 is secured to structure 12 at height 44 .
  • Post hook 32 is releasably engaged with second wall mount bar 16 a
  • slide hook 24 is releasably engaged with first wall mount bar 14 a.
  • third wall mount 46 is secured to structure 12 at height 48 a, i.e., elevationally higher than first height 42 (as shown in FIG. 13 ).
  • ball screw jack 36 is energized causing ball screw jack 36 to extend lifting screw 40 thereby increasing the vertical height of slide post 22 .
  • the actuation of ball screw jack 36 releasably engaged slide hook 24 with third wall mount bar 46 a.
  • ball screw jack 36 is energized causing ball screw jack 36 to retract lifting screw 40 thereby increasing the vertical height of main post 30 .
  • the actuation of ball screw jack 36 releasably engaged post hook 32 with first wall mount bar 14 a.
  • scaffold system 10 may be used to move down a structure.
  • the following describes the steps of moving the scaffold in a downward direction. Similar to the method described above, first wall mount 14 is secured to structure 12 at height 42 and second wall mount 16 is secured to structure 12 at height 44 .
  • Post hook 32 is releasably engaged with second wall mount bar 16 a, while slide hook 24 is releasably engaged with first wall mount bar 14 a.
  • third wall mount 46 is secured to structure 12 at height 48 b, i.e., elevationally lower than second height 44 .
  • ball screw jack 36 is energized causing ball screw jack 36 to extend lifting screw 40 thereby decreasing the vertical height of main post 30 .
  • ball screw jack 36 releasably engages post hook 32 with third wall mount bar 46 a.
  • ball screw jack 36 is energized causing ball screw jack 36 to retract lifting screw 40 thereby decreasing the vertical height of slide post 22 .
  • the actuation of ball screw jack 36 releasably engaged slide hook 24 with second wall mount bar 16 a.
  • main post 30 may include elevations marked at various increments, e.g., six inch increments, which assist in keeping the entire system, i.e., multiple adjacent scaffold systems 10 , at the same elevations. Moreover, such markings provide an operator feedback regarding how much travel remains on lifting screw 40 . Still further, in an embodiment, the lower work deck, which is used to operate scaffold system 10 , is modified to allow access from an exterior elevator and ladder system. Even yet further, in an embodiment, scaffold system 10 may be fitted with a separate hoist to transport equipment and materials to the work area.

Landscapes

  • Engineering & Computer Science (AREA)
  • Architecture (AREA)
  • Mechanical Engineering (AREA)
  • Civil Engineering (AREA)
  • Structural Engineering (AREA)
  • Movable Scaffolding (AREA)
  • Theoretical Computer Science (AREA)
  • Physics & Mathematics (AREA)
  • General Physics & Mathematics (AREA)
  • General Engineering & Computer Science (AREA)
  • Power Engineering (AREA)

Abstract

A scaffold system adapted for securing to a structure and for vertical movement relative to the structure, including first and second wall mounts, each of the wall mounts having a bar and a spring biasing the bar in a first direction, a slide post having a slide hook, a slide arm and a hanging pad secured to the slide arm, the slide post arranged for vertical axial movement within at least one of the first and second wall mounts, a main post having at least one post hook, a first deck fixedly secured to the main post, and a ball screw jack having a mounting plate and a lifting screw, the mounting plate secured to the first deck and the lifting screw secured to the hanging pad. The main post is arranged to complementarily fit within slide post.

Description

    CROSS-REFERENCE TO RELATED APPLICATIONS
  • This application is filed under 35 U.S.C. § 120 as a continuation of U.S. Non-Provisional Patent Application No. 14/143,148, filed on Dec. 30, 2013, which application is incorporated herein in its entirety.
  • FIELD
  • The invention broadly relates to scaffold systems, more specifically to a height adjustable scaffold system, and even more particularly to a height adjustable scaffold system adapted to be repositionable throughout its range of use along the full height of a structure.
  • BACKGROUND
  • Scaffold systems are often assembled as static structures. For example, ground based scaffolds and scaffolds securely affixed to the side of a structure are commonly used for construction and demolition work. Such structures must be at least partially disassembled in order to be moved to a different location, e.g., height, or in the alternatively, additionally elements, e.g., frames, must be added to the original structure in order to increase the overall height. Changes of this type are time consuming and may require multiple people to assist with the process to ensure a safe transition. Moreover, forming extremely large scaffold structures requires a large number of frames and boards thereby increasing the cost of building the structure.
  • Some scaffold systems may be moved vertically through the use of complex pulley and motor systems. For example, window washing scaffolds are mounted from a crane like apparatus on the roof of a building via cables connecting the scaffold to the crane motor. The height of the scaffold is altered by activating the crane thereby causing the scaffold to raise or lower. Such arrangements require the mounting of an additional apparatus, i.e., a crane, and further require clear paths for cables to extend from the crane to the scaffold. Other systems use hydraulic cylinders to move a scaffold up or down. Hydraulic cylinders require a hydraulic power pack, and a hydraulic power pack is bulky and reduces the load capacity of the scaffold. Moreover, such power packs are electronically powered.
  • As can be derived from the variety of devices and methods directed to securing a scaffold and subsequently altering its position, many means have been contemplated to accomplish the desired end, i.e., safe, controlled movement a scaffold. Heretofore, tradeoffs between complexity, cost and range of motion were required. Thus, there is a long-felt need for a scaffold that minimizes the number of components needed to alter the position of the scaffold while maintaining the necessary safety of the structure.
  • SUMMARY
  • The present invention broadly comprises a scaffold system adapted for securing to a structure and for vertical movement relative to the structure. The scaffold system includes first and second wall mounts, each of the wall mounts having a bar and at least one spring biasing the bar in a first direction, a slide post having a slide hook, a slide arm and a hanging pad secured to the slide arm, the slide post arranged for vertical axial movement within at least one of the first and second wall mounts, a main post having at least one post hook, a first deck fixedly secured to the main post, and a ball screw jack having a mounting plate and a lifting screw, the mounting plate secured to the first deck and the lifting screw secured to the hanging pad. The main post is arranged to complementarily fit within slide post, the slide hook is adapted for releasable engagement with the first wall mount bar or the second wall mount bar and the at least one post hook is adapted for releasable engagement with the first wall mount bar or the second wall mount bar.
  • In an embodiment, the first wall mount is secured to the structure at a first height, the second wall mount is secured to the structure at a second height elevationally lower than the first height and the slide hook is releasably engaged with the first wall mount bar. In an embodiment, the first wall mount is secured to the structure at a first height, the second wall mount is secured to the structure at a second height elevationally lower than the first height and the at least one post hook is releasably engaged with the second wall mount bar. In an embodiment, the first wall mount is secured to the structure at a first height, the second wall mount is secured to the structure at a second height elevationally lower than the first height, the slide hook is releasably engaged with the first wall mount bar and the at least one post hook is releasably engaged with the second wall mount bar.
  • In an embodiment, the scaffold system further includes a third wall mount having a bar and at least one spring biasing the bar in a first direction, wherein the first wall mount is secured to the structure at a first height, the second wall mount is secured to the structure at a second height elevationally lower than the first height, the third wall mount is secured to the structure at a third height elevationally lower than the second height and the slide hook is releasably engaged with the first wall mount bar and the at least one post hook is releasably engaged with the third wall mount bar. In an embodiment, the scaffold system further includes a third wall mount having a bar and at least one spring biasing the bar in a first direction, wherein the first wall mount is secured to the structure at a first height, the second wall mount is secured to the structure at a second height elevationally lower than the first height, the third wall mount is secured to the structure at a third height elevationally higher than the first height and the slide hook is releasably engaged with the third wall mount bar and the at least one post hook is releasably engaged with the first wall mount bar or the second wall mount bar.
  • In an embodiment, the scaffold system further includes at least one limit switch arranged to engage the hanging pad or the slide arm. In an embodiment, the scaffold system further includes a second deck positioned elevationally higher than the first deck. In an embodiment, the scaffold system further includes at least one safety lug secured to the structure and the first deck.
  • The present invention further broadly comprises a method of modifying the height of a scaffold system mounted on a structure. The scaffold system includes first and second wall mounts, a slide post having a slide hook, a slide arm and a hanging pad secured to the slide arm, a main post having at least one post hook, a first deck fixedly secured to the main post, and a ball screw jack having a mounting plate and a lifting screw. Each of the wall mounts includes a bar and at least one spring biasing the bar in a first direction, the slide post is arranged for vertical axial movement within at least one of the first and second wall mounts, the mounting plate is secured to the first deck, the lifting screw is secured to the hanging pad, the main post is arranged to complementarily fit within slide post, the slide hook is adapted for releasable engagement with the first wall mount bar or the second wall mount bar and the at least one post hook is adapted for releasable engagement with the first wall mount bar or the second wall mount bar. The method includes: a) securing the first wall mount to the structure at a first height and securing the second wall mount to the structure at a second height elevationally lower than the first height; b) releasably engaging the at least one post hook with the second wall mount bar; c) releasably engaging the slide hook with the first wall mount bar; d) securing a third wall mount to the structure at a third height elevationally higher the first height, the third wall mount includes a bar and at least one spring biasing the bar in a first direction; e) energizing the ball screw jack, wherein the ball screw jack extends the lifting screw thereby increasing a vertical height of the slide post; f) releasably engaging the slide hook with the third wall mount bar; g) energizing the ball screw jack, wherein the ball screw jack retracts the lifting screw thereby increasing the vertical height of the main post; and, h) releasably engaging the at least one post hook with first wall mount bar.
  • The present invention yet further broadly comprises a method of modifying the height of a scaffold system mounted on a structure. The scaffold system includes first and second wall mounts, a slide post having a slide hook, a slide arm and a hanging pad secured to the slide arm, a main post having at least one post hook, a first deck fixedly secured to the main post, and a ball screw jack having a mounting plate and a lifting screw. Each of the wall mounts includes a bar and at least one spring biasing the bar in a first direction, the slide post is arranged for vertical axial movement within at least one of the first and second wall mounts, the mounting plate is secured to the first deck, the lifting screw is secured to the hanging pad, the main post is arranged to complementarily fit within slide post, the slide hook is adapted for releasable engagement with the first wall mount bar or the second wall mount bar and the at least one post hook is adapted for releasable engagement with the first wall mount bar or the second wall mount bar. The method includes: a) securing the first wall mount to the structure at a first height and securing the second wall mount to the structure at a second height elevationally lower than the first height; b) releasably engaging the at least one post hook with the second wall mount bar; c) releasably engaging the slide hook with the first wall mount bar; d) securing a third wall mount to the structure at a third height elevationally lower the second height, the third wall mount includes a bar and at least one spring biasing the bar in a first direction; e) energizing the ball screw jack, wherein the ball screw jack extends the lifting screw thereby decreasing a vertical height of the main post; f) releasably engaging the at least one post hook with the third wall mount bar; g) energizing the ball screw jack, wherein the ball screw jack retracts the lifting screw thereby decreasing the vertical height of the slide post; and, h) releasably engaging the slide hook with second wall mount bar.
  • It is a general object of the present invention to provide a moveable scaffold which can alter its vertical position along an entire height of a structure without the need for excessive materials or cost.
  • It is another general object of the present invention to maintain safety while modifying the position of a scaffold system.
  • These and other objects and advantages of the present invention will be readily appreciable from the following description of preferred embodiments of the invention and from the accompanying drawings and claims.
  • BRIEF DESCRIPTION OF THE DRAWINGS
  • The nature and mode of operation of the present invention will now be more fully described in the following detailed description of the invention taken with the accompanying drawing figures, in which:
  • FIG. 1 is a perspective view of a structure, i.e., a chimney, having an embodiment of a present invention scaffold system secured thereto;
  • FIG. 2 is a side elevational view of an embodiment of a present invention scaffold system;
  • FIG. 3 is a front elevational view of an embodiment of a present invention scaffold system;
  • FIG. 4 is a top plan view of an embodiment of a wall mount;
  • FIG. 5 is a front elevational view of the wall mount of FIG. 4;
  • FIG. 6 is a side elevational view of the wall mount of FIG. 4;
  • FIG. 7 is a top plan view of an embodiment of a main post within a slide post wherein the slide post is releasably secured to a wall mount;
  • FIG. 8 is a top plan view of the wall mount of FIG. 7;
  • FIG. 9 is a top plan view of the slide post of FIG. 7;
  • FIG. 10 is a top plan view of the main post of FIG. 7;
  • FIG. 11 is a side elevational view of an embodiment of a present invention scaffold system showing a ball screw jack in a retracted position;
  • FIG. 12 is a side elevational view of an embodiment of a present invention scaffold system showing a ball screw jack in an extended position;
  • FIG. 13 is a side elevational exploded view of the embodiment of the scaffold system shown in FIG. 12;
  • FIG. 14 is a side elevational view of an embodiment of a slide post;
  • FIG. 15 is a top plan view of an embodiment of an upper deck having an access hole arranged therein; and,
  • FIG. 16 is a front elevational view of an embodiment of a present invention scaffold system including two adjacent scaffold systems connected by a folding walkway.
  • DETAILED DESCRIPTION
  • At the outset, it should be appreciated that like drawing numbers on different drawing views identify identical, or functionally similar, structural elements of the invention. While the present invention is described with respect to what is presently considered to be the preferred aspects, it is to be understood that the invention as claimed is not limited to the disclosed aspects.
  • Furthermore, it is understood that this invention is not limited to the particular methodology, materials and modifications described and as such may, of course, vary. It is also understood that the terminology used herein is for the purpose of describing particular aspects only, and is not intended to limit the scope of the present invention, which is limited only by the appended claims.
  • Unless defined otherwise, all technical and scientific terms used herein have the same meaning as commonly understood to one of ordinary skill in the art to which this invention belongs. Although any methods, devices or materials similar or equivalent to those described herein can be used in the practice or testing of the invention, the preferred methods, devices, and materials are now described.
  • Adverting now to the figures, FIG. 1 shows a perspective view of an embodiment of the present invention scaffold system 10 mounted on chimney 12. The nature and mode of operation of scaffold 10 is best understood in view of FIG. 1 through 15.
  • Scaffold system 10 is adapted for securing to structure 12, e.g., a chimney, and for vertical movement relative to structure 12. Scaffold system 10 comprises first and second wall mounts 14 and 16, respectively. Each of wall mounts 14 and 16 comprise a bar, i.e., bars 14 a and 16 a, respectively, and at least one spring, i.e., springs 14 b and 16 b, respectively, which are arranged to bias the bar in a first direction, i.e., the direction depicted by uni-directional arrow 20. Scaffold system 10 further comprises slide post 22 comprising slide hook 24, slide arm 26 and hanging pad 28 secured to slide arm 26. Slide post 22 is arranged for vertical axial movement within at least one of first and second wall mounts 14 and 16, respectively. Scaffold system 10 further comprises main post 30 comprising post hooks 32 and still yet further comprises first deck 34 fixedly secured to main post 30. Scaffold system 10 further comprises ball screw jack 36 comprising mounting plate 38 and lifting screw 40. Mounting plate 38 is secured to first deck 34 and lifting screw 40 is secured to hanging pad 28. Main post 30 is arranged to complementarily fit within slide post 22. Slide hook 24 is adapted for releasable engagement with first wall mount bar 14 a or second wall mount bar 16 a, while post hooks 32 are adapted for releasable engagement with first wall mount bar 14 a or the second wall mount bar 16 a.
  • In an embodiment, first wall mount 14 is secured to structure 12 at a first height, e.g., height 42, and second wall mount 16 is secured to structure 12 at a second height elevationally lower than the first height, e.g., height 44. In an embodiment, slide hook 24 is releasably engaged with first wall mount bar 14 a, while in another embodiment, one of post hooks 32 is releasably engaged with second wall mount bar 16 a, and in yet another embodiment, slide hook 24 is releasably engaged with first wall mount bar 14 a and one of post hooks 32 is releasably engaged with second wall mount bar 16 a.
  • In an embodiment, ball screw jack 36 is a 10-ton ball screw jack. The jack is powered with a 220 volt single phase motor, and is equipped with a brake and pendant cord with an up-and-down switch to control the scaffold movement. Existing power cords are utilized to energize ball screw jack 36.
  • In an embodiment, scaffold system 10 further comprises third wall mount 46 comprising a bar, i.e., bar 46 a, and at least one spring, i.e., springs 46 b. Springs 46 b bias bar 46 a in a first direction, i.e., the direction depicted by uni-directional arrow 20. In an embodiment, third wall mount 46 is secured to structure 12 at a third height elevationally lower than second height 44, e.g., height 48 b. In an embodiment, slide hook 24 is releasably engaged with first wall mount bar 14 a and post hook 32 is releasably engaged with third wall mount bar 46 a. Additional embodiments are described below. For example, embodiments are set forth below where third wall mount 46 is secured to structure 12 at a third height elevational higher than first height 42, e.g., height 48 a (as shown in FIG. 13).
  • In an embodiment, scaffold system 10 further comprises at least one limit switch, e.g., limit switches 50 and 52, arranged to engage hanging pad 28 when ball screw jack 36 is moving in a direction to retract lifting screw 40 or to engage slide arm 26 when ball screw jack 36 is moving in a direction to extend lifting screw 40. In view of the foregoing, it should be appreciated that limit switches provide feedback to the system regarding the position of ball screw jack 36, e.g., reaching its full extension or full retraction, thereby preventing damage to ball screw jack 36 and failure of scaffold system 10 by automatically stopping travel of the lifting mechanism. It should be further appreciated that a single limit switch may be used thereby detecting the position of ball screw jack 36 in a single location. Moreover, greater than two limit switches may be included thereby providing more detailed position information. The limit switch or switches are an added safety factor which helps eliminate human error.
  • In an embodiment, scaffold system 10 further comprises second deck 54 positioned elevationally higher than first deck 34. The arrangement of decks included with scaffold system 10 depends upon the needs of the user. For example, two levels may be needed, e.g., a first lower level for finish assembly work and a second upper level for preparation work. One of ordinary skill in the art will appreciate that more than two decks may also be included, e.g., three, and that the number of decks is limited by the structure of the scaffold and the size of the ball screw jack, e.g., 10-ton, 20-ton, etc., and such variations fall within the scope of the claims. In an embodiment, the upper working deck is eliminated from the scaffold when it is used as a demolition scaffold. The main support tubes of scaffold system 10 have been modified to allow the upper deck to be added as required for different job specific requirements, such as repair work.
  • As safety is critical with such structures, e.g., scaffolds may be mounted hundreds of feet above the ground, scaffold system 10 may include further safety features. For example, scaffold system 10 may comprise at least one safety lug, e.g., lug 56, secured to structure 12 and first deck 34. Safety lug 56 is anchored into structure 12. Lug 56 is then connected to individual scaffold sections with a steel choker and secured to the scaffold with a safety shackle secured at the top working deck. Lug 56 helps ensure the scaffold sections are secured to structure 12.
  • Furthermore, scaffold system 10 may include other safety equipment incorporated to maintain a safe working environment. In an embodiment, the scaffold system may be equipped with folding walkway 58 extending between adjacent scaffold systems (See FIG. 16), wherein the walkway minimizes or eliminates a tripping hazard as a user walks from one scaffold section to an adjacent scaffold section. Such safety equipment is essential when the scaffold systems are moving up or down. Moreover, the scaffold system may include hand rails 60, and at each open end of a deck, hand rails 60 may be equipped with a self-closing gate. The foregoing gates help secure the open ends of a deck thereby minimizing or eliminating fall hazards. The nature and mode of operation of such gates are well known to one having ordinary skill in the art.
  • First, second and third wall mounts 14, 16 and 46, respectively, share a similar structural arrangement. The structure of first wall mount 14 is described in detail herein. As each wall mount is configured in the same fashion, the description herein is applicable second and third wall mounts 16 and 46, respectively. Wall mount 14 comprises mounting plate 62 and side plates 64 extending therefrom. Side plates 64 comprise flanges 66. Springs 14 b extend between flanges 66 and mount bar 14 a. Springs 14 b bias mount bar 14 a in the direction of uni-directional arrow 20, thereby biasing mount bar 14 a away from mounting plate 62. As mount bar 14 a is actuated towards mounting plate 62, a load is applied to springs 14 b. After removal of the load, springs 14 b return mount bar 14 a to its rest position. In view of the foregoing, it should be appreciated that a load is applied to mount bar 14 a during each instance of a hook, e.g., slide hook 24 and post hooks 32, passing by mount bar 14 a. Moreover, in order to release a hook from a mount bar so that slide post 22 or main post 30 may pass by the mount bar, a load must be applied to mount bar 14 a in a direction opposite than uni-directional arrow 20, for example, by an operator.
  • Slide post 22 and main post 30 are arranged in a nested relationship. The nested arrangement is described herein. In order to permit the free movement of slide post 22 relative to main post 30, main post 30 is positioned partially within opening 68 and moves vertically within opening 68 and slot 70. Embodiments using the foregoing arrangement are set forth herebelow.
  • The nature of the operation of the present invention scaffold system will now be more fully explained. The operation differs depending upon the direction of movement, i.e., upwardly or downwardly. First, upward movement of scaffold system 10 is discussed.
  • In order to move scaffold system 10 upwardly, first wall mount 14 is secured to structure 12 at height 42 and second wall mount 16 is secured to structure 12 at height 44. Post hook 32 is releasably engaged with second wall mount bar 16 a, while slide hook 24 is releasably engaged with first wall mount bar 14 a. Next, third wall mount 46 is secured to structure 12 at height 48 a, i.e., elevationally higher than first height 42 (as shown in FIG. 13). Then, ball screw jack 36 is energized causing ball screw jack 36 to extend lifting screw 40 thereby increasing the vertical height of slide post 22. The actuation of ball screw jack 36 releasably engaged slide hook 24 with third wall mount bar 46 a. Next, ball screw jack 36 is energized causing ball screw jack 36 to retract lifting screw 40 thereby increasing the vertical height of main post 30. The actuation of ball screw jack 36 releasably engaged post hook 32 with first wall mount bar 14 a.
  • Alternatively, scaffold system 10 may be used to move down a structure. The following describes the steps of moving the scaffold in a downward direction. Similar to the method described above, first wall mount 14 is secured to structure 12 at height 42 and second wall mount 16 is secured to structure 12 at height 44. Post hook 32 is releasably engaged with second wall mount bar 16 a, while slide hook 24 is releasably engaged with first wall mount bar 14 a. Next, third wall mount 46 is secured to structure 12 at height 48 b, i.e., elevationally lower than second height 44. Then, ball screw jack 36 is energized causing ball screw jack 36 to extend lifting screw 40 thereby decreasing the vertical height of main post 30. The actuation of ball screw jack 36 releasably engages post hook 32 with third wall mount bar 46 a. Next, ball screw jack 36 is energized causing ball screw jack 36 to retract lifting screw 40 thereby decreasing the vertical height of slide post 22. The actuation of ball screw jack 36 releasably engaged slide hook 24 with second wall mount bar 16 a.
  • The present invention includes other features which increase its safety, utility and effectiveness. For example, main post 30 may include elevations marked at various increments, e.g., six inch increments, which assist in keeping the entire system, i.e., multiple adjacent scaffold systems 10, at the same elevations. Moreover, such markings provide an operator feedback regarding how much travel remains on lifting screw 40. Still further, in an embodiment, the lower work deck, which is used to operate scaffold system 10, is modified to allow access from an exterior elevator and ladder system. Even yet further, in an embodiment, scaffold system 10 may be fitted with a separate hoist to transport equipment and materials to the work area.
  • Thus, it is seen that the objects of the present invention are efficiently obtained, although modifications and changes to the invention should be readily apparent to those having ordinary skill in the art, which modifications are intended to be within the spirit and scope of the invention as claimed. It also is understood that the foregoing description is illustrative of the present invention and should not be considered as limiting. Therefore, other embodiments of the present invention are possible without departing from the spirit and scope of the present invention.

Claims (9)

What I claim is:
1. A scaffold system adapted for securing to a structure and for vertical movement relative to the structure, the scaffold system comprising:
first and second wall mounts, each of the wall mounts comprising a bar and at least one spring biasing the bar in a first direction;
a slide post comprising a slide hook, a slide arm and a hanging pad secured to the slide arm, the slide post arranged for vertical axial movement within at least one of the first and second wall mounts;
a main post comprising at least one post hook;
a first deck fixedly secured to the main post; and,
a ball screw jack comprising a mounting plate and a lifting screw, the mounting plate secured to the first deck and the lifting screw secured to the hanging pad, wherein the main post is arranged to complementarily fit within the slide post, the slide hook is adapted for releasable engagement with the first wall mount bar or the second wall mount bar and the at least one post hook is adapted for releasable engagement with the first wall mount bar or the second wall mount bar.
2. The scaffold system of claim 1, wherein the first wall mount is secured to the structure at a first height, the second wall mount is secured to the structure at a second height elevationally lower than the first height and the slide hook is releasably engaged with the first wall mount bar.
3. The scaffold system of claim 1, wherein the first wall mount is secured to the structure at a first height, the second wall mount is secured to the structure at a second height elevationally lower than the first height and the at least one post hook is releasably engaged with the second wall mount bar.
4. The scaffold system of claim 1, wherein the first wall mount is secured to the structure at a first height, the second wall mount is secured to the structure at a second height elevationally lower than the first height, the slide hook is releasably engaged with the first wall mount bar and the at least one post hook is releasably engaged with the second wall mount bar.
5. The scaffold system of claim 1, further comprising a third wall mount comprising a bar and at least one spring biasing the bar in a first direction, wherein the first wall mount is secured to the structure at a first height, the second wall mount is secured to the structure at a second height elevationally lower than the first height, the third wall mount is secured to the structure at a third height elevationally lower than the second height and the slide hook is releasably engaged with the first wall mount bar and the at least one post hook is releasably engaged with the third wall mount bar.
6. The scaffold system of claim 1, further comprising a third wall mount comprising a bar and at least one spring biasing the bar in a first direction, wherein the first wall mount is secured to the structure at a first height, the second wall mount is secured to the structure at a second height elevationally lower than the first height, the third wall mount is secured to the structure at a third height elevationally higher than the first height and the slide hook is releasably engaged with the third wall mount bar and the at least one post hook is releasably engaged with the first wall mount bar or the second wall mount bar.
7. The scaffold system of claim 1, further comprising at least one limit switch arranged to engage the hanging pad or the slide arm.
8. The scaffold system of claim 1, further comprising a second deck positioned elevationally higher than the first deck.
9. The scaffold system of claim 1, further comprising at least one safety lug secured to the structure and the first deck.
US16/458,281 2013-12-30 2019-07-01 Scaffold system Abandoned US20190324069A1 (en)

Priority Applications (1)

Application Number Priority Date Filing Date Title
US16/458,281 US20190324069A1 (en) 2013-12-30 2019-07-01 Scaffold system

Applications Claiming Priority (2)

Application Number Priority Date Filing Date Title
US14/143,148 US10428536B2 (en) 2013-12-30 2013-12-30 Scaffold system
US16/458,281 US20190324069A1 (en) 2013-12-30 2019-07-01 Scaffold system

Related Parent Applications (1)

Application Number Title Priority Date Filing Date
US14/143,149 Continuation US9995773B2 (en) 2011-01-14 2013-12-30 Dynamic DC-offset determination for proximity sensing

Publications (1)

Publication Number Publication Date
US20190324069A1 true US20190324069A1 (en) 2019-10-24

Family

ID=53481112

Family Applications (2)

Application Number Title Priority Date Filing Date
US14/143,148 Active 2034-11-29 US10428536B2 (en) 2013-12-30 2013-12-30 Scaffold system
US16/458,281 Abandoned US20190324069A1 (en) 2013-12-30 2019-07-01 Scaffold system

Family Applications Before (1)

Application Number Title Priority Date Filing Date
US14/143,148 Active 2034-11-29 US10428536B2 (en) 2013-12-30 2013-12-30 Scaffold system

Country Status (2)

Country Link
US (2) US10428536B2 (en)
CA (1) CA2838259C (en)

Families Citing this family (26)

* Cited by examiner, † Cited by third party
Publication number Priority date Publication date Assignee Title
SE538828C2 (en) * 2013-08-15 2016-12-20 Incoform Ab Concrete form for forming a wall or the like and a method for forming a said wall or the like and a support
US10428536B2 (en) * 2013-12-30 2019-10-01 International Chimney Corporation Scaffold system
PL3212862T3 (en) * 2014-10-31 2020-01-31 Soletanche Freyssinet Method for manufacturing concrete construction blocks for a wind-turbine tower and associated system
PT3034870T (en) * 2014-12-15 2022-09-13 Nordex Energy Spain S A Wind turbine with concrete tower and assembly process of wind turbine with concrete tower
CN104947927B (en) * 2015-07-05 2017-01-18 张冬梅 Automatic hanging basket
ITUB20154872A1 (en) * 2015-10-27 2017-04-27 Despe S P A Climbing system and method for building construction
DE102016205956A1 (en) * 2016-04-08 2017-10-12 Peri Gmbh Self-climbing system, self-climbing unit and method for implementing such a self-climbing unit on a concrete structure
DE102016125549A1 (en) * 2016-12-23 2018-06-28 Tries Gmbh & Co. Kg Climbing device with a climbing rail
US20180179767A1 (en) 2016-12-28 2018-06-28 Curt Wylde Scaffold extensions
WO2018140477A1 (en) * 2017-01-25 2018-08-02 Bechtel Oil, Gas And Chemicals, Inc. Scaffolding system for use with curvilinear walls and method of use
EP3388379A1 (en) * 2017-04-10 2018-10-17 KONE Corporation Elevator arrangement and method
DE102017109839A1 (en) * 2017-05-08 2018-12-20 Kewazo Gmbh Scaffold transport system, method for controlling a scaffold transport system and use of a scaffold transport system
EP3425136B1 (en) * 2017-07-05 2020-02-26 Alimak Group Management AB Transportation systems, elevator systems, kits, tower sections and methods for performing assembly or maintenance operations in towers
CN107190975B (en) * 2017-07-14 2018-11-23 四川华西集团有限公司 Construction of super highrise building integrates form frame system
CN107299755A (en) * 2017-07-14 2017-10-27 四川华西集团有限公司 The hydraulic lifting steel platform of outer mould bases and the overall and local jacking of steel platform can be achieved
CN107654059A (en) * 2017-08-31 2018-02-02 上海宝冶集团有限公司 For the mobile operating platform constructed in elevator hoistway
DE102018117727A1 (en) * 2018-07-23 2020-01-23 Peri Gmbh LIFT DRIVE FOR A RAILWAY CLIMBING SYSTEM
CN109469309A (en) * 2018-11-28 2019-03-15 中国建筑第七工程局有限公司 A kind of multi-functional construction operation platform for vertical hoistway
CN109853926B (en) * 2018-12-20 2021-07-13 青岛中建联合集团有限公司 Construction protection device for external wall panel of prefabricated building
CN109704213A (en) * 2019-01-28 2019-05-03 江苏久和机械有限公司 Stable, efficient, high-quality wall-attaching equipment
CN110306776B (en) * 2019-06-25 2020-05-29 湖北勇胜建设工程有限公司 Lifting platform for high-rise building elevator shaft construction
US11655641B2 (en) * 2019-12-29 2023-05-23 The Third Construction Co., Ltd Of China Construction Third Engneering Bureau Construction building equipment and construction method thereof
CN111576840B (en) * 2020-04-21 2021-08-13 中国建筑第八工程局有限公司 Wall attaching device for climbing equipment and climbing method thereof
CN111764626B (en) * 2020-06-05 2022-05-20 中船澄西船舶修造有限公司 Cantilever type scaffold
CN112663844B (en) * 2021-01-22 2022-03-29 广东长海建设工程有限公司 Green building engineering curtain wall construction support and use method thereof
CN114892945A (en) * 2022-06-09 2022-08-12 山东方圆建筑材料有限公司 Elevator shaft operation protection platform and installation method

Citations (10)

* Cited by examiner, † Cited by third party
Publication number Priority date Publication date Assignee Title
US4040774A (en) * 1976-04-29 1977-08-09 Research-Cottrel, Inc. Apparatus for constructing concrete walls
US4709899A (en) * 1985-10-28 1987-12-01 Shimizu Construction Co., Ltd. Climbing formwork apparatus for concrete placing
US4962828A (en) * 1989-02-21 1990-10-16 Duncan Charles W Debris net/scaffolding frame lifting system
US6557817B2 (en) * 2000-01-18 2003-05-06 Wilian Holding Company Wall climbing form hoist
US20070119116A1 (en) * 2003-11-27 2007-05-31 Alberto Arozena Bergaretxe Climbing system for shuttering, scaffolding and loads in general
US20120247870A1 (en) * 2011-03-29 2012-10-04 Iturbe Beristain Eneko Perimetric protection system for buildings undergoing construction
US8708100B2 (en) * 2005-06-29 2014-04-29 Peri Gmbh Rail-guided climbing system
US9175487B2 (en) * 2010-03-05 2015-11-03 Ulma C Y E, S.Coop Self-climbing perimetric protection system for construction works in buildings
US9297173B2 (en) * 2008-01-22 2016-03-29 Dayton Superior Corporation Jump form system
US10428536B2 (en) * 2013-12-30 2019-10-01 International Chimney Corporation Scaffold system

Family Cites Families (51)

* Cited by examiner, † Cited by third party
Publication number Priority date Publication date Assignee Title
FR340379A (en) * 1904-02-11 1904-07-05 Theodor Macharaceck scaffolding
US898368A (en) * 1908-08-10 1908-09-08 George E Humphries Scaffolding.
US2673711A (en) 1951-10-29 1954-03-30 Clifford L Lutton Lift assembly for mounting on scaffolding
US2718378A (en) 1951-10-29 1955-09-20 Clifford L Lutton Material lift assembly for scaffold
US2762659A (en) * 1953-03-16 1956-09-11 Harlan Campbell Allen Extensible scaffold
DE1116378B (en) * 1956-01-17 1961-11-02 Bernhard Schwarz Console frame
US2893786A (en) * 1956-02-10 1959-07-07 Faye Louis Bracket type scaffolding, adjustable in height, slidingly, for concrete wall erection
US2882100A (en) * 1956-10-24 1959-04-14 Morton L Bank Jack device for lifting fixtures and the like
US3148857A (en) * 1963-06-06 1964-09-15 Ralph W Hutchison Staging bracket
US3371551A (en) * 1966-09-01 1968-03-05 Duff Norton Co Nut and screw mechanism
US4078633A (en) * 1976-02-09 1978-03-14 Fahy Michael B Modular staging with platform jacks
US4157129A (en) * 1978-04-26 1979-06-05 Christopher Gordon W Stabbing board assembly
US4275797A (en) 1979-04-27 1981-06-30 Johnson Raymond R Scaffolding power attachment
DE2921636C2 (en) * 1979-05-28 1982-09-09 Hünnebeck GmbH, 4030 Ratingen Device with lifting device for climbing on a wall
US4276957A (en) * 1980-01-08 1981-07-07 Kilgore H Lee Portable scaffold assembly with movable anchor
FR2487410A1 (en) * 1980-07-24 1982-01-29 Bouygues Sa Climbing shutter for casting concrete wall - has single jack to raise brackets retaining shutter sections on shoes detachably fixed to wall
GB2112440A (en) * 1981-10-29 1983-07-20 Acrow Scaffolding
US4476958A (en) 1982-09-07 1984-10-16 Lawrence Stafford Safety device for scaffold
US4498556A (en) * 1982-09-11 1985-02-12 Access Engineering Ltd. Vertically movable, road towable work platform
GB8408346D0 (en) * 1984-03-30 1984-05-10 Airlec Vehicles Ltd Mobile lift loaders
DE8702952U1 (en) * 1987-02-26 1987-09-10 Hauser, Juergen, 7960 Aulendorf, De
US4817759A (en) * 1988-04-20 1989-04-04 Marv Galyardt Access platform for sliding glass windows
US5099953A (en) 1990-07-06 1992-03-31 Staghorn Products Foldable scaffold
DE9106022U1 (en) 1991-05-15 1991-07-25 Oesterreichische Doka Schalungstechnik Ges.M.B.H., Amstetten, At
EP0594720A1 (en) 1991-07-15 1994-05-04 O'KANE, Kevin John Anchorage device
US5152369A (en) 1991-09-10 1992-10-06 Mori Nakaoka Apparatus and method for hoisting a platform adjacent a scaffolding
US5505318A (en) * 1994-01-24 1996-04-09 Advanced Micro Devices, Inc. Collapsible rack
US5579866A (en) 1994-07-08 1996-12-03 Sky Climber, Inc. Suspended access platform
TW253924B (en) 1994-09-14 1995-08-11 Nippon Kotetsu Kokusai Kk Elevatable work facility
JP3454290B2 (en) 1994-10-26 2003-10-06 株式会社フジタ Jack device for pushing up large structures
US5810114A (en) 1997-03-04 1998-09-22 Wcm Development Company, Llc Scaffolding
US6220391B1 (en) 1997-03-04 2001-04-24 Wcm Development Company Scaffolding structure
US5909783A (en) 1997-05-28 1999-06-08 Quality Steel Products, Inc. Motorized scaffold hoisting apparatus
SE9801065D0 (en) 1998-03-27 1998-03-27 Alimak Ab Device for rack-operated elevators, construction platforms or the like
JP2000001984A (en) 1998-06-12 2000-01-07 Kumagai Gumi Co Ltd Automatic elevation type form and footing device for construction of high structure, and construction method using same
US6431316B1 (en) 1999-07-13 2002-08-13 Timothy Benson Bothwell Scaffold plank and method of making the same
US7090053B2 (en) 1999-07-13 2006-08-15 Bothwell Enterprises, Inc. Scaffold plank with end connector and method of making the same
US6443262B1 (en) 1999-12-30 2002-09-03 Waco International Corporation Tubular frame scaffolding
CA2313513C (en) * 2000-07-06 2008-10-14 Michel Philippe Scaffolding
US6883642B2 (en) 2001-09-17 2005-04-26 Larry Matty Method of ladder-supported scaffold erection, and ladder bracing and scaffolding system for use therewith
US7140467B2 (en) * 2004-04-29 2006-11-28 Aluminum Ladder Co Bulk material transport vehicle access structure
US7857097B2 (en) * 2004-11-10 2010-12-28 Patrick Evinger Scaffolding apparatus and method
US20060163001A1 (en) * 2005-01-24 2006-07-27 Pozell Charles A Wall hanging scaffold
US20070000724A1 (en) 2005-06-29 2007-01-04 Sky Climber Llc Self-erecting suspension platform system
US8302735B2 (en) 2005-06-29 2012-11-06 Sky Climber, Llc Self-erecting suspension platform system
US20070278041A1 (en) 2006-05-31 2007-12-06 Sonny Scaffolds, Inc. Quick-connect/disconnect guardrail scaffolding system and method
DE102006026201B4 (en) * 2006-06-06 2008-04-10 Doka Industrie Gmbh Self Climbing System
US20120312940A1 (en) * 2006-12-21 2012-12-13 Xavier Julliard Mobile anchoring and fall prevention device
US20080179477A1 (en) 2007-01-31 2008-07-31 Regency Innovations, Llc Scaffolding securement system
US8757320B2 (en) * 2011-09-29 2014-06-24 Fu-Chang Liao Suspending and moving device
US9016025B2 (en) * 2012-06-11 2015-04-28 Zhejiang Construction Engineering Group Co., Ltd Constructing method for concrete cylinder of construction steel bar of high-rise steel structure

Patent Citations (10)

* Cited by examiner, † Cited by third party
Publication number Priority date Publication date Assignee Title
US4040774A (en) * 1976-04-29 1977-08-09 Research-Cottrel, Inc. Apparatus for constructing concrete walls
US4709899A (en) * 1985-10-28 1987-12-01 Shimizu Construction Co., Ltd. Climbing formwork apparatus for concrete placing
US4962828A (en) * 1989-02-21 1990-10-16 Duncan Charles W Debris net/scaffolding frame lifting system
US6557817B2 (en) * 2000-01-18 2003-05-06 Wilian Holding Company Wall climbing form hoist
US20070119116A1 (en) * 2003-11-27 2007-05-31 Alberto Arozena Bergaretxe Climbing system for shuttering, scaffolding and loads in general
US8708100B2 (en) * 2005-06-29 2014-04-29 Peri Gmbh Rail-guided climbing system
US9297173B2 (en) * 2008-01-22 2016-03-29 Dayton Superior Corporation Jump form system
US9175487B2 (en) * 2010-03-05 2015-11-03 Ulma C Y E, S.Coop Self-climbing perimetric protection system for construction works in buildings
US20120247870A1 (en) * 2011-03-29 2012-10-04 Iturbe Beristain Eneko Perimetric protection system for buildings undergoing construction
US10428536B2 (en) * 2013-12-30 2019-10-01 International Chimney Corporation Scaffold system

Also Published As

Publication number Publication date
US10428536B2 (en) 2019-10-01
CA2838259C (en) 2020-08-18
CA2838259A1 (en) 2015-06-30
US20150184402A1 (en) 2015-07-02

Similar Documents

Publication Publication Date Title
US20190324069A1 (en) Scaffold system
JP5349322B2 (en) Movable anchor fixed fall prevention device
US9963889B2 (en) Sealed and integrated climbing scaffold and method for using the same
US9617747B2 (en) Folding guard rail method and apparatus
US20170355582A1 (en) Apparatus for providing safety netting on closed-sided manlifts
KR20180116170A (en) The elevated workbench equipped with safety equipment for safety work and its safety equipment
WO2004020766A1 (en) A lifting or transporting means using a reciprocating jack
KR20220014561A (en) Working platform for installing and maintaining of elevator
US20160130115A1 (en) Retractable overhead access platform for machine room less elevator systems
JP4092346B2 (en) Construction method and dismantling method of scaffold for high-rise building
KR20120114106A (en) Zig for moving cart rail
KR20220125633A (en) Work boarding device
KR20220048897A (en) Gondola for work at height
US7857097B2 (en) Scaffolding apparatus and method
RU2335452C2 (en) Crane for loads lifting into window aperture, on recessed balconies and balconies of buildings being under construction or repair
KR101820954B1 (en) Foldable work stage for suspension scaffold
EP1414731A1 (en) Lift especially for mounting on a substantially vertical building and security arrangement for said lift
CN116249668A (en) Elevator apparatus
CN109537868A (en) A kind of portable operating platform for assembled main cable and girder
KR102447971B1 (en) Rolling Scaffold Tower
WO2011107573A1 (en) Modular structure for scaffolding
CN103334721A (en) Pumping unit
AU2003254411B2 (en) A lifting or transporting means using a reciprocating jack
CN213569151U (en) Tower crane lifts by crane and uses fixing device
JP5968162B2 (en) Elevator toe guard

Legal Events

Date Code Title Description
STPP Information on status: patent application and granting procedure in general

Free format text: DOCKETED NEW CASE - READY FOR EXAMINATION

STPP Information on status: patent application and granting procedure in general

Free format text: NON FINAL ACTION MAILED

STCB Information on status: application discontinuation

Free format text: ABANDONED -- FAILURE TO RESPOND TO AN OFFICE ACTION