US20140371935A1 - System and methods to assess, manage and control distributed renewable energy resources on a grid or microgrid and achieve a 100% renewable energy grid or microgrid from clean, carbon free, and water conserving distributed renewable energy technologies and resources - Google Patents

System and methods to assess, manage and control distributed renewable energy resources on a grid or microgrid and achieve a 100% renewable energy grid or microgrid from clean, carbon free, and water conserving distributed renewable energy technologies and resources Download PDF

Info

Publication number
US20140371935A1
US20140371935A1 US14/470,790 US201414470790A US2014371935A1 US 20140371935 A1 US20140371935 A1 US 20140371935A1 US 201414470790 A US201414470790 A US 201414470790A US 2014371935 A1 US2014371935 A1 US 2014371935A1
Authority
US
United States
Prior art keywords
energy
data
facility
measurement
excess
Prior art date
Legal status (The legal status is an assumption and is not a legal conclusion. Google has not performed a legal analysis and makes no representation as to the accuracy of the status listed.)
Abandoned
Application number
US14/470,790
Inventor
Michel Roger Kamel
Paul W. Donahue
Jeffrey Alan Dankworth
Current Assignee (The listed assignees may be inaccurate. Google has not performed a legal analysis and makes no representation or warranty as to the accuracy of the list.)
MELROK LLC
EXPANERGY LLC
Original Assignee
EXPANERGY LLC
Priority date (The priority date is an assumption and is not a legal conclusion. Google has not performed a legal analysis and makes no representation as to the accuracy of the date listed.)
Filing date
Publication date
Application filed by EXPANERGY LLC filed Critical EXPANERGY LLC
Priority to US14/470,790 priority Critical patent/US20140371935A1/en
Publication of US20140371935A1 publication Critical patent/US20140371935A1/en
Assigned to EXPANERGY, LLC reassignment EXPANERGY, LLC ASSIGNMENT OF ASSIGNORS INTEREST (SEE DOCUMENT FOR DETAILS). Assignors: DANKWORTH, JEFFREY ALAN, DONAHUE, PAUL W., KAMEL, MICHEL ROGER
Assigned to EXCORDA, LLC reassignment EXCORDA, LLC ASSIGNMENT OF ASSIGNORS INTEREST (SEE DOCUMENT FOR DETAILS). Assignors: EXPANERGY, LLC
Assigned to MELROK, LLC reassignment MELROK, LLC CHANGE OF NAME (SEE DOCUMENT FOR DETAILS). Assignors: EXCORDA, LLC
Abandoned legal-status Critical Current

Links

Images

Classifications

    • GPHYSICS
    • G05CONTROLLING; REGULATING
    • G05FSYSTEMS FOR REGULATING ELECTRIC OR MAGNETIC VARIABLES
    • G05F1/00Automatic systems in which deviations of an electric quantity from one or more predetermined values are detected at the output of the system and fed back to a device within the system to restore the detected quantity to its predetermined value or values, i.e. retroactive systems
    • G05F1/66Regulating electric power
    • GPHYSICS
    • G01MEASURING; TESTING
    • G01RMEASURING ELECTRIC VARIABLES; MEASURING MAGNETIC VARIABLES
    • G01R21/00Arrangements for measuring electric power or power factor
    • G01R21/001Measuring real or reactive component; Measuring apparent energy
    • GPHYSICS
    • G01MEASURING; TESTING
    • G01RMEASURING ELECTRIC VARIABLES; MEASURING MAGNETIC VARIABLES
    • G01R21/00Arrangements for measuring electric power or power factor
    • G01R21/133Arrangements for measuring electric power or power factor by using digital technique
    • GPHYSICS
    • G01MEASURING; TESTING
    • G01RMEASURING ELECTRIC VARIABLES; MEASURING MAGNETIC VARIABLES
    • G01R21/00Arrangements for measuring electric power or power factor
    • G01R21/133Arrangements for measuring electric power or power factor by using digital technique
    • G01R21/1333Arrangements for measuring electric power or power factor by using digital technique adapted for special tariff measuring
    • GPHYSICS
    • G05CONTROLLING; REGULATING
    • G05BCONTROL OR REGULATING SYSTEMS IN GENERAL; FUNCTIONAL ELEMENTS OF SUCH SYSTEMS; MONITORING OR TESTING ARRANGEMENTS FOR SUCH SYSTEMS OR ELEMENTS
    • G05B15/00Systems controlled by a computer
    • G05B15/02Systems controlled by a computer electric
    • GPHYSICS
    • G06COMPUTING; CALCULATING OR COUNTING
    • G06QINFORMATION AND COMMUNICATION TECHNOLOGY [ICT] SPECIALLY ADAPTED FOR ADMINISTRATIVE, COMMERCIAL, FINANCIAL, MANAGERIAL OR SUPERVISORY PURPOSES; SYSTEMS OR METHODS SPECIALLY ADAPTED FOR ADMINISTRATIVE, COMMERCIAL, FINANCIAL, MANAGERIAL OR SUPERVISORY PURPOSES, NOT OTHERWISE PROVIDED FOR
    • G06Q10/00Administration; Management
    • G06Q10/06Resources, workflows, human or project management; Enterprise or organisation planning; Enterprise or organisation modelling
    • G06Q10/063Operations research, analysis or management
    • G06Q10/0631Resource planning, allocation, distributing or scheduling for enterprises or organisations
    • G06Q10/06312Adjustment or analysis of established resource schedule, e.g. resource or task levelling, or dynamic rescheduling
    • GPHYSICS
    • G06COMPUTING; CALCULATING OR COUNTING
    • G06QINFORMATION AND COMMUNICATION TECHNOLOGY [ICT] SPECIALLY ADAPTED FOR ADMINISTRATIVE, COMMERCIAL, FINANCIAL, MANAGERIAL OR SUPERVISORY PURPOSES; SYSTEMS OR METHODS SPECIALLY ADAPTED FOR ADMINISTRATIVE, COMMERCIAL, FINANCIAL, MANAGERIAL OR SUPERVISORY PURPOSES, NOT OTHERWISE PROVIDED FOR
    • G06Q30/00Commerce
    • G06Q30/06Buying, selling or leasing transactions
    • GPHYSICS
    • G06COMPUTING; CALCULATING OR COUNTING
    • G06QINFORMATION AND COMMUNICATION TECHNOLOGY [ICT] SPECIALLY ADAPTED FOR ADMINISTRATIVE, COMMERCIAL, FINANCIAL, MANAGERIAL OR SUPERVISORY PURPOSES; SYSTEMS OR METHODS SPECIALLY ADAPTED FOR ADMINISTRATIVE, COMMERCIAL, FINANCIAL, MANAGERIAL OR SUPERVISORY PURPOSES, NOT OTHERWISE PROVIDED FOR
    • G06Q50/00Information and communication technology [ICT] specially adapted for implementation of business processes of specific business sectors, e.g. utilities or tourism
    • G06Q50/06Energy or water supply
    • HELECTRICITY
    • H02GENERATION; CONVERSION OR DISTRIBUTION OF ELECTRIC POWER
    • H02JCIRCUIT ARRANGEMENTS OR SYSTEMS FOR SUPPLYING OR DISTRIBUTING ELECTRIC POWER; SYSTEMS FOR STORING ELECTRIC ENERGY
    • H02J13/00Circuit arrangements for providing remote indication of network conditions, e.g. an instantaneous record of the open or closed condition of each circuitbreaker in the network; Circuit arrangements for providing remote control of switching means in a power distribution network, e.g. switching in and out of current consumers by using a pulse code signal carried by the network
    • H02J13/00002Circuit arrangements for providing remote indication of network conditions, e.g. an instantaneous record of the open or closed condition of each circuitbreaker in the network; Circuit arrangements for providing remote control of switching means in a power distribution network, e.g. switching in and out of current consumers by using a pulse code signal carried by the network characterised by monitoring
    • HELECTRICITY
    • H02GENERATION; CONVERSION OR DISTRIBUTION OF ELECTRIC POWER
    • H02JCIRCUIT ARRANGEMENTS OR SYSTEMS FOR SUPPLYING OR DISTRIBUTING ELECTRIC POWER; SYSTEMS FOR STORING ELECTRIC ENERGY
    • H02J13/00Circuit arrangements for providing remote indication of network conditions, e.g. an instantaneous record of the open or closed condition of each circuitbreaker in the network; Circuit arrangements for providing remote control of switching means in a power distribution network, e.g. switching in and out of current consumers by using a pulse code signal carried by the network
    • H02J13/00004Circuit arrangements for providing remote indication of network conditions, e.g. an instantaneous record of the open or closed condition of each circuitbreaker in the network; Circuit arrangements for providing remote control of switching means in a power distribution network, e.g. switching in and out of current consumers by using a pulse code signal carried by the network characterised by the power network being locally controlled
    • HELECTRICITY
    • H02GENERATION; CONVERSION OR DISTRIBUTION OF ELECTRIC POWER
    • H02JCIRCUIT ARRANGEMENTS OR SYSTEMS FOR SUPPLYING OR DISTRIBUTING ELECTRIC POWER; SYSTEMS FOR STORING ELECTRIC ENERGY
    • H02J13/00Circuit arrangements for providing remote indication of network conditions, e.g. an instantaneous record of the open or closed condition of each circuitbreaker in the network; Circuit arrangements for providing remote control of switching means in a power distribution network, e.g. switching in and out of current consumers by using a pulse code signal carried by the network
    • H02J13/00006Circuit arrangements for providing remote indication of network conditions, e.g. an instantaneous record of the open or closed condition of each circuitbreaker in the network; Circuit arrangements for providing remote control of switching means in a power distribution network, e.g. switching in and out of current consumers by using a pulse code signal carried by the network characterised by information or instructions transport means between the monitoring, controlling or managing units and monitored, controlled or operated power network element or electrical equipment
    • H02J13/00012Circuit arrangements for providing remote indication of network conditions, e.g. an instantaneous record of the open or closed condition of each circuitbreaker in the network; Circuit arrangements for providing remote control of switching means in a power distribution network, e.g. switching in and out of current consumers by using a pulse code signal carried by the network characterised by information or instructions transport means between the monitoring, controlling or managing units and monitored, controlled or operated power network element or electrical equipment using an auxiliary transmission line
    • H02J13/00014Circuit arrangements for providing remote indication of network conditions, e.g. an instantaneous record of the open or closed condition of each circuitbreaker in the network; Circuit arrangements for providing remote control of switching means in a power distribution network, e.g. switching in and out of current consumers by using a pulse code signal carried by the network characterised by information or instructions transport means between the monitoring, controlling or managing units and monitored, controlled or operated power network element or electrical equipment using an auxiliary transmission line carrying signals having the network frequency or DC signals
    • HELECTRICITY
    • H02GENERATION; CONVERSION OR DISTRIBUTION OF ELECTRIC POWER
    • H02JCIRCUIT ARRANGEMENTS OR SYSTEMS FOR SUPPLYING OR DISTRIBUTING ELECTRIC POWER; SYSTEMS FOR STORING ELECTRIC ENERGY
    • H02J13/00Circuit arrangements for providing remote indication of network conditions, e.g. an instantaneous record of the open or closed condition of each circuitbreaker in the network; Circuit arrangements for providing remote control of switching means in a power distribution network, e.g. switching in and out of current consumers by using a pulse code signal carried by the network
    • H02J13/00006Circuit arrangements for providing remote indication of network conditions, e.g. an instantaneous record of the open or closed condition of each circuitbreaker in the network; Circuit arrangements for providing remote control of switching means in a power distribution network, e.g. switching in and out of current consumers by using a pulse code signal carried by the network characterised by information or instructions transport means between the monitoring, controlling or managing units and monitored, controlled or operated power network element or electrical equipment
    • H02J13/00022Circuit arrangements for providing remote indication of network conditions, e.g. an instantaneous record of the open or closed condition of each circuitbreaker in the network; Circuit arrangements for providing remote control of switching means in a power distribution network, e.g. switching in and out of current consumers by using a pulse code signal carried by the network characterised by information or instructions transport means between the monitoring, controlling or managing units and monitored, controlled or operated power network element or electrical equipment using wireless data transmission
    • HELECTRICITY
    • H02GENERATION; CONVERSION OR DISTRIBUTION OF ELECTRIC POWER
    • H02JCIRCUIT ARRANGEMENTS OR SYSTEMS FOR SUPPLYING OR DISTRIBUTING ELECTRIC POWER; SYSTEMS FOR STORING ELECTRIC ENERGY
    • H02J13/00Circuit arrangements for providing remote indication of network conditions, e.g. an instantaneous record of the open or closed condition of each circuitbreaker in the network; Circuit arrangements for providing remote control of switching means in a power distribution network, e.g. switching in and out of current consumers by using a pulse code signal carried by the network
    • H02J13/00032Systems characterised by the controlled or operated power network elements or equipment, the power network elements or equipment not otherwise provided for
    • H02J13/00034Systems characterised by the controlled or operated power network elements or equipment, the power network elements or equipment not otherwise provided for the elements or equipment being or involving an electric power substation
    • HELECTRICITY
    • H02GENERATION; CONVERSION OR DISTRIBUTION OF ELECTRIC POWER
    • H02JCIRCUIT ARRANGEMENTS OR SYSTEMS FOR SUPPLYING OR DISTRIBUTING ELECTRIC POWER; SYSTEMS FOR STORING ELECTRIC ENERGY
    • H02J3/00Circuit arrangements for ac mains or ac distribution networks
    • HELECTRICITY
    • H02GENERATION; CONVERSION OR DISTRIBUTION OF ELECTRIC POWER
    • H02JCIRCUIT ARRANGEMENTS OR SYSTEMS FOR SUPPLYING OR DISTRIBUTING ELECTRIC POWER; SYSTEMS FOR STORING ELECTRIC ENERGY
    • H02J2203/00Indexing scheme relating to details of circuit arrangements for AC mains or AC distribution networks
    • H02J2203/20Simulating, e g planning, reliability check, modelling or computer assisted design [CAD]
    • HELECTRICITY
    • H02GENERATION; CONVERSION OR DISTRIBUTION OF ELECTRIC POWER
    • H02JCIRCUIT ARRANGEMENTS OR SYSTEMS FOR SUPPLYING OR DISTRIBUTING ELECTRIC POWER; SYSTEMS FOR STORING ELECTRIC ENERGY
    • H02J2310/00The network for supplying or distributing electric power characterised by its spatial reach or by the load
    • H02J2310/10The network having a local or delimited stationary reach
    • HELECTRICITY
    • H02GENERATION; CONVERSION OR DISTRIBUTION OF ELECTRIC POWER
    • H02JCIRCUIT ARRANGEMENTS OR SYSTEMS FOR SUPPLYING OR DISTRIBUTING ELECTRIC POWER; SYSTEMS FOR STORING ELECTRIC ENERGY
    • H02J2310/00The network for supplying or distributing electric power characterised by its spatial reach or by the load
    • H02J2310/10The network having a local or delimited stationary reach
    • H02J2310/12The local stationary network supplying a household or a building
    • H02J2310/16The load or loads being an Information and Communication Technology [ICT] facility
    • YGENERAL TAGGING OF NEW TECHNOLOGICAL DEVELOPMENTS; GENERAL TAGGING OF CROSS-SECTIONAL TECHNOLOGIES SPANNING OVER SEVERAL SECTIONS OF THE IPC; TECHNICAL SUBJECTS COVERED BY FORMER USPC CROSS-REFERENCE ART COLLECTIONS [XRACs] AND DIGESTS
    • Y02TECHNOLOGIES OR APPLICATIONS FOR MITIGATION OR ADAPTATION AGAINST CLIMATE CHANGE
    • Y02BCLIMATE CHANGE MITIGATION TECHNOLOGIES RELATED TO BUILDINGS, e.g. HOUSING, HOUSE APPLIANCES OR RELATED END-USER APPLICATIONS
    • Y02B70/00Technologies for an efficient end-user side electric power management and consumption
    • Y02B70/30Systems integrating technologies related to power network operation and communication or information technologies for improving the carbon footprint of the management of residential or tertiary loads, i.e. smart grids as climate change mitigation technology in the buildings sector, including also the last stages of power distribution and the control, monitoring or operating management systems at local level
    • YGENERAL TAGGING OF NEW TECHNOLOGICAL DEVELOPMENTS; GENERAL TAGGING OF CROSS-SECTIONAL TECHNOLOGIES SPANNING OVER SEVERAL SECTIONS OF THE IPC; TECHNICAL SUBJECTS COVERED BY FORMER USPC CROSS-REFERENCE ART COLLECTIONS [XRACs] AND DIGESTS
    • Y02TECHNOLOGIES OR APPLICATIONS FOR MITIGATION OR ADAPTATION AGAINST CLIMATE CHANGE
    • Y02BCLIMATE CHANGE MITIGATION TECHNOLOGIES RELATED TO BUILDINGS, e.g. HOUSING, HOUSE APPLIANCES OR RELATED END-USER APPLICATIONS
    • Y02B70/00Technologies for an efficient end-user side electric power management and consumption
    • Y02B70/30Systems integrating technologies related to power network operation and communication or information technologies for improving the carbon footprint of the management of residential or tertiary loads, i.e. smart grids as climate change mitigation technology in the buildings sector, including also the last stages of power distribution and the control, monitoring or operating management systems at local level
    • Y02B70/3225Demand response systems, e.g. load shedding, peak shaving
    • YGENERAL TAGGING OF NEW TECHNOLOGICAL DEVELOPMENTS; GENERAL TAGGING OF CROSS-SECTIONAL TECHNOLOGIES SPANNING OVER SEVERAL SECTIONS OF THE IPC; TECHNICAL SUBJECTS COVERED BY FORMER USPC CROSS-REFERENCE ART COLLECTIONS [XRACs] AND DIGESTS
    • Y02TECHNOLOGIES OR APPLICATIONS FOR MITIGATION OR ADAPTATION AGAINST CLIMATE CHANGE
    • Y02BCLIMATE CHANGE MITIGATION TECHNOLOGIES RELATED TO BUILDINGS, e.g. HOUSING, HOUSE APPLIANCES OR RELATED END-USER APPLICATIONS
    • Y02B90/00Enabling technologies or technologies with a potential or indirect contribution to GHG emissions mitigation
    • Y02B90/20Smart grids as enabling technology in buildings sector
    • YGENERAL TAGGING OF NEW TECHNOLOGICAL DEVELOPMENTS; GENERAL TAGGING OF CROSS-SECTIONAL TECHNOLOGIES SPANNING OVER SEVERAL SECTIONS OF THE IPC; TECHNICAL SUBJECTS COVERED BY FORMER USPC CROSS-REFERENCE ART COLLECTIONS [XRACs] AND DIGESTS
    • Y02TECHNOLOGIES OR APPLICATIONS FOR MITIGATION OR ADAPTATION AGAINST CLIMATE CHANGE
    • Y02EREDUCTION OF GREENHOUSE GAS [GHG] EMISSIONS, RELATED TO ENERGY GENERATION, TRANSMISSION OR DISTRIBUTION
    • Y02E60/00Enabling technologies; Technologies with a potential or indirect contribution to GHG emissions mitigation
    • YGENERAL TAGGING OF NEW TECHNOLOGICAL DEVELOPMENTS; GENERAL TAGGING OF CROSS-SECTIONAL TECHNOLOGIES SPANNING OVER SEVERAL SECTIONS OF THE IPC; TECHNICAL SUBJECTS COVERED BY FORMER USPC CROSS-REFERENCE ART COLLECTIONS [XRACs] AND DIGESTS
    • Y02TECHNOLOGIES OR APPLICATIONS FOR MITIGATION OR ADAPTATION AGAINST CLIMATE CHANGE
    • Y02PCLIMATE CHANGE MITIGATION TECHNOLOGIES IN THE PRODUCTION OR PROCESSING OF GOODS
    • Y02P80/00Climate change mitigation technologies for sector-wide applications
    • Y02P80/10Efficient use of energy, e.g. using compressed air or pressurized fluid as energy carrier
    • YGENERAL TAGGING OF NEW TECHNOLOGICAL DEVELOPMENTS; GENERAL TAGGING OF CROSS-SECTIONAL TECHNOLOGIES SPANNING OVER SEVERAL SECTIONS OF THE IPC; TECHNICAL SUBJECTS COVERED BY FORMER USPC CROSS-REFERENCE ART COLLECTIONS [XRACs] AND DIGESTS
    • Y02TECHNOLOGIES OR APPLICATIONS FOR MITIGATION OR ADAPTATION AGAINST CLIMATE CHANGE
    • Y02PCLIMATE CHANGE MITIGATION TECHNOLOGIES IN THE PRODUCTION OR PROCESSING OF GOODS
    • Y02P90/00Enabling technologies with a potential contribution to greenhouse gas [GHG] emissions mitigation
    • Y02P90/80Management or planning
    • Y02P90/82Energy audits or management systems therefor
    • YGENERAL TAGGING OF NEW TECHNOLOGICAL DEVELOPMENTS; GENERAL TAGGING OF CROSS-SECTIONAL TECHNOLOGIES SPANNING OVER SEVERAL SECTIONS OF THE IPC; TECHNICAL SUBJECTS COVERED BY FORMER USPC CROSS-REFERENCE ART COLLECTIONS [XRACs] AND DIGESTS
    • Y02TECHNOLOGIES OR APPLICATIONS FOR MITIGATION OR ADAPTATION AGAINST CLIMATE CHANGE
    • Y02PCLIMATE CHANGE MITIGATION TECHNOLOGIES IN THE PRODUCTION OR PROCESSING OF GOODS
    • Y02P90/00Enabling technologies with a potential contribution to greenhouse gas [GHG] emissions mitigation
    • Y02P90/80Management or planning
    • Y02P90/84Greenhouse gas [GHG] management systems
    • YGENERAL TAGGING OF NEW TECHNOLOGICAL DEVELOPMENTS; GENERAL TAGGING OF CROSS-SECTIONAL TECHNOLOGIES SPANNING OVER SEVERAL SECTIONS OF THE IPC; TECHNICAL SUBJECTS COVERED BY FORMER USPC CROSS-REFERENCE ART COLLECTIONS [XRACs] AND DIGESTS
    • Y02TECHNOLOGIES OR APPLICATIONS FOR MITIGATION OR ADAPTATION AGAINST CLIMATE CHANGE
    • Y02PCLIMATE CHANGE MITIGATION TECHNOLOGIES IN THE PRODUCTION OR PROCESSING OF GOODS
    • Y02P90/00Enabling technologies with a potential contribution to greenhouse gas [GHG] emissions mitigation
    • Y02P90/80Management or planning
    • Y02P90/84Greenhouse gas [GHG] management systems
    • Y02P90/845Inventory and reporting systems for greenhouse gases [GHG]
    • YGENERAL TAGGING OF NEW TECHNOLOGICAL DEVELOPMENTS; GENERAL TAGGING OF CROSS-SECTIONAL TECHNOLOGIES SPANNING OVER SEVERAL SECTIONS OF THE IPC; TECHNICAL SUBJECTS COVERED BY FORMER USPC CROSS-REFERENCE ART COLLECTIONS [XRACs] AND DIGESTS
    • Y04INFORMATION OR COMMUNICATION TECHNOLOGIES HAVING AN IMPACT ON OTHER TECHNOLOGY AREAS
    • Y04SSYSTEMS INTEGRATING TECHNOLOGIES RELATED TO POWER NETWORK OPERATION, COMMUNICATION OR INFORMATION TECHNOLOGIES FOR IMPROVING THE ELECTRICAL POWER GENERATION, TRANSMISSION, DISTRIBUTION, MANAGEMENT OR USAGE, i.e. SMART GRIDS
    • Y04S20/00Management or operation of end-user stationary applications or the last stages of power distribution; Controlling, monitoring or operating thereof
    • YGENERAL TAGGING OF NEW TECHNOLOGICAL DEVELOPMENTS; GENERAL TAGGING OF CROSS-SECTIONAL TECHNOLOGIES SPANNING OVER SEVERAL SECTIONS OF THE IPC; TECHNICAL SUBJECTS COVERED BY FORMER USPC CROSS-REFERENCE ART COLLECTIONS [XRACs] AND DIGESTS
    • Y04INFORMATION OR COMMUNICATION TECHNOLOGIES HAVING AN IMPACT ON OTHER TECHNOLOGY AREAS
    • Y04SSYSTEMS INTEGRATING TECHNOLOGIES RELATED TO POWER NETWORK OPERATION, COMMUNICATION OR INFORMATION TECHNOLOGIES FOR IMPROVING THE ELECTRICAL POWER GENERATION, TRANSMISSION, DISTRIBUTION, MANAGEMENT OR USAGE, i.e. SMART GRIDS
    • Y04S20/00Management or operation of end-user stationary applications or the last stages of power distribution; Controlling, monitoring or operating thereof
    • Y04S20/20End-user application control systems
    • Y04S20/221General power management systems
    • YGENERAL TAGGING OF NEW TECHNOLOGICAL DEVELOPMENTS; GENERAL TAGGING OF CROSS-SECTIONAL TECHNOLOGIES SPANNING OVER SEVERAL SECTIONS OF THE IPC; TECHNICAL SUBJECTS COVERED BY FORMER USPC CROSS-REFERENCE ART COLLECTIONS [XRACs] AND DIGESTS
    • Y04INFORMATION OR COMMUNICATION TECHNOLOGIES HAVING AN IMPACT ON OTHER TECHNOLOGY AREAS
    • Y04SSYSTEMS INTEGRATING TECHNOLOGIES RELATED TO POWER NETWORK OPERATION, COMMUNICATION OR INFORMATION TECHNOLOGIES FOR IMPROVING THE ELECTRICAL POWER GENERATION, TRANSMISSION, DISTRIBUTION, MANAGEMENT OR USAGE, i.e. SMART GRIDS
    • Y04S20/00Management or operation of end-user stationary applications or the last stages of power distribution; Controlling, monitoring or operating thereof
    • Y04S20/20End-user application control systems
    • Y04S20/222Demand response systems, e.g. load shedding, peak shaving
    • YGENERAL TAGGING OF NEW TECHNOLOGICAL DEVELOPMENTS; GENERAL TAGGING OF CROSS-SECTIONAL TECHNOLOGIES SPANNING OVER SEVERAL SECTIONS OF THE IPC; TECHNICAL SUBJECTS COVERED BY FORMER USPC CROSS-REFERENCE ART COLLECTIONS [XRACs] AND DIGESTS
    • Y04INFORMATION OR COMMUNICATION TECHNOLOGIES HAVING AN IMPACT ON OTHER TECHNOLOGY AREAS
    • Y04SSYSTEMS INTEGRATING TECHNOLOGIES RELATED TO POWER NETWORK OPERATION, COMMUNICATION OR INFORMATION TECHNOLOGIES FOR IMPROVING THE ELECTRICAL POWER GENERATION, TRANSMISSION, DISTRIBUTION, MANAGEMENT OR USAGE, i.e. SMART GRIDS
    • Y04S40/00Systems for electrical power generation, transmission, distribution or end-user application management characterised by the use of communication or information technologies, or communication or information technology specific aspects supporting them
    • Y04S40/12Systems for electrical power generation, transmission, distribution or end-user application management characterised by the use of communication or information technologies, or communication or information technology specific aspects supporting them characterised by data transport means between the monitoring, controlling or managing units and monitored, controlled or operated electrical equipment
    • Y04S40/126Systems for electrical power generation, transmission, distribution or end-user application management characterised by the use of communication or information technologies, or communication or information technology specific aspects supporting them characterised by data transport means between the monitoring, controlling or managing units and monitored, controlled or operated electrical equipment using wireless data transmission
    • YGENERAL TAGGING OF NEW TECHNOLOGICAL DEVELOPMENTS; GENERAL TAGGING OF CROSS-SECTIONAL TECHNOLOGIES SPANNING OVER SEVERAL SECTIONS OF THE IPC; TECHNICAL SUBJECTS COVERED BY FORMER USPC CROSS-REFERENCE ART COLLECTIONS [XRACs] AND DIGESTS
    • Y04INFORMATION OR COMMUNICATION TECHNOLOGIES HAVING AN IMPACT ON OTHER TECHNOLOGY AREAS
    • Y04SSYSTEMS INTEGRATING TECHNOLOGIES RELATED TO POWER NETWORK OPERATION, COMMUNICATION OR INFORMATION TECHNOLOGIES FOR IMPROVING THE ELECTRICAL POWER GENERATION, TRANSMISSION, DISTRIBUTION, MANAGEMENT OR USAGE, i.e. SMART GRIDS
    • Y04S40/00Systems for electrical power generation, transmission, distribution or end-user application management characterised by the use of communication or information technologies, or communication or information technology specific aspects supporting them
    • Y04S40/20Information technology specific aspects, e.g. CAD, simulation, modelling, system security
    • YGENERAL TAGGING OF NEW TECHNOLOGICAL DEVELOPMENTS; GENERAL TAGGING OF CROSS-SECTIONAL TECHNOLOGIES SPANNING OVER SEVERAL SECTIONS OF THE IPC; TECHNICAL SUBJECTS COVERED BY FORMER USPC CROSS-REFERENCE ART COLLECTIONS [XRACs] AND DIGESTS
    • Y04INFORMATION OR COMMUNICATION TECHNOLOGIES HAVING AN IMPACT ON OTHER TECHNOLOGY AREAS
    • Y04SSYSTEMS INTEGRATING TECHNOLOGIES RELATED TO POWER NETWORK OPERATION, COMMUNICATION OR INFORMATION TECHNOLOGIES FOR IMPROVING THE ELECTRICAL POWER GENERATION, TRANSMISSION, DISTRIBUTION, MANAGEMENT OR USAGE, i.e. SMART GRIDS
    • Y04S50/00Market activities related to the operation of systems integrating technologies related to power network operation or related to communication or information technologies
    • Y04S50/10Energy trading, including energy flowing from end-user application to grid

Definitions

  • This disclosure relates generally to evaluating energy performance of a building, a building system, and/or a collection of buildings locally or over a large geographic area.
  • the Energy Star® program has developed energy performance rating systems for several commercial and institutional building types and manufacturing facilities. These ratings, on a scale of 1 to 100, provide a means for benchmarking the energy efficiency of specific buildings and industrial plants against the energy performance of similar facilities of the same space type, based on a national average. A rating can be generated for ratable space types based on building attributes, such as square footage, weekly operating hours, and monthly energy consumption data.
  • the Energy Star® ratings rely on static analytics, estimates, and forecasting, and do not produce accurate results and can be difficult to verify.
  • Embodiments relate to an energy search engine using dynamic analytic algorithms based at least in part on, but not limited to one or more of smart meter data, other sensor data, sub-metered energy measurement data, weather data, gas data, utility rate schedules, basic facility information, such as, for example, the direction (north, south, east or west) that the building faces, total facility square footage, occupant scheduling, facility use, and the like to dynamically assess the energy sustainability of a facility.
  • a method to assess energy usage comprises receiving in a substantially continuous way a measurement of actual energy consumption, receiving in a substantially continuous way a measurement of ambient conditions, and comparing the measurement of actual energy consumption with a target energy consumption to calculate a substantially continuous energy performance assessment, wherein the target energy consumption is based at least in part on the measurement of ambient conditions.
  • the method further comprising receiving in a substantially continuous way a measurement of facility occupancy and usage, wherein the target energy consumption is based at least in part on the measurement of ambient conditions and facility usage.
  • receiving in the substantially continuous way the measurement of ambient conditions comprises receiving the measurement of ambient conditions at least every 15 minutes.
  • the substantially continuous energy performance assessment comprises comparisons occurring at least every 15 minutes of the measurement of actual energy consumption with the target energy consumption.
  • Certain embodiments relate to a method to dynamically assess energy efficiency.
  • the method comprises obtaining a minimum energy consumption of a system, receiving in a substantially continuous way a measurement of actual energy consumption of the system, and comparing the minimum energy consumption to the measurement of actual energy consumption to calculate a substantially continuous energy performance assessment.
  • the system can be at least one of a building envelope, a building, a zone within a building, an energy subsystem, a facility, a group of buildings in near proximity to each other, a geographically diverse group of buildings, and the like.
  • comparing the minimum energy consumption to the measurement of actual energy consumption comprises at least one of comparing in a substantially continuous way a theoretical minimum energy consumption of the system to the measurement of actual energy consumption to determine a theoretical energy efficiency for the system, where the theoretical minimum energy consumption is based at least in part on the theoretical performance limit of system components, comparing in a substantially continuous way an achievable minimum energy consumption of the system to the measurement of actual energy consumption to determine an achievable energy efficiency for the system, where the achievable minimum energy consumption is based at least in part on specifications for high energy efficient equivalents of the system components, and comparing in a substantially continuous way a designed minimum energy consumption of the system to the measurement of actual energy consumption to determine a designed energy efficiency for the system, where the designed minimum energy consumption is based at least in part on specifications for the system components.
  • Certain other embodiments relate to a method to dynamically assess energy usage.
  • the method comprises obtaining an expected energy usage for a building having installed building systems and a load profile, receiving in a substantially continuous way measurements of actual energy consumption after an installation of at least one energy improvement measure for the building, establishing an energy usage for the building with the load profile based at least in part on the measurements received after the installation of the at least one energy improvement measure, and determining an impact of the at least one energy improvement measure.
  • the method further comprises quantifying the effectiveness of the at least one energy improvement measure by determining at least one of a payback calculation, a payment of an incentive, a valuation of real property, and a carbon offset used in carbon trading.
  • the installed building systems can comprise at least one of an HVAC system, a lighting system, at least one plug load, a data center system, a water heating system, and the like.
  • Installed energy improvement measure can comprise installing a renewable energy system, retrofitting equipment, commissioning, load shifting, load shedding, installing energy storage, and the like.
  • an apparatus to dynamically assess energy usage of a system comprises computer hardware including at least one computer processor, and computer readable-storage comprising computer-readable instructions that, when executed by the computer processor, cause the computer hardware to perform operations defined by the computer-executable instructions comprising obtaining a minimum energy consumption of a system, receiving in a substantially continuous way a measurement of actual energy consumption of the system, and comparing the minimum energy consumption to the measurement of actual energy consumption to calculate a substantially continuous energy performance assessment.
  • the computer-executable instructions further comprise at least one of comparing in a substantially continuous way a theoretical minimum energy consumption of the system to the measurement of actual energy consumption to determine a theoretical energy efficiency for the system, where the theoretical minimum energy consumption is based at least in part on the theoretical performance limit of system components, comparing in a substantially continuous way an achievable minimum energy consumption of the system to the measurement of actual energy consumption to determine an achievable energy efficiency for the system, where the achievable minimum energy consumption is based at least in part on specifications for high energy efficient equivalents of the system components, and comparing in a substantially continuous way a designed minimum energy consumption of the system to the measurement of actual energy consumption to determine a designed energy efficiency for the system, where the designed minimum energy consumption is based at least in part on specifications for the system components.
  • the system can comprise at least one of a building, a building envelope, at least one building system, a zone within the building, a data center, and the like.
  • Receiving in the substantially continuous way the measurement of actual energy consumption of the system can comprise receiving the measurement of actual energy consumption at least every 15 minutes.
  • the substantially continuous energy performance assessment can comprise comparisons occurring at least every 15 minutes of the minimum energy consumption to the measurement of actual energy consumption and at least one of a gas energy carbon footprint, an electrical energy carbon footprint, an estimate of wasted energy, an energy rating, an energy efficiency, and a power index.
  • FIG. 1 illustrates a schematic diagram of a system to assess and optimize energy usage for a facility, according to certain embodiments.
  • FIG. 2 illustrates an exemplary schematic diagram of an energy management system, according to certain embodiments.
  • FIG. 3 is a flow chart of an exemplary energy search engine process to assess the amount of energy used for cooling and the amount of excessive cooling affected, according to certain embodiments.
  • FIG. 4 is an exemplary substantially continuous excessive cooling performance assessment, according to certain embodiments.
  • FIG. 5 is a flow chart of an exemplary energy search engine process to assess energy usage, according to certain embodiments.
  • FIG. 6 is a flow chart of an exemplary energy search engine process to dynamically assess energy efficiency, according to certain embodiments
  • FIG. 7 is a flow chart of an exemplary energy search engine process to quantify the effectiveness of energy improving measures, according to certain embodiments.
  • FIG. 8 is an exemplary substantially continuous energy performance assessment, according to certain embodiments.
  • FIG. 9 is an exemplary continuous yearly key performance indicator assessment, according to certain embodiments.
  • FIG. 10 is an exemplary continuous monthly key performance indicator assessment, according to certain embodiments.
  • FIG. 11 illustrates an exemplary block diagram of a system on a chip or circuit board for real time continuous and automated digital measurement, analysis, and communication with optional input from external sensors, analysis of energy use, analysis of external data and control of energy use and the measurement, analysis, storage, and reporting of energy quality and metrics, according to certain embodiments.
  • FIG. 12 illustrates an exemplary block diagram of an energy data reduction system that enables the use of existing communication methods and channels to handle the anticipated broadband flow of energy and control data that will emerge as “smart grid” data measurement, communication, and control tools expand in use and reach into residences, buildings, commercial facilities, industrial facilities and into smart appliances and devices, according to certain embodiments.
  • FIG. 13 illustrates an exemplary block diagram of the system of FIG. 1 , according to certain embodiments.
  • FIG. 14 represents a unique algorithm that can be used with this invention or with any energy or environmental measuring and reporting device or embodiment and/or with any network of energy or environmental devices or systems that measure, report, and optionally control energy or environmental data.
  • Embodiments of an energy search engine use dynamic energy related data to determine how well a facility is using energy and to identify wasted energy. Further embodiments dynamically guide building system adjustments to reduce energy waste, and verify the results of such actions.
  • contemporary heating, ventilation, and air conditioning (HVAC) systems use a combination of chilled coolant or chilled water, evaporative coils, forced air ducting, and hot water intermixed to provide comfort and fresh air to occupants of buildings. To provide this comfort, many building HVAC systems waste energy by simultaneously heating and cooling building air by relying on static factors and no external information to dynamically adjust the various HVAC components.
  • HVAC heating, ventilation, and air conditioning
  • a combination of dynamically varying factors are evaluated to dynamically adjust HVAC or other building systems for optimum occupancy comfort, lowest energy use, lowest tariff cost, and lowest GHG emissions.
  • factors include, but are not limited to, natural and environmental factors, occupant factors, utility tariff factors, and GHG emission factors.
  • natural and environmental factors For example, outside temperatures near a building vary hourly throughout the workday and evening. Throughout the day, the sun heats different aspects of the building which creates a variable heating component. As occupants move in and out of rooms and in and out of the building during the workday, their heat load contribution, fresh air requirements, occupant comfort requirements, and energy use via lighting, computers, and other office equipment or industrial processes in the building vary.
  • the energy search engine incorporates at least one of these dynamic variables in energy modeling algorithms to provide, for example, one or more of benchmarking energy use, comparing required energy use and costs to wasted energy use and costs, dynamically guiding building system adjustments, verifying the results of such actions, and determining an optimum size of alternate electric energy systems, such as solar, wind, fuel cells, and the like to generate energy for the building.
  • FIG. 1 illustrates an exemplary schematic diagram of a system 100 to dynamically assess and optimize energy usage for an energy subsystem of a facility, the facility or a network of facilities 104 .
  • Facilities 104 can comprise one or more buildings, residences, factories, stores, commercial facilities, industrial facilities, data centers and the like, one or more rooms, one or more offices, one or more zoned areas in a facility, one or more floors in a building, parking structures, stadiums, theatres, and the like, one or more systems, subsystems, and/or components 104 a , a zone within the building/facility 104 , a building envelope, and the like, locally or geographically remote.
  • the network of facilities 104 can comprise, for example, a geographic area, facility owner, property manager, campus, weather pattern, climate zone, facility activity type, facility total square footage, facility occupied square footage, volume of facility free space, facility schedule, facility activity levels (e.g. production quantities, number of students, etc.), utility company, applicable utility rate schedule, source of energy, type and size of local generation systems, type and size of local alternative energy systems (e.g.
  • thermal solar, thermal storage, energy storage, etc. type of construction material used, type of energy systems used, model of energy systems used, facility design specifications, required air changes, measured air changes, type of energy management system installed, model of energy management system installed, performance of any existing energy management system, applicable energy codes, applicable energy regulations, applicable energy standards, applicable greenhouse gas emissions codes, applicable greenhouse gas emissions regulations, applicable greenhouse gas emissions standards, energy service company servicing the facility, energy consulting firm servicing the facility, and the like.
  • Examples of the systems, subsystems and/or components 104 a include but are not limited to fans, pumps, motors, chillers, lights, heaters, heat exchangers, blowers, electric valves, air conditioning equipment, compressors, heat pumps, HVAC systems, lighting systems, motors, water heating systems, plug loads, data/Telco, variable air volume devices (VAV), gas systems, electrical systems, mechanical systems, electromechanical systems, electronic systems, chemical systems, and the like.
  • VAV variable air volume devices
  • the facility 104 and/or building 104 in the following discussion refer to the facility, its systems, subsystems, components, and/or a network of facilities as described above.
  • Energy entering the facility 104 can be of many forms, such as, for example, thermal, mechanical, electrical, chemical, light, and the like.
  • the most common forms are typically electricity or power, gas, thermal mass (hot or cold air, people), and solar irradiance.
  • the electrical energy can be generated from traditional fossil fuels, or alternate forms of power generation, such as solar cells, wind turbines, fuel cells, any type of electrical energy generator, and the like.
  • Ambient weather conditions such as cloudy days, or time of day, such as nighttime, may be responsible for radiant energy transfer (gains or losses).
  • the facility 104 comprises measurement devices 104 b configured to measure actual energy usage in real time.
  • sensors such as wired and/or wireless sensors and/or sensor systems, can measure kilowatt hours and energy spikes of electrical energy used to power the lighting system, to power the air compressor in the cooling system and to heat water for lavatories, cubic feet of gas consumed by a heating or HVAC system, amount of air flow from compressors in the cooling or HVAC system, and the like.
  • the sensors can comprise current sensors, voltage sensors, EMF sensors, touch sensors, contact closures, capacitive sensors, trip sensors, mechanical switches, torque sensors, temperature sensors, air flow sensors, gas flow sensors, water flow sensors, water sensors, accelerometers, vibration sensors, GPS, wind sensors, sun sensors, pressure sensors, light sensors, tension-meters, microphones, humidity sensors, occupancy sensors, motion sensors, laser sensors, gas sensors (CO2, CO), speed sensors (rotational, angular), pulse counters, and the like.
  • the facility 104 further comprises control systems, such as, for example, load shedding relays, load shifting relays, Energy Management Systems (EMS), Building Management Systems (BMS), and the like, to control energy consuming and energy saving components of the facility 104 .
  • control systems such as, for example, load shedding relays, load shifting relays, Energy Management Systems (EMS), Building Management Systems (BMS), and the like, to control energy consuming and energy saving components of the facility 104 .
  • EMS Energy Management Systems
  • BMS Building Management Systems
  • one or more controllers can raise or lower automatic blinds, shut off/reduce heating or cooling in an HVAC system in the entire or just one room of the facility 104 , switch usage of electricity from conventional generation to electricity generated by alternate forms, such as wind or solar, and the like.
  • the system 100 comprises an energy search engine 102 and a user interface 108 .
  • the energy search engine 102 is a cloud computing system based in a network 110 , such as the Internet 110 , as illustrated in FIG. 1 .
  • the energy search engine 102 is not a cloud computing system, but receives and transmits information through the network 110 , such as the Internet 110 , a wireless local network, or any other communication network.
  • the energy search engine 102 is hosted in a device located inside the facility 104 .
  • the device acquires sensor data and/or smart meter data directly from existing sensors and smart meters 104 b .
  • the device receives weather information, utility rate schedules, utility pricing information, grid usage information, BIM information, and other via RF broadcast signals.
  • the device calculates locally the energy performance, actionable information and communicates control signals to local relays 104 c , energy systems and other systems.
  • the user interface 108 allows a user to transmit information to the energy search engine 102 and receive information from the energy search engine 102 .
  • the user interface 108 comprises a Web browser and/or an application to communicate with the energy search engine 102 within or through the Internet 110 .
  • the user interface 108 is associated with a display and a user input device, such as a keyboard.
  • the energy search engine 102 receives energy usage information from the measurement devices 104 b measuring energy usage of the systems, subsystems, and components 104 c of the facility 104 in a substantially continuous way.
  • the measurement devices 104 b deliver data output that can include but is not limited to electric energy consumption data, natural or renewable gas data, air temperature data, air flow data, air quality data, building occupancy data, building zone level occupancy data, water data, environmental data, and geographic data, and the like. This data can be derived from individual circuits, critical components within the building 104 or its zones, or those systems that externally serve a building or group/network of buildings. In another embodiment, additional measurements of vibration, temperature, sound from critical motor components, and the like within buildings 104 or wherever motors are used for industrial or manufacturing processes are used to gauge the health of motor and equipment functions within the facility 104 .
  • the energy search engine 102 receives in a substantially continuous way dynamic data relating to energy usage from one or more of a Building Information Modeling (BIM) 106 , a power grid 112 , a utility company 114 , building management 116 , and an environmental service 118 .
  • BIM Building Information Modeling
  • the BIM 106 can provide, but is not limited to specifications for the systems, subsystem, and components 104 a installed in the facility 104 , specifications for the systems, subsystem, and components with a higher energy rating that could have been installed in the facility 104 , and the like.
  • the power grid 112 can provide, but is not limited to a dynamic grid response to renewable energy sources, plug-ins, projected grid demand, grid load information, energy supply capacity, and the like.
  • the utility company or other sellers of energy 114 can provide, but are not limited to utility rate tariffs, real-time energy pricing, price bids, and the like.
  • the building management 116 can provide, but is not limited to facility and zone level scheduling of the facility 104 , occupancy information, system status information (e.g. open doors, open windows, open shutters, etc.), and the like.
  • the environmental service such as a weather service, can provide, but is not limited to dynamic weather data for the location of the facility 104 , projected weather for the location of the facility 104 , sever weather alerts, geographical factors, and the like.
  • the energy search engine 102 analyzes the static data and the dynamic data received in the substantially continuous way and provides a substantially continuous energy assessment.
  • the substantially continuous energy assessment include but are not limited to reports, benchmark results, energy performance assessments for the facility 104 , network of facilities 104 or any of its systems, subsystems, and components 104 a , site energy carbon footprint, source energy carbon footprint, source energy assessment, building and systems commissioning strategies, lighting strategies, data center and Telco strategies, water performance assessment, gas performance assessment, energy retrofit assessment, renewable energy assessment, and the like.
  • the energy search engine 102 transmits commands to the control systems 104 c to control the systems, subsystems, and components 104 a to reduce or optimize the energy usage of the facility 104 .
  • the energy search engine 102 controls the systems, subsystems, and components 104 a in a substantially continuous way.
  • substantially continuous comprises within a length of time or not to exceed a length of time which occurs at regular intervals.
  • data received in a substantially continuous way comprises data that is received within a definite length of time marked off by two instances.
  • data received in a substantially continuous way is data that is received at regular time intervals, where the time interval does not exceed a pre-defined time interval.
  • the time interval is approximately within a pre-defined time interval.
  • the time interval is based at least in part on the type of information received. For example, weather can be received substantially continuously every hour, smart meter information can be received substantially continuously every 15 minutes, and grid load can be received substantially continuously every time interval which does not exceed an hour.
  • providing substantially continuous energy assessment comprises providing the energy assessment within a pre-defined time interval, not to exceed a pre-defined time interval, or the like.
  • controlling in a substantially continuous way to optimize energy usage comprises sending commands to the control systems 104 c or the like within a pre-defined time interval.
  • the time interval is based at least in part on the specific system being controlled.
  • the energy search engine may direct the facility 104 to shed or redistribute power at an interval not to exceed 5 minutes, while directing the blinds to raise or lower at an interval not to exceed 2 hours.
  • substantially continuous time intervals comprise one of time intervals not to exceed 1 minute, time intervals not to exceed 5 minutes, time intervals not to exceed 15 minutes, time intervals no to exceed 1 hour, time intervals not to exceed 1 day, and time intervals not to exceed 1 week.
  • FIG. 2 illustrates an exemplary block diagram of an embodiment of the energy search engine 102 .
  • the energy search engine 102 comprises one or more computers or processors 202 and memory 204 .
  • the memory 204 comprises modules 206 including computer-executable instructions, that when executed by the computer 202 cause the energy search engine 102 to analyze the energy data and provide the substantially continuous energy assessment metrics.
  • the memory 204 further comprises data storage 208 including one or more databases to store the dynamic and or static data by the modules 206 to analyze energy usage and provide energy usage assessments.
  • the computers 202 comprise, by way of example, processors, Field Programmable Gate Arrays (FPGAs), System on a Chip (SOC), program logic, or other substrate configurations representing data and instructions, which operate as described herein.
  • the processors 202 can comprise controller circuitry, processor circuitry, processors, general-purpose single-chip or multi-chip microprocessors, digital signal processors, embedded microprocessors, microcontrollers and the like.
  • the memory 204 can comprise one or more logical and/or physical data storage systems for storing data and applications used by the processor 202 .
  • the memory 204 can further comprise an interface module, such as a Graphic User Interface (GUI), or the like, to interface with the user interface 108 .
  • GUI Graphic User Interface
  • the energy search engine 102 calculates a score reflecting the energy performance of the facility 104 .
  • the score is a weighted average of one or more metrics that are calculated based at least in part on one or more energy variables.
  • energy variables include, but are not limited to the time history of the energy (power, water, gas) consumed by the facility, the carbon equivalent of energy used at the site, the carbon equivalent of the energy generated at the source, the time history of the ambient weather conditions, the facility activity type, the facility total square footage, the facility occupied square footage, the volume of free space in the facility, the facility schedule, the facility activity levels (e.g.
  • any existing local (or on site) generation systems e.g. thermal solar, thermal storage, energy storage, and the like
  • any existing local alternative energy systems e.g. thermal solar, thermal storage, energy storage, and the like
  • the potential for local renewable generation the potential for local alternative energy systems
  • the type of construction material used the type of energy systems used, the facility design specifications, required air change, measured air changes, the type of energy management system installed, the performance of any existing energy management system, data from any existing energy, environmental and security monitoring systems, and the like.
  • the facility 104 and/or building 104 and/or subsystems 104 a refer to one or more of the facility, its systems, subsystems, and components, multiple buildings comprising the facility located locally or remotely, and a network of facilities in the following discussion.
  • the score or energy metrics are calculated based on historical energy data for the past week, month, quarter, year or longer time period.
  • data from one time period is used to backfill data missing from another time period. For example, if the data for February of 2012 is missing, then it can be backfilled using the following:
  • X 1 is the average workday energy consumption for January 2011, X 2 is the average workday energy consumption for January 2012, and Y 1 is the 15-minute, hourly, daily, or weekly energy consumption for workdays in February 2011, and Y 2 is the 15-minute, hourly, daily, or weekly energy consumption for the corresponding workdays in February 2012.
  • the above method can be used to backfill missing energy data for off days.
  • the same missing data for February 2012 can be backfilled using the following:
  • Y 2 2*( X 1 Z 2 +Z 1 X 2 )/( X 1 Z 1 )* Y 1
  • X 1 is the average workday energy consumption for January 2011, X 2 is the average workday energy consumption for January 2012, Z 1 is the average workday energy consumption for March 2011, Z 2 is the average workday energy consumption for March 2012, and Y 1 is the 15-minute, hourly, daily, or weekly energy consumption for workdays in February 2011, and Y 2 is the 15-minute, hourly, daily, or weekly energy consumption for the corresponding workdays in February 2012.
  • the above method can be used to backfill missing energy data for off days.
  • the energy used by the facility is calculated using the following equation:
  • energy sourced by the utility is energy that is purchased from the utility company.
  • the energy generated on site (locally) is energy generated by local energy generation systems as solar PV, wind turbines, fuel cells, gas power plant, etc.
  • the energy stored on site is energy that is purchased from the utility or generated locally but is stored at the time of purchase or generation for later use in energy storage systems such as batteries, compressed air, pumped water, thermal storage, etc. If the energy storage systems are discharging, then the sign of the stored energy in the equation above is negative.
  • Each of the components in the equation above can be measured, calculated or estimated.
  • the energy score and metrics can be proportional to the energy performance of a facility relative in a specific time period compared to its performance in a base period.
  • the base period is one year.
  • the metric can be proportional to the composition of source energy (solar PV, utility power, fuel cell, solar thermal, gas generator, energy storage, etc.) relative to an optimum composition of source energy for a facility, given the measured, calculated or estimated energy usage of the facility, the type of systems in the facility, the facility schedule, the facility location, the ambient weather conditions, and the like.
  • source energy solar PV, utility power, fuel cell, solar thermal, gas generator, energy storage, etc.
  • the metrics include but are not limited to the facility electric energy use index (kwHr/ft 2 ), the facility gas use index (therms/ft 2 ), and the facility electric demand index (kw/ft 2 ).
  • the metric can be proportional to the equivalent greenhouse gas emissions of the energy used at the facility 104 , proportional to the energy generated using local renewable energy systems, proportional to the energy generated using alternative fuel systems (e.g. hydrogen fuel cells, or the like), proportional to the use of alternative energy systems, proportional to the ratio of energy used during off hours to the energy used during work hours, proportional to the ratio of energy used during work days to the energy used during off days, proportional to the minimum rate of energy consumption during a period of time (day, month, year, etc.), proportional to the simultaneous heating and cooling that may be occurring in the facility 104 , or the like.
  • alternative fuel systems e.g. hydrogen fuel cells, or the like
  • the metric can be proportional to the correlation between energy used for heating energy and heating requirements, proportional to the correlation between the energy used for cooling and the cooling requirements, proportional to the estimated, calculated, or measured energy used for heating divided by the amount of heating affected, proportional to the estimated, calculated or measured energy used for cooling divided by the amount of cooling affected, and the like.
  • Heating requirements, cooling requirements, amount of heating affected, or the amount of cooling affected can be calculated using, but not limited to one or more of the following: ambient weather, ambient environmental conditions, desired internal temperature, ventilation rates, outside air circulation, recirculation rates, recirculated air, energy consumed by loads inside the facility 104 , heat generated by other sources inside the facility 104 , heat entering or leaving the facility 104 through mass or thermal transfer, and the like.
  • the heating degree hours, a difference between ambient temperature and supply air temperature inside the facility for each hour can be used as a measure of affected heating (heating kWhr/degree heated).
  • the cooling degree hours, a difference between the ambient temperature and the supply air temperature inside the facility 104 for each hour can be used as a measure of affected cooling (cooling kWhr/degree cooled).
  • the required heating enthalpy hours, a difference between ambient enthalpy and a target temperature and humidity inside the facility can be used as a measure of required heating.
  • the required cooling enthalpy hours, a difference between ambient enthalpy and a target temperature and humidity inside the facility can be used as a measure of required cooling.
  • the affected heating enthalpy hours, a difference between ambient enthalpy and supply air enthalpy inside the facility for each hour can be used as a measure of affected heating (heating energy kWhr/kJ heated).
  • the cooling enthalpy hours, a difference between the ambient enthalpy and the supply air temperature inside the facility 104 for each hour can be used as a measure of affected cooling (cooling kWhr/KJ cooled).
  • FIG. 3 is a flow chart of an exemplary energy search engine process 300 to assess the amount of energy used for cooling and the amount of excessive cooling affected.
  • the amount of energy used for cooling during workdays during a year can be estimated from the profile of total energy used during the year.
  • the interval energy (energy consumed at regular intervals, typically 15 or 30 minutes, or any other regular interval) for a 12 month period is used.
  • the average energy and average cooling degree requirement, respectively, for each time interval during work days is calculated for each month.
  • the minimum energy profile for workdays in calculated and at block 316 , the average energy used for cooling is calculated as the difference between the energy profile and the minimum energy used during workdays.
  • the minimum energy required to cool the facility by one degree is estimated for each time interval during workdays.
  • the minimum energy needed for cooling during the year is calculated from the results of blocks 322 and 324 .
  • the amount of energy used for excessive energy i.e. the amount of energy wasted due to excessive cooling is estimated.
  • the energy profile for the year is calculated assuming the cooling and heating systems are at their peak efficiency all year long. The process can be repeated for time intervals during off-days.
  • FIG. 4 is an exemplary substantially continuous excessive cooling performance assessment 400 .
  • the performance assessment 400 is a topographical map of the facility 104 showing estimated excessive cooling energy for an average hour throughout the day in each month for a year.
  • the excessive cooling is estimated by considering the load inside the building and the cooling requirement from the ambient weather, as described in FIG. 3 .
  • the performance assessment 400 indicates total cooling costs being estimated at $117,000, with $75,000 in overcooling between 10 AM and 3 AM, and $19,000 in overcooling between 3 AM and 10 AM. Overcooling is estimated at $96,000, being up to 76% of the cooling costs.
  • color can be used to indicate energy intensity, where brighter shades of a color indicate greater energy intensity and darker shades of the color represent lighter energy intensity (or vice versa).
  • the metric can be proportional to the time history of the number of air changes, proportional to the fraction of outside air introduced to the facility, proportional to the fraction of return air recirculated, where return air is air that is exhausted from the facility using exhaust fans, proportional to the air quality inside the facility, proportional to facility peak demand and the load duration curve, which represents the time spent at each power level from the lowest demand to the peak demand, proportional to the level of compliance of the facility 104 or any of its subsystems 104 a with one or more of existing and/or future energy regulations, standards, codes, specifications and guidelines, and the like.
  • the metric can be proportional to the level of energy demand reduction or load shedding initiated in response to a request from the grid or utility.
  • the energy demand reduction can be calculated relative to a baseline that is adjusted for one or more of the following factors: ambient weather conditions, ambient environment conditions, changes in facility schedule, changes in facility activity, changes in facility occupancy, and the like.
  • the projected energy demand reduction for the facility 104 can be calculated by estimating the amount of energy that will be used for cooling as described above and assuming that a certain percentage of the cooling energy will be reduced.
  • the metric can be proportional to the change in energy consumption of the facility 104 or any of its energy subsystems 104 a compared to an energy baseline, an energy benchmark, a computed energy usage, an estimated energy usage or a projected energy usage.
  • an energy baseline can be calculated for any measured or calculated metric, and correlated with ambient weather conditions, facility usage, and facility schedule.
  • the calculated baseline can be used to project the value of the metric given projections of ambient weather conditions, facility usage, facility schedule, or changes in energy systems.
  • the metric can be proportional to the cost of total energy used at the facility 104 , proportional to the cost of gas energy used at the facility, proportional to the cost of energy used at the facility 104 from renewable energy sources, proportional to the cost of energy used at the facility 104 from alternative energy sources, proportional to the total cost to generate the energy at the source, proportional to the cost of delivering the energy from the source to the facility 104 , proportional to the total cost of electric energy used at the facility 104 , proportional to the peak electric energy demand costs at the facility 104 , proportional to the electric energy consumption costs at the facility 104 , proportional to the avoided energy consumption costs, proportional to the avoided peak demand costs, or the like.
  • the metric can be proportional to the energy consumed in the facility 104 , proportional to the total energy that can be delivered to the facility 104 , proportional to the total energy that can be generated in the facility 104 , proportional to the total energy that can be reduced in the facility 104 , proportional to the reliability of the sources of energy to the facility 104 and the total uptime of one or more of the facility's energy sources, proportional to the power quality (e.g.
  • any of the metrics can be calculated every year, month, week, day, hour, or in a substantially continuous manner.
  • any of the metrics can be calculated in the cloud-based server 102 and can be offered as a subscription-based service.
  • FIGS. 5 , 6 , and 7 are flow charts of exemplary search engine processes to actively process energy consumption data, environmental data, and building use data, examples of which are described above, in a plurality of time frames, including real time, to provide one or more of the metrics related to the minimum energy required by the facility 104 and its critical subsystems 104 a for a unique geographic location, use, environment, and occupancy associated with the facility 104 , examples of which are described above.
  • the energy search engine algorithms provide energy and sustainability ratings for commercial, municipal, campus, state, and federal buildings. Another embodiment provides carbon footprinting of buildings and facilities. Yet another embodiment evaluates the value of real property by evaluating its energy consumption and effectiveness and efficiency of installed systems and components. A further embodiment evaluates the instant demand response, load shedding, load shifting, and additional local generating potential of buildings, facilities, campuses and their systems. A yet further embodiment guides and evaluates actionable energy efficiency and demand response improvement measures, equipment retrofits, and commissioning strategies. In an embodiment, the technology enables compliance with legislated energy efficiency mandates and goals.
  • FIG. 5 is a flow chart of an exemplary energy search engine process 500 to assess energy usage for the facility 104 .
  • the facility 104 and/or building 104 and/or subsystem 104 refer to one or more of the facility, its systems, subsystems, and components, multiple buildings comprising the facility located locally or remotely, and a network of facilities in the following discussion.
  • the process 500 receives substantially continuous measurements of actual energy consumption of the facility 104 .
  • the process 500 receives measurements related to the actual energy consumption of the facility 104 from the measurement devices 104 b . Examples of the measurements of actual energy consumption are smart meter readings, electric meter readings, gas meter readings, current measurements, facility energy variables as described above, and the like.
  • receiving substantially continuous measurements comprises receiving measurements at least every 15 minutes. In another embodiment, receiving substantially continuous measurements comprises receiving measurements at least every 5 minutes. In a further embodiment, receiving substantially continuous measurements comprises receiving measurements at least every 1 hour.
  • the process 500 receives substantially continuous measurements of ambient conditions.
  • the energy search engine 102 can receive weather reports including the outside air temperature, outside air humidity, cloud coverage, UV index, precipitation level, evaporative transpiration (ET) number, weather forecast, and the like.
  • the status of doors, windows, and shutters associated with the facility 104 can change with time and can be received in a substantially continuous manner.
  • the process 500 obtains a target energy consumption of the facility 104 based at least in part on the ambient conditions.
  • Target energy consumption can be a calculated energy consumption based on baseline performance, desired environmental conditions inside the facility (temperature, humidity, air quality, etc.) projected facility schedule, projected facility usage, and projected weather conditions.
  • Average facility energy consumption at a given ambient condition and facility usage level can be calculated based on historic data. This average can be set as a target for the facility when similar weather and facility usage are anticipated.
  • the process 500 compares the measurement of the actual energy consumption with the target energy consumption for the facility 104 , and at block 518 , the process 500 calculates a substantially continuous energy performance assessment based at least in part on the comparison of the measurement of the actual energy consumption with the target energy consumption.
  • Metrics found on the performance assessment can include but are not limited to one or more of total gas and electric current energy costs per square foot of the facility 104 , baseline electric energy rating, peak electrical energy rating, gas energy rating, efficiency of heating gas use, simultaneous heating and cooling, nighttime power index, weekend power index, EMS scheduling, full time loading, an overall performance assessment, energy wasted annually, range of estimated energy wasted annually, cost to produce energy at the source, cost to deliver energy to the facility 104 , waste as a percent of total energy used, cost of annual gas and electric energy wasted annually, electrical energy carbon footprint, gas energy carbon footprint, total energy carbon footprint, target energy usage in cost per square foot of the facility 104 , annual energy savings target, historical electricity and gas usage, historical monthly peak demand for electricity, historical energy map showing annual energy usage versus the time of the day the usage occurred, wasted heating based on a comparison of heating requirements and the actual energy used for heating, simultaneous heating and cooling based on an estimated energy used for cooling during business hours and an estimated energy used for heating during business hours, wasted cooling during business hours based on
  • the metric can be proportional to the level of compliance with one or more energy standards, such as, for example, ISO 50001, LEED Silver, LEED Gold, LEED Platinum, and the like.
  • the metric can be proportional to the cost of bringing the facility to compliance with one or more energy standard.
  • the metric can be proportional to the energy savings (in consumption kWhr, demand kW or energy costs $) that can be realized by bringing the facility to compliance with one or more energy standard.
  • the metric can be proportional to the absolute efficiency of the energy subsystem or facility 104 .
  • the absolute efficiency of the energy subsystem 104 can be the ratio between the measured, calculated or estimated energy consumed by the subsystem 104 and the energy the subsystem 104 would have consumed if it operated at the theoretical limits of the subsystem 104 .
  • the metric can be proportional to the achievable efficiency of the energy subsystem or facility 104 .
  • the achievable efficiency of the energy subsystem 104 can be the ratio between the measured, calculated or estimated energy consumed by the subsystem 104 and the energy the subsystem 104 would have consumed if it operated at the highest efficiency achievable by such subsystems 104 .
  • the metric can be proportional to the design efficiency of the energy subsystem or facility 104 .
  • the design efficiency of the energy subsystem or facility 104 can be the ratio between the measured, calculated or estimated energy consumed by the subsystem 104 and the energy the subsystem 104 would have consumed if it operated per the manufacturer's design specification.
  • the metric can be proportional to the savings realized (consumption kWHr, demand KW, energy costs in $) if one or more energy subsystems is operating at its theoretical, absolute, or design efficiency.
  • FIG. 6 is a flow chart of an exemplary energy search engine process 400 to dynamically assess energy efficiency for the facility 104 .
  • Energy search engine algorithms analyze measured energy data versus computed minimum required energy to provide, for example, energy efficiency ratings, energy consumption profiles, energy load factors, critical component assessment, and life cycle analysis of critical components.
  • the process 600 obtains a minimum energy consumption for the facility 104 .
  • Obtaining the minimum energy consumption at block 410 comprises obtaining the theoretical energy consumption based at least in part on models of the installed building systems, subsystems, and components 104 a at block 612 .
  • obtaining the minimum energy consumption comprises obtaining a theoretical energy consumption based at least in part on ideal models or the theoretical limits of the installed building systems, subsystems, and components 104 a.
  • Obtaining the minimum energy consumption at block 610 further comprises obtaining an achievable minimum energy consumption based at least in part on specifications for high energy efficiency equivalents of the installed building systems, subsystems, and components 104 a at block 614 and obtaining a designed minimum energy consumption based at least in part on specifications and cumulative loads for the installed building systems, subsystems, and components 104 a at block 616 .
  • the process 600 receives substantially continuous measurements of the facility energy consumption.
  • the measurements are provided by the measurement devices 104 b .
  • measurements are calculated.
  • the measurements are estimated.
  • the process 600 compares the minimum energy consumption to the measurement of the facility energy consumption in a substantially continuous way. Comparing at block 630 comprises comparing the theoretical minimum energy consumption to the measurement of the facility energy consumption at block 632 , comparing the achievable minimum energy consumption to the measurement of the facility energy consumption at block 634 , and comparing the designed minimum energy consumption to the measurement of the facility energy consumption at block 636 .
  • the process 600 calculates a substantially continuous energy performance assessment for the facility 104 .
  • Calculating the substantially continuous energy performance at block 640 comprises determining a theoretical energy efficiency at block 642 , determining an achievable energy efficiency at block 644 , and determining a designed energy efficiency at block 646 .
  • the absolute or theoretical efficiency metric for a fan can be calculated from a measurement, estimation or calculation of one or all of the following: fan upstream pressure, fan downstream pressure, flow temperature, fan speed, mass flow rate through the fan, volumetric flow rate through the fan, and/or energy consumed by the fan.
  • the fan's absolute efficiency is then calculated by dividing the energy consumed by the energy that should have been consumed by the fan if it operated at its theoretical efficiency under the same conditions of upstream pressure, downstream pressure, fan speed, flow temperature, volumetric flow rate, or mass flow rate through the fan.
  • the achievable efficiency metric for a fan can be calculated from a measurement, estimation or calculation of one or all of the following: fan upstream pressure, fan downstream pressure, flow temperature, fan speed, mass flow rate through the fan, volumetric flow rate through the fan, and/or energy consumed by the fan.
  • the fan's achievable efficiency is then calculated by dividing the energy consumed by the energy that should have been consumed by the highest performing fan available operating under the same conditions of upstream pressure, downstream pressure, fan speed, flow temperature, volumetric flow rate, or mass flow rate through the fan.
  • the design efficiency metric for a fan can be calculated from a measurement, estimation or calculation of one or all of the following: fan upstream pressure, fan downstream pressure, flow temperature, fan speed, mass flow rate through the fan, volumetric flow rate through the fan, and/or energy consumed by the fan.
  • the fan's design efficiency is then calculated by dividing the energy consumed by the energy that should have been consumed by the fan operating per the manufacturer's design specifications under the same conditions of upstream pressure, downstream pressure, fan speed, flow temperature, volumetric flow rate, or mass flow rate through the fan.
  • the theoretical efficiency of a facility envelope on hot days can be calculated assuming a perfectly insulated facility envelope that blocks all radiant heat transfer into the facility 104 , all convective heat transfer into the facility 104 , and all infiltration of mass in and out of the facility 104 .
  • the heat generated in the facility 104 is calculated from a measurement, estimate, or calculation of the energy consumed in the facility 104 , such as indoor lighting, plug load, heating gas, etc., and the heat generated by occupants and processes in the facility 104 .
  • the heat removed from the facility 104 can be calculated from a measurement, estimate, or calculation of the difference between enthalpy of the ventilation and cooling air leaving the envelope and the enthalpy of the ventilation and cooling air entering the envelope.
  • the facility 104 can be assumed to be at constant operating temperature. For a perfectly insulated envelope at a constant internal temperature, the heat removed from the facility 104 is equal to the heat generated in the facility 104 .
  • the envelope efficiency on a hot day can be calculated as the ratio of the heat generated in the facility 104 divided by the heat removed from the facility 104 .
  • the design efficiency of a roof top packaged HVAC unit can be calculated by measuring the enthalpy (temperature, humidity and flow rate) of the air entering the HVAC system (fraction of return air+fraction of outside air), the enthalpy of the air leaving the HVAC system (supplied to the facility 104 ) and the energy consumed by the HVAC system.
  • the energy consumed by the HVAC is divided by the [enthalpy of air entering the HVAC—enthalpy of air leaving the HVAC] to yield a measured coefficient of performance (COP).
  • the measured COP is then divided by the design COP specified by the HVAC manufacturer at the given HVAC load and the resulting ratio comprises the design efficiency of the HVAC system.
  • FIG. 7 is a flow chart of an exemplary energy search engine process 500 for demand side analysis.
  • the energy search engine 102 matches varying demand side load requirements to supply side generating and grid capability to establish relative value energy pricing.
  • the exemplary process 700 quantifies the effectiveness of energy improving measures, such as rating the energy efficiency and carbon footprint of the facility 104 and/or any or all of its systems 104 a (individually or collectively) to determine opportunities to introduce energy efficiency, install retrofits, commission facilities for monitoring based commissioning (MBCx), retrocommissioning (RCx), continuous commissioning, and the like, and provide peak reduction and demand response strategies and actions.
  • energy improving measures such as rating the energy efficiency and carbon footprint of the facility 104 and/or any or all of its systems 104 a (individually or collectively) to determine opportunities to introduce energy efficiency, install retrofits, commission facilities for monitoring based commissioning (MBCx), retrocommissioning (RCx), continuous commissioning, and the like, and provide peak reduction and demand response strategies and actions.
  • the process 700 obtains an energy usage benchmark for the facility 104 .
  • the energy usage benchmark is an energy usage point of reference across a network of facilities that share something in common against which the energy usage of the facility 104 may be compared.
  • the benchmark could be one of an Energy Star® rating, historical energy use of the facility 104 , energy performance of buildings in a specific geographic area, energy performance of buildings of a certain size, energy performance of buildings of a certain activity, energy performance of buildings with a certain type of cooling technology, energy performance of buildings with a certain type of heating technology, energy performance of buildings with a certain type of construction material, energy performance of buildings with a certain brand and model of EMS, energy performance of buildings with a certain energy certification, energy performance of buildings with a certain energy rating, energy performance of buildings with a certain local energy source (e.g. solar PV), or the like.
  • Energy Star® rating historical energy use of the facility 104
  • energy performance of buildings in a specific geographic area energy performance of buildings of a certain size, energy performance of buildings of a certain activity, energy performance of buildings with a certain type of cooling technology, energy performance of buildings with a certain type of heating technology, energy performance of buildings with a certain type of construction material, energy performance of buildings with a certain brand and model of EMS, energy performance
  • the process 700 receives substantially continuous measurements of actual energy consumption for the facility 104 before installation of energy improvement measures.
  • the measurements are obtained from the measurement devices 104 b.
  • the process 700 establishes a first baseline of energy usage for the facility 104 based at least in part on the measurements of actual energy consumption received before the installation of the energy improvement measures.
  • establishing the baseline before installation comprises obtaining an expected energy usage for the facility which has installed systems, subsystems, and components 104 c , and a load profile.
  • the baseline is established by recording the energy performance of the facility over a period of time, e.g. 3 months or 1 year. Multiple baselines can be calculated, such as for night hours on work days, morning hours on work days, afternoon hours on work days, night hours on off days, morning hours on off days, afternoon hours on off days.
  • baselines can be calculated, including, but not limited to total energy consumption (kWhr), electrical energy consumption (kWhr), electrical demand (kW), gas consumption (therms), energy used for lighting (kWhr), demand due to lighting (kW), energy used for cooling (kWhr), demand due to cooling (kW), and the like.
  • Baselines can also be normalized with ambient weather conditions, cooling degree hours, heating degree hours, facility usage levels, facility occupancy, etc.
  • the baseline of energy consumed (kWhr) during morning hours on work days could be the average consumption during morning hours for all workdays of a certain segment or entire segment of the baseline calculation period.
  • the consumption baseline can be normalized to cooling degree hours by dividing the average consumption for each of the morning hours on work days with the average cooling degree hour for each of those hours.
  • the process 700 compares the benchmark with the baseline established before the installation of the at least one energy improvement measure.
  • the process 700 receives substantially continuous measurements of actual energy consumption for the facility 104 after installation of at least one energy improvement measure.
  • the measurements are obtained from the measurement devices 104 b.
  • Examples of energy improvement measures are, but not limited to, installing a renewable energy system, retrofitting equipment, commissioning, load shifting, load shedding, installing energy storage, installing LED lighting systems, installing variable frequency drive (VFD) systems, installing new windows, installing new wall insulation, replacing inefficient boilers, upgrading the insulation of hot and cold water pipes, installing economizer systems, installing evaporative cooling systems, adding circulation fans, changing the location of supply and return ventilation air ducts, installing pool covers, installing thermal storage systems, installing shades and awnings, and the like.
  • VFD variable frequency drive
  • the process 700 establishes a second baseline based at least in part on the measurements of actual energy consumption received after the installation of the energy improvement measures.
  • establishing the baseline after installation comprises obtaining an energy usage for the facility which has installed systems, subsystems, and components 104 c , and a load profile.
  • the process 700 compares the first baseline established before installation of the at least one energy improvement measure with the baseline established after installation of the at least one energy improvement measure.
  • the process 500 compares the benchmark with the baseline established after installation of the at least one energy improvement measure.
  • the process 700 quantifies the effectiveness of the at least one energy improvement measure.
  • the process 700 determines the impact of the at least one energy improvement measure against the first baseline of energy usage for the facility 104 .
  • the process 700 determines the impact of the at least one energy improvement measure against the benchmark for the facility 104 .
  • quantifying the effectiveness of the at least one energy improvement comprises determining one or more of a payback calculation, a payment of an incentive, a valuation of real property for purposes that include projecting the value of operational strategies and behaviors or equipment replacements that result in altered real property valuations, a carbon offset used in carbon trading, and the like.
  • FIG. 8 is an exemplary substantially continuous energy performance assessment 800 .
  • the assessment 800 includes information about the current energy usage of the facility 104 , rating of energy metrics, and targeted energy usage.
  • the metrics for current energy usage include the total gas and electric energy cost per square foot of the facility 104 ; low and high ranges for the annual estimated energy wasted, the percent of wasted energy out of the total energy used, the cost of the annual energy wasted; and carbon footprint metrics, such as the carbon footprint of the electrical energy used, the carbon footprint of the gas energy used, and total carbon footprint for the facility 104 .
  • Energy metrics such as the baseline energy rating, the peak electrical energy rating, the gas energy rating, the efficiency of the gas used for heating, the occurrence of simultaneous heating and cooling, the nighttime power index, the weekend power index, the energy management system scheduling, and the full time loading levels, are rated on a poor, average or good scale.
  • the assessment 600 includes a comparison of energy usage, energy savings, and carbon reductions for the current energy implementation of the facility with at least two suggested energy reduction implementations to provide a better target and a best target.
  • the energy search engine 102 provides the energy performance of a network of facilities 104 on a multi-dimensional map.
  • the multi-dimensional map plots one or more metrics on a geographical map with colors, coordinates and shapes. For example, a metric proportional to the fraction of a facility's energy demand that can be shed (reduced) at any given time can be plotted on a geographical map of the area. Every facility 104 can be indicated by a circle, with the size of the circle proportional to the levels of demand (in kW) that can be shed at each facility 104 and the color of the circle indicating the percent facility demand that can be shed. Similar maps can be used to animate the effect of a cloud passing on the potential for demand reduction across a network of facilities 104 based on demand projections calculated using the energy search engine 102 .
  • FIG. 9 is an exemplary continuous yearly key performance indicator chart 900 and FIG. 10 is an exemplary continuous monthly key performance indicator chart 1000 .
  • Both charts 900 and 1000 track key performance indicators, including but not limited to baseline electric use index, peak electrical energy use index, gas energy use index, heating gas efficiency consistency, simultaneous heating and cooling, nighttime power index, weekend power index, EMS scheduling, and full-time loading, as described above.
  • Chart 900 indicates the year to date energy performance
  • chart 1000 indicates the energy performance for a month.
  • the indicator bars are in color to represent score quality/level where red indicates a poor score, green indicates a good score, and yellow indicates a mediocre score that could be improved.
  • one or more alerts are associated with one or more of the metrics. Exceeding, or dropping below a specified metric value and for a specified amount of time will signal an alert and cause an action to be taken.
  • the action may include the closure of relays, a command to be sent via wired or wireless Ethernet®, RF module, machine interface, wired connection, or the like.
  • the action may also include a message to be sent to a computer desktop, a mobile device, a mobile application, a Facebook® page, a Twitter® account, a message board, a broadcast system, or the like.
  • one or more alerts are associated with one or more of the metrics.
  • the alerts can be initiated when a metric exceeds or drops below a certain value for a specified amount of time if one or more other metrics, measured variables, such as, for example, temperature, pressure, humidity, flow, current, or the like, estimated variables, calculated variables, and/or any mathematical combination of the metrics and/or variables are at, above, or below a specific value for a specified amount of time, where the specific value can be a function of one or more metrics, measured variables, estimated variables, calculated variables, any mathematical combination of the variables, and/or any mathematical combination of the metrics.
  • the energy search engine 102 can report a daily maintenance task list, where the energy search engine 102 generates a list of required maintenance tasks sorted by criticality, energy performance impact, cost performance impact, impact on carbon footprint, cost to fix, and the like. Further, an embodiment of the energy search engine 102 can report equipment diagnostics such that the energy search engine will continuously diagnose and rate the performance of each of the building's equipment 104 a.
  • Further embodiments of the energy search engine 102 determines and reports on when and where a building or its energy consuming or energy generating subsystems are operating properly or are in need of maintenance, tuning, load shifting, load shedding, or equipment replacement based at least in part on data level flags that correspond with incremental level changes in energy consumed or generated.
  • the energy search engine 102 uses day ahead projected hourly weather data and projected facility schedule and usage to predict energy performance (e.g. kWhr consumption, kW demand, efficiency metrics, etc.) based on a calculated baseline for the facility 104 , and correlations of energy baseline with ambient weather, facility schedule and facility usage.
  • energy performance e.g. kWhr consumption, kW demand, efficiency metrics, etc.
  • the energy search engine 102 uses day ahead projected hourly weather data, projected facility schedule, projected facility usage, utility rate information, day ahead utility pricing information, day ahead grid information, day ahead energy cost information, to predict energy cost (kW demand cost, kWhr consumption cost, gas therm cost, water gallons cost, etc.) based on a calculated baseline for the facility 104 , and correlations of energy baseline with ambient weather, facility schedule and facility usage.
  • the energy search engine 102 provides data output that are useful to benchmark and evaluate real property energy consumption and carbon emissions/footprint for purposes that include projecting the value of operational strategies and behaviors or equipment replacements that result in altered real property valuations, and the like.
  • the energy search engine 102 provides data output that are useful for auditing compliance with existing and emerging legislation on energy use, carbon emissions, and for achieving energy reduction and carbon emission reduction goals at facilities.
  • the energy search engine 102 provides preplanned or instant actionable energy optimization strategies through activation of systems and circuits that shed and/or shift energy consumption and/or provide supplemental energy resources.
  • the energy search engine 102 can provide data output to Energy Management Systems (EMS) and/or Building Management Systems (BMS) and/or load control relays to respond with either instant or preprogrammed load shedding strategies, load shifting strategies, and supplemental energy supply strategies, according to certain embodiments.
  • EMS Energy Management Systems
  • BMS Building Management Systems
  • An embodiment of the energy search engine 102 can use cloud based NOC Baseline energy management to determine instant peak demand load shedding, load shifting, supplemental local generating resources, or the like. Embodiments of the energy search engine 102 can determine and/or control the demand side potential for adjusting loads and local energy supply for each facility, campus, or n aggregate of geographically dispersed facilities.
  • FIGS. 11 , 12 and 13 illustrate exemplary block diagrams of a system that integrates universally interoperable “smart grid envisioned” digital energy measurement, energy use analysis, carbon footprint analysis, greenhouse gas emission analysis, energy quality and availability analysis, data correction algorithms, data reduction algorithms, data encryption algorithms, data storage, data communication, and the digital and/or analog control of energy used and generated or the carbon footprint or greenhouse gas emissions that are generated in such processes. Implementations may selectively include one or more of the modules described in FIGS. 11 , 12 , and 13 .
  • One embodiment of the system provides universal real time, continuous, and autonomous digital measurement of local or remotely located and energized or de-energized electric circuits that range in voltage from 0 Volts, a de-energized state, to energized states of up to 600 VAC or VDC to electric grid circuits that employ voltage levels in the kilovolt range and electric circuits in phase configurations, such as single phase, split phase, three phase Delta, three phase Wye, and the like.
  • the measured and analyzed electric circuit data by Module 1301 ADC and Module 1301 C Energy Calculations comprises, for example, line-to-line and line-to-current voltage, powers (total, active, reactive), line-to-line and line-to-neutral current, power factor, fundamental and harmonic total energy per phase and for the sum of phases, fundamental and harmonic active energy per phase and for the sum of phases, fundamental and harmonic reactive energy per phase and for the sum of phases, frequency, and harmonics in 1-n circuits, and the like.
  • the real time digital energy and carbon footprint data reporting rates are varied and substantially lower than the energy data sampling rates from Module 1301 ADC in FIG. 13 .
  • This is due to application of an energy or environmental data reduction/data compression technique an embodiment of which is illustrated in FIG. 14 and applied to a typical circuit embodiment, such as one embodiment shown in FIG. 12 , comprising Data Gateway Module 1303 , Data Analysis Module 1304 , and Data Validation and Error Correction Module 1305 ; and another embodiment shown in FIG. 13 , comprising Data Gateway Module 1303 , Data Analysis Module 1304 , and Data Validation and Error Correction Module 1305 .
  • One embodiment of the energy or environmental data reduction/data compression technique enables use of low, medium, or high speed data communication channels to deliver accurate real time energy use and carbon footprint reporting about electric circuit energy or environmental conditions that are digitally measured through the use of a higher data sampling rate that typically ranges between approximately 10 samples/second and approximately 24,000 samples/second and on 1 to n measured electric circuits, devices, or appliances. In other embodiments, energy or environmental data sampling rates can be higher or lower.
  • FIG. 13 illustrates an embodiment of the energy measurement, analysis, communication, and control system.
  • the system comprises Digital Energy Measurement Modules 1301 , 1301 B, 1301 Phase; Current/power/voltage Measurement Modules 1301 C for energy calculation or energy data processing; and Modules 1303 , 1304 , 1305 for enabling energy data quantity reduction and data error correction without compromising the value of the measured data.
  • the energy data quantity reduction is based, at least in part, on application of an embodiment of the data reduction/data compression technique illustrated in FIG. 14 and filtering parameters, such as change in measured energy (+ ⁇ x %), rate of change of measured energy (t), and the like.
  • Data Analysis Module 1304 comprises ports where analog I/O analog sensor input and output control signals are exchanged with external sensors, and devices and digital I/O modules where external digital sensor input and control information are exchanged with outside sensors and devices.
  • Module 1306 provides compensated inputs for on-board and/or remote temperature sensors.
  • Module 1306 A provides inputs from other on-board and/or remote sensors such as pressure sensors, light sensors, acceleration sensors, tension-meters, flow sensors, gas sensors, microphones, and others.
  • Module 1307 provides PWM controller outputs Class D or Class E PWM control signals for the efficient control of external electric loads through direct connection with high speed electronic switches such as Triac's, MosFets, or IGFET's.
  • Module 1308 enables optional digital data encryption.
  • Module 1309 is used for digital data storage.
  • Module 1311 provides communications and control commands.
  • Module 1310 provides global positioning or location sensing (GPS).
  • Module 1312 is a web server and Module 1313 provides a human machine interface that can be an LCD display and keypad or keyboard, or the like.
  • Modules 1301 , 1301 B, 1301 Phase, 1301 C, and 1302 perform digital energy measurement and calculations in electric circuits that are located in any residence, building, commercial or industrial facility, in electric circuits that are used for powering electric powered transportation systems and/or charging electric vehicles, and energy that is provided or delivered by any and all electric generating power systems including solar, wind, fuel cell, micro turbines, or other types of electric generating devices and systems.
  • Measurement devices 1302 are associated with an electrical circuit and acquire an analog measurement of the current, voltage or power in the associated electrical circuit.
  • Measurement devices 1302 can be, for example, current transformers (CT) or the like.
  • CT current transformers
  • a current transformer 1302 produces a reduced current accurately proportional to the current in the circuit, which can be conveniently connected to measuring and recording instruments.
  • the current transformer 1302 also isolates the measuring instruments from what may be very high voltage in the monitored circuit.
  • Modules 1301 B comprise a latching double pole double throw gate and permit the automatic correction for the polarity of the measured current, should the current transformer 1302 be incorrectly installed.
  • the position of latching DPDT gate in Module 1301 B is determined by algorithms that operate on Modules 1305 and 1306 to evaluate when the voltage phase from Phase ADC Module 1301 and the current phase from Module 1301 of a given measurement circuit are separated by more than approximately 90 degrees and less than approximately 270 degrees. When this condition exists, the CT 1302 polarity is deemed incorrect and the position of latching DPDT gate is switched to the alternate position.
  • measurement devices 1302 are Rogowski coils, DC shunts, external digital current sensors, and external analog current sensors.
  • the system provides for the intermixed use of clamp on current measuring toroid transformers (CTs), Rogowski coils, DC shunts, or other current measuring devices.
  • CTs clamp on current measuring toroid transformers
  • Rogowski coils Rogowski coils
  • DC shunts or other current measuring devices.
  • ADC Modules 1301 convert the analog measurement from the measurement devices 1302 into a digital measurement for use in the system.
  • ADC Modules 1301 comprise an analog to digital converter, and at least one jumper.
  • the analog to digital converter is an Analog Devices IC, part number ADC 5169 , or the like.
  • the jumper configuration of the ADC Module 1301 is field selectable for the accurate measurement of 1 to n electric circuit phase configurations including single phase, split phase, three phase Delta, and three phase Wye. Phase configuration and association of the ADC module with its respective voltage phase can also be done in software in another embodiment.
  • Phase ADC Module 1301 couples to energized circuits with phase A, B, and/or C through resistive voltage dividers to digitally measure voltage amplitude and phase information.
  • the digital measurement information collected by the Phase ADC Module 1301 and the ADC Modules 1301 for 1 to n measured electrical circuits is sent to the Energy Calculation Module 1301 C.
  • the data sample rate ranges between approximately 10 samples/second to approximately 24 kilo samples/second.
  • Data reduction processes comprises Modules 1303 , 1304 , and 1305 utilizing an embodiment of the data reduction/data compression technique illustrated in FIG. 14 to substantially reduce the quantity of measured energy data that will be reported in real time, stored in memory data, or “pushed” to remote or cloud data base or “pulled” from a user inquiry.
  • the reduced quantity of energy data is based on previously defined or user defined data filtering parameters such as amount of change or rate of change of measured or calculated energy data.
  • the energy or environmental data quantity reduction technique that is shown in embodiments is broadly applicable to any energy or environmental device or network of devices.
  • Module 1303 samples the measured and calculated energy data from 1 to n ADCs at frequencies up to approximately 24,000 samples per second and sends the data to the Data Validation and Correction Module 1305 for determination of data accuracy.
  • Module 1304 analyses the energy data and also receives input from other internal and external sensors, Modules 1306 and 1306 A.
  • the Analysis Module 1304 also contains algorithm for reducing the number of points passed from Module 1305 and sends the formatted and substantially reduced quantity of measurement data to at least Modules 1311 , 1312 , 1313 , and 1309 . Based on comparison of this measured energy data and input from external environmental sensors, a control signal is sent to external devices for load control through the Analog I/O, Digital I/O, or PWM Controller Module 1307 .
  • Data Validation and Correction Module 1305 and Data Analysis Module 1304 for 1-n electric circuits provide real time digital analysis, validation, and auto correction of measured energy use and the quality of energy that is available at a power generating system that is found on the grid, smart grid, micro grid, residence, building, commercial facility, or for electric vehicle and electric powered transportation systems, according to certain embodiments.
  • Embodiments include electrical circuits powered by solar, wind, fuel cells, and any type of electric energy generator.
  • Module 1305 generates signals to control the Data Analysis Module 1304 when the voltage phase and the current phase of a given ADC Module 1301 exhibits more than approximately 90 degrees and less than approximately 270 degrees of phase differential.
  • Software used by the Data Analysis Module 1305 automatically identifies the correct phase that is associated with ADC Module 1301 and attaches this phase information to the correct energy information from ADC Module 1301 in the Data Validation and Error Correction Module 1305 .
  • Module 1306 does not configure the ADC Module 1301 . Instead the output data from a specific ADC Module 1301 is correctly attached to the correct phase data (A, B, C, . . . , n) from Phase ADC Module 1301 in Module 1305 .
  • Data Validation and Correction Module 1305 analyzes energy spikes to determine whether the spike is valid or is noise or corrupted data by acquiring additional samples at approximately the same time as the energy spike from Module 1303 which provides a data gateway. If the energy spike is a valid data measurement, the amplitude of the later acquired sample will be proportional to the energy spike. If the amplitude of the later acquired data is substantially different than the energy spike, Module 1305 determines that the energy spike was caused by noise, and treats the bad data as irrelevant and not worthy of being passed on for storage or “push” or “pull” communication.
  • Data Analysis Module 1304 processes measured energy data and compares it with external environmental and facility use information to derive and deliver electric load, device, and BMS/EMS control signals that are used to reduce or increase the electric energy in a specific circuit.
  • Data Error Correction Module 1305 processes measured energy data and compares it with prior data samples to insure that only relevant and accurate data is passed from Data Gateway Module 1303 to the Communication Module 1311 or to I/Os or to PWM Controller Module 1307 .
  • Data Encryption Module 1308 optionally encrypts the data that is derived from the measuring of all electric circuits and the location of circuits and measurement apparatus using secure and anti-hacking data encryption algorithms. Module 1308 can also be positioned just downstream of Module 1304 . In one embodiment, the Data Encryption Module 1308 uses anti tamper and anti hacking handshaking through the use of existing and emerging “smart grid” security data protocols.
  • Data Storage Memory Module 1309 stores the measured and digitized electric circuit data and measured electric energy quality data.
  • the Data Storage Memory Module 1309 provides a data buffer in case communication channel with the local or remote host is broken. The buffer decouples data sampling rates and data reporting rates. The data is stored locally at the required sampling rate until the communication lines are re-established. The data is then transferred to the host ensuring no data loss during communication breakdown.
  • Data Command and Communication Module 1311 implements predetermined and automated power reduction steps in energy use systems, smart appliances, or plug loads, based at least in part on the sensor data or on external demand response commands, according to certain embodiments.
  • Module 1311 provides the system with a unique address.
  • Module 1311 can push data to and/or pull data from 3rd party hardware or software including but not limited to structured query language (SQL) and/or SAP databases, Cloud based databases, and/or any type of computing device.
  • SQL structured query language
  • SAP databases Cloud based databases
  • Data Command and Communication Module 1311 pushes digitally measured electric circuit energy use data from 1-n circuits using protocols, such as, for example, Ethernet, ZigBee, PLC (Power Line Carrier), WiFi, WiMax, GSM to a remote device for real time analysis, for real time analysis and control, and/or to a remote structured query language (SQL), SAP, or cloud data base for storage, comparison of data, data mining, and data analysis for a multiplicity of purposes including billing and control of circuit circuits, smart appliances, electric vehicle and electric transportation systems.
  • the data can be delivered in XML, JSON, CSV, ASCII Strings, Binary Strings, and other formats.
  • the Data Command and Communication Module 1311 uses data clock synchronization and system clocking via Ethernet connection.
  • Other system connections include networked TCP/IP, client-server ModBus, BacNet, mesh network ZigBee wireless, WiFi, and WiMax that are operating either individually or concurrently to interact with 3rd party hardware and software.
  • the Data Command and Communication Module 1311 can simultaneously retain a copy of the measured data in onboard memory so that it can be viewed and accessed through the web server, according to certain embodiments.
  • the Data Command and Communication Module 1311 can also act as a slave to the acquisition host, such as a PC or the like, and communicate with the master host in one of several standard protocols, such as Ethernet protocols including ModBus and BacNet, for example.
  • the Module 1311 then acts as a translation of the protocol to serial communication.
  • the software Digital I/O module and Analog I/O module interfaces with the Data and Command Communication Module 1311 and with the Data Analysis Module 1304 to enable two-way software commands and interrupts to be exchanged between the Data Analysis Module 1304 and other BMS, BEMS, electrical vehicle charge stations, motor control systems, electrical control systems, smart appliances, programmable logic controllers, and the like.
  • the Temperature Sensor Compensation Module 1306 comprises calibration compensation look up tables to correctly utilize J or K thermocouple devices or wired or wireless thermostats for external local or remote measurement of temperature.
  • the PWM Controller Module 1307 is directed either by the Data Analysis Module 1306 or the Communication and Command Module 1311 to output a signal that consists of variable duty cycle pulses for load control through external high speed electronic switches such as high power MOSFETS, IGFETs, or other high speed electronic switching devices.
  • variable width pulses enable an external high speed electronic switch to control the electric energy and carbon footprint of any electric circuit or device including lighting circuits, motor circuits, air handling systems, HVAC compressor systems, and the like.
  • This embodiment when combined with an external high speed electronic switch refers to a Class D or Class E control system design.
  • the GPS Location Information Module 1310 interfaces with the Data and Command Communication Module 1311 and maps the location of each identified circuit board that has a unique MAC address.
  • Embodiments of the system of FIG. 11 can interface with “a smart device” “a smart appliance” “a smart building” “the smart grid”, renewable energy generators, and the like.
  • Analog/digital input/output I/O modules interface external sensors with the Data Analysis Module 1304 and the Data Command and Communication Module 1311 .
  • Sensors such as, for example, temperature sensors, humidity sensors, light sensors, occupancy sensors, motion sensors, acceleration sensors, vibration sensors, flow sensors, wind speed, heat sensors, gas sensors, gas spectrometers, laser sensors, humidity sensors, and other environmental sensors such as water flow, air flow, and gas flow provide data, including environmental, fuel type, or other data, to the Module 1304 or 1311 where the data is analyzed to calculate energy loads, determine possible energy reduction, identify malfunctioning systems, and/or the like.
  • Data Command and Communication Module 1311 implements predetermined and automated power reduction steps in energy use systems, smart appliances, or plug loads, based at least in part on the sensor data or on external demand response commands, according to certain embodiments.
  • the analog/digital I/O module interfaces with analog sensor input or digital input, analog or digital control circuit input, and output circuits for localized or remote control of relays, switches, programmable logic controllers, Building Management Systems (BMS), Building Energy Management Systems (BEMS), energy management and carbon footprint reporting systems, or the like.
  • the analog/digital I/O module interfaces with pulse counters from natural gas or water meters to integrate this additional data.
  • Web server 1312 and Human Machine Interface (HMI) 1313 provide the user with a Web-based user interface to the system of FIG. 13 .
  • HMI 1313 are 8, 16, or more segment LEDs or LCD panels, Keypads, Qwerty keyboards, and the like.
  • Embodiments provide user interface software that is accessible via Ethernet from personal computers (PCs) on the local area or wide area network.
  • the user interface allows the user to define the grouping of circuits to be measured and the locations for the circuits to be measured.
  • the system provides users with “drag and drop” functionality of circuits between groups and locations and “drag and drop” functionality for charting and reporting in a mobile app. Users can also, in one embodiment, view real time or stored and “pushed” or “pulled” energy use on Mobile platforms, such as for example, I-Phone, Android, BlackBerry, and the like.
  • the user can define minimum and maximum alert thresholds on all measured and calculated metrics, such as, voltage, current, energies, energy consumption rate, powers, power factor, cost, cost rate, energy efficiency metric, energy efficiency rating, and the like, for each circuit, group of circuits and location.
  • Comparative alert thresholds are used on metrics and for circuits where alerts are triggered by relative energy signature of circuits, groups and locations with each other or with established baselines or benchmarks.
  • Predictive alert thresholds are used on metrics and for circuits where alerts are triggered by projected energy consumption of a circuit, group or location.
  • the system provides the user with an alert through email, text message, Facebook, Twitter, voicemail, RSS feeds, multi-media message automatic alerts, and the like.
  • the alert is accompanied by a description of the trigger event including charts and reports on history before alert trigger and projected consumption and results.
  • the Web Server 1312 or the push capability the user is provided with animated and interactive desktop and mobile widgets for communicating energy consumption levels, energy ratings and critical energy conservation measures to end users.
  • the system communicates energy consumption levels, energy ratings and critical energy conservation measures to end users through RSS feeds with desktop tickers.
  • the electrical signature comprises at least one of a current and/or voltage waveform, current and/or voltage levels and peaks, power factor, other sensor information, such as temperature, vibration, acceleration, rotation, speed, and the like, of any “downstream” motor or pump.
  • An embodiment of the algorithm for Energy Data Reduction relates to bandwidth issues that will be encountered on the “smart grid” just as MPEG did for audio and video. With a plethora of measurement and reporting systems running at high speed, data collection will overload a network with data. Use of this technique or method on any chip, device, circuit or computer will reduce the communication bandwidth and processing requirements of said devices.
  • Embodiments can be in the form of an enclosure mounted adjacent to the power distribution panel and connected to said panel through a circuit breaker. Current sensors are plugged into the device.
  • Examples of a power distribution panel are a main switch board, a sub panel, a distribution panel/box, an MCCR, and the like.
  • An embodiment that is embedded in the power distribution system permits “plugging in” current sensors directly into the power distribution system where voltage information can be acquired internally from the panel's main power distribution bars or through a connection to a circuit breaker.
  • current sensors can also be embedded in the circuit breakers and can communicate measured energy data and control signals via wireless, wired or PLC to the embedded device.
  • current sensors can be self-powered from the pickup and rectification of electromagnetic fields or direct connection to energized circuits with or without re-chargeable battery backup and can communicate measured energy data or control signals via wireless, wired or PLC to the embedded device.
  • current sensors can be in the form of shunt resistors modules that are placed in series with the circuit breakers and can communicate measured circuit data and command controls via wireless, wired or PLC to the embedded device.
  • Embodiments can be installed in a circuit breaker with a built-in current sensor, CT or shunt, and a wireless, wired or PLC communication and command module or connect to an adjacent circuit breaker to send and receive information.
  • An embodiment can contain circuit protection and/or circuit breaking capability. Another embodiment can contain power factor correction capability. A further embodiment can contain frequency shifting and switching capability, such currently employed by variable frequency drives, Class D or Class E control circuits, and the like that use high speed electronic switching devices such as TRIAC or MOSFET, for example.
  • Embodiments can be in the form of a small enclosure mounted in the space to be monitored.
  • An embodiment can contain a wireless or wired communication module, occupancy sensor, occupancy counter, light sensor, temperature sensor, current sensor, gas sensor, heat sensor, rechargeable battery backup, solar PV panel for self powered systems, LED displays and the like.
  • thermostats both controlling and non-controlling, VAV controllers, mechanical or electrical shades, automatic door locks, door sensors, card scanners, RFID devices, generator controller, and the like.
  • inventions can be part of a mesh network in peer-to-peer, client-server, or master-slave configuration and yet further embodiments can be a Plug & Play, install and forget, stand alone measurement, communication, and control system.
  • Embodiments can be embedded in motors, appliances, pumps, fans, lighting fixtures, electrical equipment, variable frequency devices, power supplies, generator controllers, or other electrical equipment and appliances, such as power outlets, power sockets, power strips, power extensions, power adapters, light switches, and the like.
  • inventions can contain high speed electronic switching devices, such as, for example, TRIACs or MOSFETs that operate in Class D or Class E mode and based on control signals from device for load control capability. Further embodiments can contain solid state relay or other high speed high power switching devices.
  • high speed electronic switching devices such as, for example, TRIACs or MOSFETs that operate in Class D or Class E mode and based on control signals from device for load control capability.
  • Further embodiments can contain solid state relay or other high speed high power switching devices.
  • Embodiments can contain one or more wireless or wired communication modules, occupancy sensors, occupancy counters, light sensors, temperature sensors, wireless thermostats, current sensors, gas sensors, heat sensors, rechargeable battery backups, solar PV panels for self powered systems, LED displays, and the like.
  • Other embodiments can communicate with other devices and/or instruments in the vicinity, such as, for example, controlling, non-controlling, wired or wireless thermostats, variable air volume controllers, mechanical or electrical shades, automatic door locks, door sensors, card scanners, RFID devices, and the like.
  • Embodiments can measure and analyze data from internal and external sensors including current, voltage levels and waveforms, temperature, vibration, motor speed, motor torque and mechanical load, and the like.
  • Other embodiments can calculate and communicate in real time an efficiency rating of said motor or electrical equipment that may take into consideration an ambient condition of the motor or electrical equipment in addition to the measured and analyzed data.
  • the ambient condition can be communicated to the device through the embedded communication module, analogue inputs or digital inputs.
  • inventions can be part of a network in mesh, peer-to-peer, client-server, or master-slave configuration and yet further embodiments can be a Plug & Play, install and forget, stand alone measurement and control system.
  • acts, events, or functions of any of the algorithms described herein can be performed in a different sequence, can be added, merged, or left out all together (e.g., not all described acts or events are necessary for the practice of the algorithm).
  • acts or events can be performed concurrently, e.g., through multi-threaded processing, interrupt processing, or multiple processors or processor cores or on other parallel architectures, rather than sequentially.
  • a machine such as a general purpose processor, a digital signal processor (DSP), an ASIC, a FPGA or other programmable logic device, discrete gate or transistor logic, discrete hardware components, or any combination thereof designed to perform the functions described herein.
  • DSP digital signal processor
  • a general purpose processor can be a microprocessor, but in the alternative, the processor can be a controller, microcontroller, or state machine, combinations of the same, or the like.
  • a processor can also be implemented as a combination of computing devices, e.g., a combination of a DSP and a microprocessor, a plurality of microprocessors, one or more microprocessors in conjunction with a DSP core, or any other such configuration.
  • a software module can reside in RAM memory, flash memory, ROM memory, EPROM memory, EEPROM memory, registers, hard disk, a removable disk, a CD-ROM, or any other form of computer-readable storage medium known in the art.
  • An exemplary storage medium can be coupled to the processor such that the processor can read information from, and write information to, the storage medium. In the alternative, the storage medium can be integral to the processor.
  • the processor and the storage medium can reside in an ASIC.
  • the words “comprise,” “comprising,” and the like are to be construed in an inclusive sense, as opposed to an exclusive or exhaustive sense; that is to say, in the sense of “including, but not limited to.”
  • the words “proportional to”, as generally used herein, refer to being based at least in part on.
  • the words “coupled” or connected”, as generally used herein, refer to two or more elements that may be either directly connected, or connected by way of one or more intermediate elements. Additionally, the words “herein,” “above,” “below,” and words of similar import, when used in this application, shall refer to this application as a whole and not to any particular portions of this application.
  • words in the above Detailed Description using the singular or plural number may also include the plural or singular number respectively.
  • conditional language used herein such as, among others, “can,” “could,” “might,” “may,” “e.g.,” “for example,” “such as” and the like, unless specifically stated otherwise, or otherwise understood within the context as used, is generally intended to convey that certain embodiments include, while other embodiments do not include, certain features, elements and/or states.
  • conditional language is not generally intended to imply that features, elements and/or states are in any way required for one or more embodiments or that one or more embodiments necessarily include logic for deciding, with or without author input or prompting, whether these features, elements and/or states are included or are to be performed in any particular embodiment.

Landscapes

  • Engineering & Computer Science (AREA)
  • Business, Economics & Management (AREA)
  • Human Resources & Organizations (AREA)
  • Power Engineering (AREA)
  • General Physics & Mathematics (AREA)
  • Physics & Mathematics (AREA)
  • Economics (AREA)
  • Strategic Management (AREA)
  • Theoretical Computer Science (AREA)
  • Marketing (AREA)
  • General Business, Economics & Management (AREA)
  • Health & Medical Sciences (AREA)
  • Tourism & Hospitality (AREA)
  • Accounting & Taxation (AREA)
  • Entrepreneurship & Innovation (AREA)
  • Finance (AREA)
  • Development Economics (AREA)
  • Automation & Control Theory (AREA)
  • Public Health (AREA)
  • Water Supply & Treatment (AREA)
  • Primary Health Care (AREA)
  • General Health & Medical Sciences (AREA)
  • Quality & Reliability (AREA)
  • Educational Administration (AREA)
  • Game Theory and Decision Science (AREA)
  • Operations Research (AREA)
  • Computer Networks & Wireless Communication (AREA)
  • Radar, Positioning & Navigation (AREA)
  • Electromagnetism (AREA)
  • General Engineering & Computer Science (AREA)
  • Management, Administration, Business Operations System, And Electronic Commerce (AREA)
  • Testing Of Devices, Machine Parts, Or Other Structures Thereof (AREA)

Abstract

Systems and methods dynamically measure, ascertain, and compare a local facility load with local renewable energy generation in substantially real time and determine whether excess energy exists from the local distributed renewable energy resource. Further, systems and methods forecast the available excess energy from the local distributed renewable energy resource that can be managed and controlled in increments. The increments can be fed to the grid for purchase, stored in a regional energy store, stored in a local energy store, or shed.

Description

  • Any and all applications for which a foreign or domestic priority claim is identified in the Application Data Sheet as filed with the present application are hereby incorporated by reference under 37 CFR 1.57.
  • BACKGROUND
  • This disclosure relates generally to evaluating energy performance of a building, a building system, and/or a collection of buildings locally or over a large geographic area.
  • Existing energy and greenhouse gas measurement and verification protocols rely on walk around and observe audits that are defined in, for example, International Standards Organization (ISO) 50001, American Society of Heating, Refrigerating and Air-Conditioning Engineers (ASHRAE) Level 1 audits, ASHRAE Level 2 audits, and the like. These rely on static analytics and do not produce accurate results.
  • Another example of existing energy protocols is the U.S. EPA's Energy Star® program. The Energy Star® program has developed energy performance rating systems for several commercial and institutional building types and manufacturing facilities. These ratings, on a scale of 1 to 100, provide a means for benchmarking the energy efficiency of specific buildings and industrial plants against the energy performance of similar facilities of the same space type, based on a national average. A rating can be generated for ratable space types based on building attributes, such as square footage, weekly operating hours, and monthly energy consumption data. The Energy Star® ratings rely on static analytics, estimates, and forecasting, and do not produce accurate results and can be difficult to verify.
  • As a result of the lack of accurate and consistently reliable measurement and verification standards, false claims of carbon credits, Negawatts (energy saved as a result of energy conservation or increased efficiency), and other energy reductions are being made. Further, the lack of accurate and consistent energy assessment makes it difficult to accurately determine the benefit of corrective actions to equipment and systems, to normalize energy conservation investments, to calculate paybacks from energy conservation investments and retrofits of buildings, and the like.
  • SUMMARY
  • There is a need to dynamically assess the energy sustainability of a facility, i.e., how well it is using its energy, and identify wasted energy that is consistent and accurate.
  • Embodiments relate to an energy search engine using dynamic analytic algorithms based at least in part on, but not limited to one or more of smart meter data, other sensor data, sub-metered energy measurement data, weather data, gas data, utility rate schedules, basic facility information, such as, for example, the direction (north, south, east or west) that the building faces, total facility square footage, occupant scheduling, facility use, and the like to dynamically assess the energy sustainability of a facility.
  • In accordance with various embodiments, a method to assess energy usage comprises receiving in a substantially continuous way a measurement of actual energy consumption, receiving in a substantially continuous way a measurement of ambient conditions, and comparing the measurement of actual energy consumption with a target energy consumption to calculate a substantially continuous energy performance assessment, wherein the target energy consumption is based at least in part on the measurement of ambient conditions. The method further comprising receiving in a substantially continuous way a measurement of facility occupancy and usage, wherein the target energy consumption is based at least in part on the measurement of ambient conditions and facility usage. In one embodiment, receiving in the substantially continuous way the measurement of ambient conditions comprises receiving the measurement of ambient conditions at least every 15 minutes. In one embodiment, the substantially continuous energy performance assessment comprises comparisons occurring at least every 15 minutes of the measurement of actual energy consumption with the target energy consumption.
  • Certain embodiments relate to a method to dynamically assess energy efficiency. The method comprises obtaining a minimum energy consumption of a system, receiving in a substantially continuous way a measurement of actual energy consumption of the system, and comparing the minimum energy consumption to the measurement of actual energy consumption to calculate a substantially continuous energy performance assessment. The system can be at least one of a building envelope, a building, a zone within a building, an energy subsystem, a facility, a group of buildings in near proximity to each other, a geographically diverse group of buildings, and the like.
  • In an embodiment, comparing the minimum energy consumption to the measurement of actual energy consumption comprises at least one of comparing in a substantially continuous way a theoretical minimum energy consumption of the system to the measurement of actual energy consumption to determine a theoretical energy efficiency for the system, where the theoretical minimum energy consumption is based at least in part on the theoretical performance limit of system components, comparing in a substantially continuous way an achievable minimum energy consumption of the system to the measurement of actual energy consumption to determine an achievable energy efficiency for the system, where the achievable minimum energy consumption is based at least in part on specifications for high energy efficient equivalents of the system components, and comparing in a substantially continuous way a designed minimum energy consumption of the system to the measurement of actual energy consumption to determine a designed energy efficiency for the system, where the designed minimum energy consumption is based at least in part on specifications for the system components.
  • Certain other embodiments relate to a method to dynamically assess energy usage. The method comprises obtaining an expected energy usage for a building having installed building systems and a load profile, receiving in a substantially continuous way measurements of actual energy consumption after an installation of at least one energy improvement measure for the building, establishing an energy usage for the building with the load profile based at least in part on the measurements received after the installation of the at least one energy improvement measure, and determining an impact of the at least one energy improvement measure. The method further comprises quantifying the effectiveness of the at least one energy improvement measure by determining at least one of a payback calculation, a payment of an incentive, a valuation of real property, and a carbon offset used in carbon trading. The installed building systems can comprise at least one of an HVAC system, a lighting system, at least one plug load, a data center system, a water heating system, and the like. Installed energy improvement measure can comprise installing a renewable energy system, retrofitting equipment, commissioning, load shifting, load shedding, installing energy storage, and the like.
  • According to a number of embodiments, an apparatus to dynamically assess energy usage of a system comprises computer hardware including at least one computer processor, and computer readable-storage comprising computer-readable instructions that, when executed by the computer processor, cause the computer hardware to perform operations defined by the computer-executable instructions comprising obtaining a minimum energy consumption of a system, receiving in a substantially continuous way a measurement of actual energy consumption of the system, and comparing the minimum energy consumption to the measurement of actual energy consumption to calculate a substantially continuous energy performance assessment.
  • The computer-executable instructions further comprise at least one of comparing in a substantially continuous way a theoretical minimum energy consumption of the system to the measurement of actual energy consumption to determine a theoretical energy efficiency for the system, where the theoretical minimum energy consumption is based at least in part on the theoretical performance limit of system components, comparing in a substantially continuous way an achievable minimum energy consumption of the system to the measurement of actual energy consumption to determine an achievable energy efficiency for the system, where the achievable minimum energy consumption is based at least in part on specifications for high energy efficient equivalents of the system components, and comparing in a substantially continuous way a designed minimum energy consumption of the system to the measurement of actual energy consumption to determine a designed energy efficiency for the system, where the designed minimum energy consumption is based at least in part on specifications for the system components.
  • The system can comprise at least one of a building, a building envelope, at least one building system, a zone within the building, a data center, and the like. Receiving in the substantially continuous way the measurement of actual energy consumption of the system can comprise receiving the measurement of actual energy consumption at least every 15 minutes. The substantially continuous energy performance assessment can comprise comparisons occurring at least every 15 minutes of the minimum energy consumption to the measurement of actual energy consumption and at least one of a gas energy carbon footprint, an electrical energy carbon footprint, an estimate of wasted energy, an energy rating, an energy efficiency, and a power index.
  • For purposes of summarizing the disclosure, certain aspects, advantages and novel features of the inventions have been described herein. It is to be understood that not necessarily all such advantages may be achieved in accordance with any particular embodiment of the invention. Thus, the invention may be embodied or carried out in a manner that achieves or optimizes one advantage or group of advantages as taught herein without necessarily achieving other advantages as may be taught or suggested herein.
  • BRIEF DESCRIPTION OF THE DRAWINGS
  • FIG. 1 illustrates a schematic diagram of a system to assess and optimize energy usage for a facility, according to certain embodiments.
  • FIG. 2 illustrates an exemplary schematic diagram of an energy management system, according to certain embodiments.
  • FIG. 3 is a flow chart of an exemplary energy search engine process to assess the amount of energy used for cooling and the amount of excessive cooling affected, according to certain embodiments.
  • FIG. 4 is an exemplary substantially continuous excessive cooling performance assessment, according to certain embodiments.
  • FIG. 5 is a flow chart of an exemplary energy search engine process to assess energy usage, according to certain embodiments.
  • FIG. 6 is a flow chart of an exemplary energy search engine process to dynamically assess energy efficiency, according to certain embodiments
  • FIG. 7 is a flow chart of an exemplary energy search engine process to quantify the effectiveness of energy improving measures, according to certain embodiments.
  • FIG. 8 is an exemplary substantially continuous energy performance assessment, according to certain embodiments.
  • FIG. 9 is an exemplary continuous yearly key performance indicator assessment, according to certain embodiments.
  • FIG. 10 is an exemplary continuous monthly key performance indicator assessment, according to certain embodiments.
  • FIG. 11 illustrates an exemplary block diagram of a system on a chip or circuit board for real time continuous and automated digital measurement, analysis, and communication with optional input from external sensors, analysis of energy use, analysis of external data and control of energy use and the measurement, analysis, storage, and reporting of energy quality and metrics, according to certain embodiments.
  • FIG. 12 illustrates an exemplary block diagram of an energy data reduction system that enables the use of existing communication methods and channels to handle the anticipated broadband flow of energy and control data that will emerge as “smart grid” data measurement, communication, and control tools expand in use and reach into residences, buildings, commercial facilities, industrial facilities and into smart appliances and devices, according to certain embodiments.
  • FIG. 13 illustrates an exemplary block diagram of the system of FIG. 1, according to certain embodiments.
  • FIG. 14 represents a unique algorithm that can be used with this invention or with any energy or environmental measuring and reporting device or embodiment and/or with any network of energy or environmental devices or systems that measure, report, and optionally control energy or environmental data.
  • DETAILED DESCRIPTION
  • The features of the systems and methods will now be described with reference to the drawings summarized above. Throughout the drawings, reference numbers are re-used to indicate correspondence between referenced elements. The drawings, associated descriptions, and specific implementation are provided to illustrate embodiments of the inventions and not to limit the scope of the disclosure.
  • Embodiments of an energy search engine use dynamic energy related data to determine how well a facility is using energy and to identify wasted energy. Further embodiments dynamically guide building system adjustments to reduce energy waste, and verify the results of such actions. For example, contemporary heating, ventilation, and air conditioning (HVAC) systems use a combination of chilled coolant or chilled water, evaporative coils, forced air ducting, and hot water intermixed to provide comfort and fresh air to occupants of buildings. To provide this comfort, many building HVAC systems waste energy by simultaneously heating and cooling building air by relying on static factors and no external information to dynamically adjust the various HVAC components.
  • In one embodiment, a combination of dynamically varying factors are evaluated to dynamically adjust HVAC or other building systems for optimum occupancy comfort, lowest energy use, lowest tariff cost, and lowest GHG emissions. These factors include, but are not limited to, natural and environmental factors, occupant factors, utility tariff factors, and GHG emission factors. For example, outside temperatures near a building vary hourly throughout the workday and evening. Throughout the day, the sun heats different aspects of the building which creates a variable heating component. As occupants move in and out of rooms and in and out of the building during the workday, their heat load contribution, fresh air requirements, occupant comfort requirements, and energy use via lighting, computers, and other office equipment or industrial processes in the building vary.
  • The energy search engine incorporates at least one of these dynamic variables in energy modeling algorithms to provide, for example, one or more of benchmarking energy use, comparing required energy use and costs to wasted energy use and costs, dynamically guiding building system adjustments, verifying the results of such actions, and determining an optimum size of alternate electric energy systems, such as solar, wind, fuel cells, and the like to generate energy for the building.
  • FIG. 1 illustrates an exemplary schematic diagram of a system 100 to dynamically assess and optimize energy usage for an energy subsystem of a facility, the facility or a network of facilities 104. Facilities 104 can comprise one or more buildings, residences, factories, stores, commercial facilities, industrial facilities, data centers and the like, one or more rooms, one or more offices, one or more zoned areas in a facility, one or more floors in a building, parking structures, stadiums, theatres, and the like, one or more systems, subsystems, and/or components 104 a, a zone within the building/facility 104, a building envelope, and the like, locally or geographically remote.
  • The network of facilities 104 can comprise, for example, a geographic area, facility owner, property manager, campus, weather pattern, climate zone, facility activity type, facility total square footage, facility occupied square footage, volume of facility free space, facility schedule, facility activity levels (e.g. production quantities, number of students, etc.), utility company, applicable utility rate schedule, source of energy, type and size of local generation systems, type and size of local alternative energy systems (e.g. thermal solar, thermal storage, energy storage, etc.), type of construction material used, type of energy systems used, model of energy systems used, facility design specifications, required air changes, measured air changes, type of energy management system installed, model of energy management system installed, performance of any existing energy management system, applicable energy codes, applicable energy regulations, applicable energy standards, applicable greenhouse gas emissions codes, applicable greenhouse gas emissions regulations, applicable greenhouse gas emissions standards, energy service company servicing the facility, energy consulting firm servicing the facility, and the like.
  • Examples of the systems, subsystems and/or components 104 a include but are not limited to fans, pumps, motors, chillers, lights, heaters, heat exchangers, blowers, electric valves, air conditioning equipment, compressors, heat pumps, HVAC systems, lighting systems, motors, water heating systems, plug loads, data/Telco, variable air volume devices (VAV), gas systems, electrical systems, mechanical systems, electromechanical systems, electronic systems, chemical systems, and the like.
  • The facility 104 and/or building 104 in the following discussion refer to the facility, its systems, subsystems, components, and/or a network of facilities as described above.
  • Energy entering the facility 104 can be of many forms, such as, for example, thermal, mechanical, electrical, chemical, light, and the like. The most common forms are typically electricity or power, gas, thermal mass (hot or cold air, people), and solar irradiance. The electrical energy can be generated from traditional fossil fuels, or alternate forms of power generation, such as solar cells, wind turbines, fuel cells, any type of electrical energy generator, and the like. Ambient weather conditions, such as cloudy days, or time of day, such as nighttime, may be responsible for radiant energy transfer (gains or losses).
  • The facility 104 comprises measurement devices 104 b configured to measure actual energy usage in real time. For example, sensors, such as wired and/or wireless sensors and/or sensor systems, can measure kilowatt hours and energy spikes of electrical energy used to power the lighting system, to power the air compressor in the cooling system and to heat water for lavatories, cubic feet of gas consumed by a heating or HVAC system, amount of air flow from compressors in the cooling or HVAC system, and the like. The sensors can comprise current sensors, voltage sensors, EMF sensors, touch sensors, contact closures, capacitive sensors, trip sensors, mechanical switches, torque sensors, temperature sensors, air flow sensors, gas flow sensors, water flow sensors, water sensors, accelerometers, vibration sensors, GPS, wind sensors, sun sensors, pressure sensors, light sensors, tension-meters, microphones, humidity sensors, occupancy sensors, motion sensors, laser sensors, gas sensors (CO2, CO), speed sensors (rotational, angular), pulse counters, and the like.
  • The facility 104 further comprises control systems, such as, for example, load shedding relays, load shifting relays, Energy Management Systems (EMS), Building Management Systems (BMS), and the like, to control energy consuming and energy saving components of the facility 104. For example, one or more controllers can raise or lower automatic blinds, shut off/reduce heating or cooling in an HVAC system in the entire or just one room of the facility 104, switch usage of electricity from conventional generation to electricity generated by alternate forms, such as wind or solar, and the like.
  • The system 100 comprises an energy search engine 102 and a user interface 108. In an embodiment, the energy search engine 102 is a cloud computing system based in a network 110, such as the Internet 110, as illustrated in FIG. 1.
  • In other embodiments, the energy search engine 102 is not a cloud computing system, but receives and transmits information through the network 110, such as the Internet 110, a wireless local network, or any other communication network. In an embodiment, the energy search engine 102 is hosted in a device located inside the facility 104. The device acquires sensor data and/or smart meter data directly from existing sensors and smart meters 104 b. The device receives weather information, utility rate schedules, utility pricing information, grid usage information, BIM information, and other via RF broadcast signals. The device calculates locally the energy performance, actionable information and communicates control signals to local relays 104 c, energy systems and other systems.
  • The user interface 108 allows a user to transmit information to the energy search engine 102 and receive information from the energy search engine 102. In an embodiment, the user interface 108 comprises a Web browser and/or an application to communicate with the energy search engine 102 within or through the Internet 110. In an embodiment, the user interface 108 is associated with a display and a user input device, such as a keyboard.
  • The energy search engine 102 receives energy usage information from the measurement devices 104 b measuring energy usage of the systems, subsystems, and components 104 c of the facility 104 in a substantially continuous way. The measurement devices 104 b deliver data output that can include but is not limited to electric energy consumption data, natural or renewable gas data, air temperature data, air flow data, air quality data, building occupancy data, building zone level occupancy data, water data, environmental data, and geographic data, and the like. This data can be derived from individual circuits, critical components within the building 104 or its zones, or those systems that externally serve a building or group/network of buildings. In another embodiment, additional measurements of vibration, temperature, sound from critical motor components, and the like within buildings 104 or wherever motors are used for industrial or manufacturing processes are used to gauge the health of motor and equipment functions within the facility 104.
  • Further, the energy search engine 102 receives in a substantially continuous way dynamic data relating to energy usage from one or more of a Building Information Modeling (BIM) 106, a power grid 112, a utility company 114, building management 116, and an environmental service 118. For example, the BIM 106 can provide, but is not limited to specifications for the systems, subsystem, and components 104 a installed in the facility 104, specifications for the systems, subsystem, and components with a higher energy rating that could have been installed in the facility 104, and the like. The power grid 112 can provide, but is not limited to a dynamic grid response to renewable energy sources, plug-ins, projected grid demand, grid load information, energy supply capacity, and the like. The utility company or other sellers of energy 114 can provide, but are not limited to utility rate tariffs, real-time energy pricing, price bids, and the like. The building management 116 can provide, but is not limited to facility and zone level scheduling of the facility 104, occupancy information, system status information (e.g. open doors, open windows, open shutters, etc.), and the like. The environmental service, such as a weather service, can provide, but is not limited to dynamic weather data for the location of the facility 104, projected weather for the location of the facility 104, sever weather alerts, geographical factors, and the like.
  • The energy search engine 102 analyzes the static data and the dynamic data received in the substantially continuous way and provides a substantially continuous energy assessment. Examples of the substantially continuous energy assessment include but are not limited to reports, benchmark results, energy performance assessments for the facility 104, network of facilities 104 or any of its systems, subsystems, and components 104 a, site energy carbon footprint, source energy carbon footprint, source energy assessment, building and systems commissioning strategies, lighting strategies, data center and Telco strategies, water performance assessment, gas performance assessment, energy retrofit assessment, renewable energy assessment, and the like.
  • In an embodiment, the energy search engine 102 transmits commands to the control systems 104 c to control the systems, subsystems, and components 104 a to reduce or optimize the energy usage of the facility 104. In an embodiment, the energy search engine 102 controls the systems, subsystems, and components 104 a in a substantially continuous way.
  • In an embodiment, substantially continuous comprises within a length of time or not to exceed a length of time which occurs at regular intervals. In another embodiment, data received in a substantially continuous way comprises data that is received within a definite length of time marked off by two instances. In other words, data received in a substantially continuous way is data that is received at regular time intervals, where the time interval does not exceed a pre-defined time interval. In another embodiment, the time interval is approximately within a pre-defined time interval. In another embodiment, the time interval is based at least in part on the type of information received. For example, weather can be received substantially continuously every hour, smart meter information can be received substantially continuously every 15 minutes, and grid load can be received substantially continuously every time interval which does not exceed an hour.
  • Further, in an embodiment, providing substantially continuous energy assessment comprises providing the energy assessment within a pre-defined time interval, not to exceed a pre-defined time interval, or the like. Further yet, controlling in a substantially continuous way to optimize energy usage comprises sending commands to the control systems 104 c or the like within a pre-defined time interval. Again, the time interval is based at least in part on the specific system being controlled. For example, the energy search engine may direct the facility 104 to shed or redistribute power at an interval not to exceed 5 minutes, while directing the blinds to raise or lower at an interval not to exceed 2 hours.
  • In certain embodiments, substantially continuous time intervals comprise one of time intervals not to exceed 1 minute, time intervals not to exceed 5 minutes, time intervals not to exceed 15 minutes, time intervals no to exceed 1 hour, time intervals not to exceed 1 day, and time intervals not to exceed 1 week.
  • FIG. 2 illustrates an exemplary block diagram of an embodiment of the energy search engine 102. The energy search engine 102 comprises one or more computers or processors 202 and memory 204. The memory 204 comprises modules 206 including computer-executable instructions, that when executed by the computer 202 cause the energy search engine 102 to analyze the energy data and provide the substantially continuous energy assessment metrics. The memory 204 further comprises data storage 208 including one or more databases to store the dynamic and or static data by the modules 206 to analyze energy usage and provide energy usage assessments.
  • The computers 202 comprise, by way of example, processors, Field Programmable Gate Arrays (FPGAs), System on a Chip (SOC), program logic, or other substrate configurations representing data and instructions, which operate as described herein. In other embodiments, the processors 202 can comprise controller circuitry, processor circuitry, processors, general-purpose single-chip or multi-chip microprocessors, digital signal processors, embedded microprocessors, microcontrollers and the like. The memory 204 can comprise one or more logical and/or physical data storage systems for storing data and applications used by the processor 202. The memory 204 can further comprise an interface module, such as a Graphic User Interface (GUI), or the like, to interface with the user interface 108.
  • In one embodiment, the energy search engine 102 calculates a score reflecting the energy performance of the facility 104. In an embodiment, the score is a weighted average of one or more metrics that are calculated based at least in part on one or more energy variables. Examples of energy variables include, but are not limited to the time history of the energy (power, water, gas) consumed by the facility, the carbon equivalent of energy used at the site, the carbon equivalent of the energy generated at the source, the time history of the ambient weather conditions, the facility activity type, the facility total square footage, the facility occupied square footage, the volume of free space in the facility, the facility schedule, the facility activity levels (e.g. production quantities, number of students, and the like), the location of the facility, the applicable utility rate schedule, the output of any existing local (or on site) generation systems, the output of any existing local alternative energy systems (e.g. thermal solar, thermal storage, energy storage, and the like), the potential for local renewable generation, the potential for local alternative energy systems, the type of construction material used, the type of energy systems used, the facility design specifications, required air change, measured air changes, the type of energy management system installed, the performance of any existing energy management system, data from any existing energy, environmental and security monitoring systems, and the like.
  • The facility 104 and/or building 104 and/or subsystems 104 a refer to one or more of the facility, its systems, subsystems, and components, multiple buildings comprising the facility located locally or remotely, and a network of facilities in the following discussion.
  • In an embodiment, the score or energy metrics are calculated based on historical energy data for the past week, month, quarter, year or longer time period.
  • In an embodiment, data from one time period is used to backfill data missing from another time period. For example, if the data for February of 2012 is missing, then it can be backfilled using the following:

  • Y 2 =X 2 /X 1 *Y 1
  • where X1 is the average workday energy consumption for January 2011, X2 is the average workday energy consumption for January 2012, and Y1 is the 15-minute, hourly, daily, or weekly energy consumption for workdays in February 2011, and Y2 is the 15-minute, hourly, daily, or weekly energy consumption for the corresponding workdays in February 2012. The above method can be used to backfill missing energy data for off days.
  • In another example, the same missing data for February 2012 can be backfilled using the following:

  • Y 2=2*(X 1 Z 2 +Z 1 X 2)/(X 1 Z 1)*Y 1
  • where X1 is the average workday energy consumption for January 2011, X2 is the average workday energy consumption for January 2012, Z1 is the average workday energy consumption for March 2011, Z2 is the average workday energy consumption for March 2012, and Y1 is the 15-minute, hourly, daily, or weekly energy consumption for workdays in February 2011, and Y2 is the 15-minute, hourly, daily, or weekly energy consumption for the corresponding workdays in February 2012. The above method can be used to backfill missing energy data for off days.
  • In an embodiment, the energy used by the facility is calculated using the following equation:

  • Energy Used=Energy Sourced by the Utility+Energy Generated on Site−Energy Stored on Site
  • where energy sourced by the utility is energy that is purchased from the utility company. The energy generated on site (locally) is energy generated by local energy generation systems as solar PV, wind turbines, fuel cells, gas power plant, etc. The energy stored on site is energy that is purchased from the utility or generated locally but is stored at the time of purchase or generation for later use in energy storage systems such as batteries, compressed air, pumped water, thermal storage, etc. If the energy storage systems are discharging, then the sign of the stored energy in the equation above is negative. Each of the components in the equation above can be measured, calculated or estimated.
  • In an embodiment, the energy score and metrics can be proportional to the energy performance of a facility relative in a specific time period compared to its performance in a base period. In an embodiment, the base period is one year.
  • In an embodiment, the metric can be proportional to the composition of source energy (solar PV, utility power, fuel cell, solar thermal, gas generator, energy storage, etc.) relative to an optimum composition of source energy for a facility, given the measured, calculated or estimated energy usage of the facility, the type of systems in the facility, the facility schedule, the facility location, the ambient weather conditions, and the like.
  • In an embodiment, the metrics include but are not limited to the facility electric energy use index (kwHr/ft2), the facility gas use index (therms/ft2), and the facility electric demand index (kw/ft2).
  • In an embodiment, the metric can be proportional to the equivalent greenhouse gas emissions of the energy used at the facility 104, proportional to the energy generated using local renewable energy systems, proportional to the energy generated using alternative fuel systems (e.g. hydrogen fuel cells, or the like), proportional to the use of alternative energy systems, proportional to the ratio of energy used during off hours to the energy used during work hours, proportional to the ratio of energy used during work days to the energy used during off days, proportional to the minimum rate of energy consumption during a period of time (day, month, year, etc.), proportional to the simultaneous heating and cooling that may be occurring in the facility 104, or the like.
  • In another embodiment, the metric can be proportional to the correlation between energy used for heating energy and heating requirements, proportional to the correlation between the energy used for cooling and the cooling requirements, proportional to the estimated, calculated, or measured energy used for heating divided by the amount of heating affected, proportional to the estimated, calculated or measured energy used for cooling divided by the amount of cooling affected, and the like. Heating requirements, cooling requirements, amount of heating affected, or the amount of cooling affected can be calculated using, but not limited to one or more of the following: ambient weather, ambient environmental conditions, desired internal temperature, ventilation rates, outside air circulation, recirculation rates, recirculated air, energy consumed by loads inside the facility 104, heat generated by other sources inside the facility 104, heat entering or leaving the facility 104 through mass or thermal transfer, and the like. In one embodiment, the heating degree hours, a difference between ambient temperature and supply air temperature inside the facility for each hour, can be used as a measure of affected heating (heating kWhr/degree heated). In another embodiment, the cooling degree hours, a difference between the ambient temperature and the supply air temperature inside the facility 104 for each hour, can be used as a measure of affected cooling (cooling kWhr/degree cooled).
  • In another embodiment, the required heating enthalpy hours, a difference between ambient enthalpy and a target temperature and humidity inside the facility, can be used as a measure of required heating. In another embodiment, the required cooling enthalpy hours, a difference between ambient enthalpy and a target temperature and humidity inside the facility, can be used as a measure of required cooling.
  • In another embodiment, the affected heating enthalpy hours, a difference between ambient enthalpy and supply air enthalpy inside the facility for each hour, can be used as a measure of affected heating (heating energy kWhr/kJ heated). In another embodiment, the cooling enthalpy hours, a difference between the ambient enthalpy and the supply air temperature inside the facility 104 for each hour, can be used as a measure of affected cooling (cooling kWhr/KJ cooled).
  • FIG. 3 is a flow chart of an exemplary energy search engine process 300 to assess the amount of energy used for cooling and the amount of excessive cooling affected. For example, the amount of energy used for cooling during workdays during a year can be estimated from the profile of total energy used during the year. The interval energy (energy consumed at regular intervals, typically 15 or 30 minutes, or any other regular interval) for a 12 month period is used. At blocks 310 and 312, the average energy and average cooling degree requirement, respectively, for each time interval during work days is calculated for each month.
  • At block 314, the minimum energy profile for workdays in calculated and at block 316, the average energy used for cooling is calculated as the difference between the energy profile and the minimum energy used during workdays.
  • At block 318 to block 324, the minimum energy required to cool the facility by one degree is estimated for each time interval during workdays. At block 326, the minimum energy needed for cooling during the year is calculated from the results of blocks 322 and 324.
  • At block 328, the amount of energy used for excessive energy, i.e. the amount of energy wasted due to excessive cooling is estimated. At block 330, the energy profile for the year is calculated assuming the cooling and heating systems are at their peak efficiency all year long. The process can be repeated for time intervals during off-days.
  • FIG. 4 is an exemplary substantially continuous excessive cooling performance assessment 400. The performance assessment 400 is a topographical map of the facility 104 showing estimated excessive cooling energy for an average hour throughout the day in each month for a year. The excessive cooling is estimated by considering the load inside the building and the cooling requirement from the ambient weather, as described in FIG. 3. For example, the performance assessment 400 indicates total cooling costs being estimated at $117,000, with $75,000 in overcooling between 10 AM and 3 AM, and $19,000 in overcooling between 3 AM and 10 AM. Overcooling is estimated at $96,000, being up to 76% of the cooling costs. In an embodiment of the performance assessment 400, color can be used to indicate energy intensity, where brighter shades of a color indicate greater energy intensity and darker shades of the color represent lighter energy intensity (or vice versa).
  • In an embodiment, the metric can be proportional to the time history of the number of air changes, proportional to the fraction of outside air introduced to the facility, proportional to the fraction of return air recirculated, where return air is air that is exhausted from the facility using exhaust fans, proportional to the air quality inside the facility, proportional to facility peak demand and the load duration curve, which represents the time spent at each power level from the lowest demand to the peak demand, proportional to the level of compliance of the facility 104 or any of its subsystems 104 a with one or more of existing and/or future energy regulations, standards, codes, specifications and guidelines, and the like.
  • In another embodiment, the metric can be proportional to the level of energy demand reduction or load shedding initiated in response to a request from the grid or utility. The energy demand reduction can be calculated relative to a baseline that is adjusted for one or more of the following factors: ambient weather conditions, ambient environment conditions, changes in facility schedule, changes in facility activity, changes in facility occupancy, and the like. In an embodiment, the projected energy demand reduction for the facility 104 can be calculated by estimating the amount of energy that will be used for cooling as described above and assuming that a certain percentage of the cooling energy will be reduced.
  • In a yet further embodiment, the metric can be proportional to the change in energy consumption of the facility 104 or any of its energy subsystems 104 a compared to an energy baseline, an energy benchmark, a computed energy usage, an estimated energy usage or a projected energy usage.
  • In an embodiment, an energy baseline can be calculated for any measured or calculated metric, and correlated with ambient weather conditions, facility usage, and facility schedule. The calculated baseline can be used to project the value of the metric given projections of ambient weather conditions, facility usage, facility schedule, or changes in energy systems.
  • In an embodiment, the metric can be proportional to the cost of total energy used at the facility 104, proportional to the cost of gas energy used at the facility, proportional to the cost of energy used at the facility 104 from renewable energy sources, proportional to the cost of energy used at the facility 104 from alternative energy sources, proportional to the total cost to generate the energy at the source, proportional to the cost of delivering the energy from the source to the facility 104, proportional to the total cost of electric energy used at the facility 104, proportional to the peak electric energy demand costs at the facility 104, proportional to the electric energy consumption costs at the facility 104, proportional to the avoided energy consumption costs, proportional to the avoided peak demand costs, or the like.
  • In another embodiment, the metric can be proportional to the energy consumed in the facility 104, proportional to the total energy that can be delivered to the facility 104, proportional to the total energy that can be generated in the facility 104, proportional to the total energy that can be reduced in the facility 104, proportional to the reliability of the sources of energy to the facility 104 and the total uptime of one or more of the facility's energy sources, proportional to the power quality (e.g. power factor, total harmonic distortion, energy in harmonic frequencies, voltage spikes, voltage drops, power surges, etc.) of the power in the facility 104 or any of its energy subsystems 104 a, proportional to number of megawatts (MW) or megawatt-hours (MWhr) avoided as a response to an energy emergency, or the like. An example of such avoided energy is the load shed as part of a utility's Demand Response program.
  • In another embodiment, any of the metrics can be calculated every year, month, week, day, hour, or in a substantially continuous manner.
  • In a further embodiment, any of the metrics can be calculated in the cloud-based server 102 and can be offered as a subscription-based service.
  • FIGS. 5, 6, and 7 are flow charts of exemplary search engine processes to actively process energy consumption data, environmental data, and building use data, examples of which are described above, in a plurality of time frames, including real time, to provide one or more of the metrics related to the minimum energy required by the facility 104 and its critical subsystems 104 a for a unique geographic location, use, environment, and occupancy associated with the facility 104, examples of which are described above.
  • In other embodiments, the energy search engine algorithms provide energy and sustainability ratings for commercial, municipal, campus, state, and federal buildings. Another embodiment provides carbon footprinting of buildings and facilities. Yet another embodiment evaluates the value of real property by evaluating its energy consumption and effectiveness and efficiency of installed systems and components. A further embodiment evaluates the instant demand response, load shedding, load shifting, and additional local generating potential of buildings, facilities, campuses and their systems. A yet further embodiment guides and evaluates actionable energy efficiency and demand response improvement measures, equipment retrofits, and commissioning strategies. In an embodiment, the technology enables compliance with legislated energy efficiency mandates and goals.
  • FIG. 5 is a flow chart of an exemplary energy search engine process 500 to assess energy usage for the facility 104. The facility 104 and/or building 104 and/or subsystem 104 refer to one or more of the facility, its systems, subsystems, and components, multiple buildings comprising the facility located locally or remotely, and a network of facilities in the following discussion. Beginning at block 510, the process 500 receives substantially continuous measurements of actual energy consumption of the facility 104. In an embodiment, the process 500 receives measurements related to the actual energy consumption of the facility 104 from the measurement devices 104 b. Examples of the measurements of actual energy consumption are smart meter readings, electric meter readings, gas meter readings, current measurements, facility energy variables as described above, and the like.
  • In another embodiment, receiving substantially continuous measurements comprises receiving measurements at least every 15 minutes. In another embodiment, receiving substantially continuous measurements comprises receiving measurements at least every 5 minutes. In a further embodiment, receiving substantially continuous measurements comprises receiving measurements at least every 1 hour.
  • At block 512, the process 500 receives substantially continuous measurements of ambient conditions. For example, the energy search engine 102 can receive weather reports including the outside air temperature, outside air humidity, cloud coverage, UV index, precipitation level, evaporative transpiration (ET) number, weather forecast, and the like. In another example, the status of doors, windows, and shutters associated with the facility 104 can change with time and can be received in a substantially continuous manner.
  • At block 514, the process 500 obtains a target energy consumption of the facility 104 based at least in part on the ambient conditions. Target energy consumption can be a calculated energy consumption based on baseline performance, desired environmental conditions inside the facility (temperature, humidity, air quality, etc.) projected facility schedule, projected facility usage, and projected weather conditions. Average facility energy consumption at a given ambient condition and facility usage level can be calculated based on historic data. This average can be set as a target for the facility when similar weather and facility usage are anticipated.
  • At block 516, the process 500 compares the measurement of the actual energy consumption with the target energy consumption for the facility 104, and at block 518, the process 500 calculates a substantially continuous energy performance assessment based at least in part on the comparison of the measurement of the actual energy consumption with the target energy consumption.
  • Metrics found on the performance assessment can include but are not limited to one or more of total gas and electric current energy costs per square foot of the facility 104, baseline electric energy rating, peak electrical energy rating, gas energy rating, efficiency of heating gas use, simultaneous heating and cooling, nighttime power index, weekend power index, EMS scheduling, full time loading, an overall performance assessment, energy wasted annually, range of estimated energy wasted annually, cost to produce energy at the source, cost to deliver energy to the facility 104, waste as a percent of total energy used, cost of annual gas and electric energy wasted annually, electrical energy carbon footprint, gas energy carbon footprint, total energy carbon footprint, target energy usage in cost per square foot of the facility 104, annual energy savings target, historical electricity and gas usage, historical monthly peak demand for electricity, historical energy map showing annual energy usage versus the time of the day the usage occurred, wasted heating based on a comparison of heating requirements and the actual energy used for heating, simultaneous heating and cooling based on an estimated energy used for cooling during business hours and an estimated energy used for heating during business hours, wasted cooling during business hours based on a comparison of relative cooling required during business hours and an estimated energy used for cooling during business hours, wasted cooling during non-business hours based on a comparison of relative cooling required during non-business hours and an estimated energy used for cooling during non-business hours, cooling degree hours, heating degree hours, peak reduction, energy savings recommendations, energy source planning, energy source investment payback including but not limited to fuel call, grid tied solar, thermal storage, battery-based peak shedding, and utility based on electric utility data, gas utility data, National Oceanic and Atmospheric Administration (NOAA) weather data for the facility 104, and the like.
  • In another embodiment, the metric can be proportional to the level of compliance with one or more energy standards, such as, for example, ISO 50001, LEED Silver, LEED Gold, LEED Platinum, and the like.
  • In another embodiment, the metric can be proportional to the cost of bringing the facility to compliance with one or more energy standard.
  • In another embodiment, the metric can be proportional to the energy savings (in consumption kWhr, demand kW or energy costs $) that can be realized by bringing the facility to compliance with one or more energy standard.
  • In another embodiment, the metric can be proportional to the absolute efficiency of the energy subsystem or facility 104. The absolute efficiency of the energy subsystem 104 can be the ratio between the measured, calculated or estimated energy consumed by the subsystem 104 and the energy the subsystem 104 would have consumed if it operated at the theoretical limits of the subsystem 104.
  • In another embodiment, the metric can be proportional to the achievable efficiency of the energy subsystem or facility 104. The achievable efficiency of the energy subsystem 104 can be the ratio between the measured, calculated or estimated energy consumed by the subsystem 104 and the energy the subsystem 104 would have consumed if it operated at the highest efficiency achievable by such subsystems 104.
  • In an embodiment, the metric can be proportional to the design efficiency of the energy subsystem or facility 104. The design efficiency of the energy subsystem or facility 104 can be the ratio between the measured, calculated or estimated energy consumed by the subsystem 104 and the energy the subsystem 104 would have consumed if it operated per the manufacturer's design specification.
  • In an embodiment, the metric can be proportional to the savings realized (consumption kWHr, demand KW, energy costs in $) if one or more energy subsystems is operating at its theoretical, absolute, or design efficiency.
  • FIG. 6 is a flow chart of an exemplary energy search engine process 400 to dynamically assess energy efficiency for the facility 104. Energy search engine algorithms analyze measured energy data versus computed minimum required energy to provide, for example, energy efficiency ratings, energy consumption profiles, energy load factors, critical component assessment, and life cycle analysis of critical components.
  • Beginning at block 610, the process 600 obtains a minimum energy consumption for the facility 104.
  • Obtaining the minimum energy consumption at block 410 comprises obtaining the theoretical energy consumption based at least in part on models of the installed building systems, subsystems, and components 104 a at block 612. In an embodiment, obtaining the minimum energy consumption comprises obtaining a theoretical energy consumption based at least in part on ideal models or the theoretical limits of the installed building systems, subsystems, and components 104 a.
  • Obtaining the minimum energy consumption at block 610 further comprises obtaining an achievable minimum energy consumption based at least in part on specifications for high energy efficiency equivalents of the installed building systems, subsystems, and components 104 a at block 614 and obtaining a designed minimum energy consumption based at least in part on specifications and cumulative loads for the installed building systems, subsystems, and components 104 a at block 616.
  • At block 620, the process 600 receives substantially continuous measurements of the facility energy consumption. In an embodiment, the measurements are provided by the measurement devices 104 b. In another embodiment, measurements are calculated. In a further embodiment, the measurements are estimated.
  • At block 630, the process 600 compares the minimum energy consumption to the measurement of the facility energy consumption in a substantially continuous way. Comparing at block 630 comprises comparing the theoretical minimum energy consumption to the measurement of the facility energy consumption at block 632, comparing the achievable minimum energy consumption to the measurement of the facility energy consumption at block 634, and comparing the designed minimum energy consumption to the measurement of the facility energy consumption at block 636.
  • At block 640, the process 600 calculates a substantially continuous energy performance assessment for the facility 104. Calculating the substantially continuous energy performance at block 640 comprises determining a theoretical energy efficiency at block 642, determining an achievable energy efficiency at block 644, and determining a designed energy efficiency at block 646.
  • For example, the absolute or theoretical efficiency metric for a fan can be calculated from a measurement, estimation or calculation of one or all of the following: fan upstream pressure, fan downstream pressure, flow temperature, fan speed, mass flow rate through the fan, volumetric flow rate through the fan, and/or energy consumed by the fan. The fan's absolute efficiency is then calculated by dividing the energy consumed by the energy that should have been consumed by the fan if it operated at its theoretical efficiency under the same conditions of upstream pressure, downstream pressure, fan speed, flow temperature, volumetric flow rate, or mass flow rate through the fan.
  • In another example, the achievable efficiency metric for a fan can be calculated from a measurement, estimation or calculation of one or all of the following: fan upstream pressure, fan downstream pressure, flow temperature, fan speed, mass flow rate through the fan, volumetric flow rate through the fan, and/or energy consumed by the fan. The fan's achievable efficiency is then calculated by dividing the energy consumed by the energy that should have been consumed by the highest performing fan available operating under the same conditions of upstream pressure, downstream pressure, fan speed, flow temperature, volumetric flow rate, or mass flow rate through the fan.
  • In a further example, the design efficiency metric for a fan can be calculated from a measurement, estimation or calculation of one or all of the following: fan upstream pressure, fan downstream pressure, flow temperature, fan speed, mass flow rate through the fan, volumetric flow rate through the fan, and/or energy consumed by the fan. The fan's design efficiency is then calculated by dividing the energy consumed by the energy that should have been consumed by the fan operating per the manufacturer's design specifications under the same conditions of upstream pressure, downstream pressure, fan speed, flow temperature, volumetric flow rate, or mass flow rate through the fan.
  • In another example, the theoretical efficiency of a facility envelope on hot days can be calculated assuming a perfectly insulated facility envelope that blocks all radiant heat transfer into the facility 104, all convective heat transfer into the facility 104, and all infiltration of mass in and out of the facility 104. The heat generated in the facility 104 is calculated from a measurement, estimate, or calculation of the energy consumed in the facility 104, such as indoor lighting, plug load, heating gas, etc., and the heat generated by occupants and processes in the facility 104. The heat removed from the facility 104 can be calculated from a measurement, estimate, or calculation of the difference between enthalpy of the ventilation and cooling air leaving the envelope and the enthalpy of the ventilation and cooling air entering the envelope. The facility 104 can be assumed to be at constant operating temperature. For a perfectly insulated envelope at a constant internal temperature, the heat removed from the facility 104 is equal to the heat generated in the facility 104. The envelope efficiency on a hot day can be calculated as the ratio of the heat generated in the facility 104 divided by the heat removed from the facility 104.
  • In a further example, the design efficiency of a roof top packaged HVAC unit can be calculated by measuring the enthalpy (temperature, humidity and flow rate) of the air entering the HVAC system (fraction of return air+fraction of outside air), the enthalpy of the air leaving the HVAC system (supplied to the facility 104) and the energy consumed by the HVAC system. The energy consumed by the HVAC is divided by the [enthalpy of air entering the HVAC—enthalpy of air leaving the HVAC] to yield a measured coefficient of performance (COP). The measured COP is then divided by the design COP specified by the HVAC manufacturer at the given HVAC load and the resulting ratio comprises the design efficiency of the HVAC system.
  • FIG. 7 is a flow chart of an exemplary energy search engine process 500 for demand side analysis. In one embodiment, the energy search engine 102 matches varying demand side load requirements to supply side generating and grid capability to establish relative value energy pricing.
  • The exemplary process 700 quantifies the effectiveness of energy improving measures, such as rating the energy efficiency and carbon footprint of the facility 104 and/or any or all of its systems 104 a (individually or collectively) to determine opportunities to introduce energy efficiency, install retrofits, commission facilities for monitoring based commissioning (MBCx), retrocommissioning (RCx), continuous commissioning, and the like, and provide peak reduction and demand response strategies and actions.
  • Beginning at block 710, the process 700 obtains an energy usage benchmark for the facility 104. In an embodiment, the energy usage benchmark is an energy usage point of reference across a network of facilities that share something in common against which the energy usage of the facility 104 may be compared. For example, the benchmark could be one of an Energy Star® rating, historical energy use of the facility 104, energy performance of buildings in a specific geographic area, energy performance of buildings of a certain size, energy performance of buildings of a certain activity, energy performance of buildings with a certain type of cooling technology, energy performance of buildings with a certain type of heating technology, energy performance of buildings with a certain type of construction material, energy performance of buildings with a certain brand and model of EMS, energy performance of buildings with a certain energy certification, energy performance of buildings with a certain energy rating, energy performance of buildings with a certain local energy source (e.g. solar PV), or the like.
  • At block 712, the process 700 receives substantially continuous measurements of actual energy consumption for the facility 104 before installation of energy improvement measures. In an embodiment, the measurements are obtained from the measurement devices 104 b.
  • At block 714, the process 700 establishes a first baseline of energy usage for the facility 104 based at least in part on the measurements of actual energy consumption received before the installation of the energy improvement measures. In an embodiment, establishing the baseline before installation comprises obtaining an expected energy usage for the facility which has installed systems, subsystems, and components 104 c, and a load profile. The baseline is established by recording the energy performance of the facility over a period of time, e.g. 3 months or 1 year. Multiple baselines can be calculated, such as for night hours on work days, morning hours on work days, afternoon hours on work days, night hours on off days, morning hours on off days, afternoon hours on off days.
  • Different types of baselines can be calculated, including, but not limited to total energy consumption (kWhr), electrical energy consumption (kWhr), electrical demand (kW), gas consumption (therms), energy used for lighting (kWhr), demand due to lighting (kW), energy used for cooling (kWhr), demand due to cooling (kW), and the like. Baselines can also be normalized with ambient weather conditions, cooling degree hours, heating degree hours, facility usage levels, facility occupancy, etc. For example, the baseline of energy consumed (kWhr) during morning hours on work days, could be the average consumption during morning hours for all workdays of a certain segment or entire segment of the baseline calculation period. The consumption baseline can be normalized to cooling degree hours by dividing the average consumption for each of the morning hours on work days with the average cooling degree hour for each of those hours.
  • At block 716, the process 700 compares the benchmark with the baseline established before the installation of the at least one energy improvement measure.
  • At block 718, the process 700 receives substantially continuous measurements of actual energy consumption for the facility 104 after installation of at least one energy improvement measure. In an embodiment, the measurements are obtained from the measurement devices 104 b.
  • Examples of energy improvement measures are, but not limited to, installing a renewable energy system, retrofitting equipment, commissioning, load shifting, load shedding, installing energy storage, installing LED lighting systems, installing variable frequency drive (VFD) systems, installing new windows, installing new wall insulation, replacing inefficient boilers, upgrading the insulation of hot and cold water pipes, installing economizer systems, installing evaporative cooling systems, adding circulation fans, changing the location of supply and return ventilation air ducts, installing pool covers, installing thermal storage systems, installing shades and awnings, and the like.
  • At block 720, the process 700 establishes a second baseline based at least in part on the measurements of actual energy consumption received after the installation of the energy improvement measures. In an embodiment, establishing the baseline after installation comprises obtaining an energy usage for the facility which has installed systems, subsystems, and components 104 c, and a load profile.
  • At block 722, the process 700 compares the first baseline established before installation of the at least one energy improvement measure with the baseline established after installation of the at least one energy improvement measure.
  • At block 724, the process 500 compares the benchmark with the baseline established after installation of the at least one energy improvement measure.
  • At block 726, the process 700 quantifies the effectiveness of the at least one energy improvement measure. In an embodiment, the process 700 determines the impact of the at least one energy improvement measure against the first baseline of energy usage for the facility 104. In another embodiment, the process 700 determines the impact of the at least one energy improvement measure against the benchmark for the facility 104. In an embodiment, quantifying the effectiveness of the at least one energy improvement comprises determining one or more of a payback calculation, a payment of an incentive, a valuation of real property for purposes that include projecting the value of operational strategies and behaviors or equipment replacements that result in altered real property valuations, a carbon offset used in carbon trading, and the like.
  • FIG. 8 is an exemplary substantially continuous energy performance assessment 800. The assessment 800 includes information about the current energy usage of the facility 104, rating of energy metrics, and targeted energy usage. For example, the metrics for current energy usage include the total gas and electric energy cost per square foot of the facility 104; low and high ranges for the annual estimated energy wasted, the percent of wasted energy out of the total energy used, the cost of the annual energy wasted; and carbon footprint metrics, such as the carbon footprint of the electrical energy used, the carbon footprint of the gas energy used, and total carbon footprint for the facility 104. Energy metrics, such as the baseline energy rating, the peak electrical energy rating, the gas energy rating, the efficiency of the gas used for heating, the occurrence of simultaneous heating and cooling, the nighttime power index, the weekend power index, the energy management system scheduling, and the full time loading levels, are rated on a poor, average or good scale. Finally, the assessment 600 includes a comparison of energy usage, energy savings, and carbon reductions for the current energy implementation of the facility with at least two suggested energy reduction implementations to provide a better target and a best target.
  • In an embodiment, the energy search engine 102 provides the energy performance of a network of facilities 104 on a multi-dimensional map. The multi-dimensional map plots one or more metrics on a geographical map with colors, coordinates and shapes. For example, a metric proportional to the fraction of a facility's energy demand that can be shed (reduced) at any given time can be plotted on a geographical map of the area. Every facility 104 can be indicated by a circle, with the size of the circle proportional to the levels of demand (in kW) that can be shed at each facility 104 and the color of the circle indicating the percent facility demand that can be shed. Similar maps can be used to animate the effect of a cloud passing on the potential for demand reduction across a network of facilities 104 based on demand projections calculated using the energy search engine 102.
  • In another example, several metrics can be plotted on a single map with every metric represented by a layer of a unique color, with the shades of each color proportional to the level of the metric (e.g. light shades of a color indicating smaller values of the metric and darker shades of the same color indicating larger values of the same metric).
  • FIG. 9 is an exemplary continuous yearly key performance indicator chart 900 and FIG. 10 is an exemplary continuous monthly key performance indicator chart 1000. Both charts 900 and 1000 track key performance indicators, including but not limited to baseline electric use index, peak electrical energy use index, gas energy use index, heating gas efficiency consistency, simultaneous heating and cooling, nighttime power index, weekend power index, EMS scheduling, and full-time loading, as described above. Chart 900 indicates the year to date energy performance, while chart 1000 indicates the energy performance for a month. In an embodiment, the indicator bars are in color to represent score quality/level where red indicates a poor score, green indicates a good score, and yellow indicates a mediocre score that could be improved.
  • In an embodiment, one or more alerts are associated with one or more of the metrics. Exceeding, or dropping below a specified metric value and for a specified amount of time will signal an alert and cause an action to be taken. The action may include the closure of relays, a command to be sent via wired or wireless Ethernet®, RF module, machine interface, wired connection, or the like. The action may also include a message to be sent to a computer desktop, a mobile device, a mobile application, a Facebook® page, a Twitter® account, a message board, a broadcast system, or the like.
  • In an embodiment, one or more alerts are associated with one or more of the metrics. The alerts can be initiated when a metric exceeds or drops below a certain value for a specified amount of time if one or more other metrics, measured variables, such as, for example, temperature, pressure, humidity, flow, current, or the like, estimated variables, calculated variables, and/or any mathematical combination of the metrics and/or variables are at, above, or below a specific value for a specified amount of time, where the specific value can be a function of one or more metrics, measured variables, estimated variables, calculated variables, any mathematical combination of the variables, and/or any mathematical combination of the metrics.
  • Other embodiments of the energy search engine 102 can report a daily maintenance task list, where the energy search engine 102 generates a list of required maintenance tasks sorted by criticality, energy performance impact, cost performance impact, impact on carbon footprint, cost to fix, and the like. Further, an embodiment of the energy search engine 102 can report equipment diagnostics such that the energy search engine will continuously diagnose and rate the performance of each of the building's equipment 104 a.
  • Further embodiments of the energy search engine 102 determines and reports on when and where a building or its energy consuming or energy generating subsystems are operating properly or are in need of maintenance, tuning, load shifting, load shedding, or equipment replacement based at least in part on data level flags that correspond with incremental level changes in energy consumed or generated.
  • In an embodiment, the energy search engine 102 uses day ahead projected hourly weather data and projected facility schedule and usage to predict energy performance (e.g. kWhr consumption, kW demand, efficiency metrics, etc.) based on a calculated baseline for the facility 104, and correlations of energy baseline with ambient weather, facility schedule and facility usage.
  • In another embodiment, the energy search engine 102 uses day ahead projected hourly weather data, projected facility schedule, projected facility usage, utility rate information, day ahead utility pricing information, day ahead grid information, day ahead energy cost information, to predict energy cost (kW demand cost, kWhr consumption cost, gas therm cost, water gallons cost, etc.) based on a calculated baseline for the facility 104, and correlations of energy baseline with ambient weather, facility schedule and facility usage.
  • In yet another embodiment, the energy search engine 102 provides data output that are useful to benchmark and evaluate real property energy consumption and carbon emissions/footprint for purposes that include projecting the value of operational strategies and behaviors or equipment replacements that result in altered real property valuations, and the like.
  • In yet further embodiments, the energy search engine 102 provides data output that are useful for auditing compliance with existing and emerging legislation on energy use, carbon emissions, and for achieving energy reduction and carbon emission reduction goals at facilities.
  • In other embodiments, the energy search engine 102 provides preplanned or instant actionable energy optimization strategies through activation of systems and circuits that shed and/or shift energy consumption and/or provide supplemental energy resources. The energy search engine 102 can provide data output to Energy Management Systems (EMS) and/or Building Management Systems (BMS) and/or load control relays to respond with either instant or preprogrammed load shedding strategies, load shifting strategies, and supplemental energy supply strategies, according to certain embodiments.
  • An embodiment of the energy search engine 102 can use cloud based NOC Baseline energy management to determine instant peak demand load shedding, load shifting, supplemental local generating resources, or the like. Embodiments of the energy search engine 102 can determine and/or control the demand side potential for adjusting loads and local energy supply for each facility, campus, or n aggregate of geographically dispersed facilities.
  • FIGS. 11, 12 and 13 illustrate exemplary block diagrams of a system that integrates universally interoperable “smart grid envisioned” digital energy measurement, energy use analysis, carbon footprint analysis, greenhouse gas emission analysis, energy quality and availability analysis, data correction algorithms, data reduction algorithms, data encryption algorithms, data storage, data communication, and the digital and/or analog control of energy used and generated or the carbon footprint or greenhouse gas emissions that are generated in such processes. Implementations may selectively include one or more of the modules described in FIGS. 11, 12, and 13.
  • One embodiment of the system provides universal real time, continuous, and autonomous digital measurement of local or remotely located and energized or de-energized electric circuits that range in voltage from 0 Volts, a de-energized state, to energized states of up to 600 VAC or VDC to electric grid circuits that employ voltage levels in the kilovolt range and electric circuits in phase configurations, such as single phase, split phase, three phase Delta, three phase Wye, and the like.
  • The measured and analyzed electric circuit data by Module 1301 ADC and Module 1301C Energy Calculations comprises, for example, line-to-line and line-to-current voltage, powers (total, active, reactive), line-to-line and line-to-neutral current, power factor, fundamental and harmonic total energy per phase and for the sum of phases, fundamental and harmonic active energy per phase and for the sum of phases, fundamental and harmonic reactive energy per phase and for the sum of phases, frequency, and harmonics in 1-n circuits, and the like.
  • In one embodiment, the real time digital energy and carbon footprint data reporting rates are varied and substantially lower than the energy data sampling rates from Module 1301 ADC in FIG. 13. This is due to application of an energy or environmental data reduction/data compression technique an embodiment of which is illustrated in FIG. 14 and applied to a typical circuit embodiment, such as one embodiment shown in FIG. 12, comprising Data Gateway Module 1303, Data Analysis Module 1304, and Data Validation and Error Correction Module 1305; and another embodiment shown in FIG. 13, comprising Data Gateway Module 1303, Data Analysis Module 1304, and Data Validation and Error Correction Module 1305. One embodiment of the energy or environmental data reduction/data compression technique enables use of low, medium, or high speed data communication channels to deliver accurate real time energy use and carbon footprint reporting about electric circuit energy or environmental conditions that are digitally measured through the use of a higher data sampling rate that typically ranges between approximately 10 samples/second and approximately 24,000 samples/second and on 1 to n measured electric circuits, devices, or appliances. In other embodiments, energy or environmental data sampling rates can be higher or lower.
  • FIG. 13 illustrates an embodiment of the energy measurement, analysis, communication, and control system. The system comprises Digital Energy Measurement Modules 1301, 1301B, 1301 Phase; Current/power/voltage Measurement Modules 1301C for energy calculation or energy data processing; and Modules 1303, 1304, 1305 for enabling energy data quantity reduction and data error correction without compromising the value of the measured data.
  • The energy data quantity reduction is based, at least in part, on application of an embodiment of the data reduction/data compression technique illustrated in FIG. 14 and filtering parameters, such as change in measured energy (+−x %), rate of change of measured energy (t), and the like.
  • Data Analysis Module 1304 comprises ports where analog I/O analog sensor input and output control signals are exchanged with external sensors, and devices and digital I/O modules where external digital sensor input and control information are exchanged with outside sensors and devices.
  • Module 1306 provides compensated inputs for on-board and/or remote temperature sensors. Module 1306A provides inputs from other on-board and/or remote sensors such as pressure sensors, light sensors, acceleration sensors, tension-meters, flow sensors, gas sensors, microphones, and others.
  • Module 1307 provides PWM controller outputs Class D or Class E PWM control signals for the efficient control of external electric loads through direct connection with high speed electronic switches such as Triac's, MosFets, or IGFET's.
  • Module 1308 enables optional digital data encryption. Module 1309 is used for digital data storage. Module 1311 provides communications and control commands. Module 1310 provides global positioning or location sensing (GPS). Module 1312 is a web server and Module 1313 provides a human machine interface that can be an LCD display and keypad or keyboard, or the like.
  • Digital Energy Measurement
  • Modules 1301, 1301B, 1301 Phase, 1301C, and 1302 perform digital energy measurement and calculations in electric circuits that are located in any residence, building, commercial or industrial facility, in electric circuits that are used for powering electric powered transportation systems and/or charging electric vehicles, and energy that is provided or delivered by any and all electric generating power systems including solar, wind, fuel cell, micro turbines, or other types of electric generating devices and systems.
  • Measurement devices 1302 are associated with an electrical circuit and acquire an analog measurement of the current, voltage or power in the associated electrical circuit. Measurement devices 1302 can be, for example, current transformers (CT) or the like. When current in a circuit is too high to directly apply to measuring instruments, a current transformer 1302 produces a reduced current accurately proportional to the current in the circuit, which can be conveniently connected to measuring and recording instruments. The current transformer 1302 also isolates the measuring instruments from what may be very high voltage in the monitored circuit.
  • Current transformers 1302 couple to analog to digital converter (ADC) Modules 1301 through CT Polarity Correction Modules 1301B. Modules 1301B comprise a latching double pole double throw gate and permit the automatic correction for the polarity of the measured current, should the current transformer 1302 be incorrectly installed. The position of latching DPDT gate in Module 1301B is determined by algorithms that operate on Modules 1305 and 1306 to evaluate when the voltage phase from Phase ADC Module 1301 and the current phase from Module 1301 of a given measurement circuit are separated by more than approximately 90 degrees and less than approximately 270 degrees. When this condition exists, the CT 1302 polarity is deemed incorrect and the position of latching DPDT gate is switched to the alternate position.
  • Other examples of measurement devices 1302 are Rogowski coils, DC shunts, external digital current sensors, and external analog current sensors. In one embodiment, the system provides for the intermixed use of clamp on current measuring toroid transformers (CTs), Rogowski coils, DC shunts, or other current measuring devices.
  • ADC Modules 1301 convert the analog measurement from the measurement devices 1302 into a digital measurement for use in the system. ADC Modules 1301 comprise an analog to digital converter, and at least one jumper. In one embodiment, the analog to digital converter is an Analog Devices IC, part number ADC 5169, or the like.
  • In an embodiment, the jumper configuration of the ADC Module 1301 is field selectable for the accurate measurement of 1 to n electric circuit phase configurations including single phase, split phase, three phase Delta, and three phase Wye. Phase configuration and association of the ADC module with its respective voltage phase can also be done in software in another embodiment.
  • Phase ADC Module 1301 couples to energized circuits with phase A, B, and/or C through resistive voltage dividers to digitally measure voltage amplitude and phase information.
  • The digital measurement information collected by the Phase ADC Module 1301 and the ADC Modules 1301 for 1 to n measured electrical circuits is sent to the Energy Calculation Module 1301C. The data sample rate ranges between approximately 10 samples/second to approximately 24 kilo samples/second.
  • Data reduction processes comprises Modules 1303, 1304, and 1305 utilizing an embodiment of the data reduction/data compression technique illustrated in FIG. 14 to substantially reduce the quantity of measured energy data that will be reported in real time, stored in memory data, or “pushed” to remote or cloud data base or “pulled” from a user inquiry. The reduced quantity of energy data is based on previously defined or user defined data filtering parameters such as amount of change or rate of change of measured or calculated energy data. The energy or environmental data quantity reduction technique that is shown in embodiments is broadly applicable to any energy or environmental device or network of devices. Module 1303 samples the measured and calculated energy data from 1 to n ADCs at frequencies up to approximately 24,000 samples per second and sends the data to the Data Validation and Correction Module 1305 for determination of data accuracy. Module 1304 analyses the energy data and also receives input from other internal and external sensors, Modules 1306 and 1306A. The Analysis Module 1304 also contains algorithm for reducing the number of points passed from Module 1305 and sends the formatted and substantially reduced quantity of measurement data to at least Modules 1311, 1312, 1313, and 1309. Based on comparison of this measured energy data and input from external environmental sensors, a control signal is sent to external devices for load control through the Analog I/O, Digital I/O, or PWM Controller Module 1307.
  • Digital Data Analysis with Automated Error Correcton
  • Data Validation and Correction Module 1305 and Data Analysis Module 1304 for 1-n electric circuits provide real time digital analysis, validation, and auto correction of measured energy use and the quality of energy that is available at a power generating system that is found on the grid, smart grid, micro grid, residence, building, commercial facility, or for electric vehicle and electric powered transportation systems, according to certain embodiments. Embodiments include electrical circuits powered by solar, wind, fuel cells, and any type of electric energy generator.
  • In one embodiment, Module 1305 generates signals to control the Data Analysis Module 1304 when the voltage phase and the current phase of a given ADC Module 1301 exhibits more than approximately 90 degrees and less than approximately 270 degrees of phase differential. Software used by the Data Analysis Module 1305 automatically identifies the correct phase that is associated with ADC Module 1301 and attaches this phase information to the correct energy information from ADC Module 1301 in the Data Validation and Error Correction Module 1305.
  • In an embodiment, Module 1306 does not configure the ADC Module 1301. Instead the output data from a specific ADC Module 1301 is correctly attached to the correct phase data (A, B, C, . . . , n) from Phase ADC Module 1301 in Module 1305.
  • In one embodiment, Data Validation and Correction Module 1305 analyzes energy spikes to determine whether the spike is valid or is noise or corrupted data by acquiring additional samples at approximately the same time as the energy spike from Module 1303 which provides a data gateway. If the energy spike is a valid data measurement, the amplitude of the later acquired sample will be proportional to the energy spike. If the amplitude of the later acquired data is substantially different than the energy spike, Module 1305 determines that the energy spike was caused by noise, and treats the bad data as irrelevant and not worthy of being passed on for storage or “push” or “pull” communication.
  • Data Analysis Module 1304 processes measured energy data and compares it with external environmental and facility use information to derive and deliver electric load, device, and BMS/EMS control signals that are used to reduce or increase the electric energy in a specific circuit. Data Error Correction Module 1305 processes measured energy data and compares it with prior data samples to insure that only relevant and accurate data is passed from Data Gateway Module 1303 to the Communication Module 1311 or to I/Os or to PWM Controller Module 1307.
  • Digital Data Encryption
  • Data Encryption Module 1308 optionally encrypts the data that is derived from the measuring of all electric circuits and the location of circuits and measurement apparatus using secure and anti-hacking data encryption algorithms. Module 1308 can also be positioned just downstream of Module 1304. In one embodiment, the Data Encryption Module 1308 uses anti tamper and anti hacking handshaking through the use of existing and emerging “smart grid” security data protocols.
  • Digital Data Storage
  • Data Storage Memory Module 1309 stores the measured and digitized electric circuit data and measured electric energy quality data. In an embodiment, the Data Storage Memory Module 1309 provides a data buffer in case communication channel with the local or remote host is broken. The buffer decouples data sampling rates and data reporting rates. The data is stored locally at the required sampling rate until the communication lines are re-established. The data is then transferred to the host ensuring no data loss during communication breakdown.
  • Universally Interoperable Communications and Control
  • Data Command and Communication Module 1311 implements predetermined and automated power reduction steps in energy use systems, smart appliances, or plug loads, based at least in part on the sensor data or on external demand response commands, according to certain embodiments.
  • Data Command and Communication Module 1311 provides the system with a unique address. Module 1311, in one embodiment, can push data to and/or pull data from 3rd party hardware or software including but not limited to structured query language (SQL) and/or SAP databases, Cloud based databases, and/or any type of computing device.
  • Data Command and Communication Module 1311 pushes digitally measured electric circuit energy use data from 1-n circuits using protocols, such as, for example, Ethernet, ZigBee, PLC (Power Line Carrier), WiFi, WiMax, GSM to a remote device for real time analysis, for real time analysis and control, and/or to a remote structured query language (SQL), SAP, or cloud data base for storage, comparison of data, data mining, and data analysis for a multiplicity of purposes including billing and control of circuit circuits, smart appliances, electric vehicle and electric transportation systems. The data can be delivered in XML, JSON, CSV, ASCII Strings, Binary Strings, and other formats.
  • In an embodiment, the Data Command and Communication Module 1311 uses data clock synchronization and system clocking via Ethernet connection. Other system connections include networked TCP/IP, client-server ModBus, BacNet, mesh network ZigBee wireless, WiFi, and WiMax that are operating either individually or concurrently to interact with 3rd party hardware and software.
  • The Data Command and Communication Module 1311 can simultaneously retain a copy of the measured data in onboard memory so that it can be viewed and accessed through the web server, according to certain embodiments.
  • In one embodiment, the Data Command and Communication Module 1311 can also act as a slave to the acquisition host, such as a PC or the like, and communicate with the master host in one of several standard protocols, such as Ethernet protocols including ModBus and BacNet, for example. The Module 1311 then acts as a translation of the protocol to serial communication.
  • The software Digital I/O module and Analog I/O module interfaces with the Data and Command Communication Module 1311 and with the Data Analysis Module 1304 to enable two-way software commands and interrupts to be exchanged between the Data Analysis Module 1304 and other BMS, BEMS, electrical vehicle charge stations, motor control systems, electrical control systems, smart appliances, programmable logic controllers, and the like.
  • In an embodiment, the Temperature Sensor Compensation Module 1306 comprises calibration compensation look up tables to correctly utilize J or K thermocouple devices or wired or wireless thermostats for external local or remote measurement of temperature.
  • The PWM Controller Module 1307 is directed either by the Data Analysis Module 1306 or the Communication and Command Module 1311 to output a signal that consists of variable duty cycle pulses for load control through external high speed electronic switches such as high power MOSFETS, IGFETs, or other high speed electronic switching devices. Such variable width pulses enable an external high speed electronic switch to control the electric energy and carbon footprint of any electric circuit or device including lighting circuits, motor circuits, air handling systems, HVAC compressor systems, and the like. This embodiment when combined with an external high speed electronic switch refers to a Class D or Class E control system design.
  • The GPS Location Information Module 1310 interfaces with the Data and Command Communication Module 1311 and maps the location of each identified circuit board that has a unique MAC address.
  • Universally Interoperable Control
  • Embodiments of the system of FIG. 11 can interface with “a smart device” “a smart appliance” “a smart building” “the smart grid”, renewable energy generators, and the like.
  • In an embodiment, Analog/digital input/output I/O modules interface external sensors with the Data Analysis Module 1304 and the Data Command and Communication Module 1311. Sensors, such as, for example, temperature sensors, humidity sensors, light sensors, occupancy sensors, motion sensors, acceleration sensors, vibration sensors, flow sensors, wind speed, heat sensors, gas sensors, gas spectrometers, laser sensors, humidity sensors, and other environmental sensors such as water flow, air flow, and gas flow provide data, including environmental, fuel type, or other data, to the Module 1304 or 1311 where the data is analyzed to calculate energy loads, determine possible energy reduction, identify malfunctioning systems, and/or the like.
  • Data Command and Communication Module 1311 implements predetermined and automated power reduction steps in energy use systems, smart appliances, or plug loads, based at least in part on the sensor data or on external demand response commands, according to certain embodiments.
  • Further, in an embodiment, the analog/digital I/O module interfaces with analog sensor input or digital input, analog or digital control circuit input, and output circuits for localized or remote control of relays, switches, programmable logic controllers, Building Management Systems (BMS), Building Energy Management Systems (BEMS), energy management and carbon footprint reporting systems, or the like. In another embodiment, the analog/digital I/O module interfaces with pulse counters from natural gas or water meters to integrate this additional data.
  • Customer Engagement
  • Web server 1312 and Human Machine Interface (HMI) 1313 provide the user with a Web-based user interface to the system of FIG. 13. Examples of HMI 1313 are 8, 16, or more segment LEDs or LCD panels, Keypads, Qwerty keyboards, and the like. Embodiments provide user interface software that is accessible via Ethernet from personal computers (PCs) on the local area or wide area network.
  • In one embodiment, the user interface allows the user to define the grouping of circuits to be measured and the locations for the circuits to be measured. The system provides users with “drag and drop” functionality of circuits between groups and locations and “drag and drop” functionality for charting and reporting in a mobile app. Users can also, in one embodiment, view real time or stored and “pushed” or “pulled” energy use on Mobile platforms, such as for example, I-Phone, Android, BlackBerry, and the like.
  • The user can define minimum and maximum alert thresholds on all measured and calculated metrics, such as, voltage, current, energies, energy consumption rate, powers, power factor, cost, cost rate, energy efficiency metric, energy efficiency rating, and the like, for each circuit, group of circuits and location. Comparative alert thresholds are used on metrics and for circuits where alerts are triggered by relative energy signature of circuits, groups and locations with each other or with established baselines or benchmarks. Predictive alert thresholds are used on metrics and for circuits where alerts are triggered by projected energy consumption of a circuit, group or location. When an alert is triggered, the system provides the user with an alert through email, text message, Facebook, Twitter, voicemail, RSS feeds, multi-media message automatic alerts, and the like. In one embodiment, the alert is accompanied by a description of the trigger event including charts and reports on history before alert trigger and projected consumption and results.
  • In another embodiment, through the Web Server 1312 or the push capability, the user is provided with animated and interactive desktop and mobile widgets for communicating energy consumption levels, energy ratings and critical energy conservation measures to end users. In another embodiment, the system communicates energy consumption levels, energy ratings and critical energy conservation measures to end users through RSS feeds with desktop tickers.
  • Other embodiments determine the need for air or fluid filter replacement, belt tension, belt alignment, worn or damaged bearings, worn or damaged gears, poor lubrication, damaged anchor or frame, damaged or worn brushes, unbalanced voltage, poor power quality, and the like based on the electrical signature. In an embodiment, the electrical signature comprises at least one of a current and/or voltage waveform, current and/or voltage levels and peaks, power factor, other sensor information, such as temperature, vibration, acceleration, rotation, speed, and the like, of any “downstream” motor or pump.
  • An embodiment of the algorithm for Energy Data Reduction relates to bandwidth issues that will be encountered on the “smart grid” just as MPEG did for audio and video. With a plethora of measurement and reporting systems running at high speed, data collection will overload a network with data. Use of this technique or method on any chip, device, circuit or computer will reduce the communication bandwidth and processing requirements of said devices.
  • Device Embedded in Power Distribution Panel
  • Embodiments can be in the form of an enclosure mounted adjacent to the power distribution panel and connected to said panel through a circuit breaker. Current sensors are plugged into the device. Examples of a power distribution panel are a main switch board, a sub panel, a distribution panel/box, an MCCR, and the like.
  • An embodiment that is embedded in the power distribution system permits “plugging in” current sensors directly into the power distribution system where voltage information can be acquired internally from the panel's main power distribution bars or through a connection to a circuit breaker.
  • In an embodiment, current sensors can also be embedded in the circuit breakers and can communicate measured energy data and control signals via wireless, wired or PLC to the embedded device.
  • In another embodiment, current sensors can be self-powered from the pickup and rectification of electromagnetic fields or direct connection to energized circuits with or without re-chargeable battery backup and can communicate measured energy data or control signals via wireless, wired or PLC to the embedded device.
  • In a further embodiment, current sensors can be in the form of shunt resistors modules that are placed in series with the circuit breakers and can communicate measured circuit data and command controls via wireless, wired or PLC to the embedded device.
  • Device Embedded in Construction of Circuit Breaker
  • Embodiments can be installed in a circuit breaker with a built-in current sensor, CT or shunt, and a wireless, wired or PLC communication and command module or connect to an adjacent circuit breaker to send and receive information.
  • An embodiment can contain circuit protection and/or circuit breaking capability. Another embodiment can contain power factor correction capability. A further embodiment can contain frequency shifting and switching capability, such currently employed by variable frequency drives, Class D or Class E control circuits, and the like that use high speed electronic switching devices such as TRIAC or MOSFET, for example.
  • Device Installed in Occupied or Monitored Space
  • Embodiments can be in the form of a small enclosure mounted in the space to be monitored. An embodiment can contain a wireless or wired communication module, occupancy sensor, occupancy counter, light sensor, temperature sensor, current sensor, gas sensor, heat sensor, rechargeable battery backup, solar PV panel for self powered systems, LED displays and the like.
  • Another embodiment can communicate with other devices and/or instruments in the vicinity, such as, for example, thermostats both controlling and non-controlling, VAV controllers, mechanical or electrical shades, automatic door locks, door sensors, card scanners, RFID devices, generator controller, and the like.
  • Other embodiments can be part of a mesh network in peer-to-peer, client-server, or master-slave configuration and yet further embodiments can be a Plug & Play, install and forget, stand alone measurement, communication, and control system.
  • Device Installed in Motors and Other Electrical Equipment
  • Embodiments can be embedded in motors, appliances, pumps, fans, lighting fixtures, electrical equipment, variable frequency devices, power supplies, generator controllers, or other electrical equipment and appliances, such as power outlets, power sockets, power strips, power extensions, power adapters, light switches, and the like.
  • Other embodiments can contain high speed electronic switching devices, such as, for example, TRIACs or MOSFETs that operate in Class D or Class E mode and based on control signals from device for load control capability. Further embodiments can contain solid state relay or other high speed high power switching devices.
  • Embodiments can contain one or more wireless or wired communication modules, occupancy sensors, occupancy counters, light sensors, temperature sensors, wireless thermostats, current sensors, gas sensors, heat sensors, rechargeable battery backups, solar PV panels for self powered systems, LED displays, and the like. Other embodiments can communicate with other devices and/or instruments in the vicinity, such as, for example, controlling, non-controlling, wired or wireless thermostats, variable air volume controllers, mechanical or electrical shades, automatic door locks, door sensors, card scanners, RFID devices, and the like.
  • Embodiments can measure and analyze data from internal and external sensors including current, voltage levels and waveforms, temperature, vibration, motor speed, motor torque and mechanical load, and the like.
  • Other embodiments can calculate and communicate in real time an efficiency rating of said motor or electrical equipment that may take into consideration an ambient condition of the motor or electrical equipment in addition to the measured and analyzed data. The ambient condition can be communicated to the device through the embedded communication module, analogue inputs or digital inputs.
  • Other embodiments can be part of a network in mesh, peer-to-peer, client-server, or master-slave configuration and yet further embodiments can be a Plug & Play, install and forget, stand alone measurement and control system.
  • Depending on the embodiment, certain acts, events, or functions of any of the algorithms described herein can be performed in a different sequence, can be added, merged, or left out all together (e.g., not all described acts or events are necessary for the practice of the algorithm). Moreover, in certain embodiments, acts or events can be performed concurrently, e.g., through multi-threaded processing, interrupt processing, or multiple processors or processor cores or on other parallel architectures, rather than sequentially.
  • The various illustrative logical blocks, modules, and algorithm steps described in connection with the embodiments disclosed herein can be implemented as electronic hardware, computer software, or combinations of both. To clearly illustrate this interchangeability of hardware and software, various illustrative components, blocks, modules, and steps have been described above generally in terms of their functionality. Whether such functionality is implemented as hardware or software depends upon the particular application and design constraints imposed on the overall system. The described functionality can be implemented in varying ways for each particular application, but such implementation decisions should not be interpreted as causing a departure from the scope of the disclosure.
  • The various illustrative logical blocks and modules described in connection with the embodiments disclosed herein can be implemented or performed by a machine, such as a general purpose processor, a digital signal processor (DSP), an ASIC, a FPGA or other programmable logic device, discrete gate or transistor logic, discrete hardware components, or any combination thereof designed to perform the functions described herein. A general purpose processor can be a microprocessor, but in the alternative, the processor can be a controller, microcontroller, or state machine, combinations of the same, or the like. A processor can also be implemented as a combination of computing devices, e.g., a combination of a DSP and a microprocessor, a plurality of microprocessors, one or more microprocessors in conjunction with a DSP core, or any other such configuration.
  • The steps of a method, process, or algorithm described in connection with the embodiments disclosed herein can be embodied directly in hardware, in a software module executed by a processor, or in a combination of the two. A software module can reside in RAM memory, flash memory, ROM memory, EPROM memory, EEPROM memory, registers, hard disk, a removable disk, a CD-ROM, or any other form of computer-readable storage medium known in the art. An exemplary storage medium can be coupled to the processor such that the processor can read information from, and write information to, the storage medium. In the alternative, the storage medium can be integral to the processor. The processor and the storage medium can reside in an ASIC.
  • The above detailed description of certain embodiments is not intended to be exhaustive or to limit the invention to the precise form disclosed above. While specific embodiments of, and examples for, the invention are described above for illustrative purposes, various equivalent modifications are possible within the scope of the invention, as those ordinary skilled in the relevant art will recognize. For example, while processes or blocks are presented in a given order, alternative embodiments may perform routines having steps, or employ systems having blocks, in a different order, and some processes or blocks may be deleted, moved, added, subdivided, combined, and/or modified. Each of these processes or blocks may be implemented in a variety of different ways. Also, while processes or blocks are at times shown as being performed in series, these processes or blocks may instead be performed in parallel, or may be performed at different times.
  • Unless the context clearly requires otherwise, throughout the description and the claims, the words “comprise,” “comprising,” and the like are to be construed in an inclusive sense, as opposed to an exclusive or exhaustive sense; that is to say, in the sense of “including, but not limited to.” The words “proportional to”, as generally used herein, refer to being based at least in part on. The words “coupled” or connected”, as generally used herein, refer to two or more elements that may be either directly connected, or connected by way of one or more intermediate elements. Additionally, the words “herein,” “above,” “below,” and words of similar import, when used in this application, shall refer to this application as a whole and not to any particular portions of this application. Where the context permits, words in the above Detailed Description using the singular or plural number may also include the plural or singular number respectively. The word “or” in reference to a list of two or more items, that word covers all of the following interpretations of the word: any of the items in the list, all of the items in the list, and any combination of the items in the list.
  • Moreover, conditional language used herein, such as, among others, “can,” “could,” “might,” “may,” “e.g.,” “for example,” “such as” and the like, unless specifically stated otherwise, or otherwise understood within the context as used, is generally intended to convey that certain embodiments include, while other embodiments do not include, certain features, elements and/or states. Thus, such conditional language is not generally intended to imply that features, elements and/or states are in any way required for one or more embodiments or that one or more embodiments necessarily include logic for deciding, with or without author input or prompting, whether these features, elements and/or states are included or are to be performed in any particular embodiment.
  • The teachings of the invention provided herein can be applied to other systems, not necessarily the systems described above. The elements and acts of the various embodiments described above can be combined to provide further embodiments.
  • While certain embodiments of the inventions have been described, these embodiments have been presented by way of example only, and are not intended to limit the scope of the disclosure. Indeed, the novel methods and systems described herein may be embodied in a variety of other forms; furthermore, various omissions, substitutions and changes in the form of the methods and systems described herein may be made without departing from the spirit of the disclosure. The accompanying claims and their equivalents are intended to cover such forms or modifications as would fall within the scope and spirit of the disclosure.

Claims (24)

What is claimed is:
1. A method to manage excess energy from distributed renewable energy resources, the method comprising:
automatically receiving in a substantially continuous way a measurement of energy generated by a distributed renewable energy resource;
automatically receiving in a substantially continuous way a measurement of energy consumed from the energy generated by the distributed renewable energy resource;
based at least in part on the received measurement of energy generated and the received measurement of energy consumed, automatically determining excess energy generated by the distributed renewable resource; and
controlling the excess energy with a pulse width modulation (PWM) controller.
2. The method of claim 1 wherein controlling the excess energy comprises controlling an amount of the excess energy.
3. The method of claim 2 wherein the amount of the excess energy comprises a range between approximately 0% and approximately 100%.
4. The method of claim 3 further comprising receiving a request over a network to acquire the amount of the excess energy.
5. The method of claim 4 wherein controlling the excess energy further comprises inputting the amount of the excess energy to an electrical grid in response to the request.
6. The method of claim 5 wherein the network comprises the Internet.
7. The method of claim 1 wherein controlling the excess energy comprises storing an amount of the excess energy in an energy store that is local to the distributed renewable energy resource.
8. The method of claim 1 wherein controlling the excess energy comprises shedding an amount of the excess energy.
9. The method of claim 1 wherein receiving in a substantially continuous way the measurement of energy consumed comprises receiving the measurement of energy consumed at least once every 15 minutes.
10. The method of claim 1 wherein receiving in a substantially continuous way the measurement of energy generated comprises receiving the measurement of energy generated at a rate sufficient to synchronize the energy generated by the distributed renewable resource with energy on an electrical grid.
11. The method of claim 1 further comprising aggregating the excess energy from a plurality of distributed renewable resources.
12. The method of claim 1 further comprising forecasting a quantity of excess energy for a preselected period of time based at least in part on the received measurement of energy generated and the received measurement of energy consumed.
13. An apparatus to manage excess energy from distributed renewable energy resources, the apparatus comprising:
a first analog to digital converter configured to automatically provide in a substantially continuous way a measurement related to energy generated by a distributed renewable energy resource;
a first data sampling device configured to receive the measurement related to energy generated and to provide energy generated data;
a second analog to digital converter configured to automatically provide in a substantially continuous way a measurement related to energy consumed from the energy generated by the distributed renewable energy resource;
a second data sampling device configured to receive the measurement related to energy consumed and to provide energy consumed data;
a data analyzer comprising computer hardware configured to automatically determine excess energy generated by the distributed renewable resource based at least in part on the energy generated data and the energy consumed data; and
a pulse width modulation (PWM) controller configured to control the excess energy.
14. The apparatus of claim 13 wherein controlling the excess energy comprises controlling an amount of the excess energy.
15. The apparatus of claim 14 wherein the amount of the excess energy comprises a range between approximately 0% and approximately 100%.
16. The apparatus of claim 15 further comprising a communication port configured to receive a request over a network to acquire the amount of the excess energy.
17. The apparatus of 16 wherein controlling the excess energy further comprises inputting the amount of the excess energy to an electrical grid in response to the request.
18. The apparatus of claim 17 wherein the network comprises the Internet.
19. The apparatus of claim 13 wherein controlling the excess energy comprises storing an amount of the excess energy in an energy store that is local to the distributed renewable energy resource.
20. The apparatus of claim 13 wherein controlling the excess energy comprises shedding an amount of the excess energy.
21. The method of claim 13 wherein to provide in a substantially continuous way the measurement related to energy consumed comprises to provide the measurement related to energy consumed at least once every 15 minutes.
22. The apparatus of claim 13 wherein to provide in a substantially continuous way the measurement related to energy generated comprises to provide the measurement related to energy generated at a rate sufficient to synchronize the energy generated by the distributed renewable resource with energy on an electrical grid.
23. The apparatus of claim 13 wherein the data analyzer is further configured to aggregate the excess energy from a plurality of distributed renewable resources.
24. The apparatus of claim 13 further wherein the data analyzer is further configured to forecast a quantity of excess energy for a preselected period of time based at least in part on the energy generated data and the energy consumed data.
US14/470,790 2011-11-28 2014-08-27 System and methods to assess, manage and control distributed renewable energy resources on a grid or microgrid and achieve a 100% renewable energy grid or microgrid from clean, carbon free, and water conserving distributed renewable energy technologies and resources Abandoned US20140371935A1 (en)

Priority Applications (1)

Application Number Priority Date Filing Date Title
US14/470,790 US20140371935A1 (en) 2011-11-28 2014-08-27 System and methods to assess, manage and control distributed renewable energy resources on a grid or microgrid and achieve a 100% renewable energy grid or microgrid from clean, carbon free, and water conserving distributed renewable energy technologies and resources

Applications Claiming Priority (3)

Application Number Priority Date Filing Date Title
US201161564219P 2011-11-28 2011-11-28
US13/685,478 US9727068B2 (en) 2011-11-28 2012-11-26 Energy search engine with autonomous control
US14/470,790 US20140371935A1 (en) 2011-11-28 2014-08-27 System and methods to assess, manage and control distributed renewable energy resources on a grid or microgrid and achieve a 100% renewable energy grid or microgrid from clean, carbon free, and water conserving distributed renewable energy technologies and resources

Related Parent Applications (1)

Application Number Title Priority Date Filing Date
US13/685,478 Continuation US9727068B2 (en) 2011-11-28 2012-11-26 Energy search engine with autonomous control

Publications (1)

Publication Number Publication Date
US20140371935A1 true US20140371935A1 (en) 2014-12-18

Family

ID=48466244

Family Applications (10)

Application Number Title Priority Date Filing Date
US13/685,478 Active 2036-02-24 US9727068B2 (en) 2011-11-28 2012-11-26 Energy search engine with autonomous control
US14/248,209 Abandoned US20140222232A1 (en) 2011-11-28 2014-04-08 Energy search engine methods and systems
US14/248,174 Abandoned US20140222665A1 (en) 2011-11-28 2014-04-08 Energy search engine methods and systems
US14/248,195 Abandoned US20140222231A1 (en) 2011-11-28 2014-04-08 Energy search engine methods and systems
US14/248,176 Abandoned US20140222486A1 (en) 2011-11-28 2014-04-08 Energy search engine methods and systems
US14/470,790 Abandoned US20140371935A1 (en) 2011-11-28 2014-08-27 System and methods to assess, manage and control distributed renewable energy resources on a grid or microgrid and achieve a 100% renewable energy grid or microgrid from clean, carbon free, and water conserving distributed renewable energy technologies and resources
US14/470,811 Abandoned US20140371936A1 (en) 2011-11-28 2014-08-27 System and methods to aggregate instant and forecasted excess renewable energy
US15/918,170 Active 2032-12-22 US10545525B2 (en) 2011-11-28 2018-03-12 Self-driving building energy engine
US16/773,117 Active US11275396B2 (en) 2011-11-28 2020-01-27 Method and apparatus to assess and control energy efficiency of fan installed in facility of building systems
US17/654,661 Active US11860661B2 (en) 2011-11-28 2022-03-14 Method and apparatus to assess and control energy efficiency of pump installed in facility of building systems

Family Applications Before (5)

Application Number Title Priority Date Filing Date
US13/685,478 Active 2036-02-24 US9727068B2 (en) 2011-11-28 2012-11-26 Energy search engine with autonomous control
US14/248,209 Abandoned US20140222232A1 (en) 2011-11-28 2014-04-08 Energy search engine methods and systems
US14/248,174 Abandoned US20140222665A1 (en) 2011-11-28 2014-04-08 Energy search engine methods and systems
US14/248,195 Abandoned US20140222231A1 (en) 2011-11-28 2014-04-08 Energy search engine methods and systems
US14/248,176 Abandoned US20140222486A1 (en) 2011-11-28 2014-04-08 Energy search engine methods and systems

Family Applications After (4)

Application Number Title Priority Date Filing Date
US14/470,811 Abandoned US20140371936A1 (en) 2011-11-28 2014-08-27 System and methods to aggregate instant and forecasted excess renewable energy
US15/918,170 Active 2032-12-22 US10545525B2 (en) 2011-11-28 2018-03-12 Self-driving building energy engine
US16/773,117 Active US11275396B2 (en) 2011-11-28 2020-01-27 Method and apparatus to assess and control energy efficiency of fan installed in facility of building systems
US17/654,661 Active US11860661B2 (en) 2011-11-28 2022-03-14 Method and apparatus to assess and control energy efficiency of pump installed in facility of building systems

Country Status (6)

Country Link
US (10) US9727068B2 (en)
EP (1) EP2786337A4 (en)
JP (1) JP6258861B2 (en)
CN (1) CN104303203B (en)
CA (1) CA2856887C (en)
WO (1) WO2013081978A1 (en)

Cited By (15)

* Cited by examiner, † Cited by third party
Publication number Priority date Publication date Assignee Title
US9014996B2 (en) 2011-04-22 2015-04-21 Excorda, Llc Universal energy internet of things apparatus and methods
US20160072291A1 (en) * 2013-04-25 2016-03-10 Mada Energie Ltd Energy processing and storage
US20160330285A1 (en) * 2015-05-04 2016-11-10 Johnson Controls Technology Company Hvac controller with integrated wireless network processor chip
US9727068B2 (en) 2011-11-28 2017-08-08 Melrok, Llc Energy search engine with autonomous control
US20170271915A1 (en) * 2016-03-16 2017-09-21 Why Energy, LLC Energy Demand Monitoring System and Smart micro-Grid Controller
US20170301036A1 (en) * 2016-04-14 2017-10-19 Vivint, Inc. Correlating resource usage data to a waste scoring system
WO2020198041A1 (en) * 2019-03-22 2020-10-01 Landis+Gyr Innovations, Inc. Validating fundamental-only energy measurement
US11243004B1 (en) * 2015-05-26 2022-02-08 Alarm.Com Incorporated Enthalpy measurement and system control
US11309734B2 (en) * 2018-03-23 2022-04-19 Electricity North West Property Limited System for controlling power consumption on a distribution grid
US11322940B2 (en) * 2018-03-23 2022-05-03 Electricty North West Property Limited System for frequency regulation on a power distribution network
WO2022115086A1 (en) * 2020-11-24 2022-06-02 Turkcell Teknoloji Arastirma Ve Gelistirme Anonim Sirketi A system for determining points of renewable energy generation
US20220253757A1 (en) * 2021-02-06 2022-08-11 Grownetics, Inc. Metaheuristics optimizer for controlled environment agriculture
US11422523B2 (en) 2021-01-22 2022-08-23 Toyota Motor North America, Inc. Prioritized building energy management
TWI778548B (en) * 2020-11-24 2022-09-21 日商東芝三菱電機產業系統股份有限公司 Plant monitoring and controlling system
US11731527B2 (en) 2021-01-22 2023-08-22 Toyota Motor North America, Inc. Transport charge capability re-routing

Families Citing this family (115)

* Cited by examiner, † Cited by third party
Publication number Priority date Publication date Assignee Title
US9715261B2 (en) * 2012-02-29 2017-07-25 Thomas Wilkins Continuous dynamic balancing of generation and loads
AU2013243953A1 (en) * 2012-04-02 2014-10-30 Modernatx, Inc. Modified polynucleotides for the production of nuclear proteins
WO2013151666A2 (en) * 2012-04-02 2013-10-10 modeRNA Therapeutics Modified polynucleotides for the production of biologics and proteins associated with human disease
JP2015534701A (en) * 2012-08-28 2015-12-03 デロス リビング エルエルシーDelos Living Llc Systems, methods, and articles for promoting wellness associated with living environments
CN103679306A (en) * 2012-08-31 2014-03-26 国际商业机器公司 Method and system for saving building energy consumption
US9002531B2 (en) * 2012-09-28 2015-04-07 Sharp Laboratories Of America, Inc. System and method for predictive peak load management via integrated load management
JP2016500245A (en) 2012-11-19 2016-01-07 リロス パワー ソリューション アクチエボラグ Battery charger for electric vehicles installed on a light pole
DE102012112369A1 (en) * 2012-12-17 2014-06-18 Krones Ag Method for determining a resource efficiency of a plant for producing beverage containers
US9439036B2 (en) 2013-01-25 2016-09-06 Visa International Service Association Systems and methods to select locations of interest based on distance from route points or route paths
KR20140096717A (en) * 2013-01-29 2014-08-06 한국전자통신연구원 BIM-based building energy management apparatus and method
US9599973B2 (en) * 2013-03-14 2017-03-21 International Business Machines Corporation Interactive energy device for environmental stewardship
US9704146B1 (en) 2013-03-14 2017-07-11 Square, Inc. Generating an online storefront
US9940616B1 (en) 2013-03-14 2018-04-10 Square, Inc. Verifying proximity during payment transactions
US11373191B2 (en) * 2013-03-15 2022-06-28 Usgbc Systems, devices, components and methods for dynamically displaying performance scores associated with the performance of a building or structure
US10055751B2 (en) * 2013-04-05 2018-08-21 Visa International Service Association Systems and methods to enhance search results using transaction data of merchants
US20150032661A1 (en) * 2013-07-26 2015-01-29 Recargo, Inc. Scoring charging stations used by electric vehicles
US10282794B2 (en) 2013-08-28 2019-05-07 Signify Holding B.V. System and method for determining energy and greenhouse gas (GHG) apportionment
US10417635B1 (en) 2013-10-22 2019-09-17 Square, Inc. Authorizing a purchase transaction using a mobile device
US9922321B2 (en) 2013-10-22 2018-03-20 Square, Inc. Proxy for multiple payment mechanisms
US8892462B1 (en) 2013-10-22 2014-11-18 Square, Inc. Proxy card payment with digital receipt delivery
US9836739B1 (en) 2013-10-22 2017-12-05 Square, Inc. Changing a financial account after initiating a payment using a proxy card
TWI525560B (en) * 2013-11-07 2016-03-11 財團法人資訊工業策進會 Performance management system, method and computer readable storage medium thereof
US20150134439A1 (en) 2013-11-08 2015-05-14 Square, Inc. Interactive digital receipt
US10810682B2 (en) 2013-12-26 2020-10-20 Square, Inc. Automatic triggering of receipt delivery
US10621563B1 (en) 2013-12-27 2020-04-14 Square, Inc. Apportioning a payment card transaction among multiple payers
US10495674B2 (en) * 2014-01-29 2019-12-03 Nec Corporation Monitoring device, monitoring system, monitoring method, correction information generation device, correction information generation method, and non-transitory storage medium
US10789396B1 (en) 2014-02-03 2020-09-29 Clean Power Research, L.L.C. Computer-implemented system and method for facilitating implementation of holistic zero net energy consumption
US10719636B1 (en) 2014-02-03 2020-07-21 Clean Power Research, L.L.C. Computer-implemented system and method for estimating gross energy load of a building
WO2015120141A1 (en) * 2014-02-05 2015-08-13 Texas State University Location mapping of grid devices using features of passively-observed current disturbances
CN103824124B (en) * 2014-02-08 2017-01-04 国家电网公司 A kind of energy potential evaluation method for grid company
US10198731B1 (en) 2014-02-18 2019-02-05 Square, Inc. Performing actions based on the location of mobile device during a card swipe
MX2016011107A (en) 2014-02-28 2017-02-17 Delos Living Llc Systems, methods and articles for enhancing wellness associated with habitable environments.
US9224141B1 (en) 2014-03-05 2015-12-29 Square, Inc. Encoding a magnetic stripe of a card with data of multiple cards
US10692059B1 (en) 2014-03-13 2020-06-23 Square, Inc. Selecting a financial account associated with a proxy object based on fund availability
US9864986B1 (en) 2014-03-25 2018-01-09 Square, Inc. Associating a monetary value card with a payment object
US9619792B1 (en) 2014-03-25 2017-04-11 Square, Inc. Associating an account with a card based on a photo
US10401401B2 (en) * 2014-03-31 2019-09-03 Panoramic Power Ltd. System and methods thereof for monitoring of energy consumption cycles
US20150288183A1 (en) 2014-04-06 2015-10-08 CleanSpark Technologies LLC Establishing communication and power sharing links between components of a distributed energy system
CN103884906A (en) * 2014-04-16 2014-06-25 上海市岩土工程检测中心 Energy efficiency comprehensive testing instrument
US20150332223A1 (en) 2014-05-19 2015-11-19 Square, Inc. Transaction information collection for mobile payment experience
US20150339266A1 (en) * 2014-05-23 2015-11-26 King Fahd University Of Petroleum And Minerals Ranking method for hybrid renewable distributed generation systems
GB201409495D0 (en) * 2014-05-28 2014-07-09 Oe Innovation Ltd Smart switches
EP3149665A1 (en) 2014-05-28 2017-04-05 Siemens Schweiz AG System and method for providing optimization or improvement measures for one or more buildings
US20150378381A1 (en) * 2014-06-30 2015-12-31 Qualcomm Incorporated Systems and methods for energy cost optimization
US10304053B1 (en) 2014-08-08 2019-05-28 Square, Inc. Shopping check-out with a payment card
US10296910B1 (en) 2014-08-08 2019-05-21 Square, Inc. Pay-by-name payment check-in with a payment card
US10614450B1 (en) 2014-08-08 2020-04-07 Squre, Inc. Controlled emulation of payment cards
US9951965B2 (en) * 2014-09-02 2018-04-24 Vivint, Inc. Smart HVAC
JP6404650B2 (en) * 2014-09-11 2018-10-10 株式会社東芝 Device operation set value determination device, device operation set value determination method, and device operation set value determination program
US9651929B2 (en) 2014-09-29 2017-05-16 International Business Machines Corporation HVAC system control integrated with demand response, on-site energy storage system and on-site energy generation system
US20160131688A1 (en) * 2014-11-11 2016-05-12 Solarcity Corporation Determining an orientation of a metering device in an energy generation system
US10473348B2 (en) * 2014-11-10 2019-11-12 Internal Air Flow Dynamics, Llc Method and system for eliminating air stratification via ductless devices
CN104392185B (en) * 2014-12-01 2017-11-10 公安部第三研究所 The method that data integrity validation is realized in cloud environment daily record evidence obtaining
US9992308B2 (en) * 2014-12-15 2018-06-05 Schneider Electric Software, Llc Historical summarization in a process control environment
AU2016202287B2 (en) 2015-01-13 2021-04-01 Delos Living Llc Systems, methods and articles for monitoring and enhancing human wellness
US11921478B2 (en) 2015-02-25 2024-03-05 Clean Power Research, L.L.C. System and method for estimating periodic fuel consumption for cooling of a building with the aid of a digital computer
US10339232B1 (en) * 2015-02-25 2019-07-02 Clean Power Research, L.L.C. Computer-implemented system and method for modeling building heating energy consumption
ES2820774T3 (en) * 2015-04-09 2021-04-22 Abb France Method for remote notification of user information from a building management system
CN104898618A (en) * 2015-05-08 2015-09-09 无锡中粮工程科技有限公司 Grain and oil processing production line energy management system and management method
US10026062B1 (en) 2015-06-04 2018-07-17 Square, Inc. Apparatuses, methods, and systems for generating interactive digital receipts
US10788228B2 (en) 2015-07-08 2020-09-29 Berner International Corporation Enhanced techniques for air curtain control
EP3337009A4 (en) * 2015-08-12 2019-03-20 Kyocera Corporation Management server, management method, and management system
US10394266B2 (en) 2015-08-26 2019-08-27 International Business Machines Corporation Energy consumption assessment
FR3041200A1 (en) * 2015-09-14 2017-03-17 Swg-Ta SYSTEM FOR CALCULATING AT LEAST ONE PARAMETER RELATING TO ENERGY PERFORMANCE OF A LOCAL AND ASSOCIATED METHOD
US11052776B2 (en) * 2015-09-24 2021-07-06 Ford Global Technologies, Llc Charging station for electrified vehicles
US20170088008A1 (en) * 2015-09-25 2017-03-30 Atieva, Inc. External Auxiliary Thermal Management System for an Electric Vehicle
US20170088007A1 (en) * 2015-09-25 2017-03-30 Atieva, Inc. External Auxiliary Thermal Management System for an Electric Vehicle
US10789587B2 (en) 2015-12-15 2020-09-29 Visa International Service Association Wireless short range communication link transmission of line item data in real time
US11214157B2 (en) * 2015-12-30 2022-01-04 Proterra Inc. Electric vehicle charging to reduce utility cost
US10636019B1 (en) 2016-03-31 2020-04-28 Square, Inc. Interactive gratuity platform
US10385829B2 (en) * 2016-05-11 2019-08-20 General Electric Company System and method for validating optimization of a wind farm
US10599204B1 (en) * 2016-06-29 2020-03-24 Amazon Technologies, Inc. Performance efficiency monitoring system
US10444210B2 (en) * 2016-07-29 2019-10-15 Baton Intelligent Power Limited System and method for real-time carbon emissions calculation for electrical devices
CN107726538B (en) * 2016-08-10 2020-12-22 国家电网公司 Intelligent building power utilization regulation and control method
US11338107B2 (en) 2016-08-24 2022-05-24 Delos Living Llc Systems, methods and articles for enhancing wellness associated with habitable environments
CN107368044A (en) * 2016-10-13 2017-11-21 宋显峰 A kind of real-time control method of intelligent electric appliance, system
CN108075465A (en) * 2016-11-18 2018-05-25 松下电器产业株式会社 Power-saving control method and electricity-saving control system
US20190024917A9 (en) * 2017-02-09 2019-01-24 James Eric Taylor Site-customized benchmark for operating an air conditioning system in real time
US11867417B2 (en) 2017-02-09 2024-01-09 James Eric Taylor On-site controller for an HVAC system
KR101892118B1 (en) 2017-02-14 2018-10-05 한국에너지기술연구원 Apparatus and method for measuring energy usage using a temperature sensor, and method for recommending home appliance using the energy usage
CN107194565B (en) * 2017-05-17 2019-12-24 国家电网公司 Power grid scheduling optimization method and system based on cloud decision
CN107092764A (en) * 2017-06-14 2017-08-25 成都智建新业建筑设计咨询有限公司 A kind of concrete assembled construction method based on BIM
CN107194112A (en) * 2017-06-14 2017-09-22 成都智建新业建筑设计咨询有限公司 The method being laid out based on BIM to garden landscape
CN107220785B (en) * 2017-07-17 2020-05-12 国家电网有限公司 Reasonable operation efficiency evaluation method and system for coordinating transmission network safety and development
US11668481B2 (en) 2017-08-30 2023-06-06 Delos Living Llc Systems, methods and articles for assessing and/or improving health and well-being
CN107862419A (en) * 2017-12-08 2018-03-30 清华大学 The low-carbon Optimization Scheduling and system of a kind of multipotency source network
US10466760B2 (en) * 2018-01-09 2019-11-05 Landis+Gyr Innovations, Inc. Energy consumption management based on game theoretical device prioritization
US11268996B2 (en) * 2018-03-30 2022-03-08 Johnson Controls Tyco IP Holdings LLP Building energy management system with virtual audit metrics
CN108829036B (en) * 2018-06-12 2021-05-14 昆明理工大学 Optimized scheduling method for metal casting blank cutting forming machining process
CN109190967B (en) * 2018-08-29 2020-09-01 华电电力科学研究院有限公司 Carbon emission accounting method and system for thermal generator set
EP3850458A4 (en) 2018-09-14 2022-06-08 Delos Living, LLC Systems and methods for air remediation
CN109543750A (en) * 2018-11-22 2019-03-29 广东省智能制造研究所 A kind of power consumption user energy efficiency evaluating method
CN109596196A (en) * 2018-12-06 2019-04-09 上海置信碳资产管理有限公司 Subsidiary carbon emission calculates the belted electronic balance and carbon emission accounting method of function
US20200271348A1 (en) * 2019-02-21 2020-08-27 Scientific Environmental Design, Inc. Hvac system and control methods for operation within a microgrid
US11844163B2 (en) 2019-02-26 2023-12-12 Delos Living Llc Method and apparatus for lighting in an office environment
CN109726875B (en) * 2019-03-08 2021-06-01 华北电力大学 Power dispatching prediction method based on three-way dispatching and economic dispatching
CN109787261B (en) * 2019-03-14 2020-12-29 国网江苏省电力有限公司镇江供电分公司 Power grid side and user side energy storage system capacity optimization configuration method
WO2020198183A1 (en) 2019-03-25 2020-10-01 Delos Living Llc Systems and methods for acoustic monitoring
EP3726307A1 (en) * 2019-04-17 2020-10-21 Carrier Corporation Method for controlling building power consumption
EP3968039B1 (en) * 2019-05-07 2023-11-01 Tatsumi Ryoki Co., Ltd Load testing device
CN110135662B (en) * 2019-06-06 2021-04-20 杭州电子科技大学 Energy storage site selection constant volume multi-objective optimization method considering reduction of peak-valley difference
US11079731B2 (en) 2019-10-07 2021-08-03 Honeywell International Inc. Multi-site building management system
KR102253734B1 (en) * 2019-11-26 2021-05-20 주식회사 비엠티 Power demand management system for buildings
CN111105096A (en) * 2019-12-23 2020-05-05 南方电网科学研究院有限责任公司 New energy grid-connected layout planning method and system
FI129082B (en) * 2020-04-01 2021-06-30 Rasmus Relander Determining Maintenance Need of Air Conditioning Unit
US11760223B2 (en) 2020-06-23 2023-09-19 Toyota Motor North America, Inc. Need-based energy sharing
US11345251B2 (en) 2020-06-23 2022-05-31 Toyota Motor North America, Inc. Priority-based energy transfer
US20220004902A1 (en) * 2020-07-02 2022-01-06 Energy Optimization System Laboratories Llc Methods for remote building intelligence, energy waste detection, efficiency tracking, utility management and analytics
US11586422B2 (en) * 2021-05-06 2023-02-21 International Business Machines Corporation Automated system capacity optimization
US20230114427A1 (en) * 2021-10-13 2023-04-13 Johnson Controls Tyco IP Holdings LLP Building system for building equipment with occupant feedback based verification
CN114527247B (en) * 2021-12-20 2023-12-22 广州迪森数字能源科技有限公司 Comprehensive boiler water quality monitoring method, system and equipment based on Internet of things
US11818006B2 (en) * 2022-01-25 2023-11-14 Cisco Technology, Inc. Environmental sustainability of networking devices and systems
WO2024050409A1 (en) * 2022-09-01 2024-03-07 Blocpower L.L.C. System and methods for retrofit energy prediction
CN116109216B (en) * 2023-04-13 2023-06-23 国网湖北省电力有限公司营销服务中心(计量中心) Adjustability assessment method of source network storage system
CN117474360B (en) * 2023-11-08 2024-04-09 胜利油田胜兴集团有限责任公司 Intelligent heating environment assessment system suitable for trough type solar energy

Citations (9)

* Cited by examiner, † Cited by third party
Publication number Priority date Publication date Assignee Title
US6487509B1 (en) * 1996-02-20 2002-11-26 Wrap Spa Method for the energy management in a domestic environment
US20100023174A1 (en) * 2007-03-26 2010-01-28 Satoshi Nagata Electric power system
US20100030391A1 (en) * 2006-07-31 2010-02-04 Jean-Marc Oury Method and System of Real Time Management and Modulation of Electricity Consumption
US20100217452A1 (en) * 2009-02-26 2010-08-26 Mccord Alan Overlay packet data network for managing energy and method for using same
US20110082598A1 (en) * 2009-10-02 2011-04-07 Tod Boretto Electrical Power Time Shifting
US20120158198A1 (en) * 2010-12-17 2012-06-21 General Electric Company System and method for managing cold load pickup using demand response
US20120249278A1 (en) * 2011-03-31 2012-10-04 General Electric Company System and method for operating a tap changer
US20120253539A1 (en) * 2011-03-30 2012-10-04 General Electric Company Systems and methods for synchronizing switching within a power distribution network
US20120316691A1 (en) * 2011-06-08 2012-12-13 Alstom Grid Load phase balancing at multiple tiers of a multi-tier hierarchical intelligent power distribution grid

Family Cites Families (148)

* Cited by examiner, † Cited by third party
Publication number Priority date Publication date Assignee Title
US4956875A (en) 1988-07-05 1990-09-11 Com-Ser Laboratories, Inc. Emergency radio alerting and message transmitting system directable to selected classes and numbers of receivers
DK35390D0 (en) 1990-02-09 1990-02-09 Elforsynings Andelsselskabet S CONTROL AND COMMUNICATION SYSTEM
CA2052500C (en) 1991-09-30 1995-09-19 Jozef Z. Babiarz Pabx common channel relay system
US5590195A (en) 1993-03-15 1996-12-31 Command Audio Corporation Information dissemination using various transmission modes
US5406626A (en) 1993-03-15 1995-04-11 Macrovision Corporation Radio receiver for information dissemenation using subcarrier
US6167389A (en) 1996-12-23 2000-12-26 Comverge Technologies, Inc. Method and apparatus using distributed intelligence for applying real time pricing and time of use rates in wide area network including a headend and subscriber
US6005894A (en) 1997-04-04 1999-12-21 Kumar; Derek D. AM-compatible digital broadcasting method and system
JPH11262176A (en) 1998-03-11 1999-09-24 Toshiba Corp Power system monitor/control system and power system monitor/control method therefor
US20030158826A1 (en) 1998-03-13 2003-08-21 Michael C. Burke Methods and apparatus for a utility processing system
JP2000115162A (en) 1998-10-08 2000-04-21 Kodo Ido Tsushin Security Gijutsu Kenkyusho:Kk Secure communication equipment and storage device
US6707811B2 (en) 1999-03-19 2004-03-16 Estara, Inc. Internet telephony for ecommerce
AU6097600A (en) 1999-07-15 2001-02-05 Ebidenergy.Com User interface to facilitate, analyze and manage resource consumption
JP2001312523A (en) 2000-04-28 2001-11-09 Daikin Ind Ltd Method and apparatus for energy saving diagonosis
AU2001278923A1 (en) * 2000-07-13 2002-01-30 Nxegen System and method for monitoring and controlling energy usage
US6466938B1 (en) 2000-07-31 2002-10-15 Motorola, Inc. Method and apparatus for locating a device using a database containing hybrid location data
US6938005B2 (en) 2000-12-21 2005-08-30 Intel Corporation Digital content distribution
US6842706B1 (en) 2001-01-17 2005-01-11 Smart Disaster Response Technologies, Inc. Methods, apparatus, media, and signals for managing utility usage
US6708147B2 (en) 2001-02-28 2004-03-16 Telefonaktiebolaget Lm Ericsson(Publ) Method and apparatus for providing comfort noise in communication system with discontinuous transmission
US7587481B1 (en) 2001-04-05 2009-09-08 Dj Inventions, Llc Enterprise server for SCADA system with security interface
US6865450B2 (en) 2001-05-10 2005-03-08 Siemens Westinghouse Power Corporation Schedule-based load estimator and method for electric power and other utilities and resources
US7346463B2 (en) 2001-08-09 2008-03-18 Hunt Technologies, Llc System for controlling electrically-powered devices in an electrical network
JP4609690B2 (en) * 2001-08-31 2011-01-12 清水建設株式会社 Thermal load pattern calculation system and method, and computer program
US7356548B1 (en) 2001-12-03 2008-04-08 The Texas A&M University System System and method for remote monitoring and controlling of facility energy consumption
US6937946B1 (en) 2001-12-04 2005-08-30 The Texas A&M University System System and method for remote identification of energy consumption systems and components
JP4334176B2 (en) * 2002-01-22 2009-09-30 株式会社東芝 Building energy conservation evaluation monitoring device
WO2003084022A1 (en) * 2002-03-28 2003-10-09 Robertshaw Controls Company Energy management system and method
US7069117B2 (en) 2002-04-01 2006-06-27 Programmable Control Services, Inc. Electrical power distribution control systems and processes
US7049976B2 (en) 2002-04-15 2006-05-23 Hunt Power, L.P. User-installable power consumption monitoring system
JP2004112371A (en) 2002-09-19 2004-04-08 Sanyo Electric Co Ltd Broadcast receiver, apparatus with broadcast reception function, and broadcast reception control system
JP4623992B2 (en) 2003-04-18 2011-02-02 パナソニック株式会社 Transmitter and receiver
JP2004350044A (en) 2003-05-22 2004-12-09 Tdk Corp Transmitter, receiver, communication system, and communication method
US20070043478A1 (en) * 2003-07-28 2007-02-22 Ehlers Gregory A System and method of controlling an HVAC system
WO2005098673A1 (en) 2004-04-09 2005-10-20 Sony Corporation Preference information collecting system, device, method, and program
US20050240427A1 (en) 2004-04-26 2005-10-27 Crichlow Henry B Energy management method and process using analytic metrics.
US7239044B1 (en) 2004-12-09 2007-07-03 Sandia Corporation Enhanced distributed energy resource system
US7991426B2 (en) 2004-12-13 2011-08-02 Broadcom Corporation Method and system for joint broadcast receiving and cellular communication via a mobile terminal or device with UMTS as an integration channel
US7181293B2 (en) 2004-12-27 2007-02-20 Intel Corporation System and method for enabling home power management
US8666688B2 (en) 2005-01-27 2014-03-04 Electro Industries/Gauge Tech High speed digital transient waveform detection system and method for use in an intelligent electronic device
US8190381B2 (en) 2005-01-27 2012-05-29 Electro Industries/Gauge Tech Intelligent electronic device with enhanced power quality monitoring and communications capabilities
US7809342B2 (en) 2005-02-08 2010-10-05 E-Radio Usa, Inc. Systems and methods for providing product information over a carrier wave
FI117653B (en) 2005-02-21 2006-12-29 Eigenor Oy Procedure and arrangement for sensing objects with a radar
GB2439490B (en) 2005-03-08 2008-12-17 Radio Usa Inc E Systems and methods for modifying power usage
US7508884B2 (en) 2005-03-24 2009-03-24 Harris Corporation System and method for communicating data using constant amplitude equalized waveform
JP4769475B2 (en) 2005-04-06 2011-09-07 株式会社ハートランド CONTENT DISTRIBUTION SERVER AND CONTENT DISTRIBUTION SYSTEM HAVING THE SAME
US7840993B2 (en) 2005-05-04 2010-11-23 Tricipher, Inc. Protecting one-time-passwords against man-in-the-middle attacks
KR100679118B1 (en) 2005-05-19 2007-02-06 이경수 Service system and method for management and ASP service of establishments assets using a optimized management technique of facilities
US7647516B2 (en) * 2005-09-22 2010-01-12 Hewlett-Packard Development Company, L.P. Power consumption management among compute nodes
WO2007041693A2 (en) 2005-10-04 2007-04-12 Thompson Technology Industries, Inc. System and method for array and string level monitoring of a grid-connected photovoltaic power system
JP4597028B2 (en) 2005-10-20 2010-12-15 住友林業株式会社 Ventilation / thermal diagnosis system
CA2630862A1 (en) 2005-11-23 2007-05-31 Quadlogic Controls Corporation Systems and methods for electricity metering
WO2007118128A2 (en) 2006-04-07 2007-10-18 I-Conserve, Llc Artificial-intelligence-based energy auditing, monitoring and control
US20070265780A1 (en) 2006-04-21 2007-11-15 Kevin Kesler System and method for predicting future rail temperature
US7476987B2 (en) 2006-04-25 2009-01-13 The University Of New Brunswick Stand-alone wind turbine system, apparatus, and method suitable for operating the same
US8103389B2 (en) 2006-05-18 2012-01-24 Gridpoint, Inc. Modular energy control system
US7885917B2 (en) * 2006-05-26 2011-02-08 Board Of Regents Of The Nevada System Of Higher Education, On Behalf Of The Desert Research Institute Utility monitoring and disaggregation systems and methods of use
KR100701298B1 (en) 2006-07-07 2007-03-29 주식회사 실버크리너 Ubiquitous automatic meter reading and cutting system using home automation system, and method thereof
US20080046387A1 (en) 2006-07-23 2008-02-21 Rajeev Gopal System and method for policy based control of local electrical energy generation and use
US7844370B2 (en) 2006-08-10 2010-11-30 Gridpoint, Inc. Scheduling and control in a power aggregation system for distributed electric resources
US8914433B2 (en) 2006-09-20 2014-12-16 At&T Intellectual Property I, L.P. Publish-subscription platforms for alert messages and related methods and computer program products
JP2008102709A (en) * 2006-10-18 2008-05-01 Toshiba Corp Energy management system and energy management method
JP2008102708A (en) 2006-10-18 2008-05-01 Toshiba Corp Energy management support device
US8473250B2 (en) 2006-12-06 2013-06-25 Solaredge, Ltd. Monitoring of distributed power harvesting systems using DC power sources
US20080177678A1 (en) 2007-01-24 2008-07-24 Paul Di Martini Method of communicating between a utility and its customer locations
US8103465B2 (en) 2007-04-09 2012-01-24 Noveda Technologies, Inc. System and method for monitoring and managing energy performance
US7756464B2 (en) 2007-06-12 2010-07-13 Broadcom Corporation Alternate radio channel selection adapted per user patterns
US10295969B2 (en) 2007-08-28 2019-05-21 Causam Energy, Inc. System and method for generating and providing dispatchable operating reserve energy capacity through use of active load management
JP2009070339A (en) 2007-09-18 2009-04-02 Denso Facilities Corp Energy consumption information announcing system
US8140279B2 (en) 2007-09-24 2012-03-20 Budderfly Ventures, Llc Computer based energy management
JP2009088641A (en) 2007-09-27 2009-04-23 Kyocera Corp Transmission reception method, communication system and transmitter
EP2098827A1 (en) 2008-03-04 2009-09-09 Alcatel Lucent Method of remote metering of energy
US8063775B2 (en) 2008-04-11 2011-11-22 Bay Controls, Llc Energy management system
CA2724288A1 (en) 2008-05-12 2009-11-19 Energy And Power Solutions, Inc. Systems and methods for assessing and optimizing energy use and environmental impact
US20090307573A1 (en) 2008-06-06 2009-12-10 Enthenergy, Llc Energy management system
US20100019574A1 (en) 2008-07-24 2010-01-28 John Baldassarre Energy management system for auxiliary power source
TWI364518B (en) * 2008-07-29 2012-05-21 Ind Tech Res Inst Power saving managing method and system using the same
US7953518B2 (en) 2008-09-08 2011-05-31 Microsoft Corporation Energy cost reduction and ad delivery
GB0816721D0 (en) 2008-09-13 2008-10-22 Daniel Simon R Systems,devices and methods for electricity provision,usage monitoring,analysis and enabling improvements in efficiency
US8559197B2 (en) 2008-10-13 2013-10-15 Infinia Corporation Electrical control circuits for an energy converting apparatus
US8260469B2 (en) 2008-11-04 2012-09-04 Green Energy Corporation Distributed hybrid renewable energy power plant and methods, systems, and comptuer readable media for controlling a distributed hybrid renewable energy power plant
CA2743667A1 (en) 2008-11-14 2010-05-20 Thinkeco Power Inc. System and method of democratizing power to create a meta-exchange
CN201327587Y (en) 2008-11-21 2009-10-14 杜晓通 Energy management system of building based on energy efficiency
US20100145884A1 (en) * 2008-12-04 2010-06-10 American Power Conversion Corporation Energy savings aggregation
EP2387776A4 (en) 2009-01-14 2013-03-20 Integral Analytics Inc Optimization of microgrid energy use and distribution
US8706650B2 (en) 2009-01-14 2014-04-22 Integral Analytics, Inc. Optimization of microgrid energy use and distribution
ATE517353T1 (en) 2009-02-19 2011-08-15 Abb Research Ltd METHOD FOR TESTING A POWER DISTRIBUTION SYSTEM AND POWER DISTRIBUTION SYSTEM ANALYZER
WO2010102150A1 (en) * 2009-03-04 2010-09-10 Server Technology, Inc. Monitoring power-related parameters in a power distribution unit
CN101510686B (en) 2009-03-26 2011-01-26 上海交通大学 Micro electric network coordination control system based on multi-proxy technology
JP2010237774A (en) * 2009-03-30 2010-10-21 Omron Corp System, method, device, and program for supporting consumed energy improvement, and recording medium
US20110004406A1 (en) 2009-03-31 2011-01-06 Gridpoint, Inc. Systems and methods for location determination of devices using network fingerprints for power management
US8532808B2 (en) * 2009-06-22 2013-09-10 Johnson Controls Technology Company Systems and methods for measuring and verifying energy savings in buildings
US8600556B2 (en) 2009-06-22 2013-12-03 Johnson Controls Technology Company Smart building manager
US8700224B2 (en) 2009-06-25 2014-04-15 Renewable Energy Technology Group Ltd. (RETG) System for a single point plug-in, connection of any combination of electric energy supply sources combined with smart load management and control of both supply and consumption of electric energy by a home or small business
US8369997B2 (en) 2010-04-28 2013-02-05 David Valin Solar panel wind turbine communication server network apparatus method and mechanism
US8775846B2 (en) 2009-07-10 2014-07-08 Protonex Technology Corporation Portable power manager having one or more device ports for connecting with external power loads
US7925387B2 (en) 2009-07-14 2011-04-12 General Electric Company Method and systems for utilizing excess energy generated by a renewable power generation system to treat organic waste material
JP4783453B2 (en) 2009-09-10 2011-09-28 力也 阿部 Multi-terminal type asynchronous interconnection device, power equipment control terminal device, power network system and control method therefor
US8185250B2 (en) 2009-09-23 2012-05-22 Peoplewave, Inc. Power load control system for utility power system
JP5479182B2 (en) 2009-09-30 2014-04-23 三洋電機株式会社 Power generation system and charge / discharge control device
KR101542409B1 (en) 2009-11-26 2015-08-12 엘지전자 주식회사 Electric Appliance for power management
EP2348596B1 (en) 2010-01-25 2021-09-08 Accenture Global Services Limited Analytics for consumer power consumption
JP2013518556A (en) 2010-01-25 2013-05-20 ジェネヴァ クリーンテック インコーポレイテッド Automatic detection of home appliances
WO2011109757A1 (en) 2010-03-05 2011-09-09 Efficient Energy America Incorporated System and method for providing automated electrical energy demand management
CN201622466U (en) 2010-03-17 2010-11-03 山东光辉数码科技有限公司 Building energy-saving control management system based on energy efficiency optimization
JP2011223841A (en) 2010-04-14 2011-11-04 Sharp Corp Power supply system and network system
WO2011156776A2 (en) 2010-06-10 2011-12-15 The Regents Of The University Of California Smart electric vehicle (ev) charging and grid integration apparatus and methods
US8335596B2 (en) 2010-07-16 2012-12-18 Verizon Patent And Licensing Inc. Remote energy management using persistent smart grid network context
US8918220B2 (en) * 2010-08-05 2014-12-23 Trane U.S. Inc. Building energy management method and system
JP5615090B2 (en) 2010-08-20 2014-10-29 三菱重工業株式会社 Management device, management method, computer program, in-vehicle device, and communication method
JP5395764B2 (en) 2010-08-24 2014-01-22 株式会社日立製作所 Electric vehicle charging control method, charging monitoring control center, in-vehicle car navigation system, and power system stabilization system
US8352083B2 (en) 2010-08-26 2013-01-08 Comverge, Inc. System and method for establishing local control of a space conditioning load during a direct load control event
US8560133B2 (en) 2010-09-01 2013-10-15 General Electric Company Energy smart system
US20120078547A1 (en) 2010-09-27 2012-03-29 Lutron Electronics Co., Inc. Internet based energy control system
US20120083934A1 (en) * 2010-09-30 2012-04-05 Sharp Laboratories Of America, Inc. Monitoring and controlling energy in an office environment
US8930037B2 (en) * 2010-10-01 2015-01-06 General Electric Company Energy manager with minimum use energy profile
CN101976390A (en) 2010-10-27 2011-02-16 深圳市海亿达电子有限公司 Energy managing method, energy managing system and energy dispatching and managing center
US8401711B2 (en) 2010-10-28 2013-03-19 Solar Chief, Llc System and method for managing distributed renewable energy systems
US10069454B2 (en) 2010-10-28 2018-09-04 Solar Chief, Llc System and method for managing distributed renewable energy systems and service providers
US20120143539A1 (en) 2010-12-02 2012-06-07 Damian Krause Energy Monitor
US20120176252A1 (en) * 2011-01-12 2012-07-12 Emerson Electric Co. Apparatus and Method for Determining Load of Energy Consuming Appliances Within a Premises
US8892061B2 (en) 2011-03-24 2014-11-18 At&T Intellectual Property I, L.P. Methods, devices, and computer program products for tracking receipt and determining effectiveness of radio broadcast signals
US9837821B2 (en) 2011-03-25 2017-12-05 Green Charge Networks Llc Energy allocation for energy storage cooperation
US8666685B2 (en) 2011-04-19 2014-03-04 Schneider Electronic IT Corporation System of intelligent sensors in an electrical panelboard
EP2700061A4 (en) 2011-04-22 2014-11-19 Expanergy Llc Systems and methods for analyzing energy usage
EP2715478A4 (en) 2011-05-26 2014-10-29 Ice Energy Inc System and method for improving grid efficiency utilizing statistical distribution control
US9250308B2 (en) * 2011-06-03 2016-02-02 Veris Industries, Llc Simplified energy meter configuration
US20120323382A1 (en) 2011-06-15 2012-12-20 Expanergy, Llc Systems and methods to assess and optimize energy usage for a facility
US20130066482A1 (en) 2011-09-13 2013-03-14 Samsung Electronics Co., Ltd. Apparatus and method for executing energy demand response process in an electrical power network
US8645239B2 (en) 2011-11-03 2014-02-04 Florida Power & Light Company Systems and methods for advanced metering infrastructure customer portal
EP2786337A4 (en) 2011-11-28 2015-08-26 Expanergy Llc Energy search engine methods and systems
CN103259826B (en) 2012-02-20 2016-06-01 伊顿公司 For the data transmission device between charger and electric motor car and method
US20130274936A1 (en) 2012-04-15 2013-10-17 Swan, Llc Broadcast energy demand systems and methods
US9363103B2 (en) 2012-06-22 2016-06-07 Alcatel Lucent Energy-management in a user-premises area network
US20140019384A1 (en) 2012-07-10 2014-01-16 General Electric Company Utility meter system
US9563215B2 (en) 2012-07-14 2017-02-07 Causam Energy, Inc. Method and apparatus for actively managing electric power supply for an electric power grid
US9307027B2 (en) 2013-01-15 2016-04-05 Toyota Jidosha Kabushiki Kaisha Identifying server protocol for translation in smart grid
US20140229031A1 (en) 2013-02-14 2014-08-14 Petra Solar, Inc. Micro-Inverter Based AC-Coupled Photovoltaic Microgrid System with Wireless Smart-Grid Controls
US20150005968A1 (en) 2013-07-01 2015-01-01 Enernoc, Inc. Apparatus and method for determining device participation in an energy management program
US9733623B2 (en) 2013-07-31 2017-08-15 Abb Research Ltd. Microgrid energy management system and method for controlling operation of a microgrid
US9812870B2 (en) 2013-08-21 2017-11-07 Nec Corporation Microgrid reactive power management for voltage regulation during and subsequent to islanding
US10135247B2 (en) 2013-10-17 2018-11-20 General Electric Company Methods and systems for integrated Volt/VAr control in electric network
EP3149665A1 (en) * 2014-05-28 2017-04-05 Siemens Schweiz AG System and method for providing optimization or improvement measures for one or more buildings
US20160033986A1 (en) 2014-07-30 2016-02-04 Melrok, Llc Systems and methods to manage renewable energy on the electric grid
CN204376420U (en) 2014-12-09 2015-06-03 三峡大学 A kind of microgrid energy management control system
US9998434B2 (en) 2015-01-26 2018-06-12 Listat Ltd. Secure dynamic communication network and protocol
WO2016168503A1 (en) 2015-04-15 2016-10-20 Melrok, Llc Secure broadcast systems and methods for internet of things devices
US9960637B2 (en) 2015-07-04 2018-05-01 Sunverge Energy, Inc. Renewable energy integrated storage and generation systems, apparatus, and methods with cloud distributed energy management services
DE102015113799A1 (en) 2015-08-20 2017-02-23 Rwe Ag Charging station for electric vehicles and interface device in such a charging station and method for operating a charging station
US20170302065A1 (en) 2016-04-13 2017-10-19 Sweep Energy Energy monitoring system

Patent Citations (9)

* Cited by examiner, † Cited by third party
Publication number Priority date Publication date Assignee Title
US6487509B1 (en) * 1996-02-20 2002-11-26 Wrap Spa Method for the energy management in a domestic environment
US20100030391A1 (en) * 2006-07-31 2010-02-04 Jean-Marc Oury Method and System of Real Time Management and Modulation of Electricity Consumption
US20100023174A1 (en) * 2007-03-26 2010-01-28 Satoshi Nagata Electric power system
US20100217452A1 (en) * 2009-02-26 2010-08-26 Mccord Alan Overlay packet data network for managing energy and method for using same
US20110082598A1 (en) * 2009-10-02 2011-04-07 Tod Boretto Electrical Power Time Shifting
US20120158198A1 (en) * 2010-12-17 2012-06-21 General Electric Company System and method for managing cold load pickup using demand response
US20120253539A1 (en) * 2011-03-30 2012-10-04 General Electric Company Systems and methods for synchronizing switching within a power distribution network
US20120249278A1 (en) * 2011-03-31 2012-10-04 General Electric Company System and method for operating a tap changer
US20120316691A1 (en) * 2011-06-08 2012-12-13 Alstom Grid Load phase balancing at multiple tiers of a multi-tier hierarchical intelligent power distribution grid

Cited By (30)

* Cited by examiner, † Cited by third party
Publication number Priority date Publication date Assignee Title
US9052216B2 (en) 2011-04-22 2015-06-09 Excorda, Llc Universal internet of things apparatus and methods
US11670959B2 (en) 2011-04-22 2023-06-06 Melrok, Llc Systems and methods to manage and control energy management systems
US9909901B2 (en) 2011-04-22 2018-03-06 Melrok, Llc Systems and methods to manage and control renewable distributed energy resources
US10228265B2 (en) 2011-04-22 2019-03-12 Melrok, Llc Systems and methods to manage and control renewable distributed energy resources
US9014996B2 (en) 2011-04-22 2015-04-21 Excorda, Llc Universal energy internet of things apparatus and methods
US10768015B2 (en) 2011-04-22 2020-09-08 Melrok, Llc Systems and methods to manage and control energy management systems
US10545525B2 (en) 2011-11-28 2020-01-28 Melrok, Llc Self-driving building energy engine
US11860661B2 (en) 2011-11-28 2024-01-02 Melrok, Llc Method and apparatus to assess and control energy efficiency of pump installed in facility of building systems
US9727068B2 (en) 2011-11-28 2017-08-08 Melrok, Llc Energy search engine with autonomous control
US11275396B2 (en) 2011-11-28 2022-03-15 Melrok, Llc Method and apparatus to assess and control energy efficiency of fan installed in facility of building systems
US20160072291A1 (en) * 2013-04-25 2016-03-10 Mada Energie Ltd Energy processing and storage
US10798177B2 (en) 2015-05-04 2020-10-06 Johnson Controls Technology Company HVAC controller with integrated wireless network processor chip
US20160330285A1 (en) * 2015-05-04 2016-11-10 Johnson Controls Technology Company Hvac controller with integrated wireless network processor chip
US11770453B2 (en) 2015-05-04 2023-09-26 Johnson Controls Technology Company HVAC controller with integrated wireless network processor chip
US11196814B2 (en) 2015-05-04 2021-12-07 Johnson Controls Technology Company HVAC controller with integrated wireless network processor chip
US10484478B2 (en) * 2015-05-04 2019-11-19 Johnson Controls Technology Company HVAC controller with integrated wireless network processor chip
US11243004B1 (en) * 2015-05-26 2022-02-08 Alarm.Com Incorporated Enthalpy measurement and system control
US20170271915A1 (en) * 2016-03-16 2017-09-21 Why Energy, LLC Energy Demand Monitoring System and Smart micro-Grid Controller
US10395322B2 (en) * 2016-04-14 2019-08-27 Vivint, Inc. Correlating resource usage data to a waste scoring system
US11100594B1 (en) * 2016-04-14 2021-08-24 Vivint, Inc. Correlating resource usage data to a waste scoring system
US20170301036A1 (en) * 2016-04-14 2017-10-19 Vivint, Inc. Correlating resource usage data to a waste scoring system
US11309734B2 (en) * 2018-03-23 2022-04-19 Electricity North West Property Limited System for controlling power consumption on a distribution grid
US11322940B2 (en) * 2018-03-23 2022-05-03 Electricty North West Property Limited System for frequency regulation on a power distribution network
US10830859B2 (en) 2019-03-22 2020-11-10 Landis+Gyr Innovations, Inc. Validating fundamental-only energy measurement
WO2020198041A1 (en) * 2019-03-22 2020-10-01 Landis+Gyr Innovations, Inc. Validating fundamental-only energy measurement
WO2022115086A1 (en) * 2020-11-24 2022-06-02 Turkcell Teknoloji Arastirma Ve Gelistirme Anonim Sirketi A system for determining points of renewable energy generation
TWI778548B (en) * 2020-11-24 2022-09-21 日商東芝三菱電機產業系統股份有限公司 Plant monitoring and controlling system
US11422523B2 (en) 2021-01-22 2022-08-23 Toyota Motor North America, Inc. Prioritized building energy management
US11731527B2 (en) 2021-01-22 2023-08-22 Toyota Motor North America, Inc. Transport charge capability re-routing
US20220253757A1 (en) * 2021-02-06 2022-08-11 Grownetics, Inc. Metaheuristics optimizer for controlled environment agriculture

Also Published As

Publication number Publication date
US20200393863A1 (en) 2020-12-17
US9727068B2 (en) 2017-08-08
US20140222231A1 (en) 2014-08-07
US20140222232A1 (en) 2014-08-07
CN104303203A (en) 2015-01-21
JP2015504567A (en) 2015-02-12
US20140222486A1 (en) 2014-08-07
US20140371936A1 (en) 2014-12-18
US10545525B2 (en) 2020-01-28
JP6258861B2 (en) 2018-01-10
US11275396B2 (en) 2022-03-15
EP2786337A1 (en) 2014-10-08
US20230036128A1 (en) 2023-02-02
WO2013081978A1 (en) 2013-06-06
US20140222665A1 (en) 2014-08-07
CA2856887C (en) 2021-06-15
CA2856887A1 (en) 2013-06-06
EP2786337A4 (en) 2015-08-26
US11860661B2 (en) 2024-01-02
US20180299917A1 (en) 2018-10-18
CN104303203B (en) 2018-04-13
US20130134962A1 (en) 2013-05-30

Similar Documents

Publication Publication Date Title
US11860661B2 (en) Method and apparatus to assess and control energy efficiency of pump installed in facility of building systems
US11670959B2 (en) Systems and methods to manage and control energy management systems
US20140379156A1 (en) System and methods to wirelessly control distributed renewable energy on the grid or microgrid
CA2784548C (en) Method, system and computer program product for scheduling demand events
US20100262313A1 (en) System and method for energy consumption management
SG178116A1 (en) Responsive load monitoring system and method
Sayed et al. Building energy management systems (BEMS)
Avotins et al. IoT solution approach for energy consumption reduction in buildings: Part 1. Existing situation and problems regarding electrical consumption
Samuel Control of Smart Building Using Advanced SCADA
Bleyl et al. Simplified measurement & verification+ quality assurance instruments for energy, water and CO 2 savings—methodologies and examples
Perez Analysis, modeling and optimization of residential energy use from smart meter data

Legal Events

Date Code Title Description
AS Assignment

Owner name: EXCORDA, LLC, NEVADA

Free format text: ASSIGNMENT OF ASSIGNORS INTEREST;ASSIGNOR:EXPANERGY, LLC;REEL/FRAME:034885/0375

Effective date: 20150127

Owner name: EXPANERGY, LLC, NEVADA

Free format text: ASSIGNMENT OF ASSIGNORS INTEREST;ASSIGNORS:KAMEL, MICHEL ROGER;DONAHUE, PAUL W.;DANKWORTH, JEFFREY ALAN;SIGNING DATES FROM 20150127 TO 20150130;REEL/FRAME:034885/0253

AS Assignment

Owner name: MELROK, LLC, NEVADA

Free format text: CHANGE OF NAME;ASSIGNOR:EXCORDA, LLC;REEL/FRAME:036527/0621

Effective date: 20150514

STCB Information on status: application discontinuation

Free format text: ABANDONED -- FAILURE TO RESPOND TO AN OFFICE ACTION