KR101838024B1 - Smart construction method of electric work - Google Patents

Smart construction method of electric work Download PDF

Info

Publication number
KR101838024B1
KR101838024B1 KR1020170123606A KR20170123606A KR101838024B1 KR 101838024 B1 KR101838024 B1 KR 101838024B1 KR 1020170123606 A KR1020170123606 A KR 1020170123606A KR 20170123606 A KR20170123606 A KR 20170123606A KR 101838024 B1 KR101838024 B1 KR 101838024B1
Authority
KR
South Korea
Prior art keywords
work
terminal
worker
construction
schedule
Prior art date
Application number
KR1020170123606A
Other languages
Korean (ko)
Inventor
송호균
Original Assignee
(주) 우진일렉트
Priority date (The priority date is an assumption and is not a legal conclusion. Google has not performed a legal analysis and makes no representation as to the accuracy of the date listed.)
Filing date
Publication date
Application filed by (주) 우진일렉트 filed Critical (주) 우진일렉트
Priority to KR1020170123606A priority Critical patent/KR101838024B1/en
Application granted granted Critical
Publication of KR101838024B1 publication Critical patent/KR101838024B1/en

Links

Images

Classifications

    • GPHYSICS
    • G06COMPUTING; CALCULATING OR COUNTING
    • G06QINFORMATION AND COMMUNICATION TECHNOLOGY [ICT] SPECIALLY ADAPTED FOR ADMINISTRATIVE, COMMERCIAL, FINANCIAL, MANAGERIAL OR SUPERVISORY PURPOSES; SYSTEMS OR METHODS SPECIALLY ADAPTED FOR ADMINISTRATIVE, COMMERCIAL, FINANCIAL, MANAGERIAL OR SUPERVISORY PURPOSES, NOT OTHERWISE PROVIDED FOR
    • G06Q50/00Systems or methods specially adapted for specific business sectors, e.g. utilities or tourism
    • G06Q50/08Construction
    • GPHYSICS
    • G06COMPUTING; CALCULATING OR COUNTING
    • G06QINFORMATION AND COMMUNICATION TECHNOLOGY [ICT] SPECIALLY ADAPTED FOR ADMINISTRATIVE, COMMERCIAL, FINANCIAL, MANAGERIAL OR SUPERVISORY PURPOSES; SYSTEMS OR METHODS SPECIALLY ADAPTED FOR ADMINISTRATIVE, COMMERCIAL, FINANCIAL, MANAGERIAL OR SUPERVISORY PURPOSES, NOT OTHERWISE PROVIDED FOR
    • G06Q10/00Administration; Management
    • G06Q10/06Resources, workflows, human or project management; Enterprise or organisation planning; Enterprise or organisation modelling
    • G06Q10/063Operations research, analysis or management
    • G06Q10/0631Resource planning, allocation, distributing or scheduling for enterprises or organisations
    • G06Q10/06311Scheduling, planning or task assignment for a person or group
    • G06Q10/063116Schedule adjustment for a person or group
    • GPHYSICS
    • G06COMPUTING; CALCULATING OR COUNTING
    • G06QINFORMATION AND COMMUNICATION TECHNOLOGY [ICT] SPECIALLY ADAPTED FOR ADMINISTRATIVE, COMMERCIAL, FINANCIAL, MANAGERIAL OR SUPERVISORY PURPOSES; SYSTEMS OR METHODS SPECIALLY ADAPTED FOR ADMINISTRATIVE, COMMERCIAL, FINANCIAL, MANAGERIAL OR SUPERVISORY PURPOSES, NOT OTHERWISE PROVIDED FOR
    • G06Q10/00Administration; Management
    • G06Q10/06Resources, workflows, human or project management; Enterprise or organisation planning; Enterprise or organisation modelling
    • G06Q10/063Operations research, analysis or management
    • G06Q10/0635Risk analysis of enterprise or organisation activities

Abstract

Disclosed is a smart electric construction method to prevent an air delay which comprises: a schedule input step of inputting a construction schedule in a manager terminal; a boundary setting step of setting a work region where an electric construction is performed by the input schedule; a work time setting step of setting a work time expected by the construction schedule in the manager terminal; a construction step of performing construction since a worker has a worker terminal in the set work region during the set work time; and a check step of checking whether the worker terminal performing a construction work is positioned in the set work region for the set work time.

Description

스마트 전기공사 시공방법{SMART CONSTRUCTION METHOD OF ELECTRIC WORK}{SMART CONSTRUCTION METHOD OF ELECTRIC WORK}

본 기술은 스마트 전기공사 시공방법에 관한 것이다. This technology relates to a method of constructing a smart electrical work.

특히 스케줄을 설정하고, 스케줄에 따라 작업이 진행되는지 여부를 지속적으로 체크하며, 시공 시 설계내용을 모듈화 하여 공기지연을 방지할 수 있는 스마트 전기공사 시공방법에 관한 것이다.And more particularly, to a smart electric construction method capable of setting a schedule, continuously checking whether a work progresses according to a schedule, and modifying a design content at the time of construction to prevent air delay.

전기는 현대 사회에서는 필수적 요소이다.Electricity is an essential element in modern society.

전기는 세워진 전주에 애자를 통하여 전선을 가설하거나, 지하에 케이블의 매설, 변압기 ·안전기 등의 장치, 외등의 설치되며, 건물에는 인입선을 통하여 분전반 등으로 연결되어 건물로 공급된다. Electricity is supplied to the building by electric wires installed in the electric poles built up by the insulators, underground cables, devices such as transformers and safety devices, and external lights.

전기는 완공된 건물에서는 단순히 스위치를 동작시키거나, 커넥터를 연결하면 각종 장치들에 전기가 공급되어 동작되지만 이와 같이 동작되기 위하여 시공 시 각종 배선박스, 분전박스, 배관, 전선작업 등이 건물을 시공할 때 함께 시공되어 기설계된 상태로 설치되어야 한다. 즉, 건물의 시공은 전기설비의 설치, 시공을 포함하는 개념이 될 수 있다. Electricity is supplied to the various devices by operating the switch or simply connecting the connector in the completed building. However, in order to operate like this, various wiring box, distribution box, piping, When installed, it must be installed and designed. That is, the construction of the building can be a concept including the installation and construction of the electric equipment.

시공의 목적은 주어진 공사를 요구된 기간에 안전하게 품질을 만족하며 완성하는 것이나, 시공분야에서 오랫동안 해결되지 않은 골칫거리인 공기지연은 해결되지 못하고 있다.The purpose of the construction is to satisfy the quality of the given construction safely in the required period, but the air delay which is a problem that has not been solved for a long time in the construction field has not been solved.

공기지연의 사유를 뽑으려면, 기온, 풍속, 강우와 같은 기후요인, 지급자재로 인한 공기지연, 돌발상황의 발생, 보상지연의 발생, 설계 도면이나, 시방서 상 변경, 작업 태만, 지반변경 등 다양한 요건이 있을 것이다. 이러한 공기지연은 시공사에게, 발주자에게도 모두 부담으로 다가오며, 특히나 공기지연에 따라 발생되는 인건비는 큰 손실로 다가오고 있는 실정이다.To select reasons for air delay, there are various factors such as climate factors such as temperature, wind speed, rainfall, air delay due to payment materials, occurrence of unexpected situation, delay of compensation, design drawing, specification change, There will be a requirement. This air delay is burdensome to the contractor and the client, and the labor cost caused by the air delay is coming to a great loss.

불가항력에 의한 공기지연은 어쩔 수 없이 전기공사 시공사가 감안을 하여야 하는 것이지만, 불가항력 이외에 관리, 감독할 수 있는 부분은 지속적으로 관리, 감독을 한다면 공기지연을 단축시킬 수 있을 것이다.The air delay due to force majeure must be taken into consideration by the electric contractor. However, if the management and supervision of parts other than the force majeure force are continuously managed and supervised, air delay can be shortened.

한편, 최근에는 IT기술이 눈부시게 발전되고 있다. IT기술은 정보의 생산과 응용, 관리에 관련한 모든 기술. 초고속 인터넷, 이동 통신, 광통신, 홈 네트워크 등 통신 기술과 컴퓨터, 소프트웨어, 데이터베이스, 멀티미디어 등 정보 기술의 융합에 따른 정보 통신 기술로, 이를 활용한다면 종래의 시공 작업과 다르게 시공을 실시간으로 관리, 감독할 수 있을 것이다.On the other hand, IT technology has been remarkably developed in recent years. IT technology is all technology related to the production, application and management of information. If information and communication technologies are combined with information technologies such as high-speed internet, mobile communication, optical communication, home network, and information technology such as computer, software, database, multimedia, etc., this can be used to manage and supervise construction in real- It will be possible.

이는 인력을 효율적으로 활용함으로써 불가항력 이외의 공기지연을 방지할 수 있을 것이다.This can prevent air delays other than force majeure by using manpower efficiently.

국내 공개특허 출원번호 "10-2013-0165406" "자재 자체변경시공 가능여부 관리시스템(The system which manages a possibilities about a self alterative construction of a resources)"Korean Patent Application No. "10-2013-0165406" "" The system for managing the availability of materials for self-alteration & 국내 공개특허 출원번호 "10-2014-0081176" "케이블 시공 관리 시스템 및 방법(System and method of managing cable construction)"Korean Patent Application No. 10-2014-0081176 "" System and method of managing cable construction"

본 발명은 스케줄에 따라 작업공간, 작업시간을 실시간으로 설정하고, 해당 작업공간, 작업시간에 예정되로 작업이 진행되는지를 확인하여 공기지연을 방지할 수 있는 스마트 전기공사 시공방법을 제공하는데 목적이 있다.The present invention provides a smart electric work construction method that can set a work space and a work time in real time according to a schedule and check whether a work is progressing in the work space or a work time to prevent an air delay .

또한, 본 발명은 시공에 따라 위험한 지역을 기설정하고, 해당 공간에서 작업하는 작업자의 단말기와 설정된 시간을 두고 신호를 송수신하여 작업자의 안전을 도모할 수 있는 스마트 전기공사 시공방법을 제공하는데 목적이 있다.It is another object of the present invention to provide a method of constructing a smart electric work which can set a dangerous area according to construction and transmit a signal to a terminal of an operator working in the space in a predetermined time, have.

또한, 본 발명은 확정된 설계도면에 따라 설치될 장치를 모듈화하고, 직관적으로 인지될 수 있도록 하여 작업이 재빠르게 진행될 수 있도록 하여 공기지연을 방지할 수 있는 스마트 전기공사 시공방법을 제공하는데 목적이 있다.It is another object of the present invention to provide a smart electric work construction method capable of modularizing a device to be installed according to a definite design drawing and intuitively recognizing it, have.

본 발명이 이루고자 하는 기술적 과제는 이상에서 언급한 기술적 과제로 제한되지 않으며 언급되지 않은 또 다른 기술적 과제들은 아래의 기재로부터 본 발명이 속하는 기술분야에서 통상의 지식을 가진 자에게 명확하게 이해될 수 있을 것이다.The technical object of the present invention is not limited to the above-mentioned technical objects and other technical objects which are not mentioned can be clearly understood by those skilled in the art from the following description will be.

본 발명인 스마트 전기공사 시공방법은 공기지연을 방지하기 위한 것을 목적으로 한다.A method of constructing a smart electric work according to the present invention aims at preventing air delay.

본 발명인 스마트 전기공사 시공방법은 관리자단말기에 시공스케줄을 입력하는 스케줄입력단계; 입력된 스케줄에 따라 전기공사가 진행되는 작업영역을 설정하는 바운더리설정단계; 상기 관리자단말기에서 상기 시공스케줄에 따라 예상되는 작업시간을 설정하는 작업시간설정단계; 상기 설정된 작업시간에 상기 설정된 작업영역에서 작업자가 작업자단말기를 소지하고 공사를 진행하는 시공단계; 및 상기 설정된 작업시간에 상기 설정된 작업영역에 공사작업을 수행하는 작업자단말기가 위치하는지를 체크하는 확인단계를 포함한다.A smart electric construction method according to the present invention includes: a schedule input step of inputting a construction schedule to an administrator terminal; A boundary setting step of setting a work area in which electric work is performed according to an inputted schedule; A work time setting step of setting an expected work time in the manager terminal according to the construction schedule; A construction step in which the worker carries on work with the worker terminal in the set work area at the set work time; And a checking step of checking whether a worker terminal performing a construction work is located in the set work area at the set work time.

여기서, 바운더리설정단계에서는 상기 시공스케줄에 따라 복수의 층에 대하여 각각 작업영역을 설정하여 각 층별로 복수개의 작업영역을 설정하면서, 사고가 발생될 작업영역을 설정하는 위험바운더리설정단계를 포함하여, 상기 작업영역과 상기 위험영역을 각각의 층별로 각각 설정하고, 상기 확인단계에서는, 상기 관리자단말기는 상기 작업자단말기의 고도송신부와 GPS부가 송신하는 각각의 고도에 대한 정보와 위치의 정보를 수신하여 상기 작업자단말기의 위치하는 고도 및 위치를 기반으로 상기 작업자단말기의 위치를 고도에 따라 작업영역에 위치하는지 아는지를 확인하며, 상기 작업자단말기의 활성화부가 송신하는 신호를 상기 관리자단말기가 수신하여 상기 작업자단말기를 소지한 작업자가 작업의 시작여부 및 작업의 수행여부를 확인하되, 상기 작업자단말기가 상기 사고가 발생될 작업영역에 인접한 위치에 위치되면 상기 작업자단말기의 알림부를 통하여 위험에 대한 경고 신호를 상기 관리자단말기는 송신하며, 상기 관리자단말기가 상기 설정된 작업시간에 설정된 간격을 두고 촬영신호를 상기 작업자단말기로 송신하고, 상기 촬영신호를 수신한 상기 작업자단말기가 촬영을 수행하여 설정된 간격을 가지고 생성된 복수의 촬영데이터를 상기 관리자단말기로 송부하여 전기공사 작업이 진행되는지를 확인하되 상기 관리자단말기는 상기 수신된 촬영데이터가 동일한 GPS좌표를 가지는 경우 먼저 수신된 촬영데이터에 설정된 포인트를 지정하고, 나중에 수신된 촬영데이터에 상기 먼저 수신된 촬영데이터와 동일한 설정된 포인트를 지정하고 비교, 대조하여 설정된 포인트의 개수가 증가되는지를 감지하여 작업진행 정도를 판단하는 것을 특징으로 한다.Here, the boundary setting step may include a risk boundary setting step of setting a work area for a plurality of layers according to the construction schedule, setting a plurality of work areas for each layer, and setting a work area where an accident will occur, Wherein the manager terminal is configured to receive the information on the altitude and the position information transmitted by the altitude transmitter and the GPS unit of the worker terminal in the ascertaining step, The operator terminal confirms whether the position of the worker terminal is located in the work area according to the altitude based on the altitude and the position of the worker terminal and receives a signal transmitted by the activator of the worker terminal, The worker has to check whether the work is started or not If the worker terminal is located at a position adjacent to the work area where the accident occurs, the manager terminal transmits a warning signal about the danger through the notification unit of the worker terminal. When the manager terminal detects an interval The operator terminal that has received the photographing signal performs a photographing operation and sends a plurality of pieces of photographing data generated at predetermined intervals to the manager terminal, When the received photographic data has the same GPS coordinates, the administrator terminal designates a point set in the photographed data received first, designates the same set point as the previously received photographed data with respect to the photographed data received later, , The number of points set in contrast Detect that the to is characterized in that to determine the degree of progress.

여기서, 작업을 수행하는 작업자가 작업자단말기를 이용하여 변경된 스케줄에 따라 변경신호를 상기 관리자단말기로 송신하면 상기 관리자단말기는 상기 변경신호를 수신하여 상기 시공스케줄을 변경하고, 상기 작업영역을 수정하여 바운더리를 재설정하고, 상기 작업시간을 재설정하는 수정단계를 포함하는 것을 특징으로 한다.Here, if an operator performing an operation transmits a change signal to the administrator terminal according to a changed schedule using the worker terminal, the administrator terminal receives the change signal to change the construction schedule, corrects the work area, And resetting the operation time.

여기서, 확인단계에서는, 상기 작업영역은 복수로 지정되어 복수개의 바운더리라 형성될 수 있으며, 상기 복수의 바운더리 각각에는 상기 스케줄에 따라 상기 작업영역에 위치할 상기 작업자단말기가 개수가 기설정되어 있어서 상기 각각의 바운더리에 기설정된 개수의 작업자단말기가 위치하는지를 확인하는 것을 특징으로 한다.Here, in the confirming step, the work area may be designated as a plurality of boundaries, and each of the plurality of boundaries includes a number of the worker terminals to be located in the work area according to the schedule, And confirms whether a predetermined number of worker terminals are located at respective boundaries.

여기서, 상기 시공단계에서는, 시공 전 설계도면의 진행여부를 확정하는 설계확정단계; 상기 설계도면에 배치되되, 외측에는 일방향으로 돌출되되 설정된 제1이격간격을 가지고 원주형태에 따라 배치된 제1가압핑거가 형성되되 적어도 동일하지 않은 상이한 색을 가지는 제1가압브라켓을 복수개 구비한 배선박스를 복수개 준비하는 배선박스준비단계; 상기 배선박스에 연결되되 상기 연결되는 위치에 배치된 제1가압브라켓의 색과 동일한 색을 갖도록 복수개 형성되어 연결위치가 용이하게 파악되는 배관을 준비하고, 상기 상이한 색을 가지는 배관의 일측에는 연결되는 상기 제1가압브라켓과 동일한 색을 가지되, 상기 제1이격간격과 어긋난 간격인 제2이격간격을 가지는 제2가압핑거가 형성되어 상기 제1가압핑거에 엇갈리게 삽입되는 경우 상호 가압되어 고정되는 제2가압브라켓을 상기 배관에 삽입하는 배관준비단계; 및 상기 공사가 진행되는 위치로 상기 배선박스 및 상기 배관을 이동시켜 상기 설계도면에 따라 상기 배선박스를 배치하고, 제1가압브라켓에 상기 제2가압브라켓을 연결하여 고정하는 설치단계를 포함한다.Here, in the construction step, a design confirmation step of determining whether or not the design drawing is proceeded before construction; A plurality of first pressure brackets arranged in the design drawing and protruding in one direction at a first spacing interval and having first pressure fingers arranged in a circumferential shape with a predetermined spacing, A wiring box preparation step of preparing a plurality of boxes; A plurality of pipes connected to the wiring box and having the same color as the colors of the first pressure brackets disposed at the connected positions are prepared to easily identify the connection positions, and the pipes are connected to one side of the pipes having different colors A second pressing finger having the same color as that of the first pressing bracket and having a second spacing interval which is a gap deviated from the first spacing distance is formed and when the first pressing finger is staggeredly inserted into the first pressing finger, A piping preparing step of inserting the 2-pressure bracket into the piping; And a mounting step of moving the wiring box and the pipe to a position where the construction is progressed, disposing the wiring box according to the design drawing, and fixing and connecting the second pressure bracket to the first pressure bracket.

여기서, 배선박스준비단계에서 상기 배선박스는 상기 배선박스의 외측에 형성된 일측이 개방되며 라운드하게 형성된 라운드홈을 구비하며 외측에는 나사산이 형성된 연결체; 상기 라운드홈에 배치되는 연결볼과 상기 연결볼의 일측에서 연장되어 단부에 연결공이 형성된 고정체; 및 상기 연결체를 둘러싸는 형태로 상기 연결체의 외측의 나사산에 결합되며 회전에 따라 연결체를 가압하여 상기 고정체와 상기 연결체를 견고하게 고정시키는 회전매개체를 포함하며 상기 연결공에는 연결핀이 삽입되어 고정될 수 있는 것을 특징으로 한다.Here, in the wiring box preparation step, the wiring box may have a round groove formed at an outer side of the wiring box and open at one side thereof, and a threaded connection formed at the outer side thereof; A connection ball disposed in the round groove and a fixing member extending from one side of the connection ball and having a connection hole formed at an end thereof; And a rotating medium coupled to a thread on the outer side of the connecting body in a form surrounding the connecting body and pressing the connecting body according to the rotation to firmly fix the fixing body and the connecting body, Can be inserted and fixed.

본 발명은 스케줄에 따라 작업공간, 작업시간을 실시간으로 설정하고, 해당 작업공간, 작업시간에 예정되로 작업이 진행되는지를 확인하여 공기지연을 할 수 있다.According to the present invention, the work space and the work time can be set in real time according to the schedule, and the air delay can be performed by checking whether the work is progressing in the work space or the work time.

또한, 본 발명은 시공에 따라 위험한 지역을 기설정하고, 해당 공간에서 작업하는 작업자의 단말기와 설정된 시간을 두고 신호를 송수신하여 작업자의 안전을 도모할 수 있다.In addition, according to the present invention, a dangerous area can be preset according to construction, and a safety of the operator can be achieved by transmitting / receiving a signal to a terminal of an operator working in the space with a predetermined time.

또한, 본 발명은 확정된 설계도면에 따라 설치될 장치를 모듈화하고, 직관적으로 인지될 수 있도록 하여 작업이 재빠르게 진행될 수 있도록 하여 공기지연을 방지할 수 있다.In addition, the present invention modularizes a device to be installed according to a determined design drawing, and intuitively recognizes the device so that a work can be rapidly performed, thereby preventing air delay.

도 1은 본 발명인 스마트 전기공사 시공방법을 구현하는 각 구성을 도시한 것이다.
도 2a는 바운더리설정단계에 따라 설정된 작업영역에 작업자단말기가 각각 위치하는 것을 도시한 것이며, 도 2b는 위험바운더리설정단계에 따라 설정된 위험영역에 인접하여 작업자단말기가 위치한 것을 도시한 것이며, 도 2c는 설정된 작업영역에 설정된 수의 작업자단말기가 위치되지 않은 상태를 도시한 것이다.
도 3a는 본 발명인 스마트 전기공사 시공방법의 각 단계를 블럭도로 도시한 것이며, 도 3b는 시공단계를 구성하는 각 단계를 블럭도로 도시한 것이다.
도 4에서 (a)는 확인단계에서 제1시간에 관리자단말기가 수신한 촬영데이터에 포인트를 설정한 것을 도시한 것이고 (b)는 확인단계에서 제2시간에 관리자단말기가 수신한 촬영데이터에 포인트를 설정한 것을 도시한 것이다.
도 5a는 본 발명의 스마트 전기공사 시공방법에서 활용되는 배선박스를 도시한 것이며, 도 5b는 배선박스의 제1가압브라켓과 제2가압브라켓을 확대 도시한 것이다.
도 6a는 본 발명의 시공단계에서 색으로 구분된 배선박스, 제1가압브라켓, 제2가압브라켓, 배관을 도시한 것이고, 도 6b는 일예시에 따라 본 발명의 시공단계에서 확정된 설계도면에 의하여 배선박스를 배치하고 연결하고, 배관과 연결한 것을 도시한 것이다.
1 is a perspective view illustrating a construction of a smart electric construction method according to the present invention.
FIG. 2A shows that the worker terminals are located in the work area set according to the boundary setting step, FIG. 2B shows that the worker terminal is located adjacent to the danger area set according to the dangerous boundary setting step, FIG. And the number of worker terminals set in the set work area is not positioned.
FIG. 3A is a block diagram showing each step of the method for constructing a smart electric work according to the present invention, and FIG. 3B is a block diagram showing each step constituting the construction step.
4 (a) shows that the point is set in the shooting data received by the administrator terminal at the first time in the checking step, and (b) shows that the shooting data received by the manager terminal at the second time As shown in Fig.
FIG. 5A shows a wiring box used in the smart electric construction method of the present invention, and FIG. 5B is an enlarged view of the first pressure bracket and the second pressure bracket of the wiring box.
FIG. 6A illustrates a wiring box, a first pressurizing bracket, a second pressurizing bracket, and a pipe separated by color in the construction step of the present invention. FIG. 6B is a cross- The wiring box is arranged and connected, and connected to the piping.

이하, 본 발명의 일실시예를 예시적인 도면을 통해 상세하게 설명한다. 그러나 이는 본 발명의 범위를 한정하려고 의도된 것은 아니다. Hereinafter, an embodiment of the present invention will be described in detail with reference to exemplary drawings. However, this is not intended to limit the scope of the invention.

각 도면의 구성요소들에 참조부호를 부가함에 있어서, 동일한 구성요소들에 대해서는 비록 다른 도면상에 표시되더라도 가능한 한 동일한 부호를 가지도록 하고 있음에 유의해야 한다. 또한, 본 발명을 설명함에 있어, 관련된 공지 구성 또는 기능에 대한 구체적인 설명이 본 발명의 요지를 흐릴 수 있다고 판단되는 경우에는 그 상세한 설명은 생략한다.It should be noted that, in adding reference numerals to the constituent elements of the drawings, the same constituent elements are denoted by the same reference symbols as possible even if they are shown in different drawings. In the following description of the present invention, a detailed description of known functions and configurations incorporated herein will be omitted when it may make the subject matter of the present invention rather unclear.

또한, 도면에 도시된 구성요소의 크기나 형상 등은 설명의 명료성과 편의상 과장되게 도시될 수 있다. 또한, 본 발명의 구성 및 작용을 고려하여 특별히 정의된 용어들은 본 발명의 실시예를 설명하기 위한 것일 뿐이고, 본 발명의 범위를 한정하는 것이 아니다.In addition, the size and shape of the components shown in the drawings may be exaggerated for clarity and convenience of explanation. In addition, terms specifically defined in consideration of the constitution and operation of the present invention are only for explaining the embodiments of the present invention, and do not limit the scope of the present invention.

명세서 전체에서, 어떤 부분이 어떤 구성요소를 "포함"한다고 할 때, 이는 특별히 반대되는 기재가 없는 한 다른 구성요소를 제외하는 것이 아니라 다른 구성요소를 더 포함할 수 있는 것을 의미한다. 또한, 명세서에 기재된 "…부", "…기", "모듈", "장치" 등의 용어는 적어도 하나의 기능이나 동작을 처리하는 단위를 의미하며, 이는 하드웨어 및/또는 소프트웨어의 결합으로 구현될 수 있다.Throughout the specification, when an element is referred to as "comprising ", it means that it can include other elements as well, without excluding other elements unless specifically stated otherwise. It should be noted that the terms such as " part, "" module, " .

도 1은 본 발명인 스마트 전기공사 시공방법을 구현하는 각 구성을 도시한 것이다.1 is a perspective view illustrating a construction of a smart electric construction method according to the present invention.

도 3a는 본 발명인 스마트 전기공사 시공방법의 각 단계를 블럭도로 도시한 것이며, 도 3b는 시공단계를 구성하는 각 단계를 블럭도로 도시한 것이다.FIG. 3A is a block diagram showing each step of the method for constructing a smart electric work according to the present invention, and FIG. 3B is a block diagram showing each step constituting the construction step.

본 발명인 스마트 전기공사 시공방법은 관리자단말기(100), 작업자단말기(200)의 신호의 송수신을 통하여 구현될 수 있다. 작업자단말기(200)는 웨어러블 디바이스 등 작업자의 동작을 방해하지 않으며, 관리자단말기(100)와 신호를 송수신할 수 있는 디바이스를 모두 포함한다. The smart electric construction method according to the present invention can be implemented through transmission and reception of signals between the manager terminal 100 and the worker terminal 200. The worker terminal 200 includes all the devices capable of transmitting and receiving signals with the manager terminal 100 without interfering with the operation of the worker such as a wearable device.

관리자단말기(100)는 송신부(190), 수신부(195), 바운더리설정부(180), 작업시간설정부(170), 스케줄관리부(120), 기후데이터(130)부, 연산부(140), 주의신호생성부(150), 저장부(110)를 포함한다. The administrator terminal 100 includes a transmitting unit 190, a receiving unit 195, a boundary setting unit 180, a working time setting unit 170, a schedule managing unit 120, a climate data 130, A signal generation unit 150, and a storage unit 110.

작업자단말기(200)는 송신부(290), 수신부(295), 촬영부(230), GPS부(240), 고도송신부(260), 활성화부(210), 알림부(230), 변경상황보고부(250)를 포함한다.The operator terminal 200 includes a transmitter 290, a receiver 295, a photographing unit 230, a GPS unit 240, an altitude transmitter 260, an activating unit 210, a notification unit 230, (250).

여기서, 관리자단말기(100)와 작업자단말기(200)의 송신부(190, 290), 수신부(195, 295)는 각종 신호를 송신하고, 수신하는 역할을 한다.Here, the transmitting units 190 and 290 and the receiving units 195 and 295 of the manager terminal 100 and the worker terminal 200 transmit and receive various signals.

관리자단말기(100)와 작업자단말기(200)의 신호 송수신을 통하여 본 발명인 스마트 전기공사 시공방법은 구성된다.A method of constructing a smart electric work according to the present invention is configured through signal transmission / reception between the manager terminal 100 and the worker terminal 200.

스케줄입력단계(S1)는 관리자단말기(100)에 시공스케줄을 입력하는 단계이다.The schedule input step S1 is a step of inputting a construction schedule to the administrator terminal 100. [

관리자단말기(100)의 스케줄관리부(120)에는 시공에 대한 스케줄이 입력될 수 있다. 예를 들어 A월B일C시 철근배근공사, 작업완료예정시간 A월D일E시와 같이 설정될 수 있다. 예를 들면 전기공사의 시공은 철근배근이 완료된 후 배선박스(300), 분전반 등을 설치하고, 배관(400)을 설치한 후 컨트리트를 타설하는 순으로 진행될 수 있는데 이처럼 시공의 스케줄에 따라 전기공사 시공은 조율됨으로 스케줄관리부(120)에 입력된 스케줄에 따라 전기설비의 시공 일정을 설정할 수 있다.A schedule for construction can be input to the schedule management unit 120 of the administrator terminal 100. [ For example, it can be set as A, B, C, C, steel reinforcement work, scheduled work time A, D, E, and so on. For example, in the construction of the electric work, the wiring box 300, the distribution panel, and the like may be installed after the reinforcement is completed, the piping 400 may be installed, and then the concrete may be laid. In this way, The work schedule of the electric equipment can be set according to the schedule input to the schedule management unit 120 by coordinating the construction work.

여기서, 관리자단말기(100)의 기후데이터(130)를 통하여 관리자단말기(100)는 시공의 스케줄의 진행여부 등에 대한 가상의 작업진행여부데이터를 설정한다. 기후데이터(130)는 기온, 풍속, 강우에 따라 시공의 진행 정도에 대한 데이터들이 저장되어 있다. 예를 들어 기온X, 풍속Y, 강우Z인 경우 기온이 너무 높아서 AM10:00 ~ 16:00까지는 예정 작업수행률 20%라는 데이터들이 저장되어 있다. 또 다른 실시예로는 기온A, 풍속B, 강우C인 경우 풍속때문에 작업수행불가로 작업 수행률이 0%라는 데이터가 저장되어 있다. 이를 통하여 관리자단말기(100)는 시공이 예정된 당일의 기온, 풍속, 강우를 입력받아 스케줄관리부(120)에서 예정된 시공진행여부를 예측하여, 작업자의 작업시간 및 바운더리를 재설정할 수 있다.Here, the manager terminal 100 sets virtual work progress data on whether or not the construction schedule is progressed through the climatic data 130 of the administrator terminal 100. Climate data 130 stores data on the progress of construction according to temperature, wind speed, and rainfall. For example, in case of temperature X, wind speed Y, rainfall Z, temperature is too high, and data of scheduled work execution rate of 20% is stored from 10:00 to 16:00. In another embodiment, when the temperature is A, the wind speed is B, and the rainfall is C, data is stored that the work execution rate is 0% because the work can not be performed due to the wind speed. The manager terminal 100 receives the temperature, wind speed, and rainfall of the day on which the construction is scheduled, and predicts whether the construction progresses in the schedule management unit 120, thereby resetting the work time and the boundary of the worker.

또한, 작업자단말기(200)의 변경상황보고부(250)가 송신하는 변경상황신호를 통하여 사용자의 스케줄관리부(120)는 스케줄이 수정되며 입력될 수 있다. 일예시적으로 시공자가 설계 내용을 변경한 경우 작업자는 작업자단말기(200)의 변경상황보고부(250)를 통하여 변경상황신호를 관리자단말기(100)로 송신하고, 관리자단말기(100)는 해당 신호를 수신한 후 스케줄관리부(120)를 통하여 시공 스케줄을 변경할 수 있다.Also, the schedule management unit 120 of the user can modify the schedule through the change status signal transmitted from the change status reporting unit 250 of the worker terminal 200. The worker transmits a change status signal to the manager terminal 100 through the change status reporting unit 250 of the worker terminal 200 and the manager terminal 100 transmits the change signal to the corresponding signal The schedule management unit 120 can change the construction schedule.

도 2a는 바운더리설정단계에 따라 설정된 작업영역에 작업자단말기가 각각 위치하는 것을 도시한 것이며, 도 2b는 위험바운더리설정단계에 따라 설정된 위험영역에 인접하여 작업자단말기가 위치한 것을 도시한 것이며, 도 2c는 설정된 작업영역에 설정된 수의 작업자단말기가 위치되지 않은 상태를 도시한 것이다.FIG. 2A shows that the worker terminals are located in the work area set according to the boundary setting step, FIG. 2B shows that the worker terminal is located adjacent to the danger area set according to the dangerous boundary setting step, FIG. And the number of worker terminals set in the set work area is not positioned.

바운더리설정단계(S2)는 작업영역을 설정하는 단계이다.The boundary setting step S2 is a step of setting a work area.

관리자단말기(100)는 입력된 시공 스케줄을 기초로 하여 작업자가 작업할 바운더리를 설정하는 단계이다. 예를 들어 건물의 2층의 A구역과 4층의 B구역에 각각 배선을 위한 배관(400)공사 및 배선공사가 예정되는 경우 관리자단말기(100)는 시공이 예정된 2층의 A영역에 바운더리를 설정하여 작업자가 작업을 수행할 영역을 설정한다. 또한, 4층의 B구역 또한, 바운더리를 설정하여 작업자가 작업을 수행할 영역을 설정한다.The administrator terminal 100 sets the boundary to be worked by the operator based on the inputted construction schedule. For example, when the piping (400) for wiring and the wiring work are scheduled for the A and B sections of the second floor and the fourth floor of the building, the manager terminal (100) And sets the area where the operator performs the work. In addition, the B zone of the fourth floor also sets a boundary to set an area where an operator performs an operation.

작업자단말기(200)는 GPS부(240), 고도송신부(260), 활성화부(210)를 포함한다. The worker terminal 200 includes a GPS unit 240, an altitude transmission unit 260, and an activation unit 210.

작업자단말기(200)의 GPS부(240)는 작업자단말기(200)가 위치한 좌표에 대한 신호를 송신하여 작업자단말기(200)가 위치하는 위치를 파악할 수 있도록 한다.The GPS unit 240 of the worker terminal 200 transmits a signal for the coordinates at which the worker terminal 200 is located so that the position of the worker terminal 200 can be grasped.

또한, 작업자단말기(200)의 고도송신부(260)는 작업자단말기(200)의 고도에 대한 정보를 관리자단말기(100)로 송신한다. 예를 들어 제1작업자단말기(200)가 지상으로부터 2층의 건물의 높이에 위치하고, 제2작업자단말기(200)가 지상으로부터 4층의 건물의 높이에 위치하면 고도정보신호를 각각 관리자단말기(100)로 송신한다. 따라서 관리자단말기(100)는 제1작업자단말기(200)를 소지한 작업자가 시공되는 건물의 2층에 위치하고, 제2작업자단말기(200)를 소지한 작업자가 시공되는 건물의 4층에 위치한 것으로 파악할 수 있다. In addition, the altitude transmission unit 260 of the worker terminal 200 transmits information about the altitude of the worker terminal 200 to the administrator terminal 100. For example, when the first worker terminal 200 is located at the height of the two-story building from above and the second worker terminal 200 is located at the height of the four-story building from above, ). Therefore, the manager terminal 100 is located on the second floor of the building where the worker carrying the first worker terminal 200 is installed, and the worker having the second worker terminal 200 is located on the fourth floor of the building .

작업자단말기(200)의 활성화부(210)는 작업여부에 대한 신호를 관리자단말기(100)로 송신하여 관리자단말기(100)가 작업자가 작업을 수행하는지 아닌지를 판단할 수 있다.The activation unit 210 of the worker terminal 200 may transmit a signal indicating whether the worker has performed an operation to the administrator terminal 100 so that the administrator terminal 100 can determine whether the worker performs an operation.

예를 들어 작업자단말기(200)의 활성화부(210)에서 제1작업신호를 관리자단말기(100)로 송신하면 관리자단말기(100)는 작업자단말기(200)를 소지한 작업자가 작업을 시작하는 것으로 판단하고, 제2작업신호를 송신하면 작업자단말기(200)를 소지한 작업자가 휴식을 취하는 것으로 판단하며, 제3작업신호를 송신하면 작업자단말기(200)를 소지한 작업자가 작업을 종료하였음으로 판단할 수 있다.For example, when the activating unit 210 of the worker terminal 200 transmits the first job signal to the manager terminal 100, the manager terminal 100 judges that the worker having the worker terminal 200 starts work If the second work signal is transmitted, it is determined that the worker having the worker terminal 200 rests. If the third worker signal is transmitted, the worker having the worker terminal 200 determines that the worker has finished the work .

바운더리설정단계(S2)는 위험바운더리설정단계(S2)를 포함할 수 있다.The boundary setting step S2 may include a dangerous boundary setting step S2.

위험바운더리설정단계(S2)는 사고가 발생될 작업영역을 설정하는 것이다. 도 2c를 통하여 이를 설명하면 10층에 설치된 C구역은 비계가 일부 허술하게 설치되어 추락의 위험이 존재한다. 이 경우, 작업자는 C구역의 인접한 F구역에서 전기설비 시공작업을 수행할 예정이다. 여기서, 관리자단말기(100)의 바운더리설정부(180)는 10층의 C구역을 사고발생지역으로 바운더리하여 설정할 수 있다. 작업자의 작업자단말기(200)는 고도송신부(260)를 통하여 고도정보신호를 관리자단말기(100)로 송신한다. 또한, 작업자단말기(200)의 GPS부(240)에서 송신하는 좌표정보가 C구역에서 인접하여 위치되면 관리자단말기(100)의 주의신호생성부(150)는 주의신호를 작업자단말기(200)로 송신한다. 그러면 작업자단말기(200)의 알림부(230)는 작업자단말기(200)를 소지한 작업자에게 작업 시 주의할 것을 알려준다.The dangerous boundary setting step S2 is to set a work area where an accident will occur. Referring to FIG. 2C, there is a risk of falling due to some poorly installed scaffolding in the C zone installed on the 10th floor. In this case, the operator will perform electrical installation work in the adjacent F zone of zone C. Here, the boundary setting unit 180 of the administrator terminal 100 may set the C zone of the 10th floor as an accident occurrence area. The operator's worker terminal 200 transmits the altitude information signal to the manager terminal 100 through the altitude transmitter 260. [ When the coordinate information transmitted from the GPS unit 240 of the worker terminal 200 is located adjacent to the C zone, the attention signal generator 150 of the manager terminal 100 transmits a caution signal to the worker terminal 200 do. Then, the notification unit 230 of the worker terminal 200 informs the worker holding the worker terminal 200 to pay attention to the work.

여기서, 알림부(230)는 음성, 진동, 시각화 등을 통하여 C구역에 인접하여 작업을 수행하는 경우 작업 시 주의할 것을 알려준다.Here, the notification unit 230 informs the user of caution when performing an operation adjacent to the C zone through voice, vibration, visualization, or the like.

위험바운더리설정단계(S2)는 수정위험바운더리설정단계(S2)를 포함한다.The dangerous boundary setting step S2 includes a correction risk boundary setting step S2.

수정위험바운더리설정단계(S2)는 실시간으로 작업자의 작업자단말기(200)를 통하여 보고되는 신호를 통하여 관리자단말기(100)의 바운더리설정부(180)가 위험 구역을 실시간으로 설정할 수 있다. 이 경우 작업자단말기(200)는 촬영부(230)를 통하여 촬영하여 생성한 촬영데이터를 변경상황보고부(250)를 통하여 관리자단말기(100)로 송신한다. 관리자단말기(100)는 전술한 것과 같이 작업자단말기(200)의 기확인된 위치를 기반으로 위험 구역을 재설정한다.The modified risk boundary setting step S2 can set the dangerous area in real time by the boundary setting unit 180 of the administrator terminal 100 through a signal reported through the operator's worker terminal 200 in real time. In this case, the worker terminal 200 transmits the photographed data photographed and generated through the photographing unit 230 to the manager terminal 100 through the change status reporting unit 250. The administrator terminal 100 resets the danger zone based on the previously identified position of the worker terminal 200 as described above.

위험 구역을 재설정한 경우 관리자단말기(100)는 전술한 것과 동일하게 작업자가 소지한 작업자단말기(200)의 알림부(230)를 동작 시킬 수 있다.When the dangerous area is reset, the administrator terminal 100 can operate the notification unit 230 of the worker terminal 200 owned by the worker in the same manner as described above.

이 경우 작업자는 작업자단말기(200)의 촬영부(230)를 이용하여 해당 위험 구역의 위험요소가 더 이상 존재하지 않음을 변경상황보고부(250)를 통하여 관리자단말기(100)로 알릴 수 있으며 관리자단말기(100)의 바운더리설정부(180)는 해당 구역을 위험 구역에서 해제할 수 있다. In this case, the operator can notify the manager terminal 100 of the dangerous element of the dangerous zone no longer present using the photographing unit 230 of the worker terminal 200 through the change status reporting unit 250, The boundary setting unit 180 of the terminal 100 may release the zone from the danger zone.

작업시간설정단계(S3)는 관리자단말기(100)에서 시공스케줄에 따라 예상되는 작업시간을 설정하는 단계이다. 예를 들면 작업자의 작업시간은 오전 9시에서 오후 4시로 설정될 수 있다.The work time setting step S3 is a step of setting the expected work time according to the construction schedule in the administrator terminal 100. [ For example, the worker's work time can be set from 9 am to 4 pm.

작업시간설정단계(S3)는 전술한 것과 같이 스케줄관리부(120)에 의하여 작업시간이 재설정될 수 있다. 이에 따라 작업자의 작업시간을 효율적으로 관리할 수 있다.In the work time setting step S3, the work time can be reset by the schedule management unit 120 as described above. Accordingly, the work time of the operator can be efficiently managed.

도 5a는 본 발명의 스마트 전기공사 시공방법에서 활용되는 배선박스를 도시한 것이며, 도 5b는 배선박스의 제1가압브라켓과 제2가압브라켓을 확대 도시한 것이다.FIG. 5A shows a wiring box used in the smart electric construction method of the present invention, and FIG. 5B is an enlarged view of the first pressure bracket and the second pressure bracket of the wiring box.

도 6a는 본 발명의 시공단계에서 색으로 구분된 배선박스, 제1가압브라켓, 제2가압브라켓, 배관을 도시한 것이고, 도 6b는 일예시에 따라 본 발명의 시공단계에서 확정된 설계도면에 의하여 배선박스를 배치하고 연결하고, 배관과 연결한 것을 도시한 것이다.FIG. 6A illustrates a wiring box, a first pressurizing bracket, a second pressurizing bracket, and a pipe separated by color in the construction step of the present invention. FIG. 6B is a cross- The wiring box is arranged and connected, and connected to the piping.

시공단계(S4)는 설정된 작업시간에 바운더리를 통하여 설정된 작업영역에서 작업자가 작업자단말기(200)를 소지하여 공사를 진행하는 단계이다.In the construction step S4, the worker carries the work by carrying the worker terminal 200 in the work area set through the boundary at the set work time.

여기서, 시공단계(S4)는 모듈화를 통하여 작업시간이 단축될 수 있다.Here, in the construction step S4, the working time can be shortened through the modularization.

시공단계(S4)는 설계확정단계, 배선박스준비단계(A2), 배관준비단계(A3), 설치단계(A4)를 포함한다. 설계확정단계는 관리자단말기(100)의 설계확정부(160)를 통하여 시공 전 설계될 설계도면(A1)을 확정하는 단계이다. 설계도면(A1)이 확정되지 않은 채로 모듈화작업을 수행하면 설계도면(A1)이 변경된 경우 재모듈화작업을 하여야 함으로, 공기지연이 발생될 수 있음으로 모듈화되기 전 시공이 예정된 설계도면(A1)을 확정 후 동작되도록 한다.The construction step S4 includes a design confirmation step, a wiring box preparation step A2, a piping preparation step A3, and an installation step A4. The design determination step is a step of confirming the design drawing A1 to be designed before the construction through the design decision unit 160 of the administrator terminal 100. [ If a modularization operation is carried out without the design drawing A1 being confirmed, a re-modularization operation must be performed when the design drawing A1 is changed. As a result, air delay may occur. Make sure to operate after confirmation.

확정된 설계도면(A1)을 바탕으로 배선박스준비단계(A2), 배관준비단계(A3)를 포함한다. 배선박스준비단계(A2)에서 배선박스(300)는 서로 다른 색을 가지는 제1가압핑거를 포함하는 제1가압브라켓(310)을 포함한다. 예를 들어 배선박스(300)의 둘레면에 제1가압브라켓(310)이 형성되어 제1가압브라켓(310)이 4개가 형성된 배선박스(300)를 포함할 수 있다. 여기서, 제1가압브라켓(310)은 각각 상이한 색을 가지고 있다. 따라서 제1가압핑거도 상이한 색을 가지며 형성된다. 도 6a를 통하여 이를 살펴보면 4개의 제1가압브라켓(310)은 각각 시계방향으로 빨간색, 노란색, 파란색, 보라색으로 형성될 수 있다. 따라서 제1가압핑거도 빨간색, 노란색, 파란색, 보라색으로 형성된다. 제1가압핑거는 배선박스(300)의 외측에서 일방향으로 돌출되어 형성되며, 제1이격간격을 가지고 원주형태에 따라 배치된다. 또한, 배선박스(300) 그 자체도 설정된 색을 가질 수 있다. 일예시적으로 어느 하나의 배선박스(300)는 검정색으로, 다른 배선박스(300)는 흰색으로 설정될 수 있다.(A2) and a piping preparation step (A3) based on the determined design drawing (A1). In the wiring box preparing step A2, the wiring box 300 includes a first pressing bracket 310 including first pressing fingers having different colors. For example, a wiring box 300 in which a first pressing bracket 310 is formed on the circumferential surface of the wiring box 300 and four first pressing brackets 310 are formed. Here, the first pressure brackets 310 have different colors. Therefore, the first pressing finger is also formed with a different color. Referring to FIG. 6A, the four first pressing brackets 310 may be formed in a clockwise direction of red, yellow, blue, and purple. Accordingly, the first pressing finger is also formed in red, yellow, blue, and purple. The first pressure fingers protrude in one direction from the outside of the wiring box 300 and are arranged in a circumferential shape with a first spacing distance. Also, the wiring box 300 itself can have a predetermined color. For example, one of the wiring boxes 300 may be set to black, and the other wiring box 300 may be set to white.

배관(400)은 복수개가 구비될 수 있다. 배관(400)은 설계도면(A1)에 따라서 절곡된 형상을 가지는 것, 직선을 가지는 것 등 다양한 배관(400)이 구비될 수 있다. 여기서, 배관(400)은 제1가압브라켓(310)에 연결되는 각각의 배관(400)으로 구분되도록 설정된 색을 가지며 형성될 수 있다. 즉, 일예시적으로 전술한 빨간색의 제1가압브라켓(310)과 연결되는 배관(400)은 빨간색으로, 노란색의 제1가압브라켓(310)에 연결되는 배관(400)은 노란색으로 채색될 수 있다. 이러한 배관(400)은 그 자체로 절곡되지 않고, T관 L관 소켓 등을 통하여 연결되어 전체적인 형태가 설계도면(A1)의 배관(400)에 따른 형태로 변경될 수 있다.A plurality of piping 400 may be provided. The pipe 400 may have various shapes such as a shape bent in accordance with the design drawing A1, a pipe having a straight line, and the like. Here, the pipe 400 may have a color set to be divided into the respective pipes 400 connected to the first pressure bracket 310. That is, for example, the pipe 400 connected to the red first pressurizing bracket 310 is red, and the pipe 400 connected to the yellow first pressurizing bracket 310 can be colored yellow have. The pipe 400 is not bent by itself, but may be connected to the pipe through a pipe such as a T pipe, so that the overall shape of the pipe 400 can be changed according to the pipe 400 of the design drawing A1.

배관(400)의 단부에는 제2가압브라켓(320)이 설치된다. 제2가압브라켓(320)은 연결되는 제1가압브라켓(310)과 동일한 색으로 형성된다. 즉, 빨간색의 제1가압브라켓(310)에는 빨간색으로 채색된 배관(400)에 빨간색의 제2가압브라켓(320)이 설치된다. 제2가압브라켓(320)은 제2이격간격을 가지고 원주방향으로 배치된 제2가압핑거를 포함한다. 제2이격간격은 제1이격간격과 어긋나도록 형성되어 있다. 따라서 제2가압핑거는 제1가압핑거의 제1이격간격으로 위치되고, 제1가압핑거는 제2가압핑거의 제2이격간격에 위치된다.A second pressurizing bracket 320 is installed at an end of the pipe 400. The second pressurizing bracket 320 is formed in the same color as the first pressurizing bracket 310 connected thereto. That is, the red first pressure bracket 310 is provided with a red second pressure bracket 320 on the piping 400 colored red. The second pressurizing bracket 320 includes a second press finger arranged circumferentially with a second spacing distance. The second spacing distance is formed to be offset from the first spacing distance. Thus, the second press finger is positioned at a first spacing distance of the first press finger, and the first press finger is positioned at the second spacing distance of the second press finger.

이를 통하여 제1가압핑거와 제2가압핑거가 결합되는 경우 각각 상호 내측으로 이동되며 점진적으로 가압된다. 따라서 단순히 제1가압핑거와 제2가압핑거를 서로 반대되는 방향으로 가압하면 제1가압핑거와 제2가압핑거는 어긋난 상태로 상호 가압하여 연결될 수 있다. 이를 통하여 간단하고 직관적인 방법으로 배선박스(300) 사이를 배관(400)으로 연결할 수 있다.When the first pressing finger and the second pressing finger are coupled to each other, they are moved inward and gradually pressed. Therefore, when the first pressing finger and the second pressing finger are pressed in directions opposite to each other, the first pressing finger and the second pressing finger can be pressed and connected to each other in a misaligned state. Thus, the wiring box 300 can be connected to the pipe 400 by a simple and intuitive method.

도 6b를 통하여 이를 설명하면 설계도면(A1)에 따라 배선박스(300)와 배관(400)을 설치하는 경우, 검정색의 배선박스(300)는 가운데 두고, 그 양측에는 각각 흰색과 파란색의 배선박스(300)를 배치한다. 그 후 검정색의 배선박스(300)의 빨간색의 제1가압브라켓(310)에 빨간색으로 채색된 배관(400)의 일측에 빨간색으로 채색된 제2가압브라켓(320)을 연결하여 검정색의 배선박스(300)와 배관(400)을 연결하고, 나머지 흰색의 배선박스(300)의 빨간색의 제1가압브라켓(310)에 검정색의 배선박스(300)와 연결되며 빨간색으로 채색된 배관(400)의 타측에 빨간색으로 채색된 제2가압브라켓(320)을 연결하는 방식으로 연결한다. 이처럼 색을 통하여 미리 구분된 배선박스(300)와 배관(400)을 설계도면(A1)에 따라 배치하고 연결하기만 하면 됨으로 작업시간을 단축시킬 수 있다.6B, when the wiring box 300 and the pipe 400 are installed according to the design drawing A1, the black wiring box 300 is placed in the center, and white and blue wiring boxes (300). Then, a second pressurizing bracket 320 colored red is connected to one side of the red colored first pressurizing bracket 310 of the black wiring box 300 to form a black wiring box 300 and the piping 400 are connected to the red wiring box 300 and the red wiring line box 300 is connected to the red first pressing bracket 310 of the remaining white wiring box 300, The second pressurizing bracket 320, which is colored red, is connected. As described above, the wiring box 300 and the piping 400, which are preliminarily classified through color, are arranged and connected according to the design drawing A1, so that the working time can be shortened.

여기서, 제1가압브라켓(310)과 제2가압브라켓(320)의 외측에는 가압원형부체가 설치되어 제1가압브라켓(310)과 제2가압브라켓(320)의 연결을 더욱 견고하게 할 수 있다.Here, the first pressurizing bracket 310 and the second pressurizing bracket 320 are provided on the outer sides of the first pressurizing bracket 310 and the second pressurizing bracket 320 so that the connection between the first pressurizing bracket 310 and the second pressurizing bracket 320 can be further strengthened .

또한, 배선박스(300)의 외측에는 연결체(350), 고정체(360)가 설치될 수 있다. 배선박스(300)는 거푸집 또는 지면 등에 고정될 필요가 있는데, 이 경우 연결체(350)와 고정체(360), 회전매개체(370), 연결핀을 통하여 고정될 수 있다.A connector 350 and a fixing body 360 may be provided on the outside of the wiring box 300. The wiring box 300 needs to be fixed to a form or a ground or the like. In this case, the wiring box 300 can be fixed through the connecting body 350 and the fixing body 360, the rotating medium 370, and the connecting pin.

연결체(350)는 배선박스(300)의 외측에서 형성되며, 일측이 개방되며 라운드하게 형성된 라운드홈을 구비한다. 연결체(350)의 외측에는 나사산이 형성된다.The connector 350 is formed on the outside of the wiring box 300, and has round openings formed on one side thereof. A thread is formed on the outside of the connector 350.

고정체(360)는 라운드홈에 배치되는 연결볼(361)을 구비하며, 연결볼(361)의 일측에서 연장되며 단부에는 연결공(362)이 형성된다.The fixing body 360 has a connecting ball 361 disposed in a round groove and extends from one side of the connecting ball 361 and has a connecting hole 362 formed at an end thereof.

여기서 라운드홈과 연결볼(361) 중 어느 하나는 외주면을 따라 돌기가 형성되고 나머지 하나에는 돌기홈이 형성된다. 도 5a에서는 돌기홈이 라운드홈에 형성되고, 돌기가 연결볼(361)에 형성된 것으로 하였다. 돌기는 이동시 지속적으로 돌기홈에 삽입되어 고정되어 라운드홈에 연결볼(361)이 완전하게 자유롭게 이동되는 것을 방지한다. 이는 고정체(360)가 연결체(350)에서 자유로운 각도로 이동되되 순간순간 이동을 제한하여 설치의 용이성을 부여한다.Here, one of the round groove and the connection ball 361 has a protrusion along the outer circumferential surface and the other has a protrusion groove. In Fig. 5A, the protruding grooves are formed in the round grooves, and the protrusions are formed in the connecting balls 361. The protrusion is inserted and fixed in the protrusion groove continuously during the movement to prevent the connection ball 361 from being completely freely moved in the round groove. This allows the fixture 360 to be moved at an angle free from the connector 350 and to limit instantaneous movement to provide ease of installation.

회전매개체(370)는 연결체(350)의 외측에 설치된다. 회전매개체(370)의 내측면에는 나사산과 결합되는 나사산이 형성되어 있다. 작업자는 회전매개체(370)를 일방향으로 돌려서 회전매개체(370)가 연결체(350)를 가압하도록 한다. 이를 통하여 연결체(350)와 고정체(360)는 가압력에 의하여 고정될 수 있다. The rotating medium 370 is installed outside the connecting body 350. On the inner surface of the rotating medium 370 is formed a thread to be engaged with a thread. The operator turns the rotating medium 370 in one direction so that the rotating medium 370 presses the connecting body 350. The connecting body 350 and the fixing body 360 can be fixed by a pressing force.

연결공(362)에는 연결핀이 삽입될 수 있다. 일예시적으로 연결공(362)과 연결핀은 각각 볼트와 너트 일 수 있으며 또 다른 예로는 연결핀은 압정과 같은 가압체일 수 있다. 이를 통하여 배선박스(300)는 고정되고자 하는 곳에 안정적으로 고정될 수 있다.A connecting pin can be inserted into the connecting hole 362. As an example, the connecting hole 362 and the connecting pin may be bolts and nuts, respectively, and in another example, the connecting pin may be a pressing body such as a pushpin. Through this, the wiring box 300 can be stably fixed to the place to be fixed.

확인단계(S5)는 설정된 작업시간에 설정된 작업영역에서 작업자가 공사작업을 수행하는지를 지속적으로 확인하는 단계이다.The confirmation step S5 is a step of continuously checking whether the worker performs the construction work in the work area set at the set work time.

즉, 설정된 시간에 작업자단말기(200)의 활성화부(210)가 제1작업신호를 송신하였으며, GPS부(240)가 전송하는 좌표정보가 설정된 작업영역에 위치하는지를 판단하는 단계이다. 이를 통하여 관리자단말기(100)는 작업자가 작업을 수행하는지를 지속적으로 관리, 감독할 수 있다.That is, it is determined whether the activating unit 210 of the worker terminal 200 has transmitted the first operation signal and the coordinate information transmitted by the GPS unit 240 is located in the set working area. Through this, the administrator terminal 100 can continuously manage and supervise whether the worker performs the work.

한편, 확인단계(S5)에서는 관리자단말기(100)는 제1작업신호를 송신한 작업자단말기(200)에 설정된 간격을 두고 촬영신호를 송신할 수 있다. 즉, 관리자단말기(100)는 제1시간에 촬영신호를 송신하고, 제2시간에 촬영신호를 송신할 수 있다. 촬영신호를 수신한 작업자단말기(200)의 촬영부(230)는 촬영을 수행하여 촬영데이터를 생성하고, 관리자단말기(100)로 송신할 수 있다.On the other hand, in the confirmation step S5, the administrator terminal 100 can transmit a photographing signal to the worker terminal 200, which has transmitted the first operation signal, at an interval set at the operator terminal. That is, the administrator terminal 100 can transmit the photographing signal at the first time and the photographing signal at the second time. The photographing unit 230 of the operator terminal 200 that has received the photographing signal may perform photographing to generate photographing data and transmit the photographing data to the administrator terminal 100. [

관리자단말기(100)는 관리자단말기(100)가 송신하는 촬영데이터를 수신하고, 차례로 이를 저장부(110)에 저장할 수 있다. 이를 통하여 관리자단말기(100)는 작업자가 설정된 작업영역에서 작업을 수행하지를 파악할 수 있다.The administrator terminal 100 may receive the image pickup data transmitted from the administrator terminal 100 and store the image pickup data in the storage unit 110 in order. Accordingly, the administrator terminal 100 can grasp that the worker does not perform the work in the set work area.

도 4에서 (a)는 확인단계에서 제1시간에 관리자단말기가 수신한 촬영데이터에 포인트를 설정한 것을 도시한 것이고 (b)는 확인단계에서 제2시간에 관리자단말기가 수신한 촬영데이터에 포인트를 설정한 것을 도시한 것이다. 4 (a) shows that the point is set in the shooting data received by the administrator terminal at the first time in the checking step, and (b) shows that the shooting data received by the manager terminal at the second time As shown in Fig.

한편, 관리자단말기(100)는 작업자단말기(200)가 설정된 간격을 두고 송신한 촬영데이터가 동일한 GPS좌표를 가지는 경우, 연산부(140)를 통하여 비교 분석하여 작업의 진행 정도를 파악할 수 있다.Meanwhile, when the photographing data transmitted by the operator terminal 200 at the set intervals have the same GPS coordinates, the manager terminal 100 can compute and analyze the progress of the work through the operation unit 140. [

예를 들어, 작업자단말기(200)가 제1시간에 송신한 촬영데이터가 도 4(a)에서 확인되는 것과 같은 경우 배선박스(300)의 제1가압브라켓(310)의 4지점을 포인트로 지정할 수 있다. 그후 도 4(b)에서 도시된 것과 같이 제2시간에 송신한 촬영데이터는 제1가압브라켓(310)의 4지점과 제2가압브라켓(320)의 4지점을 포인트로 지정할 수 있다. 즉, 작업자단말기(200)는 제1시간에 수신된 촬영데이터의 포인트와 제2시간에 수신된 촬영데이터의 포인트를 비교, 분석한다. 이경우 포인트의 변경이 발생되었으므로, 작업이 진행되는 것으로 판단한다.For example, when the photographed data transmitted by the operator terminal 200 at the first time is as shown in FIG. 4 (a), four points of the first pressure bracket 310 of the wiring box 300 are designated as points . Then, as shown in FIG. 4 (b), the photographic data transmitted at the second time can designate four points of the first pressure bracket 310 and four points of the second pressure bracket 320 as points. That is, the worker terminal 200 compares and analyzes the point of the photographed data received at the first time with the point of the photographed data received at the second time. In this case, since the change of the point has occurred, it is judged that the work is proceeding.

이에 반하여 관리자단말기(100)의 연산부(140)가 포인트를 설정하고, 비교한 결과 포인트에 변화가 없다면 관리자단말기(100)의 주의신호생성부(150)가 동작되어 작업자단말기(200)의 알림부(230)를 동작 시킬 수 있다.The operation unit 140 of the administrator terminal 100 sets a point and if there is no change in the comparison result point, the attention signal generation unit 150 of the administrator terminal 100 is operated, (230).

또한, 확인단계(S5)에서는 바운더리가 설정된 작업영역에 기설정된 작업자단말기(200)가 기설정된 개수로 위치하는지를 확인하는 작업을 수행할 수 있다.Also, in the checking step S5, it is possible to check whether the preset number of the operator terminal 200 preset in the work area in which the boundary is set is located.

예를 들어, A구역에 2명의 작업자가 작업을 수행하도록 예정되어 있으면, 관리자단말기(100)는 바운더리가 설정된 A구역에 작업자단말기(200)가 2개가 위치하는지를 작업자단말기(200)의 GPS부(240)를 통하여 확인할 수 있으며, 만약 기설정된 작업 예정 시간에 2개의 작업자단말기(200)가 A구역에 위치되지 않으면 관리자단말기(100)의 주의신호생성부(150)가 동작되어 A구역에 위치한 작업자단말기(200)의 알림부(230)를 동작 시킬 수 있다.For example, if two workers are scheduled to perform work in the A zone, the manager terminal 100 determines whether the two worker terminals 200 are located in the A zone where the boundary is set, If the two worker terminals 200 are not located in the A zone at the scheduled work scheduled time, the attention signal generator 150 of the manager terminal 100 is operated and the operator The notification unit 230 of the terminal 200 can be operated.

또한, 본 발명인 스마트 전기공사 시공방법은 작업자단말기(200)별로 저장부(110)에 작업을 수행한 내용을 데이터화하여 저장할 수 있다. 이 경우, 작업자단말기(200)별로 저장부(110)에 수행한 내용을 데이터화하여 작업의 진행정도를 지속적으로 업데이트하여 관리, 감독하여 만약 중간에 퇴사한 작업자의 업무를 인수 인계하는 새로 고용된 작업자가 어떠한 업무를 수행하고, 어느 작업영역에, 어느 작업시간에 위치되면 되는지를 파악할 수 있어서 작업자의 작업의 연속성을 보장할 수 있다.In addition, the smart electric construction method according to the present invention can store data of work performed in the storage unit 110 for each worker terminal 200 by data. In this case, the content of the work performed in the storage unit 110 for each worker terminal 200 is converted into data, and the progress of the work is continuously updated, managed, and supervised. If the newly employed worker The work area, and the work time, so that the continuity of the worker's work can be ensured.

본 발명은 특정한 실시 예에 관련하여 도시하고 설명하였지만, 이하의 특허청구범위에 의해 제공되는 본 발명의 기술적 사상을 벗어나지 않는 한도 내에서, 본 발명이 다양하게 개량 및 변화될 수 있다는 것은 당 업계에서 통상의 지식을 가진 자에게 있어서 자명할 것이다.While the present invention has been particularly shown and described with reference to specific embodiments thereof, it will be understood by those skilled in the art that various changes in form and details may be made therein without departing from the spirit and scope of the invention as defined by the following claims It will be apparent to those of ordinary skill in the art.

100 : 관리자단말기 110 : 저장부
120 : 스케줄관리부 130 : 기후데이터
140 : 연산부 150 : 주의신호생성부
160 : 설계확정부 170 : 작업시간설정부
180 : 바운더리설정부 190 : (관리자단말기의)송신부
195 : (관리자단말기의)수신부
200 : 작업자단말기 210 : 활성화부
220 : 촬영부 230 : 알림부
240 : GPS부 250 : 변경상황보고부
260 : 고도송신부 290 : (작업자단말기의)송신부
295 : (작업자단말기의)수신부
300 : 배선박스 310 : 제1가압브라켓
320 : 제2가압브라켓 350 : 연결체
360 : 고정체 361 : 연결볼
362 : 연결공 370 : 회전매개체
400 : 배관
S1 : 스케줄입력단계 S2 : 바운더리설정단계
S3 : 작업시간설정단계 S4 : 시공단계
S5 : 확인단계 S6 : 수정단계
A1 : 설계도면 A2 : 배선박스준비단계
A3 : 배관준비단계 A4 : 설치단계
100: Administrator terminal 110:
120: schedule management unit 130: climate data
140: operation unit 150:
160: design decision section 170: work time setting section
180: boundary setting unit 190: transmitting unit (of the administrator terminal)
195: Receiver (of the administrator terminal)
200: worker terminal 210:
220: photographing unit 230:
240: GPS unit 250: Change status reporting unit
260: altitude transmitter 290: transmitter (of the operator terminal)
295: Receiver (of the operator terminal)
300: wiring box 310: first pressurizing bracket
320: second pressure bracket 350: connecting body
360: Fixture 361: Connection ball
362: connecting ball 370: rotating medium
400: Piping
S1: Schedule input step S2: Boundary setting step
S3: Set working time Step S4: Construction step
S5: Confirmation step S6: Modification step
A1: Design drawing A2: Wiring box preparation step
A3: Piping preparation step A4: Installation step

Claims (6)

공기지연을 방지하기 위한 스마트 전기공사 시공방법에 있어서,
관리자단말기에 시공스케줄을 입력하는 스케줄입력단계;
입력된 스케줄에 따라 전기공사가 진행되는 작업영역을 설정하는 바운더리설정단계;
상기 관리자단말기에서 상기 시공스케줄에 따라 예상되는 작업시간을 설정하는 작업시간설정단계;
상기 설정된 작업시간에 상기 설정된 작업영역에서 작업자가 작업자단말기를 소지하고 공사를 진행하는 시공단계; 및
상기 설정된 작업시간에 상기 설정된 작업영역에 공사작업을 수행하는 작업자단말기가 위치하는지를 체크하는 확인단계를 포함하며
상기 바운더리설정단계에서는
상기 시공스케줄에 따라 복수의 층에 대하여 각각 작업영역을 설정하여 각 층별로 복수개의 작업영역을 설정하면서,
사고가 발생될 작업영역을 설정하는 위험바운더리설정단계를 포함하여, 상기 작업영역과 위험영역을 각각의 층별로 각각 설정하고,
상기 확인단계에서는,
상기 관리자단말기는 상기 작업자단말기의 고도송신부와 GPS부가 송신하는 각각의 고도에 대한 정보와 위치의 정보를 수신하여 상기 작업자단말기의 위치하는 고도 및 위치를 기반으로 상기 작업자단말기의 위치를 고도에 따라 작업영역에 위치하는지 아는지를 확인하며,
상기 작업자단말기의 활성화부가 송신하는 신호를 상기 관리자단말기가 수신하여 상기 작업자단말기를 소지한 작업자가 작업의 시작여부 및 작업의 수행여부를 확인하되, 상기 작업자단말기가 상기 사고가 발생될 작업영역에 인접한 위치에 위치되면 상기 작업자단말기의 알림부를 통하여 위험에 대한 경고 신호를 상기 관리자단말기는 송신하며,
상기 관리자단말기가 상기 설정된 작업시간에 설정된 간격을 두고 촬영신호를 상기 작업자단말기로 송신하고, 상기 촬영신호를 수신한 상기 작업자단말기가 촬영을 수행하여 설정된 간격을 가지고 생성된 복수의 촬영데이터를 상기 관리자단말기로 송부하여 전기공사 작업이 진행되는지를 확인하되
상기 관리자단말기는 상기 수신된 촬영데이터가 동일한 GPS좌표를 가지는 경우 먼저 수신된 촬영데이터에 설정된 포인트를 지정하고, 나중에 수신된 촬영데이터에 상기 먼저 수신된 촬영데이터와 동일한 설정된 포인트를 지정하고 비교, 대조하여 설정된 포인트의 개수가 증가되는지를 감지하여 작업진행 정도를 판단하고,
상기 작업을 수행하는 작업자가 작업자단말기를 이용하여 변경된 스케줄에 따라 변경신호를 상기 관리자단말기로 송신하면 상기 관리자단말기는 상기 변경신호를 수신하여 상기 시공스케줄을 변경하고, 상기 작업영역을 수정하여 바운더리를 재설정하고, 상기 작업시간을 재설정하는 수정단계를 포함하며,
상기 확인단계에서는,
상기 작업영역은 복수로 지정되어 복수개의 바운더리라 형성될 수 있으며, 상기 복수의 바운더리 각각에는 상기 스케줄에 따라 상기 작업영역에 위치할 상기 작업자단말기가 개수가 기설정되어 있어서 상기 각각의 바운더리에 기설정된 개수의 작업자단말기가 위치하는지를 확인하고,
상기 시공단계에서는,
시공 전 설계도면의 진행여부를 확정하는 설계확정단계;
상기 설계도면에 배치되되, 외측에는 일방향으로 돌출되되 설정된 제1이격간격을 가지고 원주형태에 따라 배치된 제1가압핑거가 형성되되 적어도 동일하지 않은 상이한 색을 가지는 제1가압브라켓을 복수개 구비한 배선박스를 복수개 준비하는 배선박스준비단계;
상기 배선박스에 연결되되 상기 연결되는 위치에 배치된 제1가압브라켓의 색과 동일한 색을 갖도록 복수개 형성되어 연결위치가 용이하게 파악되는 배관을 준비하고, 상기 상이한 색을 가지는 배관의 일측에는 연결되는 상기 제1가압브라켓과 동일한 색을 가지되, 상기 제1이격간격과 어긋난 간격인 제2이격간격을 가지는 제2가압핑거가 형성되어 상기 제1가압핑거에 엇갈리게 삽입되는 경우 상호 가압되어 고정되는 제2가압브라켓을 상기 배관에 삽입하는 배관준비단계; 및
상기 공사가 진행되는 위치로 상기 배선박스 및 상기 배관을 이동시켜 상기 설계도면에 따라 상기 배선박스를 배치하고, 제1가압브라켓에 상기 제2가압브라켓을 연결하여 고정하는 설치단계
를 포함하는 스마트 전기공사 시공방법.
A method of constructing a smart electric work for preventing air delay,
A schedule input step of inputting a construction schedule to an administrator terminal;
A boundary setting step of setting a work area in which electric work is performed according to an inputted schedule;
A work time setting step of setting an expected work time in the manager terminal according to the construction schedule;
A construction step in which the worker carries on work with the worker terminal in the set work area at the set work time; And
And checking whether the worker terminal performing the construction work is located in the set work area at the set work time
In the boundary setting step
Setting a work area for each of a plurality of layers according to the construction schedule, setting a plurality of work areas for each layer,
And a risk boundary setting step of setting a work area where an accident will occur, wherein the work area and the danger area are set for respective layers,
In the confirming step,
The manager terminal receives the information of the altitude and the position of each altitude transmitted by the altitude transmitter and the GPS unit of the worker terminal and determines the position of the worker terminal based on altitude and position of the worker terminal, Lt; RTI ID = 0.0 > region, < / RTI >
Wherein the manager terminal receives a signal transmitted by the activator of the worker terminal and confirms whether the worker carrying the worker terminal starts the work and whether or not the work is performed, The manager terminal transmits a warning signal about the danger through the notification unit of the worker terminal,
The manager terminal transmits a photographing signal to the operator terminal at an interval set in the set working time, and the operator terminal, which has received the photographing signal, Please send it to the terminal to check if the electric work is going on.
The manager terminal designates a point set in the received photographing data when the received photographing data has the same GPS coordinates, designates the same set point as the previously received photographing data in the photographing data received later, And determines whether the number of points is increased,
When the worker performing the job transmits a change signal to the administrator terminal according to the changed schedule using the worker terminal, the administrator terminal receives the change signal to change the construction schedule, and corrects the work area to change the boundary And a correction step of resetting the operation time,
In the confirming step,
The plurality of work areas may be designated as a plurality of boundaries, and each of the plurality of boundaries includes a number of worker terminals to be located in the work area according to the schedule, The number of worker terminals is located,
In the construction step,
A design confirmation step for determining whether the design drawing is proceeded before construction;
A plurality of first pressure brackets arranged in the design drawing and protruding in one direction at a first spacing interval and having first pressure fingers arranged in a circumferential shape with a predetermined spacing, A wiring box preparation step of preparing a plurality of boxes;
A plurality of pipes connected to the wiring box and having the same color as the colors of the first pressure brackets disposed at the connected positions are prepared to easily identify the connection positions, and the pipes are connected to one side of the pipes having different colors A second pressing finger having the same color as that of the first pressing bracket and having a second spacing interval which is a gap deviated from the first spacing distance is formed and when the first pressing finger is staggeredly inserted into the first pressing finger, A piping preparing step of inserting the 2-pressure bracket into the piping; And
A step of moving the wiring box and the piping to a position where the construction is progressed to arrange the wiring box according to the design drawing and fixing the second pressurizing bracket to the first pressurizing bracket,
A method of constructing a smart electrical work comprising:
삭제delete 삭제delete 삭제delete 삭제delete 제1항에 있어서,
상기 배선박스준비단계에서 상기 배선박스는
상기 배선박스의 외측에 형성된 일측이 개방되며 라운드하게 형성된 라운드홈을 구비하며 외측에는 나사산이 형성된 연결체;
상기 라운드홈에 배치되는 연결볼과 상기 연결볼의 일측에서 연장되어 단부에 연결공이 형성된 고정체; 및
상기 연결체를 둘러싸는 형태로 상기 연결체의 외측의 나사산에 결합되며 회전에 따라 연결체를 가압하여 상기 고정체와 상기 연결체를 견고하게 고정시키는 회전매개체를 포함하며
상기 연결공에는 연결핀이 삽입되어 고정될 수 있는 것
을 특징으로 하는 스마트 전기공사 시공방법.
The method according to claim 1,
In the wiring box preparation step, the wiring box
A connection body having a round groove formed on an outer side of the wiring box and having a round opening,
A connection ball disposed in the round groove and a fixing member extending from one side of the connection ball and having a connection hole formed at an end thereof; And
And a rotating medium coupled to the thread on the outer side of the connecting body in the form of surrounding the connecting body and pressing the connecting body along with the rotation to firmly fix the fixing body and the connecting body,
The connection pin may be inserted and fixed to the connection hole
The method comprising the steps of:
KR1020170123606A 2017-09-25 2017-09-25 Smart construction method of electric work KR101838024B1 (en)

Priority Applications (1)

Application Number Priority Date Filing Date Title
KR1020170123606A KR101838024B1 (en) 2017-09-25 2017-09-25 Smart construction method of electric work

Applications Claiming Priority (1)

Application Number Priority Date Filing Date Title
KR1020170123606A KR101838024B1 (en) 2017-09-25 2017-09-25 Smart construction method of electric work

Publications (1)

Publication Number Publication Date
KR101838024B1 true KR101838024B1 (en) 2018-04-27

Family

ID=62081751

Family Applications (1)

Application Number Title Priority Date Filing Date
KR1020170123606A KR101838024B1 (en) 2017-09-25 2017-09-25 Smart construction method of electric work

Country Status (1)

Country Link
KR (1) KR101838024B1 (en)

Cited By (7)

* Cited by examiner, † Cited by third party
Publication number Priority date Publication date Assignee Title
KR102084565B1 (en) * 2018-10-30 2020-04-20 (주)오픈웍스 Security Management Apparatus Customized at Site and Driving Method Thereof
CN112241837A (en) * 2020-10-12 2021-01-19 深圳市欧瑞博科技股份有限公司 Intelligent construction scheme generation method and device, intelligent equipment and storage medium
KR102272486B1 (en) 2020-06-22 2021-07-01 이재남 Mathod for construction of electric work
KR102292974B1 (en) 2021-02-01 2021-08-23 전준열 Firefighting electrical work construction method
KR102316632B1 (en) * 2021-03-17 2021-10-22 (주)엘다임 Method for estimating risk of construction field
KR102351250B1 (en) * 2021-03-16 2022-01-14 (주)엘다임 Method for managing construction site
KR102655511B1 (en) 2023-12-27 2024-04-05 박원준 Method for scheduling tile installation considering material loss

Citations (2)

* Cited by examiner, † Cited by third party
Publication number Priority date Publication date Assignee Title
KR101682861B1 (en) * 2016-07-21 2016-12-06 김대진 System for managing construction work for shipbuilding offshore plant, and method thereof
KR101745670B1 (en) * 2017-02-08 2017-06-27 김동관 System for managing worker using position information

Patent Citations (2)

* Cited by examiner, † Cited by third party
Publication number Priority date Publication date Assignee Title
KR101682861B1 (en) * 2016-07-21 2016-12-06 김대진 System for managing construction work for shipbuilding offshore plant, and method thereof
KR101745670B1 (en) * 2017-02-08 2017-06-27 김동관 System for managing worker using position information

Cited By (7)

* Cited by examiner, † Cited by third party
Publication number Priority date Publication date Assignee Title
KR102084565B1 (en) * 2018-10-30 2020-04-20 (주)오픈웍스 Security Management Apparatus Customized at Site and Driving Method Thereof
KR102272486B1 (en) 2020-06-22 2021-07-01 이재남 Mathod for construction of electric work
CN112241837A (en) * 2020-10-12 2021-01-19 深圳市欧瑞博科技股份有限公司 Intelligent construction scheme generation method and device, intelligent equipment and storage medium
KR102292974B1 (en) 2021-02-01 2021-08-23 전준열 Firefighting electrical work construction method
KR102351250B1 (en) * 2021-03-16 2022-01-14 (주)엘다임 Method for managing construction site
KR102316632B1 (en) * 2021-03-17 2021-10-22 (주)엘다임 Method for estimating risk of construction field
KR102655511B1 (en) 2023-12-27 2024-04-05 박원준 Method for scheduling tile installation considering material loss

Similar Documents

Publication Publication Date Title
KR101838024B1 (en) Smart construction method of electric work
CN102801752B (en) A kind of train network equipment data real time monitoring and debugging apparatus and method thereof
CN110830488A (en) Network security risk analysis and restoration method for electric power monitoring system
JP6106144B2 (en) Optical fiber test apparatus and optical fiber test system
KR101891926B1 (en) Remote control system for automation equipment
CN112633697A (en) Digital intelligent mine system
KR102468546B1 (en) Electric power supply apparatus management system for telegraph pole using IoT
US20220406158A1 (en) System, server and method for monitoring utility systems
CN105792132A (en) Building online electronic patrolling system
US6658311B1 (en) Maintenance management system for press line
KR20230099629A (en) Management device for substrate processing system and management method of substrate processing system
JP6632897B2 (en) Disaster prevention system
KR101824595B1 (en) System for distributing power and communication signals comprising multi-cable
CN106559747A (en) Side is stood firm position monitoring system and method
KR102039032B1 (en) Apparatus for detecting trip of circuit breaker ana circuit breaker monitoring method using lpwa
KR102272486B1 (en) Mathod for construction of electric work
CN216623705U (en) Cable walking direction indication stake and stake management system
KR101689283B1 (en) Network system comprising multi-cable for work in place on a ship or ocean engineering
CN216146391U (en) Fracturing construction well site equipment network intelligent monitoring system
WO2023032327A1 (en) Information processing method, information processing device, and information processing program
CN111025350B (en) Control method and device for positioning calculation, terminal equipment and positioning system
CN109159304A (en) A kind of concrete mixing plant remote wireless control system
CN116317172B (en) Cable laying monitoring system and method
KR102614657B1 (en) Wireless communication-based video management system for underground workshops and operation method therefor
CN110769448B (en) Monitoring method, monitoring device and monitoring system

Legal Events

Date Code Title Description
E701 Decision to grant or registration of patent right
GRNT Written decision to grant