KR101230462B1 - Method of schedule management and apparatus thereof - Google Patents

Method of schedule management and apparatus thereof Download PDF

Info

Publication number
KR101230462B1
KR101230462B1 KR1020120046436A KR20120046436A KR101230462B1 KR 101230462 B1 KR101230462 B1 KR 101230462B1 KR 1020120046436 A KR1020120046436 A KR 1020120046436A KR 20120046436 A KR20120046436 A KR 20120046436A KR 101230462 B1 KR101230462 B1 KR 101230462B1
Authority
KR
South Korea
Prior art keywords
project
schedule
activity
communication terminal
user
Prior art date
Application number
KR1020120046436A
Other languages
Korean (ko)
Inventor
윤영식
Original Assignee
윤영식
Priority date (The priority date is an assumption and is not a legal conclusion. Google has not performed a legal analysis and makes no representation as to the accuracy of the date listed.)
Filing date
Publication date
Application filed by 윤영식 filed Critical 윤영식
Priority to KR1020120046436A priority Critical patent/KR101230462B1/en
Application granted granted Critical
Publication of KR101230462B1 publication Critical patent/KR101230462B1/en
Priority to PCT/KR2013/002820 priority patent/WO2013165099A1/en

Links

Images

Classifications

    • GPHYSICS
    • G06COMPUTING; CALCULATING OR COUNTING
    • G06QINFORMATION AND COMMUNICATION TECHNOLOGY [ICT] SPECIALLY ADAPTED FOR ADMINISTRATIVE, COMMERCIAL, FINANCIAL, MANAGERIAL OR SUPERVISORY PURPOSES; SYSTEMS OR METHODS SPECIALLY ADAPTED FOR ADMINISTRATIVE, COMMERCIAL, FINANCIAL, MANAGERIAL OR SUPERVISORY PURPOSES, NOT OTHERWISE PROVIDED FOR
    • G06Q10/00Administration; Management
    • G06Q10/10Office automation; Time management
    • GPHYSICS
    • G06COMPUTING; CALCULATING OR COUNTING
    • G06QINFORMATION AND COMMUNICATION TECHNOLOGY [ICT] SPECIALLY ADAPTED FOR ADMINISTRATIVE, COMMERCIAL, FINANCIAL, MANAGERIAL OR SUPERVISORY PURPOSES; SYSTEMS OR METHODS SPECIALLY ADAPTED FOR ADMINISTRATIVE, COMMERCIAL, FINANCIAL, MANAGERIAL OR SUPERVISORY PURPOSES, NOT OTHERWISE PROVIDED FOR
    • G06Q50/00Information and communication technology [ICT] specially adapted for implementation of business processes of specific business sectors, e.g. utilities or tourism
    • G06Q50/40Business processes related to the transportation industry

Landscapes

  • Business, Economics & Management (AREA)
  • Engineering & Computer Science (AREA)
  • Strategic Management (AREA)
  • Human Resources & Organizations (AREA)
  • Entrepreneurship & Innovation (AREA)
  • General Business, Economics & Management (AREA)
  • Economics (AREA)
  • Marketing (AREA)
  • Theoretical Computer Science (AREA)
  • General Physics & Mathematics (AREA)
  • Tourism & Hospitality (AREA)
  • Physics & Mathematics (AREA)
  • Data Mining & Analysis (AREA)
  • Quality & Reliability (AREA)
  • Operations Research (AREA)
  • Health & Medical Sciences (AREA)
  • General Health & Medical Sciences (AREA)
  • Primary Health Care (AREA)
  • Management, Administration, Business Operations System, And Electronic Commerce (AREA)

Abstract

PURPOSE: A schedule management method and a device thereof are provided to allow a communication terminal user to rearrange a project with grouped activities corresponding to the new schedule of a user or for a special purpose, thereby utilizing the rearranged project. CONSTITUTION: A data communication unit(210) processes transmitting/receiving data related to the download of a specific project of which the schedule is rearranged by a user. A project management unit(220) automatically rearranges a schedule of each activity within the project downloaded from a server computer based on a new determined schedule. An activity management unit(230) groups related activities. [Reference numerals] (210) Data communication unit; (220) Project management unit; (230) Activity management unit; (240) Schedule management unit; (250) Storage unit; (260) Schedule performance check unit; (270) Control unit

Description

일정관리방법 및 그 장치{Method of schedule management and apparatus thereof}Schedule management and apparatus thereof

본 발명은 사용자가 서비스 운영자 또는 커뮤니티를 통해 서로 관련 있는 액티비티(구체적 날짜 또는 어떤 날짜의 구체적인 시간에 어떤 일을 할 지가 결정된 이벤트)들을 그룹화한 프로젝트나 각 액티비티를 다운로드받아 자신의 일정에 따라 조정하여 활용하거나, 서비스 운영자 또는 커뮤니티를 통해 프로젝트나 각 액티비티의 일정을 자신의 일정에 따라 조정한 후 다운로드받아 활용할 수 있는 일정관리방법 및 그 장치에 관한 것이다.According to the present invention, a user downloads a project or grouping activities related to each other through a service operator or a community (an event in which a specific date or a specific time is determined at a specific time) and adjusts them according to their schedule. The present invention relates to a schedule management method and apparatus that can be downloaded and used after adjusting the schedule of a project or each activity according to its own schedule through a service operator or a community.

최근 들어 효율적인 시간 관리, 일정 관리가 행복하고 성공적인 삶을 살기 위한 방법이라는 인식이 확산되면서 여러 가지 종류의 일정 관리 도구를 사용하였다. 수첩에 일정을 기록하기도 하고, 특별한 형태로 인쇄된 일정 관리 도구도 사용하였다. 개인용 컴퓨터가 보급되면서 개인용 컴퓨터상에서 일정을 관리할 수 있는 프로그램들이 보급되었고, 인터넷 이용이 일반화되면서부터 인터넷상에서도 개인의 일정을 관리할 수 있는 서비스가 제공되고 있다. 휴대폰이 보급되면서 휴대폰에서도 일정을 관리할 수 있게 되었고, 최근 스마트폰이 보급이 확산되면서 스마트폰 상에서 일정을 관리할 수 있는 프로그램 또한 많이 배포되고 있다.In recent years, various types of schedule management tools have been used as the recognition that efficient time management and schedule management is a way to live a happy and successful life. I used to write schedules in my notebooks, and I used a special type of schedule management tool. With the spread of personal computers, programs for managing schedules on personal computers have been distributed. Since the use of the Internet has become commonplace, services for managing personal schedules on the Internet have been provided. With the spread of mobile phones, it is possible to manage schedules in mobile phones. Recently, as the spread of smart phones has spread, many programs for managing schedules on smart phones are also being distributed.

일정 관리 도구뿐만 아니라, 일정 관리 방법과 관련해서도 다양한 방법이 제시되고 있다. 단순하게 약속을 기록하고 찾아볼 수 있게 하는 것에서 출발하여 해야 할 일들을 날짜와 시간별로 기록한 후, 수행하였는지의 여부 등을 체크할 수 있게 하는 것도 있다. 단순히 해야 할 일을 체크하는데 그치지 않고 실행 결과를 기록하여 계획과 비교한 후 개선하도록 하는 방법도 있고, 해야 할 일만 관리하는 것이 아니라 사명서에서 출발하여 인생의 가치관에 따라 일정을 관리하는 방법도 제시되고 있다.In addition to the schedule management tools, various methods have been proposed regarding the schedule management method. You can start by simply recording and browsing your appointments, recording things you need to do by date and time, and then checking whether you've done them. Instead of simply checking what needs to be done, there are ways to record the results of the execution, compare them with the plan, and then improve.In addition, you can start with the mission statement and manage the schedule according to the values of life. have.

네트워크가 발전하면서 자신의 일정을 타인에게 보내 공유할 수 있도록 하기도 하고, 자신의 일정 중 특정 부분을 인터넷에서 타인이 볼 수 있도록 하는 서비스도 제공되고 있다.As the network evolves, some people send their schedules to others so that they can share them, and others can view certain parts of their schedules on the Internet.

이와 같이 다양한 일정 관리 도구와 방법이 제공되고 있음에도 불구하고 하나의 일정 관리 도구와 방법을 이용하여 지속적으로 자신의 일정을 관리하는 사람이 많지 않은 것이 현실이다. 일정을 기록하여야 할 시점에 일정 관리 도구를 가지고 있지 않거나, 현재까지 제공되고 있는 일정 관리 도구가 사용하기에 불편하거나, 일정이 생길 때마다 꼬박꼬박 입력하는 것이 귀찮아서, 또는 일정을 관리하고 싶어도 어떻게 일정을 수립하여야 할지를 몰라서 일정 관리 도구를 사용하지 않을 수도 있다.Although various schedule management tools and methods are provided in this way, there are not many people who continuously manage their schedules using one schedule management tool and method. Even if you don't have a schedule management tool at the time you need to record it, or if you're not comfortable using the existing schedule management tool, or you're bothered to enter it every time a schedule is created, or how you want to manage your schedule, They may not use schedule management tools because they do not know whether they should be established.

일정 관리 도구는 다양한 형태로 존재하지만, 필요할 때 항상 사용할 수 있어야 한다는 측면에서 최근 스마트폰 애플리케이션 형태의 일정 관리 도구가 주목받고 있다. 프랭클린 플래너 등 과거부터 애용되어 오던 종이 형태의 일정 관리 도구가 아직도 꾸준히 사용되고 있지만, 항상 휴대하기가 쉽지 않을 뿐만 아니라 부피가 크고, 검색 기능 등 편의 기능 측면에서 불편한 것이 사실이다. 개인용 컴퓨터 프로그램 형태의 일정 관리 도구 또한 컴퓨터 앞에 있지 않을 경우 사용할 수 없는 제한이 있고, 인터넷으로 제공되는 서비스의 경우 스마트폰에서도 이용할 수 있지만, 접속하기까지의 과정이 번거로운 측면이 있다. 피처폰 형태의 휴대폰에 탑재된 일정 관리 도구의 경우 출시될 때 제공되는 기능 외에 다른 여러 가지 기능을 추가하여 사용하기 힘든 한계가 있다.Although the schedule management tool exists in various forms, in recent years, the schedule management tool in the form of a smartphone application has attracted attention in that it must be available when needed. Paper-based schedule management tools, such as Franklin Planner, which have been used in the past, are still used, but they are not always easy to carry, but bulky and inconvenient in terms of convenience functions such as search functions. The schedule management tool in the form of a personal computer program also has limitations that cannot be used if it is not in front of the computer, and the service provided on the Internet can be used on a smartphone, but the process of connecting to the service is cumbersome. In the case of a feature phone-type mobile phone, the schedule management tool has limitations that are difficult to use by adding various functions in addition to those provided at the time of release.

현재 사용되고 있는 스마트폰 애플리케이션 형태의 일정 관리 도구들을 살펴보면, 사용 중인 일정 관리 도구는 대화 도중 신속히 일정을 기록하기에 힘들 정도로 사용이 불편한 경우가 대부분이다. 따로 시간을 내어 일정을 기록하고자 할 경우에도 입력을 하거나 선택해야 할 사항이 너무 복잡하여 사용하기 불편한 경우도 있다. 불규칙적으로 반복되는 일들을 입력하고자 할 경우에는 하나하나의 일들을 따로 입력할 수밖에 없어 불편하기도 하다.Looking at the schedule management tools in the form of smartphone applications currently in use, most of the schedule management tools in use are inconvenient enough to record the schedule quickly during the conversation. Even if you want to take time to record your schedule, there are times when you have to enter or select something too complicated to use. If you want to input irregularly repeated things, it is inconvenient to enter only one by one separately.

현재 사용되고 있는 일정 관리 도구들은 매주 동일한 요일에 반복되는 일정이나, 매월 또는 매년 단위로 동일한 날짜에 반복되는 일정 이외에는 모든 일정 하나하나를 따로 관리하도록 되어 있다. 매주, 매월, 매일 단위로 반복되는 일은 아니지만, 어떤 특별한 사건이 있으면 그 사건으로부터 특별한 간격의 날짜에 반복되는 사건들의 집합이 있을 수 있다. 자동차 영업 사원이 자동차를 판매하면 각 고객마다 판매일을 기준으로 며칠 후에 감사 전화를 하고, 그로부터 며칠 후에 자동차 상태를 확인하기 위한 전화를 하고, 또 몇 달 후에는 자동차 유지 보수와 관련된 안내를 하기 위해 전화를 할 수 있다. 이 일정들을 일정 관리 도구에서 관리하기 위해서는 각 고객별로 각각의 일정을 하나하나 입력할 수밖에 없다. 자신의 일정 중 어떤 상황이 발생하면 동일하게 반복되는 일정들이 있을 경우 이러한 일정들을 하나의 그룹으로 묶은 후 관련 상황이 발생할 때마다 관련 일정들이 자동으로 계산되어 일정 관리 도구에 반영될 수 있다면 일정 관리 도구를 훨씬 편리하게 사용할 수 있을 것이다. 나아가 자신이 정형화한 일정을 다른 사람들이 검색하고 필요하면 이를 활용할 수 있도록 제공한다면 또 다른 보람을 느낄 수 있을 것이다.Currently used schedule management tools manage all schedules separately, except schedules that repeat on the same day every week or on the same day every month or every year. Although not repeated weekly, monthly, or daily, there may be a set of events that repeat on a particular interval date from that event if there is a particular event. When a car salesman sells a car, each customer calls a thank you phone a few days after the sale date, a few days later to check the car's condition, and a few months later to provide guidance on car maintenance. I can make a phone call. In order to manage these schedules in the schedule management tool, each customer has to enter each schedule one by one. If there are schedules that are equally repeated when something happens in your schedule, group these schedules into a group, and the schedules can be automatically calculated and reflected in the schedule management tool whenever the related situation occurs. Will be much more convenient. Furthermore, if you provide someone else with a standardized schedule that you can search for and use if you need it, you will find it more rewarding.

한 개인에게는 일생동안 자주 발생하지 않지만, 많은 사람에게 그러한 일이 발생하고, 그러한 일이 발생하면 관련된 여러 가지 일들을 해야 하는 상황이 있다. 아기를 출산할 경우 출산일로부터 특정한 날짜가 지날 때마다 각종 예방 접종을 해야 한다든지, 특정한 날짜가 지날 때마다 아동의 발달 단계를 살펴보아야 하는 일들이 있다. 이러한 일정들을 일정 관리 도구로 관리하고자 할 경우 각 자가 일정 관리 도구에 일정들을 하나하나 입력할 수밖에 없다. 출산일을 기준으로 작성된 일정 그룹이 있고, 이러한 일정 그룹을 다운로드 받아 출산일에 자산의 아기의 실제 생일을 입력하면 관련 일정들이 자동으로 계산되어 일정 관리 도구에 반영될 수 있다면 일정 관리 도구에 각각의 일정을 입력해야 하는 불편을 겪지 않을 수 있을 것이다.There is a situation in which an individual does not happen often in life, but many people do that, and when that happens they have to do a number of related things. When you give birth to your baby, you may need to be vaccinated after a certain date from your birth date, or you may want to look at your child's developmental stages after a certain date. If you want to manage these schedules with a schedule management tool, each person has no choice but to enter schedules one by one in the schedule management tool. If you have a schedule group created on the date of birth, and you download the schedule group and enter the asset's actual birth date on the date of birth, related schedules can be automatically calculated and reflected in the schedule management tool. You may not have to enter a schedule.

여행을 계획하면서 각 시간대 별로 이동하거나 관광할 내용을 일정 관리 도구에 입력하여 활용할 수 있다. 자신의 여행이 만족스러웠고, 이 일정을 다른 사람들에게 알려 공유하고자 할 경우 관련된 일정을 하나의 그룹으로 만든 후 특정한 사건(예를 들어, 어떤 도시에 도착하는 것)의 날짜를 기준으로 인터넷 등에 게시할 수 있고, 다른 사람들이 이 일정을 다운로드 받아 특정한 사건의 날짜에 자신이 계획한 날짜를 반영하면 자신의 일정이 자동으로 계산되어 자신의 일정 관리 도구에 반영할 수 있다면 일정을 공유하는 새로운 방법이 될 수 있다.As you plan your trip, you can use the schedule management tool to move around each time zone or to see what you want to see. If you're happy with your trip and want to share it with others, you can create a group of related events and post them on the Internet based on the date of a particular event (for example, arriving in a city). If other people download this calendar and reflect their planned dates on the date of a particular event, their calendar will be automatically calculated and reflected in their calendaring tools, a new way to share the calendar. Can be.

학생들의 경우 새로운 교재를 스스로 학습하고자 할 경우 하루 어느 정도씩 얼마동안에 걸쳐 학습하면 학습을 완료할 수 있을지 미리 알 수 있다면 계획을 수립하고 이를 실천함으로써 실력을 높일 수 있을 것이나, 도대체 어느 정도씩 얼마나 공부해야 할지 감을 잡지 못해 시작도 못해 보는 경우도 많이 있다. 따라서 할 수 있는 일정을 어렵게 구했다고 하더라도 이를 자신의 일정 관리 도구에 기록하려면 일정을 하나하나 기록할 수밖에 없다. 만약 학생들이 어떤 교재를 학습하고자 할 경우 수준별로 참고할 수 있는 일정을 쉽게 찾아볼 수 있고, 필요할 경우 그 일정을 자신의 일정 관리 도구에 다운로드받아 바로 활용할 수 있다면 도움이 될 수 있을 것이다.If students want to learn new texts themselves, if they can know in advance how long and how long they will be able to complete their studies, they can develop a plan and practice to improve their skills. There are many cases where you can't start because you don't know what to do. Therefore, even if you have a difficult schedule, you have to record each schedule to record it in your schedule management tool. If a student wants to learn a textbook, it can be helpful to find a schedule that can be referenced at each level and, if necessary, download the schedule into their schedule management tool and immediately use it.

힘들게 일정 관리 도구에 계획한 일정을 기록했다고 하더라도 계획된 일정대로 실행하는 것은 별개의 문제이다. 자신이 계획한 일정을 얼마나 실행하고 있는지 쉽게 시각적으로 확인할 수 있다면 계획대로 실천할 수 있는 계기가 될 수 있을 것이다.Even if you have a hard time recording your schedule in a scheduling tool, running it on a planned schedule is a separate matter. If you can easily visually see how you are doing your planned schedule, it will be a good time to do what you expect.

수업 시간표를 일정 관리 도구에 기록했다고 하더라도 각 수업별로 발생하는 과제 수행이나 리포트 제출 일정들을 관리하기 위해서는 각자가 별도로 기록한 후 관리할 수밖에 없다. 만약 같은 수업을 듣는 학생 중 한 명 또는 담당 교수가 수업 시간 중에 부여된 과제나 리포트 제출 일정 등을 같은 수업을 듣는 모든 학생에게 보내고, 다른 학생들이 이를 일정 관리 도구에 다운로드받아 바로 활용할 수 있다면 도움이 될 수 있을 것이다. 그러나 이를 위해서는 모든 학생 하나하나를 수신자로 지정하여 발송하든지, 수업을 듣는 학생들을 그룹으로 관리할 수 있는 별도의 프로그램이나 서비스를 이용할 수밖에 없을 것이다. 만약 어떤 일정을 자신의 일정 관리 도구에 다운로드받은 사람들을 하나의 그룹으로 관리하여 그 그룹 구성원에게 관련된 일정이나 메모 등을 전송할 수 있도록 한다면 이 또한 도움이 될 수 있을 것이다.Even if the class schedule is recorded in the schedule management tool, each of them has to record and manage separately to manage the assignment schedule or report submission schedule that occurs for each class. If one of the students in the same class, or the professor, sends the assignment or report submission schedule assigned to the class to all students in the same class, and other students can download it to the scheduling tool and use it immediately, Could be. However, to do this, all students will be designated as recipients, or they will have no choice but to use a separate program or service to manage their students as a group. This can also be helpful if you manage a group of people who have downloaded their calendars into a group and can send related calendars and notes to the group members.

대한민국 공개특허공보 제10-2007-0023286호 2007. 02. 28.Republic of Korea Patent Publication No. 10-2007-0023286 2007. 02. 28. 대한민국 등록특허공보 제10-0715796호 2007. 05. 01.Republic of Korea Patent Publication No. 10-0715796 2007. 05. 01. 대한민국 등록특허공보 제10-0817285호 2008. 03. 20.Republic of Korea Patent Publication No. 10-0817285 2008. 03. 20.

본 발명은, 통신 단말기 사용자가 서비스 운영자 또는 커뮤니티를 통해 서로 관련 있는 액티비티들을 그룹화한 프로젝트를 다운로드받은 후, 사용자 자신의 일정에 따라 프로젝트의 액티비티들의 기존 일정을 재조정하여 활용하도록 하거나, 통신 단말기 사용자가 서비스 운영자 또는 커뮤니티를 통해 서로 관련 있는 액티비티들을 그룹화한 프로젝트의 기존 일정을 자신의 일정에 따라 재조정한 후 다운로드받아 활용하도록 하는 일정관리방법 및 그 장치를 제공한다.According to an embodiment of the present invention, after a communication terminal user downloads a project grouping activities related to each other through a service operator or a community, the communication terminal user readjusts and utilizes an existing schedule of activities of the project according to a user's own schedule. Provides a schedule management method and apparatus for re-scheduling an existing schedule of a project grouping related activities through a service operator or a community according to one's own schedule, and then downloading and using the same.

본 발명은, 통신 단말기 사용자가 서비스 운영자 또는 커뮤니티를 통해 서로 관련 있는 액티비티들을 그룹화한 프로젝트를 다운로드받아 자신의 일정에 맞도록 재활용할 수 있도록 하기 위하여, 통신 단말기 사용자가 자신의 통신 단말기에서 다운로드받은 프로젝트를 선택하면 그 프로젝트에 포함된 액티비티들의 일정들 중 가장 빠른 일자 또는 가장 늦은 일자를 보여주거나 가장 빠른 일자와 가장 늦은 일자를 함께 보여주고, 통신 단말기 사용자가 가장 빠른 일자 또는 가장 늦은 일자 중 하나를 자신의 일정으로 변경한 후 저장하면, 해당 프로젝트에 포함된 모든 액티비티들의 일정들과 사용자가 변경하기 전의 일정과의 간격을 계산한 후 변경된 일정을 기준으로 동일한 간격이 되도록 자동으로 재조정하도록 하는 일정관리방법 및 그 장치를 제공한다.The present invention is a project that a communication terminal user has downloaded from his or her communication terminal in order to allow the communication terminal user to download a project grouping activities related to each other through a service operator or a community and recycle them according to their own schedule. If you select, the earliest or latest date among the activities of the activities included in the project is displayed or the earliest and latest date are displayed together. If you change the schedule to and save it, the schedule management method calculates the interval between all the activities included in the project and the schedule before the user changes the schedule, and automatically reschedules it to be the same interval based on the changed schedule. And provide that device do.

본 발명은, 통신 단말기 사용자가 서비스 운영자 또는 커뮤니티를 통해 서로 관련 있는 액티비티들을 그룹화한 프로젝트를 다운로드받아 자신의 일정에 맞도록 재활용할 수 있도록 하기 위하여, 통신 단말기 사용자가 자신의 통신 단말기에서 다운로드받은 프로젝트에 포함된 액티비티들 중 하나의 액티비티를 선택하여 그 액티비티의 일정을 자신의 일정으로 변경하여 저장할 때 동일한 프로젝트에 포함된 액티비티들 중 해당 액티비티의 기존 일정 이후의 모든 액티비티들의 일정을 변경된 일정을 기준으로 동일한 간격을 유지하도록 재조정할 수 있는 일정관리방법 및 그 장치를 제공한다.The present invention is a project that a communication terminal user has downloaded from his or her communication terminal in order to allow the communication terminal user to download a project grouping activities related to each other through a service operator or a community and recycle them according to their own schedule. When you select one of the activities included in and change the schedule of the activity to your own schedule and save it, the schedule of all the activities included in the same project after the existing schedule of the activity is based on the changed schedule. Provided are a schedule management method and an apparatus which can be readjusted to maintain the same interval.

본 발명은, 통신 단말기 사용자가 서비스 운영자 또는 커뮤니티를 통해 서로 관련있는 액티비티들을 그룹화한 프로젝트를 다운로드받아 자신의 일정에 맞도록 재활용할 수 있도록 하기 위하여, 프로젝트에 포함된 각 액티비티의 일정을 디데이를 기준으로 한 일정(예를 들어, 디데이, 디데이 몇 일 전 또는 디데이 몇 일 후)으로 정해 두고 통신 단말기 사용자가 다운로드받은 프로젝트를 선택하면 디데이에 사용될 자신의 일정을 입력하도록 하고, 통신 단말기 사용자가 입력한 일정을 기준으로 프로젝트에 포함된 모든 액티비티들의 일정을 변경하도록 하는 일정관리방법 및 그 장치를 제공한다.According to the present invention, in order to enable a communication terminal user to download a project grouping activities related to each other through a service operator or a community, and to reuse the project according to their own schedule, the schedule of each activity included in the project is based on the D-day. Set a schedule (for example, D-Day, D-Day days before or D-Day days), and when the communication terminal user selects the downloaded project, the user inputs his schedule to be used for the D-Day. Provides a schedule management method and apparatus for changing the schedule of all activities included in the project based on the schedule.

본 발명은, 통신 단말기 사용자가 서비스 운영자 또는 커뮤니티를 통해 서로 관련 있는 액티비티들을 그룹화한 프로젝트를 자신의 일정에 맞도록 재조정한 후 다운로드받아 활용할 수 있도록 하기 위하여, 통신 단말기 사용자가 서비스 운영자 또는 커뮤니티에 있는 프로젝트를 선택하면 그 프로젝트에 포함된 액티비티들의 일정들 중 가장 빠른 일자 또는 가장 늦은 일자를 보여주거나 가장 빠른 일자와 가장 늦은 일자를 함께 보여주고, 통신 단말기 사용자가 가장 빠른 일자 또는 가장 늦은 일자 중 하나를 자신의 일정으로 변경하면, 해당 프로젝트에 포함된 모든 액티비티들의 일정들과 사용자가 변경하기 전의 일정과의 간격을 계산한 후 변경된 일정을 기준으로 동일한 간격이 되도록 자동으로 재조정한 후 다운로드 되도록 하는 일정관리방법 및 그 장치를 제공한다.The present invention provides a communication terminal user in a service operator or community in order to enable the communication terminal user to download and use after re-scheduling a project grouping activities related to each other through a service operator or community according to their own schedule When you select a project, the schedule shows the earliest or latest date of the activities included in the project, or the earliest and latest date together, and the user of the telecommunications terminal can select one of the earliest or latest date. If you change to your own schedule, it calculates the interval between the schedules of all activities in the project and the schedule before the user changes, and automatically reschedules them to the same interval based on the changed schedule and downloads them. Method and It provides an apparatus.

본 발명은, 통신 단말기 사용자가 서비스 운영자 또는 커뮤니티를 통해 서로 관련 있는 액티비티들을 그룹화한 프로젝트를 자신의 일정에 맞도록 재조정한 후 다운로드받아 활용할 수 있도록 하기 위하여, 통신 단말기 사용자가 서비스 운영자 또는 커뮤니티에 있는 프로젝트를 선택한 후 그 프로젝트를 시작할 자신의 일정, 즉 그 프로젝트에 포함된 액티비티들 중 일자가 가장 빠른 액티비티를 실시할 자신의 일정을 입력하도록 하되, 입력 시점의 날짜를 제시한 후 사용자가 변경할 수 있도록 하고, 사용자가 선택한 날짜를 기준으로 프로젝트에 포함된 모든 액티비티의 일정을 재조정한 후 다운로드 되도록 하는 일정관리방법 및 그 장치를 제공한다.The present invention provides a communication terminal user in a service operator or community in order to enable the communication terminal user to download and use after re-scheduling a project grouping activities related to each other through a service operator or community according to their own schedule After you select a project, enter your own schedule to start the project, that is, the date on which the activities included in the project will run, which will be the fastest. In addition, the present invention provides a schedule management method and apparatus for re-scheduling and downloading all activities included in a project based on a date selected by a user.

본 발명은, 통신 단말기 사용자가 서비스 운영자 또는 커뮤니티를 통해 서로 관련있는 액티비티들을 그룹화한 프로젝트를 자신의 일정에 맞도록 재조정한 후 다운로드받아 활용할 수 있도록 하기 위하여, 프로젝트에 포함된 각 액티비티의 일정을 디데이를 기준으로 한 일정(예를 들어, 디데이, 디데이 몇 일 전 또는 디데이 몇 일 후)으로 정해 두고 통신 단말기 사용자가 프로젝트를 선택하면 디데이에 사용될 자신의 일정을 입력하도록 하고, 통신 단말기 사용자가 입력한 일정을 기준으로 프로젝트에 포함된 모든 액티비티들의 일정을 변경한 후 다운로드 되도록 하는 일정관리방법 및 그 장치를 제공한다.According to the present invention, a schedule of each activity included in a project can be downloaded so that a communication terminal user can download and utilize a project grouping activities related to each other through a service operator or a community according to his or her schedule. Set the schedule based on (for example, D-Day, D-Day before or D-Day), and when the communication terminal user selects a project, enter his or her schedule to be used on the D-Day. Provides schedule management method and device to download after changing schedule of all activities included in project based on schedule.

본 발명은, 통신 단말기 사용자가 서비스 운영자 또는 커뮤니티를 통해 각종 액티비티들을 다운로드받은 후, 다운로드받은 액티비티들 중 서로 연관 있는 액티비티를 선택하여 그룹화하고, 그룹화된 액티비티들의 기준이 되는 날짜를 디데이로 결정하면 디데이에 따라 그룹 내 각 액티비티들의 일정을 계산하여 프로젝트를 생성하고, 생성된 프로젝트를 일정에 따라 활용하도록 하는 일정관리방법 및 그 장치를 제공한다.According to an embodiment of the present invention, after a user of a communication terminal downloads various activities through a service operator or a community, the user selects and groups related activities among the downloaded activities, and determines the date of the grouped activities as a D-day. According to the present invention, a schedule management method and apparatus for calculating a schedule of activities in a group, generating a project, and utilizing the generated project according to a schedule are provided.

본 발명은, 통신 단말기 사용자가 이전에 직접 생성하여 사용한 프로젝트의 디데이를 자신의 일정에 따라 새롭게 결정하고, 새롭게 결정된 디데이에 따라 프로젝트 내 액티비티들의 일정을 재조정하여 활용하도록 하는 일정관리방법 및 그 장치를 제공한다.The present invention provides a schedule management method and apparatus for allowing a communication terminal user to newly determine a D-day of a project previously created and used according to his / her schedule, and to reschedule and use activities in the project according to the newly-determined D-day. to provide.

본 발명은, 계획된 일정의 실천이 잘 이루어지고 있는지의 여부를 확인하기 위하여 프로젝트 내 액티비티들의 실천 여부를 체크하도록 설정한 후, 각 액티비티들의 수행 비율을 계산하여 시각적으로 표시하도록 하는 일정관리방법 및 그 장치를 제공한다.The present invention is set to check whether the activities in the project in order to check whether the implementation of the planned schedule is well carried out, and then the schedule management method to calculate and display the performance ratio of each activity visually and its Provide a device.

본 발명은, 언제 시작해서 언제 종료할지를 날짜로 관리하는 할 일 프로그램, 어떤 날짜의 특정 시간에 어떤 일을 할지를 관리하는 일정 프로그램, 아직 일정을 정하지 못한 일을 관리하는 메모 프로그램을 하나의 프로그램으로 통합하여 관리하도록 하는 일정관리방법 및 그 장치를 제공한다.The present invention integrates a to-do program that manages when and when to start a date, a schedule program that manages what to do at a particular time of day, and a memo program that manages tasks not yet scheduled into one program. To provide a schedule management method and the device to manage.

본 발명은, 통신 단말기 사용자가 직접 생성하거나, 서비스 운영자 또는 커뮤니티를 통해 다운로드받은 서로 연관 있는 액티비티들을 그룹화한 프로젝트에 새로운 액티비티를 추가하거나, 기존 액티비티의 삭제 및 변경을 수행할 수 있도록 하는 일정관리방법 및 그 장치를 제공한다.The present invention provides a schedule management method that enables a user of a communication terminal to directly add a new activity to a project grouping related activities downloaded through a service operator or a community, or to delete or change an existing activity. And its apparatus.

본 발명의 일 실시예에 따른 일정관리방법은, (1) 통신 단말기는, 네트워크 통신망을 통해 일정관리에 사용할 개별 액티비티 또는 서로 연관 있는 액티비티들을 그룹화한 프로젝트를 관리하는 서버 컴퓨터로 통신 접속을 진행하고, 서버 운영자 측에서 생성하거나 다른 사용자들이 생성하여 등록한 액티비티 또는 프로젝트의 리스트 확인 및 검색을 수행하는 단계와, (2) 서버 컴퓨터는, (1) 단계를 통해 액티비티 또는 프로젝트의 리스트 확인 및 검색을 수행한 사용자의 특정 액티비티 또는 프로젝트의 다운로드 선택을 확인하고, 다운로드가 선택되면 해당 통신 단말기로 일정관리에 사용할 특정 액티비티 또는 프로젝트를 다운로드하는 단계와, (3) 통신 단말기는, 사용자의 조작을 확인하여 서버 컴퓨터로부터 다운로드받은 특정 프로젝트의 활용이 선택되는지를 판단하는 단계와, (4) (3) 단계의 판단결과 프로젝트의 활용이 선택되면, 통신 단말기는 사용자가 변경하여 입력하는 일정을 확인하고, 새롭게 결정된 일정을 토대로 서버 컴퓨터로부터 다운로드받은 프로젝트 내 각 액티비티의 일정을 자동으로 재조정하는 단계, 그리고 (5) 통신 단말기는, 일정관리도구를 통해 (4) 단계에서 일정이 재조정된 프로젝트 내 각 액티비티들을 해당 날짜에 저장하여 일정관리를 수행하는 단계를 포함할 수 있다.According to an embodiment of the present invention, a schedule management method includes: (1) a communication terminal performing a communication connection to a server computer managing a project grouping individual activities or related activities to be used for scheduling through a network communication network; Performing a check and retrieval of a list of activities or projects created or registered by the server operator or registered by other users; and (2) the server computer performs a check and retrieval of a list of activities or projects through step (1). Confirming the download selection of a specific activity or project of a user, and downloading the selected activity or project to be used for scheduling to the corresponding communication terminal, and (3) the communication terminal confirms the user's operation to the server. The use of a specific project downloaded from a computer (4) If the use of the project is selected as a result of the determination in step (4) and (3), the communication terminal checks the schedule that the user changes and inputs, and based on the newly determined schedule, the communication terminal checks in the project downloaded from the server computer. (B) automatically rescheduling each activity, and (5) the communication terminal stores the activities of the rescheduled project in the step (4) through the schedule management tool on the corresponding date to perform the schedule management. It may include.

그리고 본 발명의 일 실시예에 따른 일정관리방법은, (6) 서버 컴퓨터는, (1) 단계를 통해 액티비티 또는 프로젝트의 리스트 확인 및 검색을 수행한 사용자의 특정 프로젝트의 일정 재조정 및 다운로드 선택을 확인하고, 일정 재조정 및 다운로드가 선택되면 서버 운영자 측에서 생성하거나 다른 사용자들이 생성하여 커뮤니티에 등록한 프로젝트의 기존 일정을 자신의 일정에 따라 재조정하고, 일정이 재조정된 프로젝트를 해당 통신 단말기로 다운로드하는 단계, 그리고 (7) 통신 단말기는, 일정관리도구를 통해 (6) 단계에서 서버 컴퓨터로부터 일정을 재조정한 후 다운로드받은 프로젝트 내 각 액티비티들을 해당 날짜에 저장하여 일정관리를 수행하는 단계를 더 수행할 수 있다.In addition, the schedule management method according to an embodiment of the present invention, (6) the server computer, re-scheduling and download selection of the specific project of the user who performed the check and search of the activity or project list through step (1) If reschedule and download is selected, rescheduling the existing schedule of the project generated by the server operator or created by other users in the community according to their schedule, and downloading the rescheduled project to the corresponding communication terminal, (7) The communication terminal may further perform a step of performing schedule management by rescheduling the schedule from the server computer in step (6) through the schedule management tool and storing each downloaded activity in the project on the corresponding date. .

그리고 본 발명의 일 실시예에 따른 일정관리방법은, (5) 단계 이후, (8) 통신 단말기는, 계획된 일정의 실천 여부 확인을 위해 특정 프로젝트를 선택한 후 실천여부 확인기능이 작동되도록 설정하면, 일정관리도구를 통해 사용자의 조작을 확인하여 프로젝트 내 각 액티비티들의 실천 여부 체크를 확인하고, 실천 여부 체크 결과를 토대로 각 액티비티들의 수행 비율을 계산한 후, 수행 비율 결과를 화면상에 표시하는 단계를 더 수행할 수 있다.And the schedule management method according to an embodiment of the present invention, after the step (5), (8) the communication terminal, if the specific project is selected to confirm whether or not the practice of the planned schedule is set to enable the operation check function, Checking the user's operation through the schedule management tool to check the activity of each activity in the project, calculating the performance ratio of each activity based on the result of the activity check, and displaying the result of the performance ratio on the screen. You can do more.

그리고 본 발명의 일 실시예에 따른 일정관리방법은, (9) (3) 단계의 판단결과 서버 컴퓨터로부터 다운로드받은 특정 프로젝트의 활용이 아니면, 통신 단말기는 서버 컴퓨터로부터 다운로드받은 각 액티비티들 중 서로 연관 있는 액티비티들을 그룹화하여 프로젝트를 생성하는 것이 선택되는지를 판단하는 단계, 그리고 (10) (9) 단계의 판단결과 서로 연관 있는 액티비티들을 그룹화하여 프로젝트를 생성하는 것이 선택되면, 통신 단말기는 사용자의 조작을 확인하여 서버 컴퓨터로부터 다운로드받은 액티비티들 중 서로 연관 있는 액티비티를 그룹화한 후, 그룹화된 액티비티들의 기준이 되는 날짜가 결정되면 그룹 내 각 액티비티들의 일정을 계산하여 프로젝트를 생성하는 단계를 더 수행할 수 있다.The schedule management method according to an embodiment of the present invention, (9) (3) If the determination result of step (3) is not utilizing the specific project downloaded from the server computer, the communication terminal is associated with each other among the activities downloaded from the server computer Judging whether it is selected to create a project by grouping existing activities, and (10) (9), when selecting to generate a project by grouping activities related to each other, the communication terminal performs a user's operation. After checking and grouping activities related to each other among the activities downloaded from the server computer, if the base date of the grouped activities is determined, the step of calculating the schedule of each activity in the group may be further performed. .

본 발명의 다른 실시예에 따른 일정관리방법은, (a) 통신 단말기는, 사용자의 조작을 확인하여 해당 사용자가 이전에 사용한 프로젝트 중 어느 하나의 프로젝트의 활용이 선택되는지를 판단하는 단계와, (b) 판단결과 이전에 사용한 프로젝트 중 어느 하나의 프로젝트의 활용이 선택되면, 통신 단말기는 사용자가 변경하여 입력하는 일정을 확인하고, 새롭게 결정된 일정을 토대로 프로젝트 내 각 액티비티의 일정을 자동으로 재조정하는 단계, 그리고 (c) 통신 단말기는, 일정관리도구를 통해 (b) 단계에서 일정이 재조정된 프로젝트 내 각 액티비티들을 해당 날짜에 저장하여 일정관리를 수행하는 단계를 포함할 수 있다.According to another aspect of the present invention, a method for managing a schedule may include: (a) determining, by a communication terminal, a user's operation to determine which one of the projects previously used by the user is selected; b) If the determination result shows that the utilization of any one of the previously used projects is selected, the communication terminal checks the schedule inputted by the user and automatically reschedules each activity in the project based on the newly determined schedule. And, (c) the communication terminal, through the schedule management tool may include the step of performing the schedule management by storing each activity in the project rescheduled in step (b) on the corresponding date.

또한, 본 발명의 일 실시예에 따른 일정관리장치는, 불특정 다수의 통신회선을 연결하여 상호간에 일정관리에 관련된 데이터 통신이 이루어지도록 하는 네트워크 통신망과, 네트워크 통신망을 통해 통신 접속된 서버 컴퓨터와 일정관리에 사용할 액티비티 또는 프로젝트의 리스트 확인, 검색을 수행하고, 사용자의 다운로드 선택에 따라 서버 컴퓨터로부터 특정 액티비티 또는 프로젝트를 다운로드받은 이후, 다운로드받은 프로젝트의 사용자가 입력하는 새롭게 결정된 일정을 토대로 서버 컴퓨터로부터 다운로드받은 프로젝트 내 각 액티비티의 일정을 자동으로 재조정하거나, 또는 사용자의 서버 컴퓨터의 커뮤니티에 등록되어 있는 특정 프로젝트의 일정 재조정 후 다운로드 선택에 따라 서버 운영자 또는 타 사용자들이 등록한 서로 관련 있는 액티비티들을 그룹화한 프로젝트의 기존 일정을 자신의 일정에 따라 재조정한 이후, 일정이 재조정된 프로젝트를 서버 컴퓨터로부터 다운로드받으며, 일정관리도구를 통해 일정이 재조정된 프로젝트 내 각 액티비티들을 해당 날짜에 저장하거나 또는 일정을 재조정한 후 다운로드받은 프로젝트 내 각 액티비티들을 해당 날짜에 저장하여 일정관리를 수행하는 통신 단말기, 그리고 서버 컴퓨터 운영자 측에서 생성하거나 또는 다른 사용자들이 생성하여 등록한 일정관리에 사용하는 개별 액티비티 또는 서로 연관 있는 액티비티들을 그룹화한 프로젝트를 저장하고 있으며, 네트워크 통신망을 통해 통신 접속된 통신 단말기의 요청에 따라 개별 액티비티 또는 서로 연관 있는 액티비티들을 그룹화한 프로젝트의 다운로드를 처리하거나, 또는 서버 운영자 또는 타 사용자들이 생성하여 등록한 특정 프로젝트 내 각 액티비티의 기존 일정을 사용자 자신의 일정에 따라 재조정한 후 일정이 재조정된 프로젝트를 해당 통신 단말기로 다운로드하는 서버 컴퓨터를 포함할 수 있다.In addition, the schedule management apparatus according to an embodiment of the present invention, the network communication network to connect the unspecified multiple communication lines to each other to perform data communication related to schedule management, and the schedule schedule and the server computer connected through the network communication network Check and search the list of activities or projects to be used for management, and download specific activities or projects from the server computer according to the user's download selection, and then download them from the server computer based on the newly determined schedule entered by the user of the downloaded project. Automatically reschedule each activity in a received project, or related activities registered by a server administrator or other users, depending on the download selection after rescheduling a specific project registered in the community of the user's server computer. After rescheduling the existing schedule of the projects that grouped the activities to their own schedule, the rescheduled project is downloaded from the server computer, and each activity in the rescheduled project is saved on the date using the calendar tool, or After rescheduling, each downloaded activity in the downloaded project is saved on the relevant date, and the communication terminal performs the scheduling, and the individual activities or related activities that are created by the server computer operator or used by other users for scheduling. It stores the project grouping the existing activities, and handles the download of the project grouping the individual activities or related activities at the request of the communication terminal connected through the network network, or the server operator or Other users can create a remediation an existing schedule of activities within each specific project registered according to the user's own schedule, and then include the server computer to download the event is re-project into the communication terminal.

그리고 본 발명의 일 실시예에 따른 일정관리장치의 통신 단말기는, 계획된 일정의 실천 여부 확인을 위해 특정 프로젝트를 선택한 후 실천여부 확인기능이 작동되도록 설정하면, 일정관리도구를 통해 일정관리를 수행중인 프로젝트 내 각 액티비티들의 실천 여부 체크를 확인하고, 실천 여부 체크 결과를 토대로 각 액티비티들의 수행 비율을 계산하며, 계산된 수행 비율 결과를 문자나 그림으로 변환하여 화면상에 표시하는 기능을 더 수행하도록 구성할 수 있다.And the communication terminal of the schedule management device according to an embodiment of the present invention, if you select a specific project to confirm whether the planned schedule is carried out, if the set whether to check whether the operation is performed, the schedule management tool is performing the schedule management Check the activity check of each activity in the project, calculate the execution rate of each activity based on the check result of the action, and convert the calculated execution rate result into text or picture to perform the function of displaying on the screen. can do.

그리고 본 발명의 일 실시예에 따른 일정관리장치의 통신 단말기는, 사용자의 조작에 따라 서버 컴퓨터로부터 다운로드받은 각 액티비티들 중 서로 연관 있는 액티비티들을 그룹화하여 프로젝트를 생성하는 것이 선택되면, 서버 컴퓨터로부터 다운로드받은 액티비티들 중 서로 연관 있는 액티비티를 그룹화한 후, 그룹화된 액티비티들의 기준이 되는 날짜가 결정되면 그룹 내 각 액티비티들의 일정을 계산하여 프로젝트를 생성하며, 일정관리도구를 통해 프로젝트 내 각 액티비티들을 해당 날짜에 저장하여 일정관리를 수행하는 기능을 더 수행하도록 구성할 수 있다.If the communication terminal of the schedule management apparatus according to the embodiment of the present invention is selected to group a related activity among each of the activities downloaded from the server computer according to a user's operation, and generate a project, the communication terminal downloads from the server computer. After grouping the activities related to each other among the received activities, if the date that is the basis of the grouped activities is determined, the project is created by calculating the schedule of each activity in the group, and the schedule management tool displays the activities in the project. It can be configured to perform more functions to save schedules.

또한, 본 발명의 다른 실시예에 따른 일정관리장치는, 사용자의 조작에 따라 해당 사용자가 이전에 사용한 프로젝트 중 어느 하나의 프로젝트의 활용이 선택되면, 사용자가 변경하여 입력하는 일정을 확인한 후 새롭게 결정된 일정을 토대로 프로젝트 내 각 액티비티의 일정을 자동으로 재조정하며, 일정관리도구를 통해 일정이 재조정된 프로젝트 내 각 액티비티들을 해당 날짜에 저장하여 일정관리를 수행하도록 구성할 수 있다.In addition, the schedule management apparatus according to another embodiment of the present invention, if the utilization of any one of the project previously used by the user according to the user's operation is selected, after the user checks the schedule to change and input newly determined Based on the schedule, each activity in the project is automatically rescheduled, and the schedule management tool can be configured to save each activity in the rescheduled project on the date and perform the schedule management.

이상에서와 같이 본 발명의 일정관리방법 및 그 장치에 따르면, 통신 단말기 사용자가 직접 생성하거나, 서비스 운영자 또는 커뮤니티를 통해 다운로드받은 서로 연관 있는 액티비티들을 그룹화한 프로젝트를 자신의 새로운 일정이나 특별한 목적에 따라 재조정하여 활용할 수 있고, 통신 단말기 사용자가 서비스 운영자 또는 커뮤니티를 통해 각종 액티비티들을 다운로드받은 후 서로 연관 있는 액티비티를 그룹화시켜 프로젝트를 생성하고 이를 일정관리에 사용할 수 있으며, 통신 단말기 사용자가 서비스 운영자 또는 커뮤니티를 통해 서로 관련 있는 액티비티들을 그룹화한 프로젝트의 기존 일정을 자신의 일정에 따라 재조정한 후 다운로드받아 활용할 수 있기 때문에 각 사용자들이 손쉽게 일정을 조정하여 관리할 수 있는 효과가 있다.As described above, according to the schedule management method and apparatus of the present invention, according to a new schedule or a special purpose of a project grouping the activities that are created by the user of the communication terminal directly, or downloaded through the service operator or community After the communication terminal user downloads various activities through the service operator or community, the related activities can be grouped together to create a project and use it for scheduling. Through this, users can easily adjust and manage the schedule because the existing schedule of the project grouping related activities can be readjusted and downloaded and used according to their own schedule.

또한, 계획된 일정을 얼마나 잘 실천하고 있는지를 시각적으로 확인할 수 있으며, 종래에 개별적으로 사용하였던 메모, 할 일 및 일정을 하나의 프로그램에서 통합하여 관리하기 때문에 일정관리의 효율을 높일 수 있는 효과가 있다.In addition, it is possible to visually check how well the planned schedule is being practiced, and it is effective to increase the efficiency of schedule management because it integrates and manages memos, tasks and schedules that have been used individually in the past in one program. .

도 1은 본 발명의 일 실시예에 따른 일정관리장치의 구성을 개략적으로 나타낸 블록도,
도 2는 도 1의 통신 단말기의 구성을 보다 상세하게 나타낸 블록도,
도 3은 도 1의 서버 컴퓨터의 구성을 상세하게 나타낸 블록도,
도 4는 본 발명의 일 실시예에 따른 일정관리방법의 동작과정을 상세하게 나타낸 순서도,
도 5 내지 도 8은 도 4의 각 서브루틴의 동작과정을 보다 상세하게 나타낸 순서도,
도 9는 본 발명의 다른 실시예에 따른 일정관리방법의 동작과정을 상세하게 나타낸 순서도이다.
1 is a block diagram schematically showing the configuration of a schedule management apparatus according to an embodiment of the present invention;
2 is a block diagram showing the configuration of the communication terminal of FIG. 1 in more detail;
3 is a block diagram showing in detail the configuration of the server computer of FIG.
4 is a flow chart showing in detail the operation of the schedule management method according to an embodiment of the present invention;
5 to 8 are flowcharts showing in more detail the operation of each subroutine of FIG.
9 is a flowchart showing in detail the operation of the schedule management method according to another embodiment of the present invention.

이하, 첨부된 도면을 참조하여 본 발명의 일정관리방법 및 그 장치를 상세하게 설명한다.Hereinafter, with reference to the accompanying drawings will be described in detail the schedule management method and apparatus thereof.

도 1은 본 발명의 일 실시예에 따른 일정관리장치의 구성을 개략적으로 나타낸 블록도이다.1 is a block diagram schematically showing the configuration of a schedule management apparatus according to an embodiment of the present invention.

도시된 바와 같이 본 발명의 일정관리장치는, 네트워크 통신망(100), 통신 단말기(200), 서버 컴퓨터(300) 등으로 구성된다.As shown, the schedule management apparatus of the present invention includes a network communication network 100, a communication terminal 200, a server computer 300, and the like.

네트워크 통신망(100)은 유/무선 인터넷 등의 통신망으로서, 통신 단말기(200)와 서버 컴퓨터(300) 사이의 통신회선을 연결하여 상호간에 일정관리에 관련된 데이터 통신이 이루어지도록 한다.The network communication network 100 is a communication network such as a wired / wireless internet, and connects a communication line between the communication terminal 200 and the server computer 300 so that data communication related to schedule management is performed.

통신 단말기(200)는 휴대전화, 스마트폰, 노트북, 넷북, 태블릿 PC 등의 유/무선 인터넷 사용이 가능한 단말기로서, 사용자의 조작에 따라 네트워크 통신망(100)을 통해 서버 컴퓨터(300)와 통신 접속을 진행(예를 들어, 스마트폰에 설치된 어플리케이션 접속이나, 웹 접속 등)하며, 통신 접속된 서버 컴퓨터(300)와 일정관리에 사용할 액티비티 또는 프로젝트의 리스트 확인 및 검색을 수행한다. 그리고 사용자의 다운로드 선택에 따라 서버 컴퓨터(300)로부터 일정관리에 사용할 특정 액티비티 또는 프로젝트를 다운로드받은 이후, 다운로드받은 프로젝트의 사용자가 입력하는 새롭게 결정된 일정을 토대로 서버 컴퓨터(300)로부터 다운로드받은 프로젝트 내 각 액티비티의 일정을 자동으로 재조정하거나, 또는 사용자의 서버 컴퓨터(300)의 커뮤니티에 등록되어 있는 특정 프로젝트의 일정 재조정 후 다운로드 선택에 따라 서버 운영자 또는 타 사용자들이 등록한 서로 관련 있는 액티비티들을 그룹화한 프로젝트의 기존 일정을 자신의 일정에 따라 재조정한 이후, 일정이 재조정된 프로젝트를 서버 컴퓨터(300)로부터 다운로드받는다. 그리고 일정관리도구를 통해 일정이 재조정된 프로젝트 내 각 액티비티들을 해당 날짜에 저장하거나 또는 일정을 재조정한 후 다운로드받은 프로젝트 내 각 액티비티들을 해당 날짜에 저장하여 일정관리를 수행한다.The communication terminal 200 is a terminal capable of using a wired / wireless internet such as a mobile phone, a smartphone, a laptop, a netbook, a tablet PC, and the like, and communicates with the server computer 300 through the network communication network 100 according to a user's operation. Proceed with (for example, access to the application installed on the smartphone, web access, etc.), and checks and searches the list of activities or projects to be used for schedule management and server computer 300 is connected to the communication. After downloading a specific activity or project to be used for scheduling from the server computer 300 according to the user's download selection, each project in the project downloaded from the server computer 300 based on a newly determined schedule input by the user of the downloaded project. Automatically reschedule an activity, or reschedule a specific project registered in the community of the user's server computer 300, and then re-select the existing activity of the group of related activities registered by the server administrator or other users according to the download selection. After rescheduling the schedule according to its own schedule, the rescheduled project is downloaded from the server computer 300. In addition, the schedule management tool saves each activity in the rescheduled project on the corresponding date, or reschedules and saves the downloaded activities in the corresponding date.

또한, 통신 단말기(200)는 계획된 일정의 실천 여부 확인을 위해 특정 프로젝트를 선택한 후 실천여부 확인기능이 작동되도록 설정하면, 일정관리도구를 통해 일정관리를 수행중인 프로젝트 내 각 액티비티들의 실천 여부 체크를 확인하고, 실천 여부 체크 결과를 토대로 각 액티비티들의 수행 비율을 계산하며, 계산된 수행 비율 결과를 문자(예를 들어, 숫자, 기호 등)나 그림(예를 들어, 표, 도형 등)으로 변환하여 화면상에 표시하는 기능을 더 수행할 수 있다.In addition, when the communication terminal 200 selects a specific project to confirm whether or not the scheduled schedule is implemented, and checks whether or not to execute the check function, the communication terminal 200 checks whether or not the activities of each activity in the project are being executed through the schedule management tool. Check the performance, calculate the performance rate of each activity, and convert the calculated performance rate result to a character (for example, a number, a symbol, etc.) or a picture (for example, a table, a figure, etc.) You can further perform the function to display on the screen.

또한, 통신 단말기(200)는 사용자의 조작에 따라 서버 컴퓨터(300)로부터 다운로드받은 각 액티비티들 중 서로 연관 있는 액티비티들을 그룹화하여 프로젝트를 생성하는 것이 선택되면, 서버 컴퓨터(300)로부터 다운로드받은 액티비티들 중 서로 연관 있는 액티비티를 그룹화한 후, 그룹화된 액티비티들의 기준이 되는 날짜가 결정되면 그룹 내 각 액티비티들의 일정을 계산하여 프로젝트를 생성하며, 일정관리도구를 통해 프로젝트 내 각 액티비티들을 해당 날짜에 저장하여 일정관리를 수행하는 기능을 더 수행할 수 있다.In addition, when the communication terminal 200 selects to generate a project by grouping related activities among the activities downloaded from the server computer 300 according to a user's operation, the activities downloaded from the server computer 300. After grouping activities related to each other, and when the base date of the grouped activities is determined, the project is created by calculating the schedule of each activity in the group, and each activity in the project is saved on the corresponding date by the schedule management tool. Can perform the function to perform the schedule management.

서버 컴퓨터(300)는 서버 운영자 측에서 직접 생성하거나 또는 다른 사용자들이 생성하여 등록한 일정관리에 사용하는 개별 액티비티 또는 서로 연관 있는 액티비티들을 그룹화한 프로젝트를 저장(예를 들어, 게시판 형식으로 관리, 저장)하고 있으며, 네트워크 통신망(100)을 통해 통신 접속된 통신 단말기(200)의 요청에 따라 개별 액티비티 또는 서로 연관 있는 액티비티들을 그룹화한 프로젝트의 다운로드를 처리하거나, 또는 서버 운영자 또는 타 사용자들이 생성하여 등록한 특정 프로젝트 내 각 액티비티의 기존 일정을 사용자 자신의 일정에 따라 재조정한 후 일정이 재조정된 프로젝트를 해당 통신 단말기(200)로 다운로드한다.The server computer 300 stores an individual activity or a project grouping activities related to each other, which are directly generated by the server operator or used for a schedule created and registered by other users (for example, in a bulletin board format). In response to a request of the communication terminal 200 connected through the network communication network 100, a specific activity or a download of a project grouping activities related to each other is processed, or a server operator or another user creates and registers a specific project. After rescheduling an existing schedule of each activity in the project according to the user's own schedule, the rescheduled project is downloaded to the corresponding communication terminal 200.

이때 서버 컴퓨터(300)에 등록된 액티비티는 구체적인 날짜 또는 어떤 날짜의 구체적인 시간에 어떠한 일을 수행할 것인지가 결정된 이벤트 정보이며, 프로젝트는 서로 관련 있는 액티비티들을 그룹화한 것이다.In this case, the activity registered in the server computer 300 is event information that determines what to perform on a specific date or a specific time of a certain date, and the project is a grouping of activities related to each other.

또한, 서버 컴퓨터(300)는 서버 운영자 측에서 생성하거나 다른 사용자들이 생성하여 등록한 각각의 프로젝트별로 커뮤니티를 구성하는 기능을 더 수행할 수 있다. 이 경우 각 통신 단말기(200) 사용자들은 각 프로젝트별 커뮤니티를 통해 상호간에 추가적인 일정이나 정보를 주고받을 수 있고, 서버 컴퓨터(300)는 통신 단말기(200)로부터 프로젝트를 다운로드 받을 때 해당 프로젝트의 커뮤니티에 자동으로 가입하는 것에 대한 동의를 받고, 자동가입에 대한 동의를 수행한 해당 통신 단말기(200)로 프로젝트를 다운로드할 때 반대 의사표시를 하지 않으면 프로젝트의 커뮤니티에 가입되도록 처리한다. 즉 서버 컴퓨터(300)는 일정관리도구를 통해 SNS(Social Network Service)를 구성하고, 동일한 프로젝트를 공유하는 사람별로 손쉽게 커뮤니티를 구성하기 위해 프로젝트를 다운로드받는 행위를 커뮤니티에 가입하는 행위로 만드는 것이다.In addition, the server computer 300 may further perform a function of configuring a community for each project generated by the server operator or registered by other users. In this case, users of each communication terminal 200 may exchange additional schedules or information with each other through the community for each project, and the server computer 300 may download the project from the communication terminal 200 to the community of the corresponding project. When receiving the consent to automatically join, and download the project to the corresponding communication terminal 200 that has performed the agreement for automatic subscription, if not expressed intention to process the process to join the community of the project. In other words, the server computer 300 configures an SNS (Social Network Service) through a schedule management tool, and makes the act of joining a community to download a project in order to easily form a community for each person who shares the same project.

한편, 서버 컴퓨터(300)로부터 일정관리에 사용할 액티비티 또는 프로젝트를 다운로드받는 방식이나 서버 컴퓨터(300)의 커뮤니티에 등록된 프로젝트의 일정을 재조정한 후 다운로드받는 방식의 상술한 실시예와는 달리, 통신 단말기(200)는 사용자가 이전에 사용하였던 프로젝트 중 어느 하나의 프로젝트를 활용하여 일정관리를 수행할 수도 있다. 이 경우 통신 단말기(200)는 사용자가 변경하여 입력하는 일정을 확인한 후, 새롭게 결정된 일정을 토대로 프로젝트 내 각 액티비티의 일정을 자동으로 재조정하며, 일정관리도구를 통해 일정이 재조정된 프로젝트 내 각 액티비티들을 해당 날짜에 저장하여 일정관리를 수행하게 된다.On the other hand, unlike the above-described embodiment of the method of downloading the activity or project to be used for schedule management from the server computer 300 or the method of downloading after rescheduling the schedule registered in the community of the server computer 300, communication The terminal 200 may perform a schedule management by using any one project among the projects previously used by the user. In this case, the communication terminal 200 checks the schedule inputted by the user, and automatically reschedules each activity in the project based on the newly determined schedule, and schedules each activity in the rescheduled project through the schedule management tool. The schedule will be saved by saving on the date.

도 2는 상술한 도 1의 통신 단말기(200)의 구성을 보다 상세하게 나타낸 블록도이다.FIG. 2 is a block diagram illustrating in detail the configuration of the communication terminal 200 of FIG. 1.

도시된 바와 같이 통신 단말기(200)는, 데이터 통신부(210), 프로젝트 관리부(220), 액티비티 관리부(230), 일정관리부(240), 저장부(250), 일정수행 확인부(260), 제어부(270) 등으로 구성된다.As illustrated, the communication terminal 200 includes a data communication unit 210, a project management unit 220, an activity management unit 230, a schedule management unit 240, a storage unit 250, a schedule performance checking unit 260, and a control unit. 270 and the like.

데이터 통신부(210)는 네트워크 통신망(100)을 통해 통신 접속된 서버 컴퓨터(300)와 일정관리에 사용할 액티비티 또는 프로젝트의 리스트 확인 및 검색, 서버 운영자 또는 타 사용자들이 등록한 특정 액티비티 또는 서로 관련 있는 액티비티들을 그룹화한 프로젝트의 다운로드, 서버 컴퓨터(300)에서 사용자가 직접 일정을 재조정한 특정 프로젝트의 다운로드와 관련된 데이터 송수신을 처리한다.The data communication unit 210 checks and retrieves a list of activities or projects to be used for scheduling and server server 300 connected through the network communication network 100, specific activities registered by a server operator or other users, or related activities. Downloading and grouping of projects, the server computer 300 processes data transmission and reception associated with the download of a specific project that the user has rescheduled.

프로젝트 관리부(220)는 사용자의 조작에 따라 서버 컴퓨터(300)로부터 다운로드받은 특정 프로젝트의 활용이 선택되는지를 판단하고, 서버 컴퓨터(300)로부터 다운로드받은 특정 프로젝트의 활용을 선택한 사용자의 조작에 따라 해당 프로젝트의 새로운 일정이 결정되면, 새롭게 결정된 일정을 토대로 서버 컴퓨터(300)로부터 다운로드받은 프로젝트 내 각 액티비티의 일정을 자동으로 재조정한다.The project manager 220 determines whether the utilization of the specific project downloaded from the server computer 300 is selected according to the user's operation, and the corresponding project management unit 220 selects the utilization of the specific project downloaded from the server computer 300. When a new schedule of the project is determined, the schedule of each activity in the project downloaded from the server computer 300 is automatically rescheduled based on the newly determined schedule.

이때 프로젝트 관리부(220)는 사용자의 조작을 확인하여 서버 컴퓨터(300)로부터 다운로드받은 프로젝트의 일정 재조정이 선택되면, 해당 프로젝트 내 각 액티비티의 일정 중 가장 빠른 일자 및/또는 가장 늦은 일자를 화면상에 표시하며, 가장 빠른 일자 또는 가장 늦은 일자 중 하나가 선택된 후 사용자 자신의 일정으로 변경하면 프로젝트 내 각 액티비티들의 일정과 사용자가 변경하기 전의 일정과의 간격을 계산한 후 변경된 사용자 자신의 일정을 토대로 동일 간격이 되도록 자동으로 재조정할 수 있다.At this time, the project management unit 220 confirms the user's operation and if the reschedule of the project downloaded from the server computer 300 is selected, the earliest date and / or latest date of the schedule of each activity in the project is displayed on the screen. If you change to your own schedule after one of the earliest or latest dates is selected, the schedule is calculated based on the schedule of each activity in the project and the schedule of the user before the change. The interval can be adjusted automatically.

또한, 프로젝트 관리부(220)는 사용자의 조작을 확인하여 서버 컴퓨터(300)로부터 다운로드받은 프로젝트의 일정 재조정이 선택되면, 서버 컴퓨터(300)로부터 다운로드받은 프로젝트 내 각 액티비티 중 어느 하나의 액티비티가 선택되는지를 판단하며, 프로젝트 내 각 액티비티 중 어느 하나의 액티비티가 선택되면 사용자가 선택한 특정 액티비티의 일정을 자신의 일정으로 변경하는지를 확인한 후 사용자 자신의 일정으로 변경된 액티비티 이후의 모든 액티비티의 일정을 변경된 일정을 토대로 동일 간격이 되도록 재조정할 수도 있다.In addition, the project management unit 220 confirms the user's operation and if the rescheduling of the project downloaded from the server computer 300 is selected, which one of the activities in the project downloaded from the server computer 300 is selected. When one of the activities in the project is selected, it checks whether the schedule of the specific activity selected by the user is changed to his own schedule, and then based on the changed schedule of all the activities after the changed activity to the user's own schedule. It can also be readjusted to be equally spaced.

또한, 프로젝트 관리부(220)는 사용자의 조작을 확인하여 서버 컴퓨터(300)로부터 다운로드받은 프로젝트의 일정 재조정이 선택되면, 서버 컴퓨터(300)로부터 다운로드받은 프로젝트의 디데이로 사용될 자신의 일정이 입력되는지를 판단하며, 디데이로 사용될 자신의 일정이 입력되면 프로젝트 내 각 액티비티의 일정을 사용자가 입력한 디데이를 기준으로 한 일정으로 변경할 수도 있다.In addition, the project management unit 220 checks the user's operation and if the rescheduling of the project downloaded from the server computer 300 is selected, it is determined whether the own schedule to be used as the D-day of the project downloaded from the server computer 300 is input. If the user's schedule to be used as a D-day is input, the schedule of each activity in the project can be changed to a schedule based on the D-day input by the user.

또한, 프로젝트 관리부(220)는 사용자의 입력조작에 의해 새롭게 결정된 디데이를 기준으로 각 액티비티의 구체적 수행날짜를 자동으로 재조정할 때, 각 액티비티별로 재조정된 구체적인 일정을 사용자가 직접 변경할 수도 있다.In addition, when the project manager 220 automatically readjusts the specific execution date of each activity based on the D-day newly determined by the user's input operation, the project manager 220 may directly change the specific schedule readjusted for each activity.

또한, 프로젝트 관리부(220)는 서버 컴퓨터(300)로부터 다운로드받은 프로젝트 내 각 액티비티의 일정 재조정을 수행하기 이전에, 사용자의 조작에 따라 서버 컴퓨터(300)로부터 다운로드받은 프로젝트에 새로운 액티비티의 추가, 기존 액티비티의 삭제 또는 변경이 수행되면, 해당 프로젝트에 새로운 액티비티의 추가, 기존 액티비티의 삭제 또는 변경을 처리하는 기능을 더 수행할 수 있다.In addition, the project management unit 220 adds new activities to the project downloaded from the server computer 300 according to the user's operation, before rescheduling each activity in the project downloaded from the server computer 300. When an activity is deleted or changed, you can further perform the functions of adding new activities to the project, deleting or changing existing activities.

한편, 프로젝트 관리부(220)는 상술한 바와 같이 서버 컴퓨터(300)로부터 다운로드받은 특정 프로젝트의 일정을 조정하여 활용하는 방식 이외에, 사용자가 서버 컴퓨터(300)의 커뮤니티에서 직접 일정을 재조정한 후 다운로드받는 방식을 사용할 수도 있다(이에 대한 상세 동작은 후술되는 도 3에서 설명한다). 즉 서버 컴퓨터(300)에 통신 접속된 사용자의 조작에 따라 서버 운영자 또는 타 사용자들이 등록한 서로 관련 있는 액티비티들을 그룹화한 프로젝트의 기존 일정을 자신의 일정에 따라 재조정한 이후, 일정이 재조정된 프로젝트를 서버 컴퓨터(300)로부터 다운로드받는다.On the other hand, the project management unit 220, in addition to the method of adjusting and utilizing the schedule of the specific project downloaded from the server computer 300 as described above, the user can download after rescheduling the schedule directly from the community of the server computer 300 Method may be used (the detailed operation thereof will be described with reference to FIG. 3). That is, after re-adjusting the existing schedule of the project grouping related activities registered by the server operator or other users according to the user's schedule according to the user's operation connected to the server computer 300, the server is rescheduled. Download from computer 300.

액티비티 관리부(230)는 사용자의 조작에 따라 서버 컴퓨터(300)로부터 다운로드받은 개별 액티비티를 서로 연관 있는 액티비티로 그룹화하여 프로젝트를 생성하는 것이 선택되는지를 판단하고, 액티비티의 그룹화를 통한 프로젝트의 생성이 선택되면 사용자의 조작에 따라 각 액티비티들 중 서로 연관 있는 액티비티를 그룹화하고, 사용자에 의해 그룹화된 액티비티들의 기준이 되는 날짜가 결정되어 입력되면 해당 날짜에 따라 그룹 내 각 액티비티들의 일정을 계산하며, 일정이 계산된 각 액티비티들을 토대로 프로젝트를 생성한다.The activity management unit 230 determines whether to generate a project by grouping individual activities downloaded from the server computer 300 into related activities according to a user's operation, and selecting whether to generate a project through grouping activities. If the user's operation grouped the activities related to each other among the activities, and if the base date of the activities grouped by the user is determined and inputted, the schedule of each activity in the group is calculated according to the date. Create a project based on each calculated activity.

일정관리부(240)는 프로젝트 관리부(220)에서 재조정된 프로젝트 내 각 액티비티들을 해당 날짜에 저장하여 일정관리를 수행하거나 또는 서버 컴퓨터(300)의 커뮤니티에 등록된 특정 프로젝트의 일정을 재조정한 이후 다운로드받은 특정 프로젝트 내 각 액티비티들을 해당 날짜에 저장하여 일정관리를 수행한다. 그리고 액티비티 관리부(230)에서 생성된 프로젝트 내 각 액티비티들을 해당 날짜에 저장하여 일정관리를 수행하며, 특정 프로젝트를 선택한 후 실천여부 확인기능이 작동되도록 설정할 수 있다.The scheduler 240 stores the activities in the rescheduled project in the project manager 220 on the corresponding date to perform the schedule management or downloads after rescheduling a specific project registered in the community of the server computer 300. Schedule activities by storing each activity in a specific project on that date. In addition, each activity in the project generated by the activity management unit 230 may be stored in a corresponding date to perform a schedule management. After selecting a specific project, a check function may be set to operate.

저장부(250)는 서버 컴퓨터(300)로부터 다운로드받은 개별 액티비티 및 프로젝트를 저장하고 있고, 서버 컴퓨터(300)에서 사용자가 직접 일정을 재조정한 후 다운로드받은 특정 프로젝트를 저장하고 있으며, 프로젝트 관리부(220)에서 일정이 재조정된 프로젝트와 액티비티 관리부(230)에서 생성된 서로 연관 있는 액티비티들을 그룹화한 프로젝트를 저장한다.The storage unit 250 stores individual activities and projects downloaded from the server computer 300, and stores a specific project downloaded after the user directly reschedules the schedule in the server computer 300, and the project manager 220 In step), the rescheduled project and the project grouping related activities generated by the activity management unit 230 are stored.

일정수행 확인부(260)는 일정관리부(240)의 제어에 따라 실천여부 확인기능이 작동되도록 설정된 프로젝트를 대상으로 프로젝트 내 각 액티비티들의 일정을 수행하는 사용자들로부터 실천 여부가 체크되는지를 확인하고, 사용자의 실천 여부 체크 결과를 토대로 각 액티비티들이 정상적으로 수행되었는지를 알기 위한 수행 비율을 계산하며, 계산된 수행 비율 결과를 사용자가 시각적으로 인식할 수 있는 수단(예를 들어, 숫자나 기호를 포함한 문자, 표와 도형을 포함한 그림 등)으로 변환하여 화면상에 표시한다.The schedule execution checker 260 checks whether the practice is checked from the users who perform the schedule of each activity in the project for the project in which the practice check function is set to operate under the control of the schedule manager 240, Based on the result of the user's check of performance, the performance rate is calculated to know whether each activity has been performed normally, and the means by which the user can visually recognize the calculated performance rate result (for example, a character including a number or a symbol, The image is converted into a table including figures and figures) and displayed on the screen.

제어부(270)는 네트워크 통신망(100)을 통해 통신 접속된 서버 컴퓨터(300)와의 일정관리에 사용할 액티비티 또는 프로젝트의 리스트 확인 및 검색, 특정 액티비티 또는 서로 관련 있는 액티비티들을 그룹화한 프로젝트의 다운로드, 서버 컴퓨터(300)에서 사용자가 직접 일정을 재조정한 특정 프로젝트의 다운로드를 제어한다. 그리고 사용자의 선택을 토대로 서버 컴퓨터(300)로부터 다운로드받은 특정 프로젝트의 활용 또는 서버 컴퓨터(300)의 커뮤니티를 통한 특정 프로젝트의 일정 재조정 및 다운로드, 서버 컴퓨터(300)로부터 다운로드받은 액티비티를 그룹화하는 프로젝트 생성을 제어한다. 그리고 프로젝트 관리부(220)에서 일정이 재조정된 프로젝트 내의 각 액티비티 또는 서버 컴퓨터(300)의 커뮤니티에 등록된 특정 프로젝트의 일정을 재조정한 이후 다운로드받은 특정 프로젝트 내의 각 액티비티, 액티비티 관리부(230)에서 생성된 서로 연관 있는 액티비티들을 그룹화한 프로젝트 내의 각 액티비티에 대한 일정관리부(240)에서의 일정관리 수행을 제어한다.The control unit 270 checks and retrieves a list of activities or projects to be used for schedule management with the server computer 300 connected through the network communication network 100, downloading a project grouping specific activities or related activities, and the server computer. In 300, the user controls the download of a specific project that has been rescheduled. Based on the user's selection, utilization of a specific project downloaded from the server computer 300 or rescheduling and downloading of a specific project through the community of the server computer 300 and generating a project grouping activities downloaded from the server computer 300. To control. Then, after rescheduling a specific project registered in each activity or a project registered in the community of the server computer 300 in the rescheduled project by the project management unit 220, each activity in the downloaded specific project, the activity management unit 230 generated Controls the schedule management in the scheduler 240 for each activity in the project grouping activities related to each other.

도 3은 상술한 도 1의 서버 컴퓨터(300)의 구성을 보다 상세하게 나타낸 블록도이다.3 is a block diagram illustrating the configuration of the server computer 300 of FIG. 1 described above in more detail.

도시된 바와 같이 서버 컴퓨터(300)는, 통신부(310), 커뮤니티 관리부(320), 프로젝트 재조정부(330), 다운로드 처리부(340), 데이터베이스(350), 제어부(360) 등으로 구성된다.As illustrated, the server computer 300 includes a communication unit 310, a community management unit 320, a project readjustment unit 330, a download processing unit 340, a database 350, a control unit 360, and the like.

통신부(310)는 네트워크 통신망(100)을 통해 통신 접속된 통신 단말기(200)와 일정관리에 사용할 액티비티 또는 프로젝트의 리스트 확인 및 검색, 서버 운영자 또는 타 사용자들이 등록한 특정 액티비티 또는 서로 관련 있는 액티비티들을 그룹화한 프로젝트의 다운로드, 서버 컴퓨터(300)에서 사용자가 직접 일정을 재조정한 특정 프로젝트의 다운로드와 관련된 데이터 송수신을 처리한다. 그리고 서버 컴퓨터(300)에 일정관리에 사용하는 액티비티 또는 프로젝트를 등록하기 위한 타 통신 단말기 사용자들의 통신 접속 및 데이터 업로드를 처리한다.The communication unit 310 checks and retrieves a list of activities or projects to be used for scheduling and communication with the communication terminal 200 connected through the network 100, grouping specific activities registered by a server operator or other users or related activities. Downloading of a project, the server computer 300 processes data transmission and reception related to the download of a specific project that the user has rescheduled. The server computer 300 processes communication connection and data upload of other communication terminal users for registering an activity or a project used for scheduling.

커뮤니티 관리부(320)는 제어부(360)의 제어에 따라 운영자가 직접 생성하거나 또는 각 통신 단말기(200)로부터 제공되는 일정관리에 사용하는 개별 액티비티 또는 서로 연관 있는 액티비티들을 그룹화한 프로젝트의 등록을 처리하며, 통신부(310)를 통해 접속된 통신 단말기(200)의 요청에 따라 등록된 액티비티 또는 프로젝트의 리스트 확인 및 검색을 처리한다.The community manager 320 processes the registration of a project in which an individual group or activities related to each other are generated by an operator under the control of the controller 360 or used for a schedule management provided from each communication terminal 200. In response to a request of the communication terminal 200 connected through the communication unit 310, a process of checking and searching a list of registered activities or projects is processed.

프로젝트 재조정부(330)는 커뮤니티 관리부(320)를 통해 서버 운영자 측에서 생성하거나 또는 다른 사용자들이 생성하여 등록한 프로젝트를 확인한 통신 단말기(200)의 특정 프로젝트의 일정 재조정 선택에 따라 해당 프로젝트 내 각 액티비티의 기존 일정을 사용자 자신이 입력하는 일정에 따라 재조정한다.The project rebalancing unit 330 may determine the rescheduling of a specific project of the communication terminal 200 which is generated by the server operator through the community manager 320 or by other users, and confirms the project. Reschedule the existing schedule according to the schedule you enter.

이때 프로젝트 재조정부(330)는 통신 단말기(200)로부터 커뮤니티에 등록되어 있는 특정 프로젝트의 일정 재조정이 선택되면, 프로젝트 내 각 액티비티의 일정 중 가장 빠른 일자 및/또는 가장 늦은 일자를 통신 단말기(200)로 제공하며, 통신 단말기(200)로부터 가장 빠른 일자 또는 가장 늦은 일자 중 하나가 선택된 후 사용자 자신의 일정으로 변경되면 프로젝트 내 각 액티비티들의 일정과 사용자가 변경하기 전의 일정과의 간격을 계산한 후 변경된 사용자 자신의 일정을 토대로 동일 간격이 되도록 자동으로 재조정하여, 다운로드 처리부(340)를 통해 해당 통신 단말기(200)로 다운로드될 수 있도록 한다.At this time, if the schedule rescheduling unit 330 is selected to reschedule a specific project registered in the community from the communication terminal 200, the earliest date and / or the latest date of the schedule of each activity in the project communication terminal 200 If one of the earliest date or the latest date is selected from the communication terminal 200 and then changed to the user's own schedule, the schedule is changed after calculating the interval between the schedule of each activity in the project and the schedule before the user changes. Automatically readjusted to be the same interval based on the user's own schedule, so that it can be downloaded to the communication terminal 200 through the download processor 340.

또한, 프로젝트 재조정부(330)는 통신 단말기(200)로부터 커뮤니티에 등록되어 있는 특정 프로젝트의 일정 재조정이 선택되면, 통신 단말기(200)로부터 프로젝트 내 각 액티비티들 중 일자가 가장 빠른 액티비티를 실시할 사용자 자신의 일정을 입력받되, 입력 시점의 날짜를 제시한 후 사용자가 변경할 수 있도록 하며, 통신 단말기(200)로부터 입력받은 날짜를 기준으로 프로젝트 내 각 액티비티의 일정을 재조정하여, 다운로드 처리부(340)를 통해 해당 통신 단말기(200)로 다운로드될 수 있도록 한다.In addition, the project rescheduling unit 330 is a user who will perform the fastest activity among the activities in the project from the communication terminal 200, if the schedule rescheduling of the specific project registered in the community from the communication terminal 200 is selected Receives his schedule, but after presenting the date of the input point so that the user can change, re-schedule each activity in the project based on the date received from the communication terminal 200, the download processing unit 340 It can be downloaded to the communication terminal 200 through.

또한, 프로젝트 재조정부(330)는 통신 단말기(200)로부터 커뮤니티에 등록되어 있는 특정 프로젝트의 일정 재조정이 선택되면, 통신 단말기(200)로부터 프로젝트의 디데이로 사용될 자신의 일정이 입력되는지를 판단하며, 통신 단말기(200)로부터 디데이로 사용될 자신의 일정이 입력되면 프로젝트 내 각 액티비티의 일정을 통신 단말기(200)로부터 입력된 디데이를 기준으로 한 일정으로 변경하여, 다운로드 처리부(340)를 통해 해당 통신 단말기(200)로 다운로드될 수 있도록 한다.In addition, if the project rescheduling unit 330 is selected to reschedule a specific project registered in the community from the communication terminal 200, and determines whether the schedule of their own to be used as the D-day of the project from the communication terminal 200, When the schedule of the user to be used as the D-day is input from the communication terminal 200, the schedule of each activity in the project is changed to the schedule based on the D-day input from the communication terminal 200, and the corresponding communication terminal is downloaded through the download processor 340. To be downloaded to 200.

다운로드 처리부(340)는 커뮤니티 관리부(320)를 통해 리스트 확인 및 검색을 수행한 통신 단말기(200)의 요청에 따라 일정관리에 사용할 특정 액티비티 또는 프로젝트를 해당 통신 단말기(200)로 다운로드하며, 프로젝트 재조정부(330)를 통해 사용자 자신이 입력한 일정에 따라 일정이 재조정된 프로젝트를 해당 통신 단말기(200)로 다운로드한다.The download processor 340 downloads a specific activity or project to be used for schedule management to the corresponding communication terminal 200 in response to a request of the communication terminal 200 that has performed a list check and search through the community manager 320, and reconstructs a project. The government 330 downloads the rescheduled project according to the schedule input by the user to the corresponding communication terminal 200.

데이터베이스(350)는 일정관리를 이용하는 각 통신 단말기(200)의 회원 정보 및 다운로드 정보, 커뮤니티 관리부(320)를 통해 운영자가 직접 생성하거나 또는 각 통신 단말기(200)로부터 등록되는 일정관리에 사용할 개별 액티비티 또는 서로 연관 있는 액티비티들을 그룹화한 프로젝트를 저장한다.The database 350 is a member activity and download information of each communication terminal 200 using the schedule management, an individual activity that is directly generated by the operator through the community management unit 320 or used for schedule management registered from each communication terminal 200. Or save a project that groups activities related to each other.

제어부(360)는 커뮤니티 관리부(320)를 통해 운영자 측에서 직접 생성하거나 또는 각 통신 단말기(200)로부터 제공되는 일정관리에 사용하는 개별 액티비티 또는 서로 연관 있는 액티비티들을 그룹화한 프로젝트의 등록 및 데이터베이스(350) 저장을 제어한다. 그리고 통신부(310)를 통해 통신 접속된 통신 단말기(200)와의 일정관리에 사용할 액티비티 또는 프로젝트의 리스트 확인 및 검색, 개별 액티비티 또는 서로 연관 있는 액티비티들을 그룹화한 프로젝트의 다운로드 처리, 또는 서버 운영자나 타 사용자들이 생성하여 커뮤니티에 등록한 특정 프로젝트 내의 각 액티비티의 기존 일정을 사용자 자신의 일정에 따른 재조정 및 일정이 재조정된 프로젝트의 해당 통신 단말기(200)로의 다운로드 처리를 제어한다.The control unit 360 registers and projects 350 a project in which individual activities or related activities are grouped together, which are directly generated by an operator through the community management unit 320 or used for scheduling provided from each communication terminal 200. Control storage. And checking and retrieving a list of activities or projects to be used for schedule management with the communication terminal 200 connected through the communication unit 310, downloading of individual activities or projects grouping related activities, or a server operator or another user. They control the process of re-scheduling the existing schedule of each activity in a specific project registered and created in the community according to the user's own schedule and the download process to the corresponding communication terminal 200 of the rescheduled project.

한편, 본 발명의 특징 중 하나는, 통신 단말기(200)의 일정관리도구에서 구체적 실행날짜가 결정된 각 액티비티의 일정관리를 수행하는 기능을 수행함과 동시에, 언제 시작해서 언제 종료할지를 날짜로 관리하는 할 일 프로그램과, 어떤 날짜의 특정 시간(몇 시부터 몇 시까지)에 어떤 일을 할지를 관리하는 일정 프로그램과, 아직 일정을 정하지 못한 일을 관리하는 메모 프로그램을 하나의 프로그램으로 통합하여 관리하는 기능을 더 수행할 수 있는 것이다.On the other hand, one of the features of the present invention, in the schedule management tool of the communication terminal 200 to perform the function of performing the schedule management of each activity whose specific execution date is determined, and to manage when to start and when to end by date Integrate and manage a day program, a schedule program that manages what to do at a certain time (from what time to what time), and a memo program that manages tasks that have not been scheduled yet. You can do more.

즉 종래에 개별적으로 사용하였던 메모, 할 일 및 일정을 하나의 프로그램에서 통합하여 관리하는 것이다. 기존에는 메모, 할 일 및 일정을 각각 다른 프로그램으로 관리하고 있어서 그 날짜에 해야 할 일을 살피기 위해 할 일 프로그램과 일정 프로그램을 각각 살펴보아야 하였고, 아직 일정을 정하지 못한 일은 메모 프로그램에서 관리하다가 일정을 정하면 일정 프로그램에 새로 입력하여야 하였다. 같은 일정이지만, 언제 시작해서 언제 종료할지를 날짜로 관리하는 것이 할 일 프로그램이고, 어떤 날의 특정 시간에 어떤 일을 할지를 관리하는 것은 일정 프로그램이 담당한다.In other words, it manages by integrating the memo, to-do and schedule previously used individually in one program. In the past, memos, tasks, and schedules are managed by different programs, so you have to look at the to-do and schedule programs to see what you need to do on that date. If it was decided, new schedule had to be entered. It's the same schedule, but it's a to-do program to keep track of when to start and when to finish, and the schedule program manages what to do at a particular time of day.

본 발명은 이의 통합을 위해 메모, 할 일 및 일정을 동일한 데이터베이스 구조로 생성하였다. 예를 들어, 입력할 때 언제 해야할지를 따로 정하지 않고 저장하면 메모로 저장되도록 하고, 이후 메모 목록에서 해당 메모를 선택한 후 편집으로 들어가 일정을 정하면 액티비티로 바로 전환되도록 한다. 액티비티의 경우 언제 할 것인지 시작과 종료를 정할 수 있는데, 시작과 종료를 정할 때 날짜 기준으로만 정한 것과 시작시간과 종료시간까지 정한 것을 구분한다. 시작시간과 종료시간까지 정한 것은 시간이 표시되는 일간 일정이나 주간 일정에서 해당 시간대에 일정을 표시하고, 시작시간과 종료시간 없이 기간으로만 정해진 것은 시간이 표시되는 것 공간 아래에 표시하고, 목록보기 형태로 볼 때에는 그 날짜의 목록에 시작시간과 종료시간까지 정한 액티비티와 함께 표시한다.The present invention has created memos, tasks and schedules in the same database structure for integration thereof. For example, when you type, you don't have to decide when to do it, but when you save it, it's saved as a note, then you select the note in the note list, enter edit, and schedule it to switch directly to the activity. In the case of activities, you can set the start and end of when to do it. When you start and end, you distinguish between what you set by date and what you set by start and end time. The schedules defined by the start time and the end time are displayed in the time zone in the daily schedule or weekly schedule where the time is displayed, and the ones defined as the period without the start time and end time are displayed under the time space. When viewed in the form, the list of dates is displayed with the activities specified by the start time and end time.

이때 메모의 경우 메모를 카테고리별로 나눠 관리할 수 있도록 별도의 필드가 필요한데, 이 필드에는 액티비티이라는 것이 포함되어 있다. 메모를 액티비티로 변경하면, 즉 날짜 또는 날짜 및 시간을 선택하면 이 필드가 액티비티로 표시된다. 액티비티에서 언제 해야하는 날짜 또는 날짜 및 시간을 삭제하면 메모가 되는데, 이 경우에는 메모의 카테고리를 선택하는 난이 표시된다. 메모는 언제 실행할지에 대한 정보가 없는 반면 메모를 작성한 날짜 또는 최종 수정한 날짜가 관리된다. 메모를 액티비티로 변경하면 작성일 또는 최종 수정일을 표시하지 않고, 언제 실행할지에 대한 정보를 표시한다. 액티비티를 메모로 변경하면 그 변경 시점을 최종 수정일로 관리한다. 메모를 액티비티로 변경한 후 그 액티비티를 다시 메모로 변경할 경우 이전 메모에서 선택한 카테고리가 있으면 액티비티에서 다시 메모로 변경할 때 기존에 선택되었던 카테고리를 표시한 후 변경할 수 있도록 하고 있고, 액티비티를 최초로 메모로 변경할 때에는 기타 라는 카테고리로 분류한 후 사용자가 변경할 수 있도록 하고 있다. 할 일 프로그램과 일정 프로그램은 구체적인 시간을 선택하였지는 여부로 구분하고, 나머지는 동일하게 관리한다.In this case, a memo needs a separate field so that memos can be divided and managed by categories. This field includes an activity. If you change the note to activity, that is, select a date or date and time, this field is displayed as the activity. If you delete the date or the date and time you need to do in the activity, the note becomes a note, in which case you will be prompted to select a category for the note. Notes have no information about when to run them, while the date the note was created or last modified is maintained. When you change a memo to an activity, it displays information about when it will run, rather than the date of creation or last modification. When you change an activity to a note, you manage that change as the last modified date. When you change a note to an activity and then change the activity back to a note, if there is a category selected in the previous note, when you change the activity back to a note, you can mark the previously selected category and then change the activity to the first note. When it is classified into other category, the user can change it. The to-do program and the schedule program are divided according to whether or not a specific time is selected, and the remainder is managed in the same way.

다음에는, 이와 같이 구성된 본 발명에 따른 일정관리방법을 도 4 내지 도 9를 참조하여 상세하게 설명한다.Next, the schedule management method according to the present invention configured as described above will be described in detail with reference to FIGS. 4 to 9.

도 4 내지 도 8은 본 발명의 일 실시예에 따른 일정관리방법의 동작과정을 상세하게 나타낸 순서도이며, 도 9는 본 발명의 다른 실시예에 따른 일정관리방법의 동작과정을 상세하게 나타낸 순서도이다.4 to 8 are flowcharts showing in detail the operation process of the schedule management method according to an embodiment of the present invention, Figure 9 is a flow chart showing in detail the operation process of the schedule management method according to another embodiment of the present invention. .

우선, 통신 단말기(200)는 네트워크 통신망(100)을 통해 일정관리에 사용할 개별 액티비티 또는 서로 연관 있는 액티비티들을 그룹화한 프로젝트를 관리하는 서버 컴퓨터(300)로 통신 접속을 진행하고, 사용자의 조작을 토대로 서버 운영자 측에서 생성하거나 다른 사용자들이 생성하여 등록한 일정관리에 사용할 액티비티 또는 프로젝트의 리스트 확인 및 검색을 수행한다(S100).First, the communication terminal 200 performs a communication connection through the network communication network 100 to the server computer 300 that manages a grouping of individual activities or related activities to be used for schedule management, and based on the user's operation. The server operator checks or searches a list of activities or projects to be used for schedule management generated or registered by other users (S100).

이때 S100 단계를 통해 서버 컴퓨터(300)에서 관리하는 서버 운영자 측에서 생성하거나 다른 사용자들이 생성하여 등록한 프로젝트는, 각 프로젝트별로 커뮤니티를 구성할 수 있다. 즉 서버 컴퓨터(300)는 각 프로젝트별 커뮤니티를 통해 각 통신 단말기(200) 상호간에 추가적인 일정이나 정보를 주고받을 수 있고, 통신 단말기(200)로부터 프로젝트를 다운로드시 해당 프로젝트의 커뮤니티에 자동으로 가입하는 것에 대한 동의를 받고, 자동가입에 대한 동의를 수행한 통신 단말기(200)로 프로젝트를 다운로드할 때 반대 의사표시를 하지 않으면 프로젝트의 커뮤니티에 가입되도록 하는 것이다. 이에 따라 일정관리도구를 통해 SNS를 구성할 수 있음은 물론, 동일한 프로젝트를 공유하는 사람별로 손쉽게 커뮤니티를 구성할 수 있다.In this case, a project generated by the server operator managed by the server computer 300 through the step S100 or created and registered by other users may configure a community for each project. That is, the server computer 300 may send and receive additional schedules or information between each communication terminal 200 through the community for each project, and automatically join the community of the corresponding project when downloading the project from the communication terminal 200. If you do not indicate the objection when downloading the project to the communication terminal 200 that has received the consent for the automatic subscription, the consent to the automatic subscription is to be joined to the community of the project. Accordingly, SNS can be configured through a schedule management tool, and a community can be easily configured for each person who shares the same project.

통신 단말기(200)의 통신 접속을 수행한 서버 컴퓨터(300)는 S100 단계를 통해 액티비티 또는 프로젝트의 리스트 확인 및 검색을 수행한 사용자의 특정 액티비티 또는 프로젝트의 다운로드 선택을 확인하고, 다운로드가 선택되면 해당 통신 단말기(200)로 일정관리에 사용할 특정 액티비티 또는 프로젝트를 다운로드한다(S200).The server computer 300 performing the communication connection of the communication terminal 200 confirms the download selection of the specific activity or project of the user who has performed the check and search of the activity or the project list through step S100, and if the download is selected, Download a specific activity or project to be used for scheduling to the communication terminal 200 (S200).

이때 액티비티는 구체적인 날짜 또는 어떤 날짜의 구체적인 시간에 어떠한 일을 수행할 것인지가 결정된 이벤트 정보이며, 프로젝트는 서로 관련 있는 액티비티들을 그룹화한 것이다.In this case, the activity is event information that determines what to do at a specific date or at a specific time of day, and the project is a grouping of related activities.

서버 컴퓨터(300)로부터 일정관리에 사용할 특정 액티비티 또는 프로젝트를 선택하여 다운로드받은 이후, 통신 단말기(200)는 사용자가 서버 컴퓨터(300)로부터 다운로드받은 특정 프로젝트의 활용을 선택하는지를 판단한다(S300).After selecting and downloading a specific activity or project to be used for scheduling from the server computer 300, the communication terminal 200 determines whether the user selects to utilize the specific project downloaded from the server computer 300 (S300).

S300 단계의 판단결과 프로젝트의 활용이 선택되면, 통신 단말기(200)는 사용자가 변경하여 입력하는 일정을 확인하고, 새롭게 결정된 일정을 토대로 서버 컴퓨터(300)로부터 다운로드받은 프로젝트 내 각 액티비티의 일정을 자동으로 재조정한다(S400).As a result of the determination of step S300, when the utilization of the project is selected, the communication terminal 200 confirms the schedule inputted by the user, and automatically schedules the schedule of each activity in the project downloaded from the server computer 300 based on the newly determined schedule. To readjust (S400).

이를 도 5를 참조하여 상세하게 설명하면, 통신 단말기(200)는 사용자의 조작을 확인하여 서버 컴퓨터(300)로부터 다운로드받은 프로젝트 내 각 액티비티의 일정 재조정이 선택되는지를 판단하고(S410), 판단결과 일정 재조정이 선택되면 프로젝트 내 각 액티비티의 일정 중 가장 빠른 일자 및/또는 가장 늦은 일자를 화면상에 표시하고(S420), 사용자의 조작을 확인하여 프로젝트 내 각 액티비티의 일정 중 가장 빠른 일자 또는 가장 늦은 일자 중 하나가 선택된 후 사용자 자신의 일정으로 변경되는지를 판단한다(S430).This will be described in detail with reference to FIG. 5, and the communication terminal 200 checks the user's operation to determine whether a rescheduling of activities in the project downloaded from the server computer 300 is selected (S410). If the reschedule is selected, the earliest date and / or latest date of the schedule of each activity in the project is displayed on the screen (S420), and the user's operation is confirmed to determine the earliest date or latest of the schedule of each activity in the project. It is determined whether one of the dates is selected and then changed to the user's own schedule (S430).

판단결과 가장 빠른 일자 또는 가장 늦은 일자 중 하나가 선택된 후 사용자 자신의 일정으로 변경되면, 통신 단말기(200)는 프로젝트 내 각 액티비티들의 일정과 사용자가 변경하기 전의 일정과의 간격을 계산한 후 변경된 사용자 자신의 일정을 토대로 동일 간격이 되도록 자동으로 재조정한다(S440).As a result of the determination, if one of the earliest date or the latest date is selected and then changed to the user's own schedule, the communication terminal 200 calculates the interval between the schedule of each activity in the project and the schedule before the user changes the changed user. Automatically readjusted to be the same interval based on their schedule (S440).

또한, S410 단계의 판단결과 일정 재조정이 선택되면, 통신 단말기(200)는 서버 컴퓨터(300)로부터 다운로드받은 프로젝트 내 각 액티비티 중 어느 하나의 액티비티가 선택되는지를 판단한다(S450).In addition, if the schedule reschedule is selected in step S410, the communication terminal 200 determines whether any one of the activities in the project downloaded from the server computer 300 is selected (S450).

판단결과 프로젝트 내 각 액티비티 중 어느 하나의 액티비티가 선택되면, 통신 단말기(200)는 사용자가 선택한 특정 액티비티의 일정을 자신의 일정으로 변경하는지를 판단하고(S460), 특정 액티비티의 일정을 자신의 일정으로 변경하면, 동일한 프로젝트에 포함되어 있는 액티비티들 중 S460 단계를 통해 사용자 자신의 일정으로 변경된 액티비티 이후의 모든 액티비티의 일정을 변경된 일정을 토대로 변경되기 전 일정과 동일 간격이 되도록 재조정한다(S470).As a result of the determination, if any one activity of each activity in the project is selected, the communication terminal 200 determines whether the schedule of the specific activity selected by the user is changed to his schedule (S460), and the schedule of the specific activity is set to his schedule. If the change is made, the schedules of all activities after the activity changed to the user's own schedule through the step S460 among the activities included in the same project are readjusted to be the same interval as the schedule before the change based on the changed schedule (S470).

또한, 상술한 S410 단계의 판단결과 일정 재조정이 선택되면, 통신 단말기(200)는 사용자의 조작을 확인하여 서버 컴퓨터(300)로부터 다운로드받은 프로젝트의 디데이로 사용될 자신의 일정이 입력되는지를 판단하고(S480), 디데이로 사용될 자신의 일정이 입력되면, 프로젝트 내 각 액티비티의 일정을 사용자가 입력한 디데이를 기준으로 한 일정으로 변경한다(S490).In addition, when the rescheduling is selected as a result of the determination in step S410 described above, the communication terminal 200 checks the user's operation to determine whether the own schedule to be used as the D-day of the project downloaded from the server computer 300 is input ( In step S480, when the user's schedule to be used as a D-day is input, the schedule of each activity in the project is changed to a schedule based on the D-day input by the user (S490).

이때 S490 단계에서 사용자가 입력한 디데이를 기준으로 한 일정으로 변경되는 프로젝트 내 각 액티비티의 구체적 수행날짜는, 사용자의 조작에 따라 임의로 변경이 가능함은 물론이다.In this case, the specific execution date of each activity in the project that is changed to a schedule based on the D-day input by the user in step S490 may be arbitrarily changed according to the user's operation.

또한, S410 단계를 통해 서버 컴퓨터(300)로부터 다운로드받은 프로젝트 내 각 액티비티의 일정 재조정을 선택하기 이전에, 통신 단말기(200)는 사용자의 조작에 따라 서버 컴퓨터(300)로부터 다운로드받은 프로젝트에 새로운 액티비티의 추가, 기존 액티비티의 삭제 또는 변경이 수행되면, 해당 프로젝트에 새로운 액티비티의 추가, 기존 액티비티의 삭제 또는 변경을 처리할 수 있다.In addition, before selecting to reschedule each activity in the project downloaded from the server computer 300 through step S410, the communication terminal 200 according to the user's operation to the new activity downloaded to the project downloaded from the server computer 300 If you add, delete, or change an existing activity, you can add new activities to the project, delete or change existing activities.

이제, 통신 단말기(200)는 일정관리도구를 통해 S400 단계에서 일정이 재조정된 프로젝트 내 각 액티비티들을 해당 날짜에 저장하여 일정관리를 수행한다(S500). 이때 S500 단계는 후술되는 S1000 단계를 통해 서버 컴퓨터(300)로부터 다운로드받은 각 액티비티들의 선택을 토대로 한 프로젝트의 생성을 수행한 이후에도 해당 프로젝트 내 각 액티비티들을 해당 날짜에 저장하여 일정관리를 시작할 수 있다.Now, the communication terminal 200 performs schedule management by storing each activity in the project whose schedule is rescheduled at step S400 through a schedule management tool on a corresponding date (S500). In this case, in step S500, even after generating a project based on the selection of each activity downloaded from the server computer 300 through step S1000, the schedule management may be performed by storing each activity in the corresponding project on the corresponding date.

S500 단계에서 구체적 실행날짜가 결정된 각 액티비티의 일정관리를 수행하는 통신 단말기(200)의 일정관리도구는, 언제 시작해서 언제 종료할지를 날짜로 관리하는 할 일 프로그램과, 어떤 날짜의 특정 시간에 어떤 일을 할지를 관리하는 일정 프로그램과, 아직 일정을 정하지 못한 일을 관리하는 메모 프로그램을 하나로 통합하여 관리하는 기능을 더 수행할 수도 있다.The schedule management tool of the communication terminal 200 that performs the schedule management of each activity whose specific execution date is determined in step S500, a to-do program for managing when to start and when to end with a date, and what day at a specific time of day In addition, a schedule program that manages whether to manage and a memo program that manages tasks not yet scheduled may be integrated into one function.

또한, 통신 단말기(200)의 통신 접속을 수행한 서버 컴퓨터(300)는 S100 단계를 통해 액티비티 또는 프로젝트의 리스트 확인 및 검색을 수행한 사용자의 특정 프로젝트의 일정 재조정 및 다운로드 선택을 확인하고, 일정 재조정 및 다운로드가 선택되면 서버 운영자 측에서 생성하거나 다른 사용자들이 생성하여 커뮤니티에 등록한 프로젝트의 기존 일정을 자신의 일정에 따라 재조정하고, 일정이 재조정된 프로젝트를 해당 통신 단말기(200)로 다운로드한다(S600).In addition, the server computer 300 performing the communication connection of the communication terminal 200 confirms the rescheduling and downloading selection of the specific project of the user who has performed the check or search of the activity or the project list through step S100, and reschedules the schedule. And download is selected by the server operator or readjust the existing schedule of the project created by other users and registered in the community according to their own schedule, and downloads the rescheduled project to the corresponding communication terminal 200 (S600). .

이를 도 6을 참조하여 상세하게 설명하면, 서버 컴퓨터(300)는 통신 단말기(200)로부터 커뮤니티에 등록되어 있는 특정 프로젝트의 일정 재조정이 선택되는지를 판단한다(S610).6, the server computer 300 determines whether to reschedule a specific project registered in the community from the communication terminal 200 (S610).

S610 단계의 판단결과 액티비티 기준의 일정 재조정이 선택되면, 서버 컴퓨터(300)는 프로젝트 내 각 액티비티의 일정 중 가장 빠른 일자 및/또는 가장 늦은 일자를 통신 단말기(200)로 제공하여 사용자가 화면을 통해 이를 확인하도록 한다(S620).As a result of the determination in step S610, if the schedule reschedule is selected, the server computer 300 provides the communication terminal 200 with the earliest date and / or the latest date of the schedule of each activity in the project, so that the user may change the schedule. To confirm this (S620).

이후 서버 컴퓨터(300)는 프로젝트 내 각 액티비티의 일정 중 가장 빠른 일자 및/또는 가장 늦은 일자를 확인한 통신 단말기(200)로부터 가장 빠른 일자 또는 가장 늦은 일자 중 하나가 선택된 후 사용자 자신의 일정으로 변경되는지를 판단한다(S630).Thereafter, the server computer 300 selects one of the earliest date or the latest date from the communication terminal 200 confirming the earliest date and / or the latest date of each activity in the project, and then changes to the user's own schedule. Determine (S630).

S630 단계의 판단결과 통신 단말기(200)로부터 가장 빠른 일자 또는 가장 늦은 일자 중 하나가 선택된 후 사용자 자신의 일정으로 변경되면, 서버 컴퓨터(300)는 프로젝트 내 각 액티비티들의 일정과 사용자가 변경하기 전의 일정과의 간격을 계산한 후 변경된 사용자 자신의 일정을 토대로 동일 간격이 되도록 자동으로 재조정한다(S640).As a result of the determination in step S630, if one of the earliest date or the latest date is selected from the communication terminal 200 and then changed to the user's own schedule, the server computer 300 schedules each activity in the project and the schedule before the user changes. After calculating the interval between and automatically adjusts to the same interval based on the changed user's schedule (S640).

이후 서버 컴퓨터(300)는 S640 단계를 통해 일정이 재조정된 프로젝트를 해당 통신 단말기(200)로 다운로드한다(S650).Thereafter, the server computer 300 downloads the rescheduled project to the corresponding communication terminal 200 through step S640 (S650).

또한, S610 단계의 판단결과 커뮤니티에 등록되어 있는 특정 프로젝트의 일정 재조정이 선택되면, 서버 컴퓨터(300)는 통신 단말기(200)로부터 프로젝트 내 각 액티비티들 중 일자가 가장 빠른 액티비티를 실시할 사용자 자신의 일정을 입력받되, 입력 시점의 날짜를 제시한 후 사용자가 변경할 수 있도록 한다(S660).In addition, if the rescheduling of a specific project registered in the community is selected as a result of the step S610, the server computer 300 from the communication terminal 200 of the user himself or herself to perform the fastest activity among the activities in the project Although the schedule is input, the user can change the present time after presenting the input time (S660).

그리고 서버 컴퓨터(300)는 S660 단계를 통해 통신 단말기(200)로부터 입력받은 날짜를 기준으로 프로젝트 내 각 액티비티의 일정을 재조정하여(S670), 일정이 재조정된 프로젝트를 해당 통신 단말기(200)로 다운로드되도록 한다.The server computer 300 readjusts the schedule of each activity in the project based on the date input from the communication terminal 200 through step S660 (S670), and downloads the rescheduled project to the corresponding communication terminal 200. Be sure to

또한, S610 단계의 판단결과 커뮤니티에 등록되어 있는 특정 프로젝트의 일정 재조정이 선택되면, 서버 컴퓨터(300)는 통신 단말기(200)로부터 프로젝트의 디데이로 사용될 자신의 일정이 입력되는지를 판단하고(S680), 통신 단말기(200)로부터 디데이로 사용될 자신의 일정이 입력되면, 프로젝트 내 각 액티비티의 일정을 통신 단말기(200)로부터 입력된 디데이를 기준으로 한 일정으로 변경하여(S690), 일정이 재조정된 프로젝트를 해당 통신 단말기(200)로 다운로드되도록 한다.In addition, when the rescheduling of a specific project registered in the community is selected as a result of the determination in step S610, the server computer 300 determines whether or not its schedule to be used as the D-day of the project is input from the communication terminal 200 (S680). When the user's schedule to be used as a D-day is input from the communication terminal 200, the schedule of each activity in the project is changed to a schedule based on the D-day input from the communication terminal 200 (S690), and the schedule is rescheduled. To be downloaded to the communication terminal 200.

이처럼 S600 단계를 통해 사용자의 선택에 따라 특정 프로젝트의 일정을 재조정하고 일정이 재조정된 프로젝트를 서버 컴퓨터(300)로부터 다운로드받은 이후, 통신 단말기(200)는 일정관리도구를 통해 서버 컴퓨터(300)로부터 일정을 재조정한 후 다운로드받은 프로젝트 내 각 액티비티들을 해당 날짜에 저장하여 일정관리를 수행한다(S700).After rescheduling a specific project according to the user's selection through the step S600 and downloading the rescheduled project from the server computer 300, the communication terminal 200 from the server computer 300 through the schedule management tool After rescheduling the schedule, each activity in the downloaded project is stored in the corresponding date to perform a schedule management (S700).

이제, S500 또는 S700 단계를 통해 일정관리를 시작한 이후, 통신 단말기(200)는 계획된 일정의 실천 여부 확인을 위해 특정 프로젝트를 선택한 후 실천여부 확인기능이 작동되도록 설정하면, 일정관리도구를 통해 사용자의 조작을 확인하여 프로젝트 내 각 액티비티들의 실천 여부 체크를 확인하고, 실천 여부 체크 결과를 토대로 각 액티비티들의 수행 비율을 계산한 후, 수행 비율 결과를 화면상에 표시한다(S800).Now, after starting the schedule management through the step S500 or S700, the communication terminal 200 selects a specific project to confirm the implementation of the planned schedule, and then set to check whether the action is activated, the user through the schedule management tool After confirming the operation, checks whether each activity in the project is checked for execution, calculates the execution rate of each activity based on the result of checking whether the result is displayed, and displays the result of the execution rate on the screen (S800).

이를 도 7을 참조하여 상세하게 설명하면, 통신 단말기(200)는 계획된 일정의 실천 여부 확인을 위한 사용자의 특정 프로젝트 선택을 확인하여, 해당 프로젝트에 대한 실천여부 확인기능을 작동하도록 설정한다(S810).Referring to this in detail with reference to Figure 7, the communication terminal 200 confirms the user's specific project selection for checking the implementation of the planned schedule, and set to operate the operation check function for the corresponding project (S810). .

그리고 통신 단말기(200)는 사용자의 조작을 확인하여 구체적 실행날짜가 결정된 프로젝트 내 각 액티비티의 실천 여부를 확인한다(S820).In addition, the communication terminal 200 checks the user's operation and checks whether or not each activity in the project in which the specific execution date is determined is performed (S820).

이때 S820 단계에서 프로젝트 내 각 액티비티의 실행 여부 확인은, 일정관리도구를 통해 일정관리를 수행하는 사용자의 각 액티비티별 실행 여부를 확인하는 클릭 조작 또는 각 액티비티별 시작시간과 종료시간 입력을 토대로 확인하는 것이 일반적이다.In this case, whether or not each activity in the project is executed in step S820 is checked based on a click operation for checking whether each activity of a user who performs a schedule through the calendar tool or inputting start and end time for each activity. Is common.

이후 통신 단말기(200)는 S820 단계에서 확인된 각 액티비티의 실천 여부 결과를 토대로 실제 수행 비율을 계산한다(S830).Thereafter, the communication terminal 200 calculates an actual performance ratio based on a result of whether each activity is checked in step S820 (S830).

그리고 계산된 각 액티비티의 수행 비율 결과를 사용자가 시각적으로 인식할 수 있는 수단으로 변환, 작성하고(S840), 시각적으로 인식할 수 있는 수단으로 변환, 작성된 각 액티비티의 수행 비율 결과를 화면상에 표시한다(S850). 즉 통신 단말기(200)는 사용자의 일정 실천 여부를 일간, 주간, 월간 달력 형태 또는 프로젝트의 액티비티 목록 형태에 숫자나 기호를 포함한 문자, 표와 도형을 포함한 그림 등으로 표시하여 사용자가 일정의 수행 여부를 손쉽게 확인하도록 하는 것이다.In addition, the calculated performance ratio result of each activity is converted into a means that can be visually recognized by the user (S840), and converted into a visually recognizable means, and the performance ratio result of each created activity is displayed on the screen. (S850). That is, the communication terminal 200 displays whether or not the user performs the schedule by displaying the user's schedule in practice in the form of daily, weekly, monthly calendar or activity list of the project as a letter including a number or a symbol, a figure including a table and a figure. It is easy to check.

또한, 상술한 S300 단계의 판단결과 서버 컴퓨터(300)로부터 다운로드받은 특정 프로젝트의 활용이 아니면, 통신 단말기(200)는 서버 컴퓨터(300)로부터 다운로드받은 각 액티비티들 중 서로 연관 있는 액티비티들을 그룹화하여 프로젝트를 생성하는 것이 선택되는지를 판단한다(S900).In addition, as a result of the above-described determination in step S300, if the specific project downloaded from the server computer 300 is not utilized, the communication terminal 200 groups the activities related to each other among the activities downloaded from the server computer 300 to project them. It is determined whether generating is selected (S900).

S900 단계의 판단결과 서로 연관 있는 액티비티들을 그룹화하여 프로젝트를 생성하는 것이 선택되면, 통신 단말기(200)는 서버 컴퓨터(300)로부터 다운로드받은 액티비티들 중 서로 연관 있는 액티비티를 그룹화한 후, 그룹화된 액티비티들의 기준이 되는 날짜가 결정되면 그룹 내 각 액티비티들의 일정을 계산하여 프로젝트를 생성한다(S1000). 즉 통신 단말기(200)는 사용자의 조작을 확인하여 서버 컴퓨터(300)로부터 다운로드받은 액티비티들 중 서로 연관 있는 액티비티를 그룹화하고, 그룹화된 액티비티들의 기준이 되는 날짜가 결정되면 그룹 내 각 액티비티들의 일정을 계산하여 프로젝트를 생성하며, 일정관리도구를 통해 프로젝트 내 각 액티비티들을 해당 날짜에 저장하여 일정관리를 수행하는 기능을 더 수행할 수 있도록 하는 것이다.As a result of the determination in step S900, if a group of activities related to each other is selected to generate a project, the communication terminal 200 groups the activities related to each other among the activities downloaded from the server computer 300, and then the grouped activities When the date of reference is determined, a project is generated by calculating a schedule of activities in the group (S1000). That is, the communication terminal 200 checks a user's operation to group activities related to each other among the activities downloaded from the server computer 300, and when a date serving as a reference for the grouped activities is determined, schedules of each activity in the group. The project is created by calculation, and the schedule management tool saves each activity in the project on the corresponding date so that it can perform the function of scheduling.

이를 도 8을 참조하여 상세하게 설명하면, 통신 단말기(200)는 사용자가 서버 컴퓨터(300)로부터 다운로드받은 각 액티비티들 중 서로 연관 있는 액티비티들을 선택하는지를 판단한다(S1010).Referring to FIG. 8 in detail, the communication terminal 200 determines whether the user selects activities related to each other among the activities downloaded from the server computer 300 (S1010).

판단결과 사용자가 서버 컴퓨터(300)로부터 다운로드받은 각 액티비티들 중 서로 연관 있는 액티비티들을 선택되면, 통신 단말기(200)는 해당 액티비티들을 그룹화하고(S1020), 사용자가 그룹화된 액티비티들의 기준이 되는 날짜를 결정하여 입력하는지를 판단한다(S1030).As a result of the determination, when the user selects activities related to each other among the activities downloaded from the server computer 300, the communication terminal 200 groups the corresponding activities (S1020), and sets the date on which the user becomes the reference of the grouped activities. Determine and determine whether to enter (S1030).

판단결과 사용자가 그룹화된 액티비티들의 기준이 되는 날짜를 결정하여 입력하면, 통신 단말기(200)는 해당 사용자가 결정한 기준이 되는 날짜를 기준으로 그룹화된 각 액티비티별 구체적 수행날짜를 계산한다(S1040).As a result of the determination, when the user determines and inputs a date that is a standard of the grouped activities, the communication terminal 200 calculates a specific execution date for each grouped activity on the basis of the date that is determined by the corresponding user (S1040).

그룹화된 각 액티비티별 구체적 수행날짜를 계산한 이후, 통신 단말기(200)는 구체적 수행날짜가 계산된 각 액티비티들이 포함된 프로젝트를 생성하여 저장한다(S1050).After calculating the specific execution date for each grouped activity, the communication terminal 200 generates and stores a project including the activities for which the specific execution date is calculated (S1050).

한편, 상술한 실시예에서는 통신 단말기(200)가 서버 컴퓨터(300)로부터 일정관리에 사용할 액티비티 또는 프로젝트를 다운로드받아 활용하는 방식과, 서버 컴퓨터(300)의 커뮤니티에 등록된 프로젝트의 일정을 재조정한 후 다운로드받는 방식에 대하여 설명하였으나, 서버 컴퓨터(300)로부터 액티비티나 프로젝트를 다운로드받지 않고 사용자가 이전에 직접 생성하여 사용하였던 프로젝트 중 어느 하나의 프로젝트를 활용하여 일정관리를 수행할 수도 있을 것이다.Meanwhile, in the above-described embodiment, the communication terminal 200 downloads and utilizes an activity or project to be used for schedule management from the server computer 300, and reschedules a project registered in the community of the server computer 300. After the download method has been described, schedule management may be performed by using any one project that the user has previously created and used directly without downloading an activity or a project from the server computer 300.

도 9는 이에 대한 실시예를 설명하기 위한 도면으로서, S1200 단계와 S1400 단계의 세부적인 동작과정은 상술한 도 5, 도 7과 동일하므로 여기에서의 상세한 설명은 생략한다.FIG. 9 is a diagram for describing an exemplary embodiment. Since detailed operations of steps S1200 and S1400 are the same as those of FIGS. 5 and 7 described above, detailed descriptions thereof will be omitted.

통신 단말기(200)는 사용자가 이전에 직접 생성하여 사용한 프로젝트 중 어느 하나의 프로젝트의 활용을 선택하는지를 판단한다(S1100).The communication terminal 200 determines whether the user selects the utilization of one of the projects previously created and used (S1100).

판단결과 사용자가 이전에 사용한 프로젝트 중 어느 하나의 프로젝트의 활용이 선택되면, 통신 단말기(200)는 사용자가 변경하여 입력하는 일정을 확인하고, 새롭게 결정된 일정을 토대로 프로젝트 내 각 액티비티의 일정을 자동으로 재조정한다(S1200).As a result of the determination, when the user selects to use one of the previously used projects, the communication terminal 200 checks the schedule that the user changes and inputs, and automatically schedules the schedule of each activity in the project based on the newly determined schedule. It readjusts (S1200).

이후 통신 단말기(200)는 일정관리도구를 통해 S1200 단계에서 일정이 재조정된 프로젝트 내 각 액티비티들을 해당 날짜에 저장하여 일정관리를 시작한다(S1300).Afterwards, the communication terminal 200 starts the schedule management by storing each activity in the project whose schedule is rescheduled at step S1200 through a schedule management tool on a corresponding date (S1300).

S1300 단계를 통해 일정관리를 시작한 이후, 통신 단말기(200)는 계획된 일정의 실천 여부 확인을 위해 특정 프로젝트를 선택한 후 실천여부 확인기능이 작동되도록 설정하면, 일정관리도구를 통해 사용자의 조작을 확인하여 프로젝트 내 각 액티비티들의 실천 여부 체크를 확인하고, 실천 여부 체크 결과를 토대로 각 액티비티들의 수행 비율을 계산한 후, 수행 비율 결과를 화면상에 표시한다(S1400).After starting the schedule management through the step S1300, the communication terminal 200 selects a specific project for checking the implementation of the planned schedule, and then set the check whether the implementation of the operation, check the user's operation through the schedule management tool After checking the activity check of each activity in the project and calculating the execution rate of each activity based on the check result of the action, the result of the execution rate is displayed on the screen (S1400).

여기에서, 상술한 본 발명에서는 바람직한 실시예를 참조하여 설명하였지만, 해당 기술분야의 숙련된 당업자는 하기의 특허청구범위에 기재된 본 발명의 사상 및 영역으로부터 벗어나지 않는 범위 내에서 본 발명을 다양하게 수정 및 변경할 수 있음을 이해할 수 있을 것이다.Herein, while the present invention has been described with reference to the preferred embodiments, those skilled in the art will variously modify the present invention without departing from the spirit and scope of the invention as set forth in the claims below. And can be changed.

100 : 네트워크 통신망 200 : 통신 단말기
210 : 데이터 통신부 220 : 프로젝트 관리부
230 : 액티비티 관리부 240 : 일정관리부
250 : 저장부 260 : 일정수행 확인부
270 : 제어부 300 : 서버 컴퓨터
310 : 통신부 320 : 커뮤니티 관리부
330 : 프로젝트 재조정부 340 : 다운로드 처리부
350 : 데이터베이스 360 : 제어부
100: network communication network 200: communication terminal
210: data communication unit 220: project management unit
230: activity management unit 240: schedule management unit
250: storage unit 260: schedule performance check unit
270 control unit 300 server computer
310: communication unit 320: community management unit
330: Project rebalancing unit 340: Download processing unit
350: database 360: control unit

Claims (37)

(1) 통신 단말기는, 네트워크 통신망을 통해 일정관리에 사용할 개별 액티비티 또는 서로 연관 있는 액티비티들을 그룹화한 프로젝트를 관리하는 서버 컴퓨터로 통신 접속을 진행하고, 서버 운영자 측에서 생성하거나 다른 사용자들이 생성하여 등록한 액티비티 또는 프로젝트의 리스트 확인 및 검색을 수행하는 단계,
(2) 상기 서버 컴퓨터는, 상기 (1) 단계를 통해 액티비티 또는 프로젝트의 리스트 확인 및 검색을 수행한 사용자의 특정 액티비티 또는 프로젝트의 다운로드 선택을 확인하고, 다운로드가 선택되면 해당 통신 단말기로 일정관리에 사용할 특정 액티비티 또는 프로젝트를 다운로드하는 단계,
(3) 상기 통신 단말기는, 사용자의 조작을 확인하여 상기 서버 컴퓨터로부터 다운로드받은 특정 프로젝트의 활용이 선택되는지를 판단하는 단계,
(4) 상기 (3) 단계의 판단결과 프로젝트의 활용이 선택되면, 상기 통신 단말기는 사용자가 변경하여 입력하는 일정을 확인하고, 새롭게 결정된 일정을 토대로 상기 서버 컴퓨터로부터 다운로드받은 프로젝트 내 각 액티비티의 일정을 자동으로 재조정하는 단계, 그리고
(5) 상기 통신 단말기는, 일정관리도구를 통해 상기 (4) 단계에서 일정이 재조정된 프로젝트 내 각 액티비티들을 해당 날짜에 저장하여 일정관리를 수행하는 단계를 포함하며,
상기 (4) 단계는,
(4-1) 상기 통신 단말기는, 사용자의 조작을 확인하여 상기 서버 컴퓨터로부터 다운로드받은 프로젝트 내 각 액티비티의 일정 재조정이 선택되는지를 판단하는 단계,
(4-2) 상기 (4-1) 단계의 판단결과 일정 재조정이 선택되면, 상기 통신 단말기는 프로젝트 내 각 액티비티의 일정에서 가장 빠른 일자, 가장 늦은 일자 중 적어도 하나 이상을 화면상에 표시하는 단계,
(4-3) 상기 통신 단말기는, 사용자의 조작을 확인하여 가장 빠른 일자 또는 가장 늦은 일자 중 하나가 선택된 후 사용자 자신의 일정으로 변경되는지를 판단하는 단계, 그리고
(4-4) 상기 (4-3) 단계의 판단결과 가장 빠른 일자 또는 가장 늦은 일자 중 하나가 선택된 후 사용자 자신의 일정으로 변경되면, 상기 통신 단말기는 프로젝트 내 각 액티비티들의 일정과 사용자가 변경하기 전의 일정과의 간격을 계산한 후 변경된 사용자 자신의 일정을 토대로 동일 간격이 되도록 자동으로 재조정하는 단계를 포함하는 일정관리방법.
(1) The communication terminal makes a communication connection to a server computer that manages an individual activity to be used for schedule management or a project grouping related activities through a network communication network, and is generated on the server operator side or created and registered by other users. Performing a list check and retrieval of activities or projects,
(2) The server computer confirms the download selection of the specific activity or project of the user who performed the checking and retrieval of the list of activities or projects through the step (1), and if the download is selected, manages the schedule with the corresponding communication terminal. Downloading specific activities or projects to use,
(3) the communication terminal checking the user's operation to determine whether the utilization of the specific project downloaded from the server computer is selected;
(4) If the use of the project is selected as a result of the determination in step (3), the communication terminal checks the schedule inputted by the user, and schedules each activity in the project downloaded from the server computer based on the newly determined schedule. Recalibrate automatically, and
(5) the communication terminal, by performing a schedule management by storing each activity in the project rescheduled in the step (4) in the schedule management tool on the corresponding date,
Step (4) is,
(4-1) the communication terminal checking the user's operation to determine whether to reschedule each activity in the project downloaded from the server computer;
(4-2) If rescheduling is selected as a result of the determination in step (4-1), the communication terminal displays at least one or more of the earliest date and the latest date in the schedule of each activity in the project. ,
(4-3) the communication terminal checking the user's operation to determine whether one of the earliest date or the latest date is selected and then changed to the user's own schedule, and
(4-4) If one of the earliest date or the latest date is selected and changed to the user's own schedule after the determination of the step (4-3), the communication terminal changes the schedule and the user's schedule of each activity in the project. After calculating the interval with the previous schedule, the schedule management method comprising the step of automatically rescheduling the same interval based on the user's own schedule changed.
제 1 항에 있어서,
(6) 상기 서버 컴퓨터는, 상기 (1) 단계를 통해 액티비티 또는 프로젝트의 리스트 확인 및 검색을 수행한 사용자의 특정 프로젝트의 일정 재조정 및 다운로드 선택을 확인하고, 일정 재조정 및 다운로드가 선택되면 서버 운영자 측에서 생성하거나 다른 사용자들이 생성하여 커뮤니티에 등록한 프로젝트의 기존 일정을 자신의 일정에 따라 재조정하고, 일정이 재조정된 프로젝트를 해당 통신 단말기로 다운로드하는 단계, 그리고
(7) 상기 통신 단말기는, 일정관리도구를 통해 상기 (6) 단계에서 상기 서버 컴퓨터로부터 일정을 재조정한 후 다운로드받은 프로젝트 내 각 액티비티들을 해당 날짜에 저장하여 일정관리를 수행하는 단계를 더 수행하는 일정관리방법.
The method of claim 1,
(6) The server computer confirms the rescheduling and downloading selection of the specific project of the user who performed the checking and retrieval of the activity or the project list through the step (1), and if the rescheduling and downloading is selected, the server operator side Rescheduling an existing schedule of a project created by or created by other users and registered in the community according to their schedule, and downloading the rescheduled project to the corresponding communication terminal, and
(7) The communication terminal further performs a step of performing schedule management by rescheduling the schedule from the server computer in step (6) through a schedule management tool and storing each downloaded activity in the project on the corresponding date. How to manage your schedule.
제 1 항에 있어서,
상기 (5) 단계 이후,
(8) 상기 통신 단말기는, 계획된 일정의 실천 여부 확인을 위해 특정 프로젝트를 선택한 후 실천여부 확인기능이 작동되도록 설정하면, 일정관리도구를 통해 사용자의 조작을 확인하여 프로젝트 내 각 액티비티들의 실천 여부 체크를 확인하고, 실천 여부 체크 결과를 토대로 각 액티비티들의 수행 비율을 계산한 후, 수행 비율 결과를 화면상에 표시하는 단계를 더 수행하는 일정관리방법.
The method of claim 1,
After the step (5),
(8) When the communication terminal selects a specific project to confirm whether the scheduled schedule is implemented, and sets the execution status checking function to be activated, the user checks the operation of the user through the schedule management tool to check whether the activities in the project are implemented. After confirming, calculates the performance ratio of each activity based on the check result of the practice, and then performing the step of displaying the results of the performance ratio on the screen.
제 1 항에 있어서,
(9) 상기 (3) 단계의 판단결과 상기 서버 컴퓨터로부터 다운로드받은 특정 프로젝트의 활용이 아니면, 상기 통신 단말기는 상기 서버 컴퓨터로부터 다운로드받은 각 액티비티들 중 서로 연관 있는 액티비티들을 그룹화하여 프로젝트를 생성하는 것이 선택되는지를 판단하는 단계, 그리고
(10) 상기 (9) 단계의 판단결과 서로 연관 있는 액티비티들을 그룹화하여 프로젝트를 생성하는 것이 선택되면, 상기 통신 단말기는 사용자의 조작을 확인하여 상기 서버 컴퓨터로부터 다운로드받은 액티비티들 중 서로 연관 있는 액티비티를 그룹화한 후, 그룹화된 액티비티들의 기준이 되는 날짜가 결정되면 그룹 내 각 액티비티들의 일정을 계산하여 프로젝트를 생성하는 단계를 더 수행하는 일정관리방법.
The method of claim 1,
(9) If the determination result of step (3) does not utilize the specific project downloaded from the server computer, the communication terminal generates a project by grouping activities related to each other among the activities downloaded from the server computer. Determining whether it is selected, and
(10) As a result of the determination in step (9), if the grouping of activities related to each other is selected to generate a project, the communication terminal checks the user's operation and selects activities related to each other among the activities downloaded from the server computer. After grouping, if the date that is the basis of the grouped activities is determined, the schedule management method further comprises the step of generating a project by calculating the schedule of each activity in the group.
제 1 항에 있어서,
상기 액티비티는 구체적인 날짜 또는 어떤 날짜의 구체적인 시간에 어떠한 일을 수행할 것인지가 결정된 이벤트 정보이며, 상기 프로젝트는 서로 관련 있는 액티비티들을 그룹화한 것인 일정관리방법.
The method of claim 1,
The activity is event information that determines what to perform at a specific date or at a specific time of a certain date, wherein the project is a grouping of activities related to each other.
삭제delete 제 1 항에 있어서,
(4-5) 상기 (4-1) 단계의 판단결과 일정 재조정이 선택되면, 상기 통신 단말기는 상기 서버 컴퓨터로부터 다운로드받은 프로젝트 내 각 액티비티 중 어느 하나의 액티비티가 선택되는지를 판단하는 단계,
(4-6) 상기 (4-5) 단계의 판단결과 프로젝트 내 각 액티비티 중 어느 하나의 액티비티가 선택되면, 상기 통신 단말기는 사용자가 선택한 특정 액티비티의 일정을 자신의 일정으로 변경하는지를 판단하는 단계, 그리고
(4-7) 상기 (4-6) 단계의 판단결과 특정 액티비티의 일정을 자신의 일정으로 변경하면, 상기 통신 단말기는 동일한 프로젝트에 포함되어 있는 액티비티들 중 상기 (4-6) 단계를 통해 사용자 자신의 일정으로 변경된 액티비티 이후의 모든 액티비티의 일정을 변경된 일정을 토대로 변경되기 전 일정과 동일 간격이 되도록 재조정하는 단계를 더 수행하는 일정관리방법.
The method of claim 1,
(4-5) if rescheduling is selected as a result of the determination in step (4-1), the communication terminal determines which one of the activities in the project downloaded from the server computer is selected;
(4-6) if any one of the activities in the project is selected as a result of the determination in step (4-5), the communication terminal determines whether the schedule of the specific activity selected by the user is changed to the own schedule; And
(4-7) As a result of the determination in step (4-6), if the schedule of a specific activity is changed to its own schedule, the communication terminal is a user through the step (4-6) of the activities included in the same project. A schedule management method further comprising the step of rescheduling all activities after the activity changed to their own schedule to be the same interval as the schedule before the change based on the changed schedule.
제 1 항에 있어서,
(4-8) 상기 (4-1) 단계의 판단결과 일정 재조정이 선택되면, 상기 통신 단말기는 사용자의 조작을 확인하여 상기 서버 컴퓨터로부터 다운로드받은 프로젝트의 디데이로 사용될 자신의 일정이 입력되는지를 판단하는 단계, 그리고
(4-9) 상기 (4-8) 단계의 판단결과 디데이로 사용될 자신의 일정이 입력되면, 상기 통신 단말기는 프로젝트 내 각 액티비티의 일정을 사용자가 입력한 디데이를 기준으로 한 일정으로 변경하는 단계를 더 수행하는 일정관리방법.
The method of claim 1,
(4-8) If the reschedule is selected as a result of the determination in step (4-1), the communication terminal checks the user's operation to determine whether the user's schedule to be used as the D-day of the project downloaded from the server computer is input. To do, and
(4-9) If the schedule of the user to be used as the D-day is input as a result of the determination in the step (4-8), the communication terminal changes the schedule of each activity in the project to the schedule based on the D-day input by the user. How to do more scheduling.
제 8 항에 있어서,
상기 (4-9) 단계에서 사용자가 입력한 디데이를 기준으로 한 일정으로 변경되는 프로젝트 내 각 액티비티의 구체적 수행날짜는, 사용자의 조작에 따라 임의로 변경이 가능한 일정관리방법.
The method of claim 8,
A schedule management method in which the specific execution date of each activity in the project that is changed to a schedule based on the D-day input by the user in step (4-9) can be arbitrarily changed according to the user's operation.
제 1 항에 있어서,
상기 (4-1) 단계를 통해 상기 서버 컴퓨터로부터 다운로드받은 프로젝트 내 각 액티비티의 일정 재조정을 선택하기 이전에,
상기 통신 단말기는, 사용자의 조작에 따라 상기 서버 컴퓨터로부터 다운로드받은 프로젝트에 새로운 액티비티의 추가, 기존 액티비티의 삭제 또는 변경이 수행되면, 해당 프로젝트에 새로운 액티비티의 추가, 기존 액티비티의 삭제 또는 변경을 처리하는 일정관리방법.
The method of claim 1,
Before selecting to reschedule each activity in the project downloaded from the server computer through step (4-1),
When the communication terminal adds a new activity, deletes an existing activity, or changes an existing activity to a project downloaded from the server computer according to a user's operation, the communication terminal handles adding a new activity to the corresponding project, deleting an existing activity, or changing the existing activity. How to manage your schedule.
제 2 항에 있어서,
상기 (6) 단계는,
(6-1) 상기 서버 컴퓨터는, 상기 통신 단말기로부터 커뮤니티에 등록되어 있는 특정 프로젝트의 일정 재조정이 선택되는지를 판단하는 단계,
(6-2) 상기 (6-1) 단계의 판단결과 커뮤니티에 등록되어 있는 특정 프로젝트의 일정 재조정이 선택되면, 상기 서버 컴퓨터는 프로젝트 내 각 액티비티의 일정에서 가장 빠른 일자, 가장 늦은 일자 중 적어도 하나 이상을 상기 통신 단말기로 제공하는 단계,
(6-3) 상기 서버 컴퓨터는, 프로젝트 내 각 액티비티의 일정에서 가장 빠른 일자, 가장 늦은 일자 중 적어도 하나 이상을 확인한 상기 통신 단말기로부터 가장 빠른 일자 또는 가장 늦은 일자 중 하나가 선택된 후 사용자 자신의 일정으로 변경되는지를 판단하는 단계,
(6-4) 상기 (6-3) 단계의 판단결과 상기 통신 단말기로부터 가장 빠른 일자 또는 가장 늦은 일자 중 하나가 선택된 후 사용자 자신의 일정으로 변경되면, 상기 서버 컴퓨터는 프로젝트 내 각 액티비티들의 일정과 사용자가 변경하기 전의 일정과의 간격을 계산한 후 변경된 사용자 자신의 일정을 토대로 동일 간격이 되도록 자동으로 재조정하는 단계, 그리고
(6-5) 상기 서버 컴퓨터는, 일정이 재조정된 프로젝트를 해당 통신 단말기로 다운로드하는 단계를 포함하는 일정관리방법.
The method of claim 2,
In step (6),
(6-1) the server computer determining whether rescheduling of a specific project registered in the community from the communication terminal is selected;
(6-2) If the rescheduling of a specific project registered in the community is selected as a result of the determination in step (6-1), the server computer selects at least one of the earliest date and the latest date in the schedule of each activity in the project. Providing an abnormality to the communication terminal,
(6-3) The server computer selects one of the earliest date or the latest date from the communication terminal that has confirmed at least one or more of the earliest date and the latest date in the schedule of each activity in the project. Determining whether it changes to
(6-4) As a result of the determination in step (6-3), if one of the earliest date or the latest date is selected from the communication terminal and changed to the user's own schedule, the server computer checks the schedule of each activity in the project. Calculate the interval with the schedule before the user changes, and automatically readjust the same interval based on the changed schedule of the user; and
(6-5) The server computer, the schedule management method comprising the step of downloading the rescheduled project to the communication terminal.
제 11 항에 있어서,
(6-6) 상기 (6-1) 단계의 판단결과 커뮤니티에 등록되어 있는 특정 프로젝트의 일정 재조정이 선택되면, 상기 서버 컴퓨터는 상기 통신 단말기로부터 프로젝트 내 각 액티비티들 중 일자가 가장 빠른 액티비티를 실시할 사용자 자신의 일정을 입력받되, 입력 시점의 날짜를 제시한 후 사용자가 변경할 수 있도록 하는 단계, 그리고
(6-7) 상기 서버 컴퓨터는 상기 (6-6) 단계를 통해 상기 통신 단말기로부터 입력받은 날짜를 기준으로 프로젝트 내 각 액티비티의 일정을 재조정하는 단계를 더 수행하는 일정관리방법.
The method of claim 11,
(6-6) When the rescheduling of the specific project registered in the community is selected as the result of the determination in step (6-1), the server computer executes the earliest activity among the activities in the project from the communication terminal. Receiving a user's own schedule to be inputted, providing a date at the time of input, and allowing the user to change the schedule; and
(6-7) The server computer further performs the step of rescheduling each activity in the project based on the date received from the communication terminal through the step (6-6).
제 11 항에 있어서,
(6-8) 상기 (6-1) 단계의 판단결과 커뮤니티에 등록되어 있는 특정 프로젝트의 일정 재조정이 선택되면, 상기 서버 컴퓨터는 상기 통신 단말기로부터 프로젝트의 디데이로 사용될 자신의 일정이 입력되는지를 판단하는 단계, 그리고
(6-9) 상기 (6-8) 단계의 판단결과 상기 통신 단말기로부터 디데이로 사용될 자신의 일정이 입력되면, 상기 서버 컴퓨터는 프로젝트 내 각 액티비티의 일정을 상기 통신 단말기로부터 입력된 디데이를 기준으로 한 일정으로 변경하는 단계를 더 수행하는 일정관리방법.
The method of claim 11,
(6-8) If the rescheduling of a specific project registered in the community is selected as a result of the determination in step (6-1), the server computer determines whether its schedule to be used as a D-day of the project is input from the communication terminal. To do, and
(6-9) As a result of the determination in step (6-8), when a schedule of its own to be used as a D-day is input from the communication terminal, the server computer sets the schedule of each activity in the project based on the D-day input from the communication terminal. Schedule management method that performs more steps to change to one schedule.
제 3 항에 있어서,
상기 (8) 단계는,
(8-1) 상기 통신 단말기는, 계획된 일정의 실천 여부 확인을 위한 사용자의 특정 프로젝트 선택을 확인하여, 해당 프로젝트에 대한 실천여부 확인기능을 작동하도록 설정하는 단계,
(8-2) 상기 통신 단말기는, 사용자의 조작을 확인하여 구체적 실행날짜가 결정된 프로젝트 내 각 액티비티의 실천 여부를 확인하는 단계,
(8-3) 상기 통신 단말기는, 상기 (8-2) 단계에서 확인된 각 액티비티의 실천 여부 결과를 토대로 실제 수행 비율을 계산하는 단계,
(8-4) 상기 통신 단말기는, 상기 (8-3) 단계에서 계산된 각 액티비티의 수행 비율 결과를 사용자가 시각적으로 인식할 수 있는 수단으로 변환, 작성하는 단계, 그리고
(8-5) 상기 통신 단말기는, 상기 (8-4) 단계에서 시각적으로 인식할 수 있는 수단으로 변환, 작성된 각 액티비티의 수행 비율 결과를 화면상에 표시하는 단계를 포함하는 일정관리방법.
The method of claim 3, wherein
Step (8),
(8-1) the communication terminal checking the user's specific project selection for confirming whether or not the scheduled schedule is implemented, and setting a function of checking whether or not the project is implemented;
(8-2) the communication terminal checking the operation of the user to confirm whether or not each activity in the project whose specific execution date is determined is practiced;
(8-3) calculating, by the communication terminal, an actual performance ratio based on a result of whether each activity is confirmed in step (8-2);
(8-4) the communication terminal converting and creating the performance ratio result of each activity calculated in the step (8-3) into means that the user can visually recognize, and
(8-5) The schedule management method comprising the step of displaying, on the screen, the result of the performance ratio of each activity converted and created by means of visual recognition in the step (8-4).
제 14 항에 있어서,
상기 (8-2) 단계에서 프로젝트 내 각 액티비티의 실행 여부 확인은,
일정관리도구를 통해 일정관리를 수행하는 사용자의 각 액티비티별 실행 여부를 확인하는 클릭 조작 또는 각 액티비티별 시작시간과 종료시간 입력을 토대로 확인하는 일정관리방법.
15. The method of claim 14,
In step (8-2), it is checked whether each activity in the project is executed.
A schedule management method that checks based on a click operation for checking whether each calendar user executes a schedule through a calendar tool or inputting start and end times for each activity.
제 4 항에 있어서,
상기 (10) 단계는,
(10-1) 상기 통신 단말기는, 사용자의 조작을 확인하여 상기 서버 컴퓨터로부터 다운로드받은 각 액티비티들 중 서로 연관 있는 액티비티들이 선택되는지를 판단하는 단계,
(10-2) 판단결과 서로 연관 있는 액티비티들이 선택되면, 상기 통신 단말기는 해당 액티비티들을 그룹화하는 단계,
(10-3) 상기 통신 단말기는, 사용자의 조작을 확인하여 그룹화된 액티비티들의 기준이 되는 날짜가 결정되어 입력되는지를 판단하는 단계,
(10-4) 판단결과 그룹화된 액티비티들의 기준이 되는 날짜가 결정되면, 상기 통신 단말기는 결정된 기준이 되는 날짜를 기준으로 각 액티비티별 구체적 수행날짜를 계산하는 단계, 그리고
(10-5) 상기 통신 단말기는, 구체적 수행날짜가 계산된 각 액티비티들이 포함된 프로젝트를 생성하는 단계를 포함하는 일정관리방법.
The method of claim 4, wherein
Step (10),
(10-1) the communication terminal checking the user's operation to determine whether related activities among the activities downloaded from the server computer are selected;
(10-2) if the activities associated with each other are selected as a result of the determination, the communication terminal groups the corresponding activities;
(10-3) checking, by the communication terminal, a user's operation to determine whether a date serving as a reference for the grouped activities is determined and inputted;
(10-4) if it is determined that the reference date of the grouped activities is determined, the communication terminal calculates a specific execution date for each activity based on the determined reference date; and
(10-5) The communication terminal, the schedule management method comprising the step of generating a project containing each activity whose specific execution date is calculated.
제 1 항에 있어서,
상기 (5) 단계에서 구체적 실행날짜가 결정된 각 액티비티의 일정관리를 수행하는 상기 통신 단말기의 일정관리도구는,
언제 시작해서 언제 종료할지를 날짜로 관리하는 할 일 프로그램과, 어떤 날짜의 특정 시간에 어떤 일을 할지를 관리하는 일정 프로그램과, 아직 일정을 정하지 못한 일을 관리하는 메모 프로그램을 하나로 통합하여 관리하는 기능을 더 수행하는 일정관리방법.
The method of claim 1,
In the step (5), the schedule management tool of the communication terminal that performs the schedule management of each activity whose execution date is determined in detail,
A to-do program that manages when and when to start by date, a schedule program that manages what to do at a particular time of day, and a memo program that manages tasks not yet scheduled. How to do more scheduling.
제 1 항에 있어서,
상기 (1) 단계를 통해 상기 서버 컴퓨터에서 관리하는 서버 운영자 측에서 생성하거나 다른 사용자들이 생성하여 등록한 프로젝트는,
각 프로젝트별로 커뮤니티를 구성할 수 있으며,
각 프로젝트별 커뮤니티를 통해 각 통신 단말기는 상호간에 추가적인 일정이나 정보를 주고받을 수 있고, 상기 통신 단말기로부터 상기 프로젝트를 다운로드 받을 때 해당 프로젝트의 커뮤니티에 자동으로 가입하는 것에 대한 동의를 받고, 자동가입에 대한 동의를 수행한 해당 통신 단말기로 프로젝트를 다운로드할 때 반대 의사표시를 하지 않으면 프로젝트의 커뮤니티에 가입되도록 하는 일정관리방법.
The method of claim 1,
The project created by the server operator managed by the server computer through the step (1) or created and registered by other users,
You can organize your community by project.
Each communication terminal can exchange additional schedules or information with each other through the community of each project, and when receiving the project from the communication terminal, it is agreed to automatically join the community of the corresponding project. A schedule management method that allows a user to join the project's community if he / she does not disagree when downloading the project to the corresponding communication terminal that has agreed to the agreement.
(a) 통신 단말기는, 사용자의 조작을 확인하여 해당 사용자가 이전에 사용한 프로젝트 중 어느 하나의 프로젝트의 활용이 선택되는지를 판단하는 단계,
(b) 판단결과 이전에 사용한 프로젝트 중 어느 하나의 프로젝트의 활용이 선택되면, 상기 통신 단말기는 사용자가 변경하여 입력하는 일정을 확인하고, 새롭게 결정된 일정을 토대로 프로젝트 내 각 액티비티의 일정을 자동으로 재조정하는 단계, 그리고
(c) 상기 통신 단말기는, 일정관리도구를 통해 상기 (b) 단계에서 일정이 재조정된 프로젝트 내 각 액티비티들을 해당 날짜에 저장하여 일정관리를 수행하는 단계를 포함하며,
상기 (b) 단계는,
상기 통신 단말기는, 사용자의 조작을 확인하여 이전에 사용한 프로젝트 중 어느 하나의 프로젝트의 활용이 선택되는지를 판단하는 단계,
판단결과 이전에 사용한 프로젝트 중 어느 하나의 프로젝트의 활용이 선택되면, 상기 통신 단말기는 프로젝트 내 각 액티비티의 일정에서 가장 빠른 일자, 가장 늦은 일자 중 적어도 하나 이상을 화면상에 표시하는 단계,
상기 통신 단말기는, 사용자의 조작을 확인하여 가장 빠른 일자 또는 가장 늦은 일자 중 하나가 선택된 후 사용자 자신의 일정으로 변경되는지를 판단하는 단계, 그리고
판단결과 가장 빠른 일자 또는 가장 늦은 일자 중 하나가 선택된 후 사용자 자신의 일정으로 변경되면, 상기 통신 단말기는 프로젝트 내 각 액티비티들의 일정과 사용자가 변경하기 전의 일정과의 간격을 계산한 후 변경된 사용자 자신의 일정을 토대로 동일 간격이 되도록 자동으로 재조정하는 단계를 포함하는 일정관리방법.
(a) the communication terminal checking the operation of the user to determine which one of the projects previously used by the user is selected;
(b) If it is determined that the utilization of any one of the previously used projects is selected, the communication terminal checks the schedule inputted by the user and automatically reschedules each activity in the project based on the newly determined schedule. To do, and
(c) the communication terminal, performing a schedule management by storing each activity in the project whose schedule is rescheduled in the step (b) through a schedule management tool on a corresponding date;
The step (b)
Checking, by the communication terminal, a user's operation to determine which one of the previously used projects is selected;
If it is determined that the utilization of any one of the projects previously used is selected, the communication terminal displays at least one or more of the earliest date and the latest date in the schedule of each activity in the project,
Checking the user's operation to determine whether one of the earliest date or the latest date is selected and then changed to the user's own schedule; and
If it is determined that one of the earliest date or the latest date is selected and then changed to the user's own schedule, the communication terminal calculates the interval between the schedules of the activities in the project and the schedule before the user changes the user's changed schedule. A schedule management method comprising the step of automatically rescheduling the same interval based on the schedule.
제 1 항 내지 제 5 항, 제 7 항 내지 19 항의 방법 중 어느 한 항의 방법을 컴퓨터로 실행시킬 수 있는 컴퓨터 프로그램을 기록한 컴퓨터로 읽을 수 있는 기록매체.A computer-readable recording medium having recorded thereon a computer program capable of executing the method of any one of claims 1 to 5 and 7 to 19. 불특정 다수의 통신회선을 연결하여 상호간에 일정관리에 관련된 데이터 통신이 이루어지도록 하는 네트워크 통신망,
상기 네트워크 통신망을 통해 통신 접속된 서버 컴퓨터와 일정관리에 사용할 액티비티 또는 프로젝트의 리스트 확인, 검색을 수행하고, 사용자의 다운로드 선택에 따라 서버 컴퓨터로부터 특정 액티비티 또는 프로젝트를 다운로드받은 이후, 다운로드받은 프로젝트의 사용자가 입력하는 새롭게 결정된 일정을 토대로 상기 서버 컴퓨터로부터 다운로드받은 프로젝트 내 각 액티비티의 일정을 자동으로 재조정하거나, 또는 사용자의 서버 컴퓨터의 커뮤니티에 등록되어 있는 특정 프로젝트의 일정 재조정 후 다운로드 선택에 따라 서버 운영자 또는 타 사용자들이 등록한 서로 관련 있는 액티비티들을 그룹화한 프로젝트의 기존 일정을 자신의 일정에 따라 재조정한 이후, 일정이 재조정된 프로젝트를 서버 컴퓨터로부터 다운로드받으며, 일정관리도구를 통해 일정이 재조정된 프로젝트 내 각 액티비티들을 해당 날짜에 저장하거나 또는 일정을 재조정한 후 다운로드받은 프로젝트 내 각 액티비티들을 해당 날짜에 저장하여 일정관리를 수행하는 통신 단말기, 그리고
서버 컴퓨터 운영자 측에서 생성하거나 또는 다른 사용자들이 생성하여 등록한 일정관리에 사용하는 개별 액티비티 또는 서로 연관 있는 액티비티들을 그룹화한 프로젝트를 저장하고 있으며, 상기 네트워크 통신망을 통해 통신 접속된 상기 통신 단말기의 요청에 따라 개별 액티비티 또는 서로 연관 있는 액티비티들을 그룹화한 프로젝트의 다운로드를 처리하거나, 또는 서버 운영자 또는 타 사용자들이 생성하여 등록한 특정 프로젝트 내 각 액티비티의 기존 일정을 사용자 자신의 일정에 따라 재조정한 후 일정이 재조정된 프로젝트를 해당 통신 단말기로 다운로드하는 서버 컴퓨터를 포함하며,
상기 통신 단말기는, 사용자의 조작을 확인하여 상기 서버 컴퓨터로부터 다운로드받은 프로젝트의 일정 재조정이 선택되면, 해당 프로젝트 내 각 액티비티의 일정에서 가장 빠른 일자, 가장 늦은 일자 중 적어도 하나 이상을 화면상에 표시하며, 가장 빠른 일자 또는 가장 늦은 일자 중 하나가 선택된 후 사용자 자신의 일정으로 변경하면 프로젝트 내 각 액티비티들의 일정과 사용자가 변경하기 전의 일정과의 간격을 계산한 후 변경된 사용자 자신의 일정을 토대로 동일 간격이 되도록 자동으로 재조정하는 일정관리장치.
A network communication network which connects a plurality of unspecified communication lines to perform data communication related to schedule management between each other;
The user of the downloaded project after checking and searching a list of activities or projects to be used for schedule management and server computer connected through the network communication network, and downloading a specific activity or project from the server computer according to the user's download selection. Automatically reschedule each activity in the project downloaded from the server computer based on the newly determined schedule entered by the server, or after rescheduling a specific project registered in the community of the user's server computer. After rescheduling the existing schedule of the project grouping related activities registered by other users according to their own schedule, the rescheduled project is downloaded from the server computer and the schedule management tool is downloaded. Communication terminal that performs the schedule management by storing each activity in the rescheduled project through the corresponding date through the rescheduled project or storing the downloaded activity in the corresponding date after rescheduling, and
It stores individual activities or groups of related activities that are created by the server computer operator or used for scheduling created by other users, and are grouped with each other, and according to the request of the communication terminal connected through the network communication network. A rescheduled project that handles the download of a project that groups individual activities or groups of related activities, or reschedules an existing schedule for each activity in a specific project created and registered by a server administrator or other users, according to your own schedule. It includes a server computer for downloading the to the communication terminal,
The communication terminal, when rescheduling of the project downloaded from the server computer is selected by confirming the user's operation, displays at least one of the earliest date and the latest date in the schedule of each activity in the project on the screen. If you change to your own schedule after one of the earliest or latest dates is selected, you can calculate the interval between the activities of each activity in the project and the schedule before you make changes, and then change the same interval based on your own schedule. A scheduler that automatically readjusts as much as possible.
제 21 항에 있어서,
상기 통신 단말기는,
계획된 일정의 실천 여부 확인을 위해 특정 프로젝트를 선택한 후 실천여부 확인기능이 작동되도록 설정하면, 일정관리도구를 통해 일정관리를 수행중인 프로젝트 내 각 액티비티들의 실천 여부 체크를 확인하고, 실천 여부 체크 결과를 토대로 각 액티비티들의 수행 비율을 계산하며, 계산된 수행 비율 결과를 문자나 그림으로 변환하여 화면상에 표시하는 기능을 더 수행하는 일정관리장치.
22. The method of claim 21,
The communication terminal includes:
If you select a specific project to check the execution of the planned schedule and set the action check function to work, check the activity check of each activity in the project that is performing the schedule management through the schedule management tool, and check the result of the execution check. A schedule management device that calculates the performance ratio of each activity based on the above, and performs the function of converting the calculated performance ratio result into a text or a picture and displaying it on the screen.
제 21 항에 있어서,
상기 통신 단말기는,
사용자의 조작에 따라 상기 서버 컴퓨터로부터 다운로드받은 각 액티비티들 중 서로 연관 있는 액티비티들을 그룹화하여 프로젝트를 생성하는 것이 선택되면, 상기 서버 컴퓨터로부터 다운로드받은 액티비티들 중 서로 연관 있는 액티비티를 그룹화한 후, 그룹화된 액티비티들의 기준이 되는 날짜가 결정되면 그룹 내 각 액티비티들의 일정을 계산하여 프로젝트를 생성하며, 일정관리도구를 통해 프로젝트 내 각 액티비티들을 해당 날짜에 저장하여 일정관리를 수행하는 기능을 더 수행하는 일정관리장치.
22. The method of claim 21,
The communication terminal includes:
According to the user's manipulation, if the group is selected to create a project by grouping related activities among the activities downloaded from the server computer, the grouped activities among the activities downloaded from the server computer are grouped and then grouped. When the date of the activities is decided, the schedule is generated by calculating the schedule of each activity in the group, and the schedule management tool stores the activities in the project on the corresponding date through the schedule management tool to perform the schedule management function. Device.
제 21 항에 있어서,
상기 서버 컴퓨터에 등록된 액티비티와 프로젝트는,
구체적인 날짜 또는 어떤 날짜의 구체적인 시간에 어떠한 일을 수행할 것인지가 결정된 이벤트 정보와, 서로 관련 있는 액티비티들을 그룹화한 것인 일정관리장치.
22. The method of claim 21,
Activities and projects registered on the server computer,
The schedule management apparatus is a grouping of activities related to the event information determined to be performed at a specific date or at a specific time of the date and related activities.
제 21 항에 있어서,
상기 통신 단말기는,
상기 네트워크 통신망을 통해 통신 접속된 상기 서버 컴퓨터와 일정관리에 사용할 액티비티 또는 프로젝트의 리스트 확인 및 검색, 서버 운영자 또는 타 사용자들이 등록한 특정 액티비티 또는 서로 관련 있는 액티비티들을 그룹화한 프로젝트의 다운로드, 서버 컴퓨터에서 사용자가 직접 일정을 재조정한 특정 프로젝트의 다운로드와 관련된 데이터 송수신을 처리하는 데이터 통신부,
상기 서버 컴퓨터로부터 다운로드받은 특정 프로젝트의 활용을 선택한 사용자의 조작에 따라 해당 프로젝트의 새로운 일정이 결정되면, 새롭게 결정된 일정을 토대로 상기 서버 컴퓨터로부터 다운로드받은 프로젝트 내 각 액티비티의 일정을 자동으로 재조정하되, 사용자의 조작을 확인하여 상기 서버 컴퓨터로부터 다운로드받은 프로젝트의 일정 재조정이 선택되면 해당 프로젝트 내 각 액티비티의 일정에서 가장 빠른 일자, 가장 늦은 일자 중 적어도 하나 이상을 화면상에 표시하고 가장 빠른 일자 또는 가장 늦은 일자 중 하나가 선택된 후 사용자 자신의 일정으로 변경하면 프로젝트 내 각 액티비티들의 일정과 사용자가 변경하기 전의 일정과의 간격을 계산한 후 변경된 사용자 자신의 일정을 토대로 동일 간격이 되도록 자동으로 재조정하며, 상기 서버 컴퓨터에 통신 접속된 사용자의 조작에 따라 서버 운영자 또는 타 사용자들이 등록한 서로 관련 있는 액티비티들을 그룹화한 프로젝트의 기존 일정을 자신의 일정에 따라 재조정한 이후, 일정이 재조정된 프로젝트를 서버 컴퓨터로부터 다운로드받는 프로젝트 관리부,
상기 서버 컴퓨터로부터 다운로드받은 액티비티를 그룹화하는 프로젝트 생성을 선택한 사용자의 조작에 따라 각 액티비티들 중 서로 연관 있는 액티비티를 그룹화하고, 사용자에 의해 그룹화된 액티비티들의 기준이 되는 날짜가 결정되면 해당 날짜에 따라 그룹 내 각 액티비티들의 일정을 계산하여 프로젝트를 생성하는 액티비티 관리부,
상기 프로젝트 관리부에서 재조정된 프로젝트 내 각 액티비티들을 해당 날짜에 저장하여 일정관리를 수행하거나 또는 상기 서버 컴퓨터의 커뮤니티에 등록된 특정 프로젝트의 일정을 재조정한 이후 다운로드받은 특정 프로젝트 내 각 액티비티들을 해당 날짜에 저장하여 일정관리를 수행하고, 상기 액티비티 관리부에서 생성된 프로젝트 내 각 액티비티들을 해당 날짜에 저장하여 일정관리를 수행하며, 특정 프로젝트를 선택한 후 실천여부 확인기능이 작동되도록 설정할 수 있는 일정관리부,
상기 서버 컴퓨터로부터 다운로드받은 개별 액티비티 및 프로젝트를 저장하고 있고, 상기 서버 컴퓨터에서 사용자가 직접 일정을 재조정한 후 다운로드받은 특정 프로젝트를 저장하고 있으며, 상기 프로젝트 관리부에서 일정이 재조정된 프로젝트와 상기 액티비티 관리부에서 생성된 프로젝트를 저장하는 저장부,
상기 일정관리부의 제어에 따라 일정 수행중인 프로젝트 내 각 액티비티들의 실천 여부 체크를 확인하고, 실천 여부 체크 결과를 토대로 각 액티비티들의 수행 비율을 계산하며, 계산된 수행 비율 결과를 문자나 그림으로 변환하여 화면상에 표시하는 일정수행 확인부, 그리고
상기 네트워크 통신망을 통해 통신 접속된 상기 서버 컴퓨터와의 일정관리에 사용할 액티비티 또는 프로젝트의 리스트 확인 및 검색, 특정 액티비티 또는 서로 관련 있는 액티비티들을 그룹화한 프로젝트의 다운로드, 상기 서버 컴퓨터에서 사용자가 직접 일정을 재조정한 특정 프로젝트의 다운로드를 제어하고, 사용자의 선택을 토대로 상기 서버 컴퓨터로부터 다운로드받은 특정 프로젝트의 활용 또는 상기 서버 컴퓨터의 커뮤니티를 통한 특정 프로젝트의 일정 재조정 및 다운로드, 상기 서버 컴퓨터로부터 다운로드받은 액티비티를 그룹화하는 프로젝트 생성을 제어하며, 상기 프로젝트 관리부에서 일정이 재조정된 프로젝트 내의 각 액티비티 또는 상기 서버 컴퓨터의 커뮤니티에 등록된 특정 프로젝트의 일정을 재조정한 이후 다운로드받은 특정 프로젝트 내의 각 액티비티, 상기 액티비티 관리부에서 생성된 서로 연관 있는 액티비티들을 그룹화한 프로젝트 내의 각 액티비티에 대한 상기 일정관리부에서의 일정관리 수행을 제어하는 제어부를 포함하는 일정관리장치.
22. The method of claim 21,
The communication terminal includes:
Check and search the list of activities or projects to be used for the schedule management with the server computer connected through the network communication network, download a project grouping specific activities or related activities registered by the server operator or other users, user on the server computer Communication unit that handles data transmission and reception related to the download of a specific project which has been manually rescheduled
When a new schedule of the project is determined according to the operation of a user who has selected to utilize a specific project downloaded from the server computer, the schedule of each activity in the project downloaded from the server computer is automatically rescheduled based on the newly determined schedule. When the reschedule of the project downloaded from the server computer is selected by checking the operation of, the at least one of the earliest date and the latest date in the schedule of each activity in the project is displayed on the screen, and the earliest date or the latest date is displayed. If one is selected and changed to the user's own schedule, the schedule between each activity in the project and the schedule before the change is calculated, and automatically adjusted to be the same interval based on the changed user's schedule. After rescheduling the existing schedule of the project grouping related activities registered by the server administrator or other users according to the user's schedule according to the user's operation connected to the server computer, the rescheduled project is downloaded from the server computer. Project Management Department,
Group activities related to each other among the activities according to the operation of the user who selects the project creation to group the activities downloaded from the server computer, and if the date to be the basis of the activities grouped by the user is determined, the group according to the corresponding date Activity management unit that generates a project by calculating the schedule of each activity in the activity,
The project management unit stores the activities in the rescheduled project on the corresponding date to perform the schedule management, or stores the activities in the specific project downloaded after the rescheduling of the specific project registered in the community of the server computer on the corresponding date. A schedule management unit that performs schedule management, stores each activity in the project generated by the activity management unit on a corresponding date, and performs schedule management, and selects a specific project and sets a function to check whether or not to implement the schedule management unit.
It stores individual activities and projects downloaded from the server computer, and saves a specific project downloaded after the user reschedules the server computer directly, and in the project management unit the rescheduled project and the activity management unit Storage unit for storing the generated project,
Under the control of the schedule management unit, checks whether each activity in the schedule is being executed, calculates the execution rate of each activity based on the result of the execution check, converts the calculated execution rate result into a character or a picture, and displays the screen. Schedule performance confirmation unit to be displayed on, and
Check and search the list of activities or projects to be used for scheduling with the server computer connected through the network communication network, download a project grouping specific activities or related activities, and reschedule the user directly on the server computer. Controlling the download of a specific project, utilizing the specific project downloaded from the server computer or rescheduling and downloading a specific project through the server computer's community, and grouping activities downloaded from the server computer based on the user's selection Controls project creation, and downloads after the project management unit reschedules a specific project registered in each activity in the rescheduled project or the community of the server computer And a control unit for controlling the schedule management in the schedule management unit for each activity in the project grouping each activity in the project and activities related to each other generated by the activity management unit.
삭제delete 제 25 항에 있어서,
상기 프로젝트 관리부는,
사용자의 조작을 확인하여 상기 서버 컴퓨터로부터 다운로드받은 프로젝트의 일정 재조정이 선택되면, 상기 서버 컴퓨터로부터 다운로드받은 프로젝트 내 각 액티비티 중 어느 하나의 액티비티가 선택되는지를 판단하며, 프로젝트 내 각 액티비티 중 어느 하나의 액티비티가 선택되면 사용자가 선택한 특정 액티비티의 일정을 자신의 일정으로 변경하는지를 확인한 후 사용자 자신의 일정으로 변경된 액티비티 이후의 모든 액티비티의 일정을 변경된 일정을 토대로 동일 간격이 되도록 재조정하는 일정관리장치.
The method of claim 25,
The project management unit,
When rescheduling of the project downloaded from the server computer is selected by checking the user's operation, it is determined whether one of the activities in the project downloaded from the server computer is selected, and any one of the activities in the project is selected. When an activity is selected, the scheduler checks whether the user changes the schedule of the selected activity to his or her own schedule, and then reschedules all activities after the activity changed to the user's own schedule to have the same interval based on the changed schedule.
제 25 항에 있어서,
상기 프로젝트 관리부는,
사용자의 조작을 확인하여 상기 서버 컴퓨터로부터 다운로드받은 프로젝트의 일정 재조정이 선택되면, 상기 서버 컴퓨터로부터 다운로드받은 프로젝트의 디데이로 사용될 자신의 일정이 입력되는지를 판단하며, 디데이로 사용될 자신의 일정이 입력되면 프로젝트 내 각 액티비티의 일정을 사용자가 입력한 디데이를 기준으로 한 일정으로 변경하는 일정관리장치.
The method of claim 25,
The project management unit,
When rescheduling of the project downloaded from the server computer is selected by checking the user's operation, it is determined whether the user's schedule to be used as the D-day of the project downloaded from the server computer is inputted. A scheduler that changes the schedule of each activity in the project to a schedule based on the D-day entered by the user.
제 25 항에 있어서,
상기 프로젝트 관리부는,
사용자의 입력조작에 의해 새롭게 결정된 디데이를 기준으로 각 액티비티의 구체적 수행날짜를 자동으로 재조정할 때, 각 액티비티별로 사용자가 임의로 일정을 변경할 수 있는 일정관리장치.
The method of claim 25,
The project management unit,
A schedule management device that allows the user to arbitrarily change the schedule for each activity when the specific execution date of each activity is automatically readjusted based on the D-day newly determined by the user's input operation.
제 25 항에 있어서,
상기 프로젝트 관리부는,
상기 서버 컴퓨터로부터 다운로드받은 프로젝트 내 각 액티비티의 일정 재조정을 수행하기 이전에, 사용자의 조작에 따라 상기 서버 컴퓨터로부터 다운로드받은 프로젝트에 새로운 액티비티의 추가, 기존 액티비티의 삭제 또는 변경이 수행되면, 해당 프로젝트에 새로운 액티비티의 추가, 기존 액티비티의 삭제 또는 변경을 처리하는 기능을 더 수행하는 일정관리장치.
The method of claim 25,
The project management unit,
Before rescheduling each activity in the project downloaded from the server computer, if a new activity is added to the project downloaded from the server computer, the existing activity is deleted or changed, A calendar device that further handles the addition of new activities, deletion or changes to existing activities.
제 21 항에 있어서,
상기 서버 컴퓨터는,
상기 네트워크 통신망을 통해 통신 접속된 상기 통신 단말기와 일정관리에 사용할 액티비티 또는 프로젝트의 리스트 확인 및 검색, 서버 운영자 또는 타 사용자들이 등록한 특정 액티비티 또는 서로 관련 있는 액티비티들을 그룹화한 프로젝트의 다운로드, 상기 서버 컴퓨터에서 사용자가 직접 일정을 재조정한 특정 프로젝트의 다운로드와 관련된 데이터 송수신을 처리하는 통신부,
운영자 또는 각 통신 단말기로부터 제공되는 일정관리에 사용하는 개별 액티비티 또는 서로 연관 있는 액티비티들을 그룹화한 프로젝트의 등록을 처리하며, 상기 통신 단말기의 요청에 따른 등록된 액티비티 또는 프로젝트의 리스트 확인 및 검색을 처리하는 커뮤니티 관리부,
상기 커뮤니티 관리부를 통해 서버 운영자 측에서 생성하거나 또는 다른 사용자들이 생성하여 등록한 프로젝트를 확인한 상기 통신 단말기의 특정 프로젝트의 일정 재조정 선택에 따라 해당 프로젝트 내 각 액티비티의 기존 일정을 사용자 자신이 입력하는 일정에 따라 재조정하는 프로젝트 재조정부,
상기 커뮤니티 관리부를 통해 리스트 확인 및 검색을 수행한 상기 통신 단말기의 요청에 따라 일정관리에 사용할 특정 액티비티 또는 프로젝트를 해당 통신 단말기로 다운로드하며, 상기 프로젝트 재조정부를 통해 사용자 자신이 입력한 일정에 따라 일정이 재조정된 프로젝트를 해당 통신 단말기로 다운로드하는 다운로드 처리부,
일정관리를 이용하는 각 통신 단말기의 회원 정보 및 다운로드 정보, 상기 커뮤니티 관리부를 통해 운영자 또는 각 통신 단말기로부터 등록되는 일정관리에 사용할 개별 액티비티 또는 서로 연관 있는 액티비티들을 그룹화한 프로젝트를 저장하는 데이터베이스, 그리고
상기 커뮤니티 관리부를 통해 운영자 측에서 직접 생성하거나 또는 각 통신 단말기로부터 제공되는 일정관리에 사용하는 개별 액티비티 또는 서로 연관 있는 액티비티들을 그룹화한 프로젝트의 등록 및 데이터베이스 저장을 제어하며, 상기 통신 단말기와의 일정관리에 사용할 액티비티 또는 프로젝트의 리스트 확인 및 검색, 개별 액티비티 또는 서로 연관 있는 액티비티들을 그룹화한 프로젝트의 다운로드 처리, 또는 서버 운영자나 타 사용자들이 생성하여 커뮤니티에 등록한 특정 프로젝트 내의 각 액티비티의 기존 일정을 사용자 자신의 일정에 따른 재조정 및 일정이 재조정된 프로젝트의 다운로드 처리를 제어하는 제어부를 포함하는 일정관리장치.
22. The method of claim 21,
The server computer,
Checking and retrieving a list of activities or projects to be used for schedule management with the communication terminal connected through the network communication network, downloading a project grouping specific activities or related activities registered by a server operator or other users, at the server computer Communication unit for handling data transmission and reception related to the download of a specific project that the user rescheduled,
It handles the registration of projects that group individual activities or related activities to be used for schedule management provided from the operator or each communication terminal, and processes the checking and retrieval of the list of registered activities or projects according to the request of the communication terminal. Community Management,
According to the schedule that the user inputs the existing schedule of each activity in the corresponding project according to the rescheduling selection of the specific project of the communication terminal which the server operator side created through the community manager or the other users created and registered Rebalancing project rebalancing,
The specific activity or project to be used for schedule management is downloaded to the corresponding communication terminal according to the request of the communication terminal which has performed a list check and search through the community manager, and the schedule is adjusted according to the schedule input by the user through the project readjustment unit. A download processing unit for downloading the readjusted project to the communication terminal;
Membership and download information of each communication terminal using a schedule management, a database for storing a project grouping the individual activities or related activities to be used for the schedule management registered from the operator or each communication terminal through the community management unit, and
Control the registration and database storage of individual activities or groups of activities related to each other that are generated by the operator directly or used in the schedule management provided from each communication terminal through the community management unit, and schedule management with the communication terminal View and retrieve a list of activities or projects to be used in the project, process downloads of individual activities or groups of related activities, or create an existing schedule for each activity in a specific project created by a server administrator or other user and registered with the community. And a control unit for controlling rescheduling according to a schedule and downloading processing of the rescheduled project.
제 31 항에 있어서,
상기 프로젝트 재조정부는,
상기 통신 단말기로부터 커뮤니티에 등록되어 있는 특정 프로젝트의 일정 재조정이 선택되면, 프로젝트 내 각 액티비티의 일정에서 가장 빠른 일자, 가장 늦은 일자 중 적어도 하나 이상을 상기 통신 단말기로 제공하며, 상기 통신 단말기로부터 가장 빠른 일자 또는 가장 늦은 일자 중 하나가 선택된 후 사용자 자신의 일정으로 변경되면 프로젝트 내 각 액티비티들의 일정과 사용자가 변경하기 전의 일정과의 간격을 계산한 후 변경된 사용자 자신의 일정을 토대로 동일 간격이 되도록 자동으로 재조정하여 상기 다운로드 처리부를 통해 해당 통신 단말기로 다운로드되도록 하는 일정관리장치.
The method of claim 31, wherein
The project readjustment unit,
If rescheduling of a particular project registered in the community is selected from the communication terminal, at least one of the earliest date and the latest date in the schedule of each activity in the project is provided to the communication terminal, and the earliest from the communication terminal. If a date or one of the latest dates is selected and then changed to your own schedule, the time between each activity in the project and the schedule before the change is calculated, and automatically adjusted to be the same interval based on your changed schedule. And reschedule to download to the communication terminal through the download processing unit.
제 31 항에 있어서,
상기 프로젝트 재조정부는,
상기 통신 단말기로부터 커뮤니티에 등록되어 있는 특정 프로젝트의 일정 재조정이 선택되면, 상기 통신 단말기로부터 프로젝트 내 각 액티비티들 중 일자가 가장 빠른 액티비티를 실시할 사용자 자신의 일정을 입력받되, 입력 시점의 날짜를 제시한 후 사용자가 변경할 수 있도록 하며, 상기 통신 단말기로부터 입력받은 날짜를 기준으로 프로젝트 내 각 액티비티의 일정을 재조정하여 상기 다운로드 처리부를 통해 해당 통신 단말기로 다운로드되도록 하는 일정관리장치.
The method of claim 31, wherein
The project readjustment unit,
If the schedule rescheduling of a specific project registered in the community is selected from the communication terminal, the user receives the schedule of the user who will execute the earliest activity among the activities in the project from the communication terminal and presents the date of the input time. And then allow the user to change and reschedule each activity in the project on the basis of the date received from the communication terminal to be downloaded to the communication terminal through the download processing unit.
제 31 항에 있어서,
상기 프로젝트 재조정부는,
상기 통신 단말기로부터 커뮤니티에 등록되어 있는 특정 프로젝트의 일정 재조정이 선택되면, 상기 통신 단말기로부터 프로젝트의 디데이로 사용될 자신의 일정이 입력되는지를 판단하며, 상기 통신 단말기로부터 디데이로 사용될 자신의 일정이 입력되면 프로젝트 내 각 액티비티의 일정을 상기 통신 단말기로부터 입력된 디데이를 기준으로 한 일정으로 변경하여 상기 다운로드 처리부를 통해 해당 통신 단말기로 다운로드되도록 하는 일정관리장치.
The method of claim 31, wherein
The project readjustment unit,
If rescheduling of a particular project registered in the community is selected from the communication terminal, it is determined whether the own schedule to be used as the D-day of the project is input from the communication terminal, and if the schedule to be used as the D-day is input from the communication terminal. A schedule management device for changing the schedule of each activity in the project to a schedule based on the D-day input from the communication terminal to be downloaded to the communication terminal through the download processing unit.
제 21 항에 있어서,
상기 통신 단말기의 일정관리도구는,
구체적 실행날짜가 결정된 각 액티비티의 일정관리를 수행하는 기능을 수행함과 동시에, 언제 시작해서 언제 종료할지를 날짜로 관리하는 할 일 프로그램과, 어떤 날짜의 특정 시간에 어떤 일을 할지를 관리하는 일정 프로그램과, 아직 일정을 정하지 못한 일을 관리하는 메모 프로그램을 하나의 프로그램으로 통합, 관리하는 일정관리장치.
22. The method of claim 21,
The schedule management tool of the communication terminal,
A to-do program that manages the activities of each activity whose execution date is determined in detail, a to-do program that manages when and when to start a date, a schedule program that manages what to do at a particular time of day, and Schedule management device that integrates and manages a memo program that manages work that has not yet been scheduled.
제 21 항에 있어서,
상기 서버 컴퓨터는,
서버 운영자 측에서 생성하거나 다른 사용자들이 생성하여 등록한 각각의 프로젝트별로 커뮤니티를 구성하는 기능을 더 수행할 수 있으며,
각 프로젝트별 커뮤니티를 통해 각 통신 단말기는 상호간에 추가적인 일정이나 정보를 주고받을 수 있고, 상기 통신 단말기로부터 상기 프로젝트를 다운로드 받을 때 해당 프로젝트의 커뮤니티에 자동으로 가입하는 것에 대한 동의를 받고, 자동가입에 대한 동의를 수행한 해당 통신 단말기로 프로젝트를 다운로드할 때 반대 의사표시를 하지 않으면 프로젝트의 커뮤니티에 가입되도록 하는 일정관리장치.
22. The method of claim 21,
The server computer,
It is possible to perform community function for each project that is created by server administrator or created and registered by other users.
Each communication terminal can exchange additional schedules or information with each other through the community of each project, and when receiving the project from the communication terminal, it is agreed to automatically join the community of the corresponding project. A scheduler that allows a user to join the project's community unless he or she disagrees with the download of the project to the corresponding communication terminal that has agreed to the agreement.
제 21 항에 있어서,
상기 통신 단말기는,
사용자의 조작에 따라 해당 사용자가 이전에 사용한 프로젝트 중 어느 하나의 프로젝트의 활용이 선택되면, 프로젝트 내 각 액티비티의 일정에서 가장 빠른 일자, 가장 늦은 일자 중 적어도 하나 이상을 화면상에 표시하고, 가장 빠른 일자 또는 가장 늦은 일자 중 하나가 선택되어 사용자 자신의 일정으로 변경되면, 프로젝트 내 각 액티비티들의 일정과 사용자가 변경하기 전의 일정과의 간격을 계산한 후 변경된 사용자 자신의 일정을 토대로 동일 간격이 되도록 자동으로 재조정하며, 일정관리도구를 통해 일정이 재조정된 프로젝트 내 각 액티비티들을 해당 날짜에 저장하여 일정관리를 수행하는 일정관리장치.
22. The method of claim 21,
The communication terminal includes:
According to the user's operation, if the utilization of one of the projects previously used by the user is selected, at least one of the earliest date and the latest date in the schedule of each activity in the project is displayed on the screen, and the fastest If a date or one of the latest dates is selected and changed to your own schedule, the schedule between each activity in the project and the schedule before the change is automatically calculated and automatically adjusted to be the same interval based on the changed user's schedule. It is a schedule management device that schedules by rescheduling and storing each activity in the rescheduled project through the schedule management tool on the corresponding date.
KR1020120046436A 2012-05-02 2012-05-02 Method of schedule management and apparatus thereof KR101230462B1 (en)

Priority Applications (2)

Application Number Priority Date Filing Date Title
KR1020120046436A KR101230462B1 (en) 2012-05-02 2012-05-02 Method of schedule management and apparatus thereof
PCT/KR2013/002820 WO2013165099A1 (en) 2012-05-02 2013-04-04 Scheduling method and apparatus therefor

Applications Claiming Priority (1)

Application Number Priority Date Filing Date Title
KR1020120046436A KR101230462B1 (en) 2012-05-02 2012-05-02 Method of schedule management and apparatus thereof

Publications (1)

Publication Number Publication Date
KR101230462B1 true KR101230462B1 (en) 2013-02-06

Family

ID=47899012

Family Applications (1)

Application Number Title Priority Date Filing Date
KR1020120046436A KR101230462B1 (en) 2012-05-02 2012-05-02 Method of schedule management and apparatus thereof

Country Status (2)

Country Link
KR (1) KR101230462B1 (en)
WO (1) WO2013165099A1 (en)

Cited By (3)

* Cited by examiner, † Cited by third party
Publication number Priority date Publication date Assignee Title
WO2015142136A1 (en) * 2014-03-21 2015-09-24 삼성전자 주식회사 Method for collecting multimedia information and device therefor
KR20160142537A (en) 2015-06-03 2016-12-13 주식회사 에스이든 Project control and cutover management system
WO2017039029A1 (en) * 2015-08-28 2017-03-09 주식회사 코노랩스 Method, system and non-temporary computer-readable recording medium for supporting schedule management

Families Citing this family (3)

* Cited by examiner, † Cited by third party
Publication number Priority date Publication date Assignee Title
US9794387B1 (en) 2016-12-13 2017-10-17 Sorenson Ip Holdings, Llc Automatically establishing a communication session associated with an event
US11494744B2 (en) * 2019-11-28 2022-11-08 Ricoh Company, Ltd. Information processing apparatus, information processing system, and information processing method
KR102478301B1 (en) * 2022-08-05 2022-12-19 (주)시지태테크놀러지 Method for reusing task information

Citations (2)

* Cited by examiner, † Cited by third party
Publication number Priority date Publication date Assignee Title
KR20090062417A (en) * 2007-12-13 2009-06-17 대림산업 주식회사 All working process management system of all working process using e.v.m.s progrem
KR100968708B1 (en) * 2010-04-08 2010-07-06 지에스건설 주식회사 System and method to creation of the construction project schedule

Family Cites Families (2)

* Cited by examiner, † Cited by third party
Publication number Priority date Publication date Assignee Title
KR20070023286A (en) * 2005-08-24 2007-02-28 주식회사 팬택 Apparatus and Method for administrating schedule information
KR100817285B1 (en) * 2005-12-29 2008-03-27 엘지전자 주식회사 Method for managing associated schedule and mobile phone using the same

Patent Citations (2)

* Cited by examiner, † Cited by third party
Publication number Priority date Publication date Assignee Title
KR20090062417A (en) * 2007-12-13 2009-06-17 대림산업 주식회사 All working process management system of all working process using e.v.m.s progrem
KR100968708B1 (en) * 2010-04-08 2010-07-06 지에스건설 주식회사 System and method to creation of the construction project schedule

Cited By (6)

* Cited by examiner, † Cited by third party
Publication number Priority date Publication date Assignee Title
WO2015142136A1 (en) * 2014-03-21 2015-09-24 삼성전자 주식회사 Method for collecting multimedia information and device therefor
KR20170015408A (en) * 2014-03-21 2017-02-08 삼성전자주식회사 Method for collection multimedia information and device thereof
KR101871366B1 (en) * 2014-03-21 2018-06-26 삼성전자주식회사 Method for collection multimedia information and device thereof
US10509818B2 (en) 2014-03-21 2019-12-17 Samsung Electronics Co., Ltd. Method for collecting multimedia information and device thereof
KR20160142537A (en) 2015-06-03 2016-12-13 주식회사 에스이든 Project control and cutover management system
WO2017039029A1 (en) * 2015-08-28 2017-03-09 주식회사 코노랩스 Method, system and non-temporary computer-readable recording medium for supporting schedule management

Also Published As

Publication number Publication date
WO2013165099A1 (en) 2013-11-07

Similar Documents

Publication Publication Date Title
KR101230462B1 (en) Method of schedule management and apparatus thereof
US8200520B2 (en) Methods, systems, and apparatuses for automated confirmations of meetings
US9659260B2 (en) Calendar based task and time management systems and methods
US20150347987A1 (en) Integrated Daily Digital Planner
CN109906463A (en) Improved efficiency in task management application
US20070250370A1 (en) Scheduling application and distribution method
US20090006161A1 (en) Systems and methods for managing events of event scheduling applications
US20080178105A1 (en) System and method for planning student assignments
US20030076353A1 (en) Graphical user interface for collaboration
US20090248480A1 (en) Controlled synchronization between a group calendar and individual work calendars
JPH0628361A (en) Apparatus and method for data processing
JPWO2006097971A1 (en) Career development system
JPH01171059A (en) Demanding of status of schedule on system
US20170337501A1 (en) System and method for coordinating and controlling production processes and inter-related decision making processes
US20140278653A1 (en) Method And System For Optimizing Field Service Appoint Scheduling
US9378476B1 (en) Method and apparatus for real time automated intelligent self-scheduling
US20080065447A1 (en) Interactive and Incremental Event Scheduling
WO2015039209A1 (en) Computer networked calendar
KR20210010256A (en) Group information collection system and its apparatus through individual schedule management
JP7178060B2 (en) Signboard-based business processing device and business processing method
JP2022068796A (en) Accountancy support system
US20170140342A1 (en) Value-based organization
KR102081278B1 (en) Method for providing multi-mode scheduling service integrating time table with calendar
US11263595B2 (en) Electronic scheduling assistant utilizing categories of participants
US8015050B2 (en) Operation supporting system and operation supporting method

Legal Events

Date Code Title Description
A201 Request for examination
A302 Request for accelerated examination