KR100780103B1 - Method for yieding material requirement and product planning requirement and record media recored program for realizing the same - Google Patents

Method for yieding material requirement and product planning requirement and record media recored program for realizing the same Download PDF

Info

Publication number
KR100780103B1
KR100780103B1 KR1020050102580A KR20050102580A KR100780103B1 KR 100780103 B1 KR100780103 B1 KR 100780103B1 KR 1020050102580 A KR1020050102580 A KR 1020050102580A KR 20050102580 A KR20050102580 A KR 20050102580A KR 100780103 B1 KR100780103 B1 KR 100780103B1
Authority
KR
South Korea
Prior art keywords
information
requirements
requirement
safety stock
production
Prior art date
Application number
KR1020050102580A
Other languages
Korean (ko)
Other versions
KR20070045845A (en
Inventor
최영휘
Original Assignee
최영휘
Priority date (The priority date is an assumption and is not a legal conclusion. Google has not performed a legal analysis and makes no representation as to the accuracy of the date listed.)
Filing date
Publication date
Application filed by 최영휘 filed Critical 최영휘
Priority to KR1020050102580A priority Critical patent/KR100780103B1/en
Publication of KR20070045845A publication Critical patent/KR20070045845A/en
Application granted granted Critical
Publication of KR100780103B1 publication Critical patent/KR100780103B1/en

Links

Images

Classifications

    • GPHYSICS
    • G06COMPUTING; CALCULATING OR COUNTING
    • G06QINFORMATION AND COMMUNICATION TECHNOLOGY [ICT] SPECIALLY ADAPTED FOR ADMINISTRATIVE, COMMERCIAL, FINANCIAL, MANAGERIAL OR SUPERVISORY PURPOSES; SYSTEMS OR METHODS SPECIALLY ADAPTED FOR ADMINISTRATIVE, COMMERCIAL, FINANCIAL, MANAGERIAL OR SUPERVISORY PURPOSES, NOT OTHERWISE PROVIDED FOR
    • G06Q10/00Administration; Management
    • G06Q10/06Resources, workflows, human or project management; Enterprise or organisation planning; Enterprise or organisation modelling
    • G06Q10/063Operations research, analysis or management
    • G06Q10/0631Resource planning, allocation, distributing or scheduling for enterprises or organisations
    • G06Q10/06315Needs-based resource requirements planning or analysis
    • GPHYSICS
    • G06COMPUTING; CALCULATING OR COUNTING
    • G06QINFORMATION AND COMMUNICATION TECHNOLOGY [ICT] SPECIALLY ADAPTED FOR ADMINISTRATIVE, COMMERCIAL, FINANCIAL, MANAGERIAL OR SUPERVISORY PURPOSES; SYSTEMS OR METHODS SPECIALLY ADAPTED FOR ADMINISTRATIVE, COMMERCIAL, FINANCIAL, MANAGERIAL OR SUPERVISORY PURPOSES, NOT OTHERWISE PROVIDED FOR
    • G06Q10/00Administration; Management
    • G06Q10/08Logistics, e.g. warehousing, loading or distribution; Inventory or stock management
    • G06Q10/087Inventory or stock management, e.g. order filling, procurement or balancing against orders

Landscapes

  • Business, Economics & Management (AREA)
  • Human Resources & Organizations (AREA)
  • Engineering & Computer Science (AREA)
  • Economics (AREA)
  • Entrepreneurship & Innovation (AREA)
  • Strategic Management (AREA)
  • General Physics & Mathematics (AREA)
  • Physics & Mathematics (AREA)
  • Theoretical Computer Science (AREA)
  • Marketing (AREA)
  • Operations Research (AREA)
  • Quality & Reliability (AREA)
  • Tourism & Hospitality (AREA)
  • Development Economics (AREA)
  • General Business, Economics & Management (AREA)
  • Game Theory and Decision Science (AREA)
  • Educational Administration (AREA)
  • Accounting & Taxation (AREA)
  • Finance (AREA)
  • General Factory Administration (AREA)
  • Management, Administration, Business Operations System, And Electronic Commerce (AREA)

Abstract

본 발명은 자재 소요량 및 생산 계획 소요량 산출 방법 및 이를 구현하기 위한 프로그램이 기록된 기록매체에 관한 것으로서, 자재 또는 제품의 매출 수량 및 안전 재고율을 이용하여 최소 안전 재고 수량을 설정하는 단계(a); 상기 설정된 최소 안전 재고 수량, 월간 판매 계획 정보, 재공 및 재고 정보를 이용하여 러닝 전 자재 소요량을 산출하는 단계(b)-상기 월간 판매 계획 정보는 복수의 주간 판매 계획 정보로 분할됨-; 러닝 시 입력되는 수주 정보를 수신하는 단계(c); 및 상기 수주 정보 및 전월말에 설정된 주간 판매 계획 정보 중 상기 수주 정보가 입력된 시점 이후의 주간 판매 계획 정보, 출고 정보, 상기 최소 안전 재고 수량 및 재공 및 재고 정보를 이용하여 소요량을 자동 산출하는 단계(d)를 포함하는 소요량 산출 방법에 관한 것이다. 본 발명에 따르면, 정확한 최소 안전 재고 수량을 이용한 자재 소요량 산출이 가능하며, 수주 정보를 이용하여 자재 소요량 및 생산 소요량을 조정함으로써 정확한 물류 확보가 가능하며, 정확한 자재 소요량 산출 및 생산 소요량 변경이 가능하다는 장점이 있다. The present invention relates to a recording medium on which a material requirement and a production plan requirement calculation method and a program for implementing the same are recorded, the method comprising the steps of: (a) setting a minimum safety stock quantity using a sales quantity and a safety stock ratio of a material or a product; Calculating a pre-running material requirement using the set minimum safety stock quantity, monthly sales plan information, inventory and inventory information, wherein the monthly sales plan information is divided into a plurality of weekly sales plan information; (C) receiving order information input when running; And automatically calculating the requirements using the weekly sales plan information, the release information, the minimum safety stock quantity, the availability and the inventory information after the time when the order information is input among the order information and the weekly sales plan information set at the end of the previous month. It relates to a requirement calculation method comprising d). According to the present invention, it is possible to calculate the material requirements using the exact minimum safety stock quantity, it is possible to secure accurate logistics by adjusting the material requirements and production requirements using the order information, it is possible to accurately calculate the material requirements and change the production requirements There is an advantage.

자재 소요량, 안전 재고, 수주 정보, 주간 판매 계획, MRP, 생산 계획 소요량 Material requirements, safety stock, order information, weekly sales plan, MRP, production plan requirements

Description

자재 소요량 및 생산 계획 소요량 산출 방법 및 이를 구현하기 위한 프로그램이 기록된 기록매체{METHOD FOR YIEDING MATERIAL REQUIREMENT AND PRODUCT PLANNING REQUIREMENT AND RECORD MEDIA RECORED PROGRAM FOR REALIZING THE SAME}METHOD FOR YIEDING MATERIAL REQUIREMENT AND PRODUCT PLANNING REQUIREMENT AND RECORD MEDIA RECORED PROGRAM FOR REALIZING THE SAME}

도 1은 종래 기술에 따른 소요량 계획(MRP) 프로세스를 도시한 도면.1 illustrates a requirement planning (MRP) process according to the prior art.

도 2는 본 발명의 바람직한 일 실시예에 따른 MRP 프로세스를 도시한 도면. 2 illustrates an MRP process in accordance with a preferred embodiment of the present invention.

도 3은 본 발명의 바람직한 일 실시예에 따른 MRP 어플리케이션의 모듈 구성을 도시한 도면. 3 is a diagram illustrating a module configuration of an MRP application according to an embodiment of the present invention.

도 4는 본 발명에 따른 생산 지시 체계를 도시한 도면. 4 illustrates a production instruction system in accordance with the present invention.

도 5는 본 발명에 따른 자재 소요량 및 생산 계획 소요량 산출 과정을 도시한 순서도.5 is a flow chart showing the material requirements and production planning requirements calculation process according to the present invention.

도 6은 본 발명에 따른 안전 재고 설정을 위한 인터페이스를 도시한 도면. 6 illustrates an interface for setting a safety inventory in accordance with the present invention.

도 7a 내지 도 7d는 월간 판매 계획 정보를 입력하기 위한 인터페이스를 도시한 도면. 7A to 7D illustrate an interface for inputting monthly sales plan information.

도 8은 월간 판매 계획 정보만을 입력한 경우의 소요량을 표시하는 화면을 도시한 도면. 8 is a diagram showing a screen for displaying a requirement when only monthly sales plan information is input.

도 9a 내지 9d는 수주 정보를 입력한 경우의 예시 화면을 도시한 도면. 9A to 9D are diagrams showing example screens when order information is input.

도 10은 수정 정보 입력에 따라 소요량을 자동으로 산출한 경우의 예시 화면 을 도시한 도면. 10 is a view showing an example screen in the case of automatically calculating the required amount according to the correction information input.

도 11a 내지 도 11d는 자동으로 산출된 소요량에 따라 로트를 분할하는 경우의 예시 화면을 도시한 도면.11A to 11D are diagrams showing an example screen in the case of dividing a lot according to automatically calculated requirements.

본 발명은 자재 소요량 및 생산 계획 소요량 산출 방법 및 이를 구현하기 위한 프로그램이 기록된 기록매체에 관한 것으로서, 보다 상세하게는 적절한 물류를 보유할 수 있도록 하는 자재 소요량 및 생산 계획 소요량 산출 방법 및 이를 구현하기 위한 프로그램이 기록된 기록매체에 관한 것이다. The present invention relates to a method for calculating a material requirement and a production plan requirement, and a recording medium on which a program for implementing the same is recorded. More specifically, the method for calculating a material requirement and a production plan requirement for maintaining proper logistics and implementing the same The present invention relates to a recording medium having recorded thereon a program.

MRP(Material Requirement Planning), 즉, 자재 소요량 계획은 생산에 필요한 자재가 얼만큼 소요될 것인지 계획을 세우는 것으로서, 필요한 자재의 적량적시 구입, 제품 재공 및 재고의 수준을 조정하기 위한 활동/일련의 시스템을 의미한다. Material Requirement Planning (MRP), or material requirements planning, is the planning of how much material will be needed for production, and is an activity / sequence system for adjusting the level of timely purchase of required materials, product deliveries, and inventory. it means.

또한, 자재 소요량 계획은 제품 생산에 소요되는 시간(Lead Time)의 상관 관계를 논리적으로 분석하여 제품에 대한 수요 요건, 즉, 납품 시기와 납품량을 전제로 하고, 제품을 납품 시기까지 생산하는데 어떤 자재가 얼마만큼 준비되어야 하는가를 결정하여 재고 비용을 최소화하기 위해 반드시 필요한 활동이다. In addition, material requirements planning logically analyzes the correlation of lead time to produce a product, which is based on the demand requirements for the product, that is, on the basis of the delivery time and delivery quantity, Is a necessary activity to minimize inventory costs by determining how much to prepare.

기업은 자재 소요량 계획에 의해 여건 변화에 민감한 자재에 대한 계획을 미 리 수립할 수 있으며, 생산 시간의 단축과 사전 납기의 통제 및 생산과 재고 관리의 유기적인 결합이 가능해지게 된다. Material requirements planning allows companies to plan ahead for materials that are sensitive to changing conditions, enabling shorter production times, control of pre-delivery times, and an organic combination of production and inventory management.

한편, 자재 소요량 계획은 제품의 생산 과정이 복잡하고, 특히 여러 개의 조립 단계를 거쳐 제품이 완성되는 경우, 제조 및 구매 리드타임이 상대적으로 긴 경우, 제품 원가가 높은 경우 및 최종 제품의 생산 공정이 긴 경우에 특히 유용하게 사용될 수 있다. Material requirements planning, on the other hand, is a complex production process, especially when the product is completed through multiple assembly steps, when manufacturing and purchasing lead times are relatively long, when product costs are high, and when the final product is produced. It can be especially useful for long cases.

이와 같은 자재 소요량 계획은 기업 입장에서 이론적으로 많은 이로움을 제공하고 있으나, 실제로 현장에서 적용되는 자재 소요량 계획은 이론대로 적용되지 못하고 수주 정보에 기초하여 임의적으로 결정되는 것이 일반적이었다. This material requirement plan provides a lot of theoretical benefits for the enterprise, but in practice, the material requirement plan applied in the field was not applied theoretically and was decided arbitrarily based on order information.

도 1은 종래 기술에 따른 자재 소요량 계획(MRP) 프로세스를 도시한 도면이다. 1 is a diagram illustrating a material requirement planning (MRP) process according to the prior art.

도 1을 참조하면, 자재 소요량 산출을 위해서는 수주 정보, 제품 정보, 자재 정보, BOM 정보, 제품 재고 정보, 제품 재공 정보 및 자재 재고 정보가 이용되며, 작업자가 기간 마감을 선택하는 경우에 자재 소요량을 산출하는 방식을 사용하였다. Referring to FIG. 1, order information, product information, material information, BOM information, product inventory information, product availability information, and material inventory information are used to calculate a material requirement. The calculation method was used.

여기서, 제품 정보는 제조 리드타임 및 제품에 대한 안전 재고 수량에 관한 정보를 포함할 수 있으며, 제조 리드타임은 주문을 받은 시점에서 출고하는 시점까지의 기간을 의미한다. Here, the product information may include information on manufacturing lead time and the safety stock quantity for the product, and manufacturing lead time means a period from the time of receiving the order to the time of shipping.

안전 재고는 생산 또는 자재 조달의 불확실성에 대처하기 위하여 보유하는 재고로서, 완충 재고(buffer stock)라고도 한다. Safety stock is a stock that is held to meet the uncertainty of production or material procurement, also known as buffer stock.

안전 재고는 재고 부족으로 인한 손실이 안전 재고의 유지비보다 클 경우와 안전 재고의 유지비가 소액인 경우에 안전 재고를 유지하는 것이 바람직하며, 그 수준은 수요와 조달 기간의 변동에 의한다. It is desirable to maintain a safety stock when the loss due to lack of stock is greater than the maintenance cost of the safety stock and when the maintenance cost of the safety stock is small, and the level is dependent on the change in demand and procurement period.

한편, 자재 정보는 자재의 구매 리드타임과 자재에 대한 안전 재고 수량을 포함하며, BOM(Bill of Material)은 특정 제품이 어떤 부품들로 구성되는 가에 대한 데이터로서, BOM에서 가장 기본이 되는 정보는 '제품 구조 정보(Product Structure)'라고 할 수 있다. On the other hand, the material information includes the purchase lead time of the material and the safety stock quantity of the material.Bill of Material (BOM) is data about which parts of a specific product are composed, which is the most basic information in the BOM. May be referred to as 'Product Structure Information'.

그밖에 재고는 생산 완료된 자재 또는 제품, 재공은 생산 중인 제품에 대한 정보를 의미한다. In addition, inventory means information about a finished product or product, and work in progress refers to information about the product being produced.

종래의 자재 소요량은 안전 재고 수량과 수주 정보, 제품 및 자재에 대한 재고 및 재공 수치를 이용하여 산출되었는데, 수주 정보, 자재 정보, 제품 및 자재에 대한 재고 및 재공 정보는 현실적으로 존재하는 객관적인 수치이고, 안전 재고에 관한 정보는 작업자에 예측에 의한 정보라는 점에서 정확한 소요량 산출을 위해서는 안전 재고 수량이 정확하게 결정되어야 한다. Conventional material requirements were calculated using safety stock quantities and order information, inventory and inventory numbers for products and materials. Order information, material information, inventory and inventory information for products and materials are realistic objectives, Since the information on the safety stock is information that is predicted to the worker, the quantity of the safety stock must be accurately determined for accurate requirements calculation.

그러나, 종래에는 안전 재고 산출 공식이 존재함에도 불구하고, 안전 재고 산출 공식이 복잡하며, 작업자가 수요와 조달 기간의 변동을 예측하기가 어려워 일반적으로 경험에 따라 안전 재고 수량을 정하기 때문에 안전 재고 수량의 부정확성과 임의성으로 인해 제품 및 자재의 재고가 크게 증가하거나 부족해지는 문제점이 있었다.However, despite the existing safety stock calculation formula, the safety stock calculation formula is complicated, and it is difficult for an operator to predict fluctuations in demand and procurement period. Due to inaccuracy and randomness, there is a problem that the inventory of products and materials is greatly increased or insufficient.

한편, 자재 소요량 계획에 있어서, 전월말에 안전 재고 수량, 월간 판매 계 획 및 제품의 재고 및 재공을 이용하여 소요량을 산출하고, 그에 따른 생산 계획 소요량을 수립하며, 수립된 생산 계획 소요량에 따라 로트를 분할하는 과정을 수행하는데, 종래에는 수주 생산 방식만을 적용하기 때문에 해당 월에 진입하여 제품 생산이 진행되는 경우(러닝 시) 수주가 있는 시점마다 기간 마감을 수행하여 자재 소요량을 산출하여야 한다. On the other hand, in material requirements planning, at the end of the previous month, the requirements are calculated using the safety stock quantity, monthly sales plan, and the inventory and work of the product, the production plan requirements are established accordingly, and the lot is made according to the established production plan requirements. In order to perform the division process, conventionally, only the order production method is applied. Therefore, when the product is entered in the month and the production of the product is progressing (when running), the material requirement should be calculated by closing the period every time there is an order.

그러나, 다품종 소량 생산을 주로 하는 기업에 있어서 잦은 수주 변동과 단납기(제조 리드타임보다 수주 주기가 짧은 경우)인 경우, 수주 변동 시 마다 기간 마감을 수행하는 것이 불가능하기 때문에 종래에는 주로 월 단위로만 기간 마감을 수행하며, 이로 인해, 각 주마다 잦은 수주 변동이 존재하는 경우에도 전월말의 생산 계획 소요량대로 제품을 생산하여, 많은 재고 및 제공이 쌓이거나 그와 반대로 수주가 폭증하는 경우, 물량이 부족해지는 문제점이 있었다. However, in the case of companies that mainly produce small quantities of various kinds, in case of frequent order fluctuations and short delivery time (when the order cycle is shorter than the manufacturing lead time), it is impossible to close the period every order fluctuations. In the event that there is frequent order fluctuations in each state, this would result in production according to the production plan requirements at the end of the previous month, resulting in a shortage in the event of a large inventory and provision buildup or vice versa. There was a problem with getting lost.

본 발명에서는 상기한 바와 같은 종래기술의 문제점을 해결하기 위해, 안전 재고 정보를 정확히 결정하여 정확한 자재 소요량을 산출할 수 있도록 하는 자재 소요량 및 생산 소요량 산출 방법 및 이를 구현하기 위한 프로그램이 기록된 기록매체를 제안하고자 한다. In the present invention, in order to solve the problems of the prior art as described above, the method for calculating the material requirements and production requirements to accurately determine the safety stock information to calculate the exact material requirements, and a recording medium having a program for implementing the same I would like to propose.

본 발명의 다른 목적은 다품종 소량 생산이며, 단납기인 제품에 대해 정확한 자재 소요량을 산출할 수 있도록 하는 본 발명은 자재 소요량 및 생산 계획 소요량 산출 방법 및 이를 구현하기 위한 프로그램이 기록된 기록매체를 제공하는 것이다. Another object of the present invention is a multi-quantity small quantity production, the present invention to enable the accurate material requirements for the short-term delivery of the present invention provides a method for calculating the material requirements and production planning requirements, and a recording medium recording a program for implementing the same It is.

본 발명의 다른 목적은 수주 변동 시마다 소요량을 자동 산출하여 제품을 생 산하는 러닝(running) 시 로트를 변경할 수 있는 본 발명은 자재 소요량 및 생산 계획 소요량 산출 방법 및 이를 구현하기 위한 프로그램이 기록된 기록매체를 제공하는 것이다. Another object of the present invention is the present invention that can change the lot at the time of running to produce the product by automatically calculating the requirements for every order change, the material requirements and production planning requirements calculation method and record for recording the program for implementing the same To provide a medium.

본 발명의 다른 목적은 다품종 소량 생산에 있어서, 계획 생산이 가능하도록 하는 본 발명은 자재 소요량 및 생산 계획 소요량 산출 방법 및 이를 구현하기 위한 프로그램이 기록된 기록매체를 제공하는 것이다. Another object of the present invention is to provide a recording medium in which a method for calculating material requirements and production plan requirements and a program for implementing the same are recorded.

상기한 바와 같은 목적을 달성하기 위해, 본 발명의 바람직한 일 실시예에 따르면, 자재 또는 제품의 매출 수량 및 안전 재고율을 이용하여 안전 재고 수량을 설정하는 단계(a); 상기 설정된 안전 재고 수량, 월간 판매 계획 정보, 재공 및 재고 정보를 이용하여 러닝 전 자재 소요량을 산출하는 단계(b)-상기 월간 판매 계획 정보는 복수의 주간 판매 계획 정보로 분할됨-; 러닝 시 입력되는 수주 정보를 수신하는 단계(c); 및 상기 수주 정보 및 전월말에 설정된 주간 판매 계획 정보 중 상기 수주 정보가 입력된 시점 이후의 주간 판매 계획 정보, 출고 정보, 상기 안전 재고 수량 및 재공 및 재고 정보를 이용하여 소요량을 자동 산출하는 단계(d)를 포함하는 소요량 산출 방법이 제공된다. In order to achieve the above object, according to a preferred embodiment of the present invention, the step of (a) setting the safety stock quantity using the sales quantity and the safety stock ratio of the material or product; Calculating a pre-running material requirement using the set safety stock quantity, monthly sales plan information, inventory and inventory information, wherein the monthly sales plan information is divided into a plurality of weekly sales plan information; (C) receiving order information input when running; And automatically calculating the requirements using the weekly sales plan information, the release information, the safety stock quantity, the availability and the inventory information after the time the order information is input among the order information and the weekly sales plan information set at the end of the previous month (d A requirement calculation method is provided.

상기 주간 판매 계획 정보는 상기 월간 판매 계획을 제품 특성에 따라 분할하고, 상기 수주 정보가 입력되는 경우, 상기 해당 주의 주간 판매 계획 정보는 상기 수주 정보로 조정되는 것이 바람직하다. The weekly sales plan information divides the monthly sales plan according to product characteristics, and when the order information is input, the weekly sales plan information of the corresponding week is preferably adjusted to the order information.

또한, 본 발명에 따르면, 러닝 전 상기 소요량에 따라 생산 계획 소요량이 결정되고, 상기 결정된 생산 계획 소요량은 하나 이상의 로트(LOT)로 분할되며, 상기 (d) 단계에서 자동 산출된 소요량과 해당 주의 잔여 생산 계획 소요량을 비교하여 과부족을 연산하는 단계(e); 및 상기 연산된 과부족 수치에 따라 상기 분할된 로트를 조정하는 단계(f)를 더 포함할 수 있다. Further, according to the present invention, the production planning requirements are determined according to the requirements before running, the determined production planning requirements are divided into one or more lots (LOT), the requirements automatically calculated in the step (d) and the remainder of the week (E) calculating excess or deficiency by comparing the production plan requirements; And adjusting the divided lot according to the calculated excess or deficiency value.

작업이 진행되지 않은 로트 중 최종 로트에 대해 이루어지는 것이 바람직하다. It is preferred that the work be done on the last lot of the lots that have not been run.

한편, 본 발명의 다른 측면에 따르면, 상기한 방법을 수행하는 프로그램이 기록된 기록매체가 제공된다. On the other hand, according to another aspect of the present invention, there is provided a recording medium on which a program for performing the above method is recorded.

이하에서, 첨부된 도면을 참조하여 본 발명에 따른 본 발명은 자재 소요량 및 생산 계획 소요량 산출 방법 및 이를 구현하기 위한 프로그램이 기록된 기록매체에 관한 바람직한 실시예를 상세하게 설명한다. Hereinafter, the present invention according to the present invention with reference to the accompanying drawings will be described in detail a preferred embodiment of a method for calculating the material requirements and production planning requirements and a recording medium on which a program for implementing the same is recorded.

본 발명은 정확한 자재 소요량 및 생산 계획 소요량 자동 산출을 통해 기업이 적절한 물량을 보유할 수 있도록 하는 것으로서, 본 발명은 소정의 어플리케이션 프로그램에 의해 기업에 설치된 단말기에서 수행될 수 있으며, 이와 달리, 기업에 설치된 단말기로부터 필요한 정보를 네트워크를 통해 수신하여 원격지에 구비된 서버에서 수행될 수도 있을 것이다. The present invention is to enable the enterprise to hold the appropriate quantity through the automatic calculation of the exact material requirements and production plan requirements, the present invention can be performed in a terminal installed in the enterprise by a predetermined application program, on the contrary, It may be performed in a server provided at a remote location by receiving the necessary information from the installed terminal via the network.

도 2는 본 발명의 바람직한 일 실시예에 따른 MRP 프로세스를 도시한 도면이다. 2 is a diagram illustrating an MRP process according to an embodiment of the present invention.

도 2를 참조하면, 본 발명에 따른 자재 소요량 계획은 수주 정보, 주간 판매 계획 정보, 제품 정보, 자재 정보, BOM 정보, 제품 출고 정보, 제품 재고 정보, 제품 재공 정보 및 자재 재고 정보를 이용할 수 있다. Referring to FIG. 2, the material requirement planning according to the present invention may use order information, weekly sales planning information, product information, material information, BOM information, product release information, product inventory information, product availability information, and material inventory information. .

본 발명에 따른 자재 소요량 계획은 종래기술과 달리 최소 안전 재고 수량을 결정함에 있어서, 최소 안전 재고 비율 정보 및 매출 정보를 이용한다. Unlike the prior art, the material requirement planning according to the present invention uses the minimum safety stock ratio information and the sales information in determining the minimum safety stock quantity.

최소 안전 재고 수량은 제품 및 자재에 대해 요구될 수 있는데, 본 발명에 따르면, 제품에 대한 최소 안전 재고 수량은 N개월 매출 수량 평균과 제1 안전 재고율의 곱 결정될 수 있으며, 자재에 대한 최소 안전 재고 수량은 N개월 매출 수량과 제2 안전 재고율의 곱으로 결정될 수 있다. The minimum safety stock quantity may be required for the product and the material. According to the present invention, the minimum safety stock quantity for the product may be determined as the product of the N-month sales quantity average and the first safety stock ratio, and the minimum safety stock for the material. The quantity can be determined as the product of the N-month sales quantity and the second safety inventory rate.

여기서, 제1 안전 재고율은 제품에 대한 안전 재고 비율로서, 본 발명에 따르면, 제조 리드타임 및 월 평균 조업 일수를 통해 결정될 수 있다. Here, the first safety stock rate is a safety stock rate for the product, and according to the present invention, it may be determined through the manufacturing lead time and the average monthly working days.

예를 들어, A 제품의 N개월 매출 수량이 5000개, 제조 리드타임이 5일이고, 월 평균 조업 일수가 22일 경우, 최소 안전 재고율은 5/22=22.72 퍼센트로 결정될 수 있으며, 이에 따라 A 제품의 최소 안전 재고 수량은 5000 x 0.2272=1136개로 결정될 수 있다. For example, if product A has 5000 N-month sales, manufacturing lead time is 5 days, and the average monthly number of operating days is 22, then the minimum safety stock rate can be determined as 5/22 = 22.72 percent. The minimum safe stock quantity of a product can be determined as 5000 x 0.2272 = 1136.

또한, A 제품의 제조에 필요한 a' 자재의 구매 리드타임이 7일인 경우에는 a' 자재의 최소 안전 재고율은 7/22=31.81 퍼센트로 결정되고, 이에 따라 최소 안전 재고 수량은 5000 x 0.3181=1590개로 결정될 수 있다. In addition, if the purchase lead time of material a 'for the manufacture of product A is 7 days, then the minimum safety stock ratio of material a' is determined to be 7/22 = 31.81 percent, so the minimum safety stock quantity is 5000 x 0.3181 = 1590 Can be determined to be dogs.

전술한 바와 같이, 종래에는 최소 안전 재고 수량을 작업자의 경험에만 의존하여 결정하는 것이 일반적이었으나, 본 발명에 따르면, 제품 또는 자재의 구매 및 제조 리드타임을 이용하여 안전 재고의 비율을 결정하며, 이를 매출 수량(수요량)과 결부시켜 결정하기 때문에 정확한 최소 안전 재고 수량의 결정이 가능해진다. As described above, in the past, it was common to determine the minimum safety stock quantity only based on the operator's experience, but according to the present invention, the ratio of the safety stock is determined using the purchase and manufacturing lead time of the product or material, The decision is made in conjunction with the sales quantity (demand quantity), which enables the accurate determination of the minimum safety stock quantity.

한편, 본 발명에 따르면, 자재 소요량 산출 및 생산 계획 소요량 산출에 있어서 주간 판매 계획 정보 및 제품 출고 정보가 추가적으로 이용될 수 있다. Meanwhile, according to the present invention, the weekly sales plan information and the product release information may be additionally used in the material requirement calculation and the production plan requirement calculation.

종래에는 러닝 시 그때마다의 수주 정보만이 중요하기 때문에 최소 안전 재고 수량과 수주 정보만을 이용하여 소요량을 산출하였으나, 본 발명에 따르면, 계획 생산과 수주 생산을 병행하기 위해 주간 판매 계획 정보 및 제품 출고 정보를 추가적으로 이용한다. Conventionally, since only the order information is important at the time of running, the requirements are calculated using only the minimum safety stock quantity and the order information. However, according to the present invention, the weekly sales plan information and the product release to parallel the planned production and the order production Use additional information.

일반적으로 자재 소요량 계획에 있어서, 전월말의 월간 판매 계획에 따른 주간 판매 계획 정보가 결정되는데, 본 발명에 따르면, 러닝 시, 특정 주에 입력되는 수주 정보가 그 주의 주간 판매 계획으로 대체되며, 상기한 수주 정보, 출고 정보 및 나머지 주의 주간 판매 계획 정보 등을 이용하여 자재 소요량을 산출한다. In general, in the material requirements planning, the weekly sales plan information according to the monthly sales plan at the end of the previous month is determined. According to the present invention, the order information entered in a particular week is replaced by the weekly sales plan of the week during the run. Material requirements are calculated using order information, goods issue information and weekly sales planning information for the rest of the week.

한편, 생산 계획 소요량 계획에 있어서, 러닝 전 생산 계획 소요량은 전월말의 자재 소요량에 따라 결정될 수 있으며-여기서, 러닝 전 자재 소요량은 월간 판매 계획, 최소 안전 재고 수량 및 재공, 재고 정보를 이용하여 산출됨-, 생산 계획 소요량에 따라 로트가 분할 확정될 수 있는데, 본 발명은 자재 소요량이 수주 변동 시마다 자동 산출되는 경우, 이전 생산 계획 소요량과 자동 산출된 자재 소요량 사이의 과부족을 연산하고, 이를 통해 아직 작업이 진행되지 않은 로트를 변경하는 과정을 수행한다. On the other hand, in production planning requirements planning, pre-running production planning requirements can be determined according to material requirements at the end of the previous month, where pre-running material requirements are calculated using monthly sales plans, minimum safety stock quantities and restocking, and inventory information. -Lots can be determined according to production plan requirements. In the present invention, when the material requirements are automatically calculated for each change in orders, the present invention calculates an oversufficiency between the previous production plan requirements and the automatically calculated material requirements, and thus still works. It carries out the process of changing the lot that has not progressed.

상기와 같이 로트가 변경되는 경우, 다음 러닝 시의 생산 계획 소요량이 산 출될 수 있다. If the lot is changed as described above, production planning requirements for the next run can be calculated.

도 3은 본 발명의 바람직한 일 실시예에 따른 MRP 어플리케이션의 모듈 구성을 도시한 도면으로서, 도 3에 도시된 바와 같이, 본 발명에 따른 MRP 어플리케이션은 안전 재고 설정 모듈(300), 수주 정보 수신 모듈(302), 출고 정보 수신 모듈(304), 자재 소요량 산출 모듈(306), 과부족 연산 모듈(308) 및 로트 조정 모듈(310)을 포함할 수 있다.3 is a view showing the module configuration of the MRP application according to an embodiment of the present invention, as shown in Figure 3, MRP application according to the present invention is a safety inventory setting module 300, order information receiving module 302, the shipment information receiving module 304, the material requirement calculation module 306, the oversufficient calculation module 308, and the lot adjustment module 310 may be included.

도 3을 설명함에 있어서, 도 4에 도시된 생산 지시 체계를 참조하며, 제품 1 내지 제품 3 중에서 제품 1를 예시로 하여 설명한다. Referring to FIG. 3, the production instruction system shown in FIG. 4 will be referred to, and product 1 will be described as an example among products 1 to 3.

안전 재고 설정 모듈(300)은 최소 안전 재고 수량을 설정하는 것으로서, 상기한 바와 같이, 각 자재와 제품에 대해 매출 수량 평균 및 최소 안전 재고율 정보를 이용하여 안전 재고를 설정한다. The safety inventory setting module 300 sets a minimum safety stock quantity. As described above, the safety stock setting module 300 sets the safety stock using the sales quantity average and the minimum safety stock ratio information for each material and product.

도 4에서 제품 1에 대한 안전 재고는 3개월 평균 매출 수량을 기준으로 정해지며, 안전 재고율을 100 퍼센트로 설정된다. In FIG. 4, the safety stock for product 1 is determined based on the 3-month average sales quantity, and the safety stock ratio is set to 100 percent.

도 4에서 전월말에 최소 안전 재고 수량, 제품의 재고 및 재공 정보, 월간 판매 계획 정보를 통해 러닝 전 자재 소요량이 결정된다. At the end of the previous month in Figure 4 material requirements before the run is determined through the minimum safety stock quantity, product inventory and inventory information, monthly sales planning information.

즉, 러닝 전 자재 소요량은 월간 판매 계획 정보와 최소 안전 재고 수량을 합산한 수치에서 제품의 재고 및 재공을 차감한 값이 되며, 생산 계획 소요량은 전월말에 계산된 소요량을 기준으로 결정된다. 생산 계획 소요량에 따라 작업자는 로트 분할 정보를 입력한다. In other words, the pre-running material requirement is the sum of monthly sales plan information and the minimum safety stock quantity, which is calculated by subtracting the inventory and inventory of the product. The production plan requirement is determined based on the requirements calculated at the end of the previous month. According to the production plan requirements, the operator enters lot splitting information.

도 4에서는 생산 계획 소요량이 제품 1의 전월말 소요량에서 백 단위를 제거 하는 방식으로 결정되는 것으로 하였으나, 이는 일예에 불과하며, 그밖에 다른 방식을 통해 자재 소요량에서 생산 계획 소요량을 결정하는 것도 가능할 것이다. In FIG. 4, the production plan requirement is determined by removing one hundred units from the end of the previous month of the product 1, but this is only an example, and other methods may be used to determine the production plan requirement from the material requirement.

한편, 본 발명의 바람직한 실시예에 따르면, 수주 정보 입력 시 주간 단위로 자재 소요량 및 생산 계획 소요량 산출 과정이 수행될 수 있는데, 수주 정보 수신 모듈(302)이 러닝 시 수주 정보를 수신하고, 출고 정보 수신 모듈(304)이 해당 주의 출고 정보를 수신하는 경우, 자재 소요량 산출 모듈(306)은 상기한 정보와 주간 판매 계획 정보를 이용하여 자재 소요량을 산출하는 과정을 수행한다. Meanwhile, according to a preferred embodiment of the present invention, when the order information is input, a material requirement and a production plan requirement calculation process may be performed on a weekly basis, and the order information receiving module 302 receives the order information when running and release information. When the receiving module 304 receives the release information of the corresponding week, the material requirement calculation module 306 performs a process of calculating the material requirement using the above information and the weekly sales plan information.

도 4를 참조하면, 제품 1의 전월말 주간 판매 계획 정보는 각 주마다 13000으로 설정되어 있고, 전월말에는 각 주의 주간 판매 계획 정보를 이용하여 자재 소요량을 산출하였으나, 1주차에 수주 정보가 6500로 입력되는 경우, 자재 소요량 산출 모듈(306)은 최소 안전 재고 수량과 1주차의 수주 정보 및 나머지 주의 주간 판매 계획 정보를 합산한 수치에서 재공, 재고 및 출고 정보를 차감하여 산출한다. Referring to FIG. 4, the end-monthly weekly sales plan information of Product 1 is set to 13000 for each week, and at the end of the previous month, the material requirements are calculated using the weekly sales plan information of each week, but the order information is input to 6500 in the first week. If necessary, the material requirement calculation module 306 calculates by subtracting the inventory, inventory, and release information from the sum of the minimum safety stock quantity, the order information for the first week, and the weekly sales plan information for the rest of the week.

예를 들어, 도 4의 제품 1의 1주차 소요량은 (10333+6500+13000x3)-(7500+16500+6500)=25333으로 자동 산출될 수 있다. For example, the week 1 requirement of product 1 of FIG. 4 may be automatically calculated as (10333 + 6500 + 13000x3) − (7500 + 16500 + 6500) = 25333.

한편, 도 4에서 전월말의 생산 계획 소요량에 의해 제품 1의 로트는 19000, 15000, 15000로 분할되며, 각 로트는 1, 2 및 3주 단위로 순차적으로 이루어지는 것으로 가정한다. Meanwhile, in FIG. 4, it is assumed that lots of product 1 are divided into 19000, 15000, and 15000 according to production plan requirements at the end of the previous month, and each lot is sequentially formed in units of 1, 2, and 3 weeks.

따라서, 러닝 시 19000개에 대한 작업은 이미 진행되고 있으므로 1주차의 현재 생산 계획 소요량은 30000이 된다. As a result, 19000 jobs are already in progress at run time, so the current production plan requirement for Week 1 is 30000.

상기와 같이 1주차의 소요량이 25333으로 산출되는 경우, 현재 생산 계획 소 요량과 자동 산출된 자재 소요량의 차이가 존재하게 되는데, 본 발명에 따른 과부족 연산 모듈(308)은 자재 소요량이 새로이 산출되는 경우, 산출된 자재 소요량과 현재 생산 계획 소요량 사이의 과부족을 연산하는 과정을 수행한다. When the requirement of the first week is calculated as 25333 as described above, there is a difference between the current production planning requirements and the automatically calculated material requirements, the oversufficiency calculation module 308 according to the present invention is a new material requirements In addition, the process of calculating the excess and deficiency between the calculated material requirements and the current production plan requirements is performed.

도 4에서, 1주차에 제품 1에 대해서는 4667의 과부족이 발생한다. In FIG. 4, oversight of 4667 occurs for product 1 at week 1.

+4667 과부족은 그 수치만큼 필요 이상의 제품이 생산된다는 의미이므로, 본 발명에 따른 로트 조정 모듈(310)은 과부족 수치에 따라 아직 작업이 진행되지 않은 로트를 조정하는 과정을 수행한다. Since +4667 oversufficiency means that more than necessary products are produced by the value, the lot adjustment module 310 according to the present invention performs a process of adjusting a lot that has not been processed yet according to the oversufficient value.

이때, 분할된 로트 중 수치 조정이 이루어지는 로트 번호는 다양한 방법으로 설정될 수 있는데, 예를 들어, 도 4에 도시된 바와 같이, 마지막 로트를 조정하는 것으로 설정될 수 있으며, 이와 달리, 작업 미진행 로트를 균등하게 조정하는 것으로 설정될 수 있다. At this time, the lot number in which the numerical adjustment is performed among the divided lots may be set in various ways. For example, as shown in FIG. 4, the lot number may be set to adjust the last lot. It can be set to adjust the lot evenly.

도 4에서 1주차 과부족 4667에 따라 로트3이 처음 계획된 15000으로부터 조정되는데, 그 값은 계산의 편의를 위해 십 단위를 제거한 4600만큼 감소된 10400으로 조정될 수 있다. In FIG. 4, lot 3 is adjusted from the originally planned 15000 according to week 1 oversufficiency 4667, the value of which may be adjusted to 10400, reduced by 4600 with ten units removed for ease of calculation.

그러나, 이는 일예에 불과하며, 과부족 수치를 그대로 반영할 수도 있다는 점은 당업자에게 있어 자명할 것이다.However, this is only one example, and it will be apparent to those skilled in the art that the present invention may be used as it is.

상기와 같이, 연산된 과부족에 따라 로트가 조정되는 경우, 생산 계획 소요량 산출 모듈(312)은 다음 생산 계획 소요량이 자동을 변경하는 과정을 수행하며, 1주차에서 제품 1의 다음 생산 계획 소요량은 10400으로 변경되었다. As described above, when the lot is adjusted according to the calculated excess or deficiency, the production plan requirement calculation module 312 performs a process of automatically changing the next production plan requirement, and the next production plan requirement of the product 1 in week 1 is 10400. Was changed.

한편, 2주차에 들어서 수주가 6500만큼 발생하는 경우, 자재 소요량 산출 모 듈(306)은 최소 안전 재고 수량(10333)과 1 및 2주차의 조정된 주간 판매 계획 정보와 나머지 주간 판매 계획 정보(6500+6500+13000x2)를 합산한 수치에서 2주차의 재공, 재고 및 출고 정보를 차감하여 자재 소요량(4833개)을 산출한다. On the other hand, in the second week, if 6500 orders are generated, the material requirement calculation module 306 may include the minimum safety stock quantity 10333, the adjusted weekly sales plan information of the weeks 1 and 2, and the remaining weekly sales plan information (6500). From the sum of + 6500 + 13000x2), the material requirement (4833) is calculated by subtracting the 2nd week's stock, inventory and release information.

한편, 과부족 연산 모듈(310)은 상기와 같이 산출된 자재 소요량과 2주차의 생산 계획 소요량(이는 1주차에 변경된 생산 계획 소요량에 해당됨)을 이용하여 과부족을 연산하며, 로트 조정 모듈(312)은 과부족을 고려하여 현재 로트 3을 4900으로 조정하는 과정을 수행한다. On the other hand, the oversufficiency calculation module 310 calculates the oversufficiency by using the material requirements calculated as described above and the production plan requirements of Week 2 (which corresponds to the production plan requirements changed in Week 1), and the lot adjustment module 312 The process of adjusting the current lot 3 to 4900, taking into account excess and deficiency.

여기서, 상기한 로트 3의 수치가 변경된 다음 생산 계획 소요량에 해당한다. Here, the value of the lot 3 is changed and corresponds to the production plan requirement.

상기에서는 제품에 대해 소요량을 산출하는 것으로 설정하였으나, 제품 생산을 위해 필요한 자재에 대해서도 마찬가지 방법으로 소요량 산출 과정이 수행될 수 있다. In the above, the requirement is calculated for the product, but the requirement calculation process may be performed in the same manner with respect to the material required for producing the product.

상기와 같이, 본 발명에 따른 자재 소요량 및 생산 계획 소요량 산출을 전월말의 주간 판매 계획 정보와 현실에서의 수주 정보를 동시에 이용하며, 별도의 기간 마감 없이 산출되기 때문에 계획 생산이 가능해지며, 자재 소요량 및 생산 계획 소요량 산출이 실시간으로 이루어지는 장점이 있다. As described above, the use of the weekly sales plan information and the actual order information at the end of the previous month to calculate the material requirements and production plan requirements according to the present invention, and because it is calculated without a separate period, the planned production is possible, material requirements and Production plan requirements are calculated in real time.

또한, 자동 산출된 소요량에 따라 이전에 분할 확정된 로트를 조정함으로써 적절할 물류 보유가 가능해진다. In addition, it is possible to maintain proper logistics by adjusting the lot previously determined according to the automatically calculated requirements.

도 5는 본 발명에 따른 자재 소요량 산출 과정을 도시한 순서도이다. 5 is a flowchart illustrating a material requirement calculation process according to the present invention.

도 5를 참조하면, 우선, 본 발명에 따른 MRP 프로그램은 특정 제품 및 자재에 대한 안전 재고를 설정하는 과정을 수행한다(S500).Referring to FIG. 5, first, the MRP program according to the present invention performs a process of setting a safety inventory for a specific product and material (S500).

도 6은 본 발명에 따른 안전 재고 설정을 위한 인터페이스를 도시한 도면으로서, 도 6에 도시된 바와 같이, 작업자는 도 6에 도시된 인터페이스를 통해 매출 기준을 위한 개월 수를 결정할 수 있으며, 최소 안전 재고율을 결정할 수 있다. FIG. 6 is a diagram illustrating an interface for setting a safety inventory according to the present invention. As illustrated in FIG. 6, an operator may determine the number of months for sales criteria through the interface illustrated in FIG. 6, and the minimum safety. Inventory rates can be determined.

도 6에는 3개월 매출 수량 평균 및 30%의 최소 안전 재고율을 설정하는 것으로 예시하고 있으나, 이는 일예에 불과하며, 최소 안전 재고율을 이보다 더 높게 설정할 수도 있다. Although FIG. 6 illustrates that a three month sales quantity average and a minimum safety stock rate of 30% are set, this is only an example, and the minimum safety stock rate may be set higher than this.

이후, 본 발명은 전월말의 자재 소요량 산출 과정을 수행한다(S502).Then, the present invention performs the material requirements calculation process at the end of the previous month (S502).

전술한 바와 같이, 전월말의 소요량 산출을 위해서는 월간 판매 계획 정보가 이용될 수 있는데, 도 7a 내지 도 7d는 각 자재의 월간 판매 계획 정보를 입력하기 위한 인터페이스를 도시한 도면으로서, 작업자가 월간 판매 계획 정보를 입력하는 경우, 도 8에 도시된 바와 같이, 본 발명에 따른 MRP 프로세스는 입력된 월간 판매 계획 정보, 최소 안전 재고 수량 및 재고 정보를 이용하여 전월말의 소요량을 산출한다. As described above, the monthly sales plan information may be used to calculate the requirement at the end of the previous month. FIGS. 7A to 7D illustrate an interface for inputting the monthly sales plan information of each material, and the operator plans the monthly sales plan. In the case of inputting information, as shown in FIG. 8, the MRP process according to the present invention calculates the requirement at the end of the previous month by using the inputted monthly sales plan information, minimum safety stock quantity, and inventory information.

전월말의 소요량에 따라 작업자는 로트 분할 정보를 입력할 수 있는데, 본 발명에 따른 MRP 프로세스는 로트 분할 정보를 수신하여 저장한다(S504). According to the requirement at the end of the previous month, the operator can input the lot split information, MRP process according to the invention receives and stores the lot split information (S504).

다음으로, 수주에 따른 제품 생산이 시작되는 경우, MRP 프로세스는 작업자가 입력하는 수주 정보를 수신한다(S506). 작업자의 수주 정보 입력은 도 9a 내지 9d에 도시된 바와 같이 이루어질 수 있다. Next, when the production of the product according to the order is started, the MRP process receives the order information input by the worker (S506). The operator's order information input may be performed as shown in FIGS. 9A to 9D.

또한, 제품의 출고 정보를 수신하며(S508), MRP 프로세스는 수신된 수주 정보, 출고 정보 및 나머지 주의 주간 판매 계획 정보, 최소 안전 재고 수량, 출고 정보, 재공, 재고 정보를 이용하여 자재 소요량을 자동 산출하는 과정을 수행한다(S510).In addition, it receives the goods issue information of the product (S508), the MRP process automatically receives the material requirements by using the received order information, release information and the rest of the weekly sales planning information, minimum safety stock quantity, release information, work in progress, inventory information A calculation process is performed (S510).

도 10은 수정 정보 입력에 따라 소요량을 자동으로 산출한 경우의 예시 화면을 도시한 도면으로서, 도 10에 도시된 바와 같이, 별도의 기간 마감 없이 작업자가 수주 정보를 입력하는 경우, 각 제품의 소요량이 자동 산출된다.FIG. 10 is a diagram illustrating an example screen in which a requirement is automatically calculated according to correction information input. As shown in FIG. 10, when an operator inputs order information without closing a separate period, requirements of each product are shown. This is calculated automatically.

이후, MRP 프로세스는 새로 산출된 자재(제품) 소요량과 전월말의 생산 계획 소요량 사이에 과부족이 발생하는지 여부를 판단하며(S512), 과부족이 발생하는 경우에는 로트를 조정한다(S514). Thereafter, the MRP process determines whether there is an oversufficiency between the newly calculated material (product) requirements and the production plan requirements at the end of the previous month (S512), and if the oversufficiency occurs (S514).

도 11a 내지 도 11d는 자동으로 산출된 소요량에 따라 로트를 분할하는 경우의 예시 화면을 도시한 도면으로서, 도 11a 내지 도 11d에 도시된 바와 같이, 연산된 과부족에 따라 로트 조정이 이루어질 수 있다. 11A to 11D are diagrams illustrating an example of a case in which a lot is divided according to automatically calculated requirements, and as illustrated in FIGS. 11A to 11D, lot adjustment may be performed according to the calculated oversufficiency.

본 발명에 따른 MRP 프로세스는 상기한 과부족에 따라 최종 로트를 조정하거나 또는 아직 작업이 진행되지 않은 각 로트를 균등 또는 미리 설정된 비율만큼 증가 또는 감소시키는 과정을 수행한다. The MRP process according to the present invention performs a process of adjusting the final lot according to the above-mentioned shortage, or increasing or decreasing each lot that has not been in operation yet by an equal or preset ratio.

한편, 상기와 같이, 로트가 조정되는 경우, MRP 프로세스는 생산 계획 소요량을 산출하는 과정을 수행한다(S516). On the other hand, as described above, when the lot is adjusted, the MRP process performs a process of calculating the production plan requirements (S516).

본 명세서에서는 로트 조정에 의해 생산 계획 소요량이 산출된다는 용어를 사용하였으나, 실질적으로 로트 조정에 의해 생산 계획 소요량은 자동으로 변경될 수 있다. In this specification, the term production plan requirement is calculated by lot adjustment, but the production plan requirement may be automatically changed by lot adjustment.

이후, MRP 프로세스는 기준 기간이 만료되는지를 판단하여(S518) 아직 기준 기간이 만료되지 않은 경우에는 상기 단계(S506 내지 S516)를 반복 수행한다. Thereafter, the MRP process determines whether the reference period has expired (S518), and if the reference period has not yet expired, repeats the steps (S506 to S516).

여기서, 기준 기간은 주로 월 단위를 의미할 수 있다. Here, the reference period may mainly mean monthly units.

상기한 본 발명의 바람직한 실시예는 예시의 목적을 위해 개시된 것이고, 본 발명에 대해 통상의 지식을 가진 당업자라면 본 발명의 사상과 범위 안에서 다양한 수정, 변경, 부가가 가능할 것이며, 이러한 수정, 변경 및 부가는 하기의 특허청구범위에 속하는 것으로 보아야 할 것이다. Preferred embodiments of the present invention described above are disclosed for purposes of illustration, and those skilled in the art will be able to make various modifications, changes, and additions within the spirit and scope of the present invention. Additions should be considered to be within the scope of the following claims.

이상에서 설명한 바와 같이, 본 발명에 따르면, 안전 재고 정보를 매출 수량 및 비율 정보를 이용하여 결정하기 때문에 최소 안전 재고 수량을 시장 요건을 반영하여 결정할 수 있어 소요량을 정확히 산출할 수 있는 장점이 있다. As described above, according to the present invention, since the safety stock information is determined using the sales quantity and the ratio information, the minimum safety stock quantity can be determined by reflecting the market requirement, and thus there is an advantage that the required amount can be accurately calculated.

또한, 본 발명에 따르면, 별도의 기간 마감을 수행하지 않고 수주 변동 시마다 즉시 소요량이 산출되기 때문에 특히 다품종 소량 생산이며, 단납기인 제품에 대해 정확한 자재 소요량을 산출할 수 있는 장점이 있다. In addition, according to the present invention, since the requirements are calculated immediately every time the order changes without performing a separate period, there is an advantage in that it is possible to calculate the exact material requirements for the small quantity production, especially for short-term products.

또한, 본 발명에 따르면, 수주 변동 시마다 소요량을 자동 산출하여 제품을 생산하는 러닝(running) 시 로트를 현재 수준에 맞추어 변경할 수 있는 장점이 있다. In addition, according to the present invention, there is an advantage that the running lot to produce a product by automatically calculating the requirements for each change in order to change to the current level.

또한, 본 발명에 따르면, 러닝 시 주간 판매 계획 정보를 계속적으로 이용하여 소요량을 산출하기 때문에 계획 생산이 가능해진다는 장점이 있다. In addition, according to the present invention, there is an advantage that the planned production is possible because the demand is continuously calculated using the weekly sales plan information during the run.

Claims (6)

MRP(Material Requirement Planning) 어플리케이션에 의해 수행되는 자재 소요량 및 생산 계획 소요량 산출 방법에 있어서,In the material requirements and production planning requirements calculation method performed by a material requirement planning (MRP) application, 매출 수량 및 자재 또는 제품의 최소 안전 재고율을 이용하여 최소 안전 재고 수량이 설정되는 단계(a);(A) setting a minimum safety stock quantity using the sales quantity and the minimum safety stock rate of the material or product; 상기 설정된 최소 안전 재고 수량, 월간 판매 계획 정보, 재공 및 재고 정보를 이용하여 제품 생산 진행기간인 러닝 전 자재 소요량을 산출하는 단계(b)-상기 월간 판매 계획 정보는 복수의 주간 판매 계획 정보로 분할됨-;(B) calculating the pre-running material requirement, which is a product production progress period, by using the set minimum safety stock quantity, monthly sales plan information, inventory and inventory information (b)-the monthly sales plan information is divided into a plurality of weekly sales plan information being-; 러닝 시 입력되는 수주 정보를 수신하는 단계(c); 및 (C) receiving order information input when running; And 상기 수주 정보 및 전월말에 설정된 주간 판매 계획 정보 중 상기 수주 정보가 입력된 시점 이후의 주간 판매 계획 정보, 출고 정보, 상기 최소 안전 재고 수량 및 재공 및 재고 정보를 이용하여 소요량을 자동 산출하는 단계(d)를 포함하되,Automatically calculating the requirements using the weekly sales plan information, the release information, the minimum safety stock quantity and the availability and inventory information after the time the order information is input among the order information and the weekly sales plan information set at the end of the previous month (d ), 상기 월간 판매 계획은 제품 특성에 따라 복수의 상기 주간 판매 계획 정보로 분할되고, 상기 해당 주의 주간 판매 계획 정보는 상기 수신된 수주 정보에 의해 조정되는 것을 특징으로 하는 자재 소요량 및 생산 계획 소요량 산출 방법.The monthly sales plan is divided into a plurality of weekly sales plan information according to a product characteristic, and the weekly sales plan information of the corresponding week is adjusted by the received order information. 제1항에 있어서, The method of claim 1, 상기 매출 수량은 N개월 동안의 매출 수량의 평균으로 결정되되,The sales quantity is determined as the average of sales quantity for N months, 상기 N은 임의의 자연수인 것을 특징으로 하는 자재 소요량 및 생산 계획 소요량 산출 방법. The method for calculating material requirements and production plan requirements, characterized in that N is any natural number. 삭제delete 제1항에 있어서,The method of claim 1, 전월말의 상기 자재 소요량에 따라 생산 계획 소요량이 결정되고, 상기 결정된 생산 계획 소요량은 하나 이상의 로트(LOT)로 분할되며, Production plan requirements are determined according to the material requirements at the end of the previous month, the determined production plan requirements are divided into one or more lots, 상기 (d) 단계에서 자동 산출된 소요량과 해당 주의 이전 생산 계획 소요량을 비교하여 과부족을 연산하는 단계(e); 및(E) calculating an excess or deficiency by comparing the requirement automatically calculated in the step (d) with the previous production plan requirement of the week; And 상기 연산된 과부족 수치에 따라 상기 분할된 로트를 조정하는 단계(f)를 더 포함하는 것을 특징으로 하는 자재 소요량 및 생산 계획 소요량 산출 방법.And adjusting the divided lot in accordance with the calculated excess or deficiency value. 제4항에 있어서,The method of claim 4, wherein 상기 (f) 단계는 작업이 진행되지 않은 상기 분할된 로트(LOT) 중 최종 로트를 조정하는 것을 특징으로 하는 자재 소요량 및 생산 계획 소요량 산출 방법.The step (f) is a method for calculating material requirements and production planning requirements, characterized in that for adjusting the final lot of the divided lot (LOT) that is not in progress. 제1항, 제2항, 제4항 또는 제5항 중 어느 한 항을 실행하는 프로그램이 기록된 기록매체.A recording medium on which a program for executing any one of claims 1, 2, 4 or 5 is recorded.
KR1020050102580A 2005-10-28 2005-10-28 Method for yieding material requirement and product planning requirement and record media recored program for realizing the same KR100780103B1 (en)

Priority Applications (1)

Application Number Priority Date Filing Date Title
KR1020050102580A KR100780103B1 (en) 2005-10-28 2005-10-28 Method for yieding material requirement and product planning requirement and record media recored program for realizing the same

Applications Claiming Priority (1)

Application Number Priority Date Filing Date Title
KR1020050102580A KR100780103B1 (en) 2005-10-28 2005-10-28 Method for yieding material requirement and product planning requirement and record media recored program for realizing the same

Publications (2)

Publication Number Publication Date
KR20070045845A KR20070045845A (en) 2007-05-02
KR100780103B1 true KR100780103B1 (en) 2007-11-29

Family

ID=38271512

Family Applications (1)

Application Number Title Priority Date Filing Date
KR1020050102580A KR100780103B1 (en) 2005-10-28 2005-10-28 Method for yieding material requirement and product planning requirement and record media recored program for realizing the same

Country Status (1)

Country Link
KR (1) KR100780103B1 (en)

Cited By (1)

* Cited by examiner, † Cited by third party
Publication number Priority date Publication date Assignee Title
KR102211437B1 (en) * 2019-10-22 2021-02-03 윤종열 Production of orders with forecasts, inventory management, integrated planning operating methods

Families Citing this family (2)

* Cited by examiner, † Cited by third party
Publication number Priority date Publication date Assignee Title
CN111861208B (en) * 2020-07-20 2024-02-20 精效新软新技术(北京)有限公司 Automatic calculation method, system and medium for MRP material demand in production management
CN115526491B (en) * 2022-09-28 2023-11-17 惠州市海葵信息技术有限公司 Data processing method, equipment and storage medium for material demand planning

Cited By (1)

* Cited by examiner, † Cited by third party
Publication number Priority date Publication date Assignee Title
KR102211437B1 (en) * 2019-10-22 2021-02-03 윤종열 Production of orders with forecasts, inventory management, integrated planning operating methods

Also Published As

Publication number Publication date
KR20070045845A (en) 2007-05-02

Similar Documents

Publication Publication Date Title
US20190130330A1 (en) Method and system for management and control of highly complex projects
Sürie et al. Supply chain analysis
Porras et al. An inventory control system for spare parts at a refinery: An empirical comparison of different re-order point methods
US20070219929A1 (en) Planning granularity in manufacturing computing systems
US20030033180A1 (en) System and method for optimizing resource plans
US7412295B2 (en) Modeling manufacturing processes to include defined markers
JP2009140350A (en) Supply chain evaluation system, method, and program
US11500369B2 (en) Operation/maintenance management method, program, and operation/maintenance management system
Lee‐Mortimer A continuing lean journey: an electronic manufacturer's adopting of Kanban
US7324860B2 (en) Method, apparatus and program storage device for providing a cascading timeline of manufacturing events leading to completion of a manufactured product
Zhen et al. A stochastic programming model for multi-product oriented multi-channel component replenishment
Tavaghof-Gigloo et al. Planning approaches for stochastic capacitated lot-sizing with service level constraints
Teo et al. An application of master schedule smoothing and planned lead time control
Chinguwa et al. A decision framework based on aggregate production planning strategies in a multi-product factory: A furniture industry case study
Huang Information architecture for effective Workload Control: an insight from a successful implementation
US8027857B2 (en) Rough-cut manufacturing operations for use in planning
KR100780103B1 (en) Method for yieding material requirement and product planning requirement and record media recored program for realizing the same
JP4753590B2 (en) Method and system for selecting inventory replenishment model
JP6067630B2 (en) Profit / loss prediction apparatus and profit / loss prediction program
WO2012137492A1 (en) Worker positioning assistance device
US11238482B1 (en) Method and system for managing clearance items
US20070255605A1 (en) Multi-period financial simulator of a manufacturing operation
JP2007279998A (en) Inventory balance simulation system of type taking change to prior plan into account
US20040167831A1 (en) Rehandling planning system and rehandling planning method
Bangash et al. Inventory requirements planning at lucent technologies

Legal Events

Date Code Title Description
A201 Request for examination
E902 Notification of reason for refusal
E902 Notification of reason for refusal
E701 Decision to grant or registration of patent right
GRNT Written decision to grant
G170 Publication of correction
FPAY Annual fee payment

Payment date: 20121025

Year of fee payment: 6

FPAY Annual fee payment

Payment date: 20131118

Year of fee payment: 7

FPAY Annual fee payment

Payment date: 20140912

Year of fee payment: 8

FPAY Annual fee payment

Payment date: 20150910

Year of fee payment: 9

FPAY Annual fee payment

Payment date: 20161021

Year of fee payment: 10

FPAY Annual fee payment

Payment date: 20180124

Year of fee payment: 11

FPAY Annual fee payment

Payment date: 20181120

Year of fee payment: 12

FPAY Annual fee payment

Payment date: 20200108

Year of fee payment: 13