JPH10214293A - Load allocating method, deadline determining method, load allocating system, deadline determining system, production method, production system and recording medium - Google Patents

Load allocating method, deadline determining method, load allocating system, deadline determining system, production method, production system and recording medium

Info

Publication number
JPH10214293A
JPH10214293A JP1836397A JP1836397A JPH10214293A JP H10214293 A JPH10214293 A JP H10214293A JP 1836397 A JP1836397 A JP 1836397A JP 1836397 A JP1836397 A JP 1836397A JP H10214293 A JPH10214293 A JP H10214293A
Authority
JP
Japan
Prior art keywords
load
order
frame
capacity
production
Prior art date
Legal status (The legal status is an assumption and is not a legal conclusion. Google has not performed a legal analysis and makes no representation as to the accuracy of the status listed.)
Pending
Application number
JP1836397A
Other languages
Japanese (ja)
Inventor
Masaaki Oba
正明 大場
Sunao Wakatsuki
直 若槻
Yoshiteru Aikawa
芳輝 相川
Koji Fukushima
康二 福島
Toshibumi Uetake
俊文 植竹
Current Assignee (The listed assignees may be inaccurate. Google has not performed a legal analysis and makes no representation or warranty as to the accuracy of the list.)
Konica Minolta Inc
Original Assignee
Konica Minolta Inc
Priority date (The priority date is an assumption and is not a legal conclusion. Google has not performed a legal analysis and makes no representation as to the accuracy of the date listed.)
Filing date
Publication date
Application filed by Konica Minolta Inc filed Critical Konica Minolta Inc
Priority to JP1836397A priority Critical patent/JPH10214293A/en
Publication of JPH10214293A publication Critical patent/JPH10214293A/en
Pending legal-status Critical Current

Links

Classifications

    • YGENERAL TAGGING OF NEW TECHNOLOGICAL DEVELOPMENTS; GENERAL TAGGING OF CROSS-SECTIONAL TECHNOLOGIES SPANNING OVER SEVERAL SECTIONS OF THE IPC; TECHNICAL SUBJECTS COVERED BY FORMER USPC CROSS-REFERENCE ART COLLECTIONS [XRACs] AND DIGESTS
    • Y02TECHNOLOGIES OR APPLICATIONS FOR MITIGATION OR ADAPTATION AGAINST CLIMATE CHANGE
    • Y02PCLIMATE CHANGE MITIGATION TECHNOLOGIES IN THE PRODUCTION OR PROCESSING OF GOODS
    • Y02P90/00Enabling technologies with a potential contribution to greenhouse gas [GHG] emissions mitigation
    • Y02P90/02Total factory control, e.g. smart factories, flexible manufacturing systems [FMS] or integrated manufacturing systems [IMS]
    • YGENERAL TAGGING OF NEW TECHNOLOGICAL DEVELOPMENTS; GENERAL TAGGING OF CROSS-SECTIONAL TECHNOLOGIES SPANNING OVER SEVERAL SECTIONS OF THE IPC; TECHNICAL SUBJECTS COVERED BY FORMER USPC CROSS-REFERENCE ART COLLECTIONS [XRACs] AND DIGESTS
    • Y02TECHNOLOGIES OR APPLICATIONS FOR MITIGATION OR ADAPTATION AGAINST CLIMATE CHANGE
    • Y02PCLIMATE CHANGE MITIGATION TECHNOLOGIES IN THE PRODUCTION OR PROCESSING OF GOODS
    • Y02P90/00Enabling technologies with a potential contribution to greenhouse gas [GHG] emissions mitigation
    • Y02P90/30Computing systems specially adapted for manufacturing

Landscapes

  • Control By Computers (AREA)
  • Management, Administration, Business Operations System, And Electronic Commerce (AREA)
  • Multi-Process Working Machines And Systems (AREA)
  • General Factory Administration (AREA)

Abstract

PROBLEM TO BE SOLVED: To easily provide an exact deadline in a short time from the reception of order and further to provide a production managing system for decreasing the stock of complete articles and materials by considering not only the ability of production line required for production but also materials as 'frames'. SOLUTION: A deadline determining system 11 has an order storage part 12, a material frame storage part 1, a material load storage part 2, an ability frame storage part 3, an ability load storage part 4, an allocated load storage part 5, a calendar storage part 6, a keyboard 7, a CRT display 8, a printer 9 and an arithmetic part 10. In this case, the material frame is previously provided for showing the total amount or one part of material loads allocatable within a prescribed period. Then, based on information concerning the articles and amount of products ordered to be produced, the material load related to that order is found. When the material frame has a space for allocating the material load, that material load is allocated to the material frame.

Description

【発明の詳細な説明】DETAILED DESCRIPTION OF THE INVENTION

【0001】[0001]

【発明の属する技術分野】本発明は、製造業、特に中間
材料や部品の供給に長時間を要する製品の製造を行う受
注生産方式の製造業において、生産管理のために受注に
基づく製造負荷の割り付けを行う負荷割り付け方法、負
荷割り付けシステム、及び新規受注物件の納期を算出
し、出力する納期決定方法、納期決定システム、生産方
法、生産システム、記録媒体に関する。
BACKGROUND OF THE INVENTION 1. Field of the Invention The present invention relates to a manufacturing industry, in particular, an order-made manufacturing system for manufacturing products requiring a long time to supply intermediate materials and parts. The present invention relates to a load allocation method for performing allocation, a load allocation system, and a delivery date determination method, a delivery date determination system, a production method, a production system, and a recording medium for calculating and outputting a delivery date of a newly ordered property.

【0002】[0002]

【従来の技術】従来の生産管理システムは、注文を受け
てから生産スケジュールを作成するシステムになってい
た。そのため、受注時の生産ラインの状態、過去の納期
の実績、製造と販売の両部門で合意された製造リードタ
イム(製造に要する時間)等を考慮して、顧客との折衡
を行い、該注文の納期を決定していた。
2. Description of the Related Art A conventional production management system is a system for creating a production schedule after receiving an order. Therefore, taking into account the condition of the production line at the time of receiving the order, the past delivery date, the production lead time (time required for production) agreed by both the production and sales departments, etc. The delivery date of the order was determined.

【0003】このため、オーダーを受けてから納期を決
定するまでに、会議などの人同士による調整が必要であ
り、納期決定を短時間で行うことができなかった。ま
た、生産計画は生産ライン毎に行われるため、1つの受
注オーダー(注文)内に複数の品目が含まれる場合、各
品目同士の納期を近づけるために生産ライン間の調整を
することが難しく、早めに完成してしまった製品はオー
ダーの全製品が完成するまで在庫として保管しておかね
ばならず、完成品の在庫が増加するという問題も生じ
る。また、生産計画を変更するためには、それまでの生
産計画をすべてキャンセルして新たに計画しなおさなけ
ればならず、多大な労力及び時間を必要とする。また、
これらの決定には経験を要求され、誰もが容易に行える
ものではなかった。以上のように、従来の生産管理シス
テムは数々の問題点があった。
[0003] For this reason, coordination between people at a meeting or the like is required from the time an order is received until the delivery date is determined, and the delivery date cannot be determined in a short time. In addition, since a production plan is performed for each production line, when a plurality of items are included in one order (order), it is difficult to make adjustments between the production lines in order to shorten the delivery time of each item. Products that have been completed early must be kept in stock until all the products in the order have been completed, causing a problem that the inventory of finished products increases. Further, in order to change the production plan, it is necessary to cancel all the previous production plans and to re-plan a new one, which requires a great deal of labor and time. Also,
These decisions required experience and were not easy for everyone to make. As described above, the conventional production management system has a number of problems.

【0004】そこで、考えだされたシステムが能力枠シ
ステム、別名、生産座席システムである。該システム
は、交通機関の座席予約システムを生産管理システムに
応用したものであり、ある期間毎、例えば1日毎に特定
の生産ラインで生産可能な製品の量を、1日に該生産ラ
インが引き受けることができる生産ライン能力負荷の総
量又は一部を予め設定しておき(通常は総量全て)、こ
れを能力枠とする。そして、該能力枠に、オーダーを割
り付けていくというものである。例えば、ある生産ライ
ンの1日の稼働時間を能力枠としたときに、オーダーに
係る製品のある品目を全て生産するのに必要な該生産ラ
インの稼働時間を求め、能力枠の空いている部分に割り
付けていく。そして、割り付けた能力枠に該当する日の
うちの最終日が、該製品の納期となる。この能力枠シス
テムにより、正確な納期を短時間で知ることができ、顧
客の希望納期に対応できるか、否か、否の場合は納期が
いつになるか等に素早く回答することができる。また、
1つの受注オーダー内に複数の品目が含まれる場合であ
っても、それぞれの品目の納期が近くなるように、オー
ダーを能力枠に割り付けることが容易であり、完成品の
在庫を減らすことができるようになった。
[0004] Thus, a system devised is a capacity quota system, also known as a production seat system. This system is an application of a transportation seat reservation system to a production management system, and the production line takes over the amount of products that can be produced on a specific production line every certain period, for example, every day. The total amount or a part of the production line capacity load that can be set is set in advance (usually the total amount), and this is set as a capacity frame. Then, an order is assigned to the capacity frame. For example, when the daily operation time of a certain production line is set as the capacity frame, the operation time of the production line required to produce all the items of the product pertaining to the order is obtained, and the vacant portion of the capacity frame is obtained. Assigned to. Then, the last day of the days corresponding to the assigned capacity frame is the delivery date of the product. With this capacity frame system, an accurate delivery date can be known in a short time, and it can be quickly answered whether or not the customer can meet the desired delivery date, and if not, when the delivery date will be. Also,
Even when one order contains a plurality of items, it is easy to assign the orders to capacity slots so that the delivery dates of the respective items are close, and the inventory of finished products can be reduced. It became so.

【0005】[0005]

【発明が解決しようとする課題】しかしながら、能力枠
システムは、材料や部品の供給が常に充分に行われてい
ることが前提である。つまり、生産ラインの能力のみを
考慮して負荷の割り付けが行われ、納期が決定される。
However, the capacity framing system is based on the premise that materials and parts are always supplied sufficiently. That is, the load is assigned in consideration of only the capacity of the production line, and the delivery date is determined.

【0006】しかしながら、例えば、写真感光材料を生
産する場合等のように、使用する材料や部品が、供給に
長時間を要し、常に安定な材料の供給を望めず、欲しい
ときに好きなだけ得ることができる材料ではないような
場合には、能力枠のみを用いた生産管理システムによ
り、納期を決定したとしても、材料の供給が遅れること
などによって、納期に間に合わないなどの問題が生じ
る。また、原材料から製品になるまでに長時間を要する
製品を生産する場合は、オーダーを受けてから原材料か
ら生産していたのでは非常に時間がかかり、顧客の希望
に対応できないため、オーダーを受けてから出荷までの
リードタイムを短くするために、中間材料を見込み生産
しておく場合がある。このような場合も、中間材料を多
量に余分に製造するわけにはいかないため、中間材料の
供給を常に十分に安定して行えるとは限らず、やはり、
材料の供給が遅れることなどによって、納期に間に合わ
ないなどの問題が生じる。また、このような不確定要素
が多いシステムのもとでは、予定納期は正確な納期とい
うことはできず、一方、不確定要素まで考慮して正確な
納期を求めようとするのは困難であり、時間もかかる。
However, as in the case of producing photographic light-sensitive materials, for example, the materials and parts to be used take a long time to be supplied, and stable supply of materials is not always desired. In the case where the material is not a material that can be obtained, even if the delivery date is determined by the production management system using only the capacity frame, there arises a problem that the supply of the material is delayed and the delivery time cannot be met. Also, when producing a product that takes a long time to become a product from raw materials, it takes a very long time to produce from raw materials after receiving an order. In order to shorten the lead time from shipment to shipment, intermediate materials are sometimes produced in anticipation. Even in such a case, the intermediate material cannot be produced in a large amount in excess, so that the supply of the intermediate material cannot always be performed sufficiently stably.
Due to a delay in the supply of materials, problems such as being unable to meet a delivery date arise. Also, under such a system with many uncertain factors, the expected delivery date cannot be an accurate delivery date, while it is difficult to obtain an accurate delivery date taking into account the uncertain factors. It takes time.

【0007】また、そのような納期遅れを生じさせない
ためには、材料を常に安定して供給できる状態にしてお
く必要があるため、材料の在庫が必要となる。
Further, in order to prevent such a delay in delivery, it is necessary to always supply the material stably, so that a stock of the material is required.

【0008】そこで、本発明者は、生産に必要な生産ラ
インの能力だけでなく、材料も「枠」として考慮するこ
とにより、上記問題点を解決できることを見いだした。
The present inventor has found that the above problem can be solved by considering not only the capacity of the production line required for production but also the material as a "frame".

【0009】したがって本発明は、材料や部品の供給に
長時間を要する製品や、中間材料を見込み生産しておく
製品など、常に材料の安定な供給を望めず、欲しいとき
に欲しいだけの量の材料を得ることが困難な製品を生産
する場合であっても、正確な納期をオーダーを受けてか
ら短時間で容易に得ることができ、さらに、完成品並び
に材料の在庫を減らすことを可能とする生産管理システ
ムを提供することを目的とするものである。
Therefore, the present invention does not always require a stable supply of materials, such as products that require a long time to supply materials and parts and products that anticipate the production of intermediate materials. Even when producing products for which it is difficult to obtain materials, accurate delivery times can be easily obtained in a short time after receiving an order, and it is possible to reduce inventory of finished products and materials. It is an object of the present invention to provide a production management system that performs

【0010】[0010]

【課題を解決するための手段】本発明の目的は以下に示
す特許請求の範囲の各請求項により達成される。
SUMMARY OF THE INVENTION The object of the present invention is achieved by the following claims.

【0011】〔請求項1〕『所定期間内に割り付けるこ
とが可能な材料負荷の総量又は一部を示す材料枠を予め
設けておき、生産のオーダーを受けた製品の品目及び数
量に関する情報に基づいて前記オーダーに係る材料負荷
を求め、前記材料負荷を割り付けることができる空きが
前記材料枠にある場合に、前記材料負荷を前記材料枠に
割り付けることを特徴とする負荷割り付け方法。』 〔請求項2〕『所定期間内に割り付けることが可能な生
産ライン能力負荷の総量又は一部を示す能力枠と、前記
所定期間内に割り付けることが可能な材料負荷の総量又
は一部を示す材料枠を予め設けておき、生産のオーダー
を受けた製品の品目及び数量に関する情報に基づいて、
前記オーダーに係る生産ライン能力負荷と材料負荷とを
求め、前記オーダーに係る前記生産ライン能力負荷を割
り付けることができる空きが、前記所定期間内の前記能
力枠にあり、かつ、前記オーダーに係る前記材料負荷を
割り付けることができる空きが、前記所定期間内の前記
材料枠にある場合に、前記オーダーに係る前記生産ライ
ン能力負荷を前記所定期間内の前記能力枠に、前記オー
ダーに係る前記材料負荷を前記所定期間内の前記材料枠
にそれぞれ割り付けることを特徴とする負荷割り付け方
法。』 〔請求項3〕『複数の所定期間を予め定め、各所定期間
内に割り付けることが可能な生産ライン能力負荷の総量
又は一部を示す能力枠と、各所定期間内に割り付けるこ
とが可能な材料負荷の総量又は一部を示す材料枠を予め
設けておき、生産のオーダーを受けた製品の品目及び数
量に関する情報に基づいて、前記オーダーに係る生産ラ
イン能力負荷と材料負荷とを求め、前記オーダーに係る
前記生産ライン能力負荷を割り付けることができる空き
が、1もしくは複数の前記所定期間に係る前記能力枠に
あり、かつ、前記オーダーに係る前記材料負荷を割り付
けることができる空きが、前記1もしくは複数の前記所
定期間と同一の、1もしくは複数の所定期間に係る前記
材料枠にある場合に、前記オーダーに係る前記生産ライ
ン能力負荷を、前記1もしくは複数の前記所定期間に係
る前記能力枠に割り付け、前記オーダーに係る前記材料
負荷を、前記オーダーに係る前記生産ライン能力負荷を
割り付けた前記1もしくは複数の前記所定期間と同一の
1もしくは複数の所定期間に係る前記材料枠に割り付け
ることを特徴とする負荷割り付け方法。』 請求項1〜3に係る発明により、材料や部品の供給に長
時間を要する製品や、中間材料を見込み生産しておく製
品など、常に材料の安定な供給を望めず、欲しいときに
欲しいだけの量の材料を得ることが困難な製品を生産す
る場合であっても、正確な納期をオーダーを受けてから
短時間で容易に、人手を介さずに得ることができ、さら
に、完成品並びに材料の在庫を減らすことが可能とな
る。
[Claim 1] "A material frame indicating the total amount or a part of the material load that can be allocated within a predetermined period is provided in advance, and based on information on the item and quantity of the product ordered for production. A load assignment method for determining a material load associated with the order and assigning the material load to the material frame when there is a space in the material frame to which the material load can be assigned. [Claim 2] "Shows the capacity frame indicating the total amount or a part of the production line capacity load that can be allocated within a predetermined period, and the total amount or a part of the material load that can be allocated within the predetermined period. Material quotas are set up in advance, and based on information on the item and quantity of the product ordered for production,
The production line capacity load and material load pertaining to the order are determined, and an empty space in which the production line capacity load pertaining to the order can be allocated is in the capacity frame within the predetermined period, and When there is a space in which the material load can be allocated in the material frame within the predetermined period, the production line capacity load related to the order is assigned to the capacity frame within the predetermined period, and the material load related to the order is changed. Allocating to the material frames within the predetermined period. [Claim 3] "A plurality of predetermined periods are determined in advance, and a capacity frame indicating the total amount or a part of the production line capacity load that can be allocated within each predetermined period, and can be allocated within each predetermined period. A material frame indicating the total amount or a part of the material load is provided in advance, and the production line capacity load and the material load related to the order are obtained based on the information on the item and the quantity of the product for which the production order has been received. The vacant space to which the production line capacity load pertaining to the order can be allocated is in the capacity frame pertaining to one or a plurality of the predetermined periods, and the vacant space to which the material load pertaining to the order can be allocated is the 1 Or the same as the plurality of predetermined periods, when in the material frame according to one or more predetermined periods, the production line capacity load according to the order, Allocating the capacity frame relating to the one or more predetermined periods, and assigning the material load relating to the order to one or more of the one or plurality of the predetermined periods that are allotting the production line capacity load relating to the order. A load assignment method, wherein the assignment is made to the material frames for a plurality of predetermined periods. According to the inventions according to claims 1 to 3, it is not always possible to expect a stable supply of materials, such as products that require a long time to supply materials and parts, and products that are expected to produce intermediate materials, but only when needed. Even when producing a product for which it is difficult to obtain an amount of material, it is possible to obtain an accurate delivery date in a short time after receiving an order, easily and without human intervention. It is possible to reduce the stock of materials.

【0012】また、生産部門と販売部門と、共にオーダ
ーの進捗状況がリアルタイムで把握できるので、生販間
の調整が不要となる。さらには、生産の負荷の平均化が
可能となる。
Further, since the progress of the order can be grasped in real time by both the production department and the sales department, there is no need to adjust between the production and sales. Furthermore, the production load can be averaged.

【0013】〔請求項4〕『前記生産のオーダーが希望
納期を有している場合に、前記生産のオーダーの希望納
期を含む所定期間に係る前記能力枠に、前記生産のオー
ダーに係る前記生産ライン能力負荷の最初の割り付けを
行い、その後、1所定期間ずつ遡って、前記生産のオー
ダーに係る前記生産ライン能力負荷の前記能力枠への割
り付けを行っていき、前記生産のオーダーに係る全ての
前記生産ライン能力負荷の割り付けが行えた場合には、
前記割り付けを完了し、前記生産のオーダーに係る全て
の前記生産ライン能力負荷の割り付けが行えなかった場
合には、さらに前記生産のオーダーの希望納期を含む所
定期間から1所定期間ずつ進んで、前記生産のオーダー
に係る前記生産ライン能力負荷の前記能力枠への割り付
けを行い、又、前記生産のオーダーの希望納期を含む所
定期間に係る前記材料枠に、前記生産のオーダーに係る
前記材料負荷の最初の割り付けを行い、その後、1所定
期間ずつ遡って、前記生産のオーダーに係る前記材料負
荷の前記材料枠への割り付けを行っていき、前記生産の
オーダーに係る全ての前記材料負荷の割り付けが行えた
場合には、前記割り付けを完了し、前記生産のオーダー
に係る全ての前記材料負荷の割り付けが行えなかった場
合には、さらに前記生産のオーダーの希望納期を含む所
定期間から1所定期間ずつ進んで、前記生産のオーダー
に係る前記材料負荷の前記材料枠への割り付けを行うこ
とを特徴とする請求項3に記載の負荷割り付け方法。』 本請求項に係る発明により、希望納期にオーダーの生産
が間に合うか否かを容易に知ることができ、間に合わな
い場合は予定納期がいつになるのかを容易に知ることが
できる。
[Claim 4] "If the production order has a desired delivery date, the capacity frame relating to a predetermined period including the desired delivery date of the production order includes the production order related to the production order. The initial allocation of the line capacity load is performed, and thereafter, the production line capacity load related to the production order is allocated to the capacity frame by going back by one predetermined period, and all the allocations related to the production order are performed. When the production line capacity load can be assigned,
If the allocation is completed and all the production line capacity loads related to the production order cannot be allocated, the production order further advances by a predetermined period from a predetermined period including a desired delivery date of the production order, Allocating the production line capacity load pertaining to the production order to the capacity frame, and assigning the material load pertaining to the production order to the material frame pertaining to a predetermined period including the desired delivery date of the production order. The first assignment is performed, and thereafter, the material load related to the production order is assigned to the material frame by going back one predetermined period, and the assignment of all the material loads related to the production order is performed. If the assignment is completed, the assignment is completed.If all the material loads related to the production order cannot be assigned, the 4. The load allocating method according to claim 3, wherein the material load relating to the production order is allocated to the material frame by advancing one predetermined period from a predetermined period including a desired delivery date of the production order. . With the invention according to the present claim, it is possible to easily know whether or not the production of the order is in time for the desired delivery date, and if not, it is possible to easily know when the scheduled delivery date will be.

【0014】〔請求項5〕『前記同一の所定期間に係る
前記能力枠に割り付ける前記生産ライン能力負荷と、前
記材料枠に割り付ける前記材料負荷とが、同一の前記製
品の品目及び同一の数量に係る前記生産ライン能力負荷
及び前記材料負荷であることを特徴とする請求項2〜4
のいずれか1項に記載の負荷割り付け方法。』 本請求項に係る発明により、実行不可能な負荷の割り付
けを行うことが防止できる。
[Claim 5] "The production line capacity load allocated to the capacity frame relating to the same predetermined period and the material load allocated to the material frame correspond to the same product item and the same quantity. 5. The production line capacity load and the material load.
The load allocation method according to any one of the above. According to the present invention, it is possible to prevent assignment of an unexecutable load.

【0015】〔請求項6〕『前記製品が写真感光材料で
あることを特徴とする請求項1〜5のいずれか1項に記
載の負荷割り付け方法。』 写真感光材料の製造は、非常に多種類の原材料から元巻
きという中間材料を経て、製造するものであるため、材
料や部品の供給に長時間を要し、常に安定な材料の供給
を望めず、用いる材料が欲しいときに好きなだけ得るこ
とができる材料ではないため、本発明の材料枠を用いた
負荷割り付け方法が非常に有効である。また、余分な在
庫を減らすことが可能になることにより、長期保存には
適さない感光性の写真感光材料の在庫による長期保存を
防止することが可能となり、安定した品質の写真感光材
料の供給を行うことが可能となる。
(6) The method according to any one of (1) to (5), wherein the product is a photographic material. The production of photographic photosensitive materials involves the production of a wide variety of raw materials through intermediate materials called original winding, so it takes a long time to supply materials and parts, and we can always expect a stable supply of materials. However, since the material to be used is not a material that can be obtained as much as desired when desired, the load allocation method using the material frame of the present invention is very effective. In addition, since it is possible to reduce excess inventory, it is possible to prevent long-term storage due to inventory of photosensitive photographic materials that are not suitable for long-term storage, and supply of stable quality photographic materials. It is possible to do.

【0016】〔請求項7〕『請求項1〜6のいずれか1
項に記載の負荷割り付け方法による割り付け結果に基づ
いて、前記オーダーの納期を決定することを特徴とする
納期決定方法。』 〔請求項8〕『前記生産のオーダーに係る前記生産ライ
ン能力負荷と前記材料負荷の割り付けを行った前記能力
枠と前記材料枠で、最も後の所定期間に係る前記能力枠
及び前記材料枠の前記所定期間を前記オーダーの納期と
することを特徴とする請求項7に記載の納期決定方
法。』 請求項7又は8に係る発明により、材料や部品の供給に
長時間を要する製品や、中間材料を見込み生産しておく
製品など、常に材料の安定な供給を望めず、欲しいとき
に欲しいだけの量の材料を得ることが困難な製品を生産
する場合であっても、正確な納期をオーダーを受けてか
ら短時間で容易に、人手を介さずに得ることができ、さ
らに、完成品並びに材料の在庫を減らすことが可能とな
る。
[Claim 7] "Any one of claims 1 to 6"
A delivery date determination method, wherein a delivery date of the order is determined based on an allocation result by the load allocation method described in the section. [Claim 8] "In the capacity frame and the material frame to which the production line capacity load and the material load related to the production order are assigned, the capacity frame and the material frame related to the last predetermined period. 8. The delivery date determining method according to claim 7, wherein the predetermined period is a delivery date of the order. According to the invention according to claim 7 or 8, a stable supply of material is not always desired, such as a product requiring a long time to supply a material or a part, or a product for which an intermediate material is expectedly produced. Even when producing a product for which it is difficult to obtain an amount of material, it is possible to obtain an accurate delivery date in a short time after receiving an order, easily and without human intervention. It is possible to reduce the stock of materials.

【0017】〔請求項9〕『請求項1〜6のいずれか1
項に記載の負荷割り付け方法による割り付け結果に基づ
いて前記製品の生産を行うことを特徴とする生産方
法。』 本請求項に係る発明により、材料や部品の供給に長時間
を要する製品や、中間材料を見込み生産しておく製品な
ど、常に材料の安定な供給を望めず、欲しいときに欲し
いだけの量の材料を得ることが困難な製品を生産する場
合であっても、納期を容易に求めることができ、生産を
計画的に行うことが可能となる。
[Claim 9] [Any one of claims 1 to 6]
A production method of producing the product based on an allocation result by the load allocation method described in the section. According to the claimed invention, a stable supply of materials is not always desired, such as products that require a long time to supply materials and parts, and products that are expected to produce intermediate materials. Even when producing a product for which it is difficult to obtain the above materials, the delivery date can be easily obtained, and the production can be performed systematically.

【0018】さらに、完成品並びに材料の在庫を減らす
ことが可能となる。
Further, it is possible to reduce inventory of finished products and materials.

【0019】〔請求項10〕『請求項1〜6のいずれか
1項に記載の負荷割り付け方法によって負荷割り付けを
行うことを特徴とする負荷割り付けシステム。』 請求項1〜3に係る発明により、材料や部品の供給に長
時間を要する製品や、中間材料を見込み生産しておく製
品など、常に材料の安定な供給を望めず、欲しいときに
欲しいだけの量の材料を得ることが困難な製品を生産す
る場合であっても、正確な納期をオーダーを受けてから
短時間で容易に、人手を介さずに得ることができ、さら
に、完成品並びに材料の在庫を減らすことが可能とな
る。
[Claim 10] [A load assignment system, wherein the load assignment is performed by the load assignment method according to any one of claims 1 to 6. According to the inventions according to claims 1 to 3, it is not always possible to expect a stable supply of materials, such as products that require a long time to supply materials and parts, and products that are expected to produce intermediate materials, but only when needed. Even when producing a product for which it is difficult to obtain an amount of material, it is possible to obtain an accurate delivery date in a short time after receiving an order, easily and without human intervention. It is possible to reduce the stock of materials.

【0020】また、生産部門と販売部門と、共にオーダ
ーの進捗状況がリアルタイムで把握できるので、生販間
の調整が不要となる。さらには、生産の負荷の平均化が
可能となる。
In addition, since the progress of the order can be grasped in real time by both the production department and the sales department, there is no need to make adjustments between live sales. Furthermore, the production load can be averaged.

【0021】〔請求項11〕『前記負荷割り付けを行っ
た結果を出力することを特徴とする請求項10に記載の
負荷割り付けシステム。』 本請求項に係る発明により、負荷割り付けを行った結果
を容易に知ることができる。
[Claim 11] [The load assignment system according to claim 10, wherein a result of the assignment is output. With the invention according to the present claim, the result of the load allocation can be easily known.

【0022】〔請求項12〕『前記負荷割り付けを行っ
た結果の出力をグラフ表示により出力することを特徴と
する請求項11に記載の負荷割り付けシステム。』 本請求項に係る発明により、負荷割り付けを行った後の
状況が視覚的により分かりやすくなる。
[Claim 12] [The load assignment system according to claim 11, wherein the output of the result of the load assignment is output as a graph. According to the invention according to the present claim, the situation after the load allocation is performed becomes visually easier to understand.

【0023】〔請求項13〕『請求項7又は8に記載の
納期決定方法によって納期を決定することを特徴とする
納期決定システム。』 本請求項に係る発明により、材料や部品の供給に長時間
を要する製品や、中間材料を見込み生産しておく製品な
ど、常に材料の安定な供給を望めず、欲しいときに欲し
いだけの量の材料を得ることが困難な製品を生産する場
合であっても、正確な納期をオーダーを受けてから短時
間で容易に、人手を介さずに得ることができ、さらに、
完成品並びに材料の在庫を減らすことが可能となる。
[Claim 13] "A delivery date determination system wherein the delivery date is determined by the delivery date determination method according to claim 7 or 8." According to the claimed invention, a stable supply of materials is not always desired, such as products that require a long time to supply materials and parts, and products that are expected to produce intermediate materials. Even in the case of producing a product for which it is difficult to obtain a material, it is possible to obtain an accurate delivery time in a short time after receiving an order, easily and without human intervention, and
It is possible to reduce inventory of finished products and materials.

【0024】〔請求項14〕『決定された前記納期を出
力することを特徴とする請求項13に記載の納期決定シ
ステム。』 本請求項に係る発明により、決定された納期を容易に知
ることができる。
[14] The delivery date determination system according to claim 13, wherein the determined delivery date is output. With the invention according to the present claim, the determined delivery date can be easily known.

【0025】〔請求項15〕『請求項9に記載の生産方
法によって前記製品の生産を行うことを特徴とする生産
システム。』 本請求項に係る発明により、材料や部品の供給に長時間
を要する製品や、中間材料を見込み生産しておく製品な
ど、常に材料の安定な供給を望めず、欲しいときに欲し
いだけの量の材料を得ることが困難な製品を生産する場
合であっても、納期を容易に求めることができ、生産を
計画的に行うことが可能となる。
[15] A production system wherein the product is produced by the production method according to claim 9. According to the claimed invention, a stable supply of materials is not always desired, such as products that require a long time to supply materials and parts, and products that are expected to produce intermediate materials. Even when producing a product for which it is difficult to obtain the above materials, the delivery date can be easily obtained, and the production can be performed systematically.

【0026】さらに、完成品並びに材料の在庫を減らす
ことが可能となる。
Further, it is possible to reduce inventory of finished products and materials.

【0027】〔請求項16〕『生産のオーダーに係る製
品の品目及び数量に関する情報を入力する入力手段と、
各品目に係る材料負荷を記憶している材料負荷記憶手段
と、各所定期間内に割り付けることが可能な材料負荷の
総量の全部又は1部を前記各所定期間毎の材料枠として
記憶する材料枠記憶手段と、前記材料枠に既に割り付け
られている材料負荷を記憶している割り付け済負荷記憶
手段と、前記入力手段により入力された情報に基づい
て、前記材料負荷記憶手段に記憶されている前記オーダ
ーに係る製品の各品目の材料負荷から、前記オーダーに
係る材料負荷を求め、前記材料枠記憶手段に記憶されて
いる前記材料枠と、前記割り付け済負荷記憶手段に記憶
されている前記材料枠に既に割り付けられている前記材
料負荷とから、前記オーダーに係る材料負荷を割り付け
ることができる空きがある前記材料枠を求め、前記空き
がある材料枠に前記オーダーに係る材料負荷を割り付け
る演算手段とを有することを特徴とする負荷割り付けシ
ステム。』 〔請求項17〕『生産のオーダーに係る製品の品目及び
数量に関する情報を入力する入力手段と、前記各品目に
係る生産ライン能力負荷を記憶している生産ライン能力
負荷記憶手段と、前記各品目に係る材料負荷を記憶して
いる材料負荷記憶手段と、各所定期間内に割り付けるこ
とが可能な生産ライン能力負荷の総量の全部又は1部を
前記各所定期間毎の能力枠として記憶する能力枠記憶手
段と、各所定期間内に割り付けることが可能な材料負荷
の総量の全部又は1部を前記各所定期間毎の材料枠とし
て記憶する材料枠記憶手段と、前記能力枠と前記材料枠
に、既に割り付けられている生産ライン能力負荷と材料
負荷を記憶している割り付け済負荷記憶手段と、前記入
力手段により入力された情報に基づいて、前記生産ライ
ン能力負荷記憶手段に記憶されている前記オーダーに係
る製品の各品目の生産ライン能力負荷から、前記オーダ
ーに係る生産ライン能力負荷を求め、前記材料負荷記憶
手段に記憶されている前記オーダーに係る製品の各品目
の材料負荷から、前記オーダーに係る材料負荷を求め、
前記能力枠記憶手段に記憶されている前記能力枠と、前
記割り付け済負荷記憶手段に記憶されている前記能力枠
に既に割り付けられている前記生産ライン能力負荷とか
ら、前記オーダーに係る生産ライン能力負荷を割り付け
ることができる空きがある前記能力枠を求め、前記材料
枠記憶手段に記憶されている前記材料枠と、前記割り付
け済負荷記憶手段に記憶されている前記材料枠に既に割
り付けられている前記材料負荷とから、前記オーダーに
係る材料負荷を割り付けることができる空きがある前記
材料枠を求め、空きがある前記能力枠に前記オーダーに
係る生産ライン能力負荷を割り付け、前記オーダーに係
る生産ライン能力負荷を割り付けた前記能力枠と同一期
間に係る空きがある前記材料枠に、前記オーダーに係る
材料負荷を割り付ける演算手段とを有することを特徴と
する負荷割り付けシステム。』 請求項16又は17に係る発明により、材料や部品の供
給に長時間を要する製品や、中間材料を見込み生産して
おく製品など、常に材料の安定な供給を望めず、欲しい
ときに欲しいだけの量の材料を得ることが困難な製品を
生産する場合であっても、正確な納期をオーダーを受け
てから短時間で容易に、人手を介さずに得ることがで
き、さらに、完成品並びに材料の在庫を減らすことが可
能となる。
[Claim 16] An input means for inputting information on an item and a quantity of a product related to a production order;
A material load storing means for storing a material load relating to each item, and a material frame for storing all or a part of the total amount of the material load that can be allocated within each predetermined period as a material frame for each of the predetermined periods A storage unit, an assigned load storage unit that stores a material load already assigned to the material frame, and the information stored in the material load storage unit based on information input by the input unit. The material load related to the order is determined from the material load of each item of the product related to the order, and the material frame stored in the material frame storage unit and the material frame stored in the allocated load storage unit. From the material load that has already been allocated to, the material frame having a vacant space to which the material load according to the order can be allocated is obtained, and the material frame having the vacant space is Load allocation system characterized by having a calculating means for allocating material load on the leader. [Claim 17] "Input means for inputting information on the item and quantity of a product pertaining to a production order, production line capacity load storage means for storing a production line capacity load pertaining to each item, A material load storing means for storing a material load relating to the item, and an ability to store all or a part of the total amount of the production line capacity load that can be allocated within each predetermined period as a capacity frame for each of the predetermined periods. Frame storage means, material frame storage means for storing all or a part of the total amount of material load that can be allocated within each predetermined period as a material frame for each of the predetermined periods, and Assigned load storage means for storing the already assigned production line capacity load and material load, and the production line capacity load storage based on information input by the input means. From the production line capacity load of each item of the product of the order stored in the means, the production line capacity load of the order is determined, and each item of the product of the order stored in the material load storage means. From the material load of, determine the material load pertaining to the order,
From the capacity frame stored in the capacity frame storage means and the production line capacity load already allocated to the capacity frame stored in the allocated load storage means, the production line capacity according to the order The capacity frame having a space to which a load can be allocated is obtained, and the capacity frame is already allocated to the material frame stored in the material frame storage unit and the material frame stored in the allocated load storage unit. From the material load, determine the material frame having a space to which the material load according to the order can be allocated, allocate the production line capacity load according to the order to the capacity frame having the space, and perform the production line according to the order. Allocate the material load related to the order to the material frame that has a vacant space for the same period as the capacity frame to which the capacity load is allocated. Load allocation system; and a calculation unit that. According to the invention according to claim 16 or 17, a stable supply of material is not always desired, such as a product requiring a long time to supply a material or a part, or a product for which an intermediate material is expectedly produced. Even when producing a product for which it is difficult to obtain an amount of material, it is possible to obtain an accurate delivery date in a short time after receiving an order, easily and without human intervention. It is possible to reduce the stock of materials.

【0028】また、生産部門と販売部門と、共にオーダ
ーの進捗状況がリアルタイムで把握できるので、生販間
の調整が不要となる。さらには、生産の負荷の平均化が
可能となる。
Further, since the progress of the order can be grasped in real time by both the production department and the sales department, there is no need to adjust between the live sales. Furthermore, the production load can be averaged.

【0029】〔請求項18〕『前記演算手段は、前記生
産のオーダーの希望納期を含む所定期間に係る前記能力
枠に、前記生産のオーダーに係る前記生産ライン能力負
荷の最初の割り付けを行い、その後、1所定期間ずつ遡
って、前記生産のオーダーに係る前記生産ライン能力負
荷の前記能力枠への割り付けを行っていき、前記生産の
オーダーに係る全ての前記生産ライン能力負荷の割り付
けが行えた場合には、前記生産ライン能力負荷の割り付
けを完了し、前記生産のオーダーに係る全ての前記生産
ライン能力負荷の割り付けが行えなかった場合には、さ
らに前記生産のオーダーの希望納期を含む所定期間から
1所定期間ずつ進んで、前記生産のオーダーに係る前記
生産ライン能力負荷の前記能力枠への割り付けを行い、
又、前記演算手段は、前記生産のオーダーの希望納期を
含む所定期間に係る前記材料枠に、前記生産のオーダー
に係る前記材料負荷の最初の割り付けを行い、その後、
1所定期間ずつ遡って、前記生産のオーダーに係る前記
材料負荷の前記材料枠への割り付けを行っていき、前記
生産のオーダーに係る全ての前記材料負荷の割り付けが
行えた場合には、前記材料負荷の割り付けを完了し、前
記生産のオーダーに係る全ての前記材料負荷の割り付け
が行えなかった場合には、さらに前記生産のオーダーの
希望納期を含む所定期間から1所定期間ずつ進んで、前
記生産のオーダーに係る前記材料負荷の前記材料枠への
割り付けを行うことを特徴とする請求項17に記載の負
荷割り付けシステム。』 本請求項に係る発明により、希望納期にオーダーの生産
が間に合うか否かを容易に知ることができ、間に合わな
い場合は予定納期がいつになるのかを容易に知ることが
できる。
[Claim 18] "The calculating means first assigns the production line capacity load related to the production order to the capacity frame related to a predetermined period including a desired delivery date of the production order, Thereafter, going back one predetermined period at a time, the production line capacity load related to the production order was assigned to the capacity frame, and all the production line capacity loads related to the production order were assigned. In the case, the allocation of the production line capacity load is completed, and if all the production line capacity loads related to the production order cannot be allocated, a predetermined period including the desired delivery date of the production order. From the production line capacity load related to the production order is assigned to the capacity frame,
Further, the calculation means performs the first assignment of the material load related to the production order to the material frame related to a predetermined period including a desired delivery date of the production order, and thereafter,
Going back one predetermined period at a time, the material load related to the production order is assigned to the material frame, and if all the material loads related to the production order are assigned, the material If the load allocation is completed and all the material loads related to the production order cannot be allocated, the production order is further advanced by one predetermined period from a predetermined period including a desired delivery date of the production order, and the production 18. The load assignment system according to claim 17, wherein the assignment of the material load according to the order of (1) to the material frame is performed. With the invention according to the present claim, it is possible to easily know whether or not the production of the order is in time for the desired delivery date, and if not, it is possible to easily know when the scheduled delivery date will be.

【0030】〔請求項19〕『前記演算手段は、同一の
前記所定期間に係る前記能力枠と前記材料枠とに割り付
ける前記生産ライン能力負荷と前記材料負荷とが、同一
の前記製品の品目及び同一の数量に係る前記生産ライン
能力負荷及び前記材料負荷となるように、前記生産のオ
ーダーに係る前記生産ライン能力負荷の前記能力枠への
割り付け、及び前記生産のオーダーに係る前記材料負荷
の前記材料枠への割り付けを行うことを特徴とする請求
項17又は18に記載の負荷割り付けシステム。』 本請求項に係る発明により、実行不可能な負荷の割り付
けを行うことが防止できる。
[Claim 19] [The arithmetic means determines that the production load capacity load and the material load assigned to the capacity frame and the material frame for the same predetermined period are the same for the product item and the product line. Allocating the production line capacity load pertaining to the production order to the capacity frame, and the material load pertaining to the production order so that the production line capacity load and the material load pertain to the same quantity. 19. The load assignment system according to claim 17, wherein assignment to a material frame is performed. According to the present invention, it is possible to prevent assignment of an unexecutable load.

【0031】〔請求項20〕『前記製品が写真感光材料
であることを特徴とする請求項16〜19のいずれか1
項に記載の負荷割り付けシステム。』 写真感光材料の製造は、非常に多種類の原材料から元巻
きという中間材料を経て、製造するものであるため、材
料や部品の供給に長時間を要し、常に安定な材料の供給
を望めず、用いる材料が欲しいときに好きなだけ得るこ
とができる材料ではないため、本発明の材料枠を用いた
負荷割り付け方法が非常に有効である。また、余分な在
庫を減らすことが可能になることにより、長期保存には
適さない感光性の写真感光材料の在庫による長期保存を
防止することが可能となり、安定した品質の写真感光材
料の供給を行うことが可能となる。
[Claim 20] "The product according to any one of claims 16 to 19, wherein the product is a photographic light-sensitive material.
Load allocation system described in section. The production of photographic photosensitive materials involves the production of a wide variety of raw materials through intermediate materials called original winding, so it takes a long time to supply materials and parts, and we can always expect a stable supply of materials. However, since the material to be used is not a material that can be obtained as much as desired when desired, the load allocation method using the material frame of the present invention is very effective. In addition, since it is possible to reduce excess inventory, it is possible to prevent long-term storage due to inventory of photosensitive photographic materials that are not suitable for long-term storage, and supply of stable quality photographic materials. It is possible to do.

【0032】〔請求項21〕『前記負荷割り付けの結果
を出力する出力手段を有することを特徴とする請求項1
6〜20のいずれか1項に記載の負荷割り付けシステ
ム。』 本請求項に係る発明により、負荷割り付けの結果を容易
に知ることができる。
[Claim 21] [The invention has an output means for outputting a result of the load assignment.
21. The load allocation system according to any one of 6 to 20. With the invention according to the present claim, the result of the load allocation can be easily known.

【0033】〔請求項22〕『前記出力手段は、前記負
荷割り付けの結果をグラフ表示により出力することを特
徴とする請求項21に記載の負荷割り付けシステム。』 本請求項に係る発明により、負荷割り付けを行った後の
状況が視覚的により分かりやすくなる。
[Claim 22] The load allocation system according to claim 21, wherein the output means outputs the result of the load allocation in a graphical display. According to the invention according to the present claim, the situation after the load allocation is performed becomes visually easier to understand.

【0034】〔請求項23〕『一度、前記材料枠に割り
付けを行った前記材料負荷を、他の空きがある材料枠に
変更して割り付けることができる請求項10〜12、1
6〜22のいずれか1項に記載の負荷割り付けシステ
ム。』 本請求項に係る発明により、急なオーダーが入った場合
等に対して、オーダーに係る材料枠の割り付けの変更を
行うことによりフレキシブルに対処することが可能とな
る。
[Claim 23] "The material load once assigned to the material frame can be changed and assigned to a material frame having another space."
23. The load allocation system according to any one of 6 to 22. With the invention according to the present claim, it is possible to flexibly cope with a case where a sudden order is placed, for example, by changing the allocation of the material frame related to the order.

【0035】〔請求項24〕『前記割り付けの変更は、
前記割り付けの変更を入力する日から所定期間経過以降
の前記材料枠間において行うことができ、前記割り付け
の変更を入力する日から所定期間経過以前の前記材料枠
間においては、前記割り付けの変更を行うことができな
いことを特徴とする請求項23に記載の負荷割り付けシ
ステム。』 本請求項に係る発明により、現実的に不可能な負荷の割
り付けの変更や、生産工程に無理な負担をかける負荷の
割り付けの変更を防止することが可能となる。
[Claim 24] "The change of the allocation is
The change of the allocation can be performed between the material frames after a lapse of a predetermined period from the date of inputting the change of the allocation, and between the material frames before the lapse of the predetermined period from the date of inputting the change of the allocation, the change of the allocation is performed. 24. The load allocation system according to claim 23, wherein the load allocation cannot be performed. With the invention according to the present claim, it is possible to prevent a change in load assignment that is not practically possible and a change in load assignment that places an unreasonable burden on the production process.

【0036】〔請求項25〕『前記割り付けの変更をす
る場合に、顧客が希望する納期である顧客希望納期以降
の前記材料枠に、前記オーダーに対応する前記材料負荷
を割り付けることができないことを特徴とする請求項2
3又は24に記載の負荷割り付けシステム。』 本請求項に係る発明により、希望納期を尊重した負荷の
割り付けを行うことが可能となり、本来ならば希望納期
に間に合うように負荷の割り付けを行える場合に、誤っ
て希望納期に遅れるような負荷の割り付けを行うことを
防止できる。
[Claim 25] "In the case of changing the allocation, it is determined that the material load corresponding to the order cannot be allocated to the material frame after the customer desired delivery date, which is the delivery date desired by the customer. Claim 2
25. The load allocation system according to 3 or 24. With the invention according to the present claim, it is possible to assign a load that respects the desired delivery date, and if the load can be assigned so as to be in time for the desired delivery date, a load that erroneously delays the desired delivery date Can be prevented from being assigned.

【0037】〔請求項26〕『一度、前記能力枠及び前
記材料枠に割り付けを行った前記生産ライン能力負荷及
び前記材料負荷を、他の空きがある能力枠及び材料枠に
変更して割り付けることができる請求項10〜12、1
6〜22のいずれか1項に記載の負荷割り付けシステ
ム。』 本請求項に係る発明により、急なオーダーが入った場合
等に対して、オーダーに係る材料枠の割り付けの変更を
行うことによりフレキシブルに対処することが可能とな
る。
[Claim 26] "The production line capacity load and the material load once allocated to the capacity frame and the material frame are changed and allocated to another capacity frame and a material frame having vacancies. Claims 10 to 12, 1
23. The load allocation system according to any one of 6 to 22. With the invention according to the present claim, it is possible to flexibly cope with a case where a sudden order is placed, for example, by changing the allocation of the material frame related to the order.

【0038】〔請求項27〕『前記割り付けの変更は、
前記割り付けの変更を入力する日から所定期間経過以降
の前記能力枠間及び前記材料枠間において行うことがで
き、前記割り付けの変更を入力する日から所定期間経過
以前の前記能力枠間及び前記材料枠間においては、前記
割り付けの変更を行うことができないことを特徴とする
請求項26に記載の負荷割り付けシステム。』 本請求項に係る発明により、現実的に不可能な負荷の割
り付けの変更や、生産工程に無理な負担をかける負荷の
割り付けの変更を防止することが可能となる。
[Claim 27] "The change of the allocation is
It can be performed between the capacity frames and the material frames after a lapse of a predetermined period from the date of inputting the change of allocation, and between the capacity frames and the material before the lapse of a predetermined period from the date of inputting the change of allocation. 27. The load allocation system according to claim 26, wherein the allocation cannot be changed between frames. With the invention according to the present claim, it is possible to prevent a change in load assignment that is not practically possible and a change in load assignment that places an unreasonable burden on the production process.

【0039】〔請求項28〕『前記割り付けの変更をす
る場合に、顧客が希望する納期である顧客希望納期以降
の前記能力枠及び材料枠に、前記顧客のオーダーに対応
する前記生産ライン能力負荷及び前記材料負荷を割り付
けることができないことを特徴とする請求項26又は2
7に記載の負荷割り付けシステム。』 本請求項に係る発明により、希望納期を尊重した負荷の
割り付けを行うことが可能となり、本来ならば希望納期
に間に合うように負荷の割り付けを行える場合に、誤っ
て希望納期に遅れるような負荷の割り付けを行うことを
防止できる。
[Claim 28] "When the allocation is changed, the production line capacity load corresponding to the customer's order is added to the capacity frame and the material frame after the customer desired delivery date, which is the delivery date desired by the customer. And the material load cannot be allocated.
8. The load assignment system according to 7. With the invention according to the present claim, it is possible to assign a load that respects the desired delivery date, and if the load can be assigned so as to be in time for the desired delivery date, a load that erroneously delays the desired delivery date Can be prevented from being assigned.

【0040】〔請求項29〕『請求項16〜28のいず
れか1項に記載の負荷割り付けシステムの演算手段によ
る負荷割り付け結果を基に前記オーダー又は前記製品の
納期を求める納期演算手段とを有することを特徴とする
納期決定システム。』 本請求項に係る発明により、材料や部品の供給に長時間
を要する製品や、中間材料を見込み生産しておく製品な
ど、常に材料の安定な供給を望めず、欲しいときに欲し
いだけの量の材料を得ることが困難な製品を生産する場
合であっても、正確な納期をオーダーを受けてから短時
間で容易に、人手を介さずに得ることができ、さらに、
完成品並びに材料の在庫を減らすことが可能となる。
[29] A delivery date calculation means for obtaining a delivery date of the order or the product based on a load allocation result by the calculation means of the load allocation system according to any one of [16] to [28]. A delivery date determination system characterized by the following. According to the claimed invention, a stable supply of materials is not always desired, such as products that require a long time to supply materials and parts, and products that are expected to produce intermediate materials. Even in the case of producing a product for which it is difficult to obtain a material, it is possible to obtain an accurate delivery time in a short time after receiving an order, easily and without human intervention, and
It is possible to reduce inventory of finished products and materials.

【0041】〔請求項30〕『前記納期演算手段は、前
記生産のオーダーに係る前記生産ライン能力負荷と前記
材料負荷の割り付けを行った前記能力枠と前記材料枠
で、最も後の所定期間に係る前記能力枠及び前記材料枠
の前記所定期間を前記オーダーの納期とすることを特徴
とする請求項29に記載の納期決定システム。』 本請求項に係る発明により、負荷を枠に割りつけた結果
から納期を容易に決定することが可能となる。
[Claim 30] "The delivery date calculation means is configured to allocate the production line capacity load and the material load pertaining to the production order to the capacity frame and the material frame in the last predetermined period. 30. The delivery date determination system according to claim 29, wherein the predetermined period of the capacity frame and the material frame is a delivery date of the order. With the invention according to the present claim, it is possible to easily determine the delivery date from the result of allocating the load to the frame.

【0042】〔請求項31〕『前記納期を出力する出力
手段を有することを特徴とする請求項30に記載の納期
決定システム。』 本請求項に係る発明により、決定された納期を容易に知
ることが可能となる。。
[Claim 31] "The delivery date determination system according to claim 30, further comprising an output means for outputting said delivery date. With the invention according to the present claim, the determined delivery date can be easily known. .

【0043】〔請求項32〕『請求項1〜6のいずれか
1項に記載の負荷割り付け方法を実行させるプログラム
を読み取り可能に記録したことを特徴とする記録媒
体。』 〔請求項33〕『請求項7又は8に記載の納期決定方法
を実行させるプログラムを読み取り可能に記録したこと
を特徴とする記録媒体。』 請求項32又は33に係る発明により、材料や部品の供
給に長時間を要する製品や、中間材料を見込み生産して
おく製品など、常に材料の安定な供給を望めず、欲しい
ときに欲しいだけの量の材料を得ることが困難な製品を
生産する場合であっても、正確な納期をオーダーを受け
てから短時間で容易に、人手を介さずに得ることがで
き、さらに、完成品並びに材料の在庫を減らすことが可
能となる。
(32) A recording medium characterized in that a program for executing the load allocation method according to any one of (1) to (6) is recorded in a readable manner. [Claim 33] [A recording medium characterized in that a program for executing the delivery date determining method according to claim 7 or 8 is recorded in a readable manner. According to the invention according to claim 32 or 33, a stable supply of material is not always desired, such as a product requiring a long time to supply a material or a part, or a product for which an intermediate material is expectedly produced, but only when desired. Even when producing a product for which it is difficult to obtain an amount of material, it is possible to obtain an accurate delivery date in a short time after receiving an order, easily and without human intervention. It is possible to reduce the stock of materials.

【0044】また、生産部門と販売部門と、共にオーダ
ーの進捗状況がリアルタイムで把握できるので、生販間
の調整が不要となる。さらには、生産の負荷の平均化が
可能となる。
Further, since the progress of the order can be grasped in real time by both the production department and the sales department, there is no need to adjust between the live sales. Furthermore, the production load can be averaged.

【0045】〔用語の説明〕本発明でいう「生産ライン
能力」とは、生産ラインの能力のことをいう。例えば、
生産ラインにおいてある製品を所定期間内に生産できる
数や、生産ラインの稼働時間等が挙げられる。具体的に
は、生産ラインAでは1日に製品Bを100個生産でき
るということで生産ライン能力を示してもよいし、製品
Bを1個生産するのに必要な生産ラインAの稼働時間が
分かっている場合に生産ラインAは1日に6時間稼働可
能であるということで生産ライン能力を示してもよい。
[Explanation of Terms] The “production line capacity” in the present invention refers to the capacity of a production line. For example,
Examples include the number of products that can be produced in a production line within a predetermined period, the operation time of the production line, and the like. Specifically, the production line A may indicate the production line capacity by being able to produce 100 products B per day, or the operation time of the production line A required to produce one product B may be indicated. If known, production line A may indicate production line capacity by being operational for six hours per day.

【0046】本発明でいう「生産ライン能力負荷」と
は、生産受注のオーダーに係る製品を生産するのに必要
な生産ライン能力のことである。例えば、オーダーに係
る製品の品目と個数で生産ライン能力負荷を表してもよ
いし、オーダーに係る製品を全て生産するのに必要な生
産ラインの種類及び稼働時間で、生産ライン能力負荷を
表すようにしてもよい。
The "production line capacity load" in the present invention refers to a production line capacity necessary for producing a product corresponding to a production order. For example, the production line capacity load may be represented by the item and the number of the product pertaining to the order, or the production line capacity load may be represented by the type and operation time of the production line required to produce all the products pertaining to the order. It may be.

【0047】本発明でいう「材料負荷」とは、オーダー
に係る製品を生産するのに必要な材料の負荷をいう。例
えば、オーダーに係る製品を生産するのに必要な材料や
部品の種類及び量で、材料負荷を表してもよいし、ま
た、1日に供給可能である材料が製品Aを100個生産
できるだけの材料であると材料枠に設定されている場合
に、製品Aを20個生産するのに必要な材料として、材
料負荷を表してもよい。
The "material load" in the present invention means a load of a material necessary for producing a product according to an order. For example, the material load may be represented by the type and amount of materials and parts necessary to produce the product according to the order, or the material that can be supplied in one day can produce only 100 products A. When the material is set in the material frame, the material load may be represented as a material necessary to produce 20 products A.

【0048】[0048]

【発明の実施の形態】以下に本発明に関する実施の形態
の例を示すが、本発明はこれらに限定されない。また、
以下の実施形態は、本発明の好ましい例を示すもので、
本発明の用語の意義や技術的範囲を限定するものではな
い。
DETAILED DESCRIPTION OF THE PREFERRED EMBODIMENTS Hereinafter, embodiments of the present invention will be described, but the present invention is not limited thereto. Also,
The following embodiments show preferred examples of the present invention,
It does not limit the meaning or technical scope of the terms of the present invention.

【0049】図1〜図11を用いて本発明に係る実施形
態の1例を説明する。本実施形態は写真関連製品、具体
的には写真フィルムの生産に本発明を用いた例である。
更に具体的には、断裁前のフィルムのロールである元巻
Aを材料として、生産ラインA(以下、「ラインA」と
略称する)で、フィルムAを製造し、元巻Bを材料とし
て、生産ラインB(以下、「ラインB」と略称する)
で、フィルムBを製造する場合に、本発明に係る納期決
定システムを用いて、オーダーに係る納期を決定する例
である。
An example of an embodiment according to the present invention will be described with reference to FIGS. The present embodiment is an example in which the present invention is used to produce a photographic-related product, specifically, a photographic film.
More specifically, a film A is manufactured on a production line A (hereinafter abbreviated as “line A”) using a material roll A, which is a roll of a film before cutting, as a material, and a material roll B is used as a material. Production line B (hereinafter abbreviated as "line B")
This is an example of determining a delivery date for an order by using the delivery date determination system according to the present invention when manufacturing a film B.

【0050】図1は、本発明に係る納期決定システム
(負荷割り付けシステムを兼ねる)の実施形態の1例を
示す概略図である。
FIG. 1 is a schematic diagram showing an example of an embodiment of a delivery date determination system (also serving as a load allocation system) according to the present invention.

【0051】本納期決定システム11は、元巻を材料と
して写真フィルムを製造する際に、オーダーに係る能力
負荷及び材料負荷を割り付け、オーダーの納期を決定す
るシステムである。本納期決定システム11は、CPU
等を有し各種演算を行う演算手段である演算部10(納
期に関する演算を行う納期演算部も兼ねる)と、納期が
決定されていないオーダー、及び納期が決定されている
オーダー等を記憶するオーダー記憶部12と、所定期間
(本実施形態では1日毎という、一定期間である)毎に
供給可能な材料の種類及び量を示す材料枠を記憶してお
く材料枠記憶手段である材料枠記憶部1と、各種製品1
個を製造するに当たり必要な材料の種類と量、又は1つ
のオーダーに係り必要な材料の種類と量(各種製品1個
あたりの材料負荷、又は1つのオーダーあたりの材料負
荷)を記憶しておく材料負荷記憶手段である材料負荷記
憶部2と、一定期間毎に稼働可能な生産ラインの種類及
び稼働時間を示す能力枠を記憶しておく能力枠記憶手段
である能力枠記憶部3と、各種製品1個を製造するに当
たり稼働する必要のある生産ラインの種類と稼働時間
(各種製品1個あたりの生産ライン能力負荷、又は1つ
のオーダーあたりの生産ライン能力負荷。尚、以下、生
産ライン能力負荷を、「能力負荷」と略称する。)を記
憶しておく能力負荷記憶手段である能力負荷記憶部4
と、能力枠及び材料枠に割り付け済の能力負荷及び材料
負荷を記憶しておく割り付け済負荷記憶手段である割り
付け済負荷記憶部5と、カレンダーを記憶しておくカレ
ンダー記憶部6と、オーダーに関する情報等の各種情報
を入力するための入力手段であるキーボード7と、能力
枠、材料枠や、演算部によって演算された負荷割り付け
の結果や決定納期を表示する出力手段であるCRTディ
スプレイ8と、能力枠、材料枠や、演算部によって演算
された負荷割り付けの結果や決定納期を印刷する出力手
段であるプリンター9とを有している。
The present delivery date determination system 11 is a system for allocating a capacity load and a material load pertaining to an order when manufacturing a photographic film using the original roll as a material, and determining a delivery date of the order. The final delivery date determination system 11 has a CPU
And an order for storing orders for which delivery dates have not been determined, orders for which delivery dates have been determined, and the like. A storage unit 12 and a material frame storage unit serving as a material frame storage unit that stores a material frame indicating the type and amount of the material that can be supplied for each predetermined period (in the present embodiment, every day, which is a fixed period). 1 and various products 1
The type and amount of material necessary for manufacturing an individual, or the type and amount of material required for one order (material load per one product or material load per order) are stored. A material load storage unit 2 serving as a material load storage unit; a capacity frame storage unit 3 serving as a capacity frame storage unit for storing a capacity frame indicating a type of a production line operable at regular intervals and an operation time; The type and operation time of the production line that must be operated to manufacture one product (production line capacity load per product or production line capacity load per order. In the following, production line capacity load Is abbreviated as “capacity load”.) The capability load storage unit 4 serving as a capability load storage unit for storing the capability load.
And an assigned load storage unit 5 as assigned load storage means for storing capacity loads and material loads assigned to the capacity and material frames, a calendar storage unit 6 for storing a calendar, and an order. A keyboard 7 which is an input means for inputting various information such as information, a CRT display 8 which is an output means for displaying a capacity frame, a material frame, a result of load allocation calculated by the calculation unit, and a determined delivery date; The printer 9 is an output unit that prints a capacity frame, a material frame, a result of load allocation calculated by the calculation unit, and a determined delivery date.

【0052】尚、本発明に係る負荷割り付けシステムは
1体の装置である必要はなく、納期決定システムも、生
産システムも1体の装置である必要はない。例えば、販
売部門と、生産部門等のそれぞれに端末用コンピュータ
ーが用意されており、該端末用コンピューターと、演算
部等を有するサーバー等をネットワークで結ぶことによ
り構成するようにしてもよい。勿論、入力手段、出力手
段は複数有することができ、更に入力手段はキーボード
に限られず、バーコードやOCR(オプティカル・キャ
ラクター・リーダー)等により入力するようにしてもよ
い。
The load allocation system according to the present invention does not need to be a single device, and neither the delivery date determination system nor the production system need to be a single device. For example, a computer for a terminal may be prepared in each of a sales department, a production department, and the like, and the terminal computer may be configured by connecting a server or the like having an arithmetic unit or the like via a network. Of course, a plurality of input means and output means can be provided, and the input means is not limited to a keyboard, but may be input by a bar code, an OCR (optical character reader), or the like.

【0053】このシステムによって、オーダーを受けて
からどのようにして負荷が割り付けられ、納期が決定さ
れるのかについて、以下に説明する。
The following describes how the load is allocated and the delivery date is determined after receiving an order by this system.

【0054】まず、能力枠と材料枠の設定と、製品1個
毎の材料負荷と能力負荷の設定を、予め行っておく必要
がある。能力枠の設定も、材料枠の設定も、製品1個毎
の材料負荷と能力負荷の設定も、CRTディスプレイ8
を見ながらキーボード7から行う。
First, the setting of the capacity frame and the material frame, and the setting of the material load and the capacity load for each product must be performed in advance. The CRT display 8 can be used to set the capacity frame, the material frame, the material load and the capacity load for each product.
From the keyboard 7 while watching the screen.

【0055】最初に能力枠の設定について説明する。図
3に該能力枠の説明図を示す。能力枠30は、一定期間
毎に稼働可能な生産ラインの種類及び稼働時間を示すも
のであり、別の言い方をすれば、一定期間毎に割り付け
可能な能力負荷を示すものである。本実施形態において
は、一定期間を1日単位としている。例えば、8月21
日(金)の能力枠31として、ラインAを3時間稼働す
ることができ、ラインBを4時間稼働することができる
旨が設定されている。したがって、8月21日(金)に
はラインAの3時間稼働分の能力負荷と、ラインBの4
時間稼働分の能力負荷を割り付けることができる。
First, the setting of the capacity frame will be described. FIG. 3 is an explanatory diagram of the capacity frame. The capacity frame 30 indicates the type of the production line and the operation time that can be operated at regular intervals, and in other words, indicates the capacity load that can be assigned at regular intervals. In the present embodiment, the certain period is set to one day. For example, August 21
As the capacity frame 31 of the day (Fri), it is set that the line A can be operated for 3 hours and the line B can be operated for 4 hours. Therefore, on August 21 (Fri), the capacity load for the three-hour operation of line A and the capacity load of line B for four hours
The capacity load for the time operation can be allocated.

【0056】カレンダー記憶部6に記憶されているカレ
ンダーを基に、日毎に稼働可能な生産ラインの種類と稼
働時間、つまり日毎に割り付け可能な能力負荷、さらに
言うなら日毎の能力枠を、CRTディスプレイ8を見な
がらキーボード7から入力することにより、能力枠30
を設定する。そして、該能力枠30は能力枠記憶部3に
記憶される。
On the basis of the calendar stored in the calendar storage unit 6, the type and the operation time of the production line that can be operated every day, that is, the capacity load that can be allocated every day, in other words, the capacity frame for each day, are displayed on the CRT display. By inputting from the keyboard 7 while looking at the screen 8, the ability frame 30
Set. Then, the capacity frame 30 is stored in the capacity frame storage unit 3.

【0057】次に、材料枠の設定について説明する。図
4に該材料枠の説明図を示す。材料枠40は、一定期間
ごとに供給可能な材料の種類及び量を示すものであり、
別の言い方をすれば、一定期間毎に割り付け可能な材料
負荷を示すものである。本実施形態においては、一定期
間を1日単位としている。例えば、8月21日(金)の
材料枠41として、元巻Aを4本供給することが可能で
あり、元巻Bを3本供給することが可能である旨が設定
されている。したがって、8月21日(金)には元巻A
の4本分の材料負荷と、元巻Bの3本分の材料負荷を割
り付けることができる。
Next, the setting of the material frame will be described. FIG. 4 is an explanatory view of the material frame. The material frame 40 indicates the type and amount of the material that can be supplied at regular intervals,
In other words, it indicates the material load that can be assigned at regular intervals. In the present embodiment, the certain period is set to one day. For example, as the material frame 41 on August 21 (Fri), it is set that four original volumes A can be supplied and three original volumes B can be supplied. Therefore, the original volume A on August 21 (Fri)
, And the material load for the three original windings B can be allocated.

【0058】カレンダー記憶部6に記憶されているカレ
ンダーを基に、日毎に供給可能な材料の種類と量、つま
り日毎に割り付け可能な材料負荷、さらに言うなら日毎
の材料枠をCRTディスプレイ8を見ながらキーボード
7から入力することにより、材料枠40を設定する。そ
して、該材料枠40は材料枠記憶部1に記憶される。
On the basis of the calendar stored in the calendar storage section 6, the type and amount of material that can be supplied on a daily basis, that is, the material load that can be allocated on a daily basis, in other words, the material frame for each day, can be viewed on the CRT display 8. While inputting from the keyboard 7, the material frame 40 is set. Then, the material frame 40 is stored in the material frame storage unit 1.

【0059】本実施形態においては、能力枠、及び材料
枠の設定は、当日から3か月間の範囲内で設定を行え、
当日から3か月後以降の設定は行えないように制御され
ている。勿論、この3か月間という期間は変更可能であ
り、期間を設定せず、能力枠、及び材料枠の設定を時期
を問わず設定可能にすることも可能である。
In the present embodiment, the setting of the capacity frame and the material frame can be performed within a range of three months from the day.
It is controlled so that setting after three months from the day cannot be performed. Of course, the period of three months can be changed, and it is possible to set the capacity frame and the material frame regardless of the time without setting the period.

【0060】尚、能力枠の設定と、材料枠の設定はどち
らを先に行ってもよい。
Either the setting of the capacity frame or the setting of the material frame may be performed first.

【0061】また、本実施形態において、元巻の単位は
本であるが、m2 でもよい。
In this embodiment, the unit of the original volume is a book, but may be m 2 .

【0062】尚、能力枠、又は材料枠において、割り付
け可能な負荷の総量の全てではなく、割り付け可能な負
荷の総量の所定の割合だけを能力枠や材料枠として表示
するようにしてもよい。(以下、この割合を「開示率」
とする。)例えば、能力枠の開示率を90%と設定した
場合、8月21日に実際に割り付けることができるライ
ンAの能力負荷の総量が3時間20分であるときは、そ
の90%である3時間を能力枠として設定し、CRTデ
ィスプレイ8に表示する。そして、8月21日を希望納
期とする緊急のオーダーが入った場合に、既にラインA
に能力負荷が3時間割り付けられており、見かけ上ライ
ンAに関してそれ以上の能力負荷を割り付けることが不
可能であっても、実際はまだラインA、3分の1時間分
の能力負荷が割り付け可能であり、緊急のオーダーに対
応することができる。このように、開示率を設定してお
く事により、緊急のオーダーに対応し易くなる。
In the capacity frame or the material frame, not all of the total load that can be allocated but only a predetermined ratio of the total amount of the load that can be allocated may be displayed as the capacity frame or the material frame. (Hereinafter, this ratio is referred to as the "disclosure rate."
And For example, if the disclosure rate of the capacity frame is set to 90%, and the total capacity load of the line A that can be actually allocated on August 21 is 3 hours 20 minutes, that is 90%. The time is set as a capacity frame and displayed on the CRT display 8. When an urgent order with the desired delivery date of August 21 is entered, the line A is already
Although the capacity load is allocated for 3 hours, even if it is apparently impossible to allocate a further capacity load for the line A, actually the capacity load for the line A for one third of the time can still be allocated. Yes, we can respond to urgent orders. By setting the disclosure rate in this way, it becomes easier to respond to urgent orders.

【0063】続いて、製品1個毎の材料負荷と能力負荷
の設定について説明する。
Next, the setting of the material load and the capacity load for each product will be described.

【0064】図6に、フィルムA1個とフィルムB1個
のそれぞれに係る材料負荷と能力負荷とを示す。図6に
示すように、フィルムAは、1個製造するのにラインA
を0.05時間稼働する必要があり、材料として元巻A
を0.03本必要としている。一方、フィルムBは、1
個製造するのにラインBを0.03時間稼働する必要が
あり、材料として元巻Bを0.01本必要としている。
言い方を変えれば、フィルムA1個に係る能力負荷はラ
インA0.05時間分であり、材料負荷は元巻A0.0
3本分である。一方、フィルムB1個に係る能力負荷は
ラインB0.03時間分であり、材料負荷は元巻B0.
01本分である。
FIG. 6 shows the material load and capacity load for each of the film A and the film B. As shown in FIG.
Must be operated for 0.05 hours, and
0.03 are required. On the other hand, film B
It is necessary to operate the line B for 0.03 hours to manufacture the individual pieces, and 0.01 of the original winding B is required as a material.
In other words, the capacity load for one film A is line A0.05 hours, and the material load is the original volume A0.0.
It is three. On the other hand, the capacity load for one film B is 0.03 hours for the line B, and the material load is the original volume B0.
It is for 01.

【0065】本納期決定システム11は、材料負荷記憶
部2と、能力負荷記憶部4とを有しており、各製品1個
に係る材料負荷と、各製品1個に係る能力負荷を、製品
毎に予めキーボード7から入力しておくことにより、該
材料負荷記憶部2に、製品の種類毎に、該製品を1個製
造するのに必要な材料の種類及び量(製品1個に係る材
料負荷)を記憶させておき、該能力負荷記憶部4には、
製品の種類毎に、該製品を1個製造するのに必要な生産
ラインの種類及び稼働時間(製品1個に係る能力負荷)
を記憶させておく。そして、新規な製品が出る度に、該
新規な製品に対応した新たな材料負荷と、能力負荷とを
設定することにより、新規な製品に対応することが可能
である。
The delivery date determination system 11 has a material load storage unit 2 and a capacity load storage unit 4, and stores the material load of each product and the capacity load of each product. By inputting data from the keyboard 7 in advance for each product, the material load storage unit 2 stores, for each product type, the type and amount of material necessary to manufacture one product (the material per product). Load) is stored in the capacity load storage unit 4.
For each type of product, the type of production line and the operating time required to manufacture one product (capacity load per product)
Is stored. Then, each time a new product is released, a new material load and a capacity load corresponding to the new product are set, so that a new product can be handled.

【0066】次に、このシステムによって、オーダーを
受けてからどのようにして能力枠及び材料枠に負荷が割
り付けられ、納期が決定されるのかについて、図2に示
したフローチャートを基に説明する。
Next, how the load is assigned to the capacity frame and the material frame and the delivery date is determined by the system after receiving the order will be described with reference to the flowchart shown in FIG.

【0067】ステップ1(S1):予め能力枠30、材
料枠40、製品1個毎の能力負荷と材料負荷が設定され
た状態で、オーダーを受け付ける。オーダーは、図5に
示すように該オーダーに係る製品の種類及び量を情報と
して少なくとも有していることが必要である。また、顧
客の希望納期も情報として有していることが好ましい。
例えば、オーダーIの希望納期は8月25日であり、オ
ーダーIに係る製品は、フィルムAが100個と、フィ
ルムBが200個である。そして、該オーダーI50
(製品の品目、数量、希望納期)をキーボード7から入
力する。入力されたオーダーI50はオーダー記憶部1
2に記憶される。
Step 1 (S1): An order is received with the capacity frame 30, the material frame 40, and the capacity load and material load for each product set in advance. As shown in FIG. 5, the order needs to have at least the type and quantity of the product related to the order as information. Further, it is preferable that the customer also have the desired delivery date as information.
For example, the desired delivery date of order I is August 25, and the products related to order I have 100 pieces of film A and 200 pieces of film B. And the order I50
(Product item, quantity, desired delivery date) is input from the keyboard 7. The input order I50 is stored in the order storage unit 1.
2 is stored.

【0068】尚、特に希望納期がない場合は、希望納期
を入力しなくても良い。
If there is no desired delivery date, it is not necessary to input the desired delivery date.

【0069】また、各々のオーダーに関する情報を管理
しやすくするために、各々のオーダーにID番号等のI
D情報や、オーダーの入力者の氏名、入力した日付等の
情報をオーダーに付与してもよい。
In order to make it easier to manage information on each order, each order has an ID number and the like.
Information such as D information, the name of the person who entered the order, and the date entered may be added to the order.

【0070】ステップ2(S2):そして、オーダー記
憶部12に記憶されたオーダー50Iの情報と、材料負
荷記憶部2と能力負荷記憶部4に記憶されている各種製
品1個の材料負荷と、各種製品1個の能力負荷の情報を
基に、演算部10において、オーダーI50に係る製品
全部を製造するのに必要な材料の種類及び量と、生産ラ
インの種類及び稼働時間、つまりオーダーIに係る材料
負荷と能力負荷とが演算され求められる。
Step 2 (S 2): The information of the order 50 I stored in the order storage unit 12, the material load of each product stored in the material load storage unit 2 and the capacity load storage unit 4, and Based on the information on the capacity load of one of the various products, the arithmetic unit 10 determines the type and amount of the materials necessary for manufacturing all the products related to the order I50, and the type and operation time of the production line, that is, the order I. The material load and the capacity load are calculated and obtained.

【0071】図7に、前述した方法で演算部10におい
て求められたオーダーI50に係る材料負荷と能力負荷
とを示す。図7に示すように、オーダーI50に係る材
料負荷は、元巻Aが3本と、元巻Bが2本であり、能力
負荷はラインAが5時間であり、ラインBが6時間であ
る。
FIG. 7 shows the material load and the capacity load according to the order I50 obtained in the arithmetic unit 10 by the method described above. As shown in FIG. 7, the material load according to the order I50 is as follows: three primary rolls A and two primary rolls B, and the capacity load is 5 hours for line A and 6 hours for line B. .

【0072】また、このようにして求めたオーダーに係
る能力負荷と材料負荷を、CRTディスプレイ8に表示
したり、プリンター9により出力するようにしてもよ
い。
The capacity load and material load related to the order thus obtained may be displayed on the CRT display 8 or output by the printer 9.

【0073】ステップ3(S3):オーダーI50に係
る能力負荷と材料負荷を求めた後、オーダーI50に係
る能力負荷の能力枠への割り付けを演算部10で行う。
Step 3 (S3): After calculating the capacity load and the material load related to the order I50, the calculation unit 10 allocates the capacity load related to the order I50 to the capacity frame.

【0074】本納期決定システム11は、割り付け済負
荷記憶部5を有しており、オーダーI50に係る能力負
荷と材料負荷を割り付ける前に、設定されている能力
枠、及び材料枠に、既に割り付けられている能力負荷及
び材料負荷が、該割り付け済負荷記憶部5において記憶
されている。
The delivery date determination system 11 has an assigned load storage unit 5 and, before assigning the capacity load and the material load related to the order I50, has already assigned to the set capacity frame and material frame. The assigned capacity load and material load are stored in the assigned load storage unit 5.

【0075】図8に、能力枠及び割り付け済の能力負荷
(以下、「負荷割り付け済能力枠」と称する)とを示
す。そして、負荷割り付け済能力枠80Aが、CRTデ
ィスプレイ8に表示される。また、プリンター9から出
力されるようにしてもよい。
FIG. 8 shows a capacity frame and allocated capacity loads (hereinafter, referred to as “load-allocated capacity frames”). Then, the load-allocated capacity frame 80A is displayed on the CRT display 8. Further, it may be output from the printer 9.

【0076】8月21日は、ラインAが3時間稼働可能
であり、ラインBが4時間稼働可能である旨が能力枠と
して予め設定されており、そのうち、ラインAを2時間
稼働させる能力負荷と、ラインBを2時間稼働させる能
力負荷とが、既に割り付けられており、割り付け済の能
力負荷として割り付け済負荷記憶部5に記憶されてい
る。したがって、これから8月21日分の能力枠に割り
付けることができる能力負荷は、ラインA、1時間分
と、ラインB、2時間分の能力負荷である。
On August 21, it is preset as a capacity frame that the line A can be operated for 3 hours and the line B can be operated for 4 hours. Among them, the capacity load for operating the line A for 2 hours is set. And the capacity load for operating the line B for two hours have already been allocated, and are stored in the allocated load storage unit 5 as allocated capacity loads. Therefore, the capacity loads that can be assigned to the capacity frame for August 21 are the capacity load for line A for one hour and the capacity load for line B for two hours.

【0077】1日毎の能力枠に、それ以上能力負荷を割
り付けることができなくなった場合には、マーク100
が、図8に示すように表示される。したがって、8月2
2日と、23日には、これ以上能力負荷を割り付けるこ
とはできない。
If it is no longer possible to assign a capacity load to the capacity frame for each day, the mark 100
Is displayed as shown in FIG. Therefore, August 2
On the 2nd and 23rd, no more capacity load can be allocated.

【0078】そして、オーダーI50に係る能力負荷
は、まだ能力負荷を割り付けることのできる能力枠に、
希望納期を考慮して演算部10により自動で割り付けら
れる。
Then, the capacity load related to the order I50 is set to a capacity frame to which the capacity load can be assigned.
It is automatically assigned by the arithmetic unit 10 in consideration of the desired delivery date.

【0079】負荷割り付け済の能力枠80Aにオーダー
I50に係る能力負荷を割り付けた結果を示した図が図
10である。本実施形態においては、オーダーI50に
係る能力負荷を割り付けた結果として、負荷割り付け済
の能力枠80BがCRTディスプレイ8に表示される。
FIG. 10 is a diagram showing a result of allocating the capacity load according to the order I50 to the capacity frame 80A to which the load has been allocated. In the present embodiment, as a result of allocating the capacity load related to the order I50, the capacity frame 80B to which the load has been allocated is displayed on the CRT display 8.

【0080】オーダーI50に係る能力負荷割り付けの
具体的な手順としては、希望納期丁度にオーダーに係る
製品が完成するように、希望納期である8月25日か
ら、8月24日、23日と遡って、能力負荷を割り付け
る事ができる空きを有する能力枠に、順次能力負荷を割
り付けていく。本実施形態においては、オーダーI50
に係る能力負荷はラインAが5時間であり、ラインBが
6時間である。したがって、ラインAにおいては、8月
25日に3時間、8月24日に2時間という能力負荷の
割り付けを行い、ラインBにおいては、8月25日に3
時間、8月24日に3時間という能力負荷の割り付けを
行うことにより、希望納期の8月25日に合わせて、能
力負荷の能力枠への割り付けを行う。
The specific procedure of the capacity load allocation related to the order I50 is as follows: from August 25, which is the desired delivery date, to August 24 and 23, so that the product related to the order is completed exactly at the desired delivery date. Retrospectively, the capacity load is sequentially assigned to a capacity frame having a space to which the capacity load can be assigned. In the present embodiment, the order I50
Is 5 hours for line A and 6 hours for line B. Therefore, in line A, the capacity load of 3 hours on August 25 and 2 hours on August 24 are allocated, and in line B, the capacity load is allocated on August 25.
By assigning a capacity load of 3 hours on the time, August 24, the capacity load is assigned to the capacity frame in accordance with the desired delivery date of August 25.

【0081】尚、能力負荷の割り付けは、本実施形態の
ように演算部10が自動で行うようにしてもよいし、本
納期決定システムのオペレーターが負荷割り付け済の能
力枠をCRTディスプレイ8等を見ながらキーボード7
から入力するようにしてもよい。
The assignment of the capacity load may be automatically performed by the arithmetic unit 10 as in the present embodiment, or the operator of the delivery date determination system may display the capacity frame to which the load has been assigned on the CRT display 8 or the like. Keyboard 7 while watching
May be input.

【0082】ステップ4(S4):次に、能力負荷の能
力枠への割り付けを行った結果、希望納期に間に合うよ
うに割り付けを行えるか否かを判断する。
Step 4 (S4): Next, as a result of allocating the capacity load to the capacity frame, it is determined whether or not the allocation can be performed in time for the desired delivery date.

【0083】希望納期から遡って、能力負荷を能力枠に
割り付けていき、オーダーに係る能力負荷を全て割り付
けることができた場合には、希望納期を予定納期とし
て、割り付けた結果を割り付け済負荷記憶部5に記憶
し、次にステップ5のオーダーに係る材料負荷の材料枠
への割り付けを行う。
The capacity load is allocated to the capacity frame retroactively from the desired delivery date, and when all the capacity loads related to the order can be allocated, the allocated result is set as the desired delivery date and the allocated load storage. This is stored in the section 5 and then the material load according to the order of step 5 is allocated to the material frame.

【0084】本実施形態においては、希望納期である8
月25日から遡って、能力負荷を能力枠に割り付けてい
き、オーダーに係る能力負荷を全て割り付けることがで
きるため、8月25日が予定納期となる。
In the present embodiment, the desired delivery date is 8
Since the capacity load can be allocated to the capacity frame retroactively from the month 25 and all the capacity loads related to the orders can be allocated, the scheduled delivery date is August 25.

【0085】一方、希望納期から遡って、能力負荷を能
力枠に割り付けていき、オーダーに係る全ての能力負荷
を割り付けることができなかった場合、つまり、希望納
期に間に合うように能力負荷の割り付けが行えなかった
場合には、さらに、希望納期である8月25日から、8
月26日、27日と進んで、能力負荷を割り付ける事が
できる空きを有する能力枠に、順次割り付けきれなかっ
た能力負荷を割り付けていき、オーダーに係る全能力負
荷を割り付けた後、能力負荷を割り付けた最終日を予定
納期として、次にステップ5のオーダーに係る材料負荷
の材料枠への割り付けを行う。そして、割り付けた結果
を割り付け済負荷記憶部5に記憶する。例えば、希望納
期が25日であるにもかかわらず、能力負荷を割り付け
た最終日が27日である場合には、予定納期は27日と
なる。
On the other hand, retroactively from the desired delivery date, the capacity load is allocated to the capacity frame, and when all the capacity loads related to the order cannot be allocated, that is, the capacity load is allocated in time for the desired delivery date. If you fail to do so, you will be asked to add 8
On the 26th and 27th of the month, the capacity load that could not be allocated is sequentially allocated to the capacity frame having a space where the capacity load can be allocated, and after the total capacity load related to the order is allocated, the capacity load is allocated. The last day of the assignment is set as the scheduled delivery date, and then the assignment of the material load related to the order in step 5 to the material frame is performed. Then, the assigned result is stored in the assigned load storage unit 5. For example, if the desired delivery date is 25 days but the last day to which the capacity load is assigned is 27 days, the scheduled delivery date is 27 days.

【0086】尚、希望納期から遡って、能力負荷を能力
枠に割り付けずに、能力負荷を割り付けることができる
最も早い日から、能力負荷を能力枠に割り付けていくよ
うにしてもよい。オーダーの希望納期に関する情報が無
い場合、好適である。
Incidentally, it is also possible to allocate the capacity load to the capacity frame from the earliest day on which the capacity load can be allocated, without allocating the capacity load to the capacity frame, going back from the desired delivery date. This is preferable when there is no information on the desired delivery date of the order.

【0087】ステップ5(S5):オーダーI50に係
る能力負荷の能力枠への割り付けを行った後に、オーダ
ーI50に係る材料負荷の材料枠への割り付けを演算部
10で行う。
Step 5 (S5): After allocating the capacity load related to the order I50 to the capacity frame, the calculation unit 10 allocates the material load related to the order I50 to the material frame.

【0088】図9に、材料枠及びオーダーI50を割り
付ける以前の割り付け済の材料負荷(以下、「負荷割り
付け済材料枠」と称する)とを示す。そして、負荷割り
付け済材料枠90Aが、CRTディスプレイ8に表示さ
れる。また、プリンター9から出力されるようにしても
よい。
FIG. 9 shows an assigned material load (hereinafter, referred to as a “load assigned material frame”) before assigning the material frame and the order I50. Then, the load-assigned material frame 90A is displayed on the CRT display 8. Further, it may be output from the printer 9.

【0089】例えば、8月21日は、元巻Aを4本供給
可能であり、元巻Bを3本供給可能である旨が材料枠と
して予め設定されており、そのうち、元巻Aを1本使用
する材料負荷と、元巻Bを1本使用する材料負荷とが、
既に割り付けられており、割り付け済の材料負荷とし
て、割り付け済負荷記憶部5に記憶されている。したが
って、これから8月21日分の材料枠に割り付けること
ができる材料負荷は、元巻A、3本分、元巻B、2本分
となる。
For example, on August 21, it is preset as a material frame that four original volumes A can be supplied and three original volumes B can be supplied. The material load to be used and the material load to use one original winding B are:
It is already assigned and stored in the assigned load storage unit 5 as the assigned material load. Therefore, the material loads that can be allocated to the material frame for August 21 from now on are the original winding A, three windings, the original winding B, and two windings.

【0090】1日毎の材料枠に、それ以上材料負荷を割
り付けることができなくなった場合には、マーク100
が表示される。したがって、8月22日、23日には、
元巻Aに係る材料負荷をこれ以上割り付けることはでき
ない。また、8月21日、22日と、23日には、元巻
Bに係る材料負荷をこれ以上割り付けることはできな
い。
If the material load can no longer be assigned to the daily material frame, the mark 100
Is displayed. Therefore, on August 22 and 23,
The material load related to the main winding A cannot be allocated any more. Further, on August 21, 22, and 23, the material load relating to the original volume B cannot be allocated any more.

【0091】そして、オーダーI50に係る材料負荷
は、まだ材料負荷を割り付けることのできる材料枠に、
予定納期、及び能力負荷の能力枠への割り付け結果を考
慮して演算部10により自動で割り付けられる。
The material load related to the order I50 is set to a material frame to which the material load can be assigned.
The calculation unit 10 automatically assigns the scheduled delivery date and the result of the assignment of the capacity load to the capacity frame.

【0092】材料枠にオーダーI50に係る材料負荷を
割り付けた結果を示した図が図11である。本実施形態
においては、オーダーI50に係る材料負荷を割り付け
た結果として、負荷割り付け済の材料枠90BがCRT
ディスプレイ8に表示される。
FIG. 11 shows the result of assigning the material load according to the order I50 to the material frame. In the present embodiment, as a result of allocating the material load related to the order I50, the load-allocated material
It is displayed on the display 8.

【0093】材料負荷割り付けの具体的な手順を以下に
述べる。まず、オーダーに係る能力負荷を割り付けた能
力枠から、ステップ5で1日毎の能力枠に割り付けた能
力負荷に係る製品の品目及び数量を1日毎に求め、該製
品の同一の品目及び同一の数量に係る材料負荷を、該能
力負荷と同一日の材料枠に割り付ける。そして、その材
料負荷の割り付けは、能力負荷の割り付けの結果に基づ
き、ステップ5で求められた予定納期から遡って行われ
る。
The specific procedure of material load assignment will be described below. First, from the capacity frame to which the capacity load related to the order is allocated, the item and quantity of the product related to the capacity load allocated to the capacity frame per day in step 5 are obtained every day, and the same item and the same quantity of the product are obtained. Is assigned to the material frame on the same day as the capacity load. Then, the assignment of the material load is performed retroactively from the scheduled delivery date obtained in step 5 based on the result of the assignment of the capacity load.

【0094】具体的には、本実施形態では、ステップ5
において、オーダーI50に係る能力負荷は、ラインA
において8月25日に3時間、24日に2時間、ライン
Bにおいて8月25日に3時間、24日に3時間ずつ割
り付けられており、その旨が割り付け済負荷記憶部5に
記憶されている。
Specifically, in the present embodiment, step 5
, The capacity load related to the order I50 is the line A
Are allocated for 3 hours on August 25, 2 hours on 24th, and 3 hours on Line 25 for 3 hours on August 25, and that fact is stored in the allocated load storage unit 5. I have.

【0095】割り付け済負荷記憶部5に記憶されてい
る、各日の能力枠に割り付けられた能力負荷と、オーダ
ー記憶部に記憶されているオーダーI50の情報、及び
能力負荷記憶部4に記憶されている製品1個当たりの能
力負荷とから、該各日の能力枠に割り付けられた能力負
荷にかかる製品の品目及び個数を演算部10で逆算す
る。ラインAにおいては、8月25日の能力枠には、3
時間÷0.05時間=60個、つまりフィルムA60個
分の能力枠が割り付けられている。同様に24日の能力
枠には、フィルムA40個分の能力枠が割り付けられて
いる。そして、ラインBにおいては、8月25日の能力
枠には、3時間÷0.03時間=100個、つまりフィ
ルムB100個分の能力負荷が割り付けられている。同
様に24日の能力枠には、フィルムB100個分の能力
負荷が割り付けられている。
The capacity load allocated to the capacity frame of each day stored in the allocated load storage section 5, the information of the order I 50 stored in the order storage section, and the information stored in the capacity load storage section 4. Based on the capacity load per product, the operation unit 10 calculates the product item and the number of products having the capacity load assigned to the capacity frame on each day. On line A, the capacity frame on August 25 is 3
Time / 0.05 hours = 60 pieces, that is, a capacity frame for 60 pieces of film A is allocated. Similarly, a capacity frame for 40 films A is allocated to the capacity frame on the 24th. In the line B, a capacity load of 3 hours / 0.03 hours = 100 pieces, that is, a capacity load for 100 films B is assigned to the capacity frame on August 25. Similarly, the capacity load for 100 films B is assigned to the capacity frame on the 24th.

【0096】そして、各日の能力負荷と同一の品目及び
個数に係る各日の材料負荷を、予定納期である8月25
日の材料枠から材料負荷の割り付けを開始し、予定納期
から遡って各日の材料枠に材料負荷の割り付けを行って
いく。したがって、8月25日にはフィルムA60個分
及びフィルムB100個分の材料負荷として、元巻A
1.8本、元巻B1.0本分という材料負荷を8月25
日の材料枠に割り付ける。そして、8月24日の材料枠
には同様に、フィルムA40個分、フィルムB100個
分の材料負荷として、元巻A1.2本、元巻B1.0本
分という材料負荷を8月24日の材料枠に割り付けるこ
とにより、予定納期の8月25日に合わせて、材料負荷
の材料枠への割り付けを行う。
Then, the material load of each day relating to the same item and number as the capacity load of each day is calculated on August 25, which is the scheduled delivery date.
The allocation of the material load is started from the material frame of the day, and the material load is allocated to the material frame of each day retroactively from the scheduled delivery date. Therefore, on August 25, as the material load for 60 films A and 100 films B, the original volume A
The material load of 1.8 pcs and 1.0 pcs of original volume was increased on August 25.
Allocate to material frame of the day. Similarly, in the material frame of August 24, the material load of the original volume A1.2 and the original volume B1.0 was set as the material load for the 40 films A and the 100 films B, respectively. The material load is assigned to the material frame in accordance with the scheduled delivery date of August 25.

【0097】尚、材料負荷の割り付けは、本実施形態の
ように演算部10が自動で行うようにしてもよいし、本
納期決定システムのオペレーターが負荷割り付け済の材
料枠をCRTディスプレイ8等を見ながらキーボード7
から入力するようにしてもよい。
The assignment of the material load may be automatically performed by the calculation unit 10 as in the present embodiment, or the operator of the delivery date determination system may display the material frame to which the load has been assigned on the CRT display 8 or the like. Keyboard 7 while watching
May be input.

【0098】ステップ6(S6):次に、能力負荷の能
力枠への割り付けを行った結果、予定納期に間に合うよ
うに割り付けを行えるか否かを判断する。
Step 6 (S6): Next, as a result of allocating the capacity load to the capacity frame, it is determined whether or not the allocation can be performed in time for the scheduled delivery date.

【0099】予定納期から遡って、オーダーに係る全て
の材料負荷の材料枠への割り付けが行えた場合は、予定
納期をオーダーI50の決定納期とする。そして、決定
納期とともにオーダーI50に関する情報が、オーダー
記憶部12に記憶される。
When all the material loads related to the order can be assigned to the material frames retroactively from the scheduled delivery date, the scheduled delivery date is set as the determined delivery date of the order I50. Then, information on the order I50 is stored in the order storage unit 12 together with the determined delivery date.

【0100】本実施形態では、顧客希望納期であり、予
定納期でもある8月25日から遡って、オーダーに係る
全ての材料負荷の材料枠への割り付けが行えたので、顧
客希望納期であり、予定納期である8月25日がオーダ
ーI50の決定納期となる。そして、決定納期とともに
オーダーI50に関する情報が、オーダー記憶部12に
記憶される。
In the present embodiment, all the material loads related to the order can be assigned to the material frames, going back from August 25, which is the customer's desired delivery date and also the scheduled delivery date. August 25, which is the scheduled delivery date, is the determined delivery date of order I50. Then, information on the order I50 is stored in the order storage unit 12 together with the determined delivery date.

【0101】一方、予定納期から遡って、オーダーに係
る材料負荷の材料枠への割り付けを行う際に、ある日の
能力枠に割り付けた能力負荷から逆算した品目及び個数
に係る材料負荷が、その日の材料枠の容量を越えている
ため、材料負荷を割り付けることができない場合は、そ
の日(以下、「不可日」と称する)の材料枠に割り付け
可能な材料負荷に係る製品の品目及び個数を求め、その
後、当該品目及び個数に係る能力負荷を求め、該結果を
割り付け済負荷記憶部5に記憶させる。そして、再度、
ステップ3に遡り、オーダーに係る能力負荷の能力枠へ
の割り付けから行う。その際、不可日の能力枠には、当
該求めた能力負荷だけを割り付けるようにする。そし
て、能力枠に能力負荷を割り付け直した後、再度材料負
荷を割り付ける。そして、材料負荷が全て割り付けるこ
とが可能になるまで、この作業を繰り返す。そして、全
ての材料負荷を割り付けることが可能になった場合の、
材料負荷を割り付けた最終日を決定納期とする。
On the other hand, when allocating the material load related to the order to the material quota retroactively from the scheduled delivery date, the material load related to the item and the number calculated back from the capacity load allocated to the capacity quota on a certain day is the same as the day. If the material load cannot be allocated because the capacity of the material frame exceeds the capacity of the material frame, calculate the item and quantity of the product related to the material load that can be allocated to the material frame on that day (hereinafter referred to as “impossible day”). Thereafter, the capacity load relating to the item and the number is obtained, and the result is stored in the allocated load storage unit 5. And again,
Going back to step 3, the process starts from the assignment of the capacity load related to the order to the capacity frame. At that time, only the obtained capacity load is allocated to the capacity frame on the impossible day. Then, after the capacity load is reassigned to the capacity frame, the material load is assigned again. This operation is repeated until all the material loads can be allocated. And when it becomes possible to assign all material loads,
The final date to which the material load is assigned is the determined delivery date.

【0102】例えば、本実施形態において8月25日の
材料枠が元巻A1.2本分であった場合を考える。8月
25日の能力枠に割り付けたラインA3時間という能力
負荷は、フィルムA60個分であり、フィルムA60個
分に係る材料負荷は元巻A1.8本分である。したがっ
て、8月25日の能力枠に割り付けた能力負荷(ライン
A3時間)から逆算した品目及び個数(フィルムA60
個)に係る材料負荷(元巻A1.8本)が、その日の材
料枠の容量(元巻A1.2本)を越えているため、当該
元巻A1.8本分の材料負荷を割り付けることができな
い。この場合、8月25日の材料枠に割り付けることの
できる材料負荷である元巻A1.2本から、それに係る
能力負荷を求める。元巻A1.2本は、フィルムA40
個分であり、それに係る能力負荷はラインA2時間であ
る。したがって、能力枠に能力負荷を割り付けなおす際
に、8月25日の能力枠には、能力負荷としてラインA
2時間を割り付けるようにして、新たに能力枠への能力
負荷の割り付けを行う。これにより、8月25日の能力
枠、材料枠に共に、同一の製品の品目及び個数に係る能
力負荷と材料負荷とを割り付けることが可能となる。
For example, let us consider a case where the material frame on August 25 is A1.2 for the original volume in this embodiment. The capacity load of the line A3 hours allocated to the capacity frame on August 25 is for 60 films A, and the material load for 60 films A is 1.8 for the original winding A. Therefore, the item and the number (film A60) calculated backward from the capacity load (line A3 hours) allocated to the capacity frame on August 25
Since the material load (1.8 pieces of the original volume) per unit exceeds the capacity of the material frame on that day (1.2 pieces of the original volume), assign the material load for the 1.8 pieces of the original volume. Can not. In this case, the capacity load related to the material load that can be allocated to the material frame on August 25, A1.2, is obtained. The original volume A1.2 is film A40
The capacity load related thereto is line A2 hours. Therefore, when re-assigning the capacity load to the capacity frame, the capacity frame on August 25
A capacity load is newly assigned to the capacity frame by allocating two hours. As a result, it is possible to allocate the capacity load and the material load related to the same product item and number to both the capacity frame and the material frame on August 25.

【0103】尚、予定納期から遡って、材料負荷を材料
枠に割り付けずに、オーダーに係る能力負荷を割り付け
た最も早い日から順に、材料負荷を材料枠に割り付けて
いくようにしてもよい。
Incidentally, the material loads may be allocated to the material frames in order from the earliest day on which the capacity load relating to the order is allocated, rather than allocating the material loads to the material frames retroactively from the scheduled delivery date.

【0104】尚、材料をある程度在庫として保管してお
く場合、材料枠にこの在庫量も加味するようにしてもよ
い。すなわち、ある日までに保管されている在庫量と、
その日に供給予定の材料の供給量の和を、その日の材料
枠としてもよい。例えば、図9において、8月21日に
は元巻Aが2本供給されるのに対して、使用予定は1本
のみであるため、元巻Aが1本余る。その元巻A1本を
在庫とすると、8月22日において、元巻Aの供給量は
0本であるが、元巻Aの在庫量が1本となるため、8月
22日の材料枠は元巻Aが1本となる。つまり、X日後
の材料枠=今までの在庫量+X日間の供給量の合計−X
日間の材料負荷の合計、である。
When the materials are stored in stock to some extent, the stock amount may be added to the material frame. That is, the amount of inventory stored up to a certain date,
The sum of the supply amounts of the materials to be supplied on that day may be used as the material frame on that day. For example, in FIG. 9, two original volumes A are supplied on August 21, but only one is to be used, so that one more original volume A is left. Assuming that one of the original volumes A is in stock, the supply volume of the original volume A is 0 on August 22, but the stock amount of the original volume A is one, so the material frame on August 22 is The original winding A becomes one. That is, the material frame after X days = the stock amount up to now + the total supply amount for X days−X
The total material load for the day.

【0105】ステップ7(S7):材料負荷の材料枠へ
の割り付けも完了したら、決定納期を、CRTディスプ
レイ8に表示する。納期が決定したら、オーダーI50
に係る材料負荷に割り付けられた材料負荷と、能力負荷
に割り付けられた能力負荷は、割り付け済負荷記憶部5
において記憶される。また、決定納期をプリンター9か
ら出力するようにしてもよい。
Step 7 (S7): When the assignment of the material load to the material frame is completed, the determined delivery date is displayed on the CRT display 8. Once the delivery date is determined, order I50
The material load allocated to the material load and the capacity load allocated to the capacity load are stored in the allocated load storage unit 5.
Is stored. Further, the determined delivery date may be output from the printer 9.

【0106】以上の、システム構成及び手順により、本
納期決定システムにおいて、オーダーI50に係る情報
を入力することにより、オーダーI50が希望納期に間
に合うか否か、間に合わない場合は納期はいつになるか
等の正確な情報を、短時間で知ることができる。
According to the system configuration and procedure described above, in the present delivery date determination system, by inputting information relating to the order I50, it is determined whether or not the order I50 will meet the desired delivery date, and if not, when will the delivery date be reached? And other accurate information in a short time.

【0107】材料枠と能力枠の設定を予め行っておきさ
えすれば、オーダー(製品の品目、数量、希望納期)を
入力すると、人手を介さずに全ての処理を演算部で行
い、負荷を割り付け、自動的に納期が決定されるように
することも勿論可能である。
As long as the material frame and the capacity frame are set in advance, when an order (item, quantity, and desired delivery date) of a product is input, all processes are performed by the arithmetic unit without manual operation, and the load is reduced. It is, of course, possible to allocate and automatically determine the delivery date.

【0108】尚、例えば、営業マンが、オーダーを取引
先で受けて、該オーダーが顧客の希望納期に間に合うか
否か、否の場合は可能な納期はいつになるか等の情報
を、生産部門のサーバーと通信可能な携帯の端末から短
時間で確認することも可能である。
[0108] For example, a salesman receives an order at a business partner and produces information such as whether or not the order meets the customer's desired delivery date, and if not, when the possible delivery date will be. It is also possible to check in a short time from a portable terminal that can communicate with the department server.

【0109】尚、本実施形態では、能力負荷の割り付け
を材料負荷の割り付けより先に行ったが、もちろん、能
力負荷の割り付けの先に材料負荷の割り付けを行うよう
にしてもよい。また、能力負荷の割り付けと、材料負荷
の割り付けをほぼ同時に行うようにしてもよい。
In this embodiment, the capacity load is assigned before the material load is assigned. However, the material load may be assigned before the capacity load is assigned. Alternatively, the assignment of the capacity load and the assignment of the material load may be performed almost simultaneously.

【0110】尚、負荷割り付けの結果、希望納期に間に
合わない場合に、本実施形態においては、納期を変更す
ることで対処したが、オーダーに係る製品の種類や量を
変更したり、オーダーを分割することにより対処できる
ようにしてもよい。
In the present embodiment, when the desired delivery date cannot be met as a result of the load assignment, the delivery date is changed. However, the type or quantity of the product related to the order is changed, or the order is divided. By doing so, it may be possible to deal with it.

【0111】また、1度設定した能力枠や材料枠を変更
できるようにしてもよい。例えば、土曜日や日曜日に工
場を稼働させる場合や、残業などを行う場合、能力枠を
増加させることが可能となる。また、ある製品を製造す
るのに必要な生産ラインが使用不能であったり、飽和状
態である場合に、該製品を製造するのに通常は用いない
生産ラインを臨時で用いる場合(例えば、通常はフィル
ムAの生産ラインはラインAだが、ラインAが飽和状態
であり、臨時でラインBを用いる場合)に、能力枠を変
更可能(ラインBの能力枠を、ラインAの能力枠と変
更)としたり、能力負荷のラインの種類を変更可能(能
力負荷がラインAとなっているのを、ラインBに変更)
としてもよい。その際、割り付ける対象となる複数の種
類の生産ラインに優先順位を付しておき、優先順位順に
割り付けの変更を行うことが好ましい。
Further, the capacity frame and the material frame which have been set once may be changed. For example, when operating a factory on Saturday or Sunday, or when performing overtime, the capacity frame can be increased. Further, when a production line required to manufacture a product is unavailable or is saturated, a production line that is not normally used to manufacture the product is temporarily used (for example, usually, The production line for film A is line A, but when line A is saturated and line B is used temporarily, the capacity frame can be changed (the capacity frame for line B is changed to the capacity frame for line A). Or change the line type of the capacity load (change the capacity load from line A to line B)
It may be. At this time, it is preferable to assign priorities to a plurality of types of production lines to be assigned, and to change the assignment in the order of priority.

【0112】また、1度能力枠及び材料枠に割り付けた
能力負荷及び材料負荷を、再度割り付け直すことができ
るようにしてもよい。例えば、オーダーAに係る負荷を
割り付けて納期を決定した後に、緊急のオーダーBが入
ってきた場合、オーダーAは納期より多少遅れても問題
がないときは、オーダーAに係る負荷を再度割り付け直
して納期を遅らせ、空いた枠に緊急のオーダーBに係る
負荷を割り付け、オーダーBの希望納期に間に合わせる
場合である。
The capacity load and the material load once assigned to the capacity frame and the material frame may be reassigned. For example, if an urgent order B comes in after allocating the load related to order A and determining the delivery date, if there is no problem even if order A is slightly delayed from the delivery date, re-assign the load related to order A again. In this case, the delivery time is delayed, the load related to the urgent order B is allocated to the empty frame, and the desired delivery time of the order B is met.

【0113】但し、当日から所定期間以内の能力枠及び
材料枠に割り付けた能力負荷及び材料負荷は、変更して
再度割り付けすることができないようにしておき、当日
から所定期間以降の能力枠及び材料枠に割り付けた能力
負荷及び材料負荷同士のみを、変更して再度割り付けす
ることができるようにすることが、生産管理を混乱させ
ないようにする点から好ましい。例えば、当日から2週
間以内の能力枠及び材料枠に割り付けてある能力負荷及
び材料負荷は再度割り付けを行うことができず、当日か
ら2週間以降の能力枠及び材料枠に割り付けてある能力
負荷及び材料負荷同士では再度割り付けを行うことがで
きる。2週間以内の負荷の再度割り付けを可能にする
と、既に生産が始まっているオーダーに係る負荷まで
も、変更(再度割り付け)される可能性があり、生産工
程が混乱してしまうからである。
However, the capacity load and the material load assigned to the capacity frame and the material frame within a predetermined period from the day are changed so that they cannot be re-assigned, and the capacity frame and the material load after the predetermined period from the day are changed. It is preferable that only the capacity load and the material load allocated to the frame can be changed and re-allocated from the viewpoint of preventing production management from being confused. For example, the capacity load and material load assigned to the capacity quota and material quota within two weeks from the day cannot be re-assigned, and the capacity load and material quota assigned to the capacity quota and material quota after two weeks from the day. The material loads can be assigned again. If the load can be re-allocated within two weeks, even the load related to the order whose production has already started may be changed (re-allocated), and the production process will be confused.

【0114】また、本実施形態に示した負荷割り付けシ
ステムを有する生産システムにより、オーダーを入力す
ると、オーダーに係る能力負荷及び材料負荷計算、及び
能力負荷及び材料負荷の能力枠及び材料枠への割り付け
を行い、納期を決定し、それと共に生産工程に該割り付
け結果に基づいて自動的に指示を出し、該製品の生産ま
でもを行うようにしてもよい。
When an order is input by the production system having the load allocation system shown in this embodiment, the capacity load and the material load relating to the order are calculated, and the capacity load and the material load are allocated to the capacity frame and the material frame. May be performed to determine a delivery date, and at the same time, automatically issue an instruction to a production process based on the allocation result to perform the production of the product.

【0115】尚、今までに述べた、負荷割り付け方法、
納期決定方法や、生産方法のプログラムを記録した記録
媒体を、コンピューターで起動させ、該プログラムを実
行することにより負荷割り付けシステム、納期決定シス
テムや、生産システムを立ち上げるようにしてもよい。
記録媒体は、特に限定されず、フロッピーディスク、C
D−ROM、MOディスク、ハードディスク等が挙げら
れる。
The load allocation method described so far
A computer may be used to start a recording medium on which a program for the delivery date determination method or the production method is recorded, and the load allocation system, the delivery date determination system, or the production system may be started by executing the program.
The recording medium is not particularly limited, and a floppy disk, C
D-ROM, MO disk, hard disk, and the like are included.

【0116】また、図8、9、10、11のように、材
料枠や能力枠に割り付けられた負荷の状況を表形式によ
りCRTディスプレイ8等に表示するのではなく、図1
2に示すように、グラフ形式により表示するようにして
もよい。
Also, as shown in FIGS. 8, 9, 10, and 11, the status of the load assigned to the material frame and the capacity frame is not displayed in a table format on the CRT display 8 or the like.
As shown in FIG. 2, it may be displayed in a graph format.

【0117】図12は、図8、9で示した負荷割り付け
済能力枠と、負荷割り付け済材料枠とをグラフ表示した
例である。マーク101は、これ以上負荷を割り付ける
ことができないことを示すマークである。勿論、材料枠
と能力枠を別々に表示してもよい。
FIG. 12 is an example in which the load-allocated capacity frame and the load-allocated material frame shown in FIGS. 8 and 9 are graphically displayed. The mark 101 is a mark indicating that no more load can be allocated. Of course, the material frame and the capacity frame may be displayed separately.

【0118】本実施形態において生産対象である写真フ
ィルムは、非常に多種類の原材料を必要とし、原材料か
ら製品になる長期間を要する製品である。また、製品の
種類も非常に多種類である。そこで、オーダーを受けて
から製品を出荷するまでの時間を短縮するために、中間
材料である元巻を見込み生産しておくことにより対処し
ている。つまり、非常に多種類の原材料から、原材料の
種類数よりは少ない種類の元巻きを見込み生産し、該元
巻きを材料として、また非常に多種類の写真フィルムを
生産している。そして、この元巻は見込み生産により生
産されているため、常に多量の安定な供給を望むのが困
難な材料である。また、在庫を保管しておくことによ
り、安定な元巻の供給を行うことも考えられるが、元巻
を保管するには広大な在庫保管スペースが必要であり、
さらに長期保管により元巻の性能が劣化するおそれもあ
り、多くの元巻を在庫として保管しておくことは好まし
くない。したがって、供給可能な元巻の種類と量(材料
枠)に合わせて、生産計画(材料負荷の割り付け)を行
ったほうが、結果として安定な元巻の供給を行うことが
可能となり、多量の在庫も必要としない。
The photographic film to be produced in the present embodiment is a product that requires a very wide variety of raw materials and requires a long period of time to be converted from raw materials to a product. In addition, the types of products are very diverse. Therefore, in order to shorten the time from receiving an order to shipping the product, a countermeasure has been taken by producing a master roll as an intermediate material in anticipation. In other words, from a very large number of kinds of raw materials, a kind of original roll less than the number of kinds of raw materials is expected to be produced, and a very large number of kinds of photographic films are produced using the original roll as a material. And since this original volume is produced by prospective production, it is difficult to always demand a large amount of stable supply. It is also conceivable to provide a stable supply of the original volume by storing the inventory, but a large inventory storage space is required to store the original volume,
Further, the performance of the original roll may deteriorate due to long-term storage, and it is not preferable to keep many original rolls in stock. Therefore, if production planning (assignment of material load) is performed in accordance with the type and amount (material frame) of the original roll that can be supplied, it becomes possible to supply a stable original roll as a result, and large inventory Also do not need.

【0119】[0119]

【発明の効果】本発明により、材料や部品の供給に長時
間を要する製品や、中間材料を見込み生産しておく製品
など、常に材料の安定な供給を望めず、欲しいときに欲
しいだけの量の材料を得ることが困難な製品を生産する
場合であっても、正確な納期をオーダーを受けてから短
時間で容易に、人手を介さずに得ることができ、さら
に、完成品並びに材料の在庫を減らすことが可能とな
る。
According to the present invention, it is not always possible to expect a stable supply of materials, such as products that require a long time to supply materials and parts, and products that are expected to produce intermediate materials. Even when producing a product for which it is difficult to obtain a material, it is possible to obtain an accurate delivery date in a short time after receiving an order, easily and without human intervention. Inventory can be reduced.

【0120】また、生産部門と販売部門と、共にオーダ
ーの進捗状況がリアルタイムで把握できるので、生販間
の調整が不要となる。さらには、生産の負荷の平均化が
可能となる。
Further, since the progress of the order can be grasped in real time by both the production department and the sales department, there is no need to adjust between the live sales. Furthermore, the production load can be averaged.

【図面の簡単な説明】[Brief description of the drawings]

【図1】本発明の納期決定システムの実施形態の1例を
示す概略図。
FIG. 1 is a schematic diagram showing an example of an embodiment of a delivery date determination system according to the present invention.

【図2】本発明の納期決定システムにおいて、納期を決
定する際のフローチャート。
FIG. 2 is a flowchart for determining a delivery date in the delivery date determination system of the present invention.

【図3】能力枠を示す図。FIG. 3 is a diagram showing a capacity frame.

【図4】材料枠を示す図。FIG. 4 is a view showing a material frame.

【図5】オーダーを示す図。FIG. 5 is a diagram showing an order.

【図6】品目1個当たりの材料負荷、及び能力負荷を示
す図。
FIG. 6 is a diagram showing a material load and a capacity load per item.

【図7】オーダーに係る材料負荷、及び能力負荷を示す
図。
FIG. 7 is a diagram showing a material load and a capacity load according to an order.

【図8】オーダーに係る能力負荷を割り付ける前の、負
荷割り付け済能力枠を示す図。
FIG. 8 is a diagram showing a load-allocated capacity frame before a capacity load related to an order is allocated.

【図9】オーダーに係る材料負荷を割り付ける前の、負
荷割り付け済材料枠を示す図。
FIG. 9 is a diagram showing a load-assigned material frame before assigning a material load relating to an order.

【図10】オーダーに係る能力負荷を割り付けた後の、
負荷割り付け済能力枠を示す図。
FIG. 10 is a diagram showing a case where a capacity load related to an order has been allocated;
The figure which shows the load assigned capacity frame.

【図11】オーダーに係る材料負荷を割り付けた後の、
負荷割り付け済材料枠を示す図。
FIG. 11 after allocating material loads pertaining to an order;
The figure which shows the load-assigned material frame.

【図12】負荷割り付け済能力枠、及び負荷割り付け済
材料枠をグラフ表示した図。
FIG. 12 is a graph showing a load-allocated capacity frame and a load-allocated material frame;

【符号の説明】[Explanation of symbols]

7 キーボード 8 CRTディスプレイ 10 演算部 11 納期決定システム 30 能力枠 40 材料枠 50 オーダー 7 Keyboard 8 CRT display 10 Operation unit 11 Delivery date determination system 30 Capacity frame 40 Material frame 50 Order

───────────────────────────────────────────────────── フロントページの続き (72)発明者 福島 康二 東京都日野市さくら町1番地コニカ株式会 社内 (72)発明者 植竹 俊文 東京都日野市さくら町1番地コニカ株式会 社内 ──────────────────────────────────────────────────の Continuing on the front page (72) Koji Fukushima, Inventor Konica Corporation, 1 Sakuramachi, Hino-shi, Tokyo In-house (72) Inventor Toshifumi Ukita, Konica Corporation, 1 Sakura-machi, Hino-shi, Tokyo

Claims (33)

【特許請求の範囲】[Claims] 【請求項1】 所定期間内に割り付けることが可能な材
料負荷の総量又はその一部を示す材料枠を予め設けてお
き、生産のオーダーを受けた製品の品目及び数量に関す
る情報に基づいて前記オーダーに係る材料負荷を求め、
前記材料負荷を割り付けることができる空きが前記材料
枠にある場合に、前記材料負荷を前記材料枠に割り付け
ることを特徴とする負荷割り付け方法。
1. A material frame indicating a total amount or a part of a material load that can be allocated within a predetermined period is provided in advance, and said order is determined based on information on an item and a quantity of a product ordered for production. The material load pertaining to
A load allocating method, wherein the material load is allocated to the material frame when there is a space in the material frame to which the material load can be allocated.
【請求項2】 所定期間内に割り付けることが可能な生
産ライン能力負荷の総量又はその一部を示す能力枠と、
前記所定期間内に割り付けることが可能な材料負荷の総
量又はその一部を示す材料枠を予め設けておき、生産の
オーダーを受けた製品の品目及び数量に関する情報に基
づいて、前記オーダーに係る生産ライン能力負荷と材料
負荷とを求め、前記オーダーに係る前記生産ライン能力
負荷を割り付けることができる空きが、前記所定期間内
の前記能力枠にあり、かつ、前記オーダーに係る前記材
料負荷を割り付けることができる空きが、前記所定期間
内の前記材料枠にある場合に、前記オーダーに係る前記
生産ライン能力負荷を前記所定期間内の前記能力枠に、
前記オーダーに係る前記材料負荷を前記所定期間内の前
記材料枠にそれぞれ割り付けることを特徴とする負荷割
り付け方法。
2. A capacity frame indicating a total or a part of a production line capacity load that can be allocated within a predetermined period;
A material frame indicating the total amount or a part of the material load that can be allocated within the predetermined period is provided in advance, and based on the information on the item and quantity of the product for which the production order has been received, the production related to the order is performed. Finding a line capacity load and a material load, and a vacant space in which the production line capacity load related to the order can be allocated is in the capacity frame within the predetermined period, and allocating the material load related to the order. When the available space is in the material frame within the predetermined period, the production line capacity load pertaining to the order is set in the capacity frame within the predetermined period,
A load allocating method, wherein the material loads related to the orders are allocated to the material frames within the predetermined period.
【請求項3】 複数の所定期間を予め定め、各所定期間
内に割り付けることが可能な生産ライン能力負荷の総量
又はその一部を示す能力枠と、各所定期間内に割り付け
ることが可能な材料負荷の総量又はその一部を示す材料
枠を予め設けておき、生産のオーダーを受けた製品の品
目及び数量に関する情報に基づいて、前記オーダーに係
る生産ライン能力負荷と材料負荷とを求め、前記オーダ
ーに係る前記生産ライン能力負荷を割り付けることがで
きる空きが、1もしくは複数の前記所定期間に係る前記
能力枠にあり、かつ、前記オーダーに係る前記材料負荷
を割り付けることができる空きが、前記1もしくは複数
の前記所定期間と同一の、1もしくは複数の所定期間に
係る前記材料枠にある場合に、前記オーダーに係る前記
生産ライン能力負荷を、前記1もしくは複数の前記所定
期間に係る前記能力枠に割り付け、前記オーダーに係る
前記材料負荷を、前記オーダーに係る前記生産ライン能
力負荷を割り付けた前記1もしくは複数の前記所定期間
と同一の1もしくは複数の所定期間に係る前記材料枠に
割り付けることを特徴とする負荷割り付け方法。
3. A capacity frame indicating a total amount or a part of a production line capacity load that can be allocated within each predetermined period, and a material that can be allocated within each predetermined period. A material frame indicating the total amount of the load or a part thereof is provided in advance, and based on the information on the item and the quantity of the product that has received the production order, the production line capacity load and the material load related to the order are obtained, The vacant space to which the production line capacity load pertaining to the order can be allocated is in the capacity frame pertaining to one or a plurality of the predetermined periods, and the vacant space to which the material load pertaining to the order can be allocated is the 1 Or, when in the material frame pertaining to one or more predetermined periods that are the same as the plurality of predetermined periods, the production line capacity load pertaining to the order Is assigned to the capacity frame related to the one or more predetermined periods, and the material load related to the order is the same as the one or more predetermined periods assigned to the production line capacity load related to the order. A load assignment method, wherein the assignment is made to the material frame relating to one or a plurality of predetermined periods.
【請求項4】 前記生産のオーダーが希望納期を有して
いる場合に、前記生産のオーダーの希望納期を含む所定
期間に係る前記能力枠に、前記生産のオーダーに係る前
記生産ライン能力負荷の最初の割り付けを行い、その
後、1所定期間ずつ遡って、前記生産のオーダーに係る
前記生産ライン能力負荷の前記能力枠への割り付けを行
っていき、前記生産のオーダーに係る全ての前記生産ラ
イン能力負荷の割り付けが行えた場合には、前記生産ラ
イン能力負荷の割り付けを完了し、前記生産のオーダー
に係る全ての前記生産ライン能力負荷の割り付けが行え
なかった場合には、さらに前記生産のオーダーの希望納
期を含む所定期間から1所定期間ずつ進んで、前記生産
のオーダーに係る前記生産ライン能力負荷の前記能力枠
への割り付けを行い、又、前記生産のオーダーの希望納
期を含む所定期間に係る前記材料枠に、前記生産のオー
ダーに係る前記材料負荷の最初の割り付けを行い、その
後、1所定期間ずつ遡って、前記生産のオーダーに係る
前記材料負荷の前記材料枠への割り付けを行っていき、
前記生産のオーダーに係る全ての前記材料負荷の割り付
けが行えた場合には、前記材料負荷の割り付けを完了
し、前記生産のオーダーに係る全ての前記材料負荷の割
り付けが行えなかった場合には、さらに前記生産のオー
ダーの希望納期を含む所定期間から1所定期間ずつ進ん
で、前記生産のオーダーに係る前記材料負荷の前記材料
枠への割り付けを行うことを特徴とする請求項3に記載
の負荷割り付け方法。
4. When the production order has a desired delivery date, the capacity of the production line related to the production order is added to the capacity frame for a predetermined period including the desired delivery date of the production order. The first allocation is performed, and thereafter, the production line capacity load related to the production order is allocated to the capacity frame by going back one predetermined period, and all the production line capacities related to the production order are performed. If the load allocation can be performed, the allocation of the production line capacity load is completed.If all the production line capacity loads related to the production order cannot be allocated, the production order is further allocated. Advancing by one predetermined period from a predetermined period including the desired delivery date, and allocating the production line capacity load related to the production order to the capacity frame, Further, the first allocation of the material load relating to the production order is performed on the material frame relating to the predetermined period including the desired delivery date of the production order, and thereafter, the production order is returned by one predetermined period to the production order. Allocating the material load to the material frame,
When the assignment of all the material loads related to the production order is performed, the assignment of the material load is completed, and when the assignment of all the material loads related to the production order is not performed, The load according to claim 3, further allocating the material load related to the production order to the material frame by advancing one predetermined period from a predetermined period including a desired delivery date of the production order. Assignment method.
【請求項5】 前記同一の所定期間に係る前記能力枠に
割り付ける前記生産ライン能力負荷及び前記材料枠に割
り付ける前記材料負荷が、同一の前記オーダーに係る同
一の品目の同一の数量に係る、前記生産ライン能力負荷
及び前記材料負荷であることを特徴とする請求項2〜4
のいずれか1項に記載の負荷割り付け方法。
5. The production line capacity load allocated to the capacity frame and the material load allocated to the material frame for the same predetermined period relate to the same quantity of the same item of the same order. 5. The production line capacity load and the material load.
The load allocation method according to any one of the above.
【請求項6】 前記製品が写真感光材料であることを特
徴とする請求項1〜5のいずれか1項に記載の負荷割り
付け方法。
6. The method according to claim 1, wherein the product is a photographic material.
【請求項7】 請求項1〜6のいずれか1項に記載の負
荷割り付け方法による割り付け結果に基づいて、前記オ
ーダーの納期を決定することを特徴とする納期決定方
法。
7. A delivery date determination method, wherein a delivery date of the order is determined based on an allocation result by the load allocation method according to any one of claims 1 to 6.
【請求項8】 前記生産のオーダーに係る前記生産ライ
ン能力負荷と前記材料負荷の割り付けを行った前記能力
枠と前記材料枠で、最も後の所定期間に係る前記能力枠
及び前記材料枠の前記所定期間を前記オーダーの納期と
することを特徴とする請求項7に記載の納期決定方法。
8. The capacity frame and the material frame to which the production line capacity load and the material load related to the production order are assigned, and the capacity frame and the material frame related to the last predetermined period are assigned. The delivery date determination method according to claim 7, wherein a predetermined period is set as a delivery date of the order.
【請求項9】 請求項1〜6のいずれか1項に記載の負
荷割り付け方法による割り付け結果に基づいて前記製品
の生産を行うことを特徴とする生産方法。
9. A production method, wherein the product is produced based on an allocation result by the load allocation method according to any one of claims 1 to 6.
【請求項10】 請求項1〜6のいずれか1項に記載の
負荷割り付け方法によって負荷割り付けを行うことを特
徴とする負荷割り付けシステム。
10. A load allocating system, wherein a load is allocated by the load allocating method according to claim 1. Description:
【請求項11】 前記負荷割り付けを行った結果を出力
することを特徴とする請求項10に記載の負荷割り付け
システム。
11. The load allocation system according to claim 10, wherein a result of the load allocation is output.
【請求項12】 前記負荷割り付けを行った結果の出力
をグラフ表示により出力することを特徴とする請求項1
1に記載の負荷割り付けシステム。
12. The apparatus according to claim 1, wherein the output of the result of the load allocation is output as a graph.
2. The load assignment system according to 1.
【請求項13】 請求項7又は8に記載の納期決定方法
によって納期を決定することを特徴とする納期決定シス
テム。
13. A delivery date determination system, wherein a delivery date is determined by the delivery date determination method according to claim 7. Description:
【請求項14】 決定された前記納期を出力することを
特徴とする請求項13に記載の納期決定システム。
14. The delivery date determination system according to claim 13, wherein the determined delivery date is output.
【請求項15】 請求項9に記載の生産方法によって前
記製品の生産を行うことを特徴とする生産システム。
15. A production system for producing the product by the production method according to claim 9.
【請求項16】 生産のオーダーに係る製品の品目及び
数量に関する情報を入力する入力手段と、各品目に係る
材料負荷を記憶している材料負荷記憶手段と、各所定期
間内に割り付けることが可能な材料負荷の総量又はその
一部を前記各所定期間毎の材料枠として記憶する材料枠
記憶手段と、前記材料枠に既に割り付けられている材料
負荷を記憶している割り付け済負荷記憶手段と、前記入
力手段により入力された情報に基づいて、前記材料負荷
記憶手段に記憶されている前記オーダーに係る製品の各
品目の材料負荷から、前記オーダーに係る材料負荷を求
め、前記材料枠記憶手段に記憶されている前記材料枠
と、前記割り付け済負荷記憶手段に記憶されている前記
材料枠に既に割り付けられている前記材料負荷とから、
前記オーダーに係る材料負荷を割り付けることができる
空きがある前記材料枠を求め、前記空きがある材料枠に
前記オーダーに係る材料負荷を割り付ける演算手段とを
有することを特徴とする負荷割り付けシステム。
16. An input means for inputting information on an item and a quantity of a product according to a production order, and a material load storage means for storing a material load on each item, and can be allocated within each predetermined period. Material frame storage means for storing the total amount or a part of the material load as a material frame for each of the predetermined periods, and an assigned load storage means for storing a material load already allocated to the material frame, Based on the information input by the input means, from the material load of each item of the product pertaining to the order stored in the material load storage means, determine the material load pertaining to the order, and in the material frame storage means From the stored material frame and the material load already allocated to the material frame stored in the allocated load storage means,
A load allocating system comprising: calculating means for determining the material frame having a space to which the material load according to the order can be allocated, and allocating the material load according to the order to the material frame having the space.
【請求項17】 生産のオーダーに係る製品の品目及び
数量に関する情報を入力する入力手段と、前記各品目に
係る生産ライン能力負荷を記憶している生産ライン能力
負荷記憶手段と、前記各品目に係る材料負荷を記憶して
いる材料負荷記憶手段と、各所定期間内に割り付けるこ
とが可能な生産ライン能力負荷の総量又は一部を前記各
所定期間毎の能力枠として記憶する能力枠記憶手段と、
各所定期間内に割り付けることが可能な材料負荷の総量
又は一部を前記各所定期間毎の材料枠として記憶する材
料枠記憶手段と、前記能力枠と前記材料枠に、既に割り
付けられている生産ライン能力負荷と材料負荷を記憶し
ている割り付け済負荷記憶手段と、前記入力手段により
入力された情報に基づいて、前記生産ライン能力負荷記
憶手段に記憶されている前記オーダーに係る製品の各品
目の生産ライン能力負荷から、前記オーダーに係る生産
ライン能力負荷を求め、前記材料負荷記憶手段に記憶さ
れている前記オーダーに係る製品の各品目の材料負荷か
ら、前記オーダーに係る材料負荷を求め、前記能力枠記
憶手段に記憶されている前記能力枠と、前記割り付け済
負荷記憶手段に記憶されている前記能力枠に既に割り付
けられている前記生産ライン能力負荷とから、前記オー
ダーに係る生産ライン能力負荷を割り付けることができ
る空きがある前記能力枠を求め、前記材料枠記憶手段に
記憶されている前記材料枠と、前記割り付け済負荷記憶
手段に記憶されている前記材料枠に既に割り付けられて
いる前記材料負荷とから、前記オーダーに係る材料負荷
を割り付けることができる空きがある前記材料枠を求
め、空きがある前記能力枠に前記オーダーに係る生産ラ
イン能力負荷を割り付け、前記オーダーに係る生産ライ
ン能力負荷を割り付けた前記能力枠と同一期間に係る空
きがある前記材料枠に、前記オーダーに係る材料負荷を
割り付ける演算手段とを有することを特徴とする負荷割
り付けシステム。
17. An input means for inputting information on an item and a quantity of a product related to a production order, a production line capacity load storage means for storing a production line capacity load for each of the items, A material load storage unit that stores the material load, and a capacity frame storage unit that stores a total amount or a part of the production line capacity load that can be allocated within each predetermined period as a capacity frame for each of the predetermined periods. ,
A material frame storage means for storing the total amount or a part of the material load that can be allocated within each predetermined period as a material frame for each of the predetermined periods, and the production amount already allocated to the capacity frame and the material frame. Assigned load storage means for storing a line capacity load and a material load, and each item of the product pertaining to the order stored in the production line capacity load storage means, based on information input by the input means. From the production line capacity load, determine the production line capacity load pertaining to the order, from the material load of each item of the product pertaining to the order stored in the material load storage means, determine the material load pertaining to the order, The capacity frame stored in the capacity frame storage means and the capacity frame already allocated to the capacity frame stored in the allocated load storage means. From the production line capacity load, the capacity frame having a space to which the production line capacity load related to the order can be allocated is obtained, and the material frame stored in the material frame storage means and the allocated load storage means are determined. From the material load already allocated to the material frame stored in the, to find the material frame having a vacant space to which the material load pertaining to the order can be allocated, Calculating means for allocating the production line capacity load, and allocating the material load according to the order to the material frame having a vacant space for the same period as the capacity frame to which the production line capacity load according to the order is allocated. Characteristic load allocation system.
【請求項18】 前記演算手段は、前記生産のオーダー
の希望納期を含む所定期間に係る前記能力枠に、前記生
産のオーダーに係る前記生産ライン能力負荷の最初の割
り付けを行い、その後、1所定期間ずつ遡って、前記生
産のオーダーに係る前記生産ライン能力負荷の前記能力
枠への割り付けを行っていき、前記生産のオーダーに係
る全ての前記生産ライン能力負荷の割り付けが行えた場
合には、前記生産ライン能力負荷の割り付けを完了し、
前記生産のオーダーに係る全ての前記生産ライン能力負
荷の割り付けが行えなかった場合には、さらに前記生産
のオーダーの希望納期を含む所定期間から1所定期間ず
つ進んで、前記生産のオーダーに係る前記生産ライン能
力負荷の前記能力枠への割り付けを行い、又、前記演算
手段は、前記生産のオーダーの希望納期を含む所定期間
に係る前記材料枠に、前記生産のオーダーに係る前記材
料負荷の最初の割り付けを行い、その後、1所定期間ず
つ遡って、前記生産のオーダーに係る前記材料負荷の前
記材料枠への割り付けを行っていき、前記生産のオーダ
ーに係る全ての前記材料負荷の割り付けが行えた場合に
は、前記材料負荷の割り付けを完了し、前記生産のオー
ダーに係る全ての前記材料負荷の割り付けが行えなかっ
た場合には、さらに前記生産のオーダーの希望納期を含
む所定期間から1所定期間ずつ進んで、前記生産のオー
ダーに係る前記材料負荷の前記材料枠への割り付けを行
うことを特徴とする請求項17に記載の負荷割り付けシ
ステム。
18. The computing means performs an initial assignment of the production line capacity load related to the production order to the capacity frame related to a predetermined period including a desired delivery date of the production order, Going back by period, the production line capacity load related to the production order is allocated to the capacity frame, and if all the production line capacity loads related to the production order can be allocated, Completing the allocation of the production line capacity load,
When all the production line capacity loads related to the production order cannot be allocated, the production order further advances by a predetermined period from a predetermined period including a desired delivery date of the production order, and the Allocating a production line capacity load to the capacity frame, and the calculating means adds the first of the material load related to the production order to the material frame related to a predetermined period including a desired delivery date of the production order. After that, the material load relating to the production order is allocated to the material frame by going back one predetermined period at a time, and all the material loads relating to the production order can be allocated. If the assignment of the material load is completed, the assignment of the material load is not completed. 18. The load assignment according to claim 17, wherein the material load related to the production order is assigned to the material frame by advancing by a predetermined period from a predetermined period including a desired delivery date of the production order. system.
【請求項19】 前記演算手段は、同一の前記所定期間
に係る前記能力枠に割り付ける前記生産ライン能力負荷
及び前記材料枠に割りつける前記材料負荷が、同一の前
記オーダーに係る同一の品目の同一の数量に係る前記生
産ライン能力負荷及び前記材料負荷となるように、前記
生産のオーダーに係る前記生産ライン能力負荷の前記能
力枠への割り付け、及び前記生産のオーダーに係る前記
材料負荷の前記材料枠への割り付けを行うことを特徴と
する請求項17又は18に記載の負荷割り付けシステ
ム。
19. The computing means according to claim 1, wherein said production line capacity load to be allocated to said capacity frame and said material load to be allocated to said material frame for the same predetermined period are the same for the same item of said order. Allocation of the production line capacity load pertaining to the production order to the capacity frame, and the material of the material load pertaining to the production order so that the production line capacity load and the material load pertain to the quantity of 19. The load assignment system according to claim 17, wherein assignment to frames is performed.
【請求項20】 前記製品が写真感光材料であることを
特徴とする請求項16〜19のいずれか1項に記載の負
荷割り付けシステム。
20. The load allocation system according to claim 16, wherein the product is a photographic material.
【請求項21】 前記負荷割り付けの結果を出力する出
力手段を有することを特徴とする請求項16〜20のい
ずれか1項に記載の負荷割り付けシステム。
21. The load allocation system according to claim 16, further comprising output means for outputting a result of the load allocation.
【請求項22】 前記出力手段は、前記負荷割り付けの
結果をグラフ表示により出力することを特徴とする請求
項21に記載の負荷割り付けシステム。
22. The load allocation system according to claim 21, wherein said output means outputs a result of said load allocation in a graphical display.
【請求項23】 一度、前記材料枠に割り付けを行った
前記材料負荷を、他の空きがある材料枠に変更して割り
付けることができる請求項10〜12、16〜22のい
ずれか1項に記載の負荷割り付けシステム。
23. The method according to claim 10, wherein the material load once assigned to the material frame can be changed and assigned to another material frame having an empty space. The load allocation system described.
【請求項24】 前記割り付けの変更は、前記割り付け
の変更を入力する日から所定期間経過以降の前記材料枠
間において行うことができ、前記割り付けの変更を入力
する日から所定期間経過以前の前記材料枠間において
は、前記割り付けの変更を行うことができないことを特
徴とする請求項23に記載の負荷割り付けシステム。
24. The change of the allocation can be performed between the material frames after a lapse of a predetermined period from the date of inputting the change of the allocation, and 24. The load allocation system according to claim 23, wherein the allocation cannot be changed between material frames.
【請求項25】 前記割り付けの変更をする場合に、顧
客が希望する納期である顧客希望納期以降の前記材料枠
に、前記オーダーに対応する前記材料負荷を割り付ける
ことができないことを特徴とする請求項23又は24に
記載の負荷割り付けシステム。
25. The method according to claim 25, wherein when changing the assignment, the material load corresponding to the order cannot be assigned to the material frame after the customer desired delivery date, which is the delivery date desired by the customer. Item 25. The load allocation system according to Item 23 or 24.
【請求項26】 一度、前記能力枠及び前記材料枠に割
り付けを行った前記生産ライン能力負荷及び前記材料負
荷を、他の空きがある能力枠及び材料枠に変更して割り
付けることができる請求項10〜12、16〜22のい
ずれか1項に記載の負荷割り付けシステム。
26. The production line capacity load and the material load once assigned to the capacity frame and the material frame can be changed and assigned to a capacity frame and a material frame having other vacancies. The load allocation system according to any one of 10 to 12, 16 to 22.
【請求項27】 前記割り付けの変更は、前記割り付け
の変更を入力する日から所定期間経過以降の前記能力枠
間及び前記材料枠間において行うことができ、前記割り
付けの変更を入力する日から所定期間経過以前の前記能
力枠間及び前記材料枠間においては、前記割り付けの変
更を行うことができないことを特徴とする請求項26に
記載の負荷割り付けシステム。
27. The assignment change can be made between the capacity slots and the material slots after a lapse of a predetermined period from the date on which the assignment change is input, and can be changed from the date on which the assignment change is input. 27. The load allocation system according to claim 26, wherein the allocation cannot be changed between the capacity frames and the material frames before a period has elapsed.
【請求項28】 前記割り付けの変更をする場合に、顧
客が希望する納期である顧客希望納期以降の前記能力枠
及び材料枠に、前記顧客のオーダーに対応する前記生産
ライン能力負荷及び前記材料負荷を割り付けることがで
きないことを特徴とする請求項26又は27に記載の負
荷割り付けシステム。
28. When the allocation is changed, the production line capacity load and the material load corresponding to the customer's order are added to the capacity frame and the material frame after the customer desired delivery date, which is the delivery date desired by the customer. 28. The load allocation system according to claim 26, wherein the load allocation cannot be performed.
【請求項29】 請求項16〜28のいずれか1項に記
載の負荷割り付けシステムの演算手段による負荷割り付
け結果を基に前記オーダー又は前記製品の納期を求める
納期演算手段とを有することを特徴とする納期決定シス
テム。
29. A delivery date calculation means for obtaining a delivery date of the order or the product based on a load assignment result by the calculation means of the load assignment system according to any one of claims 16 to 28. Delivery date determination system.
【請求項30】 前記納期演算手段は、前記生産のオー
ダーに係る前記生産ライン能力負荷と前記材料負荷の割
り付けを行った前記能力枠と前記材料枠で、最も後の所
定期間に係る前記能力枠及び前記材料枠の前記所定期間
を前記オーダーの納期とすることを特徴とする請求項2
9に記載の納期決定システム。
30. The delivery time calculating means, wherein the capacity frame to which the production line capacity load and the material load related to the production order are assigned and the capacity frame related to the last predetermined period are assigned. And the predetermined period of the material frame is a delivery date of the order.
9. The delivery date determination system according to 9.
【請求項31】 前記納期を出力する出力手段を有する
ことを特徴とする請求項30に記載の納期決定システ
ム。
31. The delivery date determination system according to claim 30, further comprising output means for outputting the delivery date.
【請求項32】 請求項1〜6のいずれか1項に記載の
負荷割り付け方法を実行させるプログラムを読み取り可
能に記録したことを特徴とする記録媒体。
32. A recording medium on which a program for executing the load assignment method according to claim 1 is recorded in a readable manner.
【請求項33】 請求項7又は8に記載の納期決定方法
を実行させるプログラムを読み取り可能に記録したこと
を特徴とする記録媒体。
33. A recording medium on which a program for executing the delivery date determining method according to claim 7 or 8 is recorded in a readable manner.
JP1836397A 1997-01-31 1997-01-31 Load allocating method, deadline determining method, load allocating system, deadline determining system, production method, production system and recording medium Pending JPH10214293A (en)

Priority Applications (1)

Application Number Priority Date Filing Date Title
JP1836397A JPH10214293A (en) 1997-01-31 1997-01-31 Load allocating method, deadline determining method, load allocating system, deadline determining system, production method, production system and recording medium

Applications Claiming Priority (1)

Application Number Priority Date Filing Date Title
JP1836397A JPH10214293A (en) 1997-01-31 1997-01-31 Load allocating method, deadline determining method, load allocating system, deadline determining system, production method, production system and recording medium

Publications (1)

Publication Number Publication Date
JPH10214293A true JPH10214293A (en) 1998-08-11

Family

ID=11969623

Family Applications (1)

Application Number Title Priority Date Filing Date
JP1836397A Pending JPH10214293A (en) 1997-01-31 1997-01-31 Load allocating method, deadline determining method, load allocating system, deadline determining system, production method, production system and recording medium

Country Status (1)

Country Link
JP (1) JPH10214293A (en)

Cited By (4)

* Cited by examiner, † Cited by third party
Publication number Priority date Publication date Assignee Title
US6629008B2 (en) 2000-06-09 2003-09-30 Mitsubishi Denki Kabushiki Kaisha Production control system and method for producing air conditioners
WO2016079843A1 (en) * 2014-11-20 2016-05-26 株式会社日立製作所 Production plan adjustment assisting device and production plan adjustment assisting method
CN113320760A (en) * 2020-12-15 2021-08-31 广州富港万嘉智能科技有限公司 Material allocation method, storage medium, server and material allocation system
WO2023176846A1 (en) * 2022-03-16 2023-09-21 三菱電機株式会社 Production planning device, production planning method, and program

Cited By (4)

* Cited by examiner, † Cited by third party
Publication number Priority date Publication date Assignee Title
US6629008B2 (en) 2000-06-09 2003-09-30 Mitsubishi Denki Kabushiki Kaisha Production control system and method for producing air conditioners
WO2016079843A1 (en) * 2014-11-20 2016-05-26 株式会社日立製作所 Production plan adjustment assisting device and production plan adjustment assisting method
CN113320760A (en) * 2020-12-15 2021-08-31 广州富港万嘉智能科技有限公司 Material allocation method, storage medium, server and material allocation system
WO2023176846A1 (en) * 2022-03-16 2023-09-21 三菱電機株式会社 Production planning device, production planning method, and program

Similar Documents

Publication Publication Date Title
US20030208392A1 (en) Optimizing resource plans
JP4847030B2 (en) Ordering system and ordering method
JP2002244711A (en) Order receiving assembling production system and method
JP3997962B2 (en) Product allocation system, product allocation method, product allocation program, and storage medium
JPH10214293A (en) Load allocating method, deadline determining method, load allocating system, deadline determining system, production method, production system and recording medium
JP2002318840A (en) Inventory management system by predicting shipping amount and managing inventory
JPH1087036A (en) Stock allocating method, and deciding method of distribution mode and stocking position, in physical distribution system
JP2020013313A (en) Shift plan data creation program
JP4559698B2 (en) Supply and demand adjustment method and system, product manufacturing method
JP2005038258A (en) Commodity allocation system, commodity allocation method, commodity allocation program, and storage medium
JP2003345419A (en) Answering method and system
JP2004280520A (en) Commodity management system and method
JP2019159511A (en) Production support device and production support method
JP2001100829A (en) Method and device for processing product delivery answer and information recording medium
JP2003337614A (en) Production reservation system
TWI784311B (en) Management device, management system, and management program
JP2006039624A (en) Demand-and-supply adjusting program and device
JP2002099596A (en) Inventory control system
JP2000190177A (en) Method and device for production plan preparation and recording medium for storing production plan preparing program
JP4325825B2 (en) Production plan control method, production plan system, and recording medium
JP2002163014A (en) Method and system for delivery and inventory control
JP2003308109A (en) Production planning system
JPH0793410A (en) Production controlling method
JPH09114897A (en) Automatic order-receiving data dividing system
JPH11114784A (en) Production schedule forming device