JPH0663296B2 - Deck plate formwork method - Google Patents

Deck plate formwork method

Info

Publication number
JPH0663296B2
JPH0663296B2 JP18975287A JP18975287A JPH0663296B2 JP H0663296 B2 JPH0663296 B2 JP H0663296B2 JP 18975287 A JP18975287 A JP 18975287A JP 18975287 A JP18975287 A JP 18975287A JP H0663296 B2 JPH0663296 B2 JP H0663296B2
Authority
JP
Japan
Prior art keywords
deck plate
plate
deck
molding machine
floor
Prior art date
Legal status (The legal status is an assumption and is not a legal conclusion. Google has not performed a legal analysis and makes no representation as to the accuracy of the status listed.)
Expired - Lifetime
Application number
JP18975287A
Other languages
Japanese (ja)
Other versions
JPS6433338A (en
Inventor
謙 山之内
Current Assignee (The listed assignees may be inaccurate. Google has not performed a legal analysis and makes no representation or warranty as to the accuracy of the list.)
Shimizu Corp
Original Assignee
Shimizu Corp
Priority date (The priority date is an assumption and is not a legal conclusion. Google has not performed a legal analysis and makes no representation as to the accuracy of the date listed.)
Filing date
Publication date
Application filed by Shimizu Corp filed Critical Shimizu Corp
Priority to JP18975287A priority Critical patent/JPH0663296B2/en
Publication of JPS6433338A publication Critical patent/JPS6433338A/en
Publication of JPH0663296B2 publication Critical patent/JPH0663296B2/en
Anticipated expiration legal-status Critical
Expired - Lifetime legal-status Critical Current

Links

Description

【発明の詳細な説明】 [産業上の利用分野] 本発明は、比較的柱間隔の大きい鉄骨造の建築物におけ
るスラブの構築方法に係り、詳しくは、このようなスラ
ブの下面型枠として打ち込みのデッキプレートを使用す
るスラブコンクリートの打設工法に関するものである。
Description: TECHNICAL FIELD The present invention relates to a method for constructing a slab in a steel-framed building having a relatively large column spacing, and more specifically, it is driven as a lower surface formwork of such a slab. It concerns the construction method of slab concrete using the deck plate of.

[従来の技術] 一般に、建築物の床スラブ用のコンクリート型枠は、下
階からの支柱による支保工を使用し、合板を敷設した下
面の型枠上にコンクリートを打設する。建築物を鉄骨造
(以下S造という)として構築するときには、階高が比
較的高く、柱間隔も比較的大きく設定し、コンクリート
の打設がスラブのみに限られることから、梁の上面には
デッキプレートを敷設し、この上に直接コンクリートを
打設して打ち込み型枠とするデッキプレート工法が広く
採用されている。このデッキプレート工法は、高い階高
のスラブ下面の支保工が不要とする特徴を有するから、
デッキプレートの原材料の鋼板は、梁間隔に対応する波
形の大小に見合って厚さが選択され、各種の製品が提供
されている。
[Prior Art] Generally, a concrete formwork for a floor slab of a building uses a support work by a pillar from a lower floor, and concrete is placed on the formwork on the lower surface on which plywood is laid. When constructing a building as a steel frame structure (hereinafter referred to as S structure), the floor height is set relatively high, the column spacing is set relatively large, and concrete placement is limited to slabs only. A deck plate construction method is widely adopted in which a deck plate is laid and concrete is directly cast on it to form a driving form. This deck plate construction method has the feature that it does not require support work on the lower surface of the slab with a high floor height,
The thickness of the steel plate, which is the raw material of the deck plate, is selected according to the size of the corrugation corresponding to the beam interval, and various products are provided.

[発明が解決しようとする問題点] 従来の床コンクリートの構築方法では、合板型枠を使用
する場合には、下階からの高所作業のための足場が必要
であり、この存続期間の損料が計上される。また、型枠
の組み付けには特に大工や一般作業員の安定した労務条
件が確保しにくく、工期に影響を及ぼす。さらに、型枠
の解体時にはとくに作業の安全性を考慮する必要があ
る。
[Problems to be Solved by the Invention] In the conventional method for constructing floor concrete, when using a plywood formwork, a scaffolding for work in a high place from the lower floor is necessary, and a loss for this lifetime is required. Is accounted for. In addition, it is difficult to secure stable working conditions for carpenters and general workers when assembling the formwork, which affects the construction period. Furthermore, it is necessary to consider the safety of work especially when dismantling the formwork.

一方、デッキプレート工法によるときには、上記の問題
点の幾つかは解消されるが、製品の運搬、移動が多くな
り、しかも、輸送条件に規制されて、定尺以上の製品の
提供を受けることができず、支持固定に工数を要するほ
か、小梁用の鋼材の所要重量も大きくなる。また、中波
以上のデッキプレートでは、鋼板の厚さがかなり大きい
ため、現場における加工が容易でなく、材料のロスが大
きくなって不経済である、などの欠点がある。
On the other hand, when the deck plate method is used, some of the above problems are solved, but the amount of transportation and movement of the product increases, and moreover, the product is regulated by the transportation conditions and the product of the standard size or more is provided. This is not possible, and in addition to requiring man-hours for supporting and fixing, the required weight of the steel material for the beam is also increased. Further, in the case of a deck plate of medium wave or higher, since the thickness of the steel plate is considerably large, it is not easy to perform processing in the field, and the loss of material is large, which is uneconomical.

[問題点を解決するための手段] 本発明は、上記のような問題点に対処し、欠点を一掃し
て、S造の建築物のスラブコンクリート工法を改善する
目的をもって開発されたものであり、スラブコンクリー
トの打設工法を提供するものである。本発明は、従来の
ように、デッキプレート工法によるスラブコンクリート
の打設工法でありながら、とくに、原材料の鋼板から現
地成型によってデッキプレートを成型し、その製品を直
接に、しかも連続的に鉄骨梁上に敷設してスラブコンク
リートの下面型枠とすることを要旨とするものである。
そして、本発明は、建築物の架構の梁上にデッキプレー
ト成型機を設置する場所を、本設を兼ねて先行して準備
する工程と、この先行床に成型機の一式を移動可能に設
置する工程と、この成型機から得られる製品を直接架構
上に送り出して連続的に敷設する工程を主工程とするこ
とを特徴としており、これによって、基本のデッキプレ
ート工法によるものでありながら、各種の難点を排除
し、この工法の特徴を生かして、経済性の改善に貢献す
る工法を達成することに成功したものである。
[Means for Solving Problems] The present invention has been developed for the purpose of addressing the above problems, eliminating the drawbacks, and improving the slab concrete construction method for an S structure. It provides a construction method for slab concrete. INDUSTRIAL APPLICABILITY The present invention is a conventional method of placing slab concrete by a deck plate construction method, but in particular, a deck plate is formed by on-site molding from a steel plate of a raw material, and the product is directly and continuously steel beam The gist is to lay it on top and use it as a bottom formwork of slab concrete.
Then, the present invention provides a step of preparing a place for installing a deck plate molding machine on a beam of a frame of a building, which also serves as a main installation, and a set of molding machines movably installed on the preceding floor. The main process is the process of laying and continuously laying the product obtained from this molding machine on the frame and laying it continuously, which makes it possible to use various deck plate construction methods. It has succeeded in eliminating the above-mentioned difficulties and utilizing the characteristics of this construction method to achieve a construction method that contributes to the improvement of economic efficiency.

[実施例] 本発明のデッキプレート型枠工法を、好適な実施例を示
す図面に基づいて詳細に説明する。第1図は、本発明を
採用した建築物の平面図であって、この建築物は、一部
を8階建の居住区とした4階建の工場建築物を例として
いる。第2図は4階建の部分の要部の断面図である。1
は建築物の全体を示し、2は建築物1の鉄骨柱であっ
て、その間隔は縦、横各10mである。3は柱2に架け
わたされた鉄骨梁、4は梁3の中間に割り付けて架けわ
たされた仮設の鋼製補助梁である。5は建築物1の平面
のほぼ中央部に、他の部分に先行して形成された1スパ
ン幅の先行床であって、後に詳細に説明するデッキプレ
ート成型機6が設置されている。この先行床5の架構体
は、建築物1の他の部分の構成と相違はないが、補助梁
4の方向は相互に直交方向である。7はデッキプレート
であって、梁3と補助梁4の上に架けわたされ、梁3の
2スパンごとに突き付けで接続されるように、約20m
の製品になっている。デッキプレート7は本発明のデッ
キプレート工法に従って、床面全面に敷設されている。
図中のSは、鋼製の仮設構台である。
[Embodiment] The deck plate formwork method of the present invention will be described in detail with reference to the drawings showing a preferred embodiment. FIG. 1 is a plan view of a building adopting the present invention. This building is an example of a 4-story factory building with a part of an 8-story living area. FIG. 2 is a sectional view of the main part of the four-story building. 1
Shows the whole building, 2 is a steel frame pillar of the building 1, and the space | interval is 10 m in each length and width. Reference numeral 3 denotes a steel frame beam laid over the pillar 2, and 4 denotes a temporary steel auxiliary beam laid in the middle of the beam 3 and hung. Reference numeral 5 is a preceding floor having a span of 1 and formed in the center of the plane of the building 1 in advance of other portions, and a deck plate molding machine 6 described in detail later is installed. The structure of the preceding floor 5 is not different from the structure of the other parts of the building 1, but the directions of the auxiliary beams 4 are orthogonal to each other. Reference numeral 7 denotes a deck plate, which is laid over the beam 3 and the auxiliary beam 4 and is connected to each other by abutting every 2 spans of the beam 3, and is about 20 m.
It is a product of. The deck plate 7 is laid on the entire floor surface according to the deck plate construction method of the present invention.
S in the figure is a temporary steel gantry.

第2図は床コンクリートの断面図であって、8はデッキ
プレート7を下面型枠として打設されたスラブコンクリ
ートであり、補強用の鉄筋は図示を省略してある。デッ
キプレート7は、0.5mm厚の鋼板の原材料から波付け
の絞り工程によって、山部71の高さを15mm、幅25
mmに成型してあり、「キーストン・プレート」と呼ばれ
るものに近似し、デッキプレートとしては比較的小波の
ものである。補助梁4には鋼製の仮設梁として市販され
ている伸縮可能の製品を使用することができ、鉄骨梁3
から吊りボルト41によって上面を揃えて支持してあ
る。もちろん、本設の鉄骨小梁が設計されていれば、こ
れを使用してもよい。
FIG. 2 is a sectional view of the floor concrete, 8 is a slab concrete that is cast using the deck plate 7 as a lower surface form, and the reinforcing bars are not shown. The deck plate 7 has a height of the ridges 71 of 15 mm and a width of 25 by a corrugating drawing process from a 0.5 mm thick steel plate raw material.
It is molded into mm and is similar to what is called a "keystone plate", and it is a relatively small wave plate as a deck plate. As the auxiliary beam 4, a stretchable product commercially available as a steel temporary beam can be used.
The upper surface is aligned and supported by the hanging bolts 41. Of course, if a permanent steel beam is designed, this may be used.

デッキプレート成型機6は、その概略を第3図に示すよ
うに、成型機の本体部61と、アンコイラーである材料
供給部62と、製品送出部63などを、枠組した基台6
4上に一体的に組み付けてあり、本体部61は成型ロー
ル65の段数が8ないし12段である。本発明では、定
尺切断機、製品パイラ等が不要であり、別に、下面には
走行車輪66を有し、全体の移動用レール67を加えた
ものとなっている。成型機6は、市販品の成型機よりは
かなり小型のものであって、全長は6m以下、全重量も
通常の折版用のものが約11トンであるのに対して、全
装備で約7トンである。その他の、成型機としての艤装
については省略する。
As shown in FIG. 3, the deck plate molding machine 6 has a base 6 that is a frame structure of a main body 61 of the molding machine, a material supply unit 62 that is an uncoiler, a product delivery unit 63, and the like.
4, and the main body 61 has 8 to 12 stages of forming rollers 65. In the present invention, a constant length cutting machine, a product pillar, etc. are not necessary, and additionally, traveling wheels 66 are provided on the lower surface, and a rail 67 for the whole movement is added. The molding machine 6 is much smaller than a commercially available molding machine, and has a total length of 6 m or less and a total weight of about 11 tons for a normal orthograph, while it is about 10 tons with all equipment. 7 tons. The other outfitting as a molding machine is omitted.

[作用] 本発明の作用を、床コンクリート工事の施工工程に基づ
いて説明する。工程の第一は、最初の階(2階)の桁行
方向ほぼ中央部の外方に、デッキプレート成型機6の設
置場所として構台Sを形成する。この構台Sに適宜の揚
重装置を使用してデッキプレート成型機6の本体部61
を建築物1の内部に向けて据付け、材料供給部62と製
品送出部63を組み付けて、成型施設6を運転可能に艤
装する。ついで、原材料のコイル鋼板9を材料供給部6
2に装着し、その一端から順次に繰りだして本体部61
に供給する。製品送出部63からは波付けされた製品の
デッキプレート7が送り出される。デッキプレートの成
型は連続的であり、梁3の間隔に従って、製品の形状が
保たれる範囲で、約20m以内に裁断される。製品のデ
ッキプレート7は順次に遠方に送られながら梁3の上面
に固定され、中間は補助梁4で支持されて、デッキプレ
ート床面を構成する。このデッキプレート上にコンクリ
ート8を打設すれば、先行床5が建築物1を横断して形
成される。次いで、この先行床5上に1対のレール67
を敷設し、このレール面上にデッキプレート成型機6を
据付ける。先行床5の形成には代替の方法を取ることが
でき、荷重条件に見合って、コンクリートを打設せずに
デッキプレート床面のままとすること、さらに、鉄骨梁
3の上に直接レール67を敷設し、デッキプレート成型
機6として予め作業床を有するものを使用すること、あ
るいは、補助梁の数を多くする、などとすることができ
る。いずれにしても、成型機6の重量は、下方から支保
工を設けずに支持するようにする。
[Operation] The operation of the present invention will be described based on the construction process of floor concrete construction. In the first step, a gantry S is formed as an installation place of the deck plate molding machine 6 on the outer side of the central portion of the first floor (second floor) in the column direction. A proper lifting device is used for this gantry S to form a main body 61 of the deck plate molding machine 6.
Is installed toward the inside of the building 1, the material supply unit 62 and the product delivery unit 63 are assembled, and the molding facility 6 is operably outfitted. Next, the coil steel plate 9 of the raw material is supplied to the material supply unit 6
2 and attach it to one end of the main body 61
Supply to. The deck plate 7 of the corrugated product is delivered from the product delivery section 63. The deck plate is continuously molded, and is cut within about 20 m within the range in which the shape of the product is maintained according to the distance between the beams 3. The deck plate 7 of the product is sequentially fixed to the upper surface of the beam 3 while being sent to the distance, and the intermediate portion is supported by the auxiliary beam 4 to form the deck plate floor surface. If concrete 8 is placed on this deck plate, the preceding floor 5 is formed across the building 1. Then, a pair of rails 67 are mounted on the preceding floor 5.
And the deck plate molding machine 6 is installed on the rail surface. An alternative method can be used to form the preceding floor 5, in order to meet the load condition, the deck plate floor surface is left without placing concrete, and the rail 67 is directly mounted on the steel beam 3. Can be laid and a deck plate molding machine 6 having a working floor in advance can be used, or the number of auxiliary beams can be increased. In any case, the weight of the molding machine 6 is to be supported from below without supporting work.

成型機6はレール67の方向に走行可能であり、その作
動方向はレール67に直角である。ついで、先行床5上
で、前記と同様にデッキプレートを成型し、製品を送り
出し、中間補助梁4で中間部を支持しながら梁3上に固
定する。このような張設作業はすべて施工中のデッキプ
レート7上で行うことができる。デッキプレート成型機
6はレール67上を順次に移動させられ、製品を連続し
て供給し、先行するデッキプレート7の側縁に所定の重
なりを形成しながら、敷設の工程が進められる。柱型な
どの床上の突出部に対しては、デッキプレートの切欠き
は容易である。建築物1の他方の半分の施工工程は製品
の押し出し方向を換えるだけで前記と同様であって、こ
れらのデッキプレート7の上面に鉄筋を配筋し、梁3に
スタッドボルトを植設すれば、床コンクリートの下面型
枠は完成する。本実施例の施工では、波形鋼板の板金工
を6人で1チームとして作業させた。コンクリート8の
打設は常法のとおりであり、養生後の作業は補助梁4の
回収だけでよい。上階での作業は、概して上記の繰返し
で行うことができるが、上階の先行床のデッキプレート
は下階で準備する。
The molding machine 6 can run in the direction of the rail 67, and its operating direction is perpendicular to the rail 67. Then, on the preceding floor 5, the deck plate is molded in the same manner as described above, the product is sent out, and the intermediate auxiliary beam 4 supports the intermediate portion to fix it on the beam 3. All such tensioning work can be performed on the deck plate 7 under construction. The deck plate molding machine 6 is sequentially moved on the rail 67 to continuously supply the products, and the laying process is performed while forming a predetermined overlap on the side edge of the preceding deck plate 7. It is easy to cut out the deck plate for pillar-shaped protrusions on the floor. The construction process of the other half of the building 1 is the same as the above except that the extrusion direction of the product is changed, and if reinforcing bars are arranged on the upper surfaces of these deck plates 7 and stud bolts are planted on the beams 3. The bottom formwork of floor concrete is completed. In the construction of this example, the corrugated steel sheet metal working was performed by six people as one team. The concrete 8 is placed in the usual manner, and the work after curing only needs to recover the auxiliary beam 4. The work on the upper floor can be generally performed by repeating the above, but the deck plate of the preceding floor on the upper floor is prepared on the lower floor.

[発明の効果] 本発明のデッキプレート型枠工法は、上述のように、建
設現場の施工場所に即してデッキプレートを成型生産
し、これを直接押し出して梁の架構上に供給するように
しているから、デッキプレート工法の主部分を構成する
材料の取扱いにおいて、輸送、運搬、移動などの作業が
一切不要となる。しかも、連続的に生産供給されるもの
であるから、施工に不都合のない限りの、最大限の長尺
の材料が得られ、固定個所が減少し、それに伴う労力
も、煩雑なデッキプレート小口の閉塞作業も削減するこ
とができる。一方、デッキプレート成型機の費用を建設
現場で負担することになるが、適宜に配設する補助梁の
支持によって、薄鋼板を使用することができるから、成
型機自体も小型のもので十分であり、先行床上での操作
も特別に困難なことはない。さらに、作業員に特殊な技
能を要求されることもなく、作業そのものもデッキプレ
ート工法の利点を損ずることはない。なお、薄鋼板の現
地加工ははさみを使用して行えるから、容易であり、か
つ、材料に無駄を生じない。総じて、6万m2の実施例の
建築物における従来のデッキプレート工法との比較試算
では、m2当たり1,000円の工事費の減額が可能であ
り、経済的な効果は極めて大きく、その上、工期の短縮
も達成されていて、優れたデッキプレート型枠工法を提
供できるものである。
[Effects of the Invention] As described above, the deck plate formwork method of the present invention molds and produces the deck plate according to the construction site of the construction site and directly extrudes the deck plate to supply it to the beam frame. Therefore, no work such as transportation, transportation, or movement is required in handling the material that constitutes the main part of the deck plate construction method. Moreover, since it is produced and supplied continuously, the maximum length of material can be obtained as long as there is no inconvenience to the construction, the number of fixing points is reduced, and the labor involved is also a complicated deck plate Blocking work can be reduced. On the other hand, the cost of the deck plate molding machine will be borne at the construction site, but since thin steel plates can be used by the support of appropriately arranged auxiliary beams, a small molding machine itself is sufficient. There is no particular difficulty in operating on the preceding floor. Further, the worker is not required to have special skills, and the work itself does not impair the advantage of the deck plate construction method. Since the thin steel sheet can be locally processed by using scissors, it is easy and the material is not wasted. Generally, according to the comparison calculation with the conventional deck plate construction method in the building of the example of 60,000 m 2 , the construction cost of 1,000 yen per m 2 can be reduced, and the economical effect is extremely large. Moreover, the shortening of the construction period has been achieved, and an excellent deck plate formwork construction method can be provided.

【図面の簡単な説明】[Brief description of drawings]

図面は本発明のデッキプレート型枠工法を実施例に基づ
いて説明するものであり、第1図は工場建築物を例とす
る平面図、第2図はスラブ部分の断面詳細図、第3図は
デッキプレート成型機の概略の斜視図である。 1…建築物、2…鉄骨柱、3…鉄骨梁、4…仮設の補助
梁、5…先行床、6…デッキプレート成型機、7…デッ
キプレート、8…スラブコンクリート、9…コイル鋼
板、41…吊りボルト、61…本体部、62…材料供給
部、63…製品送出部、64…基台、66…走行車輪、
67…レール、S…構台。
The drawings are for explaining the deck plate formwork method of the present invention based on an embodiment, FIG. 1 is a plan view of a factory building as an example, FIG. 2 is a detailed sectional view of a slab portion, and FIG. FIG. 1 is a schematic perspective view of a deck plate molding machine. 1 ... Building, 2 ... Steel column, 3 ... Steel beam, 4 ... Temporary auxiliary beam, 5 ... Preceding floor, 6 ... Deck plate molding machine, 7 ... Deck plate, 8 ... Slab concrete, 9 ... Coil steel plate, 41 ... Hanging bolts, 61 ... Main body section, 62 ... Material supply section, 63 ... Product delivery section, 64 ... Base, 66 ... Traveling wheel,
67 ... rail, S ... gantry.

Claims (4)

【特許請求の範囲】[Claims] 【請求項1】鉄骨造の建築物の梁上にデッキプレートを
敷設し、これを下面型枠に使用してコンクリートを打設
し、スラブを構築する方法において、デッキプレートは
建設現場においてコイル鋼板から成型したものであり、
このデッキプレートを直接架構体上に連続的に敷設する
ことを特徴とするデッキプレート型枠工法。
1. A method of constructing a slab by constructing a slab by laying a deck plate on a beam of a steel frame building and using the deck plate as a lower surface formwork, wherein the deck plate is a coil steel plate at a construction site. It was molded from
A deck plate formwork method characterized by continuously laying this deck plate directly on the frame structure.
【請求項2】スラブを支持する梁の架構の一部に先行床
を形成する工程、この先行床上にデッキプレート成型機
を設置する工程、上記成型機によりコイル鋼板からデッ
キプレートを成型する工程、デッキプレートの製品を連
続して成型方向に送り出す工程、上記梁上でデッキプレ
ートを支持する工程、成型機を移動させてデッキプレー
トを順次敷設する工程、デッキプレート上にコンクリー
トを打設する工程とからなることを特徴とする特許請求
の範囲第1項記載のデッキプレート型枠工法。
2. A step of forming a preceding floor on a part of a frame of a beam supporting a slab, a step of installing a deck plate molding machine on the preceding floor, a step of molding a deck plate from a coil steel plate by the molding machine, The steps of continuously sending out deck plate products in the molding direction, the steps of supporting the deck plate on the beams, the steps of laying the deck plates one after another by moving the molding machine, and the steps of placing concrete on the deck plate. The deck plate formwork method according to claim 1, characterized in that
【請求項3】コイル鋼板は、現場加工の容易な薄鋼板で
あり、その波形は、山高が15mm以上30mm以下である
ことを特徴とする特許請求の範囲第1項または第2項記
載のデッキプレート型枠工法。
3. The deck according to claim 1 or 2, wherein the coil steel plate is a thin steel plate that can be easily machined on site, and the corrugation has a peak height of 15 mm or more and 30 mm or less. Plate formwork method.
【請求項4】デッキプレートの支持には、上記の梁の中
間に仮設の補助梁を使用することを特徴とする特許請求
の範囲第1項、第2項または第3項記載のデッキプレー
ト型枠工法。
4. A deck plate type according to claim 1, 2 or 3, wherein a temporary auxiliary beam is used in the middle of the beam for supporting the deck plate. Frame construction method.
JP18975287A 1987-07-29 1987-07-29 Deck plate formwork method Expired - Lifetime JPH0663296B2 (en)

Priority Applications (1)

Application Number Priority Date Filing Date Title
JP18975287A JPH0663296B2 (en) 1987-07-29 1987-07-29 Deck plate formwork method

Applications Claiming Priority (1)

Application Number Priority Date Filing Date Title
JP18975287A JPH0663296B2 (en) 1987-07-29 1987-07-29 Deck plate formwork method

Publications (2)

Publication Number Publication Date
JPS6433338A JPS6433338A (en) 1989-02-03
JPH0663296B2 true JPH0663296B2 (en) 1994-08-22

Family

ID=16246587

Family Applications (1)

Application Number Title Priority Date Filing Date
JP18975287A Expired - Lifetime JPH0663296B2 (en) 1987-07-29 1987-07-29 Deck plate formwork method

Country Status (1)

Country Link
JP (1) JPH0663296B2 (en)

Families Citing this family (1)

* Cited by examiner, † Cited by third party
Publication number Priority date Publication date Assignee Title
JP3236137B2 (en) * 1993-07-30 2001-12-10 富士通株式会社 Semiconductor element cooling device

Also Published As

Publication number Publication date
JPS6433338A (en) 1989-02-03

Similar Documents

Publication Publication Date Title
US4685264A (en) Concrete slab-beam form system for composite metal deck concrete construction
US4372906A (en) Method and apparatus for pre-casting steel reinforced concrete box-like modules
US3785608A (en) Jig for precasting a plurality of panels
US4495131A (en) Method for pre-casting steel reinforced concrete box-like modules
US3397858A (en) Concrete slab form panel-supporting bracket
KR20230066338A (en) Formwork system and method
JPH0663296B2 (en) Deck plate formwork method
CN110820559A (en) Cement concrete bridge deck pavement and construction method
JP2709091B2 (en) Manufacturing and stocking method of unit floor
JPH07259334A (en) Bearing structure of form panel used for self-elevation type form device
WO1981002600A1 (en) Arrangement for laying concrete floors
JP3701078B2 (en) Road slab construction method
JP3000090B2 (en) Assembling method of preassembled steel rebar
JPH0298406A (en) Manufacture of precast concrete slab
CN216664131U (en) Binding jig frame of steel reinforcement cage
CN216304361U (en) Cast-in-place cement concrete pavement template locator
JPH0634495Y2 (en) Flat slab pillar structure
JPH0748813Y2 (en) Unit type deck plate
DE810073C (en) Process for the production of reinforced concrete rib ceilings on formwork
JPH0113122Y2 (en)
JPH0687518U (en) Synthetic slab
JPH08193422A (en) Construction method for building
JPS6215368Y2 (en)
JPH0432901B2 (en)
CN113047609A (en) Construction method for constructing super-thick concrete top plate by utilizing simple latticed column laminated slab system