JPH03100298A - Work controlling device for tunnel construction - Google Patents

Work controlling device for tunnel construction

Info

Publication number
JPH03100298A
JPH03100298A JP23551789A JP23551789A JPH03100298A JP H03100298 A JPH03100298 A JP H03100298A JP 23551789 A JP23551789 A JP 23551789A JP 23551789 A JP23551789 A JP 23551789A JP H03100298 A JPH03100298 A JP H03100298A
Authority
JP
Japan
Prior art keywords
signal
machine
drive signal
spraying
tunnel construction
Prior art date
Legal status (The legal status is an assumption and is not a legal conclusion. Google has not performed a legal analysis and makes no representation as to the accuracy of the status listed.)
Granted
Application number
JP23551789A
Other languages
Japanese (ja)
Other versions
JPH086549B2 (en
Inventor
Masanobu Takagi
高木 正信
Hiroshi Mizuguchi
水口 弘
Current Assignee (The listed assignees may be inaccurate. Google has not performed a legal analysis and makes no representation or warranty as to the accuracy of the list.)
Obayashi Corp
Original Assignee
Obayashi Corp
Priority date (The priority date is an assumption and is not a legal conclusion. Google has not performed a legal analysis and makes no representation as to the accuracy of the date listed.)
Filing date
Publication date
Application filed by Obayashi Corp filed Critical Obayashi Corp
Priority to JP23551789A priority Critical patent/JPH086549B2/en
Publication of JPH03100298A publication Critical patent/JPH03100298A/en
Publication of JPH086549B2 publication Critical patent/JPH086549B2/en
Anticipated expiration legal-status Critical
Expired - Lifetime legal-status Critical Current

Links

Landscapes

  • Lining And Supports For Tunnels (AREA)
  • Excavating Of Shafts Or Tunnels (AREA)
  • Earth Drilling (AREA)

Abstract

PURPOSE:To grasp the working situation in real time by inputting the electric signal corresponding to the start and end of work in each process in a tunnel construction into a calculating device and tabulating the working time in each process in the order of processes. CONSTITUTION:In a tunnel construction, a drive signal for a boring excavator in a boring process, work starting signal in a charge explosion process, and a drive signal for an explosion device are inputted in succession into a calculating device. Then, in succession, in a remaining slag taking-out process, a drive signal for a heaping-up machine for heaping up the remaining slag onto a soil/ sand transport vehicle, into-mine-introducing/withdrawing signal for a soil/sand transport vehicle for transporting the remaining slag, and a drive signal for a spraying machine in the primary spraying process are inputted similarly. Further, in succession, a drive signal for a nut fastening machine in a lock bolt device process, drive signal for a spraying machine in the secondary spraying process, and a drive signal for a rivet driving machine in a water shielding process are inputted similarly. In the calculating device, the working time in each process is tabulated in the order of the processes on the basis of these input signals.

Description

【発明の詳細な説明】 (産業上の利用分野) この発明は、トンネル工事用作業管理装置に関し、特に
、一連の作業手順で施工されるトンネル工事の実際の作
業時間を作業の進行状態とともに自動的に表示できる管
理装置に関する。
DETAILED DESCRIPTION OF THE INVENTION (Field of Industrial Application) This invention relates to a work management device for tunnel construction, and in particular, to automatically calculate the actual working time of tunnel construction, which is constructed in a series of work procedures, along with the work progress state. The present invention relates to a management device that can display information.

(発明の背景) 岩盤を掘削してトンネルなどを構築する方法として爆薬
を用いる発破工法が知られている。
(Background of the Invention) A blasting method using explosives is known as a method of excavating rock to construct tunnels and the like.

この種の発破工法では、通常、切羽の穿孔工程、穿孔に
爆薬を装着し、爆薬を爆破する装薬爆破工程、ズリだし
工程、1次吹付は工程、ロックボルトノの装着工程、2
次吹付は工程、止水工程の順に作業を進行し、この工程
を繰り返すことによりトンネルが構築される。
This type of blasting method usually involves a drilling process in the face, a charge detonation process in which an explosive is attached to the hole and the explosive is detonated, a shearing process, a primary spraying process, a rock bolt installation process, and a second process.
The next spraying process is followed by the water stop process, and the tunnel is constructed by repeating this process.

ところで、岩盤中に原油貯蔵タンクを構築する場合など
では、岩盤タンク掘削用やタンク間の連絡用トンネルな
どで多数の切羽が同じ工事現場で施工されることがある
By the way, when constructing crude oil storage tanks in bedrock, a large number of faces may be constructed at the same construction site, such as for excavating rock tanks and connecting tunnels between tanks.

このような施工状況において、各切羽の作業管理は、従
来、前述した施工工程ごとに管理責任者を選定し、選定
された管理責任者が日報などにより現場事務所に作業時
間などを報告していた。
Under such construction conditions, work management for each face has traditionally been carried out by selecting a manager for each construction process mentioned above, and having the selected manager report work hours and other information to the site office through daily reports. Ta.

しかしながら、このような作業管理手段では、日報の提
出は作業が行われた翌日になり、リアルタイムでの情報
を得ることができない上に、多数の切羽における作業の
進捗状態を全体的に把握するための集計に時間がかかる
という問題もあった。
However, with such work management methods, daily reports are only submitted the day after the work is completed, making it impossible to obtain information in real time, and it is difficult to obtain an overall understanding of the progress status of work at multiple faces. There was also the problem that it took a long time to compile the data.

この発明は、このような従来の問題点に鑑みてなされた
ものであり、その目的とするところは、作業情報がリア
ルタイムで把握できるとともに、多数の切羽における作
業の集計が簡単にできるトンネル工事用作業管理装置を
提供することにある。
This invention was made in view of these conventional problems, and its purpose is to provide a system for tunnel construction in which work information can be grasped in real time and the work at a large number of faces can be easily aggregated. The purpose of the present invention is to provide a work management device.

(課題を解決するための手段) 上記目的を達成するために、本発明は、切羽の穿孔工程
、穿孔に爆薬を装着して爆破する装薬爆破工程、ズリだ
し工程、1次吹付は工程、ロックボルトの装着工程、2
次吹付は工程、止水工程の順に繰り返されるトンネル工
事において、前記穿孔工程の穿孔掘削機の駆動信号と、
前記装薬爆破工程の作業開始信号および発破器の稼動信
号と、前記ズリだし工程でズリを土砂運搬車に積載する
積載機の稼動信号およびズリ搬出用の土砂運搬車の出入
坑信号と、前記1次吹付は工程の吹付機の稼動信号と、
前記ロックボルト装着工程のナツト締付機の駆動信号と
、前記2次吹付は工程の吹付機の稼動信号と、前記止水
工程の釘打機の駆動信号とをそれぞれ入力信号とし、こ
れらの入力信号に基づき前記各工程の作業時間を工程順
に作表する演算装置とを有することを特徴とする。
(Means for Solving the Problems) In order to achieve the above object, the present invention provides a face drilling process, a charge blasting process in which explosives are attached to the hole and detonated, a shearing process, a primary spraying process, Rock bolt installation process, 2
In tunnel construction, where the next spraying process is repeated in the order of the water stop process, the driving signal of the drilling machine in the drilling process,
A work start signal and a blaster operation signal for the charge blasting process, an operation signal for a loading machine that loads waste onto an earth and sand transport vehicle in the scrap removal process, and an entrance/exit signal for an earth and sand transport vehicle for transporting the waste; The first spraying is based on the operation signal of the spraying machine in the process,
A driving signal for a nut tightening machine in the lock bolt installation process, an operating signal for a spraying machine in the secondary spraying process, and a driving signal for a nailing machine in the water stopping process are input signals, respectively, and these input signals are used as input signals. The present invention is characterized by comprising an arithmetic device that tabulates the working time of each of the steps in the order of the steps based on the signal.

(発明の作用効果) 上記構成のトンネル工事用作業管理装置によれば、穿孔
から止水の各工程において、それぞれ作業の開始および
終了に相当する電気信号が出力されるので、各工程にお
ける作業状況をリアルタイムで把握できる。
(Operation and Effect of the Invention) According to the work management device for tunnel construction having the above configuration, electric signals corresponding to the start and end of the work are output in each process from drilling to water stoppage, so the work status in each process is can be understood in real time.

また、各工程から出力された信号は、演算装置で自動的
に処理されて工程順に作表されるので、切羽が多数あっ
ても簡単に対応でき、集計も容易になる。
Furthermore, since the signals output from each process are automatically processed by the arithmetic unit and tabulated in the order of the processes, even if there are a large number of faces, it can be easily handled and tabulation becomes easy.

(実施例) 以下、この発明の好適な実施例について添付図面を参照
にして詳細に説明する。
(Embodiments) Hereinafter, preferred embodiments of the present invention will be described in detail with reference to the accompanying drawings.

第1図から第4図は、この発明にかかるトンネル工事用
作業管理装置の一実施例を示している。
1 to 4 show an embodiment of a tunnel construction work management device according to the present invention.

同図に示す管理装置は、第1図に示す工程で施工される
トンネル工事に適用されるものであり、トンネル工事は
順に繰り返される■切羽の穿孔工程、■穿孔に爆薬を装
着して爆破する装薬爆破工程、■ズリだし工程、01次
吹付は工程、■ロックボルトの装着工程、02次吹付は
工程、■止水工程からなっている。
The control device shown in the figure is applied to tunnel construction that is constructed in the process shown in Figure 1, and the tunnel construction is repeated in the following order: ■ drilling process of the face, ■ attaching explosives to the borehole and detonating it. It consists of the charge detonation process, ① sludge removal process, 01st spraying process, ②rock bolt installation process, 02nd spraying process, and ②water stop process.

作業管理装置は、上記■〜■の各工程で使用される各種
機械の稼動により発せられる信号81〜sloと、この
信号51〜sloに基づいて前記工程■〜■の作業時間
を工程順に作表する演算装置CPUとから構成されてい
る。
The work management device tabulates the working time of the steps ■ to ■ in order of process based on the signals 81 to slo emitted by the operation of various machines used in each of the above steps and the signals 51 to slo. It consists of an arithmetic unit CPU.

上記信号81〜slOの詳細について説明すると、切羽
の穿孔工程■から送られる信号S1は、穿孔装置の駆動
開始信号と終了信号とを含んでおり、これらの信号以外
に、例えば、穿孔装置が一般的に採用されているジャン
ボ機であれば、その削孔ロッドの速度信号、打撃油圧の
大きさ1押し付は油圧の大きさなどの信号も含ませて、
これらの信号に基づいて最大削孔速度を演算装置CPt
)で計算して穿孔作業のより詳細な管理をすることもで
きる。
To explain the details of the signals 81 to slO, the signal S1 sent from the face drilling process (2) includes a drive start signal and an end signal for the drilling device. If it is a jumbo machine that is used in the industry, the speed signal of the drilling rod, the magnitude of the impact hydraulic pressure, and the pressure of the hydraulic pressure will also be included.
Based on these signals, the maximum drilling speed is calculated by the calculation device CPt.
) for more detailed management of drilling operations.

穿孔に爆薬を装着して爆破する装薬爆破工程■から送ら
れる信号は、装薬の開始でセットされる開始信号s2と
、発破器の稼動により送出される停止信号s3である。
Signals sent from the charge detonation step (3) in which explosives are loaded into the borehole and detonated are a start signal s2 that is set when the charge is started, and a stop signal s3 that is sent out when the blaster is activated.

ズリだし工程■から送られてくる信号は、ズリを外部に
搬出するためのダンプトラックDにズリを載せるホイー
ルローダ(土砂積載機)の稼動と、ダンプトラックDの
稼動との情報を含んでいる。
The signal sent from the scrap removal process ■ includes information on the operation of the wheel loader (soil loading machine) that loads the scraps onto the dump truck D for transporting the scraps to the outside, and the operation of the dump truck D. .

ホイールローダ−に関する信号s4では、パケットの上
昇および下降で発せられる信号と、ホイールローダの走
行時間信号とがある。
The signals s4 related to the wheel loader include signals emitted when the packet rises and falls, and a wheel loader running time signal.

第3図にダンプトラックDの稼動で送られて(る信号s
5の詳細を示している。
Figure 3 shows the signal s sent by the operation of the dump truck D.
5 details are shown.

同図では、現在作業が進行している切羽を有するトンネ
ルTの入口近傍に、受光器Rと、その制御器Cとが取付
けられたボールPが立設されている。
In the figure, a ball P to which a light receiver R and its controller C are attached is erected near the entrance of a tunnel T having a face where work is currently underway.

また、トンネルTの出口通路上には、重量計Wが設置さ
れている。
Moreover, a weight scale W is installed on the exit passage of the tunnel T.

一方、トンネルTに出入りするダンプトラックDには、
送信器Sと発光器Pとが装備されている。
On the other hand, the dump truck D going in and out of the tunnel T has
It is equipped with a transmitter S and a light emitter P.

トンネルTに入るダンプトラックDは、送信器Sを駆動
して発光器Pから光信号を受光器Rに送るとともに、ズ
リを搭載してトンネルTから出てきたダンプトラックD
は、重量計W上に停止して搭載されているズリの量を計
測し、再び送信器Sを駆動して受光器Rに信号を送る。
The dump truck D entering the tunnel T drives the transmitter S to send an optical signal from the emitter P to the receiver R, and at the same time, the dump truck D that comes out of the tunnel T with the waste loaded
stops on the weighing scale W to measure the amount of shear on the weighing scale W, and drives the transmitter S again to send a signal to the light receiver R.

以上の内容を含んだ信号s5を受けた演算装置CPUで
は、ズリだしの作業時間、ダンプトラックDの坑内滞留
時間、排出ズリ量の集計などが演算される。
The arithmetic unit CPU which receives the signal s5 containing the above content calculates the work time for scraping out, the residence time in the mine of the dump truck D, the total amount of discharged scrap, etc.

1次吹付は工程■から送られる信号S6は、コンクリー
ト吹付は機械の駆動、停止信号であり、これにより1次
吹付は工程の所要時間が演算される。
For the primary spraying, the signal S6 sent from the process (2) is a drive/stop signal for the concrete spraying machine, and from this, the time required for the primary spraying process is calculated.

ロックボルトの装着工程■から送られる信号は、モルタ
ルフィダーの駆動、停止信号s7と、ロックボルトナツ
トの締付は機の駆動、停止信号S8であり、締付は機の
からの信号s8には、ナツトの締付はトルクの大きさも
含ませて、作業の品質管理に利用することもできる。
The signals sent from the lock bolt installation process (■) are the mortar feeder drive and stop signal s7, and the machine drive and stop signal S8 for tightening the lock bolt nut; , Nut tightening can also be used to control the quality of work by including the torque.

2次吹付は工程■からの信号s9は、上記1次吹付けと
同様にコンクリート吹付は機械の駆動。
For the secondary spraying, the signal s9 from step ① drives the machine for concrete spraying, similar to the above-mentioned primary spraying.

停止信号である。It's a stop signal.

止水工程■からの信号sloは、釘打機の駆動。The signal slo from the water stop process ■ drives the nailer.

停止信号である。It's a stop signal.

なお、上記信号51〜sloを演算装置CPUに入力す
る際には、有線で直接接続すること以外に、無線により
信号の伝達をすることもできる。
In addition, when inputting the above-mentioned signals 51 to slo to the arithmetic unit CPU, the signals can be transmitted wirelessly instead of directly connecting by wire.

以上の信号51〜slOを受けた演算装置CPUでは、
必要な各種計算処理をし、第4図に示すように各工程■
〜■の作業時間を工程順に表示する。
In the arithmetic unit CPU that receives the above signals 51 to slO,
Perform various necessary calculations and perform each process as shown in Figure 4.
Display the work time of ~■ in order of process.

【図面の簡単な説明】[Brief explanation of drawings]

第1図は本発明にかかるトンネル工事用作業管理装置が
適用される作業工程のフローチャート図、第2図は同管
理装置の構成を示すブロック図、第3図はズリだし工程
における信号の収集状態の説明図、第4図は演算装置に
より作成された表の一例を示す説明図である。 第1図 CPU・・・・・・演算装置 p・・・・・・・・・・・・ダンプトラックS・・・・
・・・・・・・・送信器 R・・・・・・・・・・・・受信器
Fig. 1 is a flowchart of the work process to which the tunnel construction work management device according to the present invention is applied, Fig. 2 is a block diagram showing the configuration of the management device, and Fig. 3 is the signal collection state in the slip removal process. FIG. 4 is an explanatory diagram showing an example of a table created by the arithmetic device. Figure 1 CPU... Arithmetic unit p... Dump truck S...
・・・・・・・・・Transmitter R・・・・・・・・・Receiver

Claims (1)

【特許請求の範囲】[Claims] 切羽の穿孔工程、穿孔に爆薬を装着して爆破する装薬爆
破工程、ズリだし工程、1次吹付け工程、ロックボルト
の装着工程、2次吹付け工程、止水工程の順に繰り返さ
れるトンネル工事において、前記穿孔工程の穿孔掘削機
の駆動信号と、前記装薬爆破工程の作業開始信号および
発破器の稼動信号と、前記ズリだし工程でズリを土砂運
搬車に積載する積載機の稼動信号およびズリ搬出用の土
砂運搬車の出入坑信号と、前記1次吹付け工程の吹付機
の稼動信号と、前記ロックボルト装着工程のナット締付
機の駆動信号と、前記2次吹付け工程の吹付機の稼動信
号と、前記止水工程の釘打機の駆動信号とをそれぞれ入
力信号とし、これらの入力信号に基づき前記各工程の作
業時間を工程順に作表する演算装置とを有することを特
徴とするトンネル工事用作業管理装置。
Tunnel construction in which the following steps are repeated in the following order: drilling process of the face, explosives being installed in the hole and detonating it, shearing process, primary spraying process, rock bolt installation process, secondary spraying process, and water stopping process. , a drive signal for a drilling machine in the drilling process, a work start signal and a blaster activation signal in the charge blasting process, an activation signal for a loading machine that loads waste onto an earth and sand transport vehicle in the scraping process, and The input/exit signal of the earth and sand transport vehicle for removing waste, the operation signal of the spraying machine in the primary spraying process, the drive signal of the nut tightening machine in the rock bolt installation process, and the spraying signal in the secondary spraying process. It is characterized by having an arithmetic device which receives an operating signal of the machine and a driving signal of the nailing machine in the water stopping process as input signals, and tabulates the working time of each process in order of process based on these input signals. A work management device for tunnel construction.
JP23551789A 1989-09-13 1989-09-13 Work management device for tunnel construction Expired - Lifetime JPH086549B2 (en)

Priority Applications (1)

Application Number Priority Date Filing Date Title
JP23551789A JPH086549B2 (en) 1989-09-13 1989-09-13 Work management device for tunnel construction

Applications Claiming Priority (1)

Application Number Priority Date Filing Date Title
JP23551789A JPH086549B2 (en) 1989-09-13 1989-09-13 Work management device for tunnel construction

Publications (2)

Publication Number Publication Date
JPH03100298A true JPH03100298A (en) 1991-04-25
JPH086549B2 JPH086549B2 (en) 1996-01-24

Family

ID=16987158

Family Applications (1)

Application Number Title Priority Date Filing Date
JP23551789A Expired - Lifetime JPH086549B2 (en) 1989-09-13 1989-09-13 Work management device for tunnel construction

Country Status (1)

Country Link
JP (1) JPH086549B2 (en)

Cited By (2)

* Cited by examiner, † Cited by third party
Publication number Priority date Publication date Assignee Title
JP2010196315A (en) * 2009-02-24 2010-09-09 Enzan Kobo:Kk Method for measuring cycle time in tunnel construction
JP2019027097A (en) * 2017-07-28 2019-02-21 大成建設株式会社 Tunnel construction process recording device and tunnel cycle time management device, and tunnel construction process recording method and method for tunnel cycle time management method

Cited By (2)

* Cited by examiner, † Cited by third party
Publication number Priority date Publication date Assignee Title
JP2010196315A (en) * 2009-02-24 2010-09-09 Enzan Kobo:Kk Method for measuring cycle time in tunnel construction
JP2019027097A (en) * 2017-07-28 2019-02-21 大成建設株式会社 Tunnel construction process recording device and tunnel cycle time management device, and tunnel construction process recording method and method for tunnel cycle time management method

Also Published As

Publication number Publication date
JPH086549B2 (en) 1996-01-24

Similar Documents

Publication Publication Date Title
CN203559895U (en) Electric mining rope excavator, electric mining drilling machine and system
Nelson TBM performance analysis with reference to rock properties
US5844800A (en) Shot-rock diggability monitor
Phadke et al. Construction of tunnels, by new austrian tunneling method (NATM) and by tunnel boring machine (TBM)
JPH03100298A (en) Work controlling device for tunnel construction
Olsson et al. Äspö HRL. Experiences of blasting of the TASQ tunnel
Bullock Trends in non-coal underground mining technology at the close of the millennium
Gustafson et al. Face to Surface: a fragmentation study
Tuncdemir Impact hammer applications in Istanbul metro tunnels
Karwoski et al. Rock preconditioning to prevent rock bursts: report on a field demonstration
Konyukh Robotics for mining
JP2781845B2 (en) Underground obstacle removal method in propulsion work
JPH1060954A (en) Digging load measuring and display device for ground to be blasted
JP3441094B2 (en) Shelf transport method in tunnel
Hood Advances in hard rock mining technology
Clements Shotcreting in Australian underground mines: a decade of rapid improvement
Scoble et al. A study of surface mine equipment monitoring
Pawar et al. Mining Mechanism for Tunnelling
JPH06280479A (en) Carrying method for waste in tunnel
Trotter Vertical crater retreat mining in the Sudbury Basin
Morton New Blasthole Drill Rigs Feature More Autonomy
JPS63255492A (en) Method of excavating raw ore
AU2014100151A4 (en) High Speed Mine Development Methodology
Sakai et al. Development and application of remote monitoring systems for tunneling works in conventional tunnel construction
Martin et al. CHICAGO SEWER SYSTEM TUNNELS AND SHAFTS: ROOSEVELT ROAD TO OGDEN AVENUE