net
curing device
rail
pair
pillars
Prior art date
Legal status (The legal status is an assumption and is not a legal conclusion. Google has not performed a legal analysis and makes no representation as to the accuracy of the status listed.)
Active
Application number
JP2015104593A
Other languages
Japanese (ja)
Other versions
JP2016217040A (en
Inventor
洋介 三原
洋介 三原
義和 大塚
義和 大塚
功一郎 川瀬
功一郎 川瀬
周作 鬼頭
周作 鬼頭
隆 野々村
隆 野々村
宏一 生巣
宏一 生巣
Current Assignee (The listed assignees may be inaccurate. Google has not performed a legal analysis and makes no representation or warranty as to the accuracy of the list.)
Kajima Corp
Original Assignee
Kajima Corp
Priority date (The priority date is an assumption and is not a legal conclusion. Google has not performed a legal analysis and makes no representation as to the accuracy of the date listed.)
Filing date
Publication date
Application filed by Kajima Corp filed Critical Kajima Corp
Priority to JP2015104593A priority Critical patent/JP6654810B2/en
Publication of JP2016217040A publication Critical patent/JP2016217040A/en
Application granted granted Critical
Publication of JP6654810B2 publication Critical patent/JP6654810B2/en
Active legal-status Critical Current
Anticipated expiration legal-status Critical

Links

Images

Description

本発明は、養生装置に関する。   The present invention relates to a curing device.

高所作業(例えばビルの屋上)を行う際に、作業中に発生した落下物が高所から落下するのを防止するために、垂直養生を行う必要がある。このような養生装置として、例えば特許文献1に示すものが知られている。この養生装置は、ビルの屋上の全周にわたって養生をなしている。   When performing high-place work (for example, on the roof of a building), it is necessary to perform vertical curing in order to prevent falling objects generated during the work from falling from high places. As such a curing device, for example, a device shown in Patent Document 1 is known. This curing device cures all around the roof of the building.

特開2000−160827号公報JP 2000-160827 A

ここで、作業を行っていない時や強風時には、養生装置による養生を撤去することが求められるが、上述のような養生装置では、養生を撤去するのに手間がかかるという問題があった。また、養生は全周にわたって行われている必要はなく、作業が行われている場所に必要に応じて養生することが求められていた。   Here, when the work is not performed or when the wind is strong, it is required to remove the curing by the curing device. However, in the above-described curing device, there is a problem that it takes time to remove the curing. Curing does not need to be performed all around, and it is required that the place where the work is performed be cured as necessary.

本発明は、このような課題を解決するためになされたものであり、必要な場所及びタイミングで容易に養生及びその撤去を行うことができる養生装置を提供することを目的とする。   The present invention has been made in order to solve such a problem, and an object of the present invention is to provide a curing device that can easily perform curing and removal at a necessary place and timing.

本発明に係る養生装置は、上下方向に延びると共に水平方向に互いに離間する一対の柱部と、一対の柱部間に架け渡され、上下方向に広がる第1のネットと、第1のネットの上縁部を上下方向に昇降させる昇降機構と、一対の柱部を下端側でそれぞれ支持すると共に、水平方向へ移動可能な一対の移動体と、を備える。   The curing device according to the present invention includes a pair of pillars extending in the vertical direction and separated from each other in the horizontal direction, a first net extending between the pair of pillars, and extending in the vertical direction; It has an elevating mechanism for raising and lowering the upper edge in the vertical direction, and a pair of moving bodies that support the pair of pillars at the lower ends and that can move in the horizontal direction.

本発明に係る養生装置は、上下方向に延びると共に水平方向に互いに離間する一対の柱部と、一対の柱部間に架け渡され、上下方向に広がる第1のネットとを備えている。従って、養生を行うべき場所に一対の柱部を設置することで、当該場所に対して第1のネットで養生することができる。ここで、養生装置は、第1のネットの上縁部を上下方向に昇降させる昇降機構を備えている。従って、作業完了時や強風時には昇降機構を用いて第1のネットの上縁部を降ろし、容易に養生を撤去することができ、必要な時には昇降機構を用いて第1のネットの上縁部を上げて容易に養生することができる。また、養生装置は、一対の柱部を下端側でそれぞれ支持すると共に、水平方向へ移動可能な一対の移動体を備えている。従って、所定の作業場所での作業が完了した場合は、移動体が水平方向へ移動することによって、異なる作業場所で容易に養生を行うことができる。以上より、必要な場所及びタイミングで容易に養生及びその撤去を行うことができる。   The curing device according to the present invention includes a pair of pillars extending in the vertical direction and separated from each other in the horizontal direction, and a first net extending between the pair of pillars and extending in the vertical direction. Therefore, by installing a pair of pillars at a place where curing is to be performed, the place can be cured with the first net. Here, the curing device includes an elevating mechanism for elevating the upper edge of the first net in the vertical direction. Therefore, when the work is completed or when the wind is strong, the upper edge of the first net can be lowered by using the lifting mechanism, and the curing can be easily removed. Can be easily cured. In addition, the curing device includes a pair of moving bodies that support the pair of pillars at the lower ends, respectively, and that can move in the horizontal direction. Therefore, when the work in the predetermined work place is completed, the moving body moves in the horizontal direction, so that curing can be easily performed in different work places. As described above, curing and removal can be easily performed at a necessary place and timing.

また、本発明に係る養生装置において、移動体は、設置面上に設けられたレールに沿って移動可能であってよい。このような構成によれば、シンプルな構成にて、移動体がレールに沿って容易に移動を行うことができる。   In the curing device according to the present invention, the moving body may be movable along a rail provided on the installation surface. According to such a configuration, the moving body can easily move along the rail with a simple configuration.

また、本発明に係る養生装置において、昇降機構は、第1のネットの横縁部を支持し、第1のネットの上縁部の昇降をガイドするガイドロープを備えてよい。昇降機構がガイドロープを備えることで、第1のネットの横縁部及び上縁部での張力を安定させた状態で昇降を行うことができる。   In the curing device according to the present invention, the elevating mechanism may include a guide rope that supports the lateral edge of the first net and guides the upper edge of the first net to elevate. Since the elevating mechanism includes the guide rope, it is possible to perform elevating and lowering in a state where the tension at the lateral edge and the upper edge of the first net is stabilized.

また、本発明に係る養生装置は、第1のネットの下側に設けられ、一対の移動体間に架け渡される第2のネットを備えてよい。養生装置が第2のネットを備えることで、第1のネットの下側からの落下物の落下をより確実に防止することができる。   Further, the curing device according to the present invention may include a second net provided below the first net and bridged between a pair of moving bodies. Since the curing device includes the second net, falling objects falling from below the first net can be more reliably prevented.

また、本発明に係る養生装置は、移動体を設置面側に固定する固定部材を備えてよい。これによって、作業中に固定部材によって移動体を設置面側に固定することで、安全性を向上できる。   Further, the curing device according to the present invention may include a fixing member for fixing the moving body to the installation surface side. Thereby, the safety can be improved by fixing the moving body to the installation surface side by the fixing member during the work.

また、本発明に係る養生装置において、レールは、ゴンドラレールによって構成されてよい。これによって、移動体を移動させるためのレールを新たに設置する必要がなく、建物のメンテナンス等に用いられる既設のゴンドラレールを使用することができる。   In the curing device according to the present invention, the rail may be configured by a gondola rail. Thus, there is no need to newly install a rail for moving the moving body, and an existing gondola rail used for maintenance of a building or the like can be used.

本発明によれば、必要な場所及びタイミングで容易に養生及びその撤去を行うことができる。   ADVANTAGE OF THE INVENTION According to this invention, curing and its removal can be performed easily at a required place and timing.

図1は、本発明の実施形態に係る養生装置の設置状態の一例を示す図である。FIG. 1 is a diagram illustrating an example of an installation state of a curing device according to an embodiment of the present invention. 図2は、本発明の実施形態に係る養生装置の正面図である。FIG. 2 is a front view of the curing device according to the embodiment of the present invention. 図3は、本発明に実施形態に係る養生装置の側面図である。FIG. 3 is a side view of the curing device according to the embodiment of the present invention. 図4は、図2に示す養生装置の下端部付近の拡大図である。FIG. 4 is an enlarged view near the lower end of the curing device shown in FIG. 図5は、図2に示す養生装置の上端部付近の拡大図である。FIG. 5 is an enlarged view near the upper end of the curing device shown in FIG. 図6は、図3に示す養生装置の下端部付近の拡大図である。FIG. 6 is an enlarged view near the lower end of the curing device shown in FIG. 図7は、各固定部材を横方向から見た拡大図である。FIG. 7 is an enlarged view of each fixing member viewed from the lateral direction.

以下、本発明の実施形態について、図面を参照して詳細に説明する。なお、図面において、同一または同等の要素には同じ符号を付し、重複する説明を省略する。   Hereinafter, embodiments of the present invention will be described in detail with reference to the drawings. In the drawings, the same or equivalent elements have the same reference characters allotted, and overlapping description will be omitted.

図1は、本発明の実施形態に係る養生装置の設置状態の一例を示す図である。図1は、ビルの屋上FLを上方から見た図である。図1に示すように、養生装置100は、ビルの屋上FLなどのような高所に、構造物を設ける場合に用いられる。制震装置などのように高さ方向に一定以上の大きさを有する構造物をビルの屋上FLに設ける際に、養生装置100で垂直養生を行うことで、高所作業中に発生する落下物がビルの屋上FLから落下することを防止する。養生装置100は、ビルの屋上FLに設けられた一対のレール110,110上に移動可能に設けられている。   FIG. 1 is a diagram illustrating an example of an installation state of a curing device according to an embodiment of the present invention. FIG. 1 is a diagram of a roof FL of a building viewed from above. As shown in FIG. 1, the curing device 100 is used when a structure is provided at a high place such as a rooftop FL of a building. When a structure having a certain size or more in the height direction, such as a vibration damping device, is provided on the rooftop FL of a building, by using the curing device 100 to perform vertical curing, falling objects generated during work at a high place. From falling off the rooftop FL of the building. The curing device 100 is movably provided on a pair of rails 110 provided on a rooftop FL of a building.

図2は、本発明の実施形態に係る養生装置の正面図である。図3は、本発明に実施形態に係る養生装置の側面図である。図4は、図2に示す養生装置の下端部付近の拡大図である。図5は、図2に示す養生装置の上端部付近の拡大図である。図6は、図3に示す養生装置の下端部付近の拡大図である。図2及び図3に示すように、養生装置100は、一対の柱部2A,2Bと、一対の移動体3A,3Bと、連結部材4と、第1のネット6と、第2のネット7と、昇降機構8と、を備える。なお、養生装置100に対して養生対象となる構造物Sが配置される側を「後面側」と称し、それと反対側を「前面側」と称する。図2では、紙面手前側が「前面側」に該当する。   FIG. 2 is a front view of the curing device according to the embodiment of the present invention. FIG. 3 is a side view of the curing device according to the embodiment of the present invention. FIG. 4 is an enlarged view near the lower end of the curing device shown in FIG. FIG. 5 is an enlarged view near the upper end of the curing device shown in FIG. FIG. 6 is an enlarged view near the lower end of the curing device shown in FIG. As shown in FIGS. 2 and 3, the curing device 100 includes a pair of pillars 2 </ b> A, 2 </ b> B, a pair of moving bodies 3 </ b> A, 3 </ b> B, a connecting member 4, a first net 6, and a second net 7. And a lifting mechanism 8. The side on which the structure S to be cured is disposed with respect to the curing device 100 is referred to as a “rear side”, and the opposite side is referred to as a “front side”. In FIG. 2, the front side of the drawing corresponds to the “front side”.

柱部2A,2Bは、上下方向に延びると共に水平方向に互いに離間する部材である。なお、柱部2A,2Bが互いに離間する水平方向を「横方向」として以降の説明を行う。柱部2A,2Bは、例えば円柱状の部材によって構成されているが、形状は特に限定されない。柱部2A,2Bの高さは、少なくとも後面側に設けられる構造物Sの高さよりも高い。柱部2A,2Bの上端側には、他の部分に比して径が小さい状態で上下方向に延びる小径部11と、小径部11の上端から横方向内側へ延びる屈曲部12と、が設けられる(特に、図5参照)。小径部11と屈曲部12との間の角部には、滑車14を支持する支持部13が設けられる。柱部2A,2Bの下端部は、移動体3A,3Bにそれぞれ連結される。   The columns 2A and 2B are members that extend in the up-down direction and are separated from each other in the horizontal direction. The horizontal direction in which the pillars 2A and 2B are separated from each other will be referred to as the "lateral direction" and the following description will be made. The column portions 2A and 2B are formed of, for example, columnar members, but the shape is not particularly limited. The height of the pillars 2A, 2B is at least higher than the height of the structure S provided on the rear side. At the upper ends of the pillars 2A and 2B, there are provided a small-diameter portion 11 extending vertically in a state in which the diameter is smaller than other portions, and a bent portion 12 extending laterally inward from the upper end of the small-diameter portion 11. (Particularly, see FIG. 5). At a corner between the small diameter portion 11 and the bent portion 12, a support portion 13 for supporting the pulley 14 is provided. The lower ends of the pillars 2A, 2B are connected to the moving bodies 3A, 3B, respectively.

移動体3A,3Bは、柱部2A,2Bを下端側でそれぞれ支持すると共に、横方向(水平方向)へ移動可能に構成されている。本実施形態では、移動体3A,3Bは、設置面SF(図3参照)上に設けられたレール110,110に沿って移動可能である。移動体3A,3Bは、下端側に設けられる下部フレーム21と、下部フレーム21の上方に設けられる上部フレーム22と、を備える。上部フレーム22は、柱部2A,2Bの下端より上方の位置を取り囲むように矩形環状に構成されている。上部フレーム22の角部のうち、前面側であって横方向外側に形成される角部には、第2のネット7を固定するための支持柱23が立設される。   The moving bodies 3A and 3B support the pillars 2A and 2B at the lower ends, respectively, and are configured to be movable in a horizontal direction (horizontal direction). In the present embodiment, the moving bodies 3A and 3B are movable along the rails 110 provided on the installation surface SF (see FIG. 3). The moving bodies 3A and 3B include a lower frame 21 provided on the lower end side and an upper frame 22 provided above the lower frame 21. The upper frame 22 is formed in a rectangular ring shape so as to surround a position above the lower ends of the pillars 2A and 2B. Of the corners of the upper frame 22, support pillars 23 for fixing the second net 7 are erected at corners formed on the front side and laterally outward.

図4及び図6に示すように、下部フレーム21は、柱部2A,2Bの下端の位置に設けられる矩形環状の部材である。下部フレーム21は、一対のレール110,110と上方で対向する位置において、横方向に延びる一対の梁部材24,24と、前後方向に延びて梁部材24,24を横方向における両端部で連結する一対の梁部材26,26と、を備えている。なお、梁部材24,24,26,26で囲まれる部分の内側には、柱部2A,2Bの下端を固定するための梁部材(不図示)が設けられている。また、下部フレーム21と上部フレーム22は、上下方向に延びる連結材25,25で連結されている。   As shown in FIGS. 4 and 6, the lower frame 21 is a rectangular ring-shaped member provided at the lower end of the pillars 2A, 2B. The lower frame 21 is connected to a pair of beam members 24, 24 extending in the lateral direction at positions facing the pair of rails 110, 110 at the upper side, and to the beam members 24, 24 extending in the front-rear direction at both ends in the lateral direction. And a pair of beam members 26, 26. A beam member (not shown) for fixing the lower ends of the columns 2A and 2B is provided inside the portion surrounded by the beam members 24, 24, 26 and 26. The lower frame 21 and the upper frame 22 are connected by connecting members 25, 25 extending in the up-down direction.

下部フレーム21の梁部材24,24には、レール110,110にガイドされて当該レール110,110に沿って移動可能な移動部27,27が横方向に離間するように一対設けられている。移動部27,27は、例えばチルローラによって構成される。   The beam members 24 of the lower frame 21 are provided with a pair of moving parts 27, 27 guided by the rails 110, 110 and movable along the rails 110, 110 so as to be separated in the lateral direction. The moving units 27, 27 are constituted by, for example, chill rollers.

養生装置100は、移動体3A,3Bを設置面SF側に固定する固定部材30を備える。固定部材30は、下部フレーム21の梁部材24,24に設けられている。具体的には、固定部材30は、下部フレーム21をレール110から離間させる押上部31と、下部フレーム21とレール110の上側のフランジ部110aと連結させる第1の連結部32と、下部フレーム21とレール110とを連結させる第2の連結部33と、を備えている。   The curing device 100 includes a fixing member 30 for fixing the moving bodies 3A and 3B to the installation surface SF side. The fixing member 30 is provided on the beam members 24, 24 of the lower frame 21. Specifically, the fixing member 30 includes a push-up portion 31 for separating the lower frame 21 from the rail 110, a first connecting portion 32 for connecting the lower frame 21 to the upper flange portion 110 a of the rail 110, and a lower frame 21. And a second connecting portion 33 for connecting the rail 110 to the rail 110.

図4及び図7(a)に示すように、押上部31は、下部フレーム21の梁部材24の横方向における両端部に設けられた取付部31aと、取付部31aに上下方向にねじ込み可能に挿入されたボルト31bと、ボルト31bの下端に設けられた脚部31cと、によって構成されている。脚部31cは、ボルト31bが取付部31aに溶接されたナット31dにねじ込まれるに従って下方へ移動し、レール110の上側のフランジ部110aの上面と当接する。脚部31cが上側のフランジ部110aに当接した状態で更にボルト31bを取付部31aのナット31dにねじ込むことで、取付部31aを介して梁部材24全体がレール110から上方へ離間する。これによって、移動部27がレール110の上側のフランジ部110aから浮くことにより、移動体3A,3Bがレール110に対して移動不能となり、実質的に移動体3A,3Bが設置面SF側に固定された状態となる。   As shown in FIGS. 4 and 7A, the push-up portion 31 is provided with mounting portions 31 a provided at both lateral ends of the beam member 24 of the lower frame 21, and can be screwed into the mounting portion 31 a in the vertical direction. It is constituted by the inserted bolt 31b and a leg 31c provided at the lower end of the bolt 31b. The leg portion 31c moves downward as the bolt 31b is screwed into the nut 31d welded to the mounting portion 31a, and contacts the upper surface of the upper flange portion 110a of the rail 110. When the bolt 31b is further screwed into the nut 31d of the mounting portion 31a while the leg portion 31c is in contact with the upper flange portion 110a, the entire beam member 24 is separated upward from the rail 110 via the mounting portion 31a. As a result, the moving part 27 floats from the upper flange part 110a of the rail 110, so that the moving bodies 3A and 3B cannot move with respect to the rail 110, and the moving bodies 3A and 3B are substantially fixed to the installation surface SF side. It will be in the state that was done.

図4及び図7(b)に示すように、第1の連結部32は、下部フレーム21の梁部材24から前後方向に突出する取付プレート32aと、取付プレート32aに取り付けられると共にレール110と連結可能なL字金具32bと、を備えている。取付プレート32aは、上下方向に広がる板状の部材であって、梁部材24の前後方向における両側へ張り出している。L字金具32bは、取付プレート32aに接合されると共に下側へ向かってレール110へ至る位置まで延びている。また、L字金具32bは、下端部で屈曲してレール110の上側のフランジ部110aの下面と対向する位置まで回り込む屈曲部32cを備えている。屈曲部32cは、押上部31が移動部27をレール110から浮かせる前の状態では、レール110の上側のフランジ部110aの下面と離間している。しかし、押上部31が移動部27をレール110から浮かせて一定量上側へ離間させた状態では、屈曲部32cは、レール110の上側のフランジ部110aの下面と当接する。これによって、第1の連結部32がレール110と連結され、移動体3A,3Bが設置面SF側に固定される。   As shown in FIGS. 4 and 7B, the first connecting portion 32 is attached to the mounting plate 32 a protruding in the front-rear direction from the beam member 24 of the lower frame 21, and is connected to the rail 110. A possible L-shaped fitting 32b. The mounting plate 32a is a plate-shaped member that expands in the vertical direction, and protrudes to both sides in the front-rear direction of the beam member 24. The L-shaped fitting 32b is joined to the mounting plate 32a and extends downward to a position reaching the rail 110. The L-shaped bracket 32b has a bent portion 32c which bends at a lower end and turns around to a position facing the lower surface of the upper flange portion 110a of the rail 110. The bent portion 32c is separated from the lower surface of the upper flange portion 110a of the rail 110 before the push-up portion 31 raises the moving portion 27 from the rail 110. However, in a state where the push-up portion 31 lifts the moving portion 27 from the rail 110 and separates the moving portion 27 upward by a certain amount, the bent portion 32c contacts the lower surface of the upper flange portion 110a of the rail 110. Thereby, the first connecting portion 32 is connected to the rail 110, and the moving bodies 3A and 3B are fixed to the installation surface SF side.

図4及び図7(c)に示すように、第2の連結部33は、下部フレーム21の梁部材24の上面に設けられて前後方向に延びる連結部材33aと、レール110の下側のフランジ部110bの下面側に設けられて前後方向に延びる連結部材33bと、上下方向に延びて連結部材33a及び連結部材33b同士を連結するかんざしボルト33cと、を備えている。連結部材33aは梁部材24から前後方向に張り出しており、連結部材33bはレール110から前後方向に張り出している。かんざしボルト33cは、連結部材33a及び連結部材33bの前後方向の張り出し部分に連結される。連結部材33bは、押上部31が移動部27をレール110から浮かせる前の状態では、レール110の下側のフランジ部110bの下面と離間している。しかし、押上部31が移動部27をレール110から浮かせて一定量上側へ離間させた状態では、連結部材33bは、レール110の下側のフランジ部110bの下面と当接する。これによって、第2の連結部33がレール110と連結され、移動体3A,3Bが設置面SF側に固定される。   As shown in FIGS. 4 and 7C, the second connecting portion 33 includes a connecting member 33 a provided on the upper surface of the beam member 24 of the lower frame 21 and extending in the front-rear direction, and a lower flange of the rail 110. The connecting member 33b is provided on the lower surface side of the portion 110b and extends in the front-rear direction. The connecting member 33b extends in the vertical direction and connects the connecting members 33a and 33b. The connecting member 33a projects in the front-rear direction from the beam member 24, and the connecting member 33b projects in the front-rear direction from the rail 110. The hairpin bolt 33c is connected to the front and rear portions of the connecting members 33a and 33b. The connection member 33b is separated from the lower surface of the flange 110b on the lower side of the rail 110 in a state before the push-up portion 31 raises the moving portion 27 from the rail 110. However, in a state where the push-up portion 31 lifts the moving portion 27 from the rail 110 and separates the moving portion 27 upward by a certain amount, the connecting member 33b contacts the lower surface of the lower flange portion 110b of the rail 110. Thereby, the second connecting portion 33 is connected to the rail 110, and the moving bodies 3A and 3B are fixed to the installation surface SF side.

図2に示すように、第1のネット6は、柱部2A,2B間に架け渡され、上下方向に広がる網状部材である。第1のネット6の横方向の大きさ(すなわち横縁部6c,6c間の距離)は、構造物Sの横方向の大きさよりも大きい。第1のネット6の上縁部6aは、(最も高い位置に配置された状態で)横方向における中央位置付近のたわみを考慮しても、構造物Sよりも高い位置に配置される。第1のネット6の下縁部6bは、連結部材4に固定されている。   As shown in FIG. 2, the first net 6 is a net-like member that extends between the pillars 2A and 2B and that extends in the vertical direction. The lateral size of the first net 6 (that is, the distance between the lateral edges 6c, 6c) is larger than the lateral size of the structure S. The upper edge portion 6a of the first net 6 is arranged at a position higher than the structure S even in consideration of the deflection near the center position in the horizontal direction (in a state of being arranged at the highest position). The lower edge 6 b of the first net 6 is fixed to the connecting member 4.

第2のネット7は、第1のネット6の下側に設けられ、一対の移動体3A,3B間に架け渡されると共に上下方向に広がる網状部材である。第2のネット7の横縁部は、移動体3A,3Bの支持柱23に固定される。また、第2のネット7の上縁部7aは、支持柱23の上端部の高さに設定されている。第2のネット7の上縁部7a付近の一部は、第1のネット6の下縁部6b付近の一部と重なりあっている。第2のネット7の下縁部7bは、第1のネット6の下縁部6bよりも下側に配置される。第2のネット7の下縁部7bは、レール110の下端部に至る位置まで延びている。   The second net 7 is a net-like member provided below the first net 6 and spanned between the pair of moving bodies 3A and 3B and spread in the up-down direction. The lateral edges of the second net 7 are fixed to support columns 23 of the moving bodies 3A and 3B. The upper edge 7a of the second net 7 is set at the height of the upper end of the support column 23. A portion near the upper edge 7a of the second net 7 overlaps a portion near the lower edge 6b of the first net 6. The lower edge 7b of the second net 7 is disposed below the lower edge 6b of the first net 6. The lower edge 7b of the second net 7 extends to a position reaching the lower end of the rail 110.

次に、図2、図4及び図5を参照して、第1のネット6を昇降させる昇降機構8の構成について説明する。図2に示すように、昇降機構8は、第1のネット6の上縁部6aを支持するロープ41と、ロープ41を柱部2A,2B側で支持すると共に柱部2A,2Bに沿って上下方向に延びる長さ調整ロープ42,42と、長さ調整ロープ42,42の長さを調整する長さ調整部43,43と、第1のネット6の横縁部6c,6cを支持し、第1のネット6の上縁部6aの昇降をガイドするガイドロープ44,44と、を備える。   Next, with reference to FIGS. 2, 4, and 5, a configuration of the lifting mechanism 8 that raises and lowers the first net 6 will be described. As shown in FIG. 2, the lifting mechanism 8 includes a rope 41 that supports the upper edge 6 a of the first net 6, the rope 41 that is supported on the columns 2 </ b> A, 2 </ b> B, and along the columns 2 </ b> A, 2 </ b> B. The length adjusting ropes 42, 42 extending in the vertical direction, the length adjusting ropes 43, 43 for adjusting the length of the length adjusting ropes 42, 42, and the lateral edges 6c, 6c of the first net 6 are supported. And a guide rope 44 for guiding the upper edge 6a of the first net 6 up and down.

図2及び図5に示すように、ロープ41は、柱部2A,2Bとの間で横方向に延びている。ロープ41は、一定間隔で第1のネット6の上縁部6aに設けられたカラビナ46を介して、第1のネット6の上縁部6aを支持している。ロープ41の横方向における両端部は、それぞれターンバックル47及びシャックル48を介して、長さ調整ロープ42に連結されている(特に図5参照)。   As shown in FIG. 2 and FIG. 5, the rope 41 extends in the lateral direction between the pillars 2A and 2B. The rope 41 supports the upper edge 6a of the first net 6 via a carabiner 46 provided on the upper edge 6a of the first net 6 at regular intervals. Both ends of the rope 41 in the lateral direction are connected to the length adjusting rope 42 via a turnbuckle 47 and a shackle 48, respectively (see especially FIG. 5).

図5に示すように、長さ調整ロープ42は、シャックル48から横方向外側へ延びる(当該部分を部分42Aと称する)と共に、柱部2A(2B)の支持部13で支持される滑車14で支持されて、下方へ向かって延びる。図4に示すように、長さ調整ロープ42の下端は、長さ調整部43に連結されている。長さ調整部43は、例えば、長さ調整ロープ42の巻取り及び巻き戻しを行うウィンチによって構成されている。ウィンチは、作業者の手動で駆動するものであってもよくモータ等で駆動するものであってもよい。長さ調整部43が長さ調整ロープ42の巻き戻しを行うと、長さ調整ロープ42が繰出されて、部分42Aの長さが長くなる。長さ調整部43が長さ調整ロープ42の巻き取りを行うと、長さ調整ロープ42が巻き取られて、部分42Aの長さが短くなる。   As shown in FIG. 5, the length adjusting rope 42 extends laterally outward from the shackle 48 (the portion is referred to as a portion 42A) and is supported by the pulley 14 supported by the support portion 13 of the column 2A (2B). It is supported and extends downward. As shown in FIG. 4, the lower end of the length adjusting rope 42 is connected to the length adjusting unit 43. The length adjustment unit 43 is configured by, for example, a winch that winds and unwinds the length adjustment rope 42. The winch may be driven manually by an operator or may be driven by a motor or the like. When the length adjusting section 43 rewinds the length adjusting rope 42, the length adjusting rope 42 is extended, and the length of the portion 42A is increased. When the length adjusting section 43 winds up the length adjusting rope 42, the length adjusting rope 42 is wound up, and the length of the portion 42A is shortened.

図2、図4及び図5に示すように、ガイドロープ44は、柱部2A,2Bの上端と移動体3A,3Bとの間で上下方向に延びている。ガイドロープ44は、一定間隔で第1のネット6の横縁部6cに設けられたカラビナ51を介して、第1のネット6の横縁部6cを支持している。ガイドロープ44の上端部は、屈曲部12の先端にシャックル52を介して連結されている(特に図5参照)。ガイドロープ44の下端部は、上部フレーム22にターンバックル53を介して連結されている(特に図4参照)。ガイドロープ44は、長さ調整部43とロープ41とを連結するシャックル48に挿通されている。   As shown in FIGS. 2, 4 and 5, the guide rope 44 extends vertically between the upper ends of the pillars 2A and 2B and the moving bodies 3A and 3B. The guide rope 44 supports the lateral edge 6c of the first net 6 via a carabiner 51 provided on the lateral edge 6c of the first net 6 at regular intervals. The upper end of the guide rope 44 is connected to the tip of the bent portion 12 via a shackle 52 (see particularly FIG. 5). The lower end of the guide rope 44 is connected to the upper frame 22 via a turnbuckle 53 (see particularly FIG. 4). The guide rope 44 is inserted into a shackle 48 that connects the length adjustment unit 43 and the rope 41.

昇降機構8による、第1のネット6の昇降動作について説明する。まず、図2においてロープ41が実線で示されている状態が、第1のネット6の上縁部6aが最も高い位置に配置されている状態である。当該状態から、長さ調整部43で長さ調整ロープ42を巻き戻すと、長さ調整ロープ42が繰出される。ここで、ガイドロープ44は、長さ調整部43とロープ41とを連結するシャックル48に挿通されている。ロープ41の両端部の横方向における位置は、シャックル48及びガイドロープ44の連結部分で略一定となる。従って、長さ調整ロープ42が繰出されると、ロープ41のたわみは変化せず、張力が略一定に保たれた状態が維持される。一方、長さ調整ロープ42の部分42Aの長さが長くなる。すなわち、シャックル48がガイドロープ44にガイドされて下方へ移動すると共に、カラビナ51もガイドロープ44にガイドされて下方へ移動する。これによって、ロープ41及び第1のネット6の上縁部6aは、張力が略一定に保たれたままで、下方へ移動する(図2に示す二点鎖線MPを参照)。第1のネット6の横縁部6cもガイドロープ44でガイドされた状態で安定した状態で下方へ移動することができる。   The lifting operation of the first net 6 by the lifting mechanism 8 will be described. First, the state in which the rope 41 is shown by a solid line in FIG. 2 is a state in which the upper edge 6a of the first net 6 is arranged at the highest position. In this state, when the length adjusting rope 42 is rewound by the length adjusting unit 43, the length adjusting rope 42 is extended. Here, the guide rope 44 is inserted through a shackle 48 that connects the length adjustment unit 43 and the rope 41. The positions of both ends of the rope 41 in the lateral direction are substantially constant at the connecting portion of the shackle 48 and the guide rope 44. Therefore, when the length adjustment rope 42 is extended, the deflection of the rope 41 does not change, and the state in which the tension is kept substantially constant is maintained. On the other hand, the length 42A of the length adjustment rope 42 becomes longer. That is, the shackle 48 moves downward while being guided by the guide rope 44, and the carabiner 51 also moves downward while being guided by the guide rope 44. As a result, the rope 41 and the upper edge 6a of the first net 6 move downward while the tension is kept substantially constant (see the two-dot chain line MP shown in FIG. 2). The lateral edge 6c of the first net 6 can also move downward in a stable state while being guided by the guide ropes 44.

一方、長さ調整部43で長さ調整ロープ42を巻き取ると、ロープ41のたわみは変化しない一方、長さ調整ロープ42の部分42Aの長さが短くなる。すなわち、シャックル48がガイドロープ44にガイドされて上方へ移動すると共に、カラビナ51もガイドロープ44にガイドされて上方へ移動する。これによって、ロープ41及び第1のネット6の上縁部6aは、張力が略一定に保たれたままで、上方へ移動する。第1のネット6の横縁部6cもガイドロープ44でガイドされた状態で安定した状態で上方へ移動することができる。   On the other hand, when the length adjusting rope 43 is wound around the length adjusting rope 42, the deflection of the rope 41 does not change, but the length 42A of the length adjusting rope 42 becomes shorter. That is, the shackle 48 moves upward by being guided by the guide rope 44, and the carabiner 51 also moves upward by being guided by the guide rope 44. Thereby, the rope 41 and the upper edge 6a of the first net 6 move upward while the tension is kept substantially constant. The lateral edge 6c of the first net 6 can also move upward in a stable state while being guided by the guide rope 44.

次に、本実施形態に係る養生装置100の作用・効果について説明する。   Next, the operation and effect of the curing device 100 according to the present embodiment will be described.

本実施形態に係る養生装置100は、上下方向に延びると共に水平方向に互いに離間する柱部2A,2Bと、柱部2A,2B間に架け渡され、上下方向に広がる第1のネット6とを備えている。従って、養生を行うべき場所に柱部2A,2Bを設置することで、当該場所に対して第1のネット6で養生することができる。ここで、養生装置100は、第1のネット6の上縁部6aを上下方向に昇降させる昇降機構8を備えている。従って、作業完了時や強風時には昇降機構8を用いて第1のネット6の上縁部6aを降ろし、容易に養生を撤去することができ、必要な時には昇降機構を用いて第1のネットの上縁部を上げて容易に養生することができる。また、養生装置100は、柱部2A,2Bを下端側でそれぞれ支持すると共に、水平方向へ移動可能な移動体3A,3Bを備えている。従って、所定の作業場所での作業が完了した場合は、移動体3A,3Bが水平方向へ移動することによって、異なる作業場所で容易に養生を行うことができる。以上より、必要な場所及びタイミングで容易に養生及びその撤去を行うことができる。   The curing device 100 according to the present embodiment includes the pillars 2A and 2B extending in the vertical direction and separated from each other in the horizontal direction, and the first net 6 bridged between the pillars 2A and 2B and extending in the vertical direction. Have. Therefore, by setting the pillar portions 2A and 2B at a place where curing is to be performed, the first net 6 can cure the place. Here, the curing device 100 includes an elevating mechanism 8 that moves the upper edge 6a of the first net 6 up and down. Therefore, when the operation is completed or when the wind is strong, the upper edge portion 6a of the first net 6 can be lowered using the lifting mechanism 8 and the curing can be easily removed. When necessary, the first net 6 can be removed using the lifting mechanism. The upper edge can be raised for easy curing. In addition, the curing device 100 includes moving bodies 3A and 3B that support the pillars 2A and 2B at the lower ends, respectively, and that can move in the horizontal direction. Therefore, when the work at the predetermined work place is completed, the moving bodies 3A and 3B move in the horizontal direction, so that curing can be easily performed at different work places. As described above, curing and removal can be easily performed at a necessary place and timing.

例えば、図1に示すように、区画A〜Fに制震装置を設ける場合、養生装置100を用いて次のような養生を行うことができる。例えば、区画Aで設置作業を行う場合、区画Aの手前側(位置PA)に養生装置100を配置する。区画Bで設置作業を行う場合、区画Bの手前側に養生装置100を配置する。区画Cで設置作業を行う場合、区画Cの手前側(位置PB)に養生装置100を配置すると共に、区画Cの横側(位置PC)に養生装置100を配置する。区画Dで設置作業を行う場合、区画Dの手前側(位置PE)に養生装置100を配置すると共に、区画Dの横側(位置PD)に養生装置100を配置する。区画Eで設置作業を行う場合、区画Eの手前側に養生装置100を配置する。区画Fで設置作業を行う場合、区画Fの手前側(位置PF)に養生装置100を配置する。   For example, as shown in FIG. 1, when the vibration control devices are provided in the sections A to F, the following curing can be performed using the curing device 100. For example, when the installation work is performed in the section A, the curing device 100 is arranged in front of the section A (position PA). When the installation work is performed in the section B, the curing device 100 is arranged in front of the section B. When the installation work is performed in the section C, the curing device 100 is arranged on the near side (position PB) of the section C, and the curing device 100 is arranged on the side (position PC) of the section C. When the installation work is performed in the section D, the curing device 100 is arranged on the near side (position PE) of the section D, and the curing device 100 is arranged on the side (position PD) of the section D. When the installation work is performed in the section E, the curing device 100 is arranged in front of the section E. When the installation work is performed in the section F, the curing device 100 is arranged on the near side (position PF) of the section F.

図1に示すような例では、矩形状に設置されたレール110の上辺側(図1における紙面上側の辺)に一機の養生装置100が設置されている場合、移動体3A,3Bの移動によって、区画Aの設置作業が終わったら区画Bへ移動することで当該区画Bの養生を行い、区画Bの設置作業が終わったら区画Cへ移動することで当該区画Cの養生を行うことができる。また、レール110の下辺側(図1における紙面下側の辺)に一機の養生装置100が設置されている場合、移動体3A,3Bの移動によって、区画Dの設置作業が終わったら区画Eへ移動することで当該区画Eの養生を行い、区画Eの設置作業が終わったら区画Fへ移動することで当該区画Fの養生を行うことができる。なお、レール110の左右の辺(図1における紙面左右側の辺)で一機の養生装置100を用いる場合、区画Cでの設置作業が終わって区画Dの設置作業を行うときには、位置PCに配置されている養生装置100を解体して、位置PDへ養生装置100を設置する。   In the example as shown in FIG. 1, when one curing device 100 is installed on the upper side (the upper side of the paper surface in FIG. 1) of the rail 110 installed in a rectangular shape, the movement of the moving bodies 3A and 3B is performed. When the installation work of the section A is completed, the section B is cured by moving to the section B, and when the installation work of the section B is completed, the section C is cured by moving to the section C. . When one curing device 100 is installed on the lower side of the rail 110 (the lower side of the paper surface in FIG. 1), the moving of the moving bodies 3A and 3B causes the section E to be set when the installation work of the section D is completed. Then, the section E is cured by moving to the section. After the installation work of the section E is completed, the section F is cured by moving to the section F. When one curing device 100 is used on the left and right sides of the rail 110 (the left and right sides in FIG. 1), when the installation work in the section C is completed and the installation work in the section D is performed, the position PC The disposed curing device 100 is dismantled, and the curing device 100 is installed at the position PD.

また、本実施形態に係る養生装置100において、移動体3A,3Bは、設置面SF上に設けられたレール110に沿って移動可能である。このような構成によれば、シンプルな構成にて、移動体3A,3Bがレール110に沿って容易に移動を行うことができる。   In the curing device 100 according to the present embodiment, the moving bodies 3A and 3B can move along the rail 110 provided on the installation surface SF. According to such a configuration, the moving bodies 3A and 3B can easily move along the rail 110 with a simple configuration.

また、本実施形態に係る養生装置100において、昇降機構8は、第1のネット6の横縁部6cを支持し、第1のネット6の上縁部6aの昇降をガイドするガイドロープ44を備えている。昇降機構8がガイドロープ44を備えることで、第1のネット6の横縁部6c及び上縁部6aでの張力を安定させた状態で昇降を行うことができる。例えば、上縁部6aを降ろすに伴って当該上縁部6aに作用する張力が減少してたわむような場合、風が吹いたときに第1のネット6がなびくことによって、不要な力が作用してしまう。一方、昇降状態に関わらず横縁部6c及び上縁部6aでの張力が安定している場合、風になびくことを防止することができる。   In the curing device 100 according to the present embodiment, the elevating mechanism 8 supports the lateral edge 6c of the first net 6 and guides the guide rope 44 that guides the elevation of the upper edge 6a of the first net 6. Have. Since the elevating mechanism 8 includes the guide rope 44, the elevating mechanism 8 can perform elevating and lowering with the tension at the lateral edge 6c and the upper edge 6a of the first net 6 being stabilized. For example, in a case where the tension acting on the upper edge portion 6a is reduced as the upper edge portion 6a is lowered and the upper edge portion 6a is bent, unnecessary force is exerted by the first net 6 fluttering when wind blows. Resulting in. On the other hand, when the tension at the lateral edge 6c and the upper edge 6a is stable regardless of the elevating state, it is possible to prevent the wind from flying.

また、本実施形態に係る養生装置100は、第1のネット6の下側に設けられ、一対の移動体3A,3Bに架け渡される第2のネット7を備えている。養生装置100が第2のネット7を備えることで、第1のネット6の下側からの落下物の落下をより確実に防止することができる。   In addition, the curing device 100 according to the present embodiment includes a second net 7 provided below the first net 6 and bridged between the pair of moving bodies 3A and 3B. Since the curing device 100 includes the second net 7, falling objects falling from below the first net 6 can be more reliably prevented.

また、本実施形態に係る養生装置100は、移動体3A,3Bを設置面SF側に固定する固定部材30を備えている。これによって、作業中に固定部材30によって移動体3A,3Bを設置面SF側に固定することで、安全性を向上できる。   In addition, the curing device 100 according to the present embodiment includes a fixing member 30 that fixes the moving bodies 3A and 3B to the installation surface SF side. Thereby, safety can be improved by fixing the moving bodies 3A and 3B to the installation surface SF side by the fixing member 30 during the work.

本発明は、上述の実施形態に限定されるものではない。例えば、上述の柱部及び移動体の形状等は一例にすぎず、適宜変更してもよい。   The present invention is not limited to the above embodiment. For example, the shapes and the like of the pillars and the moving body are merely examples, and may be changed as appropriate.

また、移動体は、レールに沿って移動するものでなくてもよく、例えば設置面SF上を走行可能な車輪とモータを有するものであってもよい。また、レールは、施工時において設置面SF上に新たに設置するものであってよい。あるいは、レールは新たに設置するものでなくともよい。例えば、レールは、高層建物のメンテナンス(窓ふき、塗装など)に用いられるゴンドラレールを利用してもよい。これによって、移動体を移動させるためのレールを新たに設置する必要がなく、既設のゴンドラレールを使用することができる。   In addition, the moving body does not have to move along the rail, and may have, for example, a wheel and a motor that can travel on the installation surface SF. In addition, the rail may be newly installed on the installation surface SF at the time of construction. Alternatively, the rails need not be newly installed. For example, the rail may use a gondola rail used for maintenance (window cleaning, painting, etc.) of a high-rise building. Thus, it is not necessary to newly install a rail for moving the moving body, and the existing gondola rail can be used.

また、昇降機構は上述のような構成に限定されない。例えば、ガイドロープが設けられておらず、長さ調整ロープの巻きもどすことに伴い、第1のネットの上縁部がたわみながら降ろされてもよい。   Further, the lifting mechanism is not limited to the above-described configuration. For example, the guide rope may not be provided, and the upper edge of the first net may be lowered while bending the length adjusting rope.

2A,2B…柱部、3A,3B…移動体、6…第1のネット、7…第2のネット、8…昇降機構、30…固定部材、44…ガイドロープ、100…養生装置、110…レール。
2A, 2B: pillar portion, 3A, 3B: moving body, 6: first net, 7: second net, 8: elevating mechanism, 30: fixing member, 44: guide rope, 100: curing device, 110: rail.

Claims (4)

建築物の屋上に設けられ、ゴンドラレールによって構成されるレールと、
養生装置とを、備えた養生装置の設置構造であって、
前記養生装置は、
上下方向に延びると共に水平方向に互いに離間する一対の柱部と、
前記一対の柱部間に架け渡され、上下方向に広がる第1のネットと、
前記第1のネットの上縁部を上下方向に昇降させる昇降機構と、
前記一対の柱部を下端側でそれぞれ支持すると共に、水平方向へ移動可能な一対の移動体と、を備え、
前記昇降機構は、前記柱に沿って上下方向に延び、前記第1のネットの前記上縁部の昇降をガイドするガイド部材を備え、
前記第1のネットの前記上縁部は、前記ガイド部材にガイドされて上下方向へ移動する被ガイド部材に連結されることで、前記柱部に沿って上下方向に昇降し、
前記移動体は、前記レールに沿って移動可能である、養生装置の設置構造
Rails provided on the roof of the building and composed of gondola rails,
And a curing device , the installation structure of the curing device provided ,
The curing device,
A pair of pillars extending vertically and separated from each other horizontally,
A first net extending between the pair of pillars and extending in a vertical direction;
An elevating mechanism for elevating the upper edge of the first net in a vertical direction;
While supporting the pair of pillars at the lower end side, respectively, a pair of movable bodies that can move in the horizontal direction,
The elevating mechanism includes a guide member extending vertically along the pillar, and guiding the elevating of the upper edge of the first net,
The upper edge portion of the first net is connected to a guided member that moves in the up and down direction guided by the guide member, so as to move up and down along the column portion ,
The installation structure of a curing device , wherein the movable body is movable along the rail .
前記ガイド部材は、前記第1のネットの横縁部を支持する、請求項1に記載の養生装置の設置構造 The installation structure of the curing device according to claim 1, wherein the guide member supports a lateral edge of the first net. 前記第1のネットの下側に設けられ、前記一対の移動体間に架け渡される第2のネットを備える、請求項1又は2に記載の養生装置の設置構造 3. The installation structure of the curing device according to claim 1, further comprising a second net provided below the first net and bridged between the pair of moving bodies. 4. 前記移動体を設置面側に固定する固定部材を備える、請求項1〜の何れか一項に記載の養生装置の設置構造 The installation structure of the curing device according to any one of claims 1 to 3 , further comprising a fixing member that fixes the moving body to an installation surface side.
JP2015104593A 2015-05-22 2015-05-22 Installation structure of curing device Active JP6654810B2 (en)

Priority Applications (1)

Application Number Priority Date Filing Date Title
JP2015104593A JP6654810B2 (en) 2015-05-22 2015-05-22 Installation structure of curing device

Applications Claiming Priority (1)

Application Number Priority Date Filing Date Title
JP2015104593A JP6654810B2 (en) 2015-05-22 2015-05-22 Installation structure of curing device

Publications (2)

Publication Number Publication Date
JP2016217040A JP2016217040A (en) 2016-12-22
JP6654810B2 true JP6654810B2 (en) 2020-02-26

Family

ID=57580484

Family Applications (1)

Application Number Title Priority Date Filing Date
JP2015104593A Active JP6654810B2 (en) 2015-05-22 2015-05-22 Installation structure of curing device

Country Status (1)

Country Link
JP (1) JP6654810B2 (en)

Families Citing this family (1)

* Cited by examiner, † Cited by third party
Publication number Priority date Publication date Assignee Title
JP6172368B1 (en) 2016-11-07 2017-08-02 住友電気工業株式会社 Covered wire, wire with terminal, copper alloy wire, and copper alloy twisted wire

Family Cites Families (5)

* Cited by examiner, † Cited by third party
Publication number Priority date Publication date Assignee Title
JPH0743366Y2 (en) * 1990-09-12 1995-10-09 株式会社竹中工務店 Mobile safety net erection device
JP2582842Y2 (en) * 1993-08-04 1998-10-15 株式会社熊谷組 Curing net for construction work
US6186274B1 (en) * 1996-11-25 2001-02-13 Bay Nets, Inc. Safety system
JP2002061386A (en) * 2000-08-22 2002-02-28 Taisei Corp Gondola device with curing net
JP2004044185A (en) * 2002-07-11 2004-02-12 Osami Akita Safety net

Also Published As

Publication number Publication date
JP2016217040A (en) 2016-12-22

Similar Documents

Publication Publication Date Title
RU2721376C2 (en) Method for erecting elevator system, and elevator system which can be adapted to increasing building height
KR200461068Y1 (en) Device for ascending and descending of the stage establishment
CN105658562B (en) Elevator installation
JP2018070362A (en) Elevator installation method
CN113006500A (en) Safe construction installation device of full-assembly type concrete joint seismic isolation and reduction device
JP6654810B2 (en) Installation structure of curing device
JP5329031B2 (en) Elevator equipment
JP5584674B2 (en) Steel tower repair system
RU2014106376A (en) ELEVATOR SYSTEM, DOOR THRESHOLD AND METHOD FOR INSTALLING THE DOOR LADDER DOOR BLOCK
JP2008520517A (en) Installation of guide rails in elevator systems
KR101541044B1 (en) Gondola for post-tension construction
KR101773645B1 (en) Winch for construction material
KR102326391B1 (en) car for elevator system
JP5989379B2 (en) Safety fence
CN103420239B (en) Inspection apparatus for double-deck elevator
WO2015159319A1 (en) Pit entry/exit device for elevator
JP2016050102A (en) Temporary work floor device for elevator
KR200479223Y1 (en) Lift for scaffolding
CN207177305U (en) Prefabricated beam stretching jack suspension door frame
JP4817421B2 (en) Elevator rail device
JP2008063873A (en) Transfer mechanism of ceiling and execution method
JP2009220916A (en) Rope elongation adjusting device of elevator
CN104291181A (en) Guiding track support shared by elevator lift car and counter weight
JP2005350190A (en) Hoisting machine supporting device for elevator
JP5911556B1 (en) Governor rope bracing device and mounting method thereof

Legal Events

Date Code Title Description
A521 Request for written amendment filed

Free format text: JAPANESE INTERMEDIATE CODE: A821

Effective date: 20150525

A621 Written request for application examination

Free format text: JAPANESE INTERMEDIATE CODE: A621

Effective date: 20171115

A977 Report on retrieval

Free format text: JAPANESE INTERMEDIATE CODE: A971007

Effective date: 20180828

A131 Notification of reasons for refusal

Free format text: JAPANESE INTERMEDIATE CODE: A131

Effective date: 20180904

A521 Request for written amendment filed

Free format text: JAPANESE INTERMEDIATE CODE: A523

Effective date: 20181031

A131 Notification of reasons for refusal

Free format text: JAPANESE INTERMEDIATE CODE: A131

Effective date: 20190319

A521 Request for written amendment filed

Free format text: JAPANESE INTERMEDIATE CODE: A523

Effective date: 20190517

A131 Notification of reasons for refusal

Free format text: JAPANESE INTERMEDIATE CODE: A131

Effective date: 20191023

A521 Request for written amendment filed

Free format text: JAPANESE INTERMEDIATE CODE: A523

Effective date: 20191115

TRDD Decision of grant or rejection written
A01 Written decision to grant a patent or to grant a registration (utility model)

Free format text: JAPANESE INTERMEDIATE CODE: A01

Effective date: 20200107

A61 First payment of annual fees (during grant procedure)

Free format text: JAPANESE INTERMEDIATE CODE: A61

Effective date: 20200131

R150 Certificate of patent or registration of utility model

Ref document number: 6654810

Country of ref document: JP

Free format text: JAPANESE INTERMEDIATE CODE: R150

R250 Receipt of annual fees

Free format text: JAPANESE INTERMEDIATE CODE: R250