JP5528147B2 - Driving arrangement support system and driving arrangement support method - Google Patents
Driving arrangement support system and driving arrangement support method Download PDFInfo
- Publication number
- JP5528147B2 JP5528147B2 JP2010030082A JP2010030082A JP5528147B2 JP 5528147 B2 JP5528147 B2 JP 5528147B2 JP 2010030082 A JP2010030082 A JP 2010030082A JP 2010030082 A JP2010030082 A JP 2010030082A JP 5528147 B2 JP5528147 B2 JP 5528147B2
- Authority
- JP
- Japan
- Prior art keywords
- plan
- command system
- train
- train schedule
- crew
- Prior art date
- Legal status (The legal status is an assumption and is not a legal conclusion. Google has not performed a legal analysis and makes no representation as to the accuracy of the status listed.)
- Active
Links
- 238000000034 method Methods 0.000 title claims description 10
- 238000010586 diagram Methods 0.000 claims description 124
- 229910003460 diamond Inorganic materials 0.000 claims description 6
- 239000010432 diamond Substances 0.000 claims description 6
- 230000008094 contradictory effect Effects 0.000 claims description 4
- 230000005540 biological transmission Effects 0.000 description 18
- 238000012790 confirmation Methods 0.000 description 5
- 238000000605 extraction Methods 0.000 description 5
- 238000012795 verification Methods 0.000 description 5
- 238000004088 simulation Methods 0.000 description 4
- 238000007796 conventional method Methods 0.000 description 2
- 230000000694 effects Effects 0.000 description 2
- 239000000284 extract Substances 0.000 description 2
- 238000007726 management method Methods 0.000 description 2
- 230000015572 biosynthetic process Effects 0.000 description 1
- 235000012054 meals Nutrition 0.000 description 1
- 238000012797 qualification Methods 0.000 description 1
- 238000012552 review Methods 0.000 description 1
- 230000001755 vocal effect Effects 0.000 description 1
Images
Landscapes
- Train Traffic Observation, Control, And Security (AREA)
Description
本発明は、列車ダイヤの変更に際して車両運用計画および乗務員運用計画との整合を図る運転整理支援システムおよび運転整理支援方法に関する。 The present invention relates to a driving arrangement support system and a driving arrangement support method for matching a vehicle operation plan and a crew member operation plan when a train schedule is changed.
列車の運行管理では、事故や天候など様々な理由により、列車ダイヤを変更しなければならない場合が多い。しかしながら、列車ダイヤを変更する場合、その変更内容は予め車両運用指令および乗務員運用指令にも周知され、車両運用計画および乗務員運用計画の変更が可能かどうかの確認が必要となる。 In train operation management, train schedules often have to be changed for various reasons such as accidents and weather. However, when changing the train schedule, the details of the change are well known in advance in the vehicle operation command and the crew member operation command, and it is necessary to check whether the vehicle operation plan and the crew member operation plan can be changed.
特許文献1では、計画変更案を入力する複数の計画変更入力端末と、運行計画を管理する端末統括装置とを備えた列車運行管理システムにおいて、ある計画変更入力端末から計画変更案が入力されると、この計画変更案は端末統括装置へ送信され、端末統括装置では、この計画変更案の影響を受ける他の計画変更入力端末(影響端末)が特定される。そして、端末統括装置から特定された影響端末へ計画変更案が送信される。影響端末では、受信した計画変更案に基づいて、関係する指令員同士が電話等の手段により協議し、その結果、計画変更案を実際の列車運行計画に反映することが妥当であるとの結論に至った場合は、端末統括装置に対して承認応答を行う。計画変更案が妥当でないとの結論に至った場合は、端末統括装置に対して不承認応答を行う。端末統括装置では、すべての影響端末から承認を受けた場合は計画変更案に基づいて列車運行計画を変更し、一つでも不承認を受けた場合にはこの計画変更案を不承認として採用せず、その結果、計画変更案の立案から処理が繰り返される。 In Patent Document 1, in a train operation management system including a plurality of plan change input terminals for inputting a plan change plan and a terminal control device for managing the operation plan, the plan change plan is input from a certain plan change input terminal. The plan change plan is transmitted to the terminal control device, and the terminal control device identifies another plan change input terminal (influenced terminal) that is affected by the plan change plan. Then, the plan change plan is transmitted from the terminal control device to the identified affected terminal. At the affected terminal, based on the received plan change plan, it is concluded that it is appropriate that the relevant commanders discuss each other by means such as telephone and reflect the plan change plan in the actual train operation plan. If it reaches, an approval response is sent to the terminal control device. If it is concluded that the plan change plan is not appropriate, a response to the terminal control device is given. In the terminal control device, if approval is received from all affected terminals, the train operation plan is changed based on the plan change plan, and if any one is not approved, this plan change plan is not adopted as disapproval, As a result, the process is repeated from the planning change plan.
しかしながら、特許文献1に記載の従来の技術によれば、計画変更案が不承認の場合、立案を行った計画変更入力端末では、不承認という通知のみに基づいて再度計画変更案を検討する必要があり、すべての影響端末から承認される計画変更案を得るまでには時間と手間がかかるという問題点があった。 However, according to the conventional technique described in Patent Document 1, if the plan change plan is not approved, the plan change input terminal that has made the plan needs to review the plan change plan again based only on the notification of the disapproval. There is a problem that it takes time and effort to obtain a plan change plan approved from all affected terminals.
また、特許文献1では、関係する指令員同士が電話等の手段により協議し、その結果、承認または不承認を判断していることから、口頭による情報の伝達ミスが発生する可能性があるとともに時間がかかるという問題点があった。 Further, in Patent Document 1, since related commanders negotiate by means of telephone or the like and as a result determine approval or disapproval, there is a possibility that verbal information transmission errors may occur and time There was a problem that it took.
この発明は、上述の課題を解決するためになされたもので、より迅速、効率的かつ確実に列車ダイヤ変更案を確定することが可能な運転整理支援システムおよび運転整理支援方法を提供することを目的とする。 The present invention was made to solve the above-described problems, and provides a driving arrangement support system and a driving arrangement support method capable of determining a train schedule change plan more quickly, efficiently, and reliably. Objective.
上述した課題を解決し、目的を達成するために、本発明に係る運転整理支援システムは、ネットワークを介して相互に通信可能に接続された列車ダイヤ指令システム、車両運用指令システムおよび乗務員運用指令システムを備えてなる運転整理支援システムであって、前記車両運用指令システムは、前記列車ダイヤ指令システムから送信された列車ダイヤ変更案に応じて車両運用計画を予測し、予測される車両運用計画に矛盾が生じない場合は前記列車ダイヤ指令システムに対して前記列車ダイヤ変更案を承認する旨を返信し、予測される車両運用計画に矛盾が生ずる場合は前記列車ダイヤ指令システムに対して前記列車ダイヤ変更案を不承認する旨および不承認の理由を返信する車両運用計画予測部、を有し、前記乗務員運用指令システムは、前記列車ダイヤ指令システムから送信された前記列車ダイヤ変更案に応じて乗務員運用計画を予測し、予測される乗務員運用計画に矛盾が生じない場合は前記列車ダイヤ指令システムに対して前記列車ダイヤ変更案を承認する旨を返信し、予測される乗務員運用計画に矛盾が生ずる場合は前記列車ダイヤ指令システムに対して前記列車ダイヤ変更案を不承認する旨および不承認の理由を返信する乗務員運用計画予測部、を有し、前記列車ダイヤ指令システムは、前記列車ダイヤ変更案を登録し前記車両運用指令システムおよび前記乗務員運用指令システムへ送信するとともに、前記車両運用指令システムおよび前記乗務員運用指令システムの双方から前記承認の返信を得た場合は、前記列車ダイヤ変更案を確定し、少なくともいずれか一方から前記不承認の返信を得た場合は、前記不承認の理由に基づいて新たに立案された列車ダイヤ変更案の登録を行う列車ダイヤ指令部、を有する、ことを特徴とする。 In order to solve the above-described problems and achieve the object, an operation coordination support system according to the present invention includes a train diagram command system, a vehicle operation command system, and a crew member operation command system that are connected to each other via a network. The vehicle operation command system predicts a vehicle operation plan according to the train schedule change plan transmitted from the train diagram command system, and contradicts the predicted vehicle operation plan. If there is no conflict, the train schedule command system is replied to approve the train schedule change plan, and if there is a contradiction in the predicted vehicle operation plan, the train schedule command system is changed to the train schedule command system. A vehicle operation plan prediction unit for returning a plan disapproval and a reason for the disapproval, and said crew member operation command system , Predicting a crew operation plan according to the train schedule change plan transmitted from the train diagram command system, and if there is no contradiction in the predicted crew operation plan, the train diagram change to the train diagram command system A crew member operation plan prediction unit that returns a notification that the plan diagram change plan is disapproved and the reason for the disapproval to the train diagram command system when there is a contradiction in the predicted crew operation plan. The train schedule command system registers the train schedule change plan and transmits it to the vehicle operation command system and the crew operation command system, and from both the vehicle operation command system and the crew operation command system. When the approval reply is obtained, the train schedule change plan is confirmed and at least one of them is confirmed. If to give a reply of the disapproval from, has a train schedule instruction unit, for registering the train schedule changes proposal newly planned based on the reason of the disapproval, characterized in that.
この発明によれば、より迅速、効率的かつ確実に列車ダイヤ変更案を確定することができる、という効果を奏する。 According to the present invention, there is an effect that a train schedule change plan can be determined more quickly, efficiently and reliably.
以下に、本発明に係る運転整理支援システムおよび運転整理支援方法の実施の形態を図面に基づいて詳細に説明する。なお、この実施の形態によりこの発明が限定されるものではない。 Embodiments of a driving arrangement support system and a driving arrangement support method according to the present invention will be described below in detail with reference to the drawings. Note that the present invention is not limited to the embodiments.
実施の形態1.
図1は、本実施の形態に係る運転整理支援システムの構成を示すブロック図である。図1に示すように、本実施の形態に係る運転整理支援システムは、列車ダイヤ指令システム1と、車両運用指令システム2と、乗務員運用指令システム3と、これらの間を通信可能に接続するネットワーク4とを備えている。列車ダイヤ指令システム1は例えば運転指令室に、車両運用指令システム2は例えば車両区所に、乗務員運用指令システム3は例えば乗務員区所に分散して配置される。
Embodiment 1 FIG.
FIG. 1 is a block diagram showing the configuration of the driving arrangement support system according to the present embodiment. As shown in FIG. 1, the driving arrangement support system according to the present embodiment includes a train diagram command system 1, a vehicle operation command system 2, a crew member
列車ダイヤ指令システム1は、指令員等がデータの入出力を行う入出力装置5と、列車ダイヤ情報等を表示するダイヤ情報表示装置6と、列車ダイヤ変更案を登録しこの列車ダイヤ変更案を車両運用指令システム2および乗務員運用指令システム3へ送信するとともに車両運用指令システム2および乗務員運用指令システム3からの応答に基づいて列車ダイヤ変更案を列車ダイヤとして確定しまたは新たな列車ダイヤ変更案を登録する列車ダイヤ指令部7と、ネットワーク4を介してデータの送受信を行うデータ送受信部8とを備えている。
The train schedule command system 1 registers an input /
車両運用指令システム2は、指令員等がデータの入出力を行う入出力装置9と、車両運用情報等を表示する車両運用情報表示装置10と、列車ダイヤ指令システム1から受信した列車ダイヤ変更案等に基づいて車両運用計画を予測し、予測される計画に矛盾が生じていないかを検証して列車ダイヤ変更案に対して「承認」または「不承認」の判断を行い、「承認」の場合はその旨および車両運用計画の変更内容を、「不承認」の場合はその旨およびその理由を列車ダイヤ指令システム1に送信する車両運用計画予測部11と、ネットワーク4を介してデータの送受信を行うデータ送受信部12とを備えている。
The vehicle operation command system 2 includes an input /
乗務員運用指令システム3は、指令員等がデータの入出力を行う入出力装置13と、乗務員情報等を表示する乗務員運用情報表示装置14と、列車ダイヤ指令システム1から受信した列車ダイヤ変更案等に基づいて乗務員運用計画を予測し、予測される計画に矛盾が生じないかを検証して列車ダイヤ変更案に対して「承認」または「不承認」の判断を行い、「承認」の場合はその旨および乗務員運用計画の変更内容を、「不承認」の場合はその旨およびその理由を列車ダイヤ指令システム1に送信する乗務員運用計画予測部15と、ネットワーク4を介してデータの送受信を行うデータ送受信部16とを備えている。
The crew member
図2は、列車ダイヤ指令システム1におけるダイヤ変更時の機能構成を示したブロック図であり、特に、列車ダイヤ指令部7における機能構成を具体的に示した図である。ダイヤ変更時には、指令員が入出力装置5を介してダイヤ変更のためのデータを入力し、この入力データは列車ダイヤ指令部7に入力される。入力データは、列車ダイヤ指令部7内のマンマシンI/F(インタフェース)部16を介してダイヤ変更登録部17に入力される。ダイヤ変更登録部17は、その時点で登録され使用されている列車ダイヤに関する情報であるダイヤ情報(元)18と上記入力データとに基づいて列車ダイヤ変更案を作成し、これをダイヤ情報(変更)19として登録する。すなわち、指令員が運用計画の変更が必要であると判断した場合、入出力装置5を操作することにより、マンマシンI/F部16およびダイヤ変更登録部17を介して、ダイヤ情報(変更)19が作成される。
FIG. 2 is a block diagram illustrating a functional configuration at the time of a schedule change in the train diagram command system 1, and particularly a diagram specifically illustrating a functional configuration in the train
また、ダイヤ変更登録部17により列車ダイヤ変更案が登録されると、運用変更内容抽出部20は列車ダイヤの変更分を所定の形式で抽出する。すなわち、運用変更内容抽出部20は、ダイヤ情報(変更)19とダイヤ情報(元)18との差分である運用変更内容を抽出する。そして、この運用変更内容は、列車ダイヤ変更案として、データ送受信部8を介して、車両運用指令システム2および乗務員運用指令システム3へ送信される。ここで、ダイヤ変更案としてダイヤ情報(変更)19そのものを送信することもできるが、データ容量が大きくなるので、変更分である差分情報を送信するほうが好ましい。また、ダイヤ情報表示装置6では、抽出された運用変更内容などが表示される。
Further, when the train schedule change plan is registered by the diagram
図3は、車両運用指令システム2または乗務員運用指令システム3から応答を受けた時の列車ダイヤ指令システム1における機能構成を示したブロック図であり、特に、列車ダイヤ指令部7における機能構成を具体的に示した図である。車両運用指令システム2または乗務員運用指令システム3からの応答はデータ送受信部8により受信され、その受信結果は列車ダイヤ指令部7内の結果表示部21によりダイヤ情報表示装置6にて表示される。さらに、受信結果は、マンマシンI/F部16を介してダイヤ確定部22に入力される。ダイヤ確定部22は、受信結果を検証し、車両運用指令システム2および乗務員運用指令システム3の双方から「承認」を得た場合は、列車ダイヤ変更案を確定しダイヤ情報(変更)19を変更ダイヤとして設定する。
FIG. 3 is a block diagram showing a functional configuration in the train diagram command system 1 when a response is received from the vehicle operation command system 2 or the crew member
一方、車両運用指令システム2および乗務員運用指令システム3の少なくとも一方から「不承認」を得た場合は、ダイヤ確定部22は、列車ダイヤ変更案を確定することなく、「不承認」を受けた旨およびその理由をダイヤ情報表示装置6に表示する。これにより、司令員は、「不承認」の理由を具体的に把握することができるので、「不承認」の理由を勘案して適切なデータを迅速に入力することができ、ダイヤ変更登録部17を介して、新たなより適切な列車ダイヤ変更案を立案することができる。なお、「不承認」の理由の具体的内容等については後述する。
On the other hand, when “disapproved” is obtained from at least one of the vehicle operation command system 2 and the crew member
図4は、車両運用指令システム2における列車ダイヤ変更案受信時の機能構成を示したブロック図であり、特に、車両運用計画予測部11における機能構成を具体的に示した図である。
FIG. 4 is a block diagram showing a functional configuration at the time of receiving a train schedule change plan in the vehicle operation command system 2, and is a diagram specifically showing a functional configuration in the vehicle operation
列車ダイヤ指令システム1からの列車ダイヤ変更案はデータ送受信部12により受信され、その受信結果は車両運用計画予測部11内の受信表示部25により車両運用情報表示装置10にて表示される。さらに、受信結果は、マンマシンI/F部26を介して変更案予測部27に入力される。
The train schedule change plan from the train schedule command system 1 is received by the data transmission /
変更案予測部27は、受信された列車ダイヤ変更案とその時点で登録され使用されている車両運用計画である車両運用情報(元)28とに基づいて、車両運用計画のシミュレーション予測を行い、車両運用計画の変更案である車両運用情報(変更)29を作成するとともに、車両運用計画に矛盾が発生しないかどうかを検証する。このとき、変更案予測部27は、その時点で使用されている列車ダイヤ情報も保持しているので、列車ダイヤ指令システム1から受信された列車ダイヤ変更案が変更の差分情報のみを含むものであっても列車ダイヤ指令システム1が保持するダイヤ情報(変更)19と同じ情報を再現することができる。なお、車両運用計画の予測シミュレーションは、例えば特許文献2に開示された従来の技術などを利用して同様に行うことができる。
The change
変更案予測部27は、検証の結果、変更計画(車両運用計画の変更案)に矛盾が生じない場合は、列車ダイヤ変更案を車両運用計画に反映可能であるとして、列車ダイヤ変更案を「承認」し、変更計画に矛盾が生ずる場合は、列車ダイヤ変更案を車両運用計画に反映不可能であるとして、列車ダイヤ変更案を「不承認」とする。また、「不承認」の場合は、「不承認」とした理由を添付する。ここで、理由としては、車両運用に対して予め矛盾として抽出する項目を複数定めておき、その項目の中から選択されたものであって、かつ、選択された項目ごとに矛盾した予測計画内容を具体的に対応させたものとする。図13は、「不承認」の場合の理由の一例を列挙した図であり、車両運用に対しては、「滞泊場所」、「走行キロ」、「列車遅延による時刻逆転」、「編成併結」、「運用最終駅・充当開始駅不一致」、および「走行範囲」が矛盾として抽出する項目として列挙されている。なお、各項目に対して、矛盾として判断する条件が記載されている。変更案予測部27は、検証の結果、「承認」応答をする場合は、車両運用計画の変更内容の一覧である変更一覧31を作成し、「不承認」応答をする場合は、「不承認」の理由を図13の項目から選択することにより警報一覧32を作成する。なお、図13は特許文献2の図5と同じ図である。
If there is no contradiction in the change plan (change plan of the vehicle operation plan) as a result of the verification, the change
結果返信部30は、「承認」応答の場合は変更一覧31から、「不承認」の場合は警報一覧32からデータを取得し、その内容を車両運用情報表示装置10にて表示させるとともにデータ送受信部12を介して列車ダイヤ指令システム1へ送信する。
The
図5は、乗務員運用指令システム3における列車ダイヤ変更案受信時の機能構成を示したブロック図であり、特に、車両運用計画予測部11における機能構成を具体的に示した図である。
FIG. 5 is a block diagram showing a functional configuration at the time of receiving a train schedule change plan in the crew member
列車ダイヤ指令システム1からの列車ダイヤ変更案はデータ送受信部16により受信され、その受信結果は車両運用計画予測部11内の受信表示部40により乗務員運用情報表示装置14にて表示される。さらに、受信結果は、マンマシンI/F部41を介して変更案予測部42に入力される。
The train schedule change plan from the train schedule command system 1 is received by the data transmitter /
変更案予測部42は、受信された列車ダイヤ変更案とその時点で登録され使用されている乗務員運用計画である乗務員運用情報(元)43とに基づいて、乗務員運用計画のシミュレーション予測を行い、乗務員運用計画の変更案である乗務員運用情報(変更)44を作成するとともに、乗務員運用計画に矛盾が発生しないかどうかを検証する。このとき、変更案予測部42は、その時点で使用されている列車ダイヤ情報も保持しているので、列車ダイヤ指令システム1から受信された列車ダイヤ変更案が変更の差分情報のみを含むものであっても列車ダイヤ指令システム1が保持するダイヤ情報(変更)19と同じ情報を再現することができる。
The change
変更案予測部42は、検証の結果、変更計画(乗務員運用計画の変更案)に矛盾が生じない場合は、列車ダイヤ変更案を乗務員運用計画に反映可能であるとして、列車ダイヤ変更案を「承認」し、変更計画に矛盾が生ずる場合は、列車ダイヤ変更案を乗務員運用計画に反映不可能であるとして、列車ダイヤ変更案を「不承認」とする。また、「不承認」の場合は、「不承認」とした理由を添付する。ここで、理由としては、乗務員運用に対して予め矛盾として抽出する項目を複数定めておき、その項目の中から選択されたものであって、かつ、選択された項目ごとに矛盾した予測計画内容を具体的に対応させたものとする。図13では、乗務員運用に対しては、「業務キロ・業務時間」、「最終下車駅」、「食事時間」、「乗務員遅延による時刻逆転」、「下車駅・乗車駅不一致」、および「乗務員資格」が矛盾として抽出する項目として列挙されている。なお、各項目に対して、矛盾として判断する条件が記載されている。変更案予測部42は、検証の結果、「承認」応答をする場合は、乗務員運用計画の変更内容の一覧である変更一覧46を作成し、「不承認」応答をする場合は、「不承認」の理由を図13の項目から選択して警報一覧47を作成する。
If there is no contradiction in the change plan (change plan of crew member operation plan) as a result of the verification, the change
結果返信部45は、「承認」応答の場合は変更一覧46から、「不承認」の場合は警報一覧47からデータを取得し、その内容を乗務員運用情報表示装置14にて表示させるとともにデータ送受信部16を介して列車ダイヤ指令システム1へ送信する。
The
次に、本実施の形態の動作について図6を参照して説明する。図6は、本実施の形態の動作を示したフローチャートである。なお、以下では、列車ダイヤ指令システム1と車両運用指令システム2とに関する動作について説明するが、列車ダイヤ指令システム1と乗務員運用指令システム3とに関する動作についても同様である。
Next, the operation of the present embodiment will be described with reference to FIG. FIG. 6 is a flowchart showing the operation of the present embodiment. In the following description, operations related to the train diagram command system 1 and the vehicle operation command system 2 will be described, but the operations related to the train diagram command system 1 and the crew member
まず、列車ダイヤ指令システム1にて列車ダイヤ変更案を作成登録し、車両運用指令システム2および乗務員運用指令システム3へ列車ダイヤ変更案を送信する(S1)。ここで、運用変更内容抽出部20の送信内容は、例えば図7に示すような内容である。すなわち、図7では、備考欄に、列車番号126Mの列車がA駅に20分遅れて到着することが運行情報として記載され、これに対応して内容欄に、A駅−B駅間で列車番号126Mの列車と同区間を走行する別の列車(内容欄には未記載)との間で走行順序を変更する列車ダイヤ変更案が提示されている。
First, a train schedule change plan is created and registered in the train schedule command system 1, and the train schedule change plan is transmitted to the vehicle operation command system 2 and the crew member operation command system 3 (S1). Here, the transmission content of the operation change
次に、車両運用指令システム2にて列車ダイヤ変更案を受信し、この列車ダイヤ変更案に応じて、車両運用の予測を実行し対応可能かどうか判断する(S2)。すなわち、車両運用指令システム2の変更案予測部27は、受信された列車ダイヤ変更案とその時点で使用されている車両運用計画である車両運用情報(元)28とに基づいて、車両運用計画のシミュレーション予測を行い、計画に矛盾が発生しないかどうかを検証する。ここで、車両運用指令システム2の受信表示部25の受信内容は、例えば図8に示すような内容であり、備考欄および内容欄は運用変更内容抽出部20の送信内容と同じである。
Next, a train schedule change plan is received by the vehicle operation command system 2, and in accordance with this train schedule change plan, prediction of vehicle operation is executed to determine whether or not it can be handled (S2). That is, the change
予測の結果、対応可能である場合(S3、yes)、結果返信部30は列車ダイヤ指令システム1へ「承認」応答する(S4)。すなわち、変更案予測部27は、検証の結果、「承認」応答をする場合は、車両運用計画の変更内容の一覧である変更一覧31を作成し、結果返信部30はデータ送受信部12を介して「承認」の旨および車両運用計画の付帯的な変更内容を列車ダイヤ指令システム1へ送信する。ここで、結果返信部30の送信内容は、例えば図9に示すような内容である。すなわち、図9では、備考欄に、「承認」が記載され、これに対応して内容欄に、C駅−D駅間で列車番号252Mの列車と同区間を走行する別の列車(内容欄には未記載)との間で走行順序を変更し、かつ、E駅−D駅間で列車番号552Mの列車と同区間を走行する別の列車(内容欄には未記載)との間で走行順序を変更する車両運用計画変更案が提示されている。
As a result of the prediction, if the response is possible (S3, yes), the
次に、列車ダイヤ指令システム1では、車両運用指令システム2からの「承認」応答を受信すると、列車ダイヤ変更案を確定し列車ダイヤに設定する(S5)。ここで、列車ダイヤ指令システム1の結果表示部21の受信内容は、例えば図10に示すような内容であり、備考欄および内容欄は車両運用指令システム2の結果返信部30の送信内容(「承認」応答内容)と同じである。
Next, when the train schedule command system 1 receives the “approval” response from the vehicle operation command system 2, the train schedule change plan is finalized and set in the train schedule (S5). Here, the received content of the
一方、予測の結果、対応不可能である場合(S3、No)、結果返信部30は列車ダイヤ指令システム1へその理由を付して「不承認」応答する(S6)。すなわち、結果返信部30は「不承認」の理由を図13の項目から選択し、選択された項目に、矛盾する予測計画内容を具体的に対応づけることにより警報一覧32を作成し、「不承認」の旨およびその理由を、データ送受信部12を介して列車ダイヤ指令システム1へ送信する。ここで、結果返信部30の送信内容は、例えば図11に示すような内容である。
On the other hand, when it cannot respond as a result of prediction (S3, No), the
すなわち、図11では、備考欄に、「不承認」が記載され、これに対応して内容欄に「不承認」の理由が記載され、その1つ目の理由は、「運行最終駅・充当開始駅不一致」であり、この項目に対応する矛盾した予測計画内容は、具体的には、列車番号162Mの列車が出発駅のF駅を出発時刻(計画)の7:58:45に出発することが未充当になっていることである。2つ目の理由は、「運行最終駅・充当開始駅不一致」であり、具体的には、列車番号232Mの列車が出発駅のG駅を出発時刻(計画)の8:16:00に出発することが未充当になっており、3つ目の理由は、「列車遅延による時刻逆転」であり、具体的には、列車番号312Mの列車が到着駅のH駅を予測到着時刻の8:49:45に到着し、次に充当される列車の発車時刻よりも遅くなることである。 That is, in FIG. 11, “rejected” is described in the remarks column, and the reason for “rejected” is described in the content column, and the first reason is “the last station in operation / appropriation start station”. Specifically, the contradictory prediction plan content corresponding to this item is that the train with the train number 162M departs from the departure station F station at 7:58:45 of the departure time (plan). It is unappropriated. The second reason is “inconsistency between the last station of operation and the start of appropriation”. Specifically, the train with the train number 232M departs from the departure station G station at 8:16: 00 at the departure time (plan). The third reason is “time reversal due to train delay”. Specifically, the train with the train number 312M sets the arrival station H to the predicted arrival time 8: It arrives at 49:45 and is later than the departure time of the next train to be allocated.
次に、列車ダイヤ指令システム1では、車両運用指令システム2からの「不承認」応答を受信すると、再度、列車ダイヤ変更案を検討する(S7)。このとき、「不承認」の理由は、図12に示すように、予め設定された項目にしたがって具体的に提示される。したがって、指令員は、ダイヤ情報表示装置6に示された「不承認」の理由に基づき、矛盾するとして抽出された事項に関連する計画を中心に列車ダイヤ案を再検討すればよい。よって、ダイヤ変更登録部17は、「不承認」の理由に基づいて、迅速、効率的、かつ適切に新たな列車ダイヤ変更案を作成することができ、この新たな列車ダイヤ変更案を入力として再度S1からの処理が繰り返される。
Next, when the train schedule command system 1 receives the “non-approval” response from the vehicle operation command system 2, the train schedule change plan is examined again (S7). At this time, the reason for “disapproval” is specifically presented according to preset items as shown in FIG. Therefore, based on the reason of “disapproval” shown in the diagram
以上説明したように、本実施の形態では、列車ダイヤ指令システム1にて列車ダイヤを変更する際に、列車ダイヤ指令システム1から車両運用指令システム2および乗務員運用指令システム3へそれぞれ列車ダイヤ変更案を送信し、システム間で列車ダイヤ変更案を共有するようにする。そして、車両運用指令システム2および乗務員運用指令システム3はそれぞれ列車ダイヤ変更案を各計画に反映可能かどうか判断し、反映可能であれば、「承認」を返信する。反映不可能であれば、「不承認」とその理由を返信する。
As described above, in the present embodiment, when the train schedule is changed in the train schedule command system 1, the train schedule change plan is transferred from the train schedule command system 1 to the vehicle operation command system 2 and the crew member
本実施の形態によれば、車両運用指令システム2および乗務員運用指令システム3からの「不承認」応答において、「不承認」の理由を具体的な項目として提示するようにしたので、列車ダイヤ指令システム1では、提示された具体的な項目に基づいて列車ダイヤ変更案の再検討をすることができ、より適切な列車ダイヤ変更案を迅速に作成することができる。その結果、より迅速、効率的、かつ確実に変更案を確定することができる。
According to the present embodiment, the reason for “disapproval” is presented as a specific item in the “non-approval” response from the vehicle operation command system 2 and the crew member
また、従来、列車ダイヤ指令システム1の指令員は、ダイヤ変更の際に、電話等で車両運用指令システム2の指令員および乗務員運用指令システム3の指令員と協議していた。これに対して、本実施の形態では、列車ダイヤ変更案を列車ダイヤ指令システム1から車両運用指令システム2および乗務員運用指令システム3へ送信することで、電話等による協議の必要がなく手間が省けるとともに信頼性も向上する。また、車両運用指令システム2および乗務員運用指令システム3では、指令員は実際に列車ダイヤ変更案を見て確認することで、迅速かつ確実に変更内容を検討することが可能となる。
Conventionally, the trainer of the train schedule command system 1 has consulted with the commander of the vehicle operation command system 2 and the commander of the crew member
本実施の形態では、「承認」または「不承認」の判断を列車ダイヤ指令システム1で行うことなく、車両運用指令システム2および乗務員運用指令システム3にてそれぞれ分散処理するようにしているので、処理が分散されて効率的である。
In the present embodiment, the determination of “approval” or “non-approval” is performed by the vehicle operation command system 2 and the crew member
なお、特許文献1の段落[0029]、[0030]では、運行計画変更時に指令員が計画変更案を確認した上で承認を入力しまたは非承認およびコメントを入力して、返信することとなっているが、同文献では、非承認の場合にコメント等をどのように生かすかは述べられていない。さらに、コメントは、その都度、指令員が入力するものであって、本実施の形態のように、予め決められた基準にしたがって設定された項目とは異なるので、そのコメントを列車ダイヤ変更案の立案に役立てることができるか否かは明確ではなく、また、コメントは任意記載事項と解されるので利用しようとしても利用できない場合がある。したがって、特許文献1のシステムは本実施の形態とは本質的に異なるものである。 In paragraphs [0029] and [0030] of Patent Document 1, when the operation plan is changed, the commander confirms the plan change plan and inputs approval or non-approval and comments, and returns a reply. However, this document does not describe how to utilize comments in the case of non-approval. In addition, the comment is input by the commander each time, and is different from the items set according to the predetermined criteria as in this embodiment, so the comment is changed to the train schedule change proposal. It is not clear whether it can be used for planning, and comments are considered optional items and may not be used. Therefore, the system of Patent Document 1 is essentially different from the present embodiment.
実施の形態2.
実施の形態1では、「不承認」応答時に理由を付して返信していたが、本実施の形態では、車両運用指令システム2および乗務員運用指令システム3にてそれぞれ反映可能な列車ダイヤ変更案を作成し、作成された列車ダイヤ変更案を「不承認」の理由とともに列車ダイヤ指令システム1に返信する構成とする。
Embodiment 2. FIG.
In the first embodiment, a reply is given with a reason at the time of a “disapproved” response, but in this embodiment, a train schedule change plan that can be reflected in the vehicle operation command system 2 and the crew member
本実施の形態の構成は、図1〜図5と同じであるが、車両運用計画予測部11の変更案予測部27および乗務員運用計画予測部15の変更案予測部42にさらに機能が付加される。すなわち、車両運用計画予測部11の変更案予測部27は、「不承認」の場合に、「不承認」の理由に基づいて、予測される車両運用計画と矛盾がなく車両運用計画に反映可能な列車ダイヤ変更案を提案し、予測される車両運用計画と矛盾のない列車ダイヤ変更案を「不承認」の理由とともに「不承認」である旨に添付して返信する。また、乗務員運用計画予測部15の変更案予測部42は、「不承認」の場合に、「不承認」の理由に基づいて、予測される乗務員運用計画と矛盾がなく乗務員運用計画に反映可能な列車ダイヤ変更案を提案し、予測される乗務員運用計画と矛盾のない列車ダイヤ変更案を「不承認」の理由とともに「不承認」である旨に添付して返信する。
The configuration of the present embodiment is the same as that shown in FIGS. 1 to 5, but functions are added to the change
列車ダイヤ指令部7のダイヤ確定部22は、車両運用指令システム2および乗務員運用指令システム3の少なくとも一方から「不承認」を得た場合に、列車ダイヤ変更案を確定することなく、「不承認」の旨および理由ならびに提案された列車ダイヤ変更案をダイヤ情報表示装置6に表示する。これにより、司令員は、「不承認」の理由および提案された列車ダイヤ変更案を具体的に把握することができるので、表示内容を勘案して適切なデータを迅速に入力することができる。したがって、ダイヤ変更登録部17は、「不承認」の理由および提案された列車ダイヤ変更案等に基づき、新たなより適切な列車ダイヤ変更案を迅速に作成し登録することができる。
When the
本発明は、列車ダイヤの変更に際して車両運用計画および乗務員運用計画との整合を図って変更案を迅速、効率的かつ確実に確定するのに有用である。 INDUSTRIAL APPLICABILITY The present invention is useful for promptly, efficiently and reliably determining a change plan by matching with a vehicle operation plan and a crew member operation plan when changing a train schedule.
1 列車ダイヤ指令システム
2 車両運用指令システム
3 乗務員運用指令システム
4 ネットワーク
5 入出力装置
6 ダイヤ情報表示装置
7 列車ダイヤ指令部
8 データ送受信部
9 入出力装置
10 車両運用情報表示装置
11 車両運用計画予測部
12 データ送受信部
13 入出力装置
14 乗務員運用情報表示装置
15 乗務員運用計画予測部
16 データ送受信部
17 ダイヤ変更登録部
20 運用変更内容抽出部
21 結果表示部
22 ダイヤ確定部
25 受信表示部
27 変更案予測部
30 結果返信部
31 変更一覧
32 警報一覧
40 受信表示部
42 変更案予測部
45 結果返信部
46 変更一覧
47 警報一覧
DESCRIPTION OF SYMBOLS 1 Train diagram command system 2 Vehicle
Claims (6)
前記車両運用指令システムは、
前記列車ダイヤ指令システムから送信された列車ダイヤ変更案に応じて車両運用計画を予測し、予測される車両運用計画に矛盾が生じない場合は前記列車ダイヤ指令システムに対して前記列車ダイヤ変更案を承認する旨を返信し、予測される車両運用計画に矛盾が生ずる場合は前記列車ダイヤ指令システムに対して前記列車ダイヤ変更案を不承認する旨および不承認の理由を返信する車両運用計画予測部、
を有し、
前記乗務員運用指令システムは、
前記列車ダイヤ指令システムから送信された前記列車ダイヤ変更案に応じて乗務員運用計画を予測し、予測される乗務員運用計画に矛盾が生じない場合は前記列車ダイヤ指令システムに対して前記列車ダイヤ変更案を承認する旨を返信し、予測される乗務員運用計画に矛盾が生ずる場合は前記列車ダイヤ指令システムに対して前記列車ダイヤ変更案を不承認する旨および不承認の理由を返信する乗務員運用計画予測部、
を有し、
前記列車ダイヤ指令システムは、
前記列車ダイヤ変更案を作成して登録し前記車両運用指令システムおよび前記乗務員運用指令システムへ送信するとともに、前記車両運用指令システムおよび前記乗務員運用指令システムの双方から前記承認の返信を得た場合は、前記列車ダイヤ変更案を確定し、少なくともいずれか一方から前記不承認の返信を得た場合は、前記不承認の理由に基づいて新たに列車ダイヤ変更案を作成し、当該列車ダイヤ変更案の登録を行う列車ダイヤ指令部、
を有する、
ことを特徴とする運転整理支援システム。 A driving arrangement support system comprising a train schedule command system, a vehicle operation command system, and a crew member operation command system connected to each other via a network,
The vehicle operation command system is
A vehicle operation plan is predicted according to the train schedule change plan transmitted from the train diagram command system, and if there is no contradiction in the predicted vehicle operation plan, the train diagram change plan is set to the train diagram command system. A vehicle operation plan prediction unit that replies that the vehicle schedule is approved, and that the train schedule change command is rejected and the reason for the disapproval when there is a contradiction in the predicted vehicle operation plan.
Have
The crew operation command system is
A crew operation plan is predicted according to the train diagram change plan transmitted from the train diagram command system, and if there is no contradiction in the predicted crew diagram operation plan, the train diagram change plan is sent to the train diagram command system. When there is a contradiction in the predicted crew crew operation plan, the crew crew operation plan forecasting section replying to the train schedule command system that the train schedule change plan is rejected and the reason for the disapproval,
Have
The train schedule command system
When the train schedule change proposal is created and registered and transmitted to the vehicle operation command system and the crew operation command system, and when the approval reply is obtained from both the vehicle operation command system and the crew operation command system the confirm the train schedule proposed changes, if you give a reply of the disapproval from at least one, creates a new trains diamond proposed changes, registration of the train schedule proposed changes based on the reason of the disapproval Train schedule command section,
Having
A driving arrangement support system characterized by that.
前記車両運用指令システムは、The vehicle operation command system is
前記列車ダイヤ指令システムから送信された列車ダイヤ変更案に応じて車両運用計画を予測し、予測される車両運用計画に矛盾が生じない場合は前記列車ダイヤ指令システムに対して前記列車ダイヤ変更案を承認する旨を返信し、予測される車両運用計画に矛盾が生ずる場合は、車両運用計画と矛盾のない列車ダイヤ変更案を独自に提案するとともに、前記列車ダイヤ指令システムに対して前記列車ダイヤ変更案を不承認する旨および不承認の理由ならびに提案した列車ダイヤ変更案を返信する車両運用計画予測部、A vehicle operation plan is predicted according to the train schedule change plan transmitted from the train diagram command system, and if there is no contradiction in the predicted vehicle operation plan, the train diagram change plan is set to the train diagram command system. If there is a contradiction in the predicted vehicle operation plan, the train schedule change plan that is consistent with the vehicle operation plan is proposed independently and the train diagram change system is changed to the train diagram command system. The vehicle operation plan prediction unit that returns the proposal disapproval, the reason for the disapproval, and the proposed train schedule change plan,
を有し、Have
前記乗務員運用指令システムは、The crew operation command system is
前記列車ダイヤ指令システムから送信された前記列車ダイヤ変更案に応じて乗務員運用計画を予測し、予測される乗務員運用計画に矛盾が生じない場合は前記列車ダイヤ指令システムに対して前記列車ダイヤ変更案を承認する旨を返信し、予測される乗務員運用計画に矛盾が生ずる場合は、乗務員運用計画と矛盾のない列車ダイヤ変更案を独自に提案するとともに、前記列車ダイヤ指令システムに対して前記列車ダイヤ変更案を不承認する旨および不承認の理由ならびに提案した列車ダイヤ変更案を返信する乗務員運用計画予測部、A crew operation plan is predicted according to the train diagram change plan transmitted from the train diagram command system, and if there is no contradiction in the predicted crew diagram operation plan, the train diagram change plan is sent to the train diagram command system. When there is a contradiction in the predicted crew operation plan, the train schedule change plan that is consistent with the crew operation plan is proposed independently and the train diagram command system Crew member operation plan forecasting department that returns the proposed change of train schedule and the reason for the disapproval of the change proposal,
を有し、Have
前記列車ダイヤ指令システムは、The train schedule command system
前記列車ダイヤ変更案を作成して登録し前記車両運用指令システムおよび前記乗務員運用指令システムへ送信するとともに、前記車両運用指令システムおよび前記乗務員運用指令システムの双方から前記承認の返信を得た場合は、前記列車ダイヤ変更案を確定し、少なくともいずれか一方から前記不承認の返信を得た場合は、前記車両運用指令システムおよび前記乗務員運用指令システムの少なくともいずれか一方から得られた前記不承認の理由および提案された列車ダイヤ変更案に基づいて新たに列車ダイヤ変更案を作成し、当該列車ダイヤ変更案の登録を行う列車ダイヤ指令部、When the train schedule change proposal is created and registered and transmitted to the vehicle operation command system and the crew operation command system, and when the approval reply is obtained from both the vehicle operation command system and the crew operation command system , If the train schedule change plan is finalized, and when the reply of the disapproval is obtained from at least one of the reasons, the reason for the disapproval obtained from at least one of the vehicle operation instruction system and the crew member operation instruction system, and Create a new train schedule change plan based on the proposed train schedule change plan, and register the train schedule change plan,
を有する、Having
ことを特徴とする運転整理支援システム。A driving arrangement support system characterized by that.
前記乗務員運用計画予測部が返信可能な不承認の理由は、乗務員運用に対して予め設定された矛盾として抽出する複数の項目の中から選択され、かつ、選択された項目ごとに矛盾した予測計画内容を具体的に対応させたものであることを特徴とする請求項1または2に記載の運転整理支援システム。 The reason for the non-approval that the vehicle operation plan prediction unit can reply is selected from a plurality of items to be extracted as inconsistencies set in advance for vehicle operation, and the prediction plan contents inconsistent for each selected item Is a specific correspondence,
The reason for the disapproval that the crew member operation plan prediction unit can reply is selected from a plurality of items extracted as inconsistencies set in advance for the crew member operation, and the prediction plan contents inconsistent for each selected item The driving arrangement support system according to claim 1 or 2 , characterized by specifically corresponding to the above.
前記車両運用指令システムにて、前記列車ダイヤ指令システムから送信された前記列車ダイヤ変更案に応じて車両運用計画を予測し、予測される車両運用計画に矛盾が生じない場合は前記列車ダイヤ指令システムに対して前記列車ダイヤ変更案を承認する旨を返信し、予測される車両運用計画に矛盾が生ずる場合は前記列車ダイヤ指令システムに対して前記列車ダイヤ変更案を不承認する旨および不承認の理由を返信するとともに、前記乗務員運用指令システムにて、前記列車ダイヤ指令システムから送信された前記列車ダイヤ変更案に応じて乗務員運用計画を予測し、予測される乗務員運用計画に矛盾が生じない場合は前記列車ダイヤ指令システムに対して前記列車ダイヤ変更案を承認する旨を返信し、予測される乗務員運用計画に矛盾が生ずる場合は前記列車ダイヤ指令システムに対して前記列車ダイヤ変更案を不承認する旨および不承認の理由を返信するステップと、
前記列車ダイヤ指令システムにて、前記車両運用指令システムおよび前記乗務員運用指令システムの双方から前記承認の返信を得た場合は、前記列車ダイヤ変更案を確定し、少なくともいずれか一方から前記不承認の返信を得た場合は、前記不承認の理由に基づいて新たに列車ダイヤ変更案を作成し、当該列車ダイヤ変更案の登録を行うステップと、
を含むことを特徴とする運転整理支援方法。 In the train schedule command system, a train schedule change plan is created and registered, and the train schedule registration plan is transmitted to the vehicle operation command system and the crew operation command system;
In the vehicle operation command system, a vehicle operation plan is predicted according to the train schedule change plan transmitted from the train diagram command system, and if there is no contradiction in the predicted vehicle operation plan, the train diagram command system The train schedule change plan is replied, and if there is a contradiction in the predicted vehicle operation plan, the train diagram change plan is rejected and the reason for the disapproval. Reply and predict the crew operation plan according to the train diagram change plan transmitted from the train diagram command system in the crew operation command system, if there is no contradiction in the predicted crew plan Reply to the train schedule command system that the train schedule change plan is approved, and there is a contradiction in the predicted crew operation plan. And step if cunning is to send back the train that and disapproval of the reason the diamond proposed changes to non-approval with respect to the train schedule instruction system,
In the train schedule command system, if the approval response is obtained from both the vehicle operation command system and the crew operation command system, the train schedule change plan is confirmed, and the disapproval response is received from at least one of the train schedule command system. and steps if obtained, which creates a new trains diamond proposed changes based on the reason of the disapproval and registers of the train schedule proposed change,
A driving arrangement support method comprising:
前記車両運用指令システムにて、前記列車ダイヤ指令システムから送信された前記列車ダイヤ変更案に応じて車両運用計画を予測し、予測される車両運用計画に矛盾が生じない場合は前記列車ダイヤ指令システムに対して前記列車ダイヤ変更案を承認する旨を返信し、予測される車両運用計画に矛盾が生ずる場合は車両運用計画と矛盾のない列車ダイヤ変更案を独自に提案するとともに、前記列車ダイヤ指令システムに対して前記列車ダイヤ変更案を不承認する旨および不承認の理由ならびに提案した列車ダイヤ変更案を返信するとともに、前記乗務員運用指令システムにて、前記列車ダイヤ指令システムから送信された前記列車ダイヤ変更案に応じて乗務員運用計画を予測し、予測される乗務員運用計画に矛盾が生じない場合は前記列車ダイヤ指令システムに対して前記列車ダイヤ変更案を承認する旨を返信し、予測される乗務員運用計画に矛盾が生ずる場合は乗務員運用計画と矛盾のない列車ダイヤ変更案を独自に提案するとともに、前記列車ダイヤ指令システムに対して前記列車ダイヤ変更案を不承認する旨および不承認の理由ならびに提案した列車ダイヤ変更案を返信するステップと、In the vehicle operation command system, a vehicle operation plan is predicted according to the train schedule change plan transmitted from the train diagram command system, and if there is no contradiction in the predicted vehicle operation plan, the train diagram command system The train schedule change plan is approved, and if there is a contradiction in the predicted vehicle operation plan, the train schedule change plan that is consistent with the vehicle operation plan is proposed independently, and the train diagram command The train schedule change change sent from the train schedule command system in the crew member operation command system while returning the train schedule change plan to the system and the reason for the rejection and the proposed train schedule change plan The crew operation plan is predicted according to the plan, and if there is no contradiction in the predicted crew operation plan, the train Reply to approve the train schedule change plan to the Ya command system, and if there is a contradiction in the predicted crew operation plan, propose a train schedule change plan that is consistent with the crew operation plan, and Replying to the train schedule command system that the train schedule change proposal is disapproved and the reason for the disapproval and the proposed train schedule change proposal;
前記列車ダイヤ指令システムにて、前記車両運用指令システムおよび前記乗務員運用指令システムの双方から前記承認の返信を得た場合は、前記列車ダイヤ変更案を確定し、少なくともいずれか一方から前記不承認の返信を得た場合は、In the train schedule command system, if the approval response is obtained from both the vehicle operation command system and the crew operation command system, the train schedule change plan is confirmed, and the disapproval response is received from at least one of the train schedule command system. If you get
前記車両運用指令システムおよび前記乗務員運用指令システムの少なくともいずれか一方から得られた前記不承認の理由および提案された列車ダイヤ変更案に基づいて新たに列車ダイヤ変更案を作成し、当該列車ダイヤ変更案の登録を行うステップと、Based on the reason for non-approval obtained from at least one of the vehicle operation command system and the crew operation command system and a proposed train schedule change plan, a new train schedule change plan is created, and the train schedule change plan The steps to register
を含むことを特徴とする運転整理支援方法。A driving arrangement support method comprising:
前記乗務員運用指令システムから返信可能な不承認の理由は、乗務員運用に対して予め設定された矛盾として抽出する複数の項目の中から選択され、かつ、選択された項目ごとに矛盾した予測計画内容を具体的に対応させたものであることを特徴とする請求項4または5に記載の運転整理支援方法。 The vehicle operational command system or we reply possible disapproval reason is selected from among a plurality of items to be extracted as a discrepancy has been preset for the vehicle operation, and was inconsistent with each selected item prospective It is a concrete correspondence of the contents,
The reason for the disapproval that can be replied from the crew operation command system is selected from a plurality of items to be extracted as inconsistencies set in advance for the crew operation, and the contradictory prediction plan contents are selected for each selected item. 6. The driving arrangement support method according to claim 4, wherein the driving arrangement support method is specifically adapted.
Priority Applications (1)
Application Number | Priority Date | Filing Date | Title |
---|---|---|---|
JP2010030082A JP5528147B2 (en) | 2010-02-15 | 2010-02-15 | Driving arrangement support system and driving arrangement support method |
Applications Claiming Priority (1)
Application Number | Priority Date | Filing Date | Title |
---|---|---|---|
JP2010030082A JP5528147B2 (en) | 2010-02-15 | 2010-02-15 | Driving arrangement support system and driving arrangement support method |
Publications (2)
Publication Number | Publication Date |
---|---|
JP2011162155A JP2011162155A (en) | 2011-08-25 |
JP5528147B2 true JP5528147B2 (en) | 2014-06-25 |
Family
ID=44593331
Family Applications (1)
Application Number | Title | Priority Date | Filing Date |
---|---|---|---|
JP2010030082A Active JP5528147B2 (en) | 2010-02-15 | 2010-02-15 | Driving arrangement support system and driving arrangement support method |
Country Status (1)
Country | Link |
---|---|
JP (1) | JP5528147B2 (en) |
Cited By (1)
Publication number | Priority date | Publication date | Assignee | Title |
---|---|---|---|---|
CN111791923A (en) * | 2020-05-21 | 2020-10-20 | 北京交通大学 | Energy-saving-oriented single-track railway train scheduling method and system |
Families Citing this family (4)
Publication number | Priority date | Publication date | Assignee | Title |
---|---|---|---|---|
GB2537434A (en) * | 2014-09-22 | 2016-10-19 | Hitachi Ltd | Train schedule restoration system and train operation management method |
JP2018090140A (en) * | 2016-12-06 | 2018-06-14 | 東日本旅客鉄道株式会社 | Vehicle application total management system |
JP6781028B2 (en) * | 2016-12-06 | 2020-11-04 | 東日本旅客鉄道株式会社 | Vehicle operation business support system |
JP2018090138A (en) * | 2016-12-06 | 2018-06-14 | 東日本旅客鉄道株式会社 | Vehicle application business support system |
Family Cites Families (6)
Publication number | Priority date | Publication date | Assignee | Title |
---|---|---|---|---|
JP3562079B2 (en) * | 1995-12-12 | 2004-09-08 | 株式会社日立製作所 | Operation plan correction system and operation control terminal |
JP2003072554A (en) * | 2001-09-05 | 2003-03-12 | Railway Technical Res Inst | System and method for supporting preparation of operation arrangement proposal |
JP4508840B2 (en) * | 2004-11-15 | 2010-07-21 | 三菱電機株式会社 | Train operation management system |
JP4721812B2 (en) * | 2005-08-08 | 2011-07-13 | 三菱電機株式会社 | Vehicle / crew crew operation recovery device |
JP4665755B2 (en) * | 2005-12-23 | 2011-04-06 | 三菱電機株式会社 | Train operation management system |
JP2008222004A (en) * | 2007-03-12 | 2008-09-25 | Hitachi Ltd | Operation arrangement apparatus in operation management system |
-
2010
- 2010-02-15 JP JP2010030082A patent/JP5528147B2/en active Active
Cited By (1)
Publication number | Priority date | Publication date | Assignee | Title |
---|---|---|---|---|
CN111791923A (en) * | 2020-05-21 | 2020-10-20 | 北京交通大学 | Energy-saving-oriented single-track railway train scheduling method and system |
Also Published As
Publication number | Publication date |
---|---|
JP2011162155A (en) | 2011-08-25 |
Similar Documents
Publication | Publication Date | Title |
---|---|---|
USRE47835E1 (en) | Tools for railway traffic control | |
JP5528147B2 (en) | Driving arrangement support system and driving arrangement support method | |
CN110178150B (en) | Dock management system and reservation management server | |
KR100831387B1 (en) | Train operation management system | |
JP4728713B2 (en) | Train operation management system, diamond management device, and train operation information providing method | |
Ertem et al. | Freight transportation using high-speed train systems | |
JP6276866B2 (en) | Train diagram recovery system and train operation management method | |
WO2020217693A1 (en) | Vehicle operation plan creation device, vehicle operation plan creation method, and vehicle operation plan creation program | |
JP5731912B2 (en) | Driving arrangement support system | |
US20080097660A1 (en) | Train Service Managing System | |
Prandtstetter et al. | Introduction to synchromodal networks in Austria | |
JP6298665B2 (en) | Train diagram creation system, train diagram creation device, and train diagram creation method | |
US20020035417A1 (en) | Locomotive wreck repair | |
JP2011508707A (en) | Planning and management of object transportation | |
JP4858200B2 (en) | Station transfer guide information display method and transfer guide information creation device | |
JP4672749B2 (en) | Train operation management system operation management system | |
JP2014182728A (en) | Automatic ticket examination system, and method for updating master data of the automatic ticket examination system | |
JP4221254B2 (en) | Vehicle base diamond creation device | |
Ponweiser et al. | An introduction to synchromodal networks in Austria | |
JP7374509B2 (en) | Programs and information processing equipment | |
JP2016060431A (en) | Crew operation management device, method and system | |
US20230033597A1 (en) | Multi-subject cooperation plan system and multi-subject cooperation plan method | |
JP2003330519A (en) | System and method for managing production progress status, and server for the system | |
JP4792055B2 (en) | Train operation management system operation management system | |
JP5593288B2 (en) | Data management method and data management apparatus |
Legal Events
Date | Code | Title | Description |
---|---|---|---|
A621 | Written request for application examination |
Free format text: JAPANESE INTERMEDIATE CODE: A621 Effective date: 20120903 |
|
A977 | Report on retrieval |
Free format text: JAPANESE INTERMEDIATE CODE: A971007 Effective date: 20130722 |
|
A131 | Notification of reasons for refusal |
Free format text: JAPANESE INTERMEDIATE CODE: A131 Effective date: 20130827 |
|
A521 | Request for written amendment filed |
Free format text: JAPANESE INTERMEDIATE CODE: A523 Effective date: 20131017 |
|
TRDD | Decision of grant or rejection written | ||
A01 | Written decision to grant a patent or to grant a registration (utility model) |
Free format text: JAPANESE INTERMEDIATE CODE: A01 Effective date: 20140318 |
|
A61 | First payment of annual fees (during grant procedure) |
Free format text: JAPANESE INTERMEDIATE CODE: A61 Effective date: 20140415 |
|
R150 | Certificate of patent or registration of utility model |
Ref document number: 5528147 Country of ref document: JP Free format text: JAPANESE INTERMEDIATE CODE: R150 |
|
R250 | Receipt of annual fees |
Free format text: JAPANESE INTERMEDIATE CODE: R250 |
|
R250 | Receipt of annual fees |
Free format text: JAPANESE INTERMEDIATE CODE: R250 |
|
R250 | Receipt of annual fees |
Free format text: JAPANESE INTERMEDIATE CODE: R250 |
|
R250 | Receipt of annual fees |
Free format text: JAPANESE INTERMEDIATE CODE: R250 |
|
R250 | Receipt of annual fees |
Free format text: JAPANESE INTERMEDIATE CODE: R250 |
|
R250 | Receipt of annual fees |
Free format text: JAPANESE INTERMEDIATE CODE: R250 |
|
R250 | Receipt of annual fees |
Free format text: JAPANESE INTERMEDIATE CODE: R250 |
|
R250 | Receipt of annual fees |
Free format text: JAPANESE INTERMEDIATE CODE: R250 |