JP4268151B2 - Production management apparatus, production management program, and production management method - Google Patents

Production management apparatus, production management program, and production management method Download PDF

Info

Publication number
JP4268151B2
JP4268151B2 JP2005125330A JP2005125330A JP4268151B2 JP 4268151 B2 JP4268151 B2 JP 4268151B2 JP 2005125330 A JP2005125330 A JP 2005125330A JP 2005125330 A JP2005125330 A JP 2005125330A JP 4268151 B2 JP4268151 B2 JP 4268151B2
Authority
JP
Japan
Prior art keywords
production
production management
status
pile
information
Prior art date
Legal status (The legal status is an assumption and is not a legal conclusion. Google has not performed a legal analysis and makes no representation as to the accuracy of the status listed.)
Active
Application number
JP2005125330A
Other languages
Japanese (ja)
Other versions
JP2006139751A (en
Inventor
良夫 二ノ宮
Original Assignee
有限会社ティーピクスシステムズ
Priority date (The priority date is an assumption and is not a legal conclusion. Google has not performed a legal analysis and makes no representation as to the accuracy of the date listed.)
Filing date
Publication date
Application filed by 有限会社ティーピクスシステムズ filed Critical 有限会社ティーピクスシステムズ
Priority to JP2005125330A priority Critical patent/JP4268151B2/en
Priority to KR1020060007732A priority patent/KR20060101220A/en
Priority to US11/342,362 priority patent/US20060212323A1/en
Publication of JP2006139751A publication Critical patent/JP2006139751A/en
Application granted granted Critical
Publication of JP4268151B2 publication Critical patent/JP4268151B2/en
Active legal-status Critical Current
Anticipated expiration legal-status Critical

Links

Images

Classifications

    • YGENERAL TAGGING OF NEW TECHNOLOGICAL DEVELOPMENTS; GENERAL TAGGING OF CROSS-SECTIONAL TECHNOLOGIES SPANNING OVER SEVERAL SECTIONS OF THE IPC; TECHNICAL SUBJECTS COVERED BY FORMER USPC CROSS-REFERENCE ART COLLECTIONS [XRACs] AND DIGESTS
    • Y02TECHNOLOGIES OR APPLICATIONS FOR MITIGATION OR ADAPTATION AGAINST CLIMATE CHANGE
    • Y02PCLIMATE CHANGE MITIGATION TECHNOLOGIES IN THE PRODUCTION OR PROCESSING OF GOODS
    • Y02P90/00Enabling technologies with a potential contribution to greenhouse gas [GHG] emissions mitigation
    • Y02P90/30Computing systems specially adapted for manufacturing

Landscapes

  • General Factory Administration (AREA)
  • Management, Administration, Business Operations System, And Electronic Commerce (AREA)

Description

本発明は、生産管理装置、生産管理用プログラム及び生産管理方法に係り、特に、中間工程において現実にあわせてフレキシブルに生産管理を行うことが出来る生産管理装置、生産管理用プログラム、生産管理用プログラムを記録したコンピュータ読み取り可能な記録媒体及び生産管理方法に関する。   The present invention relates to a production management apparatus, a production management program, and a production management method, and in particular, a production management apparatus, a production management program, and a production management program capable of performing production management flexibly according to reality in an intermediate process. The present invention relates to a computer-readable recording medium that records the above and a production management method.

従来、生産管理装置では、個別の職場における生産管理用として、例えば、ガント・チャート方式等の中間工程の図表を表示して、これに基づき個別の案件につき具体的日程を立てて必要作業を消化する方法がとられていた。   Conventionally, production management devices display intermediate process charts such as the Gantt chart method for production management in individual workplaces, and based on this, schedule specific schedules for individual projects and digest necessary work. The way to do was taken.

しかし、従来のこれらの方式では単に実行しなければならない項目が日程に関連づけて記載されているのみであり、実際の作業を行おうとすると部品が集結しておらず作業が出来ないという問題があった。この場合に個別の職場においては、従業員、生産設備を有効に働かせるために、近日中に作業しなければならない部品を先に製作することがよく行われるが、その場合にも部品が集結しているか否か分からず混乱することが多かった。   However, in these conventional methods, the items that must be executed are simply described in association with the schedule, and there is a problem that the parts are not gathered and the work cannot be performed if an actual work is performed. It was. In this case, in order to make effective use of employees and production facilities in individual workplaces, parts that must be worked on in the near future are often produced first. I was often confused about whether or not it was.

この点について、ガント・チャート方式を採用した生産計画について、効率的な作業管理方法を提供するために、作業対象設備が付された地図を表示する方法、ウィンドをポップアップで開く方法等の数々の提案がなされている。(特許文献1、2参照)。しかし、生産準備が整っているか否かについてシステム的に対応した文献は見当たらない。より具体的には、生産管理が行われる個別の職場においては、日々刻々と変化する各工程実績データに応じて、その時々において着手可能な工程を適確に把握したいというニーズが明らかにある。にもかかわらず、数千点から数万点に及ぶ部品や各工程の情報を反映して、当該職場における工程についての着手可否をわかりやすく表示するようなシステムは提供されていない。
特開2004−54716号公報 特開2004−164408号公報
In this regard, in order to provide an efficient work management method for production plans that employ the Gantt chart method, there are numerous methods such as a method for displaying a map with work target equipment and a method for opening a window in a pop-up. Proposals have been made. (See Patent Documents 1 and 2). However, there is no literature that systematically addresses whether or not production is ready. More specifically, in individual workplaces where production management is performed, there is a clear need to accurately grasp the processes that can be started from time to time according to each process performance data that changes every day. Nevertheless, no system has been provided that reflects the information on parts and processes from thousands to tens of thousands of points and displays whether or not the process in the workplace can be started.
JP 2004-54716 A JP 2004-164408 A

本発明は、生産管理が行われる個別の職場において、生産準備が整っているか否かを各工程の実績データに基づいて自動的に算出し、具体的に対応しやすいように表示することにより、効率よく生産管理が行える生産管理装置、生産管理用プログラム、生産管理用プログラムを記録したコンピュータ読み取り可能な記録媒体及び生産管理方法を提供することを目的とする。   The present invention automatically calculates whether or not production preparation is complete in an individual workplace where production management is performed based on the results data of each process, and displays it so that it can be easily dealt with specifically, It is an object of the present invention to provide a production management apparatus capable of efficiently managing production, a production management program, a computer-readable recording medium recording the production management program, and a production management method.

上記の課題を解決するため、本発明は以下のものを提供する。
(1)生産管理装置であって、生産計画に対して、資材または部品に関しての入荷または完成の、予定または実績を含む各工程情報の入力をする各工程情報入力手段と、前記入力をされた各工程情報及び前記生産計画の生産管理情報を記憶する記憶手段と、前記記憶手段に記憶されている各工程情報と生産管理情報とに基づいて、調査希望時の生産準備状況の算出をする生産準備状況算出手段と、前記算出をされた生産準備状況および前記生産管理情報の表示をする生産状況表示手段と、を備えたことを特徴とする生産管理装置。
In order to solve the above problems, the present invention provides the following.
(1) It is a production management device, and each of the process information input means for inputting each process information including a schedule or a record of arrival or completion of materials or parts with respect to the production plan is input Production for calculating production preparation status at the time of survey request based on storage means for storing each process information and production management information of the production plan, and each process information and production management information stored in the storage means A production management apparatus comprising: a preparation status calculation means; and a production status display means for displaying the calculated production preparation status and the production management information.

調査希望時とは、生産管理装置のユーザが生産準備状況等について調査したい時をいう。生産する品種によって時は時間単位である場合、日単位の場合もある。   The survey request time is when the user of the production management apparatus wants to investigate the production preparation status and the like. Depending on the varieties to be produced, time may be in hours or in days.

(2)(1)に記載の生産管理装置であって、前記生産計画の生産管理情報に基づいて山積状況の算出をする山積状況算出手段と、前記山積状況を前記生産準備状況および前記生産管理情報と関連付けて表示する山積状況表示手段と、をさらに備えたことを特徴とする生産管理装置。   (2) The production management device according to (1), wherein the mountain status is calculated based on the production management information of the production plan, the mass status is the production preparation status and the production management. A production management apparatus, further comprising: a pile state display means for displaying in association with information.

(3)(2)に記載の生産管理装置であって、通信回線を介して、少なくとも1つの端末から前記各工程情報の受信をする受信入力手段をさらに備え、前記受信をした各工程情報ならびに前記記憶手段に記憶されている生産管理情報に基づいて、前記生産準備状況算出手段は調査希望時の生産準備状況の算出をし、前記山積状況算出手段は調査希望時の山積状況の算出をすることを特徴とする生産管理装置。   (3) The production management device according to (2), further comprising reception input means for receiving each process information from at least one terminal via a communication line, and each received process information and Based on the production management information stored in the storage means, the production preparation status calculation means calculates the production preparation status when the survey is desired, and the pile status calculation means calculates the pile status when the survey is desired. Production management device characterized by that.

(4)(2)又は(3)のいずれかに記載の生産管理装置であって、所定の資材あるいは部品に関して、前記表示をされた生産管理情報の変更入力をする変更入力手段をさらに備え、前記変更入力をされた生産管理情報に基づいて、前記生産準備状況算出手段は調査希望時の生産準備状況の算出をし、前記山積状況算出手段は調査希望時の山積状況の算出をすることを特徴とする生産管理装置。   (4) The production management apparatus according to any one of (2) and (3), further comprising a change input means for inputting a change in the displayed production management information for a predetermined material or part, Based on the changed production management information, the production preparation status calculation means calculates the production preparation status when the survey is desired, and the pile status calculation means calculates the pile status when the survey is desired. A production management device.

(5)(1)から(4)のいずれかに記載の生産管理装置であって生産資源情報入力手段をさらに備え、前記記憶手段は、前記生産資源情報をさらに記憶し、前記生産準備状況算出手段は、前記記憶手段に記憶された生産資源情報もあわせて、前記調査希望時の生産準備状況の算出をすることを特徴とする生産管理装置。   (5) The production management apparatus according to any one of (1) to (4), further including production resource information input means, wherein the storage means further stores the production resource information, and calculates the production preparation status The means for calculating the production preparation status at the time of the survey request together with the production resource information stored in the storage means.

(6)(1)から(5)のいずれかに記載の生産管理装置であって、前記生産準備状況算出手段は、前記調査希望時の前後のあらかじめ定められた期間内における生産準備状況の算出をし、前記山積状況算出手段は、前記調査希望時の前後のあらかじめ定められた期間内における山積状況の算出をすることを特徴とする生産管理装置。   (6) The production management apparatus according to any one of (1) to (5), wherein the production preparation status calculation unit calculates a production preparation status within a predetermined period before and after the survey request. In the production management apparatus, the pile condition calculation means calculates the pile condition within a predetermined period before and after the survey request.

(7)生産管理装置としてコンピュータを、生産計画に対して、資材または部品に関しての入荷または完成の、予定または実績を含む各工程情報の入力をする各工程情報入力手段、前記入力をされた各工程情報及び前記生産計画の生産管理情報を記憶する記憶手段、前記記憶手段に記憶されている各工程情報と生産管理情報とに基づいて、調査希望時の生産準備状況の算出をする生産準備状況算出手段、及び前記算出をされた生産準備状況および前記生産管理情報の表示をする生産状況表示手段、として機能させることを特徴とする生産管理用プログラム。   (7) A computer as a production management apparatus, each process information input means for inputting each process information including a schedule or a record of arrival or completion of materials or parts with respect to a production plan, Storage means for storing process information and production management information of the production plan, production preparation status for calculating the production preparation status at the time of survey request based on each process information and production management information stored in the storage means A production management program which functions as a calculation means and a production status display means for displaying the calculated production preparation status and the production management information.

(8)(7)に記載の生産管理用プログラムであって、前記コンピュータを、前記生産計画の生産管理情報に基づいて山積状況の算出をする山積状況算出手段、前記山積状況を前記生産準備状況および前記生産管理情報と関連付けて表示する山積状況表示手段、としてさらに機能させることを特徴とする生産管理用プログラム。   (8) The production management program according to (7), wherein the computer is configured to calculate a pile state based on production management information of the production plan, and the pile state is the production preparation state. And a production status display means for displaying in association with the production management information.

(9)(8)に記載の生産管理用プログラムであって、前記コンピュータを、通信回線を介して、少なくとも1つの端末から前記各工程情報の受信をする受信入力手段としてさらに機能させ、前記受信をした各工程情報ならびに前記記憶手段に記憶されている生産管理情報に基づいて、前記生産準備状況算出手段に調査希望時の生産準備状況の算出をさせ、前記山積状況算出手段に調査希望時の山積状況の算出をさせることを特徴とする生産管理用プログラム。   (9) The production management program according to (8), wherein the computer further functions as reception input means for receiving the process information from at least one terminal via a communication line, and the reception Based on each process information and the production management information stored in the storage means, the production preparation status calculation means calculates the production preparation status at the time of the survey request, and the pile status calculation means at the time of the survey request. A production management program characterized by the calculation of the state of piles.

(10)(8)又は(9)のいずれかに記載の生産管理用プログラムであって、前記コンピュータを、所定の資材あるいは部品に関して、前記表示をされた生産管理情報の変更入力をする変更入力手段としてさらに機能させ、前記変更入力をされた生産管理情報に基づいて、前記生産準備状況算出手段に、さらに調査希望時の生産準備状況の算出をさせ、前記山積状況の算出手段に、さらに山積状況の算出をさせることを特徴とする生産管理用プログラム。   (10) The production management program according to any one of (8) and (9), wherein the computer inputs a change input for changing the displayed production management information regarding a predetermined material or part. Further functioning as a means, based on the production management information that has been subjected to the change input, causing the production preparation status calculation means to further calculate the production preparation status at the time of survey request, and causing the pile status calculation means to further A production management program characterized by causing the situation to be calculated.

(11)(7)から(10)のいずれかに記載の生産管理用プログラムであって、前記コンピュータを、生産資源情報入力手段としてさらに機能させ、前記入力された生産資源情報をさらに記憶手段に記憶させ、前記生産準備状況算出手段に、さらに前記記憶手段に記憶された生産資源情報もあわせて、前記調査希望時の生産準備状況の算出をさせることを特徴とする生産管理用プログラム。   (11) The production management program according to any one of (7) to (10), further causing the computer to function as a production resource information input unit, and further storing the input production resource information in a storage unit A production management program for storing, and causing the production preparation status calculation means to further calculate the production preparation status when the survey is desired, together with the production resource information stored in the storage means.

(12)(7)から(11)のいずれかに記載の生産管理用プログラムであって、前記生産準備状況算出手段に、前記調査希望時の前後のあらかじめ定められた期間内の生産準備状況の算出をさせ、前記山積状況算出手段に、前記調査希望時の前後のあらかじめ定められた期間内における山積状況の算出をさせる、ことを特徴とする生産管理用プログラム。   (12) The production management program according to any one of (7) to (11), wherein the production preparation status calculation means is configured to store the production preparation status within a predetermined period before and after the survey request. A production management program, comprising: calculating and causing the pile state calculation means to calculate a pile state within a predetermined period before and after the survey request.

(13)(7)から(12)のいずれかに記載の生産管理用プログラムを記録したコンピュータ読み取り可能な記録媒体。   (13) A computer-readable recording medium on which the production management program according to any one of (7) to (12) is recorded.

(14)コンピュータを用いた生産管理方法であって、生産計画に対して、資材または部品に関しての入荷または完成の、予定または実績を含む各工程情報の入力をする各工程情報入力ステップと、前記入力をされた各工程情報及び前記生産計画の生産管理情報を記憶する記憶ステップと、前記記憶をした各工程情報と生産管理情報とに基づいて、調査希望時の生産準備状況の算出をする生産準備状況算出ステップと、前記算出をされた生産準備状況および前記生産管理情報の表示をする生産状況表示ステップと、を有することを特徴とする生産管理方法。   (14) A production management method using a computer, each process information input step for inputting each process information including a schedule or a record of arrival or completion of materials or parts with respect to a production plan, A storage step for storing each input process information and production management information of the production plan, and a production for calculating a production preparation status at the time of survey request based on each stored process information and production management information A production management method, comprising: a preparation status calculation step; and a production status display step for displaying the calculated production preparation status and the production management information.

(15)(14)に記載のコンピュータを用いた生産管理方法であって、前記生産計画の生産管理情報に基づいて山積状況の算出をする山積状況算出ステップと、前記山積状況を前記生産準備状況および前記生産管理情報と関連付けて表示する山積状況表示ステップと、をさらに有することを特徴とする生産管理方法。   (15) A production management method using a computer according to (14), wherein a pile state calculation step for calculating a pile state based on production management information of the production plan, and the pile state is referred to as the production preparation state. And a pile status display step of displaying in association with the production management information.

(16)(15)に記載のコンピュータを用いた生産管理方法であって、通信回線を介して、少なくとも1つの端末から前記各工程情報の受信をする受信入力ステップをさらに有し、前記受信をした前記各工程情報に基づいて、前記生産準備状況算出ステップにおいて調査希望時の生産準備状況の算出をし、前記山積状況算出ステップにおいて調査希望時の山積状況の算出をすることを特徴とする生産管理用方法。   (16) A production management method using a computer according to (15), further comprising a reception input step of receiving each process information from at least one terminal via a communication line, wherein the reception is performed. The production preparation status at the time of the survey request is calculated in the production preparation status calculation step based on each of the process information, and the mountain status at the time of the survey request is calculated in the mountain status calculation step. Administrative method.

(17)(15)又は(16)のいずれかに記載のコンピュータを用いた生産管理方法であって、所定の資材あるいは部品に関して、前記表示をされた生産管理情報の変更入力をする変更入力ステップをさらに有し、前記変更入力をされた生産管理情報に基づいて、前記生産準備状況算出ステップにおいて、調査希望時の生産準備状況の算出をし、前記山積状況算出ステップにおいて、山積状況の算出をすることを特徴とする生産管理方法。   (17) A production management method using the computer according to any one of (15) and (16), wherein a change input step of inputting a change of the displayed production management information for a predetermined material or part And calculating the production preparation status when the survey is desired in the production preparation status calculation step based on the production management information for which the change has been input, and calculating the mountain status in the mountain status calculation step. A production management method characterized by:

(18)(14)から(17)のいずれかに記載のコンピュータを用いた生産管理方法であって、生産資源情報入力をするステップをさらに有し、前記記憶ステップにおいて前記生産資源情報をさらに記憶し、前記生産準備状況算出ステップにおいて、前記記憶ステップにおいて記憶された生産資源情報もあわせて、前記調査希望時の生産準備状況の算出をすることを特徴とする生産管理方法。   (18) A production management method using the computer according to any one of (14) to (17), further comprising a step of inputting production resource information, and further storing the production resource information in the storage step. In the production preparation status calculation step, the production preparation status at the time of the survey request is calculated together with the production resource information stored in the storage step.

(19)(14)から(18)のいずれかに記載の生産管理方法であって、前記生産準備状況算出ステップにおいて、前記調査希望時の前後のあらかじめ定められた期間内の生産準備状況における算出をし、前記山積状況算出ステップにおいて、前記調査希望時の前後のあらかじめ定められた期間内における山積状況の算出をすることを特徴とする生産管理方法。   (19) The production management method according to any one of (14) to (18), wherein, in the production preparation status calculation step, calculation in a production preparation status within a predetermined period before and after the survey is requested And the step of calculating the pile state calculates the pile state within a predetermined period before and after the survey request.

(1)に記載の発明による生産管理装置を用いることにより次のような効果が期待できる。各工程情報入力手段により、生産計画に対して、資材または部品に関しての入荷または完成の、予定または実績を含む各工程情報の入力をする。入力をされた各工程情報及び前記生産計画の生産管理情報は記憶手段に記憶される。記憶手段に記憶されている各工程情報と生産管理情報とに基づいて、生産準備状況算出手段により、調査希望時の生産準備状況が算出される。生産状況表示手段により算出をされた生産準備状況および前記生産管理情報が表示される。生産管理が行われる個別の職場において、生産準備が整っているか否かを各工程の実績データに基づいて自動的に算出し、ユーザが管理する職場に関するものが選択されて表示される。その結果、個別の職場の管理者はその時点の各工程実績に応じて適切に次の工程の可否が判断できるようになるので、効率よく生産管理を行うことが出来る。この場合、生産準備状況ならびに生産状況表示手段によるその表示は、部品がすべて入荷して準備が整っている場合は、例えば「○」等のように直感的に判断できるように表示することが望ましい。同様に、部品が一部入荷して作業に取り掛かれる場合は、例えば「△」等のように表示し、部品がまったく入荷してなくて作業に取り掛かれない場合は、例えば「×」等のように表示することにより、個別の職場の管理者は直感的に判断することができる。   The following effects can be expected by using the production management apparatus according to the invention described in (1). Each process information input means inputs each process information including a schedule or a record of arrival or completion of materials or parts with respect to a production plan. The inputted process information and production management information of the production plan are stored in the storage means. Based on each process information and production management information stored in the storage means, the production preparation status when the survey is desired is calculated by the production preparation status calculation means. The production preparation status calculated by the production status display means and the production management information are displayed. In an individual workplace where production management is performed, whether or not production preparation is complete is automatically calculated based on the performance data of each process, and the items related to the workplace managed by the user are selected and displayed. As a result, an individual workplace manager can appropriately determine whether or not the next process can be performed in accordance with each process result at that time, so that production management can be performed efficiently. In this case, it is desirable that the display of the production preparation status and the production status display means is displayed so that it can be intuitively judged, for example, “○” when all the parts are received and ready. . Similarly, when a part is received and the work is started, for example, “△” or the like is displayed, and when the part is not received at all and the work cannot be started, for example, “X” or the like is displayed. By displaying like this, the manager of an individual workplace can judge intuitively.

(2)に記載の発明による生産管理装置を用いることにより次のような効果が期待できる。(1)に記載の発明による生産管理装置による効果に加えて、山積状況算出手段により、生産計画の生産管理情報に基づいて山積状況の算出をする。算出された山積状況を生産準備状況および生産管理情報と関連付けて山積状況表示手段により表示する。その結果、現場の管理者は生産準備状況が山積状況とあわせて総合的に判断することが出来る。また自分が担当する職場の負荷山積状況に基づいて、問題に対する対応がとり易くなる。   The following effects can be expected by using the production management device according to the invention described in (2). In addition to the effect of the production management device according to the invention described in (1), the mountain status is calculated based on the production management information of the production plan by the mountain status calculation means. The calculated pile status is displayed by the pile status display means in association with the production preparation status and production management information. As a result, the on-site manager can comprehensively judge the production preparation status together with the pile status. In addition, it becomes easier to respond to problems based on the load pile situation of the workplace in charge.

(3)に記載の発明による生産管理装置を用いることにより次のような効果が期待できる。受信入力手段は、通信回線を介して、少なくとも1つの端末から前記各工程情報を受信する。すなわち、例えば、部品の納入業者の端末から、通信回線を介して直接前記各工程情報を受信する。このため、当該部品の仕入れを管理している資材担当者が当該業者に部品ごとに納期を問い合わせ入力するのに比して大幅に人件費を節約できる。また、インプットミスなどによる混乱を防ぐことも出来る。さらに受信をした前記各工程情報に基づいて、前記生産準備状況算出手段は調査希望時の生産準備状況の算出をし、前記山積状況算出手段は調査希望時の山積状況の算出をする。このことにより外部の納入業者の予定が変化した場合においても、資材担当者は即座にその影響を反映した生産準備状況および山積状況を表示手段により確認し、適確な対応を検討することが出来る。   The following effects can be expected by using the production management apparatus according to the invention described in (3). The reception input means receives the process information from at least one terminal via a communication line. That is, for example, the process information is received directly from a terminal of a parts supplier via a communication line. For this reason, labor costs can be greatly reduced as compared with the case where the person in charge of materials managing the purchase of the part inquires and inputs the delivery date to the supplier for each part. It can also prevent confusion due to input errors. Further, based on the received process information, the production preparation status calculation means calculates the production preparation status when the survey is desired, and the pile status calculation means calculates the pile status when the survey is desired. As a result, even if the schedule of an external supplier changes, the material manager can immediately check the production preparation status and the pile status reflecting the effect on the display means, and can consider an appropriate response. .

より具体的には、部品または外注加工をする業者の端末は通信回線を介して生産管理装置に接続される。普通、当該業者には部品または外注加工の発注伝票とともにその要求納期が示される。この要求に対して、業者が対応できない場合は対応できる納期を端末より入力する。或いは、納期を変えずに対応可能な納入数に変更して端末より入力することもある。このような納期の延伸願いや納入数の変更願いがあった場合に、生産計画上問題になるか否かを発見することが非常に重要である。即ち、これらの変更があったとしても、生産計画上予測された歩留まりの範囲内であったり、工程上の余裕の範囲内であれば、その後の工程は予定通り実施できる。或いは、引き当て可能な在庫が存在すれば、同様に後の工程は予定通り実施できる。ところが、そうでなければ、後の工程の変更が必要になる。生産管理が行われる各職場においては、このような問題があるのか否かをすぐに発見することが必要であり、本発明による生産管理装置を用いることにより、生産準備状況算出手段、山積状況算出手段によりその影響が再計算されて表示することができる。後述するように、本発明による生産管理装置は、例えばある工程の納期の延伸によりその工程の納期がそれに続く工程の着手日より後になった場合には、その工程の計画バーが太線枠で表示されると共に工程間を結ぶ線が後戻りして表示されるため、各職場の管理者は一目で問題のある箇所を発見できる。このような効果は、特にデータ量が多い場合に顕著である。この様にして生産上の問題点を効率よく把握することが出来る。   More specifically, a part or a terminal of a contractor who performs outsourcing is connected to the production management device via a communication line. Usually, the required delivery date is shown to the contractor together with the order slip for parts or outsourcing. If the supplier cannot respond to this request, a delivery date that can be handled is input from the terminal. Alternatively, the number of deliveries can be changed without changing the delivery date and input from the terminal. It is very important to discover whether there is a problem in production planning when there is a desire to extend the delivery date or change the number of deliveries. In other words, even if these changes are made, the subsequent steps can be performed as scheduled as long as they are within the range of yield predicted in the production plan or within the margin of the process. Alternatively, if there is a stock that can be allocated, the subsequent steps can be performed as scheduled. However, if that is not the case, a later process change is required. In each workplace where production management is performed, it is necessary to immediately find out whether or not there is such a problem. By using the production management apparatus according to the present invention, production preparation status calculation means, pile status calculation The effect can be recalculated and displayed by the means. As will be described later, the production management apparatus according to the present invention displays a plan bar of a process in a bold line frame when the delivery date of the process comes after the start date of the subsequent process due to, for example, extension of the delivery date of the process At the same time, since the lines connecting the processes are displayed backwards, the manager of each workplace can find the problematic part at a glance. Such an effect is particularly remarkable when the amount of data is large. In this way, production problems can be grasped efficiently.

(4)に記載の発明による生産管理装置を用いることにより次のような効果が期待できる。(2)又は(3)のいずれかに記載の発明による生産管理装置によって、生産準備状況ならびに山積状況を見た後、生産場所等を変更することにより対策が可能と判断した場合に変更入力手段により変更入力をすることが出来る。あるいは、表示された生産管理情報の中からある生産工程を指定して着手日を変更することも出来る。変更入力されると、変更入力をされた生産管理情報に基づいて、生産準備状況算出手段は調査希望時の生産準備状況の算出をし、山積状況の算出手段は山積状況の算出をする。その結果、変更したことによる生産状況および山積状況の影響度合をあらかじめ確認してから現実の変更指示を出すことが可能となる。   By using the production management apparatus according to the invention described in (4), the following effects can be expected. Change input means when it is determined that measures can be taken by changing the production location, etc. after viewing the production preparation status and the pile status by the production management device according to the invention described in either (2) or (3) You can input changes. Alternatively, the start date can be changed by designating a certain production process from the displayed production management information. When the change is input, the production preparation status calculation means calculates the production preparation status when the survey is requested based on the changed production management information, and the pile status calculation means calculates the pile status. As a result, it is possible to issue an actual change instruction after confirming in advance the degree of influence of the production situation and the pile situation due to the change.

(5)に記載の発明による生産管理装置を用いることにより次のような効果が期待できる。(1)から(4)のいずれかに記載の発明による生産管理装置による効果に加えて、生産資源情報入力手段をさらに備えている。さらに、生産準備状況算出手段は記憶手段に記憶された生産資源情報も合わせて前記調査希望時の生産準備状況の算出をする。ここで、生産資源は、例えば人、設備、冶工具等の生産に必要な資源を含む。生産品種によっては生産資源が生産工程上の決め手となるものもある。かかる場合には部品等の情報も合わせて総合的に現場の管理者等が判断することが出来る利点がある。   The following effects can be expected by using the production management apparatus according to the invention described in (5). In addition to the effects of the production management device according to any one of (1) to (4), the apparatus further includes production resource information input means. Further, the production preparation status calculation means calculates the production preparation status at the time of the survey request together with the production resource information stored in the storage means. Here, the production resources include, for example, resources necessary for production of people, equipment, jigs and tools. For some production varieties, production resources are the decisive factor in the production process. In such a case, there is an advantage that an on-site manager or the like can make a comprehensive judgment together with information on parts and the like.

(6)に記載の発明による生産管理装置を用いることにより次のような効果が期待できる。(1)から(5)に記載の発明による生産管理装置において、生産準備状況算出手段は、調査希望時の前後のあらかじめ定められた期間内の生産準備状況の算出をし、山積状況算出手段は、前記調査希望時の前後のあらかじめ定められた期間内における山積状況の算出をする。生産管理の対象となる生産品種により、あらかじめ定められた期間は異なる。例えば、前記調査希望時から前後1週間の期間を指定することも出来る。最もユーザが使いやすく生産品種に最も適した期間をあらかじめ定めることにより時間も含めて総合的にもっとも適した対応を検討することが出来る。   The following effects can be expected by using the production management device according to the invention described in (6). In the production management device according to the invention described in (1) to (5), the production preparation status calculation means calculates the production preparation status within a predetermined period before and after the survey request, and the pile status calculation means Then, the pile state is calculated within a predetermined period before and after the survey request. The predetermined period varies depending on the production type to be managed. For example, a period of one week before and after the survey request can be specified. By predetermining the period most suitable for the production type that is most user-friendly, it is possible to examine the most suitable response comprehensively including time.

また、(7)から(12)の発明の生産管理用プログラムをコンピュータに読み込ませて、上記(1)から(6)の発明と同様な手段を機能させることにより同様な効果が期待できる。   Similar effects can be expected by causing the computer to read the production management program of the inventions (7) to (12) and causing the same means as those of the inventions (1) to (6) to function.

さらに、(13)の発明の生産管理用プログラムを記録したコンピュータ読み取り可能な記録媒体をコンピュータに読み込ませて、上記(1)から(6)の発明と同様な手段を機能させることにより同様な効果が期待できる。   Further, the same effect can be obtained by causing a computer to read a computer-readable recording medium in which the production management program of the invention of (13) is recorded and causing the same means as those of the inventions of (1) to (6) to function. Can be expected.

もしくは、(14)から(19)の発明のコンピュータを用いた生産管理方法によっても、同様な効果が期待できる。   Alternatively, the same effect can be expected by the production management method using the computer according to the inventions of (14) to (19).

本発明によれば、調査希望時の生産準備状況が各工程実績情報に基づいて自動的に算出され表示される。また、山積状況を生産準備状況および生産管理情報と関連付けて表示される。その結果現場の管理者は生産準備状況を山積状況とあわせて総合的に判断することが出来る。また、生産準備状況ならびに山積状況を見た後、生産場所等を変更することにより対策が可能と判断した場合に変更入力をすることが出来る。変更入力されると、調査希望時の生産準備状況と山積状況が表示される。その結果、個別の職場の管理者は変更する方が良いか否か適切に判断できるので、効率よく生産管理をおこなうことが出来る。   According to the present invention, the production preparation status at the time of survey request is automatically calculated and displayed based on each process result information. In addition, the pile status is displayed in association with the production preparation status and production management information. As a result, the on-site manager can comprehensively judge the production preparation status together with the pile status. In addition, after looking at the production preparation status and the pile status, it is possible to input a change when it is determined that measures can be taken by changing the production location or the like. When the change is input, the production preparation status and the pile status when the survey is desired are displayed. As a result, the manager of the individual workplace can appropriately determine whether or not it is better to change, so that production management can be performed efficiently.

また、生産品種によっては生産資源が生産工程上の決め手となる場合もある。かかる場合には生産資源の完成時期と部品等の情報も合わせて総合的に現場の管理者等が判断することが出来る点で有利である。さらに、調査希望時の前後のあらかじめ定められた期間内の生産準備状況、山積状況が表示される。このように、生産準備が整っているか否かを各工程実績情報に基づいて自動的に算出し、対応しやすいように表示される。その結果、現場の管理者がより現実に即した生産管理をすることが出来る生産管理装置、生産管理用プログラム、生産管理用プログラムを記録したコンピュータ読み取り可能な記録媒体及び生産管理方法を提供することが出来る。   Depending on the production type, the production resource may be the decisive factor in the production process. In such a case, it is advantageous in that an on-site manager or the like can comprehensively determine the completion time of production resources and information on parts and the like. In addition, the production preparation status and the pile status within a predetermined period before and after the survey request is displayed. In this way, whether or not production preparation is complete is automatically calculated based on each process result information, and displayed so that it can be easily handled. As a result, it is possible to provide a production management apparatus, a production management program, a computer readable recording medium on which a production management program is recorded, and a production management method, which can be managed more realistically by a site manager. I can do it.

以下、本発明を実施するための最良の形態について図を参照しながら説明する。なお、これはあくまでも一例であって、本発明の技術的範囲はこれに限られるものではない。   Hereinafter, the best mode for carrying out the present invention will be described with reference to the drawings. This is merely an example, and the technical scope of the present invention is not limited to this.

図1は本発明に係る生産管理装置1の構成を示すブロック図である。本発明の生産管理装置はコンピュータを用いて実現することが望ましい。バス15を介して制御手段11、記憶手段12、表示手段14、入力手段13及び受信入力手段16が結ばれており、制御手段11は生産管理装置全体を制御し、例えば、記憶手段12に記憶されたプログラムを読み出して実行することにより、上記ハードウエアと協働して後述する各種手段を実現している。また、受信入力手段16は通信回線18を介して端末20に接続されている。   FIG. 1 is a block diagram showing the configuration of a production management apparatus 1 according to the present invention. The production management apparatus of the present invention is preferably realized using a computer. The control means 11, the storage means 12, the display means 14, the input means 13 and the reception input means 16 are connected via the bus 15. The control means 11 controls the entire production management apparatus, for example, stored in the storage means 12. By reading and executing the read program, various means described later are realized in cooperation with the hardware. The reception input means 16 is connected to the terminal 20 via the communication line 18.

制御手段11には、生産準備状況算出手段112と山積状況算出手段114とが含まれる。入力手段13には、各工程情報入力手段132と変更入力手段134とが含まれる。また、表示手段14には、生産準備状況表示手段142、山積状況表示手段144が含まれる。   The control means 11 includes a production preparation status calculation means 112 and a pile status calculation means 114. The input unit 13 includes each process information input unit 132 and a change input unit 134. The display means 14 includes a production preparation status display means 142 and a pile status display means 144.

記憶手段12はハードディスクまたは半導体メモリで実現することが出来、発注した部品情報、その他生産管理装置として必要な情報を記憶する。入力手段13は、キーボード、スキャナー、または、通信回線を用いた入力受付手段(例えば、LAN)等で実現することが出来る。表示手段14は液晶ディスプレイ、ブラウン管CRT等により実現することが出来る。また、受信入力手段16は通信用のモデムやTA、ルーター等の通信用ハードウエアおよび関係ソフトウエアにより実現することができる。通信回線18は一般公衆回線やインターネットによることが出来、端末20はパーソナルコンピュータ等により実現可能である。   The storage means 12 can be realized by a hard disk or a semiconductor memory, and stores ordered part information and other information necessary as a production management device. The input unit 13 can be realized by a keyboard, a scanner, or an input receiving unit (for example, LAN) using a communication line. The display means 14 can be realized by a liquid crystal display, a cathode ray tube CRT or the like. The reception input means 16 can be realized by communication hardware such as a communication modem, TA, and router, and related software. The communication line 18 can be a general public line or the Internet, and the terminal 20 can be realized by a personal computer or the like.

図2は、本発明に係る生産管理装置1の動作を示すフローチャートである。図3は、本発明に係る生産管理装置1のガント・チャート方式による一例を生産準備状況表示手段142、山積状況表示手段144により表示された図である。図4は本発明に係る生産管理装置1の表示装置14に表示される生産管理情報明細を示す図である。
ここで、生産管理情報とは、具体的には例えば、製番、製品構成表、使用する子部品の在庫・生産場所・発注先・完成予定のことである。また、生産準備状況とは、各工程に生産準備が整っているか否かを表す情報であり。より具体的には「○」、「△」、「×」のように表すことが出来る情報である。また、山積状況とは、具体的には例えば、日毎の各製造課における作業予定量の総和である。あるいは、山積状況は分かり易くするために、同日に作業しなければならない工程の数を数字で表すこともある。
FIG. 2 is a flowchart showing the operation of the production management apparatus 1 according to the present invention. FIG. 3 is a diagram showing an example of the production management apparatus 1 according to the present invention by the Gantt chart method displayed by the production preparation status display means 142 and the pile status display means 144. FIG. 4 is a diagram showing the details of the production management information displayed on the display device 14 of the production management apparatus 1 according to the present invention.
Here, the production management information specifically refers to, for example, the product number, the product configuration table, and the inventory / production location / ordering destination / completion schedule of the child parts to be used. The production preparation status is information indicating whether production preparation is complete in each process. More specifically, the information can be expressed as “◯”, “Δ”, “×”. In addition, the pile state is, for example, the total sum of scheduled work amounts in each manufacturing section for each day. Alternatively, the number of processes that must be performed on the same day may be represented by a number in order to make it easy to understand the piled state.

以下、本発明の生産管理装置1の動作、使用方法について説明する。まず、生産計画に対して、生産管理情報があらかじめ入力手段13により入力される。生産管理情報は生産する製品の種類により異なるが、例えば、複数の製番、その製番に関連する部品構成・部品名称・数量、部品の生産場所名、各部品または各工程の完成予定などである。次に、各工程情報入力手段132により、生産管理している資材または部品に関しての入荷または完成の、予定または実績を含む各工程情報の入力をする(S110)。また、受信入力手段16により通信回線18を介して、業者の端末20より直接入力されてもよい。そしてこれらの情報を記憶手段12により記憶する(S120)。各工程情報は情報が入手される度に、または一定の期間毎に集めて、各工程情報入力手段132により入力され記憶手段12に生産計画に関連付けて記憶される。   Hereinafter, operation | movement and the usage method of the production management apparatus 1 of this invention are demonstrated. First, production management information is input in advance by the input means 13 for a production plan. Production management information varies depending on the type of product to be produced. For example, there are multiple product numbers, part configurations / part names / quantities related to the product numbers, part production location names, and scheduled completion of each part or process. is there. Next, each process information input means 132 inputs each process information including a schedule or a record of arrival or completion of a material or part that is being managed (S110). Further, it may be directly input from the vendor terminal 20 by the reception input means 16 through the communication line 18. These pieces of information are stored in the storage unit 12 (S120). Each process information is collected every time information is obtained or at regular intervals, and is input by each process information input means 132 and stored in the storage means 12 in association with the production plan.

調査希望時を入力手段13により入力する(S130)。もっとも、調査希望時を入力する代わりに生産管理装置1に時計機能を持たせておき、現在時を入力されたものとして
以下の処理を進めることも出来る。また、生産管理をする対象の品種にもよるが、時の代わりに日であっても良い。
The time when the survey is desired is input by the input means 13 (S130). Of course, instead of inputting the desired survey time, the production management apparatus 1 may have a clock function, and the following processing can be performed assuming that the current time is input. Also, depending on the type of product to be managed, day may be used instead of time.

調査希望時が入力されると、生産準備状況算出手段112により記憶手段12に記憶されている各工程情報と生産管理情報とに基づいて、調査希望時の生産準備状況の算出をする(S140)。次に、生産準備状況表示手段142により、算出をされた生産準備状況および生産管理情報の表示をする(S150)。この際に、山積状況算出手段114により生産計画の生産管理情報に基づいて山積状況の算出をし(S160)、山積状況表示手段144により、山積状況を生産準備状況および前記生産管理情報と関連付けて日時の軸等を合わせて表示する(S162)ことが望ましい。   When the survey request time is input, the production preparation status calculation unit 112 calculates the production preparation status when the survey request is made based on each process information and production management information stored in the storage unit 12 (S140). . Next, the production preparation status display means 142 displays the calculated production preparation status and production management information (S150). At this time, the pile status calculation means 114 calculates the pile status based on the production management information of the production plan (S160), and the pile status display means 144 associates the pile status with the production preparation status and the production management information. It is desirable to display the date and time axes together (S162).

図3に、生産準備状況ならびに生産管理情報をガント・チャート方式で表示した一例を示す。図3では製番、枝番、部品または工程の名称、完成予定、数量、生産場所、注番などの生産管理情報が示されると共に、各部品または工程の伝票発行日、作業日程が表示されている。該当する伝票発行日は枠の中の灰色の四角で、作業日程は淡い灰色のブロックで示されている。また、調査希望時は4月7日となっており斜線で示した部分である。また、図中で太い実線は部品が次の工程で必要である関係を示す。図3に示すようにガント・チャート方式で表示することにより、全体的な作業の予定を把握する事が出来る。このような表示において、本発明による生産準備状況は生産準備状況算出手段112により算出され、その結果が生産準備状況表示手段142により、準備が整っている部品または工程は一目見て直観的に判断し易いように「○」で表示される。4月4日の製番「se03」・枝番「3」の「電装品」、4月6日の製番「se02」・枝番「9」の「支給」、「千石金属(有)」がこれに当たる。一方、準備が整っていない部品または工程は一目見て直観的に判断し易いように「×」で表示される。4月6日の製番「se01」・枝番「2」の「総組み立て」、4月7日の製番「se02」・枝番「7」の「外注加工」、「千石金属(有)」、4月12日の製番「se03」・枝番「2」の「総組み立て」、がこれにあたる。又、図示はされていないが、準備が一部整っていない部品または工程は一目見て直観的に判断し易いように「△」で表示される。   FIG. 3 shows an example in which the production preparation status and production management information are displayed in a Gantt chart system. In FIG. 3, production management information such as a product number, branch number, part or process name, completion schedule, quantity, production location, and order number is displayed, as well as slip issue date and work schedule for each part or process. Yes. The corresponding voucher issue date is indicated by a gray square in the frame, and the work schedule is indicated by a light gray block. In addition, when the survey is requested, it is April 7th, which is a hatched portion. In the figure, a thick solid line indicates a relationship in which the part is necessary in the next process. By displaying in the Gantt chart method as shown in FIG. 3, the overall work schedule can be grasped. In such a display, the production preparation status according to the present invention is calculated by the production preparation status calculation means 112, and the result is intuitively determined by the production preparation status display means 142 at a glance at which parts or processes are ready. “○” is displayed so that it is easy to do. “Electrical equipment” with production number “se03”, branch number “3” on April 4, “Supply”, “Sengoku Metal (Yes)” with production number “se02”, branch number “9” on April 6 Is this. On the other hand, a part or process that is not ready is displayed as “x” so that it can be easily judged intuitively. April 6 production number “se01”, branch number “2” “total assembly”, April 7 production number “se02”, branch number “7” “outsourcing”, “Sengoku Metal” "Production number" se03 "on April 12 and branch number" 2 "" total assembly "corresponds to this. Although not shown in the drawing, a part or process that is not fully prepared is displayed as “Δ” so that it can be easily judged intuitively.

このように、生産準備状況が一目見て直観的に判断し易いように表示されることにより生産現場の管理者は、今現在着手可能な工程を容易に知ることができる。   In this way, the production preparation status is displayed so that it can be easily judged intuitively at a glance, so that the manager of the production site can easily know the processes that can be started now.

図3の下段には、本発明の望ましい形態である山積状況が山積状況表示手段144により数字で表示されている。もちろん、グラフまたは色を変えて表示しても良い。本実施形態においては数字の単位は同日に作業しなければならない工程の数である。作業を多く抱え問題の所は濃い枠で示されている。特に4月12日時点では製造1課が特に多くの作業を抱えていることが分かる。このように、山積状況もあわせて知ることが出来、生産現場の管理者はより適切な判断をすることができる。例えば、図3の山積状況より、製造1課の作業が集中しているため計画上問題があることが判明する。このように問題がある場合は(S170)、例えば、生産場所をS1からS2に、すなわち作業が集中している製造1課から作業予定の無い製造2課に変更する(S180)。変更入力後、登録ボタンをクリックすると、変更された内容に従い再度生産準備状況が算出され、山積状況も再度計算されて表示される。表示を見て問題が無ければ変更後の計画に従って運用することが出来る。あるいは、製造1課の担当工程の一部の着手日を変更してもよい。このような場合には、図示はしていないが、マウスのドラッグ・アンド・ドロップ操作によりガント・チャート上の計画バーを移動させることによって実現してもよい。この場合にも上記と同様に生産準備状況及び山積状況が再度計算されて表示される。   In the lower part of FIG. 3, the mountain situation which is a desirable form of the present invention is displayed numerically by the mountain situation display means 144. Of course, the graph or the color may be changed for display. In this embodiment, the numerical unit is the number of steps that must be performed on the same day. There is a lot of work and the problem areas are shown in a dark frame. In particular, as of April 12, it can be seen that the Manufacturing Division 1 has a lot of work. In this way, it is also possible to know the state of the mountain, and the production site manager can make a more appropriate decision. For example, it can be seen from the mountain situation in FIG. 3 that there is a problem in the plan because the work in the first manufacturing section is concentrated. If there is a problem as described above (S170), for example, the production location is changed from S1 to S2, that is, from the manufacturing section 1 where the work is concentrated to the manufacturing section 2 where no work is scheduled (S180). When the registration button is clicked after the change input, the production preparation status is calculated again according to the changed content, and the pile status is also calculated and displayed again. If there is no problem with the display, it can be operated according to the plan after the change. Or you may change the starting date of a part of process in charge of manufacture 1 section. In such a case, although not shown, the plan bar on the Gantt chart may be moved by dragging and dropping the mouse. In this case as well, the production preparation status and the pile status are recalculated and displayed in the same manner as described above.

図3において、着手可能となっていない「×」が示された計画バーをクリックすると、生産管理情報明細が表示される。図3において、4月12日の製番「se03」・枝番「2」の「総組み立て」の計画バーをクリックした場合に表示される例が図4である。図4において、上段は問題の工程の部分の各生産管理項目を表示する。中段は問題の総組み立てを行うために必要な部品で在庫引き当てに当たる部品が使用可能か否かを示している。図4の例では、駆動装置は在庫が1個あり使用可能なことを示している。下段は各部品の製造状況を表している。   In FIG. 3, when a plan bar indicating “x” that cannot be started is clicked, the production management information details are displayed. In FIG. 3, FIG. 4 shows an example displayed when the “total assembly” plan bar of the product number “se03” / branch number “2” on April 12 is clicked. In FIG. 4, the upper part displays each production management item of the part of the problem process. The middle row shows whether or not the parts that are necessary for total assembly in question and that are used for inventory allocation are usable. In the example of FIG. 4, the drive device has one inventory and can be used. The lower row shows the manufacturing status of each part.

次に、図3の例では、4月12日の製番「se03」・枝番「5」の計画バーが太線枠で表示されているが、その原因は、製番「se03」・枝番「5」の機構ユニットの納品日(4月13日)が、製番「se03」・枝番「2」の着手日より後で、計画が逆転しているためである。これは、この例においては、業者である駒込工業(株)が直接受信入力手段16により各工程情報を入力したものである。また、この例では計画バーを太線枠で表示しているが、計画バー自体を赤色で表示するなど、色を変えて表示してもよい。また、製番「se03」・枝番「2」の計画が「×」になっているのは、枝番「3」の電装品と枝番「5」の機構ユニットがまだ完成していないため、製番「se03」・枝番「2」の総組み立ては、現在着手できないことを示している。この場合は、総組み立てと据え付け工事の計画を2日先に延伸しなければならない。もし、客先との関係で最後の据え付け工事を延伸することが出来なければ、もう一度駒込工業に早めるよう依頼するか、総組み立ての作業工期を短くする等の対策が必要である。駒込工業に早めるように依頼する場合は、このガント・チャート上で計画を左にドラッグ・アンド・ドロップすれば、また通信手段を使って、再度望ましい計画日を業者である駒込工業(株)に送ることが出来る。   Next, in the example of FIG. 3, the plan bar of the product number “se03” and branch number “5” on April 12 is displayed with a thick line frame. The cause is the product number “se03” and branch number. This is because the delivery date (April 13) of the mechanism unit “5” is later than the start date of the production number “se03” / branch number “2” and the plan is reversed. In this example, Komagome Kogyo Co., Ltd., which is a trader, inputs each process information directly by the reception input means 16. In this example, the plan bar is displayed with a thick frame, but the plan bar itself may be displayed in red. In addition, the plans for the production number “se03” and branch number “2” are “×” because the electrical component of branch number “3” and the mechanism unit of branch number “5” are not yet completed. The total assembly of the product number “se03” and the branch number “2” indicates that it cannot be started at present. In this case, the total assembly and installation plan must be extended two days ahead. If the last installation work cannot be extended due to the relationship with the customer, it is necessary to take measures such as requesting Komagome once again or shortening the total assembly work period. If you ask Komagome to expedite, you can drag and drop the plan to the left on this Gantt chart, and use the communication means again to set the desired plan date to Komagome Kogyo Co., Ltd. I can send it.

より望ましい形態としては、調査希望時の前後のあらかじめ定められた期間の生産準備状況の算出をし、また、山積状況もあらかじめ定められた期間内における山積状況を算出して、表示することにより、製造現場の管理者は総合的に判断することが出来る。あらかじめ定められた期間は生産する品種によって適切な期間が異なる。したがって、生産現場であらかじめ決めることが望ましい。図3の例では、調査希望日の4月7日に対して過去については作業が完了していない工程を表示している。将来については、14日間をあらかじめ定められた期間として表示している。   As a more desirable form, by calculating the production preparation status for a predetermined period before and after the survey request, and calculating and displaying the mountain status within the predetermined period, The manager at the manufacturing site can make a comprehensive judgment. The predetermined period varies depending on the variety to be produced. Therefore, it is desirable to determine in advance at the production site. In the example of FIG. 3, a process in which work has not been completed for the past with respect to April 7 of the desired survey date is displayed. For the future, 14 days are displayed as a predetermined period.

以上のように、生産管理が行われる個別の職場において、生産準備が整っているか否かを工程の実績データに基づいて自動的に算出し、対応しやすいように表示することにより、効率よく生産管理が行える生産管理装置を提供することが出来る。   As described above, at each workplace where production management is performed, whether or not production preparations are complete is automatically calculated based on the performance data of the process, and displayed in an easy-to-support manner for efficient production. It is possible to provide a production management device capable of management.

次に、本発明の別の実施例について説明する。生産する品種によっては、生産に使用する生産資源が生産管理上の判断において重要な場合がある。このような場合に上記にて説明した本発明をさらに使いやすくすることを目的とする。図5は、本発明の別の実施例の生産管理装置1′の構成を示すブロック図である。図5に示す生産管理装置1′は生産資源情報入力手段136を入力手段13に追加した点のみが図1の構成と異なり、他は同様である。図6は、図5に示す生産管理装置1′の動作を示す動作を示すフローチャートであり、生産資源情報入力ステップ(S112)、設備使用状況算出ステップ(S164)、設備使用状況表示ステップ(S166)を追加した点が、図2に説明した内容と異なる。   Next, another embodiment of the present invention will be described. Depending on the varieties to be produced, the production resources used for production may be important in judging production control. In such a case, it is an object to make the present invention described above easier to use. FIG. 5 is a block diagram showing a configuration of a production management apparatus 1 ′ according to another embodiment of the present invention. The production management apparatus 1 ′ shown in FIG. 5 is different from the configuration of FIG. 1 only in that the production resource information input means 136 is added to the input means 13, and the others are the same. FIG. 6 is a flowchart showing the operation of the production management apparatus 1 ′ shown in FIG. 5, in which a production resource information input step (S112), an equipment usage status calculation step (S164), and an equipment usage status display step (S166). The point which added is different from the content demonstrated in FIG.

図5、図6に示すように、上記で説明した内容に、生産資源情報も加えた内容で生産準備状況が算出され、生産準備状況が表示されるので、生産資源が生産管理上の判断において重要な場合は、より適切に現場の管理者が判断し対応することが出来る。   As shown in FIGS. 5 and 6, the production preparation status is calculated by adding the production resource information to the content described above, and the production preparation status is displayed. When it is important, the site manager can judge and respond more appropriately.

図7は、生産準備状況表示手段142において、別の実施例を示したものである。図7に示すように、ガント・チャートの図表の上で、生産準備状況を表示するカラムを別に設けたことを特徴とする。別のカラムを設けることにより管理者が表示画面中でいつも注目すべき場所が決まっている利点がある。また、設備使用状況も表示されるので、より総合的に生産管理状況が把握でき適切な対応をすることが出来る。   FIG. 7 shows another embodiment of the production preparation status display means 142. As shown in FIG. 7, a column for displaying the production preparation status is provided separately on the chart of the Gantt chart. By providing another column, there is an advantage that a place where the administrator should always pay attention in the display screen is determined. Moreover, since the equipment usage status is also displayed, the production management status can be grasped more comprehensively and appropriate measures can be taken.

以上の例は、生産管理装置について説明したが、コンピュータに、生産管理装置で説明した手段を有する生産管理用プログラムをインストールして、そのコンピュータを手段として機能させることにより実現することが出来る。また、そのような生産管理用プログラムを記録したコンピュータ読み取り可能な記録媒体をコンピュータに読み込ませ、生産管理用プログラムをインストールして、そのコンピュータを手段として機能させることによっても実現することが出来る。   In the above example, the production management apparatus has been described. However, it can be realized by installing a production management program having the means described in the production management apparatus and causing the computer to function as the means. It can also be realized by causing a computer to read a computer-readable recording medium in which such a production management program is recorded, installing the production management program, and causing the computer to function as a means.

また、上記の生産管理装置と同等の性能を有するコンピュータに、同等の手段を有するコンピュータプログラムをインストールして、上記で説明したような方法で使用することによっても実現可能である。   It can also be realized by installing a computer program having equivalent means in a computer having the same performance as the above production management apparatus and using it by the method as described above.

以上、本発明の実施形態を用いて説明したが、本発明の技術的範囲は上記実施形態に記載の範囲には限定されない。上記実施形態に、多様な変更または改良を加えることができる。そのような変更または改良を加えた形態も本発明の技術的範囲に含まれ得ることが、特許請求の範囲の記載から明らかである。例えば、生産管理装置はコンピュータの例で説明したが、CPUのかわりにデジタルシグナルプロセッサーを採用したシステムによってもよい。また、生産準備状況表示の例としてガント・チャート方式にて説明したが、パート・タイム方式にても同様に本発明の実施が可能である。   As mentioned above, although demonstrated using embodiment of this invention, the technical scope of this invention is not limited to the range as described in the said embodiment. Various modifications or improvements can be added to the above embodiment. It is apparent from the scope of the claims that the embodiments added with such changes or improvements can be included in the technical scope of the present invention. For example, the production management apparatus has been described as an example of a computer, but a system employing a digital signal processor instead of a CPU may be used. In addition, although the Gantt chart method has been described as an example of the production preparation status display, the present invention can be similarly applied to the part time method.

本発明に係る生産管理装置の構成を示すブロック図である。It is a block diagram which shows the structure of the production management apparatus which concerns on this invention. 本発明に係る生産管理装置の動作を示すフローチャートである。It is a flowchart which shows operation | movement of the production management apparatus which concerns on this invention. 本発明に係る生産管理装置のガント・チャート方式による一例を生産状況表示手段、山積状況表示手段により表示された図である。It is the figure displayed by the production status display means and the pile status display means by way of an example by the Gantt chart method of the production management device according to the present invention. 本発明に係る生産管理装置に表示される生産管理情報明細を示す図である。It is a figure which shows the production management information details displayed on the production management apparatus which concerns on this invention. 本発明の別の実施例の生産管理装置の構成を示すブロック図である。It is a block diagram which shows the structure of the production management apparatus of another Example of this invention. 図5に示す生産管理装置の動作を示す動作を示すフローチャートである。It is a flowchart which shows the operation | movement which shows operation | movement of the production management apparatus shown in FIG. 生産準備状況表示において、別の実施例を示した図である。It is the figure which showed another Example in the production preparation status display.

符号の説明Explanation of symbols

1 生産管理装置
1′ 生産管理装置
11 制御手段
12 記憶手段
13 入力手段
13′ 入力手段
14 表示手段
15 バス
16 受信入力手段
18 通信回線
19 端末
112 生産準備状況算出手段
114 山積状況算出手段
132 各工程情報入力手段
134 変更入力手段
136 生産資源情報入力手段
142 生産準備状況表示手段
144 山積状況表示手段
DESCRIPTION OF SYMBOLS 1 Production management apparatus 1 'Production management apparatus 11 Control means 12 Storage means 13 Input means 13' Input means 14 Display means 15 Bus 16 Reception input means 18 Communication line 19 Terminal 112 Production preparation status calculation means 114 Mountain condition calculation means 132 Each process Information input means 134 Change input means 136 Production resource information input means 142 Production preparation status display means 144 Mountain status display means

Claims (19)

生産管理装置であって、
生産計画に対して、資材または部品に関しての入荷または完成の、予定または実績を含む各工程情報の入力をする各工程情報入力手段と、
前記入力をされた各工程情報及び前記生産計画の生産管理情報を記憶する記憶手段と、
前記記憶手段に記憶されている各工程情報と生産管理情報とに基づいて、前記生産管理装置のユーザが調査をしたい時を示す調査希望時の各工程の生産準備が整っているか否かを表す生産準備状況の算出をする生産準備状況算出手段と、
前記算出をされた生産準備状況および前記生産管理情報の表示をする生産状況表示手段と、
を備え、前記生産状況表示手段は、ある工程の納期がそれに続く工程の着手のために必要な関係及び前記ある工程並びに前記続く工程の準備が整っているか否かを、これらの状況に対応するシンボルにより表示することを特徴とする生産管理装置。
A production management device,
Each process information input means for inputting each process information including the schedule or actual result of arrival or completion of materials or parts with respect to the production plan,
Storage means for storing each input process information and production management information of the production plan;
Based on each process information and production management information stored in the storage means, it indicates whether or not the production management device is ready for production when the user of the production management device wants to investigate and when the survey is desired. Production preparation status calculating means for calculating the production preparation status;
Production status display means for displaying the calculated production preparation status and the production management information;
The production status display means corresponds to these situations, indicating whether the delivery date of a certain process is necessary for the start of the subsequent process and whether the certain process and the subsequent process are ready. A production management device characterized by displaying with symbols .
請求項1に記載の生産管理装置であって、
前記生産計画の生産管理情報に基づいて前記調査希望時に含まれる日毎の作業予定量の総和である山積状況の算出をする山積状況算出手段と、
前記山積状況を前記生産準備状況および前記生産管理情報と関連付けて表示する山積状況表示手段と、
をさらに備え、前記山積状況表示手段は、計画上問題があるか否かを示すことを特徴とする生産管理装置。
The production management device according to claim 1,
A pile condition calculation means for calculating a pile condition that is a sum of daily scheduled work amounts included when the survey is requested based on production management information of the production plan;
A pile status display means for displaying the pile status in association with the production preparation status and the production management information;
The production management device is characterized in that the mountain status display means indicates whether there is a problem in planning.
請求項2に記載の生産管理装置であって、
通信回線を介して、端末から前記各工程情報の受信をする受信入力手段をさらに備え、
前記受信をした各工程情報ならびに前記記憶手段に記憶されている生産管理情報に基づいて、前記生産準備状況算出手段は前記調査希望時の前記生産準備状況の算出をし、前記山積状況算出手段は前記調査希望時の前記山積状況の算出をすることを特徴とする生産管理装置。
The production management device according to claim 2,
Further comprising a reception input means for receiving each process information from the terminal via a communication line;
Based on each received process information and production management information stored in the storage means, the production preparation status calculation means calculates the production preparation status when the survey is desired, and the pile status calculation means A production management apparatus for calculating the pile state when the survey is desired.
請求項2又は請求項3のいずれかに記載の生産管理装置であって、
所定の資材あるいは部品に関して、前記表示をされた生産管理情報の変更入力をする変更入力手段をさらに備え、
前記変更入力をされた生産管理情報に基づいて、前記生産準備状況算出手段は前記調査希望時の前記生産準備状況の算出をし、前記山積状況算出手段は前記調査希望時に含まれる日毎の前記山積状況の算出をすることを特徴とする生産管理装置。
A production management device according to claim 2 or claim 3,
A change input means for inputting a change of the displayed production management information with respect to a predetermined material or part is further provided,
Based on the production management information that has been changed, the production preparation status calculation means calculates the production preparation status when the survey is desired, and the pile status calculation means is the peak for each day included when the survey is desired. A production management device characterized by calculating a situation.
請求項2から請求項4のいずれかに記載の生産管理装置であって、
生産資源情報入力手段をさらに備え、
前記記憶手段は、生産資源情報をさらに記憶し、
前記生産準備状況算出手段は、前記記憶手段に記憶された生産資源情報もあわせて、前記調査希望時の前記生産準備状況の算出をすることを特徴とする生産管理装置。
The production management device according to any one of claims 2 to 4,
It further comprises production resource information input means,
The storage means further stores production resource information,
The production management apparatus according to claim 1, wherein the production preparation status calculation means calculates the production preparation status when the survey is desired, together with production resource information stored in the storage means.
請求項2から請求項5のいずれかに記載の生産管理装置であって、
前記生産準備状況算出手段は、前記調査希望時の前後のあらかじめ定められた期間内における前記生産準備状況の算出をし、
前記山積状況算出手段は、前記調査希望時の前後のあらかじめ定められた期間内における前記山積状況の算出をすることを特徴とする生産管理装置。
The production management device according to any one of claims 2 to 5,
The production preparation status calculation means calculates the production preparation status within a predetermined period before and after the survey request,
The mass production status calculation means calculates the mass production status within a predetermined period before and after the survey request.
生産管理装置を、
生産計画に対して、資材または部品に関しての入荷または完成の、予定または実績を含む各工程情報の入力をする各工程情報入力手段、
前記入力をされた各工程情報及び前記生産計画の生産管理情報を記憶する記憶手段、
前記記憶手段に記憶されている各工程情報と生産管理情報とに基づいて、前記生産管理装置のユーザが調査をしたい時を示す調査希望時の各工程の生産準備が整っているか否かを表す生産準備状況の算出をする生産準備状況算出手段、
及び前記算出をされた生産準備状況および前記生産管理情報の表示をする生産状況表示手段、
として機能させ、前記生産状況表示手段は、ある工程の納期がそれに続く工程の着手のために必要な関係及び前記ある工程並びに前記続く工程の準備が整っているか否かを、これらの状況に対応するシンボルにより表示することを特徴とする生産管理用プログラム。
Production management equipment,
Each process information input means for inputting each process information including the schedule or actual result of the arrival or completion of materials or parts for the production plan,
Storage means for storing each input process information and production management information of the production plan,
Based on each process information and production management information stored in the storage means, it indicates whether or not the production management device is ready for production when the user of the production management device wants to investigate and when the survey is desired. Production preparation status calculation means for calculating production preparation status;
And production status display means for displaying the calculated production preparation status and the production management information,
The production status display means responds to these situations by indicating whether the delivery date of a certain process is necessary for the start of the subsequent process and whether the certain process and the subsequent process are ready. A production management program characterized by being displayed with a symbol to be displayed .
請求項7に記載の生産管理用プログラムであって、
前記生産管理装置を、
前記生産計画の生産管理情報に基づいて前記調査希望時に含まれる日毎の作業予定量の総和である山積状況の算出をする山積状況算出手段、
前記山積状況を前記生産準備状況および前記生産管理情報と関連付けて表示する山積状況表示手段、
としてさらに機能させ、前記山積状況表示手段は、計画上問題があるか否かを示すことを特徴とする生産管理用プログラム。
The production management program according to claim 7,
The production management device,
A pile condition calculation means for calculating a pile condition that is a sum of daily scheduled work amounts included when the survey is requested based on production management information of the production plan;
A pile status display means for displaying the pile status in association with the production preparation status and the production management information;
The production management program is characterized in that the pile status display means indicates whether there is a problem in planning.
請求項8に記載の生産管理用プログラムであって、
前記生産管理装置を、
通信回線を介して、端末から前記各工程情報の受信をする受信入力手段としてさらに機能させ、
前記受信をした各工程情報ならびに前記記憶手段に記憶されている生産管理情報に基づいて、前記生産準備状況算出手段に前記調査希望時の前記生産準備状況の算出をさせ、前記山積状況算出手段に前記調査希望時の前記山積状況の算出をさせることを特徴とする生産管理用プログラム。
The production management program according to claim 8,
The production management device,
Further function as a reception input means for receiving the process information from the terminal via a communication line,
Based on the received process information and the production management information stored in the storage means, the production preparation status calculation means calculates the production preparation status at the time of the survey request, and the pile status calculation means A production management program characterized by causing the pile state to be calculated when the survey is desired.
請求項8又は請求項9のいずれかに記載の生産管理用プログラムであって、
前記生産管理装置を、
所定の資材あるいは部品に関して、前記表示をされた生産管理情報の変更入力をする変更入力手段としてさらに機能させ、
前記変更入力をされた生産管理情報に基づいて、前記生産準備状況算出手段に、さらに前記調査希望時の前記生産準備状況の算出をさせ、前記山積状況の算出手段に、さらに前記調査希望時に含まれる日毎の山積状況の算出をさせることを特徴とする生産管理用プログラム。
A production management program according to claim 8 or 9, wherein
The production management device,
With respect to a predetermined material or part, it further functions as a change input means for inputting the change of the displayed production management information.
Based on the changed production management information, the production preparation status calculation means further calculates the production preparation status at the time of the survey request, and the pile status calculation means is further included at the time of the survey request. A program for production management characterized in that it calculates the state of piles for each day.
請求項8から請求項10のいずれかに記載の生産管理用プログラムであって、
前記生産管理装置を、
生産資源情報入力手段としてさらに機能させ、
前記入力された生産資源情報をさらに記憶手段に記憶させ、
前記生産準備状況算出手段に、さらに前記記憶手段に記憶された生産資源情報もあわせて、前記調査希望時の前記生産準備状況の算出をさせることを特徴とする生産管理用プログラム。
A production management program according to any one of claims 8 to 10,
The production management device,
Further function as a production resource information input means,
Storing the input production resource information in a storage means;
A production management program characterized by causing the production preparation status calculation means to calculate the production preparation status at the time of the survey request together with the production resource information stored in the storage means.
請求項8から請求項11のいずれかに記載の生産管理用プログラムであって、
前記生産準備状況算出手段に、前記調査希望時の前後のあらかじめ定められた期間内の前記生産準備状況の算出をさせ、
前記山積状況算出手段に、前記調査希望時の前後のあらかじめ定められた期間内における前記山積状況の算出をさせる、
ことを特徴とする生産管理用プログラム。
A production management program according to any one of claims 8 to 11,
Let the production preparation status calculation means calculate the production preparation status within a predetermined period before and after the survey request,
Causing the pile status calculation means to calculate the pile status within a predetermined period before and after the survey request,
A production management program characterized by this.
請求項7から請求項12のいずれかに記載の生産管理用プログラムを記録したコンピュータ読み取り可能な記録媒体。   A computer-readable recording medium on which the production management program according to any one of claims 7 to 12 is recorded. 生産管理装置による生産管理方法であって、前記生産管理装置が、
生産計画に対して、資材または部品に関しての入荷または完成の、予定または実績を含む各工程情報の入力をする各工程情報入力ステップと、
前記入力をされた各工程情報及び前記生産計画の生産管理情報を記憶する記憶ステップと、
前記記憶をした各工程情報と生産管理情報とに基づいて、前記生産管理装置のユーザが調査をしたい時を示す調査希望時の各工程の生産準備が整っているか否かを表す生産準備状況の算出をする生産準備状況算出ステップと、
前記算出をされた生産準備状況および前記生産管理情報の表示をする生産状況表示ステップと、
を有し、前記生産状況表示ステップにおいて、ある工程の納期がそれに続く工程の着手のために必要な関係及び前記ある工程並びに前記続く工程の準備が整っているか否かを、これらの状況に対応するシンボルにより表示することを特徴とする生産管理方法。
A production management method using a production management device, wherein the production management device comprises:
Each process information input step for inputting each process information including the schedule or actual result of arrival or completion of materials or parts with respect to the production plan,
A storage step of storing each input process information and production management information of the production plan;
Based on the stored process information and production management information, a production preparation status indicating whether or not the production preparation status of each process at the time of investigation request indicating that the user of the production management apparatus wants to investigate is ready. A production preparation status calculating step for calculating,
A production status display step for displaying the calculated production preparation status and the production management information;
In the production status display step, the relationship between the delivery date of a certain process necessary for the start of the subsequent process and whether or not the certain process and the subsequent process are ready corresponds to these conditions. A production management method characterized by displaying by a symbol to be displayed .
請求項14に記載の生産管理方法であって、前記生産管理装置が、
前記生産計画の生産管理情報に基づいて前記調査希望時に含まれる日毎の作業予定量の総和である山積状況の算出をする山積状況算出ステップと、
前記山積状況を前記生産準備状況および前記生産管理情報と関連付けて表示する山積状況表示ステップと、
をさらに有し、前記山積状況表示ステップは、計画上問題があるか否かを示すことを特徴とする生産管理方法。
The production management method according to claim 14, wherein the production management device comprises:
A pile condition calculation step for calculating a pile condition that is a sum of daily scheduled work amounts included when the survey is requested based on production management information of the production plan;
A pile status display step for displaying the pile status in association with the production preparation status and the production management information;
And the step of displaying the pile status indicates whether there is a problem in planning.
請求項15に記載の生産管理方法であって、前記生産管理装置が、
通信回線を介して、端末から前記各工程情報の受信をする受信入力ステップをさらに有し
前記受信をした前記各工程情報に基づいて、前記生産準備状況算出ステップにおいて前記調査希望時の前記生産準備状況の算出をし、前記山積状況算出ステップにおいて前記調査希望時の前記山積状況の算出をすることを特徴とする生産管理用方法。
The production management method according to claim 15, wherein the production management apparatus comprises:
The method further comprises a reception input step of receiving each process information from a terminal via a communication line, and based on the received each process information, the production preparation when the survey is desired in the production preparation status calculation step A method for production management, comprising: calculating a situation, and calculating the mountain situation when the survey is desired in the mountain situation calculating step.
請求項15又は請求項16のいずれかに記載の生産管理方法であって、前記生産管理装置が、
所定の資材あるいは部品に関して、前記表示をされた生産管理情報の変更入力をする変更入力ステップをさらに有し、
前記変更入力をされた生産管理情報に基づいて、前記生産準備状況算出ステップにおいて、前記調査希望時の前記生産準備状況の算出をし、前記山積状況算出ステップにおいて、前記調査希望時に含まれる日毎の山積状況の算出をすることを特徴とする生産管理方法。
The production management method according to claim 15 or 16, wherein the production management device comprises:
Regarding a predetermined material or part, the method further includes a change input step for inputting a change in the displayed production management information.
Based on the changed production management information, in the production preparation status calculation step, the production preparation status at the time of the survey request is calculated, and in the pile status calculation step, every day included at the time of the survey request. A production management method characterized by calculating a pile state.
請求項15から請求項17のいずれかに記載の生産管理方法であって、前記生産管理装置が、
生産資源情報入力をするステップをさらに有し、
前記記憶ステップにおいて生産資源情報をさらに記憶し、
前記生産準備状況算出ステップにおいて、前記記憶ステップにおいて記憶された生産資源情報もあわせて、前記調査希望時の前記生産準備状況の算出をすることを特徴とする生産管理方法。
The production management method according to any one of claims 15 to 17, wherein the production management device comprises:
The method further includes the step of inputting production resource information,
Further storing production resource information in the storage step;
In the production preparation status calculation step, the production preparation status at the time of the survey request is calculated together with the production resource information stored in the storage step.
請求項15から請求項18のいずれかに記載の生産管理方法であって、前記生産管理装置が、
前記生産準備状況算出ステップにお。いて、前記調査希望時の前後のあらかじめ定められた期間内における前記生産準備状況の算出をし、
前記山積状況算出ステップにおいて、前記調査希望時の前後のあらかじめ定められた期間内における前記山積状況の算出をすることを特徴とする生産管理方法。
The production management method according to any one of claims 15 to 18, wherein the production management device comprises:
In the production preparation status calculation step. And calculating the production preparation status within a predetermined period before and after the survey request,
The production management method according to claim 1, wherein, in the pile state calculation step, the pile state is calculated within a predetermined period before and after the survey request.
JP2005125330A 2005-03-15 2005-04-22 Production management apparatus, production management program, and production management method Active JP4268151B2 (en)

Priority Applications (3)

Application Number Priority Date Filing Date Title
JP2005125330A JP4268151B2 (en) 2005-04-22 2005-04-22 Production management apparatus, production management program, and production management method
KR1020060007732A KR20060101220A (en) 2005-03-15 2006-01-25 Production management system
US11/342,362 US20060212323A1 (en) 2005-03-15 2006-01-26 Production management system

Applications Claiming Priority (1)

Application Number Priority Date Filing Date Title
JP2005125330A JP4268151B2 (en) 2005-04-22 2005-04-22 Production management apparatus, production management program, and production management method

Publications (2)

Publication Number Publication Date
JP2006139751A JP2006139751A (en) 2006-06-01
JP4268151B2 true JP4268151B2 (en) 2009-05-27

Family

ID=36620519

Family Applications (1)

Application Number Title Priority Date Filing Date
JP2005125330A Active JP4268151B2 (en) 2005-03-15 2005-04-22 Production management apparatus, production management program, and production management method

Country Status (1)

Country Link
JP (1) JP4268151B2 (en)

Families Citing this family (2)

* Cited by examiner, † Cited by third party
Publication number Priority date Publication date Assignee Title
JP2008159000A (en) * 2006-12-26 2008-07-10 Tpics Systems:Kk Production management system, program for production management, and production management method
CN105303347A (en) * 2015-10-26 2016-02-03 烟台宝井钢材加工有限公司 Decoiling line planning method

Also Published As

Publication number Publication date
JP2006139751A (en) 2006-06-01

Similar Documents

Publication Publication Date Title
US6151531A (en) System and method for managing the alteration of garments
US20060004618A1 (en) Explaining task scheduling for a project
US20070245300A1 (en) Apparatus, system, and method for presenting project scheduling information in combination with workflow information
US20170061360A1 (en) Interactive charts with dynamic progress monitoring, notification, and resource allocation
US20110071869A1 (en) Process management system and method
KR20100126508A (en) User interface for scheduling resource assignments
US20130262528A1 (en) Mobile Sales Tracking System
US20090255153A1 (en) Group calendar interface
JP2008299762A (en) Production management program
US20050222942A1 (en) Management of tasks required of trade subcontractors in the construction industry
US20140012612A1 (en) Visualization of warehouse operations forecast
US8688596B2 (en) Project activity reporting
JP5118406B2 (en) Progress display device, progress display method, and progress display program
KR20180109785A (en) Method and apparatus for assisting strategy map management based on schedule-assessment item and todo-assessment item
JP6742125B2 (en) Business management device, information processing method, and business management program
KR20180013474A (en) Method and apparatus for assisting strategy map management based on schedule-assessment item and todo-assessment item
JP4268151B2 (en) Production management apparatus, production management program, and production management method
US20140129466A1 (en) Method and system for selecting labour resources
JP2010262361A (en) Business management system
JP2006113940A (en) Construction job supporting system and program
US7996299B2 (en) Trade services management system
US20210295274A1 (en) Workflow management device, workflow management system, method of managing workflow, and non-transitory recording medium
JP7113128B1 (en) Information processing device, information processing system, and program
JP2009211242A (en) Business management device, business management program, business management system and business management method
JP2018169674A (en) Order placement control apparatus

Legal Events

Date Code Title Description
A131 Notification of reasons for refusal

Free format text: JAPANESE INTERMEDIATE CODE: A131

Effective date: 20060919

A521 Request for written amendment filed

Free format text: JAPANESE INTERMEDIATE CODE: A523

Effective date: 20061117

A131 Notification of reasons for refusal

Free format text: JAPANESE INTERMEDIATE CODE: A131

Effective date: 20070320

A521 Request for written amendment filed

Free format text: JAPANESE INTERMEDIATE CODE: A523

Effective date: 20070521

A131 Notification of reasons for refusal

Free format text: JAPANESE INTERMEDIATE CODE: A131

Effective date: 20070626

A521 Request for written amendment filed

Free format text: JAPANESE INTERMEDIATE CODE: A523

Effective date: 20070824

TRDD Decision of grant or rejection written
A01 Written decision to grant a patent or to grant a registration (utility model)

Free format text: JAPANESE INTERMEDIATE CODE: A01

Effective date: 20090217

A01 Written decision to grant a patent or to grant a registration (utility model)

Free format text: JAPANESE INTERMEDIATE CODE: A01

A61 First payment of annual fees (during grant procedure)

Free format text: JAPANESE INTERMEDIATE CODE: A61

Effective date: 20090219

R150 Certificate of patent or registration of utility model

Ref document number: 4268151

Country of ref document: JP

Free format text: JAPANESE INTERMEDIATE CODE: R150

Free format text: JAPANESE INTERMEDIATE CODE: R150

FPAY Renewal fee payment (event date is renewal date of database)

Free format text: PAYMENT UNTIL: 20120227

Year of fee payment: 3

FPAY Renewal fee payment (event date is renewal date of database)

Free format text: PAYMENT UNTIL: 20120227

Year of fee payment: 3

FPAY Renewal fee payment (event date is renewal date of database)

Free format text: PAYMENT UNTIL: 20140227

Year of fee payment: 5

R250 Receipt of annual fees

Free format text: JAPANESE INTERMEDIATE CODE: R250

S533 Written request for registration of change of name

Free format text: JAPANESE INTERMEDIATE CODE: R313533

R360 Written notification for declining of transfer of rights

Free format text: JAPANESE INTERMEDIATE CODE: R360

R250 Receipt of annual fees

Free format text: JAPANESE INTERMEDIATE CODE: R250

R350 Written notification of registration of transfer

Free format text: JAPANESE INTERMEDIATE CODE: R350

R250 Receipt of annual fees

Free format text: JAPANESE INTERMEDIATE CODE: R250

R250 Receipt of annual fees

Free format text: JAPANESE INTERMEDIATE CODE: R250

R250 Receipt of annual fees

Free format text: JAPANESE INTERMEDIATE CODE: R250

R250 Receipt of annual fees

Free format text: JAPANESE INTERMEDIATE CODE: R250

R250 Receipt of annual fees

Free format text: JAPANESE INTERMEDIATE CODE: R250

R250 Receipt of annual fees

Free format text: JAPANESE INTERMEDIATE CODE: R250

R250 Receipt of annual fees

Free format text: JAPANESE INTERMEDIATE CODE: R250

R250 Receipt of annual fees

Free format text: JAPANESE INTERMEDIATE CODE: R250

R250 Receipt of annual fees

Free format text: JAPANESE INTERMEDIATE CODE: R250

R250 Receipt of annual fees

Free format text: JAPANESE INTERMEDIATE CODE: R250