JP2013065105A - Development process improvement effect evaluation device, evaluation method, and evaluation program - Google Patents

Development process improvement effect evaluation device, evaluation method, and evaluation program Download PDF

Info

Publication number
JP2013065105A
JP2013065105A JP2011202422A JP2011202422A JP2013065105A JP 2013065105 A JP2013065105 A JP 2013065105A JP 2011202422 A JP2011202422 A JP 2011202422A JP 2011202422 A JP2011202422 A JP 2011202422A JP 2013065105 A JP2013065105 A JP 2013065105A
Authority
JP
Japan
Prior art keywords
cost
risk
evaluation
development process
effect
Prior art date
Legal status (The legal status is an assumption and is not a legal conclusion. Google has not performed a legal analysis and makes no representation as to the accuracy of the status listed.)
Withdrawn
Application number
JP2011202422A
Other languages
Japanese (ja)
Inventor
Koji Nishida
廣治 西田
Current Assignee (The listed assignees may be inaccurate. Google has not performed a legal analysis and makes no representation or warranty as to the accuracy of the list.)
Fuji Electric Co Ltd
Original Assignee
Fuji Electric Co Ltd
Priority date (The priority date is an assumption and is not a legal conclusion. Google has not performed a legal analysis and makes no representation as to the accuracy of the date listed.)
Filing date
Publication date
Application filed by Fuji Electric Co Ltd filed Critical Fuji Electric Co Ltd
Priority to JP2011202422A priority Critical patent/JP2013065105A/en
Publication of JP2013065105A publication Critical patent/JP2013065105A/en
Withdrawn legal-status Critical Current

Links

Images

Abstract

PROBLEM TO BE SOLVED: To improve accuracy of evaluating a development process improvement effect.SOLUTION: An evaluation device, used for evaluating a development process improvement effect using a development risk, includes: development process improvement plan setup means for setting an improvement plan for a development process for each organization or project performing a development; risk estimation setup means for estimating a risk on the basis of expense data and risk data that are pre-set; risk-cost conversion means for converting at least one of cost risk, quality risk and delivery risk of risk data obtained from the risk estimation setup means into a cost; cost effectiveness obtainment means for obtaining cost effectiveness corresponding to the improvement effect of the development process on the basis of the cost obtained from the risk-cost conversion means; and evaluation result output means for outputting an evaluation result based on the calculation result obtained from the cost effectiveness obtainment means.

Description

本発明は、開発プロセス改善効果の評価装置、評価方法、及び評価プログラムに係り、特に開発プロセス改善効果の評価精度を向上させるための開発プロセス改善効果の評価装置、評価方法、及び評価プログラムに関する。   The present invention relates to a development process improvement effect evaluation apparatus, evaluation method, and evaluation program, and more particularly to a development process improvement effect evaluation apparatus, evaluation method, and evaluation program for improving the development process improvement effect evaluation accuracy.

従来の開発プロセスは、予めCMMI(Capability Maturity Model Integration;能力成熟度モデル統合)やISO12207(ソフトウェアライフサイクルプロセス)等をモデルとしたISO15504等が国際標準となっている(例えば、非特許文献1参照)。また、これらの基準は、組織やプロジェクト等により開発プロセスを実施していく上での1つの指標となっている。   As for the conventional development process, ISO 15504 and the like based on models such as CMMI (Capability Maturity Model Integration; capability maturity model integration) and ISO 12207 (Software Lifecycle Process) have become international standards in advance (for example, see Non-Patent Document 1). ). In addition, these standards are one index for carrying out the development process depending on the organization or project.

ここで、非特許文献1に示すCMMIでは、開発プロセスを「プロセス領域」として定義し、各プロセス領域について「ゴール」を設定し、更に「ゴール」を詳細化した「プラクティス」を設定している。また、ISO12207では、各プロセスに「アクティビティ」を設定し、更に「アクティビティ」を詳細化した「タスク」を設定している。また、CMMIでは、プロセス領域を組織に関するものとプロジェクトに関するものとに分類できる。   Here, in the CMMI shown in Non-Patent Document 1, a development process is defined as a “process area”, a “goal” is set for each process area, and a “practice” that further refines the “goal” is set. . In ISO 12207, “activity” is set for each process, and “task” in which “activity” is detailed is set. In CMMI, process areas can be classified into those related to organizations and those related to projects.

また、従来の開発リスクの評価手法については、例えばPMBOK(登録商標)(プロジェクト管理知識体系)にリスク発生確率とリスク影響度をパラメータとする手法が示されており、リスク影響度の定義表についても示されている(例えば、非特許文献2参照)。   In addition, with regard to conventional development risk evaluation methods, for example, PMBOK (registered trademark) (project management knowledge system) shows a method using risk occurrence probability and risk impact as parameters. Is also shown (for example, see Non-Patent Document 2).

また、従来の一般的な業務プロセス改善については、例えば業務を細分化したものについてKPI(Key Performance Indicator)を設定してモニタリングする手法が示されている(例えば、非特許文献3参照)。   As for conventional general business process improvement, for example, a method of setting and monitoring KPI (Key Performance Indicator) for a subdivided business is shown (for example, refer to Non-Patent Document 3).

更に、従来では、プロジェクト計画とプロジェクト実績とからリスク評価尺度を決定する手法が示されている(例えば、特許文献1参照)。また、従来では、ISO12207のアクティビティ毎のスキル、経験、新技術によるリスクデータに基づいてアクティビティをプロジェクト管理プロセスに取り込むか否かを決定する手法が示されている(例えば、特許文献2参照)。   Furthermore, conventionally, a method for determining a risk evaluation scale from a project plan and a project performance has been shown (see, for example, Patent Document 1). Conventionally, a method for determining whether to import an activity into the project management process based on skills, experience, and risk data based on new technology for each activity of ISO12207 has been shown (see, for example, Patent Document 2).

特開平11−66150号公報JP-A-11-66150 特開2003−296528号公報JP 2003-296528 A

Carnegie Mellon、Software Engineering Institute、「開発のためのCMMI 1.2版」、CMU/SEI−2006−TR−008、August 2006Carnegie Mellon, Software Engineering Institute, “CMMI 1.2 for Development”, CMU / SEI-2006-TR-008, August 2006 Institute,Four Campus Boulevand,Newtown Square、「プロジェクトマネジメント知識体系ガイド(PMBOKガイド)」、PA19073−3299 USAInstitute, Four Campus Boulevand, New Square, “Project Management Knowledge System Guide (PMBOK Guide)”, PA19073-3299 USA ロバート・S・キャプラン,デビッド・P・ノートン,櫻井通晴(翻訳)、「キャプランとノートンの戦略バランスト・スコアカード」、東洋経済新報社、2001年8月30日Robert S. Caplan, David P. Norton, Michiharu Sakurai (translation), “Strategic Balanced Scorecard between Caplan and Norton”, Toyo Keizai Inc., August 30, 2001

ところで、プロジェクトや組織で開発プロセスを改善しようとする場合には、開発プロセス改善の費用対効果の提示と説明が重要な事項となる。例えば、従来では、改善対象のプロジェクトや組織の状況によってCMMI等の標準開発プロセスの要求水準をそのまま実行すると、開発コストの増大が見込まれる。そのため、従来では、明確な費用対効果のバランスがとれた開発プロセス改善計画の提示と説明が必要となる。   By the way, when trying to improve the development process in a project or organization, it is important to present and explain the cost-effectiveness of the development process improvement. For example, conventionally, if the required level of the standard development process such as CMMI is executed as it is depending on the project to be improved and the situation of the organization, the development cost is expected to increase. Therefore, conventionally, it is necessary to present and explain a development process improvement plan that has a well-balanced cost-effectiveness.

しかしながら、CMMIの成熟度レベルやISO15504の能力レベル等の開発プロセス評価は、開発プロセス自体の評価であり、費用対効果を説明することができない。そのため、従来では、開発プロセス活動の予算が十分獲得できず、品質改善や納期短縮、生産性向上等のプロセス改善活動の制約となっている。   However, development process evaluations such as CMMI maturity level and ISO 15504 capability level are evaluations of the development process itself and cannot explain cost effectiveness. For this reason, conventionally, a sufficient budget for development process activities cannot be obtained, which is a limitation of process improvement activities such as quality improvement, delivery time reduction, and productivity improvement.

これらの状況を打開するためには、費用対効果を定量的に提示し説明可能とすることで、コストバランスがとれたプロセス改善計画を立案・実行し、プロセス改善を推進し、品質改善や納期短縮、生産性向上を図る必要がある。   In order to overcome these situations, we can formulate and execute cost-effective process improvement plans by presenting and explaining cost-effectiveness quantitatively, promoting process improvement, quality improvement and delivery time. It is necessary to shorten and improve productivity.

ここで、上述した特許文献1に示されているような手法は、プロジェクト計画とプロジェクト実績からリスク評価尺度を決めている。しかしながら、上述の手法は、リスク評価尺度がトラブル実績との相関で決めているため、例えば「発生確率は低いが、もし発生すると被害が甚大になる」ようなリスクを見逃す可能性がある。また、上述の手法では、リスク対策についての記載がないため、対策の評価をすることができない。   Here, the technique as shown in Patent Document 1 described above determines a risk evaluation scale from a project plan and a project performance. However, in the above-described method, since the risk evaluation scale is determined based on the correlation with the trouble record, there is a possibility that a risk such as “the probability of occurrence is low, but if it occurs, the damage becomes enormous” may be missed. Moreover, in the above-mentioned method, since there is no description about risk countermeasures, the countermeasures cannot be evaluated.

更に、上述した特許文献2に示されているような手法は、ISO12207のアクティビティ毎のリスクデータと、リスク根拠となる入力データに基づいてプロジェクト管理プロセスに取り込むか否かを決定しているが、その結果の費用対効果についての記載がないため、プロセス改善の評価をすることができない。   Furthermore, the method as shown in Patent Document 2 described above determines whether to import into the project management process based on risk data for each activity of ISO 12207 and input data that is a risk basis. Because there is no description of the cost-effectiveness of the results, process improvement cannot be evaluated.

本発明は、上述した課題に鑑みてなされたものであって、開発プロセス改善効果の評価精度を向上させるための開発プロセス改善効果の評価装置、評価方法、及び評価プログラムを提供することを目的とする。   The present invention has been made in view of the above-described problems, and an object thereof is to provide a development process improvement effect evaluation apparatus, an evaluation method, and an evaluation program for improving the evaluation accuracy of the development process improvement effect. To do.

上述した課題を解決するために、本発明は、以下の特徴を有する課題を解決するための手段を採用している。   In order to solve the above-described problems, the present invention employs means for solving the problems having the following characteristics.

本発明は、開発リスクによる開発プロセスの改善効果の評価を行う評価装置において、開発を行う組織毎又はプロジェクト毎の開発プロセスに対する改善計画を設定する開発プロセス改善計画設定手段と、前記開発プロセス改善計画設定手段により設定された改善計画データと、予め設定された費用データ及びリスクデータとに基づいてリスクを見積もりするリスク見積設定手段と、前記リスク見積設定手段により得られるリスクデータを、コストリスク、品質リスク、及び納期リスクのうち、少なくとも1つのリスクをコストに変換するリスクコスト変換手段と、前記リスクコスト変換手段により得られるコストに基づいて、前記開発プロセスの改善効果に対応する費用対効果を取得する効果費用取得手段と、前記効果費用取得手段により得られる計算結果に基づく評価結果を出力する評価結果出力手段とを有することを特徴とする。   The present invention relates to a development process improvement plan setting means for setting an improvement plan for a development process for each organization or project for development in an evaluation apparatus for evaluating an improvement effect of a development process due to a development risk, and the development process improvement plan. Risk estimation setting means for estimating risk based on improvement plan data set by the setting means, cost data and risk data set in advance, and risk data obtained by the risk estimation setting means are converted into cost risk, quality Risk cost conversion means for converting at least one of the risk and delivery date risk into cost, and cost effectiveness corresponding to the improvement effect of the development process is obtained based on the cost obtained by the risk cost conversion means Effect cost acquisition means, and the effect cost acquisition means And having an evaluation result output means for outputting the evaluation result based on the calculation result is.

また、本発明は、開発リスクによる開発プロセスの改善効果の評価を行う評価方法において、開発を行う組織毎又はプロジェクト毎の開発プロセスに対する改善計画を設定する開発プロセス改善計画設定ステップと、前記開発プロセス改善計画設定ステップにより設定された改善計画データと、予め設定された費用データ及びリスクデータとに基づいてリスクを見積もりするリスク見積設定ステップと、前記リスク見積設定ステップにより得られるリスクデータを、コストリスク、品質リスク、及び納期リスクのうち、少なくとも1つのリスクをコストに変換するリスクコスト変換ステップと、前記リスクコスト変換ステップにより得られるコストに基づいて、前記開発プロセスの改善効果に対応する費用対効果を取得する効果費用取得ステップと、前記効果費用取得ステップにより得られる計算結果に基づく評価結果を出力する評価結果出力ステップとを有することを特徴とする。   Further, the present invention provides a development process improvement plan setting step for setting an improvement plan for a development process for each organization or project for development in an evaluation method for evaluating an improvement effect of a development process due to a development risk, and the development process The risk estimate setting step for estimating the risk based on the improvement plan data set by the improvement plan setting step, the cost data and the risk data set in advance, and the risk data obtained by the risk estimate setting step are converted into cost risk Cost risk step corresponding to the improvement effect of the development process based on the cost obtained by the risk cost conversion step for converting at least one risk into a cost among the quality risk and the delivery date risk, and the cost obtained by the risk cost conversion step To get the effective cost And having a flop, and the evaluation result output step of outputting the effective cost acquisition evaluation result based on the calculation result obtained by the step.

また、本発明は、上述した評価装置が有する各手段として機能させるための評価プログラムである。   Moreover, this invention is an evaluation program for functioning as each means which the evaluation apparatus mentioned above has.

本発明によれば、開発プロセス改善効果の評価精度を向上させることができる。   According to the present invention, it is possible to improve the evaluation accuracy of the development process improvement effect.

本実施形態における評価装置のブロック構成の一例を示す図である。It is a figure which shows an example of the block configuration of the evaluation apparatus in this embodiment. 本実施形態における評価処理が実現可能なハードウェア構成の一例を示す図である。It is a figure which shows an example of the hardware constitutions which can implement | achieve the evaluation process in this embodiment. ギャップテーブルの具体例を示す図である。It is a figure which shows the specific example of a gap table. プロジェクトテーブルの具体例を示す図である。It is a figure which shows the specific example of a project table. 費用テーブルの具体例を示す図である。It is a figure which shows the specific example of an expense table. 開発プロセス改善計画入力画面ファイルの具体例を示す図である。It is a figure which shows the specific example of a development process improvement plan input screen file. 目標達成追加入力画面ファイルの具体例を示す図である。It is a figure which shows the specific example of a goal achievement addition input screen file. 達成所要コストテーブルの具体例を示す図である。It is a figure which shows the specific example of an achievement required cost table. リスク見積入力画面ファイルの具体例を示す図である。It is a figure which shows the specific example of a risk estimate input screen file. リスクコスト変換テーブルの具体例を示す図である。It is a figure which shows the specific example of a risk cost conversion table. 効果ファイルの具体例を示す図である。It is a figure which shows the specific example of an effect file. 達成効果テーブルの具体例を示す図である。It is a figure which shows the specific example of an achievement effect table. 開発プロセス改善効果の評価処理手順の一例を示すフローチャートである。It is a flowchart which shows an example of the evaluation process procedure of a development process improvement effect. 開発プロセス改善計画設定処理手順の一例を示すフローチャートである。It is a flowchart which shows an example of a development process improvement plan setting process sequence. 目標達成追加設定処理手順の一例を示すフローチャートである。It is a flowchart which shows an example of a target achievement addition setting process sequence. リスク見積設定処理手順の一例を示すフローチャートである。It is a flowchart which shows an example of a risk estimate setting process procedure. リスクコスト変換処理手順の一例を示すフローチャートである。It is a flowchart which shows an example of a risk cost conversion process procedure. 効果費用取得処理手順の一例を示すフローチャートである。It is a flowchart which shows an example of an effect cost acquisition process sequence. 評価結果出力処理手順の一例を示すフローチャートである。It is a flowchart which shows an example of an evaluation result output process sequence. 本実施形態における評価結果の一例を示す図(その1)である。It is a figure (the 1) which shows an example of the evaluation result in this embodiment. 本実施形態における評価結果の一例を示す図(その2)である。It is FIG. (2) which shows an example of the evaluation result in this embodiment. 本実施形態における評価結果の一例を示す図(その3)である。It is FIG. (3) which shows an example of the evaluation result in this embodiment.

<本発明について>
本発明は、例えば開発リスク等による開発プロセス改善効果の評価について、プロセス改善の計画に対する費用対効果や、目標水準達成による認証取得の場合の費用対効果、完了したプロジェクトの費用対効果等を選択的に提示することを可能とする。
<About the present invention>
The present invention selects, for example, the cost effectiveness of the process improvement plan, the cost effectiveness in the case of obtaining the certification by achieving the target level, the cost effectiveness of the completed project, etc. Can be presented.

以下に、本発明における開発プロセス改善効果の評価装置、評価方法、及び評価プログラムを好適に実施した形態について、図面を用いて説明する。なお、以下の実施形態では、開発プロセスの一例としてCMMIを適用した場合の例を説明するが、本発明においてはこれに限定されるものではなく、例えばISO12207やAutomotive SPICE(登録商標)等でも同様に適用することができる。   DESCRIPTION OF EMBODIMENTS Hereinafter, embodiments in which an evaluation apparatus, an evaluation method, and an evaluation program for a development process improvement effect according to the present invention are suitably implemented will be described with reference to the drawings. In the following embodiment, an example in which CMMI is applied as an example of a development process will be described. However, the present invention is not limited to this, and the same applies to, for example, ISO 12207 and Automotive SPICE (registered trademark). Can be applied to.

<開発プロセス改善効果の評価装置のブロック構成例>
まず、本実施形態における開発プロセス改善効果の評価装置について図を用いて説明する。図1は、本実施形態における評価装置のブロック構成の一例を示す図である。図1に示す評価装置10は、開発プロセス改善計画設定手段11と、目標達成追加設定手段12と、リスク見積設定手段13と、リスクコスト変換手段14と、効果費用取得手段15と、評価結果出力手段16とを有する。また、評価装置10は、ギャップテーブル21と、プロジェクトテーブル22と、費用ファイル23と、開発プロセス改善計画入力画面ファイル24と、目標達成追加入力画面ファイル25と、達成所要コストテーブル26と、リスク見積入力画面ファイル27と、リスクコスト変換テーブル28と、効果ファイル29と、達成効果テーブル30とを有する。
<Block configuration example of evaluation device for development process improvement effect>
First, a development process improvement effect evaluation apparatus according to the present embodiment will be described with reference to the drawings. FIG. 1 is a diagram illustrating an example of a block configuration of an evaluation apparatus according to the present embodiment. The evaluation device 10 shown in FIG. 1 includes a development process improvement plan setting unit 11, a goal achievement addition setting unit 12, a risk estimate setting unit 13, a risk cost conversion unit 14, an effect cost acquisition unit 15, and an evaluation result output. Means 16. The evaluation apparatus 10 also includes a gap table 21, a project table 22, a cost file 23, a development process improvement plan input screen file 24, a target achievement additional input screen file 25, an achievement required cost table 26, and a risk estimate. An input screen file 27, a risk cost conversion table 28, an effect file 29, and an achievement effect table 30 are included.

図1の例では、開発プロセス改善をCMMIのプラクティスまで詳細化して評価する。これは、例えば、ISO12207やAutomotive SPICEのタスクに相当するものである。したがって、他の実施形態としては、例えばISO12207やAutomotive SPICEのタスクで評価することもできる。   In the example of FIG. 1, development process improvement is evaluated in detail up to CMMI practices. This corresponds to, for example, a task of ISO12207 or Automotive SPICE. Therefore, as another embodiment, for example, it can be evaluated by a task of ISO12207 or Automobile SPICE.

ここで、図1に示す評価装置10では、まず、開発プロセスの達成目標水準(例えば、CMMI成熟度レベル3やISO12207の能力レベル3)等を設定し、評価を行う所要プラクティスを決定し、各プラクティスの現状とのギャップを明確にした情報を作成し、それらの情報をギャップテーブル21に格納しておく。   Here, in the evaluation apparatus 10 shown in FIG. 1, first, an achievement target level of the development process (for example, CMMI maturity level 3 or ISO 12207 capability level 3) is set, and a required practice to be evaluated is determined. Information that clarifies the gap with the current state of practice is created, and the information is stored in the gap table 21.

なお、ギャップテーブル21へのデータの入力等は、例えば評価装置10にディスプレイ等の出力手段やキーボートやマウス、タッチパネル等の入力手段等を設け、評価装置10の使用者やプロジェクトマネージャ等(ユーザ)が、ディスプレイの画面を見ながら入力手段等を用いて入力することができる。更に、ギャップテーブル21は、例えばインターネットやLAN(Local Area Network)等の通信ネットワークにより評価装置10と接続可能で、更にデータの送受信が可能な外部装置から取得してもよい。   For example, data input to the gap table 21 is provided with an output means such as a display or an input means such as a keyboard, a mouse, or a touch panel in the evaluation apparatus 10, and a user or project manager of the evaluation apparatus 10 (user). However, it is possible to input using the input means while looking at the screen of the display. Further, the gap table 21 may be obtained from an external device that can be connected to the evaluation apparatus 10 via a communication network such as the Internet or a LAN (Local Area Network) and can transmit and receive data.

次に、評価装置10における開発プロセス改善計画設定手段11は、上述したギャップテーブル21を読み込み、更に入力される開発プロセス改善計画データ等に基づいて、例えばプラクティス毎の開発プロセス改善計画や要員・ツール等の見積指標、その見積費用や見積工数等を設定する。なお、開発プロセス改善計画データとしては、例えば「計画」、「見積指標」、「見積」等があるが、本発明においてはこれに限定されるものではない。また、開発プロセス改善計画データは、例えばユーザ等により入力手段等を用いて入力してもよく、また外部装置等から取得してもよい。   Next, the development process improvement plan setting means 11 in the evaluation apparatus 10 reads the gap table 21 described above, and further develops, for example, a development process improvement plan for each practice and personnel / tool based on the input development process improvement plan data. Estimated indicators, etc., estimated costs, estimated man-hours, etc. are set. The development process improvement plan data includes, for example, “plan”, “estimated index”, “estimate”, and the like, but is not limited to this in the present invention. Further, the development process improvement plan data may be input by the user using an input unit or the like, or may be acquired from an external device or the like.

ここで、開発プロセス改善計画設定手段11において設定される見積工数は、例えばプロジェクトテーブル22のデータを用いて費用に変換される。また、開発プロセス改善計画設定手段11は、変換した費用を集計し、その結果を費用ファイル23に格納する。また、開発プロセス改善計画設定手段11は、設定された設定データを開発プロセス改善計画入力画面ファイル24に保存する。開発プロセス改善計画入力画面ファイル24の内容は、評価装置10の画面に表示することができる。   Here, the estimated man-hour set in the development process improvement plan setting means 11 is converted into a cost using, for example, data of the project table 22. Further, the development process improvement plan setting means 11 totals the converted costs and stores the results in the cost file 23. Further, the development process improvement plan setting means 11 stores the set setting data in the development process improvement plan input screen file 24. The contents of the development process improvement plan input screen file 24 can be displayed on the screen of the evaluation apparatus 10.

目標達成追加設定手段12は、上述したギャップテーブル21を読み込み、更にユーザ等により入力される目標達成のための追加データ等に基づいて、例えば開発プロセスのレベルを達成目標水準まで上げるために必要な実施項目や見積指標、その見積費用や見積工数を設定する。なお、追加データとしては、例えば「項目」、「見積指標」、「見積」等があるが、本発明においてはこれに限定されるものではない。また、追加データは、例えばユーザ等により入力手段等を用いて入力してもよく、また外部装置等から入力してもよい。   The goal achievement additional setting unit 12 reads the gap table 21 described above, and further, for example, is necessary for raising the level of the development process to the goal level based on the additional data for goal achievement inputted by the user or the like. Set the action item, estimated index, estimated cost and estimated man-hour. The additional data includes, for example, “item”, “estimation index”, “estimation”, and the like, but is not limited to this in the present invention. Further, the additional data may be input by the user using an input unit or the like, or may be input from an external device or the like.

ここで、目標達成追加設定手段12において設定される見積工数は、例えばプロジェクトテーブル22のデータを用いて費用に変換される。また、目標達成追加設定手段12は、変換した費用を集計し、その結果を費用ファイル23に格納する。また、目標達成追加設定手段12は、設定された設定データを目標達成追加入力画面ファイル25に保存する。目標達成追加入力画面ファイル25の内容は、評価装置10の画面に表示することができる。更に、目標達成追加設定手段12は、目標水準達成のための認証等の費用を、達成所要コストテーブル26から取得し、取得した費用を費用ファイル23に格納することもできる。   Here, the estimated man-hour set in the target achievement additional setting means 12 is converted into a cost using, for example, data of the project table 22. Further, the goal achievement additional setting means 12 totals the converted costs and stores the results in the cost file 23. The goal achievement addition setting means 12 stores the set setting data in the goal achievement addition input screen file 25. The contents of the goal achievement additional input screen file 25 can be displayed on the screen of the evaluation device 10. Further, the target achievement additional setting means 12 can acquire the cost for authentication for achieving the target level from the achievement required cost table 26 and store the acquired cost in the cost file 23.

リスク見積設定手段13は、入力されるリスク見積データ等に基づいて、例えばギャップテーブル21におけるリスクを評価し、開発プロセス改善計画設定手段11で設定した設定データや、目標達成追加設定手段12で設定した設定データ等により、リスクが回避できる確率等を設定する。なお、リスク見積データは、例えばユーザ等により入力手段等を用いて入力してもよく、また外部装置等から入力してもよい。また、リスク見積設定手段13は、設定された設定データをリスク見積入力画面ファイル27に格納する。リスク見積入力画面ファイル27の内容は、評価装置10の画面に表示することができる。   The risk estimate setting means 13 evaluates the risk in the gap table 21 based on the input risk estimate data and the like, and is set by the setting data set by the development process improvement plan setting means 11 or the target achievement additional setting means 12. The probability that the risk can be avoided is set by the set data. Note that the risk estimation data may be input by the user or the like using an input unit or the like, or may be input from an external device or the like. The risk estimate setting unit 13 stores the set setting data in the risk estimate input screen file 27. The contents of the risk estimate input screen file 27 can be displayed on the screen of the evaluation apparatus 10.

なお、上述した開発プロセス改善計画入力画面ファイル24、目標達成追加入力画面ファイル25、及びリスク見積入力画面ファイル27の内容は、例えば評価装置10の画面に表示されるファイルである。ユーザ等は、画面を参照しながら入力手段等を用いて各種設定の入力、変更等を行うことができる。   The contents of the development process improvement plan input screen file 24, the goal achievement addition input screen file 25, and the risk estimate input screen file 27 described above are files displayed on the screen of the evaluation apparatus 10, for example. A user or the like can input or change various settings using an input unit or the like while referring to the screen.

リスクコスト変換手段14は、リスク見積設定手段13により得られる設定データや、予めユーザ等により設定されたリスクコスト変換テーブル28及びプロジェクトテーブル22から得られるデータ等に基づいて、例えば目標水準達成により回避されるリスクを計算して費用に変換し、変換した費用等を効果ファイル29に格納する。   The risk cost conversion means 14 is avoided by achieving the target level, for example, based on the setting data obtained by the risk estimate setting means 13, data obtained from the risk cost conversion table 28 and the project table 22 set in advance by the user or the like. The calculated risk is converted into a cost, and the converted cost is stored in the effect file 29.

効果費用取得手段15は、ユーザ等により予め設定された達成効果テーブル30から、目標水準達成により追加される効果費用を取得する。また、効果費用取得手段15は、取得した効果費用を効果ファイル29に格納する。また、効果費用取得手段15は、各項目について効果費用を合計し、効果ファイル29の目標水準達成効果の項目と効果費用に格納する。更に、効果費用取得手段15は、リスクコスト変換手段14や効果費用取得手段15により得られた結果を、費用ファイル23に格納する。   The effect cost acquisition means 15 acquires the effect cost added by achievement of the target level from the achievement effect table 30 preset by the user or the like. In addition, the effect cost acquisition unit 15 stores the acquired effect cost in the effect file 29. Further, the effect cost acquisition means 15 totals the effect costs for each item, and stores them in the target level achievement effect item and the effect cost of the effect file 29. Further, the effect cost acquisition unit 15 stores the result obtained by the risk cost conversion unit 14 and the effect cost acquisition unit 15 in the cost file 23.

評価結果出力手段16は、例えば費用ファイル23、効果ファイル29、開発プロセス改善計画入力画面ファイル24、目標達成追加入力画面ファイル25のデータ等を選択的に参照し、開発プロセス改善計画の費用対効果、更に目標水準達成に要する費用とその効果等を評価結果31として画面や外部等に出力する。   The evaluation result output means 16 selectively refers to, for example, the data of the cost file 23, the effect file 29, the development process improvement plan input screen file 24, the target achievement additional input screen file 25, etc., and the cost effectiveness of the development process improvement plan. Further, the cost required for achieving the target level and the effect thereof are output as an evaluation result 31 to the screen or the outside.

なお、評価結果出力手段16は、例えば開発プロセス改善の費用対効果を評価する際に、開発プロセス改善計画設定手段11等により設定された改善計画データの費用に関係なく、実績費用や実績効果等を含めて評価することもできる。また、評価結果出力手段16は、例えば各プラクティスに関係なく、予め設定された評価区分と、その評価区分に対して予め設定された目標水準とを用いて評価することもできる。   For example, the evaluation result output unit 16 evaluates the actual cost or the actual effect regardless of the cost of the improvement plan data set by the development process improvement plan setting unit 11 or the like when evaluating the cost effectiveness of the development process improvement. Can also be evaluated. Moreover, the evaluation result output means 16 can also evaluate using the preset evaluation division and the target level preset with respect to the evaluation division irrespective of each practice, for example.

ここで、本実施形態では、上述した開発プロセス改善計画設定手段11における処理と、目標達成追加設定手段12における処理を両方行ってもよく、何れか一方のみを行ってもよい。   Here, in the present embodiment, both the process in the development process improvement plan setting unit 11 and the process in the target achievement additional setting unit 12 may be performed, or only one of them may be performed.

また、上述したファイルやテーブルの入力は、上述したようにユーザが直接入力してもよく、外部装置から取得してもよい。更に、上述した各ファイルやテーブルは、評価装置10が備える補助記憶装置等の蓄積手段に格納されており、必要に応じて読み出したり、書き込んだりすることができる。なお、上述した各ファイルやテーブルの内容、及び各手段における具体例については後述する。   Further, the input of the above-described file or table may be input directly by the user as described above, or may be acquired from an external device. Furthermore, each of the files and tables described above is stored in storage means such as an auxiliary storage device provided in the evaluation apparatus 10, and can be read or written as necessary. The contents of the files and tables described above and specific examples of each means will be described later.

<ハードウェア構成例>
ここで、上述した評価装置10においては、評価装置10が有する各手段において処理される各機能をコンピュータ(ハードウェア)に実行させることができる実行プログラム(評価プログラム)を生成し、例えば汎用のパーソナルコンピュータ、サーバ等にその実行プログラムをインストールすることにより、本発明における評価処理等を実現することができる。
<Hardware configuration example>
Here, in the evaluation apparatus 10 described above, an execution program (evaluation program) capable of causing a computer (hardware) to execute each function processed by each unit included in the evaluation apparatus 10 is generated. By installing the execution program in a computer, a server, etc., the evaluation process in the present invention can be realized.

ここで、本実施形態における評価処理が実現可能なコンピュータのハードウェア構成例について図を用いて説明する。図2は、本実施形態における評価処理が実現可能なハードウェア構成の一例を示す図である。   Here, an example of a hardware configuration of a computer capable of realizing the evaluation process in the present embodiment will be described with reference to the drawings. FIG. 2 is a diagram illustrating an example of a hardware configuration capable of realizing the evaluation process according to the present embodiment.

図2におけるコンピュータ本体には、入力装置41と、出力装置42と、ドライブ装置43と、補助記憶装置44と、メモリ装置45と、各種制御を行うCPU(Central Processing Unit)46と、ネットワーク接続装置47とを有するよう構成されており、これらはシステムバスBで相互に接続されている。   2 includes an input device 41, an output device 42, a drive device 43, an auxiliary storage device 44, a memory device 45, a CPU (Central Processing Unit) 46 that performs various controls, and a network connection device. 47, which are connected to each other by a system bus B.

入力装置41は、ユーザ等が操作するキーボード及びマウス等のポインティングデバイスを有しており、ユーザ等からのプログラムの実行等、各種操作信号を入力する。   The input device 41 has a pointing device such as a keyboard and a mouse operated by a user or the like, and inputs various operation signals such as execution of a program from the user or the like.

出力装置42は、本発明における処理を行うためのコンピュータ本体を操作するのに必要な各種ウィンドウやデータ等を表示するディスプレイを有し、CPU46が有する制御プログラムによりプログラムの実行経過や結果等を表示することができる。   The output device 42 has a display for displaying various windows and data necessary for operating the computer main body for performing processing according to the present invention, and displays the program execution progress, results, and the like by the control program of the CPU 46. can do.

なお、上述した入力した入力装置41及び出力装置42は、例えばタッチパネルのように入出力が可能な一体型の装置であってもよい。また、出力装置42は、例えばプリンタ等の印刷装置を有し、実行結果を印刷媒体等に印刷してもよい。   The input device 41 and the output device 42 that have been input may be integrated devices capable of input / output, such as a touch panel. Further, the output device 42 may include a printing device such as a printer and print the execution result on a print medium or the like.

ここで、本実施形態においてコンピュータ本体にインストールされる実行プログラムは、例えばUSB(Universal Serial Bus)メモリやCD−ROM等の可搬型の記録媒体48等により提供される。プログラムを記録した記録媒体48は、ドライブ装置43にセット可能であり、記録媒体48に含まれる実行プログラムが、記録媒体48からドライブ装置43を介して補助記憶装置44にインストールされる。   Here, the execution program installed in the computer main body in this embodiment is provided by a portable recording medium 48 such as a USB (Universal Serial Bus) memory or a CD-ROM, for example. The recording medium 48 on which the program is recorded can be set in the drive device 43, and the execution program included in the recording medium 48 is installed in the auxiliary storage device 44 from the recording medium 48 via the drive device 43.

補助記憶装置44は、ハードディスク等のストレージ手段であり、本実施形態における実行プログラムやコンピュータに設けられた制御プログラム、本実施形態における評価処理を実行するために必要な各種データや実行結果として得られる各種データ(例えば、ギャップテーブル21、プロジェクトテーブル22、費用ファイル23、開発プロセス改善計画入力画面ファイル24、目標達成追加入力画面ファイル25、達成所要コストテーブル26、リスク見積入力画面ファイル27、リスクコスト変換テーブル28、効果ファイル29、達成効果テーブル30、評価結果31)等を蓄積し、必要に応じて入出力を行うことができる。   The auxiliary storage device 44 is a storage unit such as a hard disk, and is obtained as an execution program in the present embodiment, a control program provided in the computer, various data and execution results necessary for executing the evaluation process in the present embodiment. Various data (for example, gap table 21, project table 22, cost file 23, development process improvement plan input screen file 24, goal achievement additional input screen file 25, achievement required cost table 26, risk estimate input screen file 27, risk cost conversion The table 28, the effect file 29, the achievement effect table 30, the evaluation result 31) and the like can be accumulated and input / output can be performed as necessary.

メモリ装置45は、CPU46により補助記憶装置44から読み出された実行プログラム等を格納する。なお、メモリ装置45は、ROM(Read Only Memory)やRAM(Random Access Memory)等からなる。   The memory device 45 stores an execution program read from the auxiliary storage device 44 by the CPU 46. The memory device 45 includes a ROM (Read Only Memory), a RAM (Random Access Memory), and the like.

CPU46は、OS(Operating System)等の制御プログラム、及びメモリ装置45に格納されている実行プログラムに基づいて、各種演算や各ハードウェア構成部とのデータの入出力等、コンピュータ全体の処理を制御して、本実施形態における評価処理を実現することができる。なお、プログラムの実行中に必要な各種情報等は、補助記憶装置44から取得することができ、また実行結果等を格納することもできる。   The CPU 46 controls processing of the entire computer, such as various operations and input / output of data with each hardware component, based on a control program such as an OS (Operating System) and an execution program stored in the memory device 45. Thus, the evaluation process in the present embodiment can be realized. Various information necessary during the execution of the program can be acquired from the auxiliary storage device 44, and an execution result or the like can be stored.

ネットワーク接続装置47は、通信ネットワーク等と接続することにより、実行プログラムを通信ネットワークに接続されている他の端末等から取得したり、プログラムを実行することで得られた実行結果又は本発明における実行プログラム自体を他の端末等に提供することができる。また、ネットワーク接続装置47は、通信ネットワーク等を介して外部装置から、本発明における評価処理を実施するために必要な各種データを取得することができる。   The network connection device 47 obtains an execution program from another terminal connected to the communication network by connecting to a communication network or the like, or the execution result obtained by executing the program or the execution in the present invention The program itself can be provided to other terminals. In addition, the network connection device 47 can acquire various data necessary for performing the evaluation processing according to the present invention from an external device via a communication network or the like.

上述したようなハードウェア構成により、本発明における評価処理を実行することができる。また、プログラムをインストールすることにより、汎用のパーソナルコンピュータ等で本発明における評価処理を容易に実現することができる。   With the hardware configuration as described above, the evaluation process in the present invention can be executed. Further, by installing the program, the evaluation processing in the present invention can be easily realized by a general-purpose personal computer or the like.

<テーブル、ファイルの具体例>
次に、上述した各種テーブル、ファイルの具体例について、図を用いて説明する。
<Specific examples of tables and files>
Next, specific examples of the various tables and files described above will be described with reference to the drawings.

<ギャップテーブル21の具体例>
図3は、ギャップテーブルの具体例を示す図である。図3に示すギャップテーブル21は、図3(a)に示す全体構成と、図3(b)に示すギャップテーブル構成とを有する。図3(a)に示す全体構成では、「プロジェクトプロセス領域」−「ゴール」−「プラクティス」といった構成と、「組織プロセス」−「ゴール」−「プラクティス」といった構成との2つの構成とを有する。
<Specific Example of Gap Table 21>
FIG. 3 is a diagram illustrating a specific example of the gap table. The gap table 21 shown in FIG. 3 has an overall configuration shown in FIG. 3A and a gap table configuration shown in FIG. The overall configuration shown in FIG. 3A has two configurations: “project process area” — “goal” — “practice” and “organization process” — “goal” — “practice”. .

つまり、ギャップテーブル21の全体構成では、プロジェクトプロセス領域と組織プロセス領域に大別され、各プロセス領域はゴールに詳細化され、更に各ゴールはプラクティスに詳細化される。なお、プロジェクトプロセス領域、組織プロセス領域、ゴール、及びプラクティスは、CMMIで定義されている。   That is, the overall configuration of the gap table 21 is roughly divided into a project process area and an organization process area, each process area is detailed into a goal, and each goal is further detailed into a practice. The project process area, organization process area, goal, and practice are defined by CMMI.

また、図3(b)に示すギャップテーブル構成では、項目として、「プラクティスID」、「プラクティス名称」、「ギャップ」等を有する。   In addition, the gap table configuration shown in FIG. 3B includes “practice ID”, “practice name”, “gap”, and the like as items.

「プラクティスID」は、CMMIのプラクティスに番号を付したものである。ここで、本実施形態では、プラクティスの3種類の数値が「.」で連結した構成になっており、1つ目の数値(一番左)は、CMMIのプロセスに通し番号を付したものであり、2つ目の数値(中央)と3つ目の数値(一番右)は、CMMIの固有プラクティスの番号を付したものである。   “Practice ID” is a number assigned to a CMMI practice. Here, in this embodiment, the three types of practice values are connected by “.”, And the first number (leftmost) is a CMMI process numbered serially. The second numerical value (center) and the third numerical value (rightmost) are numbers assigned to CMMI specific practices.

なお、ギャップテーブル21に格納するプラクティスIDは、例えばCMMIの全プラクティスであってもよく、またCMMIの成熟度レベル3までのプラクティス等のように、予め絞りこんだプラクティス等であってもよく、必要に応じて任意に設定を行うことができる。   The practice ID stored in the gap table 21 may be, for example, all CMMI practices, or may be practices that have been narrowed down in advance, such as practices up to CMMI maturity level 3. Any setting can be made as required.

また、「プラクティス名称」は、プロセス領域の名称とプラクティスのタイトルとを記載する。「ギャップ」は、CMMIの各プラクティスに対するギャップを設定する。つまり、「ギャップ」は、例えば目標水準と現状とのギャップを設定する。なお、「ギャップ」は、CMMIのアセスメント等により分析される。なお、「ギャップ」の項目の「−」は、そのプラクティスIDには、記載する内容がないことを示しており、以下の説明でも同様とする。   “Practice name” describes the name of the process area and the title of the practice. “Gap” sets a gap for each CMMI practice. In other words, the “gap” sets, for example, a gap between the target level and the current state. The “gap” is analyzed by CMMI assessment or the like. Note that “-” in the item of “gap” indicates that the practice ID has no content to be described, and the same applies to the following description.

<プロジェクトテーブル22の具体例>
図4は、プロジェクトテーブルの具体例を示す図である。図4に示すプロジェクトテーブル22では、項目として、「プロジェクト工数」、「プロジェクト期間」、「月あたり売上増加(工数換算)」、「工数単価」等を有する。
<Specific example of the project table 22>
FIG. 4 is a diagram showing a specific example of the project table. The project table 22 shown in FIG. 4 includes items such as “project man-hour”, “project period”, “sales increase per month (in man-hour conversion)”, “man-hour unit price”, and the like.

プロジェクトテーブル22は、プロジェクトに適用する場合の当該プロジェクトのプロジェクト工数、プロジェクトの期間、月あたり売上増加の見積値、工数の単価を格納する。月あたり売上増加は、例えば開発した製品を上市した場合に期待される売上増加額である。   The project table 22 stores the project man-hour of the project, the project period, the estimated increase in sales per month, and the unit price of the man-hour when applied to the project. The increase in sales per month is, for example, an increase in sales expected when a developed product is launched.

<費用ファイル23の具体例>
図5は、費用テーブルの具体例を示す図である。図5に示す費用ファイル23では、項目として、「分類」、「費用負担」、「内訳」、「費用(千円)」等を有する。図5に示す費用ファイル23は、開発プロセス改善計画設定手段11及び目標達成追加設定手段12等で計算した費用の集計値を格納するファイルである。「分類」は、例えば費用を開発プロセス改善計画費用と目標水準達成費用とに分類する。「費用負担」は、例えば負担元が組織かプロジェクトの何れかを記載する。
<Specific example of cost file 23>
FIG. 5 is a diagram illustrating a specific example of the cost table. The cost file 23 shown in FIG. 5 includes “classification”, “cost burden”, “breakdown”, “cost (thousand yen)”, and the like as items. The cost file 23 shown in FIG. 5 is a file for storing the total cost value calculated by the development process improvement plan setting unit 11 and the target achievement addition setting unit 12. “Classification” classifies, for example, costs into development process improvement plan costs and target level achievement costs. “Cost burden” describes, for example, whether the burden source is an organization or a project.

ここで、例えば開発プロセス改善計画費用のプロジェクトの「内訳」は、例えば要員増強、ツール導入、トレーニング、手順テーラリング等を内訳とする。これは、図3に示す全体構成のプロジェクトプロセス領域が対象となる。   Here, for example, the “breakdown” of the development process improvement plan cost project includes, for example, personnel increase, tool introduction, training, procedure tailoring, and the like. This is for the project process area of the overall configuration shown in FIG.

また、例えば、開発プロセス改善計画費用の組織の「内訳」は、例えば組織標準手順書作成費用、要員増強、ツール導入、トレーニング等を内訳とする。これは、図3に示す全体構成の組織プロセス領域が対象となる。   Further, for example, the “breakdown” of the organization of the development process improvement plan cost includes, for example, the organization standard procedure manual preparation cost, personnel increase, tool introduction, training, and the like. This is for the organization process area of the overall configuration shown in FIG.

また、目標水準達成費用のプロジェクトの「内訳」は、例えば達成所要コストテーブル26の費用負担がプロジェクトの項目をコピーしたものになる。   Further, the “breakdown” of the project of the target level achievement cost is, for example, that the cost burden of the achievement required cost table 26 is a copy of the project item.

更に、目標水準達成費用の組織の「内訳」は、例えば達成所要コストテーブル26の費用負担が組織の項目をコピーしたものになる。また、「費用」は、「内訳」に対応した費用の集計値が格納される。なお、図5の「費用」の「・・・」は、例えば必要に応じて何らかの数値等が入力されていることを示しており、以下の説明でも同様とする。   Furthermore, the “breakdown” of the organization of the target level achievement cost is, for example, that the expense burden of the achievement required cost table 26 is a copy of the organization item. In addition, “cost” stores a total cost value corresponding to “breakdown”. Note that “...” of “cost” in FIG. 5 indicates that, for example, some numerical value or the like is input as necessary, and the same applies to the following description.

<開発プロセス改善計画入力画面ファイル24の具体例>
図6は、開発プロセス改善計画入力画面ファイルの具体例を示す図である。図6に示す開発プロセス改善計画入力画面ファイル24では、項目として、「プラクティスID」、「プラクティス名称」、「ギャップ」、「※開発プロセス改善計画」、「開発プロセス改善計画費用見積」、「費用(千円)」等を有する。また、「開発プロセス改善計画費用見積」では、更に細分化した項目として、「※要員増強」、「※ツール導入」、「※トレーニング」、「※手順テーラリング」等を有する。なお、上述した※印は、ユーザ等による入力項目を示しており、以下の説明でも同様とする。
<Specific example of development process improvement plan input screen file 24>
FIG. 6 is a diagram showing a specific example of the development process improvement plan input screen file. In the development process improvement plan input screen file 24 shown in FIG. 6, “practice ID”, “practice name”, “gap”, “* development process improvement plan”, “development process improvement plan cost estimate”, “cost” (Thousand yen) ”. In addition, “Development process improvement plan cost estimate” has “* personnel increase”, “* tool introduction”, “* training”, “* procedure tailoring”, etc. as more detailed items. The above-mentioned * marks indicate items input by the user or the like, and the same applies to the following description.

開発プロセス改善計画入力画面ファイル24は、例えば開発プロセス改善計画設定手段11の設定に対して、例えば設定中に画面に表示される表示データや、ユーザ等が入力する入力データ、設定に対する何らかの演算結果を示す演算データを格納する。開発プロセス改善計画入力画面ファイル24に示す「プラクティスID」、「プラクティス名称」、及び「ギャップ」は、ギャップテーブル21の内容と同じである。   The development process improvement plan input screen file 24 is, for example, for the setting of the development process improvement plan setting means 11, for example, display data displayed on the screen during the setting, input data input by the user, etc., some calculation result for the setting Is stored. The “practice ID”, “practice name”, and “gap” shown in the development process improvement plan input screen file 24 are the same as the contents of the gap table 21.

「開発プロセス改善計画」は、各プラクティスIDのギャップを埋めるための開発プロセス改善計画の入力データを格納する。また、「開発プロセス改善費用見積」は、各プラクティスIDの開発プロセス改善計画を実施するための見積工数や費用を格納する。   The “development process improvement plan” stores input data of the development process improvement plan for filling the gap between the practice IDs. The “development process improvement cost estimate” stores an estimated man-hour and cost for executing the development process improvement plan for each practice ID.

「開発プロセス改善費用見積」の項目としては、図3に示す全体構成のプロジェクトプロセス領域の場合は、例えば要員増強、ツール導入、トレーニング、手順テーラリング等であり、組織プロセス領域の場合は、例えば組織標準手順書作成費用、要員増強、ツール導入、トレーニング等である。また、「費用」は、開発プロセス改善費用見積のデータを費用に変換して集計したデータを格納する。   In the case of the project process area of the overall configuration shown in FIG. 3, for example, the “development process improvement cost estimate” includes personnel increase, tool introduction, training, procedure tailoring, etc. Costs for creating the organization standard procedure, personnel increase, tool introduction, training, etc. Further, “cost” stores data obtained by converting development process improvement cost estimate data into costs and tabulating them.

<目標達成追加入力画面ファイル25の具体例>
図7は、目標達成追加入力画面ファイルの具体例を示す図である。図7に示す目標達成追加入力画面ファイル25では、項目として、「プラクティスID」、「プラクティス名称」、「開発プロセス改善計画」、「※目標水準達成所要項目」、「目標水準達成費用見積」、「費用(千円)」等を有する。また、「目標水準達成費用見積」では、更に細分化した項目として、「※要員増強」、「※ツール導入」、「※トレーニング」、「※手順テーラリング」等を有する。
<Specific example of goal achievement additional input screen file 25>
FIG. 7 is a diagram showing a specific example of the goal achievement additional input screen file. In the goal achievement additional input screen file 25 shown in FIG. 7, the items are “practice ID”, “practice name”, “development process improvement plan”, “* target level achievement required item”, “target level achievement cost estimate”, “Cost (thousand yen)” etc. In addition, “Target level achievement cost estimation” has “* personnel increase”, “* tool introduction”, “* training”, “* procedural tailoring”, etc. as further subdivided items.

目標達成追加入力画面ファイル25は、目標達成追加設定手段12の表示データと入力データと演算データとを格納する。   The goal achievement addition input screen file 25 stores display data, input data, and calculation data of the goal achievement addition setting means 12.

目標達成追加入力画面ファイル25において、「プラクティスID」、「プラクティス名称」、「ギャップ」、「開発プロセス改善計画」は、例えば開発プロセス改善計画入力画面ファイル24と同様の内容を格納する。   In the goal achievement addition input screen file 25, “practice ID”, “practice name”, “gap”, and “development process improvement plan” store the same contents as the development process improvement plan input screen file 24, for example.

「目標水準達成所要項目」は、各プラクティスIDのギャップと開発プロセス改善計画により埋まらないギャップを埋めるための目標水準達成所要項目の入力データを格納する。また、「目標水準達成費用見積」は、各プラクティスIDの目標水準達成所要項目を実施するための、見積工数や費用を格納する。   “Target level achievement required item” stores input data of target level achievement required items for filling gaps between practice IDs and gaps not filled by the development process improvement plan. “Target level achievement cost estimate” stores the estimated man-hours and costs for executing the target level achievement required items of each practice ID.

また、目標水準達成費用見積の項目は、図3に示す全体構成のプロジェクトプロセス領域の場合は、例えば要員増強、ツール導入、トレーニング、手順テーラリング等であり、組織プロセス領域の場合は、例えば組織標準手順書作成費用、要員増強、ツール導入、トレーニング等である。また、「費用」は、目標水準達成費用見積のデータを費用に変換して集計したデータを格納する。   The target level achievement cost estimation items are, for example, personnel increase, tool introduction, training, procedure tailoring, etc. in the case of the project process area of the overall configuration shown in FIG. Standard procedure documentation costs, personnel expansion, tool introduction, training, etc. “Cost” stores data obtained by converting the data for estimating the target level achievement cost into the cost and collecting the data.

<達成所要コストテーブル26の具体例>
図8は、達成所要コストテーブルの具体例を示す図である。図8に示す達成所要コストテーブル26では、項目として、「分類」、「費用負担」、「内訳」、「費用(千円)」等を有する。達成所要コストテーブル26は、目標水準を達成するために必要となるコストを設定したテーブルである。
<Specific Example of Achievement Required Cost Table 26>
FIG. 8 is a diagram showing a specific example of the achievement required cost table. The achievement required cost table 26 shown in FIG. 8 has items such as “classification”, “cost burden”, “breakdown”, and “cost (thousand yen)” as items. The achievement required cost table 26 is a table in which a cost necessary for achieving the target level is set.

達成所要コストテーブル26において、「分類」は、例えば所要コストの分類を記載する。また、「費用負担」は、例えば内訳に対して負担元が組織かプロジェクトの何れかを記載する。また、「内訳」は、例えば費用の内訳を記載する。また、「費用」は、例えば内訳に対応した費用を記載する。   In the achievement required cost table 26, “classification” describes, for example, classification of required cost. “Cost burden” describes, for example, whether the burden source is an organization or a project for the breakdown. “Breakdown” describes, for example, a breakdown of expenses. “Cost” describes, for example, a cost corresponding to the breakdown.

<リスク見積入力画面ファイル27の具体例>
図9は、リスク見積入力画面ファイルの具体例を示す図である。図9に示すリスク見積入力画面ファイル27は、例えば図9(a)に示すメイン画面と、図9(b)に示すサブ画面とを有する。
<Specific example of risk estimate input screen file 27>
FIG. 9 is a diagram illustrating a specific example of the risk estimate input screen file. The risk estimate input screen file 27 illustrated in FIG. 9 includes, for example, a main screen illustrated in FIG. 9A and a sub screen illustrated in FIG. 9B.

図9(a)に示すメイン画面の項目としては、例えば「プラクティスID」、「プラクティス名称」、「ギャップ」、「影響項目」、「※影響度」、「※発生確率」、「開発プロセス改善計画」、「※リスク回避確率」等を有する。   The main screen items shown in FIG. 9A include, for example, “practice ID”, “practice name”, “gap”, “influence item”, “* impact level”, “* occurrence probability”, “development process improvement” “Plan”, “Risk avoidance probability”, etc.

また、図9(b)に示すサブ画面の項目としては、例えば、「影響度」、「コスト」、「納期」、「品質」等を有する。   Further, the items of the sub screen shown in FIG. 9B include, for example, “influence”, “cost”, “delivery date”, “quality”, and the like.

リスク見積入力画面ファイル27において、「プラクティスID」、「プラクティス名称」、「ギャップ」、「開発プロセス改善計画」は、例えば開発プロセス改善計画入力画面ファイル24と同様の内容を格納する。また、「影響項目」は、例えばコスト、納期、品質等を設定する。   In the risk estimate input screen file 27, “practice ID”, “practice name”, “gap”, and “development process improvement plan” store the same contents as the development process improvement plan input screen file 24, for example. In the “influence item”, for example, cost, delivery date, quality, and the like are set.

「※影響度」と「※発生確率」は、各プラクティスIDのギャップによるリスクの影響度と発生確率の入力データを格納する。「リスク回避確率」は、開発プロセス改善計画により当該リスクが回避される確率の入力データを格納する。「リスク回避確率」は、当該プラクティスの目標水準達成(ギャップをなくすこと)をリスク回避確率100%として、ギャップに対する開発プロセス改善の度合いにより設定する。   “* Impact” and “* Occurrence probability” store the input data of the risk impact and the occurrence probability due to the gap of each practice ID. “Risk avoidance probability” stores input data of a probability that the risk is avoided by the development process improvement plan. “Risk avoidance probability” is set according to the degree of improvement of the development process with respect to the gap, assuming that the target level of the practice (to eliminate the gap) is 100% risk avoidance probability.

また、本実施形態では、リスクの影響度と発生確率の入力を支援するために、図9(b)に示すサブ画面を表示する。図9(b)に示すサブ画面は、リスクコスト変換テーブル28のリスク影響度テーブルのデータと、「コスト」、「納期」、「品質」の当該プロジェクトにおける影響割合を数値に変換したデータを表示するものである。   In the present embodiment, a sub-screen shown in FIG. 9B is displayed in order to support the input of the risk influence level and the occurrence probability. The sub-screen shown in FIG. 9B displays the data of the risk impact table of the risk cost conversion table 28 and the data obtained by converting the impact ratios of the “cost”, “delivery date”, and “quality” in the project into numerical values. To do.

<リスクコスト変換テーブル28の具体例>
図10は、リスクコスト変換テーブルの具体例を示す図である。図10に示すリスクコスト変換テーブル28は、例えば図10(a)に示すリスク影響度テーブルと、図10(b)に示す品質影響度コスト変換テーブルとを有する。
<Specific example of risk cost conversion table 28>
FIG. 10 is a diagram illustrating a specific example of the risk cost conversion table. The risk cost conversion table 28 illustrated in FIG. 10 includes, for example, a risk impact level table illustrated in FIG. 10A and a quality impact level cost conversion table illustrated in FIG.

図10(a)に示すリスク影響度テーブルの項目としては、例えば「影響度」、「コスト」、「納期」、「品質」等を有する。また、図10(b)に示す品質影響度コスト変換テーブルは、「リスク影響度」、「変換工数」等を有する。   The items in the risk impact degree table shown in FIG. 10A include, for example, “impact degree”, “cost”, “delivery date”, “quality”, and the like. The quality impact cost conversion table shown in FIG. 10B includes “risk impact”, “conversion man-hour”, and the like.

リスクコスト変換テーブル28は、図10(a)に示すリスク影響度テーブルとして、リスク影響度を5段階に設定し、コスト、納期、品質について各段階の影響度を定義している。これは、例えば、非特許文献2に記載されているリスク影響度の定義表を参考に設定することができるが、本発明においてはこれに限定されるものではない。   The risk cost conversion table 28 is a risk impact level table shown in FIG. 10 (a), in which the risk impact level is set to 5 levels, and the impact level at each level is defined for cost, delivery date, and quality. This can be set with reference to the definition table of the risk influence degree described in Non-Patent Document 2, for example, but is not limited to this in the present invention.

また、図10(b)に示す品質影響度コスト変換テーブルは、図10(a)に示すリスク影響度テーブルの品質について、コストへの変換工数率を定義したものである。なお、図10(b)に示すリスク影響度は、図10(a)のリスク影響度に対応している。また、「変換工数」は、例えばプロジェクトの全工数に対して品質リスクが発生した場合に発生するロスコストの工数比率を定義したものである。   In addition, the quality impact cost conversion table shown in FIG. 10B defines the conversion man-hour rate to cost for the quality of the risk impact degree table shown in FIG. Note that the risk influence degree shown in FIG. 10B corresponds to the risk influence degree shown in FIG. “Conversion man-hour” defines, for example, a man-hour ratio of loss cost that occurs when a quality risk occurs with respect to all man-hours of a project.

<効果ファイル29の具体例>
図11は、効果ファイルの具体例を示す図である。図11に示す効果ファイル29は、例えば図11(a)に示すプロジェクト効果と、図11(b)に示す組織効果と、図11(c)に示すプラクティス単位効果とを有する。
<Specific example of effect file 29>
FIG. 11 is a diagram illustrating a specific example of an effect file. The effect file 29 shown in FIG. 11 has, for example, a project effect shown in FIG. 11A, an organizational effect shown in FIG. 11B, and a practice unit effect shown in FIG.

図11(a)に示すプロジェクト効果の項目としては、例えば「プロジェクト効果」、「項目」、「効果費用(千円)」等を有する。また、図11(b)に示す組織効果としては、「組織効果」、「項目」、「効果費用(千円)」等を有する。また、図11(c)に示すプラクティス単位効果としては、「プラクティスID」、「開発プロセス改善項目」、「開発プロセス改善効果(千円)」、「目標水準達成項目」、「目標水準達成効果(千円)」等を有する。   The project effect items shown in FIG. 11A include, for example, “project effect”, “item”, “effective cost (thousand yen)”, and the like. Also, as the organizational effect shown in FIG. 11B, there are “organizational effect”, “item”, “effective cost (thousand yen)” and the like. The practice unit effects shown in FIG. 11C include “practice ID”, “development process improvement item”, “development process improvement effect (thousand yen)”, “target level achievement item”, and “target level achievement effect”. (Thousand yen) ”.

図11に示す効果ファイル29は、例えばリスクコスト変換手段14及び効果費用取得手段15等で計算した効果費用の集計値等を格納するファイルである。   The effect file 29 shown in FIG. 11 is a file that stores, for example, a total value of effect costs calculated by the risk cost conversion means 14 and the effect cost acquisition means 15.

効果ファイル29において、図11(a)に示すプロジェクト効果は、例えば上述した図3の全体構成のプロジェクトプロセス領域が対象となる。「プロジェクト効果」は、開発プロセス改善効果と目標水準達成効果の分類を格納する。「項目」は、「コスト削減」、「品質向上」、「納期短縮」の項目を格納する。なお、「コスト削減」、「品質向上」、「納期短縮」は、図11リスク見積入力画面ファイルの影響項目に対応した内容を格納する。「効果費用」は、計算した効果費用の集計値を格納する。   In the effect file 29, the project effect shown in FIG. 11 (a) is, for example, the project process area having the overall configuration shown in FIG. “Project effect” stores the classification of the development process improvement effect and the target level achievement effect. The “item” stores items of “cost reduction”, “quality improvement”, and “reduction of delivery date”. “Cost reduction”, “Quality improvement”, and “Delivery time reduction” store the contents corresponding to the influence items of the risk estimate input screen file in FIG. “Effective cost” stores the total value of the calculated effective cost.

また、図11(b)に示す組織効果は、例えば上述した図3に示す全体構成の組織プロセス領域が対象となる。「組織効果」は、開発プロセス改善効果と目標水準達成効果の分類を記載する。「開発プロセス改善効果」の項目は、「コスト削減」、「品質向上」、「納期短縮」の項目を記載する。「効果費用」は、計算した効果費用の集計値を格納する。   Further, the organizational effect shown in FIG. 11 (b) is, for example, the organizational process area of the overall configuration shown in FIG. 3 described above. “Organizational effects” describes the classification of development process improvement effects and target level achievement effects. The items of “development process improvement effect” include items of “cost reduction”, “quality improvement”, and “reduction of delivery date”. “Effective cost” stores the total value of the calculated effective cost.

また、「目標水準達成効果の項目」は、達成効果テーブル30の項目と、「コスト削減」、「品質向上」、「納期短縮」の項目とを記載する。図11(b)に示す達成効果テーブル30の項目の例としては、例えば「認証取得による売上増加」、「PL訴訟回避」等の項目があるが、本発明においてはこれに限定されるものではない。更に、「効果費用」は、達成効果テーブル30の効果費用と、計算したコスト削減、品質向上、納期短縮の効果費用との集計値を格納する。   The “target level achievement effect item” describes the items in the achievement effect table 30 and the items “cost reduction”, “quality improvement”, and “delivery time reduction”. Examples of items in the achievement effect table 30 shown in FIG. 11B include items such as “sales increase due to acquisition of authentication” and “avoidance of PL litigation”, but are not limited to this in the present invention. Absent. Further, “Effective Cost” stores a total value of the effective cost of the achievement effect table 30 and the calculated effective cost for cost reduction, quality improvement, and delivery time reduction.

また、図11(c)に示すプラクティス単位効果は、例えばプラクティスIDに対応した開発プロセス改善のコスト削減、品質向上、納期短縮の項目と効果費用、及び目標水準達成のコスト削減、品質向上、納期短縮の項目と効果費用を格納する。   In addition, the practice unit effect shown in FIG. 11C is, for example, the development process improvement cost reduction, quality improvement, delivery time reduction item and effect cost corresponding to the practice ID, and cost reduction, quality improvement, delivery date for achieving the target level. Store shortening items and effect costs.

<達成効果テーブル30の具体例>
図12は、達成効果テーブルの具体例を示す図である。図12に示す達成効果テーブル30では、項目として、「分類」、「項目」、「内訳」、「効果費用(千円)」等を有する。達成効果テーブル30は、目標水準に達成した場合の効果費用を設定するテーブルである。「分類」は、目標水準に達成による機会の効果、リスク回避効果に分類する。「項目」は、分類に対応して効果の項目を設定する。「内訳」は、例えば国毎の効果費用に相当する項目を設定し、効果費用に当該内訳の費用を設定する。
<Specific example of achievement effect table 30>
FIG. 12 is a diagram illustrating a specific example of the achievement effect table. The achievement effect table 30 shown in FIG. 12 includes “classification”, “item”, “breakdown”, “effective cost (thousand yen)”, and the like as items. The achievement effect table 30 is a table for setting the effect cost when the target level is achieved. “Category” is classified into the effect of opportunity and the risk avoidance effect by achieving the target level. “Item” sets an effect item corresponding to the classification. In the “Breakdown”, for example, an item corresponding to the effect cost for each country is set, and the cost of the breakdown is set as the effect cost.

なお、上述した図3〜図12に示すテーブル及びファイルの構成や内容等については、本発明においてはこの限りではなく、例えば複数のテーブルやファイルが組み合わせたテーブルやファイルを有していてもよい。   Note that the configurations and contents of the tables and files shown in FIGS. 3 to 12 described above are not limited in the present invention, and for example, a table or a file in which a plurality of tables or files are combined may be included. .

また、上述したテーブルやファイル等は、全て評価装置10の画面に表示可能なデータであり、ユーザ等は各種テーブルやファイル等が表示された画面を参照しながら、入力手段等を用いてデータの入力や変更、削除等の編集を行うことができる。   The above-described tables, files, etc. are all data that can be displayed on the screen of the evaluation apparatus 10, and the user, etc., uses the input means etc. while referring to the screen on which various tables, files, etc. are displayed. Editing such as input, change, and deletion can be performed.

<開発プロセス改善効果の評価処理手順>
次に、本実施形態における開発プロセス改善効果の評価処理手順の概要についてフローチャートを用いて説明する。図13は、開発プロセス改善効果の評価処理手順の一例を示すフローチャートである。
<Development process improvement effect evaluation procedure>
Next, the outline of the evaluation process procedure for the development process improvement effect in this embodiment will be described with reference to a flowchart. FIG. 13 is a flowchart illustrating an example of a procedure for evaluating the development process improvement effect.

図13の例では、まず開発プロセス改善計画の設定を行い(S01)、その後、目標達成追加の設定を行う(S02)。なお、本実施形態におけるS01及びS02の処理は、逆の順序で行ってもよく、また何れか一方の処理のみを行ってもよい。   In the example of FIG. 13, the development process improvement plan is first set (S01), and then the goal achievement addition is set (S02). Note that the processes of S01 and S02 in the present embodiment may be performed in the reverse order, or only one of the processes may be performed.

また、リスク見積の設定を行い(S03)、リスクからコストへの変換を行う(S04)。その後、S04の処理にて変換されたコストに基づく効果を計算し(S05)、計算されたコストに対する評価結果を評価装置10等が備えるディスプレイ等の画面又は外部装置等に出力する(S06)。   Also, a risk estimate is set (S03) and conversion from risk to cost is performed (S04). Thereafter, the effect based on the cost converted in the process of S04 is calculated (S05), and the evaluation result for the calculated cost is output to a screen such as a display provided in the evaluation device 10 or the like, an external device or the like (S06).

ここで、予め設定した開発プロセス改善効果の評価処理全体を終了するか否かを判断し(S07)、評価処理全体を終了しない場合(S07において、NO)、S01の処理に戻り、他の設定条件等に基づいて開発プロセス改善効果の評価処理を行う。また、S07の処理において、評価処理全体を終了する場合(S07においてYES)、本実施形態における評価処理を終了する。なお、S07の処理においては、例えば、ユーザからの強制終了指示等により評価処理を終了させることもできる。   Here, it is determined whether or not the entire evaluation process for the development process improvement effect set in advance is to be ended (S07). If the entire evaluation process is not to be ended (NO in S07), the process returns to S01 and other settings are made. Evaluate development process improvement effect based on conditions. Moreover, in the process of S07, when the whole evaluation process is complete | finished (in S07 YES), the evaluation process in this embodiment is complete | finished. In the process of S07, for example, the evaluation process can be terminated by a forced termination instruction or the like from the user.

上述した処理により、開発プロセス改善効果の評価精度を向上させることができる。また、プログラムをインストールすることにより、汎用のパーソナルコンピュータ等で本発明における評価処理を容易に実現することができる。次に、上述した評価処理の具体例について以下に説明する。   With the processing described above, the evaluation accuracy of the development process improvement effect can be improved. Further, by installing the program, the evaluation processing in the present invention can be easily realized by a general-purpose personal computer or the like. Next, a specific example of the above-described evaluation process will be described below.

<S01:開発プロセス改善計画設定処理手順>
まず、S01における開発プロセス改善計画設定処理手順について、フローチャートを用いて具体的に説明する。図14は、開発プロセス改善計画設定処理手順の一例を示すフローチャートである。図14の例では、開発プロセス改善計画設定処理として、まず予め設定されたギャップテーブル21を読み込み、開発プロセス改善計画入力画面を表示し、開発プロセス改善計画入力画面ファイルに格納する(S11)。なお、開発プロセス改善計画入力画面の表示フォーマットは、例えば上述した開発プロセス改善計画入力画面ファイル24と同様とする。
<S01: Development Process Improvement Plan Setting Procedure>
First, the development process improvement plan setting processing procedure in S01 will be specifically described with reference to a flowchart. FIG. 14 is a flowchart illustrating an example of a development process improvement plan setting process procedure. In the example of FIG. 14, as the development process improvement plan setting process, first, a preset gap table 21 is read, a development process improvement plan input screen is displayed, and stored in a development process improvement plan input screen file (S11). The display format of the development process improvement plan input screen is the same as that of the development process improvement plan input screen file 24 described above, for example.

次に、開発プロセス改善計画設定処理は、ユーザや外部等から入力された開発プロセス改善計画、開発プロセス改善計画費用見積等を読み込み、開発プロセス改善計画入力画面ファイルに格納する(S12)。   Next, in the development process improvement plan setting process, a development process improvement plan, a development process improvement plan cost estimate, etc. input from the user or the outside are read and stored in the development process improvement plan input screen file (S12).

次に、開発プロセス改善計画設定処理は、費用金額を計算し開発プロセス改善計画入力画面ファイルに格納する(S13)。この場合、工数は、プロジェクトテーブル22の工数単価により費用に変換する。例えば、プラクティスID1.1.3の費用の場合には、「0.1人日×4名+0.2人日=0.6人日」、「0.6人日×1000千円/20日=30千円」となる。   Next, in the development process improvement plan setting process, the cost amount is calculated and stored in the development process improvement plan input screen file (S13). In this case, the man-hour is converted into a cost by the man-hour unit price in the project table 22. For example, in the case of the expense of practice ID 1.1.3, “0.1 person day × 4 persons + 0.2 person day = 0.6 person day”, “0.6 person day × 1000 thousand yen / 20 days = 30 thousand yen ”.

次に、開発プロセス改善計画設定処理は、例えば上述した図3の全体構成で定義したプロジェクトプロセス領域について、例えば要員増強、ツール導入、トレーニング、手順テーラリング等の項目(所定の内訳項目)等について費用を集計して費用ファイル23のプロジェクトの当該項目に格納する(S14)。この場合、工数は、プロジェクトテーブル22の工数単価により費用に変換する。   Next, the development process improvement plan setting process, for example, for the project process area defined in the overall configuration of FIG. 3 described above, for example, items (predetermined breakdown items) such as personnel increase, tool introduction, training, procedure tailoring, etc. The costs are totaled and stored in the relevant item of the project in the cost file 23 (S14). In this case, the man-hour is converted into a cost by the man-hour unit price in the project table 22.

次に、開発プロセス改善計画設定処理は、例えば上述した図3に示す全体構成で定義した組織プロセス領域について、例えば組織標準手順書作成費用、要員増強、ツール導入、トレーニングの項目(所定の内訳項目)等について費用を集計して費用ファイル23の組織の当該項目に格納する(S15)。この場合、工数は、プロジェクトテーブル22の工数単価により費用に変換する。   Next, the development process improvement plan setting process, for example, for the organizational process area defined in the overall configuration shown in FIG. 3 described above, for example, organization standard procedure manual creation cost, personnel increase, tool introduction, training items (predetermined breakdown items) ) And the like are totalized and stored in the item of the organization of the cost file 23 (S15). In this case, the man-hour is converted into a cost by the man-hour unit price in the project table 22.

<S02:目標達成追加設定処理手順>
次に、S02における目標達成追加設定処理手順について、フローチャートを用いて説明する。図15は、目標達成追加設定処理手順の一例を示すフローチャートである。
<S02: Target achievement additional setting processing procedure>
Next, the target achievement additional setting processing procedure in S02 will be described using a flowchart. FIG. 15 is a flowchart illustrating an example of the target achievement additional setting processing procedure.

図15の例では、目標達成追加設定処理として、まず予め設定されたギャップテーブル21を読み込み、目標達成追加入力画面に表示し、目標達成追加入力画面ファイルに格納する(S21)。次に、目標達成追加設定処理は、開発プロセス改善計画入力画面ファイル24から開発プロセス改善計画を読み込み、目標達成追加入力画面に表示し、目標達成追加入力画面ファイル25に格納する(S22)。ここで、目標達成追加入力画面の表示フォーマットは、例えば上述した目標達成追加入力画面ファイル25と同様とする。   In the example of FIG. 15, as the goal achievement additional setting process, first, the preset gap table 21 is read, displayed on the goal achievement additional input screen, and stored in the goal achievement additional input screen file (S21). Next, in the goal achievement additional setting process, the development process improvement plan is read from the development process improvement plan input screen file 24, displayed on the goal achievement additional input screen, and stored in the goal achievement additional input screen file 25 (S22). Here, the display format of the goal achievement addition input screen is the same as that of the goal achievement addition input screen file 25 described above, for example.

次に、目標達成追加設定処理は、ユーザや外部等から入力された目標水準達成所要項目、目標水準達成費用見積を読み込み、目標達成追加入力画面ファイルに格納する(S23)。   Next, in the goal achievement additional setting process, the target level achievement required item and the goal level achievement cost estimate input from the user or the outside are read and stored in the goal achievement additional input screen file (S23).

次に、目標達成追加設定処理は、費用金額を計算し目標達成追加入力画面ファイルに格納する(S24)。この場合、工数は、プロジェクトテーブル22の工数単価により費用に変換する。例えば、プラクティスID1.1.3の費用の場合には、「3回×4人×2時間+3人日+0.2人日×4名+3人日=9.8人日」、「9.8人日×1000千円/20日=490千円」となる。   Next, in the goal achievement addition setting process, the cost amount is calculated and stored in the goal achievement addition input screen file (S24). In this case, the man-hour is converted into a cost by the man-hour unit price in the project table 22. For example, in the case of the expense of practice ID 1.1.3, “3 times × 4 people × 2 hours + 3 person days + 0.2 person days × 4 people + 3 person days = 9.8 person days”, “9.8 Person day × 1000 thousand yen / 20 days = 490 thousand yen ”.

次に、目標達成追加設定処理は、例えば上述した図3に示す全体構成で定義したプロジェクトプロセス領域について、例えば要員増強、ツール導入、トレーニング、手順テーラリング等の項目(所定の内訳項目)等について費用を集計して費用ファイル23のプロジェクトの当該項目に格納する(S25)。この場合、工数は、プロジェクトテーブル22の工数単価により費用に変換する。   Next, the goal achievement additional setting process is performed on the project process area defined in the overall configuration shown in FIG. 3 described above, for example, on items (predetermined breakdown items) such as personnel increase, tool introduction, training, procedure tailoring, etc. The costs are totaled and stored in the item of the project of the cost file 23 (S25). In this case, the man-hour is converted into a cost by the man-hour unit price in the project table 22.

次に、目標達成追加設定処理は、例えば上述した図3に示す全体構成で定義した組織プロセス領域について、例えば組織標準手順書作成費用、要員増強、ツール導入、トレーニング等の項目(所定の内訳項目)等について費用を集計して費用ファイル23の組織の当該項目に格納する(S26)。この場合、工数は、プロジェクトテーブル22の工数単価により費用に変換する。   Next, the goal achievement additional setting process is performed for the organizational process area defined in the overall configuration shown in FIG. 3 described above, for example, items such as organizational standard procedure manual creation cost, personnel increase, tool introduction, training, etc. (predetermined breakdown items) ) And the like are aggregated and stored in the item of the organization of the cost file 23 (S26). In this case, the man-hour is converted into a cost by the man-hour unit price in the project table 22.

次に、目標達成追加設定処理は、達成所要コストテーブル26のデータを読み込み、費用ファイルの目標水準達成費用の分類項目に対して、費用負担(プロジェクト、組織)で分類して内訳と費用を格納する(S27)。   Next, the goal achievement additional setting processing reads the data of the achievement required cost table 26, classifies the classification items of the target level achievement cost of the expense file by the cost burden (project, organization), and stores the breakdown and cost. (S27).

<S03:リスク見積設定処理手順>
次に、S03におけるリスク見積設定処理手順について、フローチャートを用いて説明する。図16は、リスク見積設定処理手順の一例を示すフローチャートである。図16の例では、リスク見積設定処理として、まず予め設定されたギャップテーブル21を読み込み、リスク見積入力画面に表示し、リスク見積入力画面ファイル27に格納する(S31)。また、リスク見積設定処理は、開発プロセス改善計画入力画面ファイル24から開発プロセス改善計画等の設定データを読み込み、リスク見積入力画面に表示し、リスク見積入力画面ファイル27に格納する(S32)。なお、リスク見積入力画面の表示フォーマットは、例えば上述したリスク見積入力画面ファイル27と同様とする。また、S32の処理では、例えば目標達成追加入力画面ファイル25から設定データを読み込み、リスク見積入力画面ファイル27に格納してもよい。
<S03: Risk Estimate Setting Processing Procedure>
Next, the risk estimate setting processing procedure in S03 will be described using a flowchart. FIG. 16 is a flowchart illustrating an example of a risk estimate setting process procedure. In the example of FIG. 16, as the risk estimate setting process, first, the preset gap table 21 is read, displayed on the risk estimate input screen, and stored in the risk estimate input screen file 27 (S31). In the risk estimate setting process, setting data such as a development process improvement plan is read from the development process improvement plan input screen file 24, displayed on the risk estimate input screen, and stored in the risk estimate input screen file 27 (S32). The display format of the risk estimate input screen is the same as that of the risk estimate input screen file 27 described above, for example. In the process of S32, for example, setting data may be read from the target achievement additional input screen file 25 and stored in the risk estimate input screen file 27.

次に、リスク見積設定処理は、リスクコスト変換テーブル28のリスク影響度テーブルやプロジェクトテーブル22等からプロジェクト工数とプロジェクト期間とを読み込み、例えばコスト人月と納期日数又は月数、品質コスト等を計算し、更にサブ画面として影響度を表示する(S33)。なお、サブ画面の表示フォーマットは、例えば上述した図9(b)に示すサブ画面の内容と同様とする。   Next, the risk estimation setting process reads the project man-hour and the project period from the risk impact table of the risk cost conversion table 28, the project table 22, and the like, and calculates, for example, the cost person month and the delivery date or number of months, the quality cost, etc. Further, the influence level is displayed as a sub-screen (S33). The display format of the sub screen is the same as the content of the sub screen shown in FIG. 9B described above, for example.

次に、リスク見積設定処理は、ユーザや外部等から入力された影響度、発生確率、リスク回避確率を読み込み、リスク見積入力画面ファイルに格納する(S34)。ここで、リスク回避確率は、例えば当該プラクティスの目標水準達成(ギャップをなくすこと)をリスク回避確率100%として、ギャップに対する開発プロセス改善の度合いにより設定する。   Next, in the risk estimate setting process, the influence degree, occurrence probability, and risk avoidance probability input from the user or the outside are read and stored in the risk estimate input screen file (S34). Here, the risk avoidance probability is set according to the degree of improvement of the development process with respect to the gap, for example, assuming that the target level of the practice (to eliminate the gap) is 100% risk avoidance probability.

<S04:リスクコスト変換処理手順>
次に、S04におけるリスクコスト変換処理手順について、フローチャートを用いて説明する。図17は、リスクコスト変換処理手順の一例を示すフローチャートである。
<S04: Risk cost conversion processing procedure>
Next, the risk cost conversion processing procedure in S04 will be described using a flowchart. FIG. 17 is a flowchart illustrating an example of the risk cost conversion processing procedure.

図17の例では、リスクコスト変換処理として、リスク見積入力処理画面ファイル24、リスクコスト変換テーブル28、プロジェクトテーブル22を読み込む(S41)。次に、リスクコスト変換処理は、影響度と発生確率からリスクコストを求める(S42)。   In the example of FIG. 17, the risk estimate input process screen file 24, the risk cost conversion table 28, and the project table 22 are read as the risk cost conversion process (S41). Next, the risk cost conversion process obtains a risk cost from the degree of influence and the occurrence probability (S42).

なお、リスクコストの例としては、例えばコストリスク、納期リスク、品質リスクのうち、少なくとも1つを用いるが、本発明においてはこれに限定されるものではない。コストリスクは、例えば「コストリスク=当該リスク影響度のコスト比率×発生確率×プロジェクト工数×工数単価」により算出することができる。具体的には、例えばコストリスクが影響度3、発生確率40%の場合には、「15%×40%×40人月×1000千円=2400千円」となる。   For example, at least one of cost risk, delivery date risk, and quality risk is used as the risk cost, but the present invention is not limited to this. The cost risk can be calculated by, for example, “cost risk = cost ratio of the risk impact degree × occurrence probability × project man-hour × man-hour unit price”. Specifically, for example, when the cost risk has an impact level of 3 and an occurrence probability of 40%, “15% × 40% × 40 person month × 1000 thousand yen = 2400 thousand yen”.

また、納期リスクは、例えば、「納期リスク=当該リスク影響度の期間比率×発生確率×月あたり売上増加×プロジェクト期間」により算出することができる。具体的には、例えば納期リスクが影響度3、発生確率40%の場合には、「7.5%×40%×4000千円×12か月=1440千円」となる。   The delivery date risk can be calculated by, for example, “Delivery date risk = period ratio of the risk impact degree × occurrence probability × sales increase per month × project period”. Specifically, for example, when the delivery date risk has an impact level of 3 and an occurrence probability of 40%, “7.5% × 40% × 4000 thousand yen × 12 months = 1440 thousand yen”.

更に、「品質リスク」は、例えば「品質リスク=当該リスク影響度の変換工数比率×発生確率×プロジェクト工数×工数単価」により算出することができる。具体的には、例えば品質リスクが影響度3、発生確率40%の場合には、「30%×40%×40人月×1000千円=4800千円」となる。   Furthermore, the “quality risk” can be calculated, for example, by “quality risk = conversion man-hour ratio of the risk impact degree × occurrence probability × project man-hour × man-hour unit price”. Specifically, for example, when the quality risk has an impact level of 3 and an occurrence probability of 40%, “30% × 40% × 40 person month × 1000 thousand yen = 4800 thousand yen”.

ここで、リスクコスト変換処理は、算出したコストリスクと納期リスクと品質リスクとのうち大きい方をリスクコストとする(S43)。なお、S43の処理では、例えばコストリスクと納期リスクと品質リスクとの平均をリスクコストとしてもよく、その他の手法によりリスクコストを算出してもよい。   Here, in the risk cost conversion process, the larger one of the calculated cost risk, delivery date risk and quality risk is set as the risk cost (S43). In the process of S43, for example, an average of cost risk, delivery date risk, and quality risk may be used as the risk cost, or the risk cost may be calculated by other methods.

次に、リスクコスト変換処理は、リスクコストに対する効果費用を計算し、効果ファイルの当該プラクティスに格納する(S44)。なお、S44の処理では、具体的には、「開発プロセス改善効果=リスクコスト×リスク回避確率」として効果費用を計算することができ、例えば、リスクコスト4800千円、リスク回避確率20%の場合には、「開発プロセス改善効果=4800千円×20%=960千円」となる。また、本実施形態では、「目標水準達成効果=リスクコスト×(1−リスク回避確率)」として求めることもできる。   Next, the risk cost conversion process calculates an effect cost for the risk cost and stores it in the practice of the effect file (S44). In the process of S44, specifically, the effect cost can be calculated as “development process improvement effect = risk cost × risk avoidance probability”. For example, when the risk cost is 4800 thousand yen and the risk avoidance probability is 20% Is “development process improvement effect = 4800 thousand yen × 20% = 960 thousand yen”. Further, in the present embodiment, it can also be obtained as “target level achievement effect = risk cost × (1−risk avoidance probability)”.

次に、リスクコスト変換処理は、全プラクティス完了について計算したか否かを判断し(S45)、全プラクティスの計算が完了していない場合(S45において、NO)、S42の処理に戻る。また、全プラクティスの計算が完了した場合(S45において、YES)、開発プロセス改善効果、目標水準達成効果について、例えば上述した図3に示す全体構成で定義したプロジェクトプロセス領域のプラクティスについて、例えばコスト・納期・品質毎に集計して効果ファイル29の該当項目に格納する(S46)。   Next, in the risk cost conversion process, it is determined whether or not all the practices have been calculated (S45). If all the practices have not been calculated (NO in S45), the process returns to S42. Further, when the calculation of all practices is completed (YES in S45), the development process improvement effect and the target level achievement effect, for example, the project process area practice defined in the overall configuration shown in FIG. The data is aggregated for each delivery date / quality and stored in the corresponding item of the effect file 29 (S46).

また、リスクコスト変換処理は、開発プロセス改善効果、目標水準達成効果について、例えば上述した図3に示す全体構成で定義した組織プロセス領域のプラクティスについて、例えばコスト・納期・品質毎に集計して効果ファイルの該当項目に格納する(S47)。   In addition, the risk cost conversion process is effective for the development process improvement effect and the target level achievement effect, for example, for the organization process area practice defined in the overall configuration shown in FIG. 3 described above, for example, for each cost, delivery date, and quality. Store in the corresponding item of the file (S47).

<S05:効果費用取得処理手順>
次に、S05における効果費用取得処理手順について、フローチャートを用いて説明する。図18は、効果費用取得処理手順の一例を示すフローチャートである。
<S05: Effective cost acquisition processing procedure>
Next, the effect cost acquisition processing procedure in S05 will be described using a flowchart. FIG. 18 is a flowchart illustrating an example of an effect cost acquisition processing procedure.

図18の例では、効果費用取得処理として、達成効果テーブル30から項目と効果費用を読み込む(S51)。次に、効果費用取得処理は、各項目について効果費用を合計し、効果ファイル29の目標水準達成効果の項目と効果費用に格納する(S52)。   In the example of FIG. 18, as the effect cost acquisition process, items and effect costs are read from the achievement effect table 30 (S51). Next, the effect cost acquisition process sums the effect costs for each item and stores them in the target level achievement effect item and effect cost of the effect file 29 (S52).

<S06:評価結果出力処理手順>
次に、S06における評価結果出力処理手順について、フローチャートを用いて説明する。図19は、評価結果出力処理手順の一例を示すフローチャートである。
<S06: Evaluation Result Output Processing Procedure>
Next, the evaluation result output processing procedure in S06 will be described using a flowchart. FIG. 19 is a flowchart illustrating an example of an evaluation result output processing procedure.

図19の例では、評価結果出力処理として、まず費用ファイル23を読み込み、各費用を集計する(S61)。具体的には、以下の処理を行う。なお、以下に示す処理A〜Lの記号は、後述する評価結果の全体評価の項目に付加した記号に対応している。
A=開発プロセス改善計画費用の費用負担がプロジェクトの費用を集計する。
B=開発プロセス改善計画費用の費用負担が組織の費用を集計する。
C=A+Bを計算する。
D=目標水準達成費用の費用負担がプロジェクトの費用を集計する。
E=目標水準達成費用の費用負担が組織の費用を集計する。
F=D+Eを計算する。
In the example of FIG. 19, as the evaluation result output process, first, the expense file 23 is read, and each expense is totaled (S 61). Specifically, the following processing is performed. In addition, the symbols of the processes A to L shown below correspond to symbols added to items of overall evaluation of evaluation results described later.
A = The cost of the development process improvement plan cost totals the cost of the project.
B = Development process improvement plan cost burden sums the cost of the organization.
C = A + B is calculated.
D = The cost of achieving the target level is the total cost of the project.
E = The cost of achieving the target level is the total cost of the organization.
Calculate F = D + E.

次に、評価結果出力処理は、効果ファイル29のプロジェクト効果を読み込み、各効果費用を集計する(S62)。具体的には、以下の処理を行う。
G=開発プロセス改善効果の効果費用を集計する。
H=目標水準達成効果の効果費用を集計する。
Next, in the evaluation result output process, the project effect of the effect file 29 is read and each effect cost is totaled (S62). Specifically, the following processing is performed.
G = Effective cost of development process improvement effect is tabulated.
H = Aggregate the cost of effect of achieving the target level.

次に、評価結果出力処理は、効果ファイル29の組織効果を読み込み、各効果費用を集計する(S63)。具体的には、以下の処理を行う。
I=開発プロセス改善効果の効果費用を集計する。
J=目標水準達成効果の効果費用を集計する。
K=G+Iを計算する。
L=H+Jを計算する。
Next, in the evaluation result output process, the organization effect of the effect file 29 is read, and each effect cost is totaled (S63). Specifically, the following processing is performed.
I = Aggregate the effective cost of the development process improvement effect.
J = Aggregate the cost of effect of achieving the target level.
K = G + I is calculated.
Calculate L = H + J.

次に、評価結果出力処理は、全体評価の開発プロセス改善計画、及び全体評価の目標水準達成を出力する(S64)。具体的には、評価結果出力処理は、全体評価の開発プロセス改善計画として上述したC,Kを出力する。また、評価結果出力処理は、投資利益率=K/C×100を計算して出力する。更に、評価結果出力処理は、全体評価の目標水準達成として上述したF,Lを出力する。また、評価結果出力処理は、投資利益率=L/F×100を計算して出力する。   Next, the evaluation result output process outputs a development process improvement plan for overall evaluation and achievement of the target level for overall evaluation (S64). Specifically, the evaluation result output process outputs C and K described above as a development process improvement plan for overall evaluation. The evaluation result output process calculates and outputs the return on investment = K / C × 100. Further, the evaluation result output process outputs F and L described above as achievement of the target level of the overall evaluation. In the evaluation result output process, the return on investment = L / F × 100 is calculated and output.

次に、評価結果出力処理は、組織費用対効果の開発プロセス改善計画、及び組織費用対効果の目標水準達成を出力する(S65)。具体的には、評価結果出力処理は、組織費用対効果の開発プロセス改善計画として上述したB,Iを出力する。また、評価結果出力処理は、投資利益率=I/B×100を計算して出力する。更に、評価結果出力処理は、組織費用対効果の目標水準達成として上述したE,Jを出力する。また、評価結果出力処理は、投資利益率=J/E×100を計算して出力する。   Next, the evaluation result output process outputs an organization cost effectiveness development process improvement plan and an organization cost effectiveness target level achievement (S65). Specifically, the evaluation result output process outputs B and I described above as the development process improvement plan for the organization cost effectiveness. The evaluation result output process calculates and outputs the return on investment = I / B × 100. Further, the evaluation result output process outputs E and J described above as achievement of the target level of the organizational cost effectiveness. The evaluation result output process calculates and outputs the return on investment = J / E × 100.

次に、評価結果出力処理は、プロジェクト費用対効果の開発プロセス改善計画、及びプロジェクト費用対効果の目標水準達成を出力する(S66)。具体的には、評価結果出力処理は、プロジェクト費用対効果の開発プロセス改善計画として上述したA,Gを出力する。また、評価結果出力処理は、投資利益率=G/A×100を計算して出力する。更に、評価結果出力処理は、プロジェクト費用対効果の目標水準達成として上述したD,Hを出力する。また、評価結果出力処理は、投資利益率=H/D×100を計算して出力する。   Next, the evaluation result output process outputs a development process improvement plan for project cost effectiveness and achievement of the target level for project cost effectiveness (S66). Specifically, the evaluation result output process outputs A and G described above as a development process improvement plan for project cost effectiveness. In the evaluation result output process, the return on investment = G / A × 100 is calculated and output. Further, the evaluation result output process outputs D and H described above as achievement of the target level of project cost effectiveness. In the evaluation result output process, the return on investment = H / D × 100 is calculated and output.

次に、評価結果出力処理は、開発プロセス改善評価内訳を出力する(S67)。開発プロセス改善評価内訳の例としては、例えば、評価結果出力処理は、費用ファイル23での開発プロセス改善計画費用の分類の費用負担、内訳、費用を読み込み、出力する。また、評価結果出力処理は、効果ファイル29でのプロジェクト効果の開発プロセス改善効果の項目と効果費用を読み込み、出力する。また、評価結果出力処理は、効果ファイル29での組織効果の開発プロセス改善効果の項目と効果費用を読み込み、出力する。また、評価結果出力処理は、開発プロセス改善入力画面ファイル24からプラクティスID,プラクティス名称、開発プロセス改善計画、費用を読み込み、出力する。また、評価結果出力処理は、効果ファイル29のプラクティス単位効果から開発プロセス改善効果を読み込み、出力する。   Next, the evaluation result output process outputs a development process improvement evaluation breakdown (S67). As an example of the development process improvement evaluation breakdown, for example, the evaluation result output processing reads and outputs the cost burden, breakdown, and expense of the classification of the development process improvement plan cost in the cost file 23. Also, the evaluation result output process reads and outputs the project effect development process improvement effect item and effect cost in the effect file 29. The evaluation result output process reads and outputs the item of the effect of improving the development process of the organization effect and the effect cost in the effect file 29. In the evaluation result output process, the practice ID, practice name, development process improvement plan, and cost are read from the development process improvement input screen file 24 and output. In the evaluation result output process, the development process improvement effect is read from the practice unit effect of the effect file 29 and output.

次に、評価結果出力処理は、目標水準達成評価内訳を出力する(S68)。目標水準達成評価内訳の例としては、例えば、評価結果出力処理は、費用ファイル23での目標水準達成費用の分類の費用負担、内訳、費用を読み込み、出力する。また、評価結果出力処理は、効果ファイル29でのプロジェクト効果の目標水準達成効果の項目と効果費用を読み込み、出力する。また、評価結果出力処理は、効果ファイル29での組織効果の目標水準達成効果の項目と効果費用を読み込み、出力する。また、評価結果出力処理は、目標水準達成追加入力画面ファイル25からプラクティスID,プラクティス名称、目標水準達成所要項目、費用を読み込み、出力する。また、評価結果出力処理は、効果ファイル29のプラクティス単位効果から目標水準達成効果を読み込み、出力する。なお、上述した評価処理は、例えばCPU等による制御により実行される。   Next, the evaluation result output process outputs a target level achievement evaluation breakdown (S68). As an example of the target level achievement evaluation breakdown, for example, the evaluation result output processing reads and outputs the cost burden, breakdown, and cost of the classification of the target level achievement cost in the cost file 23. Also, the evaluation result output process reads and outputs the item of effect level achievement effect and effect cost of the project effect in the effect file 29. Further, the evaluation result output process reads and outputs the item of effect of achieving the target level of the organizational effect and the effect cost in the effect file 29. The evaluation result output process reads and outputs the practice ID, practice name, target level achievement required item, and cost from the target level achievement additional input screen file 25. The evaluation result output process reads and outputs the target level achievement effect from the practice unit effect of the effect file 29. Note that the above-described evaluation process is executed by control by a CPU or the like, for example.

<評価結果31について>
次に、本実施形態において評価結果出力手段16から出力される評価結果31の一例について、図を用いて説明する、図20〜22は、本実施形態における評価結果の一例を示す図(その1〜3)である。
<About evaluation result 31>
Next, an example of the evaluation result 31 output from the evaluation result output unit 16 in the present embodiment will be described with reference to the drawings. FIGS. 20 to 22 are diagrams illustrating an example of the evaluation result in the present embodiment (part 1). ~ 3).

図20の例では、「全体評価」、「組織費用対効果」、及び「プロジェクト費用対効果」の評価結果が表示されている。なお、図20に示すA〜Lは、上述した処理A〜Lの各数式の結果が出力される。つまり、図20で出力されている内容は、主に上述した図19のS66の処理で得られた内容が図20に示す全体評価のフォーマットとして出力される。なお、本実施形態では、1つの全体評価に対し、複数の組織やプロジェクトが存在する場合のあるため、図20に示す例も1つの組織やプロジェクトだけでなく、複数の組織毎や複数のプロジェクト毎に評価結果を出力することができる。   In the example of FIG. 20, evaluation results of “overall evaluation”, “organization cost effectiveness”, and “project cost effectiveness” are displayed. Note that A to L shown in FIG. 20 output the results of the mathematical expressions of the above-described processes A to L. That is, the content output in FIG. 20 is mainly the content obtained by the processing of S66 of FIG. 19 described above as the overall evaluation format shown in FIG. In this embodiment, since there may be a plurality of organizations and projects for one overall evaluation, the example shown in FIG. 20 is not limited to a single organization or project, but for a plurality of organizations or a plurality of projects. The evaluation result can be output every time.

これにより、本実施形態では、全体評価、組織毎、プロジェクト毎に費用対効果による評価を行うことができ、開発プロセス改善効果の評価精度を向上させることができる。   Thereby, in this embodiment, evaluation by cost effectiveness can be performed for every evaluation, every organization, and every project, and the evaluation accuracy of the development process improvement effect can be improved.

また、図21では、開発プロセス改善評価の内訳を示している。ここで、図21で出力されている内容は、主に上述した図19のS67の処理で得られた内容が、開発プロセス改善評価内訳のフォーマットとして出力される。更に、図22では、目標水準達成評価の内訳を示している。ここで、図22で出力されている内容は、主に上述した図19のS68の処理で得られた内容が、目標水準達成評価内訳のフォーマットとして出力される。なお、図20〜22に示す評価結果のレイアウトについては、これに限定されるものではなく、ユーザ等による設定により任意に変更することができる。   FIG. 21 shows a breakdown of development process improvement evaluation. Here, the content output in FIG. 21 is mainly the content obtained in the process of S67 of FIG. 19 described above as the format of the development process improvement evaluation breakdown. Further, FIG. 22 shows a breakdown of the target level achievement evaluation. Here, the content output in FIG. 22 is mainly the content obtained by the processing of S68 in FIG. 19 described above as the format of the target level achievement evaluation breakdown. The layout of the evaluation results shown in FIGS. 20 to 22 is not limited to this, and can be arbitrarily changed by setting by the user or the like.

上述したように、本実施形態では、リスクの大きさだけでなく、開発プロセス改善の費用対効果をコストとして定量的に得ることができる。また、本実施形態では、費用換算にあたり、例えば認証取得等の外部から認証される目標水準に達成した場合と、それ以外の開発プロセス改善の場合についての両方に対応させて評価することができる。なお、本実施形態において、費用対効果の算定では、発生費用と効果費用とを算定する。また、効果費用は、開発プロセス改善によるリスク回避を費用に変換し、また認証取得等の外部から認証されることによる費用効果を算定する。   As described above, in the present embodiment, not only the magnitude of risk but also the cost-effectiveness of development process improvement can be obtained quantitatively as cost. In the present embodiment, for cost conversion, for example, evaluation can be performed in correspondence with both a case where a target level authenticated from outside such as acquisition of certification is achieved and a case of other development process improvement. In the present embodiment, in the cost-effectiveness calculation, the generated cost and the effective cost are calculated. Effective cost is calculated by converting the risk avoidance due to the improvement of development process into cost, and calculating the cost effect by external certification such as acquisition of certification.

また、本実施形態によれば、組織部門費用とプロジェクト費用で費用を分担して算出することができる。なお、複数の組織やプロジェクトがあった場合には、その組織単位やプロジェクト単位で評価結果を出力することができる。   Further, according to the present embodiment, it is possible to calculate by dividing the cost by the organizational department cost and the project cost. When there are a plurality of organizations or projects, the evaluation results can be output in units of the organizations or projects.

つまり、本実施形態によれば、費用・品質・納期リスク回避を費用換算して評価することができる。また、認証取得の場合は、目標水準達成による効果を追加して評価することができる。   That is, according to the present embodiment, cost, quality, and delivery date risk avoidance can be evaluated in terms of cost. In the case of certification acquisition, the effect of achieving the target level can be added and evaluated.

なお、上述の実施形態での目標水準は、例えばCMMIレベル3で要求される標準開発プロセスを詳細化した項目(以降プラクティスと呼ぶ)と、当該プラクティスの達成水準とを示している。しかしながら、本発明においては、上述した実施形態に示すようにCMMIを用いずに、予め設定された他の基準(例えば、国際標準等)に基づいて上述した評価方式を適用することができる。   The target level in the above-described embodiment indicates, for example, an item (hereinafter referred to as practice) that details the standard development process required in CMMI level 3, and the achievement level of the practice. However, in the present invention, the evaluation method described above can be applied based on other preset criteria (for example, international standards) without using CMMI as shown in the above-described embodiments.

例えば、上述した例では、CMMIに適用させて、開発プロセスを「プロセス領域」として定義し、各プロセス領域について「ゴール」を設定し、更に「ゴール」を詳細化した「プラクティス」を用いたが、例えばISO12207に適用させて、各プロセスに「アクティビティ」を設定し、更に「アクティビティ」を詳細化した「タスク」を用いて開発プロセス改善効果の評価を行ってもよい。   For example, in the example described above, the development process is defined as a “process area”, applied to CMMI, a “goal” is set for each process area, and a “practice” that further refines the “goal” is used. For example, by applying to ISO 12207, an “activity” may be set for each process, and a “task” that further refines the “activity” may be used to evaluate the development process improvement effect.

また、本実施形態を適用する場合には、例えば予め設定した評価区分や、予め設定した当該評価区分の目標水準の例としては、ISO15504に規定された「Information technology − Process assessment」の場合には、予め設定した評価区分として、Base Practice(基本プラクティス)を用い、予め設定した当該評価区分の目標水準として、Capability Level(能力水準)を用いることができる。   Further, when applying this embodiment, for example, in the case of “Information technology-Process assessment” defined in ISO 15504 as an example of a preset evaluation category or a target level of the preset evaluation category, In addition, Base Practice (basic practice) can be used as the preset evaluation category, and Capability Level (capability level) can be used as the target level of the preset evaluation category.

また、本実施形態を適用する場合には、例えば、ISO_IEC_29110に規定された「Software engineering− Lifecycle profiles for Very Small Entities (VSEs)」の場合には、予め設定した評価区分として、Task(タスク)を用い、予め設定した当該評価区分の目標水準として、Level(水準)を用いることができる。   When this embodiment is applied, for example, in the case of “Software engineering- Lifecycle profiles for Very Small Entities (VSEs)” defined in ISO_IEC — 29110, Task (task) is set as a preset evaluation category. It is possible to use Level as a target level of the evaluation category set in advance.

更に、本実施形態を適用する場合には、例えばIEC61508に規定された「Functional safety of electrical/electric/programmable electronic safety−related systems」の場合には、予め設定した評価区分として、Measure(方策)を用い、予め設定した当該評価区分の目標水準として、Safety Integrity Level(安全度水準)を用いることができる。なお、本実施形態に適用できる基準についてはこれに限定されるものではない。   Furthermore, when this embodiment is applied, for example, in the case of “Functional safety of electrical / electrical / programmable electronic safety-related systems” defined in IEC61508, a measurement method (measure) is used as a pre-set evaluation category. The Safety Integrity Level (safety level) can be used as the target level of the evaluation category set in advance. Note that the criteria applicable to the present embodiment are not limited to this.

上述したように本発明によれば、開発プロセス改善効果の評価精度を向上させることができる。具体的には、本発明では、開発リスク等による開発プロセス改善効果の評価について、開発プロセス改善の費用対効果を定量化して提示することで、開発プロセス改善計画の効果の説明や開発プロセス改善計画の見直しを容易化することで、最適な開発プロセス改善を計画し実施することができる。   As described above, according to the present invention, the evaluation accuracy of the development process improvement effect can be improved. Specifically, the present invention quantifies and presents the cost effectiveness of the development process improvement for the evaluation of the development process improvement effect due to the development risk, etc., thereby explaining the effect of the development process improvement plan and the development process improvement plan. This makes it possible to plan and implement optimal development process improvements.

また、本発明によれば、目標とする水準に達成するために更に必要とする費用対効果の評価を可能とすることで、適切な計画の見直しや中長期計画の立案も可能となる。また、リスクによる効果の評価をすることで、例えばあるプラクティスについて、改善をするしないではなく、改善の深さの度合いに対応した精密な評価をすることができる。   In addition, according to the present invention, it is possible to evaluate a cost-effectiveness further required to achieve a target level, thereby making it possible to review an appropriate plan and to make a medium- to long-term plan. In addition, by evaluating the effect of risk, for example, it is possible to perform a precise evaluation corresponding to the degree of improvement, rather than improving a certain practice.

なお、本発明は、例えば開発前の予算編成時等に、今までの実績値や予想値等を入力して開発プロセス改善効果の評価を行ってもよく、また開発プロセス実行中に、例えば所定の期間毎にその時点での実績値や予想値等を入力し、その時点での開発プロセス改善効果の評価を行ってもよい。   In the present invention, for example, at the time of budget preparation before development, etc., it is possible to evaluate the development process improvement effect by inputting actual values and predicted values so far, and during execution of the development process, for example, a predetermined value may be used. The actual value or the predicted value at that time may be input for each period of time, and the development process improvement effect at that time may be evaluated.

また、本発明は、例えばパワーエレクトロニクス製品等の分野だけでなく、その他の開発製品全般の製品開発プロセス技術等に幅広く適用することができる。   Further, the present invention can be widely applied not only to the field of, for example, power electronics products but also to product development process technologies for other developed products in general.

以上本発明の好ましい実施例について詳述したが、本発明は係る特定の実施形態に限定されるものではなく、特許請求の範囲に記載された本発明の要旨の範囲内において、種々の変形、変更が可能である。   The preferred embodiments of the present invention have been described in detail above, but the present invention is not limited to such specific embodiments, and various modifications, within the scope of the gist of the present invention described in the claims, It can be changed.

10 評価装置
11 開発プロセス改善計画設定手段
12 目標達成追加設定手段
13 リスク見積設定手段
14 リスクコスト変換手段
15 効果費用取得手段
16 評価結果出力手段
21 ギャップテーブル
22 プロジェクトテーブル
23 費用ファイル
24 開発プロセス改善計画入力画面ファイル
25 目標達成追加入力画面ファイル
26 達成所要コストテーブル
27 リスク見積入力画面ファイル
28 リスクコスト変換テーブル
29 効果ファイル
30 達成効果テーブル
31 評価結果
41 入力装置
42 出力装置
43 ドライブ装置
44 補助記憶装置
45 メモリ装置
46 CPU(Central Processing Unit)
47 ネットワーク接続装置
48 記録媒体
DESCRIPTION OF SYMBOLS 10 Evaluation apparatus 11 Development process improvement plan setting means 12 Target achievement addition setting means 13 Risk estimation setting means 14 Risk cost conversion means 15 Effective cost acquisition means 16 Evaluation result output means 21 Gap table 22 Project table 23 Cost file 24 Development process improvement plan Input screen file 25 Target achievement additional input screen file 26 Achievement required cost table 27 Risk estimate input screen file 28 Risk cost conversion table 29 Effect file 30 Achievement effect table 31 Evaluation result 41 Input device 42 Output device 43 Drive device 44 Auxiliary storage device 45 Memory device 46 CPU (Central Processing Unit)
47 Network connection device 48 Recording medium

Claims (15)

開発リスクによる開発プロセスの改善効果の評価を行う評価装置において、
開発を行う組織毎又はプロジェクト毎の開発プロセスに対する改善計画を設定する開発プロセス改善計画設定手段と、
前記開発プロセス改善計画設定手段により設定された改善計画データと、予め設定された費用データ及びリスクデータとに基づいてリスクを見積もりするリスク見積設定手段と、
前記リスク見積設定手段により得られるリスクデータを、コストリスク、品質リスク、及び納期リスクのうち、少なくとも1つのリスクをコストに変換するリスクコスト変換手段と、
前記リスクコスト変換手段により得られるコストに基づいて、前記開発プロセスの改善効果に対応する費用対効果を取得する効果費用取得手段と、
前記効果費用取得手段により得られる計算結果に基づく評価結果を出力する評価結果出力手段とを有することを特徴とする評価装置。
In the evaluation device that evaluates the improvement effect of development process due to development risk,
Development process improvement plan setting means for setting an improvement plan for the development process for each organization or project for development,
A risk estimation setting means for estimating a risk based on the improvement plan data set by the development process improvement plan setting means, and preset cost data and risk data;
Risk cost conversion means for converting risk data obtained by the risk estimate setting means into at least one risk out of cost risk, quality risk, and delivery date risk; and
Based on the cost obtained by the risk cost conversion means, an effect cost acquisition means for acquiring cost effectiveness corresponding to the improvement effect of the development process;
An evaluation apparatus comprising: an evaluation result output means for outputting an evaluation result based on a calculation result obtained by the effect cost acquisition means.
予め設定される達成目標水準まで上げるために必要な追加データを設定する目標達成追加設定手段を有することを特徴とする請求項1に記載の評価装置。   2. The evaluation apparatus according to claim 1, further comprising target achievement additional setting means for setting additional data necessary for raising to a preset achievement target level. 前記評価結果出力手段は、
前記開発プロセス改善の費用対効果を評価する際に、
費用については、前記開発プロセス改善計画設定手段で設定した改善に要する費用、及び、予め設定された認証取得に発生する費用のうち、少なくとも1つの費用で評価し、
効果については、前記開発プロセス改善の結果により回避されるリスクを定量化して費用に変換して得られる費用、及び、予め設定した認証取得による効果を費用に変換して得られる費用のうち、少なくとも1つの費用で定量化することを特徴とする請求項1又は2に記載の評価装置。
The evaluation result output means includes
In evaluating the cost effectiveness of the development process improvement,
The cost is evaluated with at least one cost out of the cost required for improvement set by the development process improvement plan setting means and the cost incurred for acquiring the preset certification,
Regarding the effect, at least of the cost obtained by quantifying the risk to be avoided by the result of the improvement of the development process and converting it into the cost, and the cost obtained by converting the effect of obtaining the preset certification into the cost. 3. The evaluation apparatus according to claim 1, wherein the quantification is performed at a single cost.
前記効果費用取得手段は、
前記費用対効果の費用を算出する際に、予め設定された各プラクティスに対して、所定の内訳項目毎に費用を算出し、前記プロジェクト毎の費用と、前記組織毎の費用とで集計することを特徴とする請求項1乃至3の何れか1項に記載の評価装置。
The effective cost acquisition means is:
When calculating the cost-effectiveness cost, for each preset practice, calculate the cost for each predetermined breakdown item, and aggregate the cost for each project and the cost for each organization. The evaluation apparatus according to claim 1, wherein:
前記効果費用取得手段は、
前記費用対効果の効果費用を算出する際に、予め設定された各プラクティスに対して、予め設定されたプラクティスの達成水準と、現状とのギャップによるリスク回避を効果費用に変換し、前記改善計画による効果費用を、前記リスク回避費用と、各プラクティスに設定したリスク回避確率とから算定し、前記プロジェクト毎の費用と、前記組織毎の費用とで集計することを特徴とする請求項1乃至4の何れか1項に記載の評価装置。
The effective cost acquisition means is:
When calculating the effective cost of the cost-effectiveness, for each preset practice, the risk avoidance due to the gap between the achievement level of the preset practice and the current situation is converted into the effective cost, and the improvement plan 5. The effect cost according to claim 1 is calculated from the risk avoidance cost and the risk avoidance probability set in each practice, and is totaled by the cost for each project and the cost for each organization. The evaluation apparatus according to any one of the above.
前記評価結果出力手段は、
前記開発プロセス改善の費用対効果を評価する際に、実績費用又は実績効果を含めて評価することを特徴とする請求項1乃至5の何れか1項に記載の評価装置。
The evaluation result output means includes
The evaluation apparatus according to any one of claims 1 to 5, wherein when evaluating the cost-effectiveness of the development process improvement, evaluation is performed including actual costs or actual results.
前記評価結果出力手段は、
予め設定された評価区分と、前記評価区分に対して予め設定された目標水準とを用いて評価することを特徴とする請求項1乃至6の何れか1項に記載の評価装置。
The evaluation result output means includes
7. The evaluation apparatus according to claim 1, wherein the evaluation is performed by using a preset evaluation category and a target level preset for the evaluation category.
開発リスクによる開発プロセスの改善効果の評価を行う評価方法において、
開発を行う組織毎又はプロジェクト毎の開発プロセスに対する改善計画を設定する開発プロセス改善計画設定ステップと、
前記開発プロセス改善計画設定ステップにより設定された改善計画データと、予め設定された費用データ及びリスクデータとに基づいてリスクを見積もりするリスク見積設定ステップと、
前記リスク見積設定ステップにより得られるリスクデータを、コストリスク、品質リスク、及び納期リスクのうち、少なくとも1つのリスクをコストに変換するリスクコスト変換ステップと、
前記リスクコスト変換ステップにより得られるコストに基づいて、前記開発プロセスの改善効果に対応する費用対効果を取得する効果費用取得ステップと、
前記効果費用取得ステップにより得られる計算結果に基づく評価結果を出力する評価結果出力ステップとを有することを特徴とする評価方法。
In the evaluation method to evaluate the improvement effect of development process due to development risk,
A development process improvement plan setting step for setting an improvement plan for a development process for each organization or project for development;
A risk estimation setting step for estimating a risk based on the improvement plan data set by the development process improvement plan setting step, and expense data and risk data set in advance;
A risk cost conversion step of converting at least one risk out of cost risk, quality risk, and delivery date risk into risk data obtained by the risk estimate setting step;
An effect cost acquisition step for acquiring a cost-effectiveness corresponding to the improvement effect of the development process based on the cost obtained by the risk cost conversion step;
An evaluation result output step of outputting an evaluation result based on the calculation result obtained by the effect cost acquisition step.
予め設定される達成目標水準まで上げるために必要な追加データを設定する目標達成追加設定ステップを有することを特徴とする請求項8に記載の評価方法。   9. The evaluation method according to claim 8, further comprising a target achievement additional setting step for setting additional data necessary for raising to a preset target level. 前記評価結果出力ステップは、
前記開発プロセス改善の費用対効果を評価する際に、
費用については、前記開発プロセス改善計画設定ステップで設定した改善に要する費用、及び、予め設定された認証取得に発生する費用のうち、少なくとも1つの費用で評価し、
効果については、前記開発プロセス改善の結果により回避されるリスクを定量化して費用に変換して得られる費用、及び、予め設定した認証取得による効果を費用に変換して得られる費用のうち、少なくとも1つの費用で定量化することを特徴とする請求項8又は9に記載の評価方法。
The evaluation result output step includes:
In evaluating the cost effectiveness of the development process improvement,
The cost is evaluated with at least one cost out of the cost required for improvement set in the development process improvement plan setting step and the cost incurred for obtaining the preset certification,
Regarding the effect, at least of the cost obtained by quantifying the risk to be avoided by the result of the improvement of the development process and converting it into the cost, and the cost obtained by converting the effect of obtaining the preset certification into the cost. 10. The evaluation method according to claim 8, wherein the quantification is performed at one cost.
前記効果費用取得ステップは、
前記費用対効果の費用を算出する際に、予め設定された各プラクティスに対して、所定の内訳項目毎に費用を算出し、前記プロジェクト毎の費用と、前記組織毎の費用とで集計することを特徴とする請求項8乃至10の何れか1項に記載の評価方法。
The effective cost acquisition step includes:
When calculating the cost-effectiveness cost, for each preset practice, calculate the cost for each predetermined breakdown item, and aggregate the cost for each project and the cost for each organization. The evaluation method according to any one of claims 8 to 10, wherein:
前記効果費用取得ステップは、
前記費用対効果の効果費用を算出する際に、予め設定された各プラクティスに対して、予め設定されたプラクティスの達成水準と、現状とのギャップによるリスク回避を効果費用に変換し、前記改善計画による効果費用を、前記リスク回避費用と、各プラクティスに設定したリスク回避確率とから算定し、前記プロジェクト毎の費用と、前記組織毎の費用とで集計することを特徴とする請求項8乃至11の何れか1項に記載の評価方法。
The effective cost acquisition step includes:
When calculating the effective cost of the cost-effectiveness, for each preset practice, the risk avoidance due to the gap between the achievement level of the preset practice and the current situation is converted into the effective cost, and the improvement plan 12. The effect cost according to claim 8 is calculated from the risk avoidance cost and the risk avoidance probability set for each practice, and totaled by the cost for each project and the cost for each organization. The evaluation method according to any one of the above.
前記評価結果出力ステップは、
前記開発プロセス改善の費用対効果を評価する際に、実績費用又は実績効果を含めて評価することを特徴とする請求項8乃至12の何れか1項に記載の評価方法。
The evaluation result output step includes:
The evaluation method according to any one of claims 8 to 12, wherein when evaluating the cost-effectiveness of the development process improvement, evaluation is performed including actual costs or actual results.
前記評価結果出力ステップは、
予め設定された評価区分と、前記評価区分に対して予め設定された目標水準とを用いて評価することを特徴とする請求項8乃至13の何れか1項に記載の評価方法。
The evaluation result output step includes:
14. The evaluation method according to claim 8, wherein the evaluation is performed using a preset evaluation category and a target level preset for the evaluation category.
コンピュータを、
請求項1乃至7の何れか1項に記載の評価装置が有する各手段として機能させるための評価プログラム。
Computer
The evaluation program for functioning as each means which the evaluation apparatus of any one of Claims 1 thru | or 7 has.
JP2011202422A 2011-09-15 2011-09-15 Development process improvement effect evaluation device, evaluation method, and evaluation program Withdrawn JP2013065105A (en)

Priority Applications (1)

Application Number Priority Date Filing Date Title
JP2011202422A JP2013065105A (en) 2011-09-15 2011-09-15 Development process improvement effect evaluation device, evaluation method, and evaluation program

Applications Claiming Priority (1)

Application Number Priority Date Filing Date Title
JP2011202422A JP2013065105A (en) 2011-09-15 2011-09-15 Development process improvement effect evaluation device, evaluation method, and evaluation program

Publications (1)

Publication Number Publication Date
JP2013065105A true JP2013065105A (en) 2013-04-11

Family

ID=48188566

Family Applications (1)

Application Number Title Priority Date Filing Date
JP2011202422A Withdrawn JP2013065105A (en) 2011-09-15 2011-09-15 Development process improvement effect evaluation device, evaluation method, and evaluation program

Country Status (1)

Country Link
JP (1) JP2013065105A (en)

Cited By (2)

* Cited by examiner, † Cited by third party
Publication number Priority date Publication date Assignee Title
WO2021182531A1 (en) * 2020-03-10 2021-09-16 株式会社マネジメントソリューションズ Project management system
US11915179B2 (en) * 2019-02-14 2024-02-27 Talisai Inc. Artificial intelligence accountability platform and extensions

Cited By (2)

* Cited by examiner, † Cited by third party
Publication number Priority date Publication date Assignee Title
US11915179B2 (en) * 2019-02-14 2024-02-27 Talisai Inc. Artificial intelligence accountability platform and extensions
WO2021182531A1 (en) * 2020-03-10 2021-09-16 株式会社マネジメントソリューションズ Project management system

Similar Documents

Publication Publication Date Title
JP6723946B2 (en) Business improvement support device and business improvement support method
Burch V et al. Global corporation rollout of ruggedised handheld devices: A Lean Six Sigma case study
Whittlestone et al. Why and how governments should monitor AI development
Alanazi The mediating role of primary TQM factors and strategy in the relationship between supportive TQM factors and organisational results: An empirical assessment using the MBNQA model
Freitas et al. Towards a maturity model for learning analytics adoption an overview of its levels and areas
Martini Anacondebt: A tool to assess and track technical debt
WO2005013089A2 (en) Process and method for lifecycle digital maturity assessment
US9886168B2 (en) Method and system for scenario-driven standard-compliant user interface design and development for effort estimation
Wiratama et al. Developing a Class Scheduling Mobile Application for Private Campus in Tangerang with the Extreme Programming (XP) Model
JP6395852B2 (en) Business situation management system and business situation management method
JP2013065105A (en) Development process improvement effect evaluation device, evaluation method, and evaluation program
Yang et al. Theoretical development of stochastic delay analysis and forecast method
Jethani Software metrics for effective project management
JP2014095952A (en) Computer mounting method, program, and system for obtaining calculation formula for calculating kpi related to business process
CN106295155A (en) Senile inpatients medical health assessment system and method
JP4572126B2 (en) Audit processing program, apparatus and method
JP6087459B1 (en) Sales analysis apparatus, sales analysis method, and sales analysis program
JP2010009153A (en) Design support system, design support device, design support program and recording medium recording same program
JP6290716B2 (en) Environmental impact assessment system and method
Vermeulen et al. Business processes capability and performance: A South African perspective
KR101698422B1 (en) Apparatus and Method for design of process map by the IWOD
JP4077420B2 (en) Knowledge utilization effect simulation device, knowledge utilization effect simulation method, and program for calculating simulation of knowledge utilization effect
JP6653604B2 (en) Information processing apparatus and information processing program
JP6879316B2 (en) Information processing equipment, graph display method and program
WO2023112203A1 (en) Information processing device, information processing method, and program

Legal Events

Date Code Title Description
A300 Application deemed to be withdrawn because no request for examination was validly filed

Free format text: JAPANESE INTERMEDIATE CODE: A300

Effective date: 20141202