JP2012218093A - Robot system - Google Patents

Robot system Download PDF

Info

Publication number
JP2012218093A
JP2012218093A JP2011084447A JP2011084447A JP2012218093A JP 2012218093 A JP2012218093 A JP 2012218093A JP 2011084447 A JP2011084447 A JP 2011084447A JP 2011084447 A JP2011084447 A JP 2011084447A JP 2012218093 A JP2012218093 A JP 2012218093A
Authority
JP
Japan
Prior art keywords
work
robot
job
unit
controller
Prior art date
Legal status (The legal status is an assumption and is not a legal conclusion. Google has not performed a legal analysis and makes no representation as to the accuracy of the status listed.)
Withdrawn
Application number
JP2011084447A
Other languages
Japanese (ja)
Inventor
Hirohisa Ota
裕久 太田
Current Assignee (The listed assignees may be inaccurate. Google has not performed a legal analysis and makes no representation or warranty as to the accuracy of the list.)
Canon Inc
Original Assignee
Canon Inc
Priority date (The priority date is an assumption and is not a legal conclusion. Google has not performed a legal analysis and makes no representation as to the accuracy of the date listed.)
Filing date
Publication date
Application filed by Canon Inc filed Critical Canon Inc
Priority to JP2011084447A priority Critical patent/JP2012218093A/en
Publication of JP2012218093A publication Critical patent/JP2012218093A/en
Withdrawn legal-status Critical Current

Links

Images

Classifications

    • YGENERAL TAGGING OF NEW TECHNOLOGICAL DEVELOPMENTS; GENERAL TAGGING OF CROSS-SECTIONAL TECHNOLOGIES SPANNING OVER SEVERAL SECTIONS OF THE IPC; TECHNICAL SUBJECTS COVERED BY FORMER USPC CROSS-REFERENCE ART COLLECTIONS [XRACs] AND DIGESTS
    • Y02TECHNOLOGIES OR APPLICATIONS FOR MITIGATION OR ADAPTATION AGAINST CLIMATE CHANGE
    • Y02PCLIMATE CHANGE MITIGATION TECHNOLOGIES IN THE PRODUCTION OR PROCESSING OF GOODS
    • Y02P90/00Enabling technologies with a potential contribution to greenhouse gas [GHG] emissions mitigation
    • Y02P90/02Total factory control, e.g. smart factories, flexible manufacturing systems [FMS] or integrated manufacturing systems [IMS]

Abstract

PROBLEM TO BE SOLVED: To provide a robot system that distributes a series of work into a plurality of work robots, and improves productivity without causing other robots to wait even if a delay occurs in any of work sections for some work robots.SOLUTION: The robot system assigns n work sections to robot controllers 4a-4d provided at arm robots 6a-6d respectively. M work sections less than n sections are assigned to a robot controller 4e provided at an arm robot 6e. When a delay occurs in a work of a work section at any arm robot 6, reassignment is executed, to assign a work section that has not been executed again to a robot controller of an arm robot located downstream of the arm robot in delay. N work sections, at a maximum, can be assigned again to the robot controllers in the reassignment.

Description

本発明は、一連の作業を複数の作業ロボットにより作業分割して実行するセル生産において、一部の作業ロボットで作業遅延が発生したとき、各作業ロボットを停止することなく、遅延を解消するためのロボットシステムに関する。   The present invention eliminates a delay without stopping each work robot when a work delay occurs in some work robots in cell production in which a series of work is divided and executed by a plurality of work robots. Related to robot systems.

組立て作業現場では従来の一貫したベルトコンベア生産方式に代わって、分散したセル生産方式が導入され着実な成果を挙げている。さらに無人化、つまりセル生産工程を複数台のロボット群による代替も行なわれている。複数の作業ロボットによるセル生産で重要となるのが作業ロボット間の同期制御である。一連の組立て作業工程を分割し、複数の作業ロボットに割付けて一つのワークを効率よく組立てるには、各作業ロボットでの作業を遂行するサイクルタイムが揃っている必要がある。もし、一部の作業ロボットにおいて、割付けられた作業工程に遅延が発生すると隣接する作業ロボットに待ち時間が発生してしまい、最終的には組立てライン全体の生産性に支障をきたす。   At the assembly work site, instead of the conventional consistent belt conveyor production method, a distributed cell production method has been introduced, and steady results have been achieved. Furthermore, unmanned operation, that is, the cell production process is replaced by a group of multiple robots. Synchronous control between work robots is important in cell production by a plurality of work robots. In order to efficiently assemble a single workpiece by dividing a series of assembly work steps and assigning them to a plurality of work robots, it is necessary to have a cycle time for performing the work of each work robot. If a delay occurs in the assigned work process in some work robots, a waiting time is generated in the adjacent work robot, and finally the productivity of the entire assembly line is hindered.

図12は、従来のロボットシステムにおいて遅延が生じた場合を示すタイムチャートであり、ここでは、5台の作業ロボット(R1〜R5)により組立工程を実現しているロボットシステムを表している。   FIG. 12 is a time chart showing a case where a delay occurs in the conventional robot system, and here, shows a robot system in which an assembly process is realized by five work robots (R1 to R5).

横軸にサイクルタイム、縦軸は各作業ロボットを表し、サイクルタイムの進行とともに各作業ロボットの作業対象とするワークWの遷移がわかる。例えば、サイクルタイムT1でワークW4は作業ロボットR2により組立てられ、次のサイクルタイムT2で同じワークW4は作業ロボットR3に渡され、次の組立てが行われる。サイクルタイムT4で作業ロボットR5の組立てによりワークW4の組立工程が完了する。   The horizontal axis represents the cycle time, and the vertical axis represents each work robot. As the cycle time progresses, the transition of the work W to be worked on by each work robot can be seen. For example, the workpiece W4 is assembled by the work robot R2 at the cycle time T1, and the same workpiece W4 is transferred to the work robot R3 at the next cycle time T2, and the next assembly is performed. The assembly process of the work W4 is completed by assembling the work robot R5 at the cycle time T4.

これに対し、ワークW5の組立て作業では、サイクルタイムT2において作業ロボットR2で遅延が生じている。このとき、作業ロボットR2は組立てているワークW5を所定のサイクルタイム内で割当てられた組立工程が完了しない。そのため、次のサイクルタイムT3では、作業ロボットR2の上流に位置する作業ロボットR1は、作業ロボットR1に割当てられたワークW6の組立工程が完了しているが、すぐにワークW6を作業ロボットR2に渡せない。従って、次のワークW7の組立てを開始するまで遅延時間D1が発生してしまう。   On the other hand, in the assembly work of the workpiece W5, the work robot R2 has a delay at the cycle time T2. At this time, the work robot R2 does not complete the assembly process in which the work W5 being assembled is allocated within a predetermined cycle time. Therefore, at the next cycle time T3, the work robot R1 located upstream of the work robot R2 has completed the assembly process of the work W6 assigned to the work robot R1, but immediately the work W6 is changed to the work robot R2. I can't pass it. Therefore, the delay time D1 occurs until the assembly of the next workpiece W7 is started.

また、同じサイクルタイムT3で、作業ロボットR2の下流に位置する作業ロボットR3も作業ロボットR3に割当てられたワークW4の組立工程が完了している。しかし、すぐにワークW5を作業ロボットR2から受け取れず、ワークW5の組立てを開始するまでに遅延時間D2が発生してしまう。   In addition, at the same cycle time T3, the assembly process of the work W4 assigned to the work robot R3 is completed for the work robot R3 located downstream of the work robot R2. However, the workpiece W5 cannot be immediately received from the work robot R2, and a delay time D2 occurs until the assembly of the workpiece W5 is started.

この後、サイクルタイムT4で作業ロボットR4に遅延時間D3が波及し、サイクルタイムT5で作業ロボットR5に遅延時間D4が波及する。そして、ワークW5以降すべてのワークの組立て完了時刻は、計画よりも時間が遅延時間D5の分遅くなってしまう。従って、一度途中で発生した遅延が解消することなく蓄積されてしまうことがわかる。   Thereafter, the delay time D3 is spread to the work robot R4 at the cycle time T4, and the delay time D4 is spread to the work robot R5 at the cycle time T5. Then, the assembly completion time of all the workpieces after the workpiece W5 is delayed by the delay time D5 from the plan. Therefore, it can be seen that the delay that has occurred once is accumulated without being eliminated.

このような他の作業ロボットへの作業遅延の影響を軽減するために、作業ロボット間にストッカーを設けた装置が開示されている(特許文献1参照)。具体的には、各作業ロボット間にストッカーを配置し、隣接する下流側の作業ロボットで遅延が生じた際は下流ロボットとの間に設けられたストッカーに組立て作業の終了したワークを移載し、次のワーク組立てに移る。逆に上流側の作業ロボットで遅延が生じた際は上流ロボットとの間に設けられたストッカーから次のワークを移載してワークの組立て作業を続行することで作業ロボットの待ち時間を解消している。   In order to reduce the influence of such work delay on other work robots, an apparatus in which a stocker is provided between work robots is disclosed (see Patent Document 1). Specifically, a stocker is placed between each work robot, and when a delay occurs between adjacent work robots, the work that has been assembled is transferred to a stocker provided between the work robots. Then, move on to the next workpiece assembly. Conversely, when a delay occurs in the upstream work robot, the work robot wait time is eliminated by transferring the next workpiece from the stocker provided between the upstream robot and continuing the work assembly work. ing.

特開平11−198074号公報JP-A-11-198074

しかし、各作業ロボット間にストッカーを設けることで隣接した作業ロボットが即時停止して待ち動作に移ることはなくなるが、ストッカーにワークが存在すること自体、それ以前に一部の作業ロボット間で遅延が生じていることを表している。この遅延をさらに他のロボットに波及することは阻止できるものの、発生した遅延を解消することはできない。また、ストッカーを設けることでコスト増加、スペースの確保という問題もあった。   However, by providing a stocker between each work robot, adjacent work robots will not stop immediately and move to a waiting operation, but there will be a delay between some work robots before the work exists in the stocker itself. Indicates that this has occurred. Although this delay can be prevented from spreading to other robots, the generated delay cannot be eliminated. In addition, there is a problem that the provision of a stocker increases costs and secures a space.

そこで、本発明は、一部の作業ロボットに発生したワークの作業の遅延が、別のワークの作業に波及するのを防止して、複数の作業ロボットによる生産性を向上させるロボットシステムを提供することを目的とする。   Therefore, the present invention provides a robot system that prevents a work delay caused by some work robots from spreading to another work and improves the productivity of a plurality of work robots. For the purpose.

本発明は、ワークを順次搬送するワーク搬送方向に並べて配置され、ワークに施す一連の作業を分担して行う複数の作業ロボットと、前記複数の作業ロボットのそれぞれに設けられたロボットコントローラと、前記複数のロボットコントローラに接続されたメインコントローラと、を備えたロボットシステムにおいて、前記メインコントローラは、前記一連の作業を分割して得られる複数の作業区分を記憶する記憶部と、前記記憶部に記憶された複数の作業区分を、前記複数のロボットコントローラのうち、ワーク搬送方向の最下流に位置する作業ロボット以外の作業ロボットに設けられたロボットコントローラにはn(≧2の正の整数)個、ワーク搬送方向の最下流に位置する作業ロボットに設けられたロボットコントローラにはm(<nの正の整数)個、作業順に割り振る割り振り処理を実行する割振部と、ワークをワーク搬送方向下流に搬送するタイミングを示す同期信号を、前記各ロボットコントローラに一定の時間間隔で送出する同期制御部と、を有し、前記各ロボットコントローラは、前記同期制御部により送出された前記同期信号のタイミングで作業ロボットにワークをワーク搬送方向下流に搬送させ、ワーク搬送方向上流から搬送されたワークに対して、割り振られた作業区分の作業を作業ロボットに実行させる処理部と、作業ロボットにおける作業区分の作業に遅延が発生した際に前記時間間隔の範囲内で作業が完了しないと予測される未実施の作業区分の情報を、前記メインコントローラに通知する通知部と、を有し、前記メインコントローラは、前記通知部により前記情報が通知された際に、前記複数のロボットコントローラのうち、作業区分の作業に遅延が発生した作業ロボットよりもワーク搬送方向下流に位置する作業ロボットに設けられたロボットコントローラに、未実施である作業区分を、n個を上限として作業順に割り振りし直す再割り振り処理を実行する再割振部を有することを特徴とする。   The present invention is arranged side by side in the workpiece transfer direction for sequentially transferring workpieces, a plurality of work robots that share a series of work performed on the workpiece, a robot controller provided in each of the plurality of work robots, In a robot system comprising a main controller connected to a plurality of robot controllers, the main controller stores a plurality of work sections obtained by dividing the series of work, and stores in the storage unit The plurality of work divisions are divided into n (≧ 2 positive integers) robot controllers provided in work robots other than the work robots located at the most downstream in the workpiece transfer direction among the plurality of robot controllers. The robot controller provided in the work robot located on the most downstream side in the workpiece transfer direction has m (<n A positive integer), an allocating unit that executes an allocation process that is allocated in the order of work, and a synchronization control unit that sends a synchronization signal indicating the timing of conveying the workpiece downstream in the workpiece conveyance direction to each robot controller at a certain time interval; And each robot controller causes the work robot to transfer the work downstream in the work transfer direction at the timing of the synchronization signal sent by the synchronization control unit, and to the work transferred from the work transfer direction upstream A processing unit for causing the work robot to execute the work of the assigned work category, and an operation that is predicted not to be completed within the time interval when a delay occurs in the work category of the work robot. A notification unit for notifying the main controller of information on work divisions, and the main controller includes the notification unit. When the above information is notified, the robot controller provided in the work robot located downstream in the work transfer direction from the work robot in which the work in the work category is delayed among the plurality of robot controllers is not implemented. It is characterized by having a reallocation part which performs the reallocation process which reallocates the work classification which is these in order of work by making n into an upper limit.

本発明によれば、あるワークに対して一連の作業を施しているときに、ある作業ロボットにおいて作業区分の作業に遅延が発生しても、未実施の作業区分の作業を下流の作業ロボットが行うので、各作業ロボットは一定の時間間隔内で作業を終えることができる。これにより、ある作業ロボットにおける一部の作業区分の作業による遅延の影響が、別のワークに対する作業ロボットの作業に波及するのを防止することができ、複数の作業ロボットによる生産性が向上する。   According to the present invention, when a series of work is performed on a work, even if a work work is delayed in a work robot, the work robot in the downstream work group does not perform the work in the work work in progress. As a result, each work robot can finish the work within a certain time interval. As a result, it is possible to prevent the influence of the delay due to the work of a part of the work division in a certain work robot from spreading to the work of the work robot with respect to another work, thereby improving the productivity of the plurality of work robots.

本発明の第1実施形態に係るロボットシステムの概略構成を示すブロック図である。1 is a block diagram showing a schematic configuration of a robot system according to a first embodiment of the present invention. 図1に示したロボットシステムの制御装置を示す制御ブロック図である。It is a control block diagram which shows the control apparatus of the robot system shown in FIG. 一連の作業を分割して得られる複数の作業区分を示す説明図である。It is explanatory drawing which shows the some work division obtained by dividing a series of work. 担当Jobの割り付けを示す概略説明図であり、(a)は遅延発生前、(b)は遅延発生後を示している。It is a schematic explanatory drawing showing the assignment of the responsible job, (a) before the occurrence of the delay, (b) shows after the occurrence of the delay. 各アームロボットによる作業の流れを示すタイムチャートである。It is a time chart which shows the flow of work by each arm robot. 本発明の第2実施形態に係るロボットシステム1Aの概略構成を示すブロック図である。It is a block diagram which shows schematic structure of the robot system 1A which concerns on 2nd Embodiment of this invention. 図6に示したロボットシステムの制御装置を示す制御ブロック図である。It is a control block diagram which shows the control apparatus of the robot system shown in FIG. 担当Jobの割り付けを示す概略説明図であり、(a)は遅延発生前、(b)は遅延発生後を示している。It is a schematic explanatory drawing showing the assignment of the responsible job, (a) before the occurrence of the delay, (b) shows after the occurrence of the delay. 各アームロボットによる作業の流れを示すタイムチャートである。It is a time chart which shows the flow of work by each arm robot. 本発明の第3実施形態に係るロボットシステム1Aの概略構成を示すブロック図である。It is a block diagram which shows schematic structure of the robot system 1A which concerns on 3rd Embodiment of this invention. 担当Jobの割り付けを示す概略説明図であり、(a)はアームロボットが作業不能となるエラー発生前、(b)はエラー発生後を示している。4A and 4B are schematic explanatory diagrams showing assignment of a job in charge, where FIG. 5A shows before an error that causes the arm robot to become inoperable, and FIG. 従来のロボットシステムにおいて遅延が生じた場合の各作業ロボットによる作業の流れを示すタイムチャートである。It is a time chart which shows the flow of work by each work robot when delay arises in the conventional robot system.

以下、本発明を実施するための形態を、図面を参照しながら詳細に説明する。   Hereinafter, embodiments for carrying out the present invention will be described in detail with reference to the drawings.

[第1実施形態]
図1は、本発明の第1実施形態に係るロボットシステムの概略構成を示すブロック図である。ロボットシステム1は、複数台のロボットステーション3を備えて構成される。図1では、5台のロボットステーション3(3a〜3e)で構成されているが、5台に限定されるものではない。
[First Embodiment]
FIG. 1 is a block diagram showing a schematic configuration of the robot system according to the first embodiment of the present invention. The robot system 1 includes a plurality of robot stations 3. In FIG. 1, the robot station 3 is composed of five robot stations 3 (3a to 3e), but is not limited to five.

各ロボットステーション3は、作業ロボットであるアームロボット6(6a〜6e)と、アームロボット6に接続され、アームロボット6を制御するロボットコントローラ4(4a〜4e)と、を有している。これら複数のロボットコントローラ4a〜4eには、通信ライン11を介して1つのメインコントローラであるセルコントローラ2がネットワーク接続されている。アームロボット6は、多関節マニピュレータであり、ワークWを把持して搬送したり、ワークW(W1〜W5)に加工や組み付けなどの作業を施したりすることができる。   Each robot station 3 includes an arm robot 6 (6a to 6e) which is a work robot, and a robot controller 4 (4a to 4e) which is connected to the arm robot 6 and controls the arm robot 6. A cell controller 2, which is one main controller, is connected to the plurality of robot controllers 4a to 4e via a communication line 11. The arm robot 6 is an articulated manipulator, and can grip and transport the workpiece W, and can perform operations such as processing and assembly on the workpiece W (W1 to W5).

また、各ロボットステーション3は、アームロボット6が固定され、ワークWの組み立て作業を行うための作業台5(5a〜5e)と、ワーク固定部7(7a〜7e)と、組付け部材設置部8(8a〜8e)とを有している。ワーク固定部7は、搬送されてきたワークWを固定する。組付け部材設置部8には、ワークWに組付ける部材が設置されている。ワーク固定部7及び組付け部材設置部8は、作業台5上に設けられている。   Each robot station 3 has a work table 5 (5a to 5e) for assembling the workpiece W, a workpiece fixing unit 7 (7a to 7e), and an assembly member installation unit to which the arm robot 6 is fixed. 8 (8a to 8e). The workpiece fixing unit 7 fixes the workpiece W that has been conveyed. A member to be assembled to the workpiece W is installed in the assembly member installation unit 8. The workpiece fixing unit 7 and the assembly member installation unit 8 are provided on the work table 5.

なお、本第1実施形態では、各ロボットステーション3はアームロボット6を1本のみ有しているが、これに限定されるものでなく、作業ロボットとして、2本すなわち双腕のアームロボットを有していてもよい。その際、ロボットコントローラ4は双腕の同期制御機能を有する。   In the first embodiment, each robot station 3 has only one arm robot 6. However, the present invention is not limited to this, and two robot arms, that is, two-arm arm robots are provided as work robots. You may do it. At that time, the robot controller 4 has a dual-arm synchronous control function.

本第1実施形態では、ロボットステーション3a〜3eが一列に並んで配置されており、各アームロボット6がワークWを把持して隣のロボットステーション3の作業台5に搬送可能に構成されている。なお、ロボットステーション3aにおけるワークWのワーク搬送方向上流には、ワーク搬入台9が配置され、ロボットステーション3eにおけるワークWのワーク搬送方向下流には、ワーク搬出台10が配置されている。これにより、ワーク搬入台9から搬入されたワークWは、ロボットステーション3a→3b→3c→3d→3eの順に順次搬送されて順番にワークWが組立てられ、ワーク搬出台10に搬出される。このように、複数のアームロボット6a〜6eにより、ワークWに施す一連の作業が分担して行われる。   In the first embodiment, the robot stations 3 a to 3 e are arranged in a line, and each arm robot 6 is configured to be able to grip the workpiece W and transfer it to the work table 5 of the adjacent robot station 3. . A work loading table 9 is disposed upstream of the workpiece W in the robot station 3a in the workpiece conveyance direction, and a workpiece loading table 10 is disposed downstream of the workpiece W in the robot station 3e in the workpiece conveyance direction. As a result, the workpieces W loaded from the workpiece loading table 9 are sequentially conveyed in the order of the robot stations 3a → 3b → 3c → 3d → 3e, the workpieces W are assembled in order, and are conveyed to the workpiece unloading table 10. In this way, a series of operations performed on the workpiece W are performed in a shared manner by the plurality of arm robots 6a to 6e.

ワーク搬入台9へはワーク搬入手段(不図示)もしくは作業員により組立て前のワークWが設置される。ワーク搬出台10は、複数のロボットステーション3a〜3eで組立てが完了したワークWを渡すための台である。組立て完了したワークWは、ロボットステーション3eのアームロボット6eがワーク搬出台10に置き、ワーク搬出手段(不図示)もしくは作業員により取り出される。   The workpiece W before assembly is set on the workpiece loading table 9 by a workpiece loading means (not shown) or a worker. The workpiece carry-out table 10 is a table for delivering the workpiece W that has been assembled by the plurality of robot stations 3a to 3e. The assembled workpiece W is placed on the workpiece carrying table 10 by the arm robot 6e of the robot station 3e and taken out by a workpiece carrying means (not shown) or a worker.

図2は、図1に示したロボットシステム1の制御装置を示す制御ブロック図である。図3は、一連の作業を分割して得られる複数の作業区分を示す説明図である。図2に示すセルコントローラ2は、ロボットステーション3a〜3eを同期して制御するためのものである。まず、図3に示すように、組立て作業を完成するまでの一連の作業(以下、「全Job」と称す)40を、時系列的に複数のより細かな作業区分(以下、「単一Job」と称す)41a〜41nに分割しておく。そして、セルコントローラ2は、いくつかの単一Jobをまとめて各ロボットコントローラ4のアームロボット6が実行する作業区分群(以下、「担当Job」と称す)42(42a〜42e)としてロボットコントローラ4(4a〜4e)に出力する。なお、各単一Job41は、想定されるアームロボット6による作業時間(遅延がないとした場合を想定した計画上の作業時間)が略同一となるように分割されている。ここで、図3では、作業区分である単一Job41a〜41nをJob[A]〜Job[N]で表しており、以下、作業区分を単一Job41(41a〜41n)又はJob[A]〜Job[N]として、適宜使い分けて説明する。   FIG. 2 is a control block diagram showing a control device of the robot system 1 shown in FIG. FIG. 3 is an explanatory diagram showing a plurality of work sections obtained by dividing a series of work. The cell controller 2 shown in FIG. 2 is for controlling the robot stations 3a to 3e in synchronization. First, as shown in FIG. 3, a series of operations (hereinafter referred to as “all jobs”) 40 until the assembly operation is completed is divided into a plurality of more detailed operation categories (hereinafter referred to as “single job”). It is divided into 41a to 41n. Then, the cell controller 2 collects several single jobs as a work classification group (hereinafter referred to as “in-charge job”) 42 (42a to 42e) executed by the arm robot 6 of each robot controller 4. (4a to 4e). Each single job 41 is divided so that the assumed work time of the arm robot 6 (planned work time assuming no delay) is substantially the same. Here, in FIG. 3, single jobs 41a to 41n, which are work divisions, are represented by Job [A] to Job [N]. Hereinafter, the work divisions are represented by single Job 41 (41a to 41n) or Job [A] to Job [N] will be described as appropriate.

図2に示す各ロボットコントローラ4は、セルコントローラ2からの担当Job42の受信やアームロボット6の作業状況およびエラー情報等の送信を行う。各ロボットコントローラ4は、それぞれ担当Job42の作業をアームロボット6に行わせ、セルコントローラ2の指令により、同一タイミングで、前工程のロボットステーション3のアームロボット6からワークWを受け取り、次のワークWの組立て作業を開始する。この際、ロボットステーション3aはワーク搬入台9よりワークを取り受け、ロボットステーション3eは、担当Jobの1工程として組立ての完了したワークをワーク搬出台10に排出する。   Each robot controller 4 shown in FIG. 2 receives the responsible job 42 from the cell controller 2 and transmits the work status and error information of the arm robot 6. Each robot controller 4 causes the arm robot 6 to perform the work of the assigned job 42, receives the workpiece W from the arm robot 6 of the robot station 3 in the previous process and receives the next workpiece W at the same timing according to the command of the cell controller 2. Start assembly work. At this time, the robot station 3a receives the workpiece from the workpiece carry-in table 9, and the robot station 3e discharges the assembled workpiece to the workpiece carry-out table 10 as one process of the job in charge.

まず、セルコントローラ2の構成について説明する。セルコントローラ2は、記憶部としての単一Jobデータベース部20と、ロボットステーションモニタ部21と、作業進行管理部としてのJob進行管理部22と、を有している。また、セルコントローラ2は、割振部としての担当Job割振部23と、再割振部としての担当Job再割振部24と、同期制御部25と、を有している。   First, the configuration of the cell controller 2 will be described. The cell controller 2 includes a single job database unit 20 as a storage unit, a robot station monitor unit 21, and a job progress management unit 22 as a work progress management unit. Further, the cell controller 2 includes a responsible job allocating unit 23 as an allocating unit, a responsible job reallocating unit 24 as a reallocating unit, and a synchronization control unit 25.

単一Jobデータベース部20には、全Job40を構成する複数の単一Job41a〜41nのデータが記憶されている。単一Job41のデータは、実行コマンドであってもよいが、単一Jobに関する情報、例えば標準工数時間、必要工具など、各ロボットコントローラ4へ担当Job42を割り振るのに必要な情報であればよい。   In the single job database unit 20, data of a plurality of single jobs 41a to 41n constituting all the jobs 40 is stored. The data of the single job 41 may be an execution command, but may be information necessary for allocating the job 42 to each robot controller 4 such as information related to the single job, for example, standard man-hour time and necessary tools.

ロボットステーションモニタ部21は、各ロボットステーション3のエラー発生などの状態を管理する。Job進行管理部22は、各ロボットステーション3のアームロボット6の作業状況を管理する。   The robot station monitor unit 21 manages the status of each robot station 3 such as an error occurrence. The job progress management unit 22 manages the work status of the arm robot 6 of each robot station 3.

担当Job割振部23は、各ロボットステーション3のロボットコントローラ4へ担当Job42を割り振る割り振り処理を実行する。具体的に説明すると、担当Job割振部23は、単一Jobデータベース部20から複数の単一Job41a〜41nのデータを読み出す。そして、担当Job割振部23は、いくつかの単一Job41を作業順にまとめた各担当Job42a〜42eのデータを各ロボットコントローラ4a〜4eに出力する。これにより、各ロボットコントローラ4には、担当Job42が割り振られる。   The assigned job allocating unit 23 executes an allocation process for assigning assigned job 42 to the robot controller 4 of each robot station 3. More specifically, the assigned job allocating unit 23 reads data of a plurality of single jobs 41 a to 41 n from the single job database unit 20. Then, the assigned job allocating unit 23 outputs data of each assigned job 42a to 42e in which several single jobs 41 are grouped in the work order to each robot controller 4a to 4e. As a result, the assigned job 42 is assigned to each robot controller 4.

具体的には、担当Job割振部23は、ワーク搬送方向の最下流に位置するアームロボット6e以外のアームロボット6a〜6dに設けられたロボットコントローラ4a〜4dにはn(≧2の正の整数)個の単一Job41を割り振る。本第1実施形態では、n=3、つまり3個の単一Job41で担当Job42a〜42dが構成される。なお、ワーク搬送方向の最下流に位置する作業ロボット以外の作業ロボットに接続されたロボットコントローラ4a〜4dに割り振る単一Job41の個数は、3個に限らず、2個以上であればよい。   Specifically, the assigned job allocating unit 23 sends n (≧ 2 positive integer) to the robot controllers 4a to 4d provided in the arm robots 6a to 6d other than the arm robot 6e located on the most downstream side in the workpiece transfer direction. ) Allocate a single job 41. In the first embodiment, n = 3, that is, three single jobs 41 constitute the responsible jobs 42a to 42d. Note that the number of the single job 41 allocated to the robot controllers 4a to 4d connected to the work robots other than the work robot located on the most downstream side in the workpiece transfer direction is not limited to three, and may be two or more.

これに対し、担当Job割振部23は、ワーク搬送方向の最下流に位置するアームロボット6eに設けられたロボットコントローラ4eにはm(<nの正の整数)個の単一Job41を割り振る。本第1実施形態では、mはnよりも小さい値であるので、m=2、つまりn個の2/3である2個の単一Job41で担当Job42eが構成される。なお、ロボットコントローラ4eに割り振る単一Job41の数は、n個の2/3に限定されるものではなく、n個よりも少ないm個であれば任意に設定できる。   On the other hand, the assigned job allocating unit 23 allocates m (<n positive integer) single jobs 41 to the robot controller 4e provided in the arm robot 6e located on the most downstream side in the workpiece transfer direction. In the first embodiment, m is a value smaller than n, and therefore m = 2, that is, two single jobs 41 that are 2/3 of n, the responsible job 42e is configured. Note that the number of the single job 41 allocated to the robot controller 4e is not limited to 2/3 of n, and can be arbitrarily set as long as m is smaller than n.

担当Job再割振部24は、ロボットステーションモニタ部21の情報及びJob進行管理部22の情報を基に、1サイクルタイムを実行するごとに見直しを行う。そして、担当Job再割振部24は、あるワークWに対する単一Job41の作業に遅延が生じた場合には、単一Job41(再構築した担当Job)の再割り振り処理を実行する。   The assigned job reallocation unit 24 performs a review each time one cycle time is executed based on information from the robot station monitor unit 21 and information from the job progress management unit 22. Then, when there is a delay in the work of the single job 41 for a certain work W, the assigned job reallocation unit 24 executes the reallocation processing of the single job 41 (reconstructed assigned job).

同期制御部25は、稼動中の各ロボットコントローラ4へ同一の時間間隔で一斉に作業を切替えるように制御する。具体的には同期制御部25は、ワークWをワーク搬送方向下流(図1の左方向)のアームロボット6へ引き渡すために、ワークWを搬送するタイミングを示す同期信号を、各ロボットコントローラ4に一定の時間間隔(サイクルタイム)で送出する。この時、各ロボットコントローラ4に指示した各担当Job42が必ずしも完遂していない状態でも作業の切替えを指令する、つまり同期信号を送出することが、本実施形態の大きな特徴である。   The synchronization control unit 25 controls the robot controllers 4 that are in operation to be switched simultaneously at the same time interval. Specifically, the synchronization control unit 25 sends a synchronization signal indicating the timing of conveying the workpiece W to each robot controller 4 in order to deliver the workpiece W to the arm robot 6 downstream in the workpiece conveyance direction (left direction in FIG. 1). Sends out at regular time intervals (cycle time). At this time, a major feature of the present embodiment is that it instructs the switching of work even if each job 42 instructed to each robot controller 4 is not necessarily completed, that is, sends a synchronization signal.

ここで、1サイクルタイム内に計画上収まる単一Job41の数がn個である。したがって、各担当Job42a〜42dがn個の単一Job41、担当Job42eがm個の単一Job41で構成されるように、サイクルタイム、つまり、同期信号を出力する時間間隔が設定されている。   Here, the number of the single job 41 that fits in plan within one cycle time is n. Therefore, the cycle time, that is, the time interval for outputting the synchronization signal is set so that each of the responsible jobs 42a to 42d is composed of n single jobs 41 and the responsible job 42e is composed of m single jobs 41.

次に、各ロボットコントローラ4の構成について説明する。各ロボットコントローラ4は、実行コマンドを記憶するコマンド記憶部26(26a〜26e)と、処理部としての担当Job処理部27(27a〜27e)と、モータ駆動部28(28a〜28e)と、センサ検出部29(29a〜29e)と、を有している。また、各ロボットコントローラ4は、ステーション状態管理部30(30a〜30e)と、通知部としてのJob進行通知部31(31a〜31e)と、を有している。   Next, the configuration of each robot controller 4 will be described. Each robot controller 4 includes a command storage unit 26 (26a to 26e) for storing execution commands, a responsible job processing unit 27 (27a to 27e) as a processing unit, a motor drive unit 28 (28a to 28e), a sensor And a detection unit 29 (29a to 29e). Each robot controller 4 includes a station state management unit 30 (30a to 30e) and a job progress notification unit 31 (31a to 31e) as a notification unit.

図4は、担当Job42の割り付けを示す概略説明図であり、図4(a)は遅延発生前、図4(b)は遅延発生後を示している。図2に示すロボットコントローラ4について図4(a)を参照しながら説明すると、各ロボットコントローラ4a〜4eには、担当Job42a〜42eが割り振られる。各ロボットコントローラ4a〜4eには、実行可能Job43a〜43eが設定されている。実行可能Job43a〜43eは、複数の単一Job41の集合である作業区分群であり、各担当Job処理部27a〜27eは、実行可能Job43a〜43eの範囲内で担当Job42の各単一Job41を実行可能に構成されている。   FIGS. 4A and 4B are schematic explanatory diagrams showing the assignment of the responsible job 42. FIG. 4A shows a state before the occurrence of delay, and FIG. 4B shows a state after the occurrence of delay. The robot controller 4 shown in FIG. 2 will be described with reference to FIG. 4A. The assigned robots 42a to 42e are assigned to the robot controllers 4a to 4e. Executable Jobs 43a to 43e are set in the robot controllers 4a to 4e. Executable Jobs 43a to 43e are work division groups that are a set of a plurality of single Jobs 41, and each responsible job processing unit 27a to 27e executes each single Job 41 of the responsible Job 42 within the range of the executable Jobs 43a to 43e. It is configured to be possible.

以下、具体的に説明すると、まず、コマンド記憶部26には、アームロボット6を動作させる命令であって、割り振られた担当Job42の各単一Job41をアームロボット6に実行させるための実行コマンドが記憶されている。例えばコマンド記憶部26aには、Job[A]〜Job[D]を、アームロボット6aに実行させるための実行コマンドが記憶されている。   More specifically, first, the command storage unit 26 has an instruction for operating the arm robot 6 and an execution command for causing the arm robot 6 to execute each single job 41 of the assigned job 42. It is remembered. For example, the command storage unit 26a stores execution commands for causing the arm robot 6a to execute Job [A] to Job [D].

そして、担当Job処理部27は、セルコントローラ2により割り振られた担当Job42を解釈し、ワーク搬送方向上流から搬送されたワークWに対して、担当Job42のそれぞれの単一Job41の作業を、順次、アームロボット6に実行させる。具体的には、担当Job処理部27は、コマンド記憶部26から担当Job42の各単一Job41に対応する実行コマンドを読み出して実行することで、アームロボット6に作業を実行させる。例えば担当Job処理部27aは、コマンド記憶部26aから担当Job42aのJob[A]〜Job[C]に対応する実行コマンドを読み出して、実行コマンドに従ってアームロボット6aに作業を実行させる。ここで、コマンド記憶部26aには、Job[A]〜Job[D]をアームロボット6aに実行させるための実行コマンドが記憶されているので、実行可能Job43aはJob[A]〜Job[D]に設定されていることとなる。同様に、図4(a)では、実行可能Job43bはJob[C]〜Job[G]、実行可能Job43cはJob[F]〜Job[J]、実行可能Job43dはJob[I]〜Job[M]、実行可能Job43eはJob[L]〜Job[N]に設定されている。   Then, the assigned job processing unit 27 interprets the assigned job 42 assigned by the cell controller 2, and sequentially performs the work of each single job 41 of the assigned job 42 on the workpiece W transferred from the upstream side of the workpiece transfer direction. The arm robot 6 is executed. Specifically, the responsible job processing unit 27 reads out and executes the execution command corresponding to each single job 41 of the responsible job 42 from the command storage unit 26, thereby causing the arm robot 6 to perform the work. For example, the responsible job processing unit 27a reads execution commands corresponding to Job [A] to Job [C] of the responsible job 42a from the command storage unit 26a, and causes the arm robot 6a to perform work according to the execution command. Here, since the command storage unit 26a stores execution commands for causing the arm robot 6a to execute Job [A] to Job [D], the executable Job 43a has Job [A] to Job [D]. It will be set to. Similarly, in FIG. 4A, the executable Job 43b is Job [C] to Job [G], the executable Job 43c is Job [F] to Job [J], and the executable Job 43d is Job [I] to Job [M]. The executable job 43e is set to Job [L] to Job [N].

互いに隣接する2つのアームロボット6に接続されたロボットコントローラ4に設定される実行可能Job43は、単一Job41が互いに重複するように設定されている。例えば実行可能Job43bと実行可能Job43cにおいては、Job[F],Job[G]が重複して設定されている。   The executable job 43 set in the robot controller 4 connected to the two arm robots 6 adjacent to each other is set so that the single job 41 overlaps each other. For example, in the executable Job 43b and the executable Job 43c, Job [F] and Job [G] are set redundantly.

また、担当Job処理部27は、セルコントローラ2の同期制御部25により送出された同期信号のタイミングでアームロボット6にワークWをワーク搬送方向下流に搬送させる。例えば、担当Job処理部27aは、同期信号のタイミングでアームロボット6aにワークWをワーク搬送方向下流に配置された作業台5b上のワーク固定部7bに搬送させる。また、担当Job処理部27eは、同期信号のタイミングでアームロボット6eにワークWをワーク搬送方向下流に配置されたワーク搬出台10に搬送させる。以上の動作により、複数のアームロボット6a〜6eは、ワークWを一斉に同期してワーク搬送方向下流に搬送することとなる。   In addition, the responsible job processing unit 27 causes the arm robot 6 to convey the workpiece W downstream in the workpiece conveyance direction at the timing of the synchronization signal transmitted by the synchronization control unit 25 of the cell controller 2. For example, the responsible job processing unit 27a causes the arm robot 6a to transfer the workpiece W to the workpiece fixing unit 7b on the work table 5b arranged downstream in the workpiece transfer direction at the timing of the synchronization signal. Further, the responsible job processing unit 27e causes the arm robot 6e to transport the workpiece W to the workpiece unloading table 10 arranged downstream in the workpiece conveying direction at the timing of the synchronization signal. By the above operation, the plurality of arm robots 6a to 6e conveys the workpiece W all at once in the workpiece conveyance direction.

モータ駆動部28は、担当Job処理部27の制御の下、アームロボット6のモータ及びワーク固定部7のモータを駆動するものである。つまり、担当Job処理部27は、モータ駆動部28によるアームロボット6のモータの駆動を制御することで、アームロボット6の動作を制御している。センサ検出部29は、アームロボット6に設けられたセンサ及びワーク固定部7に設けられたセンサにより検出を行うものである。ステーション状態管理部30は、モータ駆動部28及びセンサ検出部29の情報からロボットステーション3のエラー状況を管理し、もしエラーが発生している場合はセルコントローラ2へ通知する。   The motor driving unit 28 drives the motor of the arm robot 6 and the motor of the workpiece fixing unit 7 under the control of the responsible job processing unit 27. That is, the responsible job processing unit 27 controls the operation of the arm robot 6 by controlling the motor driving of the arm robot 6 by the motor driving unit 28. The sensor detection unit 29 performs detection using a sensor provided in the arm robot 6 and a sensor provided in the workpiece fixing unit 7. The station state management unit 30 manages the error status of the robot station 3 from the information of the motor drive unit 28 and the sensor detection unit 29, and notifies the cell controller 2 if an error has occurred.

Job進行通知部31は、今回のサイクルタイムで指示を受けた担当Job42の進行状況をセルコントローラ2へ通知する。更に、Job進行通知部31は、アームロボット6における単一Job41の作業に遅延が発生した際に、サイクルタイムTの範囲内で作業が完了しないと予測される未実施の単一Job41の情報をセルコントローラ2へ通知する。セルコントローラ2のJob進行管理部22は、ロボットコントローラ4のJob進行通知部31から受信した情報を処理し、担当Job再割振部24に出力する。   The job progress notification unit 31 notifies the cell controller 2 of the progress status of the responsible job 42 that has received an instruction at the current cycle time. Further, the job progress notifying unit 31 stores information on the unexecuted single job 41 that is predicted not to be completed within the cycle time T when the work of the single job 41 in the arm robot 6 is delayed. The cell controller 2 is notified. The job progress management unit 22 of the cell controller 2 processes the information received from the job progress notification unit 31 of the robot controller 4 and outputs it to the assigned job reallocation unit 24.

以上の構成で、セルコントローラ2の担当Job割振部23は、各担当Job42a〜42eを、各ロボットコントローラ4a〜4eに割り振る。同期制御部25は、一定の時間間隔(サイクルタイムT)で同期信号を各ロボットコントローラ4a〜4eに出力している。各ロボットコントローラ4a〜4eの担当Job処理部27は、同期信号に同期してサイクルタイムT毎に、アームロボット6にワークWをワーク搬送方向下流に搬送させる。そして、各担当Job処理部27は、ワーク搬送方向上流から搬送されたワークWに対して、割り振られた担当Job42の作業をアームロボット6に順次実行させる。各アームロボット6による各担当Job42の作業に遅延が発生していない場合には、担当Job割振部23により割り振られた各担当Job42の作業をサイクルタイムT内で終了させることができる。   With the above configuration, the assigned job allocation unit 23 of the cell controller 2 allocates each assigned job 42a to 42e to each robot controller 4a to 4e. The synchronization control unit 25 outputs a synchronization signal to each robot controller 4a to 4e at a constant time interval (cycle time T). The job processing unit 27 in charge of each of the robot controllers 4a to 4e causes the arm robot 6 to convey the workpiece W downstream in the workpiece conveyance direction at every cycle time T in synchronization with the synchronization signal. Then, each assigned job processing unit 27 causes the arm robot 6 to sequentially perform the assigned job 42 work on the workpiece W transferred from the upstream side of the workpiece transfer direction. When there is no delay in the work of each assigned job 42 by each arm robot 6, the work of each assigned job 42 allocated by the assigned job allocating unit 23 can be completed within the cycle time T.

次に、一部のアームロボット6にて担当Job42中の単一Job41の作業に遅延が発生した場合のセルコントローラ2及び各ロボットコントローラ4の動作について説明する。図4(b)では、アームロボット6bにて担当Job42b中のJob[E]の作業に遅延が発生したものとして例示している。図5は、各アームロボット6による作業の流れを示すタイムチャートである。   Next, the operation of the cell controller 2 and each robot controller 4 when a delay occurs in the work of the single job 41 in the job 42 in charge in some arm robots 6 will be described. FIG. 4B illustrates an example in which the job [Job] in the assigned job 42b is delayed in the arm robot 6b. FIG. 5 is a time chart showing a work flow by each arm robot 6.

いずれかのアームロボット6で単一Jobの作業に遅延が生じた場合、当該遅延が発生したアームロボット6に接続されたロボットコントローラ4のJob進行通知部31は、未実施の単一Jobの情報をセルコントローラ2に通知(送信)する。例えばロボットコントローラ4bのJob進行通知部31bは、サイクルタイムT2においてワークW5に対するアームロボット6bによるJob[E]の作業に遅延が発生しているので、Job[F]が未実施であること示す情報をセルコントローラ2に通知する。セルコントローラ2のJob進行管理部22は、ワークW5に対してアームロボット6bによるJob[F]の作業が未実施であることを示す信号を、担当Job再割振部24に出力する。   When a delay occurs in the operation of a single job in any of the arm robots 6, the job progress notification unit 31 of the robot controller 4 connected to the arm robot 6 in which the delay occurs causes information on the unexecuted single job. Is sent (transmitted) to the cell controller 2. For example, the job progress notification unit 31b of the robot controller 4b has information indicating that Job [F] has not been performed because a delay occurs in the job [E] by the arm robot 6b with respect to the workpiece W5 at the cycle time T2. Is notified to the cell controller 2. The job progress management unit 22 of the cell controller 2 outputs a signal indicating that the job [F] is not performed by the arm robot 6b to the work W5 to the assigned job reallocation unit 24.

担当Job再割振部24は、Job[E]の作業に遅延が発生したアームロボット6bよりもワーク搬送方向下流に位置するアームロボット6c〜6eに設けられたロボットコントローラ4c〜4eに、未実施であるJob[F]〜Job[N]を割り振りし直す。その際、担当Job再割振部24は、それぞれのロボットコントローラ4c〜4eに割り振る単一Job41の数の上限をn個として、作業順に割り振りし直す。つまり、担当Job再割振部24は、ロボットコントローラ4cには、Job[F]〜Job[H]からなる担当Job44cを割り振りし直す。担当Job再割振部24は、ロボットコントローラ4dには、Job[I]〜Job[K]からなる担当Job44dを割り振りし直す。担当Job再割振部24は、ロボットコントローラ4eには、Job[L]〜Job[N]からなる担当Job44eを割り振りし直す。   The assigned job reallocation unit 24 has not yet performed the robot controllers 4c to 4e provided in the arm robots 6c to 6e that are located downstream of the arm robot 6b in which the work of Job [E] is delayed in the work transfer direction. Reallocate a certain Job [F] to Job [N]. At that time, the assigned job reallocation unit 24 reassigns the upper limit of the number of single jobs 41 to be assigned to the respective robot controllers 4c to 4e in the order of work. That is, the assigned job reallocation unit 24 reallocates the assigned job 44c including Job [F] to Job [H] to the robot controller 4c. The assigned job reallocation unit 24 reassigns assigned job 44d including Job [I] to Job [K] to the robot controller 4d. The assigned job reallocation unit 24 reassigns assigned job 44e including Job [L] to Job [N] to the robot controller 4e.

即ち、遅延が発生したアームロボット6bの隣のアームロボット6cに接続されたロボットコントローラ4cには、ロボットコントローラ4bで未実施のJob[F]が割り振られる。その結果、Job[I]が実施できなくなるので、Job[I]はアームロボット6cの隣のアームロボット6dに接続されたロボットコントローラ6dに割り振られる。同様に、Job[L]がロボットコントローラ6eに割り振られる。   In other words, Job [F] that has not been executed by the robot controller 4b is allocated to the robot controller 4c connected to the arm robot 6c adjacent to the arm robot 6b where the delay has occurred. As a result, Job [I] cannot be executed, and Job [I] is assigned to the robot controller 6d connected to the arm robot 6d adjacent to the arm robot 6c. Similarly, Job [L] is allocated to the robot controller 6e.

このように担当Job再割振部24が再割り振り処理を行うのは、図5に示すように、作業の遅延が生じたワークW5に対してだけであり、そのワークW5以外のワークWに対しては、作業の遅延が生じていないので、再割り振り処理は行わない。したがって、ワークW5以外のワークWに対しては、担当Job割振部23により割り振られた担当Job42の単一Job41の作業が実行される。   As shown in FIG. 5, the assigned job reallocation unit 24 performs the reallocation process only for the work W5 in which the work delay has occurred, and for the work W other than the work W5. Since no work delay has occurred, no reallocation processing is performed. Therefore, for the work W other than the work W5, the work of the single job 41 of the assigned job 42 allocated by the assigned job allocating unit 23 is executed.

以上のように、担当Job再割振部24に再割り振り処理が実行されるので、ロボットステーション5cのロボットコントローラ4cの担当Job処理部27cは、サイクルタイムT3において、Job[F]〜Job[H]の作業をアームロボット6cに行わせる。また、ロボットステーション5dのロボットコントローラ4dの担当Job処理部27dは、サイクルタイムT4において、Job[I]〜Job[K]の作業をアームロボット6cに行わせる。また、ワーク搬送方向の最下流に位置するロボットステーション5eのロボットコントローラ4eの担当Job処理部27eは、サイクルタイムT5において、Job[L]〜Job[N]の作業をアームロボット6eに行わせる。   As described above, since the reallocation processing is executed for the assigned job reallocation unit 24, the assigned job processing unit 27c of the robot controller 4c of the robot station 5c performs job [F] to job [H] at the cycle time T3. The arm robot 6c performs the above operation. Also, the job processing unit 27d in charge of the robot controller 4d of the robot station 5d causes the arm robot 6c to perform the jobs [Job] [I] to Job [K] at the cycle time T4. In addition, the job processing unit 27e in charge of the robot controller 4e of the robot station 5e located on the most downstream side in the workpiece transfer direction causes the arm robot 6e to perform jobs [L] to Job [N] at the cycle time T5.

つまり、ロボットコントローラ4eには、担当Job割振部23によりm(=2)個の単一Job41が割り振られるが、アームロボット6bで未実施となった単一Job41が1個あったので、担当Job再割振部24により3個の単一Job41が割り振られる。このように、アームロボット6a〜6dによるいずれかの単一Job41の作業で遅延が発生したとしても、最下流に位置するアームロボット6eに行わせる単一Job41をサイクルタイムTの範囲内で増やすことができる。   That is, m (= 2) single job 41 is allocated to the robot controller 4e by the assigned job allocating unit 23, but there is one single job 41 that has not been executed in the arm robot 6b. Three single jobs 41 are allocated by the reallocation unit 24. Thus, even if a delay occurs in the operation of any single job 41 by the arm robots 6a to 6d, the single job 41 to be performed by the arm robot 6e located on the most downstream side is increased within the range of the cycle time T. Can do.

これにより、一部の単一Job41の作業に遅延が生じたとしても、各ロボットコントローラ4a〜4eは、割り振られた単一Job41の作業をサイクルタイムT内で終えることができる。したがって、例えばワークW5に対して一連の作業を施しているときに発生した、アームロボット6bによるJob[E]の作業の遅延が、別のワークWに対するアームロボット6a〜6eの作業に波及するのを防止することができる。つまり、別のワークWに作業を施す際に、各アームロボット6a〜6eにおいて待ち時間が生じるのを防止できる。ゆえに、複数のアームロボット6a〜6eによるワークWの生産性が向上する。   Thereby, even if a delay occurs in the work of a part of the single job 41, each robot controller 4a to 4e can finish the work of the assigned single job 41 within the cycle time T. Accordingly, for example, a delay in the job of Job [E] by the arm robot 6b, which occurs when a series of operations are performed on the workpiece W5, affects the operations of the arm robots 6a to 6e with respect to another workpiece W. Can be prevented. That is, it is possible to prevent waiting time in each of the arm robots 6a to 6e when performing work on another workpiece W. Therefore, the productivity of the workpiece W by the plurality of arm robots 6a to 6e is improved.

[第2実施形態]
次に、本発明の第2実施形態に係るロボットシステムについて説明する。図6は、本発明の第2実施形態に係るロボットシステム1Aの概略構成を示すブロック図である。図7は、図6に示したロボットシステム1Aの制御装置を示す制御ブロック図である。なお、本第2実施形態において、上記第1実施形態と同様の構成については、同一符号を付してその説明を省略する。
[Second Embodiment]
Next, a robot system according to a second embodiment of the invention will be described. FIG. 6 is a block diagram showing a schematic configuration of a robot system 1A according to the second embodiment of the present invention. FIG. 7 is a control block diagram showing a control device of the robot system 1A shown in FIG. In the second embodiment, the same components as those in the first embodiment are denoted by the same reference numerals, and the description thereof is omitted.

本第2実施形態では、ロボットシステム1Aは、ワーク搬送方向の最下流に位置するロボットステーション3e(アームロボット6e)に隣接して配置されたバッファであるロボットステーション3fを備えている。ロボットステーション3fは、アームロボット6a〜6eと同様の構成の補助用作業ロボットであるアームロボット6fと、ロボットコントローラ4a〜4eと同様の構成の補助用ロボットコントローラであるロボットコントローラ4fとを有している。また、ロボットステーション3fは、作業台5a〜5eと同様の構成の作業台5fと、ワーク固定部7a〜7eと同様の構成のワーク固定部7fと、組付け部材設置部8a〜8eと同様の構成の組付け部材設置部8fとを有している。   In the second embodiment, the robot system 1A includes a robot station 3f that is a buffer disposed adjacent to the robot station 3e (arm robot 6e) located on the most downstream side in the workpiece transfer direction. The robot station 3f includes an arm robot 6f that is an auxiliary work robot having the same configuration as the arm robots 6a to 6e, and a robot controller 4f that is an auxiliary robot controller having the same configuration as the robot controllers 4a to 4e. Yes. The robot station 3f is similar to the work table 5f having the same configuration as the work tables 5a to 5e, the work fixing unit 7f having the same configuration as the work fixing units 7a to 7e, and the assembly member installation units 8a to 8e. It has an assembly member installation portion 8f having a configuration.

ロボットコントローラ4fは、コマンド記憶部26f、補助用処理部としての担当Job処理部27f、モータ駆動部28f、センサ検出部29f、ステーション状態管理部30f及びJob進行通知部31fを有している。   The robot controller 4f includes a command storage unit 26f, a responsible job processing unit 27f as an auxiliary processing unit, a motor driving unit 28f, a sensor detection unit 29f, a station state management unit 30f, and a job progress notification unit 31f.

図8は、担当Job42の割り付けを示す概略説明図であり、図8(a)は遅延発生前、図8(b)は遅延発生後を示している。本第2実施形態では、担当Job割振部23は、ロボットコントローラ4a〜4eには、上記第1実施形態と同様に、担当Job42a〜42eを割り振る割り振り処理を実施するが、ロボットコントローラ4fに対しては担当Jobを割り振らない。また、ロボットコントローラ4fには、実行可能Job43fが設定されている。この実行可能Job43fは担当Job42eの全てもしくは一部と同一である。本第2実施形態では、実行可能Job43fは実行可能Job43eの一部と同一、例えばJob[L]、Job[M]及びJob[N]で構成されている。つまり、コマンド記憶部26fには、Job[L]、Job[M]及びJob[N]を実行させる実行コマンドが記憶されている。   8A and 8B are schematic explanatory diagrams showing assignment of the responsible job 42. FIG. 8A shows a state before the occurrence of delay and FIG. 8B shows a state after the occurrence of delay. In the second embodiment, the assigned job allocating unit 23 performs an allocation process for allocating assigned jobs 42a to 42e to the robot controllers 4a to 4e as in the first embodiment. Does not allocate a job in charge. Further, an executable Job 43f is set in the robot controller 4f. This executable Job 43f is the same as all or part of the responsible Job 42e. In the second embodiment, the executable Job 43f is the same as a part of the executable Job 43e, for example, Job [L], Job [M], and Job [N]. That is, the command storage unit 26f stores execution commands for executing Job [L], Job [M], and Job [N].

以上の構成で、各アームロボット6a〜6eによる各担当Job42の作業に遅延が発生していない場合には、担当Job割振部23により割り振られた各担当Job42の作業をサイクルタイムT内で終了させることができる。   With the above configuration, when there is no delay in the work of each assigned job 42 by each of the arm robots 6a to 6e, the work of each assigned job 42 assigned by the assigned job allocating unit 23 is completed within the cycle time T. be able to.

次に、図8(b)に示すように、アームロボット6bにおけるJob[D]の作業において遅延が発生し、Job[E]及びJob[F]が未実施であるものとする。   Next, as shown in FIG. 8B, it is assumed that a delay occurs in the job [D] in the arm robot 6b, and Job [E] and Job [F] are not executed.

各ロボットコントローラ4bのJob進行通知部31bは、Job[E]及びJob[F]が未実施であることを示す情報をセルコントローラ2に通知する。セルコントローラ2のJob進行管理部22は、アームロボット6bによるJob[E]及びJob[F]の作業が未実施であることを示す信号を、担当Job再割振部24に出力する。   The job progress notification unit 31b of each robot controller 4b notifies the cell controller 2 of information indicating that Job [E] and Job [F] are not executed. The job progress management unit 22 of the cell controller 2 outputs a signal indicating that Job [E] and Job [F] operations by the arm robot 6 b are not performed to the responsible job reallocation unit 24.

そして、担当Job再割振部24は、再割り振り処理を実行する。つまり、担当Job再割振部24は、ロボットコントローラ4cには、Job[E]〜Job[G]からなる担当Job44cを割り振りし直す。担当Job再割振部24は、ロボットコントローラ4dには、Job[H]〜Job[J]からなる担当Job44dを割り振りし直す。担当Job再割振部24は、ロボットコントローラ4eには、Job[K]〜Job[M]からなる担当Job44eを割り振りし直す。   Then, the assigned job reallocation unit 24 executes reallocation processing. That is, the assigned job reallocation unit 24 reassigns assigned job 44c composed of Job [E] to Job [G] to the robot controller 4c. The assigned job reallocation unit 24 reassigns assigned job 44d composed of Job [H] to Job [J] to the robot controller 4d. The assigned job reallocation unit 24 reassigns assigned job 44e including Job [K] to Job [M] to the robot controller 4e.

ここで、担当Job再割振部24は、ロボットコントローラ4eに割り振って上限のn(=3)個を超えた分の残りのJob[N]については、アームロボット6eでは一定の時間間隔内(T)で処理できないので、ロボットコントローラ4fに割り振る。本第2実施形態では、ロボットコントローラ4fには、Job[N]からなる担当Job44fを割り振りし直す。   Here, the assigned job reallocation unit 24 allocates the robot controller 4e to the remaining job [N] exceeding the upper limit n (= 3) within a certain time interval (T Since it cannot be processed in (), the robot controller 4f is assigned. In the second embodiment, the assigned job 44f composed of Job [N] is reassigned to the robot controller 4f.

図9は、各アームロボット6による作業の流れを示すタイムチャートである。図9に示すサイクルタイムT2において、アームロボット6bで担当Job42bのうちJob[E]及びJob[F]が未実施Jobとなっている。よって、次のサイクルタイムT3にてアームロボット6cは、セルコントローラ2からの指示よる担当Job44cとして、Job[E]から作業を実施する。同様にサイクルタイムT4でアームロボット6dはJob[H]から、サイクルタイムT5でアームロボット6eはJob[K]から作業を実施する。   FIG. 9 is a time chart showing the flow of work by each arm robot 6. At cycle time T2 shown in FIG. 9, among the assigned job 42b in the arm robot 6b, Job [E] and Job [F] are unexecuted jobs. Therefore, at the next cycle time T3, the arm robot 6c performs work from Job [E] as the responsible job 44c according to the instruction from the cell controller 2. Similarly, the arm robot 6d performs work from Job [H] at cycle time T4, and the arm robot 6e performs work from Job [K] at cycle time T5.

最下流に位置するアームロボット6eに接続されたロボットコントローラ4eに割り振られる担当Job44eは、他のロボットコントローラに比べ時間的に2/3に割り振ってあるが、サイクルタイムT5内でワークW5の組立工程を完了することができない。よって次のサイクルタイムT6でバッファのロボットコントローラ4fが担当Job44fとしてJob[N]を実行する。ワークW5の組立て完了は予定のサイクルタイムT5をオーバするが、次ワークW6は予定のサイクルタイムT6内に組立て完了しており、以降のワーク組立てに対し遅延の波及が防止できていることが分かる。   Job 44e assigned to the robot controller 4e connected to the arm robot 6e located on the most downstream side is assigned to 2/3 in time compared to other robot controllers, but the assembly process of the workpiece W5 within the cycle time T5. Can't complete. Therefore, at the next cycle time T6, the buffer robot controller 4f executes Job [N] as the responsible job 44f. Completion of the assembly of the workpiece W5 exceeds the scheduled cycle time T5, but the next workpiece W6 has been assembled within the scheduled cycle time T6, and it can be seen that the delay of the subsequent workpiece assembly can be prevented. .

以上、本第2実施形態では、最下流に位置するアームロボット6eにのみ隣接する、バッファのアームロボット6fを設けたことで、ロボットシステム1A全体のコスト、設置スペースを抑えることができる。   As described above, in the second embodiment, by providing the buffer arm robot 6f adjacent only to the arm robot 6e located on the most downstream side, the cost and installation space of the entire robot system 1A can be reduced.

[第3実施形態]
次に、本発明の第3実施形態に係るロボットシステムについて説明する。図10は、本発明の第3実施形態に係るロボットシステム1Bの概略構成を示すブロック図である。ロボットシステム1Bの制御装置の制御ブロック図は、図2と同様であるので、図2を参照しながら説明する。なお、本第3実施形態において、上記第1実施形態と同様の構成については、同一符号を付してその説明を省略する。
[Third Embodiment]
Next, a robot system according to a third embodiment of the invention will be described. FIG. 10 is a block diagram showing a schematic configuration of a robot system 1B according to the third embodiment of the present invention. The control block diagram of the control device of the robot system 1B is the same as that in FIG. 2 and will be described with reference to FIG. Note that in the present third embodiment, identical symbols are assigned to configurations similar to those in the first embodiment and descriptions thereof are omitted.

まず、本第3実施形態において上記第1実施形態と異なるのは、ワークWを直接搬送する代わりに、ワークWを載置した搬送トレイ12(12x,12a〜12e,12y)をアームロボット6が把持して搬送するようにした点である。搬送トレイ12上には、ワークW、並びにワークWに組付ける組付け部材及び冶具である組付用ユニット13(13x,13a〜13e,13y)が載置されている。搬送トレイ12を受け渡す際、搬送トレイ12上のワークWは各ロボットステーション3のワーク固定部7と嵌合させ、モータ駆動部28の指示により組立て作業時の駆動ができるようになっている。組付用ユニット13は、全Jobで組み付けるパーツ及び治工具を搭載しており、各ロボットステーション3での実行可能Jobを増やすことができる。例えば、全Jobで使用するパーツ及び治工具を組付用ユニット13に搭載すれば、どのロボットステーション3でも全Jobに含まれる単一Jobはハード構成上、実行可能となる。   First, the third embodiment is different from the first embodiment in that, instead of directly transferring the workpiece W, the arm robot 6 moves the transfer tray 12 (12x, 12a to 12e, 12y) on which the workpiece W is placed. This is a point that is gripped and conveyed. On the transport tray 12, a work W and an assembly unit 13 (13 x, 13 a to 13 e, 13 y) that is an assembly member and a jig to be assembled to the work W are placed. When the transfer tray 12 is delivered, the work W on the transfer tray 12 is fitted to the work fixing unit 7 of each robot station 3 and can be driven at the time of assembling work according to an instruction from the motor drive unit 28. The assembly unit 13 is equipped with parts and jigs to be assembled by all jobs, and the number of executable jobs at each robot station 3 can be increased. For example, if parts and jigs used in all jobs are mounted on the assembling unit 13, any robot station 3 can execute a single job included in all jobs in terms of hardware configuration.

本第3実施形態では、複数のアームロボット6a〜6eのうちいずれかのアームロボット6での単一Jobの作業で遅延が生じた場合には、上記第1実施形態と同様に、セルコントローラ2の担当Job再割振部24が再割り振り処理を実施する。   In the present third embodiment, when a delay occurs in the operation of a single job by any one of the plurality of arm robots 6a to 6e, the cell controller 2 is the same as in the first embodiment. The assigned job reallocation unit 24 performs the reallocation process.

ところで、複数のアームロボット6a〜6eのうちいずれかのアームロボット6が故障などの原因で作業不能となることがある。本第3実施形態のロボットコントローラ4のステーション状態管理部30は、アームロボット6が作業不能であることを示すエラー情報をセルコントローラ2に通知するように構成されている。   By the way, one of the arm robots 6a to 6e may be unable to work due to a failure or the like. The station state management unit 30 of the robot controller 4 according to the third embodiment is configured to notify the cell controller 2 of error information indicating that the arm robot 6 cannot work.

セルコントローラ2のロボットステーションモニタ部21は、エラー情報を処理することで、何れのアームロボット6が作業不能となったかを検知する検知部として機能する。そして、この検知結果に基づき、担当Job割振部23は、上記第1実施形態で説明した割り振り処理を、複数のロボットコントローラ4a〜4eのうち、作業不能となったアームロボットを除くアームロボットに設けられたロボットコントローラに対して行う。   The robot station monitor unit 21 of the cell controller 2 functions as a detection unit that detects which arm robot 6 has become inoperable by processing error information. Based on the detection result, the assigned job allocating unit 23 provides the allocation processing described in the first embodiment to the arm robots excluding the arm robots incapable of working among the plurality of robot controllers 4a to 4e. To the specified robot controller.

図11は、担当Job42の割り付けを示す概略説明図であり、図11(a)はアームロボット6が作業不能となるエラー発生前、図11(b)はエラー発生後を示している。なお、各ロボットコントローラ4a〜4eに設定される実行可能Job43a〜43eを、全Jobとしてもよいが、図11に示すように、一部の単一Jobで構成してもよい。   11A and 11B are schematic explanatory diagrams showing the assignment of the assigned job 42. FIG. 11A shows the state before the occurrence of an error that makes the arm robot 6 unable to work, and FIG. Note that the executable jobs 43a to 43e set in the robot controllers 4a to 4e may be all jobs, but may be configured as a part of a single job as shown in FIG.

図11(a)に示すように、上記第1実施形態と同様、各ロボットコントローラ4a〜4dには、n(=3)個の単一Jobからなる担当Job42a〜42dが割り振られる。ロボットコントローラ4eには、m(=2)個の単一Jobからなる担当Job42eが割り振られる。   As shown in FIG. 11A, as in the first embodiment, the robot controllers 4a to 4d are assigned job jobs 42a to 42d composed of n (= 3) single jobs. The robot controller 4e is assigned a responsible job 42e consisting of m (= 2) single jobs.

次に、図11(b)に示すように、例えばアームロボット6bが作業不能となった場合について説明する。担当Job割振部23は、アームロボット6bを除くアームロボット6a,6c,6d,6eに接続されたロボットコントローラ4a,4c,4d,4eに対して担当Job45a,45c,45d,45eの割り振り処理を実施する。なお、ロボットコントローラ4bには単一Jobは割り振られない、換言すれば、割り振られる担当Job45bに含まれる単一Jobの数は0である。   Next, as shown in FIG. 11B, for example, the case where the arm robot 6b becomes inoperable will be described. The assigned job allocating unit 23 assigns assigned jobs 45a, 45c, 45d, and 45e to the robot controllers 4a, 4c, 4d, and 4e connected to the arm robots 6a, 6c, 6d, and 6e except the arm robot 6b. To do. Note that no single job is assigned to the robot controller 4b, in other words, the number of single jobs included in the assigned job 45b is zero.

ロボットコントローラ4a,4c,4dの担当Jobとして処理する単一Jobの数が増えているので、サイクルタイムT’は当初のサイクルタイムTよりも、単一Jobが増加する分、長く設定されている。つまり、セルコントローラ2の同期制御部25は、サイクルタイムT’に合わせ、各ロボットコントローラ4に同期信号を送信する。   Since the number of single jobs to be processed as jobs in charge of the robot controllers 4a, 4c, and 4d is increasing, the cycle time T ′ is set longer than the initial cycle time T by the increment of the single job. . That is, the synchronization control unit 25 of the cell controller 2 transmits a synchronization signal to each robot controller 4 in accordance with the cycle time T ′.

以上、本第3実施形態では、あるアームロボット6に担当Jobが割り振れなくなった状態でも、ロボットシステム1Bを止めることなく、見直し後のサイクルタイムT’で常に一定に組立工程を実施することが可能である。   As described above, in the third embodiment, even when the assigned job cannot be assigned to a certain arm robot 6, the assembly process can be performed constantly at the cycle time T ′ after review without stopping the robot system 1B. Is possible.

なお、上記実施形態に基づいて本発明を説明したが、本発明はこれに限定されるものではない。上記実施形態は、ワークの組立てラインに関するものであったが、本発明は一連の作業工程を複数のロボットステーションで分割して実行する生産ラインに適用でき、また、生産ライン以外の多様な作業のラインにおいても適用可能である。   In addition, although this invention was demonstrated based on the said embodiment, this invention is not limited to this. The above embodiment relates to a work assembly line, but the present invention can be applied to a production line in which a series of work processes are divided and executed by a plurality of robot stations, and various work other than the production line can be performed. It is also applicable to the line.

1,1A,1B…ロボットシステム、2…セルコントローラ(メインコントローラ)、4a〜4e…ロボットコントローラ、4f…ロボットコントローラ(補助用ロボットコントローラ)、6a〜6e…アームロボット(作業ロボット)、6f…アームロボット(補助用作業ロボット)、20…単一Jobデータベース部(記憶部)、21…ロボットステーションモニタ部(検知部)、23…担当Job割振部(割振部)、24…担当Job再割振部(再割振部)、25…同期制御部、27a〜27e…担当Job処理部(処理部)、27f…担当Job処理部(補助用処理部)、31a〜31e…Job進行通知部(通知部) DESCRIPTION OF SYMBOLS 1,1A, 1B ... Robot system, 2 ... Cell controller (main controller), 4a-4e ... Robot controller, 4f ... Robot controller (auxiliary robot controller), 6a-6e ... Arm robot (working robot), 6f ... Arm Robot (auxiliary work robot), 20 ... single job database unit (storage unit), 21 ... robot station monitor unit (detection unit), 23 ... responsible job allocation unit (allocation unit), 24 ... responsible job re-allocation unit ( Reassignment unit), 25 ... synchronization control unit, 27a to 27e ... responsible job processing unit (processing unit), 27f ... responsible job processing unit (auxiliary processing unit), 31a to 31e ... job progress notification unit (notification unit)

Claims (3)

ワークを順次搬送するワーク搬送方向に並べて配置され、ワークに施す一連の作業を分担して行う複数の作業ロボットと、前記複数の作業ロボットのそれぞれに設けられたロボットコントローラと、前記複数のロボットコントローラに接続されたメインコントローラと、を備えたロボットシステムにおいて、
前記メインコントローラは、
前記一連の作業を分割して得られる複数の作業区分を記憶する記憶部と、
前記記憶部に記憶された複数の作業区分を、前記複数のロボットコントローラのうち、ワーク搬送方向の最下流に位置する作業ロボット以外の作業ロボットに設けられたロボットコントローラにはn(≧2の正の整数)個、ワーク搬送方向の最下流に位置する作業ロボットに設けられたロボットコントローラにはm(<nの正の整数)個、作業順に割り振る割り振り処理を実行する割振部と、
ワークをワーク搬送方向下流に搬送するタイミングを示す同期信号を、前記各ロボットコントローラに一定の時間間隔で送出する同期制御部と、を有し、
前記各ロボットコントローラは、
前記同期制御部により送出された前記同期信号のタイミングで作業ロボットにワークをワーク搬送方向下流に搬送させ、ワーク搬送方向上流から搬送されたワークに対して、割り振られた作業区分の作業を作業ロボットに実行させる処理部と、
作業ロボットにおける作業区分の作業に遅延が発生した際に前記時間間隔の範囲内で作業が完了しないと予測される未実施の作業区分の情報を、前記メインコントローラに通知する通知部と、を有し、
前記メインコントローラは、
前記通知部により前記情報が通知された際に、前記複数のロボットコントローラのうち、作業区分の作業に遅延が発生した作業ロボットよりもワーク搬送方向下流に位置する作業ロボットに設けられたロボットコントローラに、未実施である作業区分を、n個を上限として作業順に割り振りし直す再割り振り処理を実行する再割振部を有することを特徴とするロボットシステム。
A plurality of work robots arranged side by side in a work transfer direction for sequentially transferring a work and performing a series of operations performed on the work, a robot controller provided in each of the plurality of work robots, and the plurality of robot controllers In a robot system comprising a main controller connected to
The main controller is
A storage unit for storing a plurality of work sections obtained by dividing the series of work;
A plurality of work categories stored in the storage unit are assigned n (≧ 2 positive values) to a robot controller provided in a work robot other than the work robot located at the most downstream side in the work transfer direction among the plurality of robot controllers. An allocation unit that executes an allocation process to allocate m (<n positive integers), the order of work, to the robot controller provided in the work robot located at the most downstream in the workpiece transfer direction;
A synchronization control unit that sends a synchronization signal indicating the timing of conveying the workpiece downstream in the workpiece conveyance direction to the robot controllers at regular time intervals,
Each robot controller is
The work robot causes the work robot to transfer the work downstream in the work transfer direction at the timing of the synchronization signal sent by the synchronization control unit, and the work robot assigns work in the assigned work classification to the work transferred from the work transfer direction upstream. A processing unit to be executed,
A notification unit that notifies the main controller of information on an unexecuted work category that is predicted not to be completed within the time interval when a delay occurs in work of the work category in the work robot. And
The main controller is
When the information is notified by the notification unit, among the plurality of robot controllers, a robot controller provided in a work robot located downstream in the work transfer direction from the work robot in which work is delayed in work classification A robot system comprising: a reallocation unit that executes reallocation processing for reallocating unexecuted work categories in the order of work with n as an upper limit.
ワーク搬送方向の最下流に位置する作業ロボットに隣接して配置された補助用作業ロボットと、
前記補助用作業ロボットに設けられた補助用ロボットコントローラと、を備え、
前記補助用ロボットコントローラは、割り振られた作業区分の作業を前記補助用作業ロボットに実行させる補助用処理部を有し、
前記再割振部は、ワーク搬送方向の最下流に位置する作業ロボットに設けられたロボットコントローラに割り振って上限のn個を超えた分の作業区分については、前記補助用ロボットコントローラに割り振ることを特徴とする請求項1に記載のロボットシステム。
An auxiliary work robot arranged adjacent to the work robot located on the most downstream side in the work transfer direction;
An auxiliary robot controller provided in the auxiliary work robot,
The auxiliary robot controller has an auxiliary processing unit that causes the auxiliary work robot to execute the work of the assigned work category,
The re-allocation unit allocates to the auxiliary robot controller the work divisions that have been allocated to a robot controller provided in a work robot located on the most downstream side in the work transfer direction and have exceeded the upper limit of n. The robot system according to claim 1.
前記メインコントローラは、前記複数の作業ロボットのうち、作業不能となった作業ロボットを検知する検知部を有し、
前記割振部は、前記割り振り処理を、前記複数のロボットコントローラのうち、前記検知部により検知された作業不能となった作業ロボットを除く作業ロボットに設けられたロボットコントローラに対して行うことを特徴とする請求項1又は2に記載のロボットシステム。
The main controller has a detection unit that detects a work robot that is out of work among the plurality of work robots,
The allocating unit performs the allocation process on a robot controller provided in a work robot other than the work robot detected by the detection unit and disabled from the work robot among the plurality of robot controllers. The robot system according to claim 1 or 2.
JP2011084447A 2011-04-06 2011-04-06 Robot system Withdrawn JP2012218093A (en)

Priority Applications (1)

Application Number Priority Date Filing Date Title
JP2011084447A JP2012218093A (en) 2011-04-06 2011-04-06 Robot system

Applications Claiming Priority (1)

Application Number Priority Date Filing Date Title
JP2011084447A JP2012218093A (en) 2011-04-06 2011-04-06 Robot system

Publications (1)

Publication Number Publication Date
JP2012218093A true JP2012218093A (en) 2012-11-12

Family

ID=47270187

Family Applications (1)

Application Number Title Priority Date Filing Date
JP2011084447A Withdrawn JP2012218093A (en) 2011-04-06 2011-04-06 Robot system

Country Status (1)

Country Link
JP (1) JP2012218093A (en)

Cited By (6)

* Cited by examiner, † Cited by third party
Publication number Priority date Publication date Assignee Title
CN104057454A (en) * 2013-03-18 2014-09-24 株式会社安川电机 Workpiece assembling apparatus and workpiece assembling method
CN104062949A (en) * 2013-03-18 2014-09-24 株式会社安川电机 Production system and production method
CN107239869A (en) * 2016-03-28 2017-10-10 兄弟工业株式会社 Server unit, terminal installation determine method
WO2017203974A1 (en) * 2016-05-23 2017-11-30 日立Geニュークリア・エナジー株式会社 Autonomous work integrated management system
WO2019194316A1 (en) * 2018-04-05 2019-10-10 カワダロボティクス株式会社 Multi-function integrated work table and production system using same
JP2019197367A (en) * 2018-05-09 2019-11-14 株式会社デンソー Plan creation device

Cited By (9)

* Cited by examiner, † Cited by third party
Publication number Priority date Publication date Assignee Title
CN104057454A (en) * 2013-03-18 2014-09-24 株式会社安川电机 Workpiece assembling apparatus and workpiece assembling method
CN104062949A (en) * 2013-03-18 2014-09-24 株式会社安川电机 Production system and production method
JP2014180706A (en) * 2013-03-18 2014-09-29 Yaskawa Electric Corp Assembling device and assembling method for work
EP2784614A3 (en) * 2013-03-18 2015-04-29 Kabushiki Kaisha Yaskawa Denki Production system and production method
CN107239869A (en) * 2016-03-28 2017-10-10 兄弟工业株式会社 Server unit, terminal installation determine method
WO2017203974A1 (en) * 2016-05-23 2017-11-30 日立Geニュークリア・エナジー株式会社 Autonomous work integrated management system
WO2019194316A1 (en) * 2018-04-05 2019-10-10 カワダロボティクス株式会社 Multi-function integrated work table and production system using same
JP2019185258A (en) * 2018-04-05 2019-10-24 カワダロボティクス株式会社 Multifunction integration work table and manufacturing system utilizing the same
JP2019197367A (en) * 2018-05-09 2019-11-14 株式会社デンソー Plan creation device

Similar Documents

Publication Publication Date Title
JP2012218093A (en) Robot system
JP5741616B2 (en) Production system and product production method
US7617017B2 (en) System and method for resource reallocation based on ambient condition data
RU2576461C2 (en) Method of controlling timed production conveyor
US11385626B2 (en) Production planning apparatus
CN104603704A (en) Ultra-flexible production manufacturing
US11420323B2 (en) Method and control system for controlling movement sequences of a robot
US8452438B2 (en) Method for minimizing productivity loss while using a manufacturing scheduler
TW202225065A (en) Control method, device, apparatus and storage medium for a warehouse robot
JPWO2015019500A1 (en) Management method and management apparatus for electronic component mounting system having a plurality of production lines
JP2005038392A (en) Operation system for single path and its control method
WO2019198330A1 (en) Transport vehicle system and transport vehicle control method
WO2010073475A1 (en) Carrying vehicle system and carrying vehicle control method
JP3189883B2 (en) Automatic guided vehicle system
JP7082866B2 (en) Work instruction device
Chincholkar et al. Simultaneous optimisation of control factors in automated storage and retrieval systems and FMS using stochastic coloured Petri nets and the Taguchi method
Wilhelm Complexity of sequencing tasks in assembly cells attended by one or two robots
Müller et al. Robust flowline design for automotive body shops
JP2009237714A (en) Work device system
Wang et al. Job rescheduling by exploring the solution space of process planning for machine breakdown/arrival problems
Yonemoto et al. Reactive scheduling based on adaptive manipulator operations in a job shop configuration with two machines
Inoue et al. Scheduling for Assembly Line with Human-Robot Collaboration
Homayouni et al. Integrated Scheduling of Machines, Vehicles, and Storage Tasks in Flexible Manufacturing Systems
JP2008226044A (en) Alternate skill scheduling system, scheduling method and program
Özbayrak et al. How successfully does JIT handle machine breakdowns in an automated manufacturing system?

Legal Events

Date Code Title Description
RD04 Notification of resignation of power of attorney

Free format text: JAPANESE INTERMEDIATE CODE: A7424

Effective date: 20130228

A300 Withdrawal of application because of no request for examination

Free format text: JAPANESE INTERMEDIATE CODE: A300

Effective date: 20140701