JP2012093865A - Production schedule computation method and production schedule computing device - Google Patents

Production schedule computation method and production schedule computing device Download PDF

Info

Publication number
JP2012093865A
JP2012093865A JP2010239201A JP2010239201A JP2012093865A JP 2012093865 A JP2012093865 A JP 2012093865A JP 2010239201 A JP2010239201 A JP 2010239201A JP 2010239201 A JP2010239201 A JP 2010239201A JP 2012093865 A JP2012093865 A JP 2012093865A
Authority
JP
Japan
Prior art keywords
data
product
products
workers
production plan
Prior art date
Legal status (The legal status is an assumption and is not a legal conclusion. Google has not performed a legal analysis and makes no representation as to the accuracy of the status listed.)
Pending
Application number
JP2010239201A
Other languages
Japanese (ja)
Inventor
Akihiro Murata
明宏 村田
Current Assignee (The listed assignees may be inaccurate. Google has not performed a legal analysis and makes no representation or warranty as to the accuracy of the list.)
Sumitomo Forestry Co Ltd
Original Assignee
Sumitomo Forestry Co Ltd
Priority date (The priority date is an assumption and is not a legal conclusion. Google has not performed a legal analysis and makes no representation as to the accuracy of the date listed.)
Filing date
Publication date
Application filed by Sumitomo Forestry Co Ltd filed Critical Sumitomo Forestry Co Ltd
Priority to JP2010239201A priority Critical patent/JP2012093865A/en
Publication of JP2012093865A publication Critical patent/JP2012093865A/en
Pending legal-status Critical Current

Links

Images

Classifications

    • YGENERAL TAGGING OF NEW TECHNOLOGICAL DEVELOPMENTS; GENERAL TAGGING OF CROSS-SECTIONAL TECHNOLOGIES SPANNING OVER SEVERAL SECTIONS OF THE IPC; TECHNICAL SUBJECTS COVERED BY FORMER USPC CROSS-REFERENCE ART COLLECTIONS [XRACs] AND DIGESTS
    • Y02TECHNOLOGIES OR APPLICATIONS FOR MITIGATION OR ADAPTATION AGAINST CLIMATE CHANGE
    • Y02PCLIMATE CHANGE MITIGATION TECHNOLOGIES IN THE PRODUCTION OR PROCESSING OF GOODS
    • Y02P90/00Enabling technologies with a potential contribution to greenhouse gas [GHG] emissions mitigation
    • Y02P90/02Total factory control, e.g. smart factories, flexible manufacturing systems [FMS] or integrated manufacturing systems [IMS]

Abstract

PROBLEM TO BE SOLVED: To obtain an optimized production schedule when producing multiple kinds of products using processes commonly.SOLUTION: A storage unit 16 is used to store: worker data 18 including the total number of workers N; process data 20 including required processing time and the required number of workers for each product and the available number of products to be processed simultaneously, with respect to each process; product data 22 including process order required to produce each product; and a list of products to be produced by a due date. Production schedule data generation means 36 generates production schedule data 28 through a step for allocating each product to each process in process order, a step for allocating required workers to each process and a step for arranging states of allocating products to all processes in chronological order. Optimization means 38 searches for the earliest final process finish time 30 through a step for selecting products in random order, a step for delivering data about the selected products to the production schedule data generation means 36, and a step for changing product selection order and worker allocation order. Then, the production schedule is formed.

Description

本発明は、それぞれ一部あるいは全部が共通する複数の工程を経て製造される、複数種類の製品を、効率良く製造するための工程投入順や各工程への作業者の割付けを、コンピュータにより演算処理して最適化する、製造計画演算方法と製造計画演算装置とコンピュータプログラムとプログラム記録媒体に関する。   The present invention uses a computer to calculate the order of process input and the assignment of workers to each process to efficiently manufacture multiple types of products, each of which is manufactured through a plurality of processes that are partly or entirely in common. The present invention relates to a manufacturing plan calculation method, a manufacturing plan calculation device, a computer program, and a program recording medium that are processed and optimized.

製品を製造する工程と、それぞれ必要な要員と、時間帯毎に実際に投入できる要員数とをデータとして記憶装置に記憶させ、工程毎に要員を最適配置して生産性を高める技術が開発されている。   Developed technology to increase productivity by storing the manufacturing process of products, the necessary personnel for each, and the number of personnel that can be put in each time zone as data in the storage device, and optimally arranging the personnel for each process ing.

特開2001−249712号公報JP 2001-249712 A 特開2007−156990号公報JP 2007-156990 A

既知の従来の技術には、次のような解決すべき課題があった。
建具、階段、収納等の住宅部材を製造する工場では、いずれも、例えば、材料を切削する工程、組み立てる工程、塗装する工程、検査工程等を経る。即ち、複数の製品の製造工程の一部あるいは全部が共通する。各工程では、何種類もの製品を順に受け入れて加工処理する。しかしながら、製品の種類毎に、工程での所要時間が異なる。従って、各工程への製品の受け入れ順により、作業効率が異なる。しかも、作業者が数名必要な工程や、無人で処理される工程が混在していると、作業者の割付けも含む生産計画の最適化は容易でない。
The known prior art has the following problems to be solved.
In factories that manufacture housing components such as joinery, stairs, and storage, all undergo a process of cutting materials, a process of assembling, a process of painting, an inspection process, and the like. That is, some or all of the manufacturing processes of a plurality of products are common. In each process, several kinds of products are accepted and processed in order. However, the time required for the process differs for each type of product. Accordingly, the work efficiency varies depending on the order in which the products are received in each process. In addition, if there are processes that require several workers and processes that are processed unattended, it is not easy to optimize a production plan that includes worker assignments.

本発明は、以上の点に着目してなされたもので、各製品の製造工程への受け入れ順や作業者の割付けを最適化し、各製品の製造終了時刻を算出し、合理的な作業指示を自動的に生成し、製造原価の低減を図るといった目的に使用される、製造計画演算方法と製造計画演算装置とコンピュータプログラムとプログラム記録媒体を提供することを目的とする。   The present invention has been made paying attention to the above points, and optimizes the order of acceptance of each product into the manufacturing process and the assignment of workers, calculates the production end time of each product, and provides reasonable work instructions. An object of the present invention is to provide a manufacturing plan calculation method, a manufacturing plan calculation device, a computer program, and a program recording medium that are automatically generated and used for the purpose of reducing the manufacturing cost.

以下の構成はそれぞれ上記の課題を解決するための手段である。
〈構成1〉
いずれかの工程あるいは複数の全ての工程を、共通に利用する複数種類の製品を製造する場合に、記憶装置に対して、製造に従事することができる全作業者の識別コードと全作業者数Nを含む作業者データと、各工程について、その工程の識別コードと、製品毎の加工所要時間と、その工程に必要な作業者数と、その工程で同時に加工することができる製品の数とを含む工程データと、各製品の識別コードと、各製品の製造に必要な工程順とを含む製品データと、指定された期日までに製造を終了させる製品のリストとを記憶させて、生産計画データ生成手段が、前記製品のリストから製品が順番に選択されたとき、前記製品データを参照して、前記各製品が前記工程順に前記選択順に各工程に受け入れられるように、各製品を各工程に割付け、前記工程データを参照して、前記作業者が必要な工程を検出して、前記全作業者を、前工程から後工程に向かって、もしくは後工程から前工程に向かって順番に、各工程に必要な作業者数を満たすように割付けて、作業者が不足した工程があったときは、最も早く終了する工程の終了を待って該当する作業者を割付けて、前記全ての工程に前記製品を割付けた状態を時系列的に配置し、前記作業者の割付け結果を含む時系列割付けデータを生成し、最適化手段が、前記製品のリストから製品をランダムな順番に選択して、前記生産計画データ生成手段に前記時系列割付けデータを生成させて、前記生成された時系列割付けデータから最終工程終了時刻を検出し、その後、前記製品のリストから製品を選択する順番を変更して、前記生産計画データ生成手段に前記時系列割付けデータを生成させるという処理を繰り返して、最も早い最終工程終了時刻を探索し、前記最も早い最終工程終了時刻が検出された生産計画データの、前記製品の選択順を固定して、前記作業者を前記工程に割付ける順番を変更して、前記生産計画データ生成手段に前記時系列割付けデータを生成させるという処理を繰り返して、最も早い最終工程終了時刻を探索して、最も早い最終工程終了時刻が検出された時系列割付けデータを含む、最適化された生産計画データを出力することを特徴とする製造計画演算方法。
The following configurations are means for solving the above-described problems.
<Configuration 1>
When manufacturing multiple types of products that commonly use any process or all of a plurality of processes, the identification code and the total number of workers who can engage in the manufacturing of the storage device Worker data including N, for each process, the identification code of the process, the required processing time for each product, the number of workers required for that process, and the number of products that can be processed simultaneously in that process Process data, product data including identification codes for each product, order of processes required for the manufacture of each product, and a list of products whose production is to be terminated by a specified date. When a product is selected from the list of products in order, the data generation means refers to the product data, and each product is received in each step so that each product is received in each step in the order of selection in the order of the steps. Assigned to Referring to the process data, the operator detects necessary processes, and all the workers are moved from the previous process to the subsequent process or sequentially from the subsequent process to the previous process. When there is a process with insufficient workers, the corresponding worker is assigned after the process that ends most quickly, and the product is assigned to all the processes. Are arranged in time series, generate time series allocation data including the worker's allocation result, and the optimization means selects the products in a random order from the list of products, and performs the production. Causing the plan data generation means to generate the time-series allocation data, detect the final process end time from the generated time-series allocation data, and then change the order of selecting products from the list of products, Total production It repeats the process of generating the time series allocation data in the data generation means, searches for the earliest final process end time, and selects the product selection order of the production plan data in which the earliest final process end time is detected. Fixed, change the order of assigning the workers to the process, repeat the process of generating the time-series allocation data in the production plan data generation means, search for the earliest final process end time A production plan calculation method characterized by outputting optimized production plan data including time-series allocation data in which the earliest final process end time is detected.

〈構成2〉
構成1に記載の製造計画演算方法において、仕掛品置き場決定手段が、前記各工程で加工を終了した製品が次の工程に移るまで、前記製品の仕掛品を一時保管するための仕掛品置き場を設定し、最適化された生産計画が取得された後、その生産計画で使用をされた仕掛品置き場のみを、最小限必要な容量の仕掛品置き場に決定することを特徴とする製造計画演算方法。
<Configuration 2>
In the manufacturing plan calculation method according to Configuration 1, the work-in-process storage location determining means includes a work-in-process storage space for temporarily storing work-in-process items of the product until the product that has been processed in each step moves to the next step. After a set and optimized production plan is acquired, a work plan calculation method is characterized in that only the work in process place used in the production plan is determined as the work in process place with the minimum necessary capacity. .

〈構成3〉
構成2に記載の製造計画演算方法において、前記仕掛品置き場を、前記製品の加工所要時間をゼロとし、その工程に必要な作業者数をゼロ、同時に保管できる製品数を無制限と定義して、前記時系列データを生成し、いずれかの工程の間で、保管に使用された仕掛品置き場と、その仕掛品置き場に保管された製品数の最大値を取得して、最小限必要な容量の仕掛品置き場を決定することを特徴とする製造計画演算方法。
<Configuration 3>
In the manufacturing plan calculation method according to Configuration 2, the work in process place is defined as zero processing required time for the product, zero workers required for the process, and unlimited number of products that can be stored simultaneously, The time series data is generated, and the work-in-process storage area used for storage and the maximum number of products stored in the work-in-process storage area are acquired during any process, and the minimum required capacity is obtained. A manufacturing plan calculation method characterized by determining a work-in-process storage area.

〈構成4〉
構成1乃至3のいずれかに記載の製造計画演算方法において、製造を開始していない製品と、既に製造が開始された製品とを前記製品のリストに混在させたことを特徴とする製造計画演算方法。
<Configuration 4>
4. The manufacturing plan calculation method according to any one of configurations 1 to 3, wherein a product that has not been manufactured and a product that has already been manufactured are mixed in the product list. Method.

〈構成5〉
構成1乃至4のいずれかに記載の製造計画演算方法において、前記工程データには、その工程で作業可能な作業者を指定する作業者コードと、作業者毎の加工所要時間を示すデータを含めたことを特徴とする製造計画演算方法。
<Configuration 5>
In the manufacturing plan calculation method according to any one of Configurations 1 to 4, the process data includes an operator code for specifying an operator who can work in the process and data indicating a processing time required for each operator. A manufacturing plan calculation method characterized by that.

〈構成6〉
構成1乃至5のいずれかに記載の製造計画演算方法において、前記最適化手段は、全ての工程に必要十分な数の作業者を割り付けて前記演算処理を実行し、同時に稼働する作業者数の最大値を求めて、前記生産計画データに含めることを特徴とする製造計画演算方法。
<Configuration 6>
In the manufacturing plan calculation method according to any one of the configurations 1 to 5, the optimization unit allocates a sufficient number of workers necessary for all the processes, executes the calculation process, and calculates the number of workers operating simultaneously. A manufacturing plan calculation method characterized in that a maximum value is obtained and included in the production plan data.

〈構成7〉
構成1乃至6のいずれかに記載の製造計画演算方法において、作業者が不足して作業者の割り付けを待つ工程を生じさせるように、前記全作業者数Nの初期値を設定し、この全作業者数Nを変更した演算処理を繰り返して、前記指定された期日までに製造を終了させることができる作業者数の最小値を求めることを特徴とする製造計画演算方法。
<Configuration 7>
In the manufacturing plan calculation method according to any one of the configurations 1 to 6, an initial value of the total number of workers N is set so as to cause a process of waiting for worker assignment due to a shortage of workers. A manufacturing plan calculation method characterized in that a calculation value with a changed number of workers N is repeated to obtain a minimum value of the number of workers capable of finishing the manufacturing by the designated date.

〈構成8〉
いずれかの工程あるいは複数の全ての工程を、共通に利用する複数種類の製品を製造する生産計画をコンピュータにより演算処理する装置であって、製造に従事することができる全作業者の識別コードと全作業者数Nを含む作業者データと、各工程について、その工程の識別コードと、製品毎の加工所要時間と、その工程に必要な作業者数と、その工程で同時に加工することができる製品の数とを含む工程データと、各製品の識別コードと、各製品の製造に必要な工程順とを含む製品データと、指定された期日までに製造を終了させる製品のリストとを記憶する記憶装置と、前記製品のリストから製品が順番に選択されたとき、前記製品データを参照して、前記各製品が前記工程順に前記選択順に各工程に受け入れられるように、各製品を各工程に割付け、前記工程データを参照して、前記作業者が必要な工程を検出して、前記全作業者を、前工程から後工程に向かって、もしくは後工程から前工程に向かって順番に、各工程に必要な作業者数を満たすように割付けて、作業者が不足した工程があったときは、最も早く終了する工程の終了を待って該当する作業者を割付けて、前記全ての工程に前記製品を割付けた状態を時系列的に配置し、前記作業者の割付け結果を含む生産計画データを生成する生産計画データ生成手段と、前記製品のリストから製品をランダムな順番に選択して、前記生産計画データ生成手段に前記生産計画データを生成させて、前記生成された生産計画データから最終工程終了時刻を検出し、その後、前記製品のリストから製品を選択する順番を変更して、前記生産計画データ生成手段に前記生産計画データを生成させるという処理を繰り返して、最も早い最終工程終了時刻を探索し、前記最も早い最終工程終了時刻が検出された生産計画データの、前記製品の選択順を固定して、前記作業者を前記工程に割付ける順番を変更して、前記生産計画データ生成手段に前記生産計画データを生成させるという処理を繰り返して、最も早い最終工程終了時刻が検出された生産計画データを、最適化された生産計画データとして出力する最適化手段を備えたことを特徴とする製造計画演算装置。
<Configuration 8>
An apparatus that performs computer processing on a production plan for manufacturing a plurality of types of products that commonly use any process or all of a plurality of processes, and an identification code for all workers who can engage in manufacturing Worker data including the total number of workers N, and for each process, the process identification code, the required processing time for each product, the number of workers required for the process, and the process can be processed simultaneously. Stores process data including the number of products, product data including the identification code for each product, the order of processes required for manufacturing each product, and a list of products that will be discontinued by a specified date When a product is selected in order from the storage device and the list of products, each product is referred to by referring to the product data so that each product is accepted in each step in the order of selection in the order of the process. Referring to the process data, the worker detects necessary processes and assigns all workers in order from the previous process to the subsequent process or from the subsequent process to the previous process. , Assigning the number of workers required for each process, and when there is a process with insufficient workers, wait for the end of the process to be completed earliest, assign the appropriate workers, and The product allocation state is arranged in chronological order, production plan data generation means for generating production plan data including the worker allocation results, and products in a random order are selected from the product list. , By causing the production plan data generating means to generate the production plan data, detecting a final process end time from the generated production plan data, and then changing the order of selecting products from the list of products, The process of generating the production plan data in the production plan data generation unit is repeated to search for the earliest final process end time, and the product selection of the production plan data in which the earliest final process end time is detected The order of fixing the order, changing the order in which the worker is assigned to the process, and repeating the process of generating the production plan data in the production plan data generating means, so that the earliest final process end time is detected. A production plan calculation device comprising an optimization means for outputting the production plan data as optimized production plan data.

〈構成9〉
コンピュータを、構成7に記載の各手段として機能させる製造計画演算プログラム。
<Configuration 9>
A manufacturing plan calculation program for causing a computer to function as each means described in Configuration 7.

〈構成10〉
コンピュータを、構成7に記載の各手段として機能させる製造計画演算プログラムを記録したコンピュータで読み取り可能な記録媒体。
<Configuration 10>
A computer-readable recording medium on which a manufacturing plan calculation program for causing a computer to function as each means described in Configuration 7 is recorded.

〈構成1の効果〉
複数種類の製品の各工程への投入順と作業者の割付けの組み合わせが非常に複雑になるケースであっても、最適化された生産計画をコンピュータにより高速演算処理できる。
〈構成2の効果〉
仕掛品置き場を設けることにより、生産計画をより効率良く最適化できるほか、必要最小限の仕掛品置き場を自動的に決定できる。
〈構成3の効果〉
仕掛品置き場を工程の一種と定義することにより、工程の割付け演算と同時に仕掛品置き場の割付け演算も可能になる。
〈構成4の効果〉
製造未着手の製品も製造が開始されて製造が中断した半製品も混在させて、生産計画の演算処理ができる。
〈構成5の効果〉
作業者の能力に応じて、同じ工程でも所要時間が相違することがある。この場合でも、自動計算を可能にする。
〈構成6の効果〉
作業者が不足する工程を全く無くした生産計画を生成できる。
〈構成7の効果〉
指定された期日までに製造を終了させることができれば、最小限の作業者を担当させるのが経済的な場合がある。その演算処理を実行することかできる。
<Effect of Configuration 1>
Even in cases where the combination of the order of introduction of multiple types of products into each process and the assignment of workers becomes very complicated, an optimized production plan can be processed at high speed by a computer.
<Effect of Configuration 2>
By providing a work-in-process storage area, the production plan can be optimized more efficiently and the minimum required work-in-process storage area can be automatically determined.
<Effect of Configuration 3>
By defining the work-in-process storage area as a kind of process, it is possible to perform the work-in-process storage area allocation calculation simultaneously with the process allocation calculation.
<Effect of Configuration 4>
Products that have not yet been manufactured can be mixed with semi-finished products that have been manufactured and suspended, and the production plan can be processed.
<Effect of Configuration 5>
Depending on the ability of the operator, the required time may be different even in the same process. Even in this case, automatic calculation is possible.
<Effect of Configuration 6>
It is possible to generate a production plan that completely eliminates the process that the operator lacks.
<Effect of Configuration 7>
If production can be completed by a specified date, it may be economical to have a minimum number of workers in charge. The calculation process can be executed.

本発明の実施に適する製造計画演算装置のブロック図である。It is a block diagram of the manufacturing plan calculating apparatus suitable for implementation of this invention. コンピュータのハードウエアブロック図である。It is a hardware block diagram of a computer. 記憶装置16に記憶されたデータの具体的な構成例説明図である。4 is an explanatory diagram illustrating a specific configuration example of data stored in a storage device 16; FIG. 実施例1のための製造工程の概要説明図である。FIG. 3 is a schematic explanatory diagram of a manufacturing process for Example 1. 工程データの具体例を示す説明図である。It is explanatory drawing which shows the specific example of process data. (a)は製品リストの比較例、(b)は製品リストの実施例である。(A) is a comparative example of a product list, and (b) is an example of a product list. 時系列割り付けデータの一例を示す説明図である。It is explanatory drawing which shows an example of time series allocation data. 最適化後の時系列割り付けデータの一例を示す説明図である。It is explanatory drawing which shows an example of the time series allocation data after optimization. 仕掛品置き場を設けた実施例の工程データ説明図である。It is process data explanatory drawing of the Example which provided the work-in-process place. 読み出し順を最適化した製品リストの実施例説明図である。It is an Example explanatory drawing of the product list which optimized reading order. 最適化後の時系列割り付けデータの一例を示す説明図である。It is explanatory drawing which shows an example of the time series allocation data after optimization. 既に一部製造が開始された製品が混在している場合の工程の概略図である。It is the schematic of the process in the case of the product from which some manufacture was already started being mixed. 工程データの主要部説明図である。It is principal part explanatory drawing of process data. 実施例3の場合の時系列割り付けデータで、(a)は改良前、(b)は改良後のものである。The time-series allocation data in the case of Example 3, where (a) is before improvement and (b) is after improvement. 出力された作業者シフトデータの実施例説明図である。It is Example explanatory drawing of the output worker shift data. 出力された生産計画データの実施例説明図である。It is Example explanatory drawing of the output production plan data. 本発明のシステムの概略動作を示すフローチャートである。It is a flowchart which shows schematic operation | movement of the system of this invention. 最適化手段の前段の探索処理動作フローチャートである。It is a search process operation | movement flowchart of the front | former stage of an optimization means. 最適化手段の後段の探索処理動作フローチャートである。It is a search process operation | movement flowchart of the latter part of an optimization means. 生産計画データ生成手段の動作フローチャートである。It is an operation | movement flowchart of a production plan data generation means.

本発明の製造計画演算装置は、例えば、複数種類の製品を、指定された期日までに製造する場合の計画作成に利用される。また、あるいは、複数種類の製品をできるだけ早く製造する場合の計画作成に利用される。さらに、最少限の作業者を効率良く稼働させる計画作成に利用される。製品は、例えば、住宅建設用の建具、階段、収納等の部材である。各製品は、それぞれ一定の工程順に製造される。工程は、例えば、切断、組立、塗装、検査等の工程である。   The production plan calculation device of the present invention is used, for example, for creating a plan when a plurality of types of products are produced by a designated date. Alternatively, it is used for creating a plan when manufacturing a plurality of types of products as soon as possible. Furthermore, it is used to create a plan for efficiently operating the minimum number of workers. The product is, for example, a member such as a fitting for building a house, a staircase, or a storage. Each product is manufactured in a certain process order. The processes are, for example, processes such as cutting, assembly, painting, and inspection.

切断工程には、材料を指定された形状に切断したり孔を開けたりする設備が設けられている。組立工程には、例えば、ねじ締めや接着等のための設備が設けられている。これらの工程には、例えば、最低1名の作業者が割り付けられる。塗装工程では、前工程から集められた製品を受け入れて、塗料を噴霧し乾燥させる設備が設けられている。この工程は例えば、複数の製品を一括して全自動で加工する。作業者は要らない。検査工程では、例えば、最低1名の作業者が所定の完成検査を行う。   In the cutting process, equipment for cutting a material into a specified shape or opening a hole is provided. In the assembling process, for example, facilities for screw tightening and adhesion are provided. For example, at least one worker is assigned to these processes. In the painting process, facilities for receiving products collected from the previous process and spraying and drying the paint are provided. In this step, for example, a plurality of products are processed fully automatically. No workers are needed. In the inspection process, for example, at least one worker performs a predetermined completion inspection.

上記のような各工程では、複数種類の製品を、それぞれ設計書に基づいて加工することができる。即ち、種類の異なる各製品が、いずれかの工程あるいは複数の全ての工程を共通に利用することができる。例えば、製品毎に加工内容が異なり、作業時間が異なっていても、同じ作業者が同じ工具を使用して作業をする。   In each process as described above, a plurality of types of products can be processed based on design documents. That is, different types of products can use any process or all the processes in common. For example, even if the processing contents are different for each product and the working time is different, the same worker works using the same tool.

こうした工程を利用して複数の製品を製造する場合の、具体的な製品の時間的な流れを示したものが生産計画データである。この生産計画データを自動的に生成する場合には、予め、計算のための条件をコンピュータに入力する。製造に従事することができる全作業者数は、例えばN(正の整数)で一定とする。指定された期日まで常にN名の作業者を確保することを前提として、生産計画データを生成する。   Production plan data shows a specific time flow of a product when a plurality of products are manufactured using such a process. In order to automatically generate the production plan data, conditions for calculation are input to the computer in advance. The total number of workers who can be engaged in manufacturing is, for example, N (a positive integer) and is constant. Production plan data is generated on the premise that N workers are always secured until a designated date.

単一種類の製品を複数個製造する場合には、各製品を順番に一個ずつ、最初の工程から加工していけばよい。各工程での加工作業が最適化されていれば、製品毎の加工順は製造終了時刻に全く影響しない。しかしながら、複数種類の製品が混在すれば、各製品を工程に投入する順番を変えると、製造終了時間が変わる。本発明では、そのうちの最も早く製造が終了する順番を探索して、生産計画データを生成する。   When a plurality of single-type products are manufactured, each product may be processed in order from the first step. If the processing operations in each process are optimized, the processing order for each product has no influence on the production end time. However, if a plurality of types of products are mixed, the production end time changes if the order in which each product is put into the process is changed. In the present invention, the production order data is generated by searching for the order in which the production ends most quickly.

さらに、全ての工程に必要十分な作業者を配置すれば、いずれの製品もある工程から次の工程に進むときに、無駄な待ち時間を生じない。しかしながら、各工程の終了タイミングはまちまちだから、各工程を担当する作業者の待ち時間が生じる。従って、全ての工程に必要十分な作業者を配置するのは必ずしも経済的でない。工程に投入する全作業者数Nが必要十分な数に不足している場合には、どのタイミングでどこに作業者を配置するかによって、全体としての効率が変わり、製造終了時刻も変わる。   Furthermore, if necessary and sufficient workers are arranged in all processes, no wasteful waiting time is generated when any product proceeds from one process to the next process. However, since the end timing of each process varies, there is a waiting time for the worker in charge of each process. Therefore, it is not always economical to arrange necessary and sufficient workers for all processes. When the total number of workers N to be put into the process is insufficient and necessary, the efficiency as a whole changes depending on when and where the workers are arranged, and the production end time also changes.

本発明では、各製品を工程に投入する順番を最適化しつつ、作業者の配置の最適化を図り、必要十分な作業者数よりも少ない作業者を効率良く利用して生産計画データを生成する。そのために、以下のようにコンピュータのプログラムとデータを設定して、以下のような手順で演算処理を実行する。   In the present invention, while optimizing the order in which each product is put into the process, the arrangement of workers is optimized, and production plan data is generated by efficiently using fewer workers than the necessary and sufficient number of workers. . For this purpose, a computer program and data are set as follows, and arithmetic processing is executed in the following procedure.

(ハードウエア)
図1は、本発明の実施に適する製造計画演算装置のブロック図である。
本発明の製造計画演算装置12は、図のように1台のコンピュータにより実現する。図において、このコンピュータには、演算処理を実行する本体制御部3のほかに、ディスプレイ2、キーボード4、マウス5といったマンマシンインタフェース用ハードウエアが設けられている。ディスプレイ2はコンピュータで処理をした結果を出力するための任意の構成の表示出力装置である。ブラウン管ディスプレイ、液晶ディスプレイ、プロジェクタ等が利用できる。キーボード4やマウス5はコンピュータに指示を入力するための装置である。これらのマンマシンインタフェース用ハードウエアは、全て既知のものを使用することができるので、図示および各機能の具体的な説明は省略する。
(Hardware)
FIG. 1 is a block diagram of a manufacturing plan calculation apparatus suitable for implementing the present invention.
The manufacturing plan calculation device 12 of the present invention is realized by a single computer as shown in the figure. In the figure, this computer is provided with man-machine interface hardware such as a display 2, a keyboard 4, and a mouse 5 in addition to a main body control unit 3 that executes arithmetic processing. The display 2 is a display output device having an arbitrary configuration for outputting a result of processing by a computer. CRT displays, liquid crystal displays, projectors, etc. can be used. A keyboard 4 and a mouse 5 are devices for inputting instructions to the computer. Since all of these man-machine interface hardware can be used, illustration and specific description of each function are omitted.

図2はコンピュータのハードウエアブロック図である。
コンピュータの本体制御部3の中で、内部バス110には、CPU(中央処理装置)111と、ROM(リードオンリメモリ)112と、RAM(ランダムアクセスメモリ)113と、HDD(ハードディスク)114と、入出力インタフェース115が接続されている。入出力インタフェース115には、ディスプレイ2とキーボード4とマウス5が接続されている。
FIG. 2 is a hardware block diagram of the computer.
In the main body controller 3 of the computer, an internal bus 110 includes a CPU (Central Processing Unit) 111, a ROM (Read Only Memory) 112, a RAM (Random Access Memory) 113, an HDD (Hard Disk) 114, An input / output interface 115 is connected. A display 2, a keyboard 4, and a mouse 5 are connected to the input / output interface 115.

図1に示した記憶装置16は、ROM112やRAM113やHDD114により構成される。図1に示した演算処理装置14は、CPU111、ROM112、RAM113等により構成される。各種のデータは主としてHDD114に記憶されて保存される。CPU111が実行するコンピュータプログラムは、ROM112に記憶され、あるいはRAM113に適時ロードされる。   The storage device 16 illustrated in FIG. 1 includes a ROM 112, a RAM 113, and an HDD 114. The arithmetic processing unit 14 illustrated in FIG. 1 includes a CPU 111, a ROM 112, a RAM 113, and the like. Various data are mainly stored and stored in the HDD 114. A computer program executed by the CPU 111 is stored in the ROM 112 or loaded into the RAM 113 as appropriate.

上記のコンピュータは、図1に示すように、演算処理装置14と記憶装置16を備える。コンピュータの演算処理装置14は、図のように、生産計画データ生成手段36、最適化手段38、仕掛品置き場決定手段40等のコンピュータプログラムモジュールにより構成される。コンピュータは、予めインストールされたコンピュータプログラムを実行することにより、所定のタイミングで、演算処理装置14を構成する各手段として機能する。コンピュータは、このコンピュータプログラムの実行中に、記憶装置16を使用して、予め記憶された必要なデータを読み取る。またあるいは、新たなデータを記憶装置16に書き込んで記憶させる。   As shown in FIG. 1, the computer includes an arithmetic processing device 14 and a storage device 16. As shown in the figure, the computer processing unit 14 includes computer program modules such as a production plan data generation unit 36, an optimization unit 38, and a work-in-process storage place determination unit 40. The computer functions as each means constituting the arithmetic processing unit 14 at a predetermined timing by executing a computer program installed in advance. During execution of this computer program, the computer uses the storage device 16 to read necessary data stored in advance. Alternatively, new data is written and stored in the storage device 16.

(使用するデータ)
図3は、記憶装置16に記憶されたデータの具体的な構成例説明図である。
記憶装置16(図1)には、作業者データ18と、工程データ20と、製品データ22と、製品リスト24とを記憶させておく。作業者データ18は、製造に従事することができる全作業者の識別コード42と全作業者数(N)44を含む。作業者数Nは、全ての工程に割り付けるのに十分な数とは限らない。作業者の無駄な待ち時間を減らして、作業者を効率良く利用するために、Nは必要十分な作業者数以下の数に選定する。
(Data used)
FIG. 3 is an explanatory diagram of a specific configuration example of data stored in the storage device 16.
The storage device 16 (FIG. 1) stores worker data 18, process data 20, product data 22, and a product list 24. The worker data 18 includes an identification code 42 and a total number of workers (N) 44 of all workers who can engage in manufacturing. The number of workers N is not necessarily a number that is sufficient to assign to all processes. In order to reduce the worker's useless waiting time and efficiently use the worker, N is selected to be a number equal to or less than the necessary and sufficient number of workers.

全ての工程に必要十分な数の作業者を割り付けたときに、同時に稼働する作業者数の最大値を求めれば、作業者が不足して作業者の割り付けを待つ工程を無くすことができる。また、さらに少ない作業者で、作業者の割り付けを待つ工程があっても、要求された作業終了時刻を満たす生産計画を生成できる。作業者数を変更して上記の演算処理を繰り返すと、必要最小限の作業者数を求めることができる。この演算処理は最適化手段38が実行し、その結果は、生産計画データ28に含めて出力されるとよい。なお、作業者に能力差があるような場合には、割り付けられた作業者毎に、各工程の加工時間が異なってくる。これを考慮した最適化もできる。このときは、作業者をランク付けした評価データを作業者データ18に含めるとよい。評価データは、工程毎の加工所要時間の割り増し率等になる。   When a necessary and sufficient number of workers are assigned to all the processes, if a maximum value of the number of workers operating simultaneously is obtained, the process of waiting for worker assignment due to lack of workers can be eliminated. In addition, even when there is a process of waiting for worker assignment with fewer workers, a production plan that satisfies the requested work end time can be generated. When the number of workers is changed and the above calculation process is repeated, the minimum number of workers can be obtained. This calculation process is executed by the optimization means 38, and the result is preferably included in the production plan data 28 and output. In addition, when there is a capability difference among workers, the processing time of each process differs for each assigned worker. Optimization that takes this into account is also possible. At this time, the worker data 18 may include evaluation data ranking the workers. The evaluation data is an extra rate of processing time for each process.

工程データ20は、各工程について、その工程の識別コード46と、製品毎の加工所要時間48と、その工程に必要な作業者数50と、その工程で同時に加工することができる製品の数52とを含む。同じ工程でも、製品の種類により所要時間が異なる。この所要時間が、各製品を前工程から受け入れ、後工程に送るタイミングを決定する重要なパラメータになる。なお、説明を簡単にするために、工程間の製品の搬送時間は省略した。さらに、場合により必要になる段取替え時間も省略した。また、製品を複数同時に加工することができる工程では、例えば、製品が3個揃わなければ加工を開始させない工程や、製品を3個以上6個まで同時に加工でき、指定されたタイミングで加工を開始するといった工程も含まれていて構わない。   The process data 20 includes, for each process, the process identification code 46, the required processing time 48 for each product, the number of workers 50 required for the process, and the number 52 of products that can be processed simultaneously in the process. Including. Even in the same process, the time required varies depending on the type of product. This required time becomes an important parameter for determining the timing of receiving each product from the previous process and sending it to the subsequent process. In addition, in order to simplify description, the conveyance time of the product between processes was abbreviate | omitted. Furthermore, the setup change time which is necessary in some cases is omitted. In addition, in a process that can process multiple products at the same time, for example, a process that does not start unless three products are available, or three or more products can be processed simultaneously, and processing starts at a specified timing. The process of doing may be included.

製品データ22は、各製品の識別識別コード54と、各製品の製造に必要な工程順56とを含む。各製品は必ずこの工程順に各工程に送り込まれる。なお、全ての工程を経て完成したものが製品であって、その前工程のものは仕掛品とか半製品と呼ぶべきであるが、本発明の説明を進める上で支障が無いので、全て製品と呼んで説明をすすめる。   The product data 22 includes an identification code 54 for each product and a process order 56 necessary for manufacturing each product. Each product is always sent to each process in this order. In addition, what is completed through all the steps is a product, and those in the previous step should be called work-in-process or semi-finished products, but since there is no problem in proceeding with the explanation of the present invention, all products and Call for explanation.

製品リスト24は、指定された期日までに製造を終了させる製品の製品識別コード54を列挙したものである。製造対象には、例えば、製品A、B、Cという3種類の製品が含まれる。製品Aは5個、製品Bは3個、製品Cは3個とする。各製品は、それぞれの工程に別々に投入され、これらの製品がどの工程に存在するかを常に意識する必要があるので、製品識別コードに工程投入順を示す数字を付加して、全ての製品を区別できるようにしておく。その例は、図4等で説明する。製品リスト24は、このほかに、製造終了期日60も含む。   The product list 24 is a list of product identification codes 54 of products whose production is finished by a designated date. The manufacturing target includes, for example, three types of products A, B, and C. Assume that product A is 5, product B is 3, and product C is 3. Each product is input separately in each process, and it is necessary to always be aware of which process these products exist in. Therefore, a number indicating the process input order is added to the product identification code, and all products are added. To be able to distinguish. An example of this will be described with reference to FIG. In addition to this, the product list 24 also includes a production end date 60.

(手段(プログラムモジュール)の説明)
次に、演算処理装置の各手段について説明する。生産計画データ生成手段36は、与えられた条件で、具体的な生産計画を生成する機能を持つ。最適化手段38は、生産計画データ生成手段36に与える条件を変更して、生産計画データ生成手段36に繰り返し演算処理をさせ、最適値を探索する機能を持つ。仕掛品置き場決定手段40は、生成された生産計画データから、不用な仕掛品置き場を除去して、最適値を求める機能を持つ。
(Description of means (program module))
Next, each means of the arithmetic processing unit will be described. The production plan data generating unit 36 has a function of generating a specific production plan under given conditions. The optimization unit 38 has a function of changing the conditions to be given to the production plan data generation unit 36, causing the production plan data generation unit 36 to repeatedly perform arithmetic processing, and searching for an optimum value. The work-in-process storage location determining means 40 has a function of obtaining an optimum value by removing unnecessary work-in-process storage space from the generated production plan data.

即ち、生産計画データ生成手段36は、始めに、製品リスト24を記憶装置16から読み出す。製品リスト24は、指定された期日までに製造を終了させる製品をリストアップしたものである。製品リスト24から読み出す製品識別コード54の順番を、最適化手段38が決定する。即ち、最適化手段38は、製品リスト24から所定の順番に製品識別コード54を選択して読み出し、生産計画データ生成手段36に渡す。生産計画データ生成手段36は、読み出された製品識別コード54とコードが一致する製品の製品データ22を参照して、各製品が、必要工程順56に示された各工程に順次受け入れられるように、各製品を各工程に割付ける。   That is, the production plan data generation unit 36 first reads the product list 24 from the storage device 16. The product list 24 is a list of products whose production is finished by a designated date. The optimization unit 38 determines the order of the product identification codes 54 read from the product list 24. That is, the optimization unit 38 selects and reads the product identification codes 54 from the product list 24 in a predetermined order and passes them to the production plan data generation unit 36. The production plan data generation means 36 refers to the product data 22 of the product whose code matches the read product identification code 54 so that each product is sequentially accepted in each process shown in the necessary process order 56. Each product is assigned to each process.

続いて、作業者の割り付けを行う。工程毎に、記憶装置16に記憶された該当する工程識別コード46の工程データ20を参照して、必要作業者数50が「0」でない工程を検出する。そして、全作業者を、一定の規則で一定の順に割り付ける。例えば、時間軸上で同時進行する工程を検出し、後工程から前工程に向かって順番に、各工程に最小限必要な作業者数を満たすように割付けていく。作業者が不足した工程が残ったときは、工程での作業が終了した作業者を待って、該当する作業者を割付ける。前工程から後工程に向かって順番に割り付けをするようにしても構わない。割り付けの優先順位に一定のルールを設けておく。製品識別コード54を一つずつ読み出し、時系列割り付けを実行し、作業者を割付けるという処理を繰り返して時系列割り付けデータ26を生成する。   Subsequently, workers are assigned. For each process, the process data 20 of the corresponding process identification code 46 stored in the storage device 16 is referenced to detect a process in which the required number of workers 50 is not “0”. All workers are assigned in a certain order according to certain rules. For example, the processes that proceed simultaneously on the time axis are detected and assigned in order from the subsequent process to the previous process so as to satisfy the minimum number of workers required for each process. When a process with insufficient workers remains, the process waits for the worker who has finished the work in the process and assigns the corresponding worker. You may make it allocate in order toward a back process from a pre-process. A certain rule is set for the priority of allocation. The product identification code 54 is read one by one, time series assignment is executed, and the process of assigning workers is repeated to generate time series assignment data 26.

生産計画データ生成手段36は、こうして、全ての工程に製品を割付けた状態を時系列的に配置し、作業者の割付け結果を含む時系列割り付けデータ26を生成する。時系列割り付けデータ26の具体例は後で説明する。最適化手段38は、例えば、毎回乱数を発生して、製品リスト24から製品識別コード54を読み出す製品データ読み取り順32を決定して、生産計画データ生成手段36に渡す。その処理を繰り返す。即ち、生産計画データ生成手段36に対して、ランダムな順番に選択した製品を、その順番に工程に割付けさせて、時系列割り付けデータ26を繰り返し生成させる。その結果から、全ての製品の製造が終了する製造終了期日60よりも早く、かつ、最も早い最終工程終了時刻30を探索する。   In this way, the production plan data generation means 36 arranges the state where the products are allocated to all the processes in time series, and generates the time series allocation data 26 including the worker allocation results. A specific example of the time series allocation data 26 will be described later. For example, the optimization unit 38 generates a random number every time, determines the product data reading order 32 for reading the product identification code 54 from the product list 24, and passes it to the production plan data generation unit 36. Repeat the process. That is, the production plan data generation unit 36 assigns products selected in a random order to processes in that order, and repeatedly generates time-series allocation data 26. From the result, the last process end time 30 that is earlier than the manufacturing end date 60 at which the manufacture of all the products ends and is earliest is searched.

即ち、最適化手段38は、生成された時系列割り付けデータ26から最終工程終了時刻30を検出し、その後、製品リスト24から識別コード54を読み出す製品データ読み取り順32を変更して、生産計画データ生成手段36に新たな時系列割り付けデータ26を生成させるという処理を繰り返す。このとき、例えば、山登り法や焼き鈍し法等の既知の様々な探索方法を利用して、最適値の探索を実行する。   That is, the optimizing means 38 detects the final process end time 30 from the generated time series allocation data 26, and then changes the product data reading order 32 for reading the identification code 54 from the product list 24, thereby producing the production plan data. The process of causing the generation means 36 to generate new time series allocation data 26 is repeated. At this time, for example, a search for an optimum value is performed using various known search methods such as a hill-climbing method and an annealing method.

ここで、最も早い最終工程終了時刻30が検出された時系列割り付けデータ26の、製品の選択順を固定する。そして、今度は、作業者を工程に割付ける、作業者割付け順を変更して、生産計画データ生成手段36に時系列割り付けデータ26を生成させるという処理を繰り返す。この場合にも、山登り法や焼き鈍し法等の方法で、前記指定期日よりも早く、かつ、最も早い最終工程終了時刻30を探索する。こうして、最適化された時系列割り付けデータ26を含む生産計画データ28を生成する。なお、生産計画データ28には時系列割り付けデータ26と、作業者割り付け順34を示すデータや作業者への指示書その他、実際の生産開始時に必要な各種資料の印刷用データが含まれるものとする。
以下、本発明の実施の形態を実施例毎に詳細に説明する。
Here, the product selection order of the time-series allocation data 26 in which the earliest final process end time 30 is detected is fixed. Then, this time, the process of assigning workers to processes, changing the worker assignment order, and causing the production plan data generation means 36 to generate the time-series assignment data 26 is repeated. Also in this case, the earliest final process end time 30 that is earlier than the designated date and by the method such as the hill climbing method or the annealing method is searched. In this way, production plan data 28 including the optimized time series allocation data 26 is generated. The production plan data 28 includes time-series allocation data 26, data indicating the worker allocation order 34, instructions to the workers, and other data for printing various materials necessary at the start of actual production. To do.
Hereinafter, embodiments of the present invention will be described in detail for each example.

図4は実施例1のための製造工程の概要説明図である。図5は工程データの説明図である。
図4に示すように、予定した製品を製造するために、A工程からG工程までの合計7つの工程が設けられている。A工程とC工程とG工程とは人作業であり、図5に示すように、作業者1名を必要とする。B工程は自動的に製品を加工する加工機である。D工程とF工程とは、3個の製品を次の工程への投入に備えて待機させることができるスペースである。製造する製品は2種類である。製品AA1、AA2をそれぞれ6個ずつ製造する。全ての製品の製造終了期日60(図3)は全て同一とする。全工程で必要な作業者は3名であるが、実働できる作業者は2名とする。
FIG. 4 is a schematic explanatory diagram of a manufacturing process for the first embodiment. FIG. 5 is an explanatory diagram of process data.
As shown in FIG. 4, in order to manufacture the planned product, a total of seven steps from the A step to the G step are provided. The A process, the C process, and the G process are manual operations, and require one worker as shown in FIG. B process is a processing machine which processes a product automatically. The D process and the F process are spaces in which three products can be put on standby in preparation for the next process. There are two types of products to be manufactured. Six products AA1 and AA2 are manufactured. The production end dates 60 (FIG. 3) of all products are all the same. The number of workers required in all processes is three, but the number of workers who can actually work is two.

なお、作業者を必要とする工程において、着手した加工は必ず完了させるものとする。また、B工程とE工程とは3個の製品が揃わないと加工を開始しない。3個の製品を投入すると加工を開始して、加工後の3個の製品を取り出さないと、次の製品を投入できない。また、説明を簡単にするために、搬送時間や段取り替え時間等の中継ぎ的な作業時間は省略する。製品AA1とAA2の製品データでは、いずれも、必要工程順56(図3)が、A−B−C−D−E−F−Gとされているものとする。   In addition, in the process that requires an operator, the processing that has been started is surely completed. Further, the process B and the process E are not started unless three products are prepared. If three products are thrown in, processing starts and the next three products cannot be thrown in unless the three products after machining are taken out. In order to simplify the description, intermediate work time such as transfer time and setup change time is omitted. In the product data of the products AA1 and AA2, it is assumed that the necessary process order 56 (FIG. 3) is A-B-C-D-E-F-G.

図5は、工程データの具体例を示す説明図である。
図に示すように、A工程からG工程まで、それぞれ、製品AA1とAA2の製品毎加工所要時間48(作業時間の欄)と、必要作業者数50とが表示されている。また、備考の部分には、同時加工製品数52が表示されている。なお、「ワーク」というのは、加工中の仕掛品のことである。この図表の右端の一個あたり作業時間という欄には、一個あたりの作業時間の平均値を示した。
FIG. 5 is an explanatory diagram showing a specific example of process data.
As shown in the figure, the machining required time 48 (working time column) for each product AA1 and AA2 and the required number of workers 50 are displayed from the A process to the G process, respectively. In the remarks portion, the number 52 of simultaneously processed products is displayed. The “workpiece” is a work in progress during processing. In the column of work time per piece at the right end of this chart, the average value of work time per piece is shown.

図6の(a)は製品リストの比較例、(b)は製品リストの実施例であって、読み出し順に製品識別コードが配列されている。
図の(a)において、製品はAA1とAA2の2種類であって、製品AA1を6個続けて生産し、その後製品AA2を6個続けて生産するように、製品識別コードが配列されている。ここで、同じ製品でそれぞれ別々の順番に工程に投入されるものを区別するために、投入順に連番を付した。この連番は、製品識別コードに付加されるとよい。これらの製品はどの順番に製造されても構わない。そこで、実施例では、製造する順番を入れ替えて、より早く製造が終了する条件を探索する。なお、製造終了期日60は、例えば、この図のリストの属性データに含められる。
6A is a comparative example of the product list, and FIG. 6B is an example of the product list. Product identification codes are arranged in the order of reading.
In FIG. 5A, there are two types of products, AA1 and AA2, and product identification codes are arranged so that six products AA1 are produced in succession and then six products AA2 are produced in succession. . Here, in order to distinguish the same products that are input into the process in different orders, serial numbers are given in the order of input. This serial number may be added to the product identification code. These products may be manufactured in any order. Therefore, in the embodiment, the order of manufacturing is changed, and a condition for ending manufacturing earlier is searched. The production end date 60 is included in, for example, the attribute data of the list in this figure.

(生産計画データ)
図7は、時系列割り付けデータの一例を示す説明図である。
これは、全ての工程に製品を割付けた状態を時系列的に配置したものである。即ち、例えば、最初の製品(製品識別コードはAA1)W1は、A工程での330秒の加工後に、B工程であとから続くW2、W3の加工が終了するのを待つ。始めから990秒後にW1、W2、W3が揃うと、B工程の120秒の加工が開始される。B工程の加工が終了すると、W1、W2、W3の順番に、それぞれC工程での330秒の加工が進められる。
(Production plan data)
FIG. 7 is an explanatory diagram showing an example of time-series allocation data.
This is a time-series arrangement of products assigned to all processes. That is, for example, the first product (product identification code is AA1) W1 waits for the processing of W2 and W3 to continue after the B process after 330 seconds of processing in the A process. When W1, W2, and W3 are ready after 990 seconds from the beginning, 120 seconds of processing in the B process is started. When the processing in the B process is completed, the processing for 330 seconds in the C process is advanced in the order of W1, W2, and W3.

W1は、C工程での加工後にD工程に保管されて、後から続くW2、W3の加工が終了するのを待つ。始めから2100秒後にW1、W2、W3のC工程の加工が終了すると、これらはD工程からE工程に送られて、E工程の780秒の加工が開始される。E工程の加工が終了すると、W1はすぐにG工程に投入される。W2、W3はF工程の仕掛品置き場で待機する。こうして全ての製品が順番にG工程で加工されて加工が終了すると、全作業が完了する。この例では、最終工程終了時刻は始めから6530秒後である。   W1 is stored in the D step after the processing in the C step, and waits for the subsequent processing of W2 and W3 to end. When the processing of the C process of W1, W2, and W3 is completed after 2100 seconds from the beginning, these are sent from the D process to the E process, and the processing of the E process of 780 seconds is started. When the processing in the E process is finished, W1 is immediately put into the G process. W2 and W3 stand by at the work-in-process storage area in the F process. In this way, when all the products are processed in the G process in order and the processing is completed, all the operations are completed. In this example, the final process end time is 6530 seconds after the start.

次に、各製品の工程への製品投入順の合理化による終了時刻の短縮について説明する。
図6(a)に示した製品投入順を初期値として、ランダムに2つの製品の投入順を入れ替える。そして、図6(b)に示したような新たな製品リストを得る。この順番に、次の演算処理を実行する。そして最終工程終了時刻を求める。先にした演算処理の結果得られた最終工程終了時刻30を、図1に示した記憶装置16に記憶しておく、そして、毎回演算処理をして、
その結果得られた最終工程終了時刻と比較する。
Next, shortening of the end time by rationalizing the order of product introduction into each product process will be described.
Using the product input order shown in FIG. 6A as an initial value, the input order of two products is randomly switched. Then, a new product list as shown in FIG. 6B is obtained. The following arithmetic processing is executed in this order. Then, the final process end time is obtained. The final process end time 30 obtained as a result of the previous arithmetic processing is stored in the storage device 16 shown in FIG. 1, and the arithmetic processing is performed each time.
The final process end time obtained as a result is compared.

最終工程終了時刻が減少したら採用し、減少しないときは採用しないという操作を繰り返し、最小終了時刻を求める。これは、山登り法と呼ばれる探索法である。山登り法は初期値の選び方により局所解を求めてしまう場合がある。従って、例えば、図6(a)のAA1とAA2とを入れ替えて初期値を変更して、ランダムに2つの製品の投入順を入れ替えるという処理を実行する。こうして繰り返し最小値を求めるとよい。   The operation is adopted when the final process end time decreases, and when the final process end time is not decreased, the operation of not adopting is repeated to obtain the minimum end time. This is a search method called a hill-climbing method. The hill-climbing method sometimes finds a local solution depending on how the initial value is selected. Therefore, for example, the process of changing the initial value by exchanging AA1 and AA2 in FIG. In this way, the minimum value may be obtained repeatedly.

(作業者の割付け)
次に、作業者の工程への割付け合理化による終了時刻の短縮について説明する。
上記の計算の結果、例えば、図6(b)に示す投入順で最小値が求められたものとする。今度は、この製品リストの製品読み出し順を固定したままで、作業者の各工程への割付け方法をランダムに変更する。
(Assignment of workers)
Next, shortening of the end time by rationalizing the allocation to the worker's process will be described.
As a result of the above calculation, for example, it is assumed that the minimum value is obtained in the order of input shown in FIG. This time, the assignment method to each process of the worker is randomly changed while the product reading order of the product list is fixed.

これまでは、時間軸上で同時進行する工程を検出し、後工程から前工程に向かって順番に、各工程に最小限必要な作業者数を満たすように割付けた。例えば、図7において、始めから2880秒後にG工程でW1の加工が開始され、その後順番にW2、W3が加工される。このW1の加工開始時には、A工程とC工程とG工程が同時に作業者を要求している。しかし、全作業者数は2名である。そこで、上記の一定の規則に従って、G工程とC工程に作業者を割り付けた。A工程では、W6を加工するC工程の終了を待って、W8の加工を開始した。   Until now, the process which progresses simultaneously on a time axis was detected, and it allocated so that the minimum number of workers required for each process might be satisfied in order from the post process to the previous process. For example, in FIG. 7, the processing of W1 is started in the G process after 2880 seconds from the beginning, and then W2 and W3 are processed in order. At the start of processing of W1, the A process, the C process, and the G process are requesting the worker at the same time. However, the total number of workers is two. Therefore, an operator was assigned to the G process and the C process in accordance with the above-mentioned fixed rule. In the A process, the process of W8 was started after the completion of the C process of processing W6.

従って、A工程は始めから3540秒後まで休止状態で、その後、W8の加工を開始している。しかしながら、例えば、始めから3230秒後、G工程を終えた作業者がA工程に移ってW8の加工を開始することもできる。このように、作業者の割り付けをランダムに入れ替えて、最終工程終了時刻が減少したら採用し、減少しないときは採用しないという操作を繰り返し、最小終了時刻を求める。   Therefore, the process A is in a pause state from the beginning until 3540 seconds, and then the processing of W8 is started. However, for example, after 3230 seconds from the beginning, the worker who finished the G process can move to the A process and start the processing of W8. In this way, the operator's assignment is changed at random, and when the final process end time is reduced, the operation is adopted, and when it is not reduced, the operation of not adopting is repeated to obtain the minimum end time.

図8は、最適化後の時系列割り付けデータの一例を示す説明図である。
上記の処理の結果、図7の割り付けを改善することができた。最終工程終了時刻では320秒(=6530−6210)短縮できた(短縮比5%)。なお、作業者の工程への割り付け順についても、初期値を変更して探索をすることで、局所解を求めてしまうのを避けることができる。この場合、製品投入順を最適化する処理で、最適解に近い解で最適解とは別の解を記憶装置に記憶させておけば、初期値を変更することができる。
FIG. 8 is an explanatory diagram illustrating an example of time-series allocation data after optimization.
As a result of the above processing, the allocation of FIG. 7 could be improved. 320 seconds (= 6530-6210) could be shortened at the end time of the final process (shortening ratio 5%). In addition, regarding the order of assignment to the processes of the workers, it is possible to avoid obtaining a local solution by searching by changing the initial value. In this case, the initial value can be changed if the storage device stores a solution different from the optimal solution that is close to the optimal solution in the process of optimizing the product input order.

また、最適化手段38が、全ての工程に必要十分な数の作業者を割り付けて上記の演算処理を実行し、同時に稼働する作業者数の最大値Nmaxを求めれば、作業者が不足する工程を全く無くした生産計画を生成できる。これは、全製品を最速で生産する結果に結びつく可能性か高い。一方、全作業者数Nの初期値をNmaxより少なく設定し、この全作業者数Nを変更した演算処理を繰り返せば、指定された期日までに製造を終了させることができる場合とできない場合とがわかる。指定された期日までに製造を終了させることができる、限界の作業者数Nが、適正な作業者数Nの最小値になる。最小限の作業者を担当させて、経済的な生産が可能になる。   In addition, if the optimization unit 38 allocates a sufficient number of workers for all processes and executes the above-described arithmetic processing, and obtains the maximum value Nmax of the number of workers operating at the same time, a process in which workers are insufficient. It is possible to generate a production plan that eliminates all of the above. This is likely to result in the fastest production of all products. On the other hand, if the initial value of the total number of workers N is set to be smaller than Nmax and the calculation process with the total number of workers N changed is repeated, the production can be completed and the case where it cannot be completed by the designated date. I understand. The limit number N of workers who can finish the production by the designated date becomes the minimum value of the appropriate number N of workers. Economic production is possible with the minimum number of workers.

図9は、仕掛品置き場を設けた実施例の工程データ説明図である。
この実施例では、工程間に仕掛品置き場を設けたときの、置き場容量の適正値を求める方法を説明する。これまでの実施例では、3個同時に加工をする工程であって、製品が加工を待機したり、次工程へ投入される前の待機のために、当初から十分と思われる仕掛品置き場を設定した。図4に示したE工程の前後のD工程とF工程がその例である。
FIG. 9 is an explanatory diagram of the process data of the embodiment in which the work-in-process storage area is provided.
In this embodiment, a method for obtaining an appropriate value for the storage capacity when a work-in-process storage space is provided between the processes will be described. In the examples so far, it is a process to process 3 pieces at the same time, and a work place storage place that seems to be sufficient from the beginning is set up to wait for the product to wait for processing or before being put into the next process did. Examples are the D process and F process before and after the E process shown in FIG.

一方、例えば、製品を1個ずつ加工する工程が連続しているとき、後工程で製品の加工中は、前工程で製品の加工を終えていても、製品を後工程に投入できない。このとき、前工程では、次に加工する製品が待機していても、加工を始めることができない。そのために工程間に仕掛品置き場を設ける。仕掛品置き場が十分にあればこの問題は無くなるが、工場の有効スペースを狭めるという問題がある。   On the other hand, for example, when the process of processing one product at a time is continuous, during the processing of the product in the subsequent process, the product cannot be put into the subsequent process even if the processing of the product is completed in the previous process. At this time, in the previous process, even if the product to be processed next is on standby, the process cannot be started. For this purpose, an in-process storage area is provided between the processes. This problem is eliminated if there is enough work in process storage, but there is a problem of reducing the effective space of the factory.

この実施例では、他の工程と同様の扱いで、任意に仕掛品置き場を設定して、上記の演算処理を実行する。製品の加工所要時間をゼロとし、その工程に必要な作業者数をゼロ、同時に保管できる製品数を無制限と定義する。仕掛品置き場では、次工程の受け入れ準備ができ次第次工程に製品を移す。A工程からB工程へ製品を最短時間で投入するという条件下で、B工程が終了前の場合は、B工程が終了するまで、製品をa工程に保持するという条件を設定して演算処理を実行する。   In this embodiment, in the same manner as in the other steps, the work in process place is arbitrarily set, and the above arithmetic processing is executed. The time required for processing a product is defined as zero, the number of workers required for the process is defined as zero, and the number of products that can be stored simultaneously is defined as unlimited. In the work in process storage area, the product is transferred to the next process as soon as it is ready for the next process. Under the condition that the product is introduced from the A process to the B process in the shortest time, if the B process is not completed, the condition is set to hold the product in the a process until the B process is completed. Execute.

上記の演算処理で、全ての工程間に十分な容量の仕掛品置場を仮配置して演算処理を実行したところ、A工程とB工程の間に最大2個の仕掛品を置く結果になった。そこで、図9の例では、例えば、A工程とB工程の間に、製品を2個置ける仕掛品置き場をa工程と設定した。即ち、十分な容量の仕掛品置場を仮配置して演算処理を実行することにより、いずれかの工程の間で、保管に使用された仕掛品置き場と、その仕掛品置き場に保管された製品数の最大値を取得して、最小限必要な容量の仕掛品置き場を決定することが可能になる。従って、工場のスペースを有効に利用して製品の製造ができる。   In the above calculation process, when the calculation process was executed by temporarily placing a work area with a sufficient capacity between all processes, the result was that a maximum of two work items were placed between process A and process B. . Therefore, in the example of FIG. 9, for example, the work-in-place storage place where two products can be placed between the A process and the B process is set as the a process. In other words, by temporarily allocating a work-in-process storage area with a sufficient capacity and executing calculation processing, the work-in-process storage area used for storage and the number of products stored in the work-in-process storage area during any of the processes It is possible to determine a work place storage area with a minimum necessary capacity by obtaining the maximum value of. Therefore, the product can be manufactured by effectively using the factory space.

図10は、読み出し順を最適化した製品リストの実施例説明図である。また、図11は、最適化後の時系列割り付けデータの一例を示す説明図である。
上記の演算処理の結果、図10示すような順番で製品を投入することで最適化が実現した。その結果、図11に示すように時系列割り付けデータが生成された。これを図7のものと比較したところ、最終工程終了時刻では830秒(=6530−5700)短縮できた(短縮比12.7%)。
FIG. 10 is an explanatory diagram of an embodiment of a product list in which the reading order is optimized. FIG. 11 is an explanatory diagram showing an example of time-series allocation data after optimization.
As a result of the above arithmetic processing, optimization was realized by putting products in the order shown in FIG. As a result, time-series allocation data was generated as shown in FIG. When this was compared with the thing of FIG. 7, it was shortened by 830 seconds (= 6530-5700) in the last process end time (shortening ratio 12.7%).

この時系列割り付けデータによれば、製造工程全体を最大効率で稼働させるために、どのタイミングでどれだけの製品がa工程で待機しているべきかがわかる。その最大値がa工程の仕掛品置き場の適正容量である。   According to this time-series allocation data, it is possible to know how many products should be waiting in the a process at which timing in order to operate the entire manufacturing process with maximum efficiency. The maximum value is the appropriate capacity of the work-in-process storage area in step a.

図12は、既に一部製造が開始された製品が混在している場合の工程の概略図で、図13は、工程データの主要部説明図である。
上記の実施例では、全ての製品が最初から製造を開始されるという前提で説明をした。しかしながら、未だ製造を開始していない製品と、既に製造が開始された状態の製品が混在していても、同様の演算処理が可能である。これは、最初に所定の生産計画で製造を開始した後に、例えば、一部の製品の納期が変更になったといった理由で生産計画を見直す場合にも有効である。
FIG. 12 is a schematic diagram of a process when products that have already been partially manufactured are mixed, and FIG. 13 is an explanatory diagram of a main part of process data.
In the above-described embodiment, description has been made on the assumption that all products are manufactured from the beginning. However, even if a product that has not yet been manufactured and a product that has already been manufactured are mixed, the same arithmetic processing is possible. This is also effective when reviewing a production plan for the reason that, for example, the delivery date of some products has been changed after starting production with a predetermined production plan for the first time.

図14は、実施例3の場合の時系列割り付けデータを示し、(a)は改良前、(b)は改良後のものである。
図12に示したように、現在、S工程にW1、B工程にW2、C工程にW3の製品が残っている状態で、作業者一人で、これらの加工作業を完了させるものとする。また、S工程の残加工時間が10秒で、C工程の残加工時間が0秒のタイミングとする。この場合には、C工程で加工を完了した製品をE工程に投入してすぐに加工を開始すると、待ち時間が最小になる。もし、D工程の置き場が無ければ、すぐにE工程を開始しなけれはならない。
FIG. 14 shows time-series allocation data in the case of Example 3, where (a) is before improvement and (b) is after improvement.
As shown in FIG. 12, it is assumed that one worker completes these machining operations with the products W1 remaining in the S step, W2 remaining in the B step, and W3 remaining in the C step. Further, the remaining machining time of the S process is 10 seconds, and the remaining machining time of the C process is 0 seconds. In this case, the waiting time is minimized if processing is started immediately after the product that has been processed in the C process is put into the E process. If there is no place for the D process, the E process must be started immediately.

しかしながら、作業者の割付けをS工程からA工程とすると、計算上最終工程終了時刻が早くなる。直前のC工程終了時に、続いて一人の作業者を割付ける工程の選択を変えるだけで、このように、最終工程終了時刻が変わる。また、C工程とE工程の間に、少なくとも1個の製品を置く仕掛品置き場が有効に機能すること、置き場に待機させることができる製品の数の最大値はこの場合は1であること等が、演算処理の結果判明する。   However, if the assignment of the worker is changed from the S process to the A process, the final process end time is calculated earlier. At the end of the immediately preceding C process, the final process end time changes in this way simply by changing the selection of the process for assigning one worker. In addition, the work-in-process storage place where at least one product is placed between the C process and the E process functions effectively, and the maximum number of products that can be kept in the storage place is 1 in this case, etc. However, the result of the arithmetic processing is revealed.

図15は出力された作業者シフトデータの実施例説明図である。図16は、出力された生産計画データの実施例説明図である。
図15に示すように、各作業者には、それぞれ作業者名と、どの工程の作業を何時から何時まで処理するか、各工程では、どの製品を加工するかといった内容の指示をリストアップした帳票を出力する。また、管理者に対して、図16に示すように、何時から何時までどの工程でとはの作業者がどの製品を加工するかが一覧表で見えるようにして、生産計画データが生成される。いずれの出力も、上記の時系列割り付けデータを使用して生成できる。
FIG. 15 is an explanatory diagram of an example of the output worker shift data. FIG. 16 is an explanatory diagram of an embodiment of the output production plan data.
As shown in FIG. 15, each worker is listed with the name of the worker, instructions on what process to process from what time to what time, and what product to process in each process. Output a form. Further, as shown in FIG. 16, the production plan data is generated so that the manager can see which product is processed by which worker in what process from what time to what time. . Either output can be generated using the time series allocation data described above.

図17は本発明のシステムの概略動作を示すフローチャートである。
以下、上記の演算処理を実行するための具体的なプログラムフローチャート例を説明する。図17において、予めステップS11で、演算処理条件を設定する。具体的には、オペレータが作業者データ18、工程データ20、製品データ22、製品リスト24等のデータを初期値として記憶装置にセットする。記憶装置16がこれらのデータを受け入れた後に、生産計画データ生成手段36と最適化手段38が起動する。生産計画データ生成手段36と最適化手段38は、ステップS12で、生産計画の最適化のための演算処理を実行する。これにより、生産計画データ28が生成される。
FIG. 17 is a flowchart showing a schematic operation of the system of the present invention.
Hereinafter, a specific example of a program flowchart for executing the above arithmetic processing will be described. In FIG. 17, calculation processing conditions are set in advance in step S11. Specifically, the operator sets data such as worker data 18, process data 20, product data 22, and product list 24 as initial values in the storage device. After the storage device 16 accepts these data, the production plan data generation means 36 and the optimization means 38 are activated. In step S12, the production plan data generation unit 36 and the optimization unit 38 execute a calculation process for optimizing the production plan. As a result, production plan data 28 is generated.

ステップS13では、生成された生産計画データ28を出力してよいかどうか評価をする。この評価は、最終工程終了時刻30が、指定納期を満たすかどうかの判断になる。指定納期を満たさないときは、ステップS11の処理に戻って条件設定をやりなおす。指定納期を満たすときはステップS15の処理に移行する。   In step S13, it is evaluated whether or not the generated production plan data 28 may be output. This evaluation is a judgment as to whether or not the final process end time 30 satisfies the specified delivery date. If the specified delivery date is not satisfied, the process returns to step S11 and the conditions are set again. When the designated delivery date is satisfied, the process proceeds to step S15.

ステップS15では、仕掛品置き場決定手段40が、生産計画データ28に含まれた余剰の仕掛品置き場を削除して、仕掛品置場容量を決定する。ステップS16では、生成された生産計画データ28出力をする。生産計画データ28は、例えば、図15に示した内容で、プリンタ116(図2)により印刷出力される。ステップS17では、作業者シフトデータの出力をする。作業者シフトデータは、例えば、図16に示した内容で、プリンタ116(図2)により印刷出力される。   In step S15, the work-in-process storage place determination means 40 deletes the surplus work-in-process storage place included in the production plan data 28 and determines the work-in-process storage capacity. In step S16, the generated production plan data 28 is output. The production plan data 28 is printed out by the printer 116 (FIG. 2) with the content shown in FIG. 15, for example. In step S17, worker shift data is output. The worker shift data is printed out by the printer 116 (FIG. 2) with the contents shown in FIG. 16, for example.

図18は、最適化手段の前段処理動作フローチャートである。
前段処理では、製品の投入順をランダムに変更して、最適値を探索する。後段処理では製品の投入順を固定したまま、作業者の割付け順をランダムに変更して最適値を探索する。図18ではその前段処理の説明をする。また、図19では、後段処理の説明をする。
FIG. 18 is a flowchart of the pre-processing operation of the optimization unit.
In the pre-stage process, the optimum value is searched by changing the order of product introduction at random. In the subsequent process, the optimal order value is searched by changing the worker assignment order at random while keeping the product input order fixed. In FIG. 18, the pre-processing will be described. Further, in FIG. 19, the post-processing will be described.

図18のステップS21では、最適化手段38が、記憶装置から作業者データ18と工程データ20と製品データ22を読み取ってその受付けをする。ステップS22では、作業者割付順を、上記のように、後工程優先といった一定ルールに固定する。ステップS23では、製品の投入順(製品データ読み取り順32)の初期値を設定する。ここで乱数を使用するとよい。ステップS24では、生産計画データ生成手段36を起動して、演算処理を実行させる。その具体例は図20で説明する。ステップS25では、最適化手段38が生産計画データ生成手段36の演算処理結果を受け取って、最終工程終了時刻30の記憶をする。   In step S21 of FIG. 18, the optimization means 38 reads the worker data 18, the process data 20, and the product data 22 from the storage device and accepts them. In step S22, the worker assignment order is fixed to a certain rule such as priority on the post-process as described above. In step S23, the initial value of the product input order (product data reading order 32) is set. A random number should be used here. In step S24, the production plan data generation means 36 is activated to execute arithmetic processing. A specific example will be described with reference to FIG. In step S25, the optimization means 38 receives the calculation processing result of the production plan data generation means 36 and stores the final process end time 30.

ステップS26では、製品の投入順(製品データ読み取り順32)を変更をする。ステップS27では、再び生産計画データ生成手段36を起動して、演算処理を実行させる。ステップS28では、最適化手段38が生産計画データ生成手段36の演算処理結果を受け取って、新たな最終工程終了時刻と記憶装置16に記憶した最終工程終了時刻30とを比較する。そして、最終工程終了時刻が短縮されたかどうかという判断をする。この判断の結果がイエスのときはステップS29の処理に移行し、ノーのときはステップS26の処理に移行して、生産計画データ生成手段36の演算処理を繰り返す。   In step S26, the product input order (product data reading order 32) is changed. In step S27, the production plan data generating means 36 is activated again to execute the arithmetic processing. In step S 28, the optimization unit 38 receives the calculation processing result of the production plan data generation unit 36 and compares the new final process end time with the final process end time 30 stored in the storage device 16. Then, it is determined whether the final process end time has been shortened. When the result of this determination is yes, the process proceeds to step S29, and when the result is no, the process proceeds to step S26, and the calculation process of the production plan data generating means 36 is repeated.

ステップS29では、今回の演算処理を実行したとき採用した製品の投入順製品データ読み取り順32)を、記憶装置16に記憶させて更新する。さらに、ステップS30では、今回の演算処理で短縮された新たな最終工程終了時刻30を記憶装置16に記憶させてデータを更新する。ステップS31では、演算処理結果は収束したかどうかという判断をする。この判断のために、予め最終工程終了時刻30の収束基準を決めておけばよい。この判断の結果がイエスのときは処理を終了する。ノーのときはステップS26の処理に戻って、生産計画データ生成手段36の演算処理を繰り返す。   In step S29, the product loading order product data reading order 32) adopted when the current arithmetic processing is executed is stored in the storage device 16 and updated. Further, in step S30, the new final process end time 30 shortened by the current arithmetic processing is stored in the storage device 16 to update the data. In step S31, it is determined whether the calculation processing result has converged. For this determination, a convergence criterion for the final process end time 30 may be determined in advance. If the result of this determination is yes, the process is terminated. If no, the process returns to step S26, and the calculation process of the production plan data generating means 36 is repeated.

図19は、最適化手段の後段処理動作フローチャートである。
この図のステップS41では、最適化手段38が、記憶装置から作業者データ18と工程データ20と製品データ22を読み取ってその受付けをする。次に、ステップS42では、製品投入順を決める。前段処理の結果得られた製品投入順で固定する。ステップS43では、作業者割り付け順34(初期値)の設定をする。例えば、前段では、後工程に優先的に作業者を割付けた。しかし、ここでは、例えば、最も後工程から2番目の工程と3番目の工程の優先度を入れ替える。ステップS44では、生産計画データ生成手段36を起動して、演算処理を実行させる。
FIG. 19 is a flowchart of the subsequent process operation of the optimization means.
In step S41 in this figure, the optimization means 38 reads the worker data 18, the process data 20, and the product data 22 from the storage device and accepts them. Next, in step S42, the order of product introduction is determined. Fix in the order of product input obtained as a result of the previous process. In step S43, the worker allocation order 34 (initial value) is set. For example, in the former stage, workers were assigned with priority to the subsequent process. However, here, for example, the priorities of the second and third steps from the most subsequent step are switched. In step S44, the production plan data generating means 36 is activated to execute arithmetic processing.

ステップS45では、最適化手段38が生産計画データ生成手段36の演算処理結果を受け取って、最終工程終了時刻30の記憶をする。ステップS46では、再度作業者割付順を変更する。例えば、最も後工程から3番目の工程と4番目の工程の優先度を入れ替える。このような優先度の入れ替え方法を毎回ランダムに選択する。ステップS47では、再び生産計画データ生成手段36を起動して、演算処理を実行させる。ステップS48では、最適化手段38が生産計画データ生成手段36の演算処理結果を受け取って、新たな最終工程終了時刻と記憶装置16に記憶した最終工程終了時刻30とを比較する。そして、最終工程終了時刻が短縮されたかどうかという判断をする。この判断の結果がイエスのときはステップS49の処理に移行し、ノーのときはステップS46の処理に移行して、生産計画データ生成手段36の演算処理を繰り返す。   In step S45, the optimization means 38 receives the calculation processing result of the production plan data generation means 36, and stores the final process end time 30. In step S46, the worker assignment order is changed again. For example, the priority of the third process and the fourth process from the most subsequent process is switched. Such a priority switching method is randomly selected each time. In step S47, the production plan data generating means 36 is activated again to execute arithmetic processing. In step S <b> 48, the optimization unit 38 receives the calculation processing result of the production plan data generation unit 36 and compares the new final process end time with the final process end time 30 stored in the storage device 16. Then, it is determined whether the final process end time has been shortened. When the result of this determination is yes, the process proceeds to step S49, and when the result is no, the process proceeds to step S46, and the calculation process of the production plan data generating means 36 is repeated.

ステップS49では、今回の演算処理を実行したとき採用した作業者割り付け順34を、記憶装置16に記憶させて更新する。さらに、ステップS50では、今回の演算処理で短縮された新たな最終工程終了時刻30を記憶装置16に記憶させてデータを更新する。ステップS31では、演算処理結果は収束したかどうかという判断をする。この判断のために、予め最終工程終了時刻30の収束基準を決めておけばよい。この判断の結果がイエスのときは処理を終了する。ノーのときはステップS26の処理に戻って、生産計画データ生成手段36の演算処理を繰り返す。   In step S49, the operator assignment order 34 employed when the current arithmetic processing is executed is stored in the storage device 16 and updated. Further, in step S50, the new final process end time 30 shortened by the current arithmetic processing is stored in the storage device 16 to update the data. In step S31, it is determined whether the calculation processing result has converged. For this determination, a convergence criterion for the final process end time 30 may be determined in advance. If the result of this determination is yes, the process is terminated. If no, the process returns to step S26, and the calculation process of the production plan data generating means 36 is repeated.

図20は、生産計画データ生成手段の動作例フローチャートである。
生産計画データ生成手段36は、上記の処理中で、最適化手段38から次に工程に投入する製品の製品識別コードや作業者割付け順のルールを受け取って、この処理を開始する。ステップS61では、時系列データの生成を開始するために、時刻=0のセットをする。その後は、単位時間ずつ時刻をシフトさせながら、各製品を工程に割付けていく。ステップS62では、受け取った製品を空き工程に投入する。
FIG. 20 is a flowchart illustrating an operation example of the production plan data generation unit.
The production plan data generation unit 36 receives the product identification code of the product to be input to the next process and the rule of the worker allocation order from the optimization unit 38 in the above process, and starts this process. In step S61, time = 0 is set to start generation of time-series data. After that, each product is assigned to a process while shifting the time by unit time. In step S62, the received product is put into an empty process.

ステップS63では、投入する工程は人作業かどうかという判断をする。この判断の結果がイエスのときはステップS64の処理に移行し、ノーのときはステップS67の処理に移行する。ステップS64では、空き作業者がいるかどうかという判断をする。この判断の結果がイエスのときはステップS65の処理に移行し、ノーのときはステップS67の処理に移行する。ステップS65では、ルールどおり作業者を割付ける。ステップS66では、時刻単位時間進ませる。これを、時系列割り付けデータ26の生成まで繰り返す。即ち、ステップS67で、全製品の工程が完了し、全製品が完了したかどうかという判断をする。この判断の結果がイエスのときはステップS68の処理に移行し、ノーのときはステップS62の処理に戻る。ステップS67では、時系列割り付けデータ26の生成をして処理を終了する。その結果は最適化手段38にわたされる。   In step S63, it is determined whether the input process is a manual operation. When the result of this determination is yes, the process proceeds to step S64, and when no, the process proceeds to step S67. In step S64, it is determined whether there is an empty worker. If the result of this determination is yes, the process proceeds to step S65, and if no, the process proceeds to step S67. In step S65, workers are assigned according to the rules. In step S66, the time unit time is advanced. This is repeated until the time-series allocation data 26 is generated. That is, in step S67, it is determined whether all products have been processed and all products have been completed. If the result of this determination is yes, the process proceeds to step S68, and if no, the process returns to step S62. In step S67, the time series allocation data 26 is generated and the process is terminated. The result is passed to the optimization means 38.

なお、上記の演算処理装置で実行されるコンピュータプログラムは、機能ブロックで図示した単位でモジュール化されてもよいし、複数の機能ブロックを組み合わせて一体化されてもよい。また、上記のコンピュータプログラムは、既存のアプリケーションプログラムに組み込んで使用してもよい。本発明を実現するためのコンピュータプログラムは、例えばCD−ROMのようなコンピュータで読み取り可能な記録媒体に記録して、任意の情報処理装置にインストールして利用することができる。   Note that the computer program executed by the arithmetic processing unit may be modularized in units illustrated in functional blocks, or may be integrated by combining a plurality of functional blocks. Further, the above computer program may be used by being incorporated into an existing application program. The computer program for realizing the present invention can be recorded on a computer-readable recording medium such as a CD-ROM and installed in any information processing apparatus for use.

12 製造計画演算装置
14 演算処理装置
16 記憶装置
18 作業者データ
20 工程データ
22 製品データ
24 製品リスト
26 時系列割り付けデータ
28 生産計画データ
30 最終工程終了時刻
32 製品データ読み取り順
34 作業者割り付け順
36 生産計画データ生成手段
38 最適化手段
40 仕掛品置き場決定手段
42 作業者識別コード
44 全作業者数N
46 工程識別コード
48 製品毎加工所要時間
50 必要作業者数
52 同時加工製品数
54 製品識別コード
56 必要工程順
58 製品コード
60 製造終了期日
DESCRIPTION OF SYMBOLS 12 Manufacturing plan calculating apparatus 14 Arithmetic processing apparatus 16 Memory | storage device 18 Worker data 20 Process data 22 Product data 24 Product list 26 Time series allocation data 28 Production plan data 30 Final process end time 32 Product data reading order 34 Worker allocation order 36 Production plan data generation means 38 Optimization means 40 Work-in-process storage place determination means 42 Worker identification code 44 Total number of workers N
46 Process identification code 48 Time required for machining per product 50 Number of required workers 52 Number of simultaneously processed products 54 Product identification code 56 Order of required processes 58 Product code 60

Claims (10)

いずれかの工程あるいは複数の全ての工程を、共通に利用する複数種類の製品を製造する場合に、
記憶装置に対して、
製造に従事することができる全作業者の識別コードと全作業者数Nを含む作業者データと、各工程について、その工程の識別コードと、製品毎の加工所要時間と、その工程に必要な作業者数と、その工程で同時に加工することができる製品の数とを含む工程データと、
各製品の識別コードと、各製品の製造に必要な工程順とを含む製品データと、
指定された期日までに製造を終了させる製品のリストとを記憶させて、
生産計画データ生成手段が、
前記製品のリストから製品が順番に選択されたとき、
前記製品データを参照して、前記各製品が前記工程順に前記選択順に各工程に受け入れられるように、各製品を各工程に割付け、
前記工程データを参照して、前記作業者が必要な工程を検出して、前記全作業者を、前工程から後工程に向かって、もしくは後工程から前工程に向かって順番に、各工程に必要な作業者数を満たすように割付けて、作業者が不足した工程があったときは、最も早く終了する工程の終了を待って該当する作業者を割付けて、
前記全ての工程に前記製品を割付けた状態を時系列的に配置し、前記作業者の割付け結果を含む時系列割付けデータを生成し、
最適化手段が、
前記製品のリストから製品をランダムな順番に選択して、前記生産計画データ生成手段に前記時系列割付けデータを生成させて、
前記生成された時系列割付けデータから最終工程終了時刻を検出し、
その後、前記製品のリストから製品を選択する順番を変更して、前記生産計画データ生成手段に前記時系列割付けデータを生成させるという処理を繰り返して、最も早い最終工程終了時刻を探索し、
前記最も早い最終工程終了時刻が検出された生産計画データの、前記製品の選択順を固定して、前記作業者を前記工程に割付ける順番を変更して、前記生産計画データ生成手段に前記時系列割付けデータを生成させるという処理を繰り返して、最も早い最終工程終了時刻を探索して、
最も早い最終工程終了時刻が検出された時系列割付けデータを含む、最適化された生産計画データを出力することを特徴とする製造計画演算方法。
When manufacturing multiple types of products that use any process or all multiple processes in common,
For storage devices
Identification data of all workers who can engage in manufacturing, worker data including the total number N of workers, identification code of each process for each process, processing time required for each product, and necessary for that process Process data including the number of workers and the number of products that can be processed simultaneously in the process,
Product data including an identification code for each product and the sequence of steps required to manufacture each product;
Remember the list of products that will be discontinued by the specified date,
Production plan data generation means
When products are selected in order from the list of products,
Referring to the product data, assign each product to each step so that each product is accepted in each step in the order of selection in the order of selection,
Referring to the process data, the worker detects necessary processes, and all the workers are moved from the previous process to the subsequent process or from the subsequent process to the previous process in each process. When there is a process with insufficient workers, assign the appropriate workers after the end of the process that finishes the earliest.
Arranging the state in which the products are allocated to all the processes in time series, and generating time series allocation data including the worker allocation results,
Optimization means
Select products in a random order from the list of products, let the production plan data generation means generate the time series allocation data,
Detecting the final process end time from the generated time series allocation data,
Then, change the order of selecting products from the list of products, repeat the process of generating the time series allocation data in the production plan data generation means, search for the earliest final process end time,
The production plan data in which the earliest final process end time is detected is fixed in the selection order of the products, the order in which the workers are assigned to the processes is changed, and the production plan data generating means Repeat the process of generating the series allocation data, search for the earliest final process end time,
A production plan calculation method characterized by outputting optimized production plan data including time series allocation data in which the earliest final process end time is detected.
請求項1に記載の製造計画演算方法において、
仕掛品置き場決定手段が、
前記各工程で加工を終了した製品が次の工程に移るまで、前記製品の仕掛品を一時保管するための仕掛品置き場を設定し、
最適化された生産計画が取得された後、その生産計画で使用をされた仕掛品置き場のみを、最小限必要な容量の仕掛品置き場に決定することを特徴とする製造計画演算方法。
In the manufacturing plan calculation method according to claim 1,
The work in process storage location determination means
Set the work in process storage area to temporarily store the work in progress of the product until the product finished processing in each step moves to the next process,
A manufacturing plan calculation method characterized in that after an optimized production plan is acquired, only a work in process place used in the production plan is determined as a work in process place with a minimum necessary capacity.
請求項2に記載の製造計画演算方法において、
前記仕掛品置き場を、前記製品の加工所要時間をゼロとし、その工程に必要な作業者数をゼロ、同時に保管できる製品数を無制限と定義して、前記時系列データを生成し、いずれかの工程の間で、保管に使用された仕掛品置き場と、その仕掛品置き場に保管された製品数の最大値を取得して、最小限必要な容量の仕掛品置き場を決定することを特徴とする製造計画演算方法。
In the manufacturing plan calculation method according to claim 2,
The time-series data is generated by defining the work-in-process storage area as zero processing time for the product, defining the number of workers required for the process as zero, and limiting the number of products that can be stored at the same time, It is characterized by obtaining the maximum value of the work in process storage used for storage and the maximum number of products stored in the work in progress storage between processes, and determining the minimum work in process storage. Manufacturing plan calculation method.
請求項1乃至3のいずれかに記載の製造計画演算方法において、
製造を開始していない製品と、既に製造が開始された製品とを前記製品のリストに混在させたことを特徴とする製造計画演算方法。
In the manufacturing plan calculation method according to any one of claims 1 to 3,
A manufacturing plan calculation method characterized in that a product that has not been manufactured and a product that has already been manufactured are mixed in the list of products.
請求項1乃至4のいずれかに記載の製造計画演算方法において、
前記工程データには、その工程で作業可能な作業者を指定する作業者コードと、作業者毎の加工所要時間を示すデータを含めたことを特徴とする製造計画演算方法。
In the manufacturing plan calculation method according to any one of claims 1 to 4,
A manufacturing plan calculation method characterized in that the process data includes an operator code for specifying an operator who can perform an operation in the process and data indicating a processing time required for each operator.
請求項1乃至5のいずれかに記載の製造計画演算方法において、
前記最適化手段は、全ての工程に必要十分な数の作業者を割り付けて前記演算処理を実行し、同時に稼働する作業者数の最大値を求めて、前記生産計画データに含めることを特徴とする製造計画演算方法。
In the manufacturing plan calculation method according to any one of claims 1 to 5,
The optimization means allocates a sufficient number of workers necessary for all processes and executes the calculation process, obtains a maximum value of the number of workers operating simultaneously, and includes it in the production plan data. Manufacturing plan calculation method.
請求項1乃至6のいずれかに記載の製造計画演算方法において、
作業者が不足して作業者の割り付けを待つ工程を生じさせるように、前記全作業者数Nの初期値を設定し、この全作業者数Nを変更した演算処理を繰り返して、前記指定された期日までに製造を終了させることができる作業者数の最小値を求めることを特徴とする製造計画演算方法。
In the manufacturing plan calculation method according to any one of claims 1 to 6,
An initial value of the total number of workers N is set so as to cause a process of waiting for workers to be assigned due to a shortage of workers, and the arithmetic processing with the total number of workers N being changed is repeated to specify the specified value. A method for calculating a production plan, characterized in that a minimum value of the number of workers capable of finishing the production by a predetermined date is obtained.
いずれかの工程あるいは複数の全ての工程を、共通に利用する複数種類の製品を製造する生産計画をコンピュータにより演算処理する装置であって、
製造に従事することができる全作業者の識別コードと全作業者数Nを含む作業者データと、各工程について、その工程の識別コードと、製品毎の加工所要時間と、その工程に必要な作業者数と、その工程で同時に加工することができる製品の数とを含む工程データと、
各製品の識別コードと、各製品の製造に必要な工程順とを含む製品データと、指定された期日までに製造を終了させる製品のリストとを記憶する記憶装置と、
前記製品のリストから製品が順番に選択されたとき、前記製品データを参照して、前記各製品が前記工程順に前記選択順に各工程に受け入れられるように、各製品を各工程に割付け、前記工程データを参照して、前記作業者が必要な工程を検出して、前記全作業者を、前工程から後工程に向かって、もしくは後工程から前工程に向かって順番に、各工程に必要な作業者数を満たすように割付けて、作業者が不足した工程があったときは、最も早く終了する工程の終了を待って該当する作業者を割付けて、前記全ての工程に前記製品を割付けた状態を時系列的に配置し、前記作業者の割付け結果を含む生産計画データを生成する生産計画データ生成手段と、
前記製品のリストから製品をランダムな順番に選択して、前記生産計画データ生成手段に前記生産計画データを生成させて、前記生成された生産計画データから最終工程終了時刻を検出し、その後、前記製品のリストから製品を選択する順番を変更して、前記生産計画データ生成手段に前記生産計画データを生成させるという処理を繰り返して、最も早い最終工程終了時刻を探索し、前記最も早い最終工程終了時刻が検出された生産計画データの、前記製品の選択順を固定して、前記作業者を前記工程に割付ける順番を変更して、前記生産計画データ生成手段に前記生産計画データを生成させるという処理を繰り返して、最も早い最終工程終了時刻が検出された生産計画データを、最適化された生産計画データとして出力する最適化手段を備えたことを特徴とする製造計画演算装置。
A device for computing a production plan for manufacturing a plurality of types of products that commonly use any process or all of a plurality of processes by a computer,
Identification data of all workers who can engage in manufacturing, worker data including the total number N of workers, identification code of each process for each process, processing time required for each product, and necessary for that process Process data including the number of workers and the number of products that can be processed simultaneously in the process,
A storage device for storing product data including an identification code of each product, a process order necessary for manufacturing each product, and a list of products whose production is to be terminated by a specified date;
When products are selected in order from the list of products, each product is assigned to each step so that each product is accepted in each step in the selection order in the order of the steps with reference to the product data. Referring to the data, the operator detects the necessary steps, and all the workers are required for each step from the previous step to the subsequent step or from the subsequent step to the previous step. When there was a process with insufficient workers, the number of workers was allocated to meet the number of workers, and the corresponding workers were allocated after the process that ended first was completed, and the product was allocated to all the processes. Production plan data generating means for arranging the states in time series and generating production plan data including the worker's allocation results;
Select products in a random order from the list of products, let the production plan data generation means generate the production plan data, detect the final process end time from the generated production plan data, Change the order of selecting products from the list of products, repeat the process of causing the production plan data generation means to generate the production plan data, search for the earliest final process end time, and end the earliest final process The production plan data from which the time is detected is fixed in the selection order of the products, the order in which the workers are assigned to the processes is changed, and the production plan data generation means generates the production plan data. Optimized means to output the production plan data with the earliest final process end time detected as optimized production plan data by repeating the process Production planning calculation apparatus characterized by a.
コンピュータを、請求項7に記載の各手段として機能させる製造計画演算プログラム。   A manufacturing plan calculation program for causing a computer to function as each means according to claim 7. コンピュータを、請求項7に記載の各手段として機能させる製造計画演算プログラムを記録したコンピュータで読み取り可能な記録媒体。   A computer-readable recording medium having recorded thereon a manufacturing plan calculation program that causes the computer to function as each means according to claim 7.
JP2010239201A 2010-10-26 2010-10-26 Production schedule computation method and production schedule computing device Pending JP2012093865A (en)

Priority Applications (1)

Application Number Priority Date Filing Date Title
JP2010239201A JP2012093865A (en) 2010-10-26 2010-10-26 Production schedule computation method and production schedule computing device

Applications Claiming Priority (1)

Application Number Priority Date Filing Date Title
JP2010239201A JP2012093865A (en) 2010-10-26 2010-10-26 Production schedule computation method and production schedule computing device

Publications (1)

Publication Number Publication Date
JP2012093865A true JP2012093865A (en) 2012-05-17

Family

ID=46387141

Family Applications (1)

Application Number Title Priority Date Filing Date
JP2010239201A Pending JP2012093865A (en) 2010-10-26 2010-10-26 Production schedule computation method and production schedule computing device

Country Status (1)

Country Link
JP (1) JP2012093865A (en)

Cited By (5)

* Cited by examiner, † Cited by third party
Publication number Priority date Publication date Assignee Title
KR101995275B1 (en) * 2019-01-29 2019-07-03 호전실업 주식회사 Method and system for optimizing production of clothes and operation of apparel production factory
US20190302747A1 (en) * 2018-03-30 2019-10-03 Panasonic Intellectual Property Management Co., Ltd. Preparation schedule creating method and preparation schedule creating apparatus
KR102189901B1 (en) * 2020-04-23 2020-12-11 주식회사 더온에프앤비 Method and apparatus for optimizing cooking time of ordered food
CN113052376A (en) * 2021-03-19 2021-06-29 杭州晨龙智能科技有限公司 Production scheduling method and device, storage medium and electronic equipment
CN113807730A (en) * 2021-09-28 2021-12-17 重庆允成互联网科技有限公司 Work order generation method, system, equipment and storage medium based on discrete management

Citations (6)

* Cited by examiner, † Cited by third party
Publication number Priority date Publication date Assignee Title
JPS6374558A (en) * 1986-09-16 1988-04-05 Matsushita Electric Ind Co Ltd Creating device for schedule
JPS63295163A (en) * 1987-05-27 1988-12-01 Nec Corp Determining method for product cast-in sequence
JPH08314526A (en) * 1995-05-18 1996-11-29 Fujitsu Ltd Manufacture management system
JP2007034429A (en) * 2005-07-22 2007-02-08 Matsushita Electric Works Ltd Production planning system
JP2007072747A (en) * 2005-09-07 2007-03-22 Kobe Steel Ltd Production schedule preparation method, production schedule preparation device and program
JP2010176388A (en) * 2009-01-29 2010-08-12 Mitsubishi Heavy Ind Ltd Work schedule planning apparatus, work schedule planning method, and program of same

Patent Citations (6)

* Cited by examiner, † Cited by third party
Publication number Priority date Publication date Assignee Title
JPS6374558A (en) * 1986-09-16 1988-04-05 Matsushita Electric Ind Co Ltd Creating device for schedule
JPS63295163A (en) * 1987-05-27 1988-12-01 Nec Corp Determining method for product cast-in sequence
JPH08314526A (en) * 1995-05-18 1996-11-29 Fujitsu Ltd Manufacture management system
JP2007034429A (en) * 2005-07-22 2007-02-08 Matsushita Electric Works Ltd Production planning system
JP2007072747A (en) * 2005-09-07 2007-03-22 Kobe Steel Ltd Production schedule preparation method, production schedule preparation device and program
JP2010176388A (en) * 2009-01-29 2010-08-12 Mitsubishi Heavy Ind Ltd Work schedule planning apparatus, work schedule planning method, and program of same

Cited By (7)

* Cited by examiner, † Cited by third party
Publication number Priority date Publication date Assignee Title
US20190302747A1 (en) * 2018-03-30 2019-10-03 Panasonic Intellectual Property Management Co., Ltd. Preparation schedule creating method and preparation schedule creating apparatus
US11009860B2 (en) * 2018-03-30 2021-05-18 Panasonic Intellectual Property Management Co., Ltd. Preparation schedule creating method and preparation schedule creating apparatus
KR101995275B1 (en) * 2019-01-29 2019-07-03 호전실업 주식회사 Method and system for optimizing production of clothes and operation of apparel production factory
WO2020159066A1 (en) * 2019-01-29 2020-08-06 호전실업 주식회사 Method and system for optimizing manufacture and operation of garment manufacturing factory
KR102189901B1 (en) * 2020-04-23 2020-12-11 주식회사 더온에프앤비 Method and apparatus for optimizing cooking time of ordered food
CN113052376A (en) * 2021-03-19 2021-06-29 杭州晨龙智能科技有限公司 Production scheduling method and device, storage medium and electronic equipment
CN113807730A (en) * 2021-09-28 2021-12-17 重庆允成互联网科技有限公司 Work order generation method, system, equipment and storage medium based on discrete management

Similar Documents

Publication Publication Date Title
CN104915251B (en) Method for scheduling task and device
CN110955206B (en) Order scheduling and distribution scheduling method and system
Jain et al. An integrated scheme for process planning and scheduling in FMS
Gravel et al. A multicriterion view of optimal resource allocation in job-shop production
JP2012093865A (en) Production schedule computation method and production schedule computing device
CN111400868B (en) Distributed workshop scheduling optimization method and system with order and robot carrying functions
JP2013003617A (en) Member assignment system
Gan et al. Scheduling of flexible-sequenced process plans in a mould manufacturing shop
CN111950761A (en) Development resource integrated scheduling method for high-end equipment complex layered task network
JP3832235B2 (en) Production control method
Wang et al. Job rescheduling by exploring the solution space of process planning for machine breakdown/arrival problems
KR20230058857A (en) Multi-machine and performance based continuous production planning global optimization scheduling method and device
CN110716522B (en) Manufacturing enterprise workshop scheduling optimization method based on arbitrary time A-heuristic search
Dauzère-Pérès et al. Extensions of an integrated approach for multi-resource shop scheduling
Jiang et al. A hybrid algorithm of product-service framework for the multi-project scheduling in ETO assembly process
CN113627888A (en) Project plan generation method and device, storage medium and processor
JP2008226044A (en) Alternate skill scheduling system, scheduling method and program
Sanchidrián et al. Exact and heuristic methods for an aeronautical assembly line time-constrained scheduling problem with multiple modes and a resource leveling objective
JP2005190062A (en) Production planning method and program, and production planning system
JP3114149B2 (en) Schedule automatic creation processing method
CN113377073B (en) Flexible job shop scheduling optimization method based on double-layer multi-agent system
JP7193431B2 (en) Scheduling device, scheduling method and storage medium
Kurt et al. Unrelated parallel machine scheduling under machine availability and eligibility constraints to minimize the makespan of non-resumable jobs
JPH09282373A (en) Schedule control method
CN113822615A (en) Order distribution method and device, readable storage medium and electronic equipment

Legal Events

Date Code Title Description
A621 Written request for application examination

Free format text: JAPANESE INTERMEDIATE CODE: A621

Effective date: 20131021

A977 Report on retrieval

Free format text: JAPANESE INTERMEDIATE CODE: A971007

Effective date: 20140709

A131 Notification of reasons for refusal

Free format text: JAPANESE INTERMEDIATE CODE: A131

Effective date: 20140717

A02 Decision of refusal

Free format text: JAPANESE INTERMEDIATE CODE: A02

Effective date: 20141113