JP2010113507A - System and program for estimating period required to supply power - Google Patents

System and program for estimating period required to supply power Download PDF

Info

Publication number
JP2010113507A
JP2010113507A JP2008285441A JP2008285441A JP2010113507A JP 2010113507 A JP2010113507 A JP 2010113507A JP 2008285441 A JP2008285441 A JP 2008285441A JP 2008285441 A JP2008285441 A JP 2008285441A JP 2010113507 A JP2010113507 A JP 2010113507A
Authority
JP
Japan
Prior art keywords
power
work
period
supply
power requirement
Prior art date
Legal status (The legal status is an assumption and is not a legal conclusion. Google has not performed a legal analysis and makes no representation as to the accuracy of the status listed.)
Granted
Application number
JP2008285441A
Other languages
Japanese (ja)
Other versions
JP5208682B2 (en
Inventor
Tokuro Irie
徳郎 入江
Current Assignee (The listed assignees may be inaccurate. Google has not performed a legal analysis and makes no representation or warranty as to the accuracy of the list.)
Chugoku Electric Power Co Inc
Original Assignee
Chugoku Electric Power Co Inc
Priority date (The priority date is an assumption and is not a legal conclusion. Google has not performed a legal analysis and makes no representation as to the accuracy of the date listed.)
Filing date
Publication date
Application filed by Chugoku Electric Power Co Inc filed Critical Chugoku Electric Power Co Inc
Priority to JP2008285441A priority Critical patent/JP5208682B2/en
Publication of JP2010113507A publication Critical patent/JP2010113507A/en
Application granted granted Critical
Publication of JP5208682B2 publication Critical patent/JP5208682B2/en
Expired - Fee Related legal-status Critical Current
Anticipated expiration legal-status Critical

Links

Images

Landscapes

  • Management, Administration, Business Operations System, And Electronic Commerce (AREA)

Abstract

<P>PROBLEM TO BE SOLVED: To estimate the period required to supply power that matches a customer's demand. <P>SOLUTION: A system for estimating the period required to supply power includes: an installation database 32 for storing installation information about the kind, capacity, installation site of a power installation, etc., while using a site where use of power is planned and planned load as power requirement specifications; a work determination task 33 for determining the work required to supply the power matching the power requirement specifications, and determining whether an application and notification for permission and authorization to perform the work are needed, based on the inputted power requirement specifications and the installation information stored in the installation database 32; and an estimation task 34 for estimating the period required to supply the power matching the power requirement specifications, based on the results determined by the work determination task 33. <P>COPYRIGHT: (C)2010,JPO&INPIT

Description

この発明は、新築家屋などに電力(電気)を供給するのに要する期間を見積もる、電力供給に要する期間見積システムおよび期間見積プログラムに関する。   The present invention relates to a period estimation system and a period estimation program required for power supply for estimating a period required to supply power (electricity) to a newly built house or the like.

例えば、新築の家屋に電力を供給する場合、従来、次のような手順・工程を経て行われていた。まず、需要家(家屋の購入者)が建築会社に家屋購入の手続きを行うと、建築会社から電気工事店に電気設備の工事が依頼される。そして、建築会社と電気工事店とによって、電力の負荷設備や引込方法、屋内配線方法および、電気の使用開始予定日(引渡し日)などが協議、決定される。その後、電気工事店から電力会社に電気の使用申し込みが行われ、電力会社の設計担当者が、申込内容に合った電力を供給するのに工事などを要するかどうかを判断していた。すなわち、変圧器や電柱の新設などの外線工事が必要かどうか、引込線が国道を横断するために所轄官庁へ占用申請を行う必要があるかどうか、などの判断を設計担当者が行っていた。   For example, when power is supplied to a newly built house, the following procedures and processes have been conventionally performed. First, when a consumer (a purchaser of a house) performs a procedure for purchasing a house from a construction company, the construction company requests the construction of an electrical facility from the construction company. Then, the construction company and the electric construction shop discuss and determine the power load facility, the pull-in method, the indoor wiring method, the scheduled start date (delivery date) of electricity, and the like. After that, an electrician applied to the electric power company from the electric construction shop, and the electric power company's designer in charge determined whether construction or the like was required to supply the electric power suitable for the application. In other words, the design engineer made decisions such as whether or not external work such as the construction of a transformer or utility pole was necessary, and whether or not it was necessary to apply for private use to the competent authority in order to cross the national highway.

また、需要家からの電気使用の申込内容を電力会社の設計部門に回付する必要があるか否かを判定するシステムが知られている(例えば、特許文献1参照。)。このシステムは、申込内容に含まれる契約種別から電力の適用範囲を特定し、この電力の適用範囲が許容電力容量を超えるか否かを判断することなどによって、申込内容を設計部門に回付する必要があるか否かを判定するものである。
特開2007−299046号公報
There is also known a system for determining whether or not it is necessary to circulate application details for electricity usage from a customer to a design department of an electric power company (see, for example, Patent Document 1). This system identifies the power application range from the contract type included in the application content, and circulates the application content to the design department by determining whether or not this power application range exceeds the allowable power capacity. It is determined whether or not it is necessary.
JP 2007-299046 A

ところで、電力会社の設計担当者による検討の結果、外線工事を要したり、所轄官庁への占用申請を要したりすると、電力供給までに長時間を要することになる。しかしながら、上記従来のような手順・工程では、建築会社と電気工事店とによって電気の使用開始予定日などが協議、決定された後に、電気工事店から電力会社に電気の使用申し込みが行わる。また、電気の使用開始予定日は、需要家の希望などに基づいて決められる。つまり、電気の使用開始予定日は、外線工事の要否や所轄官庁への申請の要否などに係わらず決定される。このため、外線工事や所轄官庁への申請などを要する場合には、使用開始予定日までに電力を供給できない事態が生じ得る。特に、電気工事店から電力会社への申し込みまでに長時間を要した場合などには、外線工事や所轄官庁への申請などを行える期間が短縮されることになり、使用開始予定日までに電力を供給できない事態が生じ得る。そして、このような事態を回避するために、建築会社や電気工事店、さらには需要家が、電気を使用できるようになるまでの期間、つまり電力を供給するのに要する期間を知ることができることが望まれる。   By the way, as a result of the examination by the design person in charge of the electric power company, it takes a long time to supply the electric power if an outside line construction is required or a private application is required to the competent authority. However, in the conventional procedures / processes described above, after the construction company and the electric construction shop discuss and determine the scheduled start date of the use of electricity, the electric construction shop applies to the electric power company for use of electricity. In addition, the scheduled start date for using electricity is determined based on the desires of consumers. That is, the scheduled start date of electricity is determined regardless of whether or not the outside line construction is necessary and whether or not an application to the competent authority is required. For this reason, when an outside line construction or an application to the competent authority is required, there may be a situation where power cannot be supplied by the scheduled start date of use. In particular, when it takes a long time to apply to an electric power company from an electric construction shop, the period during which outside line construction or application to the competent authority will be shortened, and power will be used by the scheduled start date of use. There may be situations where it is not possible to supply And in order to avoid such a situation, it is possible for construction companies, electric construction shops and even customers to know the period until electricity can be used, that is, the period required to supply power. Is desired.

そこでこの発明は、需要家の要望に適合した電力を供給するのに要する期間を見積もることが可能な、電力供給に要する期間見積システムおよび期間見積プログラムを提供することを目的とする。   SUMMARY OF THE INVENTION Accordingly, an object of the present invention is to provide a period estimation system and a period estimation program required for power supply capable of estimating a period required to supply electric power that meets the demands of consumers.

上記目的を達成するために請求項1に記載の発明は、電力を使用する予定場所や予定負荷などの電力要求仕様を入力する仕様入力手段と、前記仕様入力手段で入力された電力要求仕様を受信する仕様受信手段と、電力設備の種類や容量、設置場所などの設備情報を記憶する記憶手段と、前記仕様受信手段で受信された電力要求仕様と前記記憶手段に記憶されている設備情報とに基づいて、前記電力要求仕様に適合する電力を供給するのに要する作業と、該作業を行うために許認可の申請や届出が必要か否かを割り出す作業割出手段と、前記作業割出手段で割り出された結果に基づいて、前記電力要求仕様に適合する電力を供給するのに要する期間を見積もる見積手段と、を備えることを特徴とする電力供給に要する期間見積システムである。ここで、作業には各種工事が含まれる。   In order to achieve the above object, the invention described in claim 1 includes specification input means for inputting a power requirement specification such as a planned place where power is used and a planned load, and a power requirement specification input by the specification input means. Specification receiving means for receiving, storage means for storing equipment information such as the type, capacity, and installation location of power equipment, power requirement specifications received by the specification receiving means, and equipment information stored in the storage means Based on the power requirement specifications, work indexing means for determining whether or not an application for approval or notification is required to perform the work, and the work indexing means A period estimation system required for power supply, comprising: estimation means for estimating a period required to supply power that conforms to the power requirement specification based on the result determined in step (b). Here, the work includes various works.

この発明によれば、例えば、仕様入力手段を電気工事店に設け、仕様受信手段と記憶手段と作業割出手段と見積手段を電力会社に設ける。そして、仕様入力手段で電力要求仕様を入力すると、仕様受信手段によって電力要求仕様が受信され、この電力要求仕様と記憶手段に記憶されている設備情報とに基づいて作業割出手段によって、電力を供給するのに要する作業と、許認可の申請や届出の要否が割り出される。さらに、この割出結果に基づいて見積手段によって、電力要求仕様に適合する電力を供給するのに要する期間が見積もられる。この見積結果を電気工事店に送信などすることで、電力を供給するのに要する期間を電気工事店で知得できる。   According to the present invention, for example, the specification input means is provided in the electric construction shop, and the specification receiving means, the storage means, the work indexing means, and the estimation means are provided in the electric power company. Then, when the power requirement specification is inputted by the specification input means, the power requirement specification is received by the specification receiving means, and the power is obtained by the work indexing means based on the power requirement specification and the facility information stored in the storage means. The work required for supply and whether or not to apply for permission and notification are determined. Further, based on the result of the indexing, the estimation means estimates the period required to supply power that meets the power requirement specification. By transmitting this estimated result to an electric construction shop, the electric construction shop can know the period required to supply power.

請求項2に記載の発明は、電力を使用する予定場所や予定負荷などを電力要求仕様とし、コンピュータを、電力設備の種類や容量、設置場所などの設備情報を記憶する記憶手段と、入力された電力要求仕様と前記記憶手段に記憶されている設備情報とに基づいて、前記電力要求仕様に適合する電力を供給するのに要する作業と、該作業を行うために許認可の申請や届出が必要か否かを割り出す作業割出手段と、前記作業割出手段で割り出された結果に基づいて、前記電力要求仕様に適合する電力を供給するのに要する期間を見積もる見積手段、として機能させるための電力供給に要する期間見積プログラムである。   According to the second aspect of the present invention, the planned location where the power is used and the planned load are used as the power requirement specifications, and the computer is input with storage means for storing facility information such as the type, capacity, and installation location of the power facility. Based on the required power specifications and the facility information stored in the storage means, work required to supply power that conforms to the power required specifications, and permission application or notification is required to perform the work To function as work indexing means for determining whether or not, and an estimation means for estimating a period of time required to supply power that conforms to the power requirement specification based on the result determined by the work indexing means It is a period estimation program required for power supply.

請求項1および2に記載の発明によれば、電力を使用する予定場所や予定負荷などと、電力設備の種類や容量、設置場所などとに基づいて、電力を供給するための作業と、その許認可の申請や届出の要否が割り出され、その結果に基づいて電力を供給するのに要する期間が見積もられる。すなわち、外線工事などの作業や所轄官庁への申請などを考慮して、需要家の要望に適合した電力を供給するための適正な期間が見積もられる。そして、この見積結果を建築会社や電気工事店、さらには需要家が共有することで、電気を使用できるようになるまでの期間を知ることができる。   According to the first and second aspects of the present invention, the work for supplying power based on the planned location or planned load where the power is used and the type, capacity, installation location, etc. of the power facility, Necessity of application for approval and notification is determined, and based on the result, the period required to supply power is estimated. That is, an appropriate period for supplying electric power that meets the demands of the consumer can be estimated in consideration of work such as outside line construction and application to the competent authority. Then, by sharing this estimation result with a construction company, an electric construction shop, or even a customer, it is possible to know a period until electricity can be used.

以下、この発明を図示の実施の形態に基づいて説明する。   The present invention will be described below based on the illustrated embodiments.

図1は、この発明の実施の形態に係る電力供給に要する期間見積システム(以下、「期間見積システム」という)1を示す概略構成図である。この期間見積システム1は、需要家の要望に適合した電力を供給するのに要する期間を見積もるシステムであり、パーソナルコンピュータ(仕様入力手段)2と見積サーバ3とが、通信網(インターネット)NWを介して通信可能に接続されている。また、この実施の形態では、パーソナルコンピュータ2は電気工事店に設置され、見積サーバ3は電力会社に設置されている。   FIG. 1 is a schematic configuration diagram showing a period estimation system (hereinafter referred to as “period estimation system”) 1 required for power supply according to an embodiment of the present invention. This period estimation system 1 is a system that estimates the period required to supply power that meets the demands of the customer. The personal computer (specification input means) 2 and the estimation server 3 configure a communication network (Internet) NW. Via a communicable connection. In this embodiment, the personal computer 2 is installed in an electric construction shop, and the estimation server 3 is installed in an electric power company.

パーソナルコンピュータ2は、キーボードやマウスなどを備え、電力を使用する予定場所や予定負荷などの電力要求仕様を入力する端末となっている。すなわち、後述するように、見積サーバ3のWebページにアクセスすることで申込受付タスク31が起動され、この申込受付タスク31による入力画面に従って電力要求仕様を入力するものである。また、送信操作をすることで、入力した電力要求仕様が見積サーバ3に送信されるようになっている。ここで、具体的に電力要求仕様としては、申込者である需要家の氏名、住所、電力を引き込む電柱の番号、予定負荷、契約種別、電気の使用開始予定日などが含まれる。   The personal computer 2 includes a keyboard and a mouse, and is a terminal for inputting power requirement specifications such as a planned place where power is used and a planned load. That is, as will be described later, the application reception task 31 is activated by accessing the Web page of the estimation server 3, and the power requirement specification is input according to the input screen by the application reception task 31. In addition, the input power requirement specification is transmitted to the estimation server 3 by performing a transmission operation. Here, the power requirement specification specifically includes the name and address of the customer who is the applicant, the number of the utility pole from which power is drawn, the planned load, the contract type, the scheduled start date of use of electricity, and the like.

見積サーバ3は、主として、申込受付タスク(仕様受信手段)31と、設備データベース(記憶手段)32と、作業割出タスク(作業割出手段)33と、見積タスク(見積手段)34と、これらを制御などする中央処理部35とを備えている。   The estimation server 3 mainly includes an application reception task (specification receiving means) 31, an equipment database (storage means) 32, a work indexing task (work indexing means) 33, an estimation task (estimating means) 34, and these And a central processing unit 35 for controlling the above.

申込受付タスク31は、パーソナルコンピュータ2で入力された電力要求仕様を受信するタスクである。すなわち、見積サーバ3のWebページ中の電気使用申込メニュを構成し、このメニュにアクセスされると電力要求仕様を入力する入力画面を表示する。そして、上記のように、この入力画面に従って電力要求仕様が入力され見積サーバ3に送信されると、電力要求仕様を読み取りメモリに記憶するものである。   The application reception task 31 is a task for receiving the power requirement specification input by the personal computer 2. That is, an electricity usage application menu in the Web page of the estimation server 3 is configured, and when this menu is accessed, an input screen for inputting power requirement specifications is displayed. Then, as described above, when the power requirement specification is input and transmitted to the estimation server 3 according to this input screen, the power requirement specification is read and stored in the memory.

設備データベース32は、電力会社で保有している既設の電力設備の種類や容量、設置場所、さらには各設備の使用状況(バンク負荷状況等)などの設備情報を記憶するデータベースである。具体的には、例えば図2に示す電柱データ321には、電柱を識別する電柱番号ごとに、この電柱に設置されている変圧器の電力容量(変圧器容量)と、この変圧器から引き込まれている需要家の契約電力容量(既契約容量)とが記憶されている。そして、この電柱データ321は、後述する作業割出タスク33において、例えば、既設の変圧器に新たな需要家を接続する場合に電力容量が十分か否かを判定するために参照される。また、図3に示すような地図データ322には、各電力設備の位置・設置場所が地図上に記憶されている。ここで、図中「●」は電柱を示し、破線は配電線を示す。そして、この地図データ322は、後述する作業割出タスク33において、例えば、国道等を占用するか否かを判定するために参照される。   The equipment database 32 is a database that stores equipment information such as the type and capacity of the existing power equipment owned by the power company, the installation location, and the usage status (bank load status, etc.) of each equipment. Specifically, for example, in the utility pole data 321 shown in FIG. 2, for each utility pole number for identifying the utility pole, the power capacity (transformer capacity) of the transformer installed on this utility pole and the power pole data 321 are drawn from this transformer. The contracted power capacity (existing contracted capacity) of the customer who is in charge is stored. The utility pole data 321 is referred to in the work indexing task 33 described later in order to determine whether the power capacity is sufficient when, for example, a new consumer is connected to an existing transformer. Further, in the map data 322 as shown in FIG. 3, the position / installation location of each electric power facility is stored on the map. Here, “●” in the figure indicates a power pole, and a broken line indicates a distribution line. And this map data 322 is referred in order to determine whether to occupy a national highway etc. in the work indexing task 33 described later.

作業割出タスク33は、申込受付タスク31で受信された電力要求仕様と設備データベース32に記憶されている設備情報とに基づいて、電力要求仕様に適合する電力を供給するのに要する作業と、この作業を行うために許認可の申請や届出が必要か否かを割り出すタスク(プログラム)である。具体的には、作業を割り出す第1の割出タスク331と、申請などの要否を割り出す第2の割出タスク332とから構成されている。   The work indexing task 33 is based on the power requirement specification received by the application reception task 31 and the facility information stored in the facility database 32, and the work required to supply power that conforms to the power requirement specification, It is a task (program) that determines whether or not a license application or notification is required to perform this work. Specifically, it comprises a first indexing task 331 for determining work and a second indexing task 332 for determining whether or not an application is necessary.

第1の割出タスク331では、図4、5に示すように、まず、電力要求仕様が高圧電力の新規申込であるか否かを判断する(ステップS1)。そして、高圧電力の新規申込である場合には、受電点(需要家宅)付近に高圧線が架設された電柱が設置されているか否かを、設備データベース32に基づいて判断する(ステップS2)。この結果、高圧電柱が設置されている場合には、必要な作業を高圧線の延長とし、メモリの作業エリアに「高圧線延長工事」を記憶する(ステップS3)。一方、高圧電柱が設置されていない場合には、必要な作業を電柱の新設と高圧線の新設とし、メモリの作業エリアに「電柱+高圧線新設工事」を記憶する(ステップS4)。   In the first indexing task 331, as shown in FIGS. 4 and 5, it is first determined whether or not the power requirement specification is a new application for high-voltage power (step S1). If it is a new application for high-voltage power, it is determined on the basis of the equipment database 32 whether or not a power pole with a high-voltage line is installed near the power receiving point (customer's house) (step S2). As a result, when the high piezoelectric column is installed, the necessary work is set as the extension of the high voltage line, and the “high voltage line extension work” is stored in the work area of the memory (step S3). On the other hand, if the high piezoelectric pole is not installed, the necessary work is newly installed as a utility pole and a new high-voltage line, and “electric pole + high-voltage line new construction” is stored in the work area of the memory (step S4).

ステップS1において電力要求仕様が高圧電力の新規申込でない場合には、単相線路に対する動力負荷供給の申込であるか否かを、電力要求仕様および設備データベース32に基づいて判断する(ステップS5)。そして、単相線路への動力負荷供給の申込である場合には、その単相線路が高圧線路であるか低圧線路であるかを、設備データベース32に基づいて判断する(ステップS6)。この結果、高圧線路である場合には、必要な作業を高圧線路の三相化とし、メモリの作業エリアに「高圧三相化工事」を記憶する(ステップS7)。一方、低圧線路である場合には、必要な作業を低圧線路の三相化とし、メモリの作業エリアに「低圧三相化工事」を記憶する(ステップS8)。   If the power requirement specification is not a new application for high-voltage power in step S1, it is determined based on the power requirement specification and the facility database 32 whether or not it is an application for power load supply to a single-phase line (step S5). And when it is an application of power load supply to a single phase track, it is judged based on equipment database 32 whether the single phase track is a high voltage track or a low voltage track (Step S6). As a result, in the case of a high-voltage line, the necessary work is changed to a three-phase high-voltage line, and “high-voltage three-phase construction” is stored in the work area of the memory (step S7). On the other hand, in the case of a low-voltage line, the necessary work is made into a three-phase low-voltage line, and “low-pressure three-phase construction” is stored in the work area of the memory (step S8).

ステップS5において単相線路への動力負荷供給の申込でない場合には、需要家宅から所定の範囲内に電柱が設置されているか否かを、電力要求仕様および設備データベース32に基づいて判断する(ステップS9)。そして、電柱が設置されていない場合には、必要な作業を電柱の新設とし、メモリの作業エリアに「電柱新設工事」を記憶する(ステップS10)。ここで、電力要求仕様に電柱番号が含まれている場合には、この電柱番号の電柱を需要家宅付近の電柱とし、以下の処理についても同様とする。   If it is not an application for power load supply to the single-phase line in step S5, it is determined based on the power requirement specification and the facility database 32 whether or not a power pole is installed within a predetermined range from the customer's house (step S5). S9). If the utility pole is not installed, the necessary work is set as a new utility pole, and “new utility pole construction” is stored in the work area of the memory (step S10). Here, when a power pole number is included in the power requirement specification, the power pole with this power pole number is set as a power pole near the customer's house, and the same applies to the following processing.

ステップS9において需要家宅付近に電柱が設置されている場合には、この電柱に変圧器、低圧線が設置されているか否かを、設備データベース32に基づいて判断する(ステップS11)。そして、変圧器、低圧線が設置されていない場合には、低圧線を有する他の電柱から需要家宅付近の電柱まで低圧線を延長することが可能か否かを、設備データベース32に基づいて判断する(ステップS12)。この結果、延長が可能な場合には、必要な作業を低圧線の延長とし、メモリの作業エリアに「低圧線延長工事」を記憶する(ステップS13)。一方、延長が不可能な場合には、必要な作業を変圧器の新設とし、メモリの作業エリアに「変圧器新設工事」を記憶する(ステップS14)。   If a power pole is installed near the customer's house in step S9, it is determined based on the equipment database 32 whether or not a transformer and a low-voltage line are installed on the power pole (step S11). If no transformer or low-voltage line is installed, it is determined based on the equipment database 32 whether or not the low-voltage line can be extended from another utility pole having a low-voltage line to a utility pole near the customer's house. (Step S12). As a result, if the extension is possible, the necessary work is set as the extension of the low voltage line, and “low voltage line extension work” is stored in the work area of the memory (step S13). On the other hand, if the extension is impossible, the necessary work is newly installed, and “transformer new construction” is stored in the work area of the memory (step S14).

ステップS11において需要家宅付近の電柱に変圧器、低圧線が設置されている場合には、変圧器の電力量などを算出する(ステップS15)。すなわち、電力要求仕様および設備データベース32に基づいて、この電力要求仕様による電力を供給する場合の電灯変圧器の電力量、電圧降下量、低圧線に流れる電流値を算出する。そして、算出した電灯変圧器の電力量が、この変圧器の許容値(例えば、容量の160%)を超える場合(ステップS16で「Y」の場合)には、必要な作業を変圧器の取り替えとし、メモリの作業エリアに「変圧器取替工事」を記憶する(ステップS17)。   When a transformer and a low voltage line are installed on the utility pole near the customer's house in step S11, the amount of power of the transformer and the like are calculated (step S15). That is, based on the power requirement specification and the facility database 32, the amount of power of the lamp transformer, the amount of voltage drop, and the value of the current flowing through the low voltage line when power is supplied according to the power requirement specification are calculated. If the calculated power amount of the light transformer exceeds the allowable value (for example, 160% of the capacity) of the transformer (in the case of “Y” in step S16), the necessary work is replaced with the transformer. And "transformer replacement work" is stored in the work area of the memory (step S17).

また、算出した電圧降下量が、予め設定されている許容値(例えば、5V)を超える場合(ステップS18で「Y」の場合)には、必要な作業を変圧器の移動とし、メモリの作業エリアに「変圧器移動工事」を記憶する(ステップS19)。なお、必要な作業を高圧線の変調などとしてもよい。さらに、算出した低圧線に流れる電流値が、各線種(線径)ごとに定められている許容電流値を超える場合(ステップS20で「Y」の場合)には、必要な作業を低圧線の線種変更(太い線径に変更)とし、メモリの作業エリアに「低圧線変更工事」を記憶する(ステップS21)。なお、必要な作業を負荷の分割などとしてもよい。   If the calculated voltage drop exceeds a preset allowable value (for example, 5 V) (in the case of “Y” in step S18), the necessary work is taken as the movement of the transformer, and the work of the memory is performed. The “transformer moving work” is stored in the area (step S19). The necessary work may be modulation of a high voltage line. Furthermore, when the calculated current value flowing through the low-voltage line exceeds the allowable current value determined for each line type (wire diameter) (in the case of “Y” in step S20), the necessary work is performed on the low-voltage line. The line type is changed (changed to a thicker wire diameter), and “low-voltage line change work” is stored in the work area of the memory (step S21). The necessary work may be divided into loads.

一方、これらの外線工事に該当しない場合(ステップS20で「N」の場合)には、必要な作業を外線工事を要しない作業とし、メモリの作業エリアに「非外線工事」を記憶する(ステップS22)ものである。   On the other hand, when it does not correspond to these external line works (in the case of “N” in step S20), the necessary work is regarded as work that does not require external line work, and “non-external line work” is stored in the work area of the memory (step S22).

以上のようにこの第1の割出タスク331では、ひとつの電力要求仕様に対してひとつの作業のみを割り出すようになっているが、複数の作業を割り出すようにしてもよい。すなわち、例えば、ステップS3またはS4の処理後にステップS5に進み、さらにステップS7またはS8の処理後にステップS9に進むなどして、すべての作業(外線工事)の該当性について判断するようにしてもよい。   As described above, in the first indexing task 331, only one operation is determined for one power requirement specification, but a plurality of operations may be determined. That is, for example, the process proceeds to step S5 after the process of step S3 or S4, and further proceeds to step S9 after the process of step S7 or S8. .

第2の割出タスク332では、図6に示すように、まず、作業(工事)の位置関係を検討する(ステップS31)。すなわち、電柱から需要家宅に引き込む引込線の位置や、作業対象の電柱と作業を行うために必要な場所(道路)との関係などを、第1の割出タスク331で割り出した作業と電力要求仕様および設備データベース32に基づいて検討し、割り出す。その結果、図7に示すように、新設の引込線が国道や県道、河川などを横断、縦断したり(上空占用する)、官公庁土地に電柱を設置したりする場合(ケース1)には、占用申請が必要と判断し、メモリの申請等エリアに「占用申請」を記憶する(ステップS32)。   In the second indexing task 332, as shown in FIG. 6, first, the positional relationship of work (construction) is examined (step S31). That is, the work and power requirement specifications determined by the first indexing task 331, such as the position of the lead-in line drawn from the power pole to the customer's house, the relationship between the work pole and the place (road) necessary for the work, etc. And based on the equipment database 32, it is determined. As a result, as shown in Fig. 7, when a new service line crosses and traverses national roads, prefectural roads, rivers, etc. (occupies the sky) or installs utility poles on public land (case 1), It is determined that an application is necessary, and “occupation application” is stored in the application application area in the memory (step S32).

同様に、外線工事のために交通規制を行って国道などを一時的に占用する場合(ケース2)には、一時占用申請が必要と判断し、メモリの申請等エリアに「一時占用申請」を記憶する(ステップS33)。さらに、作業が歩道での簡易な作業などの場合(ケース3)には、作業の届出が必要と判断し、メモリの申請等エリアに「作業の届出」を記憶する(ステップS34)。一方、いずれのケース1〜3にも該当しない場合には、申請等は不要と判断し、メモリの申請等エリアに「不要」を記憶する(ステップS35)ものである。   Similarly, when traffic restrictions are imposed for outside line construction and national roads are temporarily occupied (case 2), it is determined that a temporary occupation application is required, and a “temporary occupation application” is entered in the memory application area, etc. Store (step S33). Further, when the work is a simple work on the sidewalk (case 3), it is determined that the work report is necessary, and “work report” is stored in the memory application area (step S34). On the other hand, if none of the cases 1 to 3 is applicable, it is determined that the application is unnecessary, and “unnecessary” is stored in the application application area of the memory (step S35).

見積タスク34は、作業割出タスク33で割り出された結果(作業と申請などの要否)に基づいて、電力要求仕様に適合する電力を供給するのに要する期間(必要期間)を見積もるタスクであり、図8に示すフローチャートに基づいている。   The estimation task 34 is a task for estimating a period (necessary period) required to supply power that conforms to the power requirement specification based on the result (the necessity of work and application) calculated by the work indexing task 33. And based on the flowchart shown in FIG.

まず、割り出された作業に対する標準工期を取得する(ステップS41)。具体的には、図9に示すように工事内容ごとの標準工期が記憶された標準工期テーブル341が設けられ、この標準工期テーブル341から該当する作業の標準工期を取得する。次に、割り出された申請などに対する標準許可期間を取得する(ステップS42)。具体的には、図10に示すように申請等の種類ごとの標準許可期間(許認可されるまでの標準的な期間)が記憶された標準許可期間テーブル342が設けられ、この標準許可期間テーブル342から該当する申請などの標準許可期間を取得する。   First, a standard work period for the determined work is acquired (step S41). Specifically, as shown in FIG. 9, a standard work schedule table 341 in which a standard work schedule for each work content is stored is provided, and the standard work schedule of the corresponding work is acquired from the standard work schedule table 341. Next, a standard permission period for the determined application is acquired (step S42). Specifically, as shown in FIG. 10, a standard permission period table 342 storing a standard permission period (standard period until permission is granted) for each type of application or the like is provided, and this standard permission period table 342 is provided. Obtain a standard permission period for applicable applications from.

続いて、作業割出タスク33で割り出された作業と申請などとを同時進行することが可能か否かを判断する(ステップS43)。すなわち、許認可がおりるまでの期間中に作業の準備などを行うことが可能で、標準工期と標準許可期間とが重なることが可能か否かを判断する。この判断は、作業の内容と申請などの内容とに基づいて行われる。そして、同時進行が可能な場合には、標準工期と標準許可期間とのうち長い方の期間を必要期間とし(ステップS44)、同時進行ができない場合には、標準工期と標準許可期間とを加算した期間を必要期間とする(ステップS45)ものである。   Subsequently, it is determined whether or not the work determined by the work indexing task 33 and the application can proceed simultaneously (step S43). In other words, it is possible to prepare for work during the period until permission is granted, and determine whether the standard construction period and the standard permission period can overlap. This determination is made based on the contents of the work and the contents of the application. If simultaneous progress is possible, the longer period of the standard work period and standard permission period is set as the required period (step S44). If simultaneous progress is not possible, the standard work period and standard permission period are added. This period is set as a necessary period (step S45).

ここで、上記のように第1の割出タスク331において複数の作業を割り出す場合には、各作業に対する標準工期を取得し、これらの作業が同時進行可能か否かによって、最も長い標準工期を工期としたり、すべての標準工期を加算して工期としたりする。そして、この工期と標準許可期間とに基づいて、上記と同様にして(ステップS44、S45)必要期間を見積もる。   Here, when a plurality of operations are determined in the first indexing task 331 as described above, the standard construction period for each work is acquired, and the longest standard construction period is determined depending on whether these operations can proceed simultaneously. Set the work period or add all the standard work periods to make the work period. Based on the construction period and the standard permission period, the necessary period is estimated in the same manner as described above (steps S44 and S45).

次に、このような構成の期間見積システム1の作用などについて、図11に示すタイミングチャートに基づいて説明する。   Next, the operation of the period estimation system 1 having such a configuration will be described based on the timing chart shown in FIG.

まず、パーソナルコンピュータ2から見積サーバ3のWebページの電気使用申込メニュにアクセスすると(ステップS51)、電力要求仕様を入力する入力画面が表示される。そして、例えば建築会社と電気工事店とが協議しながら、入力画面に従って電力要求仕様を入力し、送信操作を行うと(ステップS52)、入力した電力要求仕様が見積サーバ3に送信され(ステップS53)、上記のようにして申込受付タスク31によって電力要求仕様がメモリに記憶される。   First, when the personal computer 2 accesses the electricity use application menu on the Web page of the estimation server 3 (step S51), an input screen for inputting power requirement specifications is displayed. Then, for example, when a construction company and an electric construction shop discuss and input a power requirement specification according to the input screen and perform a transmission operation (step S52), the input power requirement specification is transmitted to the estimation server 3 (step S53). ), The power requirement specification is stored in the memory by the application reception task 31 as described above.

次に、見積サーバ3において第1の割出タスク331が起動され(ステップS54)、上記のようにして電力要求仕様に適合する電力を供給するのに要する作業が割り出される。さらに、第2の割出タスク332が起動され(ステップS55)、上記のようにして作業を行うためにどのような申請や届出が必要か、あるいは不要であるかが割り出される。続いて、見積タスク34が起動され(ステップS56)、上記のようにして電力要求仕様に適合する電力を供給するのに要する期間(必要期間)が見積もられる。そして、見積もられた必要期間が、割り出された作業と申請等とともにパーソナルコンピュータ2に送信されるものである(ステップS57)。   Next, the first indexing task 331 is activated in the estimation server 3 (step S54), and the work required to supply power that conforms to the power requirement specification is determined as described above. Further, the second indexing task 332 is activated (step S55), and it is determined what kind of application or notification is necessary or unnecessary for performing the work as described above. Subsequently, the estimation task 34 is activated (step S56), and a period (necessary period) required to supply power that conforms to the power requirement specification is estimated as described above. Then, the estimated necessary period is transmitted to the personal computer 2 together with the determined work and application (step S57).

以上のように、この期間見積システム1によれば、電気工事店のパーソナルコンピュータ2から電力要求仕様を入力、送信することで、電力要求仕様に適合する電力を供給するのに要する期間が見積サーバ3からパーソナルコンピュータ2に送信される。このため、電気工事店や建築会社、あるいは需要家(家屋の購入者)は、電気を使用できるようになるまでの期間を迅速かつ容易に知ることができる。この結果、屋内配線の計画や電気の使用開始予定日などを適正に決定することが可能となる。   As described above, according to the period estimation system 1, the period required to supply power that conforms to the power requirement specification by inputting and transmitting the power requirement specification from the personal computer 2 of the electric construction shop is estimated server. 3 to the personal computer 2. For this reason, an electric construction shop, a construction company, or a customer (a purchaser of a house) can quickly and easily know the period until electricity can be used. As a result, it is possible to appropriately determine a plan for indoor wiring, a scheduled date for starting use of electricity, and the like.

しかも、電力を使用する予定場所や予定負荷などと、電力設備の種類や容量、設置場所などとに基づいて、電力を供給するための作業と、その許認可の申請や届出の要否、内容を割り出し、その結果に基づいて電力を供給するのに要する期間を見積もる。すなわち、外線工事などの作業や所轄官庁への申請などを考慮して、必要期間を見積もるため、需要家の要望に適合した適正な必要期間が見積もられる。さらに、見積もられた必要期間とともに、電力供給に必要な作業と申請等とがパーソナルコンピュータ2に送信されるため、電気工事店や建築会社などは、どうような作業や申請などのためにどのくらいの期間を要するかを知得することができる。   In addition, based on the planned location where power is used and the planned load, and the type, capacity, location, etc. of the power facility, the work to supply power, the necessity of application and notification of permission and notification, and the contents Determine the time required to supply power based on the result. In other words, since the necessary period is estimated in consideration of work such as outside line construction or application to the competent authority, an appropriate necessary period suitable for the demand of the customer is estimated. In addition, the work and application necessary for power supply are transmitted to the personal computer 2 together with the estimated required period, so how much work or application the electrical construction shop or construction company has for what kind of work or application. It is possible to know whether this period is required.

以上、この発明の実施の形態について説明したが、具体的な構成は、上記の実施の形態に限られるものではなく、この発明の要旨を逸脱しない範囲の設計の変更等があっても、この発明に含まれる。例えば、作業割出タスク33における判断要素は上記の判断要素(ステップS1、S5、S9など)に限らず、その他の判断要素・条件に基づいて作業を割り出してもよい。また、上記の実施の形態は、インターネットNWを介して電力要求仕様や見積結果の送信などを行うようにしているが、電話網を介して音声により電力要求仕様や見積結果の通知などを行うようにしてもよい。さらに、新築家屋に電力を供給する場合のみならず、電力使用の契約変更に伴う負荷増設の場合や、臨時電力を供給する場合などにも適用することができる。   Although the embodiment of the present invention has been described above, the specific configuration is not limited to the above embodiment, and even if there is a design change or the like without departing from the gist of the present invention, Included in the invention. For example, the determination element in the work determination task 33 is not limited to the above determination elements (steps S1, S5, S9, etc.), and the work may be determined based on other determination elements / conditions. In the above embodiment, the power requirement specification and the estimation result are transmitted via the Internet NW, but the power requirement specification and the estimation result are notified by voice via the telephone network. It may be. Furthermore, the present invention can be applied not only to supplying power to a newly-built house, but also to adding a load accompanying a change in power usage contract or supplying temporary power.

ところで、次のような電力供給に要する期間見積プログラム(以下、「期間見積プログラム」という)を汎用のコンピュータにインストールしてもよい。すなわち、電力を使用する予定場所や予定負荷などを電力要求仕様とし、コンピュータを、電力設備の種類や容量、設置場所などの設備情報を記憶する記憶手段(設備データベース32に該当)と、入力された電力要求仕様と記憶手段に記憶されている設備情報とに基づいて、電力要求仕様に適合する電力を供給するのに要する作業と、該作業を行うために許認可の申請や届出が必要か否かを割り出す作業割出手段(作業割出タスク33に該当)と、作業割出手段で割り出された結果に基づいて、電力要求仕様に適合する電力を供給するのに要する期間を見積もる見積手段(見積タスク34に該当)、として機能させるための期間見積プログラムとする。これにより、いずれの建築会社や電気工事店などにおいても、電力供給に要する期間を容易かつ迅速に知得することができる。   Incidentally, the following period estimation program (hereinafter referred to as “period estimation program”) required for power supply may be installed in a general-purpose computer. That is, the planned location where power is used, the planned load, etc. are used as power requirement specifications, and the computer is input as storage means (corresponding to the facility database 32) for storing facility information such as the type, capacity, and location of the power facility. Work required to supply power that conforms to the power requirement specification based on the power requirement specification and the facility information stored in the storage means, and whether or not an application for approval or notification is required to perform the task A work indexing means (corresponding to the work indexing task 33) for estimating the power, and an estimation means for estimating a time period required to supply power that conforms to the power requirement specification based on the result calculated by the work indexing means (Corresponding to the estimation task 34). Thereby, in any construction company or electric construction shop, the period required for power supply can be easily and quickly known.

この発明の実施の形態に係る期間見積システムを示す概略構成図である。It is a schematic block diagram which shows the period estimation system which concerns on embodiment of this invention. 図1のシステムの設備データベースに記憶されている電柱データを示すデータ構成図である。It is a data block diagram which shows the utility pole data memorize | stored in the equipment database of the system of FIG. 図1のシステムの設備データベースに記憶されている地図データの一例を示す図である。It is a figure which shows an example of the map data memorize | stored in the equipment database of the system of FIG. 図1のシステムの作業割出タスクの第1の割出タスクのフローチャートである。It is a flowchart of the 1st indexing task of the work indexing task of the system of FIG. 図4の続きを示すフローチャートである。5 is a flowchart showing a continuation of FIG. 図1のシステムの作業割出タスクの第2の割出タスクのフローチャートである。It is a flowchart of the 2nd indexing task of the work indexing task of the system of FIG. 図6の第2の割出タスクにおいてケース1に該当する一例を示す図である。FIG. 7 is a diagram illustrating an example corresponding to case 1 in the second indexing task of FIG. 6. 図1のシステムの見積タスクのフローチャートである。It is a flowchart of the estimation task of the system of FIG. 図8の見積タスクにおける標準工期テーブルの一例を示す図である。It is a figure which shows an example of the standard work schedule table in the estimation task of FIG. 図8の見積タスクにおける標準許可期間テーブルの一例を示す図である。It is a figure which shows an example of the standard permission period table in the estimation task of FIG. 図1のシステムの作用などを示すタイミングチャートである。It is a timing chart which shows the effect | action of the system of FIG.

符号の説明Explanation of symbols

1 期間見積システム
2 パーソナルコンピュータ(仕様入力手段)
3 見積サーバ
31 申込受付タスク(仕様受信手段)
32 設備データベース(記憶手段)
321 電柱データ
322 地図データ
33 作業割出タスク(作業割出手段)
331 第1の割出タスク
332 第2の割出タスク
34 見積タスク(見積手段)
341 標準工期テーブル
342 標準許可期間テーブル
NW 通信網(インターネット)
1 Period estimation system 2 Personal computer (specification input means)
3 Estimate server 31 Application acceptance task (specification receiving means)
32 Equipment database (storage means)
321 Telephone pole data 322 Map data 33 Work indexing task (work indexing means)
331 First indexing task 332 Second indexing task 34 Estimating task (estimating means)
341 Standard construction period table 342 Standard permission period table NW Communication network (Internet)

Claims (2)

電力を使用する予定場所や予定負荷などの電力要求仕様を入力する仕様入力手段と、
前記仕様入力手段で入力された電力要求仕様を受信する仕様受信手段と、
電力設備の種類や容量、設置場所などの設備情報を記憶する記憶手段と、
前記仕様受信手段で受信された電力要求仕様と前記記憶手段に記憶されている設備情報とに基づいて、前記電力要求仕様に適合する電力を供給するのに要する作業と、該作業を行うために許認可の申請や届出が必要か否かを割り出す作業割出手段と、
前記作業割出手段で割り出された結果に基づいて、前記電力要求仕様に適合する電力を供給するのに要する期間を見積もる見積手段と、
を備えることを特徴とする電力供給に要する期間見積システム。
Specification input means for inputting power requirement specifications such as a planned place where power is used and a planned load;
Specification receiving means for receiving the power requirement specification input by the specification input means;
Storage means for storing equipment information such as type and capacity of power equipment, installation location;
Based on the power requirement specification received by the specification receiving means and the facility information stored in the storage means, work required to supply power that conforms to the power requirement specification, and for performing the work A work indexing means for determining whether or not a license application or notification is necessary,
Estimating means for estimating a period of time required to supply power that conforms to the power requirement specification based on the result determined by the work indexing means;
A period estimation system required for power supply, comprising:
電力を使用する予定場所や予定負荷などを電力要求仕様とし、
コンピュータを、
電力設備の種類や容量、設置場所などの設備情報を記憶する記憶手段と、
入力された電力要求仕様と前記記憶手段に記憶されている設備情報とに基づいて、前記電力要求仕様に適合する電力を供給するのに要する作業と、該作業を行うために許認可の申請や届出が必要か否かを割り出す作業割出手段と、
前記作業割出手段で割り出された結果に基づいて、前記電力要求仕様に適合する電力を供給するのに要する期間を見積もる見積手段、
として機能させるための電力供給に要する期間見積プログラム。
The power demand specification is the place where the power is to be used and the planned load.
Computer
Storage means for storing equipment information such as type and capacity of power equipment, installation location;
Based on the input power requirement specification and the facility information stored in the storage means, work required to supply power that conforms to the power requirement specification, and application and notification of permission to perform the task Work indexing means for determining whether or not is necessary,
Estimating means for estimating a period of time required to supply power that conforms to the power requirement specification based on the result determined by the work indexing means;
A program for estimating the period of time required for power supply to function.
JP2008285441A 2008-11-06 2008-11-06 Period estimation system and period estimation program required for power supply Expired - Fee Related JP5208682B2 (en)

Priority Applications (1)

Application Number Priority Date Filing Date Title
JP2008285441A JP5208682B2 (en) 2008-11-06 2008-11-06 Period estimation system and period estimation program required for power supply

Applications Claiming Priority (1)

Application Number Priority Date Filing Date Title
JP2008285441A JP5208682B2 (en) 2008-11-06 2008-11-06 Period estimation system and period estimation program required for power supply

Publications (2)

Publication Number Publication Date
JP2010113507A true JP2010113507A (en) 2010-05-20
JP5208682B2 JP5208682B2 (en) 2013-06-12

Family

ID=42302026

Family Applications (1)

Application Number Title Priority Date Filing Date
JP2008285441A Expired - Fee Related JP5208682B2 (en) 2008-11-06 2008-11-06 Period estimation system and period estimation program required for power supply

Country Status (1)

Country Link
JP (1) JP5208682B2 (en)

Citations (1)

* Cited by examiner, † Cited by third party
Publication number Priority date Publication date Assignee Title
JP2003132120A (en) * 2001-10-19 2003-05-09 Burisu Direct Kk Electric power sale support system and computer readable recording medium

Patent Citations (1)

* Cited by examiner, † Cited by third party
Publication number Priority date Publication date Assignee Title
JP2003132120A (en) * 2001-10-19 2003-05-09 Burisu Direct Kk Electric power sale support system and computer readable recording medium

Also Published As

Publication number Publication date
JP5208682B2 (en) 2013-06-12

Similar Documents

Publication Publication Date Title
US11714465B2 (en) Systems and methods for aggregation and integration of distributed grid elements inputs for providing an interactive electric power grid geographic visualization
Burnham et al. Enabling fast charging–Infrastructure and economic considerations
Dow et al. A novel approach for evaluating the impact of electric vehicles on the power distribution system
US10281507B2 (en) Generator sizing
US20150206229A1 (en) Apparatus and method for renting vehicle using reverse auction mechanism
Andrade et al. Regional‐scale allocation of fast charging stations: travel times and distribution system reinforcements
JP2015042071A (en) Power distribution system facility evaluation device and power distribution system facility evaluation method
JP6405871B2 (en) Information output method for power distribution equipment, information output program for power distribution equipment, and information output device
CN110197290A (en) Vehicle management equipment, vehicles management method and non-transient computer-readable media
Dallmer‐Zerbe et al. Analysis of the exploitation of EV fast charging to prevent extensive grid investments in suburban areas
JP5208682B2 (en) Period estimation system and period estimation program required for power supply
US8660821B2 (en) Designing utility networks for a geographic area
Stanfield et al. Key Decisions for Hosting Capacity Analyses
JP2008077369A (en) Information providing server, information providing method, and information providing program
US20150134387A1 (en) Optimizing inspection and maintenance of components using mobile device
Dutrieux et al. Assessing the impacts of distribution grid planning rules on the integration of renewable energy sources
Tokombayev et al. High temperature low sag upgrades and payback for the economic operation improvement of power transmission systems
Modarresi et al. An operating reserve risk map for quantifiable reliability performances in renewable power systems
JP5971346B2 (en) Distribution management device, voltage determination method, and voltage determination program
Baptista et al. IEVCC-A Mesh Managed Network for Electric Vehicle Charging
Van Oosten et al. Optimal Design and Operation of Temporary Power Installations: Case Study on CO2 and Cost Savings for Outdoor Festivals in the Netherlands
Cuenca et al. Event-informed allocation of energy storage, voltage regulators and infrastructure upgrades in distribution network planning
Kheswa Residential electrification design topology evaluation model-the sustainable approach for residential developments
Beucker et al. Climate-neutral districts with decentralized energy production, E-Mobility and through the formation of an energy community exchange of electricity and heat
Butler et al. Connectmore: enabling connections for EV stakeholders

Legal Events

Date Code Title Description
A621 Written request for application examination

Free format text: JAPANESE INTERMEDIATE CODE: A621

Effective date: 20110524

A977 Report on retrieval

Free format text: JAPANESE INTERMEDIATE CODE: A971007

Effective date: 20121115

A131 Notification of reasons for refusal

Free format text: JAPANESE INTERMEDIATE CODE: A131

Effective date: 20121120

A521 Request for written amendment filed

Free format text: JAPANESE INTERMEDIATE CODE: A523

Effective date: 20130110

TRDD Decision of grant or rejection written
A01 Written decision to grant a patent or to grant a registration (utility model)

Free format text: JAPANESE INTERMEDIATE CODE: A01

Effective date: 20130205

A61 First payment of annual fees (during grant procedure)

Free format text: JAPANESE INTERMEDIATE CODE: A61

Effective date: 20130220

FPAY Renewal fee payment (event date is renewal date of database)

Free format text: PAYMENT UNTIL: 20160301

Year of fee payment: 3

R150 Certificate of patent or registration of utility model

Ref document number: 5208682

Country of ref document: JP

Free format text: JAPANESE INTERMEDIATE CODE: R150

Free format text: JAPANESE INTERMEDIATE CODE: R150

FPAY Renewal fee payment (event date is renewal date of database)

Free format text: PAYMENT UNTIL: 20160301

Year of fee payment: 3

R250 Receipt of annual fees

Free format text: JAPANESE INTERMEDIATE CODE: R250

R250 Receipt of annual fees

Free format text: JAPANESE INTERMEDIATE CODE: R250

R250 Receipt of annual fees

Free format text: JAPANESE INTERMEDIATE CODE: R250

R250 Receipt of annual fees

Free format text: JAPANESE INTERMEDIATE CODE: R250

LAPS Cancellation because of no payment of annual fees