JP2006119842A - Power generation facilities construction management apparatus and power generation facilities construction management method - Google Patents

Power generation facilities construction management apparatus and power generation facilities construction management method Download PDF

Info

Publication number
JP2006119842A
JP2006119842A JP2004305976A JP2004305976A JP2006119842A JP 2006119842 A JP2006119842 A JP 2006119842A JP 2004305976 A JP2004305976 A JP 2004305976A JP 2004305976 A JP2004305976 A JP 2004305976A JP 2006119842 A JP2006119842 A JP 2006119842A
Authority
JP
Japan
Prior art keywords
power generation
database
sub
registered
generation facility
Prior art date
Legal status (The legal status is an assumption and is not a legal conclusion. Google has not performed a legal analysis and makes no representation as to the accuracy of the status listed.)
Pending
Application number
JP2004305976A
Other languages
Japanese (ja)
Inventor
Yasuhiko Katsube
安彦 勝部
Hiromichi Yamamoto
博通 山本
Yoshiyuki Kawaguchi
善之 川口
Mutsumi Hashimoto
睦 橋本
Current Assignee (The listed assignees may be inaccurate. Google has not performed a legal analysis and makes no representation or warranty as to the accuracy of the list.)
Tokyo Electric Power Company Holdings Inc
Original Assignee
Tokyo Electric Power Co Inc
Priority date (The priority date is an assumption and is not a legal conclusion. Google has not performed a legal analysis and makes no representation as to the accuracy of the date listed.)
Filing date
Publication date
Application filed by Tokyo Electric Power Co Inc filed Critical Tokyo Electric Power Co Inc
Priority to JP2004305976A priority Critical patent/JP2006119842A/en
Publication of JP2006119842A publication Critical patent/JP2006119842A/en
Pending legal-status Critical Current

Links

Images

Landscapes

  • Management, Administration, Business Operations System, And Electronic Commerce (AREA)

Abstract

<P>PROBLEM TO BE SOLVED: To provide a power generation facilities construction management apparatus and power generation facilities management method capable of managing processes for the construction-scheduled power generation facilities while compensating for a leakage of concealment information on knowhow or the like between participants, and easily grasping a system and processes on a stage of construction project basis. <P>SOLUTION: The power generation facilities construction management apparatus comprises: an entire project management means 131 registering the actual results of a major process for the constructed power generation facilities provided by an electric power company T as a major process for the construction-scheduled power facilities on a database 12; an individual process management means 132 registering the actual results of a sub-process of the constructed power generation facilities provided by the participants A, B, C as the sub-process for the construction-scheduled power generation facilities by associating the sub-process with the major process on the database; and an access permission means 133 permitting the access of registration contents toward the database 12. The access permission means 133 permits the electric power company T to access the major process and the sub-process in the database 12, and permits each of the participants A, B, C to access the sub-process in the database 12. <P>COPYRIGHT: (C)2006,JPO&NCIPI

Description

本発明は、建設予定の発電設備の工程を、既建設の発電設備についての電力会社および参加者の工程履歴に基づき参加者間のノウハウ等の秘匿情報の漏洩を補償しつつ管理できる発電設備建設管理装置および発電設備建設管理方法、ならびに建設予定の発電設備の工程を参加者間のノウハウ等の秘匿情報の漏洩を補償しつつ管理できる発電設備建設管理装置および発電設備建設管理方法に関する。   The present invention relates to a power generation facility construction capable of managing a process of a power generation facility scheduled to be constructed while compensating for leakage of secret information such as know-how between participants based on the process history of the power company and the participants regarding the power generation facilities already constructed. The present invention relates to a management apparatus and a power generation facility construction management method, and a power generation facility construction management apparatus and a power generation facility construction management method capable of managing a process of a power generation facility to be constructed while compensating for leakage of secret information such as know-how among participants.

発電設備の建設に際しては、電力会社Tは、建設会社A(複数社であることもある)に建築構造物を発注し、主機メーカB(たとえば、一社)に機械・電気設備を発注する。   When constructing a power generation facility, the electric power company T orders a building structure from the construction company A (which may be a plurality of companies) and orders mechanical / electrical equipment from the main machine manufacturer B (for example, one company).

従来、主機の付随設備(たとえば、制御装置、監視装置、水処理設備等)については、たとえば主機メーカBが指定したメーカが設置工事等を行う。   Conventionally, for the auxiliary equipment (for example, a control device, a monitoring device, a water treatment facility, etc.) of the main machine, for example, a manufacturer designated by the main machine manufacturer B performs installation work and the like.

ところで、近時、建設コストを下げるため、電力会社Tは、主機の付随設備については、当該設備のメーカ(以下、「分離メーカ」と言う)に直接、設置工事を発注することがある。この場合、図1に示すように、電力会社Tは主要工程表910を、建設会社Aは建築・土木工程表911を、主機メーカBは系統別工程表912を持ち寄り、三者T,A,Bにより発電設備の開始から完成に至るまでの作業手順について調整・検討(X)を行い、詳細な建設スケジュール92を作成する。この建設スケジュール92は、通常、膨大なページ数の紙の情報であり、これらは関係者に配布される。   By the way, recently, in order to reduce the construction cost, the electric power company T may place an order for installation of the auxiliary equipment of the main machine directly from the manufacturer of the equipment (hereinafter referred to as “separation maker”). In this case, as shown in FIG. 1, the electric power company T brings the main process table 910, the construction company A brings the building / civil engineering process table 911, the main machine manufacturer B brings the system-specific process table 912, and the three parties T, A, The detailed construction schedule 92 is prepared by adjusting and examining (X) the work procedure from the start to the completion of the power generation facility by B. The construction schedule 92 is usually paper information with a huge number of pages, and these are distributed to the parties concerned.

また、建設工事が開始された後は、たとえば毎月、建設会社A、主機メーカB、分離メーカC(通常複数)は、作業手順について見直し・確認等を含む調整・検討x(k)を行い、当月、翌月についての予定工程および前月の実績工程を、作業エリアごとに作成する。なお、kは1,2,3,・・・nであり、工期が5年で予定通り建設がなされる場合にはn=12(月)×5(年)=60(月)である。たとえば、具体的には、建設会社Aは建築・土木3ヶ月工程表931を、主機メーカBは系統別3ヶ月工程表932を、分離メーカCは分離系統3ヶ月工程表933を作成する。一方、電力会社Tは、必要な帳票930を適時(たとえば、一月ごとに)検討・調査して作成する。これらの3ヶ月工程表931,932,933、帳票930も、通常、膨大なページ数の紙の情報であり、これらは関係者に配布される。   Also, after the construction work is started, for example, every month, construction company A, main machine maker B, and separation maker C (usually multiple) perform adjustment / examination x (k) including review and confirmation of work procedures, The scheduled process for the current month and the next month and the actual process for the previous month are created for each work area. K is 1, 2, 3,..., And n = 12 (months) × 5 (years) = 60 (months) when the construction period is 5 years and construction is performed as planned. For example, the construction company A creates a three-month process table 931 for construction and civil engineering, the main manufacturer B creates a three-month process table 932 for each system, and the separation manufacturer C creates a three-month process table 933 for a separated system. On the other hand, the electric power company T creates a necessary form 930 by examining and investigating it in a timely manner (for example, every month). These three-month process charts 931, 932, 933, and a form 930 are also usually information on paper with a huge number of pages, and these are distributed to the parties concerned.

ところで、電力会社Tは、建設スケジュール92や、3ヶ月工程表931,932,933を、対応して吟味することで、工事の進捗具合の把握等を含む工程管理(Y)をしなくてはならないが、工程の表示スタイルは、建設スケジュール92と、3ヶ月工程表931,932,933とで、互いに異なる(すなわち、統一されていない)場合がある。このため、工程管理に熟練していない者にとって、たとえば取り合いの調整等の工程管理(Y)を効率良く行うことができないという不都合がある。   By the way, the electric power company T must perform the process management (Y) including grasping the progress of the construction by examining the construction schedule 92 and the three-month schedules 931, 932, and 933 correspondingly. However, the process display style may differ (i.e., not unified) between the construction schedule 92 and the three-month process tables 931, 932, and 933. For this reason, there is an inconvenience for those who are not skilled in process management that, for example, process management (Y) such as adjustment of the balance cannot be performed efficiently.

本発明の目的は、建設予定の発電設備の工程を、既建設の発電設備についての電力会社および参加者(建設会社、主機メーカ、分離メーカ等)の工程履歴に基づき参加者間のノウハウ等の秘匿情報の漏洩を補償しつつ管理でき、系統の把握、工区別の工程把握が容易な発電設備建設管理装置および発電設備建設管理方法を提供することにある。   The purpose of the present invention is to determine the process of the power generation facility to be constructed, such as know-how between participants based on the process history of the power company and participants (construction company, main machine manufacturer, separation manufacturer, etc.) of the existing power generation facility. It is an object of the present invention to provide a power generation facility construction management apparatus and a power generation facility construction management method that can be managed while compensating for leakage of confidential information, and that can easily grasp the system and the process differentiation process.

本発明の目的は、建設予定の発電設備の工程を参加者間のノウハウ等の秘匿情報の漏洩を補償しつつ管理でき、系統の把握、工区別の工程把握が容易な発電設備建設管理装置および発電設備建設管理方法を提供することにある。   An object of the present invention is to manage a power generation facility planned to be constructed while compensating for leakage of secret information such as know-how between participants, and to easily grasp the system and the process of distinguishing the construction, It is to provide a power generation facility construction management method.

本発明の発電設備建設管理装置は、建設予定の発電設備の工程を、既建設の発電設備についての電力会社および参加者(参加企業:建設会社、主機メーカ、分離メーカ等)の工程履歴に基づき管理するものであって、前記既建設の発電設備についての前記電力会社により提供される主要工程の実績を、前記建設予定の発電設備の主要工程として、データベースに登録する全体プロジェクト管理手段と、前記既建設の発電設備についての前記参加者により提供される副工程の実績を、前記建設予定の発電設備の副工程として、前記主要工程に関連付けして前記データベースに登録する個別工事管理手段と、前記データベースへの登録内容へのアクセスを許可するアクセス許可手段とを備え、前記アクセス許可手段は、前記電力会社に対し前記データベースに登録された前記主要工程および前記副工程の内容へのアクセスを許可し、前記各参加者に対し前記データベースに登録された各自が提供した前記副工程の内容にアクセスを許可し、前記データベースに登録された他の参加者が提供した前記副工程に自己の工程実行に必要な場合にのみアクセスを許可することを特徴とする。本発明の発電設備建設管理装置を、入力支援システムまたは管理支援システムとして使用することで、建設予定の発電設備の工程を参加者間のノウハウ等の秘匿情報の漏洩を補償しつつ管理でき、系統の把握、工区別の工程把握が容易となる。   The power generation facility construction management apparatus according to the present invention determines the process of the power generation facility to be constructed based on the process history of the power company and the participants (participating companies: construction company, main machine manufacturer, separation manufacturer, etc.) regarding the already-constructed power generation facility. An overall project management means for registering, as a main process of the power generation facility to be built, a main process of the power generation facility to be registered in a database. Individual construction management means for registering in the database in association with the main process, as a sub-process of the power generation facility scheduled to be constructed, as a sub-process of the sub-process provided by the participant for the power generation facility already constructed; Access permission means for permitting access to the registered contents in the database, the access permission means for the power company Allowing access to the contents of the main process and the sub-process registered in the database, permitting each participant to access the contents of the sub-process provided by each registered in the database, and the database Access to the sub-process provided by another participant registered in the above is permitted only when it is necessary for its own process execution. By using the power generation facility construction management device of the present invention as an input support system or a management support system, it is possible to manage the power generation facility process scheduled for construction while compensating for leakage of secret information such as know-how among participants, This makes it easy to grasp the process and distinguish between processes.

また、本発明の発電設備建設管理装置は、建設予定の発電設備の工程を管理するものであって、前記建設予定の発電設備の主要工程をデータベースに登録する全体プロジェクト管理手段と、
前記建設予定の発電設備の副工程を前記主要工程に関連付けして前記データベースに登録する個別工事管理手段と、前記データベースへの登録内容へのアクセスを許可するアクセス権許可手段とを備え、前記アクセス許可手段は、前記電力会社に対し前記データベースに登録された前記主要工程および前記副工程の内容にアクセスを許可し、前記各参加者に対し前記データベースに登録された各自が提供した前記副工程の内容にアクセスを許可し、前記データベースに登録された他の参加者が提供した前記副工程に自己の工程実行に必要な場合にのみアクセスを許可することをも特徴とする。
Further, the power generation facility construction management device of the present invention manages the process of the power generation facility scheduled to be constructed, and the whole project management means for registering the main process of the power generation facility planned for construction in the database,
An individual construction management means for registering the sub-process of the power generation facility to be constructed in the database in association with the main process; and an access right permission means for permitting access to the registered contents in the database. The permission means permits the electric power company to access the contents of the main process and the sub-process registered in the database, and the sub-process provided by each registered in the database for each participant. It is also characterized in that access is permitted to the contents, and access is permitted only when it is necessary for execution of its own process in the sub-process provided by another participant registered in the database.

本発明の発電設備建設管理装置では、前記電力会社による、前記主要工程登録手段に登録された前記主要工程の内容へのアクセスは登録内容の書き換えを含み、前記各参加者による、各自が提供した前記個別工事管理手段に登録された前記副工程の内容へのアクセスは、登録内容の書き換えを含むことができる。
本発明の発電設備建設管理装置では、前記電力会社による、登録内容の書き換えは、前記各参加者による工程の取り合い調整手順を含むことができる。
In the power generation facility construction management apparatus of the present invention, access to the contents of the main process registered in the main process registration means by the power company includes rewriting of the registered contents, and each participant provided by each participant Access to the contents of the sub-process registered in the individual construction management means can include rewriting of the registered contents.
In the power generation facility construction management device according to the present invention, the rewriting of the registered content by the electric power company can include a process coordination adjustment procedure by each participant.

本発明の発電設備建設管理装置では、前記電力会社による、前記個別工事管理手段に登録された前記副工程の内容へのアクセスは閲覧であり、前記各参加者による、他の参加者が提供した前記個別工事管理手段に登録された前記副工程の内容へのアクセスは閲覧であるようにできる。   In the power generation facility construction management device of the present invention, access to the contents of the sub-process registered in the individual construction management means by the power company is browsing, and provided by other participants by each participant. Access to the contents of the sub-process registered in the individual construction management means can be browsing.

本発明の発電設備建設管理装置では、建設予定の発電設備の一連の工程を抽出し、これをグループ化し、そのグループの作業工程をブレークダウンし、階層的に工程の内容を定義して管理を行うことができ、実行される作業工程を時系列で表現し、前記データベースには、前記電力会社および前記各参加者による各工程をワークパッケージとして登録することができる。すなわち、工程管理にWBS(ワークブレークダウンストラクチャー)の技法を導入することにより、各業務の品質,コスト,納期等を適切かつ明確に管理することができる。この場合には、データベースは、前記電力会社および前記各参加者による各工程がワークパッケージとして登録されるように構成される。   In the power generation facility construction management apparatus of the present invention, a series of processes of a power generation facility to be constructed is extracted, grouped, and the work process of the group is broken down, and the contents of the processes are defined hierarchically and managed. The work process to be executed can be expressed in a time series, and each process by the electric power company and each participant can be registered as a work package in the database. That is, by introducing WBS (Work Breakdown Structure) technique to process management, the quality, cost, delivery date, etc. of each business can be managed appropriately and clearly. In this case, the database is configured such that each process by the electric power company and each participant is registered as a work package.

本発明の発電設備建設管理方法は、建設予定の発電設備の工程を、既建設の発電設備についての電力会社および参加者の工程履歴に基づき管理するものであって、前記既建設の発電設備についての前記電力会社により提供される主要工程の実績を、前記建設予定の発電設備の主要工程として、データベースに登録し、前記既建設の発電設備についての前記参加者により提供される副工程の実績を、前記建設予定の発電設備の副工程として、前記主要工程に関連付けして前記データベースに登録し、前記電力会社に対し前記データベースに登録された前記主要工程および前記副工程の内容にアクセスを許可し、前記各参加者に対し前記データベースに登録された各自が提供した前記副工程の内容にアクセスを許可し、前記データベースに登録された他の参加者が提供した前記副工程の内容には自己の工程実行に必要な場合にのみアクセスを許可することを特徴とする。   The power generation facility construction management method of the present invention manages the process of the power generation facility scheduled to be built based on the process history of the electric power company and the participants regarding the already constructed power generation facility. The result of the main process provided by the electric power company is registered in the database as the main process of the power generation facility to be constructed, and the result of the sub-process provided by the participant for the power generation equipment already constructed The sub-process of the power generation facility to be constructed is registered in the database in association with the main process, and the power company is allowed to access the contents of the main process and the sub-process registered in the database. , Allowing each participant to access the contents of the sub-process provided by each registered in the database and registered in the database. The said contents of the secondary steps other participants provided and permits access only when required for self-process execution.

本発明の発電設備建設管理方法は、建設予定の発電設備の工程を管理する発電設備管理するものであって、前記建設予定の発電設備の主要工程をデータベースに登録し、前記建設予定の発電設備の副工程を前記主要工程に関連付けして前記データベースに登録し、前記既建設の発電設備についての前記参加者により提供される副工程の実績を、前記建設予定の発電設備の副工程として、前記主要工程に関連付けして前記データベースに登録し、前記電力会社に対し前記データベースに登録された前記主要工程および前記副工程の内容へのアクセスを許可し、前記各参加者に対し前記データベースに登録された各自が提供した前記副工程の内容にアクセスを許可し、前記データベースに登録された他の参加者が提供した前記副工程の内容には自己の工程実行に必要な場合にのみアクセスを許可することをも特徴とする。   The power generation facility construction management method of the present invention manages power generation facilities for managing the processes of the power generation facilities scheduled for construction, registers the main processes of the power generation facilities planned for construction in a database, and The sub-process is registered in the database in association with the main process, and the results of the sub-process provided by the participant for the already-constructed power generation facility are the sub-process of the power generation facility scheduled to be constructed, Register in the database in association with the main process, permit the electric power company to access the contents of the main process and the sub-process registered in the database, and be registered in the database for each participant The access to the contents of the sub-process provided by each person is permitted, and the contents of the sub-process provided by other participants registered in the database are Also and permits access only when steps required to perform.

本発明の、発電設備建設管理装置および発電設備建設管理方法では、過去に建設された発電設備の実績データを使用することができる。参加者は、他の参加者により提供されたデータのうち必要な部分以外にはアクセスすることができないので、参加者のノウハウ等が保護される。一方で、データベースの一元化が担保できる。具体的には、全体工程は全体工程表により把握できるし、分離工程(工区)は分離工程表によりその詳細を知ることができる。従来の情報が紙で残っているので、それをデジタルデータ化して、データベースに組み込む。   In the power generation facility construction management apparatus and the power generation facility construction management method of the present invention, it is possible to use actual data of power generation facilities constructed in the past. Participants cannot access only necessary portions of the data provided by other participants, so that the know-how of the participants is protected. On the other hand, centralization of the database can be ensured. Specifically, the entire process can be grasped from the entire process chart, and the details of the separation process (work zone) can be known from the separation process chart. Since conventional information remains on paper, it is converted into digital data and incorporated into a database.

また、取り合いの調整(他社との関係でのスケジュールの調整)を、矢印等により時間に関連付けて表示すること等により、取り合いの調整が容易となる
また、本発明の発電設備建設管理装置および発電設備建設管理方法では、スケジュール調整機能に加えて、工事に関する付記情報を、全体工程表、分離工程表の適宜箇所に埋め込むことができる。たとえば、全体工程表中のある工程に、リンク情報を埋め込むことができる。したがって、発電設備の建設に際してスケジュール変更(通常は、マイナーチェンジ)が容易となる。
In addition, the adjustment of the relationship (the adjustment of the schedule in relation to the other company) is displayed in association with the time by using an arrow or the like, so that the adjustment of the relationship is facilitated. In the facility construction management method, in addition to the schedule adjustment function, supplementary information related to the construction can be embedded in appropriate places in the entire process chart and the separation process chart. For example, link information can be embedded in a certain process in the entire process chart. Therefore, it is easy to change the schedule (usually a minor change) when constructing the power generation facility.

特に本発明の発電設備建設管理装置および発電設備建設管理方法では、必要な人が、必要な時に、必要な場所で、必要な事項を、必要な見方で見ることができ、文言定義等の整合性をとることも容易である。本発明では、汎用コンピュータ等から、検索を行い、複数の表示方式から最適なものを選択して見ることができる。   In particular, in the power generation facility construction management apparatus and power generation facility construction management method of the present invention, a necessary person can see necessary matters at a necessary place when necessary, in a necessary way, and match the definition of wording. It is easy to take sex. In the present invention, it is possible to perform a search from a general-purpose computer or the like, and select and view an optimum one from a plurality of display methods.

図2〜図5により本発明の一実施形態を説明する。図2において、発電設備建設管理装置1は、建設予定の発電設備の工程を、既建設の発電設備についての電力会社Tおよび参加者(図2では、建設会社A、主機メーカB、分離メーカC)の工程履歴に基づき管理する。   An embodiment of the present invention will be described with reference to FIGS. In FIG. 2, the power generation facility construction management apparatus 1 performs the process of the power generation facility scheduled to be constructed by the power company T and the participants (in FIG. 2, the construction company A, the main machine manufacturer B, and the separation manufacturer C). ) Based on the process history.

発電設備建設管理装置1は、制御手段(制御装置)11と、データベース12と、全体プロジェクト管理手段131と、個別工事管理手段132と、アクセス許可手段133と、関連情報登録手段134とを備えている。   The power generation facility construction management device 1 includes a control means (control device) 11, a database 12, an overall project management means 131, an individual construction management means 132, an access permission means 133, and a related information registration means 134. Yes.

制御手段11は、データベース12,全体プロジェクト管理手段131,個別工事管理手段132,アクセス許可手段133,関連情報登録手段134を管理するもので、具体的には、CPUと、ROMまたはRAMに格納されて動作する管理プログラム、アクセス許可プログラム、登録プログラム等のアプリケーションプログラム等の各種プログラムからなる。   The control unit 11 manages the database 12, the overall project management unit 131, the individual construction management unit 132, the access permission unit 133, and the related information registration unit 134. Specifically, the control unit 11 is stored in the CPU and ROM or RAM. Management programs, access permission programs, and application programs such as a registration program.

全体プロジェクト管理手段131は、既建設の発電設備についての電力会社Tにより提供される主要工程の実績を、建設予定の発電設備の主要工程として、データベース12に登録する。   The overall project management means 131 registers the results of the main processes provided by the electric power company T for the already constructed power generation equipment in the database 12 as the main processes of the power generation equipment to be built.

個別工事管理手段132は、既建設の発電設備についての参加者(建設会社A、主機メーカB、分離メーカC)により提供される副工程の実績を、建設予定の発電設備の副工程として、主要工程に関連付けしてデータベース12に登録する。   The individual construction management means 132 uses the results of the sub-processes provided by the participants (construction company A, main machine maker B, separation maker C) for the existing power generation facilities as the sub-processes of the power generation facilities to be constructed. It is registered in the database 12 in association with the process.

アクセス許可手段133は、データベース12への登録内容へのアクセスを許可するものである。アクセス許可手段133は、電力会社Tに対しデータベース12に登録された主要工程および副工程の内容へのアクセスを許可し、各参加者(建設会社A、主機メーカB、分離メーカC)に対しデータベース12に登録された各自が提供した副工程の内容にアクセスを許可し、データベース12に登録された他の参加者が提供した副工程に自己の工程実行に必要な場合にのみアクセスを許可する。   The access permission unit 133 permits access to the registered contents in the database 12. The access permission means 133 permits the power company T to access the contents of the main process and the sub-process registered in the database 12, and the database for each participant (construction company A, main machine maker B, separation maker C). The access is permitted to the contents of the sub-process provided by each of the users registered in 12, and the sub-process provided by the other participants registered in the database 12 is allowed access only when necessary for the execution of the process.

電力会社Tは、主要工程登録手段131に登録された主要工程の内容にアクセスし、登録内容を書き換えることができる。たとえば、電力会社Tは、取り合い調整手順のために、依頼するべき参加者の特定、作業開始日、作業終了日等を書き換えることができる。   The electric power company T can access the contents of the main process registered in the main process registration means 131 and rewrite the registered contents. For example, the power company T can rewrite the identification of the participant to be requested, the work start date, the work end date, and the like for the trade adjustment procedure.

また、電力会社Tは、参加者(建設会社A、主機メーカB、分離メーカC)が提供した個別工事管理手段に登録された副工程の内容にアクセスして、登録内容を書き換えることができるようにしてもよい。電力会社Tは、個別工事管理手段に登録された副工程の内容を閲覧しかできないようにしてもよいが、この場合には、副工程の内容を書き換える必要があると判断した場合には、参加者(建設会社A、主機メーカB、分離メーカC)に書き換えを要求するようにしてもよい。   In addition, the electric power company T can access the contents of the sub-process registered in the individual construction management means provided by the participants (construction company A, main machine maker B, separation maker C) and rewrite the registered contents. It may be. The electric power company T may be able to only browse the contents of the sub-process registered in the individual construction management means, but in this case, if it is determined that it is necessary to rewrite the contents of the sub-process, participation Rewriting may be requested to a person (construction company A, main machine maker B, separation maker C).

また、参加者(建設会社A、主機メーカB、分離メーカC)は、各自が提供した個別工事管理手段に登録された副工程の内容にアクセスし、登録内容を書き換えることができ、他の参加者が提供した個別工事管理手段に登録された副工程の内容にアクセスして閲覧をすることができる。
データベース12には、電力会社Tおよび参加者による各工程がワークパッケージ(WP)として登録されている。
Participants (construction company A, main machine maker B, and separation maker C) can access the contents of the sub-processes registered in the individual construction management means provided by themselves, and can rewrite the registered contents. The contents of the sub-process registered in the individual construction management means provided by the person can be accessed and browsed.
Each process by the electric power company T and the participants is registered in the database 12 as a work package (WP).

データベース12の構築に際し、図3に示すように、主要工程ディレクトリD1、全体プロジェクト管理ディレクトリD2、個別工事管理ディレクトリD3、関連情報ディレクトリD4を記憶装置上に定義する。   When constructing the database 12, as shown in FIG. 3, a main process directory D1, an overall project management directory D2, an individual construction management directory D3, and a related information directory D4 are defined on the storage device.

個別工事管理ディレクトリD3には、個別工事ディレクトリ(ここでは、D301〜304)、土木・建築工程ディレクトリD31、主機工程ディレクトリD32、系統試験工程管理ディレクトリD33、起動試験工程管理ディレクトリD34のサブディレクトリが定義される。図3では、個別工事ディレクトリは、電力会社Tおよび参加者(分離メーカC)から提供されたデータに基づき作成された、主変圧器新設工事D301、水処理設備工事D302を含んでいる。   In the individual construction management directory D3, subdirectories of an individual construction directory (here, D301 to 304), a civil engineering / building process directory D31, a main machine process directory D32, a system test process management directory D33, and a startup test process management directory D34 are defined. Is done. In FIG. 3, the individual construction directory includes a main transformer new construction D301 and a water treatment facility construction D302 created based on data provided from the electric power company T and the participants (separated manufacturer C).

データベース12に登録される各種データは、もともと紙ベースのドキュメントであってもよいし、表計算アプリケーション、スケジューリング用アプリケーション等により作成されたデータであってもよい。   The various data registered in the database 12 may be originally paper-based documents, or may be data created by a spreadsheet application, a scheduling application, or the like.

たとえば、電力会社Tから提供される発電設備の実績データのうち、「主要工程」データは主要工程ディレクトリD1に主要工程ワークパッケージ(WP)として登録される。   For example, among the performance data of the power generation facilities provided by the electric power company T, the “main process” data is registered in the main process directory D1 as a main process work package (WP).

たとえば、建設会社Aから提供される発電設備の実績データのうち、「土木・建築現地工事」データは土木・建築工程ディレクトリD31に土木・建築工程WPとして登録される。   For example, among the actual power generation facility data provided by the construction company A, “civil engineering / architecture local construction” data is registered in the civil engineering / architecture process directory D31 as a civil engineering / architecture process WP.

たとえば、主機メーカAから提供される発電設備の実績データのうち、「主機現地工事」データは主機工程ディレクトリD32に主機工程WPとして登録され、「系統試験工程」データは系統試験工程管理ディレクトリD33に系統試験工程WPとして登録され、「起動試験工程」データは起動試験工程管理ディレクトリD34に起動試験工程WPとして登録される。   For example, among the actual power generation facility data provided by the main machine manufacturer A, the “main machine local construction” data is registered as the main machine process WP in the main machine process directory D32, and the “system test process” data is stored in the system test process management directory D33. The system test process WP is registered, and the “start-up test process” data is registered as the start-up test process WP in the start-up test process management directory D34.

たとえば、分離メーカCから提供される発電設備の実績データのうち、「現地工事」データは個別工事ディレクトリD31(I(1)〜I(N))に現地工事WPとして登録され、「系統試験工程」データは系統試験工程管理ディレクトリD33に系統試験工程WPとして登録される。   For example, among the actual data of the power generation equipment provided by the separate manufacturer C, the “local construction” data is registered as the local construction WP in the individual construction directory D31 (I (1) to I (N)), and the “system test process” The data is registered in the system test process management directory D33 as the system test process WP.

図3のデータベース(ディレクトリ構成)では、水処理設備工事を例にとり、電力会社Tが作成したエンジニアリング工程aを参照して、参加者(受注メーカ)が作成した現地工事工程bの取合い設定cを行う場合を例示してある。この取合いの設定cにおいては、図3では全体プロジェクト管理D2の取合い先WP(d)および主機工程D32の原子炉設備工事の取合い先WP(e:既存の発電設備の建設に際しての取合い先WP)を参照して、新設工事を行う参加者の工程管理を行う。   In the database (directory structure) in FIG. 3, the water treatment facility construction is taken as an example, the engineering process a created by the electric power company T is referred to, and the connection setting c of the local construction process b created by the participant (order manufacturer) is set. The case of performing is illustrated. In this connection setting c, in FIG. 3, the destination WP (d) of the overall project management D2 and the destination WP of the reactor equipment construction in the main engine process D32 (e: the destination WP for the construction of the existing power generation facility) Referring to the above, process management will be performed for participants who will perform new construction.

図4(A),(B)に示すように、電力会社Tのユーザインタフェース画面に取合いの時間の前後関係を明示しておけば、取合いの調整がされている場合(図4(A))と、されていない場合(図4(B))とを明示することができる。   As shown in FIGS. 4 (A) and 4 (B), if the relationship between the times of engagement is clearly shown on the user interface screen of the electric power company T, the adjustment of the interaction is made (FIG. 4 (A)). And the case where it is not done (FIG. 4B) can be specified.

図5は、データベース構造の説明図であり、上記したデータは、業務に関する情報(FWBS)、機器や系統に関する情報(EBS)、時間に関する情報(TBS)、所掌に関する情報(OBS)、エリアに関する情報(ABS)に分けられて(すなわち、WPとして)データベース化されている。   FIG. 5 is an explanatory diagram of the database structure, and the above-mentioned data includes information relating to business (FWBS), information relating to devices and systems (EBS), information relating to time (TBS), information relating to responsibility (OBS), and information relating to areas. The database is divided into (ABS) (ie, as WP).

発電設備建設管理装置1は、全体プロジェクト管理手段131と、個別工事管理手段132と、アクセス許可手段133、スケジュール管理手段134とを備えており、具体的には、主要工程表(予定・実績)、許認可工程表(予定・実績)、工認工程表(予定・実績)、使用前検査工程表(予定・実績)を出力することができる。   The power generation facility construction management device 1 includes an overall project management means 131, an individual construction management means 132, an access permission means 133, and a schedule management means 134. Specifically, the main process chart (plan / actual result) It is possible to output an approval process chart (plan / actual), an approval process chart (plan / actual), and a pre-use inspection process chart (plan / actual).

全体プロジェクト管理手段131は、主要工程管理、許認可管理、使用前検査管理、着工前エンジニアリング、工事計画認可管理を行う。アクセス許可手段133は、電力会社Tによるアクセス(検索,工程表出力,帳票出力,データ書き換え等)に制限を設けない。   The overall project management means 131 performs main process management, permit / license management, pre-use inspection management, pre-construction engineering, and construction plan approval management. The access permission unit 133 does not limit the access (search, process table output, form output, data rewrite, etc.) by the power company T.

また、個別工事管理手段132は、分離工事管理(エンジニアリング工程管理、現地工事工程管理)を行うことができる。具体的には、分離件名工程表(予定・実績)、各種帳票を出力することができる。アクセス許可手段133は、電力会社Tによるアクセスに制限を設けない。   The individual construction management means 132 can perform separation construction management (engineering process management, local construction process management). Specifically, a separation subject process chart (plan / actual result) and various forms can be output. The access permission unit 133 does not limit access by the power company T.

個別工事管理手段132は、建設会社A,主機メーカB,分離メーカCからの要求により、新主要工程表,建築工程表、大型特殊機器工程表,エリア工程表、主機/分離工程表、ヤード工程表、炉内試験工程表、起動試験工程表、系統試験工程表、起動試験工程表を出力することができる。アクセス許可手段133は、建設会社A,主機メーカB,分離メーカCによるアクセス(検索,工程表出力,データ書き換え等)を一定条件のもとに許す(アクセスを制限する)機能を備えている。具体的には、アクセス制限テーブルAUTを備えており、アクセスが制限されているデータへのアクセス要求を受け取ったときは、アクセス制限テーブルAUTを参照して、アクセスを許可するか否かを決定する。このアクセス制限テーブルAUTは、例えば、各ファイル(ワークパッケージのデータ)と、そのファイルに対してアクセス可能な(アクセス権を保有する)者を特定する情報(コード等)を関連づけたテーブル構造とすることができる。これにより、このテーブルに載っていない者のアクセスは許可されない。   The individual construction management means 132 is requested by the construction company A, main machine maker B, and separation maker C. New main process chart, building process chart, large special equipment process chart, area process chart, main machine / separation process chart, yard process Table, in-core test process table, start-up test process table, system test process table, start-up test process table can be output. The access permission means 133 has a function of permitting (restricting access) the access (search, process table output, data rewriting, etc.) by the construction company A, main machine manufacturer B, and separation manufacturer C under certain conditions. Specifically, an access restriction table AUT is provided, and when an access request to data with restricted access is received, the access restriction table AUT is referenced to determine whether or not to permit access. . The access restriction table AUT has, for example, a table structure in which each file (work package data) is associated with information (code or the like) specifying a person who can access the file (has access rights). be able to. As a result, access by persons not on this table is not permitted.

工程管理(Y)にWBSを導入する場合、建設会社A、主機メーカB、分離メーカCの工程の手順等は、アクセス制限機能により制限される。すなわち、建設会社A、主機メーカB、分離メーカCにより行われる工程には、種々の作業等のノウハウが含まれることがあり、建設会社A、主機メーカB、分離メーカCにとっては、これらノウハウは財産であり、他社への公開を望まない。   When the WBS is introduced into the process management (Y), the process procedures of the construction company A, main machine maker B, and separation maker C are restricted by the access restriction function. That is, the processes performed by the construction company A, the main machine maker B, and the separation maker C may include know-how on various operations. For the construction company A, the main machine maker B, and the separation maker C, these know-how It is a property and does not want to be disclosed to other companies.

個別工事管理手段132により作成された各参加者における各工程の手順等は、アクセス制限許可手段133により、原則としてプロジェクトに参加する他の参加者に公開されない。よって、プロジェクトの参加者のノウハウ等の秘匿は担保される。また、各参加者は、個別工事管理手段132により、自己の工程を適宜編集することができる。そして、実際の工事の進捗状況は、必ずしも当初予定した通りに進むとは限らず、日々変化することがある。係る場合、各参加者は、自己の工程に関する変更を個別工事管理手段132を用いてデータベースに登録することができる。これにより、係る変化に応じて工程表(終了日等)の変更が行われるため、アクセス制限のない電力会社Tは、最新の工程表(予定・実績)を見ることにより、現況を容易に把握できる。   The procedure of each process for each participant created by the individual construction management means 132 is not disclosed to other participants who participate in the project by the access restriction permission means 133 in principle. Therefore, the confidentiality of the know-how of the project participants is secured. Further, each participant can edit his / her process as appropriate by the individual construction management means 132. And the progress of actual construction does not always proceed as originally planned, but may change daily. In such a case, each participant can register changes related to his / her process in the database using the individual construction management means 132. As a result, the process schedule (end date, etc.) is changed according to the change, so the electric power company T without access restrictions can easily grasp the current situation by looking at the latest process schedule (planned / actual). it can.

また、工程表の変更を行い、その工程aの完了日時が遅れるような場合がある。係る場合、その工程aの遅れが別の工程bへ影響を与えることがある。つまり、工程bは工程aの完了を前提とするような場合、工程aの実際の終了日が、工程bの当初の開始予定日よりも遅くなると、それに合わせて工程bの開始日も遅らせる必要がある。逆に工程bの開始日を変更できない場合には、工程aの完了日は工程bの開始日よりも前にする必要がある。工程aと工程bが同一の参加者が行う場合には、自社内で調整を図り、工程bの開始予定日を遅らせるか、工程aの作業を早く行い、完了日をとにかく工程bの開始日前になるようにする。   In addition, the process table may be changed, and the completion date and time of the process a may be delayed. In such a case, the delay of the process a may affect another process b. In other words, when the process b is premised on the completion of the process a, if the actual end date of the process a is later than the initial start date of the process b, the start date of the process b needs to be delayed accordingly. There is. Conversely, when the start date of step b cannot be changed, the completion date of step a needs to be earlier than the start date of step b. If process a and process b are performed by the same participant, make adjustments within the company and delay the scheduled start date of process b or perform the work of process a earlier, before the completion date of process b. To be.

一方、工程aと工程bとが、それぞれ異なる参加者における作業の場合、参加者間での取り合い調整を行う必要がある。係る場合、取り合い調整が必要か否かは、図4に示す表示形態をとっているため、容易に判断することができる。すなわち、工程aを実施する参加者は、工程aと関係する工程bについてもアクセス許可を受けているため、工程bの開始日を確認でき、図4に示す表示形態を見ることができる。そして、予め工程aの遅れを見越したり、別の要因で工程bの開始日が決定され、元々工程aの完了日との間に一定期間の余裕がある場合がある。係る場合、仮に工程aの完了日を遅らせた状態で更新登録した後、自己に関係する工程表を表示した際に、図4(A)に示すようになると、工程bを実施する参加者に対し取り合いの調整を申し込むことなく日程の変更が行える。しかし、図4(B)に示すようになると、工程bの開始日よりも工程aの完了日の方が遅いことが一目で理解できるので、工程bを実施する参加者との間で日程の調整(取り合い調整)を行い、不整合を解消する。   On the other hand, in the case where the process a and the process b are performed by different participants, it is necessary to adjust the relationship between the participants. In such a case, whether or not the balance adjustment is necessary can be easily determined because the display form shown in FIG. 4 is adopted. That is, since the participant who performs the process a is also permitted to access the process b related to the process a, the start date of the process b can be confirmed and the display form shown in FIG. 4 can be seen. In some cases, the delay of the process a is anticipated in advance, or the start date of the process b is determined by another factor, and there is a certain period of margin between the completion date of the process a. In such a case, after updating and registering with the completion date of process a delayed, when the process chart related to self is displayed, as shown in FIG. It is possible to change the schedule without applying for adjustments. However, as shown in FIG. 4B, it can be understood at a glance that the completion date of the process a is later than the start date of the process b. Make adjustments (match adjustments) to eliminate inconsistencies.

工程管理(Y)にWBSを導入する場合、プロジェクトの参加者、すなわち建設会社A、主機メーカB、分離メーカCの工程の手順等は、相互にオープンにされる(本発明では、電力会社Tにより調整される)。このため、プロジェクトの参加者のノウハウ等の秘匿が担保されないことがある。また、既存の発電設備の建設に際しての、建設会社A、主機メーカB、分離メーカCの工程の手順等のドキュメントを単純にデータベース化して利用することも考えられるが、この場合にも、プロジェクトの参加者相互に、ドキュメントをオープンにしたのでは、ノウハウ等の秘匿が担保されない。
発電設備の建設に際しては、複数の分離メーカC間での、いわゆる取り合いの調整が必要であるが、取り合いを矢印で示してあるのでそのまま適用することができる。
When the WBS is introduced into the process management (Y), the process procedures of the project participants, that is, the construction company A, the main machine maker B, and the separation maker C are open to each other (in the present invention, the power company T Adjusted by). For this reason, the confidentiality of the know-how of project participants may not be guaranteed. In addition, it is conceivable to simply create a database of documents such as the construction procedures of construction company A, main machine manufacturer B, and separation manufacturer C when constructing an existing power generation facility. The confidentiality of know-how, etc. is not guaranteed if the documents are open to the participants.
When constructing a power generation facility, it is necessary to adjust a so-called relationship between a plurality of separated manufacturers C. However, since the relationship is indicated by an arrow, it can be applied as it is.

図6以降の図により発電設備建設管理装置1の動作を説明する。図6のユーザインタフェース画面G1に示すように、参加者は、個別工事スケジュール登録を行うことができる。このユーザインタフェース画面G1には、予定スケジュールの種類の選択部と、WPの種類の選択部と、WPの情報(件名、FWBS、EBS、ABS、所掌箇所、開始日、終了日)が入力される。   The operation of the power generation facility construction management apparatus 1 will be described with reference to FIG. As shown in the user interface screen G1 in FIG. 6, the participant can perform individual construction schedule registration. On this user interface screen G1, a scheduled schedule type selection unit, a WP type selection unit, and WP information (title, FWBS, EBS, ABS, jurisdiction location, start date, end date) are input. .

なお、図6の左欄のメニュー中、「検索」の「WP検索」はWP(工程データ)の検索、「件名検索」は個別工事件名の検索、「関連情報検索」は帳票に使用する関連情報の検索にかかるものであり、「新規登録」の「件名登録」は個別工事の件名とその他情報の新規登録を、「主要工程登録」は着工、受電など大工程のデータの登録を、「全体スケジュール登録」は個別の工程に依存しない工程データ(許認可やプロジェクトの着工前エンジニアリング等)の登録を、「個別スケジュール登録」は個別工事件名の工事データの登録を、それぞれ行うためのものである。   In the menu in the left column of FIG. 6, “WP Search” in “Search” is a search for WP (process data), “Subject Search” is a search for individual construction subject, and “Related Information Search” is a related item used for a form. It is related to information search. “Subject registration” of “New registration” is a new registration of subject and other information of individual construction, “Main process registration” is registration of large process data such as construction and power reception, "Register entire schedule" is for registering process data (licenses and pre-construction engineering, etc.) that does not depend on individual processes, and "Individual schedule registration" is for registering construction data for individual construction subjects. .

また、図7,図8に示すように建設会社A、主機メーカB、分離メーカCは、新規に個別工事の件名登録を行うことができる。図7は個別工事件名登録のためのユーザインタフェース画面G2を示しており、図8は個別工事件名登録を行うに際しての既建設の発電設備についての個別工事登録の実績データ画面G21を示している。ユーザは、ユーザインタフェース画面G2の「コピー元検索」ボタンを用いて、個別工事件名登録の実績データ画面G21を呼び出すことができる。電力会社Tは、図9に示す主要工事登録のためのユーザインタフェース画面G3を用いて、主要工程の登録(予定または実績の何れか)を行うことができる。   Further, as shown in FIGS. 7 and 8, construction company A, main machine maker B, and separation maker C can newly register the subject of individual works. FIG. 7 shows a user interface screen G2 for individual construction subject registration, and FIG. 8 shows an individual construction registration result data screen G21 for an already-constructed power generation facility when performing individual construction subject registration. The user can call up the performance data screen G21 for individual construction subject registration using the “copy source search” button on the user interface screen G2. The electric power company T can register the main process (either scheduled or actual) using the user interface screen G3 for main construction registration shown in FIG.

図10,図11は、工事工程の登録情報を示す図であり、図10は電力会社Aが必要とする工程データ(スケジュール表S1)を示し、図11は水処理設備メーカにて検索した工程データ(スケジュール表S2)を示している。図11に示すように、水処理設備メーカにて検索した工程データは、電力会社Aが必要とする工程データと異なり、水処理設備メーカが必要としないデータは表示されない。   10 and 11 are diagrams showing the registration information of the construction process. FIG. 10 shows process data (schedule table S1) required by the electric power company A, and FIG. 11 shows the process searched by the water treatment equipment manufacturer. Data (schedule table S2) is shown. As shown in FIG. 11, the process data searched by the water treatment equipment manufacturer is different from the process data required by the electric power company A, and data not required by the water treatment equipment manufacturer is not displayed.

図12,図13は、WP検索の一例を示しており、図12はWP検索のためのユーザインタフェース画面G41であり、図12のユーザインタフェース画面G41からの検索により図13のユーザインタフェース画面G42に示す検索結果を得ることができる。   12 and 13 show an example of the WP search. FIG. 12 shows a user interface screen G41 for WP search. The search from the user interface screen G41 in FIG. 12 changes to the user interface screen G42 in FIG. The search result shown can be obtained.

図14から図16は、ユーザは個別工事件名検索のためのユーザインタフェース画面であり、図14のユーザインタフェース画面G51からの検索により図15のユーザインタフェース画面G52に示す検索結果を得ることができる。ユーザは、図16のユーザインタフェース画面G53(個別工事件名編集画面)を用いて、たとえば、既存の発電設備の建設に際して作成した個別工事の個別工事件名等の編集を行い、新規の工事に適応することができる。   14 to 16 are user interface screens for individual construction subject search, and the search results shown in the user interface screen G52 of FIG. 15 can be obtained by searching from the user interface screen G51 of FIG. The user uses the user interface screen G53 (individual construction subject editing screen) in FIG. 16, for example, to edit the individual construction subject of the individual construction created at the time of constructing the existing power generation facility, and adapts to the new construction. be able to.

図17,図18は、関連情報の検索のためのユーザインタフェース画面であり、図17のユーザインタフェース画面G61からの検索により図18のユーザインタフェース画面G62に示す検索結果を得ることができる。   FIGS. 17 and 18 are user interface screens for searching for related information, and the search results shown in the user interface screen G62 in FIG. 18 can be obtained by searching from the user interface screen G61 in FIG.

図19から図21は、ユーザは工事計画認可情報検索のためのユーザインタフェース画面であり、図19のユーザインタフェース画面G71からの検索により図20のユーザインタフェース画面G72に示す編集画面に移行することができる。ユーザは、図19のユーザインタフェース画面G71のサーチボタンから図21のサーチのためのユーザインタフェース画面G73に移行することもできる。   19 to 21 are user interface screens for searching for construction plan authorization information. The user can move to the edit screen shown in the user interface screen G72 of FIG. 20 by searching from the user interface screen G71 of FIG. it can. The user can also move from the search button on the user interface screen G71 in FIG. 19 to the user interface screen G73 for search in FIG.

従来の発電設備建設管理装置のブロック図である。It is a block diagram of the conventional power generation equipment construction management apparatus. 本発明の、発電設備建設管理装置を示すブロック図である。It is a block diagram which shows the power generation equipment construction management apparatus of this invention. 図2の発電設備建設管理装置のディレクトリ構造を示す説明図である。It is explanatory drawing which shows the directory structure of the power generation equipment construction management apparatus of FIG. 取合いの説明図である。It is explanatory drawing of a connection. 図2の発電設備建設管理装置のデータ構造を示す説明図である。It is explanatory drawing which shows the data structure of the power generation equipment construction management apparatus of FIG. 個別工事スケジュール登録のためのユーザインタフェース画面を示す図である。It is a figure which shows the user interface screen for individual construction schedule registration. 個別工事件名登録のためのユーザインタフェース画面を示す図である。It is a figure which shows the user interface screen for individual construction subject name registration. 個別工事件名登録を行うに際しての既建設の発電設備についての個別工事登録の実績データ画面を示す図である。It is a figure which shows the performance data screen of the individual construction registration about the already-built power generation equipment at the time of performing individual construction subject registration. 主要工事登録のためのユーザインタフェース画面を示す図である。It is a figure which shows the user interface screen for main construction registration. 工事工程の登録情報を示す図であり、電力会社Aが必要とする工程データを示す図である。It is a figure which shows the registration information of a construction process, and is a figure which shows the process data which the electric power company A requires. 工事工程の登録情報を示す図であり、水処理設備メーカにて検索した工程データを示す図である。It is a figure which shows the registration information of a construction process, and is a figure which shows the process data searched in the water treatment equipment manufacturer. WP検索の一例を示しており、WP検索のためのユーザインタフェース画面を示す図である。It is a figure which shows an example of WP search and shows the user interface screen for WP search. WP検索の一例を示しており、検索結果を示す図である。It is a figure which shows an example of WP search and shows a search result. 個別工事件名検索のためのユーザインタフェース画面における検索画面を示す図である。It is a figure which shows the search screen in the user interface screen for an individual construction subject search. 個別工事件名検索のためのユーザインタフェース画面における検索結果示す図である。It is a figure which shows the search result in the user interface screen for an individual construction subject search. 個別工事件名検索のためのユーザインタフェース画面における編集画面を示す図である。It is a figure which shows the edit screen in the user interface screen for an individual construction subject search. 関連情報の検索のためのユーザインタフェース画面における検索画面を示す図である。It is a figure which shows the search screen in the user interface screen for the search of related information. 関連情報の検索のためのユーザインタフェース画面における検索結果を示す図である。It is a figure which shows the search result in the user interface screen for the search of related information. 工事計画認可情報検索のためのユーザインタフェース画面における検索画面を示す図、である。It is a figure which shows the search screen in the user interface screen for construction plan authorization information search. 工事計画認可情報検索のためのユーザインタフェース画面における編集画面を示す図である。It is a figure which shows the edit screen in the user interface screen for construction plan authorization information search. 工事計画認可情報検索のためのユーザインタフェース画面におけるサーチのためのユーザインタフェース画面を示す図である。It is a figure which shows the user interface screen for a search in the user interface screen for construction plan authorization information search.

符号の説明Explanation of symbols

1 発電設備建設管理装置
11 制御手段(制御装置)
12 データベース
131 全体プロジェクト管理手段
132 個別工事管理手段
133 アクセス許可手段
D31 個別工事ディレクトリ
D32 主機工程ディレクトリ
D33 系統試験工程管理ディレクトリ
D34 起動試験工程管理ディレクトリ
1 Power generation equipment construction management device 11 Control means (control device)
12 Database 131 Overall project management means 132 Individual construction management means 133 Access permission means D31 Individual construction directory D32 Main machine process directory D33 System test process management directory D34 Startup test process management directory

Claims (8)

建設予定の発電設備の工程を、既建設の発電設備についての電力会社および参加者の工程履歴に基づき管理する発電設備建設管理装置であって、
前記既建設の発電設備についての前記電力会社により提供される主要工程の実績を、前記建設予定の発電設備の主要工程として、データベースに登録する全体プロジェクト管理手段と、
前記既建設の発電設備についての前記参加者により提供される副工程の実績を、前記建設予定の発電設備の副工程として、前記主要工程に関連付けして前記データベースに登録する個別工事管理手段と、
前記データベースへの登録内容へのアクセスを許可するアクセス許可手段と、
を備え、
前記アクセス許可手段は、
前記電力会社に対し前記データベースに登録された前記主要工程および前記副工程の内容へのアクセスを許可し、
前記各参加者に対し前記データベースに登録された各自が提供した前記副工程の内容にアクセスを許可し、前記データベースに登録された他の参加者が提供した前記副工程に自己の工程実行に必要な場合にのみアクセスを許可する、
ことを特徴とする発電設備建設管理装置。
A power generation facility construction management device for managing the process of a power generation facility to be constructed based on the process history of an electric power company and a participant about an already constructed power generation facility,
An overall project management means for registering, as a main process of the power generation facility scheduled to be constructed, a database for a main process provided by the electric power company for the power generation facility already constructed;
Individual construction management means for registering in the database in association with the main process, as a sub-process of the power generation equipment scheduled to be constructed, as a sub-process of the sub-process provided by the participant for the power generation equipment already constructed;
Access permission means for permitting access to the registered content in the database;
With
The access permission means includes
Permit access to the contents of the main process and sub-process registered in the database for the electric power company,
Permits each participant to access the contents of the sub-process provided by each registered in the database, and is necessary for executing the sub-process provided by other participants registered in the database. Allow access only if
A power generation facility construction management device characterized by that.
建設予定の発電設備の工程を管理する発電設備建設管理装置であって、
前記建設予定の発電設備の主要工程をデータベースに登録する全体プロジェクト管理手段と、
前記建設予定の発電設備の副工程を前記主要工程に関連付けして前記データベースに登録する個別工事管理手段と、
前記データベースへの登録内容へのアクセスを許可するアクセス権許可手段と、
を備え、
前記アクセス許可手段は、
前記電力会社に対し前記データベースに登録された前記主要工程および前記副工程の内容にアクセスを許可し、
前記各参加者に対し前記データベースに登録された各自が提供した前記副工程の内容にアクセスを許可し、前記データベースに登録された他の参加者が提供した前記副工程に自己の工程実行に必要な場合にのみアクセスを許可する、
ことを特徴とする発電設備建設管理装置。
A power generation facility construction management device for managing the process of a power generation facility to be constructed,
An overall project management means for registering the main process of the power generation facility to be constructed in a database;
Individual construction management means for registering the sub-process of the power generation facility to be constructed in the database in association with the main process;
Access right permission means for permitting access to the registered content in the database;
With
The access permission means includes
Permit access to the contents of the main process and sub-process registered in the database for the electric power company,
Permits each participant to access the contents of the sub-process provided by each registered in the database, and is necessary for executing the sub-process provided by other participants registered in the database. Allow access only if
A power generation facility construction management device characterized by that.
前記電力会社による、前記主要工程登録手段に登録された前記主要工程の内容へのアクセスは登録内容の書き換えを含み、
前記各参加者による、各自が提供した前記個別工事管理手段に登録された前記副工程の内容へのアクセスは、登録内容の書き換えを含む、
ことを特徴とする請求項1または2に記載の発電設備建設管理装置。
Access to the contents of the main process registered in the main process registration means by the electric power company includes rewriting of the registered contents,
Access to the contents of the sub-process registered in the individual construction management means provided by each participant by each participant includes rewriting of registered contents,
The power generation facility construction management device according to claim 1 or 2.
前記電力会社による、登録内容の書き換えは、前記各参加者による工程の取り合い調整手順を含むことを特徴とする請求項1から3の何れかに記載の発電設備建設管理装置。   4. The power generation facility construction management apparatus according to claim 1, wherein rewriting of registered contents by the electric power company includes a process adjustment procedure for each participant. 5. 前記電力会社による、前記個別工事管理手段に登録された前記副工程の内容へのアクセスは閲覧であり、
前記各参加者よる、他の参加者が提供した前記個別工事管理手段に登録された前記副工程の内容へのアクセスは閲覧である、
ことを特徴とする請求項1から4の何れかに記載の発電設備建設管理装置。
Access to the contents of the sub-process registered in the individual construction management means by the electric power company is browsing,
Access to the contents of the sub-process registered in the individual construction management means provided by other participants by each participant is browsing.
The power generation facility construction management device according to any one of claims 1 to 4, wherein
建設予定の発電設備の一連の工程を抽出し、これをグループ化し、そのグループの作業工程をブレークダウンし、階層的に工程の内容を定義して管理を行う発電設備建設管理装置であって、
実行される作業工程を時系列で表現し、前記データベースには、前記電力会社および前記各参加者による各工程をワークパッケージとして登録したことを特徴とする請求項1から5の何れかに記載の発電設備建設管理装置。
A power generation facility construction management device that extracts a series of processes of power generation facilities to be constructed, groups them, breaks down the work processes of the group, and defines and manages the contents of the processes hierarchically,
The work process to be executed is expressed in time series, and each process by the electric power company and each participant is registered in the database as a work package. Power generation equipment construction management device.
建設予定の発電設備の工程を、既建設の発電設備についての電力会社および参加者の工程履歴に基づき管理する発電設備建設管理方法であって、
前記既建設の発電設備についての前記電力会社により提供される主要工程の実績を、前記建設予定の発電設備の主要工程として、データベースに登録し、
前記既建設の発電設備についての前記参加者により提供される副工程の実績を、前記建設予定の発電設備の副工程として、前記主要工程に関連付けして前記データベースに登録し、
前記電力会社に対し前記データベースに登録された前記主要工程および前記副工程の内容にアクセスを許可し、
前記各参加者に対し前記データベースに登録された各自が提供した前記副工程の内容にアクセスを許可し、前記データベースに登録された他の参加者が提供した前記副工程の内容には自己の工程実行に必要な場合にのみアクセスを許可する、
ことを特徴とする発電設備建設管理方法。
A power generation facility construction management method for managing a process of a power generation facility to be constructed based on a process history of an electric power company and a participant about an already-constructed power generation facility,
Record the main process results provided by the electric power company for the already constructed power generation facility as a main process of the power generation facility scheduled to be built, in the database,
The results of sub-processes provided by the participants for the already constructed power generation facilities are registered in the database in association with the main processes as sub-processes of the power generation facilities scheduled to be constructed,
Permit access to the contents of the main process and sub-process registered in the database for the electric power company,
Each participant is allowed to access the contents of the sub-process provided by each person registered in the database, and the contents of the sub-process provided by other participants registered in the database are self-processed. Allow access only when necessary to run,
A power generation facility construction management method characterized by the above.
建設予定の発電設備の工程を管理する発電設備建設管理方法であって、
前記建設予定の発電設備の主要工程をデータベースに登録し、
前記建設予定の発電設備の副工程を前記主要工程に関連付けして前記データベースに登録し、
前記既建設の発電設備についての前記参加者により提供される副工程の実績を、前記建設予定の発電設備の副工程として、前記主要工程に関連付けして前記データベースに登録し、
前記電力会社に対し前記データベースに登録された前記主要工程および前記副工程の内容へのアクセスを許可し、
前記各参加者に対し前記データベースに登録された各自が提供した前記副工程の内容にアクセスを許可し、前記データベースに登録された他の参加者が提供した前記副工程の内容には自己の工程実行に必要な場合にのみアクセスを許可する、
ことを特徴とする発電設備建設管理方法。
A power generation facility construction management method for managing a process of a power generation facility to be constructed,
Register the main process of the power plant to be constructed in the database,
Substituting the sub-process of the power generation facility to be constructed in association with the main process in the database,
The results of sub-processes provided by the participants for the already constructed power generation facilities are registered in the database in association with the main processes as sub-processes of the power generation facilities scheduled to be constructed,
Permit access to the contents of the main process and sub-process registered in the database for the electric power company,
Each participant is allowed to access the contents of the sub-process provided by each person registered in the database, and the contents of the sub-process provided by other participants registered in the database are self-processed. Allow access only when necessary to run,
A power generation facility construction management method characterized by the above.
JP2004305976A 2004-10-20 2004-10-20 Power generation facilities construction management apparatus and power generation facilities construction management method Pending JP2006119842A (en)

Priority Applications (1)

Application Number Priority Date Filing Date Title
JP2004305976A JP2006119842A (en) 2004-10-20 2004-10-20 Power generation facilities construction management apparatus and power generation facilities construction management method

Applications Claiming Priority (1)

Application Number Priority Date Filing Date Title
JP2004305976A JP2006119842A (en) 2004-10-20 2004-10-20 Power generation facilities construction management apparatus and power generation facilities construction management method

Publications (1)

Publication Number Publication Date
JP2006119842A true JP2006119842A (en) 2006-05-11

Family

ID=36537677

Family Applications (1)

Application Number Title Priority Date Filing Date
JP2004305976A Pending JP2006119842A (en) 2004-10-20 2004-10-20 Power generation facilities construction management apparatus and power generation facilities construction management method

Country Status (1)

Country Link
JP (1) JP2006119842A (en)

Cited By (2)

* Cited by examiner, † Cited by third party
Publication number Priority date Publication date Assignee Title
US8720159B2 (en) 2009-09-17 2014-05-13 Kabushiki Kaisha Toshiba Floor construction method in machinery preceding conveyance area in building
WO2020170713A1 (en) * 2019-02-21 2020-08-27 三菱重工環境・化学エンジニアリング株式会社 Plant apparatus information management system

Citations (3)

* Cited by examiner, † Cited by third party
Publication number Priority date Publication date Assignee Title
JP2002007657A (en) * 2000-06-26 2002-01-11 Fujitsu Systems Construction Ltd Project managing device and recording medium
JP2002123577A (en) * 2000-10-17 2002-04-26 Sangikyou:Kk System and method for supporting construction
JP2003288457A (en) * 2002-03-27 2003-10-10 Web I Laboratories Inc Data management system and object repository server available for the same system

Patent Citations (3)

* Cited by examiner, † Cited by third party
Publication number Priority date Publication date Assignee Title
JP2002007657A (en) * 2000-06-26 2002-01-11 Fujitsu Systems Construction Ltd Project managing device and recording medium
JP2002123577A (en) * 2000-10-17 2002-04-26 Sangikyou:Kk System and method for supporting construction
JP2003288457A (en) * 2002-03-27 2003-10-10 Web I Laboratories Inc Data management system and object repository server available for the same system

Cited By (3)

* Cited by examiner, † Cited by third party
Publication number Priority date Publication date Assignee Title
US8720159B2 (en) 2009-09-17 2014-05-13 Kabushiki Kaisha Toshiba Floor construction method in machinery preceding conveyance area in building
WO2020170713A1 (en) * 2019-02-21 2020-08-27 三菱重工環境・化学エンジニアリング株式会社 Plant apparatus information management system
JP2020135538A (en) * 2019-02-21 2020-08-31 三菱重工環境・化学エンジニアリング株式会社 Plant equipment information management system

Similar Documents

Publication Publication Date Title
KR100738603B1 (en) System, method, and computer readable medium for electronically managing privileged and non-privileged documents
Hart et al. Inter-organization networks, computer integration, and shifts in interdependence: The case of the semiconductor industry
US20080082929A1 (en) Document-centric workflow systems, methods, and software based on document contents, metadata, and context
US20030101086A1 (en) Decision tree software system
CN1773541A (en) Asset maintenance or inspection system and method
US20060200792A1 (en) Process templates for software creation
CA2267479A1 (en) Multi-layer online calendering and purchasing
CN101151631A (en) Systems, methods, software for integration of case law, legal briefs, and litigation documents into law firm workflow
JP2009238191A (en) Web application system
CN1391186A (en) Automatic management for developing project files on network
US20030055937A1 (en) Qualification information management method and apparatus
JP2003323528A (en) Personnel management system and method
JP2007265123A (en) Business procedure support system, business procedure support method, business procedure support apparatus, and program
US11836191B2 (en) System and method for automated record creation and management
JP2014182603A (en) Document administration system, document administration method, and document administration program
US20090199079A1 (en) Embedded cues to facilitate application development
JP2006119842A (en) Power generation facilities construction management apparatus and power generation facilities construction management method
JP2004054716A (en) Work management method and display method for work
JP4152284B2 (en) Medical support system
JP5873300B2 (en) Business management system and computer program
JP2005285008A (en) Data security management system, program, and data security management method
JPH11154011A (en) Plant maintenance planning support system
JPH10154090A (en) Data management system
Greiner et al. Requirements for web-based integrated management systems in the production of image processing components
Grael et al. Glance Information System for ATLAS Management

Legal Events

Date Code Title Description
A621 Written request for application examination

Free format text: JAPANESE INTERMEDIATE CODE: A621

Effective date: 20070802

A977 Report on retrieval

Free format text: JAPANESE INTERMEDIATE CODE: A971007

Effective date: 20091208

A131 Notification of reasons for refusal

Free format text: JAPANESE INTERMEDIATE CODE: A131

Effective date: 20091215

A02 Decision of refusal

Free format text: JAPANESE INTERMEDIATE CODE: A02

Effective date: 20100506