JP2006099794A - Progress management method for transaction between enterprises - Google Patents

Progress management method for transaction between enterprises Download PDF

Info

Publication number
JP2006099794A
JP2006099794A JP2005314190A JP2005314190A JP2006099794A JP 2006099794 A JP2006099794 A JP 2006099794A JP 2005314190 A JP2005314190 A JP 2005314190A JP 2005314190 A JP2005314190 A JP 2005314190A JP 2006099794 A JP2006099794 A JP 2006099794A
Authority
JP
Japan
Prior art keywords
transaction
progress
work
company
information
Prior art date
Legal status (The legal status is an assumption and is not a legal conclusion. Google has not performed a legal analysis and makes no representation as to the accuracy of the status listed.)
Granted
Application number
JP2005314190A
Other languages
Japanese (ja)
Other versions
JP4241922B2 (en
Inventor
Tsuyoshi Miyake
強志 三宅
Hiromitsu Shiina
洋充 椎名
Current Assignee (The listed assignees may be inaccurate. Google has not performed a legal analysis and makes no representation or warranty as to the accuracy of the list.)
Hitachi Ltd
Original Assignee
Hitachi Ltd
Priority date (The priority date is an assumption and is not a legal conclusion. Google has not performed a legal analysis and makes no representation as to the accuracy of the date listed.)
Filing date
Publication date
Application filed by Hitachi Ltd filed Critical Hitachi Ltd
Priority to JP2005314190A priority Critical patent/JP4241922B2/en
Publication of JP2006099794A publication Critical patent/JP2006099794A/en
Application granted granted Critical
Publication of JP4241922B2 publication Critical patent/JP4241922B2/en
Anticipated expiration legal-status Critical
Expired - Fee Related legal-status Critical Current

Links

Images

Classifications

    • YGENERAL TAGGING OF NEW TECHNOLOGICAL DEVELOPMENTS; GENERAL TAGGING OF CROSS-SECTIONAL TECHNOLOGIES SPANNING OVER SEVERAL SECTIONS OF THE IPC; TECHNICAL SUBJECTS COVERED BY FORMER USPC CROSS-REFERENCE ART COLLECTIONS [XRACs] AND DIGESTS
    • Y02TECHNOLOGIES OR APPLICATIONS FOR MITIGATION OR ADAPTATION AGAINST CLIMATE CHANGE
    • Y02PCLIMATE CHANGE MITIGATION TECHNOLOGIES IN THE PRODUCTION OR PROCESSING OF GOODS
    • Y02P90/00Enabling technologies with a potential contribution to greenhouse gas [GHG] emissions mitigation
    • Y02P90/30Computing systems specially adapted for manufacturing

Landscapes

  • Management, Administration, Business Operations System, And Electronic Commerce (AREA)

Abstract

<P>PROBLEM TO BE SOLVED: To perform progress management of a project and a transaction such that a plurality of enterprises interlock and participate in accordance with a delivery time when delivering a final product to a customer. <P>SOLUTION: A relay part 22 of a server 11 relays transaction information transmitted from a transaction information transmission terminal 12 of a certain enterprise to a transaction information reception terminal 13. An inter-enterprise progress management part 24 performs development to a work schedule comprising a plurality of work processes when receiving ordering information of a commodity from the relay part 22, and performs storage into a progress situation database 21. When acquiring a results report of the related work process through the relay part 22 or a reception part 23, a results date is recorded in the schedule, and a change date about the succeeding work process is recorded when being late for a scheduled date. A retrieval part 27 takes out a corresponding progress situation from the progress situation database 21 in response to inquiry from a progress situation inquiry terminal 14, and transmits it to the progress situation inquiry terminal 14 through an editing part 28 and an output part 29. <P>COPYRIGHT: (C)2006,JPO&NCIPI

Description

本発明は、コンピュータを利用する取引の進捗管理方法および装置に係わり、特に企業間に伝送される取引情報を基にして複数企業が関与する作業スケジュールの進捗管理を行う方法および装置に関する。   The present invention relates to a transaction progress management method and apparatus using a computer, and more particularly to a method and apparatus for managing the progress of a work schedule involving a plurality of companies based on transaction information transmitted between the companies.

コンピュータを利用する単一企業内の生産管理やプロジェクトの工程管理は多くの企業で実施され、その技術は良く知られている。例えば特開平7−129667号公報(特許文献1)は、プロジェクトを管理する業務の工程管理方法を開示する。   Production management and project process management within a single company using computers are carried out by many companies, and their techniques are well known. For example, Japanese Patent Laid-Open No. 7-129667 (Patent Document 1) discloses a process management method for business to manage a project.

特開平7−129667号公報JP-A-7-129667

顧客に最終製品を納入するときの納期に合わせて部品の製造と出荷、装置の組立と出荷など最終製品を納入するまでの間に複数企業の連動を必要とする商品がある。このように最上流の作業工程から最終製品の納入に至るまで複数の企業が一連の納期条件の下に関与するような取引あるいはプロジェクトの進捗管理をする場合には、従来の同一企業内の工程管理技術をそのまま適用することはできない。すなわちこのような企業間取引の進捗管理をするサーバが関連する企業の企業内サーバにアクセスして生産管理や在庫管理のデータを引き出すことは困難であるし、企業によるデータ形式やコード体系の相違から目的とする取引又はプロジェクトの進捗管理のために有用なデータを収集することはさらに困難である。このような事情によって従来発注した商品についてどの企業までの作業が終了していて予定に対して遅れがないか否かを把握することが困難であった。   There are products that require the cooperation of multiple companies before the final product is delivered, such as the manufacture and shipment of parts and the assembly and shipment of equipment in accordance with the delivery date when the final product is delivered to the customer. In this way, when managing the progress of transactions or projects where multiple companies are involved under a series of delivery date conditions, from the most upstream work process to the delivery of the final product, the conventional process within the same company Management technology cannot be applied as it is. In other words, it is difficult for such a server that manages the progress of inter-company transactions to access the company's internal server and extract data for production management and inventory management. It is even more difficult to collect useful data for managing the progress of a targeted transaction or project. Due to such circumstances, it has been difficult to grasp to which company work has been completed and there is no delay with respect to the schedule for the products ordered in the past.

本発明の目的は、上記従来の問題点を解決することにあり、複数企業が関与する取引の進捗管理をする方法および装置を提供することにある。   An object of the present invention is to solve the above-mentioned conventional problems, and to provide a method and apparatus for managing the progress of transactions involving a plurality of companies.

本発明は、ネットワークを介して企業間に伝送される取引情報を取得し、この取引情報を基にして複数の企業に亘る複数の作業工程と完了予定日を含む作業スケジュールに展開し、この作業工程について作業の実績報告を取得したとき作業スケジュールに実績日を記録し、実績日が完了予定日より遅れたとき遅れ日数に応じて後続の作業工程の完了予定日を修正する変更日をスケジュールに記録する企業間の取引進捗管理方法および装置を特徴とする。ここで作業の実績報告は、展開された複数の作業工程のうちの1つに対応付けできるものとし、その作業完了予定日と報告された実績日を比較できるものとする。   The present invention acquires transaction information transmitted between companies via a network, and develops a work schedule including a plurality of work processes and completion dates for a plurality of companies based on the transaction information. Record the actual date in the work schedule when the work performance report is obtained for the process, and schedule the change date to correct the scheduled completion date of the subsequent work process according to the number of days delayed when the actual date is delayed from the planned completion date It features a transaction progress management method and apparatus between companies for recording. Here, the work result report can be associated with one of a plurality of developed work processes, and the work completion scheduled date can be compared with the reported result date.

以上説明したように本発明によれば、複数企業が関与する取引について統合的な進捗管理を行うので、その進捗状況を即座に把握できる。   As described above, according to the present invention, since integrated progress management is performed for transactions involving a plurality of companies, the progress status can be immediately grasped.

以下、本発明の一実施形態について図面を用いて説明する。   Hereinafter, an embodiment of the present invention will be described with reference to the drawings.

図1は、本実施形態の進捗管理システムの構成図である。システムはサーバ11と、ネットワーク15を介してサーバ11に接続され、クライアントとなる取引情報送信端末12、取引情報受信端末13及び進捗状況照会端末14から構成される。取引情報送信端末12は、一方の企業に設置され、ネットワーク15を介してサーバ11へ取引情報を送信する。取引情報受信端末13は、他の企業に設置され、ネットワーク15を介してサーバ11から取引情報を受信する。サーバ11は、取引情報送信端末12から受信した商品の発注に関する取引情報を取引情報受信端末13へ中継するとともに商品の製造から納入までの作業の進捗状況テーブルを作成し、その進捗状況を管理する。進捗状況照会端末14は、ネットワーク15を介してサーバ11へ特定の商品発注についてその進捗状況を問い合わせ、進捗状況データを取得する。   FIG. 1 is a configuration diagram of the progress management system of the present embodiment. The system is connected to the server 11 via the server 11 and the network 15, and includes a transaction information transmission terminal 12, a transaction information reception terminal 13, and a progress status inquiry terminal 14 that are clients. The transaction information transmission terminal 12 is installed in one company and transmits transaction information to the server 11 via the network 15. The transaction information receiving terminal 13 is installed in another company and receives transaction information from the server 11 via the network 15. The server 11 relays the transaction information regarding the order of the product received from the transaction information transmission terminal 12 to the transaction information reception terminal 13, creates a progress status table of work from product manufacture to delivery, and manages the progress status . The progress inquiry terminal 14 inquires of the server 11 about the progress of a specific product order via the network 15 and acquires the progress data.

取引情報送信端末12、取引情報受信端末13及び進捗状況照会端末14は、パーソナルコンピュータ等の情報処理装置である。各端末装置の名称はその情報処理装置で実行されるアプリケーションプログラム(AP)の機能を表しているので、1台の情報処理装置がこれら端末の2つ以上の機能を備えることが可能である。サーバ11は、パソコン、ワークステーション、メインフレームコンピュータ、並列計算機等の情報処理装置である。ネットワーク15は、複数企業間で利用できるインターネット、VAN業者が提供する専用線などのネットワークである。   The transaction information transmitting terminal 12, the transaction information receiving terminal 13, and the progress status inquiry terminal 14 are information processing apparatuses such as personal computers. Since the name of each terminal device represents the function of an application program (AP) executed by the information processing device, one information processing device can have two or more functions of these terminals. The server 11 is an information processing apparatus such as a personal computer, a workstation, a mainframe computer, or a parallel computer. The network 15 is a network such as the Internet that can be used among a plurality of companies and a dedicated line provided by a VAN contractor.

図2は、サーバ11が保持するデータベース及び機能モジュールの構成を示す図である。進捗状況データベース21は、企業間の商品の発注を元にして複数の企業に亘る製品の製造、出荷、納入などの作業の進捗状況のデータを格納する。中継部22は、取引情報送信端末12から受信した取引情報を取引情報受信端末13へ中継するとともに企業間進捗管理部24に渡す。なお取引情報送信端末12は、同報通信によって同一の取引情報を取引情報受信端末13とサーバ11の両方に送信してもよい。その場合には中継部22は、取引情報の単なる受信部となる。受信部23は、取引情報送信端末12などの送信端末から受信した作業実績データを企業間進捗管理部24に渡す。企業間進捗管理部24は、中継部22から受けた商品の発注取引情報を進捗状況テーブルの形式に展開して進捗状況データベース21に格納する処理部である。また企業間進捗管理部24は、中継部22又は受信部23から受けた取引情報又は作業実績データによって進捗状況データベース21の該当する進捗状況テーブルを更新する。その結果として作業スケジュールに遅れが生じる場合に、アラーム/作業指示送信部25は関連企業の取引情報受信端末13などの受信端末へアラームまたは作業指示を送信する。受付部26は、進捗状況照会端末14から取引の進捗状況照会を受信する処理部である。検索部27は、進捗状況データベース21を検索して該当する進捗状況テーブルを取得する処理部である。編集部28は、取得した進捗状況テーブルを編集する処理部である。出力部29は、作成した進捗状況データを進捗状況照会端末14へ送信する処理部である。なお上記機能モジュールを含むAPを記憶媒体に格納し、サーバ11がこの記憶媒体上のAPを読み取って実行することが可能である。   FIG. 2 is a diagram illustrating a configuration of a database and functional modules held by the server 11. The progress database 21 stores data on the progress of work such as manufacturing, shipping, and delivery of products across a plurality of companies based on the ordering of products between companies. The relay unit 22 relays the transaction information received from the transaction information transmission terminal 12 to the transaction information reception terminal 13 and passes it to the inter-company progress management unit 24. The transaction information transmitting terminal 12 may transmit the same transaction information to both the transaction information receiving terminal 13 and the server 11 by broadcast communication. In that case, the relay unit 22 is merely a transaction information receiving unit. The receiving unit 23 passes work result data received from a transmitting terminal such as the transaction information transmitting terminal 12 to the inter-company progress management unit 24. The inter-company progress management unit 24 is a processing unit that develops the ordering transaction information of the product received from the relay unit 22 in the form of a progress status table and stores it in the progress status database 21. Further, the inter-company progress management unit 24 updates the corresponding progress status table in the progress status database 21 with the transaction information or work performance data received from the relay unit 22 or the reception unit 23. As a result, when the work schedule is delayed, the alarm / work instruction transmission unit 25 transmits an alarm or work instruction to a receiving terminal such as the transaction information receiving terminal 13 of the affiliated company. The accepting unit 26 is a processing unit that receives a transaction progress inquiry from the progress inquiry terminal 14. The search unit 27 is a processing unit that searches the progress database 21 and acquires a corresponding progress table. The editing unit 28 is a processing unit that edits the acquired progress situation table. The output unit 29 is a processing unit that transmits the created progress status data to the progress status inquiry terminal 14. It is possible to store the AP including the functional module in a storage medium, and the server 11 can read and execute the AP on the storage medium.

図3は、取引情報送信端末12から取引情報受信端末13へ送信される取引情報35のデータ例を示す図である。図3(a)は、A社からX社へ送信される発注情報であり、商品番号、数量、納期、発注者、受注者及び発注番号から成る。図3(b)は、C社からY社へ送信される出荷情報であり、商品番号、数量、納期、発注者、受注者、発注番号、出荷番号及び実際の出荷日から成る。なお取引情報の書式としてCIIシンタックスルール、EDIFACTのような標準書式に準拠することができる。また発注番号や商品番号などは企業間のコード体系の統一基準に従って統一されているものとする。   FIG. 3 is a diagram illustrating a data example of the transaction information 35 transmitted from the transaction information transmitting terminal 12 to the transaction information receiving terminal 13. FIG. 3A shows the ordering information transmitted from the company A to the company X, and includes the product number, quantity, delivery date, orderer, contractor, and order number. FIG. 3B shows shipping information transmitted from the C company to the Y company, which includes a product number, quantity, delivery date, orderer, contractor, order number, shipping number, and actual shipping date. The transaction information format can conform to standard formats such as CII syntax rules and EDIFACT. In addition, it is assumed that the order number, product number, and the like are standardized according to the standard for the code system between companies.

図4は、進捗状況データベース21に格納される進捗状況データの構成を示す図である。進捗状況データは、各商品発注について関連する企業の作業の順に進捗状況を示すスケジュール・テーブルである。テーブルは列方向に発注番号、企業名、作業名、作業完了予定日、作業実績日及び作業変更日を配列し、行方向に同一商品発注に係わる各企業の作業とその進捗状況を作業順に配列する。企業名は単独の企業名又は企業間取引に係わる2つの企業名を示す。発注番号、企業名、作業名及び作業完了予定日は、最初の商品発注のとき作業展開によって設定されたデータである。作業実績日及び作業変更日は、企業の実績報告又は取引情報35によって格納されるデータである。作業変更日は実績報告のあった作業工程より後続の作業工程の作業完了予定日を修正するものである。例えばC社からY社への出荷についてその作業実績日は、C社からY社への取引情報35から抽出されたものである。各作業について付加されているアラーム及び作業指示は、作業遅れに伴って後続の作業を担当する企業へ送信されるアラーム及び作業指示を示している。図4の例は、C社からY社への出荷が1日遅れたために、Y社からB社への納入が1日遅れ、その結果として仕向先の企業であるB社へ「納入遅れ」を警告することを示している。またB社の製造スケジュールを変更する代わりにB社へ「リードタイム短縮」を指示することを示している。またB社からX社への出荷が遅れる恐れがあるので、X社へ「緊急出荷」を指示し、X社からA社への出荷が遅れる恐れがあるので、A社へ「納入遅れのおそれあり」を警告することを示している。アラーム及び作業指示の内容は、作業の種類と遅れ日数に応じてパターンを用意する。アラーム及び作業指示を進捗状況データベース21に登録する必要はないが、各作業に対応して発生するので便宜的に各作業の進捗状況と並列して示した。   FIG. 4 is a diagram showing a structure of progress status data stored in the progress status database 21. The progress status data is a schedule table that indicates the progress status in the order of the work of the company related to each product order. The table arranges the order number, company name, work name, scheduled work completion date, actual work date, and work modification date in the column direction, and the work of each company related to the same product order and its progress status in the row direction. To do. The company name indicates a single company name or two company names related to inter-company transactions. The order number, company name, work name, and scheduled work completion date are data set by work expansion at the time of the first product order. The work performance date and the work change date are data stored in the company performance report or transaction information 35. The work change date is to correct the work completion scheduled date of the work process subsequent to the work process for which the result has been reported. For example, the work performance date for shipment from the C company to the Y company is extracted from the transaction information 35 from the C company to the Y company. The alarm and work instruction added for each work indicate the alarm and work instruction transmitted to the company in charge of the subsequent work with work delay. In the example of FIG. 4, the shipment from Company C to Company Y was delayed by one day, so delivery from Company Y to Company B was delayed by one day, and as a result, “Delayed delivery” to Company B, the destination company. Indicates a warning. In addition, instead of changing the manufacturing schedule of company B, it is indicated to instruct B company to reduce the lead time. In addition, since there is a risk that shipment from Company B to Company X will be delayed, we will give an instruction to Company X to "emergency shipment" and there will be a delay in shipment from Company X to Company A. "Yes" is indicated. The contents of the alarm and work instructions are prepared according to the type of work and the number of days delayed. Although alarms and work instructions do not need to be registered in the progress database 21, they are generated in correspondence with each work, and are shown in parallel with the progress of each work for convenience.

なおC社及びB社のような単独企業の製造工程を設けずにC社−Y社及びB社−X社の出荷取引情報によってその中に製造工程を含ませてもよい。「出荷」は製造を伴う場合の商品の引き渡しを意味し、「納入」は販売店や商社を経由するときのように製造を伴わない場合の商品の引き渡しを意味している。なお図4の例は作業工程が直列に接続される単純な例であるが、複数の作業工程が並列して進行し、各企業で製造される部品をアセンブルして最終製品を組み立てて発注者に納入する複雑な作業スケジュールの場合も同様に1つの商品発注を進捗状況テーブルに展開し、企業の実績報告又は取引情報35によって作業実績日及び作業変更日を設定可能である。   In addition, a manufacturing process may be included in the shipping transaction information of company C-company Y and company B-company X without providing a manufacturing process for a single company such as company C and company B. “Shipment” means delivery of a product when production is involved, and “delivery” means delivery of a product without production as in the case of passing through a store or a trading company. The example in FIG. 4 is a simple example in which work processes are connected in series, but a plurality of work processes proceed in parallel, assemble parts manufactured by each company, assemble the final product, and orderer. Similarly, in the case of a complicated work schedule to be delivered, one product order can be developed in the progress status table, and the work result date and work change date can be set by the company result report or transaction information 35.

図5は、サーバ11の企業間進捗管理部24及びアラーム/作業指示送信部25の処理の流れを示すフローチャートである。企業間進捗管理部24は、中継部22又は受信部23から取引情報35又は作業実績データを受信すると(ステップ51)、発注番号によって進捗状況データベース21を検索し(ステップ52)、進捗状況データベース21に登録されていない新規の商品発注の取引情報か否か判定する(ステップ53)。新規の商品発注であれば(ステップ53YES)、あらかじめ記憶装置に設定された企業名、作業名及び標準作業日数をプロトタイプのスケジュールとして作業展開し(ステップ54)、進捗状況データベース21に登録し(ステップ55)、処理を終了する。発注情報に含まれる受注者−発注者を最後の納入作業又は出荷作業の企業名として設定し、商品の納期が最後の納入作業又は出荷作業の作業完了予定日として設定する。新規の商品発注でなければ(ステップ53NO)、既登録の商品発注の企業間取引情報又は作業実績報告かを判定する(ステップ56)。既発注商品の取引情報/実績報告であれば(ステップ56YES)、進捗状況テーブルに当該発注番号の該当する作業の作業実績日を設定し、それによって作業完了予定日に変更が生じる場合にはその遅れ日数に応じて作業変更日に変更日を設定する(ステップ57)。次に作成した進捗状況テーブルによって進捗状況データベース21を更新する(ステップ58)。ステップ57の処理の結果、作業実績日が作業完了予定日より遅れない場合には(ステップ59NO)、処理を終了する。納期遅れが生じる場合には(ステップ59YES)、制御はアラーム/作業指示送信部25に渡り、アラーム/作業指示送信部25は、あらかじめ設定されたアラーム及び作業指示のパターンに従って関連する企業の受信端末へ発注番号、作業名、アラーム又は作業指示を送信する(ステップ60)。送信端末から受信した取引情報又は企業内情報が既登録の発注商品の進捗状況に関係しないものであれば(ステップ56NO)、処理を終了する。なお進捗状況テーブルの中に単独企業の製造工程を設けない場合には、企業間進捗管理部24に入力される情報に受信部23からの情報はなく、中継部22から入力される企業間取引情報だけである。   FIG. 5 is a flowchart showing a processing flow of the inter-company progress management unit 24 and the alarm / work instruction transmission unit 25 of the server 11. When the inter-company progress management unit 24 receives the transaction information 35 or the work performance data from the relay unit 22 or the receiving unit 23 (step 51), the inter-company progress management unit 24 searches the progress database 21 by the order number (step 52). It is determined whether or not the transaction information is for a new product order that is not registered in (step 53). If it is a new product order (step 53 YES), the company name, work name, and standard work days set in the storage device in advance are expanded as a prototype schedule (step 54) and registered in the progress database 21 (step 53). 55) The process is terminated. The contractor-orderer included in the ordering information is set as the company name of the final delivery work or shipping work, and the delivery date of the product is set as the scheduled completion date of the final delivery work or shipping work. If it is not a new merchandise order (step 53 NO), it is determined whether the registered merchandise order is inter-company transaction information or a work performance report (step 56). If it is the transaction information / result report of the already ordered product (step 56 YES), the work result date of the work corresponding to the order number is set in the progress status table, and if the work completion scheduled date is changed as a result, A change date is set on the work change date according to the delay days (step 57). Next, the progress database 21 is updated with the created progress table (step 58). As a result of the process in step 57, if the work result date is not delayed from the work completion scheduled date (NO in step 59), the process is terminated. If there is a delay in delivery (YES in step 59), the control is passed to the alarm / work instruction transmission unit 25, and the alarm / work instruction transmission unit 25 receives the related enterprise receiving terminal according to the preset alarm and work instruction pattern. An order number, work name, alarm, or work instruction is transmitted to (step 60). If the transaction information or the in-company information received from the transmission terminal is not related to the progress status of the already-registered ordered product (NO in step 56), the process is terminated. In the case where the manufacturing process of a single company is not provided in the progress status table, there is no information from the receiving unit 23 in the information input to the inter-company progress management unit 24, and the inter-company transaction input from the relay unit 22 Information only.

なおステップ54の作業展開の際に部品の在庫があり/なしに応じてそれぞれ別の作業プロトタイプを採用することができる。例えば図4に示す例でB社が発注された商品の数量に見合う部品の在庫をもっているという情報が得られれば、作業プロトタイプはB社の製造から開始すればよい。サーバ11はB社の最新の部品在庫情報を保有するか、またはB社のサーバに問い合わせて取得することができる。   It should be noted that different work prototypes can be adopted depending on whether or not parts are in stock at the time of the work development in step 54. For example, in the example shown in FIG. 4, if it is possible to obtain information that company B has an inventory of parts commensurate with the quantity of products ordered, the work prototype may be started from manufacture of company B. The server 11 holds the latest parts inventory information of the B company, or can obtain it by inquiring the server of the B company.

図6は、進捗状況照会端末14からサーバ11へ送信される進捗状況照会65のデータ例を示す図である。進捗状況照会65は、発注番号、発注者、受注者、納期のような情報から成る。   FIG. 6 is a diagram illustrating a data example of the progress status inquiry 65 transmitted from the progress status inquiry terminal 14 to the server 11. The progress status inquiry 65 includes information such as an order number, an orderer, a contractor, and a delivery date.

図7は、サーバ11から進捗状況照会端末14へ送信される照会結果である進捗状況データ75のデータ例を示す図である。進捗状況データ75は、指定された発注番号の進捗状況テーブルを人が見易い表の形式に編集したものである。なお進捗状況データとして、進捗状況テーブルを図形を用いて表現する工程管理図の形式に編集することも可能である。   FIG. 7 is a diagram illustrating a data example of the progress status data 75 that is a query result transmitted from the server 11 to the progress status query terminal 14. The progress data 75 is obtained by editing the progress table of the designated order number into a table format that is easy for humans to see. As the progress data, it is possible to edit the progress table into a process control chart format that uses graphics.

図8は、サーバ11の受付部26から出力部29までの処理の流れを示すフローチャートである。受付部26は進捗状況照会端末14から進捗状況照会65を受信し(ステップ81)、検索部27は進捗状況データベース21を検索して指定された発注番号の進捗状況テーブルを取り出す(ステップ82)。編集部28は取得した進捗状況テーブルを進捗状況データ75の形式に編集し(ステップ83)、出力部29は作成した進捗状況データ75を進捗状況照会端末14へ送信する(ステップ84)。   FIG. 8 is a flowchart showing the flow of processing from the receiving unit 26 to the output unit 29 of the server 11. The receiving unit 26 receives the progress status inquiry 65 from the progress status inquiry terminal 14 (step 81), and the search unit 27 searches the progress status database 21 and retrieves the progress status table of the designated order number (step 82). The editing unit 28 edits the acquired progress status table into the format of progress status data 75 (step 83), and the output unit 29 transmits the created progress status data 75 to the progress status inquiry terminal 14 (step 84).

なおサーバ11が各取引情報送信端末12から取引情報受信端末13へ伝送される取引情報をとらえて進捗状況データベース21に進捗状況テーブルを登録したり更新する代わりに、各企業の企業情報システム内で取引情報送信端末12から送信された取引情報を企業内サーバによって中継して取引情報受信端末13へ伝送し、各企業の企業内サーバからサーバ11へ取引情報を送信してもよい。   Instead of the server 11 capturing the transaction information transmitted from each transaction information transmitting terminal 12 to the transaction information receiving terminal 13 and registering or updating the progress table in the progress database 21, the server 11 stores the information in the company information system of each company. The transaction information transmitted from the transaction information transmitting terminal 12 may be relayed by the in-company server and transmitted to the transaction information receiving terminal 13, and the transaction information may be transmitted from the in-company server of each company to the server 11.

実施形態のシステムの構成を示す図である。It is a figure which shows the structure of the system of embodiment. 実施形態のサーバ11の内部構成を示す図である。It is a figure which shows the internal structure of the server 11 of embodiment. 取引情報35のデータ例を示す図である。It is a figure which shows the example of data of the transaction information 35. FIG. 実施形態の進捗状況データベース21のデータ構成を示す図である。It is a figure which shows the data structure of the progress condition database 21 of embodiment. 実施形態の企業間進捗管理部24及びアラーム/作業指示送信部25の処理の流れを示すフローチャートである。It is a flowchart which shows the flow of a process of the progress management part 24 between companies, and the alarm / work instruction | indication transmission part 25 of embodiment. 進捗状況照会65のデータ例を示す図である。It is a figure which shows the example of data of the progress condition inquiry 65. FIG. 進捗状況データ75のデータ例を示す図である。It is a figure which shows the example of data of the progress status data 75. FIG. 実施形態の進捗状況照会処理の処理の流れを示すフローチャートである。It is a flowchart which shows the flow of a process of the progress condition inquiry process of embodiment.

符号の説明Explanation of symbols

11:サーバ、12:取引情報送信端末、13:取引情報受信端末、14:進捗状況照会端末、21:進捗状況データベース、24:企業間進捗管理部、35:取引情報   11: Server, 12: Transaction information transmission terminal, 13: Transaction information reception terminal, 14: Progress status inquiry terminal, 21: Progress status database, 24: Inter-company progress management section, 35: Transaction information

Claims (5)

企業間の取引の進捗状況を管理するサーバを利用する企業間の取引進捗管理方法において、
前記サーバは、複数の企業に亘る複数の作業工程を含む取引と前記取引の作業工程ごとの完了予定日を含む取引の進捗状況とを対応付けて格納する記憶部を有し、
前記格納されている前記取引に含まれる作業工程の実績日を示す情報を、ネットワークを介して取得し、取得した情報を基に前記実績日を前記格納されている作業工程の完了予定日に対応付けて前記記憶部に格納し、
前記ネットワークを介して接続する情報処理装置から取引の進捗状況について照会要求を受け、前記受けた照会要求を基に該当する取引の進捗状況が格納されているか検索し、
前記検索の結果、格納されている場合は前記該当する取引と前記取引の進捗状況とを取得し、
前記取得した取引の進捗状況に含まれる前記取引の作業工程の完了予定日と前記実績日との対応付けと、前記取得した取引と前記取引の進捗状況との対応付けとに基づいて表示形式に編集された情報を前記情報処理装置へ送信することを特徴とする企業間の取引進捗管理方法。
In the transaction progress management method between companies using a server that manages the progress of transactions between companies,
The server includes a storage unit that stores a transaction including a plurality of work processes across a plurality of companies in association with a progress of a transaction including a scheduled completion date for each work process of the transaction,
Information indicating the actual date of the work process included in the stored transaction is acquired via a network, and the actual date is associated with the scheduled completion date of the stored work process based on the acquired information. And store in the storage unit,
Receiving an inquiry request about the progress of a transaction from the information processing apparatus connected via the network, and searching whether the progress of the corresponding transaction is stored based on the received inquiry request;
As a result of the search, if stored, the corresponding transaction and the progress of the transaction are acquired,
Based on the association between the scheduled completion date of the work process of the transaction and the actual date included in the progress of the acquired transaction, and the association between the acquired transaction and the progress of the transaction A transaction progress management method between companies, wherein edited information is transmitted to the information processing apparatus.
請求項1記載の取引進捗管理方法において、
前記取引の進捗状況の情報として、前記複数の作業工程に対応する企業名をさらに対応付けて前記記憶部に格納し、
前記検索においては、前記取得した取引の進捗状況に含まれる前記取引の作業工程のうち相互に関連する作業工程について前記企業名を複数前記記憶部から読み出し、
前記送信される編集された情報は、前記相互に関連する作業工程を前記読み出した企業名ごとに並べて表の形式に編集されたデータであることを特徴とする企業間の取引進捗管理方法。
In the transaction progress management method according to claim 1,
As the information on the progress of the transaction, the company name corresponding to the plurality of work steps is further correlated and stored in the storage unit,
In the search, a plurality of the company names are read from the storage unit for work processes related to each other among the work processes of the transaction included in the progress of the acquired transaction,
The method for managing transaction progress between companies, wherein the edited information to be transmitted is data in which the interrelated work processes are arranged for each of the read company names and edited in a table format.
前記作業実績日が前記完了予定日より遅れた場合は、前記他の作業工程の作業の種類と遅れ日数とに応じて前記作業工程を担当する企業側の情報処理装置にメッセージを送信することを特徴とする請求項2記載の取引進捗管理方法。   When the work performance date is delayed from the scheduled completion date, a message is sent to the information processing device on the company side in charge of the work process according to the type of work and the number of days delayed. The transaction progress management method according to claim 2, wherein 前記メッセージは、当該企業に対する警告のメッセージであることを特徴とする請求項3記載の取引進捗管理方法。   The transaction progress management method according to claim 3, wherein the message is a warning message for the company. 前記取引情報は、ネットワークを介して企業側の情報処理装置から受信した情報であって、さらに前記取引情報を前記取引情報の取引相手である企業側の情報処理装置で送信することを特徴とする請求項2記載の取引進捗管理方法。
The transaction information is information received from a company-side information processing apparatus via a network, and the transaction information is further transmitted by a company-side information processing apparatus that is a trading partner of the transaction information. The transaction progress management method according to claim 2.
JP2005314190A 2005-10-28 2005-10-28 Inter-company transaction progress management method Expired - Fee Related JP4241922B2 (en)

Priority Applications (1)

Application Number Priority Date Filing Date Title
JP2005314190A JP4241922B2 (en) 2005-10-28 2005-10-28 Inter-company transaction progress management method

Applications Claiming Priority (1)

Application Number Priority Date Filing Date Title
JP2005314190A JP4241922B2 (en) 2005-10-28 2005-10-28 Inter-company transaction progress management method

Related Parent Applications (1)

Application Number Title Priority Date Filing Date
JP18791197A Division JP4312846B2 (en) 1997-03-31 1997-07-14 Transaction progress management method

Publications (2)

Publication Number Publication Date
JP2006099794A true JP2006099794A (en) 2006-04-13
JP4241922B2 JP4241922B2 (en) 2009-03-18

Family

ID=36239450

Family Applications (1)

Application Number Title Priority Date Filing Date
JP2005314190A Expired - Fee Related JP4241922B2 (en) 2005-10-28 2005-10-28 Inter-company transaction progress management method

Country Status (1)

Country Link
JP (1) JP4241922B2 (en)

Cited By (1)

* Cited by examiner, † Cited by third party
Publication number Priority date Publication date Assignee Title
JP2011018170A (en) * 2009-07-08 2011-01-27 Nec Corp Debt and credit management system and device, ordering side management device, order reception side management device, debt and credit management method, and program

Cited By (1)

* Cited by examiner, † Cited by third party
Publication number Priority date Publication date Assignee Title
JP2011018170A (en) * 2009-07-08 2011-01-27 Nec Corp Debt and credit management system and device, ordering side management device, order reception side management device, debt and credit management method, and program

Also Published As

Publication number Publication date
JP4241922B2 (en) 2009-03-18

Similar Documents

Publication Publication Date Title
US7657534B2 (en) Order commitment method and system
US7218980B1 (en) Prediction based optimization of a semiconductor supply chain using an adaptive real time work-in-progress tracking system
Li et al. Internet-based geographical information systems system for E-commerce application in construction material procurement
JP6144730B2 (en) A method adapted to be used for commercial transactions
US20030050852A1 (en) Purchase order tracking system and method for providing online purchase order manipulation progress report to customer
JP2007536607A (en) System and method for user creation and command of rich content lifecycle
US8406910B2 (en) Management device, production management device, production management system
CA2413437A1 (en) Computer implemented system and method for project development
JP4312846B2 (en) Transaction progress management method
CN101221435B (en) System and method for module positioning in industrial environment
US20040193435A1 (en) EDI declaration management system and method
US20030131018A1 (en) Common business data management
JP2005070835A (en) Test supporting program and test supporting method
US20140379415A1 (en) Social workflow engine
JP4241922B2 (en) Inter-company transaction progress management method
US20030217035A1 (en) System and method for integrating and processing data from different data sources
US20030229530A1 (en) Methods for production forecasting and ordering
JP2007304951A (en) Business process management method, business process management program, and business process management server
JP2004102929A (en) Housing material production management method and device therefor
KR100423865B1 (en) Agile information system and management method
Hassan et al. Development of an order processing system using Google Sheets and Appsheet for a Malaysian automotive SME factory warehouse
JP2004178150A (en) Integrated production management method and system by production process management chart
JP2007334393A (en) Method and system for managing parts list data
US20070198544A1 (en) Data management systems and methods for networks
JP4340016B2 (en) Information processing apparatus, network system, production management method, and storage medium

Legal Events

Date Code Title Description
A131 Notification of reasons for refusal

Free format text: JAPANESE INTERMEDIATE CODE: A131

Effective date: 20080819

A521 Request for written amendment filed

Free format text: JAPANESE INTERMEDIATE CODE: A523

Effective date: 20081015

TRDD Decision of grant or rejection written
A01 Written decision to grant a patent or to grant a registration (utility model)

Free format text: JAPANESE INTERMEDIATE CODE: A01

Effective date: 20081202

A01 Written decision to grant a patent or to grant a registration (utility model)

Free format text: JAPANESE INTERMEDIATE CODE: A01

A61 First payment of annual fees (during grant procedure)

Free format text: JAPANESE INTERMEDIATE CODE: A61

Effective date: 20081223

FPAY Renewal fee payment (event date is renewal date of database)

Free format text: PAYMENT UNTIL: 20120109

Year of fee payment: 3

R150 Certificate of patent or registration of utility model

Free format text: JAPANESE INTERMEDIATE CODE: R150

LAPS Cancellation because of no payment of annual fees